STORMWATER POLLUTION PREVENTION PLAN
for
CALIMESA - AVENUE L STORM DRAIN, STAGE 2 PROJECT NO. 5-0-00165
LUP TYPE 1
Legally Responsible Person (LRP): Warren D. Williams, P.E., General Manager-Chief Engineer
951.955.1250
Approved Signatory: Robert J. Cullen, P.E., Chief of Design and Construction Division
951.955.1200
Prepared for: RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
1995 MARKET STREET RIVERSIDE, CA 92501
Project Address:
AVENUE L AND CALIFORNIA STREET, CALIMESA, CA
SWPPP Prepared by: [Company Name]
[Address] [QSD's Name]
SWPPP Preparation Date
[Date]
Estimated Project Dates:
Start of Construction Completion of Construction
CGP App ID No.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP i January 2012
Table of Contents Table of Contents ........................................................................................................................... i
Qualified SWPPP Developer ........................................................................................................ 1
Legally Responsible Person .......................................................................................................... 2
Amendment Log ............................................................................................................................ 3
Section 1 SWPPP Requirements ...................................................................................... 4 1.1 Introduction ..................................................................................................................... 4
1.2 Permit Registration Documents ...................................................................................... 5
1.3 SWPPP Availability and Implementation ....................................................................... 6
1.4 SWPPP Amendments...................................................................................................... 6
1.5 Retention of Records ....................................................................................................... 7
1.6 Required Non-Compliance Reporting ............................................................................ 7
1.7 Annual Report ................................................................................................................. 8
1.8 Changes to Permit Coverage ........................................................................................... 8
1.9 Notice of Termination ..................................................................................................... 8
1.10 References ....................................................................................................................... 9
Section 2 Project Information ........................................................................................ 10 2.1 Project and Site Description .......................................................................................... 10
2.1.1 Site Description ......................................................................................................... 10
2.1.2 Existing Conditions ................................................................................................... 10
2.1.3 Existing Drainage ...................................................................................................... 10
2.1.4 Geology and Groundwater ........................................................................................ 10
2.1.5 Project Description .................................................................................................... 11
2.1.6 Developed Condition ................................................................................................ 11
2.2 Permits and Governing Documents .............................................................................. 11
2.3 Stormwater Run-On from Offsite Areas ....................................................................... 12
2.4 Findings of the Construction Site Sediment and Receiving Water Risk Determination ............................................................................................................. 13
2.5 Construction Schedule .................................................................................................. 14
2.6 Potential Construction Activity and Pollutant Sources ................................................. 14
2.7 Identification of Non-Stormwater Discharges .............................................................. 14
2.8 Required Site Map Information .................................................................................... 15
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP ii January 2012
Section 3 Best Management Practices ........................................................................... 17
3.1 Schedule for BMP Implementation .............................................................................. 17
3.2 Erosion and Sediment Control ...................................................................................... 17
3.2.1 Erosion Control ......................................................................................................... 17
3.2.2 Sediment Controls ..................................................................................................... 20
3.3 Non-Stormwater Controls and Waste and Materials Management .............................. 22
3.3.1 Non-Stormwater Controls ......................................................................................... 22
3.3.2 Materials Management and Waste Management ...................................................... 26
3.4 Post Construction Stormwater Management Measures ................................................ 30
Section 4 BMP Inspection and Maintenance ................................................................ 31
4.1 BMP Inspection and Maintenance ................................................................................ 31
Section 5 Training ........................................................................................................... 34
Section 6 Responsible Parties and Operators ............................................................... 35
6.1 Responsible Parties ....................................................................................................... 35
6.2 Contractor List .............................................................................................................. 36
Section 7 Monitoring and Reporting Program (M&RP) ............................................. 37 7.1 Objectives .......................................................................................................................... 37
7.2 M&RP Implementation Schedule ................................................................................... 37
7.3 LUP Type 1 Monitoring and Reporting Requirements................................................. 38
7.3.1 Inspection Requirements ....................................................................................... 38
7.4 Monitoring For Non-Visible Pollutants .......................................................................... 39
7.4.1 Non-Visible Pollutant Sampling Strategy (NVPSS) ........................................... 39
7.4.2 Identification of Potential Sources of Non-Visible Pollutants ............................ 40
7.4.3 Pre-Construction Activities ................................................................................. 40
7.4.4 Construction Activities ....................................................................................... 40
7.4.5 Construction Materials ........................................................................................ 40
7.4.6 Non-Visible Pollutants to be Monitored ............................................................. 43
7.4.7 Implementation of NVPSS .................................................................................. 44
7.4.8 Monitoring Locations.......................................................................................... 45
7.4.8.1 Site Sampling Locations for Non-Visible Pollutants. ..................................... 46
7.4.8.2 Control Samples .............................................................................................. 46
7.4.9 Sample Collection Strategy and Schedule .......................................................... 46
7.4.9.1 Weather Tracking ............................................................................................. 46
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP iii January 2012
7.4.9.2 Pre-Event Mobilization (Action Levels Pre-Alert and Alert) ......................... 47
7.4.9.2.1 Sampling Equipment ................................................................................... 48
7.4.9.2.2 Sample Bottles ............................................................................................ 48
7.4.9.3 Sample Collection and Handling ................................................................ 49
7.4.9.4 Post-Storm Event Procedures ..................................................................... 50
7.4.10 Analytical Data Evaluation ............................................................................. 50
7.4.11 Sampling and Analysis Records ..................................................................... 51
7.4.12 Modification to This Procedure ...................................................................... 51
7.4.13 Training For Sampling Personnel ................................................................... 51
Section 8 References ........................................................................................................ 55
Appendix A: Calculations and Risk Determination ............................................................. 56
Appendix B: Site Maps .......................................................................................................... 57
Appendix C: Permit Registration Documents....................................................................... 58
Appendix D: SWPPP Amendment Certifications ................................................................. 60
Appendix E: Submitted Changes to PRDs ............................................................................ 62
Appendix F: Construction Schedule ..................................................................................... 64
Appendix G: Construction Activities, Materials Used, and Associated Pollutants ............. 65
Appendix H: CASQA Stormwater BMP Handbook Portal: Construction Fact Sheets ...... 68
Appendix I: BMP Inspection Form ..................................................................................... 69
Appendix J: Rain Event Action Plan (REAP) ..................................................................... 76
Appendix K: Training Reporting Form ................................................................................ 78
Appendix L: Responsible Parties .......................................................................................... 80
Appendix M: Contractors and Subcontractors ...................................................................... 83
Appendix N: Construction General Permit........................................................................... 84
Appendix O: Weather Reports ............................................................................................... 84
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 1 January 2012
Qualified SWPPP Developer Approval and Certification of the Stormwater Pollution Prevention Plan
Project Name: CALIMESA - AVENUE L STORM DRAIN, STAGE 2
"I certify that this Stormwater Pollution Prevention Plan and Attachments meet the requirements of the California Construction General Permit (SWRCB Orders No. 2009-009-DWQ as amended by Order 2010-0014-DWQ). I certify that I am a Qualified SWPPP Developer in good standing as of the date signed below."
QSD Signature Date
QSD Name QSD Certificate Number
Title and Affiliation Telephone Number
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 2 January 2012
Legally Responsible Person Approval and Certification of the Stormwater Pollution Prevention Plan
Project Name: CALIMESA - AVENUE L STORM DRAIN, STAGE 2
"I certify under penalty of law that this document and all Attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, to the best of my knowledge and belief, the information submitted is, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."
Warren D. Williams, P.E.
Legally Responsible Person
Signature of Authorized Representative of Legally Responsible Person or Approved Signatory
Date
Robert J. Cullen, P.E. 951.955.1200
Name of Authorized Representative of Legally Responsible Person or Approved Signatory
Telephone Number
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 3 January 2012
Amendment Log
Project Name: CALIMESA - AVENUE L STORM DRAIN, STAGE 2
Amendment No. Date Brief Description of Amendment, include
section and page number Prepared and Approved By
Name: QSD#
Name: QSD#
Name: QSD#
Name: QSD#
Name: QSD#
Name: QSD#
Name: QSD#
Name: QSD#
Name: QSD#
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 4 January 2012
Section 1 SWPPP Requirements
1.1 INTRODUCTION This SWPPP has been prepared for the Calimesa - Avenue L Storm Drain, Stage 2 project, located in the city of Calimesa, Riverside County, California, and generally consists of the installation of reinforced concrete pipe storm drain beneath existing paved streets. The project begins approximately 200 feet east of the Avenue L and 4th Street intersection, and traverses approximately 7,100 feet northeasterly ending on Douglas Street. The project's location is shown on the Site Maps in Appendix B.
The terms "discharger", "legally responsible party", "legally responsible person", and "LRP" are used interchangeably in this document and universally refer to the Riverside County Flood Control and Water Conservation District. This Stormwater Pollution Prevention Plan (SWPPP) is designed to comply with California's General Permit for Stormwater Discharges Associated with Construction and Land Disturbance Activities (General Permit or CGP) Order No. 2009-0009-DWQ as amended by Order No. 2010-0014-DWQ (NPDES No. CAS000002) issued by the State Water Resources Control Board (State Water Board).
This SWPPP has been prepared following the SWPPP Template provided on the California Stormwater Quality Association Stormwater Best Management Practice Handbook Portal: Construction (CASQA, 2010). In accordance with the General Permit, Section XIV, this SWPPP is designed to address the following:
• Pollutants and their sources, including sources of sediment associated with construction, construction site erosion and other activities associated with LUP activity are controlled;
• Where not otherwise required to be under a Regional Water Quality Control Board (Regional Water Board) permit, all non-stormwater discharges are identified and eliminated, controlled, or treated; and
• Site BMPs are effective and result in the reduction or elimination of pollutants in stormwater discharges and authorized non-stormwater discharges from construction activity to the Best Available Technology/Best Control Technology (BAT/BCT) standard.
The Calimesa - Avenue L Storm Drain, Stage 2 project is a Linear Underground/Overhead Project (LUP) and, therefore, must comply with provisions set forth in Attachment A of the CGP.
This SWPPP must be evaluated and revised on an ongoing basis by a QSP in order to document the changes and progression of construction activity throughout the life of the project.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 5 January 2012
1.2 PERMIT REGISTRATION DOCUMENTS Required Permit Registration Documents (PRDs) shall be submitted to the State Water Board via the Stormwater Multi Application and Report Tracking System (SMARTS) by the Legally Responsible Person (LRP), or authorized personnel (i.e., Approved Signatory) under the direction of the LRP.
The project-specific PRDs include (per CGP Attachment A, Section B):
1. Notice of Intent (NOI)
Prior to construction activities, the LRP of a proposed linear underground/overhead project shall utilize the processes and methods provided in Attachment A.2, Permit Registration Documents (PRDs) – General Instructions for Linear Underground/Overhead Projects to comply with the Construction General Permit.
2. Risk Assessment (Construction Site Sediment and Receiving Water Risk Determination)
3. Site Map
LRPs submitting PRDs shall include at least 3 maps. The first map will be a zoomed 1000-1500 ft vicinity map that shows the starting point of the project. The second will be a zoomed map of 1000-1500 ft showing the ending location of the project. The third will be a larger view vicinity map, 1000 ft to 2000 ft, displaying the entire project location depending on the project size, and indicating the LUP type (1, 2 or 3) areas within the total project footprint.
4. Drawings
LRPs submitting PRDs shall include a construction drawing(s) or other appropriate drawing(s) or map(s) that shows the locations of storm drain inlets and waterbodies that may receive discharges from the construction activities and that shows the locations of BMPs to be installed for all those BMPs that can be illustrated on the revisable drawing(s) or map(s). If storm drain inlets, waterbodies, and/or BMPs cannot be adequately shown on the drawing(s) or map(s) they should be described in detail within the SWPPP.
5. Signed Certification Statement (LRP Certification is provided electronically with SMARTS PRD submittal);
6. SWPPP
LUP dischargers shall comply with the SWPPP Preparation, Implementation, and Oversight requirements in Section K of CGP Attachment A.
7. Contact information
LUP dischargers shall include contact information for all contractors (or subcontractors) responsible for each area of an LUP project. This should include the names, telephone numbers, and addresses of contact personnel. Specific areas of responsibility of each contact, and emergency contact numbers should also be included.
A copy of the submitted PRDs shall also be kept in Appendix C along with the CGP App ID confirmation.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 6 January 2012
1.3 SWPPP AVAILABILITY AND IMPLEMENTATION The discharger shall make the SWPPP available at the construction site during working hours (see Section 7.5 of CSMP for working hours) while construction is occurring and shall be made available upon request by a State or Municipal inspector. When the original SWPPP is retained by a crewmember in a construction vehicle and is not currently at the construction site, current copies of the BMPs and map/drawing will be left with the field crew and the original SWPPP shall be made available via a request by radio/telephone. (CGP Section XIV.C)
The SWPPP shall be implemented concurrently with the start of ground disturbing activities.
1.4 SWPPP AMENDMENTS The SWPPP should be revised when:
• If there is a General Permit violation;
• When there is a reduction or increase in total disturbed acreage (General Permit Section II Part C); or
• BMPs do not meet the objectives of reducing or eliminating pollutants in stormwater discharges.
Additionally, the SWPPP shall be amended when:
• There is a change in construction or operations which may affect the discharge of pollutants to surface waters, groundwater(s), or a municipal separate storm sewer system (MS4);
• When there is a change in the project duration that changes the project's risk level; or
• When deemed necessary by the QSD. The QSD has determined that the changes listed in Table 1.1 can be field determined by the QSP. All other changes shall be made by the QSD as formal amendments to the SWPPP.
The following items shall be included in each amendment:
• Who requested the amendment;
• The location of proposed change;
• The reason for change;
• The original BMP proposed, if any; and
• The new BMP proposed.
The amendment shall be logged at the front of the SWPPP and certification kept in Appendix D. The SWPPP text shall be revised, replaced, and/or hand annotated as necessary to properly convey the amendment. SWPPP amendments must be made by a QSD. The following changes have been designated by the QSD as "to be field determined" and constitute minor changes that the QSP may implement based on field conditions.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 7 January 2012
Table 1.1 List of Changes to be Field Determined
Candidate changes for field location or determination by QSP(1)
Check changes that can be field located or field determined by QSP
Increase quantity of an Erosion or Sediment Control Measure
Relocate/Add stockpiles or stored materials
Relocate or add toilets
Relocate vehicle storage and/or fueling locations
Relocate areas for waste storage
Relocate water storage and/or water transfer location
Changes to access points (entrance/exits)
Change type of Erosion or Sediment Control Measure
Changes to location of erosion or sediment control
Minor changes to schedule or phases
Changes in construction materials
(1) Any field changes not identified for field location or field determination by QSP must be approved by QSD
1.5 RETENTION OF RECORDS Paper or electronic records of documents required by this SWPPP shall be retained for a minimum of three years from the date generated or date submitted, whichever is later.
These records shall be available at the Site until construction is complete. Records assisting in the determination of compliance with the General Permit shall be made available within a reasonable time to the Regional Water Board, State Water Board or U.S. Environmental Protection Agency (EPA) upon request. Requests by the Regional Water Board for retention of records for a period longer than three years shall be adhered to.
1.6 REQUIRED NON-COMPLIANCE REPORTING If a discharge violation occurs the QSP shall immediately notify the LRP and the LRP shall file a violation report electronically to the Regional Water Board within 30 days of identification of non-compliance using SMARTS. Corrective measures will be implemented immediately following the discharge or written notice of non-compliance from the Regional Water Board. Discharges and corrective actions will be documented on the NAL/NEL Exceedance Site Evaluation Report Form in CSMP Attachment 3 "Example Forms."
The report to the LRP and to the Regional Water Board will contain the following items:
• The date, time, location, nature of operation and type of unauthorized discharge.
• The cause or nature of the notice or order.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 8 January 2012
• The control measures (BMPs) deployed before the discharge event, or prior to receiving notice or order.
The date of deployment and type of control measures (BMPs) deployed after the discharge event, or after receiving the notice or order, including additional measures installed or planned to reduce or prevent re-occurrence.
1.7 ANNUAL REPORT The General Permit requires that all Permittees prepare, certify, and electronically submit an Annual Report no later than September 1st of each year. Reporting requirements include (but are not limited to) providing a summary of:
1) Sampling and analysis results, including laboratory reports, analytical methods and reporting limits, and chain of custody forms (if any);
2) Corrective actions and compliance activities, including those not implemented;
3) Violations of the General Permit;
4) Date, time, place, and name(s) of the inspector(s) for all sampling, inspections, and field measurement activities;
5) Visual observation and sample collection exception records; and
6) Training documentation of all personnel responsible for General Permit compliance activities.
1.8 CHANGES TO PERMIT COVERAGE The General Permit allows for the reduction or increase of the total acreage covered under the General Permit when: a portion of the project is complete and/or conditions for termination of coverage have been met; when ownership of a portion of the project is purchased by a different entity; or when new acreage is added to the project.
Modified PRDs shall be filed electronically within 30 days of a reduction or increase in total disturbed area if a change in permit covered acreage is to be sought. The SWPPP shall be modified appropriately, shall be logged at the front of the SWPPP and certification of SWPPP amendments are to be kept in Appendix D. Updated PRDs submitted electronically via SMARTS can be found in Appendix E.
1.9 NOTICE OF TERMINATION To terminate coverage under the General Permit, a Notice of Termination (NOT) must be submitted electronically via SMARTS. A "final site map" and photos are required to be submitted with the NOT. Filing a NOT certifies that all General Permit requirements have been met. The NOT is submitted when the construction project is complete and within 90 days of meeting all General Permit requirements for termination and final stabilization, including:
• The site will not pose any additional sediment discharge risk than it did prior to construction activity;
• All construction related equipment, materials and any temporary BMPs no longer needed are removed from the site; and
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 9 January 2012
• Post-construction stormwater management measures are installed and a long-term maintenance plan that is designed for a minimum of five years has been developed.
The NOT must demonstrate through photos, Revised Universal Soil Loss Equation (RUSLE) results, or results of testing and analysis that the project meets all of the requirements of Section II.D.1 of the General Permit by the following method:
• 70% final cover method (no computational proof required).
1.10 REFERENCES The following documents are made a part of this SWPPP by reference:
• Project plans and specifications prepared by the Riverside County Flood Control and Water Conservation District;
• State Water Resources Control Board's (SWRCB) National Pollutant Discharge Elimination System (NPDES) General Permit for Stormwater Discharges Associated with Construction and Land Disturbance Activities Order No. 2009-0009-DWQ, NPDES No. CAS000002; and
• California Stormwater Quality Association (CASQA) Construction Site Best Management Practices Manual, dated January 2011.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 10 January 2012
Section 2 Project Information
2.1 PROJECT AND SITE DESCRIPTION This Stormwater Pollution Prevention Plan (SWPPP) has been created for the Calimesa - Avenue L Storm Drain, Stage 2 project. Refer to the vicinity map located in Appendix B for the site location.
2.1.1 Site Description The project is located entirely in the city of Calimesa, Riverside County. The project is located in Section 13 of Township 2 South, Range 1 West and Section 18 of Township 2 South, Range 2 West of the U.S. Geological Survey 7.5-minute topographic quadrangle maps for El Casco and Yucaipa (33.9994 North / 117.0444 West).
The project is a linear underground/overhead project (LUP) and begins approximately 200 feet east of the Avenue "L" and 4th Street intersection, and traverses approximately 7,100 feet northeasterly, ending on Douglas Street. Construction of short laterals (less than 100') and catch basins will also occur on the North-South streets intersecting Avenue L namely, Second Street, California Street and Bryant Street. An approximately 150' lateral will be installed North from Avenue L on Third Street. Project exhibits are located in Appendix B of this SWPPP.
Based on the proposed construction activity and the criteria in Attachment A.2 of the CGP ("Calculating Land Disturbance Areas of LUPs"), the initial estimated disturbance area for the Calimesa - Avenue L Storm Drain, Stage 2 project is 6.9 acres (4.6 acres of pavement overlay, 1.3 acres of full depth in-trench pavement replacement, and a 1 acre storage or staging area). Any changes to the initial estimate must be reported electronically (via SMARTS) and recorded in Appendix E of this SWPPP.
2.1.2 Existing Conditions Approximately 100% of the pre-project disturbance area is impervious and post-project imperviousness will not increase.
2.1.3 Existing Drainage Existing drainage in the project area is entirely overland. The tributary area for the project is comprised substantially of residential parcels draining to the public streets, with only two known commercial parcels (also draining to the public streets). The local drainage pattern flows from North to South and East to West and is largely contained in street right of way for the 10 year 24-hour event. Near the beginning of this LUP project there exists several catch basins which tie into the Calimesa - Avenue L Storm Drain, Stage 1 (District Drawing No. 5-197), which runs West in Avenue L to Calimesa Boulevard, where it travels North and West, ending in a sump located near Interstate 10.
2.1.4 Geology and Groundwater Per the project geotechnical report, the majority of the proposed storm drain alignment is underlain by a two-layer sequence of detrital alluvial materials: the upper layer consisting of loose to medium dense very silty sand and stiff to hard non-plastic sandy silt; the lower layer
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 11 January 2012
consisting of massive to indistinctly stratified medium dense to dense silty sand, clayey sand, gravelly sand, and uncommon sandy gravel. No groundwater was encountered in any of the exploratory borings, and is speculated by the project geotechnical report to be very deep. Nearby groundwater monitoring wells have found the average static groundwater surface elevation to vary from 150 to 170 feet below ground surface.
2.1.5 Project Description The project entails the construction of below-ground storm drain facilities as well as related above- and below-ground drainage structures, such as access manholes and catch basins. Street paving, both full depth structural replacement in-trench and pavement overlay outside of trench, will also occur.
The project includes the following type of facilities:
• Storm drain, constructed below ground
• Surface and below ground drainage structures
• Street paving
2.1.6 Developed Condition
Table 2.1 Construction Site Estimates
Construction site area 6.9 acres
Percent impervious before construction 100 %
Runoff coefficient before construction 0.90
Percent impervious after construction 100 %
Runoff coefficient after construction 0.90
2.2 PERMITS AND GOVERNING DOCUMENTS In addition to the General Permit, the following documents have been taken into account while preparing this SWPPP
• Regional Water Board requirements
• Basin Plan requirements
• Contract Documents
• Air Quality Regulations and Permits
• Federal Endangered Species Act
• National Historic Preservation Act/Requirements of the State Historic Preservation Office
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 12 January 2012
• State of California Endangered Species Act
• Clean Water Act Section 401 Water Quality Certifications and 404 Permits
• CA Department of Fish and Game 1600 Streambed Alteration Agreement
2.3 STORMWATER RUN-ON FROM OFFSITE AREAS Runoff and run-on controls are not required for Type 1 LUP.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 13 January 2012
2.4 FINDINGS OF THE CONSTRUCTION SITE SEDIMENT AND RECEIVING WATER RISK DETERMINATION
A construction site risk assessment has been performed for the project. The result is that this project is classified as a Type 1 LUP, which has the following requirements:
• Less than 30% of soil disturbances occur on unpaved surfaces (including staging areas).
• At the end of the work day, the construction site must be returned to pre-development or equivalent condition. For this project, all disturbed soil piles from trench excavation must be covered and secured with sandbags or other means around the perimeter. Any pipe lain within an open trench will be plugged at the downstream end to eliminate runoff leaving the site via the already installed storm drain line.
The risk level was determined by a site specific analysis. The risk level is based on project duration, location, proximity to impaired receiving waters and soil conditions. A copy of the Risk Level determination submitted on SMARTS with the PRDs is included in Appendix C.
Table 2.2 and Table 2.3 summarize the sediment and receiving water risk factors and document the sources of information used to derive the factors.
Table 2.2 Summary of Sediment Risk RUSLE Factor Value Method for establishing value
R 23.27 EPA website calculator (see Appendix C)
K 0.34 Project geotechnical report
LS 1.12 Table from Renard el. Al., 1997 (see Appendix C) Overall Sediment Risk Low Sediment Risk < 15 tons/ acre Medium Sediment Risk >= 15 and < 75 tons/acre High Sediment Risk >= 75 tons/acre
Low Medium High
Runoff from the project site discharges into the Calimesa - Avenue L Storm Drain, Stage 1, which eventually reaches San Timoteo Creek, then confluences with the Santa Ana River, Reach 5.
Table 2.3 Summary of Receiving Water Risk
Receiving Water Name 303(d) Listed for Sediment Related Pollutant(1)
TMDL for Sediment Related Pollutant(1)
Beneficial Uses of COLD, SPAWN, and MIGRATORY(1)
Santa Ana River Reach 5 Yes No Yes No Yes No
Overall Receiving Water Risk Low High
(1) If yes is selected for any option the Receiving Water Risk is High
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 14 January 2012
2.5 CONSTRUCTION SCHEDULE
The site sediment risk was determined based on construction taking place between April 18, 2012 and November 14, 2012. Modification or extension of the schedule (start and end dates) may affect risk determination and permit requirements. The LRP shall contact the QSD if the schedule changes during construction to address potential impact to the SWPPP. The estimated schedule for planned work can be found in Appendix F.
2.6 POTENTIAL CONSTRUCTION ACTIVITY AND POLLUTANT SOURCES Appendix G includes a list of construction activities and associated materials that are anticipated to be used onsite. These activities and associated materials will or could potentially contribute pollutants, other than sediment, to stormwater runoff.
The anticipated activities and associated pollutants were used in Section 3 to select the Best Management Practices for the project. Location of anticipated pollutants and associated BMPs are show on the Site Map in Appendix B.
2.7 IDENTIFICATION OF NON-STORMWATER DISCHARGES Non-stormwater discharges consist of discharges which do not originate from precipitation events. The General Permit provides allowances for specified non-stormwater discharges that do not cause erosion or carry other pollutants.
Non-stormwater discharges into storm drainage systems or waterways, which are not authorized under the General Permit and listed in the SWPPP, or authorized under a separate NPDES permit, are prohibited.
Non-stormwater discharges that are authorized from this project site include the following:
• None
These authorized non-stormwater discharges will be managed with the stormwater and non-stormwater BMPs described in Section 3 of this SWPPP and will be minimized by the QSP.
Activities at this site that may result in unauthorized non-stormwater discharges include:
•
Steps will be taken, including the implementation of appropriate BMPs, to ensure that unauthorized discharges are eliminated, controlled, disposed, or treated onsite.
Discharges of construction materials and wastes, such as fuel or paint, resulting from dumping, spills, or direct contact with rainwater or stormwater runoff, are also prohibited.
The following additional information is provided regarding non-stormwater discharges:
Dewatering (Discharge of Ponded/Retained Stormwater to Surface Waters
It is the responsibility of the Contractor to contact the appropriate California Regional Water Quality Control Board (Regional Board) to see if a permit is required for this activity. If there is a situation where there is ponded water due to rainfall collecting in a temporary sump condition caused by construction, the water may need to be removed. If approved by the Site LRP, the water may be pumped out of the sump and discharged at the site as long as the water is not pumped directly into the storm drain. The water must
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 15 January 2012
be pumped into an open area, with vegetation, with prior permission of the property owner, so that it can naturally percolate into the ground and not discharge into the storm drain system. In all other cases the water must be pumped to a truck and shipped offsite for proper disposal.
2.8 REQUIRED SITE MAP INFORMATION The Site Maps and Drawings are included in Appendix B of this SWPPP.
Site Maps
In accordance with the CGP, three site maps must be included with the PRDs. The first will be a 1000-1500 ft vicinity map that shows the starting point of the project. The second will be a zoomed map of 1000-1500 ft showing the ending location of the project. The third will be a larger view vicinity map, 1000 ft to 2000 ft, displaying the entire project location depending on the project size, and indicating the LUP type (1, 2 or 3) areas within the total project footprint.
Drawings
Construction drawing(s) or other appropriate drawing(s) or map(s) that show: the locations of the storm drain inlets and waterbodies that may receive discharges from the construction activities; and the locations of BMPs to be installed for all those BMPs that can be illustrated on revisable drawing(s) or map(s).
As conditions change it may be necessary to amend the site maps. Table 2.4 identifies sheet numbers where required elements are illustrated.
Table 2.4 Required Map Information
Included on Map/Plan Sheet
No. (1) Required Element
1 The project's surrounding area (vicinity)
1 Site layout
1-17 Construction site boundaries
1-17 Drainage areas
1-17 Discharge locations
1-17 Sampling locations
1-17 Areas of soil disturbance (temporary or permanent)
1-17 Active areas of soil disturbance (cut or fill)
1-17 Locations of run-off BMPs
1-17 Locations of erosion control BMPs
1-17 Locations of sediment control BMPs
N/A ATS location (if applicable)
N/A Locations of sensitive habitats, watercourses, or other features which are not to be disturbed
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 16 January 2012
Table 2.4 Required Map Information
Included on Map/Plan Sheet
No. (1) Required Element
N/A Locations of all post construction BMPs
1-17 Waste storage areas
1-17 Vehicle storage areas
1-17 Material storage areas
1-17 Entrance and Exits
1-17 Fueling Locations
1-17 Background Sampling Location Notes: (1) Indicate maps or drawings that information is included on (e.g., Vicinity Map, Site Map, Drainage Plans, Grading Plans, Progress Maps, etc.).
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 17 January 2012
Section 3 Best Management Practices
3.1 SCHEDULE FOR BMP IMPLEMENTATION
Table 3.1 BMP Implementation Schedule
BMP Implementation Duration
Ero
sion
Con
trol
EC-1, Scheduling Prior to Construction Entirety of Project
Sedi
men
t Con
trol
SE-1, Silt Fence Prior to Construction Entirety of Project
SE-5, Fiber Rolls Around Staging Area if area is not paved Entirety of Project
SE-7, Street Sweeping and Vacuuming
When sediment is tracked onto roadway Entirety of Project
SE-8, Sandbag Barrier Start of Construction Entirety of Project
SE-10, Storm Drain Inlet Protection Start of Construction Entirety of Project
Tra
ckin
g C
ontr
ol
TC-1, Stabilized Construction Entrance/Exit Prior to Construction Entirety of Project
SE-7, Street Sweeping and Vacuuming
When sediment is tracked onto roadway Entirety of Project
Win
d E
rosi
on
WE-1, Wind Erosion Control As necessary to disturbed areas and stockpiles Entirety of Project
3.2 EROSION AND SEDIMENT CONTROL Erosion and sediment controls are required by the General Permit to provide effective reduction or elimination of sediment related pollutants in stormwater discharges and authorized non-stormwater discharges from the Site. Applicable BMPs are identified in this section for erosion control, sediment control, tracking control, and wind erosion control.
3.2.1 Erosion Control Erosion control, also referred to as soil stabilization, consists of source control measures that are designed to prevent soil particles from detaching and becoming transported in stormwater runoff. Erosion control BMPs protect the soil surface by covering and/or binding soil particles.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 18 January 2012
This construction project will implement the following practices to provide effective temporary and final erosion control during construction:
1. Preserve existing vegetation where required and when feasible.
2. The area of soil disturbing operations shall be controlled such that the Contractor is able to implement erosion control BMPs quickly and effectively.
3. Stabilize non-active areas within 14 days of cessation of construction activities or sooner if stipulated by local requirements.
4. Control erosion in concentrated flow paths by applying erosion control blankets, check dams, erosion control seeding or alternate methods.
5. Prior to the completion of construction, apply permanent erosion control to remaining disturbed soil areas.
Sufficient erosion control materials shall be maintained onsite to allow implementation in conformance with this SWPPP.
The following temporary erosion control BMP selection table indicates the BMPs that shall be implemented to control erosion on the construction site. Fact Sheets for temporary erosion control BMPs are provided in Appendix H.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 19 January 2012
Table 3.2 Temporary Erosion Control BMPs
CASQA Fact Sheet
BMP Name Meets a
Minimum Requirement(1)
BMP Used If not used, state reason
YES NO
EC-1 Scheduling
EC-2 Preservation of Existing Vegetation There is no vegetation to be preserved; project is located in street
right-of-way. EC-3 Hydraulic Mulch (2) No slopes are disturbed. EC-4 Hydroseed (2) No slopes are disturbed. EC-5 Soil Binders (2) Project is not expected to have inactive areas. EC-6 Straw Mulch (2) No areas require temporary protection EC-7 Geotextiles and Mats (2) No slopes are disturbed. EC-8 Wood Mulching (2) No areas require temporary protection. EC-9 Earth Dike and Drainage Swales (3) Will use sandbag barriers instead EC-10 Velocity Dissipation Devices No outlets near project. EC-11 Slope Drains No slopes are disturbed. EC-12 Stream Bank Stabilization Project not near a stream bank. EC-14 Compost Blankets (2) No slopes are disturbed. EC-15 Soil Preparation-Roughening No slopes are disturbed. EC-16 Non-Vegetated Stabilization (2) No areas need temporary stabilization. WE-1 Wind Erosion Control
Alternate BMPs Used: If used, state reason:
(1) Applicability to a specific project shall be determined by the QSD. (2) The QSD shall ensure implementation of one of the minimum measures listed or a combination thereof to achieve and maintain the Risk Level requirements. (3) Run-on from offsite shall be directed away from all disturbed areas, diversion of offsite flows may require design/analysis by a licensed civil engineer and/or additional environmental permitting
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 20 January 2012
These temporary erosion control BMPs shall be implemented in conformance with the following guidelines and as outlined in the BMP Factsheets provided in Appendix H. If there is a conflict between documents, the Site Map will prevail over narrative in the body of the SWPPP or guidance in the BMP Fact Sheets. Site specific details in the Site Map prevail over standard details included in the Site Map. The narrative in the body of the SWPPP prevails over guidance in the BMP Fact Sheets.
Scheduling EC-1 Scheduling - The project schedule will show how BMP implementation relates to soil disturbing and re-stabilization practices. Non-active areas will be stabilized within 14 days of the cessation of any soil disturbing activities or one day prior to the onset of precipitation, whichever occurs first. The weather forecast will be monitored for rainfall. When rainfall is predicted, the schedule shall be adjusted to allow for the implementation of soil stabilization and sediment controls on any disturbed areas prior to the onset of rain.
Wind Erosion Control WE – 1 Wind Erosion Control – Water will be applied to disturbed areas and stockpiles as necessary to prevent or alleviate erosion by the forces of wind.
3.2.2 Sediment Controls Sediment controls are temporary or permanent structural measures that are intended to complement the selected erosion control measures and reduce sediment discharges from active construction areas. Sediment controls are designed to intercept and settle out soil particles that have been detached and transported by the force of water.
The following sediment control BMP selection table indicates the BMPs that shall be implemented to control sediment on the construction site. Fact Sheets for temporary sediment control BMPs are provided in Appendix H.
Calimesa – Avenue L Storm Drain, Stage 2 SWPPP 21 January 2012
Table 3.3 Temporary Sediment Control BMPs
CASQA Fact Sheet
BMP Name Meets a
Minimum Requirement(1)
BMP used If not used, state reason
YES NO SE-1 Silt Fence (2) (3) √ SE-2 Sediment Basin √ Not expecting sediment-laden water SE-3 Sediment Trap √ Not expecting sediment-laden water SE-4 Check Dams √ Steep slopes are not an issue in this project SE-5 Fiber Rolls (2)(3) √ SE-6 Gravel Bag Berm (3) √ Will use SE-8 Sandbag Barrier SE-7 Street Sweeping √ SE-8 Sandbag Barrier √ SE-9 Straw Bale Barrier √ Will use SE-1, SE-5, or SE-8 SE-10 Storm Drain Inlet Protection RL2&3 √ SE-11 ATS √ N/A SE-12 Temporary Silt Dike √ Will use SE-1, SE-5, or SE-8 SE-13 Compost Sock and Berm (3) √ Used SE-1 and SE-5 SE-14 Biofilter Bags (3) √ Used SE-10 TC-1 Stabilized Construction Entrance and Exit √ TC-2 Stabilized Construction Roadway √ Project is not a roadway construction TC-3 Entrance Outlet Tire Wash √ Used TC-1
Alternate BMPs Used: If used, state reason:
(1) Applicability to a specific project shall be determined by the QSD. (2) The QSD shall ensure implementation of one of the minimum measures listed or a combination thereof to achieve and maintain the Risk Level requirements. (3) Risk Level 2 &3 shall provide linear sediment control along toe of slope, face of slope, and at the grade breaks of exposed slope.
Calimesa – Avenue L Storm Drain, Stage 2 SWPPP 22 January 2012
These temporary sediment control BMPs shall be implemented in conformance with the following guidelines and in accordance with the BMP Fact Sheets provided in Appendix H. If there is a conflict between documents, the Site Map will prevail over narrative in the body of the SWPPP or guidance in the BMP Fact Sheets. Site specific details in the Site Map prevail over standard details included in the Site Map. The narrative in the body of the SWPPP prevails over guidance in the BMP Fact Sheets.
Silt Fence SE-1 Silt Fence - Linear sediment controls (silt fencing, fiber rolls, etc.) will be used as a perimeter control to contain sediment within the project area. It is not necessary to deploy perimeter controls at locations where sediment is unable to leave the project site (such as areas that slope inward).
Fiber Rolls SE-5 Fiber Rolls - Linear sediment controls (silt fencing, fiber rolls, etc.) will be used as a perimeter control to contain sediment within the project area. It is not necessary to deploy perimeter controls at locations where sediment is unable to leave the project site (such as areas that slope inward).
Street Sweeping SE-7 Street Sweeping and Vacuuming - The Contractor shall inspect all immediate access roads daily. The Contractor shall remove any sediment or other construction activity related material that is deposited on the roads by vacuuming or sweeping on a daily basis (when necessary) and prior to any rain event.
Sandbag Barrier SE-8 Sandbag Barrier – The sandbag barrier will be used to divert run-on around active construction areas.
Storm Drain Inlet Protection
SE-10 Storm Drain Inlet Protection - Storm drain inlets down gradient of disturbed soil areas will be protected with Type 3, 4 or 5 inlet protection.
Stabilized Construction Entrance and Exit TC-1 Stabilized Construction Entrance/Exit - A stabilized construction entrance/exit will be constructed. Additional entrances/exits will be constructed as needed. Construction activity traffic to and from the Project will be limited to these stabilized construction entrances/exits.
3.3 NON-STORMWATER CONTROLS AND WASTE AND MATERIALS MANAGEMENT
3.3.1 Non-Stormwater Controls Non-stormwater discharges into storm drainage systems or waterways, which are not authorized under the General Permit, are prohibited. Non-stormwater discharges for which a separate
Calimesa – Avenue L Storm Drain, Stage 2 SWPPP 23 January 2012
NPDES permit is required by the local Regional Water Board are prohibited unless coverage under the separate NPDES permit has been obtained for the discharge. The selection of non-stormwater BMPs is based on the list of construction activities with a potential for non-stormwater discharges identified in Section 2.7 of this SWPPP.
The following non-stormwater control BMP selection table indicates the BMPs that shall be implemented to control sediment on the construction site. Fact Sheets for temporary non-stormwater control BMPs are provided in Appendix H.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 24 January 2012
Table 3.4 Temporary Non-Stormwater BMPs
CASQA Fact Sheet BMP Name
Meets a Minimum
Requirement(1)
BMP used If not used, state reason
YES NO
NS-1 Water Conservation Practices √
NS-2 Dewatering Operation √ Not anticipating any dewatering
NS-3 Paving and Grinding Operation √
NS-4 Temporary Stream Crossing √ No stream crossing encounter
NS-5 Clear Water Diversion √ No water diversion expected
NS-6 Illicit Connection- Illegal Discharge Connection √
NS-7 Potable Water Irrigation Discharge Detection
√ Not anticipating irrigation discharge
NS-8 Vehicle and Equipment Cleaning √
NS-9 Vehicle and Equipment Fueling √
NS-10 Vehicle and Equipment Maintenance √
NS-11 Pile Driving Operation √ No pile driving operations.
NS-12 Concrete Curing √
NS-13 Concrete Finishing √
NS-14 Material and Equipment Use Over Water √ Project location is not over water
NS-15 Demolition Removal Adjacent to Water √ No demolition removal adjacent to water
NS-16 Temporary Batch Plants √ No batch plant expected
Alternate BMPs Used: If used, state reason:
(1) Applicability to a specific project shall be determined by the QSD
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 25 January 2012
Non-stormwater BMPs shall be implemented in conformance with the following guidelines and in accordance with the BMP Fact Sheets provided in Appendix H. If there is a conflict between documents, the Site Map will prevail over narrative in the body of the SWPPP or guidance in the BMP Fact Sheets. Site specific details in the Site Map prevail over standard details included in the Site Map. The narrative in the body of the SWPPP prevails over guidance in the BMP Fact Sheets.
Water Conservation Practices NS-1 Water Conservation Practices - Water equipment will be kept in good working condition. Leaks will be repaired immediately. Vehicles and equipment will not be washed on site. Water will not be used to clean construction areas.
Paving and Grinding Operation NS-3 Paving and Grinding Operations - Plastic material will be placed under paving equipment when not in use to catch drips or leaks. Paving equipment will be parked overnight at the staging area with plastic material placed underneath. Asphalt coated equipment will be cleaned off-site when possible. Residue from grinding or removal operations will be picked up by mechanical or manual means and disposed of properly. Inlets adjacent to paving operations will be protected. Following paving operations, the area will be swept and the inlets will be inspected for paving materials. If placing thermoplastic striping, the Contractor will fill the pre-heater carefully to avoid spillage and leave 6 inches of space at the top to allow for movement. Thermoplastic or bituminous material will not be transferred, pre-heated or loaded near drain inlets or water courses. Truck beds will be cleaned daily of loose debris and melted thermoplastic.
Illicit Connection- Illegal Discharge Connection NS-6 Illicit Connection/Illegal Discharge Detection and Reporting - The site will be inspected before the Project commences and regularly during the Project for illicit connections or illegal dumping or discharge. If any are found, they will be reported to the Engineering Project Manager and Project Manager at the time of discovery.
Vehicle and Equipment Cleaning NS-8 Vehicle and Equipment Cleaning - Vehicles and equipment will be cleaned off-site. Rinse water, wash waters or wash materials will not be disposed of on any impervious or pervious site surfaces, nor will they be disposed of into the storm drain system.
Vehicle and Equipment Fueling NS-9 Vehicle and Equipment Fueling - Onsite vehicle and equipment fueling should only be used where it is impractical to send vehicles and equipment offsite for fueling. A dedicated fueling area will be designated at the project site. The dedicated fueling area will be located on a level-grade area located at least 50 feet away from downstream drainage facilities and watercourses. The dedicated fueling area will be protected with berms and/or dikes to prevent run-on and run-off and to contain spills.
Absorbent spill clean-up materials and spill kits will be available at the dedicated fueling area. Tanks will not be "topped off". Oil, grease, and fuel will be prevented from leaking to the
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 26 January 2012
ground, storm drains or surface waters. Fluid and oil leaks will be repaired immediately. Leaked material shall be disposed of properly.
Vehicle and Equipment Maintenance NS-10 Vehicle and Equipment Maintenance - Onsite vehicle and equipment maintenance should only be used where it is impractical to send vehicles and equipment offsite for maintenance. A dedicated maintenance area will be designated at the project site. The dedicated maintenance area will be located on a level-grade area located at least 50 feet away from downstream drainage facilities and watercourses. The dedicated maintenance area will be protected with berms and/or dikes to prevent run-on and run-off and to contain spills. Only minor maintenance, such as adding oil, fluids or lubricants will occur at the project site. Drip pans or plastic sheeting will be used when maintenance work is performed. Absorbent spill cleanup materials and spill kits will be available at the dedicated maintenance area. Oil, grease, and fuel will be prevented from leaking to the ground, storm drains or surface waters. Fluid and oil leaks will be repaired immediately. Leaked material shall be disposed of properly.
Concrete Curing NS-12 Concrete Curing - If curing compounds are used, overspray will be avoided. The drift of the curing compound will be minimized by applying the compound close to the concrete surface. An amount of compound that covers the surface but does not allow any run-off of the compound will be applied. Cure water will be directed away from inlets and watercourses to collection areas for proper removal.
Concrete Finishing NS-13 Concrete Finishing – Drift of dust and blast material will be minimized by keeping blasting nozzle close to the surface. Inlets will be protected during sandblasting operations, and water from blasting operations will be directed away from inlets and watercourses to collection areas for infiltration or other means of removal (dewatering).
3.3.2 Materials Management and Waste Management Materials management control practices consist of implementing procedural and structural BMPs for handling, storing and using construction materials to prevent the release of those materials into stormwater discharges. The amount and type of construction materials to be utilized at the site will depend upon the type of construction and the length of the construction period. The materials may be used continuously, such as fuel for vehicles and equipment, or the materials may be used for a discrete period, such as soil binders for temporary stabilization.
Waste management consists of implementing procedural and structural BMPs for handling, storing and ensuring proper disposal of wastes to prevent the release of those wastes into stormwater discharges.
Materials and waste management pollution control BMPs shall be implemented to minimize stormwater contact with construction materials, wastes and service areas; and to prevent materials and wastes from being discharged offsite. The primary mechanisms for stormwater contact that shall be addressed include:
• Direct contact with precipitation
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 27 January 2012
• Contact with stormwater run-on and run-off
• Wind dispersion of loose materials
• Direct discharge to the storm drain system through spills or dumping
• Extended contact with some materials and wastes, such as asphalt cold mix and treated wood products, which can leach pollutants into stormwater
A list of construction activities is provided in Section 2.6. The following Materials and Waste Management BMP selection table indicates the BMPs that shall be implemented to handle materials and control construction site wastes associated with these construction activities. Fact Sheets for Materials and Waste Management BMPs are provided in Appendix H.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 28 January 2012
Table 3.5 Temporary Materials Management BMPs
CASQA Fact Sheet BMP Name
Meets a Minimum
Requirement(1)
BMP used If not used, state reason
YES NO
WM-01 Material Delivery and Storage √
WM-02 Material Use √
WM-03 Stockpile Management √
WM-04 Spill Preservation and Control √
WM-05 Solid Waste Management √
WM-06 Hazardous Waste Management √
WM-07 Contaminated Soil Management √ Contaminated soil is not expected
WM-08 Concrete Waste Management √
WM-09 Sanitary-Septic Waste Management √
WM-10 Liquid Waste Management √ Drilling and dredging is not expected for this project
Alternate BMPs Used: If used, state reason:
(1) Applicability to a specific project shall be determined by the QSD.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 29 January 2012
Material management BMPs shall be implemented in conformance with the following guidelines and in accordance with the BMP Fact Sheets provided in Appendix H. If there is a conflict between documents, the Site Map will prevail over narrative in the body of the SWPPP or guidance in the BMP Fact Sheets. Site specific details in the Site Map prevail over standard details included in the Site Map. The narrative in the body of the SWPPP prevails over guidance in the BMP Fact Sheets.
Material Delivery and Storage WM-l Material Delivery and Storage - A staging area will be designated at the project site by the Project Manager. The staging area will be used for storage, as needed. Construction materials will be delivered to the site and used quickly. Chemicals will be stored in watertight containers (with appropriate secondary containment to prevent any spillage or leakage) or in a completely enclosed storage shed. Spills and leaks will be contained and cleaned immediately. The exposure of construction materials to precipitation will be minimized. This does not include materials and equipment that are designed to be outdoors and exposed to environmental conditions (i.e. poles, equipment pads, cabinets, conductors, insulators, bricks, etc.). Backfill materials will be stockpiled per BMP WM-3 "Stockpile Management" when not in use.
Material Use
WM-2 Material Use – Hazardous materials use will be minimized onsite, and Material Safety Data Sheets (MSDS) will be available for all materials. Materials will be used only when and where needed to complete the construction activity. Use of erodible landscape materials will be discontinued two (2) days prior to a forecasted rain event, and materials will be covered/stored.
Stockpile Management WM-3 Stockpile Management - Any stockpiles will be located a minimum of 50 feet away from concentrated flows of stormwater, drainage courses, and inlets. All stockpiles will be bermed. Additionally, stockpiles will be covered at all times (to protect them from the wind and the rain) when they are not actively being used. Stockpiles that are unstabilized during construction activities will be sprayed with water as needed for dust control.
Spill Preservation and Control
WM-4 Spill Prevention and Control - The Contractor will assign and train appropriate spill response personnel. Oil, grease, and fuel will be prevented from leaking to the ground, storm drains or surface waters. All spills and leaks will be reported, contained and cleaned up immediately. All spill and leak wastes will be properly disposed of. The Project Manager and the Engineering Project Manager will be immediately notified of any spills and leaks. Spill and leak clean-up materials will be located near storage, unloading and use areas.
Solid Waste Management WM-5 Solid Waste Management- Solid wastes will be loaded directly into trucks and/or waste disposal containers for off-site disposal. Waste disposal containers will be covered at the end of every business day and during rain events. Discharges from waste disposal containers will be prevented from discharging to the stormwater drainage system or receiving water. Construction
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 30 January 2012
debris and litter from the project will be removed weekly and by the end of the project. Collected litter and debris will not be placed by drain inlets or drainage systems.
Hazardous Waste Management WM-6 Hazardous Waste Management - If hazardous materials are encountered or used, such materials will be handled, treated, stored, and disposed of per the project's Special Provisions and all applicable laws and regulations. Hazardous spills will be reported, contained and cleaned up immediately.
Concrete Waste Management WM-8 Concrete Waste Management- All PCC waste shall be collected and properly disposed of. The waste shall be collected by sweeping, shoveling, and/or other mechanical means. The waste should not be allowed to enter the storm drains or watercourses. An above grade or mobile concrete washout will be constructed or placed at the staging area if concrete trucks or concrete equipment will be washed on-site. The washout will be located a minimum of 50 feet away from concentrated flows of stormwater, drainage courses, and inlets. Additional washouts will be utilized as needed. Washouts will be contained so that there is no discharge into the underlying soil and onto the surrounding areas.
Sanitary-Septic Waste Management WM-9 Sanitary/Septic Waste Management- A licensed service will deliver and maintain portable restrooms to the project area. The restrooms will be located away from traffic and drainage facilities on level hard-packed or paved surfaces. Portable restrooms will be contained to prevent discharges of pollutants to the stormwater drainage system or receiving water. The restrooms will be inspected regularly for cleanliness, leaks and spills. They will be cleaned and replaced when needed.
3.4 POST CONSTRUCTION STORMWATER MANAGEMENT MEASURES Post construction BMPs are permanent measures installed during construction, designed to reduce or eliminate pollutant discharges from the site after construction is completed.
The Project Owner (Riverside County Flood Control and Water Conservation District) is responsible for post-construction BMPs (inspection, long term maintenance, etc.). The Owner will identify site design, source controls and treatment controls that will be included in the permanent project as well as a funding mechanism for long term BMP maintenance as applicable. The General Permit requires that all dischargers implement BMPs to reduce pollutants in stormwater discharges that are reasonably foreseeable after all construction phases have been completed at the site. The project is located in an area subject to the requirements of the Santa Ana Regional Water Quality Control Board's Phase I Municipal Separate Storm Sewer System (MS4) Permit (Order No. R8-2010-0033) and the run-off reduction requirements therein.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 31 January 2012
Section 4 BMP Inspection and Maintenance
4.1 BMP INSPECTION AND MAINTENANCE This section is taken directly from Attachment A of the Construction General Permit.
LUP Type 1 Monitoring and Reporting Requirements
a. LUP Type 1 Inspection Requirements
i. LUP Type 1 dischargers shall ensure that all inspections are conducted by trained personnel. The name(s) and contact number(s) of the assigned inspection personnel should be listed in the SWPPP.
ii. LUP Type 1 dischargers shall ensure that all visual inspections are conducted daily during working hours and in conjunction with other daily activities in areas where active construction is occurring.
iii. LUP Type 1 dischargers shall ensure that photographs of the site taken before, during, and after storm events are taken during inspections, and submitted through the State Water Board's SMARTS website once every three rain events.
iv. LUP Type 1 dischargers shall conduct daily visual inspections to verify that:
(1) Appropriate BMPs for stormwater and non-stormwater are being implemented in areas where active construction is occurring (including staging areas);
(2) Project excavations are closed, with properly protected spoils, and that road surfaces are cleaned of excavated material and construction materials such as chemicals by either removing or storing the material in protective storage containers at the end of every construction day;
(3) Land areas disturbed during construction are returned to pre-construction conditions or an equivalent protection is used at the end of each workday to eliminate or minimize erosion and the possible discharge of sediment or other pollutants during a rain event.
v. Inspections may be discontinued in non-active construction areas where soil-disturbing activities are completed and final soil stabilization is achieved (e.g., paving is completed, substructures are installed, vegetation meets minimum cover requirements for final stabilization, or other stabilization requirements are met).
vi. Inspection programs are required for LUP Type 1 projects where temporary and permanent stabilization BMPs are installed and are to be monitored after active construction is completed. Inspection activities shall continue until adequate permanent stabilization is established and, in areas where re-vegetation is chosen, until minimum vegetative coverage is established in accordance with Section C.1 of this Attachment.
b. LUP Type 1 Monitoring Requirements for Non-Visible Pollutants: LUP Type 1 dischargers shall implement sampling and analysis requirements to monitor non-visible pollutants associated with (1) construction sites; (2) activities producing
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 32 January 2012
pollutants that are not visually detectable in stormwater discharges; and (3) activities which could cause or contribute to an exceedance of water quality objectives in the receiving waters.
i. Sampling and analysis for non-visible pollutants is only required where the LUP Type 1 discharger believes pollutants associated with construction activities have the potential to be discharged with stormwater runoff due to a spill or in the event there was a breach, malfunction, failure and/or leak of any BMP. Also, failure to implement BMPs may require sample collection.
(1) Visual observations made during the monitoring program described above will help the LUP Type 1 discharger determine when to collect samples.
(2) The LUP Type 1 discharger is not required to sample if one of the conditions described above (e.g., breach or spill) occurs and the site is cleaned of material and pollutants and/or BMPs are implemented prior to the next storm event.
ii. LUP Type 1 dischargers shall collect samples down-gradient from all discharge locations where the visual observations were made triggering the monitoring, and which can be safely accessed. For sites where sampling and analysis is required, personnel trained in water quality sampling procedures shall collect stormwater samples.
iii. If sampling for non-visible pollutant parameters is required, LUP Type 1 dischargers shall ensure that samples be analyzed for parameters indicating the presence of pollutants identified in the pollutant source assessment required in Section J.2.a.i.
iv. LUP Type 1 dischargers shall collect samples during the first two hours of discharge from rain events that occur during business hours and which generate runoff.
v. LUP Type 1 dischargers shall ensure that a sufficiently large sample of stormwater that has not come into contact with the disturbed soil or the materials stored or used on-site (uncontaminated sample12) will be collected for comparison with the discharge sample. Samples shall be collected during the first two hours of discharge from rain events that occur during daylight hours and which generate run off.
vi. LUP Type 1 dischargers shall compare the uncontaminated sample to the samples of discharge using field analysis or through laboratory analysis. Analyses may include, but are not limited to, indicator parameters such as: pH, specific conductance, dissolved oxygen, conductivity, salinity, and Total Dissolved Solids (TDS).
vii. For laboratory analyses, all sampling, sample preservation, and other analyses must be conducted according to test procedures pursuant to 40 C.F.R. Part 136. LUP Type 1 dischargers shall ensure that field samples are collected and analyzed according to manufacturer specifications of the sampling devices employed. Portable meters shall be calibrated according to manufacturer's specification.
viii. LUP Type 1 dischargers shall ensure that all field and/or analytical data are kept in the SWPPP document.
c. LUP Type 1 Visual Observation Exceptions
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 33 January 2012
i. LUP Type 1 dischargers shall be prepared to collect samples and conduct visual observation (inspections) to meet the minimum visual observation requirements of this Attachment. The Type 1 LUP discharger is not required to physically collect samples or conduct visual observation (inspections) under the following conditions:
(1) During dangerous weather conditions such as flooding and electrical storms;
(2) Outside of scheduled site business hours.
(3) When access to the site is unsafe due to storm events.
ii. If the LUP Type 1 discharger does not collect the required samples or visual observation (inspections) due to these exceptions, an explanation why the sampling or visual observation (inspections) were not conducted shall be included in both the SWPPP and the Annual Report.
d. Particle Size Analysis for Risk Justification: LUP Type 1 dischargers utilizing justifying an alternative project risk shall report a soil particle size analysis used to determine the RUSLE K-Factor. ASTM D-422 (Standard Test Method for Particle-Size Analysis of Soils), as revised, shall be used to determine the percentages of sand, very fine sand, silt, and clay on the site.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 34 January 2012
Section 5 Training Appendix L identifies the QSPs for the project. To promote stormwater management awareness specific for this project, periodic training of job-site personnel shall be included as part of routine project meetings (e.g., daily/weekly tailgate safety meetings), or task specific trainings as needed.
The QSP shall be responsible for providing this information at the meetings, and subsequently completing the training logs shown in Appendix K, which identifies the site-specific stormwater topics covered as well as the names of site personnel who attended the meeting. Tasks may be delegated to trained employees by the QSP provided adequate supervision and oversight is provided. Training shall correspond to the specific task delegated including: SWPPP implementation; BMP inspection and maintenance; and record keeping.
Documentation of training activities (formal and informal) is retained in SWPPP Appendix K.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 35 January 2012
Section 6 Responsible Parties and Operators
6.1 RESPONSIBLE PARTIES Approved Signatories who are responsible for SWPPP implementation and have authority to sign permit-related documents are listed below. Written authorizations from the LRP for these individuals are provided in Appendix L. The Approved Signatories assigned to this project are:
Name Title Phone Number
Warren D. Williams, P.E. General Manager-Chief Engineer 951.955.1250
Robert J. Cullen, P.E. Chief of Design and Construction 951.955.1200
QSPs identified for the project are identified in Appendix L. The QSP shall have primary responsibility and significant authority for the implementation, maintenance and inspection/monitoring of SWPPP requirements. The QSP will be available at all times throughout the duration of the project. Duties of the QSP include but are not limited to:
• Implementing all elements of the General Permit and SWPPP, including but not limited to:
o Ensuring all BMPs are implemented, inspected, and properly maintained;
o Performing non-stormwater and stormwater visual observations and inspections;
o Performing non-stormwater and storm sampling and analysis, as required;
o Performing routine inspections and observations;
o Implementing non-stormwater management, and materials and waste management activities such as monitoring discharges; general Site clean-up; vehicle and equipment cleaning, fueling and maintenance; spill control; and ensuring that no materials other than stormwater are discharged in quantities which will have an adverse effect on receiving waters or storm drain systems, etc.;
• The QSP may delegate these inspections and activities to an appropriately trained employee, but shall ensure adequacy and adequate deployment.
• Ensuring elimination of unauthorized discharges.
• The QSPs shall be assigned authority by the LRP to mobilize crews in order to make immediate repairs to the control measures.
• Coordinate with the Contractor(s) to assure all of the necessary corrections/repairs are made immediately and that the project complies with the SWPPP, the General Permit and approved plans at all times.
• Notifying the LRP or Authorized Signatory immediately of off-site discharges or other non-compliance events.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 36 January 2012
6.2 CONTRACTOR LIST
Contractor
Name:
Title:
Company:
Address:
Phone Number:
Number (24/7):
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 37 January 2012
Section 7 Monitoring and Reporting Program (M&RP) LUP Summary of Monitoring Requirements:
LUP TYPE
VISUAL INSPECTIONS SAMPLE COLLECTION
DAILY SITE BMP
PRE-STORM EVENT DAILY
STORMBMP
POST STORM
STORMWATER DISCHARGE
RECEIVING WATER
NON-VISIBLE(WHEN
APPLICABLE)BASELINE 1 X X
Construction Site Monitoring Program Requirements for Risk Level 1
7.1 OBJECTIVES The purpose of the monitoring and reporting program (M&RP) is to protect water quality during the construction project. The M&RP must be prepared prior to the start of construction and implemented at all times throughout the life of the project. The QSP will implement the M&RP and the QSD will revise the plan as necessary. The M&RP must be part of the SWPPP, included as a separate chapter.
7.2 M&RP IMPLEMENTATION SCHEDULE The Contractor shall implement the requirements of this Section at the time of commencement of construction activity and until the activity is complete and the site is stabilized.
The QSD shall revise the M&RP when:
• Site conditions or construction activities change such that a change in monitoring is required in order to comply with the requirements and intent of the COP.
• The Regional Board requires the QSD revise the M&RP based on its review of the document. Revisions may include conducting additional site inspections, submitting reports, and certifications. Revisions shall be submitted via postal mail or electronic email.
• The Regional Board may require additional monitoring and reporting program requirements including sampling and analysis of discharges to CWA § 303(d) - listed water bodies. Additional requirements imposed by the Regional Board shall be consistent with the overall monitoring effort in the receiving waters.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 38 January 2012
7.3 LUP TYPE 1 MONITORING AND REPORTING REQUIREMENTS
7.3.1 Inspection Requirements a. Ensure all inspections are conducted by trained personnel. Space is provided below to list
the name and contact information of the person conducting the inspections.
Name:
Phone Number:
Emergency Phone Number:
Qualifications:
The person listed above shall include a copy of their training qualifications in Appendix K of this SWPPP.
b. All visual inspections are to be conducted daily during working hours and in conjunction with other daily activities in areas where active construction is occurring.
c. Photographs of the site shall be taken before, during, and after storm events and during site inspections. These photographs shall be submitted through SMARTS website once every three rain events.
d. Daily visual site inspection shall be conducted to verify that:
1. Appropriate BMPs for stormwater and non-stormwater are being implemented in areas where active construction is occurring (including staging areas).
2. Excavations are closed, with properly protected spoils, and that road surfaces are cleaned of excavated material and construction materials such as chemicals by either removing or storing the material in protective storage containers at the end of every construction day.
3. Land areas disturbed during construction are returned to pre-construction conditions or an equivalent protection is used at the end of each workday to eliminate or minimize erosion and the possible discharge of sediment or other pollutants during a rain event.
e. Inspections may be discontinued in non-active construction areas where soil-disturbing activities are completed and final soil stabilization is achieved (e.g., paving is completed, substructures are installed, vegetation meets minimum cover requirements for final stabilization, or other stabilization requirements are met).
f. An inspection program is required where temporary and permanent stabilization BMPs are installed and are to be monitored after active construction is completed. Inspection activities shall continue until adequate permanent stabilization is established and, in areas where re- vegetation is chosen, until minimum vegetative coverage is established in accordance with Section C.A of Attachment A of the CGP. This project does not include the planting and re- establishment of vegetation.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 39 January 2012
7.4 MONITORING FOR NON-VISIBLE POLLUTANTS
7.4.1 Non-Visible Pollutant Sampling Strategy (NVPSS) As a Type 1 LUP this project is subject to the sampling requirements for non-visible pollutants. Sampling and analysis is required to determine if non-visible pollutants are present in the discharges from the construction activity and enter the receiving water. This site shall monitor non-visible pollutants associated with (1) construction sites; (2) activities producing pollutants that are not visually detectable in stormwater discharges; and (3) activities which could cause or contribute to an exceedance of water quality objectives in the receiving waters.
Sampling and analysis for non-visible pollutants is required only if the Contractor believes pollutants associated with construction activities have the potential to be discharged with stormwater runoff due to a spill or in the event there was a breach, malfunction, failure and/or leak of any BMPs. Also, failure to implement BMPs may require sample collection.
In the event non-visible pollutant sampling is required it is anticipated that the time required to perform stormwater sampling will be approximately one half hour per location. In order to complete stormwater sampling during the required time period (up to 2 hours after the start of runoff from the storm event), sufficient personnel shall be assigned to complete the task based on the number of sampling locations.
It is also anticipated that stormwater monitoring and visual observations may identify visible pollutants leaving the site, and indicate a need for action on the construction site to identify and repair failed or compromised BMPs. If necessary, additional on-call personnel will respond when action is required in the field to identify and repair failed or compromised BMPs. It is anticipated that for this project, two people will be needed to collect stormwater samples and one person will be needed on-call for as-needed response. The Contractor will be responsible to list the personnel responsible for site inspection, stormwater sampling, and as-needed response in the space provided below:
Name:
Responsibility:
Phone Number:
Name:
Responsibility:
Phone Number:
Name:
Responsibility:
Phone Number:
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 40 January 2012
7.4.2 Identification of Potential Sources of Non-Visible Pollutants Per Attachment A of the CGP LUP Type 1 dischargers shall implement sampling and analysis requirements to monitor non-visible pollutants associated with (1) construction sites; (2) activities producing pollutants that are not visually detectable in stormwater discharges; and (3) activities which could cause or contribute to an exceedance of water quality objectives in the receiving waters.
7.4.3 Pre-Construction Activities No pre-construction activities were in place prior to the commencement of construction activities associated with this project.
7.4.4 Construction Activities During the construction process, the Contractor and Subcontractors will use a mix of heavy equipment and vehicles typical for construction activities such as; trenching, road construction, paving, and transport of construction materials. Operation and maintenance of this equipment may cause oil and grease and petroleum hydrocarbons to come into contact with stormwater.
7.4.5 Construction Materials During the construction process, many different materials will be used on-site. Table 7.1 lists various categories of construction activities as well as typical construction materials that may be used during those activities.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 41 January 2012
Table 7.1
List of Typical Construction Materials
Activity Typical Materials Asphalt Work Asphalt (conventional and
rubberized) Asphalt emulsion Asphalt releases- Monocyclic Terpet Liquid asphalt Aluminate Aluminum sulfate
Concrete Work Concrete curing compound - resin based "Monkey blood" (a retardant compound used for concrete curing) Arbitolor Arabitol (1,2,3,4,5-pentane pentol) pH from concrete sawing or freshly placed or washed off Portland cement products Cement Diesel fuel (sprayed on wooden forms as a non-sticking compound between concrete and wood)
Cleaning Various citrus based cleaners Solvents Thinners Detergents Trisodium phosphate Sodium Hypochlorite
Vehicle and Equipment Oil Grease Coolants Diesel Gasoline Hydraulic fluid
Pipe Work Pipe joint compound ABS and PVC primers Chlorine -water line flushing disinfection
Painting Paints Thinners Mineral spirits Latex paint (propylene glycol) Epoxy Silicone
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 42 January 2012
Activity Typical Materials Landscaping Herbicides
Pesticides Fertilizers Mulch Compost
Brick Work Etching compounds Acid wash of brick work
Soil Stabilization Wood fiber mulch Compost Wood and bark chips Straw mulch Emulsified asphalt Lime Plant gums Bonded fiber matrix Coconut fiber Paper mulch Grass Various proprietary products
Dust Palliatives - petroleum based (Note these are not recommended because of groundwater concerns and plant growth inhibition)
Bunker oil Asphalt primer Emulsified asphalt
Dust Palliatives- salts (note these are not recommended because they inhibit plant
Magnesium chloride Calcium chloride Natural
Dust Palliatives- organic Calcium lignosulfate Sodium lignosulfate Ammonium
Woodwork Lumber treatment/ preservative Water sealants Stains Sawdust
Structural finishing Plaster Fire retardants Epoxies Paints (see painting) Tar Urethane
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 43 January 2012
7.4.6 Non-Visible Pollutants to be Monitored Based on the sources of non-visible pollutants identified above, the following indicator parameters will be analyzed to determine if pollutants are being conveyed from the site by stormwater:
• pH
• Biological Oxygen Demand (BOD)
• Nitrate
• Total Dissolved Solids (TDS)
• Oil and Grease
Additional testing may be necessary based on the pollutant suspected to have entered stormwater. The analyses will be performed by an analytical laboratory that has been accredited by the California Department of Health Services Environmental Laboratory Accreditation Program (ELAP). The laboratory will be selected by the Contractor prior to the commencement of construction activities.
The following analyses may be performed in the field using field meters: pH and Turbidity. This Non-Visible Pollutant Sampling Strategy (NVPSS) assumes that field meters will not be used, and all constituents will be analyzed by an analytical laboratory. If field meters are used, the meters will be calibrated, maintained, and operated by trained staff according to the manufacturer's specifications, and calibration records will be stored at the end of this document.
The Contractor has selected and contacted the following analytical laboratory(ies) for sample analyses. (The Contractor will be responsible to list the name, address, phone number, and contact person of the selected laboratory):
Analytical laboratory:
Street:
City, State Zip Code:
Phone Number:
Contact Name:
The laboratory will provide properly cleaned and preserved (if applicable) sampling containers (bottles) for the samples, and labels on the sample bottles. The sample bottle labels will identify the analysis to be performed and any preservative contained in the bottles, and provide room for recording the sample location and time and date of collection. The laboratory will also provide chain-of-custody forms. The laboratory will conduct analyses in accordance with 40 CFR Part 136. Table 7.2 lists the EPA method numbers for the laboratory analytical methods to be used and requirements for sample collection bottles, preservatives, and holding times for the analyses. The holding time is the amount of time after collection of the sample within which the laboratory analysis must be performed.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 44 January 2012
Table 7.2
Laboratory Requirements for Sample Collection Bottles, Preservatives, and Holding Times for the Constituents to be Monitored
Analyte
EPA Analytical Method Number
Minimum Sample Volume1
Sampling Container Preservative2 Holding Time
pH EPA 150.1 100 mL Polypropylene
or glass None
Analyze immediately
upon receipt at the laboratory
BOD EPA 405.1 or 405.2 600 mL Polypropylene None 24 hours
Nitrate as Nitrogen
EPA 352.1 or 354.1 25 mL
Polypropylene or glass None 48 hours
TDS EPA 160.1 100 mL Polypropylene None 7 days
Oil and Grease EPA 1664 1 L Amber glass
HCl or H2SO4 to pH<2 28 days
1Minimum sample volume recommended. Specific volume requirements will vary by laboratory and must be verified with the laboratory when bottles are ordered. 2Do not pre‐rinse or overfill sample containers that contain preservative.3All samples must be kept chilled to 4°C (keep samples on ice for delivery to analytical laboratory)
7.4.7 Implementation of NVPSS Sampling and analysis is required when non-visible pollutants have the potential to contact stormwater and be conveyed from the construction site by stormwater into a storm drainage system or water body. Some examples of this situation are:
• Where construction materials and compounds are stored or used such that they are in contact with stormwater.
• For construction projects that utilize soil amendments that are in contact with stormwater runoff, unless independent test data are available that demonstrate acceptable concentration levels.
• When a leakage or spill occurs prior to a storm event and is not fully contained and cleaned.
• When a leakage or spill occurs during a storm event and it cannot immediately be isolated and/or cleaned up, and the possibility of an off-site discharge exists.
• During regular inspections of stockpiles it is discovered that cover and containment BMPs have been compromised and stormwater comes in contact with the materials, and the resulting runoff discharges into a storm drain system or water body.
• If material storage BMPs have been compromised, breached, or have failed.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 45 January 2012
If the Contractor determines that none of the conditions listed above exist at the site, and the following conditions are met, stormwater sampling may not be required. However, this NVPSS will be maintained in the SWPPP and sampling equipment and bottles will be kept at the site as a contingency sampling plan to be used in the event of an incidental discharge. Under the following conditions, sampling may not be required to be implemented:
• Where a construction project is "self-contained", meaning that the project contributes no runoff to other sources or areas and that any potential discharge of pollutants can be totally contained within the construction project site without discharging to a water body or storm drain system.
• Where construction materials and compounds are kept or used so that they are not in contact with stormwater (e.g., in water tight containers, under a water-tight roof, inside a building, etc.).
• Where for specific pollutants, the BMPs implemented at the construction site fully contain the exposed pollutants (e.g., bermed concrete washout area).
• For building materials that are in their final constructed form (e.g., fence materials, support structures and equipment that will remain exposed at the completion of the project, etc.).
• Where pollutants that may have been spilled or released on-site but have been properly cleaned up and stormwater exposure has been eliminated prior to a storm event.
• For stockpiles of construction materials for which both cover and containment BMPs have been properly implemented to protect them from run-on and from contributing pollutants to stormwater runoff.
The Contractor will apply a benchmark criteria discussed below to cease stormwater sampling at outfalls where laboratory data for three consecutive rain events for the specific outfall indicates that the discharges at that outfall are below benchmarks for the analyte and no new construction activity or materials have been added in the area draining to the outfall. However, if construction activity in the area draining to the outfall changes, a spill or breach occurs within the drainage area, or a BMP in the area is observed to be compromised, the Contractor will re-institute testing at that outfall.
7.4.8 Monitoring Locations The objective of sampling direct runoff from the construction site for non-visible pollutants is to determine whether materials or activities on the site have contributed to contamination of runoff leaving the site.
The control sample is a sample of stormwater that has not come in contact with the disturbed soil or the materials stored or used on-site (''uncontaminated sample"). Uncontaminated samples may be collected from discharge locations from the construction site where activities are not occurring on the site.
The Contractor will identify the non-visible pollutant sampling locations based on the activities occurring on the jobsite which might contribute to a discharge of non-visible pollutants. Space is provided below to list monitoring locations for non-visible pollutants as applicable.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 46 January 2012
7.4.8.1 Site Sampling Locations for Non-Visible Pollutants.
The monitoring locations below represent locations where stormwater runoff has come into contact with material which has spilled or leaked at the project site.
Monitoring Location A: Immediately upstream of existing catch basins on Avenue L, approximately 150' east of 4th Street (see Site Maps Sheet 2).
Monitoring Location B:
Monitoring Location C:
Monitoring Location D:
Monitoring Location E:
7.4.8.2 Control Samples
Stormwater uncontaminated sampling locations (control locations) must represent locations where stormwater runoff has not come into contact with material which has spilled or leaked at the project site. The below locations represent the project's control sampling locations.
Monitoring Location F: Sundar/Avenue L intersection (see Site Maps Sheet 3)
Monitoring Location G: 2nd Place/Avenue L intersection (see Site Maps Sheet 7)
Monitoring Location H: Bryant Street, approximately 100' north of Avenue L intersection (see Site Maps Sheet 13)
Monitoring Location I: North of project end, on Douglas Street (see Site Maps Sheet 17)
7.4.9 Sample Collection Strategy and Schedule A sample collection schedule is not applicable to this program due to the variable nature of the weather as well as the changing construction activities occurring on-site. Stormwater runoff samples will be collected during storm events in which material has leaked or spilled or there is reason to believe the discharge of stormwater from the project may result in the discharge of non-visible pollutants regardless of the time of year or status of the construction. Sampling will be conducted during the first 2-hours of runoff, during business hours only.
7.4.9.1 Weather Tracking
Each day, the QSP shall consult the NOAA website at http://www.srh.noaa.gov for the current weather forecast. Weather reports should be printed and maintained with the SWPPP in Appendix O, "Weather Reports".
If a storm is forecasted this will trigger mobilization for non-visible pollutant stormwater sample collection. Table 7.3 describes different stages of action based on forecasted weather. Table 7.3 refers to Sections below for actions such as mobilization, sampling and post-storm event procedures.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 47 January 2012
Table 7.3 Action Based on Forecasted Weather
Action Level Forecast Action Non-Monitoring
No storm systems developing Monitor weather forecasts weekly.
Standby Potential storm system developing Monitor weather forecasts daily, during business hours.
Pre-Alert Storm event expected within the next 48 hours
Begin mobilization. Monitor weather forecasts daily, during business hours.
Alert Storm event expected within the next 24 hours
Complete mobilization. Monitor weather forecasts every 6 hours.
Go Storm event has started Note time of storm event start and record on Sampling Event Worksheet. Begin storm event field visual inspection. Note time of runoff start and record on storm event worksheet. Proceed with sampling at start of runoff. Note: Only non-visible pollutant sampling is required for this project.
Post-Storm Event
Precipitation and runoff have ceased or stormwater sampling and site inspections have been completed
Demobilize and complete storm event paperwork. Monitor weather forecasts daily or weekly depending on whether further storm systems are currently developing.
7.4.9.2 Pre-Event Mobilization (Action Levels Pre-Alert and Alert)
Mobilization for stormwater sampling must begin when a storm event is predicted to occur within 48 hours. Use the following procedure to mobilize for stormwater sampling. Begin early because storms may approach faster than originally forecasted.
When a storm is predicted to occur within the next 48 hours (Pre-Alert):
1. Review inventory of stormwater sampling equipment - use Sampling Equipment Checklist.
2. If necessary, obtain any equipment that has been removed from the inventory.
When a storm event is predicted to occur within 24 hours (Alert):
1. Load the sampling equipment and paperwork into the vehicle that will be used for storm event field inspection and stormwater sampling.
2. Contact the analytical laboratory if it is anticipated that the delivery of samples may occur after the laboratory's normal business hours to arrange a late or weekend drop-off of samples.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 48 January 2012
On the day that the storm event is predicted to occur, buy ice and place the ice in the cooler.
7.4.9.2.1 Sampling Equipment
All sampling equipment will be kept on-site in an accessible location. Typical sampling equipment will include:
• Sample bottle sets appropriate to the samples that will be collected. Note all sample bottles require labels.
• New, clean sample collection containers appropriate to the sample locations, "disposable" containers for single use are preferred. This may include plastic buckets with handle and pourable lip, plastic cups, plastic dipper cup attached to pole, plastic dustpans (for collection of shallow sheet flow).
• Sampling Event Worksheet
• Visual Observation Worksheets
• Chain-of-Custody forms
• Clipboard
• Wax pencils, felt tip markers, or other appropriate writing instrument for wet conditions
• Paper towels
• Crowbar, if necessary to access cleanout or manhole
• Rope, if necessary for lowering buckets into flow
• Keys or record of lock combinations, if necessary to access sampling locations
• Any other equipment necessary for site access
• Alconox soap
• Gallon jugs of distilled water
• 5-gallon bucket or other container to carry equipment
• 5-gallon bucket to rinse sampling equipment
• Cooler(s) adequate to carry filled sample bottles
• Field meters, if applicable
When a storm event is expected to occur, ice will be purchased and stored in the cooler(s).
7.4.9.2.2 Sample Bottles
Sample bottles are to be provided by the analytical laboratory. The sample bottles require labels indicating the analysis, preservative (if applicable), and space to record the sample collection location, date and time. The laboratory must provide bottles appropriate to the expected sampling parameters, and certify that the bottles are clean. An order for bottles must be placed prior to the first mobilization of the season so that the bottles will be on hand for mobilization. Enough bottles should be ordered for multiple events in order to have plenty of bottles on hand.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 49 January 2012
Different bottles are used for different sampling parameters. Table 7.2 lists sampling parameters and appropriate bottles. Sets of bottles should be pre-assembled for the suite of analyses for each location to be sampled (i.e., for each sampling location on the project, a box or Ziploc bag containing the appropriate sample bottles for the location should be prepared in advance of sampling). The bottles may be pre-labeled with the sampling location if known.
7.4.9.3 Sample Collection and Handling
Upon the start of a sampling storm event, the personnel responsible for site inspection and stormwater sampling will begin the site inspection and proceed to the sampling points to collect samples of stormwater runoff. All necessary equipment mobilized during pre-event mobilization will be transported to the sampling locations. Samples will be collected during the first two hours of runoff from the site.
Samples will be collected manually "grab samples" by filling the bottles directly in the flow of stormwater where possible, or by dipping a bucket or other container in the flow and decanting the stormwater into the bottles. For samples that cannot be collected directly into the sample bottle, new, clean, disposable buckets or other containers will be used for each sampling location. The sample bottle or sampling container will be pre-rinsed in the flow of stormwater to be collected prior to collection of the sample, with the exception of sample bottles that contain preservatives. Bottles will be filled completely and closed tightly. If it is necessary to use the same equipment at multiple locations, the equipment will be rinsed in a bucket with Alconox soap and distilled water between sample locations.
The time and date of the sample and the sampling location will be recorded on the sample bottles. Each sample will be recorded on a chain of custody form. Samples will be placed in a cooler with ice. Concurrently with sample collection, visual observation of runoff at each sampling location will be performed. A Visual Observation Worksheet will be filled for each sampling location and storm event. Visual Observation Worksheets are provided in Appendix A. If visual observations indicate that visible pollutants are being transported from the site, appropriate personnel will be contacted to determine the source of the pollutants, contain the pollutants, and repair or replace any BMPs that are determined to have failed or been compromised.
After samples have been collected from all locations, they will be immediately transported to the analytical laboratory. Samples must be transported to the laboratory on the day of collection to ensure that the laboratory may complete the requested analyses within the required holding time (refer to Table 7.2). If sample collection will be completed outside of the analytical laboratory's normal business hours, call the laboratory in advance to arrange for a late or weekend drop-off of the samples.
The chain-of-custody form will be transported to the analytical laboratory with the samples. Upon receipt of the samples, the analytical laboratory will log in the samples received in their logbook. The sampling personnel and the analytical laboratory will sign the chain-of-custody form releasing the samples to the analytical laboratory, and the analytical laboratory will provide a signed copy of the chain-of-custody form to the person delivering the samples. If the samples are transported by a courier, the sampling personnel and the courier will sign the chain-of- custody form releasing the samples to the courier, and the courier will release the samples to the analytical laboratory by the same procedure.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 50 January 2012
7.4.9.4 Post-Storm Event Procedures
Following completion of stormwater sampling and site inspection for a storm event, all Visual Observation Worksheets and field Visual Inspection Forms will be reviewed to determine if further action is required on the site to correct any failed or compromised BMPs. Corrective actions that were taken on the site will be recorded on the Visual Observation Worksheets where visual observations indicated that action was required.
All sampling equipment will be cleaned and inspected. New bottles will be obtained to replace bottles used for sampling as necessary. Any compromised pieces of equipment will be replaced.
The Sampling Event Worksheet will be completed and filed with the Visual Observation Worksheets and the Chain of Custody forms in Appendix G of this SWPPP.
7.4.10 Analytical Data Evaluation
Typical laboratory turnaround time to return sample results ranges from 10 days to several weeks. If visual observations made during the storm event indicate that action is required in the field to correct failed or compromised BMPs, the action will be taken immediately, before sample results are received. Upon receipt of sample results, the results will be reviewed and compared with Visual Observation Worksheets and field Visual Inspection Forms to determine whether further action is required on the site to upgrade BMPs (e.g., if it is found that visual observations in the field did not indicate that action was required, but sample results exceed benchmark levels discussed below). The Contractor will be responsible to designate the person(s) responsible for this task and record the information:
Name: Phone number: If it is determined that BMPs must be upgraded based on sample results, the SWPPP will be amended accordingly and the SWPPP Amendment is to be logged in at the beginning of this SWPPP and certified by the QSD in Appendix D.
Table H.4 Benchmark Criteria for Decision Making
Analyte Benchmark Concentration Reference pH <6.5 or>8.5 Basin Plan BOD >30 mgll USEPA* Nitrate >45 mg/1 as nitrate Basin Plan TDS >500 mg/L Basin Plan Oil and Grease >15 mg/1 USEPA *United States Environmental Protection Agency Multi-Sector Industrial Permit
When laboratory analysis shows that a tested analyte exceeds the benchmark concentration, the Contractor will perform a root cause analysis. Records of any corrective action take are to be kept in Appendix G of this SWPPP.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 51 January 2012
7.4.11 Sampling and Analysis Records
All Sampling Event Worksheets, Visual Observation Worksheets, chain-of-custody forms laboratory analysis data, and other documentation relating to sampling and analysis will be kept on-site with the SWPPP, which is to remain at the construction site at all times until a Notice of Termination for the project is submitted and approved. The General Construction Permit requires that records of all inspections, compliance certifications, and non-compliance reporting must be retained for a period of at least three years from the date generated or after project completion.
7.4.12 Modification to This Procedure
The QSD will review this procedure after the first sampled storm event and periodically during its implementation, and will revise procedures as needed. Anticipated situations that may cause the QSD to revise the SWPPP or NVPSS include but are not limited to:
• Comparison of analytical results with benchmarks for analytes tested
• Changes in construction activity occurring on-site that result in changes to pollutants of concern
7.4.13 Training For Sampling Personnel
Samples will be collected by personnel trained in field sample collection and the objectives of this NVPSS. The Contractor will provide training prior to the first mobilization for stormwater sample collection.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 52 January 2012
SAMPLING EQUIPMENT CHECKLIST NON-VISIBLE POLLUTANT SAMPLING EVENT
Sample bottle sets with labels attached Complete this box upon receiving bottles from analytical laboratory Sample bottle sets include: for pH for Biological Oxygen Demand (BOD) for Nitrate or Nitrate as Nitrogen for Total Dissolved Solids (TDS) for Oil and Grease Sample collection containers Clipboard Sampling Event Worksheet Visual Observation Worksheet Chain-of-Custody forms Wax pencils, sharpie markers, or other writing instrument Paper towels Crowbar Rope Keys (or lock combinations ) Alconox soap Gallon jugs of distilled water 5-gallon bucket or other container to carry equipment 5-gallon bucket to rinse sampling equipment Cooler(s) adequate to carry filled sample bottles Field meters Other
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 53 January 2012
SAMPLING EVENT WORKSHEET NON-VISIBLE POLLUTANT SAMPLING EVENT
Storm Event Date(s) Describe the reason for sampling including a spill or breach, failure of BMP, or presence of a historical non-visible pollutant. Was sample within the first 2-hours of runoff? Was storm event preceded by 48 hours of dry weather? Storm Start Time Storm End Time Runoff Start Time Total Precipitation Locations Sampled
Location Sampled By Time Laboratory ID Number
assigned to Samples*
*Contractor to obtain a chain-of-custody form from the laboratory where samples will be taken to be processed prior to the commencement of construction activities. Action was taken to correct failed or compromised BMPs (see Visual Inspection Forms
and Maintenance Record) Based on Visual Observation Worksheets and Visual Inspection Forms, action was not
required to correct failed or compromised BMPs
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 54 January 2012
VISUAL OBSERVATION WORKSHEET NON-VISIBLE POLLUTANT SAMPLING EVENT
Storm Event Date Monitoring Location Sample Collection Time
Stormwater Characteristics Characteristic Observation (Circle one) Color Clear Brown Gray Yellow Red Other Clarity Clear Cloudy Opaque Floatables None Vegetation Mulch Trash Foam Other Oily Sheen None Slight Heavy Odor None Sewage Other
Field Measurements if Performed Analysis Result Units pH N/A Turbidity NTU Based on visual observation of the runoff, further action is not required on-site to identify and correct failed or compromised BMPs Based on visual observation of the runoff, further action is required on-site to identify and correct failed or compromised BMPs. Describe action taken below:
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 55 January 2012
Section 8 References Project Plans and Specifications, DWG# 5-217 prepared by RCFC&WCD.
State Water Resources Control Board (2009). Order 2009-0009-DWQ, NPDES General Permit No. CAS000002: National Pollutant Discharges Elimination System (NPDES) California General Permit for Stormwater Discharge Associated with Construction and Land Disturbing Activities. Available on-line at: http://www.waterboards.ca.gov/water_issues/programs/ stormwater/construction.shtml. State Water Resources Control Board (2010). Order 2010-0014-DWQ, NPDES General Permit No. CAS000002: National Pollutant Discharges Elimination System (NPDES) California General Permit for Stormwater Discharge Associated with Construction and Land Disturbing Activities. Available on-line at: http://www.waterboards.ca.gov/water_issues/programs/ stormwater/construction.shtml. CASQA 2009, Stormwater BMP Handbook Portal: Construction, November 2009, www.casqa.org
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 56 January 2012
Appendix A: Calculations and Risk Determination
CALIMESA--AVENUE L STROM DRAIN, STAGE 2PROJECT NO. 5-0-00165
AED 10-20-2011
Low Medium High
Low Level 1
High Level 3
Project Sediment Risk: Low 1
Project RW Risk: Low 1
Project Combined Risk: Level 1
Combined Risk Level Matrix
Sediment Risk
Rec
eivi
ng W
ater
R
isk Level 2
Level 2
1
CALIMESA--AVENUE L STROM DRAIN, STAGE 2PROJECT NO. 5-0-00165
AED 10-20-2011
1
2
34
5
6
7
8
9
10
11
12
1314
15
1617181920
A B C
Entry
23.27
0.34
1.12
Watershed Erosion Estimate (=RxKxLS) in tons/acre
Site Sediment Risk FactorLow Sediment Risk: < 15 tons/acre
Medium Sediment Risk: >=15 and <75 tons/acreHigh Sediment Risk: >= 75 tons/acre
K Factor Value
LS Factor Value
Low
C) LS Factor (weighted average, by area, for all slopes)
The soil-erodibility factor K represents: (1) susceptibility of soil or surface material to erosion, (2) transportability of the sediment, and (3) the amount and rate of runoff given a particular rainfall input, as measured under a standard condition. Fine-textured soils that are high in clay have low K values (about 0.05 to 0.15) because the particles are resistant to detachment. Coarse-textured soils, such as sandy soils, also have low K values (about 0.05 to 0.2) because of high infiltration resulting in low runoff even though these particles are easily detached. Medium-textured soils, such as a silt loam, have moderate K values (about 0.25 to 0.45) because they are moderately susceptible to particle detachment and they produce runoff at moderate rates. Soils having a high silt content are especially susceptible to erosion and have high K values, which can exceed 0.45 and can be as large as 0.65. Silt-size particles are easily detached and tend to crust, producing high rates and large volumes of runoff. Use Site-specific data must be submitted.
The effect of topography on erosion is accounted for by the LS factor, which combines the effects of a hillslope-length factor, L, and a hillslope-gradient factor, S. Generally speaking, as hillslope length and/or hillslope gradient increase, soil loss increases. As hillslope length increases, total soil loss and soil loss per unit area increase due to the progressive accumulation of runoff in the downslope direction. As the hillslope gradient increases, the velocity and erosivity of runoff increases. Use the LS table located in separate tab of this spreadsheet to determine LS factors. Estimate the weighted LS for the site prior to construction.
8.861216
Site-specific K factor guidance
LS Table
Sediment Risk Factor Worksheet
A) R Factor
R Factor Value
B) K Factor (weighted average, by area, for all site soils)
Analyses of data indicated that when factors other than rainfall are held constant, soil loss is directly proportional to a rainfall factor composed of total storm kinetic energy (E) times the maximum 30-min intensity (I30) (Wischmeier and Smith, 1958). The numerical value of R is the average annual sum of EI30 for storm events during a rainfall record of at least 22 years. "Isoerodent" maps were developed based on R values calculated for more than 1000 locations in the Western U.S. Refer to the link below to determine the R factor for the project site.http://cfpub.epa.gov/npdes/stormwater/LEW/lewCalculator.cfm
2
National Pollutant Discharge Elimination System (NPDES) Recent Additions | Contact Us | Print Version Search NPDES:
EPA Home > OW Home > OWM Home > NPDES Home >
Basic Information eNOI Municipal MS4s Construction Activities Industrial Activities Road-Related MS4s Menu of BMPs Green Infrastructure Urban BMP Tool Stormwater Home
NPDES Topics Alphabetical Index Glossary About NPDES
Rainfall Erosivity Factor Calculator for Small Construction Sites
Facility Information
Facility Name: Calimesa Avenue L Storm Drain, Stage 2Start Date: 04/02/2012End Date: 12/03/2012
Latitude: 33.9994Longitutde: -117.0444
Erosivity Index Calculator Results AN EROSIVITY INDEX VALUE OF 23.27 HAS BEEN DETERMINED FOR THE CONSTRUCTION PERIOD OF 04/02/2012 - 12/03/2012. A rainfall erosivity factor of 5.0 or greater has been calculated for your site and period of construction. You do not qualify for a waiver from NPDES permitting requirements.
Start Over
Stormwater Information
Recent Additions FAQs Publications Regulations Training & Meetings Links Contacts
The documents on this site
are best viewed with Acrobat 8.0
Office of Water | Office of Wastewater Management | Disclaimer | Search EPA
EPA Home | Privacy and Security Notice | Contact Us
Last updated on August 07, 2009 3:37 PM URL:http://cfpub.epa.gov/npdes/stormwater/LEW/erosivity_index_result.cfm
Thursday, October 20, 2011
http://cfpub.epa.gov/npdes/stormwater/LEW/erosivity_index_result.cfm
3
Address Calimesa Avenue L Storm Drain, Stage 2 33.9994, -117.0444
©2011 Google -
Thursday, October 20, 2011
http://maps.google.com/maps?f=q&source=s_q&hl=en&geocode=&q=33.9994,+-117.0444+(Calimesa+Ave...
4
ID Section Task Name Work Start Finish Duration % Work Complete Resource Names Predecessors Successors
1 PHO Utility review & coordination 12 wks 8/8/11 10/28/11 12 wks 78% Jim McNeill 26
2 DC Request Partner Cooperative Agreement 0 wks 8/8/11 8/8/11 0 wks 100% Alex Deuson 3
3 AG Process Partner Cooperative Agreement 12 wks 8/8/11 10/28/11 12 wks 78% Teresa Tung 2 22
4 OM O&M check 2 wks 10/26/11 11/9/11 2 wks 0% Imad G 10 18
5 SUR Survey stake-ability check 2 wks 10/26/11 11/9/11 2 wks 0% Gary Poor 10 18
6 90% Plan 11.5 wks 8/8/11 10/26/11 11.5 wks 82%
7 DC Implement DWR-required changes to design 5 wks 8/8/11 9/9/11 5 wks 100% Alex Deuson 8
8 DC ENG-90% Plan Preparation 3 wks 9/12/11 9/30/11 3 wks 100% Alex Deuson 7 9
9 DC DFT-90% Plan Preparation 2 wks 10/3/11 10/14/11 2 wks 70% Design Technician 8 10
10 DC 90% Plan Approval Meeting 1.5 wks 10/17/11 10/26/11 1.5 wks 0% Alex Deuson 9 14,15,17,18,11,16,4,5
11 OA DWR second submittal review 8 wks 10/26/11 12/21/11 8 wks 0% Outside Agency 10 12
12 DC Receive DWR Permit number 0 wks 12/21/11 12/21/11 0 wks 0% Alex Deuson 11 22
13 100% Plan 11 wks 10/26/11 12/28/11 9 wks 0%
14 DC Specifications 1 wk 10/26/11 11/9/11 2 wks 0% Alex Deuson[50%] 10 22,20
15 DC Estimates 1 wk 10/26/11 11/9/11 2 wks 0% Alex Deuson[50%] 10 22,20
16 DC 90% SWPPP 0 wks 10/26/11 10/26/11 0 wks 0% Alex Deuson 10 26
17 DC Final Field Check 0 wks 10/26/11 10/26/11 0 wks 0% Alex Deuson 10 22
18 DC ENG-100% Plan Preparation 2 wks 11/9/11 11/23/11 2 wks 0% Alex Deuson 10,4,5 19
19 DC DFT-100% Plan Preparation 3 wks 11/23/11 12/14/11 3 wks 0% Design Technician 18 22,20
20 DC Section and Division Head Review of PSE 4 wks 12/14/11 12/28/11 2 wks 0% Mike Wong,Bob Cullen 14,15,19 22
21 Post-Engineering Admin Work 0.2 wks 12/28/11 1/25/12 4 wks 0%
22 DC Mylar & Sign plans 0.05 wks 12/28/11 1/4/12 1 wk 0% Alex Deuson[5%] 3,19,14,15,17,12,20 23
23 DC Repro binds books 0.05 wks 1/4/12 1/11/12 1 wk 0% Alex Deuson[5%] 22 24
24 DC County Counsel reviews highlighted book 0.05 wks 1/11/12 1/18/12 1 wk 0% Alex Deuson[5%] 23 25
25 DC Chief Review 0.05 wks 1/18/12 1/25/12 1 wk 0% Alex Deuson[5%] 24 26
26 DC Advertise Project 0 wks 1/25/12 1/25/12 0 wks 0% Alex Deuson[5%] 1,25,16 28,27FS+4 wks
27 DC Bid Opening 0 wks 2/22/12 2/22/12 0 wks 0% Alex Deuson[5%] 26FS+4 wks 28
28 CA Award Project (Insurance in order) 4 wks 2/22/12 3/21/12 4 wks 0% Henry Olivo 26,27 29
29 CA SWPPP Approval 4 wks 3/21/12 4/18/12 4 wks 0% Henry Olivo 28 30
30 CA Construction 30 wks 4/18/12 11/14/12 30 wks 0% Henry Olivo 29
Utility review & coordination
Request Partner Cooperative Agreement
Process Partner Cooperative Agreement
O&M check
Survey stake-ability check
90% Plan
Implement DWR-required changes to design
ENG-90% Plan Preparation
DFT-90% Plan Preparation
90% Plan Approval Meeting
DWR second submittal review
Receive DWR Permit number
100% Plan
Specifications
Estimates
90% SWPPP
Final Field Check
ENG-100% Plan Preparation
DFT-100% Plan Preparation
Section and Division Head Review of PSE
Post-Engineering Admin Work
Mylar & Sign plans
Repro binds books
County Counsel reviews highlighted book
Chief Review
Advertise ProjectAdvertise Project
Bid OpeningBid Opening
Award Project (Insurance in order)
SWPPP Approval
Construction
AugSepOctNovDecJanFebMarAprMayJun Jul AugSepOctNovDecJanFebMarAprMayJun Jul AugSepOctNovDecJanFebMarA3, 2010 Qtr 4, 2010 Qtr 1, 2011Qtr 2, 2011Qtr 3, 2011 Qtr 4, 2011 Qtr 1, 2012Qtr 2, 2012Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013Q
Critical Split Task Milestone Critical Milestone Rolled Up Progress Summary Task Critical Summary Task Critical
Page 1 of 1
Calimesa Avenue L Storm Drain (6-0Calimesa Ave L.mpp 10/20/11
5
Riverside County Flood Control & Water Conservation District May 16, 2011Project No. 4056-SF Page No. 24
Aragón Geotechnical, Inc.
AGI recommends the uppermost 12 inches of soil materials below pavement
subgrades be processed and compacted to a minimum of 95 percent of the
laboratory maximum dry density determined by ASTM D 1557-09. Caltrans Class
2 aggregate base material should be compacted to a minimum of 95 percent of
maximum dry density. Pavement gradients should result in rapid and unimpaired
flows of runoff water to road shoulders and the new drainage improvements.
6.11 Soil Corrosivity
Chemical analyses were performed to provide a general evaluation of the corrosivity
of native alluvial soils. Tests included soluble sulfate and chloride ion contents, pH,
and saturated resistivity. Findings indicate the project soils should not be highly
aggressive to concrete but may be moderately corrosive to metal. Analytic tests of
3 samples of older alluvium reported peak soluble sulfate and chloride contents of
0.0029 percent and 20 parts per million respectively, with pH values of 6.7 to 7.0,
and a lowest-value saturated minimum resistivity of 3,000 ohm-cm. District
standards or a qualified corrosion engineer should be consulted for design details
and/or more in-depth evaluations of soils effects on buried ferrous objects, and for
any special corrosion protection design that may be required.
The very low sulfate concentrations indicate that normal Type I-II cement should be
suitable for concrete mix designs utilized for this project, based on American
Concrete Institute (ACI) 318 Table 4.3.1. AGI recommends that all concrete which
will contact on-site soil materials be selected, batched, and placed in accordance
with the latest Standard Specifications for Public Works Construction “Greenbook”
and ACI technical recommendations.
6.12 Soil Erosion Potential
The proposed construction will be taking place entirely within developed areas, and
will not be representative of disturbances in virgin ground. Soil erosion from local
streets is currently nil. However, some migration of soils from private property to the
streets has been observed by AGI staff during storms within the last two years.
6
Riverside County Flood Control & Water Conservation District May 16, 2011Project No. 4056-SF Page No. 25
Aragón Geotechnical, Inc.
A soil’s resistance to sheet and rill erosion is a function of textural gradation, clay
type, organic content, vegetation cover, structure of the surface horizon, and
permeability. Using data and estimations from this investigation, AGI would assign
a soil erodibility “K” factor of 0.15 to vacant bare-ground or tilled Calimesa older
alluvium per the methods of Wischmeier, Johnson and Cross (1971). For a typical
local construction site, this value would rise to roughly 0.20 considering surface
compaction and reduced infiltration capacity. Soil stockpiles would have lower “K”
factors.
Later work by the USDA distilled the Wischmeier et al. equation into a triangular
nomograph utilizing only the variables of percent silt + fine sand (0.002-0.1 mm),
percent sand (0.1-2.0 mm), and percent clay. A tested sample of near-surface
alluvium along the project alignment had about 58 percent, 34 percent, and 8
percent of these constituents, respectively, on a normalized basis minus coarser
fractions. The resulting “K” factor would be approximately 0.34. This highest-
estimated value would be conservative if needed for site risk classification in storm
water pollution plans or other water quality permit requirements.
6.13 Construction Observations
The preliminary geotechnical recommendations presented in this report are based
on the assumption that flood control improvements will be placed on competent
native materials or properly compacted engineered fill approved by this office. It is
recommended that trench backfill and street restoration operations be performed
with observation and quality control testing by AGI personnel. AGI services would
exclude direction of the contractor’s means and methods, field supervision of the
contractor’s workmen, or assumption of any responsibility for jobsite safety.
6.14 Investigation Limitations
The findings in this preliminary report may require modification as a result of later
field exploration or observations made prior to or during drain installation. If
conditions encountered during construction vary significantly from those indicated by
this report, then additional geotechnical recommendations may be required from this
7
2011-10-20_Risk determination worksheet.xlsx
Average Watershed Slope (%)Sheet Flow Length (ft) 0.2 0.5 1.0 2.0 3.0 4.0 5.0 6.0 8.0 10.0 12.0 14.0
<3 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.35 0.36 0.386 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.37 0.41 0.459 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.38 0.45 0.51
12 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.39 0.47 0.5515 0.05 0.07 0.09 0.13 0.17 0.20 0.23 0.26 0.32 0.40 0.49 0.5825 0.05 0.07 0.10 0.16 0.21 0.26 0.31 0.36 0.45 0.57 0.71 0.8550 0.05 0.08 0.13 0.21 0.30 0.38 0.46 0.54 0.70 0.91 1.15 1.4075 0.05 0.08 0.14 0.25 0.36 0.47 0.58 0.69 0.91 1.20 1.54 1.87
100 0.05 0.09 0.15 0.28 0.41 0.55 0.68 0.82 1.10 1.46 1.88 2.31150 0.05 0.09 0.17 0.33 0.50 0.68 0.86 1.05 1.43 1.92 2.51 3.09200 0.06 0.10 0.18 0.37 0.57 0.79 1.02 1.25 1.72 2.34 3.07 3.81250 0.06 0.10 0.19 0.40 0.64 0.89 1.16 1.43 1.99 2.72 3.60 4.48300 0.06 0.10 0.20 0.43 0.69 0.98 1.28 1.60 2.24 3.09 4.09 5.11400 0.06 0.11 0.22 0.48 0.80 1.14 1.51 1.90 2.70 3.75 5.01 6.30600 0.06 0.12 0.24 0.56 0.96 1.42 1.91 2.43 3.52 4.95 6.67 8.45800 0.06 0.12 0.26 0.63 1.10 1.65 2.25 2.89 4.24 6.03 8.17 10.40
1000 0.06 0.13 0.27 0.69 1.23 1.86 2.55 3.30 4.91 7.02 9.57 12.23
2.8%: 1.122 LS Factors for Construction Sites. Table from Renard et. al., 1997.
Alex DeusonRCFCCD10-20-2011
8
Station Upstream el.Reach length,
ft El difference, ft SlopeWeighted reach
length, ftWeighted slope
10+00.00 2444.86 ‐10+90.11 2447.797 90.11 2.937 3.26% 0.012848335 0.0419%11+97.67 2451.303 107.56 3.506 3.26% 0.015336444 0.0500%12+02.33 2451.424 4.66 0.121 2.60% 0.000664446 0.0017%15+47.67 2460.339 345.34 8.915 2.58% 0.049240307 0.1271%16+47.67 2461.515 100.00 1.176 1.18% 0.014258501 0.0168%16+52.33 2461.57 4.66 0.055 1.18% 0.000664446 0.0008%19+78.36 2465.402 326.03 3.832 1.18% 0.046486991 0.0546%19+80.36 2465.426 2.00 0.024 1.20% 0.00028517 0.0003%20+25.99 2465.962 45.63 0.536 1.17% 0.006506154 0.0076%20+27.99 2465.986 2.00 0.024 1.20% 0.00028517 0.0003%20+69.77 2466.477 41.78 0.491 1.18% 0.005957202 0.0070%20+81.93 2466.67 12.16 0.193 1.59% 0.001733834 0.0028%21+15.93 2466.898 34.00 0.228 0.67% 0.00484789 0.0033%24+16.20 2475.713 300.27 8.815 2.94% 0.042814001 0.1257%24+18.20 2475.771 2.00 0.058 2.90% 0.00028517 0.0008%25+72.67 2480.306 154.47 4.535 2.94% 0.022025106 0.0647%25+77.33 2480.443 4.66 0.137 2.94% 0.000664446 0.0020%26+79.05 2483.411 101.72 2.968 2.92% 0.014503747 0.0423%26+81.05 2483.469 2.00 0.058 2.90% 0.00028517 0.0008%30+36.67 2493.848 355.62 10.379 2.92% 0.050706081 0.1480%30+41.33 2494.847 4.66 0.999 21.44% 0.000664446 0.0142%34+08.73 2505.753 367.40 10.906 2.97% 0.052385732 0.1555%34+13.39 2505.892 4.66 0.139 2.98% 0.000664446 0.0020%34+87.67 2508.096 74.28 2.204 2.97% 0.010591214 0.0314%34+92.33 2508.201 4.66 0.105 2.25% 0.000664446 0.0015%36+55.09 2512.862 162.76 4.661 2.86% 0.023207136 0.0665%36+57.09 2512.919 2.00 0.057 2.85% 0.00028517 0.0008%37+75.56 2516.312 118.47 3.393 2.86% 0.016892046 0.0484%39+82.67 2522.243 207.11 5.931 2.86% 0.029530781 0.0846%39+87.33 2522.393 4.66 0.15 3.22% 0.000664446 0.0021%40+21.33 2523.482 34.00 1.089 3.20% 0.00484789 0.0155%40+23.33 2523.546 2.00 0.064 3.20% 0.00028517 0.0009%41+85.77 2528.75 162.44 5.204 3.20% 0.023161509 0.0742%41+87.77 2528.814 2.00 0.064 3.20% 0.00028517 0.0009%44+47.67 2537.139 259.90 8.325 3.20% 0.037057844 0.1187%44+52.33 2537.206 4.66 0.067 1.44% 0.000664446 0.0010%46+48.96 2540.039 196.63 2.833 1.44% 0.02803649 0.0404%46+50.96 2540.068 2.00 0.029 1.45% 0.00028517 0.0004%
Prj: Calimesa Avenue L Storm Drain, Stage 2No: 6‐0‐0165Date: 10‐20‐2011 Eng: AED
9
47+25.76 2541.145 74.80 1.077 1.44% 0.010665359 0.0154%47+27.67 2541.173 1.91 0.028 1.47% 0.000272337 0.0004%47+58.76 2541.621 31.09 0.448 1.44% 0.004432968 0.0064%47+60.76 2541.65 2.00 0.029 1.45% 0.00028517 0.0004%47+97.66 2542.181 36.90 0.531 1.44% 0.005261387 0.0076%48+02.33 2542.748 4.67 0.567 12.14% 0.000665872 0.0081%48+14.20 2543.432 11.87 0.684 5.76% 0.001692484 0.0098%48+59.17 2546.021 44.97 2.589 5.76% 0.006412048 0.0369%49+04.13 2548.61 44.96 2.589 5.76% 0.006410622 0.0369%49+27.67 2549.965 23.54 1.355 5.76% 0.003356451 0.0193%49+32.33 2550.169 4.66 0.204 4.38% 0.000664446 0.0029%49+99.01 2552.329 66.68 2.16 3.24% 0.009507568 0.0308%50+01.01 2552.394 2.00 0.065 3.25% 0.00028517 0.0009%53+54.62 2563.849 353.61 11.455 3.24% 0.050419485 0.1633%53+56.62 2563.914 2.00 0.065 3.25% 0.00028517 0.0009%53+68.34 2564.294 11.72 0.38 3.24% 0.001671096 0.0054%53+70.33 2564.358 1.99 0.064 3.22% 0.000283744 0.0009%54+27.67 2566.216 57.34 1.858 3.24% 0.008175824 0.0265%54+32.33 2566.374 4.66 0.158 3.39% 0.000664446 0.0023%58+83.04 2578.811 450.71 12.437 2.76% 0.064264489 0.1773%58+89.04 2579.016 6.00 0.205 3.42% 0.00085551 0.0029%59+02.34 2579.285 13.30 0.269 2.02% 0.001896381 0.0038%59+26.89 2579.783 24.55 0.498 2.03% 0.003500462 0.0071%59+44.10 2580.132 17.21 0.349 2.03% 0.002453888 0.0050%59+68.66 2580.63 24.56 0.498 2.03% 0.003501888 0.0071%59+72.63 2580.71 3.97 0.08 2.02% 0.000566062 0.0011%60+04.77 2584.842 32.14 4.132 12.86% 0.004582682 0.0589%60+06.75 2585.097 1.98 0.255 12.88% 0.000282318 0.0036%60+43.87 2589.869 37.12 4.772 12.86% 0.005292756 0.0680%60+51.86 2590.363 7.99 0.494 6.18% 0.001139254 0.0070%60+89.13 2591.643 37.27 1.28 3.43% 0.005314143 0.0183%60+91.05 2591.71 1.92 0.067 3.49% 0.000273763 0.0010%60+93.23 2591.788 2.18 0.078 3.58% 0.000310835 0.0011%61+17.10 2592.633 23.87 0.845 3.54% 0.003403504 0.0120%61+32.16 2593.166 15.06 0.533 3.54% 0.00214733 0.0076%61+56.03 2594.011 23.87 0.845 3.54% 0.003403504 0.0120%62+33.67 2596.76 77.64 2.749 3.54% 0.0110703 0.0392%62+38.33 2597.76 4.66 1 21.46% 0.000664446 0.0143%63+86.86 2598.737 148.53 0.977 0.66% 0.021178151 0.0139%66+72.67 2609.342 285.81 10.605 3.71% 0.040752221 0.1512%66+77.33 2609.516 4.66 0.174 3.73% 0.000664446 0.0025%68+44.00 2614.07 166.67 4.554 2.73% 0.023764643 0.0649%68+46.00 2614.125 2.00 0.055 2.75% 0.00028517 0.0008%70+72.67 2620.32 226.67 6.195 2.73% 0.032319744 0.0883%70+77.33 2620.447 4.66 0.127 2.73% 0.000664446 0.0018%73+40.34 2627.356 263.01 6.909 2.63% 0.037501283 0.0985%73+42.34 2627.409 2.00 0.053 2.65% 0.00028517 0.0008%
10
73+50.28 2627.617 7.94 0.208 2.62% 0.001132125 0.0030%74+20.95 2629.474 70.67 1.857 2.63% 0.010076483 0.0265%74+27.67 2629.65 6.72 0.176 2.62% 0.000958171 0.0025%74+32.33 2629.674 4.66 0.024 0.52% 0.000664446 0.0003%76+95.65 2630.963 263.32 1.289 0.49% 0.037545485 0.0184%76+97.65 2630.973 2.00 0.01 0.50% 0.00028517 0.0001%77+77.67 2631.364 80.02 0.391 0.49% 0.011409652 0.0056%77+82.33 2631.387 4.66 0.023 0.49% 0.000664446 0.0003%78+58.35 2631.688 76.02 0.301 0.40% 0.010839312 0.0043%78+60.35 2631.696 2.00 0.008 0.40% 0.00028517 0.0001%79+63.00 2632.102 102.65 0.406 0.40% 0.014636351 0.0058%79+67.34 2633.873 4.34 1.771 40.81% 0.000618819 0.0253%79+77.50 2635.43 10.16 1.557 15.32% 0.001448664 0.0222%80+13.36 2640.922 35.86 5.492 15.32% 0.005113098 0.0783%80+13.36 2640.9227013.36 Total reach Σ: 2.7956%
11
CALIMESA--AVENUE L STROM DRAIN, STAGE 2PROJECT NO. 5-0-00165
AED 10-20-2011
Receiving Water (RW) Risk Factor Worksheet Entry Score
A. Watershed Characteristics yes/noA.1. Does the disturbed area discharge (either directly or indirectly) to a303(d)-listed waterbody impaired by sediment? For help with impaired waterbodies please check the attached worksheet or visit the link below:2006 Approved Sediment-impared WBs Worksheet
http://www.waterboards.ca.gov/water_issues/programs/tmdl/303d_lists2006_epa.shtml
ORA.2. Does the disturbed area discharge to a waterbody with designated beneficial uses of SPAWN & COLD & MIGRATORY?
http://www.ice.ucdavis.edu/geowbs/asp/wbquse.asp
no Low
12
1
LINEAR UNDERGROUND/OVERHEAD PROJECT FLOWCHARTS Chart Number I
Determining if your project qualifies for coverage State Water Board Order 2009-0009-DWQ
The construction project may be
subject to a construction
permit.
Contact your RWQCB
*See Definition of Terms
Start
Start Over
Yes
Yes
Yes
Yes Yes
No
No
No
No
Yes
No Don’t know
MS4 = Municipal Separate Storm Sewer System RWQCB = Regional Water Quality Control Board NPDES = National Pollutant Discharge Elimination System
No
STOP Permit coverage may not be
required. Contact your RWQCB if necessary.
Are the activities
to be conducted associated with a
construction project that will result in land
disturbances?
STOP This project may
Not be subject to this Attachment. It may be subject to
traditional construction requirements or an individual
NPDES permit.
Is the project associated with a linear type
construction activity*?
Is this project owned or
operated by an entity currently permitted
by an MS4 permit?
Is the MS4 permit a
Phase II permit?
Is the MS4 permit a
Phase I permit?
Does the MS4 permit
regulate construction activities in Lieu of a
separate NPDES permit?
STOP You do not need a separate permit.
A
A
2
Chart Number II Determining if your project qualifies for coverage
State Water Board Order 2009-0009-DWQ
A
The State of CA does not have authority to permit discharges on sovereign
lands - you should contact the tribal EPA or USEPA
C
*See Definition of Terms
CGP = Construction General Permit LUP = Linear Underground/Overhead Project NPDES = National Pollutant Discharge Elimination System SW = Storm Water
This project is associated with
pre-development activities*.
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
YesNo
No No
Yes
Yes
No No
Yes
No
Yes
No
B
Will any or all of the construction
occur on Tribal Lands?
Will the construction
occur in the Lake Tahoe
Hydrologic Unit?
The Lahontan RWQCB has a separate construction
stormwater permit for this basin - you should contact the RWQCB to obtain the
applicable permit
Are these activities considered a
maintenance* project?
Are these activities for
the purpose of responding to an
emergency*?
The activities may be exempt from the
requirements of this CGP. Contact your
RWQCB or SWRCB contact to verify.
Are these activities for
the purpose of planning/designing
* a new project?
Are these activities only for a “tie-in”*
immediately adjacent to an energized or
pressurized facility?
Are all other Linear
construction activities associated with the tie-in covered under the CGP by a 3rd party or
municipal agency?
Are these activities for oil
or gas exploration, transmission,
processing, treatment, or production?
These activities are exempt from
obtaining coverage under the CGP.
Do the activities comply with the CWA oil & gas SW permit
exemption conditions?
Are these activities
associated with a private or public New Development Project or a Re-Development
Project?
Are these activities to
relocate linear facilities prior to construction of a
project?
3
Chart Number III
Determining if your project qualifies for coverage State Water Board Order 2009-0009-DWQ
B Coverage under the
CGP is not required for the linear activities.
A construction SW NPDES Permit may be required for the linear activities.
Coverage under the CGP is required for all
the linear activities.
Coverage under the CGP is required;
See Attachment A.1
No
Yes
Yes
No
Yes
* See Attachment No. 1 – Definition of Terms ** Note: The “developer” is associated with the New Development Project or Redevelopment Project* and the CGP is the Construction General Permit issued by the State Water Board.
CGP = Construction General Permit LUP = Linear Underground/Overhead Project NPDES = National Pollutant Discharge Elimination System SD = Soil Disturbance SW = Storm Water
Yes
Is the developer**
covering all of the linear activities
under their CGP?
Is the New Development or Redevelopment* Project SD < 1
acre?
Is the developer**
covering only the linear activities inside
the development under the
CGP?
Is the soil disturbance from these linear
activities ≥ 1 acre?
The developer ** is covering none of
the linear activities under the CGP
Determine the area of soil disturbance for the linear activities to be conducted by the LUP discharger.
Coverage under the CGP may be required for the
linear activities conducted outside the development
boundary.
Determine the area of soil disturbance for the linear activities to be conducted by the LUP discharger.
No
No These linear
activities do not require coverage under the CGP.
4
Chart Number IV
Determining if your project qualifies for coverage State Water Board Order 2009-0009-DWQ
Linear Only Projects and
Relocations Prior to New Development Projects or Redevelopment Projects*
C
These linear activities do not require coverage under the CGP.
No
Yes
* See Definition of Terms
CGP = Construction General Permit NPDES = National Pollutant Discharge Elimination System SW = Storm Water
Is the soil
disturbance from these linear
activities ≥ 1 acre?
See Attachment A.1
5
LUP Flowcharts - Definition of Terms Determining if your project qualifies for coverage
State Water Board Order 2009-0009-DWQ 1. Emergency Activities – These are activities associated with responding to emergencies to protect public health and
safety and restoration of public services after natural or manmade disasters. 2. Linear Construction Activity – Linear construction activity consists of underground/ overhead facilities that
typically include, but are not limited to, any conveyance, pipe or pipeline for the transportation of any gaseous, liquid (including water, wastewater for domestic municipal services), liquescent, or slurry substance; any cable line or wire for the transmission of electrical energy; any cable line or wire for communications (e.g., telephone, telegraph, radio or television messages); and associated ancillary facilities. Construction activities associated with LUPs include, but are not limited to those activities necessary for the installation of underground and overhead linear facilities (e.g., conduits, substructures, pipelines, towers, poles, cables, wires, connectors, switching, regulating and transforming equipment and associated ancillary facilities) and include, but are not limited to, underground utility mark-out, potholing, concrete and asphalt cutting and removal, trenching, excavation, boring and drilling, access road and pole/ tower pad and cable/ wire pull station, substation construction, substructure installation, construction of tower footings and/or foundations, pole and tower installations, pipeline installations, welding, concrete and/or pavement repair or replacement, and stockpile/ borrow locations.
3. Planning/ Designing Activities – These are field activities associated with the planning and design of a project (e.g., activities associated with route selection). These could include, but are not limited to, potholing, sediment coring, and limited excavations to verify conflicts or contaminated soils.
4. Pre-Development Activities – These are construction activities associated with LUPs conducted by a discharger or its authorized representative to remove and/or relocate lines and facilities prior to the start of construction for new development and redevelopment projects that are owned or operated by third parties or municipal agencies. Soil disturbances from preconstruction projects are considered separately from the development or redevelopment projects for the purposes of determining if they meet minimum threshold requirements for areas of soil disturbance that would require coverage by a construction storm water permit.
5. Redevelopment Projects – Involve construction activities associated with LUPs constructed by the discharger to relocate lines or convert facilities from overhead to underground as a result of a redevelopment project owned or operated by a third party or municipal agency.
6. Routine Maintenance Activities – Activities associated with operations and maintenance activities that are conducted on existing lines and facilities and within existing right-of-ways, easements, franchise agreements, or other legally binding agreements of the discharger. Routine maintenance projects include, but are not limited to projects conducted to:
a. Maintain the original purpose of the facility or hydraulic capacity. b. Update existing lines1 and facilities to comply with applicable codes, standards, and regulations
regardless if such projects result in increased capacity. c. Repairing leaks
Routine maintenance does not include construction of new2 lines or facilities resulting from compliance with applicable coders, standards, and regulations. Routine maintenance does not include those areas of maintenance projects that are outside of an existing right-of-way, franchise, easements, or agreements.
7. Tie-in Activities – Activities conducted immediately adjacent to “energized” or “pressurized” facilities by the discharger or their authorized representative and are not considered small construction activities where all other LUP construction activities associated with the tie-in are covered by an NOI and SWPPP of a third party or municipal agency.
1 Update existing lines includes replacing existing lines with new materials or pipes. 2 New lines are those not associated with existing facilities and are not part of a project to update or replace existing lines.
ATTACHMENT A.1
2009-0009-DWQ as amended by 2010-0014-DWQ September 2, 2009 as modified on November 16, 2010 1
ATTACHMENT A.1
LUP Project Area or Project Section Area Type Determination
Yes
No
Will ≥ 70% of the construction
activity occur on paved
surfaces**?
No
Yes
Yes
Yes
Yes
No
No
Yes
No
No
No
E
Will the construction
activity occur on unpaved improved
roads, including their shoulders or land
immediately adjacent to them?
Will > 30%
of the construction activity occur within the non-paved shoulders or
land immediately adjacent to paved
surfaces?
Will areas disturbed be
returned to pre-construction conditions
or equivalent condition* at the end
of the day?
Will areas of
established vegetation disturbed by the
construction be stabilized and revegetated by the
end of the project?
When required, will
adequate temporary stabilization BMPs be
installed and maintained until vegetation is established to meet the Permit’s minimum
cover requirements for final stabilization?
This is a Project
Type 1 LUP
*See Definition of Terms ** Or: “Will < 30% of the soil disturbance occur on unpaved surfaces?
Yes
Will areas disturbed
be returned to pre-construction conditions
or equivalent condition* at the end
of the day?
ATTACHMENT A.1
2009-0009-DWQ as amended by 2010-0014-DWQ September 2, 2009 as modified on November 16, 2010 2
ATTACHMENT A.1 LUP Project Area or Project Section Area
Type Determination
Is the
project area or project section area
located within a Sediment Sensitive
Watershed*?
No
E
Receiving Water Risk:
“HIGH”
Yes
No
Is the
project area or section located within the flood plain or flood prone area
(riparian zone) of a Sensitive Receiving
Water Body*?
Receiving Water Risk: “MEDIUM”
Yes
Receiving Water Risk:
“LOW”
Calculate the Sediment Risk Based on Appendix 1 Risk Factor Worksheet Project Sediment Risk =
“LOW”: <15 tons/acre “MEDIUM”: ≥ 15 and < 75 tons/acre; or
“HIGH”: ≥ 75 tons/acre
* See Definition of Terms
PROJECT SEDIMENT RISK
LOW MEDIUM HIGH LOW Type 1 Type 1 Type 2
MEDIUM Type 1 Type 2 Type 3 HIGH Type 2 Type 3 Type 3
RECEIVING WATER RISK
ATTACHMENT A.1
2009-0009-DWQ as amended by 2010-0014-DWQ September 2, 2009 as modified on November 16, 2010 3
ATTACHMENT A.1 Definition of Terms
1. Equivalent Condition – Means disturbed soils such as those from trench excavation are required to be hauled
away, backfilled into the trench, and/or covered (e.g., metal plates, pavement, plastic covers over spoil piles) at the end of the construction day.
2. Linear Construction Activity – Linear construction activity consists of underground/ overhead facilities that typically include, but are not limited to, any conveyance, pipe or pipeline for the transportation of any gaseous, liquid (including water, wastewater for domestic municipal services), liquescent, or slurry substance; any cable line or wire for the transmission of electrical energy; any cable line or wire for communications (e.g., telephone, telegraph, radio or television messages); and associated ancillary facilities. Construction activities associated with LUPs include, but are not limited to those activities necessary for the installation of underground and overhead linear facilities (e.g., conduits, substructures, pipelines, towers, poles, cables, wires, connectors, switching, regulating and transforming equipment and associated ancillary facilities) and include, but are not limited to, underground utility mark-out, potholing, concrete and asphalt cutting and removal, trenching, excavation, boring and drilling, access road and pole/ tower pad and cable/ wire pull station, substation construction, substructure installation, construction of tower footings and/or foundations, pole and tower installations, pipeline installations, welding, concrete and/or pavement repair or replacement, and stockpile/ borrow locations.
3. Sediment Sensitive Receiving Water Body – Defined as a water body segment that is listed on EPA’s approved CWA 303(d) list for sedimentation/siltation, turbidity, or is designated with beneficial uses of SPAWN, MIGRATORY, and COLD.
4. Sediment Sensitive Watershed – Defined as a watershed draining into a receiving water body listed on EPA’s approved CWA 303(d) list for sedimentation/siltation, turbidity, or a water body designated with beneficial uses of SPAWN, MIGRATORY, and COLD.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 57 January 2012
Appendix B: Site Maps
1
VICINITY MAPNTS
RIVERSIDE
CORONA
TEMECULA
MURRIETA
PERRIS
MORENO
VALLEY
HEMETIDYLLWILD
ANZA
AGUANGA
ELSINORE
BEAUMONT
SAN JACINTO
BANNING
243
371
111
10
10
10
15
15
79
79
7974
74
74
74
60
79
74
215
215
111
PALM
SPRINGS
LAKE
LAKE
LAKE LAKE
PERRIS
SKINNER
ELSINORE
MATHEWS
HEMET
RESERVOIR
60
NORCO
RIV
ER
SIDE
COUNTY
COUNTY
OR
AN
GE
RIVERSIDE COUNTY
SAN BERNARDINO COUNTY
SAN DIEGO CO.
SAN DIEGO CO.
RIVERSIDE CO.
91
CALIMESA
DESERT
HOT SPRINGS
LAKE
VAIL
RESERVOIR
EASTSIDE
62
LOCATIONPROJECT
LOCATION MAP
ST
ST
2N
D
CA
LIF
OR
NIA
ST
ST
ST
FR
EM
ON
T
DO
UG
LA
S
BR
YA
NT
DO
NN
AL
N CT
LN
BA
RN
ES
WA
RD
ENDPROJECT
LN
STP
AR
KBUENA VISTA 4
TH
CT
5T
HAVENUE
HO
LL
Y
AVCOUNTY
ERWINLINE
RD
ST
ST
B
LINE
AVENUE
AV
EN
UE
CT
COUNTY
AVENUE
K
K
AR
CHIE
PL
VA
LL
EY
L
7T
H
AVENUE
L
ST
4T
H
MYRTLEWOOD DR
10
CA
LI
ME
SA
LN7TH L
N
LN
CH
ER
RY
BEGINPROJECT
ST
SU
ND
AR
DR
3R
D
SANDALWOOD
SA
ND
AL
WO
OD
MU
LB
ER
RY
ST
DR
BL
VD
RD
BR
OO
K
FR
WYS
HA
DY
RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FR
EM
ON
T
ST
2.
3.
4.
5.
6.
7.
8.
1.
WATER POLLUTION CONTROL DRAWING NOTES
LINEAR SEDIMENT CONTROLS (SILT FENCING, FIBER ROLLS, ETC.) WILL BE DEPLOYED ON DISTURBED SLOPES (IF ANY).
LINEAR SEDIMENT CONTROLS WILL ALSO BE USED AS A PERIMETER CONTROL TO CONTAIN SEDIMENT WITHIN THE PROJECT AREA.
STORM DRAIN INLETS DOWNGRADIENT OF DISTURBED SOIL AREAS WILL BE PROTECTED.
A STABILIZED CONSTRUCTION ENTRANCE/EXIT WILL BE CONSTRUCTED. ADDITIONAL ENTRANCES/EXITS WILL BE CONSTRUCTED AS NEEDED.
WATER WILL BE APPLIED TO DISTURBED AREAS AND STOCKPILES AS NECESSARY TO PREVENT OR ALLEVIATE EROSION BY THE FORCES OF WIND.
SELECTED FOR THE CONSTRUCTION SITE WILL ALSO BE IMPLEMENTED AT THE STAGING AREA. SPECIAL ATTENTION TO THE
FOLLOWING BMPS WILL BE TAKEN AT THE STAGING AREA: NS-9, NS-10, WM-1, WM-3, WM-4, WM-5, WM-8, AND WM-9.
ANY STOCKPILES WILL BE LOCATED A MINIMUM OF 50 FEET AWAY FROM CONCENTRATED FLOWS OF STORM WATER, DRAINAGE
COURSES, AND INLETS. ALL STOCKPILES WILL BE BERMED. ADDITIONALLY, STOCKPILES WILL BE COVERED AT ALL TIMES (TO PROTECT
THEM FROM WIND AND THE RAIN WHEN THEY ARE NOT ACTIVELY BEING USED. STOCKPILES THAT ARE UNSTABILIZED DURING CONSTRUCTION
ACTIVITES WILL BE SPRAYED WITH WATER AS NEEDED FOR DUST CONTROL.
AN ABOVE GRADE OR MOBILE CONCRETE WASHOUT WILL BE CONSTRUCTED OR PLACED AT THE STAGING AREA IF CONCRETE TRUCKS OR
CONCRETE EQUIPMENT WILL BE WASHED ON-SITE. THE WASHOUT WILL BE LOCATED A MINIMUM OF 50 FEET AWAY FROM CONCENTRATED
FLOWS OF STORM WATER, DRAINAGE COURSES, AND INLETS. ADDITIONAL WASHOUTS WILL BE UTILIZED AS NEEDED.
THE CONTRACTOR SHALL INSPECT ALL ROADWAYS ADJACENT TO THE PROJECT SITE DAILY. THE CONTRACTOR SHALL REMOVE ANY
SEDIMENT OR OTHER CONSTRUCTION ACTIVITY RELATED MATERIALS THAT ARE DEPOSITED ON THE ROADS BY VACUUMING OR
SWEEPING ON A DAILY BASIS (WHEN NECESSARY) AND PRIOR TO ANY RAIN EVENT.
SANDBAG BARRIER WILL BE USED TO DIVERT RUN-ON AROUND ACTIVE CONSTRUCTION SITE.
LIST OF BMPs TO BE IMPLEMENTED
EC-1
SE-7
SE-8
SE-10
WE-1
TC-1
SCHEDULING
STREET SWEEPING AND VACUUMING
SANDBAG BARRIER
STORM DRAIN INLET PROTECTION
WIND EROSION CONTROL
STABILIZED CONSTRUCTION ENTRANCE/EXIT
NS-1
NS-6
WM-4
WM-1
WM-8
WM-9
WATER CONSERVATION PRACTICES
ILLICIT CONNECTION/ILLEGAL DISCHARGE DETECTION AND REPORTING
MATERIAL DELIVERY AND STORAGE
SPILL PREVENTION AND CONTROL
SANITARY/SEPTIC WASTE MANAGEMENT
WM-6
NS-3 PAVING AND GRINDING OPERATIONS
NS-8
NS-9 VEHICLE AND EQUIPMENT FUELING
NS-10 VEHICLE AND EQUIPMENT MAINTENANCE
NS-12 CONCRETE CURING
WM-3 STOCKPILE MANAGEMENT
SE-1
SE-5
SILT FENCE
FIBER ROLLS
CONCRETE WASTE MANAGEMENT
SOLID WASTE MANAGEMENTWM-5
HAZARDOUS WASTE MANAGEMENT
12
13
10 1116
17
14 154
5
2 3 8 96 7
A STAGING AREA WILL BE DESIGNATED AT THE PROJECT SITE BY THE PROJECT MANAGER AS SHOWN ON SHEET 18. BMPS
VEHICLE AND EQUIPMENT CLEANING
LEGEND
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
S
GNV
GNV
GNV
GNV
POOL
S
T
T GCONC.
GA
TE
GA
TE
CONC.
CONC.
CONC.
CONC.
CONC.
CONC.
GATE
CONC.
ASPH.
ASPH.
CONC.
CONC.CONC.
CONC. CONC.
Z 11270
R/W
R/WR/W
R/W
R/
W
R/
W
R/
W
R/
W
R/
W
R/
W
R/W
R/W
S
G2
G2
GNV
GNV
GNV
GNV
POOL
G4 G4
G2
G2
G4
S
SS8SS8
SS8
SS
8
SS
8W6
W14
W12
T
TT T
T
W12
W6
W14
G2
W14
W6
T GCONC.
GA
TE
GA
TE
CONC.
CONC.
CONC.
W8
CONC.
CONC.
CONC.
GATE
CONC.
ASPH.
ASPH.
R/W
R/WR/W
R/W
R/
W
R/
W
NPW24
NPW24
NPW24
W8
W5
AB
AN
D
R/
W
R/
W
R/
W
R/
W
R/W
R/W
NON-POTABLE WATER
NON-POTABLE WATER
NON-POTABLE WATER
W12
SS
8
G2
W8
W14
W5
AB
AN
D
SS
8
CONC.
CONC.CONC.
CONC. CONC.
É AVENUE L
É AVENUE L
É
4T
H
ST
RE
ET
É
4T
H
ST
RE
ET
NPW24
W8
G2
2450
2450
24
55
24
60
24
60
24
60
2450
2
SE
E
SH
EE
T 3
MONITORING LOCATION A
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L
É AVENUE L
É
4T
H
ST
RE
ET
É
4T
H
ST
RE
ET
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
SE-7
SE-7
SE-7
SE-10
SE-10SE-10
SE-10
S
BRICK
CONC
GRAVEL
BRIC
K GAR
DEN EDGING
ASPH.
ASPH.
LIN
E
PL
AC
ED
PE
R
SU
RV
EY L
OC
ATIO
N
PL
AN S
HO
WS
GAS
@ 14
WE
ST
OF
C/
L
SS
TEL
ASPH.
ASPH.
CONC.
CONC.
E
TV
GATE
GATE
CONC.
GU
TT
ER
CO
NC
RE
TE
T
GATE
STA.82+00STA.81+00STA.80+00Z 11273
WP
19
WP
20
STA.79+00STA.78+00
R/W
R/WR/W R/W
R/W
S
SU
ND
AR
DRIV
EG
2
ASPH.
ASPH.
G4
G2G2
G4
LIN
E
PL
AC
ED
PE
R
SU
RV
EY L
OC
ATIO
N
PL
AN S
HO
WS
GAS
@ 14
WE
ST
OF
C/
L
SS
TEL
SS8SS8
W6W6
TT
T
ASPH.
ASPH.
CONC.
CONC.
E
TV
GATE
GATE
CONC.
GU
TT
ER
CO
NC
RE
TE
T
GATE
R/W
TV/
EL/
T
NPW24NPW24
W6
SS
8
NON-POTABLE WATER
NON-POTABLE WATERNON-POTABLE WATER
AVENUE L
G4
G2
SS8
W24
W6
T(F/O)
W8W8W8
W8
2475
2475
2465
2465
24
65
24
70
2470
2470
2470
2475
2470
3
SE
E
SH
EE
T
4
SE
E
SH
EE
T
2
MONITORING LOCATION F
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L
É
SU
ND
AR
DRIV
E
11 12 13 14 15
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
SE-7
SE-7
SE-7
SE-7
SE-7
NS-3 NS-3NS-3
NS-12
S
BRICK
CONC
CONC
GRAVEL GRAVEL
CONC
A/C
CONC
BRICK
CONC
BRICK
GA
TE
A/
C
GR
AV
EL
CONC
SIG
N
GATE
GATE
A/C
GRAVEL
T
A/C
CONC
GRAVEL
CO
NC
GAR
DEN EDGING
TV
R/W
R/WR/W
R/W
R/
W
G2
G2
G2
SS8
W24
T(F/O)
G2 ABND
G4
SS8
TV
G2
G4
W24
W6
SS8
E/
TV
W6
T(F/O)
G4
W8 W8 W8 W8
W8
G4
G6
24
80
24
80
2480
24
85
2485
24
85
2485
4
SE
E
SH
EE
T 3
SE
E
SH
EE
T 5
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE LÉ AVENUE L
16 17 18 19 20
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
SE-
7
NS-3
NS-3
NS-
3
SE-
10
SE-
10
NS-12
NS-
12
NS-
12
S
S
BRIC
K
GATE
DIRT
A/C
GRAVEL
DELLORC/A MREB
TE
L
T
CO
NC
CO
NC
GR
AS
S
A/
C
T
VE
NT
AIR
CO
NC
ROLLED A/C BERM
GRAVEL
A/C
CONC
GARDEN EDGING
A/C
A/CA/C
R/R TIES
R/
R
TIE
S
GA
RD
EN
ED
GIN
G - T
WO
BY F
OU
RS
GRAVEL
A/C BERMA/C BERM
UNABLE TO FIELD VERIFY
TV
PL
AC
ED
PE
RP
LA
N
Z 13831
A/C BERM
R/
W
R/
W
R/
W
R/W
R/W
R/W
R/WR/W
R/W
R/W
G4
SS
8
W2
4
W6
T(F/
O)
W8
SS8 SS8
SS
8
W2
4
T
T(F/
O)
G2
AB
ND
G2
AB
ND
W24
W8
G3
W24W24
SS
8
G1
TV
T24
W8
W24
SS8
G3
T(F/O)T(F/O)T(F/O)
W6
W8
G4
G4
W8
W24
W4 ABND W4 ABNDW4 ABND
W8
W6
W8
G4
2485
2485
2485
2490
2490
24
85
5
020’ 20’020’ 20’
SEE SHEET 6
SEE SHEET 4
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
PRIV
AT
E
DRIV
E
THIRD STREET
É
AV
EN
UE
L
É THIRD STREET
É THIRD STREET
20
21
22
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7SE-7
SE-7
SE-7
SE-7
NS-
3
NS-
3
NS-3
NS-
3
SE-10
SE-10
SE-10
SE-10
NS-12
NS-12
NS-12
NS-12
NS-12
S
S S
CONC
GRASS
COSS
GATE GATE
A/C
GRAVEL
GRAVEL
GATE
A/
C
BE
RM
A/
C
BE
RM
A/
C
BE
RM
A/
C
BE
RM
GUY POLE
GNV
GNV
GNV
A/C
CONC
CONC
CONC
A/C
CONC
CONC
CONC
CONC
WP
4W
P
3
Z 13834
R/W
R/
W
R/W
R/
W
R/W
R/WR/W
R/W
G2
W24
G4
SS
8
W8
W6
SS
8
W4
SS
8
G2
SS
8
W4
G4
SS8
W24
W6
T(F/O)
W24
W6
SS8
G4
SS
8
W4
W4
T(F/O)
SS8
T(F/O)
W8W8 W8
2490
2490
24
95
2495
24
95
2500
2500
25
00
25
05
2495
6
SE
E
SH
EE
T 7
SE
E
SH
EE
T
5
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L
É
BR
AD
Y
LA
NE
23 24 25 26 27 28
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
SE-7NS-3 NS-3 NS-3
SE-10
SE-10
NS-12
NS-12
NS-12
S
S
A/C
GRAVEL
CONC
DIRT
GATE
GATE
GATE
A/C
BRICK WALKWAY
A/C
CONC
A/C
TEL
A/C
T
GRAVEL
GRAVEL
GRAVEL
CONC
CONC
CONC
PAVERS
PAVERS
A/C
CONCA/C
CONC
CONC
A/C
A/C
CONC
Z 13702
R/
W
R/
W
R/W
R/W R/W
R/W
R/W
W6
W24
SS8
G4
T(F/O)
W4
G2
SS
8
SS
8
W24
W6
G4
W24
T(F/O)
SS
8
T
T(F/O)
SS8
T(F/O)
(F/O)
W8W8
W8
25
05
2510
25
10
25
15
2515
7
SE
E
SH
EE
T
8
SE
E
SH
EE
T 6
MONITORING LOCATION G
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
2N
D
PL
AC
E
É AVENUE L
É
2N
D
PL
AC
E
É AVENUE L
28 29 30 31 32 33
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7 SE-7
SE-7
SE-7
NS-3
NS-3
NS-3
SE-10NS-12
NS-12
S
T
S
BRICK WALKWAY
CONC
CONC
PAVERS
PAVERS
CONC
RO
LLE
DA/
CB
ER
M
A/
C
CO
NC
F/O
GA
TE
RO
LLE
D
A/
C
BE
RM
CONC
CONC
BRIC
K
CONC
A/C
GATE
GATE
A/C
PLACED PER PLANT(F/O)
CONC
A/C
Z 13705Z 13706
R/WR/
W
R/
W
R/W
R/W
R/
W
R/W
G4G4
G2
G2
W8
SS8
W24
SS
8
W6
T(F/O)
SS
8
T2
4
W4
AB
ND
W6
SS8
W24
T(F/O)
T2
4
E
W8
W8W8 W8 W8
G2
25
15
2515
25
20
2520
25
20
2525
2530
2530
25
30
8
SE
E
SH
EE
T
9
SE
E
SH
EE
T
7
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L
É
2N
D
ST
RE
ET
É AVENUE L
É
DO
NN
A
LA
NE
33 34 35 36 37
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
SE-7
SE-7
SE-7
NS-3
NS-3
NS-3
NS-3
NS-3
SE-10
SE-
10
SE-
10
NS-12
NS-12
NS-12
NS-
12
NS-
12
S
S
E
CONC
SIDEWALK
CO
VE
RE
D
DR
AIN
CONC
PA
VIN
G S
TO
NE
S
CONC
TV
TV
E
TV
TEL
F/O?
E
T
GATE
A/C
EL
GA
RD
EN
ED
GIN
G
POOL
MTRWTR
A/C
CONC
WP
11
WP
12
Z 13723
R/
W
R/W
R/W
R/W
R/
W
R/W
G3
G4
G4
G2
SS8
E/TV
T(F/O)
SS
8
SS
8S
S8
W8
W8
W24
W8
E/
TV/(F/
O)
G4
W8
SS8
T(F/O)
E/
TV
E
G4
SS8
W24
T(F/O)
W24
W8
SS
8
W8 W8W8
25
35
2535
2535
2540
2540
25
40
2545
25
45
25
45
2550
2550
9
SE
E
SH
EE
T
10
SE
E
SH
EE
T 8
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L
É
BA
RN
ES
CO
UR
T
É AVENUE L
38 39 40 41 42 43
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7SE-7
SE-7
SE-7
NS-3
NS-3
NS-3
NS-3
SE-10
SE-10
NS-12
NS-12
SS
T
S
BRIC
K
A/C
A/C
CONC
A/C
CO
NC
A/
C
GA
TE
CO
NC
TE
L
CO
NC
GR
AV
EL
VE
NT
AIR
IRR
IRR
EL
E
TV/TEL
TEL
TV
TVE
TEL
A/C
CONC
GRAVEL
A/C E
GATE
ROCK
ROCK
BRICK
KCIR
B
CO
NC S
UR
FA
CE
DR
AIN
F/O
AP
PR
OXIM
AT
E
LO
CA
TIO
N
POOL
CONCCONC
WP
10
WP
9
Z 13709
Z 13724
R/W
R/W
R/
W
R/
W
R/W
R/W
R/
W
R/
W
R/
W
R/
W
G3G3
G3
G4
G2
W8
W8
W24
SS8
W4
AB
ND
W4 ABND
W2
4
W24
SS
8
SS8
T
E
W8
W8
SS
8
W4
AB
ND
E
E/TVT(F/O)
T(F/O)T(F/O)
W2
4
E/
TV
T
T2
4
E
?? UNIDENTIFIED UTIL
E
E
SS8
W24
W8
G4
T24
W8W8
25
50
25
50
2550
25
55
2555
25
60
2560
25
60
2560
2565
10
SE
E
SH
EE
T 11
SE
E
SH
EE
T 9
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L
É AVENUE L
É
CA
LIF
OR
NIA
ST
RE
ET
É
CA
LIF
OR
NIA
ST
RE
ET
É
WA
RD
LA
NE
44 45 46 47 48
49
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
SE-7
SE-7
SE-7NS-3 NS-3
NS-3
NS-3
NS-3
SE-10SE-10
SE-
10S
E-
10
NS-12NS-12
NS-12
NS-12
NS-
12
NS-
12
T
S
S
A/C
GR
AV
EL
A/C
CONC
BRICK
PLANTER
A/C
GR
AV
EL
CONCCONC
GRAVEL
A/C
ST
EE
LP
LAT
EC
ON
C
CH
AN
NE
L
CONC
CONC
A/C
A/C
CONC
GR
AV
EL
A/C
CONC
CHILD CARE FACILITY?
FORMER AMUSEMENT PARK?/
A/C
R/W
R/W
R/W
R/W
W24
T(F/O)
SS
8
G3
SS8
W8
W24
T(F/O)
G3
SS8
W8
G3
SS8
W24
W8
T(F/O)
25
65
25
65
2565
25
70
2570
25
70
2575
2575
25
75
25
80
25
80
2580
25
80
11
SE
E
SH
EE
T 12
SE
E
SH
EE
T
10
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L49 50 51 52 53 54
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7 SE-7SE-7 SE-7
NS-3NS-3 NS-3
SE-10SE-10
SE-10
NS-12NS-12
NS-12NS-12
NS-12
NS-12
S
GRAVEL
A/CA/C
CONC
GRAVEL
BRIC
K
GRAVEL
GRAVEL
TEL TEL
CONC
CONC
ASPH
GRAVEL
CONC
A/C
CONC
CONC
GRAVELCONC
GRAVEL
A/C
CONC
CONC
CONCA/C
CONC
CONC
CONC
R/WR/W
R/WR/W
G3
W8
SS8
W24
T(F/O)
T(F/O)
W8
G3
SS8
W24
W8
T(F/O)
T(F/
O)
W242580
25
80
2585
2585
2590
25
90
2590
25
95
2595
25
95
12
SE
E
SH
EE
T 13
SE
E
SH
EE
T
11
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L55 56 57 58 59
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7 SE-7
SE-7
SE-
7
NS-3 NS-3NS-3
SE-10
SE-10
NS-12
NS-12
NS-12
NS-12
T
W
S
S
GR
AV
EL
GR
AV
EL
TE
LT
EL
CO
NC
CO
NC
AS
PH
CONC
A/C
BLOCK EDGING
BRICK
GRAVEL
R/
R
TIE
S
CO
NC
PO
LE
GU
Y
VE
NT
AIR
GR
AV
EL
A/
C
A/C BERMA/C BERM (3’ WIDE)GRAVEL
BRIC
K
CONC
PER FIELD LOCATION - 3.5’ WEST OF GAS PLAN
PE
R
FIE
LD
LO
CA
TIO
N
GA
TE
IN
VA
ULT
B/
O
VA
LV
E
UNABLE TOFIELD VERIFY
PL
AC
ED
PE
R
PL
AN
CO
NC
CO
NC
CO
NC
CO
NC
Z 13712
WP 13
WP 14
Z 13725
R/W
R/W
R/
W
R/W
R/W
R/
W
R/
W
R/
W
R/W
G3
G3
G1
W8
W8
W10
W54W54
SS8SS8
SS
8S
S8
W8
T(F/
O)
W24
SS
6
W4
AB
ND
W4
AB
ND
W6 ABND
W8
W8
G3G2
??
W
W ?W6 ABND
W8
W54
SS8
G3
T(F/O)
T(F/O)T(F/O)
W2
4
G6
G6G6
G6
G3
AB
ND
G3
AB
ND
2595
25
95
2595
2600
2600
26
00
2600
2600
2605
2605
26
05
2605
13
020’ 20’020’ 20’
SEE SHEET 14
SEE SHEET 12
MONITORING LOCATION H
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
SY
LL
MA
R
CIR
CLE
BRYANT STREET
É
AV
EN
UE
L
É BRYANT STREET
É BRYANT STREET
60
61
62
60+93.23
BC
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
SE-7
NS-
3
NS-
3
NS-
3
SE-10
SE-10
SE-10
SE-10
NS-12
NS-12
NS-12
NS-12
NS-12NS-12
NS-12
NS-12
S
S
CONC
CONC
CONC
GATE
CONC
GATE
CONC
CONC
A/C
DIRT
GATE
CONC
DIRT
CONC
CONC
A/CA/C
GATE
A/C
CONC
GR
AV
EL
A/C
CONC
GATE
A/C
&
GRAVEL
A/C
GATEGATE
CONCCONC
CONC
CONC
Z 13714
R/W
R/W
W8
W6
W6
W6 ABND
W4 ABND
G3
SS8
W4 ABND
W8
G3
SS8
26
10
26
10
2615
26
20
26
20
26
20
2620
2625
2625
2610
2625
14
SE
E
SH
EE
T
15
SE
E
SH
EE
T 13
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE L63 64 65 66 67 68
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7NS-3 NS-3
NS-3NS-
12
NS-
12
NS-12
S
S
DIRT
A/C
CONC
GATE
A/C
CONC
A/C
A/C
CONC
GARDEN ED
GIN
G
CONC
GATE
A/C
GATE
TWO PWR POLES
GATE
R/W
R/W
R/W R/W
R/WR/W
G3
SS
8
G3
SS8
W8
G3
SS8
W6 ABNDW6 ABND
W6 ABND
W8
2625
2625
26
30
2630
2630
26352635
2640
2625
15
SE
E
SH
EE
T 16
SE
E
SH
EE
T 14
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
020’ 20’020’ 20’
21
É AVENUE LÉ AVENUE L68 69 70 71 72 73
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
SE-7
SE-7
NS-3
NS-3
NS-3
NS-3
SE-10NS-12
NS-12
NS-12
S
S
GA
RD
EN
ED
GIN
G
CO
NC
DR
AIN
CO
VE
RE
D
CO
NC
RIB
&
GU
TT
ER
GATE GATE
ST
AIR
S
W
IRR
RO
CK
S
A/
C
CO
NC
S
CONC
CONC
A/C A/C
GATE
ROLLED A/C BERM
GRAVEL
SE
RVIC
E
TO
BA
CK
PA
RC
EL
PL
AC
ED
PE
R
PL
AN
LO
CATIO
N
APPR
OX.
PLACED PER PLAN
BRIC
K
PLANTER 6 IN. HIGH
TRAILER
A/C
WP 17
WP 18
WP 21WP 22
Z 13719
R/W
R/W
R/
W
R/W
R/
W
R/W
R/
W
R/
W
G3
G3
G2
G3
SS8SS8
SS
8
SS8
G3
W6
W8
E
E
E
E
?
W6
AB
ND
W8
W8
G3
SS8
W6 W6
2645
2645
2645
2645
2645
2645
2645
2645
2650
265026
50
2650
2650
2645
16
020’ 20’020’ 20’
SE
E
SH
EE
T
17
SEE SHEET 15
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
É
AV
EN
UE
L
É DOUGLAS STREET
É DOUGLAS STREET
73
7475 76 77
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-
7SE-7 SE-7
SE-7
SE-7
SE-7
SE-7
NS-3
NS-3 N
S-
3
NS-
3
NS-
3
NS-
3
SE-
10
SE-10SE-10
NS-
12
NS-12
NS-12
NS-12
NS-12
S
CONC
A/C
GATE
A/C BERM
MREB C/A DELLOR
E
TEL
GRAVEL
A/C
SSCO
GATE GATE
CONC
GATE
CONC
DIRT
GATE
AP
PR
OXIM
AT
E
LO
CA
TIO
N
Z 13718
R/W
R/WR/W
R/W
SS8
G3
T/
TV/
E
W6W6
SS8
G3
26452645
2645
2645
2650
2650
26
50
2650
2650
2655
17
020’ 20’020’ 20’
SE
E
SH
EE
T 16
MONITORING LOCATION I
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
É DOUGLAS STREET
78 79
80
NOTES
1.
REFER TO NOTE 1 ON SHEET 1.
LINEAR SEDIMENT CONTROLS WILL BE DEPLOYED AS NEEDED.
2. THE FOLLOWING BMP’S WILL BE DEPLOYED THROUGHOUT
THE PROJECT AREA: EC-1, WE-1, NS-1, NS-6, WM-2, WM-3
WM-4, WM-5, WM-6.
LEGEND
SE-7
STORM DRAIN INLET PROTECTIONSE-10
SE-8 SANDBAG BARRIER
NS-3
STREET SWEEPING AND VACUUMING
PAVING AND GRINDING OPERATIONSNS-3
SE-7
FLOW DIRECTION
STORM DRAIN ALIGNMENT
NS-12 NS-12 CONCRETE CURING
SE-7
SE-7
SE-7
NS-
3
NS-
3
SE-10
SE-10
NS-12
NS-12
NS-12
NS-12
020’ 20’0 200’200’
VICINITY MAP NO. 1 (START OF PROJECT)
PROJECT
OF
START
18
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
11 12 13 14 15
ERWIN ST
PA
RK
AV
7T
H P
L
COUNTY LINE RD
COUNTY LINE LN
COUNTY LINE RD
5T
H S
T
UNNAMED
AR
CHIE
VA
LLE
Y
CT
CA
LIM
ES
A
BL
VD
AVE K
ROGERS CT
4T
H S
T
UNNAMED
PA
RK
AV
AVE K
AV
E B
AVE K
CA
LIM
ES
A
BL
VD
COUNTY LINE RD
4T
H S
T
COUNTY LINE RDCOUNTY LINE RD
UN
NA
ME
D
COUNTY
LINE R
D
COUNTY LINE RDUN
NA
ME
D
CA
LIM
ES
A
BL
VD
COUNTY LINE RD7T
H P
L
FR
WY
FR
WY
I-10 E E
XIT 87
5T
H S
T
MYRTLEWOOD DR
5T
H S
T
UNNAMED
HO
LL
Y
LN
VILLA CA
LIMES
A LN
HALBERTA CIR
5T
H S
T
PONDEROSA TR
MU
LB
ER
RY
LN
SM
OKERID
GE T
R
MYRTLE
WOOD DR
CA
LIM
ES
A
BL
VD
CH
ER
RY
LN
SU
ND
AR
DR
AVE L
7TH ST
4T
H S
T
AVE LAVE L
5T
H S
T
AVE L
CA
LIM
ES
A
BL
VD
AVE LAVE LAVE L
7T
H P
L
SMOKERIDGE TR
MU
LB
ER
RY
LN
SANDALWOOD
DR
AV
E B
FR
WY
UN
NA
MED
I-10
W
EXIT 87
FR
WY
FLORDASON DR
4T
H S
T
4T
H S
T
7T
H S
T
MYRTLEWOOD DR
BUENA VISTA CT
5T
H S
T
AVE L
I-10 FR
WY
I-10 FR
WY
020’ 20’0 200’200’
PROJECT
OF
END
VICINITY MAP NO. 2 (END OF PROJECT)19
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
53 54 55 56 57 58 59
60 61
62 63 64 65 66 67 68 69 70 71 72 73
74
75
76
77
78
79
80
60+93.23
BC
COUNTY LINE RDCOUNTY LINE RD
OA
KW
OO
D
CT
ROSEWOOD DR
COTTONWOOD DRB
RY
AN
T S
T
GR
AN
T S
T
COUNTRY PL
ST
EA
RNS S
T
DO
UG
LA
S P
L
BR
YA
NT S
T
DO
UG
LA
S S
T
UN
NA
ME
D
UN
NA
ME
D
UN
NA
ME
D
E AVE L
E AVE LE AVE L
UN
NA
ME
D
UNNAMED
GREEN TREE CIR
BR
YA
NT S
T
PINEWOOD CT
CO
TT
ON
WO
OD
DR
UNNAMED
SELR
OCC
O
DR
LORETTA WY
HIL
LCR
ES
T
CT
UNNAMED
UNNAMED
SYLLMAR CIR
BR
YA
NT S
T
DO
UG
LA
S S
T
FR
EM
ON
T S
T
00 350’
PROJECT
OF
END
VICINITY MAP NO. 3 (ENTIRE PROJECT)
PROJECT
OF
START
350’
ENTIRE PROJECT IS LUP TYPE 120
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
49 50 51 52 53 54 55 56 57 58 59
60 61
62 63 64 65 66 67 68 69 70 71 72 73
74
75
76
77
78
79
80
60+93.23
BC
FISHER CT
ERWIN ST
PA
RK
AV
3R
D S
T
EL SERENE LN
3R
D S
T
OA
KW
OO
D
CT
ROSEWOOD DR
COTTONWOOD DR
5T
H S
T
UNNAMED
COUNTY LINE RD
2N
D S
T
ROGERS LN
CA
LIM
ES
A
BL
VD
AVE K
BR
YA
NT S
T
2N
D S
T
VICTORIA LN
ROGERS CT
4T
H S
T
COUNTY LINE RD
3R
D S
T
UNNAMED
PA
RK
AV
AVE K
AV
E B
AVE K
CA
LIM
ES
A
BL
VD
COUNTY LINE RD
4T
H S
T
COUNTY LINE RDCOUNTY LINE RD
UN
NA
ME
D
COUNTY
LINE R
D
COUNTY LINE RDUN
NA
ME
D
CA
LIM
ES
A
BL
VD
COUNTY LINE RD
COUNTRY PL
CA
LIF
OR
NIA
ST
ST
EA
RNS S
T
DO
UG
LA
S P
L
BR
YA
NT S
T
2N
D S
T
5T
H S
T
HARRUBY DR
MYRTLEWOOD DR
SANDALWOOD DR
ALTON CT
5T
H S
T
HARRUBY DR
2N
D P
L
UN
NA
ME
D
CLIN
G
WY
WEDGEWOOD CIR
2N
D P
L
DO
UG
LA
S S
T
UN
NA
ME
D
HARRUBY DR
HO
LL
Y
LN
VILLA CA
LIMES
A LN
HALBERTA CIR
UN
NA
ME
D
UN
NA
ME
D UN
NA
ME
D
UNNAMED
5T
H S
T
SANDALWOOD DR
E AVE L
CA
LIF
OR
NIA
ST
E AVE L
CA
LIF
OR
NIA
ST
3R
D S
T
MIDORI LN
PONDEROSA TR
MU
LB
ER
RY
LN
W AVE LW AVE LW AVE L
2N
D S
T
SM
OKERID
GE T
R
MYRTLE
WOOD DR
CA
LIM
ES
A
BL
VD
UNNAMED
SANDALWOOD DR
CH
ER
RY
LN
AVE LAVE L
3R
D S
T
AVE L
SU
ND
AR
DR
AVE L
CA
LIF
OR
NIA
ST
UN
NA
ME
D
UNNAMED
2ND PL
SUMMIT VIEW DR
3R
D S
T
BELLE R
D
4T
H S
T
AVE LAVE L
2ND PL2ND PL
5T
H S
T
AVE L
CA
LIM
ES
A
BL
VD
MYRTLEWOOD DR
DO
NN
A
LN
AVE L
BA
RN
ES
CT
2N
D P
L
GREEN TREE CIR
BR
YA
NT S
T
MYRTLEWOOD DR
BR
AD
Y
LN
SMOKERIDGE TR
MU
LB
ER
RY
LN UNNAMED
SUSAN LEE CT
MYRTLEWOOD DR
UN
NA
ME
D
UNNAMED
PINEWOOD CT
CO
TT
ON
WO
OD
DR
3R
D S
T
FLORDASON DR
SANDALWOOD
DR
AV
E B
LORETTA WY
FLORDASON DR
4T
H S
T
HIL
LCR
ES
T
CT
4T
H S
T
UNNAMED
SLA
CK PL
SLACK PL
VISTA L
N
2N
D S
T
UNNAMED
MYRTLEWOOD DR
3R
D S
T
SYLLMAR CIR
BR
YA
NT S
T
2N
D S
T
BUENA VISTA CT
5T
H S
T
DO
UG
LA
S S
T
I-10 FR
WY
I-10 FR
WY
LEGEND
21
PROJECT NO.
SHEET NO.
OF
5-0-00165
STORM DRAIN, STAGE 2
CALIMESA-AVENUE L
SITE MAPS
21
WITH ORANGE CONESMARK BOUNDARY OF AREA
FOR VEHICLES/EQUIPMENTPARKING AREA
LSC LSC LSC
LSC LSC LSC
LS
CL
SC
LS
CL
SC
LS
C
TYPICAL STAGING AREA
*
*
CONTRACTOR MAY FIELD ADJUST LAYOUT OF STAGING AREA AS NEEDED.
NS-8
NS-9
NS-10
VEHICLE AND EQUIPMENT FUELING
VEHICLE AND EQUIPMENT MAINTENANCE
WM-1 MATERIAL STORAGE AREA
WM-3
WM-4
WM-5 SOLID WASTE MANAGEMENT
WM-9
TC-1
STOCKPILE MANAGEMENT
SPILL PREVENTION AND CONTROL
SANITARY/SEPTIC WASTE MANAGEMENT
STABILIZED CONSTRUCTION ENTRANCE/EXIT
SE-1
SE-5
SILT FENCING
FIBER ROLLS
IF AREA IS NOT PAVED.PERIMETER OF STAGING AREA(SE-1, SE-5, ETC.) AROUNDLINEAR SEDIMENT CONTROL
WM-1
WM-3
WM-4
NS-10
NS-9
NS-8
WM-5
TC-1
WM-9
WM-6 HAZARDOUS WASTE MANAGEMENT
WM-6
VEHICLE AND EQUIPMENT CLEANING
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 58 January 2012
Appendix C: Permit Registration Documents
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 59 January 2012
Permit Registration Documents included in this Appendix
Y/N Permit Registration Document
Notice of Intent
Risk Assessment
Certification
Post Construction Water Balance
Copy of Annual Fee Receipt
ATS Design Documents
Site Map, see Appendix B
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 60 January 2012
Appendix D: SWPPP Amendment Certifications
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 61 January 2012
SWPPP Amendment No.
Project Name: CALIMESA - AVENUE L STORM DRAIN, STAGE 2
Qualified SWPPP Developer's Certification of the
Stormwater Pollution Prevention Plan Amendment
"This Stormwater Pollution Prevention Plan and attachments were prepared under my direction to meet the requirements of the California Construction General Permit (SWRCB Order No. 2009-009-DWQ as amended by 2010-0014-DWQ). I certify that I am a Qualified SWPPP Developer in good standing as of the date signed below."
QSD's Signature Date
QSD Name QSD Certificate Number
Title and Affiliation Telephone
Address Email
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 62 January 2012
Appendix E: Submitted Changes to PRDs
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 63 January 2012
Log of Updated PRDs The General Permit allows for the reduction or increase of the total acreage covered under the General Permit when a portion of the project is complete and/or conditions for termination of coverage have been met; when ownership of a portion of the project is purchased by a different entity; or when new acreage is added to the project.
Modified PRDs shall be filed electronically within 30 days of a reduction or increase in total disturbed area if a change in permit covered acreage is to be sought. The SWPPP shall be modified appropriately, with revisions and amendments recorded in Appendix C. Updated PRDs submitted electronically via SMARTS can be found in this Appendix.
This appendix includes all of the following updated PRDs (check all that apply):
Revised Notice of Intent (NOI);
Revised Site Map;
Revised Risk Assessment;
New landowner's information (name, address, phone number, email address); and
New signed certification statement.
Legally Responsible Person
Signature of Authorized Representative of Legally Responsible Person or Approved Signatory
Date
Name of Authorized Representative of Legally Responsible Person or Approved Signatory
Telephone Number
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 64 January 2012
Appendix F: Construction Schedule
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 65 January 2012
Appendix G: Construction Activities, Materials Used, and Associated Pollutants
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 66 January 2012
Table G.a POLLUTANTS ASSOCIATED WITH CONSTRUCTION ACTIVITIES General Work Activity/Products with
Potential Stormwater Pollutants Specific Work Activity/Products with Potential
Stormwater Pollutants Pollutant Categories
Adhesives • Adhesives, glues, resins, epoxy synthetics, PVC cement
• Caulks, sealers, putty, sealing agents • Coal tars (naphtha, pitch)
Oil and Grease Synthetic Organics1
Asphalt Paving/Curbs • Hot and cold mix asphalt Oil and Grease Cleaners • Polishes (metal, ceramic, tile)
• Etching agents • Cleaners, ammonia, lye, caustic sodas, bleaching
agents and chromate salts
Metals, Synthetic Organics
Concrete/Masonry • Cement and brick dust • Colored chalks • Concrete curing compounds • Glazing compounds • Surface cleaners • Saw cut slurries • Tile cutting
Metals, Synthetic Organics
Drywall • Saw cutting drywall Metals Framing/Carpentry • Sawdust, particle board dust, and treated woods
• Saw cut slurries Metals, Synthetic Organics
Heating, Ventilation, Air Conditioning • Demolition or construction of air condition and heating systems
Metals, Synthetic Organics
Insulation • Demolition or construction involving insulation, venting systems
Metals, Synthetic Organics
Liquid Waste • Wash waters • Irrigation line testing/flushing
Metals, Synthetic Organics
Painting • Paint thinners, acetone, methyl ethyl ketone, stripper paints, lacquers, varnish, enamels, turpentine, gum spirit, solvents, dyes, stripping pigments and sanding
Metals, Synthetic Organics
Planting/Vegetation Management • Vegetation control (pesticides/herbicides) • Planting • Plant maintenance • Vegetation removal
Nutrients, Metals, Synthetic Organics
Plumbing • Solder (lead, tin), flux (zinc chloride), pipe fitting • Galvanized metal in nails, fences, and electric wiring
Metals, Synthetic Organics
Pools/Fountains • Chlorinated water Synthetic Organics Removal of Existing Structures • Demolition of asphalt, concrete, masonry, framing,
roofing, metal structures Metals, Oil and Grease, Synthetic Organics
Roofing • Flashing • Saw cut slurries (tile cutting) • Shingle scrap and debris
Metals, Oil and Grease, Synthetic Organics
Sanitary Waste • Portable toilets • Disturbance of existing sewer lines
Nutrients
Soil Preparation/Amendments • Use of soil additives/amendments Nutrients Solid Waste • Litter, trash and debris
• Vegetation Gross Pollutants
Utility Line Testing and Flushing • Hydrostatic test water • Pipe flushing
Synthetic Organics
Vehicle and Equipment Use • Equipment operation • Equipment maintenance • Equipment washing • Equipment fueling
Oil and Grease
1Synthetic Organics are defined in Table 1.2 of the CASQA Stormwater BMP Handbook Portal: Construction as adhesives, cleaners, sealants, solvents, etc. These are generally categorized as VOCs or SVOCs.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 67 January 2012
Table G.1 Construction Activities and Associated Pollutants Phase Activity Associated Materials or
Pollutants Pollutant Category(1)
Gra
ding
and
Lan
d D
evel
opm
ent
Stre
ets
and
Util
ities
Ph
ase
Vert
ical
Con
stru
ctio
n Ph
ase
Land
scap
ing
and
Site
St
abili
zatio
n Ph
ase
(1)Categories per CASQA BMP Handbook (i.e., Sediment, Nutrients, Bacteria and Viruses, Oil and Grease, Metals, Synthetic Organics, Pesticides, Gross Pollutants, and Vector Production).
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 68 January 2012
Appendix H: CASQA Stormwater BMP Handbook Portal: Construction Fact Sheets
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 69 January 2012
Appendix I: BMP Inspection Form
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 70 January 2012
BMP INSPECTION REPORT
Date and Time of Inspection: Date Report Written:
Inspection Type: (Circle one)
Weekly Complete Parts
I,II,III and VII
Pre-Storm Complete Parts I,II,III,IV and VII
During Rain Event Complete Parts I, II,
III, V, and VII
Post-Storm Complete Parts I,II,III,VI and VII
Part I. General Information
Site Information Construction Site Name:
Construction stage and completed activities:
Approximate area of site that is exposed:
Photos Taken: (Circle one) Yes No
Photo Reference IDs:
Weather Estimate storm beginning: (date and time)
Estimate storm duration: (hours)
Estimate time since last storm: (days or hours)
Rain gauge reading and location: (in)
Is a "Qualifying Event" predicted or did one occur (i.e., 0.5" rain with 48-hrs or greater between events)? (Y/N) If yes, summarize forecast: Exemption Documentation (explanation required if inspection could not be conducted). Visual inspections are not required outside of business hours or during dangerous weather conditions such as flooding or electrical storms.
Inspector Information
Inspector Name: Inspector Title:
Signature: Date:
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 71 January 2012
Part II. BMP Observations. Describe deficiencies in Part III.
Minimum BMPs for Risk Level _____ Sites Failures or other short comings
(yes, no, N/A)
Action Required (yes/no)
Action Implemented
(Date)
Good Housekeeping for Construction Materials
Inventory of products (excluding materials designed to be outdoors)
Stockpiled construction materials not actively in use are covered and bermed
All chemicals are stored in watertight containers with appropriate secondary containment, or in a completely enclosed storage shed
Construction materials are minimally exposed to precipitation
BMPs preventing the off-site tracking of materials are implemented and properly effective
Good Housekeeping for Waste Management Wash/rinse water and materials are prevented from being disposed into the storm drain system
Portable toilets are contained to prevent discharges of waste
Sanitation facilities are clean and with no apparent for leaks and spills
Equipment is in place to cover waste disposal containers at the end of business day and during rain events
Discharges from waste disposal containers are prevented from discharging to the storm drain system / receiving water
Stockpiled waste material is securely protected from wind and rain if not actively in use
Procedures are in place for addressing hazardous and non-hazardous spills
Appropriate spill response personnel are assigned and trained
Equipment and materials for cleanup of spills is available onsite
Washout areas (e.g., concrete) are contained appropriately to prevent discharge or infiltration into the underlying soil
Good Housekeeping for Vehicle Storage and Maintenance
Measures are in place to prevent oil, grease, or fuel from leaking into the ground, storm drains, or surface waters
All equipment or vehicles are fueled, maintained, and stored in a designated area with appropriate BMPs
Vehicle and equipment leaks are cleaned immediately and disposed of properly
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 72 January 2012
Part II. BMP Observations Continued. Describe deficiencies in Part III.
Minimum BMPs for Risk Level _____ Sites
Adequately designed,
implemented and effective
(yes, no, N/A)
Action Required (yes/no)
Action Implemented
(Date)
Good Housekeeping for Landscape Materials
Stockpiled landscape materials such as mulches and topsoil are contained and covered when not actively in use
Erodible landscape material has not been applied 2 days before a forecasted rain event or during an event
Erodible landscape materials are applied at quantities and rates in accordance with manufacturer recommendations
Bagged erodible landscape materials are stored on pallets and covered
Good Housekeeping for Air Deposition of Site Materials
Good housekeeping measures are implemented onsite to control the air deposition of site materials and from site operations
Non-Stormwater Management
Non-Stormwater discharges are properly controlled
Vehicles are washed in a manner to prevent non-stormwater discharges to surface waters or drainage systems
Streets are cleaned in a manner to prevent unauthorized non-stormwater discharges to surface waters or drainage systems.
Erosion Controls
Wind erosion controls are effectively implemented
Effective soil cover is provided for disturbed areas inactive (i.e., not scheduled to be disturbed for 14 days) as well as finished slopes, open space, utility backfill, and completed lots
The use of plastic materials is limited in cases when a more sustainable, environmentally friendly alternative exists.
Sediment Controls
Perimeter controls are established and effective at controlling erosion and sediment discharges from the site
Entrances and exits are stabilized to control erosion and sediment discharges from the site
Sediment basins are properly maintained
Linear sediment control along toe of slope, face of slope an at grade breaks (Risk Level 2 & 3 Only)
Limit construction activity to and from site to entrances and exits that employ effective controls to prevent offsite tracking (Risk Level 2 & 3 Only)
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 73 January 2012
Ensure all storm, drain inlets and perimeter controls, runoff control BMPs and pollutants controls at entrances and exits are maintained and protected from activities the reduce their effectiveness (Risk Level 2 & 3 Only)
Inspect all immediate access roads daily (Risk Level 2 & 3 Only)
Run-On and Run-Off Controls
Run-on to the site is effectively managed and directed away from all disturbed areas.
Other Are the project SWPPP and BMP plan up to date, available on-site and being properly implemented?
Part III. Descriptions of BMP Deficiencies
Deficiency
Repairs Implemented: Note - Repairs must begin within 72 hours of identification and,
complete repairs as soon as possible.
Start Date Action
1.
2.
3.
4.
Part IV. Additional Pre-Storm Observations. Note the presence or absence of floating and suspended materials, sheen, discoloration, turbidity, odors, and source(s) of pollutants(s). Yes, No, N/A
Do stormwater storage and containment areas have adequate freeboard? If no, complete Part III.
Are drainage areas free of spills, leaks, or uncontrolled pollutant sources? If no, complete Part VII and describe below.
Notes: Are stormwater storage and containment areas free of leaks? If no, complete Parts III and/or VII and describe below.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 74 January 2012
Notes:
Part V. Additional During Storm Observations. If BMPs cannot be inspected during inclement weather, list the results of visual inspections at all relevant outfalls, discharge points, and downstream locations. Note odors or visible sheen on the surface of discharges. Complete Part VII (Corrective Actions) as needed.
Outfall, Discharge Point, or Other Downstream Location
Location Description
Location Description
Location Description
Location Description
Location Description
Location Description
Location Description
Location Description
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 75 January 2012
Part VI. Additional Post-Storm Observations. Visually observe (inspect) stormwater discharges at all discharge locations within two business days (48 hours) after each qualifying rain event, and observe (inspect) the discharge of stored or contained stormwater that is derived from and discharged subsequent to a qualifying rain event producing precipitation of ½ inch or more at the time of discharge. Complete Part VII (Corrective Actions) as needed. Discharge Location, Storage or Containment Area
Visual Observation
Part VII. Additional Corrective Actions Required. Identify additional corrective actions not included with BMP Deficiencies (Part III) above. Note if SWPPP change is required.
Required Actions Implementation Date
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 76 January 2012
Appendix J: Rain Event Action Plan (REAP)
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 77 January 2012
A REAP is not required for LUP Type 1.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 78 January 2012
Appendix K: Training Reporting Form
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 79 January 2012
Trained Contractor Personnel Log Stormwater Management Training Log and Documentation Project Name: CGP App ID #:
Stormwater Management Topic: (check as appropriate)
Erosion Control Sediment Control
Wind Erosion Control Tracking Control
Non-Stormwater Management Waste Management and Materials Pollution Control
Stormwater Sampling
Specific Training Objective:
Location: Date: _
Instructor: Telephone:
Course Length (hours):
Attendee Roster (Attach additional forms if necessary) Name Company Phone
As needed, add proof of external training (e.g., course completion certificates, credentials for QSP, QSD).
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 80 January 2012
Appendix L: Responsible Parties
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 81 January 2012
Contact Information / List of Responsible Parties The Legally Responsible Person (LRP) for this project is: Name: Warren D. Williams Phone: 951-955-1200 Company Name: Riverside County Flood Control and Water Conservation District Address: 1995 Market St. City, State, Zip: Riverside CA 92501 An LRP is the person who possesses the title of the land or the leasehold interest of a mineral estate upon which the construction activities will occur for the regulated site. For linear underground/overhead projects, it is the person in charge of the municipality, utility company, or other public or private company or agency that owns or operates the LUP. The Qualified SWPPP Developer (QSD) assigned to this project is: Name: Phone: Company Name: Address: City, State, Zip: A QSD is an individual who is authorized to develop and revise a SWPPP.
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 82 January 2012
Identification of QSP Project Name:
CGP App ID #:
The following are QSPs associated with this project
Name of Personnel(1) Company Date
(1) If additional QSPs are required on the job site add additional lines and include information here
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 83 January 2012
Appendix M: Contractors and Subcontractors
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 84 January 2012
Appendix N: Construction General Permit
Calimesa - Avenue L Storm Drain, Stage 2 SWPPP 85 January 2012
Appendix O: Weather Reports