Significance of Project Accounting
• Project accounting is the practice of creating financial reports
specifically designed to track the financial progress of projects,
which can then be used by managers to aid project management
• The relevance and significance of Project Accounting can be
attributed to three key factors, namely:-
• Long-term implications and consequences
• Substantial commitment of funds.
• Decisions once taken are irreversible
Project Cycle (Initiation, Sanction & Execution)
• Based on the technical requirements and load flow studies, the investment
plan is prepared
• Upon identification of projects are segregated as “To be funded” and “To be
executed out of internal resources”
• For the “To be funded” projects, the work of tying up of funds is initiated
• Based on the indication of sanction of loan provided by the lending
agencies, project report for each of the identified schemes is prepared in the
Corporate office and administrative approval is communicated
• For the schemes that to be funded internally, estimates
are prepared, sanctioned and works executed with in the
approved Budget Provision
• Project execution is taken up immediately after
administrative approval is obtained, the funding for the
project is tied-up simultaneously.
• Technical Sanction for the works to be taken up based
on the estimates submitted
Project Cycle….
• The Technical Sanction contains detailed estimate
covering:
• Head of sanction
• Cost of the materials,
• Cost of labour,
• Other expenses viz. transportation, establishment & general expenses
• Tree cut / crop compensation
• Taxes and levies,
• Land acquisition
• Contingencies etc.
• The material rates adopted in the estimate are the latest
procurement rates and the labour rates are based on the
latest Standard Schedule of Rates of the company
Project Cycle….
•In APCPDCL the capital expenditure incurred at field used to be recorded in a construction and operation ledger [CAOL] maintained for the purpose.
• The CAOL is maintained work order wise, wherein the expenditure incurred towards material and labour was recorded.
•Based on the monthly information received from the field in form of plan progress report, the capital expenditure was monitored.
•The capitlaisation of the expenditure incurred was done at corporate level based on the returns submitted by field officers along with the physical and financial completion reports.
•For better monitoring of the project expenditure APCPDCL has implemented project systems module in sap ECC 6.0 version.
Accounting for Projects
Project System: To control all tasks in project execution, you need an
organizational form that is specific to the project and which is shared by all departments involved. The main view of project structure based on the following.
By structures, using a work breakdown structure (WBS) By process, using individual activities (work packages)
Work Breakdown Structure: It is a model of the work to be performed in a project
organized in a hierarchical structure. The WBS is an important tool which helps to keep an overview of the project. The Project Structure can be represented according to the following criteria:
By phase (logic oriented) By function (function oriented) By object (object oriented)
Objectives of Project system
Network: A network can represent the sequence of activities in a
project. The essential components of a network are: Activities Relationships between the activities
Activities: Activities are the key tasks to be completed. These
activities map to internal activities, external activities, cost activities and materials components.
Work Packages: A work package is a quantitative and qualitative
description of an activity to be carried out in the project. The work packages can be on any level in the work breakdown structure
Objectives of Project system…
© SAP 2009 / Page 9
Process Flow for Bulk Projects (HVDS) in Project System
Ananthapur Circle
Construction Sub-Div.-1 (Agmt-1) Construction Sub-Div.-2 (Agmt-2) Construction Sub-Div.-3 (Agmt-3)
1st Mother DTR
Ananthapur Construction Div
1st Mother DTR
Survey & Preparation of Sketches……..
Supply & Erection of Pin Insulators
Supply & Erection of Intermediate Poles…...
Supply & Erection of 16/25KVA DTRs
Removal of Mother DTRs and Handing over
to Stores…...
2nd Mother DTR
2nd Mother DTR
Survey & Preparation of Sketches……..
Supply & Erection of Pin Insulators
Supply & Erection of Intermediate Poles…...
Supply & Erection of 16/25KVA DTRs
Removal of Mother DTRs and Handing over
to Stores…...
nth Mother DTR
nth Mother DTR
Survey & Preparation of Sketches……..
Supply & Erection of Pin Insulators
Supply & Erection of Intermediate Poles…...
Supply & Erection of 16/25KVA DTRs
Removal of Mother DTRs and Handing over
to Stores…...
WBS Element
Network Element
Activity
HVDS Project
Grouping of various Projects - Example
Bulk Projects: HVDS APDRP and APDRP – R P:SI Schemes JBIC P:IE (RGGVY, INDIRAMMA) SPA:PE All bulk schemes that would come up in near future.
T & D Improvements: All improvements works.
Contribution Works: Release of service with minor and major extensions. Deposit Contribution Works Contribution Works
Process Flow in Project System
Estimate preparation in SAP
Approval process
Allocation of Budget
Tendering Process
IM
PO, Material Receipt etcMM
Work Execution
Monitoring
Closure
Templates for Preparation of Estimates is available in SAP
© SAP 2008 / Page 15
Budget Distribution to Projects (Defined
at Division Level)
Once budget is set,
estimates/ actual cannot
exceed this value.
Supplementary
amendments to be
based on prior approvals
© SAP 2008 / Page 17
Master - Work Package creation
Project Status – Create,
Released, Budget
Availability, Goods
consumption, Technical
completion and closure
Status set to Tehco – work
package is closed for operation
Capitalisation of Project
• Steps in Settlement Process of WBS elements other than DCW/TCW orders are :-
Settlement of costs from Network order to
WBS element
Overhead Capitalisation on WBS element
Execution of IDC on WBS Element
Settlement of WBS element costs to AUC
Final Settlement from AUC to Fixed Assets
Monthly
process
After project
completion
Material control (under implementation)
• Materials assigned code on entering stores
• On issue to project, the functional code will be changed from “Stores” to “Location installed”
• Asset will be tracked from this location code
• Technical completion will be generated by the system