analysis of customer requirement fulfillment process at hval
TRANSCRIPT
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
1/38
OperationsOperationsManagement AtManagement At
HVALHVAL
Arijit MitraArijit Mitra
Inderjit SinghInderjit SinghMridulMridul
SharmaSharma
Rahul RaiRahul Rai
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
2/38
HVAL
Formed in March 2000
Manufacturing Axles & Axle parts for Medium & HeavyCommercial vehicles
B2B Entity
Capacity of over 3.6 lakh axles per annum.
&VAL in M HCV Indianndustr &VAL in M HCV Tata MotorsLtd
Meritor,Tongil,Steyr
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
3/38
PRODUCTS OF HVAL
LIVE FRONT AXLE REAR AXLE
NORMAL FRONT AXLE
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
4/38
. (S Aich AGM Planni
.AJamaiyar
( )COO.G Ahuja( )CFO
. .P KChoudhury
( .)DGM Engg
DHBUFABURABUPPCHR and BES. &Matl ADD&CQ CM
. . (A B Lall CEO HVAL and)HVTL
BUSINESSUNITS
Organizational Chart
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
5/38
ROCESS PLANNING
TRATEGIC CAPACITY PLANNING
/ .PE RA TI ON S AG G P LA NN IN G
UPPLY NETWORK PLANNINGORECASTING AND DEMANDMANAGEMENT
MANUFACTURING SERVICESLOGISTICS
.ATL EQUIREMENTSPLANNING
RDERSCHEDULING
APACITYPLANNING
DISPATCHING
/H RECEIPTLANNING
AILY ORKFORCESCHEDULING
IDEAL PROCESS FLOW DIAGRAM
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
6/38
ENTERPRISE PROCESS MODELENTERPRISE PROCESS MODEL
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
7/38
HVAL PROCESS MANAGEMENTPYRAMID
VisionMissionore ValuestrategicDirectioneader System
S tr a t
e g ic L
e v el
I m pl e m
e n ta t i
o nL e v
e l
B u si n
e s sL e v
e l EVEL 1
EVEL 2
EVEL3
PM 9 Top level processesPM 9 Top level processes
+PM 40 sub processes
NPI
Infrastructure creation and maintenance
Finance
,Vendor mgmt material and logistics,HR Legal and Admin,Production QA and maintenance Customer support
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
8/38
VALUE CREATION SYSTEM
SUPPORT SYSTEM
EMAND CREATIONCustomer requirement determination
DEMAND FULFILLMENTPRODUCT
DEVELOPMENTPROCESS
PRODUCTION AND
DELIVERY PROCESS
AFTER SALES AND
SUPPORT PROCESS
,Expectations StatutoryRequirements
uman Resource Mgmt Finance and budgetinga ci li ty an d E nv iro nm ent M gm t
LEA
DE
RSHIP
SYST
EM
. &Devbudgeting of.NPI prod Plan
&MonitoringExecution of
NPI Project
.Prod Design.and Dev
ProductionPlanning
Manufacturing
Maintenance
Vendor Management
. Warranty Mgmt
.Spare Parts Mgmt
Customer Complaint
.mgmt
1
23
6
5
9
d i liP N 5 P d i & D li
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
9/38
Process No. 5: Production & DeliveryProcess No. 5: Production & DeliveryProcessProcess
SUB PROCESS NOSUB PROCESS NO SUB PROCESS NAMESUB PROCESS NAME OWNER DEPT.OWNER DEPT.
5-015-01 Production, Planning & SchedulingProduction, Planning & Scheduling PPCPPC
5-025-02 Produce aggregates and componentsProduce aggregates and components Central Quality and MaintenanceCentral Quality and Maintenance
5-035-03 Maintenance of machines and equipmentMaintenance of machines and equipment Central Quality and MaintenanceCentral Quality and Maintenance
5-045-04 Selection and development of VendorsSelection and development of Vendors Materials & ADDMaterials & ADD
5-055-05 Part Development ProcessPart Development Process Materials & ADDMaterials & ADD
5-065-06 Procurement processProcurement process Materials & ADDMaterials & ADD
5-075-07 Vendor Performance Monitoring & Improvement ProcessVendor Performance Monitoring & Improvement Process Materials & ADDMaterials & ADD
5-085-08 Vendor Rationalization ProcessVendor Rationalization Process Materials & ADDMaterials & ADD
5-095-09 Performance ImprovementPerformance Improvement Materials & ADDMaterials & ADD
5-105-10 Process Design & ImprovementProcess Design & Improvement EngineeringEngineering
5-115-11 Manage SafetyManage Safety COOCOO
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
10/38
ROCESS PLANNING
TRATEGIC CAPACITY PLANNING
/ .PE RA TI ON S AG G P LA NN IN G
UPPLY NETWORK PLANNINGORECASTING AND DEMANDMANAGEMENT
MANUFACTURING SERVICESLOGISTICS
.ATL EQUIREMENTSPLANNING
RDERSCHEDULING
APACITYPLANNING
DISPATCHING
/H RECEIPTLANNING
AILY ORKFORCESCHEDULING
IDEAL PROCESS FLOW DIAGRAM WITH EPM
-01
- -04 to 5 09
-01
-10
-01-01
&aken care of by HR B
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
11/38
HUMAN RESOURCE( )PSD
ENGINEERINGRESEARCH
CENTRE
NEW PRODUCTINTRODUCTION
PRODUCTION&PLANNING
CONTROL
AUTODEVELOPMENT
DEPARTMENT
MATERIALS
DHBURABUFABU
SPIG
MASTERPRODUCTION
SCHEDULE
MANPOWER
MRPINBOUNDLOGISTIC
DISPATCHepartmentepartmentInteractionsnteractions EW PRODUCTEW PRODUCT EGULAREGULARPRODUCTRODUCT
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
12/38
PRODUCTION PLANNINGCONTROL
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
13/38
PPC Structure
( . )AGM R P Singh
MI M2 M3
SUPERVISIORS
E Grades Temporary Grade
- ( )TM2 TM3 Manager Grade
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
14/38
,ay plan from TML PPC Jamshedpur& ( . .)Confirmation from ADD Material dept and Production Dept 9 to 10 a m ( All aggregate PPC meeting at TML to freeze schedule for next day This is c
( : . )Production meeting at HVAL 3 30 p m to freeze the productioProductionDispatch for all customer
- (day plan process For only)amshedpur Plant
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
15/38
( ) -from TML Vehicle level on 26 27th of previous month (Order transferred at axle level Two sub part DOMESTI
,Circulation of the requirement to ADD Material and CO( - )etting information from Material for deciding the priority Confirmation of 4 5 Days( ) ( , , )nt final to every department HR Quality Production etc
(onthly Process Common to all)ustomers
( - )Orders Received at the Vehicle Level 18 19 Models
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
16/38
Demand Forecasting
Method of forecasting: Done by Tata Motors. Mainly experience from the past sales and datagiven by Sales and Marketing
Error in forecasting: Cost is born by Tata Motors, so they take care of. Demand is Dependentin nature.
Demand sources Tata motors (Jamshedpur, Lucknow and Pune)
Spare parts,
Vehicle factory Jabalpur (Defense),
Telcon
Dutch Lanka Trailer.
Key Points Bullwhip effect is not considerable as less number of parties are involved in the supply chain
Demand of vehicle is cyclical. It increases in Jan to March and decreases from April to June
Cyclical component: model based. Overall it is cyclic
HVAL is answerable to Board if they are not able to meet the demand.
Inventory Audit is done on daily basis.
Lucknow-Bucket Plan (May be for a week)
Spare parts (Monthly Plan)
Seasonality factors: Yes, some bonus in some season
Random variation: Taken care at the time of release
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
17/38
Planning strategy: Determined byPSD, Dominantly chase
Backordering cost: Indirect cost isthere. HVAL is answerable to board.
Inventory control: PPC isresponsible for the FG inventory.
Inventory calculation: Manualaudit and SAP.
D A ILY P LA N
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
18/38
D A ILY P LA N
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
19/38
MONTHLY PLAN
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
20/38
AUTO DEVELOPMENTDEPARTMENT
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
21/38
( )List given by NPI BOMalong with design
documents
Categorization from( , ,BOM given by NPI A B C
-Requirement sent to 3 4suppliers with documents
and quotation asked
,Quotation if obtainedsent to Price panel for
.estimation of cost acc ToZero Based Costing
Negotiation ofsupplier with price
panel
OK?
NO
YES
PO released
,Sample with FMEAProcess flow diagram
.etc from suppliers
QA checking of sample
with all documentsOK?
NO
YES
Again sample has tobe given by supplier
PPAP lotdemanded
Inspectionby SQIG
OK?YES
Rejected
Ownershiptransferred to
.materials deptfor regular
supply
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
22/38
Supplier Selection basis:
Quality (both for new and regular part)(% of Rejection)
Cost (both for new and regular part)
Capability (both for new and regular part)
Delivery time (for regular part)
Requirement of documents from suppliers
Inspection Check
PFP
Control Plan
Failure Mode Effect
Metallurgical grain flow report
Commitment Inventory Category
A- Inventory up to 10 days
B- Not expensive, inventory up to month
C- Low value items, up to 3 months
Key Points
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
23/38
MATERIALS DEPARTMENT
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
24/38
ERC
NPI
PPC
Demandschedule
NEW
REGULAR
ADD
Aggregate
Part
Source,Yearly
&monthlyDaily schedule
for supply
Follow up withsuppliers
Supply tostore
OK?
NSPECTIONY SPIG( )A
NO
YESSupply toProduction line
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
25/38
Inventory control
11 days inventory is being kept by Material dept. Value based Inventorysystem.
Basis of the 11 days:Geographic location
Cost of part
Lead time Shelf life of the material
Order quantity/volume
Key Points Generally 6 vendors are kept for each component
5-10% extra order
For local vendor, JIT concept is applicable.
MRP Structure: SAP is used
Placing order: Price panel and Materials dept. jointly take decision
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
26/38
PRODUCTIVITY SERVICEDEPARTMENT
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
27/38
PROJECT
NEW PROJECT REGULARPROJECT
PROJECTED VOL OF PRODUCTION( ) WITH VARIATION
MANPOWER CALCULATED AS PER(STANDARD FOR THE VARIATION
)ALSO
ARRANGEMENT OF MANPOWER
PLANNING
MANPOWERREQUIREMENT
ASSESSMENT BYPSD
ARRANGEMENT OF MANPOWER
Demand fromproduction
OK
YES
NO
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
28/38
Recruitment: From employment exchangesand local diploma colleges (Students from ITI,ITDR)
Operators pay decision:
Productivity Index of the company
Quality Index of the company
Safety Index of the company
EBIT of the company
Calculation: Payment = Fixed payment + Variable payment
Variable payment = f (Productivity Index of thecompany, Quality Index of the company,Safety Index of the company and EBIT of the
company).
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
29/38
SCORECARD ASSESSMENT
DIVISIONAL HEADFEEDBACK
,PSD HR AND DIVISION HEADREVIEW
FINAL GRADING
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
30/38
Key Activities:
Audit for document adherence (Mainly for NPI, ERC andQuality Department) as per the guidelines of TataBusiness Excellence model
Supplier quality Assurance (at the supplier end)
Quality inspection before sending to assembly line
Pre-dispatch inspection of the finished product
Statistical process control:
DFMEA and PFMEA Flow chart
Run Chart
Pareto chart
Fish Bone diagram
Check-sheet Opportunity Flow diagram
Process control chart
Quality at supplier end:
Zig and fixture quality (critical dimensions checking)
Process capability of supplier
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
31/38
Quality Assurancedepartment
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
32/38
An example of Quality ControlProcess
Failure
Fish Bone diagram
DFMEA/PFMEA
Root cause found (if it is criticaldimension related)
Process control chart used tostandardize the design/process
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
33/38
New Product Introduction
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
34/38
Different types of project Handled byNPI
/Existing Regular
Mix and Match
ProductImprovement
Green Field
ow ost High
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
35/38
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
36/38
Maintenance
dopted Nakajima s TPM model mplementation at the PlantLevel uarter Kaizen program PM Manual EE measurement
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
37/38
Operational Strategy
-
8/7/2019 Analysis of Customer Requirement Fulfillment Process at HVAL
38/38
Technology Management
Outsourced to Tata Technologies Limited.
Critical Technologies are as follows
Digital manufacturing technology (Delmia) Pro-E for computer aided Design Product lifecycle management software System Application Product (SAP) Software for Design and Analysis (Gear Engineer Pro, MS
Nastran, LS Diana etc.)