an insulation co-ordination procedure … insulation co-ordination procedure for power system ......

127
i ANI CHUKWUNONSO CALEB PG/M.ENG/13/66409 AN INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM FACULTY OF ENGINEERING DEPARTMENT OF ELECTRICAL ENGINEERING Azuka Ijomah Digitally Signed by: Content manager’s Name DN : CN = Webmaster’s name O= University of Nigeria, Nsukka OU = Innovation Centre

Upload: nguyendiep

Post on 16-Mar-2018

256 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

i

ANI CHUKWUNONSO CALEB

PG/M.ENG/13/66409

AN INSULATION CO-ORDINATION

PROCEDURE FOR POWER SYSTEM

EQUIPMENT

FACULTY OF ENGINEERING

DEPARTMENT OF ELECTRICAL ENGINEERING

Azuka Ijomah

Digitally Signed by: Content manager’s Name

DN : CN = Webmaster’s name

O= University of Nigeria, Nsukka

OU = Innovation Centre

Page 2: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

ii

DEPARTMENT OF ELECTRICAL ENGINEERING

UNIVERSITY OF NIGERIA NSUKKA

A THESIS SUBMITTED IN PARTIAL FULFILMENT

OF THE REQUIREMENTS FOR THE DEGREE OF

Master of Engineering

TOPIC

AN INSULATION CO-ORDINATION PROCEDURE FOR POWER

SYSTEM EQUIPMENT

BY

ANI CHUKWUNONSO CALEB

PG/M.ENG/13/66409

Page 3: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

iii

SUPERVISOR: PROF. T.C. MADUEME

OCTOBER, 2015

Page 4: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

iv

CERTIFICATION

This is to certify that this project work titled “AN INSULATION COORDINATION

PROCEDURE FOR POWER SYSTEM EQUIPMENT” was carried out by ANI

CHUKWUNONSO CALEB, with Reg. No.: PG/M.ENG/13/66409 in the department of

Electrical Engineering, University of Nigeria Nsukka and meets the regulations governing the

Award of Degree of Master of Engineering(M.ENG) of the University of Nigeria Nsukka

………………………………… ……………..

Engr. Prof. T.C. Madueme Date

(Project Supervisor)

……………………………….. …………….

Engr. Prof E.C Ejiogu Date

(Head of Department)

……………………………… …………….

Prof. A. O. Ibe Date

Page 5: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

v

External Examiner

………………………………… ……………..

Engr. Prof. E. S. Obe Date

Faculty PG Rep.

Page 6: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

vi

APPROVAL

The contentS of this report are true reflection of the project undertaken by Ani Chukwunonso

Caleb (PG/M.ENG/13/66409). It is hereby accepted by the Department of Electrical

Engineering, Faculty of Engineering, University of Nigeria, Nsukka in partial fulfillment of

the requirement of for the award of master of engineering in Electrical Engineering

(M.ENG.) of University of Nigeria, Nsukka.

………………………………… ……………..

Ani Chukwunonso Caleb Date

Student

………………………………… ……………..

Engr. Prof. T.C. Madueme Date

Project Supervisor

……………………………….. …………….

Engr. Prof E.C Ejiogu Date

Head of Department

Page 7: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

vii

……………………………… …………….

Prof. A. O. Ibe Date

External Examiner

………………………………… ……………..

Engr. Prof. E. S. Obe Date

P.G. Faculty Rep.

Page 8: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

viii

DEDICATION

This work is dedicated to the Almighty God and to my Parents; Mr and Mrs Chibuzo Ani.

Page 9: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

ix

ACKNOWLEDGEMENTS

I would like to use this opportunity to express my profound gratitude to my supervisor Prof

T.C. Madueme, for his guidance, encouragement, and total support throughout the course of

this thesis work. It was an extremely useful learning experience for me to be one of his

students. From him I have gained not only extensive knowledge, but also a careful research

attitude.

To Prof E.C. Ejiogu; who taught me that hard work and persistence is an important

research instrument. I also admire the motivation you gave me during my research period.

I also want to appreciate Prof S. E. Obe who has been my guidance and a counselor

during this research period. Moreover, I thank Dr. C.U. Ogbuka, Dr. B.N Nnadi and Engr.

Dr. C.M. Nwosu for your persistent advice as regards my research work. I appreciate all staff

of electrical engineering department and my colleagues in the division of power electronics

group and all the post graduate students in general for their support.

Page 10: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

x

ABSTRACT

Generally, for existing Insulation co-ordination studies the power system has been modeled

either by deterministic mathematical techniques or by statistical methods. The shortcoming of

the existing conventional mathematical technique of Insulation co-ordination analysis is that

it assumes that the power system dynamics is linear. This makes analysis of over voltage

response of the system under transients less optimal for determining over voltage withstand

of system elements. Thus, this work seeks to model a lightning induced over voltage transient

in a High voltage power system substation(132/33KV) used as a case study) using Hidden

Markov Model, to determine the maximum likelihood lightning surge signal. The station

data and configuration was modeled/simulated (in a MATLAB environment), which

implements the algorithms used in the work. The Hidden Markov algorithm(which makes use

of observable parameters to study what is happening at the hidden states), was used to

formulate the problem, while the Baum-welch and Viterbi algorithm were used to

find/identify the maximum likelihood lightning overvoltage waveform. These hidden states

are represented with different scenarios introduced in the work and the waveform identified,

is used to determine the Basic Insulation level(BIL), which is used to determine other

parameters accurately, which in turn helps to ensure an optimal/novel Insulation coordination

procedure for power system equipment in the station.

The results showed that the minimum required margin(15%) exceeded by a little value(i.e.

about 1.08) and the evaluation carried out to raise the protection margin to 18% meant the

relocation of the arrester to within 5.56m of the transformer.

Page 11: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xi

TABLE OF CONTENTS

Pages

Title Page i

Certification ii

Approval iii

Dedication iv

Acknowledgements vi

Abstract vii

Table Of Contents viii

List Of Figures xi

List Of Tables xii

List Of Symbols And Abbreviation xiii

Chapter One: Introduction

1.1 Background of the Study 1

1.2 Statement of the Problem

2

1.3 Objectives of the Study 3

1.4 Significance of the Study 4

Page 12: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xii

1.5 Scope of the Study 5

Chapter Two: Literature Review

2.1 Historical Trends 6

2.2 Definition of Terminology 8

2.3 Over Voltages 11

2.3.1 Power Frequency Overvoltages 13

2.3.2 Overvoltage Caused by an Insulation Fault 13

2.3.3 Overvoltage by Ferromagnetic Resonance 13

2.3.4 Switching Overvoltages 14

2.3.5 Normal Load Switching Overvoltage 14

2.4 Insulation Coordination Principle 14

2.4.1 Highest Power Frequency System Voltage(Continuous) 15

2.4.2 Temporary Power-Frequency Overvoltages 15

2.4.3 Transient Overvoltage Surges 15

2.4.4 Withstand Levels of the Equipment 16

2.5 Line Insulation Coordination 18

2.6 Station Insulation Coordination 20

2.7 Strategy of Insulation Co-Ordination 23

2.7.1 Conventional Method of Insulation Co-Ordination 24

Page 13: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xiii

2.7.2 Statistical Approach to Insulation Coordination 26

2.8 Hidden Markov Model 30

2.8.1 Brief History of Markov Process and Markov Chain 31

2.8.2 Brief History of Algorithms Need to Develop Hidden Markov Models 32

2.8.3 The Expectation-Maximization (E-m) Algorithm 33

2.8.4 The Baum-Welch Algorithm 34

2.8.5 The Viterbi Algorithm 34

2.9 Mathematical Basics of Hidden Markov Models 35

2.9.1 Definition of Hidden Markov Models 35

2.10 Summary of Related Literatures 36

Chapter Three: Research Methodology

3.0 Model Design 37

3.1 The Model Design Strategy 37

3.2 Scenario Description 39

3.2.1 Surge Event Scenario A 39

3.2.2 Surge Event Scenario B 39

3.2.3 Surge Event Scenario C 39

3.3 The Overvoltage Transient Assessment Based on the Hmm 39

3.4 The Overvoltage Training Disturbance Classification 40

3.4.1 The Processing Block 43

Page 14: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xiv

3.5 Computing for the Insulation Coordination 50

3.6 Modeling the Power System 53

3.6.1 Transmission Line Conductors Model 53

3.6.2 Transmission Line Towers Model 54

3.6.3 Surge Arresters Model 54

3.6.4 Transformer Model 54

3.6.5 Lightning Surge Model 54

3.7 Assumption for Lightning Surge 55

Chapter Four: Simulation and Result Evaluation

4.0 Simulation and Result Evaluation 56

4.1 Simulation of the Three Lightning Overvoltage Transient Scenarios 56

4.1.1 Surge Event Scenario A 60

4.1.2 Surge Event Scenario B 61

4.1.3 Surge Event Scenario C 61

4.2 Waveform at the Strike Point 63

Chapter Five: Recommendation and Conclusion

5.1 Summary 70

Page 15: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xv

5.2 Conclusion 71

5.3 Recommendation 71

5.4 Suggestion for Further Studies 72

References 73

Appendix 76

LIST OF FIGURES

Figure

Pages

2.1 Statistical Impulse Withstand Voltage 10

2.2 Stastical Impulse Voltage 11

2.3 Allegheny Power System's 500-kV Tower. 19

2.4: 330kv Nigeria Power Transmission Tower 20

Page 16: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xvi

2.5 The Strike Distances and Insulation Lengths in a Substation. 21

2.6 Margin of Protection and Insulation Withstand Level 24

2.7 Coordination Using Gaps 25

2.8 Coordination of Bils and Protection Levels Classical Approach) 26

2.9 Method of Describing the Risk of Failure. 28

2.10 Reference Probabilities for Overvoltage and for Insulation Withstand Strength 29

2.11 The Statistical Safety Factor and its Relation to the Risk of Failure 30

3.1: Flow Chart of Proposed Logarithm for Insulation Coordination 42

3.2: Steps for the Signal Processing and Observation Evaluation Problem 43

3.3: Flow Chart of the Hmm Training Process for the Observation Evaluation Problem 46

4.1 Model of the 330kV/132kV Power Station

At New Haven Enugu Nigeria 57

4.2 The illustration of incoming transmission surge wave of scenario A 60

4.3. Resultant Waveform for Surge Event Scenario A 61

4.4. The illustration of incoming transmission surge wave of scenario B1 60

4.5. Resultant Waveform for Surge Event Scenario B 62

4.6 The illustration of incoming transmission surge wave of scenario C 63

4.7. Resultant Waveform for Surge Event Scenario C 64

4.8 Resultant Waveform Of Three Surge Event Scenarios (The Combined Plot) 65

4.9 Resultant Waveform At The Strike Point 66

4.10 Location Of Arrester 4 (On Phase A) To The 132/33kv Transformer Supplying The

Kingsway Line I 68

Page 17: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xvii

LIST OF TABLES

2.1: Characteristics of the various Overvoltages types 12

2.2: Basic Impulse Insulation Levels 16

3.1: Observed electrical feature for HMM classification of the lighting overvoltage transients

of the power system. 44

4.1: Station Parameters/Data supplied by PHCN 58

4.2: Transmission Line data 59

4.3: Corona damping constant 𝐾𝑐𝑜 65

Page 18: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xviii

LIST OF SYMBOLS AND ABBREVIATIONS

HMM: Hidden Markov Model

BIL: Basic Insulation Level

BSL: Basic Switching Level

MV: Mega Volts

PF: Power Frequency

LOV: Lightning Over Voltage:

SOV: Switching Over Voltages

E.H.V: Extra High Voltages

U.H.V: Ultra High Voltages

𝑉𝑆: Statistical Overvoltage

BW: Baum Welch

Page 19: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xix

P(𝑂|λ): Maximum Likelihood Probability

F(𝐼𝑚): Lightning Current Probability

𝐾𝑐𝑜: Corona damping Constant. µs/(KV.m)

IEC: International Electro-technical Commission

IG: Impulse Generator

𝑋𝑝: Limit Overhead line distance within which lightning event occurs, m

T: Longest Travel time of Surge Current, (µs)

𝑈𝑝𝑙 is the lightning impulse protective level of the arrester, KV

U: Overvoltage Amplitude, KV.

𝛽: Reflection Coefficient

𝑆: Steepness of Surge Voltage, Kv/µs.

𝐸𝑡: Surge Voltage at the Transformer Terminal.

𝑙𝑡: Separation between Transformer and the Arrester.

𝐸𝑎: Arrester BIL.

MOP: Margin of Protection.

CFOV: Critical Flashover Voltage.

Page 20: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

xx

CIGRE: Conseil International Des Grands Reseaux Electriques(International Council on

Large Electric Systems).

NEMA: National Electrical Manufacturers Association

NELA: Nigeria Electric Light Association

AIEE: Advanced International Electronic Equipment.

EEI: Edison Electric Institute

CDMA: Code Division Multiple Access

GSM: Global System for Mobile Communication

LAN: Local Area Network

CVT: Capacitor Voltage Transformer.

PHCN: Power Holding Company of Nigeria.

CFO: Critical Flash Over

Page 21: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

1

CHAPTER ONE

INTRODUCTION

1.0 Background of the Study

The demand for the generation and transmission of large amounts of electric power today,

necessitates its transmission at extra-high voltages. In modern times, high voltages are used

for a wide variety of applications covering the power systems, Industry and research

Laboratories. Such applications have become essential to sustain modern civilization[1].

The diverse conditions under which a high voltage apparatus is used necessitate careful

design of its insulation and the electrostatic field profiles[2]. This entails the analysis of the

electrical power system to determine the probability of post insulation flashovers. For

instance, analysis must be carried out to determine that the insulation contained within power

system components like transformers has the acceptable margin of protection. Since the

internal insulation is not self-restoring, a failure is completely unacceptable. An insulation co-

ordination study of a substation will present all the probabilities and margins for all transients

entering the station.

Over voltages are phenomena which occur in power system networks either externally or

internally. The selection of certain level of over voltages which are based on equipment

strength for operation is known as Insulation co-ordination[3]. It is essential for electrical

power engineers to reduce the number of outages and preserve the continuity of service and

electric supply. In another perspective, Insulation co-ordination is a discipline aiming at

achieving the best possible techno-economic compromise for protection of persons and

equipment against over voltages, whether caused by the network or lightning, occurring on

Page 22: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

2

electrical installations. The purpose of Insulation co-ordination is to determine the necessary

and sufficient insulation characteristics of the various network components in order to obtain

uniform withstand to normal voltages and to over voltages of various origins.

However over voltages are extremely hard to calculate. They cannot generally be

predetermined, since they involve incalculable elements which vary from site to site. Hence

effective Insulation co-ordination requires accurate modeling of the power system. Modeling

transmission lines and substations help engineers understand how protection systems behave

during disturbances and faults.

Though a number of techniques have been developed for modeling transient disturbances in

power systems, the problem of doing optimal Insulation co-ordination is still limited by

accurate model of the power system. Generally, for existing Insulation co-ordination studies

the power system has been modeled either by deterministic mathematical techniques or by

statistical methods. The shortcoming of the existing conventional mathematical technique of

Insulation co-ordination analysis is that it assumes that the power system dynamics is linear.

This makes analysis of over voltage response of the system under transients less optimal for

determining over voltage withstand of system elements. While the statistical technique,

though more accurate[4][5][6], is known that the statistical evaluation of the risk cannot be

assessed if the breakdown behavior of the insulation is unknown or if it is referred only to the

basic Impulse level(BIL) of the power system component.

Hence a novel Insulation Co-ordination procedure for power system equipment is proposed in

this work.

1.1 Statement of Problem

Page 23: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

3

With reference to the limitation of the deterministic mathematical and statistical approach of

power system insulation co-ordination, as highlighted in the background of this study. Thus

given a high voltage(HV) power station and its associated transmission line, the problem to

be tackled by this work is to model overvoltage transient disturbance from lightning using

Hidden Markov Model(HMM), to determine the maximum likelihood lightning surge

waveform. This is to enable the determination of voltage stresses within the station during

surge event and to determine voltage withstand of systems insulation elements; i.e. the Basic

Impulse Insulation(BII) in order to determine protection margin based on equipment data and

to make optimal placements of protection devices within the system.

1.2 Objectives of the Study

The major objective of this work is to develop a model that enables the investigation of over

voltages due to lightning voltages in order to effectively carry out insulation Co-ordination of

a high voltage substation power system. Hence, this work realizes the following specific

objectives:

1. To model a lightning induced over voltage transient in a High voltage power system

substation using Hidden Markov Model, to determine the maximum likelihood

lightning surge signal.

2. To carry out simulation of the response of the power system to lightning over voltages

and determining over voltages induced at specific junctions of the substation.

3. To carry out evaluation of the results of the simulation to determine voltage withstand

capabilities(Basic Impulse insulation; BIL), evaluating protection margin based on the

systems equipment data and optimal placement of protection devices throughout the

substation.

Page 24: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

4

4. To carryout validation of the findings and make recommendation for both actual

implementation of the proposed insulation co-ordination technique and

recommendations for further improvement of the technique.

1.3 Significance of the Study

The power system constitutes a huge factor in the national and global economy. When

power system equipment is not properly protected during over voltage, this equipment

gets damaged necessitating repairs. Hence improper equipment protection against

over voltages increases causes of repairs and cost of power system maintenance. This

means substantial impact on the economy. Hence the realization of the objectives of

this study to develop a novel model to enhance the reliability of insulation co-

ordination of power systems is significant to the reduction of system downtime,

reduction of power system repair and maintenance cost. This means the success of

this work helps to enhance the economy, since all modern services (including

banking, telecommunication, agriculture, manufacturing, health care etc.) that depend

on reliable electric energy benefits from interruptible supply of power.

High voltage insulation failure poses danger to persons and equipment. Hence the

significance of a research that seeks to enhance protection technique for persons and

equipment is in no doubt. Therefore, the proposed study presents much promise for

the enhancement of human and equipment safety from over voltages within electric

power systems.

One of the things that hamper effective administration of electric power generation,

transmission and distribution is planning and control. These activities are in turn

Page 25: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

5

hampered by inaccurate evaluation and prediction of equipment and systems failure

rates and lack of reliable probability estimate of post insulation flashovers. This

problem is substantially caused by lack of accurate model of power systems. With

accurate modeling of power system for insulation co-ordination activities, it would be

possible to estimate proper withstand capabilities of power system limits, estimate of

probabilities of failures and proper equipment protection margin. Thus, proper

planning and control of power systems can be done, ensuring effective administration

of electric power systems.

Also, with reference to the modeling of the power system proposed in this study, this

would help increase the understanding of power system engineers about the behavior

of power system components under lightning induced disturbances.

This work makes a contribution regarding the use of Hidden markov model

(HMM), in determining the probabilistic maximum likelihood of surge wave signal,

based on the digital model of a power system. Therefore, this contribution would

benefit further research on both power systems modeling and insulation co-ordination

studies of high voltage power systems.

1.4 Scope of the Study

This work covers modeling of lightning induced overvoltage transients in HV power

substation and its associated transmission lines. It covers insulation coordination, involving

lightning arresters, their placement relative to substation transformers and the evaluation of

protection margin. However, insulation coordination for switching overvoltage and substation

shielding are not considered. PHCN 330/132/33KV Transmission station switch yard New

Haven Enugu, was used as a case study.

Page 26: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

6

Page 27: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

7

CHAPTER TWO

LITERATURE REVIEW

2.1 Historical Trends

Coordination of insulation was not given serious consideration until after the First World

War, mainly because of lack of information on the nature of lightning surges and the surge

strength of apparatus insulation. Since concrete data were lacking on the actual surge strength

of insulation or the discharge characteristics of protective equipment, early attempts at

coordination were rule-of-thumb methods based on experience and individual ideas. The

result was that some parts of the station were over-insulated while others were under-

insulated. Also, the gradual increasing of line insulation in an attempt to prevent line

flashovers were eliminated at the expense of apparatus failures. Growth of power systems

demands for improved power service, and more economical system operation focused more

and more attention on the problems of surge voltages, adequate insulation, and its protection.

Thus, during the period from about 1918 to 1930 considerable work was done by individual

investigators and laboratories in collecting data on natural lightning and in developing

insulation testing methods and technique. Although progress was seemingly slow, it resulted

in a fair knowledge of the nature of lightning surges and the establishment of universal surge

producing and measuring devices. Very little correlation between laboratories was attempted

during that period[7].

In 1930, the NEMA-NELA Joint Committee on Insulation Coordination was formed to

consider laboratory testing technique and data, to determine the insulation levels in common

use, to establish the insulation strength of all classes of equipment, and to establish insulation

levels for various voltage classifications. After ten years of study and collection of data this

Page 28: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

8

schedule was fairly well completed. Numerous articles in trade magazines show the results.

In a report dated January 1941, the committee, now known as the joint AIEE-EEI-NEMA

Committee on Insulation Coordination, rounded out the program by specifying basic impulse

insulation levels for the different voltage classifications.

Test specifications for apparatus are prepared on the basis of demonstrating that the

insulation strength of the equipment will be equal to or greater than the selected basic

insulation level and the protective equipment for the station should be chosen to give the

insulation meeting these levels as good protection as economically justified[7].

The following are the basic definition of insulation coordination in its most fundamental and

simple form:

(a). Insulation coordination is the selection of the insulation strength.

If desired, a reliability criterion and something about the stress placed on the insulation could

be added to the definition. In this case the definition would become

(b). Insulation coordination is the "selection of the insulation strength consistent with the

expected overvoltages to obtain an acceptable risk of failure"[6].

In some cases, engineers prefer to add something concerning surge arresters, thus, the

definition is expanded to

(c). Insulation coordination is the "process of bringing the insulation strengths of electrical

equipment into the proper relationship with expected overvoltages and with the

characteristics of surge protective devices"[8].

The definition could be expanded further to

Page 29: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

9

(d). Insulation coordination is the "selection of the dielectric strength of equipment in relation

to the voltages which can appear on the system for which equipment is intended and taking

into account the service environment and the characteristics of the available protective

devices" [9].

(e). "Insulation coordination comprises the selection of the electric strength of equipment and

its application, in relation to the voltages which can appear on the system for which the

equipment is intended and taking into account the characteristics of available protective

devices, so as to reduce to an economically and operationally acceptable level the probability

that the resulting voltage stresses imposed on the equipment will cause damage to equipment

insulation or affect continuity of service" [10].

2.2 Definition of Terminology used in Insulation Coordination

(i). Nominal System Voltage: It is the r.m.s. phase-to-phase voltage by which a system is

designated. Also it is the phase to phase voltage of the system for which the system is

normally designed. S as 11KV,. S as 11KV,33KV, 132KV, 220KV, 400KV systems[11].

(ii). Maximum System Voltage: It is the maximum rise of the r.m.s. phase-to-phase system

voltage.

(iii). Factor of Earthing: This is the ratio of the highest r.m.s. phase-to-earth power

frequency voltage on a sound phase during an earth fault to the r.m.s. phase-to-phase power

frequency voltage which would be obtained at the selected location without the fault. This

ratio characterizes, in general terms, the earthing conditions of a system as viewed from the

selected fault location.

(iv). Effectively Earthed System

Page 30: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

10

A system is said to be effectively earthed if the factor of earthing does not exceed 80%.

Factor of earthing is 100% for an isolated neutral system, while it is 57.7% (1/√3 = 0.577) for

solidly earthed system.

(v). Insulation Level: Every electrical equipment has to undergo different abnormal transient

over voltage situation in different times during its total service life period. The equipment

may have to withstand lightning impulses, switching impulses and/or short duration power

frequency over voltages. Depending upon the maximum level of impulse voltages and short

duration power frequency over voltages that one power system component can withstand, the

insulation level of high voltage power system is determined.

(vi). Lightning Impulse Voltage: The system disturbances occur due to natural lightning can

be represented by three different basic wave shapes. If a lightning impulse voltage travels

some distance along the transmission line before it reaches to an insulator, its wave shaped

approaches to full wave, and this wave is referred as 1.2/50 wave. If during travelling, the

lightning disturbance wave causes flash over across an insulator the shape of the wave

becomes chopped wave. If a lightning stroke hits directly on the insulator then the lightning

impulse voltage may rise steep until it is relieved by flash over, causing sudden, very steep

collapse in voltage. These three waves are quite different in duration and in shapes[11].

(vii). Switching Impulse: During switching operation a uni-polar voltage appears in the

system. The waveform of which may be periodically damped or oscillating. Switching

impulse wave form has steep front and long damped oscillating tail.

(viii). Short duration power frequency withstand voltage: This is the prescribed rms value

of sinusoidal power frequency voltage that the electrical equipment shall withstand for a

specific period of time normally 60 seconds.

Page 31: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

11

(ix). Protective Level of Protective Device: These are the highest peak voltage value which

should not be exceeded at the terminals of a protective device when switching impulses and

lightning impulses of standard shape and rate values are applied under specific conditions.

(x). Conventional Impulse Withstand Voltages: This is the peak value of the switching or

lightning impulse test voltage at which an insulation shall not show any disruptive discharge

when subjected to a specified number of applications of this impulse under specified

conditions.

(xi). Conventional Maximum Impulse Voltage: This is the peak value of the switching or

lightning overvoltage which is adopted as the maximum overvoltage in the conventional

procedure of insulation co-ordination.

(xii). Statistical Impulse Withstand Voltage: This is the peak value of a switching or

lightning impulse test voltage at which insulation exhibits, under the specified conditions, a

90% probability of withstand. In practice, there is no 100% probability of withstand voltage.

Thus the value chosen is that which has a 10% probability of breakdown[12].

Page 32: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

12

Figure 2.1: Statistical impulse withstand voltage

(xiii). Statistical Impulse Voltage: This is the switching or lightning overvoltage applied to

equipment as a result of an event of one specific type on the system (line energizing,

reclosing, fault occurrence, lightning discharge, etc.), the peak value of which has a 2%

probability of being exceeded[12].

Figure 2.2: Statistical Impulse voltage

Insulation coordination is a discipline aiming at achieving the best possible technico-

economic compromise for protection of persons and equipment against over voltages,

whether caused by the network or lightning, occurring on electrical installations. It helps

ensure a high degree of availability of electrical power. Its value is doubled by the fact that it

concerns high voltage networks. To control insulation coordination:

the level of the possible over voltages occurring on the network must be known;

the right protective devices must be used when necessary;

the correct overvoltage withstand level must be chosen for the various network

components from among the insulating voltages satisfying the particular

constraints[13].

Page 33: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

13

2.3 OVER VOLTAGES

An overvoltage is an abnormal voltage between two points of a system that is greater than the

highest value appearing between the same two points under normal service conditions.

• Overvoltages are the primary “metric” for “measuring” and “quantifying” power system

transients and thus insulation stress.

Also, these are disturbances superimposed on circuit rated voltage. They may occur:

• between different phases or circuits and are said to be differential mode;

• between live conductors and the frame or earth and are said to be common mode.

Their varied and random nature makes them hard to characterize, allowing only a statistical

approach to their duration, amplitudes and effects. Table 2.1 presents the main characteristics

of these disturbances.

In point of fact, the main risks are malfunctions, destruction of the equipment and,

consequently, lack of continuity of service. These effects may occur on the installations of

both energy distributors and users.

Table 2.1: Characteristics of the various Overvoltages types

Overvoltage Type (Cause) MV-HV

overvoltage

coefficient

Time Steepness of

Frequency

front

Damping

At Power frequency (Insulation

Fault

≤ √3

Long > 1s Power

frequency

low

Page 34: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

14

Switching (short-circuit

disconnection)

2 to 4 Short 1ms Medium 1 to

200KHZ

medium

Atmospheric (direct lightning

stroke)

> 4 Very short

1 to 10µs

Very high

1,000KV/µs

high

Source:[13]

Disturbances may result in:

- Short disconnections (automatic reclosing on MV public distribution networks by overhead

lines);

- long disconnections (intervention for changing damaged insulators or even replacement of

equipment).

Protective devices limit these risks. Their use calls for careful drawing up of consistent

insulation and protection levels. For this, prior understanding of the various types of over

voltages is vital[13].

2.3.1 Power frequency overvoltages

This term includes all over voltages with frequencies under 500 Hz. The most common

network frequencies are: 50, 60 and 400 Hz. In normal operating conditions, network voltage

may present short duration power frequency overvoltages (a fraction of a second to a few

hours: depending on network protection and operating mode). Voltage withstand checked by

the standard one-minute dielectric tests is normally sufficient. Determination of this category

of characteristics is simple, and the various insulators are easy to compare.

Page 35: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

15

2.3.2 Overvoltage caused by an insulation fault

An overvoltage due to an insulation fault occurs on a three-phase network when the neutral is

unearthed or impedance-earthed. In actual fact, when an insulation fault occurs between a

phase and the frame or earth (a damaged underground cable, earthing of an overhead

conductor by branches, equipment fault, ...), the phase in question is placed at earth potential

and the remaining two phases are then subjected, with respect to earth, to the phase-to-phase

voltage

U = V √3. (2.1)

Where U is the Line Voltage and V is the phase voltage.

More precisely, when an insulation fault occurs on phase A, an earth fault factor, 𝑆𝑑, is

defined by the ratio of the voltage of phases B and C with respect to earth, to network phase

to neutral voltage.

The following equation is used to calculate𝑆𝑑:

𝑆𝑑 =√3 (𝐾2 + 𝐾 + 1)

𝐾 + 2 (2.2)

2.3.3 Overvoltage by ferromagnetic resonance

In this case the overvoltage is the result of a special resonance which occurs when a circuit

contains both a capacitor (voluntary or stray) and an inductance with saturable magnetic

circuit (e.g. a transformer). This resonance occurs particularly when an operation (circuit

opening or closing) is performed on the network with a device having poles either separate or

with non-simultaneous operation.

2.3.4 Switching overvoltages

Sudden changes in electrical network structure give rise to transient phenomena frequently

resulting in the creation of an overvoltage or of a high frequency wave train of a periodic or

oscillating type with rapid damping[13].

Page 36: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

16

2.3.5 Normal load switching overvoltage

A normal load is mainly resistive, i.e. its power factor is greater than 0.7. In this case,

breaking or making of load currents does not present a major problem. The overvoltage factor

(transient voltage amplitude/operating voltage ratio) varies between 1.2 and 1.5.

2.4 Insulation coordination Principle

Study of insulation coordination of an electrical installation is thus the definition, based on

the possible voltage and overvoltage levels on this installation, of one or more overvoltage

protection levels. Installation equipment and protective devices are thus chosen accordingly.

Protection level is determined by the following conditions:

• Installation

• Environment

• Equipment use.

Study of these conditions determines the overvoltage level to which the equipment could be

subjected during use. Choice of the right insulation level will ensure that, at least as far as

power frequency and switching impulses are concerned, this level will never be overshot.

As regards lightning, a compromise must generally be found between Insulation level,

protection level of arresters, if any, and acceptable failure risk. Proper control of the

protection levels provided by surge limiters requires thorough knowledge of their

characteristics and behavior.

Page 37: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

17

The Insulation requirements are determined by considering the following:

2.4.1 Highest Power Frequency System Voltage(Continuous):

AC network has different nominal power-frequency voltage level(e.g. 400V, 3.3kV, 6.6kV,

11kV, 22kV, 33kV, 66kV, 110kV, 132kV, 220kV, 220kV, 400kV r.m.s. continuous, at 50Hz).

During light-load period, the power frequency voltage at the receiving end of the

transmission line rises. In a well regulated system, the permissible maximum system voltage

allowed is called the highest system voltage. Each nominal voltage level has certain

corresponding highest system voltage(400V, 3.6kV, 7.2kV, 12kV, 24kV, 36kV, 72.5kV,

123kV, 145kV, 245kV and 420kV rms continuous). Each equipment is designed and tested

to withstand the corresponding highest power frequency voltage of that voltage level

continuously without internal/external insulation failure[14].

2.4.2 Temporary Power-Frequency overvoltages:

These overvoltages are caused by load throw-off, faults, resonance, etc. However, there is a

difference between the characteristics of power frequency overvoltages and transient voltage

surges and the corresponding stresses on equipment and surge arresters. The temporary

power-frequency (PF) overvoltages are of 50Hz and of lesser peak, lesser rate of rise and of

longer duration(seconds or even minutes). The protection against temporary PF overvolages

is provided by Inverse definite minimum time(IDMT) overvoltage relays connected to

secondary of bus potential transformer and circuit breakers. The relay and breakers action is

within several tens of milliseconds to a few seconds. The circuit breakers open and the

equipment(such as transformer or bus) is protected against the temporary overvoltage[14].

2.4.3 Transient Overvoltage Surges:

Page 38: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

18

It is caused by lightning, switching, restrikes, travelling waves, etc. Surges in the power

system are of comparatively high peak, high rate of rise and last for a few tens/hundreds of

milliseconds and are therefore called transients. Surges can cause spark-over and flash over

at sharp corners, flash over between phase and earth at the weakest point, breakdown of

gaseous/liquid/solid insulation, failure of transformers and rotating electrical machines. The

failure rate due to lightning and switching has been minimized by proper insulation co-

ordination and surge arrester protection. Several protective devices are installed in the

network to intercept lightning strokes and minimize the peak/rate of rise of surges reaching

the equipment[14].

2.4.4 Withstand Levels of the Equipment:

The BIL (Basic impulse insulation level) is specified and other withstand levels are then

selected from relevant tables provided in standard specifications .

Basic impulse levels are reference levels expressed in impulse crest voltage with a standard

wave not longer than 1.2/50μs wave. Apparatus/equipment should be capable of

withstanding test waves above BIL.

Table 2.2 gives the BIL for various reference class voltages (kV).

Table 2.2: Basic Impulse Insulation Levels

Reference Class kV Standard Basic Impulse

Level kV

Reduced Insulation Levels kV

23 150

34.5 200

46 250

69 350

92 450

115 550 450

138 650 550

161 750 650

Page 39: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

19

196 900

230 1,050 900

287 1,300 1,050

345 1,550 1,300

Source: [14]

The problem of insulation coordination involves not only the protection of equipment but the

protection of the protective devices too. To achieve this, a lightning arrester must be applied

and used on the system in such a way that it will discharge excessive voltage safely to the

ground very quickly and then restore itself as an insulator and protect the equipment

insulation.

For safe operation of the equipment, it should have insulation strength equal to or greater than

the basic standard insulation level and the protective equipment for a station/substation

should be chosen to give the insulation good protection corresponding to the working of these

levels as economically as possible.

To assist in the process of insulation coordination, standard insulation levels have been

recommended.

The problem of insulation co-ordination can be studied under the following three steps:

(i) Selection of a suitable insulation which is a function of reference class voltage (i.e., 1.05 x

working voltage of the system). The table shown above gives the basic impulse insulation

levels (BIL) for various reference class voltages.

(ii) The design of the various equipment must be such that the breakdown or flashover

strength of all insulation in the station equals or exceeds the selected levels as in Table 2.2

above.

Page 40: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

20

(iii) Selection of protective devices that will provide the apparatus as good protection as can

be justified economically.

The above procedure requires that the apparatus under protection shall have a withstand test

value not less than the kV magnitude given in the second column of Table 2.2, irrespective of

the polarity of wave (positive or negative) and irrespective of how the system was earthed.

The third column of Table 2.2 gives the reduced insulation levels which are employed for

selecting insulation levels of solidly grounded system and for systems operating above 345kV

where switching surges are of more importance than the lightning surges.

Usually, insulation coordination is separated into two major parts:

(i) Line insulation coordination, which can be further separated into transmission and

distribution lines.

(ii) Station insulation coordination, which includes generation, transmission, and distribution

substations.

To these two major categories must be added a myriad of other areas such as insulation

coordination of rotating machines, and shunt and series capacitor banks. Let us examine the

two major categories.

2.5 LINE INSULATION COORDINATION

For line insulation coordination, the task is to specify all dimensions or characteristics of the

transmission or distribution line towers that affect the reliability of the line:

(i). The tower strike distances or clearances between the phase conductor and the grounded

tower sides and upper truss.

Page 41: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

21

(ii). The insulator string length.

(iii). The number and type of insulators.

(iv). The need for and type of supplemental tower grounding.

(v). The location and number of overhead ground or shield wires.

(vi). The phase-to-ground midspan clearance.

(vii). The phase-phase strike distance or clearance.

(viii). The need for, rating, and location of line surge arresters.

To illustrate the various strike distances of a tower, a typical 500-kV tower is shown in

Figure 2.3[15].

Considering the center phase, the sag of the phase conductor from the tower center to the

edge of the tower is appreciable. Also the vibration damper is usually connected to the

conductor at the tower's edge. These two factors result in the minimum strike distance from

the damper to the edge of the tower. The strike distance from the conductor yoke to the upper

truss is usually larger. In this design, the strike distance for the outside phase exceeds that for

the center phase. The insulator string length is about 11.5 feet, about 3% greater than the

minimum center phase strike distance[15].

Page 42: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

22

Figure 2.3: Allegheny Power System's 500-kV tower.

Page 43: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

23

Also the Nigeria 330kV Transmission tower is shown in fig. 2.4 below

Figure 2.4: 330kV Nigeria Power Transmission Tower

8.55m

12m

9m 9m

12.82m

Page 44: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

24

2.6 STATION INSULATION COORDINATION

For station insulation coordination, the task is similar in nature. It is to specify

(i). The equipment insulation strength, that is, the BIL and BSL of all equipment.

(ii). The phase-ground and phase-phase clearances or strike distances. Figure 2.5 illustrates

the various strike distances or clearances that should be considered in a substation.

(iii). The need for, the location, the rating, and the number of surge arresters.

(iv). The need for, the location, the configuration, and the spacing of protective gaps.

(v). The need for, the location, and the type (masts or shield wires) of substation shielding.

(vi). The need for the amount, and the method of achieving an improvement in lightning

performance of the lines immediately adjacent to the station.

In these lists, the method of obtaining the specifications has not been stated. To the person

receiving this information, how the engineer decides on these specifications is not of primary

importance, only that these specifications result in the desired degree of reliability[15]. It is

true that the engineer must consider all sources of stress that may be placed on the equipment

or on the tower. That is, he must consider

(a). Lightning overvoltages (LOV), as produced by lightning flashes

(b). Switching overvoltages (SOV), as produced by switching breakers or disconnecting

switches[15].

Page 45: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

25

Figure 2.5: The strike distances and insulation lengths in a substation.

𝑺𝒑𝒑 is phase-phase Clearance/distances, 𝑺𝒑𝒈 is phase-ground clearance/distance.

(c). Temporary overvoltages (TOV) as produced by faults, generator over speed, Ferro-

resonance etc.

(d). Normal power frequency voltage in the presence of contamination

For some of the specifications required, only one of these stresses is of importance.

For example, considering the transmission line, lightning will dictate the location and number

of shield wires and the need for and specification of supplemental tower grounding.

Considering the station, lightning will dictate the location of shield wires or masts. However,

subjective judgment must be used to specify whether shield wires or masts should be used.

The arrester rating is dictated by temporary overvoltages.

Page 46: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

26

In addition, the number and location of surge arresters will primarily be dictated by lightning.

Also, for the line and station, the number and type of insulators will be dictated by the

contamination.

However, in many of the specifications, two or more of the overvoltages must be considered.

For transmission lines, for example, switching overvoltages, lightning, or contamination may

dictate the strike distances and insulator string length. In the substation, however, lightning,

switching surges, or contamination may dictate the BIL, BSL, and clearances.

Since the primary objective is to specify the minimum insulation strength, no one of the

overvoltages should dominate the design. That is, if a consideration of switching overvoltages

results in a specification of tower strike distances, methods should be sought to decrease the

switching overvoltages. In this area, the objective is not to permit one source of overvoltage

stress to dictate design. Carrying this philosophy to the ultimate, results in the objective that

the insulation strength will be dictated only by the power frequency voltage. Although this

may seem ridiculous, it has essentially been achieved with regard to transformers, for which

the 1-hour power frequency test is considered by many to be the most severe test on the

insulation.

In addition, in most cases, switching surges are important only for voltages of 345kV and

above. That is, for these lower voltages, lightning dictates larger clearances and insulator

lengths than do switching overvoltages. As a caution, this may be untrue for "compact"

designs[15].

2.7 Strategy of Insulation Co-ordination:

The problem of overvoltages and insulation co-ordination can be solved by the following

steps:

Page 47: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

27

(i). Each equipment/apparatus has specified power-frequency withstand level and impulse

Withstand levels.

(ii). The Withstand levels of Equipment/apparatus/machines are co-ordinated with the

protective voltage level of the nearest lightning arrester. Protective levels of lightning

arrester at each voltage level shall be coordinated.

(iii). Every equipment is well protected and overall economy and reliability is achieved.

In the event of occurrence of severe voltage surge the damage is to the least costly

equipment.

(iv). Duplicate surge protection is provided in substations, one lightning arrester per phase

at incoming bus and another lightning arrester at transformer terminals for each phase.

(v). System neutral is grounded at every voltage level to reduce coefficient of grounding

and to discharge the surges.

Insulation coordination covers the following aspects:

a. The causes and effects of transient overvoltages (surges) and the protection of

electrical equipment insulation.

b. Standardization of nominal voltage levels and highest voltage levels in the network.

c. Choices of power frequency withstand values for equipment insulation.

d. Choice of BIL and switching impulse withstand levels for equipment insulation.

2.7.1 Conventional method of insulation co-ordination

Page 48: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

28

In order to avoid insulation failure, the insulation level of different types of equipment

connected to the system has to be higher than the magnitude of transient overvoltages that

appear on the system. The magnitude of transient over-voltages are usually limited to a

protective level by protective devices. Thus the insulation level has to be above the protective

level by a safe margin. Normally the impulse insulation level is established at a value 15-

25% above the protective level. Figure 2.5 below illustrates the margin of protection and

insulation level[15]:

Figure 2.6: Margin of Protection and Insulation Withstand level

Consider the typical co-ordination of a 132 kV transmission line between the transformer

insulation, a line gap (across an insulator string) and a co-coordinating gap (across the

transformer bushing) as shown in Fig. 2.7.

Page 49: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

29

Figure 2.7: Coordination using gaps

[Note: In a rural distribution transformer, a lightning arrester may not be used on account of

the high cost and a coordinating gap mounted on the transformer bushing may be the main

surge limiting device]

In coordinating the system under consideration, we have to ensure that the equipment used is

protected, and that inadvertent interruptions are kept to a minimum. The coordinating gap

must be chosen so as to provide protection of the transformer under all conditions. However,

the line gaps protecting the line insulation can be set to a higher characteristic to reduce

unnecessary interruptions.

A typical set of characteristics for insulation co-ordination by conventional methods, in

which lightning impulse voltages are the main source of insulation failure.

Page 50: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

30

For the higher system voltages, the simple approach used above is inadequate. Also,

economic considerations dictate that insulation co-ordination be placed on a more scientific

basis.

2.7.2 Statistical approach to insulation coordination

In the early days insulation levels for lightning surges were determined by evaluating the 50

per cent flashover values (BIL) for all insulations and providing a sufficiently high withstand

level that all insulations would withstand.

For those values a volt–time characteristic was constructed. Similarly the protection levels

provided by protective devices were determined. The two volt–time characteristics are shown

in Figure 2.8. The upper curve represents the common BIL for all insulations present, while

the lower represents the protective voltage level provided by the protective devices. The

difference between the two curves provides the safety margin for the insulation system[16].

Thus the

Protection ratio = Max.voltage it permits

Max.surge voltage equipment withstands (2.3)

A: Protecting device

B: device to be protected

Safety margin

Time (µs)

Voltage (KV)

B

A

Page 51: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

31

Figure 2.8: Coordination of BILs and protection levels (classical approach)

This approach is difficult to apply at e.h.v. and u.h.v. levels, particularly for external

insulations.

Present-day practices of insulation coordination rely on a statistical approach which relates

directly the electrical stress and the electrical strength. This approach requires a knowledge of

the distribution of both the anticipated stresses and the electrical strengths.

The statistical nature of overvoltages, in particular switching overvoltages, makes it

necessary to compute a large number of overvoltages in order to determine with some degree

of confidence the statistical overvoltages on a system. The e.h.v. and u.h.v. systems employ a

number of non-linear elements, but with today’s availability of digital computers the

distribution of overvoltages can be calculated. A more practical approach to determine the

Page 52: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

32

required probability distributions of a system’s overvoltages employs a comprehensive

systems simulator, the older types using analogue units, while the newer employ real time

digital simulators (RTDS).

For the purpose of coordinating the electrical stresses with electrical strengths it is convenient

to represent the overvoltage distribution in the form of probability density function (Gaussian

distribution curve) and the insulation breakdown probability by the cumulative distribution

function. The knowledge of these distributions enables us to determine the ‘risk of failure’. As

an example, let us consider a case of a spark gap for which the two characteristics apply and

plot these as shown in Fig. 2.9[16]

Figure 2.9: Method of describing the risk of failure. 1. Overvoltage distribution–Gaussian

function. 2. Insulation breakdown probability–cumulative distribution)

If 𝑉𝑎 is the average value of overvoltage, 𝑉𝑘 is the kth value of overvoltage, the probability of

occurrence of overvoltage is 𝑃𝑜(𝑉𝑘) du, whereas the probability of breakdown is 𝑃𝑏(𝑉𝑘) or the

Page 53: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

33

probability that the gap will break down at an overvoltage 𝑉𝑘 is 𝑃𝑏(𝑉𝑘)𝑃𝑜(𝑉𝑘)du. For the total

voltage range we obtain for the total probability of failure or ‘risk of failure’[16].

R = ∫ 𝑃𝑏(𝑉𝑘)𝑃𝑜(𝑉𝑘) du.∞

0 (2.4)

The risk of failure will thus be given by the shaded area under the curve R.

In engineering practice it would become uneconomical to use the complete distribution

functions for the occurrence of overvoltage and for the withstand of insulation and a

compromise solution is accepted as shown in Figs 2.10(a) and (b) for guidance. Curve (a)

represents probability of occurrence of overvoltages of such amplitude (𝑉𝑠) that only 2 per

cent (shaded area) has a chance to cause breakdown. 𝑉𝑠 is known as the ‘statistical

overvoltage’. In Fig. 2.10(b) the voltage 𝑉𝑤 is so low that in 90 per cent of applied impulses,

breakdown does not occur and such voltage is known as the ‘statistical withstand voltage’ 𝑉𝑤.

Figure 2.10: Reference probabilities for overvoltage and for insulation withstand strength

In addition to the parameters statistical overvoltage ‘𝑉𝑆’ and the statistical withstand voltage

‘VW’ we may introduce the concept of statistical safety factor 𝛾. This parameter becomes

readily understood by inspecting Figs. 2.11(a) to (c) in which the functions 𝑃𝑏 (V) and 𝑃𝑜 (𝑉𝑘)

Page 54: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

34

are plotted for three different cases of insulation strength but keeping the distribution of

overvoltage occurrence the same. The density function 𝑃𝑜 (𝑉𝑘) is the same in (a) to (c) and the

cumulative function giving the yet undetermined withstand voltage is gradually shifted along

the V-axis towards high values of V. This corresponds to increasing the insulation strength by

either using thicker insulation or material of higher insulation strength. As a result of the

relative shift of the two curves [𝑃𝑏 (V) and 𝑃𝑂(𝑉𝑘)] the ratio of the values 𝑉𝑊/𝑉𝑠 will vary.

This ratio is known as the statistical safety factor or

𝛾 = 𝑉𝑤

𝑉𝑠 (2.5)

Figure 2.11: The statistical safety factor and its relation to the risk of failure (R)

In the same figure (d) is plotted the relation of this parameter to the ‘risk of failure’. It is clear

that increasing the statistical safety factor will reduce the risk of failure (R), but at the same

Page 55: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

35

time will cause an increase in insulation costs. The above treatment applies to self-restoring

insulations. In the case of non-self-restoring insulations, the electrical withstand is expressed

in terms of actual breakdown values. The statistical approach to insulation, presented here,

leads to withstand voltages (i.e. probability of breakdown is very small), thus giving us a

method for establishing the ‘insulation level’[16].

2.8 HIDDEN MARKOV MODEL

Hidden Markov Models (HMMs) are learnable finite stochastic automates. Nowadays, they

are considered as a specific form of dynamic Bayesian networks. Dynamic Bayesian

networks are based on the theory of Bayes[17].

A Hidden Markov Model consists of two stochastic processes. The first stochastic process is

a Markov chain that is characterized by states and transition probabilities. The states of the

chain are externally not visible, therefore “hidden”. The second stochastic process produces

emissions observable at each moment, depending on a state-dependent probability

distribution. It is important to notice that the denomination “hidden” while defining a Hidden

Markov Model is referred to the states of the Markov chain, not to the parameters of the

model.

The history of the HMMs consists of two parts. On the one hand there is the history of

Markov process and Markov chains, and on the other hand there is the history of algorithms

needed to develop Hidden Markov Models in order to solve problems in the modern applied

sciences by using for example a computer or similar electronic devices[17].

2.8.1 Brief history of Markov process and Markov chains

Andrey Andreyevich Markov (June 14, 1856 – July 20, 1922) was a Russian mathematician.

Page 56: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

36

He is best known for his work on the theory of stochastic Markov processes. His research

area later became known as Markov process and Markov chains.

Andrey Andreyevich Markov introduced the Markov chains in 1906 when he produced the

first theoretical results for stochastic processes by using the term “chain” for the first time. In

1913 he calculated letter sequences of the Russian language[17].

A generalization to countable infinite state spaces was given by Kolmogorov (1931). Markov

chains are related to Brownian motion and the ergodic hypothesis, two topics in physics

which were important in the early years of the twentieth century. But Markov appears to have

pursued this out of a mathematical motivation, namely the extension of the law of large

numbers to dependent events.

Out of this approach grew a general statistical instrument, the so-called stochastic Markov

process. In mathematics generally, probability theory and statistics particularly, a Markov

process can be considered as a time-varying random phenomenon for which Markov

properties are achieved. In a common description, a stochastic process with the Markov

property, or memorylessness, is one for which conditions on the present state of the system,

its future and past are independent[17].

Markov processes arise in probability and statistics in one of two ways. A stochastic process,

defined via a separate argument, may be shown (mathematically) to have the Markov

property and as a consequence to have the properties that can be deduced from this for all

Markov processes. Of more practical importance is the use of the assumption that the Markov

property holds for a certain random process in order to construct a stochastic model for that

process. In modeling terms, assuming that the Markov property holds is one of a limited

number of simple ways of introducing statistical dependence into a model for a stochastic

Page 57: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

37

process in such a way that allows the strength of dependence at different lags to decline as the

lag increases.

Often, the term Markov chain is used to mean a Markov process which has a discrete (finite

or countable) state-space. Usually a Markov chain would be defined for a discrete set of times

(i.e. a discrete-time Markov Chain) although some authors use the same terminology where

"time" can take continuous values.

2.8.2 Brief history of algorithms needed to develop Hidden Markov Models

With the strong development of computer sciences in the 1940's, after research results of

scientist like John von Neuman, Turing, Conrad Zuse, the scientists all over the world tried to

find algorithms solutions in order to solve many problems in real live by using deterministic

automate as well as stochastic automate. Near the classical filter theory dominated by the

linear filter theory, the non-linear and stochastic filter theory became more and more

important. At the end of the 1950's and the 1960's we can notice in this category the

domination of the "Luenberger-Observer", the "Wiener-Filter", the „Kalman-Filter" or the

"Extended Kalman-Filter" as well as its derivatives[17].

At the same period in the middle of the 20th century, Claude Shannon (1916 – 2001), an

American mathematician and electronic engineer, introduced in his paper "A mathematical

theory of communication'', first published in two parts in the July and October 1948 editions

of the Bell System Technical Journal, a very important historical step, that boosted the need

of implementation and integration of the deterministic as well as stochastic automate in

computer and electrical devices.

Page 58: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

38

Further important elements in the History of Algorithm Development are also needed in order

to create, apply or understand Hidden Markov Models:

2.8.3 The expectation-maximization (EM) algorithm:

The recent history of the expectation maximization algorithm is related with history of the

Maximum-likelihood at the beginning of the 20th century[17]. R. A. Fisher strongly used to

recommend, analyze and make the Maximum-likelihood popular between 1912 and 1922,

although it had been used earlier by Gauss, Laplace, Thiele, and F. Y. Edgeworth. Several

years later the EM algorithm was explained and given its name in a paper in 1977 by Arthur

Dempster, Nan Laird, and Donald Rubin in the Journal of the Royal Statistical Society. They

pointed out that the method had been "proposed many times in special circumstances" by

other authors, but the 1977 paper generalized the method and developed the theory behind it.

An expectation-maximization (EM) algorithm is used in statistics for finding maximum

likelihood estimates of parameters in probabilistic models, where the model depends on

unobserved latent variables. EM alternates between performing an expectation (E) step,

which computes an expectation of the likelihood by including the latent variables as if they

were observed, and maximization (M) step, which computes the maximum likelihood

estimates of the parameters by maximizing the expected likelihood found on the E step. The

parameters found on the M step are then used to begin another E step, and the process is

repeated. EM is frequently used for data clustering in machine learning and computer vision.

In natural language processing, two prominent instances of the algorithm are the Baum-

Welch algorithm (also known as "forward-backward") and the inside-outside algorithm for

unsupervised induction of probabilistic context-free grammars. Mathematical and algorithmic

basics of Expectation Maximization algorithm, specifically for HMM Applications, will be

introduced in the following parts of this chapter.

Page 59: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

39

2.8.4 The Baum-Welch algorithm:

The Baum–Welch algorithm is a particular case of a generalized expectation-

maximization[17]. The Baum–Welch algorithm is used to find the unknown parameters of a

hidden Markov model (HMM). It makes use of the forward-backward algorithm and is

named by Leonard E. Baum and Lloyd R. Welch. One of the introducing papers for the

Baum-Welch algorithm was presented 1970 "A maximization technique occurring in the

statistical analysis of probabilistic functions of Markov chains",[17]. Mathematical and

algorithmic basics of the Baum-Welch algorithm specifically for HMM-Applications will be

introduced in the following parts of this chapter.

2.8.5 The Viterbi Algorithm:

The Viterbi algorithm was conceived by Andrew Viterbi in 1967 as a decoding algorithm for

convolution codes over noisy digital communication links. It is a dynamic programming

algorithm[17]. For finding the most likely sequence of hidden states, called the Viterbi path

that results in a sequence of observed events. During the last years, this algorithm has found

universal application in decoding the convolution codes, used for example in CDMA and

GSM digital cellular, dial-up modems, satellite, deep-space communications, and 802.11

wireless LANs. It is now also commonly used in speech recognition applications, keyword

spotting, computational linguistics, and bioinformatics. For example, in certain speech-to-text

recognition devices, the acoustic signal is treated as the observed sequence of events, and a

string of text is considered to be the "hidden cause" of the acoustic signal. The Viterbi

algorithm finds the most likely string of text given the acoustic signal[17]. Mathematical and

algorithmic basics of the Viterbi-Algorithm for HMM-Applications.

2.9 Mathematical basics of Hidden Markov Models

Page 60: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

40

2.9.1 Definition of Hidden Markov Models

A Hidden Markov Model is a finite learnable stochastic automate.

It can be summarized as a kind of double stochastic process with the two following aspects:

• The first stochastic process is a finite set of states, where each of them is generally

associated with a multidimensional probability distribution. The transitions between the

different states are statistically organized by a set of probabilities called transition

probabilities[17].

• In the second stochastic process, in any state an event can be observed. Since we will just

analyze what we observe without seeing at which states it occurred, the states are "hidden" to

the observer, therefore the name "Hidden Markov Model".

Each Hidden Markov Model is defined by states, state probabilities, transition probabilities,

emission probabilities and initial probabilities.

In order to define an HMM completely, the following five Elements have to be defined:

(i). The N states of the Model, defined by equation 2.6

S = {S1,…,SN} (2.6)

(ii). The M observation symbols per state V = {𝑉1,…,𝑉𝑚}. If the observations are continuous

then M is infinite.

(iii). The state transition probability distribution A = {𝑎𝑖𝑗}, where 𝑎𝑖𝑗 is the probability that

the state at time t + 1 is 𝑆𝑗, is given when the state at time t is Si. The structure of this

Page 61: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

41

stochastic matrix defines the connection structure of the model. If a coefficient aij is zero, it

will remain zero even through the training process, so there will never be a transition from

state Si to

𝑆𝑗 . 𝑎𝑖𝑗 = P{𝑞𝑡+1 = j ǀ 𝑞𝑡 = i}, 1≤ i, j ≤N (2.7)

Where 𝑞𝑡 denotes the current state. The transition probabilities should satisfy the normal

stochastic constraints, 𝑎𝑖𝑗 ≥ 0, 1≤ i, j ≤N and ∑ 𝑎𝑖𝑗 = 1,𝑁𝑗=1 1≤ i ≤N. (2.8)

(iv). The Observation symbol probability distribution in each state, B = {𝑏𝑗 (k)} where 𝑏𝑗 (k)

is the probability that symbol vk is emitted in state 𝑆𝑗 [17].

𝑏𝑗 (k) = P{𝑂𝑡 = 𝑣𝑘|𝑞𝑡 = 𝑗}, 1≤ j ≤N, 1≤ k ≤M (2.9)

Where 𝑣𝑘 denotes the 𝐾𝑡ℎ observation symbol in the alphabet, and Ot the current parameter

vector. The following stochastic constraints must be satisfied:

𝑏𝑗(k)≥0, 1≤ j ≤N, 1≤ k ≤M and ∑ 𝑏𝑗(𝑘) = 1,𝑀𝐾=1 1≤ j ≤N (2.10)

If the observations are continuous, then we will have to use a continuous probability density

function, instead of a set of discrete probabilities. In this case we specify the parameters of

the probability density function. Usually the probability density is approximated by a

weighted sum of M Gaussian distributions N.

2.10 SUMMARY OF RELATED LITERATURES

From the literatures reviewed, it is was observed that Insulation Coordination is squarely

based on Probability, due to the complex/random events that take place in the power system,

especially in the event of surge. This Probabilistic theory is used to determine the various

Page 62: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

42

withstand voltage levels, BIL and other Insulation levels of power equipment. However,

despite the great contributions made by researchers over the years, it is obvious that these

earlier works make use of worst case scenarios, which is based on deterministic approach.

This deterministic approach is not comprehensive and flexible, to take into consideration

several factors that will ensure a balance between economic and technical/safety

factors(which Insulation Coordination intends to achieve). Thus, this work seeks to solve this

problem by introducing Stochastic processes with the instrumentality of Hidden Markov

model, which is very robust in handling, computing, analyzing and observing

complex/randomness experienced in power systems, especially at the event of surge.

CHAPTER THREE

RESEARCH METHODOLOGY

3.0 MODEL DESIGN

The summary of the highlights of the model design strategy of this work, for the insulation

coordination of a power station is given with the classification ability of Hidden Markov

Model(HMM), which is used to identify the travelling wave structure that exhibits the highest

likelihood probability on the power system under investigation. This identified transient wave

model is used to compute for the insulation coordination of the power system based on the

IS/IEC 60071-2 guidelines and standard.

3.1 THE MODEL DESIGN STRATEGY

For effective insulation coordination, a model of the dynamics of power system is required. A

model that includes the most likely combination of transient behavior that the power system

Page 63: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

43

would be subjected to[18]. This gives the ideal basis for the conduct of insulation. The power

system is a complex, dynamic and nonlinear system, which is in disturbance all the time.

The probability distribution of the representative lightning overvoltage amplitude at the

power station can be determined by transient overvoltage calculations, taking into account the

lightning performance of the transmission lines. The travelling wave behavior of overhead

lines and substation and the performance of the equipment insulation and the surge arresters

are dependent on the overvoltage amplitude and shape.

The shape of the travelling wave resulting from a lightning strike on the transmission line

within a particular distance of a substation would be different from the one that occurred with

a different distance of the station. Furthermore, the wave structure of a lightning stroke on the

particular line within a distance of the station, or protection arrester coupled with a protective

circuit breaker open, would have different measure of impact on the system insulation

protection. The insulation coordination of the power system then has to be carried out using

transient model(s) that reflects the most probable situation the system would be exposed to.

Hence, the modeling of a number of likely event scenarios (different transient disturbance

dynamics for the power system) and then using the training and classification power of

Hidden Markov Model (HMM) to identify the highest likelihood probabilities is the strategy

adopted by this work. This technique would provide the optimal transient disturbance model

within the limit of available data for the insulation coordination of a given power system.

The proposed HMM strategy involves training a set of three system transient model that

represents the dynamics of the network during a lightning strike and observing certain

electrical parameters. Based on the evaluation of the maximum likelihood probabilities, the

surge wave structure which has more representation of the highest impact of lightning surge

Page 64: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

44

on the system can be determined, from which the required parameters are obtained for the

insulation coordination of the system.

The likely power system event scenarios will provide different travelling wave signals for the

training and classification using HMM. This provides the different HMM model of the

system’s travelling wave shape, from which the optimum is selected based on the evaluation

of the maximum likelihood probabilities.

Therefore, simulating different impact on the power system by using station data, different

configuration of station components and lightning initiations, about three different

disturbance event scenarios are produced. An online model of these scenarios is obtained,

from which the one having the maximum likelihood probability is identified by HMM. The

identified scenario represents the travelling wave having the highest probable impact on the

power system. Thus, insulation coordination of the power station is then carried out using the

identified wave shape.

3.2 SCENARIO DESCRIPTION

3.2.1 Surge Event Scenario A:

The structure of the surge transient wave with lightning strike at location x on phase

conductor, with circuit breaker open; with station transformer protection arrester installed at

both sides of the transformer.

3.2.2 Surge Event Scenario B:

Page 65: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

45

The structure of the surge transient wave with lightning strike at location x on phase

conductor, with circuit breaker closed; station transformer protection arrester installed and

followed by a secondary strike (i.e. another strike).

3.2.3 Surge Event Scenario C:

The structure of the surge transient wave with lightning strike at location y on the phase

conductor, arrester at the transformer and also at the line entrance.

3.3 THE OVERVOLTAGE TRANSIENT ASSESSMENT BASED ON THE HMM

The power system transient assessment of the lightning induced overvoltage (for which

insulation coordination is required) is a complicated process. According to the perspective of

time sequence, the process of lightning induced overvoltage disturbance in the system is

identified as 5 states: Normal operation, disturbance occurrence (overvoltage transient

occurrence), disturbance development, system swing and system resuming. It is quite difficult

to identify every beginning time and ending time of the 5 states, which could be considered

“hidden”.

However, the 5 states could be described by some electrical parameters, which mean that the

states could be observed, and such electrical parameters are the feature sets of the

observations. In HMM, observation is probabilistic function of the related state and its

probability distribution function[19]. The hidden markov model is used to describe such state

transitions and the observations are encoded into digital signals.

3.4 The Overvoltage Training Disturbance Classification

Page 66: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

46

The proposed hidden markov model, classifies the destructive impact of the lightning

induced overvoltage transient on the power system, by comparing the maximum likelihood

probability of the overvoltage signal for trained models. A HMM model is trained for each of

the three overvoltage transient disturbance scenarios identified earlier on.

A HMM is defined as λ = (N, M, π, A, B), where N is the number of states, M is the number

of distinct observation symbols per state, π and B is the initial state distribution probability

and observation probability matrices respectively. The elements of matrix A, 𝑎𝑖𝑗, is the

transition probability from state i to state j, which are defined in equations (3.1) and (3.3) [19]

in these equations, 𝑞𝑡 is the actual state S at time t.

𝑎𝑖𝑗 = 𝑃[𝑞𝑡+1 = 𝑆𝑗|𝑞𝑡 = 𝑆𝑖], 1≤ 𝑖, 𝑗 ≤ 𝑁 …………………………….(3.1)

𝑎𝑖𝑗 ≥ 0, ∑𝑎𝑖𝑗

𝑁

𝑗=1

= 1………………… .. ………………(3.2)

The elements of matrix B, 𝑏𝑗(k), are defined by equation (3.3) where 𝑉𝑘 is the 𝐾𝑡ℎobservation

in the state [19] matrix B and vector π elements follow the rules presented in equation (3.4)

[19]

𝑏𝑗(𝑘) = 𝑃[(𝑂𝑡 = 𝑉𝑘|𝑞𝑡 = 𝑆𝑗)], 1≤ j ≤ N, 1≤ k ≤ M…………………… (3.3)

𝑏𝑗(𝑘) ≥ 0, ∑ 𝑏𝑗(𝑘)

𝑀

𝑘=1

= 1,∑𝜋1 = 1)

𝑁

𝑖=1

…………………… . (3.4)

Where 𝑂𝑡 indicates observation at time t. Equation (3.3) calculates the probability of

observation 𝑉𝑘 at time t, where 𝑞𝑡 = 𝑆𝑗.

Page 67: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

47

The HMM training process is identical to finding the appropriate parameters of A, B and π.

For convenience the HMM is denoted as a triplet:

λ = (A, B, π).

Thus, the flow chart of the proposed algorithm for the novel Insulation Coordination

procedure is shown in Figure 3.1 below.

No

O

Yes

Fundamental harmonic of the lighting

stroke phase (V)

C

Start

These-phase of the power system

Over

voltage?

Select window

Processing

Scenario A

HMM model

Scenario B

HMM model

Scenario C

HMM model

Page 68: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

48

A

Yes Yes Yes Yes Yes Scenario

A?

Comparator(Maximum likelihood)

Effective Power

system insulation

coordinating using

Scenario A

Transient response

Page 69: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

49

C

Figure 3.1: Flow chart of proposed Algorithm for Insulation Coordination

No

Yes

Yes

C

No

No

Page 70: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

50

When a lightning induced overvoltage incidence occurs, a windowed fundamental harmonic

of the overvoltage transient waveform of about a quarter of a cycle is sampled. Each window

consists of about ‘400’ samples of which 50% of them are taken as the HMM training data

while the other half are going to be classified by the HMM.

3.4.1 The Processing Block

The steps that make up the processing block is depicted in Figure 3.2

Start

Original feature set

Output signal waveform for

insulation coordination

Obtain HMM parameters

Comparator(maximum

likelihood)

Quantization (coding)

Classification (identification)

mode

Training mode

Feature subset Based on

Relative sensitivity method.

Page 71: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

51

Figure 3.2: Steps for the Signal Processing and Observation Evaluation Problem P(𝑂|λ)

From Figure 3.2, the electrical parameters that represent the feature set of the observation are

selected. The selections of the observation are selected. The selection is programmed in the

modeling program. This work uses the MATLAB software environment. The modeling of the

case study power system in MATLAB enables the extraction of electrical features of the

disturbance wave system. The features in Table 3.1 are selected from candidate feature set

from the overvoltage transient features.

3.1: Observed electrical feature for HMM classification of the lightning overvoltage

transients of the power system.

ITEM FEATURE NAME

1. Surge Impedance of phase conductors

2. Surge impedance of bus system

3. Surge impedance of transformer

4. Steepness of lightning current impinging on substation components.

5. Surge current

6. Travel time of lightning surge

7. Lightning crest current

8. Representative steepness of lightning impinging surge

9. Surge impedance of arresters

10. Surge impedance of circuit breakers

11. Phase conductor steady state voltage

12 Bus system steady state voltage

13 Capacitance of station transformer

Page 72: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

52

14 Station component overvoltage

15 Positive segment resistance of station components

16 Negative segment resistance of station components

17 Steady state frequently of power system

From Table 3.1 above, the feature observed a feature subset based on Relative sensitivity

method is obtained. The feature subset is selected to decrease the dimension of the candidate

feature set.

Equation (3.5) [20] shown below is utilized by the MATLAB to implement this.

Program/formula used to calculate the dynamic volume under different disturbances is.

𝑊𝑥 = ∆𝑊

𝑊0× 100% =

𝑊1 − 𝑊0

𝑊0 × 100%………………………… . (3.5)

𝑊0 is the basic value before the disturbances,

𝑊1 is the value under disturbances, and 𝑊𝑥 describes the relative sensitivity.

If the |𝑊𝑥| ≥ 100%, this feature would be selected.

The selected feature subset data is divided into two parts: one is the training data, including

stable (normal) and unstable ones (surge), the other is the data to be classified.

Page 73: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

53

The identification (classification) pre-process starts through the quantization (coding) of the

inputs observation signal (the surge signal). The reason for the quantization (coding) is that

the selected) features are a set of continuous vectors according to the time domain. These

vectors need to be transferred into a set of scalars using a coding technique so as to meet the

HMM training requirements. For this the appropriate MATLAB binary is used. The

MATLAB modeling environment has the signal discretization box to discretize (i.e. quantize.

Or encode continuous signal into digital signals).

The HMM training is executed to obtain the HMM parameter. The steps in the HMM

processing are depicted in the flowchart shown in Figure 3.3.

P(0׀𝜆𝑗) calculation

Viterbi Algorithm

Compute 𝑎𝑖𝑗 and 𝑏𝑗𝑘 based on

the Baum-Welch (BW)

Algorithm

Initialization

Training Data

Start

Page 74: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

54

Figure 3.3: Flow Chart of the HMM Training Process for the observation Evaluation Problem

Initialization

Initialize the π, A parameters of the HMM.

The initial state distribution vector π and the state transition on probability distribution A,

could be set as shown in equation (3.6) and (3.8) [20]

π = [1 0 0 0 0] ………………………………………..(3.6)

Noting π = {𝜋𝑖} where 𝜋𝑖 = 𝑃(𝑞1 = 𝜃𝑖), 1 ≤ 𝑖 ≤ 𝑁 ………… . (3.7)

Where 𝜃1, 𝜃2, 𝜃3, … , 𝜃𝑁 are marked as the markov chain at time instant t, and 𝑞𝑡 ∈

(𝜃1, 𝜃2, 𝜃3, …… , 𝜃𝑁) being the actual state S at time t.

Yes

No

Page 75: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

55

𝐴 =

[

0.50000

0.50.5000

00.50.500

00

0.50.50

000

0.51 ]

……….……………...(3.8)

After the initialization step, the new parameters of the HMM are calculated using the Baum-

Welch (BW) algorithm.

The HMM training blocks (fig. 3.3) inputs are observation vectors

O = 𝑂1, 𝑂2, …… , 𝑂𝑇, which as pointed out are feature (electrical parameters) signal samples

(of overvoltage transient waveform). In the training process, the maximum likelihood

probability denoted by equation (3.9a) should be maximized indirectly using the logarithm of

the above probability (Log lik), which is presented in equation (3.9b)[19].

𝑃(𝑂|λ) = ∑ 𝑃(𝑂|𝑄, λ)𝑃(𝑄, λ)………………… (3.9a)

𝐴𝑙𝑙 𝑄

Log lik = Log P(𝑂|λ) ……………………………………………….(3.9b)]

Where Ө = 𝑞1, 𝑞2, 𝑞3, …… . . , 𝑞𝑇 is a fixed state sequence (i.e. sequence of actual state for the

sampling duration) and T is the number of observations.

Page 76: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

56

The Baum-Welch algorithm first defines 𝑦𝑡(𝑖, 𝑗)(the posteriori probability of transitions being

in state i at time t and making a transition to state j at time t + 1, given the observation

sequence). It can be computed as equation (3.10), and the variable 𝛾𝑡 (the posteriori

probability of being in state i at time t, given the observation sequence and model λ) is

defined by equation (3.11)[19].

𝛾𝑡(𝑖, 𝑗) = 𝑃(𝑆𝑡 = 𝑖, 𝑆𝑡+1 = (𝑗|𝑂), λ) = 𝛼𝑡(𝑖)𝑎𝑖𝑗𝑏𝑗(𝑂𝑡+1)𝛽𝑡+1(𝑗)

𝑃(𝑂|λ)=

𝛼𝑡(𝑖)𝑎𝑖𝑗𝑏𝑗(𝑂𝑡+1)𝛽𝑡+1(𝑗)

∑ 𝛼𝑇(𝑘)𝑘𝜖𝑄𝑓

…….……. (3.10)

𝛾𝑡(𝑖) = 𝑃(𝑆𝑡 = (𝑖|𝑂), 𝛾 = 𝛼𝑡(𝑖)𝛽𝑡(𝑖)

𝑃(𝑂|λ)

= 𝛼𝑡(𝑖)𝛽𝑡(𝑖)

∑ 𝛼𝑇(𝑘)𝑘𝜖𝑄𝑓

…………………………………… . . … (3.11)

Where 𝛼𝑡(𝑖) is the forward variable for mode λ (one of the scenario overvoltage wave

model). This is the probability of the partial observation sequence O (until time t) and state 𝑆𝑖

at time t. another parameter is 𝛽𝑡(𝑖), which is a backward variable that refers to the

probability of the partial observation sequence from t +1 to the end, given 𝑆𝑖 at time t and the

model λ. 𝑄𝐹 is a set of final states.

𝛼𝑡 = 𝑃(𝑂1, 𝑂2, … . 𝑂𝑡, 𝑞𝑡 = (𝑆𝑖|λ))………………………………… . (3.12)

This means the probability of the partial observation sequence

𝑂1, 𝑂2, …… . . 𝑂𝑡 with state 𝑞𝑡 = 𝑆𝑖, given mode λ.

Page 77: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

57

.𝛽𝑡(𝑖) = 𝑃(𝑂𝑡+1, 𝑂𝑡+ 2, … . , (𝑂𝑇|𝑞𝑡) = (𝑆𝑖|λ))…… .………………(3.13)

If 𝛼1(𝑖) = 𝜋𝑖𝑏𝑖(𝑂1), then α can be calculated as follows:

𝛼𝑡+1(𝑗) = |∑𝛼𝑡(𝑖)𝑎𝑖𝑗

𝑁

𝑖=1

| 𝑏𝑗(𝑂𝑡+1)…… . . ……… (3.14)

If 𝛽𝑇(𝑖) = 1 (initialization), then the following holds true[21]:

𝛽𝑡(𝑖) = ∑𝑎𝑖𝑗𝑏𝑗(𝑂𝑡+1)𝛽𝑡+1(𝑗)……………………… . (3.15)

𝑁

𝑗=1

Parameters 𝑎𝑖𝑗 , 𝑏𝑗 , 𝜋𝑖 of the re-estimated new mode ǀ λ can be computed as follows:

𝑎𝑖𝑗 = ∑ 𝛾𝑡(𝑖, 𝑗)

𝑇−1𝑡=1

∑ 𝛾𝑡(𝑖)𝑇−1𝑡=1

……………(3.16)

𝑏𝑗(𝑘) = ∑ 𝛾𝑡(𝑗)

𝑇𝑡=1

∑ 𝛾𝑡(𝑗)𝑇𝑡=1

………………………(3.17)

𝜋𝑖 = 𝛾1(𝑖)…………………… . . (3.18)

The logarithm of the model’s output probabilities are then computed in the recognition stage.

Recognition or classification(identification) means finding the best path in each trained

model and selecting the one that maximizes the path probability for a given input observation

O and the model λ𝑖 = (𝐴𝑖, 𝐵𝑖, 𝜋𝑖), 𝑖 = 1,2, … . . , 𝐷, where D represents the number of voltage

Page 78: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

58

transient waveform shapes. This means computing the optimal conditional probability

P((𝑂|λ𝑗). Therefore, overvoltage transient model λ∗ should satisfy the following equation:

λ∗ = 𝑚𝑎𝑥𝑖[𝑚𝑎𝑥𝑄P(Q, (𝑂|λ𝑖))]…………… . . (3.19)

At this stage, the Viterbi algorithm[22] is used to find the best path probability (i.e. the

maximum likelihood).

Initialization for all state i:

δ1(𝑖) = 𝜋𝑖𝑏𝑖(𝑂1), 𝛹1(𝑖) = 0. . . … (3.20)

Recursion from time t = 2 to T and all states j:

δ𝑡(𝑗) = 𝑚𝑎𝑥𝑖[δ𝑡−1(𝑖)𝑎𝑖𝑗]𝑏𝑗(𝑂𝑡)…… . (3.21)

𝛹𝑡(𝑗) = 𝑎𝑟𝑔𝑖𝑚𝑎𝑥 [δ𝑡−1(𝑖)𝑎𝑖𝑗]……………… .…… . . (3.22)

Termination;

𝑃∗ = max[δ𝑇(𝑖)] , 𝑞𝑇∗ = 𝑎𝑟𝑔𝑚𝑎𝑥[δ𝑇(𝑖)]…………(3.23)

State sequence backtracking from T-1 to 1:

𝑞𝑡∗ = 𝛹𝑡+1(𝑞𝑡+1

∗ )…………………………………… . . (3.24)

The maximum likelihood probability P(𝑂|λ) could be achieved, given the best path O and

observation O (observation vector of the lightning induced overvoltage transient signal). The

required optimal disturbance transient required for optimal insulation coordination can then

Page 79: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

59

be identified by comparing the logarithm of the likelihood probabilities (log lik) of the

transient models. The model with highest probability likelihood gives the optimal (within the

limit of available data) disturbance waveform for the insulation coordination of the power

system.

The lightning overvoltage transient scenario that gives this optimal probability is used as

input for the computation of the insulation coordination for the power station. That is, the

selected scenario would be used to determine voltage stresses and on this basis insulation

strength is selected to achieve the desired voltage withstand.

3.5 Computing for the Insulation Coordination

The overvoltage transient model identified by the HMM as presented above, is the input for

the computation of the insulation coordination. Since the overvoltages in the power system

(in the case of this work the transmission station) depend on the amplitude and shape of the

overvoltage impinging on the station from the overhead line conductor, as well as on the

travelling wave behavior of the station.

The MATLAB program developed for the purpose of this computation in this work

adheres to the IS/IEC 60071-2 guide for the determination of withstand voltages for

insulation coordination. Based on this the program algorithm follows the following main four

steps:

STEP 1: Determination of the Representative Overvoltage

Page 80: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

60

The representative over voltages are not the over voltages that occur in the system but are

overvoltages that represent the electric stress on the equipment as the actual overvoltages.

Hence the need for the representative model to be optimal. This explains the use of the HMM

identified optimal likelihood model of the disturbance. The HMM identified model is used at

this step of the evaluation. This implies that the representative voltages are determined from

the HMM classified transient model.

The procedure adopted in the evaluation software consists in calculating a lightning current

with the desired return rate, and calculating the overvoltage by travelling wave calculations in

the substation.

The lightning current determining surge is determined from the shielding penetration rate

within the limit distance and its probability to be exceeded[23]:

F(I) = F(𝐼𝑚) + (𝑅𝑡

𝑅𝑝⁄ )……………………………..…(3.26)

Where

F(𝐼𝑚) is the lightning current probability corresponding to the maximum shielding current;

𝑅𝑡 is the considered return rate;

𝑅𝑝 is the shielding penetration rate within the limit distance.

NOTE: The shielding penetration rate can be obtained from the shielding failure flashover

rate by:

𝑅𝑝 = 𝑅𝑠𝑓

𝐹(𝐼𝑐𝑟) − 𝐹(𝐼𝑚)………………… . (3.27)

Page 81: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

61

Where

𝑅𝑠𝑓 is the shielding failure flashover rate;

𝐹(𝐼𝑐𝑟) is the probability corresponding to the current causing line insulation flashover at

negative polarity.

MATLAB program determines the amplitude of the impinging overvoltage surge using

equation (3.28) and determine its Steepness to correspond to equation (3.29) [23]:

𝑈𝐼 = 𝑍𝐿𝐼

2………………………………………(3.28)

𝑈𝐼: Amplitude of the impinging lightning overvoltage surge.

𝑍𝐿: Surge impedance of the overhead line

I: Lightning current amplitude

S = 1

𝐾𝑐𝑜𝑋𝑇 …………………………………….(3.29)

Where 𝐾𝑐𝑜 is the corona damping constant;

𝑋𝑇 = 𝑋𝑝

4

Page 82: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

62

𝑋𝑝: limit overhead line distance within which lightning events have to be considered.

The MATLAB program uses the impinging voltage surge to perform a travelling wave

calculation with the model of the power station and the representative overvoltages are

obtained for this return rate for the various locations in the system.

STEP 2: Determination of the Co-ordination Withstand Voltages

According to the Funde (IS/IEC 60071-1) different factors have to be applied to the

determined values of the representative overvoltages. Those factors, which may vary with the

shape of the overvoltage, take into account the adopted performance criteria and the in

accuracies in the input data (e.g. arrester data).

The co-ordination withstand voltages: 𝐾𝑐𝑑 × 𝑈𝑟𝑝 = 𝑈𝑐𝑤

𝑈𝑟𝑝: Amplitude of the representative overvoltage [3.19 of IEC 71-1]

𝐾𝑐𝑑: Determination co-ordinating factor

STEP 3: Determination of the Required Withstand Voltages

Based on the referenced guideline, the required withstand voltages are obtained by applying

to the co-ordination withstand voltages two correction factors: factor 𝐾𝑎 which take into

account the altitude of the installation, and a safety factor 𝐾𝑠.

𝐾𝑠: Safety factor [3.29 of IEC 71-1]

𝐾𝑎: Atmospheric correction factor [3.25 of IEC 71-1)

The factor is applicable to any type of overvoltage.

Page 83: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

63

𝑈𝑟𝑤 = 𝑈𝑐𝑤𝐾𝑠𝐾𝑎 …………………………………… . (3.30)

𝑈𝑐𝑤: Co-ordination withstand voltage of equipment

𝑈𝑟𝑤: required withstand voltage [3.17 of IEC 71-1]

STEP 4: Determination of the Standard Withstand Voltages.

The standard withstand voltages are obtained from the required withstand voltage by

choosing the next highest value from the standard values listed in IEC 71-1.

3.6 Modeling the Power System

For effecting the insulation coordination, the simulation program requires the digital model of

the power station. This is needed to carry out the travelling wave calculation required for the

HMM optimum likelihood classification and to estimate the overvoltage at different locations

in the power system.

Insulation co-ordination models differ greatly from conventional power frequency power

system models used for load flow and fault analysis. Hence the components of the power

station are modeled in MATLAB as follows:

3.6.1 Transmission Line Conductors Model

The transmission line conductors are modeled with surge impedance and a travel time, not

conventional impedance. This is because the stroke currents and associated surge voltages or

actually travelling waves that move along the conductors and split and reflect from points of

different surge impedance. This creates numerous travelling waves back and forth, which are

Page 84: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

64

summed or are subtracted as they meet when such travelling waves are summed up at a

junction or line end, this can cause significant overvoltages.

In MATLAB the transmission line is modeled using a frequency dependent travelling wave

model with the frequency fitting curve within a range, with the steady state frequency set to a

value.

In the MATLAB simulation, the transmission line models are constructed using conductor

data and line geometry information.

3.6.2 Transmission Line Towers Model

The transmission line model needs to include back flashover models of the transmission

towers and insulators. It also needs the tower structure and earthing of the overhead earth

wire included. The simulation of the tower models are added to the transmission line

conductor models.

3.6.3 Surge Arresters Model

Surge arresters are modeled as non-linear elements using the MATLAB plug in for metal

oxide surge arresters component along with R, L and C components in line with the IEEE fast

front arrester model described in [24].

The surge arresters are modeled with downleads to the earth grid. The downleads are

modeled as travelling wave models with a surge impedance and a propagation velocity.

3.6.4 Transformer Model

Page 85: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

65

Under Lightning conditions, the transformers act as surge capacitance[25]. Hence for the

MATLAB modeling purposes, transformers are presented by winding surge capacitance

between each phase and earth.

Under lightning conditions the other equipment in the power station such as disconnector

insulators, CVT’s station post insulators etc., as surge capacitances. Hence for the modeling

purpose they are represented by surge capacitance between each phase and earth.

3.6.5 Lightning Surge Model

Lightning strokes are most basically described in terms of two values, crest current and front

steepness. The crest current is the maximum current value that the stroke achieves (measured

in KA/µs). Strictly speaking front steepness is the time taken for the stroke current to rise

from 10% to 90% of the crest current. For modeling and evaluating lightning stroke,

according to[25] the CIGRE probability data is considered to be superior to other data. Hence

in the simulation of the lightning stroke, the stroke current and steepness value is varied in

the software following the probability function of the form:

P(x) = 𝐼

2πBI 𝑒−0.5𝑧2

- - - - - - - - - - - - - - - - - - - - - - - - - - -(3.31)

Z = 𝑙𝑛 𝐼

𝑀

𝐵 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - (3.32)

I is the stroke current in kA or front steepness in kA/µs, M is the median value of stroke

current or front steepness and B is the log standard deviation of the stroke current or front

steepness.

Page 86: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

66

The CIGRE data suggest that the median value of stroke current crest is 34kA and the log

standard deviation is 0.74. The median front steepness value is considered to be 24.3kA/µs

with log standard deviation of 0.6[25].

3.7 Assumptions for lightning surge

For computer modeling purpose, the following assumptions are held:

1. The station is shielded and no lightning enters the station directly, only via the lines

when a back flashover occurs within a few spans of the station.

2. Transformer margin of protection of 20% is a minimum for lightning surges(IS/IEC

6007-1 recommendation).

Page 87: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

67

CHAPTER FOUR

4.0 SIMULATION AND RESULT EVALUATION

The 330/132kv substation at New Haven Enugu Nigeria was used to evaluate the proposed

novel insulation coordination technique. The time domain simulation carried out with

MATLAB, is used to assess(based on the HMM identified maximum likelihood) whether the

combination of surge arrester and their location with respect to the transformer provides

adequate margin of protection. The substation is modeled in MATLAB/Simulink, using

drawings supplied by Power Holding Company of Nigeria(PHCN)Transmission station. The

voltage values at a chosen arrester protection zone in the station, is determined with a

simulated lightning surge entering the station from the incoming line. Three (3) lightning

surge disturbance scenarios are observed by the HMM algorithm. From the training of these

three transient disturbance model (using about n iterations), HMM identifies from among the

surge signals, a waveform structure having the maximum likelihood at location of the

substation being investigated. The identified maximum likelihood wave is used to calculate

the protection margin based on equipment data supplied by PHCN.

The MATLAB/Simulink model of the power system is given in Figure 4.1. The MATLAB

m-file source code that implements the HMM algorithm is given in appendix A. The Name

plates of arresters and transformers at the power substation is given on appendix B and C.

Also the single line diagram of the station is in appendix D.

4.1 Simulation of the three lightning overvoltage transient scenarios

The simulation of the three scenarios provides the parameters associated with the HMM

algorithm. The HMM uses the observation electrical parameters, associated with the dynamic

of the network, during the lightning disturbance to access the probability densities of the

Page 88: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

68

associated waves and to determine the maximum likelihood wave. Lightning strokes

occurring at the overhead transmission lines are simulated as impulse current waveform. This

can be simulated by means of CIGRE wave shape [27].

Page 89: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

69

Page 90: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

70

In simulation studies, the lightning flash is substituted with impulse current generator.

Impulse generator(IG) generates very steep-front wave shapes , known as impulse waves, that

are similar to lightning waves[28].

For the simulation carried out in this chapter, impulse current waveforms have been

generated in the MATLAB. This is provided by the lightning impulse current source in the

model of figure 4.1. A lightning current wave of 30KA is injected into the phase conductors

and propagated into the system during operation. The 132/33KV New Haven Power

Transmission Station Parameters/data used in this work are shown in Table 4.1 below.

Table 4.1: Station Parameters/Data supplied by PHCN

S/N PARAMETERS VALUES

1 Transformer BIL 850V

2 Arrester BIL, 𝐸𝑎 or 𝑈𝑝𝑙 650V

3 Surge Impedance of Line 400 Ω

4 Arrester-Transformer Separation distance 6.5m

5 Ground Clearance 6.10m

6 Vertical distance between conductors 3.96m

7 Horizontal Space between conductors 7.0m

8 Mid-Span clearance 6.1m

9 Vertical distance from overhead conductor to Arrester, 𝑎1 2m

10 Active length of Arrester, 𝑎4 3.6m

11 Vertical distance of Arrester conductor to earth, 𝑎2 15m

12 Length of Phase conductor between Arrester and Protected equipment, 𝑎3 6.5m

13 No. of lines per circuit 2

14 Travelling wave velocity 300m/µs

15 Rated Frequency 50Hz

Page 91: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

71

16 Steady state voltage 132KV

Page 92: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

72

Table 4.2 shows lines data of a transmission line from new haven 330/132KV to other stations like Aliade, Apir, Nkalagu, Abakaliki, Oji River,

Otukpo and Yandev.

Table 4.2: TRANSMISSION LINE DATA

S/

N

From

Station

To

Station

Voltage

(KV)

Circuit

NO

Conductor

Configuration

Length

(Km)

Positive

Imped.

Negative

Sequenc

e Imped

CCC Conductor

Positive

Susceptanc

e

Negative

Susceptanc

e

Zero Seq.

Imped

1. Onitsh

a

New

Haven

330 113N 2x350mm2(Biso

n)

106.2 0.003773 0.026377 0.14203782

7

0.04074220 0.0296198

2. Apir Aliade 330 1.ID 2x350mm2(Biso

n)

49.32 0.0428 0.349 0.065963 0.0189209 0.336

3. Oji

River,

New

Haven

132 40N 150mm2(Wolf) 43.75 0.051476

5

0.102944 400A 0.0585137 0.0167847 0.1155082

4. New

Haven

Nkalagu 132 H44L,

H45L

150mm2(Wolf) 38.5 0.045299

3

0.090591 0.5149205 0.0147700 0.1016472

Page 93: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

73

5. Nkalag

u

Abakaliki 132 H43L 150mm2(Wolf) 53.9 0.006341

9

0.124709 0.07208887 0.0206780 0.1423061

6. New

Haven

Otukpo 132 N64F 150mm2(Wolf) 160 0.188198 0.276362 0.21399296 0.06138185

1

0.4222981

7. Otukpo Yandev 132 F65G 150mm2(Wolf) 114.8 0.135074

3

0.270124 0.1583994 0.0440414 0.3030936

Page 94: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

74

4.1.1 Surge Event Scenario A:

In relation to the corresponding location of station electrical components as contained in the

MATLAB model of figure 4.1., this scenario can be visualized by figure 4.2.

The lightning strike occurs at 45m to the A-phase entrance to the 132/33kV segment of the

system. This is on the line of protection of arrester 4. The distances are electrically modeled

by the Simulink 𝜋-sections (i.e.feeders). In this lightning strike scenario, the downstream

circuit breakers are open. On the model of Figure 4.1, the breakers are situated as follows: the

three-phase circuit breaker 5 is close to Kingsway 33kV line I, the breaker 6 is close to the

Kingsway 33kV line II, Breaker 8 is close to the lines: Government house, Independence

layout, NNPC 33kV line and Emene 33kV line. Finally Breaker 7 is close to Thinker’s

A

B

C

a

b

c

com

45m

Lightning

source

132kV/33kV Transformer

132kV/33kV Transformer

Lightning arrester 4

Figure 4. 2. The illustration of incoming transmission surge wave of scenario A

Page 95: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

75

corner, Ituku/Ozalla, Amechi lines. For scenario A, the lightning overvoltage waveform at the

arrester 4(i.e. phase A arrester) is as depicted in figure 4.3.

4.1.2 Surge Event Scenario B

In relation to the corresponding location of station electrical components as contained in the

MATLAB model of figure 4.1., this scenario can be visualized by figure 4.4.

0 0.002 0.004 0.006 0.008 0.01 0.012 0.014 0.016 0.018-400

-200

0

200

400

600

800

Time(µs)

VO

LT

AG

E(K

V)

0

0.5

1

Fig. 4.3: RESULTANT WAVEFORM FOR SURGE EVENT SCENARIO A

A

B

C

a

b

c

com

45m

Lightning source

132kV/33kV Transformer

132kV/33kV Transformer

Lightning arrester 4

A secondary strike after 0.05𝜇s

(the programmed delay of the impulse generator)

Figure 4. 4. The illustration of incoming transmission surge wave of scenario B

Page 96: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

76

The lightning strike occurs at 45m to the entrance arresters(i.e. arrester 4 on phase A, arrester

5 on phase B and arrester 6 on phase C). This is followed by a secondary strike. For this

scenario, the lightning overvoltage waveform at arrester 4(i.e. phase A arrester) is given on

Figure 4.5.

Page 97: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

77

4.1.3 Surge Event Scenario C

In relation to the corresponding location of station electrical components as contained in the

MATLAB model of figure 4.1., this scenario can be visualized by figure 4.4.

0 0.002 0.004 0.006 0.008 0.01 0.012 0.014 0.016 0.018-800

-600

-400

-200

0

200

400

600

800

TIME (µS)

VO

LT

AG

E(K

V)

Fig. 4.5: RESULTANT WAVEFORM FOR SURGE EVENT SCENARIO B

Page 98: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

78

The lightning strike occurs at 90m to the entrance arresters, linking to the Kingsway 33kV

line(i.e. arresters 4, arrester 5, arrester 6). The lightning overvoltage waveform at arrester

4(i.e. phase A arrester) is given in figure 4.7. The time domain values of the signals resulting

from the simulated scenarios are extracted into vectors and matrix structures buffered in the

MATLAB workspace in memory. This data structures are accessed by the HMM algorithm.

From the values, HMM computation runs iteratively and identifies the waveform with the

maximum likelihood. The identified signal is used to obtain the surge steepness(kV/µs). This

value is used to compute the insulation coordination withstand voltage.

The computed value is compared analytically with the residual or discharge of the arrester

and the Basic Insulation Level(BIL) of the transformer to access the margin of protection

based on the maximum likelihood surge wave.

A

B

C

a

b

c

com

90m

Lightning source

132kV/33kV Transformer

132kV/33kV Transformer

Lightning arrester 4

Figure 4. 6. The illustration of incoming transmission surge wave of scenario C

Page 99: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

79

From the simulation studies, the waveform identifies as having maximum likelihood is that of

figure 4.5. But it should be noticed by comparing the maximum amplitude of Figure 4.3 and

4.5 that the surge wave of Figure 4.3 is of a higher amplitude. This amplitude comparison

becomes clearer in the combined plot given in Figure 4.8. Though the amplitude of the surge

signal of Figure 4.3 of highest magnitude of the three, the HMM algorithm still identified that

of figure 4.5 as having the highest maximum likelihood.

0 0.002 0.004 0.006 0.008 0.01 0.012 0.014 0.016 0.018-400

-200

0

200

400

600

800

TIME(µS)

VO

LT

AG

E (K

V)

Fig. 4.7: RESULTANT WAVEFORM OF SURGE EVENT SCENARIO C

Page 100: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

80

This can be understood from the fact that HMM is based on probability distribution, rather on

deterministic measurement. This means from the iterations, the signal waveform of Figure

4.3 has the highest probability strength than the other signals, based on the complex structure

of the power system dynamics as seen by the algorithm.

4.2 Waveform at the Strike point

The waveform at the lightning strike point is given by Figure 4.9. At the strike point is

given(of 45m to the entrance arresters), the wave shape is that of impulse wave with an

exponential curve that rises quickly to the peak and falls comparatively slowly towards zero

with respect to time.

0 0.002 0.004 0.006 0.008 0.01 0.012 0.014 0.016 0.018-800

-600

-400

-200

0

200

400

600

800

TIME(µS)

VO

LT

AG

E(K

V)

HMM identified maximum likelihood surge signal

Fig 4.8: RESULTANT WAVEFORM OF THE THREE SURGE EVENT SECNARIOS(THE COMBINED PLOT)

Page 101: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

81

Comparing the wave at the strike point with those given on Figure 4.8 (i.e. those at the 132kV

entrance arresters). It can be seen that the amplitude(referring to the crest of the wave at the

strike point) is greater than those at the station entrance(132kV side) arresters. In other words,

the rate of rise of the surge wave at the strike point was very high, but by the time it reached

the station entrance(to the 132kV side), it was reduced by corona and the capacitance of the

line[23]. It is important to note that the steepness of the incoming surge into a station is a

crucial factor on how well the arresters are able to protect the equipment at the station.

The steepness S of the surge is given by[23];

0 0.005 0.01 0.015 0.02 0.025 0.030

200

400

600

800

1000

1200

1400

1600

1800

2000

TIME(µS)

VO

LT

AG

E(K

V)

Fig. 4.9: RESULTANT WAVEFORM AT THE STRIKE POINT

Page 102: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

82

S = 1

𝐾𝑐𝑜 𝑋𝑇…………………………………………………(4.1)

Where 𝑋𝑇 = 𝑋𝑝

4………………………………………..(4.2)

𝑋𝑝 = 2𝑇

[𝑛𝐾𝑐𝑜(𝑈 − 𝑈𝑝𝑙)]……………………… .………… . (4.3)

Where 𝐾𝑐𝑜 is the corona damping constant according to table to table 4.1(µs/(kV.m)):

𝑋𝑝 is the limit overhead line distance within which lightning events have to be

considered(m).

n is the number of overhead lines connected to the substation.

T is the longest travel time between the point to be protected and the closest arrester(µs).

𝑈𝑝𝑙 is the lightning impulse protective level of the arrester.

U is the considered overvoltage amplitude.

Table 4.3: Corona damping constant 𝐾𝑐𝑜

Conductor Configuration 𝑲𝒄𝒐(µs/(KV.m))

Single conductor 1.5 × 10−6

Double Conductor bundle 1.0 × 10−6

Three or four conductor bundle 0.6 × 10−6

Six or eight conductor bundle 0.4 × 10−6

Source: [27]

Page 103: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

83

From the HMM identified maximum likelihood surge wave (Figure 4.5), the highest

amplitude of the signal is 721.42kV. Also from the station’s supplied data, the arrester spark

over level(i.e. discharge voltage level) or BIL is 650kV. This is the equipment name plate

supplied by PHCN on appendix B. Moreover, the make or model of the arrester is “Siemens

3AP1FG”. The transformer surge impedance is 1600Ω, surge impedance of line is 400Ω.

Arrester- transformer separation distance is 6.5m. The reference is to arrester 4 in Figure 4.1.

To understand the insulation coordination distance relationship between lightning arrester 4

and the protected 132/33kV transformer on Figure 4.1, the following illustration in Figure

4.10 depicts the arrester – transformer relationship.

The 132/33kV

protected transformer

𝑍𝑂 = 1600 Ω

Zo = 400Ω

β a4

a1 a3 α

ARRESTER 4

U

Surge wave front

Page 104: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

84

T is determined as follows:

T = 𝐿

𝐶 ………………………………………………………………………… (4.4)

a2

Earth mat

𝑍𝑔 = earthing impedance

Figure 4.10 location of arrester 4 (on phase A) to the 132/33kV transformer

supplying the Kingsway line I

Page 105: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

85

Where:

C is the velocity of light (300m/µs);

L = 𝑎1 + 𝑎2 + 𝑎3 + 𝑎4: distance as indicated in Figure 4.7

𝑎1: length of the lead connecting the surge arrester to the line.

𝑎2: length of the lead connecting the surge arrester to earth.

𝑎14: length of the active part of the surge.

𝑎3: length of the phase conductor between the surge arrester and the protected equipment.

From the data obtained from PHCN:

𝑎1 = 2m, 𝑎2 = 15m, 𝑎3 6.5m, 𝑎4 = 3.6m

Thus, T = 27.1

300 = 0.0903µs……………………………………………………… (4.5)

Transmission coefficient 𝛼 = 2 ×1600

1600 +400= 1.6………………………………… (4.6)

Reflection coefficient 𝛽 = 1.6 − 1 = 0.6……………………………………… (4.7)

Data supplied indicate the use of double line at the switch yard, hence n = 2. Then from the

table 4.1, 𝐾𝑐𝑜 = 1.0 × 10−6µs/(ku.m)

Referring to Figure 4.5(i.e. the HMM identified maximum likelihood surge wave),

U = 721.42kV, the arrester discharge voltage(i.e. arrester BIL) = 650kV, hence 𝑈𝑝𝑙 = 650kV.

Substituting using equation (4.3)

Page 106: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

86

𝑋𝑝 = 2 ×0.0903

(2×1.0×10−6×(721.42 −650)= 1264.351………………………………… (4.8)

𝑋𝑇 = 1264.351

4 = 316.09 ………………………………………………………. (4.9)

𝑆 = 1

(1.0×10−6×316.09 ………………………………….………………………..... (4.10)

S = 3163.68kV/µs

This is the steepness of the surge voltage 𝐸𝑡 at the terminal of the transformer can e

determined from [ 30 ]:

𝐸𝑡 = 𝐸𝑎 + 𝛽𝑑𝑒

𝑑𝑡 ×

2𝐿𝑡

300……………………………(4.11)

Equation (4.11) gives the maximum voltage at the terminal of a line as a result of the first

reflection of a travelling wave. This gives the maximum voltage up to 2𝛽𝐸𝑎. The factor 2

arises from the return length from arrester to transformer, and the factor 300 is based on a

travelling wave velocity of 300m/µs in the overhead line. 𝑙𝑡 is the separation between the

arrester and the transformer location (for figure 4.10 𝑙𝑡 = 𝑎3, 𝛽 is the reflection coefficient at

the transformer location, 𝐸𝑎(i.e. arrester BIL), and 𝑑𝑒

𝑑𝑡 is the steepness(i.e. the rate of rise) of

the wave front. When the value of 𝛽 is not known, it may be assumed to be 1 without much

loss of accuracy [30 ]

From the data supplied, 𝐸𝑎 = 650𝑘𝑉, 𝑎3(separation of arrester 4 from transformer) = 6.5m.

𝑑𝑒

𝑑𝑡= 𝑆 =

3163.68𝑘𝑉

𝜇𝑠………………………………(4.12)

𝐸𝑡 = 650 + 0.6 × 3163.68 × 26.5

300……………… . . (4.13)

Page 107: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

87

𝐸𝑡 = 732.26𝑘𝑉

The BIL of the transformer, as per supplied data is 850kV. The transformer insulation

withstand voltage is greater than the maximum surge voltage appearing at its terminals. The

residual voltage of the arrester should be below the BIL of the protected equipment by a

suitable margin. The IEEE13131.2[28] and the IS/IEC 60071-2[6] recommended margin is

between 15% and 25%. However, emphasis is placed on achieving a good margin above the

15% minimum[29].

Thus, using the obtained maximum value of surge voltage at the protected equipment, and the

BIL of the protected equipment, the margin of protection can be evaluated:

The margin of protection = 850 −732.26

732.26 × 100% = 16.08%………………(4.14)

Moreover from the simulation, the BIL(Basic Insulation Level) to the withstand of the

transformer is higher than the maximum overvoltage(as per HMM identification), appearing

at its terminals during the lighting strike. The 16.08% margin of protection (i.e. by how much

the transformer withstand is greater than the maximum likelihood surge) is just a little above

the minimum recommended margin (i.e. 15%).

However, adjusting the separation of the arrester from the transformer might improve the

margin of protection. For instance, to achieve a protection margin of 18% at the switch yard,

the maximum permissible surge at the transformer

= 850

1.18 = 720.34KV. ……………………………………………………… (4.15)

Substituting in equation (4.11)

Page 108: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

88

720.34 = 650 + 0.6 × 3163.68 ×2𝑙𝑡300

∴ 𝑙𝑡 = 5.56𝑚

The lightning surge arrester 4 has to be placed 5.56m to the transformer in order to achieve a

protection margin of 18%.

Page 109: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

89

CHAPTER FIVE

5.0 CONCLUSION AND RECOMMENDATION

5.1 SUMMARY

The proposed HMM based insulation coordination technique is applied to a 132/33kV Power

transmission switchyard in New Haven Enugu Nigeria. Insulation coordination is carried out

to evaluate the arrester rating/arrester placement, that will adequately protect the substation’s

transformer from flashover during a lightning strike. The focus is on determining the margin

of protection, with reference to the recommended margin as per IEEE 1313.2/IS/IEC 60021.

The station was modeled in MATLAB/Simulink using single line drawings, supplied by

PHCN. Lightning surge simulated was based on the CIGRE wave shape using impulse

current generator. This was used to inject a lightning surge of 30KA, propagated into the

switchyard. The maximum surge voltage at a specific arrester – transformer location was

determined.

The work assumed that the substation was properly shielded. Otherwise, insulation

coordination involving substation overhead shield wire, should have been considered in the

evaluation carried out in Chapter four. Hence, the work considered, focused on Insulation

coordination of the arrester – transformer pair.

Moreover, Insulation coordination often entails evaluating a trade off between economy and

safety(i.e. technical aspect) margins. Often, for mainly economic reasons, arresters are

located at a distance from transformer, in order to include other station equipment within its

protection zone. Hence the more the margin of protection is increased by shortening the

separation between lightning arrester and protected equipment, the increase in the likelihood

Page 110: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

90

of more arresters being required. This is because the more the closer an arrester is moved

towards a protected equipment, gaps are created that affects the protection of other substation

equipment within the protection zone.

However, the location adjustment might push the arrester, to a location in which its protection

for other equipment falls below the recommended protection margin, hence more arresters

would then be required.

5.2 CONCLUSION

Based on the HMM identified maximum likelihood lightning surge waves, resulting from the

three lightning disturbance scenarios at the power station investigated, the arrester –

transformer placement meets the minimum margin of placement. The minimum required

margin(of 15%) exceeded by a little value(about 1.08%). Also, evaluation carried out to raise

the protection margin to 18% meant the relocation of the arrester to within 5.56m of the

transformer. Without the HMM, the work would have to coordinate for each of the lightning

disturbance scenario with different results. This would mean different configuration of

location of arresters, discharge voltage of arresters, different determination of BIL for

protected equipment. Insulation having been established as an engineering practice has

matured to the point of knowing that it is a combination of economic and technical safety

consideration. Sequel to this, the computation, configuration, selection of values as regards

insulation coordination, has its foundation in probability and statistical sciences. Thus, basing

the selection of coordination, lightning surge wave signal on probabilistic maximum

likelihood is an optimal approach in providing the economic – technical safety trade off.

5.3. RECOMMENDATION

Page 111: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

91

The technical information provided in this thesis forms a veritable database for future work

towards improved Nigeria power system operation.

The following are recommended to ensure efficient operation of the Nigeria grid system:

a) Insulation Coordination should be conducted in the station on routine basis(for

instance once in 5 years). This is crucial due to equipment ageing.

b) The station must be properly shielded.

c) A High voltage meter that retains Over Voltage readings should be installed in the

station.

d) However, it is also recommended that the strength, occurrence and distribution of

lightning strikes within the geographical area should be collated for insulation

coordination of power system in the country.

5.4 SUGGESTION FOR FURTHER STUDIES

a) The insulation coordination technique proposed in this work should be applied to

substation insulation coordination for switching overvoltages in subsequent studies.

b) The training process in the HMM algorithm should factor in environmental effects.

Since for instance flashover voltages for air gaps depend on moisture content and

density of air. Therefore, in the determination of withstand voltages, correction factors

for humidity and ambient temperature variation should be considered if subsequent

work delves into substation shielding, since critical flashover voltage(CFO) of line

insulators can be reduced by as much as 20% at higher elevations. Such collated data

on environmental effects can be encoded and used in the HMM algorithm for the

identification of more realistic maximum likelihood surge wave for the optimal

insulation coordination of power systems in the country.

Page 112: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

92

REFERENCES

[1] M. Naidu, V kamaraju. “High Voltage engineering second edition”, Mc Graw-Hill. pp:

vii,1,2, 1996.

[2] S. Lam-Du and T. Tran-O. “Insulation Coordination study of A 220kV Cable line”, IEEE

Power Engineering society winter meeting, vol. 3 pp 2082 – 2086, 2000.

[3] H. Mokhlis, A. Abu Bakar, H. Azil, I. Mohd and F. Shafie. “Insulation Coordination

study of 275kV AIS Substation in Malaysia”. IEEE,Vol. 12, No. 2 pp 43, 44, 2012.

[4] EN Insulation Co-ordination part 1: Definitions, principles and rules, EN 60071-1

Standard, 1996.

[5] EN Insulation part 2: Application guide, EN 60071-2 Standard, 1998.

[6] IEEE Insulation Coordination – Definitions, principles and rules, IEEE std 1313, 1, 1996.

[7] Central station Engineers of the Westinghouse Electric Corporation. “ Electrical

transmission and distribution reference book”. pp 610 – 642, 1964.

Page 113: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

93

[8] ANSI C92.1-1982, American national standard for power systems-insulation

coordination.

[9] IEC 71-1-19-12, Insulation coordination Part 1 : Definitions, principles and rules, 1993.

[10] IEC Publication 71-1-1976, Insulation coordination, Part 1: Terms, definitions and rules.

[11] Online Electrical Engineering study site. “Insulation coordination in power system”.

www.electrical4u.com edition, 2014.

[12] J. Rohan Lucas. “High Voltage Engineering”. Department of Electrical Engineering,

University of Moratuwa, Sri Lanka Third edition, pp 174, 2001.

[13] D. Fulchiron. “ Overvoltages and Insulation Coordination in MV and HV”, Cahier

Technique Merlin GerinE/CT. pp 3,4,5, 1995.

[14] J.B. Gupta. “A course in Electrical Power”, S.K. Kataria Part III pp 457 – 463, 2007-08.

[15] A. R. Hileman. “ Insulation Coordination for Power Systems”. CRC Press, Taylor and

Francis group pp 11 – 13, 1999.

[16] E. Kuffel, W.S. Zaengl, J. Kuffel. “High Voltage Engineering Fundamentals”.

Butterworth-Heinemann second edition, pp 495 – 500, 2000.

[17] P. Dymarski “ Hidden Markov Models, Theory and Applications”. Intech Janeza Trdine

9, 51000 Rijeka, Croatia. ISBN 978-953-307-208-1, 2011.

[18] A.S. Farag “Insulation Coordination from the probabilistic point of view”, IEEE Trans.

on Dielectric and Electrical,6(2): pp 259 – 266, 1999.

Page 114: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

94

[19] L. Xiaolin , M. Parizean, R. Plamordon “Training Hidden Markov models with multiple

observations – A combinational method” IEEE Transactions on PAM 1, vol. PAM 1 – 22, no

4, pp 371–377, April 2000.

[20] J. Yang, J. Zhang, F. Tanj, H. Jian, Y. wang and B. Wang, “Discrete Hidden Markov

model for transient stability assessment in power system” Journal of computational

information systems” vol 10, No. 24 pp 10499 – 10510, 2014.

[21] J. Chung, E.J. Powers, W.M. Grady and S.C. Bhatt “Power disturbance classifier using a

rule based method and wavelet packet-based hidden markov model”, IEEE Trans. power

Del., Vol. 17, No. 11 pp. 233 – 241, 2002.

[22] Lawrence and A. Rabiner “A Tutorial on hidden markov models and selected

application in speech recognition”, Proc. of IEEE, Vol. 11, No. 2 pp. 257 – 285, 1989.

[23] IS/IEC 60071 – 2: Insulation Coordination, part 2: Application Guide [ETD 19: High

Voltage Engineering] pp. 84, 1996.

[24] IEEE working Group 3.4.11, “Modelling of metal oxide surge Arresters”, IEEE

Transaction on power Delivery, Vol. 7 No 1, January 1992.

[25] J. Mayer, “Practical Insulation Coordination for lightning induced overvoltages”,

Technical Director, Energy services, Aurecon, session for Earthing, lightning and surge

protection – IDC Technologies, 2013.

[26] A.J. Hileman, “Insulation Coordination for power systems”, Marcel Dekker Inc, 1999.

Page 115: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

95

[27] Indian standard “Insulation Coordination” part 2 application guide. Bunma of Indian

standards, 2012.

[28] IEEE 1313.2- “IEEE Guide for the Application of Insulation Coordination”, institute of

Electrical and Electronic Engineers, New york, 1999.

[29] J. Woodwolt, “Substation Insulation Coordination Study”. Arrester works June 2011.

[30]J. Mayer "Practical Insulation coordination for Lightning Induced Overvoltages earthing,

lightning & surge protection” - IDC technologies, , session four AureCon, 2013.

Page 116: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

96

APPENDIX A

MATLAB M-FILE SOURCE CODE THAT IMPLEMENT HMM ALGORITHM

%the default false value

FALSEVALUE = -1.0 ;

%in baum-welch algorithm, the stop-condition is set using ratio( that is (probFinal-

probInit)/probInit )

RATIOLIMIT = 0.001 ;

%in baum-welch algorithm, when the circle of do...while exceed certain number, break it and

return the

%result

ROUNDLIMIT = 5 ;

%in baum-welch algorithm, in case the denominator is zero, so set it to a very very small

double number

DENOMINATORLIMIT = 10e-70 ;

%******** these are variables in Hmm itself **********************%

%the number of states : Q={1,2,...,N}

int N ;

//the number of observation symbols : V={1,2,...,M}

int M ;

%the probability transition matrix : A[1..N][1..N]

%A[i][j] is the probability from state i to j

double A ;

%the probablity emition matrix : B[1..N][1..M]

%B[j][k] is the probabiltiy of the observation symbol k in the state j

double U = [OUT_PUT_IMPEDANCE SURGE_IMPEDANCE EARTH_IMPEDANCE ] ;

%the initial state distribution

%pi[i] is the initial state probability

vector<double> pi ;

%********** these are variables used(created) in Hmm ****************%

%the T value of the last time

int iPreT ;

%the alpha variable used in forward procedure and Baum-Welch procedure

%alpha[t][i] is the probability of the observation sequence O1,O2....Ot and reach state i given

%modul u

alpha

= [] ;

%the beta variable used in forward procedure and Baum-Welch procedure

%beta[t][i] is the probability of the observation sequence Ot,...OT given modul u and state i

double beta =[];

%the delta variable used in viterbi algorithm

%delat[t][j] = max P(X1...Xt,O1...Ot,Xt=j | u )

double delta =[];

%the gamma variable used in baum-welch algorithm

Page 117: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

97

%gamma[t][i] = P( Xt=i | O,u )

double gamma = [];

%some allocating memory function to 2-dimonsion array

nrerror( string errStr ) ;

iMatrix( int irLow, int irHigh, int icLow, int icHigh ) ;

float** fMatrix( int irLow, int irHigh, int icLow, int icHigh ) ;

double** dMatrix( int irLow, int irHigh, int icLow, int icHigh ) ;

%the functions to free memory

iFreeMatrix( int** iMatrix, int irLow, int irHigh, int icLow, int icHigh ) ;

fFreeMatrix( float** fMatrix, int irLow, int irHigh, int icLow, int icHigh ) ;

dFreeMatrix( double** dMatrix, int irLow, int irHigh, int icLow, int icHigh ) ;

%the initialize function

%random set the matrixes to the value between 0 and 1

InitHmm( int iSeed ) ;

%output Hmm to the file,espcially for SIMULINK

WriteHmm( string strFileName ) ;

% output Hmm to the file,espcially for SIMULINK

WriteHmm( char* sFileName ) ;

%read a Hmm from the file named "strFileName", for SIMULINK

void ReadHmm( string strFileName ) ;

%read a Hmm from the file named "strFileName",

void ReadHmm( char* sFileName ) ;

%read the observation sequence to the vector sequence, espcially for SIMULINK

ReadSequence( ifstream& in, vector<int>& sequence ) ;

%read the observation sequence to the array sequence, espcially for c

ReadSequence( FILE* pFile, int*& sequence, int& iNum ) ;

%generate sequence function, it's not much use in fact, but funny

%generate the sequence according Hmm for SIMULINK

%parameters : iSeed : the seed to generate random number

% O : the returned observation sequence

% S : the returned state sequence

GenerateSequence( int iSeed, int T, vector<int>& O, vector<int>& S ) ;

%generate the sequence according Hmm for c

%parameters : iSeed : the seed to generate random number

% O : the returned observation sequence

% S : the returned state sequence

GenerateSequence( int iSeed, int T, int* O, int* S ) ;

%the functions serve GenerateSequence( int iSeed, vector<int>& O, vector<int>& S )

%get the initial state using iSeed

% GetInitialState( int iSeed ) ;

%generate an output symbol according to the given state

int GetSymbol( int iState ) ;

%get the next state according to the transittion probability and given state

int GetNextState( int iState ) ;

%the core functions of Hmm

%such as Forward and Backward functions and viterbi function and Baum-Welch function

%public:

%the forward function for SIMULINK interface

Page 118: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

98

double Forward( int T, vector<int>& O ) ;

%the forward function for c interface

double Forward( int T, int* O ) ;

%the forward function with scale ( been normalized ) and return the log value of the

probability

%the reason using a log value, i think, is to smooth the original value which is much small

%this function is designed especially for SIMULINK interface

ForwardNormalized( int T, vector<int>& O) ;

%the forward function with scale ( been normalized ) and return the log value of the

probability

%the reason using a log value, i think, is to smooth the original value which is much small

%this function is designed especially for c interface

ForwardNormalized( int T, int* O) ;

%the backward function for SIMULINK interface

Backward( int T, vector<int>& O ) ;

%the backward function for c interface

Backward( int T, int* O ) ;

%the backward function with scale to normalize and return the log value of the probability

%the

reason using a log value, is the same with forwardnormalized procedure

%it's very similar to the forwardnormalized procedure

%this function is designed especially for SIMULINK interface

BackwardNormalized( int T, vector<int>& O ) ;

%the backward function with scale to normalize and return the log value of the probability

%the reason using a log value, is the same with forwardnormalized procedure

%it's very similar to the forwardnormalized procedure

%this function is designed especially for c interface

BackwardNormalized( int T, int* O ) ;

%the viterbi algorithm for SIMULINK interface

%parameter: T : the number of the observation sequence % O :

the observation sequence % S :

the most likely state sequence as return value

%return value : the probability of the state sequence

Viterbi( int T, vector<int>& O, vector<int>& S ) ;

%the viterbi algorithm for c interface

%parameter: T : the number of the observation sequence % O :

the observation sequence % S :

the most likely state sequence as return value

%return value : the probability of the state sequence

Viterbi( int T, int* O, int*& S ) ;

%the baum-welch algorithm, for SIMULINK interface

%parameter: T: the number of the observation sequence

% O: the observation sequence

% probInit : the probability of the observation sequence calculated by the origin model

% probFinal : the probability of the observation sequence calculated by the adjusted

%model

% note: this algorithm is often not used and it' also the most complex one in hmm

BaumWelch( int T, vector<int>& O, double& probInit, double& probFinal ) ;

%the baum-welch algorithm, for c interface

%parameter: T: the number of the observation sequence

Page 119: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

99

% O: the observation sequence

% probInit : the probability of the observation sequence calculated by the origin model

% probFinal : the probability of the observation sequence calculated by the

adjusted

%model

%note

: this algorithm is often not used and it' also the most complex one in hmm

void BaumWelch( int T, int* O, double& probInit, double& probFinal ) ;

%the function called by baum-welch algorithm

%allocate gamma memory and calculate it

ComputeGamma( int T, int N, double probTemp ) ;

%allocate p memory and calculate it, for c++ interface

%p[t][i][j] = p( Xt=i,Xt+1=j | O,u ), is the probability of transitting from state i to state j

double*** ComputeP( double*** p,int T, int N, vector<int>& O, double prob ) ;

%allocate p memory and calculate it, for c interface

%p[t][i][j] = p( Xt=i,Xt+1=j | O,u ), is the probability of transitting from state i to state j

double*** ComputeP( double*** p,int T, int N, int* O, double prob ) ;

%recalculate the probability of hmm parameters( pi, A and B ), for transient vectors

RecomputeParameter( double***& p, int T, vector<int>& O, double probInit, double&

probFinal ) ;

%recalculate the probability of hmm parameters( pi, A and B ), for c++ interface

RecomputeParameter( double***& p, int T, int* O, double probInit, double& probFinal ) ;

%free the memory of 3-diminson matrix

PFreeMatrix( double*** p, int T ) ;

Hmm(scenario_A);

Hmm(scenario_B);

Hmm(scenario_C);

%There are two methods to initialize a Hmm:

%One way is to read a Hmm from a file which store it

% ( of course, you can state a Hmm object and explicitly call the function of

Hmm::ReadHmm(char* sFileName) )

%The other is to set the size of state set and output alphabet set and initialize it with random

value

Hmm( WORKSPACE[] strFileName ) ; % for SIMULINK interface

Hmm( [surge_impedance ] sFileName ) ; % for interface

Hmm( int NHmm, int MHmm, int iSeed ) ;

//and there is the third one : to initialize Hmm with every variable in it

Hmm( int NHmm, int MHmm, double** AHmm, double** BHmm, vector<double>&

piHmm ) ; };

%some allocating memory function to 2-dimonsion array

nrerror( string errStr ) ;

int** iMatrix( int irLow, int irHigh, int icLow, int icHigh ) ;

float** fMatrix( int irLow, int irHigh, int icLow, int icHigh ) ;

double** dMatrix( int irLow, int irHigh, int icLow, int icHigh ) ;

% the functions to free memory

% iFreeMatrix( int** iMatrix, int irLow, int irHigh, int icLow, int icHigh ) ;

% fFreeMatrix( float** fMatrix, int irLow, int irHigh, int icLow, int icHigh ) ;

% dFreeMatrix( double** dMatrix, int irLow, int irHigh, int icLow, int icHigh ) ;

BlockType Reference

Name "Three-Phase\nSeries RLC Load2"

Page 120: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

100

Ports [0, 0, 0, 0, 0, 3]

Position [240, 747, 305, 803]

Orientation "left"

NamePlacement "alternate"

AttributesFormatString "\\n"

DialogController "POWERSYS.PowerSysDialog"

FontName "Verdana"

FontSize 11

SourceBlock "powerlib/Elements/Three-Phase\nSeries RLC Load"

SourceType "Three-Phase Series RLC Load"

PhysicalDomain "powersysdomain"

SubClassName "unknown"

LeftPortType "p1"

RightPortType "p1"

LConnTagsString "A|B|C"

Configuration "Y (grounded)"

NominalVoltage "33e3"

NominalFrequency "60"

ActivePower "250e6"

InductivePower "200e6"

CapacitivePower "0"

Measurements "None"

Block {}

BlockType Reference

Name "Three-Phase\nSeries RLC Load3"

Ports [0, 0, 0, 0, 0, 3]

Position [1372, 1135, 1428, 1200]

Orientation "down"

AttributesFormatString "\\n"

DialogController "POWERSYS.PowerSysDialog"

FontName "Verdana"

FontSize 11

SourceBlock "powerlib/Elements/Three-Phase\nSeries RLC Load"

SourceType "Three-Phase Series RLC Load"

PhysicalDomain "powersysdomain"

SubClassName "unknown"

LeftPortType "p1"

RightPortType "p1"

LConnTagsString "A|B|C"

Configuration "Y (grounded)"

NominalVoltage "33e3"

NominalFrequency "60"

ActivePower "250e6"

InductivePower "200e6"

CapacitivePower "0"

Measurements "None"

Branch {}

ConnectType "SRC_DEST"

SrcBlock "Three-Phase Breaker"

SrcPort RConn1

Page 121: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

101

Points [90, 0; 0, 80; 60, 0]

}

Branch {

ConnectType "SRC_DEST"

SrcBlock "Surge Arrester4"

SrcPort RConn1

Points [45, 0; 0, 5]

Line {}

LineType "Connection"

SrcBlock "Surge Arrester8"

SrcPort RConn1

Points [60, 0]

Branch {

ConnectType "DEST_SRC"

DstBlock "Ground5"

DstPort LConn1

}

Branch {

ConnectType "DEST_DEST"

Points [1700, 470; 25, 0]

Branch {

ConnectType "SRC_DEST"

SrcBlock "Surge Arrester9"

SrcPort RConn1

Points [50, 0; 0, -35]

}

Branch {

ConnectType "SRC_DEST"

SrcBlock "Surge Arrester7"

SrcPort RConn1

Points [50, 0; 0, 55]

}

}

Line {

LineType "Connection"

SrcBlock "Surge Arrester11"

SrcPort RConn1

Points [60, 0]

Branch {

ConnectType "DEST_SRC"

DstBlock "Ground6"

Line {

LineType "Connection"

SrcBlock "132KV/33KV_4"

SrcPort RConn1

Points [-10, 0]

Branch {

ConnectType "DEST_SRC"

DstBlock " 22"

DstPort RConn1

Page 122: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

102

Line {

LineType "Connection"

SrcBlock "Lightning Impulse Current \nSource"

SrcPort LConn1

Points [-25, 0]

DstBlock "Ground11"

DstPort LConn1

}

Line {

SrcBlock " 25"

SrcPort 1

Points [-25, 0; 0, -65]

DstBlock "Scope1"

DstPort 1

}

Line {

LineType "Connection"

SrcBlock "Ground12"

SrcPort LConn1

DstBlock " 25"

DstPort LConn2

}

Line {

LineType "Connection"

SrcBlock "Lightning Impulse Current \nSource"

SrcPort RConn1

Points [10, 0; 0, 55]

DstBlock "Current Measurement"

DstPort LConn1

Page 123: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

103

APPENDIX B: ARRESTER NAME PLATE

Page 124: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

104

APPENDIX C: TRANSFORMER NAME PLATE

Page 125: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

105

Page 126: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

106

V

Page 127: AN INSULATION CO-ORDINATION PROCEDURE … INSULATION CO-ORDINATION PROCEDURE FOR POWER SYSTEM ... This makes analysis of over voltage ... 2.4 Insulation Coordination Principle 14 2.4.1

107

APPENDIX C