standard bm monthly report - 2012 03
Post on 30-Oct-2015
18 Views
Preview:
DESCRIPTION
TRANSCRIPT
-
BUILDING MATERIALS PRICES
February-2012 March-2012and
-
Building Materials Prices for Johor
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorOrdinary Portland Cement, bag
Ordinary Portland Cement, 50 kg bag 16.67 16.331 Bag 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorOrdinary Portland Cement, bulk
Ordinary Portland Cement in bulk 310.00 323.332 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorWhite Cement
White Cement 40 kg per bag , collection in MT 744.00 732.333 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorGranite 3/4"
Granite Aggregate 3/4" 22.67 23.004 MT 60 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorNormal River Sand
Normal River Sand- Ex 16.00 15.835 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorFine River Sand
Fine River Sand for Plastering -Ex 24.00 24.676 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorNormal Mining Sand
Normal Mining Sand 16.17 16.337 MT 30 Ex-Factory
Page 2 of9523 April 2012
-
Building Materials Prices for Johor
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorFine Mining Sand
Fine Mining Sand for Plastering 24.00 24.008 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorMild Steel Round Bar
Mild Steel Round Bar R10, MS146 2516.67 2550.009 MT 60 Delivered
Mild Steel Round Bar R12, MS146 2516.67 2550.0010 MT 60 Delivered
Mild Steel Round Bar R16, MS146 2416.67 2450.0011 MT 60 Delivered
Mild Steel Round Bar R20, MS146 2466.67 2500.0012 MT 60 Delivered
Mild Steel Round Bar R22, MS146 2466.67 2500.0013 MT 60 Delivered
Mild Steel Round Bar R25, MS146 2466.67 2500.0014 MT 60 Delivered
Mild Steel Round Bar R32, MS146 2410.00 2500.0015 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorHigh Tensile Deformed Bar
High Tensile Deformed Bar-Y10, MS146 2516.67 2550.0016 MT 60 Delivered
High Tensile Deformed Bar - Y12, MS146 2516.67 2550.0017 MT 60 Delivered
High Tensile Deformed Bar- Y16, MS146 2383.33 2416.6718 MT 60 Delivered
High Tensile Deformed Bar - Y20, MS146 2383.33 2416.6719 MT 60 Delivered
High Tensile Deformed Bar- Y25, MS146 2383.33 2416.6720 MT 60 Delivered
Page 3 of9523 April 2012
-
Building Materials Prices for Johor
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorHigh Tensile Deformed Bar
High Tensile Deformed Bar- Y32, MS146 2383.33 2416.6721 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorBRC Fabric
BRC A6, MS145 6.12 6.1222 m2 30 Delivered
BRC A7, MS145 8.22 8.2223 m2 30 Delivered
BRC A8, MS145 10.86 10.8624 m2 30 Delivered
BRC A9, MS145 13.79 13.7925 m2 30 Delivered
BRC A10, MS145 16.51 16.5126 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorReady Mix Concrete-Granite
Ready Mix Concrete - Normal Mix - Grade 10,Granite
171.30 171.9727 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 15,Granite
177.47 183.8028 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 20,Granite
184.60 188.2729 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 25,Granite
191.53 196.5330 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 30,Granite
198.87 203.2031 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Granite
213.80 217.4732 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Granite
228.33 232.0033 m3 30 Delivered
Page 4 of9523 April 2012
-
Building Materials Prices for Johor
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorCommon Clay Bricks
Common Clay Bricks - Pallet 0.40 0.4034 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorCement Sand Bricks
Cement Sand Brick - Pallet 0.24 0.2435 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorSmooth Face Facing Bricks
Smooth Face Facing Brick, Red 1.05 1.1536 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorConcrete Roof Tiles
Interlocking Concrete Tiles - Standard DuotoneColour (Monier Elabana)
1.55 1.5537 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorMetal Sheet Decking
MS Decking - Lysaght Colourbond- Spandek Hi-Ten 0.47mm TCT
51.10 52.4038 m2 30 Delivered
MS Decking - Lysaght Colourbond -Kliplok Hi-Ten0.53mm TCT
56.57 56.5739 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorCorrugated Roofing Sheet
Corrugated Roofing Sheet- 76mm Double Width,1065mm x 2440mm x 4mm (Hume/Malex/UAC)
24.83 27.7340 Sheet 60 Delivered
Page 5 of9523 April 2012
-
Building Materials Prices for Johor
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorCeramic Floor Tiles
Glazed Ceramic Floor Tiles, Standard Light Colour200mm x 200mm x 8mm - Grade 1
0.98 0.9341 Piece 60 Delivered
Glazed Ceramic Floor Tiles, Standard Light Colour300mm x 300mm x 8mm - Grade 1
1.84 1.8442 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorHomogeneous Ceramic Tiles
Plain Homogeneous Floor Tiles, Standard LightColour 200mm x 200mm x 8mm - Grade 1
1.34 1.3443 Piece 60 Delivered
Plain Homogeneous Floor Tiles, Standard LightColour 300mm x 300mm x 8mm - Grade 1
2.50 2.3744 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorPaver
Uni-Espave - 200mm x 190mm 0.89 0.8945 Piece 60 Delivered
Uni-Pave/ Sunpave, 225mm x 112.5mm 0.84 0.8446 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorPlain Cellulose Fibre
Plain Cellulose Fibre Ceiling Sheet, 610mm x1220mm x 3.2mm (UAC/ HUME/ MALEX)
3.92 3.9247 Sheet 60 Delivered
Plain Cellulose Fibre Ceiling Sheet, 610mm x1220mm x 4.5mm (UAC / Hume/ Malex)
6.78 6.7848 Sheet 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorGypsum Ceiling Board
Plain Gypsum Ceiling Board, 610mm x 1220mm x9.5mm (Boral/Armstrong)
4.97 4.9749 Sheet 60 Delivered
Page 6 of9523 April 2012
-
Building Materials Prices for Johor
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorTimber door
Solid Decorative Timber Door 3' x 7' (Branded),Certified by SIRIM
212.00 212.0050 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorGI Pipes
Galvanised Iron Pipes Class A- 20mm Diameter(Maruichi), MS863
35.50 35.5051 6mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorPVC Pipes
PVC Pressure Pipes Class D, Grey Colour- 50mmDiameter (Paling), MS 628
26.10 26.1052 4mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorHDPE Pipes
HDPE Pipe PN 10 - 50mm Diameter, MS1058 427.67 427.6753 100mroll
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorABS Pipes
ABS Pipe PN 15 Class E - 20mm, MS1419 23.23 23.2354 5.8mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorPolytank
Polyethylene Water Tank (Polytank) - Circular, 100Gallons, MS1225 - Weida Equivelant
118.57 118.5755 No. 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorWash Hand Basin
Wash Hand Basin - 560mm x 406mm, WhiteColour - Jacqueline WB 142, Claytan
71.47 71.4756 Set 60 Delivered
Page 7 of9523 April 2012
-
Building Materials Prices for Johor
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorWater Closets
Water Closet Western Type - WC 644, WhiteColour Without Cistern, Claytan
139.10 139.1057 Item 60 Delivered
Water Closet Eastern Type- Bengal ACBL-000,Without Cistern,White Colour, Johnson-Suisse
53.50 53.5058 Item 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorStainless Steel Sink
Stainless Steel Sinks - Single Bowl Single Drainer -Lay OnType, 42'' x 18''
82.57 82.5759 Item 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorNippon
Paint - Nippon Standard Colour - Gloss Oilbase,9000 Gloss Finish
95.67 95.6760 5Litres
60 Delivered
Paint - Nippon Standard Colour - Internal EmulsionLuxury, Waterbase, Satin Glo
88.73 88.7361 5Litres
60 Delivered
Paint - Nippon - Internal Emulsion WaterbaseFinish, Standard Colour - Super Matex
31.67 31.6762 7Litres
60 Delivered
Paint - Nippon Standard Colour - External AcrylicEmulsion, Weatherbond
95.47 95.4763 5Litres
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorSquare Hollow Sections
Square Hollow Sections - 50mm x 50mm x 3.0mm(4.38kg/m)
3182.67 3182.6764 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorRectangular Hollow Sections
Rectangular Hollow Sections - 150mm x 100mm x4.5mm (16.9kg/m)
3347.67 3347.6765 MT 60 Delivered
Page 8 of9523 April 2012
-
Building Materials Prices for Johor
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorUniversal Beams
Universal Beams - 356mm x 368mm x 13.33mm(162.2kg/m)
3500.00 3500.0066 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorEqual Angles
Equal Angles - 50mm x 50mm x 4mm (3.06kg/m) 2581.33 2581.3367 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
JohorPlywood
Plywood - Shuttering Board, 4' x 8' x 12mm 53.27 53.2768 Piece 60 Delivered
Plywood - Shuttering Board, 4' x 8' x 25mm 1stGrade
134.00 134.0069 Piece 60 Delivered
Page 9 of9523 April 2012
-
Building Materials Prices for Kelantan
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanOrdinary Portland Cement, bag
Ordinary Portland Cement, 50 kg bag 16.70 16.701 Bag 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanOrdinary Portland Cement, bulk
Ordinary Portland Cement in bulk 330.00 330.002 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanWhite Cement
White Cement 40 kg per bag , collection in MT 744.00 732.333 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanGranite 3/4"
Granite Aggregate 3/4" 25.67 25.674 MT 60 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanNormal River Sand
Normal River Sand- Ex 10.67 10.675 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanFine River Sand
Fine River Sand for Plastering -Ex 18.33 18.336 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanNormal Mining Sand
Normal Mining Sand 15.67 15.677 MT 30 Ex-Factory
Page 10 of9523 April 2012
-
Building Materials Prices for Kelantan
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanFine Mining Sand
Fine Mining Sand for Plastering 21.00 21.008 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanMild Steel Round Bar
Mild Steel Round Bar R10, MS146 2583.33 2616.679 MT 60 Delivered
Mild Steel Round Bar R12, MS146 2583.33 2616.6710 MT 60 Delivered
Mild Steel Round Bar R16, MS146 2483.33 2516.6711 MT 60 Delivered
Mild Steel Round Bar R20, MS146 2533.33 2566.6712 MT 60 Delivered
Mild Steel Round Bar R22, MS146 2533.33 2566.6713 MT 60 Delivered
Mild Steel Round Bar R25, MS146 2533.33 2566.6714 MT 60 Delivered
Mild Steel Round Bar R32, MS146 2533.33 2566.6715 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanHigh Tensile Deformed Bar
High Tensile Deformed Bar-Y10, MS146 2583.33 2616.6716 MT 60 Delivered
High Tensile Deformed Bar - Y12, MS146 2583.33 2616.6717 MT 60 Delivered
High Tensile Deformed Bar- Y16, MS146 2450.00 2483.3318 MT 60 Delivered
High Tensile Deformed Bar - Y20, MS146 2450.00 2483.3319 MT 60 Delivered
High Tensile Deformed Bar- Y25, MS146 2450.00 2483.3320 MT 60 Delivered
Page 11 of9523 April 2012
-
Building Materials Prices for Kelantan
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanHigh Tensile Deformed Bar
High Tensile Deformed Bar- Y32, MS146 2450.00 2483.3321 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanBRC Fabric
BRC A6, MS145 6.65 6.7222 m2 30 Delivered
BRC A7, MS145 8.79 8.7923 m2 30 Delivered
BRC A8, MS145 12.07 12.0724 m2 30 Delivered
BRC A9, MS145 15.29 15.2925 m2 30 Delivered
BRC A10, MS145 17.83 17.8326 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanReady Mix Concrete-Granite
Ready Mix Concrete - Normal Mix - Grade 10,Granite
186.63 186.6327 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 15,Granite
192.13 192.1328 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 20,Granite
195.93 195.9329 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 25,Granite
204.20 204.2030 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 30,Granite
212.83 212.8331 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Granite
223.13 223.1332 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Granite
238.00 238.0033 m3 30 Delivered
Page 12 of9523 April 2012
-
Building Materials Prices for Kelantan
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanCommon Clay Bricks
Common Clay Bricks - Pallet 0.46 0.4634 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanCement Sand Bricks
Cement Sand Brick - Pallet 0.28 0.2835 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanSmooth Face Facing Bricks
Smooth Face Facing Brick, Red 1.17 1.2036 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanConcrete Roof Tiles
Interlocking Concrete Tiles - Standard DuotoneColour (Monier Elabana)
1.73 1.7337 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanMetal Sheet Decking
MS Decking - Lysaght Colourbond- Spandek Hi-Ten 0.47mm TCT
54.00 54.0038 m2 30 Delivered
MS Decking - Lysaght Colourbond -Kliplok Hi-Ten0.53mm TCT
57.63 57.6339 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanCorrugated Roofing Sheet
Corrugated Roofing Sheet- 76mm Double Width,1065mm x 2440mm x 4mm (Hume/Malex/UAC)
28.67 28.6740 Sheet 60 Delivered
Page 13 of9523 April 2012
-
Building Materials Prices for Kelantan
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanCeramic Floor Tiles
Glazed Ceramic Floor Tiles, Standard Light Colour200mm x 200mm x 8mm - Grade 1
0.97 0.9741 Piece 60 Delivered
Glazed Ceramic Floor Tiles, Standard Light Colour300mm x 300mm x 8mm - Grade 1
1.90 1.9042 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanHomogeneous Ceramic Tiles
Plain Homogeneous Floor Tiles, Standard LightColour 200mm x 200mm x 8mm - Grade 1
1.38 1.3843 Piece 60 Delivered
Plain Homogeneous Floor Tiles, Standard LightColour 300mm x 300mm x 8mm - Grade 1
2.42 2.4044 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanPaver
Uni-Espave - 200mm x 190mm 1.01 1.0145 Piece 60 Delivered
Uni-Pave/ Sunpave, 225mm x 112.5mm 0.97 0.9746 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanPlain Cellulose Fibre
Plain Cellulose Fibre Ceiling Sheet, 610mm x1220mm x 3.2mm (UAC/ HUME/ MALEX)
3.92 3.9247 Sheet 60 Delivered
Plain Cellulose Fibre Ceiling Sheet, 610mm x1220mm x 4.5mm (UAC / Hume/ Malex)
7.18 7.1848 Sheet 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanGypsum Ceiling Board
Plain Gypsum Ceiling Board, 610mm x 1220mm x9.5mm (Boral/Armstrong)
4.97 4.9749 Sheet 60 Delivered
Page 14 of9523 April 2012
-
Building Materials Prices for Kelantan
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanTimber door
Solid Decorative Timber Door 3' x 7' (Branded),Certified by SIRIM
257.00 257.0050 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanGI Pipes
Galvanised Iron Pipes Class A- 20mm Diameter(Maruichi), MS863
35.40 35.4051 6mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanPVC Pipes
PVC Pressure Pipes Class D, Grey Colour- 50mmDiameter (Paling), MS 628
28.87 29.2052 4mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanHDPE Pipes
HDPE Pipe PN 10 - 50mm Diameter, MS1058 437.90 437.9053 100mroll
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanABS Pipes
ABS Pipe PN 15 Class E - 20mm, MS1419 24.17 24.1754 5.8mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanPolytank
Polyethylene Water Tank (Polytank) - Circular, 100Gallons, MS1225 - Weida Equivelant
121.90 121.9055 No. 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanWash Hand Basin
Wash Hand Basin - 560mm x 406mm, WhiteColour - Jacqueline WB 142, Claytan
71.47 71.4756 Set 60 Delivered
Page 15 of9523 April 2012
-
Building Materials Prices for Kelantan
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanWater Closets
Water Closet Western Type - WC 644, WhiteColour Without Cistern, Claytan
142.77 142.7757 Item 60 Delivered
Water Closet Eastern Type- Bengal ACBL-000,Without Cistern,White Colour, Johnson-Suisse
54.17 54.1758 Item 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanStainless Steel Sink
Stainless Steel Sinks - Single Bowl Single Drainer -Lay OnType, 42'' x 18''
82.57 82.5759 Item 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanNippon
Paint - Nippon Standard Colour - Gloss Oilbase,9000 Gloss Finish
98.27 98.2760 5Litres
60 Delivered
Paint - Nippon Standard Colour - Internal EmulsionLuxury, Waterbase, Satin Glo
91.07 91.0761 5Litres
60 Delivered
Paint - Nippon - Internal Emulsion WaterbaseFinish, Standard Colour - Super Matex
31.67 31.6762 7Litres
60 Delivered
Paint - Nippon Standard Colour - External AcrylicEmulsion, Weatherbond
97.47 97.4763 5Litres
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanSquare Hollow Sections
Square Hollow Sections - 50mm x 50mm x 3.0mm(4.38kg/m)
3213.67 3213.6764 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanRectangular Hollow Sections
Rectangular Hollow Sections - 150mm x 100mm x4.5mm (16.9kg/m)
3258.33 3258.3365 MT 60 Delivered
Page 16 of9523 April 2012
-
Building Materials Prices for Kelantan
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanUniversal Beams
Universal Beams - 356mm x 368mm x 13.33mm(162.2kg/m)
3350.67 3350.6766 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanEqual Angles
Equal Angles - 50mm x 50mm x 4mm (3.06kg/m) 2583.33 2583.3367 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KelantanPlywood
Plywood - Shuttering Board, 4' x 8' x 12mm 53.93 53.9368 Piece 60 Delivered
Plywood - Shuttering Board, 4' x 8' x 25mm 1stGrade
130.67 134.0069 Piece 60 Delivered
Page 17 of9523 April 2012
-
Building Materials Prices for Kota Kinabalu
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluOrdinary Portland Cement, bag
Ordinary Portland Cement, 50 kg bag - (30) 17.20 17.201 Bag 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluWhite Cement
White Cement 25kg per bag , collection in MT - (30) 880.00 880.002 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluGranite 3/4"
Granite Aggregate 3/4" - (30) 54.33 54.673 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluSandstone
Sandstone Aggregates 3/4" 48.67 49.334 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluNormal River Sand
Normal River Sand - Delivery 39.33 40.005 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluFine River Sand
Fine River Sand for Plastering- Delivery 43.33 43.676 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluMild Steel Round Bar
Mild Steel Round Bar R10, MS146 - (30) 2750.00 2750.007 MT 30 Delivered
Mild Steel Round Bar R12, MS146 - (30) 2700.00 2750.008 MT 30 Delivered
Page 18 of9523 April 2012
-
Building Materials Prices for Kota Kinabalu
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluMild Steel Round Bar
Mild Steel Round Bar R16, MS146 - (30) 2650.00 2630.009 MT 30 Delivered
Mild Steel Round Bar R20, MS146 - (30) 2650.00 2900.0010 MT 30 Delivered
Mild Steel Round Bars - R25, MS146 - (30) 2650.00 2900.0011 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluHigh Tensile Deformed Bar
High Tensile Deformed Bar Y10, MS146 - (30) 2800.00 2750.0012 MT 60 Delivered
High Tensile Deformed Bar Y12, MS146 - (30) 2750.00 2750.0013 MT 60 Delivered
High Tensile Deformed Bar Y16, MS146 - (30) 2700.00 2630.0014 MT 60 Delivered
High Tensile Deformed Bar Y20, MS146 - (30) 2700.00 2630.0015 MT 60 Delivered
High Tensile Deformed Bar Y25, MS146 - (30) 2700.00 2630.0016 MT 60 Delivered
High Tensile Deformed Bar Y32, MS146 - (30) 2700.00 2630.0017 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluBRC Fabric
BRC A6, MS145 8.50 8.5018 m2 30 Delivered
BRC A7, MS145 9.50 9.5019 m2 30 Delivered
BRC A8, MS145 12.50 12.4720 m2 30 Delivered
BRC A9, MS145 16.00 16.0021 m2 30 Delivered
Page 19 of9523 April 2012
-
Building Materials Prices for Kota Kinabalu
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluBRC Fabric
BRC A10, MS145 19.33 19.3322 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluReady Mix Concrete-Granite
Ready Mix Concrete - Normal Mix - Grade 30,Granite
290.00 290.0023 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Granite
308.33 310.0024 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Granite
320.00 320.0025 m3 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluReady Mix Concrete-Sandstone
Ready Mix Concrete - Normal Mix - Grade 10 ,Sandstone - (30)
215.00 216.6726 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 15,Sandstone- (30)
223.33 225.0027 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 20,Sandstone- (30)
233.33 233.3328 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 25 ,Sandstone- (30)
243.33 245.0029 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 30 ,Sandstone- (30)
288.33 291.6730 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Sandstone- (30)
320.00 325.0031 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Sandstone- (30)
306.67 311.6732 m3 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluCommon Clay Bricks
Common Clay Bricks - Pallet 0.32 0.3233 Piece 30 Delivered
Page 20 of9523 April 2012
-
Building Materials Prices for Kota Kinabalu
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluCement Sand Bricks
Cement Sand Bricks - Pallet -(30) 0.30 0.3034 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluSmooth Face Facing Bricks
Smooth Face Facing Brick, Red 0.85 0.8535 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluConcrete Roof Tiles
Interlocking Concrete Tiles - Standard DuotoneColour, Local Product - (30)
1.77 1.7736 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluMetal Sheet Decking
MS Decking - Lysaght Colourbond- Spandek Hi-Ten 0.48mm TCT -(30)
53.67 54.6737 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluCorrugated Roofing Sheet
Corrugated Roofing Sheet- 76mm Double Width,1065mm x 2440mm (Hume/Malex/UAC) - (30)
31.33 31.6738 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluCeramic Floor Tiles
Glazed Ceramic Floor Tiles - Standard Light Colour- 200mm x 200mm x 8mm - (30)
1.68 1.7039 Piece 30 Delivered
Glazed Ceramic Tiles -Standard Light Colour300mm x 300mm x 8mm Thick - (30)
3.48 3.5040 Piece 30 Delivered
Page 21 of9523 April 2012
-
Building Materials Prices for Kota Kinabalu
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluHomogeneous Ceramic Tiles
Plain Homogeneous Ceramic Tiles - Standard LightColour 200mm x 200mm x 8mm Thick - (30)
3.00 3.0041 Piece 30 Delivered
Plain Homogeneous Ceramic Tiles - Standard LightColour 300mm x 300mm x 8mm Thick - (30)
4.50 4.5042 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluPaver
Uni-Espave- 200mm x 190mm - (30) 1.42 1.4343 Piece 30 Delivered
Uni-Pave/ Sunpave, 225mm x 112.5mm - (30) 1.33 1.3344 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluPlain Cellulose Fibre
Plain Cellulose Fibre Ceiling Sheet 1220mm x1220mm x 3.2mm - (30)
9.00 9.0045 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluGypsum Ceiling Board
Plain Gypsum Ceiling Board, 610mm x 1220mm x4.5mm (Boral/Armstrong)- (30)
7.50 7.5046 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluTimber door
Solid Wooden Timber Door, 3' x 7' (Handmade) -(30)
261.00 263.3347 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluGI Pipes
Galvanised Iron Pipes - Class B, 20mm Diameter,MS863 - (30)
63.33 64.0048 6mrun
30 Delivered
Page 22 of9523 April 2012
-
Building Materials Prices for Kota Kinabalu
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluPVC Pipes
PVC Pressure Pipes Class E, Grey Colour -50mmDiameter, MS 628- (30)
38.33 38.6749 6mrun
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluHDPE Pipes
HDPE Pipe PN 10 - 50mm Diameter, MS1058 -(30)
710.00 718.3350 100mroll
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluABS Pipes
ABS Pipe PN 15 Class E - 20mm, MS1419 - (30) 18.33 18.6751 5.8mrun
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluPolytank
Polyethylene Water Tank (Polytank) - Circular, 100Gallons, MS1225 - (30)
163.33 165.0052 No. 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluWash Hand Basin
Wash Basin- Ripley L-57,White Colour, KIMWARE- (30)
43.67 43.6753 Set 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluWater Closets
Water Closet Eastern Type -Kingston 1, C-28 S/P -Squatting Pan (back inlet) S or P trap,Without
65.00 65.3354 Item 30 Delivered
Water Closet Western Type - Baltimore, C-56Syphonic W.C. With S or P trap, With Cistern,
183.33 185.0055 Set 30 Delivered
Page 23 of9523 April 2012
-
Building Materials Prices for Kota Kinabalu
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluStainless Steel Sink
Stainless Steel Sinks - Single Bowl Single Drainer -Lay On Type, 106CM X 45CM - (30)
85.00 87.0056 Item 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluNippon
Paint - Nippon Standard Colour - External AcrylicEmulsion, Weatherbond - (30)
100.00 100.0057 5Litres
30 Delivered
Paint - Nippon Standard Colour - Internal Emulsion,Luxury, Waterbase, Satin Glo -(30)
85.00 85.3358 5Litres
30 Delivered
Paint - Nippon - Internal Emulsion Waterbase,Standard Colour - Super Matex - (30)
44.33 44.6759 7Litres
30 Delivered
Paint - Nippon -Standard Colour , Gloss Oil Base -9000 Gloss Finish - (30)
96.00 96.3360 5Litres
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluSquare Hollow Sections
Square Hollow Sections - 50mm x 50mm x 3.0mm(4.38kg/m) -- (30)
2883.33 2900.0061 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluRectangular Hollow Sections
Rectangular Hollow Sections - 150mm x 100mm x4.5mm (16.9kg/m)- (30)
3900.00 3900.0062 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluUniversal Beams
Universal Beams - 300mm x 300mm x 3.0mm(96.73kg/m)- (30)
3366.67 3400.0063 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluEqual Angles
Equal Angles - 50mm x 50mm x 4mm (3.06kg/m) -(30)
2383.33 2400.0064 MT 30 Delivered
Page 24 of9523 April 2012
-
Building Materials Prices for Kota Kinabalu
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Kota KinabaluPlywood
Plywood - Shuttering Board, 4' x 8' x 12mm - (30) 77.00 76.3365 Piece 30 Delivered
Plywood - Shuttering Board, 4' x 8' x 25mm 1stGrade - (30)
157.00 157.0066 Piece 30 Delivered
Page 25 of9523 April 2012
-
Building Materials Prices for Kuching
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingOrdinary Portland Cement, bag
Ordinary Portland Cement, 50 kg bag - (30) 15.80 15.801 Bag 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingWhite Cement
White Cement 25kg per bag , collection in MT - (30) 840.00 831.672 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingGranite 3/4"
Granite Aggregate 3/4" - (30) 36.00 36.003 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingLimestone
Limestone Aggregates 3/4" 28.00 28.004 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingNormal River Sand
Normal River Sand - Delivery 31.67 32.005 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingFine River Sand
Fine River Sand for Plastering- Delivery 35.00 35.006 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingMild Steel Round Bar
Mild Steel Round Bar R10, MS146 - (30) 2700.00 2650.007 MT 30 Delivered
Mild Steel Round Bar R12, MS146 - (30) 2650.00 2650.008 MT 30 Delivered
Page 26 of9523 April 2012
-
Building Materials Prices for Kuching
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingMild Steel Round Bar
Mild Steel Round Bar R16, MS146 - (30) 2600.00 2530.009 MT 30 Delivered
Mild Steel Round Bar R20, MS146 - (30) 2600.00 2800.0010 MT 30 Delivered
Mild Steel Round Bars - R25, MS146 - (30) 2600.00 2800.0011 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingHigh Tensile Deformed Bar
High Tensile Deformed Bar Y10, MS146 - (30) 2750.00 2650.0012 MT 60 Delivered
High Tensile Deformed Bar Y12, MS146 - (30) 2700.00 2650.0013 MT 60 Delivered
High Tensile Deformed Bar Y16, MS146 - (30) 2600.00 2550.0014 MT 60 Delivered
High Tensile Deformed Bar Y20, MS146 - (30) 2600.00 2550.0015 MT 60 Delivered
High Tensile Deformed Bar Y25, MS146 - (30) 2600.00 2550.0016 MT 60 Delivered
High Tensile Deformed Bar Y32, MS146 - (30) 2600.00 2550.0017 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingBRC Fabric
BRC A6, MS145 7.00 7.0018 m2 30 Delivered
BRC A7, MS145 9.00 8.5019 m2 30 Delivered
BRC A8, MS145 12.00 11.6320 m2 30 Delivered
BRC A9, MS145 15.00 14.4321 m2 30 Delivered
Page 27 of9523 April 2012
-
Building Materials Prices for Kuching
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingBRC Fabric
BRC A10, MS145 18.50 17.8022 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingReady Mix Concrete-Granite
Ready Mix Concrete - Normal Mix - Grade 30,Granite
288.00 288.3323 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Granite
303.33 303.3324 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Granite
301.67 301.6725 m3 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingReady Mix Concrete-Sandstone
Ready Mix Concrete - Normal Mix - Grade 10 ,Sandstone - (30)
220.00 217.6726 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 15,Sandstone- (30)
220.00 220.0027 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 20,Sandstone- (30)
233.33 230.0028 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 25 ,Sandstone- (30)
255.00 253.3329 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 30 ,Sandstone- (30)
263.33 261.0030 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Sandstone- (30)
280.00 280.0031 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Sandstone- (30)
300.00 300.0032 m3 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingCommon Clay Bricks
Common Clay Bricks - Pallet 0.30 0.3033 Piece 30 Delivered
Page 28 of9523 April 2012
-
Building Materials Prices for Kuching
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingCement Sand Bricks
Cement Sand Bricks - Pallet -(30) 0.32 0.3234 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingConcrete Roof Tiles
Interlocking Concrete Tiles - Standard DuotoneColour, Shanta- (30)
1.28 1.2835 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingMetal Sheet Decking
MS Decking - Lysaght Colourbond- Spandek Hi-Ten 0.48mm TCT -(30)
55.00 54.6736 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingCorrugated Roofing Sheet
Corrugated Roofing Sheet- 76mm (3'') DoubleWidth, Grey 1065mm x 2440mm - (30)
32.00 32.3337 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingCeramic Floor Tiles
Glazed Ceramic Floor Tiles - Standard Light Colour- 200mm x 200mm x 8mm - (30)
1.00 1.0038 Piece 30 Delivered
Glazed Ceramic Tiles -Standard Light Colour300mm x 300mm x 8mm Thick - (30)
3.00 3.0039 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingHomogeneous Ceramic Tiles
Plain Homogeneous Ceramic Tiles - Standard LightColour 200mm x 200mm x 8mm Thick - (30)
3.00 3.0040 Piece 30 Delivered
Plain Homogeneous Ceramic Tiles - Standard LightColour 300mm x 300mm x 8mm Thick - (30)
4.13 4.1741 Piece 30 Delivered
Page 29 of9523 April 2012
-
Building Materials Prices for Kuching
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingPaver
Uni-Espave- 200mm x 190mm - (30) 1.00 1.0042 Piece 30 Delivered
Uni-Pave/ Sunpave, 225mm x 112.5mm - (30) 1.00 1.0043 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingPlain Cellulose Fibre
Plain Cellulose Fibre Ceiling Sheet 1220mm x1220mm x 3.2mm - (30)
9.00 8.8344 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingGypsum Ceiling Board
Plain Gypsum Ceiling Board, 610mm x 1220mm x4.5mm (Boral/Armstrong)- (30)
7.60 7.5345 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingTimber door
Solid Wooden Timber Door, 3' x 7' (Handmade) -(30)
313.33 311.6746 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingGI Pipes
Galvanised Iron Pipes - Class B, 20mm Diameter,MS863 - (30)
57.33 56.6747 6mrun
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingPVC Pipes
PVC Pressure Pipes Class E, Grey Colour -50mmDiameter, MS 628- (30)
38.67 38.6748 6mrun
30 Delivered
Page 30 of9523 April 2012
-
Building Materials Prices for Kuching
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingHDPE Pipes
HDPE Pipe PN 10 - 50mm Diameter, MS1058 -(30)
726.67 725.0049 100mroll
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingABS Pipes
ABS Pipe PN 15 Class E - 20mm, MS1419 - (30) 18.33 18.6750 5.8mrun
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingPolytank
Polyethylene Water Tank (Polytank) - Circular, 100Gallons, MS1225 - (30)
161.67 163.3351 No. 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingWash Hand Basin
Wash Basin- Ripley L-57,White Colour, KIMWARE- (30)
60.67 61.6752 Set 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingWater Closets
Water Closet Eastern Type -Kingston 1, C-28 S/P -Squatting Pan (back inlet) S or P trap,Without
66.33 64.3353 Item 30 Delivered
Water Closet Western Type - Camelot C - 74Washdown W.C With S-trap, With Cistern.White
205.00 201.6754 Set 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingStainless Steel Sink
Stainless Steel Sinks - Single Bowl Single Drainer -Lay On Type, 106CM X 45CM - (30)
78.00 78.6755 Item 30 Delivered
Page 31 of9523 April 2012
-
Building Materials Prices for Kuching
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingNippon
Paint - Nippon Standard Colour - External AcrylicEmulsion, Weatherbond - (30)
101.67 100.0056 5Litres
30 Delivered
Paint - Nippon Standard Colour - Internal Emulsion,Luxury, Waterbase, Satin Glo -(30)
83.67 84.3357 5Litres
30 Delivered
Paint - Nippon - Internal Emulsion Waterbase,Standard Colour - Super Matex - (30)
33.00 33.0058 7Litres
30 Delivered
Paint - Nippon -Standard Colour , Gloss Oil Base -9000 Gloss Finish - (30)
80.00 80.0059 5Litres
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingSquare Hollow Sections
Square Hollow Sections - 50mm x 50mm x 3.0mm(4.38kg/m) -- (30)
2810.00 2816.6760 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingRectangular Hollow Sections
Rectangular Hollow Sections - 150mm x 100mm x4.5mm (16.9kg/m)- (30)
3016.67 3000.0061 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingUniversal Beams
Universal Beams - 300mm x 300mm x 3.0mm(96.73kg/m)- (30)
3366.67 3350.0062 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingEqual Angles
Equal Angles - 50mm x 50mm x 4mm (3.06kg/m) -(30)
2816.67 2816.6763 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingPlywood
Plywood - Shuttering Board, 4' x 8' x 12mm - (30) 70.00 70.0064 Piece 30 Delivered
Page 32 of9523 April 2012
-
Building Materials Prices for Kuching
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
KuchingPlywood
Plywood - Shuttering Board, 4' x 8' x 25mm 1stGrade - (30)
163.33 163.3365 Piece 30 Delivered
Page 33 of9523 April 2012
-
Building Materials Prices for Miri
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriOrdinary Portland Cement, bag
Ordinary Portland Cement, 50 kg bag - (30) 17.00 17.001 Bag 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriWhite Cement
White Cement 25kg per bag , collection in MT - (30) 860.00 860.002 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriLimestone
Limestone Aggregates 3/4" 32.00 32.003 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriNormal River Sand
Normal River Sand - Delivery 31.00 31.004 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriFine River Sand
Fine River Sand for Plastering- Delivery 34.00 34.005 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriMild Steel Round Bar
Mild Steel Round Bar R10, MS146 - (30) 2750.00 2680.006 MT 30 Delivered
Mild Steel Round Bar R12, MS146 - (30) 2700.00 2680.007 MT 30 Delivered
Mild Steel Round Bar R16, MS146 - (30) 2600.00 2560.008 MT 30 Delivered
Mild Steel Round Bar R20, MS146 - (30) 2650.00 2850.009 MT 30 Delivered
Page 34 of9523 April 2012
-
Building Materials Prices for Miri
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriMild Steel Round Bar
Mild Steel Round Bars - R25, MS146 - (30) 2650.00 2850.0010 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriHigh Tensile Deformed Bar
High Tensile Deformed Bar Y10, MS146 - (30) 2800.00 2700.0011 MT 60 Delivered
High Tensile Deformed Bar Y12, MS146 - (30) 2750.00 2700.0012 MT 60 Delivered
High Tensile Deformed Bar Y16, MS146 - (30) 2700.00 2600.0013 MT 60 Delivered
High Tensile Deformed Bar Y20, MS146 - (30) 2700.00 2600.0014 MT 60 Delivered
High Tensile Deformed Bar Y25, MS146 - (30) 2700.00 2600.0015 MT 60 Delivered
High Tensile Deformed Bar Y32, MS146 - (30) 2700.00 2600.0016 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriBRC Fabric
BRC A6, MS145 8.43 8.5017 m2 30 Delivered
BRC A7, MS145 10.50 10.4318 m2 30 Delivered
BRC A8, MS145 13.53 13.1719 m2 30 Delivered
BRC A9, MS145 16.57 16.1720 m2 30 Delivered
BRC A10, MS145 20.83 20.6721 m2 30 Delivered
Page 35 of9523 April 2012
-
Building Materials Prices for Miri
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriReady Mix Concrete-Granite
Ready Mix Concrete - Normal Mix - Grade 30,Granite
296.67 293.3322 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Granite
316.67 318.3323 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Granite
323.33 320.0024 m3 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriReady Mix Concrete-Sandstone
Ready Mix Concrete - Normal Mix - Grade 10 ,Sandstone - (30)
223.33 223.3325 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 15,Sandstone- (30)
235.33 233.3326 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 20,Sandstone- (30)
246.67 246.6727 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 25 ,Sandstone- (30)
258.33 253.3328 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 30 ,Sandstone- (30)
270.67 270.0029 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Sandstone- (30)
283.33 283.3330 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Sandstone- (30)
290.00 288.3331 m3 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriCommon Clay Bricks
Common Clay Bricks - Pallet 0.34 0.3432 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriCement Sand Bricks
Cement Sand Bricks - Pallet -(30) 0.33 0.3333 Piece 30 Delivered
Page 36 of9523 April 2012
-
Building Materials Prices for Miri
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriConcrete Roof Tiles
Interlocking Concrete Tiles - Standard DuotoneColour, Shanta- (30)
1.30 1.2834 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriMetal Sheet Decking
MS Decking - Lysaght Colourbond- Spandek Hi-Ten 0.48mm TCT -(30)
52.67 51.6735 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriCorrugated Roofing Sheet
Corrugated Roofing Sheet- 76mm (3'') DoubleWidth, Grey 1065mm x 2440mm - (30)
33.00 32.6736 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriCeramic Floor Tiles
Glazed Ceramic Floor Tiles - Standard Light Colour- 200mm x 200mm x 8mm - (30)
1.00 1.0037 Piece 30 Delivered
Glazed Ceramic Tiles -Standard Light Colour300mm x 300mm x 8mm Thick - (30)
3.00 3.0038 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriHomogeneous Ceramic Tiles
Plain Homogeneous Ceramic Tiles - Standard LightColour 200mm x 200mm x 8mm Thick - (30)
3.20 3.0739 Piece 30 Delivered
Plain Homogeneous Ceramic Tiles - Standard LightColour 300mm x 300mm x 8mm Thick - (30)
4.50 4.4340 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriPaver
Uni-Espave- 200mm x 190mm - (30) 1.20 1.2041 Piece 30 Delivered
Uni-Pave/ Sunpave, 225mm x 112.5mm - (30) 1.03 1.0342 Piece 30 Delivered
Page 37 of9523 April 2012
-
Building Materials Prices for Miri
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriPaver
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriPlain Cellulose Fibre
Plain Cellulose Fibre Ceiling Sheet 1220mm x1220mm x 3.2mm - (30)
9.50 9.4343 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriGypsum Ceiling Board
Plain Gypsum Ceiling Board, 610mm x 1220mm x4.5mm (Boral/Armstrong)- (30)
8.00 8.0044 Sheet 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriTimber door
Solid Wooden Timber Door, 3' x 7' (Handmade) -(30)
285.00 285.0045 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriGI Pipes
Galvanised Iron Pipes - Class B, 20mm Diameter,MS863 - (30)
65.33 65.0046 6mrun
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriPVC Pipes
PVC Pressure Pipes Class E, Grey Colour -50mmDiameter, MS 628- (30)
42.00 42.3347 6mrun
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriHDPE Pipes
HDPE Pipe PN 10 - 50mm Diameter, MS1058 -(30)
745.00 746.6748 100mroll
30 Delivered
Page 38 of9523 April 2012
-
Building Materials Prices for Miri
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriABS Pipes
ABS Pipe PN 15 Class E - 20mm, MS1419 - (30) 17.67 17.3349 5.8mrun
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriPolytank
Polyethylene Water Tank (Polytank) - Circular, 100Gallons, MS1225 - (30)
166.00 165.6750 No. 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriWash Hand Basin
Wash Basin- Ripley L-57,White Colour, KIMWARE- (30)
57.00 55.3351 Set 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriWater Closets
Water Closet Eastern Type -Kingston 1, C-28 S/P -Squatting Pan (back inlet) S or P trap,Without
68.00 67.0052 Item 30 Delivered
Water Closet Western Type - Camelot C - 74Washdown W.C With S-trap, With Cistern.White
200.00 200.0053 Set 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriStainless Steel Sink
Stainless Steel Sinks - Single Bowl Single Drainer -Lay On Type, 106CM X 45CM - (30)
74.33 74.3354 Item 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriNippon
Paint - Nippon Standard Colour - External AcrylicEmulsion, Weatherbond - (30)
100.00 99.3355 5Litres
30 Delivered
Paint - Nippon Standard Colour - Internal Emulsion,Luxury, Waterbase, Satin Glo -(30)
85.67 85.6756 5Litres
30 Delivered
Paint - Nippon - Internal Emulsion Waterbase,Standard Colour - Super Matex - (30)
32.33 32.6757 7Litres
30 Delivered
Page 39 of9523 April 2012
-
Building Materials Prices for Miri
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriNippon
Paint - Nippon -Standard Colour , Gloss Oil Base -9000 Gloss Finish - (30)
75.33 74.6758 5Litres
30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriSquare Hollow Sections
Square Hollow Sections - 50mm x 50mm x 3.0mm(4.38kg/m) -- (30)
2960.00 2960.0059 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriRectangular Hollow Sections
Rectangular Hollow Sections - 150mm x 100mm x4.5mm (16.9kg/m)- (30)
3100.00 3066.6760 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriUniversal Beams
Universal Beams - 300mm x 300mm x 3.0mm(96.73kg/m)- (30)
3366.67 3366.6761 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriEqual Angles
Equal Angles - 50mm x 50mm x 4mm (3.06kg/m) -(30)
2966.67 2966.6762 MT 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
MiriPlywood
Plywood - Shuttering Board, 4' x 8' x 12mm - (30) 75.00 75.0063 Piece 30 Delivered
Plywood - Shuttering Board, 4' x 8' x 25mm 1stGrade - (30)
167.67 167.0064 Piece 30 Delivered
Page 40 of9523 April 2012
-
Building Materials Prices for Pahang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangOrdinary Portland Cement, bag
Ordinary Portland Cement, 50 kg bag 16.70 16.701 Bag 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangOrdinary Portland Cement, bulk
Ordinary Portland Cement in bulk 330.00 330.002 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangWhite Cement
White Cement 40 kg per bag , collection in MT 732.33 732.333 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangGranite 3/4"
Granite Aggregate 3/4" 24.00 24.004 MT 60 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangNormal River Sand
Normal River Sand- Ex 9.00 9.005 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangFine River Sand
Fine River Sand for Plastering -Ex 11.00 11.006 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangNormal Mining Sand
Normal Mining Sand 16.33 16.337 MT 30 Ex-Factory
Page 41 of9523 April 2012
-
Building Materials Prices for Pahang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangFine Mining Sand
Fine Mining Sand for Plastering 21.33 21.338 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangMild Steel Round Bar
Mild Steel Round Bar R10, MS146 2583.33 2616.679 MT 60 Delivered
Mild Steel Round Bar R12, MS146 2533.33 2566.6710 MT 60 Delivered
Mild Steel Round Bar R16, MS146 2400.00 2433.3311 MT 60 Delivered
Mild Steel Round Bar R20, MS146 2483.33 2516.6712 MT 60 Delivered
Mild Steel Round Bar R22, MS146 2483.33 2500.0013 MT 60 Delivered
Mild Steel Round Bar R25, MS146 2483.33 2516.6714 MT 60 Delivered
Mild Steel Round Bar R32, MS146 2483.33 2516.6715 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangHigh Tensile Deformed Bar
High Tensile Deformed Bar-Y10, MS146 2500.00 2533.3316 MT 60 Delivered
High Tensile Deformed Bar - Y12, MS146 2533.33 2566.6717 MT 60 Delivered
High Tensile Deformed Bar- Y16, MS146 2400.00 2433.3318 MT 60 Delivered
High Tensile Deformed Bar - Y20, MS146 2400.00 2433.3319 MT 60 Delivered
High Tensile Deformed Bar- Y25, MS146 2400.00 2433.3320 MT 60 Delivered
Page 42 of9523 April 2012
-
Building Materials Prices for Pahang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangHigh Tensile Deformed Bar
High Tensile Deformed Bar- Y32, MS146 2400.00 2433.3321 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangBRC Fabric
BRC A6, MS145 6.47 6.4722 m2 30 Delivered
BRC A7, MS145 9.03 9.0323 m2 30 Delivered
BRC A8, MS145 11.48 11.4824 m2 30 Delivered
BRC A9, MS145 14.38 14.3825 m2 30 Delivered
BRC A10, MS145 17.48 17.4826 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangReady Mix Concrete-Granite
Ready Mix Concrete - Normal Mix - Grade 10,Granite
175.97 175.9727 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 15,Granite
181.47 181.4728 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 20,Granite
188.60 188.0029 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 25,Granite
194.20 194.2030 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 30,Granite
206.53 206.5331 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Granite
213.80 210.4732 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Granite
230.17 230.1733 m3 30 Delivered
Page 43 of9523 April 2012
-
Building Materials Prices for Pahang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangCommon Clay Bricks
Common Clay Bricks - Pallet 0.42 0.4234 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangCement Sand Bricks
Cement Sand Brick - Pallet 0.24 0.2435 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangSmooth Face Facing Bricks
Smooth Face Facing Brick, Red 1.20 1.2036 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangConcrete Roof Tiles
Interlocking Concrete Tiles - Standard DuotoneColour (Monier Elabana)
1.56 1.5637 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangMetal Sheet Decking
MS Decking - Lysaght Colourbond- Spandek Hi-Ten 0.47mm TCT
54.00 54.0038 m2 30 Delivered
MS Decking - Lysaght Colourbond -Kliplok Hi-Ten0.53mm TCT
57.63 57.6339 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangCorrugated Roofing Sheet
Corrugated Roofing Sheet- 76mm Double Width,1065mm x 2440mm x 4mm (Hume/Malex/UAC)
29.07 29.0740 Sheet 60 Delivered
Page 44 of9523 April 2012
-
Building Materials Prices for Pahang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangCeramic Floor Tiles
Glazed Ceramic Floor Tiles, Standard Light Colour200mm x 200mm x 8mm - Grade 1
0.93 0.9341 Piece 60 Delivered
Glazed Ceramic Floor Tiles, Standard Light Colour300mm x 300mm x 8mm - Grade 1
1.93 1.8442 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangHomogeneous Ceramic Tiles
Plain Homogeneous Floor Tiles, Standard LightColour 200mm x 200mm x 8mm - Grade 1
1.34 1.3443 Piece 60 Delivered
Plain Homogeneous Floor Tiles, Standard LightColour 300mm x 300mm x 8mm - Grade 1
2.31 2.3144 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangPaver
Uni-Espave - 200mm x 190mm 0.87 0.8745 Piece 60 Delivered
Uni-Pave/ Sunpave, 225mm x 112.5mm 0.84 0.8446 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangPlain Cellulose Fibre
Plain Cellulose Fibre Ceiling Sheet, 610mm x1220mm x 3.2mm (UAC/ HUME/ MALEX)
3.85 3.8547 Sheet 60 Delivered
Plain Cellulose Fibre Ceiling Sheet, 610mm x1220mm x 4.5mm (UAC / Hume/ Malex)
6.83 6.7048 Sheet 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangGypsum Ceiling Board
Plain Gypsum Ceiling Board, 610mm x 1220mm x9.5mm (Boral/Armstrong)
4.97 4.9749 Sheet 60 Delivered
Page 45 of9523 April 2012
-
Building Materials Prices for Pahang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangTimber door
Solid Decorative Timber Door 3' x 7' (Branded),Certified by SIRIM
245.33 245.3350 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangGI Pipes
Galvanised Iron Pipes Class A- 20mm Diameter(Maruichi), MS863
35.93 35.9351 6mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangPVC Pipes
PVC Pressure Pipes Class D, Grey Colour- 50mmDiameter (Paling), MS 628
27.37 27.3352 4mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangHDPE Pipes
HDPE Pipe PN 10 - 50mm Diameter, MS1058 407.13 407.1353 100mroll
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangABS Pipes
ABS Pipe PN 15 Class E - 20mm, MS1419 23.00 23.0054 5.8mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangPolytank
Polyethylene Water Tank (Polytank) - Circular, 100Gallons, MS1225 - Weida Equivelant
120.67 120.6755 No. 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangWash Hand Basin
Wash Hand Basin - 560mm x 406mm, WhiteColour - Jacqueline WB 142, Claytan
70.60 70.6056 Set 60 Delivered
Page 46 of9523 April 2012
-
Building Materials Prices for Pahang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangWater Closets
Water Closet Western Type - WC 644, WhiteColour Without Cistern, Claytan
135.80 135.8057 Item 60 Delivered
Water Closet Eastern Type- Bengal ACBL-000,Without Cistern,White Colour, Johnson-Suisse
55.53 55.5358 Item 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangStainless Steel Sink
Stainless Steel Sinks - Single Bowl Single Drainer -Lay OnType, 42'' x 18''
84.47 84.4759 Item 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangNippon
Paint - Nippon Standard Colour - Gloss Oilbase,9000 Gloss Finish
100.27 100.2760 5Litres
60 Delivered
Paint - Nippon Standard Colour - Internal EmulsionLuxury, Waterbase, Satin Glo
91.13 91.1361 5Litres
60 Delivered
Paint - Nippon - Internal Emulsion WaterbaseFinish, Standard Colour - Super Matex
31.67 31.7762 7Litres
60 Delivered
Paint - Nippon Standard Colour - External AcrylicEmulsion, Weatherbond
99.67 97.0063 5Litres
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangSquare Hollow Sections
Square Hollow Sections - 50mm x 50mm x 3.0mm(4.38kg/m)
3159.33 3159.3364 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangRectangular Hollow Sections
Rectangular Hollow Sections - 150mm x 100mm x4.5mm (16.9kg/m)
3277.33 3277.3365 MT 60 Delivered
Page 47 of9523 April 2012
-
Building Materials Prices for Pahang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangUniversal Beams
Universal Beams - 356mm x 368mm x 13.33mm(162.2kg/m)
3191.33 3234.6766 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangEqual Angles
Equal Angles - 50mm x 50mm x 4mm (3.06kg/m) 2533.33 2533.3367 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PahangPlywood
Plywood - Shuttering Board, 4' x 8' x 12mm 50.57 50.5768 Piece 60 Delivered
Plywood - Shuttering Board, 4' x 8' x 25mm 1stGrade
113.57 113.5769 Piece 60 Delivered
Page 48 of9523 April 2012
-
Building Materials Prices for Perak
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakOrdinary Portland Cement, bag
Ordinary Portland Cement, 50 kg bag 14.70 15.871 Bag 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakOrdinary Portland Cement, bulk
Ordinary Portland Cement in bulk 315.00 316.672 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakWhite Cement
White Cement 40 kg per bag , collection in MT 744.00 732.333 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakGranite 3/4"
Granite Aggregate 3/4" 22.67 22.674 MT 60 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakNormal River Sand
Normal River Sand- Ex 10.00 10.005 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakFine River Sand
Fine River Sand for Plastering -Ex 11.33 11.676 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakNormal Mining Sand
Normal Mining Sand 10.33 10.337 MT 30 Ex-Factory
Page 49 of9523 April 2012
-
Building Materials Prices for Perak
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakFine Mining Sand
Fine Mining Sand for Plastering 11.33 11.338 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakMild Steel Round Bar
Mild Steel Round Bar R10, MS146 2583.33 2550.009 MT 60 Delivered
Mild Steel Round Bar R12, MS146 2583.33 2550.0010 MT 60 Delivered
Mild Steel Round Bar R16, MS146 2450.00 2416.6711 MT 60 Delivered
Mild Steel Round Bar R20, MS146 2533.33 2500.0012 MT 60 Delivered
Mild Steel Round Bar R22, MS146 2533.33 2500.0013 MT 60 Delivered
Mild Steel Round Bar R25, MS146 2533.33 2500.0014 MT 60 Delivered
Mild Steel Round Bar R32, MS146 2533.33 2500.0015 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakHigh Tensile Deformed Bar
High Tensile Deformed Bar-Y10, MS146 2583.33 2550.0016 MT 60 Delivered
High Tensile Deformed Bar - Y12, MS146 2583.33 2600.0017 MT 60 Delivered
High Tensile Deformed Bar- Y16, MS146 2450.00 2416.6718 MT 60 Delivered
High Tensile Deformed Bar - Y20, MS146 2500.00 2466.6719 MT 60 Delivered
High Tensile Deformed Bar- Y25, MS146 2450.00 2416.6720 MT 60 Delivered
Page 50 of9523 April 2012
-
Building Materials Prices for Perak
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakHigh Tensile Deformed Bar
High Tensile Deformed Bar- Y32, MS146 2450.00 2416.6721 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakBRC Fabric
BRC A6, MS145 6.40 6.0322 m2 30 Delivered
BRC A7, MS145 9.17 9.2123 m2 30 Delivered
BRC A8, MS145 11.66 11.7524 m2 30 Delivered
BRC A9, MS145 13.47 13.5625 m2 30 Delivered
BRC A10, MS145 17.76 17.6826 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakReady Mix Concrete-Granite
Ready Mix Concrete - Normal Mix - Grade 10,Granite
164.60 164.6027 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 15,Granite
162.73 172.4028 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 20,Granite
163.20 172.8729 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 25,Granite
170.80 180.8030 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 30,Granite
187.77 191.4331 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Granite
195.07 201.7332 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Granite
204.43 204.4333 m3 30 Delivered
Page 51 of9523 April 2012
-
Building Materials Prices for Perak
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakCommon Clay Bricks
Common Clay Bricks - Pallet 0.40 0.4034 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakCement Sand Bricks
Cement Sand Brick - Pallet 0.23 0.2435 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakSmooth Face Facing Bricks
Smooth Face Facing Brick, Red 1.07 1.0836 Piece 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakConcrete Roof Tiles
Interlocking Concrete Tiles - Standard DuotoneColour (Monier Elabana)
1.76 1.6737 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakMetal Sheet Decking
MS Decking - Lysaght Colourbond- Spandek Hi-Ten 0.47mm TCT
52.90 52.9038 m2 30 Delivered
MS Decking - Lysaght Colourbond -Kliplok Hi-Ten0.53mm TCT
56.23 56.2339 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakCorrugated Roofing Sheet
Corrugated Roofing Sheet- 76mm Double Width,1065mm x 2440mm x 4mm (Hume/Malex/UAC)
26.73 27.7340 Sheet 60 Delivered
Page 52 of9523 April 2012
-
Building Materials Prices for Perak
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakCeramic Floor Tiles
Glazed Ceramic Floor Tiles, Standard Light Colour200mm x 200mm x 8mm - Grade 1
0.96 0.9341 Piece 60 Delivered
Glazed Ceramic Floor Tiles, Standard Light Colour300mm x 300mm x 8mm - Grade 1
1.88 1.8442 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakHomogeneous Ceramic Tiles
Plain Homogeneous Floor Tiles, Standard LightColour 200mm x 200mm x 8mm - Grade 1
1.34 1.2743 Piece 60 Delivered
Plain Homogeneous Floor Tiles, Standard LightColour 300mm x 300mm x 8mm - Grade 1
2.51 2.3744 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakPaver
Uni-Espave - 200mm x 190mm 0.90 0.8745 Piece 60 Delivered
Uni-Pave/ Sunpave, 225mm x 112.5mm 0.84 0.8446 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakPlain Cellulose Fibre
Plain Cellulose Fibre Ceiling Sheet, 610mm x1220mm x 3.2mm (UAC/ HUME/ MALEX)
3.85 3.8547 Sheet 60 Delivered
Plain Cellulose Fibre Ceiling Sheet, 610mm x1220mm x 4.5mm (UAC / Hume/ Malex)
6.48 6.4848 Sheet 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakGypsum Ceiling Board
Plain Gypsum Ceiling Board, 610mm x 1220mm x9.5mm (Boral/Armstrong)
4.97 4.9749 Sheet 60 Delivered
Page 53 of9523 April 2012
-
Building Materials Prices for Perak
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakTimber door
Solid Decorative Timber Door 3' x 7' (Branded),Certified by SIRIM
195.33 195.3350 Piece 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakGI Pipes
Galvanised Iron Pipes Class A- 20mm Diameter(Maruichi), MS863
37.50 33.0751 6mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakPVC Pipes
PVC Pressure Pipes Class D, Grey Colour- 50mmDiameter (Paling), MS 628
26.00 25.3352 4mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakHDPE Pipes
HDPE Pipe PN 10 - 50mm Diameter, MS1058 405.90 400.9053 100mroll
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakABS Pipes
ABS Pipe PN 15 Class E - 20mm, MS1419 23.13 23.1354 5.8mrun
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakPolytank
Polyethylene Water Tank (Polytank) - Circular, 100Gallons, MS1225 - Weida Equivelant
120.90 120.9055 No. 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakWash Hand Basin
Wash Hand Basin - 560mm x 406mm, WhiteColour - Jacqueline WB 142, Claytan
76.47 71.4756 Set 60 Delivered
Page 54 of9523 April 2012
-
Building Materials Prices for Perak
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakWater Closets
Water Closet Western Type - WC 644, WhiteColour Without Cistern, Claytan
141.80 141.8057 Item 60 Delivered
Water Closet Eastern Type- Bengal ACBL-000,Without Cistern,White Colour, Johnson-Suisse
54.17 54.1758 Item 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakStainless Steel Sink
Stainless Steel Sinks - Single Bowl Single Drainer -Lay OnType, 42'' x 18''
82.57 82.5759 Item 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakNippon
Paint - Nippon Standard Colour - Gloss Oilbase,9000 Gloss Finish
98.00 98.2760 5Litres
60 Delivered
Paint - Nippon Standard Colour - Internal EmulsionLuxury, Waterbase, Satin Glo
91.07 91.0761 5Litres
60 Delivered
Paint - Nippon - Internal Emulsion WaterbaseFinish, Standard Colour - Super Matex
31.43 31.4362 7Litres
60 Delivered
Paint - Nippon Standard Colour - External AcrylicEmulsion, Weatherbond
96.67 96.6763 5Litres
60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakSquare Hollow Sections
Square Hollow Sections - 50mm x 50mm x 3.0mm(4.38kg/m)
3154.33 3154.3364 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakRectangular Hollow Sections
Rectangular Hollow Sections - 150mm x 100mm x4.5mm (16.9kg/m)
3245.33 3245.3365 MT 60 Delivered
Page 55 of9523 April 2012
-
Building Materials Prices for Perak
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakUniversal Beams
Universal Beams - 356mm x 368mm x 13.33mm(162.2kg/m)
3191.33 3234.6766 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakEqual Angles
Equal Angles - 50mm x 50mm x 4mm (3.06kg/m) 2533.33 2533.3367 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
PerakPlywood
Plywood - Shuttering Board, 4' x 8' x 12mm 52.27 52.2768 Piece 60 Delivered
Plywood - Shuttering Board, 4' x 8' x 25mm 1stGrade
118.33 118.3369 Piece 60 Delivered
Page 56 of9523 April 2012
-
Building Materials Prices for Pulau Pinang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangOrdinary Portland Cement, bag
Ordinary Portland Cement, 50 kg bag 15.37 15.871 Bag 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangOrdinary Portland Cement, bulk
Ordinary Portland Cement in bulk 316.67 316.672 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangWhite Cement
White Cement 40 kg per bag , collection in MT 744.00 732.333 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangGranite 3/4"
Granite Aggregate 3/4" 23.00 23.334 MT 60 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangNormal River Sand
Normal River Sand- Ex 14.00 14.005 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangFine River Sand
Fine River Sand for Plastering -Ex 18.00 17.676 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangNormal Mining Sand
Normal Mining Sand 17.33 17.337 MT 30 Ex-Factory
Page 57 of9523 April 2012
-
Building Materials Prices for Pulau Pinang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangFine Mining Sand
Fine Mining Sand for Plastering 16.00 16.008 MT 30 Ex-Factory
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangMild Steel Round Bar
Mild Steel Round Bar R10, MS146 2500.00 2550.009 MT 60 Delivered
Mild Steel Round Bar R12, MS146 2500.00 2550.0010 MT 60 Delivered
Mild Steel Round Bar R16, MS146 2400.00 2433.3311 MT 60 Delivered
Mild Steel Round Bar R20, MS146 2450.00 2500.0012 MT 60 Delivered
Mild Steel Round Bar R22, MS146 2533.33 2500.0013 MT 60 Delivered
Mild Steel Round Bar R25, MS146 2533.33 2500.0014 MT 60 Delivered
Mild Steel Round Bar R32, MS146 2583.33 2550.0015 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangHigh Tensile Deformed Bar
High Tensile Deformed Bar-Y10, MS146 2550.00 2516.6716 MT 60 Delivered
High Tensile Deformed Bar - Y12, MS146 2583.33 2550.0017 MT 60 Delivered
High Tensile Deformed Bar- Y16, MS146 2450.00 2416.6718 MT 60 Delivered
High Tensile Deformed Bar - Y20, MS146 2450.00 2416.6719 MT 60 Delivered
High Tensile Deformed Bar- Y25, MS146 2450.00 2416.6720 MT 60 Delivered
Page 58 of9523 April 2012
-
Building Materials Prices for Pulau Pinang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangHigh Tensile Deformed Bar
High Tensile Deformed Bar- Y32, MS146 2450.00 2416.6721 MT 60 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangBRC Fabric
BRC A6, MS145 6.73 6.7022 m2 30 Delivered
BRC A7, MS145 8.38 8.3823 m2 30 Delivered
BRC A8, MS145 12.00 10.7524 m2 30 Delivered
BRC A9, MS145 15.13 13.5625 m2 30 Delivered
BRC A10, MS145 16.37 16.3726 m2 30 Delivered
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangReady Mix Concrete-Granite
Ready Mix Concrete - Normal Mix - Grade 10,Granite
174.47 174.7727 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 15,Granite
188.27 188.2728 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 20,Granite
190.40 190.4029 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 25,Granite
198.33 198.3330 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 30,Granite
206.30 206.3031 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 35,Granite
215.93 215.9332 m3 30 Delivered
Ready Mix Concrete - Normal Mix - Grade 40,Granite
226.97 226.9733 m3 30 Delivered
Page 59 of9523 April 2012
-
Building Materials Prices for Pulau Pinang
UnitCredit Term
(Days) Del or ExDescription
No.
Feb-2012(RM)
Mar-2012(RM)
Pulau PinangCommon Clay Bricks
Common Clay Bricks - Pallet 0
top related