Northern Virginia Chapter of the

Construction Specifications InstituteKevin Volbrecht

Deputy Director, Construction

February 13, 2013

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project At-a-Glance

3

Route MapRoute Map

4

Nearing the Finish LineNearing the Finish LineConstruction Marching ForwardConstruction Marching ForwardPhase 1 from I-66 to RestonConstruction of the Dulles Corridor Metrorail Project is under way along the 11.7-mile corridor, from East Falls Church to Reston

CONSTRUCTION IS 88% CONSTRUCTION IS 88%

COMPLETECOMPLETE• Tracks almost complete

• Stations – elevators, escalators, systems being installed

• Pedestrian bridges and pavilions almost complete

• Completion – Summer 2013

• Opening – To Be Determined by WMATA

5 West Falls Church YardWest Falls Church Yard

6West Falls Church YardWest Falls Church Yard

7Orange Line Tie-InOrange Line Tie-In

McLean Station

9McLean Station Pedestrian Bridge Work

10McLean Station Stair and Escalator Installation

11Tysons Corner Station Pedestrian BridgeTysons Corner Station Pedestrian Bridge

12Tysons Corner Station First Span of the Pedestrian Tysons Corner Station First Span of the Pedestrian

BridgeBridge

Tysons Corner StationTysons Corner Station

14 Tunnel Entrance at Route 123

15 Tunnels at Route 123 and Route 7

16 Cut and Cover Tunnel at Route 123 and Route 7

17 Greensboro Station

18Greensboro Station Looking West

19 Spring Hill Station

Guideway from Route 7 to Dulles International Airport Guideway from Route 7 to Dulles International Airport Access Highway/Dulles Toll RoadAccess Highway/Dulles Toll Road

Wiehle-Reston East Station (Wiehle Ave.)(Wiehle Ave.)Wiehle –Reston East StationWiehle –Reston East Station

22 Comstock Development at Wiehle Avenue Station

23Tail Track at Wiehle-Reston East Station

24 Clearance Car Running the Alignment

25

Phase 2Phase 2

• 11.4 –mile extension from Wiehle Avenue in Reston to Ashburn  

• 6 stations:• Reston Town Center• Herndon• Innovation Center• Dulles Airport• Route 606• Route 772/Ashburn

• Rail Yard & Maintenance Facility

• 5 Parking Garages

  

View from Platform to TerminalView from Platform to Terminal

• The Dulles Airport Station will feature an aerial station approximately 1,000 feet north of the terminal near the Daily 2 (North) Garage.

• The station will be linked to the terminal via the existing tunnel that connects with the North Garage and includes a number of moving walkways

Dulles Airport Location DetailsDulles Airport Location Details

Phase 2 StatusPhase 2 Status

Completed Preliminary Engineering

February 2012

Qualifications Information Received

September 2012

Short-list Phase 2 Teams Selected

October 2012

Bechtel Transit PartnersBechtel Infrastructure Corporation

Capital Rail ConstructorsClark Construction Group, LLCKiewit Infrastructure South Co.

Dulles APC RailbuildersArcher Western Contractors, LLCPCL Civil Constructors, Inc.Corman Construction, Inc.

Dulles Metrorail ConnectorsSkanska USA Civil Southeast / Granite Construction CompanyG.A. & F.C. Wagman, Inc. / Trumbull CorporationFacchina Construction Company, Inc.

Silver Line ConstructorsFluor Enterprises, Inc. / Tutor Perini Corporation / Stacy and Witbeck, Inc.

Price Proposals Due April 2013

Contract Awarded May 2013

28

Contact Information

1593 Spring Hill Road Suite 300

Vienna, VA 22182

marcia.mcallister@dullesmetro.com

703-572-0500

www.dullesmetro.com

www.mwaa.com