DIPLOMA IN OCCUPATIONAL SAFETY AND HEALTH

(DOSHM)

WORKPLACE ASSIGNMENT OF HAZARD IDENTIFICATION, RISK ASESSMENT AND RISK CONTROL (HIRARC)

PROJECT 3415

(NAME)

(STUDENT ID)

FRONT

PAGE

COVER

WORKPLACE ASSIGNMENT VERIFICATION

“ I HEREBY CERTIFY THAT THIS DOCUMENT WAS PREPARED FOR THE DOSHM FINAL TEST BASED ON MY ORIGINAL WORK AND EXCEPT FOR CITATION AND QUATATION”

MODULE CODE/ SUBJECT PROJECT 3415/ HIRARC

NAME

IC NO

ID NO

SIGNATURE

DATE

ABSTRACT (10 MARKS)

ABC Company is a …………., comprises …….department. Located at……., this nominated company had been choose to perform the Hazard Identification, Risk Assessment and Risk Control (HIRARC) report. The objective of this report is to identify five (5) Safety Hazards and three (3) Health Hazards at the nominated workplace. There are few methodology that have been used to gather all information needed including site observation, face to face interview and documentation data such accident or incident reports, inspection……………The most critical hazards from the…………activities are …………for safety hazards and ………..for health hazards. The appropriate control measures ……………. have been suggested to overcome the ……..problem. These control measures hope, will improve the safe work practice as well as give benefits for both parties, employer and employee and reduce or minimize the number of injuries and accidents.

1 PAGE ONLY

1.0 INTRODUCTION (12 MARKS)

1. Company background, activities

2. Organization structure

3. No’s of employees

4. Work process & the chosen work process to perform HIRARC (also to simplify in form of work process flow/ diagram)

5. 2 to 3 pages

2.0 OBJECTIVE (5 MARKS)

The objective of this report are:

1. To identify 5 safety and 3 health hazards through out the work process.

2. To assess the safety and health hazards based on the risk matrix rating and ascertained the most critical hazards.

3. To develop effective suggestions as control measures to manage and minimize the risk.

4. To propose appropriate recommendation to the management to ensure the effectiveness of the control measures.

3.0 METHODOLOGY (20 MARKS)

3.1 Hazard Identification Process

***Identify & described 3 methods to identify the hazards

i. Job Observation

- Explanation

ii. Interview and discussion

- Explanation

iii. Documentation

- Workplace inspection, accident and incident statistic

3.2 Risk Assessment Technique

- by using (Semi-quantitative) technique:

i. Likelihood table

ii. Severity table

iii. Relative Risk table (High, Medium, Low)

iv. Risk Matrix table (split by color: red, yellow, green) (4 x 4) or (5 x 5)

3.0 METHODOLOGY (20 MARKS)

Likelihood table

Table B indicates severity using the following values –

Severity table

iii. Risk Matrix table

iv. Relative Risk table

3.3 One example each; safety & health hazards

3.0 METHODOLOGY (20 MARKS)

Hazard Consequences Likelihood Severity Risk Level

Fall from height Death 3 4 12(Medium)

Dust Pneumonocosis 4 3 12(Medium)

4.0 FINDING RESULTS AND DISCUSSION (20 MARKS)

• List down 8 hazards (5 safety, 3 health)• Give priority of hazard based on risk rating (1 safety & 1 health)• Table form

Hazard Identification Risk Analysis RC Attach

No Work Activity

Hazard Effect Existing Control Measures

L S R Recom Pic

5.0 RECOMMENDATION (30 MARKS)

*** Explain in detail the best control measures to be implemented for both critical hazards

Hazard Risk Recommendation PIC Action Plan

Safety L X S Contractor 3 weeks after

Health L X S En Ahmad 25/ 3/ 2012

Explain in detail (wording statement)

6.0 CONCLUSION

7.0 REFERENCE (3 MARKS)

(Books Reference)

Author, Book title, Publisher, Year Factory and Machinery Act 1967, MDC Publisher Sdn Bhd, 2010

Edition.

(Website Reference) http:/www.osha.gov/oshpubs/perpro.html

8.0 ATTACHMENT

END OF REPORT

ORAL PRESENTATION SLIDES

SLIDES

1. Introduction about the workplace (1/2 slides)

2. Work process (1 slide) – in diagram form

3. Objective (1 slide)

4. Methodology (5 slides: method IH, likelihood table, severity table, risk matrix table, risk relative table)

5. Hazards summary table (list out all the hazards- 1 slide)

6. Result

7. Recommendation (2 slides – 1 safety & 1 health hazard)

8. Action Plan

9. Conclusion (1 slide)e.g: Lim, Teh

Presentation: 20 minutesQ & A : 20 minutes