SCHOOL BUILDINGS STATUS & ACCOMPLISHMENTS

Presented by:

ROLANDO M. PACURIBOT

Acting City Engineer

ON-GOING PROJECTS

16 CL 3-STOREY (COVERED ROOFDECK) Balulang National High School Building

16 CL 3-STOREY (COVERED ROOFDECK) Macasandig National High School Building

16 CL 3-STOREY (COVERED ROOFDECK) Tablon National High School Building

10 CL 3-STOREY (COVERED ROOFDECK) Camaman-an Elementary School Building

16 CL 3-STOREY (COVERED ROOFDECK) Pagatpat Elementary School Building

21 CL 3-STOREY with Roofdeck P.N. Roa Elementary School Building

8 CL 3-STOREY (COVERED ROOFDECK) Pagatpat National High School Building

8 CL 1-STOREY Dansolihon National High School Building

3 CL 1-STOREY Man-ai National High School Building

6 CL 1-STOREY Tumpagon National High School Building

6 CL 1-STOREY Tuburan National High School Building

16 Classroom 3-Storey (Covered Roofdeck) Balulang National High School (Phase I)

Contract Amount: 14,494,741.70 Date Started: April 25,2014 Actual Accomplishment: 68.00%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

16 Classroom 3-Storey (Covered Roofdeck) Macasandig National High School (Phase I)

Contract Amount: 14,494,061.77Date Started: June 17, 2014Actual Accomplishment: 10.60%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

16 Classroom 3-Storey (Covered Roofdeck) Tablon National High School (Phase I)

Contract Amount: 14,451,175.88 Date Started: June 2, 2014Actual Accomplishment: 5.00%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

10 Classroom 3-Storey (Covered Roofdeck) Camaman-an Elementary School Building (Phase I)Contract Amount: 9,194,173.87Date Started: June 16, 2014Actual Accomplishment: 30.00%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

21 Classroom 3-Storey with Covered RoofdeckP.N. Roa Sr. Elementary School Building

Contract Amount: 25,338,965.05Date Started: June 5, 2014Actual Accomplishment: 25.00%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

8 Classroom 1-Storey Dansolihon National High School Building

Contract Amount: 7,197,202.94Date Started: June 19, 2014Actual Accomplishment: 10.00%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

8 Classroom 3-Storey (Covered Roofdeck) Pagatpat National High School Building

Contract Amount: 11,195,144.70Date Started: June 19, 2014Actual Accomplishment: 10.00%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

16 Classroom 3-Storey (Covered Roofdeck) Pagatpat Elementary School Building

Contract Amount: 19,870,810.32Date Started: June 19, 2014Actual Accomplishment: 2.00%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

3 Classroom 1-Storey Man-ai National High School Building

Contract Amount: 2,847,627.75Date Started: June 19, 2014Actual Accomplishment: 19.52%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

6 Classroom 1-Storey Tuburan National High School Building

Contract Amount: 5,488,839.99Date Started: June 17,2014Actual Accomplishment: 2.00%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

6 Classroom 1-Storey Tumpagon National High School Building

Contract Amount: 5,488,839.99Date Started: June 17, 2014 Actual Accomplishment: 60.80%

“ G i k a n s a K a t a w h a n , I b a l i k s a K a t a w h a n ”

Projects for CAF Issuance:

Proposed 6 CL 2-Storey Macasandig National High SchoolABC: 7,000,000.00

Projects for Bidding:

Proposed 39 CL 3-Storey (Covered Roofdeck) Gusa National High School

ABC: 51,244,863.29

Proposed 14 CL 2-Storey Fr. Masterson Elementary SchoolABC: 15,099,106.90

Proposed 40 CL 2-Storey (2-Buildings) Bugo National High SchoolABC: 41,682,890.99

Summary of Accomplishments:

On Going – 126 Classrooms

For Bidding – 6 Classrooms

For CAF Issuance – 93 Classrooms

TOTAL – 225 ClassroomsTotal Contracted Amount = Php. 130,061,583.96CAF Issued = Php. 153, 261,583.96