UTA Airport TRAX LineNorth Temple Viaduct &

Construction Phasing

North Temple Viaduct Detours

North Temple viaduct closure and construction begins April 18. Construction will take 18 months

Alternative A• Westbound detour – 300 West to 600 North to 900 West

Alternative B• Eastbound detour – 900 West to 400 South to 300 West

UTA Bus Routes

UTA bus routes that travel North Temple will be rerouted beginning April 4. For specific route information visit www.rideuta.com

When Is the Airport Line Being Built?

North Temple Construction - Phases

Phase 1Phase 2

Phase 3Phase 4

Phase 5

North Temple Phasing – Spring 2010

North Temple Phasing – Spring/Summer 2010

North Temple Phasing – Summer/Fall 2010

North Temple Phasing – Spring 2011

North Temple Phasing – Summer 2011

Downtown Phasing – Spring 2012 – Fall 2012

Communications and Marketing

• Weekly construction updates• Regular one-on-one visits to corridor properties• Comprehensive marketing plan

• Milestone events • Direct mail• Radio• Billboards• Print

• Looking for others ways to communicate construction information

Airport Construction & Viaduct Open House

Thursday, March 185 p.m. to 7 p.m.

UTA FrontLines Headquarters669 West 200 South

Thank youMatt Sibul, UTA Airport TRAX Project Manager: 801-236-4731

Chad Saley, UTA Public Involvement: 801-287-2290Bill Knowles, Downtown Salt Lake Ombudsman: 801-580-2626

24-Hour Construction Issue Hotline: 1-888-800-8854www.rideuta.com