KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

a. Electrical

Electrical Manhole not yet finished and no cables installed.

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

Electrical Room , No panelboard and main cable installed

.

Grounding Rod with Bare Copper outside the Building

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

Disconnecting Switches for ACCU

Electrical Recessed Indoor Luminaire on Mezzanine

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

Electrical Pendant Highbay Industrial Luminaire Installed on Main Storage Area

Surface Mounted Luminaires in Electrical and Communication Room

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

Outdoor Luminaire

WC Downlight Luminaire

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

Pendant Mounted Indoor Luminaire Installed on Loading/Unloading Area

Exit Lights Installed on all Exit Doors

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

Floor Mounted Socket Installed at Mezzanine

Switches and Sockets

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

On/Off Pushbutton Switch for Highbay Lightings

Dip Switch

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

Duplex Socket Outlet at Main Storage Area

380 Volts Industrial Outlet Sample on Site

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________

Wall Mounted Duplex Socket in Rooms

Disconnecting Switch and Push Button for Roll up Shutter

KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS

Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station

TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.

Date: 09.11.1436 (25.08.2015)____________________________________________________________________________