windsor woods tide gate - sites.wp.odu.edu · windsor lake trashmore northgate plaza ball fields...

Post on 15-Oct-2020

4 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Windsor Woods Tide Gate

Stop the Tide, Save the Storage

July 31, 2020

Hampton Roads Adaptation Forum

2

Presenters

Michael Bumbaco III, PE City of Virginia Beach Stormwater

Nicole Dane, PE Michael Baker International

Curtis HickmanWetland Studies and Solutions Inc.

PROJECT AREA

3

AtlanticOcean

Chesapeake Bay

Oceana Naval Base

City ofVirginia

Beach Limits

Lynnhaven River

MountTrashmore

Park

PROJECTAREA

N

TownCenter

4

Total Project Area – 2,600 Acres (8,500 Parcels)Windsor Woods – 1,300 Acres (3,700 Parcels)

Princess Anne Plaza – 1,100 Acres (3,800 Parcels)The Lakes – 185 Acres (1,000 Parcels)

Total Assessed Value – $2B

Windsor WoodsPrincess Anne

Plaza

TheLakes

▪ Flooded Homes and Property Damage

▪ Flooded Roads

▪Access Limited for:

o Emergency First Responders

oCity Maintenance Crews

oResidents

▪Areas Isolated until Flooding recedes

5

The Problem = Flooding

▪ Infrastructure is ± 50 years old (Built in 1960’s)

▪Area is Fully-Developed

▪ Existing storm drains are inadequate or non-existent

▪ Lack of storage

▪ Elevations in the area are low and flat

▪ Frequency & severity of storms is increasing

▪Area is tidally influenced

6

Why the Problem?

PROJECT AREA

Tidal Influence & Natural Drainage

Patterns7

PROJECTAREA

AtlanticOcean

Chesapeake Bay

N

City ofVirginia Beach

Limits

8

Risk Assessment Map

Sewells Point Tide Gauge Data

24-Hour Precipitation Return PeriodNorfolk Airport Rain Gauge (NOAA/NWS)

Hurricane Matthew

▪ Rainfall from Hurricane Matthew (Oct 2016) resulted in extreme flooding

▪ 800 Residences Reported Damage (Modeling approximates over 1,400)

▪ Many streets were impassable

▪ Flood Insurance Rates have significantly increased

11

Flooding from Hurricane Matthew (2016)

4412

Work Leading to the Tide Gate?

▪ Public Outreach and Involvement

▪ Windsor Woods Stormwater Management System Flood Mitigation Plan -CDM Smith - April 2018

▪ Final Windsor Woods Drainage Improvements PER –Michael Baker – September 2019

13

Overall Solutions

▪Gates to Block Incoming Tide

▪ Stormwater Pump Stations

▪Additional Storage

▪ Flood Barriers

▪ Storm Drains

14

15

Overall Preliminary Concept Plan(Recommended Infrastructure)

Lynnhaven P

kw

y

Lake

Windsor

Lake

Trashmore

Northgate Plaza

Ball Fields

POTENTIAL STORMWATER

STORAGE

NEW STORM DRAINS WILL BE

INSTALLED THROUGHOUTTHE PROJECT

AREA

POTENTIAL NORTH PUMP STATION,

TIDE GATE & BARRIER

LOCATION

WINDSOR WOODS PUMP STATION, TIDE GATE &

BARRIER LOCATION

POTENTIAL SOUTH TIDE GATE,

CHANNELS & BARRIER

LOCATION

Windsor Woods Tide Gate Project

16

▪ Windsor Woods Tide Gate Selected by City to Move Forward

o Tide Gate (60 feet wide; 4 bays)o Pump Station (750 cfs)o Barriers (100-year)

Gate Blocks Incoming Tide Stormwater Storage

Windsor Woods

17

Lake Trashmore

Natural Drainage Patterns

Windsor Woods

18

Tidal Impacts

Lake Trashmore

Windsor Woods19

Proposed Pump

Station

Proposed Tide Gate

Lake Trashmore

20

Proposed Barrier

Windsor Woods

Lake Trashmore

21

Windsor Woods Tide Gate & Pump Station Site

Lake Windsor

22

Windsor Woods Tide Gate & Pump Station Rendering

Lake Windsor

Windsor Woods Tide Gate Rendering

23

24

Windsor Woods Tide Gate & Pump Station Rendering

25

Windsor Woods Tide Gate & Pump Station Site

Lake Windsor

Lake Windsor

Lake Windsor

Mount TrashmoreSkatepark

Mount TrashmoreSkatepark

26

Lake Windsor – Ex. Conditions (Low Tide)

Water Level at Low Tide

Thalia Creek

Lake Windsor

High Tide –

Low Tide –

UPSTREAMDOWNSTREAM

Available Storage Capacity at Low Tide

Natural Flow of Drainage

27

Lake Windsor – Ex. Conditions (High Tide)

Water Level at Low Tide

Thalia Creek

Lake Windsor

Water Level at High TideHigh Tide –

Low Tide –

Tide Fills Available Storage

Incoming Tide

UPSTREAMDOWNSTREAM

28

Lake Windsor – Ex. Conditions During Storm

Lake WindsorThalia

Creek

UPSTREAMDOWNSTREAM

Storage Capacity Exceeded Quickly and Flooding Occurs

Low Tide –

High Tide –

Water Level at Low Tide

Water Level at High Tide

29

Lake Windsor – After Tide Gate Installation(Post-Improvements)

Water Level at Low Tide Lake

Windsor

Water Level at High Tide

Tide Gate in the Open Position

Normal Water LevelHigh Tide –

Low Tide –

UPSTREAMDOWNSTREAM

Thalia Creek

30

Lake Windsor – After Tide Gate Installation(Post-Improvements)

Water Level at Low Tide

Lake Windsor

Tide Gate in the Closed Position

High Tide –

Thalia Creek

UPSTREAMDOWNSTREAM

Low Tide –

Storage Now Available Since Tidal Influence Eliminated

31

Lake Windsor – After Gate & Pump Installed

Lake Windsor

Tide Gate and Pump Station In

Operation

High Tide –

UPSTREAMDOWNSTREAM

Pumps Used to Maintain Water

Levels Behind Gate

Additional Storage Created

by Pump Drawdown

Low Tide –

Thalia Creek

Regulatory

Pump Station

Storage(Water Quality)

Gates & Barriers

Storm Drain Network

Key Program Components

Regulatory Permitting

33

▪ Permitting o Corps and DEQ Individual Permits

o Early Regulatory Coordination and Agency Involvemento Public Outreach and Buy Ino Alternatives Evaluation – Couldn’t Have Found a Better Site

▪ Aquatic Life o Frequency and Duration of Closureo Maintenance of Low Flow o Intake Structures – Entrainment

This is a Great Site for LEDPA!!!

34LEDPA – Least Environmentally Damaging Practicable Alternative

Fish Passage - Frequency and Duration of Closure

▪ Typically open during “Sunny Day” conditions

▪ Closed ~5-8 times a year

▪ ~24 to 48-hour pre-storm pump down

35

Maintenance of Low Flow - Aquatic Life

36

Intake Structures - Entrainment

37

Intake Structures

38

39

All Permits Received

▪ USACE and DEQ Individual Permits Issued

▪ No VMRC Permit Required

▪ A separate permit will be necessary for the larger pump.

▪ And the process starts again!

Future Permits

40

Summary/Take-Aways

▪ Tide gate is the first project in this multi-faceted Long-term Program

▪ Permitting is Critical for Large Water Dependent Projects

▪ Regulatory Coordination needs to be Integral in Planning Process

▪ Public Involvement/Buy-In Important

▪ Pre-Storm Planning & Preparation is Critical

▪ Long-Term Operation & Maintenance Required

▪ Construction Anticipated Spring 2021

Thank You!

41

top related