CE POWER SOLUTIONS FAMILY OF COMPANIES

CE Power - Kentucky

CE Power - Florida

CE Power - Tennessee

Hope Engineering - Michigan

3rd Party NETA Independent Testing Companies

CE Power - Ohio

CE Power - Minnesota

www.cepower.net

800.434.0415

Client Type: Utility-Fossil Power Plant

Challenge/Issue: Due to an aging protection system the client was required to upgrade all plant protection for 600MW steam turbine units, 50MW black start turbine, GSU, (3) auxiliary transformers

Equipment Involved: Protective relays, control cabinets, all components included with cabinets, interconnect cable

Solutions: Provide turnkey solution to include conceptual design, engineering, drawing upates, material procurement, relay cabinet assembly/testing, scheduling, logistics, demolition of existing protection system, installation of new protection system, testing and commissioning

Scope/Deliverables: Turnkey installation of redundant relaying configuration