using constructive search in resource scheduling by andrei missine
Post on 18-Jan-2018
219 Views
Preview:
DESCRIPTION
TRANSCRIPT
Using Constructive Search in Resource
Scheduling
By Andrei Missine
Overview• Brief Introduction to Constructive
Search• Running examples• Basic Terms and Concepts in Resource
Scheduling• Some common propagators
– Disjunctive Constraint– Edge Finding
Overview• Scheduling Algorithms
– Branching by dynamic release dates– Branching by assigning generalized
precedence constraints– Branching by assigning or delaying start
times of activities• Conclusion
Brief Intro to Constructive Search
• Complete• Builds and
systematically traverses the search tree
• Root node of the tree contains assumptions only from the problem statement
• At each node a decision is made
• If a child backtracks to the parent the parent considers the next decision
• If there are no more decisions to consider at a node, backtrack
• Terminate when backtracking out of the root node
Running Examples• There will be two running examples,
one for the unit-capacity resource and one for the capacitated resource.
• A unit capacity resource is a resource with a capacity of exactly 1 unit.
• A capacitated resource is a resource with a capacity that is greater than or equal to 1.
Running Example - Unit Capacity Resource (1)
• The resource is the classroom• The “activities” are the 3 classes:
– Class A and class B can start at 12:00 and must finish by 14:00
– Class C can start at 12:00 and must finish by 16:00
– Each class runs for an hour• Find a schedule with the smallest “makespan”
such that all classes are scheduled and there are no clashes
Running Example - Capacitated Resource (2)
• A computer lab with 100 computers is the resource
• Classes are the “activities”:– Class A and B start at 12:00 and must finish by
13:30– Class C starts at 12:00 and must finish by 14:00– Each class requires 50 computers for 1 hour
• Find a schedule with minimal makespan such that all classes can use the lab without going over the 100 computer limit
Resource Scheduling Terms and Concepts
• Time windows – an activity must execute in a given time window defined by the earliest start time and the latest end time
• Generalized precedence constraints –impose a minimum delay between the start times of A and B
Resource Scheduling Terms and Concepts
• EST - Earliest start time of an activity
• LST - Latest start time of an activity
• EET - Earliest end time of an activity
• LET - Latest end time of an activity
• Core execution interval - the time interval when the activity must execute, if any
• Makespan - the maximum of the latest end times of all activities
Resource Scheduling Terms and Concepts
Distance matrix - an n by n matrix where the entry (i, j) is the delay between the start time of activity i and the start time of activity j
• Active / Dominating schedule - a schedule such that all activities are scheduled as early as possible without violating any of the constraints
Resource Scheduling Terms and Concepts
• Active / Dominating schedule - a schedule such that all activities are scheduled as early as possible without violating any of the constraints
Common Propagators: Disjunctive Constraint
• When two activities’ combined capacity requirement exceeds the resource capacity the two activities are in disjunction
• If start time of one activity is fixed then propagator can prune the other activity’s start time domain.
Common Propagators: Edge-Finding (Baptiste et al, 2003)
• Edge-finding can be applied when resource usage of a subset of activities exceeds the resource capacity
• Considers activities one by one, trying to prune their start times.
• Pruning occurs when it is evident that given any feasible assignment of the remainder of the subset, the current domain of activity under consideration must be pruned.
Common Propagators: Edge-Finding
• This is done by considering core execution intervals and overall resource usage in an interval
• Can be costly - O(n2)
Disjunctive Propagator versus Edge-Finding
• Edge-finding is overkill in unit-capacity resource problems
• Disjunctive propagator can be too weak on general capacitated resources
• Edge-finding is expensive - O(n2)
• Disjunctive propagator is cheap - O(1)
• Bottom line - use disjunctive whenever you can and edge finding only when necessary (e.g. for pre-processing)
Propagators applied to the Examples
• For the disjunctive propagator, note that it will not deduce any extra info on the capacitated example
• Edge-finding is more powerful than disjunctive constraint
• For the disjunctive case and example 1, assume that class A is already scheduled to start at 12:00
• The propagator can then deduce that B and C must start at 13:00 or later, and after a second iteration that C must start at 14:00 or later
Propagators applied to the Examples
• For edge-finding and example 2 it is possible to deduce that class C cannot start earlier than 13:00 even without any extra information
• The reasoning is because both A and B have a core execution interval [12:30 - 13:00)
• Thus C will not have any computers available if it starts any time before 13:00
• Applying edge-finding to example 1 we note that edge finding will be able to deduce that C must start at 14:00 or later, even without knowing any extra info
The Branch-and-Bound idea• Search for a solution• Once a solution is
found, remember it• Keep searching• If it becomes evident at
a node that nothing below it leads to a solution better than the current, backtrack
• In the algorithms that follow the bound is on the makespan
• Lower-bound avoids exploring overly optimistic branches
• Upper-bound avoids exploring overly pessimistic branches
• Good bounds can greatly improve performance
Branching by Dynamic Release Dates
• (Fest et al, 1998) introduce the idea of branching by selecting a set of activities to delay to fix broken resource utilization constraints
• Branches are formed by considering possible subsets to delay
• Overall structure of the algorithm:– Assign earliest start
times to all activities such that precedence constraints are met
– Keep delaying activities until resource constraint is fixed
– Upon backtracking pick the next delaying alternative
Branching by Dynamic Release Dates
• The resulting tree is rather bushy because there can be exponentially many different subsets to consider
• Authors present some ideas how to optimize the algorithm
• The overall performance is still rather slow
Applying to the Examples• Consider the unit-
capacity case. At root 3 possible delay subsets: {A, B}, {A, C} and {B, C}
• Taking {A, B} results in backtracking since both are delayed to the 13:00 - 14:00 slot and cannot be scheduled
• Taking {A, C} produces the schedule B (12:00), A (13:00), C (14:00)
• Taking {B, C} produces the schedule A (12:00), B (13:00), C (14:00)
Applying to Examples• Now consider the capacitated case. At root
the possible delay sets are {A}, {B} and {C}• Delaying {A} or {B} leads to immediate
backtracking (the interval 13:00 - 13:30 is too short for a 1 hour class)
• Delaying {C} results in the correct schedule where A and B start at 12:00 and C starts at 13:00
Branching by Assigning generalized precedence relationships
• (Brucker et al, 1998) suggest branching by making a decision at every node to assign either a concurrent or a disjunctive relationship between two free activities
• A leaf node in such a tree has all activities associated with some precedence relationship
• (Brucker et al, 1998) show that it is possible to tell whether or not a solution exists at such a leaf node, and if it does to find the active schedule
• Note that the branching factor is only 2
• This scheme was shown to be quite good by (Cesta et al, 2000)
Applying to Examples• The unit-capacity
example is not interesting since all activities must be in disjunction
• For the capacitated example the root node contains no precedence relationships
• By following the algorithm, the following leafs form (+ means concurrent, - means disjunctive):– A + B, A + C, B + C – A + B, A + C, B – C– A + B, A – C, B + C– A + B, A – C, B – C– A – B, A + C, B + C– A – B, A + C, B – C– A – B, A – C, B + C– A – B, A – C, B – C
Applying to Examples• The last 4 have no
solution since A and B cannot possibly be in disjunction (because their core execution intervals overlap)
• The first one has no solution also since A+B+C exceed the resource capacity
• A + B, A + C, B - C is a solution: B starts at 12:00, A starts at 12:15 and C starts at 13:00
• Similarly for A + B, A - C, B + C (A and B are reversed)
• A + B, A - C, B - C is also a solution: A and B both start at 12:00 and C starts at 13:00
Branching by Assigning or Delaying Start Times of Activities
• (Dorndorf et al, 2000) present a branching scheme that picks a free activity at each node and either assigns it the earliest start time, or delays the start time by some amount
• Algorithm makes use of 4 consistency tests:
– Precedence consistency test
– Resource consistency test
– Interval-based disjunctive consistency test
– Lag-based disjunctive consistency test
• These tests are applied at each node to further prune the search tree
Branching by Assigning or Delaying Start Times of Activities
• Selection of an activity from a subset of free activities is done as follows:– Find all activities such
that either its earliest start time matches its precedence and resource feasible start time or it must precede some other free activity
– Heuristically pick an activity from this subset
• Delaying of the selected activity:– Look at all activities
which share a resource with the current activity such that their end times are after the current activity’s start time
– If there is at least one such activity pick the minimal end time of this activity as the delay
– Otherwise delay by one
Branching by Assigning or Delaying Start Times of Activities
• Note that again, the branching factor is only 2
• Unlike the two previous schemes, this scheme does not use lower bound on the makespan
• This scheme was shown to be quite good by (Cesta et al, 2000)
Applying to Examples• Consider unit-capacity
case. Assume that the heuristics selects A
• It will first try assigning it to the earliest start time
• This will result in pruning B to [13:00, 14:00) and, consequently C to [14:00, 16:00)
• The algorithm then backtracks and will eventually find the solution B, A, C (after selecting B first) and no solutions starting with C
Applying to Examples• Now consider the general capacitated
example• The execution is very similar - selecting
C as the first activity leads to backtracking and delaying C since it is impossible to have C start at 12:00
• Selecting A or B will lead to the 3 solutions mentioned above
Conclusion• Propagators: the tradeoff between
speed versus pruning power• Branch-and-bound and usefulness of
good initial bounds• The three branch-and-bound algorithms• Disadvantages of Constructive Search
on large problem instances
References• Baptiste Philippe, Claude Le Pape, Nuijten Wim.
2003. Constraint-Based Scheduling: Applying Constraint Programming to Scheduling Problems, Second Printing. Kluwer Academic Publishers.
• Brucker Peter, Knust Sigrid, Schoo Arno, Thiele Olaf. 1998. A branch and bound algorithm for the resource-constrained project scheduling problem. European Journal of Operations Research, 107 (1998) 272-288.
References• Cesta Amedeo, Oddi Angelo, Smith F. Stephen. 2000. Iterative
Flattening: A Scalable Method for Solving Multi-Capacity Scheduling Problems. American Association for Artificial Intelligence, 2000, pp 742-747.
• Fest Andreas, Möhring Rolf H., Stork Frederik, Uetz Marc. 1998. Resource-Constrained Project Scheduling with Time Windwos: A Branching Scheme Based on Dynamic Release Dates. Technical Report 596, Technische Universit at Berlin.
• Dorndorf Ulrich, Pesch Erwin, Phan-Huy Toàn. 2000. A Time-Oriented Branch-and-Bound Algorithm for Resource-Constrained Project Scheduling with Generalised Precedence Constraints. Management Science, Vol. 46, No. 10, October 2000, pp. 1365-1384.