Rural Access ProgrammeDevelopment through access
RAP3 and the Private SectorPresentation for RAP3 Consultant’s Forum
Michael Green
June 2014
Rural Access ProgrammeDevelopment through access
RAP3 RAP3 Implementation £31.5m –
Works with district and central GON and private sector (14 districts) Employment for the poor maintaining, upgrading, constructing rural roads. (14 districts) Savings, literacy, income training as in RAP2 (14 districts) Sustainable agricultural, small businesses, economic infrastructure (8 districts) Trail Bridge construction (8 districts)
Rural Employment Guarantee Programme Support £3.6m – GON Karnali Employment Program (KEP) in Mid and Far West regions. TA in pilot districts and at the national level. (2 districts) Improving targeting, awareness, wage payment systems, registration, planning and
monitoring, transparency, capacity and coordination with local government. Lessons learned inform a National Employment Guarantee Scheme
Results, Evaluation and Policy support, £1.35m – third party continuous monitoring (8 districts) separate studies to capture lessons on specific issues inform the design of future donor and government programmes.
2
Rural Access ProgrammeDevelopment through access
Strategic SWOT Analysis – 2012
Spending in LRN sector likely to continue to increase over next ten years and outstrip capacity of DDC and DOLIDAR to manage the sector.
Without a substantial improvement in management of the sector SWAp funding aspirations of GON will not be achieved.
Chronic weaknesses that need to be overcome a) span of control -1:75 agencies vs SRN 1:1 agency b) district level planning and implementation c) M&E impact and progress reporting.
These issues will take a long time to solve in terms of GON capacity to manage LRN sector.
GON needs a shorter term strategy
Rural Access ProgrammeDevelopment through access
LRN Outsourcing Strategy Outsourcing to the private sector is probably the best
short term option and will appeal to the donors as well. DOLIDAR should therefore reposition its role as
management agency of the sector by outsourcing planning, design, supervision and M&E to the private sector through area contracts.
Payment for this support could be through TA assistance linked to donor projects or paid out of the LRN works budget.
Negotiate with donors for this in design of next generation projects post 2013.
Rural Access ProgrammeDevelopment through access
Current Span of Control
Rural Access ProgrammeDevelopment through access
Area Based Outsourcing Approach
MOFALD/DOLIDAR/SWAp
Area Contract 1 Area Contract 2 Area 3 Contract Area 4 Contract Area 5 Contract
9 15 16 19 16
DFID ADB SDC WB ADB
DDC’s supported by Area TA’s
Rural Access ProgrammeDevelopment through access
Looking to the Future
Rural Access ProgrammeDevelopment through access
RAP3 Districts
Rural Access ProgrammeDevelopment through access
Budget and Components (GBP)
Rural Access ProgrammeDevelopment through access
District Road Core NetworkNew Construction – (4)
Humla, Mugu, Bajura, Kalikot
Maintenance – (10) Doti, Achham, Dailekh, Jumla Dadeldhura, Parbat, Sindhupalchowk, Morang, Jhapa, Sankhuwasabha
SED (8) Humla, Mugu, Bajura, Kalikot (RAP2 style) Doti, Achham, Dailekh, Jumla
Capacity Building/Policy Harmonisation (14) Doti, Achham, Dailekh, Jumla, Humla, Mugu, Bajura, Kalikot Dadeldhura, Parbat, Sindhupalchowk, Morang, Jhapa, Sankhuwasabha
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
DRCN First Year FundingDistrict
RAP3: Year-1 fund allocation (NPR) Remarks
New construction Improvements Maintenance
(DDF) Total
ACH 0 0 96,000,000 96,000,000 Total allocated annual budget is from the programme and does not include budget from other sources of funding. Total length of 7 new construction corridors is 94.77km
DAD 0 30,173,725 49,826,275 80,000,000
DAI 0 52,296,000 43,704,000 96,000,000
DOT 0 7,346,000 57,654,000 65,000,000
JHA 0 71,175,000 98,825,000 170,000,000
JUM 0 42,606,000 17,394,000 60,000,000
MOR 0 91,205,478 112,794,522 204,000,000
PAR 0 41,703,000 74,297,000 116,000,000
SAN 0 0 84,000,000 84,000,000
SIN 0 0 100,000,000 100,000,000
BAJ 46,620,000 0 0 46,620,000
HUM 80,610,000 0 0 80,610,000
KAL 55,790,000 0 0 55,790,000
MUG 66,590,000 0 0 66,590,000
Total 249,610,000 336,505,203 734,494,797 1,320,610,000 Total (GBP) 1,560,063 2,103,158 4,590,592 8,253,813
Rural Access ProgrammeDevelopment through access
Example of Outsourcing - UK The UK Highways Agency's operations are split into six
regions that are roughly based on the regions of England.
These regions are subdivided into 13 operational areas. These areas are managed and maintained by an Area Team and a contractor, known as a Managing Agent (MA) or Managing Agent Contractor (MAC).
These combine supervision consulting and contracting. In addition, there are a number of sections of road that are managed by DBFO contracts separate from the area teams.
13
Rural Access ProgrammeDevelopment through access
Nepal LRN post 2013 Translated to Nepal a Central TA supports DOLIDAR DOLIDAR keeps its project managers in KTM as now
with Area TA’s supporting DTOs in Districts as per RTI Pilot.
In addition, there will be a number of projects eg SDC Bridges that can be managed through contracts that are separate from the area teams.
Once established and working move towards SWAp funding agreements with donors.
This will probably include elements of World Bank’s Program for Results
14
Rural Access ProgrammeDevelopment through access
Post 2013 New Generation Projects
15
Pursue common set of LRN policies M&E able to demonstrate LRN impact to donors Adopt harmonised Asset Management approach to cover whole of LRN network
o Planning of entire LRN Network o Programming o Maintenance o Upgrading o Rehabilitation o New construction
Demand led TA support through DTMP to reflect capacity of different districts Use of area based clusters of districts for TA support funded by donors. Donor projects adopt single GON led approach and procedures Donor projects provide capacity building to GON staff, especially in management Update 5 year DTMP and make basis for upgrading and rehabilitation of network Use of annual condition surveys for maintenance using ARMP Include Modernisation Fund mechanism and annual support plans for
institutional capacity building Use out sourcing to private sector to improve capacity and governance issues
from 2013
Rural Access ProgrammeDevelopment through access
SWAp Asset Management RAP3 supports GON SWAp programme in 14 districts LRN investment based on District Transport Master
Plans (DTMP). Identify minimum network to link VDC and District HQ-
District Core Road Network (DRCN) New GON policy puts maintenance first; upgrade to all-
weather; new last. DTMPs to guide short, medium and long term
investment by donors and GON ready by Dec. Annual investment based on ARAMP
16
Rural Access ProgrammeDevelopment through access
RAP3 Modality
LRN Maintenance through DDFLRN Upgrading – Start directNew construction – Start directIncome generation – PartnersEconomic infrastructure – Linked to IGCapacity Building – Annual Support Plans
Central GON, Districts DTOs and Private Sector
17
Rural Access ProgrammeDevelopment through access
The key to delivery of the new generation of results based LRN contracts are private sector consultants and contractors.
Can they do it?
Rural Access ProgrammeDevelopment through access
The End
Rural Access ProgrammeDevelopment through access 20
Consultant Procurement & Performance
RAP3 Consultant’s Forum
Bill Seal (Engineering Team Leader)
5th June 2014
Rural Access ProgrammeDevelopment through access 21
Purpose & ContextAn open and honest view of RAP3’s
experiences with our Consultants so far,Overview of the significant performance
issues and deficiencies (generalisations),Ambition:
Not to blame, ‘sling mud’ or squabble,Expose the issues, discuss openly and agree
on how we can improve (Consultant & Client).
Rural Access ProgrammeDevelopment through access 22
Current EngagementsStage-1 Design: 5 num (3 months) – Lump
SumImprovement Design: 3 num (3 months) –
Lump SumConstruction Supervision & Stage-2
Design: 4 num (3 years) – Time BasedLRNAM Support: 10 num (2 years) – Time
BasedTotal: 22 ongoing assignments
Rural Access ProgrammeDevelopment through access 23
Earlier ExperiencesMore than a decade of Consultant
partnerships (RAP1 & RAP2)Presumptions Summarised:
Company involvement low (‘body shops’) Inadequate care (to project / client)High staff turnover / dissatisfied staff / absenteeismLong-vacant positions (following resignations)Competency / skill issues
Rural Access ProgrammeDevelopment through access 24
RAP3 LRN StrategyP4R (‘payment for results’) where possible
Lump Sum / Milestone contractsReward performance
Multi-year contracts with extensions linked to Consultant performance
Time-based contracts for supervision / support assignments due to complexity
Quality & Cost Based Selection (QCBS)Nepal Road Sector Assessment Study
DDCs to outsource services Support development of the Private Sector
Rural Access ProgrammeDevelopment through access 25
Employment of ConsultantsWhy employ Consultants?
Flexibility for changes in work size and scopeManagement of man-power resourceTechnical back-stopping and expertiseChecking and quality assuranceValue for money
The Alternative?Develop large in-house teams (RAP3)?
Rural Access ProgrammeDevelopment through access 26
Service Procurement ChallengesHow to …..
engage competent firms?ensure value for money (judging the
appropriateness of financial bids / relationship of higher fees to better quality?)
encourage assignment of capable / appropriate staff?
retain staff – adequate expenditure on staff employment / facility packages?
Answer: not just to ‘pay higher fee rates’
Rural Access ProgrammeDevelopment through access 27
RAP3’s Procurement ApproachPre-qualification
Standing listsExpression of Interests
Specific & targeted invitation (i.e. on district-wise basis not generic)
Pre-bid Briefing MeetingQCBS
80% technical / 20% financial
Rural Access ProgrammeDevelopment through access 28
Improved ‘Request for Proposals’ (RFP) Chapter limitations:
Standard methodology provided (LS contracts only) Methodology – 7 pages max Comments on ToR – 2 pages max, etc.
CVs: Provide a summary sheet (abstract) Need not be full-time employee (benefit for 6 months previous only) Realistic ceilings on full-mark experience
Staff Provisions: Allowances – to be the same or better than those of the Client Payment of Allowances – will be treated as ‘reimbursable’ items No ‘leave in lieu’ – Client will pay only for periods assigned i.e. rates to be
inclusive (leave, overtime, bonuses etc.) Ethics:
Strong emphasis ‘Whistle blowing’ etc.
Rural Access ProgrammeDevelopment through access 29
Engineer’s Price EstimatesRAP3 intentions:
To promote the payment of ‘good’ rates (better than before)
Support private sector initiativesApproach:
Target adoption of ‘Society of Consulting Architectural & Engineering Firms’ (SCAEF) published schedule of ‘Monthly Billing Rates’
Bench-marking to earlier RAP experiences to gauge VFM
Rural Access ProgrammeDevelopment through access 30
SCAEF Schedule of Fee RatesCurrent version is 2010 (not updated)Quotes a multiplier (OH, fees etc.) of 2.61High at ‘top end’, low at ‘bottom end’
Senior Eng: NRs 267,500 p.m. IoW: NRs 85,600 p.m. AutoCAD Operator: 35,000 p.m.
Applicable for staff with > 15 years exp. 30% reduction 7 to 15 years 60% reduction 3 to 7 years
Some necessary adjustments had to be appliedBenchmarking to RAP2: approx. 30-35% higher (like for
like with inflation)
Rural Access ProgrammeDevelopment through access 31
Technical ProposalsVery little original thought – even in
‘comments / suggestions’Copy and pasteCVs (the biggest scoring section)
poorly presentedsummaries incorrect / overlooked, difficult to
evaluatenomination based on potential score not ability /
suitabilityauthenticity of CV content?
Rural Access ProgrammeDevelopment through access 32
Financial Proposals / NegotiationsPrices widely dispersed (85% - 175% of Estimate)Patterns of bidding:
‘Scatter’ vs. ‘Cluster’ (several clusters ~ 150%) Significant suggestion of collusion / lack of competition
RAP3 negotiation approach: Competition / near Estimate: no negotiation on fees (5 out
of 14 packages) Grossly high / uncompetitive: offered at Estimate (9 out of
14 packages) – all bidders accepted Bidders in negotiated packages all formally agreed:
Rates still sufficient to meet ToR without reduced quality Rates still sufficient to retain staff
Rural Access ProgrammeDevelopment through access 33
Mobilisation / ImplementationSlow mobilisation (far longer than agreed)Immediate staff changes / difficulties in finding
matching replacements (RAP3 provisioned 5% fee reduction for 6 months)
Poor understanding of ‘Inception’ / ability to design / tune an approach (HQ input needed?) Team organisation / logistics Supplementary staff proposals (LRAMS)
Late and poor quality provision of resources (office facilities, transport etc.)
Rural Access ProgrammeDevelopment through access 34
Performance Issues (Firms)1) Late staff payment (pay-when-paid approach) – despite receiving an
advance2) ‘Pay-what-paid’ approach i.e. hints of unpaid leave, unpaid travel etc.3) Professionalism – narrow consideration limited to profit / fees /
cashflow, lacking professional duty on project delivery4) Self-checking absent (reliance on Client)5) Inadequate backstopping (HQ support)6) Slow replacement of unavailable / resigned staff (to the detriment of
project)7) Arbitrary assignment of staff (Lump Sum Contracts)8) Assign inappropriate staff (age, fitness, non-drivers, attitude,
suitability, etc.)9) Lack of responsibility (safety, project delivery / cost control)10) Lack of pride?
Rural Access ProgrammeDevelopment through access 35
Performance Issues (Staff)1) Engineers or Technicians?
Technicians: apply technical procedure accurately, Engineers: direct, solve, evaluate, Interpret, judgement,
research, relevance, VFM, leadership, etc.)2) Over-reliance on software (‘blind’ application)3) Reliance on templates not understanding, inability
to truly ‘design’4) Unquestioned faith in design drawings (however
ridiculous)5) Lacking professional / self development6) Leave management / high absenteeism
Rural Access ProgrammeDevelopment through access 36
Summary of Key Issues - 1Seq Issue Strategy?1. How ‘clean’ is the sector?
If fair competition is absent the procurement approach wont work.
1. SCAEF to promote honour, integrity and professionalism.
2. Clients urge ‘whistle blowing’ and enforce ‘black-listing’
2. Lump-sum contracts unworkable in the present context?
1. Abandon LS approach - make everything input / time based?
2. Introduce Liquidated Damages to combat ‘time at large’ delivery?
3. 80/20% QCBS is not delivering value or competition
1. Adjust the split more in favour of cost say 50/50 or 40/60 (Quality / Cost)
4. Engineers lacking structured professional development
1. SCAEF to move toward introduction of a professional qualification (not merely registration),
2. SCAEF to seek to influence university degree course content, practical training etc.
3. Increase professional training opportunities
Rural Access ProgrammeDevelopment through access 37
Summary of Key Issues - 2Seq Issue Strategy?5. Take responsibility for
their deliverables (Consultants)
1. Consultants to take full responsibility for their service deliverables rather than rely on clients to do their checking and supervision i.e. develop internal systems for quality assurance.
2. Clients need greater redress; introduce requirement for Performance Securities, Indemnity Insurance etc.?
5. Lack of trust (in Consultants by Clients)
1. Earn it through delivery.2. Demonstrate a clean and competitive sector.3. More engagement workshops.
6. Commercial aspects not fully understood by Clients
1. SCAEF to lead in improving their schedule of rates, disseminating and developing credibility
Rural Access ProgrammeDevelopment through access 38
‘Step forward, or backward?’
THANK YOU
Rural Access ProgrammeDevelopment through access
RAP Consultants ForumSome Engineering Do’s and Dont’s
5th June 20147
TIMOTHY J.R STIFF Senior Technical Director (Management Services)
IMC Worldwide Ltd, UK
Rural Access ProgrammeDevelopment through access
Safety, Safety SafetyDo enforce safety on the sites
Hard HatsWellington boots
Gloves and Goggles (especially when breaking rock)
Safety Harness when working on steep slopes
Check that First Aid pack is available and restocked as necessary in good time
Rural Access ProgrammeDevelopment through access
Planning of the WorksDo Discuss, Plan and Agree how the
works are to be carried out
Ensure that everyone in the RBG understand the method of working and emphasise the key safety and
environmental issues Re-Brief as often as required so that
everybody is working to the same plan
Rural Access ProgrammeDevelopment through access
Do check excavation and fill slopes for stability
Do look for signs of slope movement
Such as tension cracks upslope or down slope, loose rocks or stones loose soil etc and warn and take corrective
action in good time
Rural Access ProgrammeDevelopment through access
The Gabions need for properly constructed gabion boxes with tightly wired edges
Do Ensure that only correctly made gabions are used in the works
Rural Access ProgrammeDevelopment through access
Do take care to check the design and detailing of retaining walls
Retaining walls are a large capital investment and need to be dsigned in strict accordance with the RAP procedureCross Sections are required at a minimum of 10 metres along the length of the proposed wall and at least 10 metres past it on each side to ensure the wall geopmentry is appropriate
Rural Access ProgrammeDevelopment through access
Gabion walls
Do bed the gabions in alternate stretcher and header courses so that it can distribute any movement most effectively
Rural Access ProgrammeDevelopment through access
Do provide adequate drainage to the base of the the retaining wall foundation and back of wall drainage on
the wall itself
Rural Access ProgrammeDevelopment through access
Do -Establish Semi permanent chainage markings
Establish chainage markers where they can be seen and on
permanent feature if possible. Re establish as necessary
Rural Access ProgrammeDevelopment through access
Road Drainage The consideration of the drainage of the road is critical in ensuring the
long term stability of the asset. Do consider where the water is going Do Minimise drainage runs to prevent concentration of water at outfalls Optimizing surface cross drainage is often more easily accomplished by
site survey and analysis of an existing segment rather than during the preconstruction phase of road development, as concentration problems and opportunities for their reduction are then readily apparent.
Therefore do visit the road during, or straight after any rains to identify problems
Field inspection of cross drainage needs is especially enlightening during intense climatic events.
Analysis of a road segment from top to bottom allows dealing with concentrations as they develop ,preventing any single concentration from reaching problematical proportions.
Rural Access ProgrammeDevelopment through access
Do pay close attention to cross Drainage Details
Do consider how the water can cross the road especially where large season streams are apparent
Use geotextile or bamboo mats under stone pitching where necessary to ensure that the raod formation does not soften and erode during each rainy season
Closely consider where the water will actually go taking account of the existing grades
Do use the Staged construction approach to fine tune any designs as necessary
Rural Access ProgrammeDevelopment through access
Do look around to identify any potential problems
Familiarity breeds contempt and walking down the same section of road results in one not actually seeing what is there
Don’t take the same short cuts each site visit otherwise lengths of road could not be looked at for long periods
Do write down any issues identified (locating them accurately using the permanent chainage markers that should be visible)
Do identify any addition recommended work in good time with estimates of time and cost implications for discussion with the DTL/EO
Rural Access ProgrammeDevelopment through access
Do Ask!
If you are not sure about any details or cause of a problem - ask don’t leave it to get worse!
Nobody will think any less of you and you may just save a large embarrassment to the Project!
Don’t be afraid to suggest alternative solutions to a problem – you may just have come up with an innovation!
Rural Access ProgrammeDevelopment through access
Thank you for listening
Any questions, comments or observations to share?
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Rural Access ProgrammeDevelopment through access
Supporting the Private Sector – International ExperiencePrivate Sector Workshop
Kirsteen Merrilees
June 2014
Rural Access ProgrammeDevelopment through access
Overview
Strong (Civil) Engineering Sector Examples of Support to Private Sector Private Sector in Nepal
Rural Access ProgrammeDevelopment through access
STRONG (CIVIL) ENGINEERING SECTOR
Rural Access ProgrammeDevelopment through access
Features of a strong sector
Strong Sector
Influence Policy
Environment
Self Regulation
Professional and Ethical Standards
Professional Developmen
t
Performance rewards
Rural Access ProgrammeDevelopment through access
Civil Engineering Sector in UK
Association for Consulting and Engineering register of firms – code of business practice and ethics
Engineering Council regulatory body for engineering profession standards for professional competence, ethics
Institution of Civil Engineers professional development and qualifications influencing government policy and strategy
Rural Access ProgrammeDevelopment through access
Professional Engineers
Professional Engineer
A. Innovation and technology
B. Engineering solutions
C. Management and leadership
D. Communication
skills
E. Professional standard and
ethics
Rural Access ProgrammeDevelopment through access
EXAMPLES OF SUPPORT TO PRIVATE SECTOR
Rural Access ProgrammeDevelopment through access
Projects with PS SupportProject Country DescriptionCross Roads Uganda • Capacity building
• Policy reform (outsourcing)
TAQA Ethiopia • Quality Management System
TA to UNRA Uganda • Model Procurement Documents
IEB Bangladesh • Professional development (ICE)
Rural Access ProgrammeDevelopment through access
ICE support to Bangladesh
Support to Bangladesh Institution of Civil EngineersProfessional QualificationsGraduate training programmeContinuing Professional Development (CPD)
Working with Universities Improve technical contentBroaden curriculum for engineers
Rural Access ProgrammeDevelopment through access
Technical Assistance to Uganda National Road Authority
Improving performance of national road sector through contracts that include / require: detailed TOR (requirements) CD with all technical manuals, specifications etc. Managing and sharing risk (time, quality, budget) Promotion of national resources (incl. expertise) Technical Audit Transfer of Knowledge Consultant QMS and Project Control Plan Address Skills Gap – technical assistants, graduate
development programme
Rural Access ProgrammeDevelopment through access
Technical Assistance for Quality Assurance, Ethiopian Road Authority
Addressing poor quality services through Quality Management Improved procurement & contract management by
ERAClearly defined requirements for service providersCompliance with legal and funding requirementsTraining in QMS requirements Auditing QMS implementation
Rural Access ProgrammeDevelopment through access
Cross Roads - GoalsCreating Opportunities for Sustainable Spending on RoadsCapacity Building
improve services, create opportunities and competitive environment
Improved Government planning long term planning, adequate & consistent funding, regulation, continuous work opportunities
Rural Access ProgrammeDevelopment through access
Cross Roads ApproachesMarket System Approach
tackling underlying causes of market inefficiencies
Policy Reform outsourcing to Private Sector, dedicated Government agency & maintenance funds
Incentives Construction guarantee fund: affordable credit for bid bonds,
performance bonds, equipment Challenge fund: develop innovative solutions to roads issues
Capacity Development Support professional and industry associations to provide better
services Develop skills of association members
Rural Access ProgrammeDevelopment through access
PRIVATE SECTOR IN NEPAL
Rural Access ProgrammeDevelopment through access
Addressing WeaknessesCurrent Weakness Possible solutionLimited sense of professionalism and responsibility within engineering community
• Develop tiered registration within Engineering Council
• Develop formal professional qualification• Develop graduate training programme• Promote Continuing Professional
DevelopmentPoor contract management by all parties
• Strengthen GON planning, procurement and contract management processes
• Improve contract documents, TOR• Training in basic contract management• Enforce contract penalties
No incentive for good performance
• Develop appropriate incentives for individuals and organisations (awards?)
Rural Access ProgrammeDevelopment through access
Addressing WeaknessesCurrent Weakness Possible solutionPoor resource planning and management
• Improve GON planning processes to better fit with construction seasons
• Ensure adequate resource provisions in contracts
• Training of managers in basic resource management (human, financial, physical)
Poor quality management – poor end product
• Develop QMS for standard engineering processes
• Training in basic QMS
Rural Access ProgrammeDevelopment through access
Weak to Strong Private Sector
Poor performance
Weak Sector
Solutions to challenges
• Technical• Management
• Business Environment
• Social and Political
Good Performance
Strong Sector
Rural Access ProgrammeDevelopment through access
Thank you.