presentation developed prior to input from 12/17/03 adobe collaborative meeting adobe upper reach 5...

Post on 26-Mar-2015

212 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Scott Wilson
The slides in this presentation were developed prior to input received at the Adobe Collaborative Meeting of December 17, 2003.

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Adobe Upper Reach 5Conceptual Plan Issues

December 9, 2003Workshop

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Modeling of Flows

• At minimum, provide capacity to convey what flows under W. Edith Ave. Bridge

• Downstream of W. Edith Ave. Bridge:– Accommodate Flows A, B1, and B2– Partially accommodate Flows A, B1, B2

and allow for overland flow on Rogez/Astiz property parallel to creek

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Top of Bank Boundaries

• Before moving forward, there must be agreement on allowable top-of-bank margin for proposed project– Line 1 – twice width of existing creek– Line 2 – matches width of creek d/s of

Robleda Drain– Line 3 – Swanson’s 1% top-of-bank

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Top-of-Bank Boundaries (cont’d)

• Middle line seems to be good working top-of-bank target

• Can land between Line 2 and Line 3 be potentially used for mitigation planting?

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Width of Creek Channel

• Upper Reach 5 should not be wider than lower Reach 5, within limits of good channel design

• Can creek be made deeper to minimize channel width w/out compromising downstream and upstream portions or acceptable creek design?

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Channel Relocation

• Removal of oxbow near Theis property is OK

• Creek channel can be moved 5-10 feet toward LAH side if needed to protect trees on Los Altos side

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Banks

• ACWG proposal includes gabion or rock rip rap for creek banks to minimize channel width

• Regulatory agencies may have issues with these options and may require mitigation for installing such “hardscape”

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Mitigation

• Mitigation may be required for:– Adding hardscape to channel – Loss of riparian habitat along top-of-

bank due to channel widening• Ratio of mitigation varies based on value of

lost habitat• Mitigation ratios? 1:1, 2:1, 3:1

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Mitigation (cont’d)

• Regulatory agencies prefer mitigation to be done at site of impacts

• District has strong interest in mitigating for impacts on site

• Minimize channel width and use portions of Rogez/Astiz properties for mitigation plantings

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Transplanting Trees

• District will evaluate this work• In the interest of cost-efficiency, this

criterion may be difficult to achieve

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Proposed Conceptual Approach

• Detailed hydrology to determine Flows A, B1, and B2

• Assume rock rip rap or gabion banks with slopes of 1:1 or 1.5:1

• Develop appropriate channel bottom slope– Match existing downstream invert and desired

invert under W. Edith Bridge– Drop structures to allow for fish passage

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Proposed Conceptual Approach (cont’d)

• Determine minimum width of channel to convey flow (A) coming under W. Edith Bridge

• Determine minimum width of channel to convey portion or all of overland flows B1 and B2

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

Proposed Conceptual Approach (cont’d)

• Follow CEQA process to determine impacts of project and develop mitigation proposal

• Maintain continual interaction with ACWG and City/Town while developing alternatives

Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting

NEXT STEPS

• Draft Proposed Project Plan (PPP) – January 28, 2004

• Review, discuss, modify PPP – February 23, 2004

• Prepare for District Board consideration – March 2004

• Present PPP to Board – April 6,2004• Incorporate into Capital Improvement

Program

top related