technical guidelines on retro-commissioning · 1. introduction. 5. technical guidelines on retro...

Post on 10-Sep-2020

11 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Technical Guidelines on Retro-commissioning

1

Seminar on Retro-commissioning in Hong Kong

簡報者
簡報註解
Good afternoon, distinguished guests, ladies and gentleman. I am KW KONG from EMSD.

Section A1. Introduction2. TG (RCx) Framework

Section B3. How we start 4. Example 5. Common difficulties & Solution

2

簡報者
簡報註解
Today, The presentation would divided into 2 section. My colleague, Patrick and me would share with you the latest development of Technical Guidelines on Retro commissioning and a case study

1. Introduction

3

Retro-commissioning web page

簡報者
簡報註解
Frist of all, I would introduce the webpage of retro commissioning. This web page has been launched by end June 2017. As you can see from this slide, The purpose of Webpage is to share successful cases and commonly findings and some typical energy saving opportunities arising from RCx

4

簡報者
簡報註解
Of course, you could download the guidelines from the webpage.

1. Introduction

5

Technical Guidelines on Retro-commissioning

Acknowledgement

簡報者
簡報註解
Or scan this QR code to download the guidelines. I would like to take this opportunity to express our utmost thanks to Hong Kong Green Building Council (HKGBC) who have shared their valuable experience on RCx and contributed to the formulation of this Technical Guidelines.

What is Retro-commissioning ?

A cost-effective systematic process to periodically check an existing building’s performance.

The process identifies operational improvements that can effectively save energy and thus lower energy bills and improve indoor environment

“Retro-commissioning” covers the scope of “existing building commissioning”, “re-commissioning” and “continuous commissioning”.

Retro-commissioning is…

1. Introduction

簡報者
簡報註解
Source: Clause 1.1 and 1.2 of TG(RCx)

Why retro-commissioning ?

We completed Energy Audit already!

1. Introduction

Retro-commissioning is different from Energy Audit

RCx is more focused on checking whether the energyconsuming systems operate properly as design or users’requirements and to identify area of improvements

Besides, RCx has an implementation of Energy SavingOpportunity (ESO) and on-going commissioning plan forthe building owners to maintain the building operating inhigh energy efficiency level.

1. Introduction

簡報者
簡報註解
Source: Clause 1.5 of TG(RC) e.g. ~ shifting of system control settings; ~ inaccuracy of sensors; ~ improper operational schedules; and ~ improper air & water balancing etc.

Retrofitting vs Retro-commissioning

Retrofitting can apply to new or existing building and involves upgrading or replacing equipment such as HVAC (boilers, chillers, …), lighting (fluorescent Lamps vs LEDs ), installing variable frequency drives (VFDs) and other energy-efficient measures.

1. Introduction

簡報者
簡報註解
What is the different between retrofitting and retro-commissioning? http://www.local-law-87.com/content/ll87

RCx applies to existing buildings and seeks to improve the functioning of equipment & controls without relying on the need for replacement.

RCx may involve corrective actions/quick fix during the investigation, measurement & verification procedures, functional testing and diagnostic monitoring.

RCx pushes towards an on-going commissioning effort

Retro-commissioning : -

1. Introduction

簡報者
簡報註解
http://www.local-law-87.com/content/ll87 - Source: Question no 7

4 Workstages of RCx

Sample Technical Approach of RCx

Forms or checklist for RCx

2. TG(RCx) FRAMEWORK

11

4 workstages

Stage 1: Planning

Stage 2: Investigation

Stage 3: Implementation

Stage 4: On-going commissioning

2. TG(RCx) FRAMEWORK

12

• Gather information from stakeholders, documentation

• Arrange meeting and interview

• Conduct walk-through Inspection

• Develop RCx plan for agreement with stakeholders

• Forms template developed in TG to facilitate theusers to carry out RCx

Stage 1: Planning

13

• Conduct site survey and identify current facilities

requirement

• Perform system adjustments and quick fix

• Conduct data logging and trending

• Short term diagnostic, monitoring and functional test plans

• Identify potential energy saving measures and improvements

• Forms templates are developed in TG(RCx)

• Investigation Report

Stage 2: Investigation

14

• Implementation of selected energy saving opportunities

- Proposed by RCx team and agreed by Stakeholder

- Suit budget, minimize disturbance to users

• Performing verification

- Effectiveness of the implemented items

• Develop a RCx Final Report

• Training for O&M Staff (maintain the RCx benefits)

Stage 3: Implementation

15

• To ensure “high” energy performance maintained after RCx

• To develop a ongoing commissioning plan

• key indicators such as

Electricity Bill, satisfaction levels of occupants, etc…

• To arrange training for O&M staffs

• Continuous monitoring – review and update

Stage 4: On-going commissioning

16

Section 2

17

簡報者
簡報註解

Technical Approach Example on Retro-commissioning

18

Seminar on Retro-commissioning in Hong Kong

1.How we start?2.Examples3.Common difficulties & solutions

19

簡報者
簡報註解
Share our experiences from those pilot projects Practical consideration concerns and difficulties on applying the RCx in real cases And how we resolve it

Venues

Building portfolio

Annual electricity consumption?

Accessibility?

System complexity?

Considerations

20

How we start?

簡報者
簡報註解
Building portfolio – building types Annual EL consumption – Higher one Accessibility – Leasing building/ multi-owner building / single own System com – saving potential

People

Operators / technicians

Engineers

Maintenance contractors

Equipment/ System Suppliers

Services Providers?

Considerations

21

How we start?

簡報者
簡報註解
Operator / technicians (familiar with the plant responds, specific requirements …) Engineers (provide professional knowledge) Maintenance contractor (plant support) Equipment/ System Supplier (specialist support) Services Provider? (professional services but still need above support)

Investment & Return

Venues (accessibility?)

People (internal-staff/ external?)

Together with retrofit?

Phasing?

Environmental concerns?

Considerations

22

How we start?

簡報者
簡報註解
When giving input we expect output Venues (accessibility?) (night works People (self-staff/ external?) Together with retrofit? Phasing? (separate the works hence to have some return first) Environmental concern? (something other than $ sign)

23

Technical approach examples

16 floor Office building with 24 hours facilities

Floor area: ~37,800m2

Annual electricity consumption ~7,060,000kwh

Water cooling chiller system

簡報者
簡報註解
Adopt energy model as trail, demonstrate the use of anaylysis BMS outdated, data logging incomplete, no sufficiency data for analysis

Planning Stage

24

Technical approach examples

25

Data collection

Familiar with the buildings

Facility / Equipment Observation

Understanding the building

• Drawings/ documents• Site conditions• Equipment's rating & conditions• Cooling load requirements• Users requirements/ constrains

簡報者
簡報註解
Drawings/ documents (need update?) Site conditions (visual inspection and quick fix. i.e. insulation, ventilation short circuit ) Equipment's rating & conditions (how is the derating? Broken parts?) Cooling load requirements (how it change through out day and nights, four seasons) Users requirements/ constrains (say data centre that need to keep certain supply temp or flow rate)

26

Technical approach examplesData handling and checking

Data quality checking and fixing

簡報者
簡報註解
Huge amount of data Quick checking Equipment / system data Trend log + data cycle (a day, a week, a month, a year)

Analysis Stage

27

28

Cooling tower performance

Cooling towers

Facility / Equipment

Technical approach examples

Outdoor temp

簡報者
簡報註解
Considered the budget, timeframe & saving potential Max range (heat rejection) Min approach

29

Cooling tower performance

N+1 Cooling towers with VSD vans

Observation 1 chiller with 1 Cooling tower

1 chiller with 2 Cooling tower

Cooling Tower Fan + Condensate water pump Power consumption

Load percentage

Technical approach examples

簡報者
簡報註解
Try two approaches first N+1 CT Improve the evaporation by using extra CT but lower the fans speed Significant especially when loading at high side

30

Cooling tower performance

Cooling tower set point reset

Facility / Equipment Observation

Technical approach examples

CT leaving water temp. set pt.

簡報者
簡報註解
Second is reset pt Lowest possible condensate water temp & balance the power use in CT Based on Estimated condensate water entering temp and wet bulb temp to develop set point

VSD Chiller COP

31

Chillers Plant Saving

Entering Condensate water Temperature

35 degree

30 degree

25 degree

20 degree

15 degree

• Different CWST gives different Chiller performance curve

• Try to lower the CWST hence to improve COPHelp the chiller lift and hence improve COP

簡報者
簡報註解
Before talking about the chiller sequence We need to understand the VSD chiller charteristic COP Part load is better than full load but its vary w the wet bulb

Building load Characteristic

32

0

100

200

300

400

500

600

700

800

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Hou

rs

Month

Chiller load distribution

<= 500.00 >500.00 to <=875.00 >875.00 to <=1250.00 >1250.00 to <=1625.00 >1625.00 to <=2000.00

>2000.00 to <=2375.00 >2375.00 to <=2750.00 >2750.00 to <=3125.00 >3125.00 to <=3500.00 > 3500.00

簡報者
簡報註解
To know how is the building load vary in each month

Mode table

33

Operation Mode Building load

No. of chiller reuiqred Chiller to operate

No of cooling tower to operate

A < 500kW 1 WCC1 2

B 500kW < and < 1700kW 1 HRC1/HRC2/WCC2/WCC3 2

C 1700kW < and < 3000kW 2

HRC1/HRC2/WCC2/WCC3 and

HRC1/HRC2/WCC2/WCC3

3

D > 3000kW 3

HRC1/HRC2/WCC2/WCC3 and

HRC1/HRC2/WCC2/WCC3 and

HRC1/HRC2/WCC2/WCC3

4

Loading range

Suggested operation

mode Loading rangeSuggested

operation mode Loading range

Suggested operation

mode RemarksJanuary < 500kW A 500kW < and < 1700kW B > 1700kW B Note 1

February < 500kW A 500kW < and < 1700kW B > 1700kW B Note 1

March < 500kW A 500kW < and < 1700kW B > 1700kW B Note 1

April < 500kW A 500kW < and < 1700kW B > 1700kW B Note 1

May 500kW < and < 1700kW B 1700kW < and < 3000kW C > 3000kW C -

June 500kW < and < 1700kW B 1700kW < and < 3000kW C > 3000kW C -

July 500kW < and < 1700kW B 1700kW < and < 3000kW C > 3000kW D -

August 500kW < and < 1700kW B 1700kW < and < 3000kW C > 3000kW D -

September 500kW < and < 1700kW B 1700kW < and < 3000kW C > 3000kW D -

October < 500kW A 500kW < and < 1700kW B > 1700kW B Note 1

November < 500kW A 500kW < and < 1700kW B > 1700kW B Note 1

December < 500kW A 500kW < and < 1700kW B > 1700kW B Note 1

Notes1. If loading more than 1 chiller capacity, extra chiller to be kick in

簡報者
簡報註解
Develop a mode table for the plant operation based on the annual load variation And further apply different mode to different months based on the monthly load variation

34

Chillers Plant Saving

Estimation (by computer simulation)

0

1

2

3

4

5

6

7

8

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

COP

Date

Chiller Plant Efficiency (kW/kW) vs time

Annual average COP improvement(estimated by simulation)

Approx. 5 -10%

Technical approach examples

Implementation Stage

35

36

Actions

With maintenance contractor• On-site data verification • Sensors replacement

With CCMS/ BMS service provider• Enable data trend logging• Enhance data storage• Review current control sequence

Sensors & data checkingTechnical approach examples

37

Operation Mode Building load No. of chiller reuiqred Chiller to operateA < 500kW 1 WCC1B 500kW < and < 1700kW 1 HRC1/HRC2/WCC2/WCC3

C 1700kW < and < 3000kW 2HRC1/HRC2/WCC2/WCC3 and

HRC1/HRC2/WCC2/WCC3

D > 3000kW 3

HRC1/HRC2/WCC2/WCC3 and HRC1/HRC2/WCC2/WCC3 and

HRC1/HRC2/WCC2/WCC3

Actions

• Understanding the technical principle• Understanding the site condition / current

operation requirements (effects to the end users)

• Agree on the test procedures and contingency plan

• One week trial• Ensure data logging

Technical approach examples

38

CT Trial Setting

Scenarios Trail duration No. of chiller CT VSD Fans' speed

settingNo of cooling

tower to operate Remarks

Baseline 8:30am - 5:30 pm 2 Automatic 2 Original setting

Day 1 8:30am - 5:30 pm 2 90% 3 Manual trial

Day 2 8:30am - 5:30 pm 2 80% 3 Manual trial

Day 3 8:30am - 5:30 pm 2 70% 3 Manual trial

Actions

• Modification of the VSD fan setting• Manual control for N+1 arrangement• Notice to the loading conditions (similar

testing conditions)• Three days trials

Technical approach examples

0

1

2

3

4

5

6

7

8

7th May 8th May 9th May 10th May39

Technical approach examplesChillers Plant Saving

Measure and verification

Actual measured data during the chillers sequencing trials

COP

Baseline

3 days average COP improvement(by measurement )

Approx. 15%

簡報者
簡報註解
Need further verification and normalization

40

Common difficulties & solutions

Regular calibration of monitoring/ control sensors / actuators

Better data documentation (BMS data storage and checking)

Fully utilize Energy Management System (Identify key indicator, i.e. COP, by pass flow rate, approach temperature…)

41

Ensure data availability, sensor accuracy and understanding plant characteristic

Carry out data analysis based on Engineering knowledge,

Translate to simple house rules for Technicians to follow

Technicians

Engineers

Provide top management supports including authority, resources, time,

investment on monitoring devices/ tools/ trainings, etc.

Owners

Common difficulties & solutions

Thank You

top related