an innovative approach to small bridge …
TRANSCRIPT
AN INNOVATIVE APPROACH TO SMALL
BRIDGE REHABILITATION
Peter Marchant
ITS Pipetech Pty Ltd,
NSW Australia
Introduction
Summary
Since first construction our principle infrastructure we are witnessing
• Increasing traffic frequency
• Heavier loading
• Requirement for a longer working life
• Increasing demands on Design
• Ever changing Design Codes
• Less opportunity for infrastructure closures
• Need for a different approach to maintain serviceability
• Keep the infrastructure open
Alternative to New Build
• Planned Inspections
• Maintenance &
Remediation
• Think out of the Box
• Understand the
Demands on the
Structure
• Simple information
provision can save
significant cost
Conditions leading to failure
Deteriorating Arch ring material
Loss of Arch thickness
Foundation movement
Loss of Arch support
Foundation scour
Impact damage
Weak or uncompacted or over
compacted fill
Water ingress and erosion
Poor design
Simple Testing
Hammer Testing
Acoustic Emission
Radar
Thermal Imaging
Ultrasonic Testing
Loading
Considerations & Assumptions
• Consider the original methodology of construction
• Potential loss of bedding and support at the side zones and deteriorated condition
• Full or partial rehabilitation
• In the absence of physical data assume the worst and design as a stand alone element
Modelling
• Modeling using the FE analysis program i.e. Strand 7, Plaxis etc.
• Two dimensional Beam model to represent the point load test as AS/NZ3725
• Three Dimensional Modelling
• Outputs determine the Concrete and Reinforcement requirements
Design
Philosophy & Parameters
• Designed as a Buried pipe to Australian Standard AS/NZ3725
• Loading to AS/NZ5100 Road & rail
• Deflection and point load tests to AS/NZ 4058
• Concrete design in accordance with AS 3600
• Design life requirement - 100 years
Design Considerations
• Soil cover
• Deformation
• Extent of Corrosion
• Rail & Road loading
• Soil Modulus
• Support Zone Compaction probing
Concrete Mix Design
• Need to ensure Quality in consistent concrete is fundamental
• Designs to AS3600
• Test and trial mixings
• Computer controlled batching for mix traceability
• Mix blending is critical
• QA testing and site checks fundamental
Concrete & Rebar design
Reinforcement Specifications
• Single or Twin Cage Reo
• Elliptical cages Deformed bar- N12 to
N20
• Distribution bar N12 to N16
• Steel Dramix fibre
Concrete Specifications
• 40, 50 & 60 Mpa special design mix -
10mm aggregate with super plasticizer
• Fly Ash or GGBS replacement
Temporary Works
• Super strong light weight modular panel system
• Each Panel weighing less than 60 Kg
• Smooth external surface
• Design checked using FE modelling
• Design sign off to Australian Standards
Profiles
Using Tunneline for Rehabilitation on Bridges
Full profile Rehab
Top Arch
Abutments
Parabolic Arches
Jack Arches
Box Bridges
Applications
Arch Bridges
Flat deck bridges
Circular Culverts
Elliptical Bridge Culverts
Box Bridge Culverts
Pedestrian Underpass
Installation
Installation
• Initially set the invert
• Followed by sides
• Finally crown panel
• Stop End
• Concrete
• Strike and move forward
Site Quality Control Reinforcement
• Accuracy in placement
• Stability of the cage during erection
• Quality Procedures to ensure
standards are met
• Final sign off pre formwork erection
Quality Control Site Procedures
• Developed ITP with hold & verification points
• Concrete Testing pre start
• Design verification by third party
• Pre shutter build check sheet
• Pre pour check sheet
• Concrete Slump and Cylinder tests
• Final visual inspection
Pre Pour Inspection
Quality Management ITS-FM-QA-069 [1]
DETAILS OF POUR (to be completed and approved prior to pour)
CONTRACT/SITE NAME: DATE: ITS ENGINEER:
CONTRACT No: DAY: ITS SUPERVISOR:
CONTRACTOR: WEATHER: DRAWING NO:
SUPPLIER: AMBIENT TEMP: INSTALLATION METHOD:
TESTING REQUIREMENTS:
SHUTTER SIZE: SHAPE: CLEANLINESS REINFORCEMENT WITHIN
TOLERANCES PERMIT TO LOAD
CHAIN YES NO YES NO YES NO YES NO
Tolerances Height :- Plus or Minus 15mm
Width :- Plus or Minus 15mm
Level :- Plus or Minus 5mm
SIGNED FOR ITS DATE & TIME SIGNED FOR VicRoads DATE & TIME
DISTRIBUTION SITE Q.A FILE
CLIENT
OTHERS
Shutter Erection Tolerance Checklist
Quality Management ITS-FM-QA-077 [1]
CONTRACT NAME: DATE: ENGINEER:
CONTRACT No: DAY: SUPERVISOR:
CONTRACTOR: SHUTTER SIZE: SHAPE: DATE CHAIN WIDTH HEIGHT LEVEL DATE CHAIN WIDTH HEIGHT LEVEL
2 52
4 54
6 56
8 58
10 60
12 62
14 64
16 66
18 68
20 70
22 72
Tolerances Height :- Plus or Minus 15mm 24 74
Width :- Plus or Minus 15mm 26 76
Level :- Plus or Minus 5mm 28 78
30 80
32 82
34 84
36 86
38 88
40 90
DISTRIBUTION SITE Q.A FILE 42 92
CLIENT 44 94
OTHERS 46 96
48 98
50 100
Benefits
• 100 Year Design Life
• No disruption to the operational infrastructure above
• Flood Immunity is not compromised
• No Road or Track Closures
• Uses time tested materials
• Designed to Australian Standards
• Low carbon footprint
• Quick Program times
Thank You for Your Attention