    i) 16 x 16 mm

    Cost of Material 11.00 Per Rft 11.00 Per Rft

    Labour Charages for Fixing 2.00 Per Rft 2.00 Per Rft

    Total 13.00 Per Rft

    Add 10% Contractor Profit 1.30 Per Rft

    Total 14.30 Per Rftii) 16 x 25 mm

    Cost of Material 14.00 Per Rft 14.00 Per Rft

    Labour Charages for Fixing 2.00 Per Rft 2.00 Per Rft

    Total 16.00 Per Rft

    Add 10% Contractor Profit 1.60 Per Rft

    Total 17.60 Per Rft

    iii) 40 x 40 mm

    Cost of Material 38.0 Per Rft 38.00 Per Rft

    Labour Charages for Fixing 2.00 Per Rft 2.00 Per Rft

    Total 40.00 Per Rft

    Add 10% Contractor Profit 4.00 Per Rft

    Total 44.00 Per Rft

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    Unit of Rate = Per Rft

    RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING &

    FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.

    ISLAMIA UNIVERSITY BAHAWALPUR

    Supply and Eraction of duct work for wiring (Dura Adamgee) with rawal

    plugs,Screws and specials complete in all respects.

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    2/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    3/242

    Description3

    Unit of Rate = Each

    Cost of Material 1 No 65 65.00 Each

    Labour Charages for Fixing 1 No 5 5.00 Each

    Total 70.00 Each

    Add 10% Contractor Profit 7.00 Each

    Total 77.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    Supply and Eraction 2 Pins 10/15 AMPS Socket imported (TURKY) complete in all

    respects.

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING &

    FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    4/242

    Description

    4 Supply and Eraction Switches 10/15 AMPS Piano type (Best quality)

    Unit of Rate = Each

    Cost of Material 1 No 20 20.00 Each

    Labour Charages for Fixing 1 No 5 5.00 Each

    Total 25.00 Each

    Add 10% Contractor Profit 2.50 Each

    Total 27.50 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING &

    FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    5/242

    Description

    5

    Unit of Rate = Each

    Cost of Material 1 No 220 220.00 Each

    Labour Charages for Fixing 1 No 10 10.00 Each

    Total 230.00 Each

    Add 10% Contractor Profit 23.00 Each

    Total 253.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    Supply and Eraction Switche,plug combined Power plug 30/35 AMPS (Bush Company)

    Submitted for Approval

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING &

    FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.

  • 8/13/2019 Analysis of Rate of Building Deportment

    6/242

    Description6 Supply and Eraction distribution board (D.B) 2'x1.50' Size with following detail.

    100 AMPS MCCB 3-Phase 240 Volts Circuit breaker

    20 AMPS MCB 1-Phase 240 Volts Circuits breaker

    10 AMPS MCB 1-Phase 240 Volts Circuits breaker

    6 AMPS MCB 1-Phase 240 Volts Circuits breaker

    All Circuit breakers Terasaki/Mitsubishi (Black) Japan to be used.

    Iron Box 2'x1.50' with Stove enameled paint.

    Unit of Rate = Each

    Cost of Iron Box 2'x1.50' 1 No 1800 1800.00 Each

    Cost of 100 AMPS 3-Phase Circuit breaker 1 No 2850 2850.00 Each

    Cost of 20 AMPS 1-Phase Circuit breaker 2 No 225 450.00 EachCost of 10 AMPS 1-Phase Circuit breaker 12 No 225 2700.00 Each

    Cost of 6 AMPS 1-Phase Circuit breaker 4 No 225 900.00 Each

    Cost of Thimbles 9 No 20 180.00 Each

    Labour Charages for Fixing 1 No 400 400.00 Each

    Total 9280.00 Each

    Add 10% Contractor Profit 928.00 Each

    Total 10208.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING &

    FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.

    Submitted for Approval

    ISLAMIA UNIVERSITY BAHAWALPUR

  • 8/13/2019 Analysis of Rate of Building Deportment

    7/242

    Description

    7

    Unit of Rate = EachCost of Light with Chock, Rod &

    Starter complete 1 No 1300 1380.00 Each

    Labour Charages for Fixing 1 No 100 100.00 Each

    Total 1480.00 Each

    Add 10% Contractor Profit 148.00 Each

    Total 1628.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    Supply and Eraction Ceiling lights 2'x2' size with reflective grill phlips rod 2' size 20 Watt,

    Philps Chock 40 Watt,Phlips Startar 20 Watt Patty Fitting (Frame of light 2'x2') Pak

    light/Equaliant i/c hanging arrangement.

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING &

    FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    8/242

    Description

    Unit of Rate = Each

    Cost of Fan 1 No 1500 1500.00 Each

    Labour Charages for Fixing 1 No 50 50.00 Each

    Total 1550.00 Each

    Add 10% Contractor Profit 155.00 Each

    Total 1705.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING &

    FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.

    Providing & Fixing Wall Bracket Fan with Plastic Body (Pak Fan, G.F.C or Royal Co. of 18"

    Sweep. Complete in all respects.

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    9/242

    Description

    Unit of Rate = Per Sft

    Cost of Material 1 Sft 12.00 12.00 Each

    Labour Charages for Fixing 1 Sft 4.00 4.00 Each

    Total 16.00 Each

    Add 10% Contractor Profit 1.60 Each

    Total 17.60 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING &

    FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.

    Submitted for Approval

    ISLAMIA UNIVERSITY BAHAWALPUR

    Providing & Fixing False ciling of plaster of paris with hanging arrangements and design

    and samples as approved by the Engineer Incharge Complete in all respects.

  • 8/13/2019 Analysis of Rate of Building Deportment

    10/242

    Description

    1. Supply and Eraction of duct work for wiring (Dura Adamgee) with rawal

    plugs,Screws and specials complete in all respects.

    i) 16 x 16 mm

    Cost of Material 11.00 Per Rft 11.00 Per Rft

    Labour Charages for Fixing 2.00 Per Rft 2.00 Per Rft

    Total 13.00 Per Rft

    Add 10% Contractor Profit 1.30 Per Rft

    Total 14.30 Per Rft

    ii) 16 x 25 mm

    Cost of Material 14.00 Per Rft 14.00 Per Rft

    Labour Charages for Fixing 2.00 Per Rft 2.00 Per Rft

    Total 16.00 Per Rft

    Add 10% Contractor Profit 1.60 Per Rft

    Total 17.60 Per Rft

    iii) 40 x 40 mm

    Cost of Material 38.0 Per Rft 38.00 Per Rft

    Labour Charages for Fixing 2.00 Per Rft 2.00 Per Rft

    Total 40.00 Per Rft

    Add 10% Contractor Profit 4.00 Per RftTotal 44.00 Per Rft

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    Submitted for Approval

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR

    CENTRAL LIBRARY AT B.J. CAMPUS.

    Unit of Rate = Per Rft

  • 8/13/2019 Analysis of Rate of Building Deportment

    11/242

    Description

    2

    Unit of Rate = Each

    Cost of Deodar wood Board 9"x4"x3" 1 No 40 40.00 Each

    Cost of Bekolite sheet 4mm thick 9"x4" 1 No 30 30.00 Each

    Labour Charages for Fixing 1 No 15 15.00 Each

    Total 85.00 Each

    Add 10% Contractor Profit 8.50 Each

    Total 93.50 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR

    CENTRAL LIBRARY AT B.J. CAMPUS.

    Supply and Eraction deodar wood box 9"x4"x3" deep I/c bekolite sheet 4mm thick I/c making holes for

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    12/242

    Description

    5

    Unit of Rate = Each

    Cost of Material 1 No 270 270.00 Each

    Labour Charages for Fixing 1 No 10 10.00 Each

    Total 280.00 Each

    Add 10% Contractor Profit 28.00 Each

    Total 308.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR

    CENTRAL LIBRARY AT B.J. CAMPUS.

    Supply and Eraction Power plug, Switche Plug combined 30/35 AMPS (Bush Company)

    including shoe 3 pins 20 AMPS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    13/242

    Project Director

    Description

    6 Supply and Eraction distribution board (D.B) 18"'x15" Size with following detail.

    100 AMPS MCCB 3-Phase 240 Volts Circuit breaker

    20 AMPS MCB 1-Phase 240 Volts Circuits breaker

    All Circuit breakers Terasaki/Mitsubishi (Black) Japan to be used.

    Iron Box 18"x15" with Stove enameled paint.

    Unit of Rate = Each

    Cost of Iron Box 18"x15" 1 No 1350 1350.00 Each

    Cost of 100 AMPS 3-Phase Circuit breaker 1 No 2850 2850.00 Each

    Cost of 20 AMPS 1-Phase Circuit breaker 8 No 225 1800.00 Each

    Labour Charages for Fixing 1 No 400 400.00 Each

    Total 6400.00 Each

    Add 10% Contractor Profit 640.00 Each

    RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR

    CENTRAL LIBRARY AT B.J. CAMPUS.

    ISLAMIA UNIVERSITY BAHAWALPUR

  • 8/13/2019 Analysis of Rate of Building Deportment

    14/242

    Total 7040.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    DescriptionSupply and Eraction of "U" Clamp for Shackle insulators with Nut bolts and Pins etc complete.

    Unit of Rate = Each

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR

    CENTRAL LIBRARY AT B.J. CAMPUS.

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    15/242

    Cost of "U" Clamp and Nut bolts & Pins 1 No 130 130.00 Each

    Cost of Labour for fixing 1 No 10 10.00 Each

    Total 140.00 Each

    Add 10% Contractor Profit 14.00 Each

    Total 154.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    16/242

    DescriptionSupply and Eraction of pole stay including enchor rod 3/4" dia with MS Plate

    galvanized as per Wapda standard with concrete block (1:2:4) 2' dia 6" thickincluding stay wire complete in all respects.

    Unit of Rate = Each

    Cost of Stay Rod 3/4" dia with MS Plate 1 No 400 400.00 Each

    Cost of Stay Wire 1 No 600 600.00 Each

    Cost of Concrete Block 2' dia 6" thick 1 No 300 300.00 Each

    Labour charges for fixing 1 No 400 400.00 Each

    Total 1700.00 Each

    Add 10% Contractor Profit 170.00 Each

    Total 1870.00 Each

    Sub Engineer Assistant Engineer Executive Engineer

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR

    CENTRAL LIBRARY AT B.J. CAMPUS.

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    17/242

    Description

    Excavation in foundation of building

    Unit of Rate = 1000 Cft

    Labour Charages:

    Excavation 1000.00 @ 148.00 % Cft

    TNP Charges 1000.00 @ 45.00 %o Cft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Rs. 1830/- %o Cft

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Approved for

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    RATE ANALYSIS

    ISLAMIA UNIVERSITY BAHAWALPUR

    Rs.1,830.00

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    18/242

    CIVIL WORKS

    Description

    Cement Concrete Brick or Stone Ballast 1.5" to 2" gauge 1:6:12

    Unit of Rate = 100 Cft

    Material Cost:

    Brick Ballast 97.00 Cft 9.00 Per Cft

    Cement 6.50 Bag 333.00 Per Bag

    Sand 48.00 Cft 9.00 Per Cft

    Total

    Labour Charages: 100.00 Cft 700.00 % Cft

    TNP Charges 100.00 Cft 81.00 % Cft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Say Rs.5100/-

    ASSISTANT ENGINEER SUB-EN

    DEPUTY PROJECT DIRECTOR

    Description

    Spraying antitermite

    Submitted for Approval

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    Project Director

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    19/242

    Unit of Rate = 100 Cft Per Sft.

    Material Cost: (for 3oo Sft) 1 Ltr 310.00 Per Lit

    TNP Charges 100.00 Sft 10.00 100 Sft

    Labour Charages: 100.00 Sft 15.00 100 Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft. Rs. 1.2 1.53

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Pacca Brick work in foundation and plinth. 1:6

    Unit of Rate = 100 Cft 100 Cft

    Material Cost:

    Bricks 1350.00

    5% Wastage 68.00

    1418.00 Nos 2200.00 1000 No

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    CIVIL WORKS

    Project Director

    A p p r o v e d

  • 8/13/2019 Analysis of Rate of Building Deportment

    20/242

    Cement 3.50 Bag 333.00 P/Bag

    Sand 26.00 Cft 9.00 P/Cft

    TNP

    I Labour Charages:

    TotalAdd 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Say

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Pacca Brick work in Ground Floor 1:5

    Unit of Rate = 100 Cft 100 Cft

    Material Cost:

    Bricks 1350.00

    5% Wastage 68.00

    1418.00 Nos 2200.00 1000 No

    Cement 4.00 Bag 333.00 P/Bag

    Sand 26.00 Cft 9.00 P/Cft

    TNP

    Labour Charges:

    RATE ANALYSIS

    CIVIL WORKS

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

  • 8/13/2019 Analysis of Rate of Building Deportment

    21/242

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Say

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Damp Proof Course 2" thick I/c bitumen coating and polythene sheet

    Unit of Rate = 100 Cft 100 Sft

    Material Cost:

    Crush 15.00 Cft 28.00 Per Cft

    Cement 2.75 Bag 333.00 P/Bag

    Sand 28.00 Cft 9.00 P/CftBitumen 10.00 Kg 45.90 Per Kg

    Polythene Sheet 500 guage 100.00 Sft 1.00 Per Sft

    TNP

    Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Say

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    CIVIL WORKS

    Project Director

    A p p r o v e d

  • 8/13/2019 Analysis of Rate of Building Deportment

    22/242

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Reinforced Cement Concrete in foundation 1:2:4

    Unit of Rate = 100 Cft Per Cft

    Material Cost:

    Crush 88.00 Cft

    5% Wastage 4.00 Cft

    Total 92.00 Cft 30.00 Per Cft

    Cement 17.60 Bag 325.00 P/Bag

    Sand 44.00 Cft 9.00 P/Cft

    TNP

    Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft 121.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    23/242

    Description

    Reinforced Cement Concrete in foundation 1:1.5:3

    Unit of Rate = 100 Cft Per Cft

    Material Cost:

    Crush 84.00 Cft

    5% Wastage 4.00 Cft

    Total 88.00 Cft 30.00 Per CftCement 22.40 Bag 325.00 P/Bag

    Sand 42.00 Cft 9.00 P/Cft

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft 139.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Submitted for Approval

    Submitted for Approval

    Project Director

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    24/242

    Description

    Reinforced Cement Concrete in foundation 1:2:4

    Unit of Rate = 100 Cft

    Material Cost:

    Crush 88.00 Cft

    5% Wastage 4.00 Cft

    Total 92.00 Cft 30.00 Per Cft

    Cement 17.60 Bag 325.00 P/Bag

    Sand 44.00 Cft 9.00 P/Cft

    TNP

    Labour Charages:Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft 121.00

    ASSISTANT ENGINEER SUB-EN

    DEPUTY PROJECT DIRECTOR

    The Islamia University of Bahawalpur

    CIVIL WORKS

    Project Director

    Project Director

    RATE ANALYSIS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    25/242

    Description

    Reinforced Cement Concrete in Ground Floor 1:1.5:3

    Unit of Rate = 100 Cft Per Cft

    Material Cost:

    Crush 84.00 Cft

    5% Wastage 4.00 Cft

    Total 88.00 Cft 30.00 Per Cft

    Cement 22.40 Bag 325.00 P/Bag

    Sand 42.00 Cft 9.00 P/Cft

    TNP

    Shuttering Charges

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft 175.00

    ASSISTANT ENGINEER SUB-EN

    DEPUTY PROJECT DIRECTOR

    Project Director

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    26/242

    Description

    Reinforced Cement Concrete in Ground Floor 1:2:4

    Unit of Rate Per Cft

    Material Cost:

    Crush 88.00 Cft5% Wastage 4.00 Cft

    Total 92.00 Cft 23.00 Per Cft

    Cement 17.60 Bag 180.00 P/Bag

    Sand 44.00 Cft 9.00 P/Cft

    TNP

    Shuttering Charges

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft 111.36

    ASSISTANT ENGINEER SUB-EN

    DEPUTY PROJECT DIRECTOR

    Description

    Fabrication of mild steel (40 grade) Prime Steel, Afco Steel

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    27/242

    Unit of Rate = 100 Cft Per kg

    Material Cost:

    Steel 100.00 Kg

    5% Wastage 5.00 Kg

    Total 105.00 Kg 3880.00 100 KgSteel Binding Wire 3.00 Kg 70.00 Per Kg

    TNP

    I Labour Charges:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Kg 55.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Fabrication of mild steel (40 grade)

    Unit of Rate Per kg

    Material Cost:

    Steel 100.00 Kg

    5% Wastage 5.00 Kg

    Total 105.00 Kg 3200.00 100 Kg

    Steel Binding Wire 3.00 Kg 60.00 Per Kg

    TNPI Labour Charges:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Kg 46.08

    Submitted for Approval

    Project Director

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    28/242

    ASSISTANT ENGINEER SUB-EN

    DY. PROJECT DIRECTOR

    Description

    Fabrication of High Tensile steel (60 grade)

    Unit of Rate = 100 Cft Per kg

    Material Cost:

    Steel 100.00 Kg

    5% Wastage 5.00 Kg

    Total 105.00 Kg 4200.00 100 Kg

    Steel Binding Wire 3.00 Kg 70.00 Per Kg

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Kg 59.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    CIVIL WORKS

    Submitted for Approval

    The Islamia University of BahawalpurRATE ANALYSIS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    29/242

    Description

    Cement plaster 1:5 1/2" thick 0' to 20' height

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.00 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per Cft

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 12.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

    Project Director

    The Islamia University of Bahawalpur

  • 8/13/2019 Analysis of Rate of Building Deportment

    30/242

    Description

    Cement plaster 1:3 3/8" thick

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.00 Bag

    Cement for neru 0.25 Bag

    1.25 Bag 333.00 Per Bag

    Sand 2.50 Cft 9.00 Per Cft

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead ChargesTotal

    Rate Per Sft 12.50

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    31/242

    Description

    Cement plaster 1:5 3/4" thick

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.50 Bag 310.00 Per Bag

    Sand 4.00 Cft 8.00 Per Cft

    TNP

    I Labour Charages: Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 12.86

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER DEPUTY

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    32/242

    Description

    Dry brick ballast 1.5" to 2" gauge

    Unit of Rate = 100 Cft Per Cft

    Material Cost: 100.00 Cft 12.00 Per CftTNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft 16.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    33/242

    Description

    Polythene Sheet 500 Gauge

    Unit of Rate = 100 Cft Per Sft

    Material Cost: 100.00 Sft 1.00 Per Sft

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 1.32

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Project Director

    The Islamia University of BahawalpurRATE ANALYSIS

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    34/242

    Description

    Vertical DPC 1:3 1/2" thick with 2 coat bitumen

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.25 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per Cft

    Bitumen 16.00 Kg 45.90 Per Kg

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 22.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Rubber Water Stopper 10" wide 1/4" thick

    Submitted for Approval

    Project Director

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    35/242

    Unit of Rate = 100 Cft Per Rft

    Material Cost: 1.00 Rft 50.00 Per Rft

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Rft 62.40

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Bitumen Coating 20 Lbs per 100 Sft.

    Unit of Rate = 100 Cft Per Sft

    Material Cost Bitumen: 16.00 Lbs 25.00 Per Lbs

    Carocine oil 1.00 ltr 40.00 Per Ltr

    TNPI Labour Charages:

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

  • 8/13/2019 Analysis of Rate of Building Deportment

    36/242

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per sft 10.50

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    First Class Brick walling 4.5" thick 1:3 hoop iron 12" apart

    Unit of Rate = 100 Cft 100 Sft

    Material Cost:

    Bricks 518.00

    5% Wastage 26.00

    544.00 Nos 2200.00 1000 No

    Cement 2.25 Bag 333.00 P/Bag

    Sand 13.00 Cft 9.00 P/Cft

    Hoop Iron 100.00 Rft 5.00 Per Rft

    CIVIL WORKS

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    37/242

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft. 40.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Spray plaster

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.00 Bag 333.00 Per Bag

    Marble Chips 5.00 Bag 25.00 Per BagTNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 13.00

    ASSISTANT ENGINEER SUB-EN

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    38/242

    EXECUTIVE ENGINEER

    Description

    Mosaic Dado or Skirting 1/2" thick (grey cement) Unit of Rate = 100 Cft Per Sft

    1 Material Cost:

    Cement 1.25 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per Cft

    TNP

    I Labour Charages:

    Total

    2 Material Cost:

    Cement 3.00 Bag 333.00 Per Bag

    Marble Chips 8.00 Bag 25.00 Per Bag

    Marble Powder 2.00 Bag 25.00 Per Bag

    TNP

    I Labour Charages:

    Griding Charges

    Polish Charges

    Total

    Gramd Total A+BAdd 10% Contractor Profit

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

  • 8/13/2019 Analysis of Rate of Building Deportment

    39/242

    Add 10% Overhead Charges

    Total

    Rate Per Sft 38.50

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Extra Labour for Arch Work

    Unit of Rate = 100 Cft Per Cft

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead ChargesTotal

    Rate Per Cft 6.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

  • 8/13/2019 Analysis of Rate of Building Deportment

    40/242

    Description

    Pacca Brick work in foundation and plinth. 1:3

    Unit of Rate = 100 Cft 100 Cft

    Material Cost:

    Bricks 1350.00

    5% Wastage 68.00

    1418.00 Nos 2200.00 1000 No

    Cement 6.00 Bag 333.00 P/Bag

    Sand 25.00 Cft 9.00 P/Cft

    TNP

    Labour Charges:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Say

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    41/242

    Description

    Earth filling under floor

    Unit of Rate = 100 Cft 1000 Cft

    1 Surplus earth from foundation

    TNP 1000.00 Cft

    I Labour Charages: 1000.00 Cft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per 1000 Cft 1400.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    42/242

    Description

    Sand filling under floor

    Unit of Rate = 100 Cft Per Cft

    1 sand 100.00 Cft 9.00 Per Cft

    TNP 100.00 Cft

    I Labour Charages: 100.00 Cft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft. 11.5

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    43/242

    Description

    Brick on edge floor

    Unit of Rate = 100 Cft Per Sft

    1 Material

    Brick 550.00 No

    5% Wastage 28.00

    578.00 No 2200.00 Per 1000

    Cement 1.25 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per Cft

    TNP 100.00 Sft

    I Labour Charages: 100.00 Cft 5.00 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 26.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    The Islamia University of Bahawalpur

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    44/242

    Description

    Mosaic Floor 1.5" thick, 1" thick 1:2:4 1/2" Mosaic Topping

    Unit of Rate = 100 Cft Per Sft

    1 Material (100 Sft)

    Cement 1:2:4 2.11 Bag 333.00 Per Bag

    Sand 5.38 Cft 9.00 Per Cft

    Crush 10.56 Cft 28.00 Per Cft

    Cement Mosaic toping 2.00 Bag 333.00 Per Bag

    Powder 2.00 Bag 25.00 Per Bag

    Chips 8.00 Bag 25.00 Per Bag

    TNP

    I Labour Charages: 100.00 Cft 8.00 Per Sft

    Griding

    Polish

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 37.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    1/4" thick glazed coloured tile for Dado & Skirting.

    Project Director

    CIVIL WORKS

    Submitted for Approval

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    45/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    46/242

    ASSISTANT ENGINEER

    EXECUTIVE ENGINEER

    Description

    Marble Strip 1.5" x 3/8" size

    Unit of Rate = 100 Cft Per Rft

    1 Material (100 (100 Rft)

    Marble strip 100.00 Rft 2.00 Per Rft

    Cement (Grey)Sand

    TNP

    I Labour Charages: 100.00 Rft 1.50 Per Rft

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Rft 5.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    The Islamia University of Bahawalpur

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    47/242

    Description

    Roof Insulation

    Unit of Rate = 100 Cft Per Sft

    1 Material (100 (100 Sft)

    Tile 9"x4.5"x1.5" 350.00

    5% Wastage 18.00

    368.00 No 2200.00 Per 1000

    Bitumen 20.00 Lbs 25.00 Per Lbs

    Polythene Sheet 500 Gauge 100.00 Sft 1.00 Per Sft

    Earth 16.00 Cft 3.00 Per Cft

    jumbo lawn 1" thick 100.00 Sft 30.00 Per Sft

    Cement 1.00 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per CftTNP

    I Labour Charages: 100.00 Sft 4.15 Per Sft

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per sft 63.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    48/242

    The Islamia University of Bahawalpur

    Description

    Khurras on roof 2'x2'x4"

    Unit of Rate = 100 Cft Per No

    1 Material

    Cement 0.30 Bag 333.00 Per Bag

    Crush 1.20 Cft 28.00 Per Cft

    Sand 0.60 Cft 9.00 Per Cft

    TNP

    I Labour Charages: 1.00 No 93.00 Per No

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per No 290.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    CIVIL WORKS

    Submitted for Approval

    Project Director

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    49/242

    Description

    Bottom Khurras

    Unit of Rate = 100 CftPer No

    1 Material

    Cement 0.50 Bag 333.00 Per Bag

    Brick 42.00 No 2200.00 Per 1000

    Crush 2.00 Cft 28.00 Per Cft

    Sand 2.00 Cft 9.00 Per Cft

    TNP

    Labour Charges: 1.00 No 78.00 Per No

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    TotalRate Per No 505.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    50/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    51/242

    Description

    Cost Iron Bend 4" dia

    Unit of Rate = 100 Cft Per No

    1 Material

    CI bend 4" dia (Tipu) 1.00 No 190.00 Per No

    Paint 2.00 Sft 7.00 Per Sft

    I Labour Charages: 1.00 No 30.00 Per No

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per No 281/-

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Solid Flush Door

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    52/242

    Unit of Rate = 100 Cft Per Sft

    1 Material (7'x4')

    Pertal Wood 2.24

    30% Wastage 0.67

    2.91 Cft 600.00 Per Cft

    Deodar Wood 0.08

    30% Wastage 0.02

    0.10 Cft 1600.00 Per Cft

    Commercial Ply 5 mm thick 56.00 Sft 15.00 Per Sft

    Gelu 2.00 Kg 50.00 Per Kg

    Kick Plate 8.00 Rft 20.00 Per Rft

    Handle 2.00 No 15.00 Per No

    Finger Plate 2.00 No 25.00 Per No

    Tower Bolt 1.00 No 30.00 Per No

    Hinges 3.00 No 25.00 Per No

    Screws

    Labour Charges: 28.00 Sft 20.00 Per Sft

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 162/-

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Safety Grill

    Unit of Rate = 100 Cft Per Sft

    1 Material (6'x6')

    Angle Iron 1"x1"x1/8" 6.00 Kg 38.00 Per Kg

    Square Bar 3/8"x3/8" 30.00 Kg 38.00 Per KgLabour for welding 36.00 Sft 20.00 Per Sft

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    53/242

    Paint 36.00 Sft 8.00 Per Sft

    Cement

    Crush

    Sand

    Labour for fixing at site

    Total

    Add 10% Contractor Profit

    Add 10% Overhead ChargesTotal

    Rate Per Sft 86.70

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Sliding Bolt 10"/12"

    Unit of Rate = 100 Cft Per No

    Sliding Bolt Cromium 1.00 No 92.50 Per No

    Labour for fixing at site 1.00 No 20.00 Per No

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per No 135.00

    Project Director

    Submitted for Approval

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    54/242

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Enamel Paint 3 Coat for doors and windows etc

    Unit of Rate = 100 Cft Per Sft

    Material (4'X7')

    Primer Paint 1.00 Qtr 35.00 Per Qtr

    Paint (ICI,Robilac) 1.00 Qtr 130.00 Per Qtr Tarbine Oil 1.00 Qtr 10.00 Per Qtr

    TNP

    Labour 28.00 Sft 2.00 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 10.00

    ASSISTANT ENGINEER SUB-EN

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    55/242

    EXECUTIVE ENGINEER

    Description

    Terrace Railing

    Unit of Rate = 100 Cft Per Rft

    Material (10 Rft)

    M.S Condute Pipe 2" dia 16 SWG 10.00 Rft 50.00 Per Rft

    M.S Bar 5/8"x5/8" 29.00 Kg 38.00 Per Kg

    M.S. Flat 1"x1/8" 2.00 Kg 38.00 Per Kg

    Labour for welding 10.00 Rft 30.00 Per Rft

    TNP

    Labour for fixing at site

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Rft 261.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    56/242

    Description

    Cement Pointing Deep Struck Joint 1:2

    Unit of Rate = 100 Cft Per Sft

    Material (100 Sft)

    Cement 1.00 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per CftTNP

    Labour charges 100.00 Sft 4.00 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 10.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

    Project Director

    The Islamia University of Bahawalpur

  • 8/13/2019 Analysis of Rate of Building Deportment

    57/242

    Description

    Extra Cost for red oxide

    Unit of Rate = 100 Cft Per Sft

    Material (100 Sft)

    Red Oxide Pigment 4.00 Kg 30.00 Per Kg

    TNP

    Labour charges 100.00 Sft 1.00 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 2.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    58/242

    Description

    Distempering of walls 3 Coat including preparation of Surface completein all respect.Colour Scheme as approved by the Engineer Incharge.

    Unit of Rate = 100 Cft Per Sft

    Material (100 Sft)

    Distemper 0.50 G Rs. 155.00 Per G

    T&P, Colour ChangeLabour charges 100.00 Sft Rs. 1.00 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft. 225/100 = 2.25

    SUB-ENGINEER Deputy P

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

  • 8/13/2019 Analysis of Rate of Building Deportment

    59/242

    Description

    White Washing 3 Coat Unit of Rate = 100 Cft Per Sft

    Material (100 Sft) 5.00 Kg 2.00 Per Kg

    Gelu

    Blue Powder

    TNP

    Labour charges 100.00 Sft 0.50 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 1.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    60/242

    Description

    P/F aluminium strip 3"x1/8" on Expension Joint

    Unit of Rate = 100 Cft Per Rft

    Material (10 Rft)

    Strip 3"x1/8" 10.00 Rft 20.40 Per Rft

    Screw/Rawal plugTNP

    Labour charges 10.00 Rft 5.00 Per Rft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Rft 34.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    61/242

    DescriptionThermopore sheet 1-1/2" thick for expension joint

    Unit of Rate = 100 Cft Per Sft

    Material

    Thermopore 1-1/2" 1.00 Sft 8.20 Per Sft

    Labour charges 1.00 Sft 1.00 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 11.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    The Islamia University of Bahawalpur

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    RATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    62/242

    Description

    6" Wide Curved Sheet on Expension Joint

    Unit of Rate = 100 Cft Per Rft

    Material

    Sheet 18 Swg 10.00 Rft 25.00 Per Rft

    Screw/Rawal Plug

    TNP

    Labour charges

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Rft 40.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Cement Concrete plain 1:2:4

    Project Director

    CIVIL WORKS

    Submitted for Approval

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    63/242

    Unit of Rate = 100 Cft Per Cft

    Material (100 Cft)

    Cement 17.60 Bag 333.00 Per Bag

    Crush 92.00 Cft 28.00 Per Cft

    Sand 44.00 Cft 9.00 Per Cft

    TNP

    Labour charges

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft 120.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    P/F Wardrobe.

    Unit of Rate = 100 Cft Per Sft

    Material 3'x7'

    M.S pipe 3"x1.5" 18 SWG 20.00 Rft 32.15 Per Rft

    Labour welding

    Commercial Win Board 3/4" thick 21.00 Sft

    10% Wastage 2.00

    23.00 Sft 27.25 Per Sft

    CIVIL WORKS

    Submitted for Approval

    Project Director

    The Islamia University of Bahawalpur

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    64/242

    Deodar Wood 0.04 Cft

    30% Wastage 0.01

    0.05 Cft 1600.00 Per Cft

    Aluminium Rod 3.00 Rft 12.00 Per Rft

    Bracket 2.00 No 20.00 Per No

    Tower Bolt 2.00 No 20.00 Per No

    Lock 808 1.00 No 35.00 Per No

    Handle 1.00 No 20.00 Per No

    Hardware Charges

    Paint 42.00 Sft 10.00 Per Sft

    Labour charges 21.00 Sft 15.00 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 146.00

    SUB-EN

    DEPUTY PROJECT DIRECTOR

    Description

    P/F STEEL GRATED DOOR.

    Unit of Rate = 100 Cft Per Sft

    Material 4'x7'

    M.S angle iron 1.5"x1.5"x3/16" 25.00 Kg

    M.S Sheet 1/16" 30.00 Kg

    55.00 Kg 40.00 Per Kg

    Welding Labour Charges 55.00 Kg 9.00 Per Kg

    Red Oxide Paint

    Sliding Bolt. 2.00 No 138.00 Each

    TNP

    Labour for fixing at site

    Total

    Add 10% Contractor Profit

    CIVIL WORKS

    Submitted for Approval

    PROEJCT DIRECTOR

    The Islamia University of Bahawalpur

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    65/242

    Add 10% Overhead Charges

    Total

    Rate Per Sft 150.89

    SUB-EN

    DEPUTY PROJECT DIRECTOR

    Description

    Steel Windwos Openable

    Unit of Rate = 100 Cft Per Sft

    Material (6'x6')

    M.S Box pipe 2"x1.5" (16 SWG) 48.00 Rft 25.00 Per Rft

    M.S Box Pipe 1.5"x1" (16 SWG) 72.00 Rft 20.00 Per Rft

    M.S Box Ppipe 1/2"x1/2" (18 SWG) 72.00 Rft 10.00 Per Rft

    M.S Box Ppipe 3/8"x3/8" (18 SWG) 72.00 Rft 8.00 Per Rft

    M.S Flat 1"x1/8" 72.00 Rft 5.00 Per Rft

    M.S Flat 3/4"x1/8" 48.00 Rft 4.00 Per Rft

    5 mm thick glass 36.00 Sft 30.00 Per Sft

    Hinges 16.00 No 20.00 Per NoHandle 4.00 No 20.00 Per No

    Stay Rod 8.00 No 25.00 Per No

    Wire Gauze 24 SWG 36.00 Sft 15.00 Per Sft

    Painting 108.00 Sft 10.00 Per Sft

    Labour for welding 36.00 Sft 29.00 Per Sft

    Labour for fixing at site

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 300.00

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    A p p r o v e d

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    66/242

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Providing & Fixing Kitchen Cabinet

    Unit of Rate = 100 Cft Size 3' x 7'

    Material

    M.S pipe 3"x1.25" 18 SWG 20.00 Rft 35.00 Per Rft

    Labour welding

    Lamination Board 3/4" thick 21.00 Sft

    10% Wastage 2.00

    23.00 Sft 32.00 Per Sft

    Deodar Wood 0.04 Cft

    30% Wastage 0.01

    0.05 Cft 1600.00 Per Cft

    Tower Bolt 2.00 No 18.00 Per No

    Lock 808 1.00 No 32.00 Per No

    Handle 1.00 No 15.00 Per No

    Hardware ChargesPaint 42.00 Sft 10.00 Per Sft

    Labour charges 21.00 Sft 15.00 Per Sft

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Cft 148.00

    ASSISTANT ENGINEER SUB-EN

    SNACK BARE OF ENGINEERING COLLEGE

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Project Director

    A p p r o v e d

  • 8/13/2019 Analysis of Rate of Building Deportment

    67/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    68/242

    Description

    Providing & Fixing open able Wardrobe Commercial Vin Board 3/4" thick for A/

    Unit of Rate = P sft

    Materials 2.25x2.75'MS pipe 1.5''x1.5'' 18 SWG 12.38 Rft 47.5 P.Rft

    Labour rate welding LS

    Commercial Vin Board 3/4" thick 5.00 Sft 50.00 Per Sft

    Wooden Beading LS 50.00

    Tower Bolts 4.00 Nos 35.00 each

    Handle 2.00 Nos 20.00 each

    Labour charges

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    RATE PSFT RATE P.SFT RS=

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER Project D

    Name of Work:Construction Faculty Hostel for Women at B.

    Director Engineering

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    NON SCHEDULE CIVIL WORKS

    Approved

  • 8/13/2019 Analysis of Rate of Building Deportment

    69/242

    Description

    Cement plaster 1:5 1/2" thick

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.00 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per Cft

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 13.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    The Islamia University of BahawalpurRATE ANALYSIS

    CIVIL WORKS

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    70/242

    Description

    Cement plaster 1:3 3/8" thick

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.00 Bag

    Cement for neru 0.25 Bag

    1.25 Bag 333.00 Per Bag

    Sand 2.50 Cft 9.00 Per Cft

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead ChargesTotal

    Rate Per Sft 13.50

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Submitted for Approval

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    71/242

    Description

    1/4" thick mat coloured tile for floor.

    Unit of Rate = 100 Cft Per Sft

    1 Material (100 Sft)

    Tile 100.00 Sft

    5% Wastage 5.00

    105.00 Sft 40.70 Per Sft

    Cement (Grey) 1.50 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per Cft

    Cement WhiteTNP

    I Labour Charages: 100.00 Sft 9.00 Per Sft

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 72.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Submitted for Approval

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    72/242

    Description

    Cement plaster 1:3 3/4" thick

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.25 Bag 333.00 Per Bag

    Sand 3.00 Cft 9.00 Per Cft

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 14.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    CIVIL WORKS

    CIVIL WORKS

    Submitted for Approval

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    73/242

    Earth filling under floor lead 3 mile.

    Unit of Rate = 1000 Cft

    Earth 1000.00 Cft 2.65 Cft

    Labour Charges:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft ######

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER

    Description

    Pacca Brick work in foundation and plinth. 1:5

    Unit of Rate = 100 Cft 100 Cft

    Material Cost:

    Submitted for Approval

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    CIVIL WORKS

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    74/242

    Bricks 1350.00

    5% Wastage 68.00

    1418.00 Nos 2200.00 1000 No

    Cement 4.00 Bag 333.00 P/Bag

    Sand 26.00 Cft 9.00 P/Cft

    TNP

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Say

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER DEPUTY

    Description

    Cement pointing struck joint on walls up to 20' height ratio 1:2

    Unit of Rate = 100 Cft Per Sft

    Material Cost:

    Cement 1.50 Bag 333.00 Per Bag

    Sand 4.00 Cft 9.00 Per Cft

    TNP

    Project Director

    A p p r o v e d

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    CIVIL WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    75/242

    I Labour Charages:

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Sft 14.00

    ASSISTANT ENGINEER SUB-EN

    EXECUTIVE ENGINEER DEPUTY

    Submitted for Approval

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    76/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    77/242

    Description

    Unit of Rate = 100 Cft Per Rft

    1 Cost of Morble 3"x12"x3/4" 1.00 No. 62.50

    2 Wastage 3%3 Carriage 1.00 No. 0.66

    4 Material Cost of Floating Coat (MRS July 2005) 0.25 Sft 336.10

    5 Cost of Martor under marble 3/4" thick (MRS Jul 05)

    6 Ratio 1:2 0.25 Sft 7.88

    7 Cost of floating coat (MRS July 2005). 0.25 Sft 336.10

    8 Cost of PCC 1:2:4 1" thick (MRS July 2005) 0.25 Sft 1103.90

    9 Cost of Pigment 0.25 Sft 4.50

    10 Cost of Labour for fixing & chemical polishing (10+14) 0.25 Sft 24.00

    Total

    Add 10% Contractor Profit on Items No. 1-3, 9 & 10

    Add 10% over head charges on Items No. 1-3, 9 & 10G. Total

    ASSISTANT ENGINEER SUB-EN

    DEPUTY PROJECT DIRECTOR

    Approved

    Cons truc ti on of Admin is t ra ti on Block for Un ivers it y Co l lege of Eng ineer ing a

    Baghd ad-ul-Jadeed Campu s

    Providing and fixing marble 3/4" thick 12" long 3" wide with pure chocklate colour with floating coat of ceme

    of 3/4" thick cement sand mortar 1:2 over 1" thick PCC 1:2:4 Gray cement, including colour pigment to mat

    colour of marble tiles, laid with cement sand mortor 1:2 rubbing and chemical polishing complete in all resp

    directed and approved by the Engineer incharge.

    SAY

    The Islamia University of Bahawalpur

    RATE ANALYSIS

    CIVIL WORKS

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    78/242

    Description

    Unit of Rate = 100 Cft Per Sft

    1 Cost of Marble 3/4" thick 36"-60"/13.5" i/c chemical polishing 1.00 Sft 135.002 Carriage 1.00 Sft 3.00

    3 Loading, unloading and stacking 1.00 Sft 5.004 Material Cost of Floating Coat (MRS July 2005) 1.00 Sft 336.10

    5 Cost of Martor under marble 3/4" thick (MRS Jul 05)

    Ratio 1:2 1.00 Sft 7.88

    6 Cost of floating coat (MRS July 2005). 1.00 Sft 336.10

    7 Cost of Pigment 1.00 Sft 4.50

    8 Cost of Labour for fixing & chemical polishing (10+14) 1.00 Sft 10.00

    Total

    Add 10% Contractor Profit on Items No. 1-3, 7 & 8

    Add 10% over head charges on Items No. 1-4, 7 & 8

    G. Total

    ASSISTANT ENGINEER SUB-EN

    Approved

    Project Director

    The Islamia University of Bahawalpur

    Construct ion of Adm inistrat ive Block for Universi ty Col lege of Engineer ing

    RATE ANALYSIS

    CIVIL WORKS

    Providing and fixing botiseana/fency marble for stair steps 3/4" thick 36"-60"/13.5" with floating co

    of 3/4" thick cement sand mortar 1:2 including colour pigment to match with the colour of marble t

    sand mortor 1:2 rubbing and chemical polishing complete in all respects as directed and approve

    incharge.

    S

  • 8/13/2019 Analysis of Rate of Building Deportment

    79/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    80/242

    1480.00

    45.00

    1525.00

    152.50

    152.50

    1830.00

    INEER

    1000 Cft

  • 8/13/2019 Analysis of Rate of Building Deportment

    81/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    82/242

    103.00

    10.00

    15.00

    128.00

    12.80

    12.80

    153.60

    INEER

    3119.60

  • 8/13/2019 Analysis of Rate of Building Deportment

    83/242

    1165.50

    234.00

    148.00

    1000.00

    5667.10566.71

    566.71

    6800.52

    6800.00

    INEER

    3119.60

    1332.00

    234.00

    200.00

    948.00

  • 8/13/2019 Analysis of Rate of Building Deportment

    84/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    85/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    86/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    87/242

    2760.00

    5720.00

    396.00

    200.00

    1000.0010076.00

    1007.60

    1007.60

    12091.20

    120.912

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    88/242

    2640.00

    7280.00

    378.00

    200.00

    3000.00

    1100.00

    14598.00

    1459.80

    1459.80

    17517.60

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    89/242

    2116.00

    3168.00

    396.00

    100.00

    3000.00

    500.00

    9280.00

    928.00

    928.00

    11136.00

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    90/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    91/242

    INEER

    4410.00

    210.00

    100.00

    200.00

    4920.00

    492.00

    492.00

    5904.00

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    92/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    93/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    94/242

    465.00

    32.00

    75.00

    500.00

    1072.00

    107.20

    107.20

    1286.40

    INEER

    PROJECT DIRECTOR

  • 8/13/2019 Analysis of Rate of Building Deportment

    95/242

    1200.00

    34.00

    100.00

    1334.00

    133.40

    133.40

    1600.80

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    96/242

    100.00

    10.00

    110.00

    11.00

    11.00

    132.00

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    97/242

    416.25

    27.00

    734.40

    156.00

    500.00

    1833.65

    183.37

    183.37

    2200.38

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    98/242

    50.00

    2.00

    52.00

    5.20

    5.20

    62.40

    INEER

    400.00

    40.00

    150.00285.00

  • 8/13/2019 Analysis of Rate of Building Deportment

    99/242

    875.00

    87.50

    87.50

    1050.00

    INEER

    1196.80

    749.25

    117.00

    500.00

  • 8/13/2019 Analysis of Rate of Building Deportment

    100/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    101/242

    416.25

    27.00

    50.00

    400.00

    893.25

    999.00

    200.00

    50.00

    200.00

    566.00

    200.00

    100.00

    2315.00

    3208.25320.83

  • 8/13/2019 Analysis of Rate of Building Deportment

    102/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    103/242

    2836.00

    1998.00

    225.00

    100.00

    675.00

    5834.00

    583.40

    583.40

    7000.80

    7000.00

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    104/242

    45.00

    1122.00

    1167.00

    116.70

    116.70

    1400.40

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    105/242

    900.00

    20.00

    38.50

    958.50

    95.85

    95.85

    1150.20

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    106/242

    1271.60

    416.25

    27.00

    52.00

    400.00

    2166.85

    216.69

    216.69

    2600.22

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    107/242

    702.63

    48.42

    295.68

    666.00

    50.00

    200.00

    100.00

    720.00

    200.00

    100.00

    3082.73

    308.27

    308.27

    3699.28

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    108/242

    4357.50

    499.50

    27.00

    150.00

    150.00

    900.00

    6084.00

    608.40

    608.40

    7300.80

    INEER

    with the structure

    400.00

    200.00

    100.00

    300.00

    150.001150.00

    115.00

    1265.00

    126.50

    126.50

    1518.00

    151.80

  • 8/13/2019 Analysis of Rate of Building Deportment

    109/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    110/242

    809.60

    500.00

    100.00

    48.00

    3000.00

    333.00

    27.0050.00

    415.00

    5282.60

    528.26

    528.26

    6339.12

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    111/242

    99.90

    33.60

    5.40

    10.00

    93.00

    241.90

    24.14

    24.14

    290.18

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    112/242

    166.50

    92.40

    56.00

    18.00

    10.00

    78.00

    420.90

    42.09

    42.09

    505.08

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    113/242

    800.00

    60.00

    63.00

    31.0010.00

    75.00

    1039.00

    103.90

    103.90

    1246.80

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    114/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    115/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    116/242

    288.00

    50.00

    20.00

    5.00

    150.00

    2601.00

    260.10

    260.103121.20

    INEER

    92.50

    20.00

    112.50

    11.25

    11.25

    135.00

  • 8/13/2019 Analysis of Rate of Building Deportment

    117/242

    INEER

    35.00

    130.0010.00

    10.00

    56.00

    241.00

    24.10

    24.10

    289.20

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    118/242

    500.00

    1102.00

    76.00

    300.00

    50.00

    150.00

    2178.00

    217.80

    217.80

    2613.60

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    119/242

    333.00

    27.0074.00

    400.00

    834.00

    83.40

    83.40

    1000.80

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    120/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    121/242

    77.50

    10.00100.00

    187.50

    18.75

    18.75

    225.00

    roject Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    122/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    123/242

    204.00

    20.0010.00

    50.00

    284.00

    28.40

    28.40

    340.80

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    124/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    125/242

    250.00

    20.00

    10.00

    53.00

    333.00

    33.30

    33.30

    399.60

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    126/242

    5860.80

    2576.00

    396.00

    175.00

    1000.00

    10007.80

    1000.78

    1000.78

    12009.36

    INEER

    643.00

    100.00

    626.75

  • 8/13/2019 Analysis of Rate of Building Deportment

    127/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    128/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    129/242

    INEER

    700.00

    100.00

    736.00

    80.00

    36.00

    32.00

    15.00

    150.00420.00

    315.00

    2584.00

    258.40

    258.40

    3100.80

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    130/242

    200.00

    10.00

    100.00

    310.00

    31.0031.00

    372.00

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    131/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    132/242

    333.00

    27.00

    50.00

    674.00

    1084.00

    108.40

    108.40

    1300.80

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    133/242

    416.25

    22.50

    75.00

    612.00

    1125.75

    112.58

    112.581350.90

    INEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    134/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    135/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    136/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    137/242

    3119.60

    1332.00

    234.00

    150.00

    1000.00

    5835.60

    583.56

    564.11

    6983.27

    7000.00

    INEER

    PROJECT DIRECTOR

    499.50

    36.00

    50.00

  • 8/13/2019 Analysis of Rate of Building Deportment

    138/242

    590.00

    1175.50

    117.55

    117.55

    1410.60

    INEER

    PROJECT DIRECTOR

  • 8/13/2019 Analysis of Rate of Building Deportment

    139/242

    Per Sft 125.00Per Sft 3.00

    Per Sft 5.00

    % Sft 3.36

    Per Sft 7.88

    % Sft 3.36

    Per Sft 4.50

    Per Sft 24.00

    176.10

    16.15

    16.15

    208.40

    208

    INEER

    ver a bed of 3/4" thick

    cement sand mortor

    ineer incharge.

    Y Rs.

    & Technology at

  • 8/13/2019 Analysis of Rate of Building Deportment

    140/242

    Each 62.50

    1.88Each 0.66

    % Sft 0.84

    Per Sft 1.97

    % Sft 0.84

    % Sft 2.76

    Per Sft 1.13

    Per Sft 6.00

    78.570

    7.22

    7.2293.002

    INEER

    nd Techn ology at

    nt over a bed

    h with the

    ects as

    Rs. 93.00 Per Rft

  • 8/13/2019 Analysis of Rate of Building Deportment

    141/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    142/242

    5

    ed in

    92.50

    20.00

    112.50

    11.25

    11.25

    135.00

    NT ENGINEER

  • 8/13/2019 Analysis of Rate of Building Deportment

    143/242

    Description

    G.I Pipe (Medium Quality).

    Unit of Rate Per Foot. 1/2" I/d 3/4" I/d 1" I/d 1.25" I/d 1.50" I/d 2" I/d

    G.I Pipe 25.00 32.00 45.00 60.00 75.00 95.00

    Accessores/Fittings. 5.00 7.00 10.00 20.00 30.00 35.00

    Labour charges 5.00 5.00 8.00 8.00 10.00 10.00

    35.00 44.00 63.00 88.00 115.00 140.00

    Add 10% Contractor Profit 3.50 4.40 6.30 8.80 11.50 14.00

    Add 10% Overhead Charges 3.50 4.40 6.30 8.80 11.50 14.00

    Total 42.00 52.80 75.60 105.60 138.00 168.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

    A p p r o v e d

  • 8/13/2019 Analysis of Rate of Building Deportment

    144/242

    Description

    Water Closet European type

    Unit of Rate Per No

    W.C (3 star-Master) Coloured 1.00 No 1600.00 Per No 1600.00

    Bend 1.00 No 150.00 Per No 150.00

    Labour charges 1.00 No 100.00 Per No 100.00

    1850.00

    Add 10% Contractor Profit 185.00

    Add 10% Overhead Charges 185.00

    Total 2220.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Rate approved for per No.

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

    Rs.2,220.00

  • 8/13/2019 Analysis of Rate of Building Deportment

    145/242

    Description

    Water Closet Orisa Pattern type

    Unit of Rate Per No

    W.C (3 star-Master) Coloured 1 No 650.00 Per No 650.00

    Cement 1 No 100.00 Each 100.00

    Sand 10.00

    PVC Bend 1 No 40.00 Each 40.00Labour charges 1 No 150.00 Per No 150.00

    Total 950.00

    Add 10% Contractor Profit 95.00

    Add 10% Overhead Charges 95.00

    Total 1140.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

  • 8/13/2019 Analysis of Rate of Building Deportment

    146/242

    Description

    Seat & Cover for European.

    Unit of Rate Per No

    Seat & Cover coloured 1 No 250.00 Per No 250.00

    Labour charges 1 No 25.00 Per No 25.00

    275.00

    Add 10% Contractor Profit 27.50

    Add 10% Overhead Charges 27.50

    Total 330.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

    A p p r o v e d

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    147/242

    Description

    Wash hand Basin 24" x 20"

    Unit of Rate Per No

    Wash hand Basin Coloured (Master-3 Star) 1 No 850.00 Per No 850.00

    Bracket Set 1 Set 75.00 Each 75.00

    Waste Pipe 1 No 40.00 Each 40.00

    Waste Coupline 1 No 125.00 Each 125.00

    Padestel 1 No 350.00 Each 350.00

    TNP 50.00

    Labour charges 1 No 150.00 Per No 150.00

    1640.00

    Add 10% Contractor Profit 164.00

    Add 10% Overhead Charges 164.00

    Total 1968.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    A p p r o v e d

    Project Director

    Plumbing Work

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    148/242

    Description

    P Trap Glazed

    Unit of Rate Per No

    P Trap (Full size) 1 No 60.00 Each 60.00

    Cement 20.00

    Labour charges 1 No 20.00 Per No 20.00

    100.00

    Add 10% Contractor Profit 10.00

    Add 10% Overhead Charges 10.00

    Total 120.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

  • 8/13/2019 Analysis of Rate of Building Deportment

    149/242

    Description

    Plastic made Flushing cistern (3 gallons) Master.

    Unit of Rate Per No

    Flushing Cistern (Coloured) 1 No 825.00 Each 825.00Brecket 1 Set 75.00 Each 75.00

    PVC Pipe 1 No 50.00 Each 50.00

    Rubber Connection 1 No 50.00 Each 50.00

    Labour charges 1 No 75.00 Each 75.00

    Total 1075.00

    Add 10% Contractor Profit 107.50

    Add 10% Overhead Charges 107.50

    Total 1290.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    RATE ANALYSIS

    Plumbing Work

    A p p r o v e d

  • 8/13/2019 Analysis of Rate of Building Deportment

    150/242

    Description

    Toilet Paper holder (Fasil/Alyas)

    Unit of Rate Per No

    Toilet Paper Holder 1 No 200.00 Each 200.00

    Labour charges 1 No 50.00 Each 50.00

    Total 250.00

    Add 10% Contractor Profit 25.00

    Add 10% Overhead Charges 25.00

    Total 300.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Plumbing Work

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

  • 8/13/2019 Analysis of Rate of Building Deportment

    151/242

    Description

    Chromium Plated Towel Rail 24" x 3/4".

    Unit of Rate Per No

    Rod 1.00 No 200.00 Each 200.00

    Brecket 2.00 No 40.00 Each 80.00

    Labour charges 1.00 No 30.00 Each 30.00

    Total 310.00

    Add 10% Contractor Profit 31.00

    Add 10% Overhead Charges 31.00Total 372.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Description

    Looking Glass Plastic Body (Master).

    RATE ANALYSIS

    Plumbing Work

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

  • 8/13/2019 Analysis of Rate of Building Deportment

    152/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    153/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    154/242

    Total 204.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Description

    Stop Cock Plastic Head 1/2" size (Fasil/Alyas).

    Unit of Rate Per No

    Stop Cock 1.00 No 250.00 Each 250.00

    Labour charges 1.00 No 20.00 Each 20.00

    Total 270.00

    Add 10% Contractor Profit 27.00

    Add 10% Overhead Charges 27.00

    Total 324.00

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

  • 8/13/2019 Analysis of Rate of Building Deportment

    155/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    156/242

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Description

    Bib Cock Plastic Head 1/2" size (Fasil/Alyas).

    Unit of Rate Per No

    Bib Cock 1.00 No 220.00 Each 220.00

    Labour charges 1.00 No 20.00 Each 20.00

    Total 240.00Add 10% Contractor Profit 24.00

    Add 10% Overhead Charges 24.00

    Total 288.00

    ASSISTANT ENGINEER SUB-ENGINEER

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

    A p p r o v e d

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    157/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    158/242

    Description

    Shower Roase 4" x 1/2" size adjustable (Fasil/Alyas).

    Unit of Rate Per No

    Shower Roase 1.00 No 180.00 Each 180.00

    Labour charges 1.00 No 20.00 Each 20.00

    Total 200.00

    Add 10% Contractor Profit 20.00

    Add 10% Overhead Charges 20.00

    Total 240.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Plumbing Work

    A p p r o v e d

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    159/242

    Description

    Mixing Valve Plastic Head (Fasil/Alyas).

    Unit of Rate Per No

    Mixing Valve 1.00 No 650.00 Each 650.00

    Labour charges 1.00 No 50.00 Each 50.00

    Total 700.00

    Add 10% Contractor Profit 70.00

    Add 10% Overhead Charges 70.00

    Total 840.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

    A p p r o v e d

  • 8/13/2019 Analysis of Rate of Building Deportment

    160/242

    Description

    Gun metal Peat/Gate Valve 1.5" to 2" (Anwar).Unit of Rate Per No

    Gun metal Peat/Gate 1.00 No 375.00 Each 375.00

    Labour charges 1.00 No 100.00 Each 100.00

    Total 475.00

    Add 10% Contractor Profit 47.50

    Add 10% Overhead Charges 47.50

    Total 570.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Plumbing Work

    A p p r o v e d

  • 8/13/2019 Analysis of Rate of Building Deportment

    161/242

    Description

    4" size glazed gully trap with chamber 12" x 12" I/c 9" dia C.I Cover & Frame.

    Unit of Rate Per No

    Gully trap 1.00 No 75.00 Each 75.00

    Bricks 20.00 No 2.00 Each 40.00

    Cement 0.25 Bag 310.00 Each 77.50

    Sand 10.00

    C.I Frame with Cover 1.00 No 250.00 Each 250.00

    Labour charges 1.00 No 100.00 Each 100.00

    Total 552.50

    Add 10% Contractor Profit 55.25

    Add 10% Overhead Charges 55.25

    Total 663.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Plumbing Work

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    162/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    163/242

    Description

    P/L 3'' I/d Upvc Pressure Pipe class B (Dadex) in trenchi/c jointing pipe with collers.clamps i/c testing.

    and entire satisfaction of Engineer Incharg.

    Unit of Rate =20 Rft

    3'' i/d uPVC pressur Pipe class B(Dadex).@1182/-per len

    3''i/d ,ELBOW etc 275.00

    3''i/d ,TEE etc

    Solution dadex

    Labour lowering pipe and jointing

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Rft =

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER Project Director

    193.70

    2324.40

    116

    1182.00

    10.00

    20.00

    1937.00

    193.70

    A p p r o v e d

    450.00

    RATE ANALYSIS

    Plumbing Work

  • 8/13/2019 Analysis of Rate of Building Deportment

    164/242

    Description

    P/L 3'' I/d Upvc double union valvei/c jointing pipe with flange i/c testing.

    and entire satisfaction of Engineer Incharg.

    Unit of Rate =I job

    P/L 3'' I/d Upvc double union valve

    3''Upvc Flange 972.00

    Solution dadex

    Labour jointing

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per job =

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER Project Director

    7560.00

    ISLAMIA UNIVERSITY BAHAWALPUR

    Director Engineeing

    10310

    A p p r o v e d

    8592.00

    859.20

    859.20

    10310.40

    10.00

    50.00

    RATE ANALYSIS

    Plumbing Work

  • 8/13/2019 Analysis of Rate of Building Deportment

    165/242

    Description

    Brass Gas Cock

    Unit of Rate Per Foot. 1/2" I/d 3/4" I/d

    Gas Cock 65.00 80.00Labour charges 20.00 28.50

    85.00 108.50

    Add 10% Contractor Profit 8.50 10.85

    Add 10% Overhead Charges 8.50 10.85

    Total 130.20

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    102.00

    Plumbing Work

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    A p p r o v e d

    Director Engineeing

  • 8/13/2019 Analysis of Rate of Building Deportment

    166/242

    Description

    RCC Pipe 1:1.5:3 as per specification BS 5911 class L.

    Unit of Rate Per Foot. 6" I/d 9" I/d

    Market Rate 50.00 56.70

    Cement 15.00 15.00Labour charges 20.00 20.00

    85.00 91.70

    Add 10% Contractor Profit 8.50 9.17

    Add 10% Overhead Charges 8.50 9.17

    Total 110.04

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Plumbing Work

    A p p r o v e d

    Project Director

    102.00

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    167/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    168/242

    Description

    P/F 3" thick RCC main hole cover with tee shaped C.I Frame of 20" Clear (37.32 Kg)

    Unit of Rate = Per No.

    Material

    C.I Frame 1.00 No 400.00 Each 400.00

    MS Angle Iron & Steel Bar 1.00 No 450.00 Each 450.00

    Cement 0.25 Bag 310.00 Per Bag 77.50

    Crush 1.00 Cft 28.00 Per Cft 28.00

    Sand 1.00 Cft 50.00 Per Cft 50.00

    TNP 50.00

    Labour Charages: 150.00

    Total 1205.50

    Add 10% Contractor Profit 120.55

    Add 10% Overhead Charges 120.55

    Total 1446.60

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    PLUMBING WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    169/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    170/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    171/242

    Description:

    PVC Pipe 25 mm dia including all specials (Beta/Galco/shaval

    Unit of Rate = Per Foot.

    PVC Pipe 10 Rft 70.00

    Accessores/Fittings. 10.00

    Labour charges 5.00

    TOTAL 85.00

    Add 10% Contractor Profit 8.50

    Add 10% Overhead Charges 8.50

    TOTAL 102.00

    Rate Per Rft 10.20

    ASSISTANT ENGINEER SUB-ENGINEER

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Project Director

    Electrical WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    172/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    173/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    174/242

    Description:

    PVC Pipe 40 mm dia including all specials (Beta/Galco/shaval

    Unit of Rate = Per Foot.

    PVC Pipe 10 Rft 95.00

    Accessores/Fittings. 12.00

    Labour charges 8.00

    TOTAL 115.00

    Add 10% Contractor Profit 11.50

    Add 10% Overhead Charges 11.50

    TOTAL 138.00

    Rate Per Rft 13.80

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Approved Rate of Rs.13.80 per Rft

    Project Director

    Electrical WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    175/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    176/242

    Approved Rate of Rs.21.00 per Rft

    Description:

    PVC Pipe 3" dia including all specials (Beta/Galco/shaval

    Unit of Rate = Per Foot.

    PVC Pipe 10 Rft 250.00

    Accessores/Fittings. 15.00

    Labour charges 10.00

    Total 275.00

    Add 10% Contractor Profit 27.50

    Add 10% Overhead Charges 27.50

    Total 330.00

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    Electrical WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    177/242

    Rate Per Rft 33.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Approved Rate of Rs.33.00 per Rft

    Description:

    Single Core PVC insulatted Copper conductor 3/0.029" Cable (Pakistan,New age)

    ISLAMIA UNIVERSITY BAHAWALPUR

    Project Director

    RATE ANALYSIS

    Electrical WORKS

  • 8/13/2019 Analysis of Rate of Building Deportment

    178/242

    Unit of Rate = Per Metre

    Cable (one coil 90 meter) 710.00

    Wastage 5% 35.50

    Accessores/Fittings. 20.00

    TNP 30.00

    Labour charges 100.00

    TOTAL 895.50

    Add 10% Contractor Profit 89.55

    Add 10% Overhead Charges 89.55

    TOTAL 1074.60

    Rate Per Mater 11.94

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Approved Rate of Rs.11.94 per Rft

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    179/242

    Description:

    Single Core PVC insulatted Copper conductor 3/0.029" Cable (Pakistan,New age)

    Unit of Rate = Per Metre

    Cable (one coil 90 meter) 710.00

    Wastage 5% 35.50

    Accessores/Fittings. 20.00

    TNP 30.00

    Labour charges 100.00

    TOTAL 895.50

    Add 10% Contractor Profit 89.55

    Add 10% Overhead Charges 89.55

    TOTAL 1074.60

    Rate Per Mater 11.94

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Approved Rate of Rs.11.94 per Rft

    Electrical WORKS

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    180/242

    Description:Single Core PVC insulatted Copper conductor 7/0.029" Cable (Pakistan,New age)

    Unit of Rate = Per Metre

    Cable (one coil 90 meter) 1250.00

    Wastage 5% 62.50

    Accessores/Fittings. 20.00

    TNP 25.00

    Labour charges 125.00

    TOTAL 1482.50

    Add 10% Contractor Profit 148.25Add 10% Overhead Charges 148.25

    TOTAL 1779.00

    Rate Per Mater 19.77

    Electrical WORKS

    RATE ANALYSIS

    ISLAMIA UNIVERSITY BAHAWALPUR

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    181/242

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Approved Rate of Rs.19.77 per Rft

    Description:

    Single Core PVC insulatted Copper conductor 7/0.044" Cable (Pakistan,New age)

    Unit of Rate = Per Metre

    Cable (one coil 90 meter) 2175.00

    Wastage 5% 108.75

    Accessores/Fittings. 40.00

    TNP 50.00

    Labour charges 150.00

    RATE ANALYSIS

    Electrical WORKS

    ISLAMIA UNIVERSITY BAHAWALPUR

    Project Director

  • 8/13/2019 Analysis of Rate of Building Deportment

    182/242

    TOTAL 2523.75

    Add 10% Contractor Profit 252.38

    Add 10% Overhead Charges 252.38

    TOTAL 3028.50

    Rate Per Mater 33.65

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Approved Rate of Rs.33.65 per Rft

    Project Director

    RATE ANALYSIS

    Electrical WORKS

    ISLAMIA UNIVERSITY BAHAWALPUR

  • 8/13/2019 Analysis of Rate of Building Deportment

    183/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    184/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    185/242

    Description:

    3 Pin switch socket & Plug combined (PPI/BBI)

    Unit of Rate Per No 5 Amp 10/15 Amp

    Plug combined switch 55.00 125.00

    Labour charges 10.00 20.00

    65.00 145.00

    Add 10% Contractor Profit 6.50 14.50

    Add 10% Overhead Charges 6.50 14.50

    Total 78.00 174.00

    ASSISTANT ENGINEER SUB-ENGINEER

    EXECUTIVE ENGINEER

    Electrical WORKS

    A p p r o v e d

    Project Director

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    186/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    187/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    188/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    189/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    190/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    191/242

  • 8/13/2019 Analysis of Rate of Building Deportment

    192/242

    Description

    Coper Conducter Cables for service connection PVC Sheeted armoured 4 core70mm

    Unit of Rate Per Rft.

    1.00 Ft. 270.00 Per Rft.

    Labour charges 1.00 Ft. 25.00 Per Rft.

    Total

    Add 10% Contractor Profit

    Add 10% Overhead Charges

    Total

    Rate Per Rft. 350/-

    ASSISTANT ENGINEER SUB-ENGIN

    EXECUTIVE ENGINEER

    ISLAMIA UNIVERSITY BAHAWALPUR

    RATE ANALYSIS

    ISLAMIA UNIVERSITY BAHAWALPUR

    Electric Work

    A p p r o v e d

    Project Director

    Cable (Pakistan-New age) 70mm

    RATE ANALYSIS

  • 8/13/2019 Analysis of Rate of Building Deportment

    193/242

    Description Shifting of Transformer of education faculty with in distance of 300' i/c disconecting,demolishing

    H.T steel wire and other electrical asessories like jumpers fuses insulators ic lowering of transformer

    with chain cupy in the supervision of experts and skilled labour i/c errection

    and placing transformer at new site with providing same actvity as mension above

    i/c errection of new steel cables jumpers fuses stays etc complete in all respect.i/c

    Providing & Fixing H.T Galvanized Steel structure single pole as per WAPDA specifications. a) H.T.Pole 35' Height with Concrete Foundation (1:2:4), 2' x 2' x 6' size using Angle Iron 2" x 2" x 5/32" siz

    for Legs and Angle Iron 1.375" x 1.375" x 1/8" size for Bracing