metode konstruksi - proyek persiapan lahan parkir jurusan teknik sipil uns
Post on 09-Aug-2015
88 Views
Preview:
TRANSCRIPT
Metode Konstruksi (Stripping, Cutting, dan Compacting di Samping Gedung 4
Fakultas Teknik UNS
Kelompok:
Andreas Nur HadiI I0113013
Baggus Prastyo I0113023
Dede Zakiyah I0113031
Fika Giri Aspia I0112052
Himamul A’la I0112075
Site Plan Kondisi Tanah
Pemilihan ALat
1. Stripping dan Cutting
Bulldozer Crawler CAT D5R
Kapasitas Blade : 4.28 m3
Rata-rata Kecepatan maju : 6.3 km/jam
Rata-rata Kecepatan mundur : 7 km/jam
Produktivitas : 229.1995 m3/jam
2. Loader
Wheel Loader CAT 938K
Kapasitas Bucket : 4 m3
Produktivitas : 285 m3/jam
3. Dump Truck
Kapasitas muatan :
18144 kg
Produktivitas : 56.7 m3/jam/truck
4.Compactor
Soil Compactor 825H
L(lebar efektif) : 1.814 m
V(Kecepatan) : 3 km/jam
Produktivitas : 40.815 m3/jam
Video Perencanaan Metode Konstruksi
Perhitungan
VOLUME TANAH:
-Volume Bank : 1251.2 m3
-Volume Stripping: 156.4 m3
-Volume Cutting : 1133.9 m3
-Volume Loose : 1360.68 m3
-Volume Compacting : 963.815 m3
PEKERJAAN STRIPPING :
ALAT : BULLDOZER D5R
PRODUKTIVITAS : 229.1995 m3/jam
VOLUME STRIPPING : 156.4 m3
WAKTU :
= VOLUME STRIPPING / PRODUKTIVITAS ALAT
= 156.4 m3 / 229.1995 m3/jam
= 0.682 JAM 1 JAM
JUMLAH ALAT : 1 BUAH
PEKERJAAN CUTTING :
ALAT : BULLDOZER D5R
PRODUKTIVITAS : 229.1995 m3/jam
VOLUME CUTTING : 1133.9 m3
WAKTU :
= VOLUME CUTTING / PRODUKTIVITAS ALAT
= 1133.9 m3/ 229.1995 m3/jam
= 4.95 JAM 5 JAM
JUMLAH ALAT : 1 BUAH
PEKERJAAN LOADING :
ALAT : Wheel Loader CAT 938K
PRODUKTIVITAS : 285 m3/jam
VOLUME LOOSE : 1360.68 m3
WAKTU :
= VOLUME STRIPPING / PRODUKTIVITAS ALAT
= 1360.68 m3/ 285 m3/jam
= 4.77 JAM 5 JAM
JUMLAH ALAT : 1 BUAH
MOVING:
ALAT : Dump Truck
PRODUKTIVITAS TRUCK : 56.7 m3/jam
PRODUKTIVITAS LOADER : 285 m3/jam
JUMLAH TRUCK YANG DIBUTUHKAN :
= PRODUKTIVITAS LOADER / PRODUKTIVITAS TRUCK
= 285 m3/jam / 56.7 m3/jam
= 5 TRUCK
PEKERJAAN COMPACTING :
ALAT : Soil Compactor 825H
PRODUKTIVITAS : 40.815 m3/jam
VOLUME COMPACT : 963.815 m3
WAKTU :
= VOLUME COMPACT / PRODUKTIVITAS ALAT
= 963.815 m3 / 40.815 m3/jam
= 23.614 JAM TIAP COMPACTOR
2 COMPACTOR 12 JAM PENGERJAAN
Perencanaan Jadwal
Rencana Anggaran Biaya
NB : Anggaran biaya tersebut belum termasuk konsumsi dan rokok pekerja
TERIMA KASIH