OWTS and soils and geologyreports must be separatereports, per LDC Secs. 8.4.8and 8.4.9. Ensure that thesereports meet the currentcriteria within these sectionsand revise accordingly.
At least two (2) test pitlocations are required for the40-acre site.
Regarding the Soils & Geologycomponent per LDC Sec.8.4.9(A)(2): The PCD Directormay approve a report that wascompleted and reviewed at anearlier stage in the subdivisionreview process. If you arerequesting to use an olderreport, please indicate so inyour letter of intent and explainhow the recommendations ofthe report and the review ofthe CGS have been followed inthe preparation of thepreliminary plan. This reportmust be prepared by aregistered geologist.