statistical analysis of new product development (npd) cycle-time data

Post on 29-Nov-2014

210 Views

Category:

Engineering

3 Downloads

Preview:

Click to see full reader

DESCRIPTION

Alpha Technologies recently concluded a comprehensive study of historical NPD performance data (cost, cycle-time, resource requirements, program type and complexity, plans versus actuals, etc.) and has successfully applied the results of this study to make measureable improvements to their NPD process. Probability-based summary data is used to aide in planning and budgeting, set statistically valid continuous improvement targets for performance scorecards, and develop a visual resource management tool for allocation of human resources to present and future NPD programs.

TRANSCRIPT

Quality and Business Excellence

Celebration

ASQ Vancouver 25th Anniversary

Statistical Analysis of New Product Development (NPD) Cycle-time Data Including Applications of Results

Steve Pratt, MEng., PE, CSSBB Director of Engineering, Alpha Technologies

Alpha Technologies

Company Background

Alpha is a Full Service Power

Systems Provider to Multiple Markets

Pratt – Slide 1

Power Modules

Indoor Power Systems

Outdoor Power Systems

Alpha’s Power Solutions Products

Pratt – Slide 2

Phase-Gate New Product

Development (NPD) Process

Deliverables: • Product Concept • Business Case • Preliminary Plan

Deliverables: •High-Level Design •Requirements •Complete Project Plan

Deliverables: • Design Outputs • DFx Reviews • Preliminary Test

Reports

Deliverables: • Pilot Doc Pack • Pilot Build • Sales Forecasts

Deliverables: • Compliance

Certifications • Training • MarCom docs

Deliverables: • Sustaining Eng • Repair/Support • Cost Reduction

Phase 2 Planning

Phase 1 Concept

Phase 3 Development

Phase 4 Qualification and Pre-Production

Phase 5 LA and Production Ramp-up

Phase 6 GA and MOL

Pratt – Slide 3

Concurrent Engineering via Cross-

Functional Core Teams

Service Supply Chain

Product Management

Program Manager

Quality

Engineering

Manufacturing

Pratt – Slide 4

Motivation for Study

Continuous Improvement:

• general perception that NPD takes too long

• lack of proper management of resources

• desire to establish performance benchmarks

Pratt – Slide 5

NPD Data Collected and Analyzed

Schedule Data

• Recorded Dates: Start, Gate 1, Gate 2, Gate 3, Gate 4 (LA) & Gate 5 (GA)

• Program Plans: estimated time to LA, estimated time to GA

• Calculated: total time, time per phase, actual vs. plan

Cost Data

• Timecard System: actual total effort (man-hours)

• Program Plans: estimated total effort

• Calculated: effort by function, effort by phase, remaining effort, actual vs. plan

Pratt – Slide 6

Tools Used in the Study

JMP – Statistical Discovery Software Analyze-Distribution Platform: • Calculations: Quantiles, Moments • Plots: Histogram, Quantile Box, Normal Quantile • Fit Distribution: Normal, Beta, Goodness of Fit Tests

Fit Y by X Platform: Bivariate Analysis • Fit Line, Fit Polynomial, Summary of Fit

Fit Y by X Platform: One-way Analysis • Calculations: Means and Standard Deviations • Plots: Mean Diamonds • Analysis of Variance (ANOVA)

Fit Model Platform • Calculations: Standard Least Squares, Summary of Fit, Effect Tests • Plots: Actual by Predicted, Effect Leverage, Residual by Predicted • Two-way ANOVA with interactions

Microsoft Excel and PowerPoint

Pratt – Slide 7

External Benchmarking Data – PDMA

Best Practices Research

Provides industry-average NPD Cycle-Time based on complexity of programs:

• new-to-the world • new-to-the firm • next-gen improvements • incremental improvements

Pratt – Slide 8

Source: Griffin A., “Product development cycle time for business-to-business products,” Industrial Marketing Management 2002;31: 291-304 *

Average NPD Cycle-Time Benchmarking

Pratt – Slide 9

Planned vs. Actual NPD Cycle-Time

Pratt – Slide 10

ANOVA to Identify Significant Factors

for Schedule Data

Pratt – Slide 11

ANOVA to Identify Significant Factors

for Effort Data

Pratt – Slide 12

Categorizing NPD Programs into 9

Buckets

Product Types:

Modules (power modules, shelves, controllers) Indoor Systems (rack-based systems, racks, distribution) OSP (outside plant power/battery systems)

Program Complexities:

A – major program requiring advanced development B – completely new, but no advanced development C – new with incremental development

Pratt – Slide 13

NPD Summary Data –

Schedule (Gate 2 to LA)

Pratt – Slide 14

NPD Summary Data –

Schedule (Gate 2 to GA)

Pratt – Slide 15

NPD Summary Data –

Effort (Total Development Hours)

Pratt – Slide 16

NPD Schedule & Effort Continuous

Probability Distributions

Pratt – Slide 17

Additional Analyses

• plan vs. actual – schedule and effort

• schedule and effort variance by phase

• time spent per phase

• total effort by function and phase

• default team size and composition

Pratt – Slide 18

Applications

Better Estimating

Pratt – Slide 19

More Accurate Gate 2 Point Estimates

of Schedule and Effort

Previous estimates were:

- subject to negotiation

- overly optimistic and aggressive

- “rose-colored” recollections of past

Pratt – Slide 20

Alpha’s Historical Schedule

Estimation Accuracy

Median MRE = 44%

Pratt – Slide 21

NPD Schedule Point-Estimation via

Historical Mean Values

Median MRE = 19%

Pratt – Slide 22

Basic Schedule Equation Using Historical Mean Effort Values

Median MRE = 21%

Pratt – Slide 23

Informal Comparisons Equation Using

NPD Mean Values

Median MRE = 20%

Pratt – Slide 24

Mean Magnitude of Relative Error –

Schedule Estimates

Pratt – Slide 25

Alpha’s Historical Effort

Estimation Accuracy

Median MRE = 36%

Pratt – Slide 26

NPD Effort Point-Estimation via

Historical Mean Values

Median MRE = 18%

Pratt – Slide 27

Mean Magnitude of Relative Error –

Effort Estimates

Pratt – Slide 28

Determine the “Cone of Uncertainty”

Pratt – Slide 29

Cone of Uncertainty for NPD Project

Estimates

Pratt – Slide 30

Cone of Uncertainty for NPD Project

Schedule Data

Pratt – Slide 31

Cone of Uncertainty Applied to the 9

NPD Project Buckets

Pratt – Slide 32

Schedule Cone of Uncertainty Quantified by Program Phase

Pratt – Slide 33

Effort Cone of Uncertainty Quantified

by Program Phase

Pratt – Slide 34

Effort Estimate Ranges by Program

Phase

Pratt – Slide 35

Applications

Top-Down Project Planning

Pratt – Slide 36

Creation of Top-Down Program

Schedules

Pratt – Slide 37

NPD – Time Spent per Phase

Pratt – Slide 38

How Much Time Should Be Spent on

Planning?

Pratt – Slide 39

Applications

Performance Goal Setting

Pratt – Slide 40

SMART Performance Improvement

Goals

• fact-based and statistically valid

• objective and quantifiable

• deterministic at the start of a program

• consistent across all types of programs

• an enabler of continuous improvement

• unambiguous and easy to calculate

An ideal performance improvement measure is:

Pratt – Slide 41

RSD: a Normalized Measure of

Dispersion

Pratt – Slide 42

Program Scoring: RSD as Performance

Unit-of-Measure

Pratt – Slide 43

2013 NPD Cycle-Time Performance

Pratt – Slide 44

Earned-Value Milestones to Score

WIP NPD Programs

Pratt – Slide 45

Applications

Better Project Selection

Pratt – Slide 46

Deterministic Business Case Analysis

“Figures of Merit”

Pratt – Slide 47

Probabilistic Business Case Analysis

Beta Distribution

Pratt – Slide 48

Monte Carlo Simulation of

Cash Flows ($000)

Trial #1 Trial #2 Trial #3 Trial #4 Trial #5000

NPV $556 $461 $681 $447 $621

NRE 562 560 597 530 664

GM$ year1

348 274 241 220 274

GM$ year2

604 653 407 579 635

GM$ year3

451 651 644 447 558

Pratt – Slide 49

Probability-Based Figures of Merit

Pratt – Slide 50

Applications

Resource Management

Pratt – Slide 51

Default Team Size and Composition

Effort divided by Schedule represents number of individuals

Pratt – Slide 52

Roadmap and Budget Planning

Pratt – Slide 53

Program Resource Management

Engineering Pokémon board

• visual resource management tool

• 9 program type/complexity buckets

• default team size/composition

Pratt – Slide 54

NPD Programs are Represented by a

Series of Magnetic Trays

Pratt – Slide 55

Program Trays Incorporate Default

Team Size/Composition

Pratt – Slide 56

NPD Team Members are Represented

by a Series of Cards

Pratt – Slide 57

Engineering Pokémon – Additional

Pieces

Program Status Indicators

Bonus Targets Add-on Resource Trays “Ghost” Cards

Important Date Indicators

Clear Plastic Overlays

Pratt – Slide 58

The Board in Action

Pratt – Slide 59

Resulting Improvements

Pratt – Slide 60

Improved New Product Development

Better planning and management of resources…

• more stability and focus / less chaos

• increased efficiency

• enhanced organizational understanding

• faster NPD cycle-time

Pratt – Slide 61

In Conclusion:

It is never too late to start recording data!

- even simple data such as key dates and time spent on activities can facilitate powerful analyses

- capture data in real-time; don’t rely on memory or post mortem activities

Pratt – Slide 62

Questions???

Pratt – Slide 63

Thank You!

STEVEN PRATT, MEng., PE

Director of Engineering

www.alpha.ca

Pratt – Slide 64

top related