amtrak contract …knowledge.urbanengineers.com/assets/amtrak... · ep 3014 01142a of plans for...

71
AMTRAK CONTRACT REQUIREMENTSISPECIFICATIONS EP# SPEC TITLE VERSION EP3006 Design and Construction Criteria for Overhead Bridges 3/26/2002 EP 3014 Maintenance and Protection of Railroad Traffc During Contractor 2/3/2006 Operations EP 3014 01141A Safety and Protection of Railroad Traffc and Property rev 3 02/03/06 Submission Documentation Required for Amtrak Review and Approval rev 3 EP 3014 01142A of Plans for Bridge Erection, Demolition and Other Crane Hoisting 12/15/05 Operations Over Railroad Right of Way EP 3014 01520A Requirements for Temporary Protection Shields for Demolition and rev 1 Construction of Overhead Bridges and Other Construction 8/7/2001 EP 3014 02261A Requirements for Temporary Sheeting and Shoring to Support Amtrak rev 2 Tracks 817101 EP 3016 Stormwater Drainage and Discharge from Adjacent Properties onto 4/2512001 Amtrak right-of-way Crashwall Requirements AREMA Chapter 8, Article 2.1.5 Insurance Requirements (Attachment B to Permit to Enter) (Limits may Feb-05 be greater for certain projects) CE-17 Temporary Permit to Enter Upon Property 2/14/2006 EP3005 020B1A Pipeline Occupancy rev 1013012002 CE-4 Specifications for Wire, Conduit, and Cable Occupations Mar-97 Roadway Clearances - Standard Track Plan Dwg. No. AM70050G 5/11/1999 Roadway Sections - Standard Track Plan Dwg. No. AM70003A 5f71999 Amtrak Standard Structures Plan SPB001 - Platorm Safety Stripe 413100 Amtrak Standard Structures Plan SP8002 - High Level Platform 4/3/00 Clearances and Edge Details EP 3003 Blasting Procedu res 1/2512001 EP 4006 Overbuild of Amtrak Right-of-Way Design Policy rev 5/5/05 63 Track Design Specification Spec No. 63 3112003 Qualified Consultants for Electrification Design - 2004 rev 2f705 Amtrak Specification - AED-1 Procedures and Design Criteria to be Employed by Electrification Consultants Engaged in the Design of rev Feb 2006 Electrifcation of Facilities on the National Railroad Passenger Corporation Elecrifed Territory O.H. Bridge Typical Protection Barrier Standard Approved Drawings ET-144-D 6f799 Electrified Territory O.H. Bridge Temporary Protection Shield & Barriers Approved Standard Drawings ET -1447 -D 1/18/00 N. E. C. Signage - Standard Drawings ET -1 099-D (8 sheets) Approved 7/1/99 JEY speclist.doc rev4f7J06

Upload: ngongoc

Post on 01-May-2018

477 views

Category:

Documents


12 download

TRANSCRIPT

Page 1: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

AMTRAK CONTRACT REQUIREMENTSISPECIFICATIONS

EP# SPEC TITLE VERSIONEP3006 Design and Construction Criteria for Overhead Bridges 3/26/2002

EP 3014 Maintenance and Protection of Railroad Traffc During Contractor2/3/2006Operations

EP 3014 01141ASafety and Protection of Railroad Traffc and Property rev 3

02/03/06Submission Documentation Required for Amtrak Review and Approval

rev 3EP 3014 01142A of Plans for Bridge Erection, Demolition and Other Crane Hoisting12/15/05Operations Over Railroad Right of Way

EP 3014 01520ARequirements for Temporary Protection Shields for Demolition and rev 1

Construction of Overhead Bridges and Other Construction 8/7/2001

EP 3014 02261ARequirements for Temporary Sheeting and Shoring to Support Amtrak rev 2Tracks 817101

EP 3016Stormwater Drainage and Discharge from Adjacent Properties onto

4/2512001Amtrak right-of-wayCrashwall Requirements AREMA Chapter 8, Article 2.1.5Insurance Requirements (Attachment B to Permit to Enter) (Limits may Feb-05be greater for certain projects)

CE-17 Temporary Permit to Enter Upon Property 2/14/2006

EP3005 020B1APipeline Occupancy rev

1013012002CE-4 Specifications for Wire, Conduit, and Cable Occupations Mar-97

Roadway Clearances - Standard Track Plan Dwg. No. AM70050G 5/11/1999Roadway Sections - Standard Track Plan Dwg. No. AM70003A 5f71999Amtrak Standard Structures Plan SPB001 - Platorm Safety Stripe 413100Amtrak Standard Structures Plan SP8002 - High Level Platform

4/3/00Clearances and Edge DetailsEP 3003 Blasting Procedu res 1/2512001EP 4006 Overbuild of Amtrak Right-of-Way Design Policy rev 5/5/05

63 Track Design Specification Spec No. 63 3112003Qualified Consultants for Electrification Design - 2004 rev 2f705Amtrak Specification - AED-1 Procedures and Design Criteria to beEmployed by Electrification Consultants Engaged in the Design of

rev Feb 2006Electrifcation of Facilities on the National Railroad PassengerCorporationElecrifed Territory O.H. Bridge Typical Protection Barrier Standard ApprovedDrawings ET-144-D 6f799Electrified Territory O.H. Bridge Temporary Protection Shield & Barriers ApprovedStandard Drawings ET -1447 -D 1/18/00N. E. C. Signage - Standard Drawings ET -1 099-D (8 sheets) Approved

7/1/99JEY speclist.doc rev4f7J06

Page 2: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

Amtrak$ ENGINEERINGPRACTICES

ORIGINAL ISSUE DATE

03126102NUMBER

REVISED DATE EP3006TITLE

DESIGN AND CONSTRUCTION CRITERIA FOROVERHEAD BRIDGES

NIA

RECOMMENDED by

K.L. Kulick

APPROVED by CHIEFENGR, STRUCTURES

James S. Richter

DATE PAGE3/26/02 1DATE OF

3/26/02 8

SCOPE AND NATURE

To establish uniform requirements for the design and construction of overhead bridges byoutside agencies.

SPECIAL REFERENCE

Standard Track Plan AM70050

ET Standard Plan ET1446-D

ET Standard Plan ET 1447-0

Engineering Practice 3003

Engineering Practice 3014 Section 02261

Engineering Practice 3014 Section 01520

Engineering Practice 3014 Section 01142

Engineering Practice 1604

AED-1 Procedures and Design Criteria to be Employed by Electrification ConsultantsEngaged in the Design of Electrification Facilities on the National RailroadPassenger Corporation

AREMA Manual for Railway Engineering - Chapter 8, Article 2.1.5

SPECIAL MATERIALS

N/A

Page 3: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE ORIGINAL ISSUE DATE

03/26/02NUMBER

DESIGN AND CONSTRUCTION CRITERIA FOROVERHEAD BRIDGES

REVISED DATE EP3006NIA

PAGE

20F8

PROCEDURE

DESIGN AND CONSTRUCTION CRITERIA FOR OVERHEAD BRIDGES

./

New or reconstructed bridges over Amtrak Railroad tracks shall meet the followingrequirements:

i. CLEARANCESa. Horizontal and Vertical Clearances shall be in accordance with the current

Standard Track Plan AM70050 - "Minimum Roadway Clearances". Whenreplacing existing bridges that have substandard clearances, every effort shall bemade to improve the clearances.

b. Temporary Construction clearances may be less if approved by Amtrak.

c. Amtrak shall be furnished as-built drawings showing actual clearances as

constructed.

d. Horizontal clearances may need to be increased if a maintenance roadway is

required by Amtrak.

e. Clearances shall be adjusted to provide for any planned changes in the trackage,including the change in track centers and raising of the tracks. Amtrak shall becontacted to obtain information on planned track changes. If the track is in a sagat the proposed overhead crossing location, it should be anticipated that the trackmay be raised to improve the condition. Clearances shall be increased to providefor this track raise.

II. CRASH WALLSAREMA Manual for Railway Engineering, Chapter 8, Article 2.1.5 Pier Protection,describes the requirements for the crash walls. Crash walls are required when face ofthe pier is closer than 25'-0" from centerline of the nearest track, measuredperpendicular to the track, unless the size of the pier satisfies the criteria for piers ofheavy construction as listed in Article II (d).

Crash walls shall meet the following requirements:

a. Crash walls for piers from 12 feet to 25 feet clear from the centerline of the trackshall have a minimum height of 6 feet above the top of raiL. Piers less than 12 feetclear from the centerline of the track shall have a minimum crash wall height of 12feet above the top of raiL. Crash walls shall be at least 2'-6" thick and at least 12feet long.

b. For multi-column piers, the crash wall shall connect the columns and extend at

least 1 foot beyond the outermost columns parallel to the track.

c. Crash walls shall be anchored to the footings and columns as applicable and shall

extend to at least four feet below the lowest surrounding grade.

Page 4: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE ORIGINAL ISSUE DATE

03/26/02NUMBER

DESIGN AND CONSTRUCTION CRITERIA FOROVERHEAD BRIDGES

REVISED DATE EP3006N/A

PAGE

30F8

d. A pier shall be considered of heavy construction if it has a cross-sectional area

equal to or greater than that required for the crash wall and the larger of itsdimensions is parallel to the track.

e. Consideration may be given to providing protection for bridge piers located morethan 25 feet from the centerline of track as conditions warrant. In making thisdetermination, account shall be taken of such factors as horizontal and verticalalignment of the track, embankment height, and an assessment of theconsequences of serious damage in the case of a collsion.

II. BARRIERSa. In the territory where there is railroad electrification, barriers shall be designed and

constructed on both faces ofthe bridge in conformance with the current ETStandard Plan ET-1446-D "Electrified Territory OH Bridge Typical ProtectionBarrier" .

b. In non-electrified territory, chain-link fence with 1" mesh fabric may be substituted

for the solid barrier.

)IV. ELECTRIFICATION SYSTEMS.

a. In electrified territory the agency responsible for the project shall be required to

comply with AED-1 "Procedures and Design Criteria to be Employed byElectrification Consultants Engaged in the Design of Electrification Facilties onthe National Railroad Passenger Corporation".

V. DRAINAGEIt is essential to maintain good drainage of railroad right-of-way during constructionand provide for good drainage after construction of the overhead crossing. Thefollowing guidelines shall be followed:

a. Piers and end slopes shall be located such that they do not interfere with railroaddrainage system, including, but not limited to, ditches, pipes, catch basins anddetention basins.

b. Drainage from the section of the bridge above railroad right-of-way shall becollected with drain pipes and drained away from the railroad right-of-way. Noopen scuppers are permitted on the portion of the bridge over the railroad right ofway. Drainage from any scuppers shall be drained away from the railroad right-of-way.

c. After completion of construction, railroad drainage ditches shall be cleaned of all

debris to the satisfaction of Amtrak representatives.

d. During construction, silt fences shall be provided to prevent siling of the ditches.

All drainage from the construction site must be collected and directed away fromrailroad property.

Page 5: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE ORIGINAL ISSUE DATE

03/26/02NUMBER

DESIGN AND CONSTRUCTION CRITERIA FOROVERHEAD BRIDGES

REVISED DATE EP3006NIA

PAGE

40F8

e. If the project wil alter drainage characteristics at the site of the crossing at any

time during or after completion of the project, three sets of the drainagecalculations and plans shall be submitted to Amtrak for approval. Approval of thedrainage plans shall not relieve the submitting agency of responsibility for thedrainage design.

f. All disturbed areas on the railroad right-of-way shall be properly seeded and

mulched to the satisfaction of Amtrak.

Vi. STRUCTURE EXCAVATION AND SHORINGShoring or sheeting protection shall be provided in conformance with the currentEngineering Practice 3014 Section 02261 - "Requirements for Temporary Sheetingand Shoring to Support Amtrak Tracks", Blasting is restricted and if required shall be inconformance with Engineering Practice 3003- "Blasting Procedures".

a. A construction procedure for temporary shoring shall be shown on the drawing.

b. Safety railing meeting OSHA requirements shall be installed when temporary

shoring is within 12 feet of track. When shoring is further than 12 feet fromcenterline of track, railng shall be provided if necessary for safety of workers andrailroad personneL.

VII. GENERAL REQUIREMENTSa. The distance from the nearest milepost at intersection of centerline of the track

and centerline of the bridge shall be shown on the General Plan.

b. Horizontal and vertical clearances shall be marked clearly on the General Plan

and Elevation.

c. Soil parameters used in designing the shoring shall be based on soil and rock

data obtained from test borings performed for the design ofthe proposedstructure.

d. It is the designer's responsibility to ensure that a constructability analysis is

performed to confirm that the structure, as designed, can be constructed in theapplicable railroad environment.

e. Piers, abutments and columns located within the railroad right-of-way shall havean anti-graffti coating consisting of a three-coat system. Each of the three coatsshall be a clear, two component, polyester type, aliphatic urethane. Each coatshall be applied at a minimum 2 mils DFT.

VII. DEMOLITION OF EXISTING STRUCTURESRailroad tracks shall be protected from damage during demolition of existing structureor replacement of deck slab. Either of the following methods may be used:

a. During demolition of the decks, a protection shield shall be erected over the right-of-way to catch fallng debris. The shield shall be designed and constructed in

Page 6: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE ORIGINAL ISSUE DATE

03/26/02NUMBER

DESIGN AND CONSTRUCTION CRITERIA FOROVERHEAD BRIDGES

REVISED DATE EP3006N/A

PAGE

50F8

conformance with the current Engineering Practice 3014 Section 01520 -"Requirements for Temporary Protection Shields for Demolition and Constructionof Overhead Bridges and Other Structures".

b. On light traffc density lines or when overhead protection shield cannot beinstalled due to limited clearance or type of superstructure, track may be protectedby timber mats placed over the track structure, subject to approval by Amtrak.Timber mats shall be made in sections such that they may be lifted in and outquickly, Mats shall not rest on ties or rails.

Geo-fabric or canvas shall be placed over the track structure to keep the ballast clean.

The contractor shall submit detailed plans of the protection shield or the timber mats tothe Project Engineer for approval prior to the start of demolition. The plans shall beprepared by a Registered Professional Engineer and shall bear his seal and signature.

Blasting will not be permitted to demolish a structure over or within the railroad right-of-way.

;, /

IX. ERECTION PROCEDUREThe contractor shall submit a detailed procedure for erecting the spans over railroadright of way. The procedure shall be in conformance with the current EngineeringPractice 3014 Section 01142 - "Submission Documentation Required for AmtrakReview and Approval of Plans for Bridge Erection, Demolition, and OtherCrane/Hoisting Operations over Railroad Right-at-Way".

X. PIPELINESAll pipelines occupying the bridge shall be designed and constructed in accordancewith Engineering Practice 1604 Pipeline Occupancy - Requirements andSpecifications.

Xl. CROSSING DATAPlans submitted for review by Amtrak shall contain, at the minimum, the followinginformation:

. Roadway name or route number

. Amtrak bridge number

. Skew angle to the railroad center line

· Proposed foundation type and elevation of bottom of footing

· Pile type and depth (if applicable)

. Top of rail elevation for all tracks

· Drainage modifications

· Elevation and cross sections of existing and proposed structure

Page 7: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE ORIGINAL ISSUE DATE

03/26/02NUMBER

DESIGN AND CONSTRUCTION CRITERIA FOROVERHEAD BRIDGES

REVISED DATE EP3006N/A

PAGE

60F8

. North arrow

· Railroad clearance information with dimensions in English units

The following "Overhead Bridge Crossing Data" sheet shall be completed andsubmitted, by the agency responsible for the project, with both the Preliminary andFinal Plan submission to Amtrak.

/

Page 8: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE ORIGINAL ISSUE DATE NUMBER

03/26/02REVISED DATE EP3006

DESIGN AND CONSTRUCTION CRITERIA FOR N/AOVERHEAD BRIDGES PAGE

70F8

OVERHEAD BRIDGE CROSSING DATA

1. LOCATION:

CITY COUNTY STATE

2. Distance from nearest Mile Post to Centerline of Bridge:

3. DOT Crossing Number:

4. State Project Number:

5. Description of Project:

6. Minimum Horizontal Clearance from Centerline of nearest Track:

A. Proposed: B. Existing (if applicable):

7. Minimum Vertical Clearance above top of high rail:

A. Proposed: B. Existing (if applicable):

8. List piers where crashwalls are provided:

Pier: Distance from centerline of track:

9. Describe how drainage from bridge is handled:

10. List piers where shoring is required to protect track:

11. Plan Submittal: Preliminary: Final:

Page 9: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE ORIGINAL ISSUE DATE NUMBER

03/26/02REVISED DATE EP3006

DESIGN AND CONSTRUCTION CRITERIA FORNIA

OVERHEAD BRIDGES PAGE

80F8

REPORTING

As detailed in procedure.

RESPONSIBILITY

Amtrak I&C Staff Comply with Procedure

Director I&C Assure Compliance

Amtrak Design Staff Comply with Procedure

Amtrak Construction Staff Comply with Procedure

Sf. Director Construction Assure Compliance

Page 10: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

:4

J \.

ENGINEERING I ORIGINALrSsu~1~~~~01

PRACTICES ¡ REVISED DATE

! 08107/01I NUMBER

I EP3014TITLE i!

.1 RECOMMENDED byKenneth KulickAPPROVED by CHIEFENGR, STRUCTURES

James Richter 2

MAINTENANCE AND PROTECTION OFRAILROAD TRAFFIC DURING CONTRACTOR

OPERATIONS

DATE

8/07/01

DATE

PAGE

1

OF

SCOPE AND NATURE

This practice provides procedures for ContractOrs to follow, when working on Amtrak Right-of-Way, adjacent to Amtrak tracks, to assure the protection of trains and maintenance ofscheduled railroad operations.

SPECIAL REFERENCE

Note: This information was included under former Engineering Practice 1305.

Contractors shall comply with procedures detailed in the following specifications, whenapplicable:

, I

Section Title RevisionNo.

1

o

RevisionDate

08/07/01

01/25/01

,i 01141A

01142A

Safety and Protection of Railroad Traffc and Property

Submission Documentation Required for Amtrak Review andApproval of Plans for Bridge Erection, pemolition and OtherCrane/ Hoisting Operations over Railroad Right-of-Way

Requirements for Temporary Protection Shields for Demolitionand Construction of Overhead Bridges and Other Structures

Requirements for Temporary Sheeting and Shoring to SupportAmtrak Tracks

08/07/01

01520A 1 08107/01

02261A 2

SPECIAL MATERIALS

Not Applicable

PROCEDURE

1. The Contractor shall conform to the applicable specifications.

2. Amtrak I&C shall assure that agencies and other third parties proposing construction onor adjacent to Amtrak Right-of-Way conform to Amtrak requirements detailed herein.

3. Amtrak Design and Construction shall review the Contractor's proposed design andconstruction procedures for conformance with specifications, with sounti ~- . ~ -~"'F

practice and with the procedures detailed in the applicable Enginei ...~ '-I actice documer

Page 11: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

-4

~

TITLE

MAINTENANCE AND PROTECTION OFRAilROAD TRAFFIC DURING CONTRACTOR

OPERATIONS

ORIGINAL ISSUE DATE

01125101REVISED DATE

08/07/01

NUMBER

EP3014

PAGE

20F2

4. Amtrak Construction shall monitor the activities of the Contractor on-site to assurecompliance/ adherence to approved procedures throughout the construction period.

REPORTING

As detailed in specifications.

RESPONSIBILITY

Amtrak I&C Staff

Director I&C

Amtrak Design Staff

Director Structures Design

Amtrak Construction Staff

Sr. Director Construction

Comply with Procedure

Assure Compliance

Comply with Procedure

Assure Compliance

Comply with Procedure

Assure compliance

Page 12: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

ENGINEERING ORIGINAL ISSUE DATE NUMBER

Amtrak$ 06/20101

PRACTICES REVISED DATE EP400605105105

TITLE

OVERBUILD OF AMTRAK RIGHT-OF-WAY RECOMMENDED by DATE PAGE

DESIGN POLICY Joseph Grella 05/04/05 1APPROVED by CHIEF DATE OFENGR, STRUCTURES

James Richter 05/05/05 4

SCOPE AND NATURE

The development of property resulting in a closed or partially enclosed overbuild structureover tracks, shall include design features to ensure adequate ventilation, ilumination,emergency egress and fire protection to provide a safe environment for Amtrak employeesand customers during normal and emergency operations. The developer shall make allaccommodations to the above grade structure, and shall be responsible for the design,construction and maintenance of the systems described below.

These criteria are intended to serve as the basis of design. It is recognized that there maybe more than one acceptable solution and Amtrak is prepared to review any scientificanalysis that accomplishes the stated function and cooperate with the developer to achievea maintainable and effective overbuild system.

The developer shall comply with National Fire Protection Association NFPA 130 andreferenced documents therein, Except, if the overbuild property is in the City of New Yorkand not already constructed, it shall be assumed to be part of a continuous overbuild longerthan 1000 feet and therefore mechanical ventiation, egress, fire protection and lighting shallbe provided accordingly. The developer shall also comply with all local, state and federalrequirements, should they be more stringent than described herein.

SPECIAL REFERENCE

American Railway Engineering and Maintenance-of-Way Association, AREMA Manual forRailwav EnQineerinQ, Chapter 6, Buildings and Support Facilties

American Society of Heating, Refrigerating and Air-Conditioning Engineers, 2003 ASHRAEHandbook HVAC Applications. Chapter 13, Enclosed Vehicular Facilities

Iluminating Engineering Society of North America, Liqhting Handbook. Chapter 11

National Fire Protection Association, NFPA 101, Code for Safety to Life from Fire inBuildinQs and Structures

National Fire Protection Association, NFPA 130, Standard for Fixed Guideway Transit andPassenqer Rail Systems

National Fire Protection Association, NFPA 502, Recommended Practice on Fire Protectionfor Limited Access HiQhwavs. Tunnels. BridQes, Elevated Roadways and Air RightStructures

Page 13: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE

OVERBUILD OF AMTRAK RIGHT-OF-WAYDESIGN POLICY

ORIGINAL ISSUE DATE

06/20101REVISED DATE

05105105

NUMBER

EP4006

PAGE

20F4

u.s. Department of Labor, 29 CFR 1910, OSHA Safety and Health Standards

Van Nostrand Reinhold, Tunnel EnQineerinQ Handbook, Chapter 19, Tunnel Ventiation

SPECIAL MATERIALS

Not applicable.

PROCEDURE

Here are special design criteria for designers to consider.

Normal Ventilation

Ventilation shall be provided as needed to control air quality. An engineering analysis to modelthe specific railroad operating scenarios of diesel locomotives within must be performed. The

) result of the analysis shall be the design of a ventilation system with appropriate controls tomaintain safe, acceptable concentrations of diesel exhaust gases. Amtrak wil have personnelroutinely assigned to work in the track area doing maintenance on tracks, signals, rollng stock,and building equipment. Hence, the prescribed occupational limits for NOx, CO, Aldehydes andunburned hydrocarbons must be met. These levels shall be as defined by OSHA and approvedby the Amtrak. Amtrak wil also provide the developer with the operating scenarios regardingtrain movement within the overbuild. Stopped locomotives with head-end power, work trainmovements and mail and baggage switching shall be specifically addressed in the engineeringanalysis.

The operation of locomotives in the traction and/or hotel power mode requires the collection ofemissions, typically though exhaust hoods, while stil hot and near the ceiling. Throat velocity ofexhaust inlets should be at least double the terminal velocity of the emissions that are to becaptured. Past designs have shown a throat velocity of 1800 to 2200 feet per minute to beapplicable approximately 19 to 22 feet above top-of-rail. Duct inlets should be close to thecenter of track, nominally 12 to 15 feet on-centers. The emission temperature at source wíl bebetween 2500 and 9500 F. A diesel locomotive that has been operating for several minutes in alightly loaded mode, wil often produce large amounts of visible smoke and emissions fromaccumulated, unburned fueL. This short-time emission is likely to occur as a train starts toaccelerate upon departure. In the affected zone of operation adjacent to the area, someproducts of combustion wil not be captured. Therefore, a general ventilation dilution systemshould be incorporated with a minimum rate of 6 air-changes per hour. This system may beoperated only during the transiting ofthe affected area and for 10-15 minutes after each transitto clear residual emissions. Make-up must be provided to balance air flows once all open areasare covered. Make-up should be introduced at a level below 4 feet above the top-of-rail toinsure make-up air does not cool the emissions or cause dispersal. Because of the high exitvelocity from some exhausts, (up to 3000 feet per minute) side baffes on ducts and structuresshould be avoided to prevent deflecting emissions away from inlet grilles. Noise levels from the

Page 14: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

"

TITLE ORIGINAL ISSUE DATE NUMBER

06120/01REVISED DATE EP4006

OVERBUILD OF AMTRK RIGHT-OF-WAY 05105105DESIGN POLICY PAGE

30F4

ventiation system shall not exceed OSHA regulations while also meeting applicable local noiseordinances.

Emer~encv Ventilation

Mechanical emergency ventilation shall be provided in the City of New York, and for overbuildsgreater than 1000 feet in length elsewhere. An engineering analysis to determine the need formechanical emergency ventilation shall be conducted in overbuilds less than 1000 feet, butgreater than 200 feet elsewhere. Mechanical emergency ventiation is not required foroverbuilds less than 200 feet in length elsewhere. The ventilation system shall:

. Provide a stream of non-contaminated air to passengers in a path of egress away from atrain fire.

. Produce air-flow rates to prevent back-layering of smoke in a path of egress away from atrain fire.

. Limit the air temperature in a path of egress away for a train fire to 140°F or less.

. Ensure visibilty during a fire suffcient to see an internally-lighted 7.5 foot-candle sign ata distance of 100 feet (light attenuation coeffcient of 0.06096/ft).

. Comply with all provisions of NFPA 130, Chapter 4.

An engineering analysis to model the effect of a fire within the limits of the mechanicallyventilated overbuild must be performed. The result of the analysis shall be the design of the

ventilation system with appropriate controls. Two fire sizes, large and small, shall be used fordesign criteria:

i. Large: For a single-track/tunnel scenario, it may be appropriate to use the SubwayEnvironmental Simulation Computer ProQram, Version 4 or later, available from the U.S.Department of Transportation. Use a fire heat release rate of 106.2 millon BTU/hr (30 MW).For a multi-track/station scenario, Computational Fluid Dynamics (CFD) may be required,Use 177.5 milion BTU/hr (50 MW) developing over a span of 26 minutes reflectinginteraction of fire spreading to adjacent passenger cars as shown below:

TIME HEAT RELEASE RATE SMOKE YIELD RATE

Minutes Milion Btu/Hr LbsJMin

0 0 03 17.1 2.7710 17.1 2.7713 34.1 5.5320 34,1 5.5326 177.5 28.78;: 26 177.5 28.78

Page 15: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE

OVERBUILD OF AMTRAK RIGHT-OF-WAYDESIGN POLICY

ORIGINAL ISSUE DATE

06120101REVISED DATE

05105105

NUMBER

EP4006

PAGE

40F4

2. Small: Verify the proposed ventilation system (if designed to rely on thermal buoyancyeffects) wil satisfactorily handle a fire heat release rate of 2.4 millon BTU/hr (0.75 MW) anda smoke yield rate of 0.387 Ibs/min, reflecting a smaller trash or electrical fire.

Ilumination

Lighting shall be provided. Ilumination levels of track and walking surfaces shall not be lessthan 2 foot-candles. Exit lights, essential signs and emergency lights shall be included in anemergency lighting system powered by a standby power system. Unless specific color renditionis required, High-Pressure Sodium (HPS) fixtures should be used for general illumination.

Egress

At least one emergency exit stairway shall be provided, and additional exits if required spacedso the distance to an emergency exit shall not exceed 1250 feet. The stairway shall leaddirectly to outdoors or to a safe refuge area. Signs shall indicate direction and distance tonearest exit. Egress points shall be illuminated. Emergency telephones shall be provided ifdeemed necessary by the authority having jurisdiction.

Fire Protection

A dry fire standpipe system, minimum 4 inch. shall be provided when the length of the overbuild

exceeds the maximum length of fire hose (permitted by the local authority having jurisdiction)minus the distance from the portal to the nearest hydrant or approved water source.

REPORTING

Not Applicable.

RESPONSIBILITY

Designers of overbuild structures.

- Comply with standards and procedures.

Supervisors of Designers

- Ensure compliance with standards and procedures.

Chief Engineer, Structures

- Ensure compliance.

Page 16: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

EXHIBIT C

NATIONAL RAILROAD PASSENGER CORPORATIONTEMPORARY PERMIT TO ENTER UPON PROPERTYLE.-l7 (REVISED 2/l4/06)

Date:File: E-47-

W.E.:

AT1N:

l. TEMPORARY PERMISSION. Temporary pennission is hereby granted toOiereinafter called

"Pennittee"), to enter propert owned and/or controlled by the National Railroad Passenger Corporation(hereinafter called "Railroad"), for the purpose of

atconditions set forth below.

, State of , mider the ternis and

2. LOCA nON AND ACCESS. (Give map reference, description or both)

(hereinafter called "Propert ").

3. INDEMNIFICA nON. Pennittee shall defend, indemnify and hold harnlless Railroad, itsoffcers, directors, employees, agents, servants, successors, assigns and subsidiaries, irespective of theirnegligence or fault, from and against any and all losses and liabilities, penalties, fines, foifeitues,demands, claims, causes of action, suits, costs and expenses (including cost of defense and attorneys'fees), which any or all of them may hereafter incur, be responsible for, or pay as a result of injury, death,disease, or occupational disease to any person, and for damage (including environmental contaniination

/ and loss of use) to or loss of any propert, including propert of Railroad, arising out of or in any degree

directly or indirectly caused by or resulting from activities of or work peifonned by Permttee, its offcers,employees, agents, servants, contractors, subcontractors, or any other person acting for or by pern1Ìssionof Permittee. The foregoing obligation shall not be limited by the existence of any insurance policy or byany limitation on the amount or type of damages, compensation, or benefits payable by or for Pern1Îttee orany contrctor or subcontractor, and shall surve the termination of this Temporary Permit for anyreason. As used in ths paragraph, the term "Railroad" also includes all commuter agencies and otherrailroads with rights to operate over Railroad propert, and their respective offcers, directors, employees,agents, servants, successors, assigns and subsidiaries.

4. CONSIDERATION FOR PREPARATION OF TEMPORAY PERMIT. Pennittee wil pay toRailroad the sum of Five Hmidred Dollars ($500.00) as compensation for the preparation of thisTemporary Pem1Ìt. This fee is to be delivered to Railroad at the address set forth in paragraph i 7 hereof.

5. STARTIG OF USE OF PROPERTY. Permittee shall notif Railroad's Deputy Chief Engineer-Constrction, or his designee, at least ten (10) days in advance before entering upon, or starting any workon, the Property. No enti upon or use of the Property will be pennitted until a fully executed copy ofthis Temporary Pern1Ît is retued to Railroad, and specific pern1Îssion to enter upon the Propert isreceived by Permittee from Railroad's Director Project Initiation & Development. (See paragraph i 7 forcontact information.)

6. RAILROAD OPERATIONS. All activities peiformed by or on behalf of Permittee shall bepeifonned so as not to inteifere with Railroad's operations or with any of Railroad's facilities. In no eventshall personnel, equipment or material cross a track or tracks without special advance pennission fromRailroad's Deputy CbiefEngineer-Constrction or bis designee. If, in the opinion of Railroad's DeputyChief Engineer-Constrction or his designee, conditions warant at any tie, Railroad will provide flagservice and/or other protection at tlie sole cost and expense of Permittee, and Permittee agrees to pay toRailroad the full cost and expense therefor.

Page 17: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

./ -',

7. CLEARANCES. All equipment and material of Permittee shall be kept at all times not less thanfifteen (15) feet from the centerline of the outside track, unless spcifically otherwise authorized inwriting by Railroad's Deputy Chief Engineer-Constrction or his designee. PemlÎttee shall conduct alloperations so that no part of any equipment shall foul an operated track; transmission, communication orsignal line; or any other structue or facility of Railroad.

8. RESTORATION OF PREMISES. Upon completion of its work, Permittee shalL, at the option ofRailroad, (a) leave the Propert in a condition satisfactory to Railroad, or (b) restore the Property to itsoriginal condition. This may include, without limitation, the restoration of any fences removed ordamaged by Peniiittee.

9. TERM OF TEMPORARY PERMIT. TIùs Temporar Permit shall commence on the dateRailroad receives a fully executed copy of this Temporar PemlÎt pursuant to paagrapli 17 hereof andshall extend until the end of the period Railroad deteniiines is necessary for Permittee to accomplish thepurose set forth in paragraph 1 hereof; provided, however, Railroad reserves the right to revoke thisTemporary Permit at any time, and in no event shall this Temporar PemlÎt extend beyond

, 200_. Under no circumstances shall this Temporary Peniiit be constred asgranting to Permittee any right, title or interest of any kind in any propert of Railroad.

10. PROTECTION. All work on, over, under, within or adjacent to the Propert shall be perfomiedin accordance with the document entitled "SPECIFICATIONS REGARDING SAFETY ANDPROTECTION OF RALROAD TRAFFIC AND PROPERTY," a copy ofwlùch is attached hereto asAttachment A and incorporated herein by reference.

1 I. INSURANCE. Before Peniiittee commences any work on, over, under, within or adjacent to the/ Propert, Permittee and its contrctors (unless Permittee opts to provide the required coverage for them),

shall furish to Railroad's Director Project Initiation & Development, evidence ofthe insurancecoverages specified in the document entitled "INSURANCE REQUIREMENTS - NATIONALRAILROAD PASSENGER CORPORATION," a copy of which is attached hereto as Attachment Bandincorprated herein by reference.

12. SAFETY ORIENTATION CLASS. No person may enter within twenty-five (25) feet oftliePropert until he/she has attended Railroad's Safety Orentation Class, as noted in paragraph 12 ofAttachment A

13. COMPLIANCE BY CONTRACTORS. Permittee shall tae all steps necessar to ensure that itscontractors and subcontractors comply with the terms and conditions of this Temporar Permit.

14. SUPPORT SERVICES: COSTS: PAYMENTS. Railroad shall not be responsible for any costsincurred by Permittee in relation to any matter whatsoever. Permittee is required to reimburse Railroadfor all costs incured by Railroad in relation to tls Temporar Permit. Without limiting the foregoing,Pennittee is required to reimburse Railroad for all costs incured by Railroad in coimection with thereview of any plans, drawings or other submissions made by Permittee.

Railroad's costs, e":penses and labor charges wil be billed to Permittee at Railroad's standard forceaccount rates. Except as specified in paragraph 4 hereof, all payments due from Permittee to Railroadunder this Temporar Pem1Ît shall be due and payable within thir (30) days from the date of invoice.Pennittee shall have no right to set off against any payment due under this Temporar Permit any sumswhich Permittee may believe are due to it from Railroad for any reason whatsoever. In the event thatPermittee shall fail to pay, when due, any amount payable by it under this Temporary Pemiit, Pem1Îtteeshall also pay to Railroad, together with such overdue payment, interest on the overdue amount at ananual rate of six (6) percentage points over and above the rate published from time to time by The Wall

Street Journal as the prime commercial lending rate (or the highest rate allowed by law, if less than the2

Page 18: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

./". foregoing), calculated from tlie date the payment was due until paid. All payments due from Permittee toRailroad hereunder shall be: (a) made by check drawn from curently available funds; (b) deemed madeonly upon receipt by Railroad of collected funds; (c) made payable to National Railroad PassengerCorporation; and (d) delivered to tlie National Railroad Passenger Corporation, P.O. Box 18266F, St.Louis, Missouri, 63 i 50. (However, the perniit fee referenced in paragrph 4 hereof and the RailroadProtective Liability premium referenced in Attachment B, if applicable, shall be delivered to Railroad attlie address set forth in paragraph 17 hereof) All payment obligations ofPennittee under ths TemporaryPennit shall survive the termination or expiration of this Temporar Pennit.

15. ENVIRONMENTAL AND GEOTECHNICAL TESTS AND STUDIES. Permittee shall notperform any environmental or geotechnical tests or studies (e.g., air, soil or water sampling) unlessspecifically identified and authorized in paragraph I of this Temporar Pennit. If any such tests orstudies are performed, Permittee shall promptly furnish to Railroad, at no cost, a copy of the resultsincluding any reports or analyses obtained or compiled. Except as may be required by applicable law oras autliorized by Railroad in writing, Pennittee shall not disclose tlie results of any such tests or stdies toanyone other than Railroad or Pennittee's client. Failure to comply Witli the provisions oftrus clauseshall result in immediate teonination of this Temporar Permit and forfeiture of all compensation paidRailroad therefor.

16. SEVERABILITY. If any provision oftl1Îs Temporary Pennit is found to be unlawful, invalid orunenforceable, that provision shall be deemed deleted without prejudice to the lawfulness, validity andenforceability of the remainder of the Temporary Permit.

17. ACCEPTANCE. To comirn acceptance of this Temporar Pennit, one fully executed copy mustbe returned to: Director Project Initiation & Development, National Railroad Passenger Corporation,30th Street Station, Mail Box 64, Philadelphia, PA 19104 (215/349-4971). TIie second copy may be

/ retained for your fie.

NATIONAL RAILROAD PASSENGER CORPORATION

By:FRANK A. VACCADEPUTY CHIEF ENGINEER - CONSTRUCTION

Date:

AGREED TO AND ACCEPTED:

By:

(signature)

Title:Must be an Owner/Partner orduly autliorized representative

Date:

FAV/MAWIJEY3

Page 19: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

A IT ACHMENT ATemporary Permit to Enter Upon Property

SPECIFICATIONS REGARDING SAFETYAND PROTECTION OF RAILROAD TRAFFIC AND PROPERTY (Revised 2/3/06)

National Railroad Passenger Corporation (Railroad)

In the following Specifications, "Railroad" shall mean the National Railroad Passenger Corporation;"Chief Engineer" shall mean Railroad's Chief Engineer and/or his duly authorized representative;"Pennittee" shaH mean the part so identified in the Temporary Permit to Enter Upon Propert; and"Contractor" shall mean the entity retained by the Permittee or the entity with whom Railroad hascontracted in a Preliminary Engineerig Agreement or Force Account Agreement, as applicable.

(1) Pre-Entr Meeting: Before entr of Permittee and/or Contractors onto Railroad's propert, a pre-

entr meeting shall be held at which time Permittee and/or Contractors shall submit for ,witten approvalof the Chief Engineer, plans, computations and a detailed description of proposed methods foraccomplishing the work, including methods for protecting Railroad's traffc. Any such written approvalshall not relieve Pennittee and/or Contractor of their complete responsibility for the adequacy and safetyof their operations.

(2) Rules, Regulations and Requirements: Railroad traffc shall be maintained at all times with

safety and continuity, and Permittee and/or Contractors shall conduct their operations in compliance withall rules, regulations, and requirements of Railroad (including these Specifications) with respect to anywork performed on, over, under, within or adjacent to Railroad's propert. Permittee and/or Contractorsshall be responsible for acquainting themselves with such rules, regulations and requirements. Anyviolation of Railroad's safety rules, regulations, or requirements shall be grounds for the iimnediatesuspension of Permittee and/or Contractor work, and the re-training of all personnel, at Permittee'sexpense.

(3) Maintenance of Safe Conditions: If trcks or other propert of Railroad are endangered durng

the work, Permittee and/or Contractor shall immediately take such steps as may be directed by Railroad torestore safe conditions, and upon failure ofPemiittee and/or Contractor to immediately car out suchdirection, Railroad may tae whatever steps are reasonably necessary to restore safe conditions. All costsand expenses of restoring safe conditions, and of repairing any damage to Railroad's trains, tracks,right-of-way or other propert caused by the operations of Permittee and/or Contractors, shall be paid byPermittee.

(4) Protection in General: Permittee and/or Contractors shall consult with the Chief Engineer to

detennine the type and extent of protection required to ensure safety and continuity of railroad traffc.

Any Inspectors, Track Foremen, Track Watchmen, Flagmen, Signalmen, Electrc Traction Linemen, orother employees deemed necessar by Railroad, at its sole discretion, for protective services shall beobtained from Railroad by Permittee and/or Contractors. The cost of same shaH be paid directly toRailroad by Permittee. The provision of such employees by Railroad, and any other precautionarmeasures taken by Railroad, shall not relieve Permittee and/or Contractors from their completeresponsibility for the adequacy and safety of their operations.

(5) Protection for Work Near Electrfied Track or Wire: Whenever work is performed in the vicinity

of electred tracks and/or high voltage wires, parcular care must be exercised, and Railroad's

requirements regarding clearance to be maintained between equipment and tracks and/or energized wires,and othen'lise regarding work in the vicinty of electred tracks, must be strctly observed. No

employees or equipment will be pennitted to work near overhead wires, except when protected by a ClassA employee of Railroad. Pem1Íttee and/or Contractors must supply an adequate length of groundingcable (4/0 copper with approved clamps) for each piece of equipment working near or adjacent to any

4

Page 20: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

overhead wire,

(6) Fouling of Track or Wire: No work will be perniitted within twenty-five (25) feet of thecenterline of track or the energized wire or have potential of getting within twenty-five (25) feet of trackwire without the approval of the Chief Engineer's representative. Penniiiee and/or Contractors shall

conduct their work so that no part of any equipment or material shall foul an active track or overhead wirewithout the written perniission of the Chief Engineer's representative. When Penniiiee and/orContractors desire to foul an active track, they must provide the Chief Engineer's representative with theirsite-specific work plan a minimum of twenty -one (21) working days in advance, so that, if approved,arrangements may be made for proper protection of Railroad. Any equipment shall be considered to befouling a tTack or overhead wire when located (a) within fifteen (15) feet from the centerline of the trackor within fifteen (15) feet from the wire, or (b) in such a position that failure of same, with or without aload, would bring it within fifteen (15) feet from the centerline of the track or within íifteen (I 5) feet fromthe wire and requires the presence of the proper Railroad protection personneL.

If acceptable to the Chief Engineer's representative, a safety barrer (approved temporar fence orbarrcade) may be installed at fifteen (I 5) feet from centerline of track or overhead wire to afford thePennittee ami/or Contractor with a work area that is not considered fouling. Nevertheless, protectionpersonnel may be required at the discretion of the Chief Engineer's representative.

(7) Track Outages: Pennittee and/or Contractors shall verify the time and schedule of track outagesfrom Railroad before scheduling any of their work on, over, under, within, or adjacent to Railroad'sright-of-way. Railroad does not guarantee the availability of any track outage at any particular time.Pennillee and/or Contractors shall schedule all work to be perfonned in such a manner as not to interferewitli Railroad operations. Pennittee and/or Contractors shall use all necessary care and precaution to

avoid accidents, delay or interference witIi Railroad's trins or other propert.

(8) Demolition: During any demolition, Contrctor must provide horizontal and vertical shields,designed by a Professional Engineer registered in the state in which the work takes place. TIiese shieldsshall be designed in accordance with the Railroad's specifications and approved by tlie Railroad, so as toprevent any debris from falling onto the Railroad's right-of-way or other propert. A grounded temporarvertical protective barier must be provided if an existing vertical protective barer is removed duringdemolition. In addition, if any openings are left in an existing bridge deck, a protective fence must beerected at both ends of the bridge to prohibit unauthorized persons from entering onto the bridge.

Ballasted track strcture shall be kept free of all constrction and demolition debris.

(9) Equipment Condition: All equipment to be used in the vicinity of operating tracks shall be in"certified" first-class condition so as to prevent failures that might cause delay to trins or damage toRailroad's propert. No equipment shall be placed or put into operation near or adjacent to operatingtracks without first obtaining pennission from the Chief Engineer's representative. Under nocircumstances shall any equipment or materials be placed or stored within twenty-five (25) feet from thecenterline of an outside track, except as approved by the Site Specific Safety Work Plan. To ensurecompliance with this requirement, Pennittee and/or Contractors must establish a twenty-five (25) footfoul line prior to the start of work by either drving stakes, taping off or erecting a temporar fence, orproviding an alternate method as approved by the Chief Engineer's representative. Penniiiee and/orContractors will be issued warning stickers which must be placed in tlie operating cabs of all equipmentas a constant reminder of the twenty-five (25) foot clearance envelope.

(10) Storage of Materials and EQuipment: No material or equipment shall be stored on Railroad'spropert without first having obtained pennission from the Chief Engineer. Any such storage wil be onthe condition that Railroad will not be liable for loss of or damage to such materials or equipment fromany cause.

5

Page 21: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

/' If permission is granted for the storage of compressed gas cy linders on Railroad propert, they shall bestored a minimum of 25 feet from the nearest track in an approved lockable enclosure. The enclosureshall be locked when the Pennittee and/or Contractor is not on the project site.

(1 I) Condition of Railroad's Propert: Permittee and/or Contractors shall keep Railroad's property

clear of all refuse and debris from its operations. Upon completion of the work, Permittee and/orContractors shall remove from Railroad's propert all machinery, equipment, surplus materials,falsework, rubbish, temporary strctures, and other propert of Permittee and/or Contrctors and shallleave Railroad's propert in a condition satisfactory to the ChicfEngineer.

(12) Safety Training: All individuals, including representatives and employees of Permittee and/orContractors, before entering onto Railroad's propert or coming within twenty-five (25) feet of thecenterline of the track or energized wire shall first attend Railroad's Safety Orentation Class. The SafetyOrientation Class will be provided by Railroad's Safety Representative at Permittee's expense. A photo1.D. wil be issued and must be wom/displayed while on Railroad propert. All costs of complying withRailroad's safety training shall be at the sole expense of Permittee. Permittee and/or Contractors shall

appoint a qualified person as their Safety Representative. He/she shall continuously ensure that allindividuals comply with Railroad's safety requirements. All safety training records shall be maintainedwith the site specific work plan.

(i 3) No Charges to Railroad: It is expressly understood that neither these Specifications, nor anydocument to which they are attached, include any work for which Railroad is to be billed by Pennitteeand/or Contractors, unless Railroad gives a written request that such work be penormed at Railroad'sexpense.

\., /1

6

Page 22: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

ATTACHMENTBTemporary Permit to Enter Upon Property

INSURANCE REQUIREMENTSNATIONAL RAILROAD PASSENGER CORPORA nON (AMTRAK)

CHICAGO UNION STATION COMPANY (CUSCO)WASHINGTON TERMINAL COMPANY (WTC)

Revised as of February 2005

DEFINITIONS

In these Insurance Requirements "Railroad" or "Amtrak" shall mean National Railroad PassengerCorporation and as appropriate, its subsidiaries Chicago Union Station Company ("CUSCO") andWashington Terminal Company ("WTC"). "Contractor" shall mean the part identified as "Permittee" inthe Temporar Permit to Enter Upon Propert Agreement or the par with whom Amtrak has contractedin the Preliminary Engineerig Agreement or Force Account Agreement, as well as its offcers,employees, agents, servants, contractors, subcontractors, or any other person acting for or by pemiissionof Permittee or Contractor. "Oprations" shall mean activities of or work peifonned by Contractor."Agreement" shall mean the Temporary Permit to Enter Upon Propert Agreement, PreliminaryEngineering Agreement, or Force Account Agreement, as applicable.

INSURANCE

Contractor shall procure and maintain, at its sole cost and expense, the types of insurance specified below.Contractor shall evidence such coverage by submitting to Amtrak the original Railroad ProtectiveLiability Policy and certcates of insurance evidencing the other required insurance, prior to

commencement of Operations. All insurance shall be procured from insurers authorized to do business inthe jursdiction(s) where the Operations are to be peiformed. Contractor shall require all subcontractorsto car the insuance required herein, or Contractor may, at its option, provide the coverage for any or allsubcontractors, provided the evidence of insurance submitted by Contractor to Amtrak so stipulates. Theinsurnce shall provide for thirt (30) days prior written notice to Amtrak in the event coverage is

substantially changed, canceled or non-renewed. All insurance shall remain in force until all Operationsare satisfactorily completed (unless otherwise noted below), all Contractor personnel and equipment havebeen removed from Railroad propert, and any work has been formally accepted. Contractor's failure tocomply with the insurance requirements set fort herein shall constitute a violation of the Agreement.

Workers' ComDensation Insurance complying with the requirements of the statutes of thejursdiction(s) in which the Operations wil be pedormed, covering all employees of Contractor.Employer's Liability coverage with limits of not less than $1 million each accident or illness shall beincluded.

In the event the Operations are to be pedormed on or over navigable waterways, a Longshoremen andHarbor Workers' Compensation Act Endorsement and a Martime Coverage Endorsement are to be added,including coverage for wages, transportation, maintenance and cure.

Commercial General Liabiltv Insurance covering liability of Contractor witIi respect to all operationsto be pedormed and all obligations assumed by Contractor under the tenns of the Agreement. Products-completed operations, independent contractors and contractual liability coverages are to be included, withthe contrctual exclusion related to constrction/demolition activity within fifty (50) feet of the railroadand any Explosion/CollapselUnderground (X-C-D) exclusions deleted. The policy shall name NationalRailroad Passenger Corporation, as appropriate CUSCO or WTC, and all commuter agencies andrailroads that operate over the propert or tracks at issue as additional insureds with respect to theoperations to be peiformed. Coverage under this policy shall have limits of liability of not less than $2

7

Page 23: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

million each occurrence, combined single limit, for bodily injur (including disease or death), personalinjur and propert damage (including loss of use) liability.

Automobile Liabilitv Insurance covering the liability of Contractor arising out of the use of anyvehicles which bear, or are required to bear, license plates according to the laws of the jurisdiction inwhich they are to be operated, and which are not covered under Contractor's Commercial GeneralLiability insurance, The policy shall name National Railroad Passenger Corporation, as appropriateCUSCO or WTC, and all commuter agencies and railroads that operate over the propert or tracks at issueas additional insureds with respect to the operations to be pedonned. Coverage under this policy shallhave limits of liability of not less than $1 millon each occurrence, combined single limit, for bodilyinjury and propert damage (including loss of use) liability .

In the event Contractor or any subcontractor will be transporting and/or disposing of any hazadousmaterial or waste off of the jobsite, a MCS-90 Endorsement is to be added to this policy and the limits ofliability are to be increased to $5 million each occurence.

Railroad Protective Liabilitv (RR) Insurance covering the Operations pedonned by Contrctor or

any subcontractor within fifty (50) feet vertically or horizontally of railroad tracks. The current ISOOccurrence Foun (claims-made fonns are unacceptable) in the name of the National Railroad PassengerCorporation (and as appropriate CUSCO or WTC, and all commuter agencies and railroads that operateover the propert or tracks at issue) shall have limits of liability of not less than $2 millon eachoccurence, combined single limit, for Coverages A and B, for losses arsing out of injur to or death ofall persons, and for physical loss or damage to or destrction of propert, including the loss of usethereof A $6 million ammal aggregate shall apply. Additionally, Policy Endorsement CG 28 31 -Pollution Exclusion Amendment, is required to be endorsed onto the policy. Furter, "Physical Damageto Propert" as defined in tlie policy is to be deleted and replaced by the following endorsement:

"It is agreed that 'Physical Damage to Propert' means direct and accidental loss of or damage toall propert owned by any named insured and all propert in any named insured's care, custodyand control arising out of the acts or omissions of the contractor named on tlie Declarations."

The original RRP Liability Insurance Policy must be submitted to Amtrak prior to commencement ofOperations.

In the alternative, and upon Amtrak's approval, Contractor may elect to have Amtrak insure theOperations under its Blanet RRP Liability Insurnce Program. The premium, which shall be determinedby the rate schedule promulgated by the insurer in effect as of the effective date of the Agreement, shallbe prepaid by Contractor. In the event Contractor and Amtrak agree to insure the Oprations underAmtrak's RR Program, Contractor shall include the RR premium of$ in addition to the Permit

Fee, and send its check made payable to National Railroad Passenger Corporation to the individual setforth below prior to commencement of Operations.

All Risk Property Insurance covering physical loss or damage to all propert used in the pedormance ofthe Oprations. The policy shall have limits of liability adequate to cover all propert of Contractor(including personal propert of others in Contrctor's care, custody or control) and shall include a waiverof subrogation against Amtrak, as appropriate CUSCO or WTC, and all commuter agencies and railroadsthat operate over the propert or tracks at issue.

Contractor's Pollution Liabiltv Insurace covering tlie liability of Contractor arsing out of any suddenand/or non-sudden pollution or iipainent of the envionment, includig clean-up costs and defense, thatarse from the Operations of Contractor with National Railroad Passenger Corporation, as appropriateCUSCO or WTC, and all commuter agencies and railroads that operate over the propert or tracks at issuenamed as additional insureds. Coverage under this policy shall have lin1Ïts of liability of not less than $2millon each occurnce with no sunset clause.

8

Page 24: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

PoUution Le2a1 Liabiltv Insurance is required if any hazardous material or waste is to be transported ordisposed of off of the jobsite. Contrctor, its subcontrctor or transporter, as well as the disposal siteoperator, shall maintain this úisuance. Contractor shall designate the disposal site. and must provide acertficate of insurance from the disposal facility to Amtrak. TIie policy shall name National RailroadPassenger Corporation, as appropriate CUSCO or WTC, and all commuter agencies and railroads thatoperate over the propert or tracks at issue as additional insureds, with limits of liability of not less than $2milion per claim,

Further, any additional insurance coverages, permits, licenses and other fOIDIS of documentation requiredby the United States Department of Transportation, the Environmental Protection Agency and/or relatedstate and local laws, rules and regulations shall be obtained by Contractor.

Professional Liabilty Insurance covering the liability of Contractor for any and all errors or omissionscommitted by Contractor in the pedoIDiance of the Oprations, regardless of the type of damages. Thecoverage shall be maintained during the term of the Operations, and for at least three (3) years followingcompletion thereof. The policy shall have limits of liability of not less tlian $2 milion per claim and inthe anual aggregate. The policy may contain a deductible of a maximum of two hundrd fifty thousanddollars ($250,000), but in such case the deductible is the sole responsibility of Contractor, and no portionof such deductible is the responsibility of Amtrak.

Contractor may elect to satisfY this requirement tlrrough the addition of endorsement CG2279 "IncidentalProfessional Liability" to its CGL policy.

Claims-Made Insurance - If any liability insurance specified above shall be provided on a claims-madebasis, then in addition to coverage requirements above, such policy shall provide tliat:

1. The retroactive date shall coincide witli or precede Contractor's start of Operations (includigsubsequent policies purchased as renewals or replacements);

2. TIie policy shall allow for the reporting of circumstances or incidents that might give rise to future

claims;

3. Contractor wil use its best efforts to maintain similar insurance under the same terms and

conditions that describe each type of policy listed above (e.g., Commercial General Liability,Professional Liability) for at least thee (3) years following completion of the Operations; and

4. If insurance is terminated for any reason, Contractor will purchase an extended reporting provision

of at least two (2) years to report claims arising from Operations.

Contractor shall furish evidence of insurance as specifed above at least :fIfeen (15) days prior tocommencing Operations. THESE DOCUMENTS SHALL INCLUDE A DESCRIPTION OF THEPROJECT AND THE LOCATION ALONG THE RAILROAD RIGHT -OF-WAY (typically given bymilepost designation) IN ORDER TO F ACILIT ATE PROCESSIN G. The fifteen (J 5) day advancenotice of coverage may be waived by Amtrak in situations where such waiver wil benefit Amtrak, butunder no circumstaces wil Contractor begin Operations without providing satisfactory evidence ofinsurance as approved by Amtrak. Such evidence of insurance coverage shall be sent to:

Director Project Initiation & DevelopmentNational Railroad Passenger Corporation30t Street Station, Mail Box 64

Philadelphia, PA 19104-2817

9

Page 25: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

I&C Specilicaiion SystemwideRev I 08/07/0 I

SECTION 01 141A - SAFETY AND PROTECTION OF RAILROAD TRAFFIC AND PROPERTY

PART I - GENERAL

l. SCOPE

A. This specification describes the safety procedures and protection provisions for Contractors andPermttees entering and working upon railroad property.

B. Use of this specification is as required by Amtrak, as described in Amtrak Engineering PracticeEP3014.

1.2 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and SupplementaiConditions and other Division 1 Specification Sections, apply to this Section.

1.3 DEFfNITIONS

A. CHIEF ENGINER: Amtrk Vice President, Chief Engineer

B. RAILROAD: National Railroad Passenger Corporation (Amtrak), and/or the duly authorizedrepresentative

C. ENGINERfNG PRACTICE: Amtrak Engineering Practices establish a system of uniformpractices, notices and instructions for the Amtrak Engineering Departent, providing current,permanent and temporary, deparmental procedures and policies.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 PRE-ENTRY MEETfNG

A. Before entr of Permittee and/or Contractors onto Railroad's property, a pre-entry meeting shallbe held at which time Permittee and/or Contractors shall submit for written approval of theChief Engineer, plans, computations and a detailed description of proposed methods foraccomplishing the work, including methods for protecting Railroad's traffic. Any such writtenapproval shall not relieve Permttee and/or Contractor of their complete responsibility for theadequacy and safety of their operations. .

3.2 RULES, REGULATIONS AND REQUIREMENTS

SAFETY AND PROTECTION OF RAILROAD TRAFFIC AND PROPERTY OII4IA-1

Page 26: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

~.

I&C Specilication SystemwideRev I 08/07/01

A. Railroad traffc shall be maintained at all times with safety and continuity, and Permittee and/orContractors shall conduct their operations in compliance with all rules, regulations, andrequirements of Railroad (including these Specifications) with respect to any work performedon, over, under, within or adjacent to Railroad's property. Permittee and/or Contractors shall beresponsible for acquainting themselves with such rules, regulations and requirements. Anyviolation of Railroads safety rules, regulations, or requirements shall be grounds for theimmediate suspension of the Permittee and/or Contractor work, and the re-training of allpersonnel, at the Permittee's expense.

3.3 MAINTENANCE OF SAFE CONDITIONS

A. If tracks or other property of Railroad are endangered during the work, Permttee and/or

Contractor shall immediately take such steps as may be directed by Railroad to restore safeconditions, and upon failure of Permttee and/or Contractor to immediately carr out suchdirection, Railroad may take whatever steps are reasonably necessaiy to restore safe conditions.All costs and expenses of restoring safe conditions, and of repairing any damage to Railroad'strains, tracks, right-of-way or other property caused by the operations of Permttee and/orContractors, shall be paid by Permttee.

3.4 PROTECTION IN GENERAL

A. Permttee and/or Contractors shall consult with the Chief Engineer to determne the type andextent of protection required to insure safety and continuity of railroad traffc. Any Inspectors,Track Foremen, Track Watchmen, Flagman, Signalmen, Electric Traction Linemen, or otheremployees deemed necessar by Railroad, at its sole discretion, for protective services shall beobtained from Railroad by Permttee and/or Contractors. The cost of same shall be paid directlyto Railroad by Pennttee. The provision of such employees by Railroad, and any other

precautionaiy measures taken by Railroad, shall not relieve Pennttee and/or Contractors fromtheir complete responsibility for the adequacy and safety oftheir operations.

:

3.5 PROTECTION FOR WORK NEAR ELECTRIFIED TRACK OR WIRE

A. Whenever work is performed in the vicinity of electrified trcks and/or high voltage wires,paricular care must be exercised, and Railroad's requirements regarding clearance to be

maintained between equipment and tracks and/or energized wires, and otherwise regardingwork in the vicinity of electrified tracks, must be strctly observed. No employees or equipmentwill be permtted to work near overhead wires, except when protected by a Class A employee ofRailroad. Permittee and/or Contractors must supply an adequate length of groundingcable (4/0 copper with approved clamps) for each piece of equipment working near oradjacent to any overhead wire.

3.6 FOULING OF TRACK OR WIRE

A. No work wil be penntted within twenty-five (25) feet of the centerline of track or theenergized wire or have potential of getting within twenty-five (25) feet of track wire without theapproval of the Chief Engineer's representative. Permttee and/or Contractors shall conduct

their work so that no par of any equipment or material shall foul an active track or overhead

SAFETY AND PROTECTION OF RAILROAD TRAFFIC AND PROPERTY Ol141A - 2

Page 27: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

I&C Spt:citication SystemwideRev I 08/07/01

wire without the written pennssion of the Chief Engineer's representative. When Pennitteeand/or Contractors desire to foul an active track, they must provide the Chief Engineer'srepresentative with their site-specific work plan a minimum of twenty-one (2 i) working days inadvance, so that, if approved, arrangements may be made for proper protection of Railroad.Any equipment shaH be considered to be fouling a track or overhead wire when located (a)within fi fteen (15) feet from the centerline of the track or within fifteen (\ 5) feet from the wire,or (b) in such a position that failure of same, with or without a load, would bring it withinfifteen (15) feet from the centerline of the track or within fifteen (15) feet from the wire andrequires the presence of the proper Railroad protection personneL.

B. If acceptable to the Chief Engineer's representative, a safety barrier (approved temporary fence

or barrcade) may be installed at fifteen (15) feet from centerline of track or overhead wire toafford the Pennittee and/or Contractor with a work area that is not considered fouling.

Nevertheless, protection personnel may be required at the discretion of the Chief Engineer'srepresentative.

3.7 TRACK OUTAGES

A. Pemuttee and/or Contractors shall verify the time and schedule of track outages from Railroadbefore scheduling any of their work on, over, under, within, or adjacent to Railroad's

right-of-way. Railroad does not guarantee the availability of any track outage at any particulartime. Pemuttee and/or Contractors shall schedule all work to be performed in such a manner asnot to intedere with Railroad operations. Pemuttee and/or Contractors shall use all necessarcare and precaution to avoid accidents, delay or interference with Railroad's trains or otherpropert.

3.8 DEMOLITION

A. During any demolition, the Contractor must provide horizontal and vertical shields, designed bya Professional Engineer registered in the state in which the work takes place. These shieldsshall be designed in accordance with the Railroad's specifications and approved by the Railroad,so as to prevent any debris from falling onto the Railroad's right-of-way or other propert. Agrounded temporary vertical protective barrier must be provided if an existing verticalprotective barrier is removed during demolition. In addition, if any openings are left in anexisting bride deck, a protective fence must be erected at both ends of the bridge to prohibitunauthorized persons from entering onto the bridge.

3.9 EQUIPMENT CONDITION

A. All equipment to be used in the vicinity of operating trcks shall be in "certified" first-classcondition so as to prevent failures that might cause delay to trains or damage to Railroad'sproperty. No equipment shall be placed or put into operation near or adjacent to operatingtracks without first obtaining pemussion from the Chief Engineer's representative. Under nocircumstances shall any equipment or materials be placed or stored within twenty-five(25) feet from the centerline of an outside track, except as approved by the Site SpecificSafety Work Plan. To insure compliance with this requirement, Permittee and/or Contractorsmust establish a twenty-five (25) foot foul line prior to the start of work by either drivingstakes, taping off or erecting a temporary fence, or providing an alternate method as approved

SAFETY AND PROTECTION OF RAILROAD TRAFFIC AND PROPERTY 01I41A-3

Page 28: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

c'

I&C Specification SystemwideRev i 08/07/0 1

by the Chief Engineer's representative. Permittee and/or Contractors will be issued warning

stickers which must be placed in the operating cabs of all equipment as a constant reminder ofthe twenty-five (25) foot clearance envelope.

3.10 STORAGE OF MA TERJALS AND EQUIPMENT

A. No material or equipment shall be stored on Railroads property without first having obtainedpermission from the Chief Engineer. Any such storage will be on the condition that Railroadwill not be liable for loss of or damage to such materials or equipment from any cause.

3.11 CONDITION OF RAILROAD'S PROPERTY

A. Permttee and/or Contractors shall keep Railroads property clear of all refuse and debris fromits operations. Upon completion of the work, PeITttee and/or Contractors shall remove fromRailroads property all machinery, equipment, surlus materials, falsework, rubbish, temporarystructures, and other propert of the PeITttee and/or Contractors and shall leave Railroadsproperty in a condition satisfactory to the Chief Engineer.

3.12 SAFETY TRAINING

A. All individuals, including representatives and employees of the Permittee and/or Contractors,

before entering onto Railroad's property or coming within twenty-five (25) feet of thecenterline of the track or energized wire shall first attend Railroads Safety Contractor/LeaseeEmployee Training Class. The Safety Orientation Class will be provided by Railroads SafetyRepresentative at Permittee's expense. A photo J.D. will be issued and must be worndisplayedwhile on Railroad property. All costs of complying with Railroads safety training shall be atthe sole expense of Permttee. Permttee and/or Contractors shall appoint a qualified person astheir Safety Representative. He/she shall continuously assure that all individuals comply withRailroads safety requirements. All safety training records shall be maintained with site specificwork plan.

3.13 NO CHARGES TO RAILROAD

A. It is expressly understood that neither these Specifications, nor any document to which they areattached, include any work for which Railroad is to be billed by Permittee and/or Contractors,únless Railroad gives a written request that such work be performed at Railroad's expense.

END OF SECTION Ol141A

SAFETY AND PROTECTION OF RAILROAD TRAFFIC AND PROPERTY 01141A-4

Page 29: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

I&C Specilìcation SystemwideRev I 12/15/05

SECTION OJ 142A - SUBMISSION DOCUMENTATION REQUIRED FOR AMTRA REVIEW ANAPPROV AL OF PLANS FOR BRIDGE ERECTION, DEMOLITON AN OTHER CRA/ HOISTINGOPERATIONS OVER RALROAD RlGHT-OF-WA Y

PART I - GENERAL

i. SCOPE

A. Amtrak requires that a site-specific work plan for accomplishing hoisting operations be prepared forevery applicable project, and for each type of lift on a project.I. The plan shall demonstrate adherence to Amtrak safety rules.

2. The plan shall demonstrate constrctibiJjty.

3. The plan shall minimize impact to rail operations.

4. The approved plan will provide the basis for field inspection! verification of the actual work.

B. Preparation, review and approval of the Crane/ Hoisting site-specific work plan does not relieve theContractor from meeting other Amtrak requirements for adequate planning and documentation ofproposed work procedures within the Right-of-Way of the railroad..

C. Current Amtrak satèty rules shall be adhered to in every respect.

D. Use of this specification is as required by Amtrak, as described in Amtrak Engineering Practice EP30J4.

,., " 1. RELATED DOCUMNTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions andother Division J SpecItìcation Sections, apply to ths Section.

1.3 DEFINITIONS

A. CHIEF ENGINEER: Amtrak Vice President, Chief Engineer

B. RAILROAD: National Railroad Passenger Corporation (Amtrak), and/or the duly authorizedrepresentative

C. ENGINERING PRACTICE: Amtrak Engineering Practices establish a system of unform practices,notices and instrctions for the Amtrak Engineerig Departent, providing curent, permanent andtemporary, deparmental procedures and policies.

1.4 SUBMISSION REQUlRE:tNTS

A. Unless otherwise directed in the Contract, the Contractor shall submit five sets of plans and calculationsto the authorized representative of the Chief Engineer, Structures, whose name and address will beprovided at the project pre-construction meeting.

B. Submitted calculations and plans shall be signed and sealed by a Professional Engineer, registered in theState in which the work will be performed.

SUBMISSION DOCUMNTATION... CRA/ HOISTING OPERATIONS... 01l42A - 1

Page 30: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

I&C Specification SystemwideRev I I 2/J 5105

C. The Contractor shall revise and resubmit plans and calculations as many times as necessary, until acomplete and correct site-specific work plan for crane! hoisting operations has been approved.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 THE CONTRCTOR SHALL PROVIDE, AT A MINIMUM, THE FOLLOWING INFORMTIONFOR REVIEW AN APPRO V AL BY AMTRAK ENGINEERING STRUCTURES:

A Plan view showing location(s) of cranes, operating radii, with delivery and/or disposal locations shown.Provide all necessary dimensions for locating the elements of the plan.

B Plans and computations showing the weight of the pick.

c. Crane rating sheets, demonstrating that cranes are adequate tòr 150% of the calculated pick weight. Thatis, the cranes shall be capable of picking I50% of the load, while maintaining normal, recommendedfactors of safety. The adequacy of the crane for the proposed pick shall be detennined by using the

manufactuer's published crane rating chart and not the maximum crane capacity. Crane and boomnomenclatue is to be indicated.

D. Calculations demonstrating that slings, shackles, lifting beams, etc. are adequate for 150% of thecalculated pick weight.

E. Location plan showing obstructions, indicating that the proposed swing is possible. "Walking" of loadusing two cranes will not be permitted. Rather, multiple picks and repositioning of the crane may bepennitted to get the load to the needed location tòr the final pick, if necessary.

F. Data sheet listing types and sizes of slings and other connecting equipment. Include copies of catalogcuts for specialized equipment Detail attachment methods on the plans.

G. A complete procedure, indicating the order of lifts and any repositioning or re-hitching of the crane orcranes.

H. Temporary support of any components or intermediate stages, as may be required.

i. A time schedule of the varous stages, as well as a schedule for the entire lifing process.

END OF SECTION 01 142A

SUBMISSION DOCUMNTATION... CRANE! HOISTING OPERATIONS... 01l42A - 2

Page 31: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

LEGEND

10'-0"

ZONE 1 - ABOVE AND OUTSIOE THE THEORETCAL

I::':,:', RAILROAD EMBANKMENT LINE.

ZONE 2- FARTHER THAN 10 FEET FROM THE

r; CENTERLINE OF TRACK, BELOW THETHEORETICAL RAILROAD EMBANKMENTLINE AND ABOVE THE THEORETICALUNDERGROUND TRACK DISTURBANCELINE.

ZONE 3- BELOW AND INSIDE OF THE THEORETICAL

I.::'.-;::;.~ UNDERGROUND TRACK DISTURBANCELINE.

TRACK

EN~OFTIE BOTTOM

1. OF TIE GROUND LINE

\'. ..f

....:~; ;';, :.::'. :;. 'ce." . :.':"'. .~;~ '.:': .:.: '.' .

::X7g:~;~'~~~!~~.:f~)S;~(: ."::~. .~:: .::. /"T~È~R~lèAL' .~. ;.... ..: ..,.: '~..

.:". ":,:': UNDERGROUND~' :::.. . '.- ... .' .. '. .,~ ~:'-:. . :.~TRACK DISTURBANCE ..'''.'''- ... .:' .: ..:.,~.. LINE. : '. ,. "'. . .~..- . ,..- ~'~:... .... ,oo ......:. .: .... .. ......:... .~.." 1 ,

: .:: ..;:.... ...: : ."'::-."':.. r ..-.... ..:.. ..:....... :..: ':':'.' ... .:..:- .':..::. ','.. 1 -.... ZONE.::.'. ....:... ............ .. ..... "'..::"' ~......"~ ._."'

... ..... ... .( ZONE 3 J. .. '. .'. h.

". :":";:~:~.:i~;::~~::..~;:;:.Y:;Y':¡:§~;~:;.':::.',,~~ _....~.. ..- ... .: .... ::"' .."':

. c: \ \ \ \ \ \ \ \ m~ \ ~ ~\J ~ ~ ~ \~ S. \ \ \ \ \ \ r

.. :::: .:...... :.:.. ..::.': THEORETICAL

i..~:::::::::::::~:::.: RAILROAD1 '~:::::::::::.:: EMBANKMENT

1 1/2'" '~::::::.::::ltNE

'.:.\/:

NORMAL REQUIREMENTS FOR SHEET PILINGADJACENT TO TRACK

G) EXCAVATIONS WITHIN ZONE 1 - ABOVE AND OUTSIDE OF THE THEORETICAL RAILROADEMBANKMENT LINE - DO NOT NORMALLY REQUIRE SHEETING TO PROTECT RAILROADROAD BED. SHEETING MAY BE REQUIRED FOR OTHER REASONS.

~ EXCAVATIONS WHOSE BOTTOMS EXTEND INTO ZONE 2 REQUIRE SHEETING, BUT THESHEETING MAY NORMALLY BE PULLED AFTER THE EXCAVATION HAS BEEN BACKFILLED.

G) EXCAVATtONS WHOSE BOTTOMS EXTEND INTO ZONE 3 WILL NORMALLY REQUIRE THESHEETING TO BE LEFT IN PLACE AND CUT-OFF PER REQUIREMENTS.

Amk~ Office of Chief EngineerSTRUCTURES

30 sr.:'li.~~~P~=~ \9\64

SKETCH 1SPEC. 02261A - REV.

f1 NoDeign No: 351Sh No. 1 of 1.,.. __ i,-l........-i ..".._ i-"-~~l-~Ð................ l- _ .. .. _.. .. ...." .. l-_.. ............."........_..........~""i-_" ii 11..s- SK-1Õ

Da 6/06/01 ~

Page 32: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

"

I&C SpecilicationSystemwide

Rc\' I 08/07/01

SECTION 01520A - REQUIREMENTS FOR TEMPORARY PROTECTION SIIELDS FOR DEMOLITIONAND CONSTRUCTION OF OVERHEAD BRIDGES AND OTHER STRUCTURES

PART I - GENERAL

i.

1.

L3

1.4

SCOPE

A. This engineering practice describes items to be included in the design and construction of temporaryprotection shields for construction overhead and near to Amtrak tracks.

B. Use of this specification is as required by Amtrak, as described in Amtrak Engineering Practice EP3014.

RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions andother Division I Specification Sections, apply to this Section.

DEFINITIONS

A. CHIEF ENGINEER: Amtrak Vice President, Chief Engineer

B. RAILROAD: National Railroad Passenger Corporation (Amtrak), and/or the duly authorizedrepresentative

c. ENGINEERING PRACTICE: Amtrak Engineering Practices establish a system of uniform practices,notices and instructions for the Amtrak Engineering Department, providing current, permanent andtemporary, departmental procedures and policies.

SUBMISSION REQUIREMENTS

A. Unless otherwise directed in the Contract, the Contractor shall submit five sets of plans and calculationsto the authorized representative of the Chief Engineer, Structures, whose name and address will beprovided at the project pre-construction meeting.

B. Submitted calculations and plans shall be signed and sealed by a Professional Engineer, registered in theState in which the work will be performed.

c. The Contractor shall revise and resubmit plans and calculations as many times as necessary, until acomplete and correct site-specific work plan for crane/ hoisting operations has been approved.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3. I CONTRACTORS WORKING ON OVERHEAD OR NEARBY DEMOLITION AND/ORCONSTRUCTION ADJACENT TO AMTRAK TRACKS, SHALL CONFORM TO THE FOLLOWING

...TEMPORARY PROTECTION SHIELDS... 01520A - I

Page 33: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

'"

I&C Spci:ilication SystemwideRev I 08/07/0 I

DESIGN AND CO:\STRUCTION REQuiRE~IENTS FOR TE:-IPORARY PROTECTIONSIIIELDIl\G:

A. The Contractor shall maintain a specified level of protection to railroad facilities. during demolition andconstruction acti\'ities that occur overhead and nearby Amtrak tracks, as shown on the Contract Plans, asdetailed in the Contract Specitications, and as described below,

B. Prior to the stan of construction, the Contractor shall submit to Amtrak for review and approval, detailed,

site specific plans for temporary protection shields. The plans will be reviewed as to the methods oferection. and as to whether or not the proposed installation will provide the required level of protection.No construction shall proceed until the Contractor has received written approval of the Contractor'scomplete, site specific plans, from Amtrak.

C. The Contractor shall design the protection shields to conform to all applicable and governing federal,state and local laws and regulations.

D. Drawings for the proposed temporary protection shields shall be signed and sealed by a LicensedProfessional Engineer. Complete design calculations, clearly referenced to the drawings, and easy toreview, shall be provided with submission of drawings.

E. Protection shields shall be designed for the following, minimum load and size criteria.

I. The horizontal shield design liveload on horizontal surfaces shall be the greater of a minimum of

100 pounds per square foot (pst) (SOOO Pascals) or the anticipated liveload to be produced by theContractor's anticipated operations. When determining the appropriate design live load, thedesigner shall consider factors such as the physical capacity of proposed debris-catching platformsto retain materials, and the type of equipment the platforms might support. Positive means ofdemolition and construction controls shall be provided to assure that debris that may collect on theshield will not exceed the design live load. The horizontal protection shield, in plan view, shallcover no less than the area directly over the tracks plus ten feet minimum beyond the centerline ofthe outermost tracks.

2. The vertical shield shall be designed to carry a minimum 30 psf(ISOO Pascals) allowance for windload. The vertical shield shall extend a minimum of 6'-6" (19S0 milimeters) above the top of theadjacent surface, such as curb or sidewalk. Anti-climb wings shall be installed at each end, asnecessary, to restrict access to the railroad property.

F. The vertical and horizontal clearance envelopes required for maintenance of railroad operations, shall beindicated on the site specific work plans. These clearances are subject to review and approval by Amtrak.If applicable, both temporary and permanent envelopes shall be indicated on the plans. The temporaryprotection shields shall be installed outside the limits of these minimum vertical and horizontal clearancesshown on the site specific work plans.

G. In electrified territory, temporary protection shields shall be bonded and grounded.

H. Temporary protection shields shall be designed and constructed to prevent dust, debris, concrete,form work, paint, tools. or anything else from fallng onto the railroad properly below.

L The temporary protection shields shall be attached to the structure in accordance with site specific workplans submitted by the Contractor and approved by Amtrak. Drilling in structural members and weldingwill generally not be permitted in members that are scheduled to remain in place in the reconstructedstructure. For existing members scheduled for demolition or for later reconstruction, any proposedattachment shall be designed with consideration of potential existing, deteriorated conditions.

J, The Contractor shall provide the Amtrak on-site representative, for review and approval prior to any

construction activity in the effected area, a proposed construction schedule for the installation,maintenance and removal of the temporary protection shields.

...TEMPORARY PROTECTION SHIELDS... 0lS20A - 2

Page 34: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

.8

. ,-:

I&C Sp.:cilìcationSyst.:mwide

R.:v I 08/07/0 I/~. ''\

K. Th.: temporary protection shields shall be installed prior to th.: start of any oth.:r work over th.: railroad inth.: effected areas. No construction shall proceed until th.: Amtrak on-sit.: representative reviews and

approves the Contractor's instalkd protection. Before proceeding with the work. Amtrak must besatisfied, in its sole judgment. that sufficient protection has been provid.:d to proceed with the work.

L. The Contractor shall install and remove temporary protection shields only when an Amtrak representative

is on-site.

M. The Contractor shall not install or remove temporary protection shields during train operations.

N. Temporary protection shields shall remain in place for the duration of construction activities over andnearby the railroad in the effected areas. The Contractor may remove temporary construction only afterapproved by Amtrak on-site representatives.

O. Where site specific conditions impose insurmountable restrictions to the design of temporary constructionconforming to the limitations listed above, the design of temporary construction shall be developed inclose coordination with Amtrak design review personneL. The Chief Engineer, Structures shall providefinal approval of temporary construction that does not conform to the above limitations.

END OF SECTION 01520A

...TEMPORARY PROTECTION SHIELDS... 01520A - 3

Page 35: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

.'

/..

I&C Specilication SystemwideRev 2 08/07/0 I

SECTION 02261A - REQUIREMENTS FOR TEMPORARY SHEETING AND SHORING TOSUPPORT AMTRAK TRACKS

PART I - GENERAL

l. SCOPE

A. This engineering practice describes items to be included in the design and construction oftemporary sheeting and shoring construction adjacent and proximate to Amtrak tracks.

B. Use of this specification is as required by Amtrak, as described in Amtrak Engineering PracticeEP3014.

I .2 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and SupplementaryConditions and other Division 1 Specification Sections, apply to this Section.

1.3 DEFINITIONS

A. CHIEF ENGINEER: Amtrak Vice President, Chief Engineer

B. RAILROAD: National Railroad Passenger Corporation (Amtrak), and/or the duly authorizedrepresentati ve

C. ENGINEERING PRACTICE: Amtrak Engineering Practices establish a system of uniformpractices, notices and instructions for the Amtrak Engineering Departent, providing current,permanent and temporary, departmental procedures and policies.

1.4 SUBMISSION REQUIREMENTS

A. Unless otherwise directed in the Contract, the Contractor shall submit five sets of plans andcalculations to the authorized representative of the Chief Engineer, Structures, whose name andaddress will be provided at the project pre-construction meeting.

B. Submitted calculations and plans shall be signed and sealed by a Professional Engineer,registered in the State in which the work will be performed.

C. The Contractor shall revise and resubmit plans and calculations as many times as necessary,until a complete and correct site-specific work plan for crane/ hoisting operations has beenapproved.

PART 2 - PRODUCTS (Not Used)

...TEMPORARY SHEETING AND SHORING TO SUPPORT AMTRAK TRACKS 02261A - I

Page 36: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

I&C Specilicaiion SystemwideRe\. :2 08/07/0 I

PART 3 - EXECUTION

3.1 CONTRACTORS INSTALLING TEMPORARY CONSTRUCTION SHEETING ANDSHORING TO SUPPORT AMTRAK TRACKS SHALL CONFORM TO THE FOLLOWING:

A. Footings for all piers, columns, walls, or other facilities shaIl be located and designed so thatany temporary sheeting and shoring for support of adjacent track or tracks during construction,will not be closer than toe of ballast slope. The dimension from gage of rail to toe of ballast,along tangent track, is 7'-5"; see dimensions on Track standard plans for curved trackdimensions. .

B. USE OF SHEETING: When support of track or tracks is necessary during construction of theabove-mentioned facilities, interlocking steel sheeting, adequately braced and designed to carCooper E80 live-load plus 50 percent impact aIlowance is required. Soldier piles and laggingwiIl be permtted for track support ONL Y when required penetration of steel sheet piling cannotbe obtained, due to site-specific conditions that make steel sheet piling placement impracticable,in the opinion of the authorized, Amtrak design review engineer.i. For usual soil conditions and limited excavations, sheeting is required when the near-

track excavation extends beneath or nearer to the track than the Theoretical RailroadEmbankment Line. The Theoretical Railroad Embankment Line is defined as a line thatstarts at grade, ten foot from the centerline of the outer track, and extends downward,away from the track, at a slope of 1-1/2 horizontal to one verticaL.

2. For special soil conditions, such as soft organic soils and rock conditions, and for unusual

excavation conditions, temporary supports for excavations may be necessary even whenthe limits fall beyond the Theoretical Railroad Embankment Line, requiring site specificanalysis by a professional, geotechnical engineer.

3. See Sketch SK-l, "Normal Requirements for Sheet Piling Adjacent to Tracks".

C. Exploratory trenches, three feet deep and 15 inches wide in the form of an "H", with outside

dimensions matching the proposed outside dimensions of sheeting, shall be hand dug, prior toplacing and driving the sheeting, in any area where railroad or utility underground instaIlationsare known or suspected. These trenches are for exploratory purposes only, and shaIl bebackfilled and immediately compacted, in layers. This work shall be performed only in the

presence of a railroad inspector.

D. Absolute use of track is required while driving sheeting adjacent to running track. Track usageshaIl be prearrnged per standard procedures, through the Amtrak project representative.

E. Cavities adjacent to sheet piling, created by pile driving, shall be filled with sand, and any

disturbed ballast shall be restored and tamped immediately.

F. Sheet piling cutoffs

1. During constrction, sheeting shall be cut off at an elevation no higher than the top of tie.2. At the completion of construction activities involving the use of sheet piling, sheet piling

may be puIled if there will be no adverse impact to the railroad track support bed, asdetennined by the Amtrak site engineer. This will generaIly be pennitted when both ofthese conditions are met:a. the sheeting face is at least ten feet distant from the centerline of track, and

b. the bottom of the excavation that the sheeting supported prior to backfilling, does

not faIl within an assumed influence zone under the tracks. The assumed influence

...TEMPORARY SHEETING AND SHORING TO SUPPORT AMTRAK TRACKS 0226lA - 2

Page 37: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

..

I&C Specification SystemwideRe\' 2 08/07/01

3.

zone is defined as the area, as seen in cross-sectional view, falling beneath theTheoretical Underground Track Disturbance Line. This line is defined as a linethat starts at the end and bottom of the ties. and extends from the track outward anddownward at a one-to-one (45-degree) slope.

Sheet piling that is to be left in-place, shall be cut off belO\v the ground linea. at least eighteen inches below final ground line at the sheeting, and

b. no higher than 24 inches below the elevation of the bottom of the nearest tiesSee Sketch SK- i, '"Normal Requirements for Sheet Piling Adjacent to Tracks".4.

G. The excavation adjacent to the track shall be covered, ramped and protected by handrails,barrcades and warning lights, as required by applicable safety regulations, and as directed byAmtrak.

H. Final backflling of excavation shall conform to project specifications.

L The Contractor shall provide Amtrak with a detailed schedule of proposed constructionoperations, detailing each step of the .proposed temporary constrction operations in proximityto Amtrak tracks, so that Amtrak may review and approve the proposed operations, and mayproperly inspect and monitor operations.

J. Drawings for the proposed temporary sheeting and shoring shall be signed and sealed by a

Licensed Professional Engineer. Complete design calculations, clearly referenced to the'drawings, and easy to review, shall be provided with submission of drawings.

K. Where site specific conditions impose insurountable restrictions to the design of temporaryconstruction confonnng to the limitations listed above, the design of temporary constrctionshall be developed in close coordination with Amtrak design review personneL. The ChiefEngineer, Strctures shall provide final approval of temporary construction that does not

conform to the above limitations.I. When Amtrak grants approval for sheeting closer than standard minimum clearances, the

Contractor shall develop a surey plan, if not already required by the project, for theadjacent tracks, to be conducted prior to, during, and after the temporary sheeting

construction operations. If settlement is detected, constrction operations shall be

suspended until the track has been returned to its initial condition, and stabilized, asdetermined by the Amtrak project site representative.

2. The Contractor shall stockpile ten (10) tons of approved ballast at the project site, andmaintain that amount in ready reserve, to allow for the possible need to restore trackprofile.

L. Particular care shall be taken in the planning, design and execution of temporary construction,

as relates to railroad slope protection and drainage facilities. Erosion and sediment control bestmanagement practices shall be designed and employed, as approved by Amtrak. Anyunintended disruption to railroad drainage facilities, caused by the temporary construction, shallbe promptly remedied, as directed by the Engineer, solely at the Contractor's cost.

M. The following Information Sketch is attached:

I. Figure No. SK- I: Nonnal Requirements for Sheet Piling Adjacent to Track

END OF SECTION 02261 A

...TEMPORARY SHEETING AND SHORING TO SUPPORT AMTRAK TRACKS 02261A - 3

Page 38: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

..

10'-0"

LEGEND

ZONE 1 - ABOVE AND OUTSIDE THE THEORETICAL

c: RAILROAD EMBANKMENT LINE.

ZONE 2- FARTHER THAN 10 FEET FROM THE

r; CENTERLINE OF TRACK, BELOW THETHEORETICAL RAILROAD EMBANKMENTLINE AND ABOVE THE THEORETICALUNDERGROUND TRACK DISTURBANCELINE.

ZONE 3- BELOW AND INSIDE OF THE THEORETICAL

I:'::":,:::.:~l UNDERGROUND TRACK DISTURBANCELINE.

TRACK

...~:::': ~~..:: :.~:~ .'. ..:~ '..::.r.. / .~:..~. ::.~.: .~- .~~~,'~ ..: ::.... : .... :

.' : ~.~.../.: '.':'::'~: :.;/;.~ ;::'.;~ ~'-':-./:j:,~,~:.~~:":. ".. .- .:. "L ,,".

.. "; .. # .......... .. ." - - . ...... ....:... -" 0. ~ .:~ ". .'~.

: .:.:....¡:.: '~'.:" ..\~E~R.~TICAL. '-. ;:." '.. .,"': '.:.:". .. .:-:. .: UNDERGROUND -' : ::-.' ... ...... "" .... ..'" ::'_" . ::'TRACK DISTURBANCE ..:.;..-... ': :' .

:. .:.:..,~.. LINE - .: . . . .,. .... '.. .:.... . -.,,- j'''. . . ". .' .. .' . ., . 'L.

;' ::..:.;..:......-:./.: :.::'._:~' -:.:: "-~". ;..~:......:..:.:.:.~.. ::: .... , ..... ZONE

. ::..". ,:.,.:". ......C ZONE"3 )-::. '...r".,' ....:: ..', .': :L: ::-".:.::::.:~ .'::. ........ :.;" ..:. : :~::..:'.:::..,::':.".''';~:_':~'-._'.~:..' ..

- :........ .~. ........ -." .....0 .. -" :.. :." .... ....~. 0.......... ';'.. .: -:. ".:- :,..::'.:. ~..~:.' .~......:.,. :'. :..... ..~.:.. .':. .:.....

.. .-'. .. ...... .......: ...... 0"" .. .. I- '0" ...........

GROUND LINE

-- .I

NORMAL REQUIREMENTS FOR SHEET PILINGADJACENT TO TRACK

CD EXCAVATIONS WITHIN ZONE 1 - ABOVE AND OUTSIDE OF THE THEORETICAL RAILROADEMBANKMENT LINE. - DO NOT NORMALLY REQUIRE SHEETING TO PROTECT RAILROADROAD BED. SHEETING MAY BE REQUIRED FOR OTHER REASONS.

ø EXCAVATIONS WHOSE BOTIOMS EXTEND INTO ZONE 2 REQUIRE SHEETING, BUT THESHEETING MAY NORMALLY BE PULLED AFTER THE EXCAVATION HAS BEEN BACKFILLED.

~ EXCAVATIONS WHOSE BOTIOMS EXTEND INTO ZONE 3 WILL NORMALLY REQUIRE THESHEETING TO BE LEFT IN PLACE AND CUT-OFF PER REQUIREMENTS.

Amtrak~F1 No: l

Office of Chief Engineer o..lgn No:1 3501

STRUCTURES SPEC: 02261 A - REV. 1 Shut No. l 1 of...... --..............l.,...... i"-.. ~ .. '" .. .. " .. _ . -- ~tiona fioa~d ~..e:ler =ti9" SK-l.. .. .. _ .. .. _ .. .. .. .. fi .. l- .... .~..-i._.."""""__ JO S eel Slo' on ha elph". Pen nia 19104 t.... __ _.,.. -i.. "- ~........~ O"IQ-l CJ I Drown ,J I Oat. tllOtl/Ol

Page 39: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

. (

ENGINEERINGPRACTICES

ORIGINAL ISSUE DATE

04124101NUMBER

REVISED DA TE EP3016TITLE

STORM WATER DRAINAGE AND DISCHARGEFROM ADJACENT PROPERTY ONTO AMTRAK

RIGHT-OF-WAY

NIA

RECOMMENDED by DATE PAGE

Anthony Scorpio 4/25/01 1APPROVED by CHIEF DATE OFENGR. STRUCTURES

James Richter 4/27/01 2

SCOPE AND NATURE

There are many areas along the railroad corridor that are receiving storm water fromadjacent property that results in flooding during the smallest of storms, Increased stormwater flow to the railroad property increases deposits of excessive amounts ofsedimentation and could cause fouling of the track structure. With the introduction of theHigh Speed Rail Trains, passenger safety is of the utmost importance. Diminished tracksupport from flooding and sedimentation wil not be allowed.

It is Amtrak's policy to limit the resultant discharge and drainage of storm water from thedevelopment of adjacent properties to no more than pre-existing conditions, asdemonstrated by engineering analyses through governmental regulatory processes.

It is Amtrak's policy to protect the railroad nght-of-way from sediment, erosion and excessrunoff during all stages of construction activities on adjacent properties, as demonstrated byengineering analyses through governmental regulatory processes.

SPECIAL REFERENCE

The following policy is to augment Specification 02861 of EP3005, Pipeline OccupancyRequirements and Specifications, and other Amtrak I&C, design and construction standards,

SPECIAL MATERIALS

N/A

PROCEDURE

The discharge of storm water onto railroad property wil be prohibited for all constructionprojects on or adjacent to Railroad property, unless the applicant can demonstrate that therewill be a "zero net runoff' result in the peak flow and total volume based on a 1 00 YearStorm event, and that receiving waters downstream wil not be impacted.

Computations indicating this design and suitable topographic plans, prepared by aProfessional Engineer, licensed in the state in which the work wil be performed, shall besubmitted to the Chief Engineer for approval at least 60 days in advance of construction. Ifthe drainage is to discharge into an existing drainage channel on or under the Railroad Rightof Way, a hydraulic analysis of the existing structures must be included.

Formal approval of the proposed design, by the appropriate governmental agency oragencies, must be submitted with the computations. Control of soil erosion andsedimentation must be demonstrated on the design plans in accordance with theappropriate state and local regulations.

Page 40: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

TITLE

STORM WATER DRAINAGE AND DISCHARGEFROM ADJACENT PROPERTY ONTO AMTRAK

RIGHT-OF-WAY

ORIGINAL ISSUE DATE

04/24101REVISED DATE

NUMBER

EP3016NIA

PAGE

20F2

The Contractor shall be responsible for control of the site and protection of railroad propertyduring the entire construction project, through completion. The design of sedimentation,erosion and runoff control during construction shall accommodate conditions of every phaseof construction.

Review, monitoring and approval process:

1. The Contractor shall conform to this Amtrak policy, and demonstrate conformance bystandard Amtrak review submissions and approvals, as noted above.

2, Amtrak I&C shall assure that agencies and other third parties proposing construction onor adjacent to Amtrak Right-of-Way conform to Amtrak policy detailed herein.

3. Amtrak Design and Construction shall review the Contractor's proposed design andconstruction procedures for conformance with Amtrak policy, as demonstrated throughappropriate engineering analyses and the government regulatory process.

4. Amtrak Construction shall monitor the activities of the Contractor on-site to assurecompliance/ adherence to approved procedures throughout the construction period.

;'REPORTING

N/A

RESPONSIBILITY

Amtrak I&C Staff

Director L&C

Amtrak Design Staff

Director Structures Design

Amtrak Construction Staff

Sr. Director Construction

Comply with Procedure

Assure Compliance

Comply with Procedure

Assure Compliance

Comply with Procedure

Assure compliance

Page 41: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

EXHIBIT B

INSURANCE REQUIREMENTS FOR TEMPORARY PERMIT TO ENTERNATIONAL RAILROAD PASSENGER CORPORATION

(AMTRAK)Revised as of December 2000

DEFINITIONS

Whenever in these Insurance Requirements or in the plans or contract documents thewords "Company,""Railroad," or "Amtrak" are used, the same shall mean NationalRailroad Passenger Corporation. "Contractor" shall be defined as the party identifiedas "Permittee" in the Permit to Enter Agreement, as well as its offcers, employees,agents, servants, contractors, subcontractors, or any other person acting for or bypermission of Permittee or the party identified as Contractor in the PreliminaryEngineering Agreement or Force Account Agreement, as well as its offcers,employees, agents, servants, contractors, subcontractors, or any other person actingfor or by permission of Contractor. "Operations" shall be defined as activities of or workpenormed by Contractor, its offcers, employees, agents, servants, contractors,subcontractors, or any other person acting for or by permission of Contractor.Agreement shall be defined as the Permit to Enter Agreement, Preliminary EngineeringAgreement, and/or Force Account Agreement.

INSURANCE

The Contractor shall procure and maintain, at its sole cost and expense, the types ofinsurance specified below, Contractor shall evidence such coverage by submittingCertificate(s) of Insurance for Workers' Compensation, Commercial General Liabilityand Automobile Liabilty, and the original Railroad Protective Liabilty Policy, prior tocommencement of Operations. All insurance shall be procured from insurersauthorized to do business in the jurisdiction(s) where the Operations are to bepenormed. The Contractor shall require all subcontractors to carry the insurancerequired herein, or Contractor may, at its option, provide the coverage for any or allsubcontractors, provided the evidence of insurance submitted by Contractor to Amtrakso stipulates, The insurance specified below shall provide for thirty (30) days priorwritten notice to Amtrak in the event coverage is substantially changed, canceled ornon-renewed. All insurance specified below shall remain in force until all Operationsare satisfactorily completed, all contractor personnel and equipment have beenremoved from railroad property, and any work has been formally accepted.Contractor's failure to comply with the insurance requirements set forth herein shallconstitute a violation of this Agreement.

Page 42: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

Workers' Compensation Insurance complying with the requirements of thestatutes of the jurisdiction(s) in which the Operations will be performed, coveringall employees of Contractor. Employer's Liabilty coverage with limits of not lessthan $1 million each accident or illness shall be included.

In the event the Operations are to be performed on or over navigable waterways, aLongshoremen and Harbor Workers' Compensation Act Endorsement and a MaritimeCoverage Endorsement are to be added, including coverage for wages, transportation,maintenance and cure.

Commercial General Liabilty Insurance covering liability of the Contractor withrespect to all Operations to be performed and all obligations assumed by the Contractorunder the terms of this Agreement. Products-completed operations, independentcontractors and contractual liabilty coverages are to be included, with the contractualexclusion related to construction/demolition activity within fifty (50) feet of the railroadand any X-C-U exclusions deleted. The policy shall name Amtrak as an additionalinsured with respect to the Operations to be performed. Coverage under this policy, orpolicies, shall have limits of liabilty of not less than $2 milion per occurrence, combinedsingle limit, for bodily injury (including disease or death), personal injury and propertydamage (including loss of use) Iiability_

Automobile Liabilty Insurance covering the liability of Contractor arising out of theuse of ANY VEHICLES which bear, or are required to bear, license plates according tothe laws of the jurisdiction in which they are to be operated, and which are not coveredunder the Contractor's Commercial General Liability insurance. The policy shall nameAmtrak as an additional insured with respect to the Operations to be performed.Coverage under this policy shall have limits of liabilty of not less than $1 millon peroccurrence, combined single limit, for bodily injury and property damage (including lossof use) liabilty,

Railroad Protective Liabilty Insurance covering the Operations performed by

Contractor or any subcontractor within fifty (50) feet vertically or horizontally of railroadtracks. The AAR-AASHTO (ISO/RIMA) Occurrence Form (claims-made forms areunacceptable) in the name of the National Railroad Passenger Corporation (and anyother railroad operating over the tracks) shall have limits of liabilty of not less than$2 milion per occurrence, combined single limit, for Coverages A and B, for lossesarising out of injury to or death of all persons, and for physical loss or damage to ordestruction of property, including the loss of use thereof. A $6 millon annual aggregateshall apply. Additionally, Policy Endorsement CG 28 31 - Pollution ExclusionAmendment, is required to be endorsed onto the policy.

Page 43: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

Further, "Physical Damage to Property" as defined in the policy is to be deleted andreplaced by the following endorsement:

"It is agreed that Physical Damage to Property is amended to read as follows:

Physical Damage to Property means direct and accidental loss of or damage toall property owned by any named insured and all property in any namedinsured's care, custody and control arising out of the acts or omissions of theContractor named on the Declarations.

The original Railroad Protective Liabilty Insurance Policy must be submitted to Amtrakprior to commencement of Operations.

In the alternative, and upon Amtrak's approval, Contractor may elect to have Amtrakinsure the Operations under its Blanket Railroad Protective Liabilty Insurance Program(RRP). The premium, which shall be determined by the rate schedule promulgated bythe insurer in effect as of the effective date of the Agreement, shall be prepaid by theContractor. In the event Contractor and Amtrak agree to insure the Operations underAmtrak's RRP, Contractor shall include RRP premium of $ in addition to the

Permit Fee, and send its check made payable to National Railroad PassengerCorporation to the individual set forth below prior to commencement of Operations.

All Risk Propert Insurance covering physical loss or damage to all property used inthe performance of the Operations. The policy shall have limits of liabilty adequate tocover all property of the Contractor (including personal property of others in Contractor'scare, custody or control) and include a waiver of subrogation against Amtrak.

Claims-Made Insurance

If any liability insurance specified above shall be provided on a claims-made basis, thenin addition to coverage requirements above, such policy shall provide that:

1. The retroactive date shall coincide with or precede Contractor's start ofOperations (including subsequent policies purchased as renewals orreplacements);

2, The policy shall allow for the reporting of circumstances or incidents that mightgive rise to future claims;

Page 44: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

..

;

3. Contractor wil use its best efforts to maintain similar insurance for at least three(3) years following completion of the Operations, including the requirement ofadding National Railroad Passenger Corporation as an additional insured; and

4. If insurance is terminated for any reason, Contractor agrees to purchase an

extended reporting provision of at least two (2) years to report claims arising fromOperations performed in connection with the Agreement.

The Contractor shall furnish evidence of insurance as specified above fifteen (15) daysprior to commencing Operations. THESE DOCUMENTS SHALL INCLUDE ADESCRIPTION OF THE PROJECT AND THE LOCATION ALONG THE RAILROADRIGHT-OF-WAY (typically given by milepost designation) IN ORDER TO FACILITATEPROCESSING. The fifteen (15) day advance notice of coverage may be waived byAmtrak in situations where such waiver wil benefit Amtrak, but under no circumstanceswil the Contractor begin Operations without providing satisfactory evidence ofinsurance as approved by Amtrak. Such evidence of insurance coverage shall be sentto:

./

Director of I&C ProjectsNational Railroad Passenger Corporation30th Street Station, 3rd Floor, South Tower, Box 64Philadelphia, PA 19104-2817

Page 45: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

LOCAT ION or OVCR-IlING

3RD. R'IL, IRACKeT AND

PRO

TC

CT

lOI

lCA

D.

OC

TA

IL "

A'

VIRCS. OTHCR THAN TROLLCY VIIlS. CROSING RAIL~D

SJi; LINlS (AT 60, o. WIND) I. C. C. ORDC. SCP..l. 1939

OY

CR

HC

AD

.RI

DO

C 'N

D O

TH

C. S

TR

UT

l..ic

s

.. iI ~ I~ jl! '" I I

~ ~ i! !' ..

¡ I! ~ ~~

16"

OR

D il

l

ni

TIP Il CONDUIT LlNC

Am

k$""

_r._

......

.___

~....

.._--

......

.."--

~,-

-.... _ ..--......... -..-

--_.

.- ..

-....

,-,.

...._

_.._

__.i.

.-...

..__

_....

II_

OF"riCE OF" THE

CH

IEF

" E

NG

INE

ER

OF

" T

RA

CK

..._.

. ....

' _.,

to, _

~t)Q

.

i; ~g

tï;'(5

:w!')

.f~

b~e,

ii~

li~dl! ~i;

hi~

~ ¡

Iiit~

td¡

....

01 x

5w ..

..~ê~~~ ii

¡:~

ii"=

i!§

~~

2~~

i!E

;iB

l:~li~

~"

iliil~

a -~

.. :t. ..~ z- ~i "'~..

....,,

-..u

f¡~!

Î~~

-..- "'..

~~i

? ..

-0.

u ~ ti~ '!ll

glid

~~~

....~

ilSi!

~!~

lt!ii.

,,-,

~!:e

":05 ~i~

.. '"

~!:;

ëi~!

=~i

.¡¡

~ ,

..~!!

~t1~

!t.. -i"

~~~

'5l

ff..'

"d;;¡

¡ ~d ,,-..

......

im CLeARANe R£OUIA'M(NTS $l i: THIS PtAH

AP.. ~Y' TD NEW c.TR\TJtJ Oi RtCONTR\T,Dr

CXISTI"' STRUTLlS AND TRACS MAY IE ..INTAI..D

AND CXTCNOCD AT PlStNT CLtMANtS. lHcn OTotovlSC

1lliIIlD IY LOCAl OR STATC AUnOlITlts.

ST

RU

YLl

S M

UT

o.T

It L

OC

AT

tD N

lAlR

TO

Tot

TRAC-i Ti- Tt- "IHJfi CL£ARNit LIMITS Si- ON

THIS PLAN AND TotSt DISTANtS SHlD K tXCttOCD

I/RC POSIBLt. CONIOCRATI() SHlD It GIVCN TO

Tot PI!lIILllY or INlIlAStD DISTANt ItTVCCN TRAC

CtH

TtR

LIN

lS. V

IOC

HIN

G _

DK

D S

IOO

CIl

"'D

_IO

CH

ING

AHD OCCPCNll, DITCo£S. AND TH: STRUTLlS SHlD IE

LOC

.TC

D A

CC

OR

DIN

GY

.

rOR

ST

AN

DA

D D

IST

ON

tS II

TV

CtN

T.A

CK

CtN

TC

.LINlS AND TH: sPACING or TRACKS _il INTtoTRACK

CL

tMA

Nt -

LIH

ITIN

G O

I..C

TS

Al L

OC

AT

tD. S

ttNV-lOO SPCciriCAlION r(J INSPCCTICJ. CONTRUTION

AND ..1 NTtNAC CT TRACK

I/RC PHSICoI CONDITICM INPC INSlJTA"'C

IlST

.I

CT

ION

. NlC

tSSI

TA

T I

.. C

LtA

lON

tS C

LO

StR

Tl-

Tlfe SPCcirltii TH: ..ne. MUT It SUINlntD TO TIC

CHltr t..INlC. r(J AN ICDirICAllOO. AND AlSO TO

TIC LOCAl (J STATt .."OIITICS ,r NtetS$A.

HIH

I.. C

LCM

AhC

S $

l ON

TH

IS p

iAN

AR

'(J

TANNT LtYtL TAACK.

r(J ci.ø T.ACK TIC rD.LOVIMl PlISION APY.

~ - NCASD VC.TlCAlLY AIO HIOH .AIL tXCtPT 'OR

~toaR ..D rRCIOHT P\ATrCR WHICH AR NtASD

PCIlNDICi.Al TO Tot PLAI CT TIP or RAIL,

~1Ã

i~T

~~c~

gci~

t~ ~

li"=

~k~A

~~~D

ClMS 13' 00 LtSS) ICll()TAlLY AND IICRCA$D IY i 1/2

INlH:S PCA ocoit or ClRATLl ov. THAT Sl

r(J TANNT TRACK (tXCePT LOV PASSCoa. PLATrll ()

cuis 13' (J LESS), IN ADDITI() Tot INSIOC CLtAAONc r(J

SLPA tLCVATCD T.ACK SHAL K ri.lTH:R INlRCAStD IT

I ltO roo tACH I INlH or SLPRCLtVATICJ rOR eAC $ retT

CT otlOHT AIO TIP or LOV RAIL,

L.CN PASseNGR PlATrDl WILL JrT K C~JrAl'tD

J"C

R C

l.YA

1UR

LP

TO

r¡-

.

rCR ClNATi. IN excess r: øt. LOW PLATrOR $tOD lC

CE

SIC

HD

AT

li: c

r R

Ail

E1.

(VA

Tltl

AN

D e

xTC

NO

(D T

O T

i. rl

E:l.

ÐS

I D

C i:

TH

C il

AR

RA

IL.

~AT

r_~"1 ~__

-(' \ je" 'Lii PlA ir_

~\\

.- .,

.y'-

. )..

r:~A

T."

-0-

\ J 1

~~ 'LcÑPlATrCJ

1.. Y

~--

r

/

VCRTICAl ICASLlICNT () ciD TRAC

*'O

R S

TA

Tt C

LtA

lON

t Ilg

uIIl

NC

NT

S. S

tt A

. ., C

, .. A

.... C..Tt. l!. StCT l() 3. 6, LCGA CLtAAONC

RE

QU

IRE

ME

Nts

IV S

TA

tes.

STANDARD T.ACK PlAN

MINIMUM ROADWAY CLe:CES

O.g. No.

AM

7D0

~. I or

I~

¥l-l

..'...

lld ~

.. I.

... ~

it....

II

II

Page 46: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

. :~

C.E. 4

March 1997

SPECIFICATIONS

FOR

WIRE, CONDUIT AND CABLE OCCUPATIONS

./ OF

NATIONAL RAILROAD PASSENGER CORPORATION

PROPERTY

Page 47: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

'f .

-~

c.E. 4

March 1997

INDEX

SUBJECT PAGE NO.

1. SCOPE... .......... .......... ............" ..........."............. ...... .... 1

2. APPLICATION.........., ..... ......... ... ..,......... .... ... ........ ... .... 1

3. APPROVAL OF PLANS..........",...,....,.............,........,... 1, 2, 3

4. CONSTRUCTION REQUiREMENTS................"........ 3

5, LONGITUDINAL OCCUPATIONS.........,....................... 4

6, INDUCTIVE INTERFERENCE..,.."........,..................... 4

APPENDIX

P LATE i...........".........................................,......,........................ 5

P LATE I I............ .......... ............. ,.."....... ........,.,..................,... ...., 6

PLATE I IA,................., .....,... .................,.,...... ...............,. ....., ..,... 7

PLATE III..~................. ....... ....,...., .,...... ......... ......... ........... ,.......... 8

PLATE IV....... ....., ............,.."..............,.. .........,. ....... ..... ,.............. 9

PLATE V..,.........,..,...,..... ..,.."... ........ ..........,...... ............. .....'.. " ... 10

Page 48: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

c.E. 4

March 1997

1. SCOPE:

A. These specifications apply to the design of electric transmission wires,cables, and conduits (power or communication) which are to be locatedover, under, across or upon Railroad propert and facilties and tracksowned by others over which the Railroad operates its equipment.

2. APPLICATION FOR OCCUPANCY

A. Individuals, corporations, municipalities (known as the owner) desiringoccupancy of Railroad propert by such wire, cable, or conduitoccupations must agree, upon approval of the construction drawings bythe Offce of the Chief Engineer of the Railroad, to execute an appropriateoccupational agreement and pay any required fees and/or rentals outlinedtherein,

B. Application for an occupancy shall be .by letter addressed to:. ¡

Commercial DevelopmentNational Railroad Passenger Corporation30th and Market Streets, 5th Floor SouthPhiladelphia, PA 19104

giving the following:

1) Name of individual, corporation or municipality desiring theoccupancy.

2) Complete mailng address of applicant.

3) Name and title of person who wil sign the agreement.

4) The State in which the applicant is incorporated.

C. All applications shall be accompanied with eight (8) copies of all

construction plans and three (3) copies of specifications and computationsconcerning the proposed occupancy.

i

Page 49: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

c.E. 4

March i 997

3. APPROVAL OF PLANS

A. No entiy upon Railroad propert for the purpose of conducting surveys,field inspections, obtaining soil information. or any other purposeassociated with the design a.nd engineering of the proposed occupancy,will be permitted without a proper entiy permit (Form CR-17) prepared bythe offce of the Chief Engineer of the Railroad and executed by theapplicant. It is to be clearly understood that the issuance of such a permitdoes not constitute authority to proceed with the actual construction whichcannot begin until a formal agreement is finally executed by the RailroadCompany and permission is received by the owner from the designatedinspection agency of the Railroad to proceed.

B. Plans for proposed wire, cable. or conduit occupations shall be submitted

to and meet the approval of the Chief Engineer of the Railroad prior tostart of construction, These plans are to be prepared in sizes as small aspossible and are to be folded to an 8~ inch by 1 inch size (foldeddimensions) with a 1 ~ inch margin on the left-hand side and a 1 inchmargin on the top so that they can be secured in a file at the upper left-hand corner and stil be unfolded to full size without being removed fromthe file.

Also. after folding. the title block and other identification of the plans shallbe visible without the necessity of unfolding at the lower right-hand corner.Each plan shall bear an individually identifying number and an originaldate. together with subsequent revision dates. clearly identified on theplan so as to be readily apparent as to just what revisions were made andwhen.

All plans are to be individually folded and where more than one plan isinvolved, they shall be assembled into complete sets before submission tothe Railroad.

C, Plans shall be drawn to scale and show the following:

(See Plates I, II. IIA, II. IV and V, hereto attached)

1) Plan review of crossing or occupation in relation to all Railroad

facilties (See Plate I).

2

Page 50: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

C.E.4March 1997

2) Location of wire, cable, or conduit (in feet) from nearest Railroad

. Mile Post, centerline of a Railroad bridge (giving bridge number), orcenter line of an existing or former passenger station. In all cases,the name of the County in which the proposed facilities are locatedmust be shown. In States where Townships, Ranges and Sectionsare used, give distance in feet to the nearest Section line andidentify the Section number, Township and Range.

3) Profile of ground on center line of pole or tower line, showing

clearances between top of rail and bottom of sag, as well asclearances from bottom wire or cable to top wire or cable of theRailroad's static, transmission, signal, trolley feeder andcommunication lines, catenary, and third rail, when present. Ifnone of these facilities are in existence at the point of crossing, theplan should so indicate. Actual under-clearances are to be shown(See Plate V for the minimum required clearances in non-electrifiedterritory).

4) Show all known propert lines, If wires, cables or conduits arewithin public highway limits, such limits should be clearly indicatedwith dimensions from center line.

5) The plan must be specific, as to:

a. Base diameter, height, class and bury of poles. Poles shall

be s.et no closer than 18'-0" from face of pole to center lineof nearest track. When necessary, however, each locationwill be analyzed to consider speed, traffc, etc.

b. Number of size, and material of power wires, as well asnumber of pairs in communication cables.

c. Nominal voltage of line.

d. Number of, location, size of, material of anchors and allguying for poles and arms.

3

Page 51: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

c.E. 4

March i 997

NOTES: Double cross-arms and deadends with backguys arerequired on poles adjacent to track where wires or cableare crossing tracks (See Plate IIA), Any tower designsmust be accompanied by engineering computations anddata.

4. CONSTRUCTION REQUIREMENTS

A Power and communication lines shall be constructed in accordance withAmtrak's Electrification Standards and "Safety Rules for the Installationand Maintenance of Electric Supply and Communication lines, NationalElectrical Safety Code Handbook", (current issue). Casing pipes tocontain power or communication wires or cables having an outsidediameter of over four (4) inches shall be constructed in accordance withthe current issue of Amtrak's "Requirements and Specifications forPipeline Occupancy", USA, ENG 1604'dated November 1987.

B. Under special conditions, Railroad wil give consideration to occupationson its catenary structures, subject to the approval of the Chief Engineer,and the Railroad's policy governing such matters.

5. LONGITUDINAL OCCUPATIONS

Wires and cables running longitudinally along Railroad right of way shall beconstructed as close to Railroad propert lines as possible. For electncal powerwires and cables with voltages of 34,500 or over and communication cablescontaining over 1800 pairs, the following information must be submitted inaddition to the detail of the pole to configuration as called for on Plate IV of thesespecifications:

a. Voltage of circuit(s) or number of pairs.

b. Phase of electrical circuit(s).c. Number of electrical circuits.d. Size (AWG or CM) and material of wires or cables.e. Length of spans clearly indicated on drawing.

4

Page 52: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

C.E. 4March 1997

Any facilities overhanging Railroad property must have approval of the Railroadand appropriate rental charges wil be applied.

6. INDUCTIVE INTERFERENCE

On agreements covering occupations, provisions wil be included that theapplicant wil conduct appropriate EMI/EMF studies and provide appropriateremedies, at his own expense, to correct any inductive interference with Railroadfacilities.

5

Page 53: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

INFORMATION TO BE SHOWN ON PLAN SECTION OF DRAWINGS

WHEN FACILITY IS A CROSSING

PLATE i C.E. 4

2/10/97

"-

Iv

l ¡ ~

/ '" c

c:.2 0"~ 0~ ~i.~ ;:

o _:J~ -

--RALROAD RIGHT OF WAYTO BE SHOWN .

~HOW HIGHWAY ~MITS ~(PA""" Je(.). PAGE 2) \

PROPOSED UNE

/

/.~..'" iì.è ~

.: Çjo ""¡; ..-o

-TO (R.R. STATION).. .

/TO (R.R. STATION). ..

~ I

* i / RALROA COMMUNICATION UNE. SlGNAL UNt:o MCI.AT&T OR t-FS Fl8ER CALES.

8

~SHOW COMMUNICATION & SIGNAL HOUSES

SHOW P:ER:NE \

J

i

oi

/

/i

~INDICATE LENGTH OF SPANOVER TReKS

SEE PARAGP.APH 3C(2). PAGE 2

i SCA OF DRAWING TO 8E SHOWN I

Q NOTE.

ALL RAILROAD ELECTRIFICATION FACIUTiES t-UST 8E SHOWN IN RELATION io PROPOSE!) UNE.

IF TiE PROPOSED UNE IS io SERVE A NEW DEVLOPMENT. A MAP SHOWING tHE AREA INRELATION íO ESTASUSHED AREA AND ROADS IS TO 8E SENT wiTH THE REQUEST.

IF THE PROPOSED UNE IS NOT WHOLLY (OR PARTILLY) WITiIN HiGHWAY UMIITS. THE SAMEINFORMATION IS REQUIRED AS SHOWN ON TiIS PLATE.

~

~,.'"..:¡e:~.; · DIMENSIONS TO 8E suppum BY OWNER

.~Am~ OFtleE OF.. V.P., Chief Engineer

En9in~~rin9

AoorovedALE. E1""I,ic r 'action

Y:

O;rtclor Eledric Tro~!ion

BY:

DoteC.E. SPECIFICATIONS

STANDARD CLEARANCES FOR WIRESHIGHWAY CROSSING RAILROADSNotionl ROiSod PQ:n."Q'-l CorptQll

J011 Stnet Stalion -;t"Õlaaclø"oG. Pet2)YGII 19104

On;ql'-l efT Oat. 2-\1-97

Page 54: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

. '1

.INFORMATION TO BE SHOWN ON PROFILE SECTION OF DRAWINGS

IN CASES OF CROSSING NON-ELECTRIFIED RAILROADS

DOUBLE DEA END

CONDUCTOR ANDSTATIC WIRE

~!..1:i'0' SHOW NUM8ER OF WIRES IN PROPER PROSPECTIVE.

I iii VOLTAGE. POWE. GROUND. &: NEUTR WIRES. ETC., iII

" l:.k -l BOTTO. OF =. '" F.

JL ~ (SEE NOTE)

., RAILROAD POLE UNE OR DUCT BANKi i, ,i :

.,a:'"c:i.'"cr'"a.ww

TOP ;1HIGH RAIL

~õI"

i

!

ct TRK, I

I

I

~ TRK. 3i

I~ TRK. 2

!

i TRK.4-

IE'-O" MIN.

PERP. TO TRACKi

18' -0" MIN.

PERP. TO TRACK

PLATE II C.E 4

2/10/97

w'zl:¡ i¡i ,D.ei I

!

NWt:'"a.

I

~

I i¡

SECTION LOOKING__________(DlRECTICN)

SCALE: H_______SCA: V________mê ~ i

i;

I.

:

.t1. ALL TRANSMISSION, STATIC. CATENAY, FEEDERS, COMMUNICATION UNES

AND THIRD RAIL SHOUL BE INDICATED AND THE PROPER CLEARANCES SHOWN.

(SEE PLATE 11A)

2. SHOW MAIMUM SAG INCREASE OF POWER WIRES OVER TRACKS IF THE SPANEXCEWS i 75 FET IN lEGTH.

J. DOU9LE DEAD END ALL CROSSING WIRES ON 80TH SIDES OF THE RAL'WAO

AND PROVIDE BACK GUYS AWAY FROM THE RALROAD.

C.E. SPECIFICATIONSSTANDARD CLEARANCES FOR WIRES

CROSSING NON-ELECTIfIED RAILROADS

POLE iOP CONFIGURATIONTO BE SHOWN

lx'"

..

.. DIMENSIONS TO BE SUPPUED BY OWNER

~Am~Hati0l1 RaoCad P03u"qat CororatÎofl

.Jll SVc-ct Stoti"-Pl'a~lci".Q. PClsynlQ 19'04

AcorovedA.C.E. Ðeelrie Traelian

y.

O~ecor O.dnc Tract;on

SY:o.,.,ed £/r Oat. 2-11-97

OFtlCE OFV.P., Chief Engineer

Engineering

Dote

Page 55: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

rINFORMATION' 10 BE SHOWN ON PROFILE SECTION OF DRAWINGS

IN CASES OF CROSSING ELECTRIFIED RAILROADS

A- ..CO__ ',,"CTCRS ("" ""c. ÆIs. oc.). .PLATE IIA C.E. 4

2/10/97REV. 9/16/97

~. ~ --on '$~N gdg --m

~~g: oV)

:z ~ i3i g~-'".. '"

DOUBLE OEA ENO

CONDUCTOR mDSTATIC WIRE

;. ..3:""'" ;.0'" g~0 ~'".. ",'"a. t5~:::z ~ i5i O~

;. ""~'";. '"

CATEy i ~ ~ .-

COMMUNICATION mD SIGNAL DUCT BANKTO BE SHOWN WHERE APPUCABLE.

i

_ i _ - I T

l I I ITRK. 1 ti ffK.2 i TRK. 3

1-TRK. 4

i i

18'-0" MIN.

I I

18'-0" MIN.

PERP. TO TRACKPERP. TO TRCK

TYPICAL ARRAGEMENT OF RAILROAD CONDUCTORS

WIRE CLEARACES FOR VOLTAGES ABOVE 25 KV

MINIMUM VETICAL ClECEVOLTAGE (TOP OF CONDUCTOR TO SOlTOM OF SAC).t

i. MINIMUM ClECE IS CACULATED AT WORST CAE WIRE SAG.

(RESULT OF t.L/,Ui. OPERTING TEPERTURE. ICE lOADING. Ere.)

2. llE ABOVE DIAGRA SHOWS A rriCA UTILI CROSSINGON THE NEW YORK TO WASHINGTON CORRIDOR. ,A unUTY CROSSINGSON THE NORTHEND ELCTRIFlCATION PROJECT WILL BE ~BOVE DiEHIGHEST RALROAD CONDUCTOR.

3. ST POLES OR TOWES THT CA SUPPORT BROKEN CONDUCTORLOADS MAY NOT NEE TO BE GUYE PENDING APPROVAL FRO'" AMTR.

34,500 S'-6"69.000 9'-6"

115.000 11'-6"

138.00012' --"

on230.000 15.-0"

0 345.000 19'-0.Õ

500.000 24' -0"õ:

'" 745,000 32' -6-.'!x 765.000 33'-0"'"w

~c.~¡;

OFFICE OFV.P., Chief Engineer

Engineering .'

A oravedA.C£. Eltr Troc~OI

BY:

Diroctor £J TmctiooBY:

Dotee.E. SPECIFICATIONSSTANDARD CLEARANCES FOR WIRESCROSSING ELECTRIFIED RAILROADSfrt. Roif'd Po..tl.. ~~

JOTl Sir StOtiOf-?tcMphoQ. P..nsyni 19104

o.... El o.t. 2-11-97

Page 56: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

INFORMATION TO "BE SHOWN ON PLAN SECTION OF DRAWINGS

IN CASES OF LONGITUDINAL OCCUPATIONS

PLATE iii C.E. 4

2/10/97

,. ¡tv¡g~ ,"qf5 C:z -.

~ 3:o E:~

HAILROAO RIGHT or WAYTO BE SHOWN \ ---- - - ----

----RALROAD SIGNAL If COM!JUNlo.nONS UNE

(IF NONE. SO STATE)

c c o o \ cTO (R.R, STAnON).. .. TO (R.R. STAnON).. ~

~ /7\

TRACK 10CENTER LINE OF TRCKS

* * \

PROPOSED LINE

RALROAD RIGHT OF WAY \TO SE SHOWN-- SE:: NOTE 3

I SCALE OF DRAWING TO BE SHOWN I

NOT:"'

~

(1 ) EACH END OF THE LINE MUST SHOW MEASUREMENTS AS CALED FOR INPARAGRAPH 3C(2), PAGE 2

(2) IF POWER UNE CROSSES ANY TRCK. TlEN THE INFORMAnoN SHOWN ONPLATE 1 IS AlO REQUIRED.

(3) wH~E ANCHOR GUYS ARE REQUIRED. SEE PARACRAH 3C(3). PACE 2.

(4) THE DISTANCE BETEEN EACH POLE IS TO BE SHOWN.

(5) ASSIGNED POLE NUMBERS TO BE SHOWN AT EACH POLE.

'"

i""x'"w~

~..· DIMENSIONS TO BE SUPPLIED BY OWNER

~Amk-~OFFICE OF

V.P., Chief EngineerEngineering

DateC.E. SPECIFICATIONS

STANDARD INrORMA nON FOR WIRESIN CASES or LONGITUDINAL OCCUPATIONSHoiiOlal Iloilo-d PQncft~et Co'lrolion

JOn. Street S(otÕO-PtWOdClph.. Pensyvc",a 19104~tri Tr12ctio

O..oqned tIT Ca~. :-',-g7

Page 57: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

INFORMATION TO BE SHOWN ON PROFILE SECTION OF DRAWINGS

IN CAES OF LONGITUDINAL OCCUPATIONS

.í POLE NUMet:~S

Jji

I

i

I (TOP Of RAii EL£ATION IOF ADJACENT TRCK

I --i--!rc~'m.~!

i

*

~

on

e~

co

~)('"w~a:~¡;

~Amk-~

~

.

e

\ ,,,om OFCROSS ARMS

ELE'¡.,\CN

,_

APPARENT SAGAT 60"F.

-- i

-r~

PLATE IV C.E. 42/10/97

,I

r -lI

POU: TOP ~ONFlGURAriON TO 9E SHOWN SIMILAR TO SAPLES ABOVE

t..oorovedA.C.E. 8ectrõc rracGonAy.

O;'4!tor et~ñe T,,,ction

9"(:

Date

NOT'. .~ IF POwER UNE CROSSES ANY TRACK. THEN INFORMAnON SHOWN ON PLATE II IS AlO

REQUIRED.

* Oll.EtlsiONS TO 8E SUPPUED BY OWNER

OfFICE OFV.P., Chief Engineer

EngineeringNot;onl Ra~cl Pass.l"9-" CorplÏon

JOIl Street StQtion-Pt\cidclø"t(~ Penn~vOf\ t9104

~ (L('¡" TlON

DISTANCE BETEEN POLES TO BE SHOWN

C.E. SPECEFICATIONSSTANDARD CLEARANCES FOR WIRES

IN CASES OF LONGITUDINAL OCCUPATIONS

D~"e4 Rev Orawn RCV lei.c..d Rev Oot. 2-10-97

Page 58: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

::

,. .C.E. 4

PLATE V. 2/10/97,

NON - ELECTRIFIED TERRITORY.'

OVERHEAD CLEARANCEVOLTAGE

(TOP OF RAIL TO BOnOM OF SAG)-

0-750 27' -0"

751-15,000 28'-0"

15,001-50,000 30'-0"

69,000 30'-8"

115,000 32'-2"

138,000 33'-0"

345,000 39'-10"

500,000 45'-0"

745,000 53'-2"

765,000 53'-10""

/

CALCULAiION IS 30'-0" + 0.4" PER 1,000 VOLTS OVER 50,000 VOLïS

-

,

'"~

:.-

Am~ Aooroved Dote C.E. SPECFICA TIONSOFFICE OFA.C.E, Ðectròc TractionV.P., Chief Engineer8.,, STANDARD CLEARANCES FOR WIREEngineeringO;,.~tor Flectric Tractio CROSSINGS, NON-ELECTRIFIED TERRITORY

Notional Aoill"od Pon.nq_ Corpo'ati~JOnt SlIct Stot.O"-PhilOdC'P".a. PensyV'"'G 19T04 gy: O..n.. Elf 10n_ OJr ICh... RG l Cote Z-I1-~1

'"

;;

'")("..3..-..

Page 59: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

ENGINEERING ORIGINAL ISSUE DATE NUMBER

Amtrak$ 01/25/01

PRACTICES REVISED DATE EP3003N/ATITLE

BLASTING PROCEDURESRECOMMENDED by DATE PAGE

CraIg Rolwood 11251(f1 1APPROVED by CHIEF DATE OFENGR, STRUCTURES

James Richter 2113101 2

SCOPE AND NATURE

To establish a uniform policy for blasting on and adjacent to Amtrak's Right-of Way.

SPECIAL REFERENCE

Note: The former number for this engineering practice is 208.

SPECIAL MATERIALS

N/A

PROCEDURE

JBlasting is restricted on and adjacent to Amtrak's Right-of-Way. Approval to blast must begiven by the Assistant Vice President or Chief Engineer of the appropriate discipline,

Requests for approval to blast must provide the information requested below and conform toall requirements listed:

1. Provide a site plan defining the blast area and location of nearest or other related

structure.

2. Provide a soil and rock profile of the blast zone.

3. Limit the peak particle velocity to two inches per second, except for certain sensitive

areas, such as tunnels, bridge piers and abutments, oilostatic duct lines, centralinstrument houses and underpinning. For these sensitive areas, limit maximum peakparticle velocity to between 0.5 inches per second and one inch per second,depending on the facilty,

4. Maintain a scale distance of 50 when maximum peak particle velocity is two inches

per second. Maintain an initial scale distance of 60 when maximum peak particlevelocity is limited to a range of 0.5 inches per second to one inch per second. Thisinitial scale distance may be adjusted to 50 after the initial blast, if conditions permit.

Scale distance = Distance from blast to structure (in feet)

VWeight of explosives per delay (in pounds)5. Use a non-electric detonation system whenever possible.

a. If electric caps are used, a check must be made for stray currents, induced

current and radio frequency energy to ensure that this hazardous, extraneouselectricity is at an acceptable leveL.

Page 60: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

'.

TITLE

l

6.

7,

8,

- - 9.

BLASTING PROCEDURES

ORIGINAL ISSUE DATE

01/25/01REVISED DATE EP3003

NUMBER

N/APAGE

20F2

b. Amtrak uses two-way radios for trains control. The radios operate at 160MHz range, and cannot be turned off during the charging and primingoperation.

Provide an open face for maximum relief for burden,

Obtain the services of a qualified vibration and blasting consultant to monitor allblasting activity.

All blasting operations must be coordinated with Amtrak's Senior Project Engineer onthe site.

A pre-blast and pcst-blæt sur,¡ey may be obtained, The survey-wil include

photographs and an inspection of all nearby, Amtrak owned and other facilties. Thesurvey wil be used to determine any changes that occurred due to the blastingoperation.

REPORTING

N/A

/RESPONSIBILITY

Area Construction Engineer

Senior Director Construction

Asst. Vice President Engineering

or Chief Engineer, Structures

Comply with procedure

Assure compliance with procedure

Approval to Blast Required

Page 61: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

. '.k 6-1.-2.,..;i 12.c: ,~ .~ 1.1.5.1 Adjaant to Rirod Track

To limii dmge by th reircon an deflecon or nii~d equipment. pier suppng bridiesove ralways an with a clea dista or le th 25 fee from th centerine of. ralro trk shl be

or hevy cosuucton (define beloVo') or sbaU be preced by a reinor coc:te cr wal, Cnh

walls for pien from 12 to 25 feet clea from th centerine or tnck shall hive a minimum bei,ht or 6 reetabove the top or niL. Pier less th 12 reel elea from th centerline or tnck shal have a minimum

cnb wall heiiht or 12 reel above th top of raiL.

1ñ crh wal sli be at leat i ree. 6 im:be thck and 'i lea 12 feet long, When IwO or mon:

colum copo a pier. th crh wall sh co th colum and extend at lus I fOO beyon th

outet column palel to the trk.. Th cr wall shal be anre to the roop L'I column.if applicale. with adua reinforg stl an sh exte 10 at le 4 feet below the lowe

sunding gr.

Pier sbi11 be coidere or heavy cocton if thy have a crs-seona ar equa 10 or grteth th reuir for the cr wal an th larer or its dimeions is pmlel to the trk.

Considetion rr~' be give to prvidig pron for brge pier OVcf 25 feet frm th centerinor Ir as conditions wart. in mig th detetion. act shl be taen or such facors as

horinta an vcnical alignent or th trk. embannt height. an an asment of theconsuen of senous dage in the ca of a collision.

1.1.5.2 Over Navigable Strea

Piers locate adjacent to chanels or navigable wateys shl have a protection system in

aa: . ") ths cha te.

a :c depth of equivalent

8b -= depth or ~quivalent reeAnicle 2.33.2(c)

av = shea span, distance betw2.35.7

ad and face or suppon-Anieles 2.29.7 and

2.2. t Notationsj

Ag

Ah

nding th main tension reinforcing ba and havingent. divided by the numbe of ba. squar inches.

of several bar siz. the number or bar shal becomputed as the to .steel ar divid' " Y the area of the largest bar useAnde 2.39

= ar or an in - utUå.I bar. squar inche \ \ ide 1.14/ .= ar of c spí;.iy reinforcd compressio'ñ mber meaure to the outside diamter or

the s . ' /"s-uar inches-Anele 2.11.2 \,. ,Ie or reinforcement in bracket or corbl resisti' moment. sq. in.-Anides 2.29.7 andD~ ~/ f..h '~:; grss ar 0 setion, squar tnc es

i: area of shea reinforcement palel to flexural tension inrorcment, sq, in.-Anic\es

2.29.7 and 2.35.7

A

Ab

Ac

Af

1990

,'-

Page 62: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

..Concrete Structures and Foundations

d--~.1.3 HIGHWAY BRIDGES (1994)

Unless otherwse specified by mghway authority, all lughway bridges shal be designed in accordance withthe latest Standard Specifcations for Highway Bridges adopted by the American Association of State

Highway and Transporttion Offcials, -

2.1.4 BUILDINGS (1994)

Unless otherwse specifed by local governing ordinances or state codes, all railway buildings shall bedesigned in accordance with the latest "Building Code Reuirements for Reinforced Concrete (ACI 318)" ofthe America Concrete Institute, subject to design loads conforming to railway requirements.

2.1.5 PIER PROTECTION (1994)

2.1.5.1 Adjacent to Railroad Tracks 1

a. 'T limit damage by the redirection and deflection of railroad equipment, piers supporting bridges over

raílways and with a clear distance ofless than 25 feet from the centerline of a railroad track shall be ofheavy construction (defined below) or shall be protected by a reinforced concrete crash wall. Crashwalls for piers from 12 to 25 feet clear from the centerline of track shall have a minimum height of6 feet above the top of raiL. Piers less than 12 feet clear from the centerline of track shall have aminimum crash wall height of 12 feet above the top of raiL.

b. The crash wall shall be at least 2'-6" truck and at least 12 feet long. When two or more columnscompose a pier, the crash wall shall connect the columns and extend at least 1 foot beyond theoutermost columns parallel to the track. The crash wall shal be anchored to the footings and columns,if applicable, with adequate reinforcing steel and shall extend to at least 4 feet below the lowestsurrounding grade.

c. Piers shall be considered of heavy construction if they have a cross-sectional area equal to or greater

than that required for the crash wall and the larger of its dimensions is parallel to the track.

d. Consideration may be given to providing protection for bridge piers over 25 feet from the centerline oftrack as conditions warrant. In making trus determination, account shall be taken of such factors ashorizontal and vertical alignment of the track, embankment height, and an assessment of theconsequences of serious damage in the case of a collsion.

2.1.5.2 Over Navigable Streams

Piers located adjacent to channels of navigable waterways shall have a protection system in accordance withPart 23, Pier Protection Systems at Spans Over Navigable Streams. .

i Se Commentary

8-2-6o 199. Amri Raiay EnginHr Asli

AREA Manual for Railway EngineerIng

Page 63: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

cp r: Ol

Ol

o j f :i f .. .. m ,g j i.~ " m ~ =

= ~ :: c ~ - o .. " ~ i ll -o m :: ~ :: $ .. 5' to

. ~

CD G 1-0" MINIli F'OR PIERS

FROM 12 TO 2~ FT. CLEAR

FROM T~ CENTER INE or

TR

AC

K. 1

2' -

0" W

ININ

UF

OR

PIE

RS

LE

SS

TH

AN

12

rT. CLEAR FRO CENTER-

LINE OF TRACK.

B~

t or COLUN &

i CRASHWALL

B

1-0"

'-""

1_""

A,,

.A C

.l.c

WALL SHALL EXTEMJ

TO

AT

LE

AS

T 4

FT

.BELOW THE LOwEST

SURROUING GRADE

. Ie .

EL

EV

AT

ION

B

EL

EV

AT

ION

C'~

' 'Y

I~..&

: ..... " n .,'. .' :,,:. . .:~ ." :'0', ,~' - ,- . - '.~.:~:"- ,.. ,

TRACK SIDE mACK SIDE

SECTION A-A SECTION C-C

TR

AC

K O

N O

NE

SID

E O

F' C

OLU

MS

TR

AC

K O

N ~

SID

E O

F C

OLU

MS

S I NGL E eOL Ul TWO OR MOE COL UfS

Figu

re C

.1. P

ier

Prot

ectio

n: M

inim

um C

rash

Wal

l Req

uire

men

ts (

Not

To

Scal

e)

. _eM

MIN

.

r T

ep tF

_ -l . RA IL

SEC

TIO

N B

-B

, ."

o o :: o .. ~ el (f 2 ~ c .. el (. lP :: a. ." o c :: fi ~ o :: CI

II

II

Page 64: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

',NATIONAL RAILROAD PASSENGER CORPORATIONTEMPORARY PERMIT TO ENTER UPON PROPERTYÇ:.E.-17 (REVISED 11-00) (GEN)/ .

Date:File: E-47-

W.O.:

ÄiTN:

1, TEMPORARY PERMISSION. Temporary permission is hereby granted to

(hereinafter called "Permittee"), to enterproperty owned and/or controlled by the National Railroad Passenger Corporation (hereinafter called"Railroad"), for the purpose of

atconditions set forth below:

, State of , under the terms and

2. LOCATION AND ACCESS. (Give map reference, description or both)

(hereinafter called "Propert").

3. INDEMNIFICATION. Permittee agrees to provide the indemnification setforth below unless it isstatutorily prohibited from doing so, in which event Permittee wil assure that each of its contractor(s)provides such indemnification:

\.drmittee agrees to defend, indemnify and hold harmless Railroad, its offcers, directors, employees,agents, servants, successors, assigns and subsidiaries, irrespective of their negligence or fault, fromand against any and all losses and liabilties, penalties, fines, forfeitures, demands, claims, causes ofaction, suits, costs and expenses incidental thereto (including cost of defense and attorney's fees),which any or all of them may hereafter incur, be responsible for, or pay as a result of injury, death,disease, or occupational disease to any person, and for damage (including environmentalcontamination and loss of use) tõ or loss of any property, including propert of Railroad, arising out ofor in any degree directly or indirectly caused by or resulting from activities of or work performed byPermittee, its offcers, employees, agents, servants, contractors, subcontractors, or any other personacting for or by permission of Permittee. The foregoing obligation shall not be limited by the existenceof any insurance policy or by any limitation on the amount or type of damages, compensation, orbenefits payable by or for Permittee or any contractor or subcontractor, and shall survive thetermination of this permit for any reason. As used in this paragraph, the term "Railroad" includes theNational Railroad Passenger Corporation, all commuter agencies and other railroads, and theirrespective offcers, directors, employees, agents, servants, successors, assigns and subsidiaries.

4. CONSIDERATION FOR PREPARATION OF TEMPORARY PERMIT. Permittee wil pay toRailroad the sum of Dollars ($ .00) as compensation forthe preparation of this Temporary Permit.

5. STARTING OF USE OF PROPERTY. Permittee shall notify Railroad's Chief Engineer-~tructures, or his designee, at least ten (10) days in advance before entering upon, or starting any

Jrk on, the Propert. No entry upon or use of the Propert wil be permitted until a fully executedcopy of this Temporary Permit is returned to Railroad, and specifc permission to enter upon theProperty is received from Director I&C Projects, 30th Street Station, Box 64, Philadelphia, PA 19104,telephone number 215-349-4971.

Page 65: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

.6: RAILROAD OPERATIONS. All activities by or on behalf of Permittee (and all contractors,subcontractors and/or any other entity or person acting for or by permission of Permittee (hereinaftercollectively called "Contractors") shall be performed so as not to interfere with Railroad's operations orv/"'l. any of Railroad's facilties. In no event shall personnel, equipment or material cross a track ortì..~ks without special advance permission from Railroad's Chief Engineer-Structures or his designee.If, in the opinion of Railroad's Chief Engineer-Structures or his designee, conditions warrant at anytime, Railroad wil provide flag service and/or other protection at the sole cost and exp_ense of

Permittee, and Permittee agrees to pay to Railroad the full cost and expense therefor.

7. CLEARANCES. All equipment and material of Permittee and Contractors shall be kept at alltimes not less than fifteen (1'5) feet from the centerline of the outside track, unless specificallyotherwise authorized in writing by Railroad's Chief Engineer-Structures or his designee. Permittee andContractors shall conduct all operations so that no part of any equipment shall foul an operated track;transmission, communication or signal line; or any other structure or facilty of Railroad.

8. RESTORATION OF PREMISES. Upon completion of its work, Permittee and Contractors shall,at the option of Railroad, (a) leave the Property in a condition satisfactory to Railroad or, (b) restore thePropert to its original condition. ïhis may include;without limitation, the restoration of any fencesremoved or damaged by Permittee or Contractors.

9. TERM OF PERMIT. This Temporary Permit shall commence on the date Railroad receives afully executed copy of this Temporary Permit pursuant to paragraph 15 hereof and shall extend untilthe end of the period Railroad determines is necessary for Permittee to accomplish the purpose setforth in Paragraph 1; provided, however, Railroad reserves the right to revoke this Temporary Permit?f~ny time, and in no event shall this Temporary Permit extend beyond ,2001.'- Jler no circumstances shall this Temporary Permit be construed as granting to Permittee orContractors any right, title or interest of any kind or character in, on, or about any property of Railroad.

10. PROTECTION. All work in, on, or about the Property shall be in accordance with the documententitled "SPECIFICATIONS REGARDING SAFETY AND PROTECTION OF RAILROAD TRAFFICAND PROPERTY," a copy of which is attached hereto as Exhibit A and incorporated herein byreference. -11. INSURANCE. Before Permittee or Contractors commence any work in, on, or about theProperty, Permittee, and Contractors (unless Permittee opts to provide coverage for them), shailfurnish to Director I&C Projects, with evidence of Workers' Compensation, Commercial GeneralLiability Insurance, and other coverages, as specified in the document entitled "INSURANCEREQUIREMENTa - NATIONAL RAILROAD PASSENGER CORPORATION," a copy of which isattached hereto as Exhibit B and incorporated here by reference.

12. SAFETY ORI ENTATION CLASS. No person may enter within twenty-five (25) feet of the.Property until he/she has attended Railroad's Safety Orientation Class, as noted in paragraph (11) ofExhibit A.

13. COMPLIANCE BY CONTRACTORS. Permittee shall take all steps necessary to assure thatContractors comply with the terms and conditions of this Temporary Permit.

2

Page 66: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

. ,14. LABOR CHARGES: PAYMENTS, Railroad's labor charges wil be biled to Permittee at. Railroad's standard force account rates. Except as specified in Paragraph 4 hereof, all costs,

payments and other amounts due from Permittee to Railroad under this Temporary

Permit shall be due".-'id payable within thirt (30) days from the date of invoice therefor. Permittee shall have no right to\ Jt off against any payment due under this Temporary Permit any sums which Permittee may believeare due to it from Railroad for any reason whatsoever. In the event that Permittee shall fail to pay,when due, any amount payable by it under this Temporary Permit, Permittee shall alsQ pay to Railroad.together with such overdue payment, interest on the overdue amount at an annual rate of six (6)percentage points over and above the rate published from time to time by The Wall Street Journal asthe prime commercial lending rate (or the highest rate allowed bylaw, if less than the foregoing),calculated from the date the payment was due until paid. All payments due from Permittee to Railroadhereunder shall be: (a) made by check drawn from currently available funds; (b) deemed made onlyupon receipt by Railroad of collected funds; (c) made payable to National Railroad PassengerCorporation; and (d) delivered to the National Railroad Passenger Corporation, P.O. Box 18266F,St. Louis, Missouri, 63150. All payment obligations of Permittee under this Temporary Permit shallsurvive the termination or expiration of this Temporary Permit.

i5. ACCEPTANCE,'.Toconfirm acceptance of

this TemporaryPermit, one fuliy executed

'copy mustbe returned to: Director I&C Projects, National Railroad Passenger Corporation. 30th Street Station.Box 64, Philadelphia, PA 19104. The second copy may be retained for your file.

NATIONAL RAILROAD PASSENGER CORPORATION

Bv:

-,_ J JAMES S. RICHTER, P. E.CHIEF ENGINEER - STRUCTURES

Date:

AGREED TO AND ACCEPTED:

By:

(signature)

Title:Must be an Owner/Partner orduly authorized representative

Date:

bc: File

JSRlKLKI

3

Page 67: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

i EXHIBIT A

SPECIFICATIONS REGARDING SAFETYAND PROTECTION OF RAILROAD TRAFFIC AND PROPERTY

National Railroad Passenqer Corporation (Railroad)

In the following Specifications "Chief Engineer" shall mean Railroad's Vice President,Chief Engineer, "Railroad" shall mean the National Railroad Passenger Corporation,and/or his/her duly authorized representative,

(1) Pre-Entry Meetinq: Before entry of Permittee and/or Contractors onto Railroad'sproperty, a pre-entry meeting shall be held at which time Permittee and/or Contractorsshall submit for written approval of the Chief Engineer, plans, computations and adetailed description of proposed methods for accomplishing the work, includingmethods for protecting Railroad's traffc. Any such written approval shall not relievePermittee and/or Contractor of their complete responsibility for the adequacy and safetyof their operations.

(2) Rules, Requlations and Requirements: Railroad traffc shall be maintained at alltimes with safety and continuity, and Permittee and/or Contractors shall conduct theiroperations in compliance with all rules, regulations, and requirements of Railroad(including these Specifications) with respect to any work performed on, over, under,within or adjacent to Railroad's property. Permittee and/or Contractors shall beresponsible for acquainting themselves with such rules, regulations and requirements.Any violation of Railroad's safety rules, regulations, or requirements shall be grounds forthe immediate suspension of the Permittee and/or Contractor work, and the re-trainingof all personnel, at the Permittee's expense.

(3) Maintenance of Safe Conditions: If tracks or other property of Railroad areendangered during the work, Permittee and/or Contractor shall immediately take suchsteps as may be directed by Railroad to restore safe conditions, and upon failure ofPermittee and/or Contractor to immediately carry out such direction, Railroad may takewhatever steps are reasonably necessary to restore safe conditions. All costs andexpenses of restoring safe conditions, and of repairing any damage to Railroad's trains,tracks, right-of-way or other property caused by the operations of Permittee and/orContractors, shall be paid by Permittee.

(4) Protection in General: Permittee and/or Contractors shall consult with the ChiefEngineer to determine the type and extent of protection required to insure safety andcontinuity of railroad traffic. Any Inspectors, Track Foremen, Track Watchmen,Flagman, Signalmen, Electric Traction Linemen, or other employees deemed necessaryby Railroad, at its sole discretion, for protective services shall be obtained from Railroadby Permittee and/or Contractors. The cost of same shall be paid directly to Railroad byPermittee. The provision of such employees by Railroad, and any other precautionarymeasures taken by Railroad, shaH not relieve Permittee and/or Contractors from theircomplete responsibility for the adequacy and safety of their operations.

Page 68: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

(5) Protection for Work Near Electrified Track or Wire: Whenever work is performedin the vicinity of electrified tracks and/or high voltage wires, particular care must beexercised, and Railroad's requirements regarding clearance to be maintained betweenequipment and tracks and/or energized wires, and otherwise regarding work in thevicinity of electrified tracks, must be strictly observed. No employees or equipment willbe permitted to work near overhead wires, except when protected by a Class Aemployee of Railroad. Permittee and/or Contractors must supply an adequatelength of grounding cable (410 copper with approved clamps) for each piece ofequipment working near or adjacent to any overhead wire,

)

(6) Foulinq of Track or Wire: No work wil be permitted within twenty-five (25)feet of the centerline of track or the energized wire or have potential of gettingwithin twenty-five (25) feet of track wire without the approval of the ChiefEngineer's representative. Permittee and/or Contractors shall conduct their work so

that no part of any equipment or material shall foul an active track or overhead wirewithout the written permission of the Chief Engineer's representative. WhenPermittee and/or Contractors desire to foul an active track, they must provide theChief Engineer's representative with their site-specifc work plan a minimum oftwenty-one (21) working days in advance, so that, if approved, arrangements maybe made for proper protection of Railroad. Any equipment shair'be considered to be

fouling a track or overhead wire when located (a) within fifteen (15) feet from thecenterline of the track or within fifteen (15) feet from the wire, or (b) in such a positionthat failure of same, with or without a load, would bring it within fifteen (15) feet from thecenterline of the track or within fifteen (15) feet from the wire and requires the presenceof the proper Railroad protection personneL.

If acceptable to the Chief Engineer's representative, a safety barrier (approvedtemporary fence or barricade) may be installed at fifteen (15) feet from centerline oftrack or overhead wire to afford the Permittee and/or Contractor with a work area that isnot considered fouling. Nevertheless, protection personnel may be required at thediscretion of the Chief Engineer's representative.

(7) Track Outaqes: Permittee and/or Contractors shall verify the time and scheduleof track outages from Railroad before scheduling any of their work on, over, under,within, or a,djacent to Railroad's right-of-way, Railroad does not guarantee theavailability of any track outage at any particular time. Permittee and/or Contractorsshall schedule all work to be performed in such a manner as not to interfere withRailroad operations. Permittee and/or Contractors shall use all necessary care andprecaution to avoid accidents, delay or interference with Railroad's trains or otherproperty.

(8) Demolition: During any demolition, the Contractor must provide horizontal andvertical shields, designed by a Professional Engineer registered in the state in which thework takes place. These shields shall be designed in accordance with the Railroad'sspecifications and approved by the Railroad, so as to prevent any debris from fallngonto the Railroad's right-of-way or other property. A grounded temporary verticalprotective barrier must be provided if an existing vertical protective barrier is removedduring demolition. In addition, if any openings are left in an existing bridge deck, a

2

Page 69: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

c.

protective fence must be erected at both ends of the bridge to prohibit unauthorizedpersons from entering onto the bridge.

(9) Equipment Condition: All equipment to be used in the vicinity of operating tracksshall be in "certified" first-class condition so as to prevent failures that might cause delayto trains or damage to Railroad's property. No equipment shall be placed or put intooperation near or adjacent to operating tracks without first obtaining permission from theChief Engineer's representative. Under no circumstances shall any equipment ormaterials be placed or stored within twenty-five (25) feet from the centerline of anoutside track, except as approved by the Site Specific Safety Work Plan, Toinsure compliance with this requirement, Permittee and/or Contractors must establisha twenty-five (25) foot foul line prior to the start of work by either driving stakes,

taping off or erecting a temporary fence, or providing an alternate method as approvedby the Chief Engineer's representative. Permittee and/or Contractors will be issued

warning stickers which must be placed in the operating cabs of all equipment as aconstant reminder of the twenty-five (25) foot clearance envelope.

(10) Storaqe of Materials and Equipment: No material or equipment shall be storedon Railroad's property without first having obtained permission from the Chief Engineer.Any such storage will be on the condition that Railroad will not be liable for loss of ordamage to such materials or equipment from any cause.

/(11) Condition of Railroad's Property: Permittee and/or Contractors shall keep

Railroad's property clear of all refuse and debris from its operations. Upon completionof the work, Permittee and/or Contractors shall remove from Railroad's property allmachinery, equipment, surplus materials, falsework, rubbish, temporary structures, andother property of the Permittee and/or Contractors and shall leave Railroad's property ina condition satisfactory to the Chief Engineer,

(12) Safety Traininq: All individuals, including representatives and employees ofthe Permittee and/or Contractors, before entering onto Railroad's property or

coming within twenty-five (25) feet of the centerline of the track or energizedwire shall first attend Railroad's Safety Contractor/Leasee Employee TrainingClass. The Safety Orientation Class will be provided by Railroad's SafetyRepresentative at Permittee's expense. A photo 1.0. will be issued and must beworn/displayed while on Railroad property. All costs of complying with Railroad's safetytraining shall be at the sole expense of Permittee, Permittee and/or Contractors shallappoint a qualified person as their Safety Representative. He/she shall continuouslyassure that all individuals comply with Railroad's safety requirements. All safetytraining records shall be maintained with site specific work plan.

(13) No Charqes to Railroad: It is expressly understood that neither theseSpecifications, nor any document to which they are attached, include any work for whichRailroad is to be billed by Permittee and/or Contractors, unless Railroad gives a writtenrequest that such work be performed at Railroad's expense.

Revised December 2000

3

Page 70: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

EXHIBIT B

INSURANCE REQUIREMENTS FOR TEMPORARY PERMIT TO ENTERNATIONAL RAILROAD PASSENGER CORPORATION

(AMTRAK)Revised as of December 2000

DEFINITIONS

Whenever in these Insurance Requirements or in the plans or contract documents thewords "Company," "Railroad," or "Amtrak" are used, the same shall mean NationalRailroad Passenger Corporation, "Contractor" shall be defined as the party identifiedas "Permittee" in the Permit to Enter Agreement, as well as its officers, employees,agents, servants, contractors, subcontractors, or any other person acting for or bypermission of Permittee or the party identified as Contractor in the PreliminaryEngineering Agreement or Force Account Agreement, as well as its officers,employees, agents, servants, contractors, subcontractors, or any other person actingfor or by permission of Contractor. "Operations" shall be defined as activities of or workperformed by Contractor, its officers, employees, agents, servants, contractors,subcontractors, or any other person acting for or by permission of Contractor.Agreement shall be defined as the Permit to Enter Agreement, Preliminary EngineeringAgreement, and/or Force Account Agreement.

INSURANCE

The Contractor shall procure and maintain, at its sole cost and expense, the types ofinsurance specified below. Contractor shall evidence such coverage by submittingCertificate(s) of Insurance for Workers' Compensation, Commercial General Liabilityand Automobile Liabilty, and the original Railroad Protective Liabilty Policy, prior tocommencement of Operations. All insurance shall be procured from insurersauthorized to do business in the jurisdiction(s) where the Operations are to beperformed. The Contractor shall require all subcontractors to carry the insurancerequired herein, or Contractor may, at its option, provide the coverage for any or allsubcontractors, provided the evidence of insurance submitted by Contractor to Amtrakso stipulates. The insurance specified below shall provide for thirt (30) days priorwritten notice to Amtrak in the event coverage is substantially changed, canceled ornon-renewed, All insurance specified below shall remain in force until all Operationsare satisfactorily completed, all contractor personnel and equipment have beenremoved from railroad property, and any work has been formally accepted.Contractor's failure to comply with the insurance requirements set forth herein shallconstitute a violation of this Agreement.

Page 71: AMTRAK CONTRACT …knowledge.urbanengineers.com/assets/AMTRAK... · EP 3014 01142A of Plans for Bridge Erection, ... ditches, pipes, catch basins and detention basins. b. ... ERECTION

Workers' Compensation Insurance complying with the requirements of thestatutes of the jurisdiction(s) in which the Operations wil be performed, coveringall employees of Contractor. Employer's Liabilty coverage with limits of not lessthan $1 million each accident or ilness shall be included.

In the event the Operations are to be performed on or over navigable waterways, aLongshoremen and Harbor Workers' Compensation Act Endorsement and a MaritimeCoverage Endorsem'ent are to be added, including coverage for wages, transportation,maintenance and cure.

Commercial General Liabilty Insurance covering liabilty of the Contractor withrespect to all Operations to be performed and all obligations assumed by the Contractorunder the terms of this Agreement. Products-completed operations, independentcontractors and contractual liability coverages are to be included, with the contractualexclusion related to construction/demolition activity within fifty (50) feet of the railroadand any X-C-U exclusions deleted. The policy shall name Amtrak as an additionalinsured with respect to the Operations to be performed. Coverage under this policy, orpolicies, shall have limits of liabilty of not less than $2 million per occurrence, combinedsingle limit, for bodily injury (including disease or death), personal injury and propertydamage (including loss of use) liability.

Automobile Liabilty Insurance covering the liabilty of Contractor arising out of theuse of ANY VEHICLES which bear, or are required to bear, license plates according tothe laws of the jurisdiction in which they are to be operated, and which are not coveredunder the Contractor's Commercial General Liabilty insurance. The policy shall nameAmtrak as an additional insured with respect to the Operations to be performed.Coverage under this policy shall have limits of liabilty of not less than $1 millon peroccurrence, combined single limit, for bodily injury and property damage (including lossof use) liability.

Railroad Protective Liabilty Insurance covering the Operations performed by

Contractor or any subcontractor within fifty (50) feet vertically or horizontally of railroadtracks. The AAR-AASHTO (ISO/RIMA) Occurrence Form (claims-made forms areunacceptable) in the name of the National Railroad Passenger Corporation (and anyother railroad operating over the tracks) shall have limits of liabilty of not less than$2 millon per occurrence, combined single limit, for Coverages A and B, for lossesarising out of injury to or death of all persons, and for physical loss or damage to ordestruction of property, including the loss of use thereof. A $6 millon annual aggregateshall apply, Additionally, Policy Endorsement CG 28 31 - Pollution ExclusionAmendment, is required to be endorsed onto the policy.