analysis of the material handling requirements for flexible manufacturing system case study: line...
TRANSCRIPT
Analysis of the Material Handling Requirements for Flexible
Manufacturing SystemCase Study: Line 155
Jessica Daly and Steven Tompkins
LEGO Systems, Inc.
Faculty Advisor: Dr. William Brown
Corporate Advisor: Aimee Crisanti, Senior Production Engineer
Project Overview
Problem Definition LEGO has not been able to create a method
for calculating the number of material handlers that are required to support their production schedule.
Project Objective To deliver a model for determining the
number of material handlers needed for the production of any given product on Assembly Line 155.
Solution Methodology
Determine Material Handler Functions Define the characteristics of the Line
that need to be quantified Determine variables for model Design logic equations that accurately
represent the system Calculate the baseline of the system Design a final model
Material Handler FunctionsDedicated Material
Handling Functions involve the loading of the following:
Box Erector Literature Special Counters Parts Feeders Bag Feeders Conveyors Decal Dispensers
Other Functions Product packaging
removal and clean-up Machine maintenance
Equation Variables Line Rate Type of Equipment Time for Loading Equipment P-Box Quantity Based on Weight of
Part Quantity of Parts Per Piece of
Equipment Number of Actual Material Handlers
Used
Sample Equation
Dedicated Material Handling Time Equation
(Rate of Line/Reload Amount)*(Time to Reload)*(Quantity needed in Final Assembly)
(Rate/P-Box Qty)*(.33mins)(1)=DMHT (Mins/Hr)
Baseline of System
Average Percent Dedicated Material Handling Time = Approx. 70%
Actual vs. Calculated - using 70%
0
0.5
1
1.5
2
2.5
3
3.5
1 3 5 7 9 11 13 15 17 19 21
Part
Mate
rial
Han
dle
rs
Actual
Calculated
System Modification
Literature Inserters no longer part of Assembly Line
Operators will be used in place of machines
Some loading times changed slightly
Baseline Modification Decrease in Dedicated Material Handling
Time New Total Material Handling Time
Calculated By: Other Time from Original System + New System
Dedicated Material Handling Time
New Percent DMHT: New System DMHT/ New Total Material Handling
Time = 55%
Final Model Characteristics
Microsoft Excel Model User-Friendly Adaptable to Other Assembly Lines Reprogrammable
Final Model - User Inputs
Rate of Line (pieces per hour) Quantity of Parts Weight of Specific Parts Type of Equipment Percent Dedicated Material Handling
Time
Final Model - Outputs
Total Dedicated Material Handling Time
Number of Material Handlers Needed for a Production Hour
Pie Charts Total Material Handling Time Distribution Dedicated Material Handling Time
Distribution
Distribution of Dedicated Material Handling Time
Distribution of Dedicated Material Handling Time
31%
4%
0%51%
3%
11%
Literature
SpecialCountersParts Feeders
Bag Feeders
Conveyors
Miscellaneous
Simulation of Line
Components Pieces of
Equipment Material Handlers Operators Conveyors Products
Benefits Visual Aid
What-If Analysis Line Modification
Adaptability for Other Lines
ABET Topics of Concern
Economic Concerns and Implications Political Concerns and Implications Environment Concerns and
Implications Sustainability Social Concerns and Implications
Conclusion Objective of Project was
Accomplished Accurate Model created including
Training Manual LEGO has approved Model and is
planning implementation Schedule of Project Maintained Training at LEGO is Scheduled Additional Simulation Created
Totals Sheet of Excel ModelMaterial Handling Model
Totals
Literature 15.67 (mins/line hour)
Special Counters 0.00 (mins/line hour)
Parts Feeders 0.00 (mins/line hour)
Bag Feeders 20.48 (mins/line hour)
Conveyors 15.89 (mins/line hour)
Miscellaneous 2.66 (mins/line hour)
Total Time 54.709 (mins/line hour)
Input % Dedicated Material Handling Time 55% (use % symbol)
(Time Material Handlers are actually handling material - normal range (50-60%)
Other Time 45%
Number of Material Handlers needed for production 1.66
Other Time (Clean Up/ Machine Jams) 44.762
Sheet 1 of Excel Model
Material Handling Model PART #3432
Input Column Time (mins)
Rate (Pcs/hour) 1680
Box Erector 8.4
Number of Instructions 1 3.92
Number of Brochures 1 1.92
Number of Posters 0 0.98
Number of Postcards 1 0.46
Total 15.67
Number of Decals 1 1.68
Other
Number of Tables 1 0.98
Number of Boxes 0 0.00
Misc. Parts (No Equipment) 0 0.00
Total 2.65944
Parts Feeders Sheet of Excel Model
Material Handling Model
Input Column Time(mins)
Rate 1680
Parts Feeders
Weight of 1st Element 0 0.000
Quantity 1
Weight of 2nd Element 0 0.000
Quantity 1
Weight of 3rd Element 0 0.000
Quantity 1
Weight of 4th Element 0 0.000
Quantity 1
Weight of 5th Element 0 0.000
Quantity 1
Weight of 6th Element 0 0.000
Quantity 1
Weight of 7th Element 0 0.000
Quantity 1