angat water transmission improvement project
TRANSCRIPT
Environmental Monitoring Report
Semestral Report January 2018
Philippines: Angat Water Transmission Improvement
Project
Prepared by the Metropolitan Waterworks and Sewerage System for the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein
do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may
be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation
of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of any
territory or area
AWTIP Tunnel 4 Semi Annual Environmental Monitoring Report 2
2017 July - December
Contents
Executive Summary 1
General 1
Assessment of compliance 1
1 Introduction 2
1.1 Background 2
1.2 Project Implementation Progress 4
2 Compliance with ADB loan covenants and applicable
government laws, regulations and requirements 18
2.1 Status of compliance with government environmental requirements: 18
3 Changes in project scope 24
4 Summary of Environmental Mitigations and
Compensation Measures Implemented 25
4.1 Emission/Wastewater Discharge (Source) Monitoring Program (if
relevant or required in the EMP) 31
4.2 Water Quality Monitoring Program 31
4.3 Air and Noise Quality Monitoring Program 58
5 Key Environmental Issues 61
5.1 Key activities implemented 61
5.2 Key Issues Identified 61
6 Complaints 63
6.1 Details of Complaint/s 63
7 Conclusion and Recommendation 64
7.1 Overall Progress of Implementation of Environmental Management
Measures 64
8 Appendices 1
8.1 AWTIP Monitoring Matrix 1
8.2 Tree Cutting Permits 2
AWTIP Tunnel 4 Semi Annual Environmental Monitoring Report 2
2017 July - December
8.3 Permits and Licenses 3
8.4 Water Quality Laboratory Results 4
8.5 Grievance Case - Invalid 5
List of Tables
Table 1. Contract Price for design and construction service ....................................................... 3
Table 2. Key information about the project .............................................................................. 3
Table 3. Key project progress .................................................................................................... 4
Table 4. Overall Progress of the project as of June 2016 ........................................................... 5
Table 5. Total Length to be concreted from STA 0+000 to STA 0+863.95 = 863.95 m ..... 6
Table 6. Workforce as of December 31, 2017 ........................................................................ 13
Table 7. Filipino Workforce as of December 31, 2017 – by geographic location ...................... 14
Table 8. Workforce as of December 31, 2017 – by Gender .................................................... 14
Table 9.. Workforce as of December 31, 2017 – Dumagats ................................................... 14
Table 10. Workforce as of December 31, 2017 – by Age Groups .......................................... 15
Table 11. Staff requirement in the next 3 months ................................................................... 15
Table 12. Contractor: CMC di Ravenna ................................................................................ 16
Table 13. Sub-contractor: First Balfour .................................................................................. 16
Table 14. Sub-contractor: Don Vic Construction .................................................................... 16
Table 15. Sub-contractor: White Moon Inc. ............................................................................ 17
Table 16. Permits ................................................................................................................. 18
Table 17. Other Permits....................................................................................................... 19
Table 18. Safety Report as of December 2017 ...................................................................... 19
AWTIP Tunnel 4 Semi Annual Monitoring Report 1
2017 January - June
Table 19. Summary of Environmental Mitigations and Compensation Measures Implemented
............................................................................................................................................... 29
Table 20. Water Quality Results for SWB1 .......................................................................... 35
Table 21. Water Quality Results for SWB2 .......................................................................... 37
Table 22. Water Quality Results for SWB3 .......................................................................... 39
Table 23. Water Quality Results for SWSM1 ....................................................................... 41
Table 24. Water Quality Results for SW IPO1 ..................................................................... 43
Table 25. Water Quality Results for SW IPO2 ..................................................................... 45
Table 26. Water Quality Results for SW IPO3 ..................................................................... 48
Table 27. Water Quality Results for SW IPO4 ..................................................................... 52
Table 28. Water Quality Results for Basin 1 ......................................................................... 55
Table 29. Turbidity monitoring results from October to December 2017 .................................. 57
Table 30. Noise level monitoring results (October-December 2017) ......................................... 59
Table 31. WHO guidelines for noise quality ........................................................................... 60
Table 32. List of grievances as of December 2017 ................................................................ 63
List of Figures
Figure 1. Project Site .............................................................................................................. 3
Figure 2. Conveyance channel area ............................................................................................ 7
Figure 3. Substation of outlet portal area .................................................................................. 7
Figure 4. Lifting of Back-up Cars for TBM Assembly ............................................................. 8
Figure 5. Probe Drilling Investigation at Launching Chamber .................................................. 8
Figure 6. Probe Drilling at Launching Chamber....................................................................... 9
Figure 7. Construction of Water Treatment Tank ..................................................................... 9
Figure 8. Construction of Tippler ............................................................................................ 10
Figure 9. Railway at Industrial Area (Sta. 0-140 onwards) ................................................... 10
Figure 10. Delivered Precast Segments .................................................................................... 11
Figure 11. Delivered Precast Segments .................................................................................... 11
Figure 12. CMC staff during earthquake drill ........................................................................ 22
Figure 13. Actual photo from the Earthquake Drill ............................................................... 22
Figure 14. Site Assembly Point Area (Holding Area/Muster Point) ..................................... 23
Figure 15. The sampling locations (Bigte and Ipo Rivers) ........................................................ 32
Figure 16. Sampling points in Bigte River ............................................................................... 33
Figure 17. Sampling points in Ipo River ................................................................................. 34
Acronyms1
AWTIP Angat Water Transmission Improvement Project
ADB Asian Development Bank
CCO Chemical Control Orders
CEMMP Contractor’s Environmental Management And Monitoring Plan
CENRO City Environment and Natural Resources Office
CMC Cooperativa Muratori Cementisti di Ravenna
DENR Department of Environment and Natural Resources
ECC Environmental Compliance Certificate
EIA Environmental Impact Assessment
EMP Environmental Management Plan
IEC Information, Education and Communication
IEE Initial Environmental Examination
IP Indigenous People
km Kilometer
L Length
MENRO Municipal Environment and Natural Resources Office
MMT Multi-partite monitoring team
MWSS Metropolitan Waterworks and Sewerage System
NA Not applicable
NCIP National Commission on Indigenous Peoples
NPC National Power Corporation
ORP Oxidation Reduction Potential
PD Presidential Decree
PO Permit to Operate
RCBC Reinforced Concrete Box Culvert
RCPC Reinforced Concrete Pipe Culvert.
ROW Right of way
SEMP Self-Environmental Management Plan
TBM Tunnel Boring Machine
1 This is a standard acronym list for all monitoring reports. The acronym may not appear in all
reports
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
1
Executive Summary
General
The Contractor, CMC di Ravenna, monitors its performance against the CEMMP obligations.
Because of this, it will record non-compliance where performance does not meet the original
obligations. In many cases this should not be taken to mean that the outcomes are bad and
where alternative courses of action have been adopted CMC and MWSS has recorded this.
This report highlights prevailing issues about the project. Only obligations which are assessed
as in progress, non-compliant (in specification and time schedule), and not applicable are
presented in the body of the report. A full review of the CEMMP obligations is presented in
the CA matrix in excel format.
The layout of this report followed recommended ADB monitoring report structure.
Assessment of compliance The following are the definition of remarks used to assess the CEMMP, EMP of IEE and EIA and other environment related project documents.
(a) COMPLIANT – completed according to schedule and specifications in the
CEMMP and other relevant ADB policies;
(b) NON-COMPLIANT – not completed according to schedule and specification
and/or not according to specification;
(c) NC time – completed beyond the date of completion stated in the CEMMP
(d) IN PROGRESS – partly compliant and pending for completion
(e) NOT APPLICABLE – obligations not applicable to AWTIP project
(f) CANNOT DOCUMENT COMPLIANCE – insufficient document or no
document provided to support assessment of compliance
A full review of the CEMMP and other relevant project documents on environment is
presented in Appendix Section 8.1.
Two grievance cases reported in the period July to December 2017.
Water quality monitoring started on August 2017. Portable turbidimeter and multimeter were
procured for in-situ measurements and monitoring of water. Monitoring using the
instruments started on October 2017.
A sound level meter was also procured to monitor sound levels onsite. Monitoring started on
October 2017.
Other monitoring and survey services/ consultancy procurement are in progress.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
2
1 Introduction
1.1 Background
The Angat Water Transmission Improvement Project (AWTIP) is part of a bigger scheme of
modernization and improvement of the Metro Manila Water Distribution Network. The
water of the Angat basin, which is fed through the Umiray tunnel, provides around 35% of
the water for domestic use to the city of Manila. Currently the transportation of water from
Ipo dam basin to the Bigte sedimentation plant happens through 4 tunnels, 2 of which are
very obsolete. The progressive deterioration of the existing tunnels (2 of which were built
more than 75 years ago), or the occurrence of an earthquake (which is very likely since the
area is close to two active faults), may seriously compromise the provision of water to millions
of people.
The project is located in the province of Bulacan, at around 50 km north of Manila, close to
Norzagaray City, of 150,000 inhabitants which hosts several important cement industries and
which is easily accessible via highway or normal roads.
More than 95% of the water supply for Metro Manila comes from a single source: The
Umiray–Angat– Ipo, or Angat system. Water from the Angat reservoir is conveyed through
three parallel tunnels followed by six parallel aqueducts, to water treatment plants in Metro
Manila. The treated water is then distributed to households, businesses, and industries in
Metro Manila, and parts of Cavite and Rizal provinces. The transmission’s tunnel system
which is about 75 years old, has not been assessed ever since. The earlier tunnels, tunnels 1
and 2 are not in compliance with current structural and seismic requirements. These factors
could lead to serious interruptions of Metro Manila’s water supply. The proposed project will
construct the urgently required fourth parallel tunnel. This new tunnel will not increase system
capacity, but it will enable the rehabilitation or decommissioning of the upstream tunnels and
downstream aqueducts.
The proposed project aims to (i) help restore the full design capacity of the Angat systems
and thus ensure the sustainable provision of the water supply distribution system, and (ii)
mitigate the risk of a total loss of water supply to Metro Manila and portions of Cavite and
Rizal provinces. Both objectives are essential for the stable economic growth of Metro Manila
and the Philippines. The government has asked the Asian Development Bank (ADB) to
finance this investment. The figure below shows the general location of the project.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
3
Figure 1. Project Site
The Angat Water Transmission Project (AWTIP) is a design and build project consists of
Design and Construction activities:
Table 1. Contract Price for design and construction service
ITEM GRAND SUMMARY CONTRACT PRICE
1 Designs Services 93,516,701.06
2 Construction Devices 3,198,038,168.46
Grand Total for Design Services and Construction Service
(1) + (2)
Php
3,291,554,869.52
1.1.1 Project Data
Table 2. Key information about the project
Project Name Angat Water Transmission Improvement Project
(AWTIP)
Components 6.4 km Tunnel Construction, Intake/Outlet
Structure, and Interconnection to Basin of
Aqueduct No. 5
Location Norzagaray, Ipo Dam to Bigte Basin
Duration 52 months (4 years and 4 months) Design Period
= 6 months Construction Period = 46 months
Source of Fund Asian Development Bank (Loan 3377 PHI-AWTIP)
Contractor Cooperativa Muratori Cementisti di Ravenna (Italy)
Contractor’s Project Manager Mr. Salvatore La Valle
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
4
Project Manager/ CO for MWSS Jose D. Dorado Jr.
Consultant’s Project Manager MWSS’s Consultant is not yet in place. MWSS,
the principal will do direct supervision
Notice to Proceed (NTP) May 31, 2016
Actual Date of Start June 01, 2016
Target Completion September 07, 2020
1.2 Project Implementation Progress
1.2.1 Overall Progress as of 31 December 2017
Table 3. Key project progress
PERIOD ENDING 31 December 2017
Project Phase Construction Phase
Target Accomplishment to Date (31
December 2017)
26.541%
Actual Accomplishment to Date 23.02%
Scheduled Accomplishment for the Month 2.855%
Actual Accomplishment for the Month 0.61%
% Variance to Date 3.523 % (-)
% Variance last Month
(Ahead/Slippage)+/-
1.275 % (-)
Contract Time Elapsed 579 c.d. or 37.12%
Delayed Activities:
1. No. 136: Slope Stabilization (Inlet) – The delay in the Slope Stabilization along inlet area
is primarily due to CMC’s claim to Redesign the Intake Structure and Slope Stabilization at Ipo dam area. Technically, the Variation on Design was approved last May 2017. MWSS Board of Directors declined the Variation on Cost. Thus, since CPF have an on-going project negotiation regarding Slope Stabilization within the area, the additional scope of work being claimed by CMC to AWTIP scope of work will be covered to Ipo Dam Slope Stabilization Project (IDSSP) being implemented by CPF.
2. Permanent Access Road – the works at the remaining areas of the Access road at IPO dam area, was on hold since 07 August 2017. The stoppage of work was CMC’s prerogative while waiting for the approval of Variation Order No.1
a. No. 123: Clearing and Grubbing b. No. 124: Subgrade Preparation c. No. 125: Road Excavation
3. Tunnel Excavation by TBM – The delay is caused mainly by the unforeseeable site
condition such as the ever- changing site condition and unforeseeable geologic feature such as transported materials, Karst-cavities and artesian aquifers discovered during the rock excavation. Due to the updated geological findings, the design of the outlet portal was revised with the introduction of the micropiles retaining wall, and extension of shotcrete area on both sides of the outlet portal. The position of the portal has been moved 10 m ahead from the original design because of this transported slope wash material and rock soil debris. Moreover, grout injection works was necessary to stabilize
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
5
the areas around the tunnel portal to avoid possible collapse or cave-ins during excavation. The rock excavation of the launching chamber prevented the TBM to be completely assembled and mobilized to the portal area. These works caused delay on the activities below:
a. No. 187 – Preparatory Works b. No. 188 – TBM Mobilization c. No. 190 – TBM Assembly
4. No. 196 – Production of Precast Segments – The delay in the precast production was due to the quality of cement used for the mix that cause slow curing time for demoulding. CMC utilized another cement supplier who is able to provide high early strength concrete, thereby producing increase in production of segments due to faster demoulding time. CMC also hired a specialist in precast rings/segment production, Mauro Spelozzi, to undertake the precasting process. His technical know-how, skills and experience will be optimized to mitigate the problem of low production rate.
1.2.2 Physical Progress
Table 4. Overall Progress of the project as of June 2016
Contract Amount Relative Weight
(%)
Accomplishment (Php Millions)
Weighted (%) % Target
Previous
This Period
To date Previous This Period
To date
1. Designs Services
P93,516,701.06 2.84% 93.517 93.517 2.84% 2.84% 2.84%
2. Construction Services
P 3,198,038,168.46 97.16% 644.141 19.996 664.137 19.57% 0.61% 20.18% 23.70%
TOTAL
P 3,291,554,869.52 100% 737.658 19.996 757.654 22.41% 0.61% 23.02% 26.54%
Note: This report shows the physical accomplishments of the Contractor’s work for items 1 and 2
Progress Status (Ahead/Slippage; +/-)
23.02 % (+)
1.2.3 On-going Site Works (as of December 2017)
(a) Facilities for the client’s office – All site facilities were completed on July 2017.
(b) Permanent Access Road (5m – width and 865m – length) All works on access road are still on hold as per Letter to MWSS Ref. No.
AWTIP_2017_OUT_0216-07/08/2017, dated 7 August 2017, except those related to security and safety due to the absence of formal response from MWSS on the formal issuance of its instruction for the redesign and relocation of Intake Structure and for CPF to award the Slope Stabilisation Design and Works.
(i) Earthworks – on hold
(ii) Basecourse Preparation – on hold
(iii) Concreting of Pavement – on hold
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
6
Table 5. Total Length to be concreted from STA 0+000 to STA 0+863.95 = 863.95 m
(iv) Slope protection – on hold
(c) Outlet
(i) Conveyance channel – Activities in progress
(ii) Rock breaking for conveyance channel
(d) TBM preparatory works (Tunnels and Portals)
(i) Railway from Sta 0-000 to Sta 0-285 - Activity in Progress
(ii) Concrete Cradle for TBM Sliding – Not yet started
(iii) Excavation and Fortifications for Launching Chamber - Completed on 12-
Dec-17
(iv) Installation of 34.5 KV Poles, Main Switch and Cables - Activity in
Progress
(v) Preparation for Rotodump assembly - Activity in Progress
(vi) Ventilation system - Activity in Progress
(vii) Water Treatment Tank - Activity in Progress
(viii) Construction of Tippler - Activity in Progress
(e) Production of Precast Segment
(i) Production of Precast Segments (3,889 out of 19,940) - Activity in Progress
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
7
1.2.4 Progress Photos (as of December 2017)
(a) Outlet Portal Area
Figure 2. Conveyance channel area
(b) TBM Excavation Works (Preparatory Works)
Figure 3. Substation of outlet portal area
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
8
Figure 4. Lifting of Back-up Cars for TBM Assembly
Figure 5. Probe Drilling Investigation at Launching Chamber
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
9
Figure 6. Probe Drilling at Launching Chamber
Figure 7. Construction of Water Treatment Tank
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
10
Figure 8. Construction of Tippler
Figure 9. Railway at Industrial Area (Sta. 0-140 onwards)
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
11
(c) Production of Precast Segments
Figure 10. Delivered Precast Segments
Figure 11. Delivered Precast Segments
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
12
1.2.5 Previous Site Works (July to November 2017)
Activities 2017
July Aug. Sept. Oct. Nov.
i. Facilities for the Client’s Office
· Living quarters ●
· All site facilities ●
ii. Outlet Portal Area General Site Facilities
· Industrial Area/Precast Segments Storage Platform
Formation ●
· Workshop and Warehouse ●
· Fuel station and tank ●
iii. Permanent Access Road (Inlet)
· Earthworks → Ø Ø Ø Ø
· Basecourse Preparation → Ø Ø Ø Ø
· Concreting of pavement → Ø Ø Ø Ø
- On-hold (Total length to be concreted from STA
0+000 to STA 863.95 = 863.95 m)
· Slope protection → Ø Ø Ø Ø
· Slope protection works from Sta 0+600 to Sta 0+620 ●
· Concreting of Access Road Pavement from Sta 0+462
to Sta 0+474 ●
· Concreting of Access Road Pavement from Sta 0+336
to Sta 0+364 ●
iv. Slope upon the Portal (Outlet)
· Installation of Geocomposite Steel Mesh with Anchor
Bolts → → → ? ?
· Installation of 28mmØ threaded rock bolts, 5 meters → → → ? ?
· Rock breaking for conveyance channel → → → → ?
· Micro piling works → → → ●
· Anchoring and Fore poling works at the Portal → ●
· Shotcrete works at Level 101 to 92 ●
v. Outlet Structure
· Excavation for Outlet Structure ●
vi. Conveyance Channel
· Earthworks (Area for Segments 2. 3 & 4) →
· Earthworks (Area for Segments 5 & 6) →
vii. Railway for TBM preparatory Works (Tunnels and
Portals)
· Large RCBC, (Sta 0+010, 4.00x1.80, L=9.50m) → → ? →
· Large RCBC (Sta 0+010, 2x 4.00x1.80 L=6.00m) → → → ●
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
13
Activities 2017
July Aug. Sept. Oct. Nov.
· Bridge overpass Aqueduct 1 (Span 3.65m, Length
33.35m) → → ? →
· Delivery of TBM “Veronica” at Site → ●
· Large RCBC (Sta 0+259.47) → ●
· Railway from Sta 0+240 to Sta 0 + 260 → ?
· Railway from Sta 0+260 to Sta 0+_?__ → ?
· Railway from Sta 0+000 to Sta 0+285 →
· Concrete Cradle for TBM Assembly ●
· Concrete Cradle for TBM Sliding -
· Excavation and Fortifications for Launching Chamber →
- (CMC conduct operations at night time for the
excavation of Launching Chamber for 3 consecutive
weeks from Nov. 20 to Dec. 9, 2017)
· Installation of 34.5 KV Poles, Main Switch and Cables →
· Preparation for Rotodump assembly →
· Ventilation system →
· Water Treatment Tank →
viii. Production of Pre-Cast Segment →
- Activity in Progress (2,725
out of
19,940)
ix. Inland Drilling by TREVI FOUNDATIONS at IPO (For
Seismic Test)
· Drilling of Core Holes ●
· Installation of PVC Pipes at Core Holes ●
· Grouting of Core Holes ●
Notes:
● - Completed
→ - Activity in progress
Ø - On-hold
- - Not yet started
1.2.6 Contractors Resources
(a) List of Production Construction Staff
Table 6. Workforce as of December 31, 2017
Entity Filipino Foreigner
TOTAL # % # %
CMC permanent staff
42 41 15 15 57
CMC contract workers / utilities
42 41 0 0 42
CMC consultants 1 1 2 3
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
14
First Balfour 77 100 0 0 77
White Moon Inc. 14 100 0 0 14
Don Vic Construction
41 100 0 0 41
TOTAL 217 93 17 7 234
Table 7. Filipino Workforce as of December 31, 2017 – by geographic location
Entity
Personnel employed from Brgy San Mateo
Personnel employed from Bgry Bigte
Personnel employed from other Bgrys in Norzagaray
Personnel employed from other municipalities/ cities in Bulacan
Personnel employed from other provinces TOTAL
# % # % # % # % # %
CMC permanent staff
4 4 7 7 3 3 15 15 28 27 57
CMC contract workers / utilities
1 1 3 3 6 6 15 15 17 17 42
CMC consultants 0 0 0 0 0 0 0 0 3 3 3
First Balfour 5 6 11 14 1 1 7 9 53 69 77
Don Vic Construction
15 37 25 61 0 0 0 0 1 2 41
White Moon Inc 0 0 8 57 0 0 0 0 6 43 14
TOTAL 25 11 54 23 10 4 37 16 108 46 234
Table 8. Workforce as of December 31, 2017 – by Gender
Entity Male Female
TOTAL # % # %
CMC permanent staff 41 40 16 16 57
CMC contract workers / utilities
37 36 5 5 42
CMC consultants 2 2 1 1 3
First Balfour 69 90 8 10 77
Don Vic Construction 37 90 4 10 41
White Moon Inc. 14 100 0 0 14
TOTAL 200 85 34 15 234
Table 9.. Workforce as of December 31, 2017 – Dumagats
Entity Male Female
TOTAL # % # %
CMC permanent staff 0 0 0 0 0
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
15
CMC contract workers / utilities
0 0 0 0 0
CMC consultants 0 0 0 0 0
First Balfour 2 100 0 0 2
Don Vic Construction 15 88 2 12 17
White Moon Inc. 0 0 3 0 21
TOTAL 17 89 2 11 19
Table 10. Workforce as of December 31, 2017 – by Age Groups
Entity 18-25 26-35 36-45 46-60 Over 60
TOTAL # % # % # % # % # %
CMC permanent staff
5 5 11 11 21 21 20 20 0 0 57
CMC contract workers / utilities
4 4 14 14 10 10 10 10 4 4 42
CMC consultants 0 0 0 0 1 1 2 2 0 0 3
First Balfour 16 21 31 40 16 21 14 18 0 0 77
Don Vic Construction
9 22 32 78 0 0 0 0 0 0 41
White Moon Inc. 4 29 4 29 4 29 2 14 0 0 14
TOTAL 38 16 92 39 52 22 48 21 4 2 234
(b) Recruitment Table 11. Staff requirement in the next 3 months
Position No. of Required
1. Health, Safety and Environment Officer 1
2. Driver 4WD 1
3. TBM/Hydraulic Mechanic 1
4. Forklift Operator 1
5. Chief Mechanic 1
6. Chief Electricians 1
7. Electronic Technicians 1
8. Helper 1
9. Tunnel Line Extension 2 1
10. Tunnel Line Extension 3 1
11. Tunnel Line Extension 4 1
12. TBM Operator 1
13. Laborers 5
14. Erector Operator/Probe Drill 2
15. Shift Boss 1
16. Driver Lorry Crane 1
17. Locomotive Operator 1
18. Driver (Mini Van) 2
19. Tippler Operator 2
20. Tippler Operator Helpper 2
21. Rail/Switch Cleaner 6
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
16
22. Surveyor 2
23. Loco Driver 4
24. Erector Operator 2
25. Grouting Supervisor 2
26. Grouting Pump Operator 4
27. Grouting Injection Operator 4
28. Pea Gravel Pump Operator 2
29. Pea Gravel Injection Operator 4
30. Segment Crane Operator 2
31. Nurse 1
TOTAL 62
(c) List of Equipment
Table 12. Contractor: CMC di Ravenna
Item Quantity (as of 31 Dec 2017)
Stand-by (as of 31 Dec 2017)
Remarks
Welding Machine 3
Generator Set 4
Tower Light 1
Air Compressor 2
Dropside Truck 1
Forklift 1
Telescopic Handler 1
60 Ton Crane (Rental) 1
Table 13. Sub-contractor: First Balfour
Item Quantity (as of 31 Dec 2017)
Stand-by (as of 31 Dec 2017)
Remarks
Backhoe(20Tons Capacity)
2
Backhoe (7Tons Capacity)
1
BHI Hydraulic Breaker 1
Service Vehicles 3
Mini Dump Truck 2
Dump Truck (15 cu.m capacity)
1
Komatsu Breaker 1
Skid Steer Loader 1
Wheel Loader 1
Shotcrete Machine 1
Compressor 1
Grout pump 1
Grout mixer 1
Bagger Mixer 1
Table 14. Sub-contractor: Don Vic Construction
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
17
Item Quantity (as of 31 Dec 2017)
Stand-by (as of 31 Dec 2017)
Remarks
Backhoe 1
Dropside Truck 1
Table 15. Sub-contractor: White Moon Inc.
Item Quantity (as of 31 Dec 2017)
Stand-by (as of 31 Dec 2017)
Remarks
Circular Saw 1
Electric Drill 2
Oxygen Acetylene Tank
1
1.2.7 Specific dates (day/month/year) site visits/inspections conducted by the supervision consultant to monitor
compliance of the contractors (and subcontractors) with the mitigation measures specified in the EMP.
The construction supervision consultants have not yet been commissioned by MWSS. MWSS
staff were the ones monitoring the compliance of CMC with the mitigating measures specified
in the Contractor’s Environmental Management and Monitoring Plan (CEMMP) Issues and
concerns were discussed in their weekly project management meeting with CMC.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
18
2 Compliance with ADB loan covenants and applicable government laws, regulations and requirements
2.1 Status of compliance with government environmental requirements:
The following table presents the permits acquired for the project. Copies
of the permits are in Appendix Section 8.2 and 8.3 of this report.
Table 16. Permits
Environmental Laws
Permits Date of Issue/ remarks Expiry Date
PD 1586 (Establishing EIS System)
ECC1 (Environmental Compliance Certificate)
ECC-CO-1508-0022
7 April 2017.
The certificate shall cover the following:
1. construction of water tunnel #4 with 6.4 kilometer length and 4 m diameter from Ipo Dam, Barangay San Mateo to Barangay Bigte, with associated facilities such as Contractor’s Work areas, Spoil Disposal Sites as enumerated in the EIS
2. Repair and rehabilitation works of Tunnel Nos 1,2,3
3. Water transmission operations of Tunnels No 1,2,3 and 4 for an aggregate water flow of up to 43 m3/sec
4. Fencing of the Right-of- way
-
RA 6969 (Toxic Substances and Hazardous and Nuclear Waste)
DENR Registry ID
No major construction activity as of this time. Only used oil
from vehicle is generated and all maintenance services of vehicles are done offsite. Permit application will be
processed when temporary Hazmat disposal area is 50%
filled.
CCO Registry (Chemical Control Order Registry)
N/A
Importer Clearance No
N/A
Permit to Transport
N/A. no major construction activity as of this time. Only
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
19
used oil from vehicle is generated and all
maintenance services of vehicles are done offsite. Permit application will be
processed when temporary Hazmat disposal area is 50%
filled.
RA 8749 (Phil Clean Air Act)
PO No.1 (permit to Operate)
FLA-17J-03BU-550 (1 unit 20KW Standby GenSet)
20 October 2017 October 30, 2018
PO No.2 (permit to Operate)
FLA- 17J03BU-549 (1 unit 40KW Standby GenSet)
20 October 2017 October 30, 2018
PD 705 (The Forestry Reform Code Of The Philippines)
Tree Cutting Permit
- Tree cutting permit dated July 10, 2017 (10 fruit bearing trees) issued by CENRO Tabang
July 25, 2017
- Tree cutting permit dated July 25, 2017 (2 Acacia Trees) issued by MENRO Norzagaray
July 30, 2017
- Tree cutting permit dated August 16, 2017 (20 assorted fruit tree species) issued by CENRO Tabang
August 31, 2017
- Tree cutting permit dated August 24, 2017 (4 Acacia trees) issued by CENRO Tabang
August 31, 2017
- Tree cutting permit dated September 11, 2017 (5 Acacia Trees) issued by CENRO Tabang
September 18, 2017
- Tree cutting permit dated September 23, 2017 (10 assorted tree species) issued by CENRO Tabang
October 8, 2017
Table 17. Other Permits
Permits Date of Issue/ remarks Expiry Date
Mayor’s Permit Permit number: 2017-0722 Date of Issue: June 5, 2017
December 31, 2017 (For renewal)
Excavation/Slope Stabilization Permit
Permit number: 2017-11-0090 Date of Issue: November 29, 2017
-
Storage Building Permit
BP #2017-11-0091 November 29, 2017
Land use Permit issued by NPC
Permit number: 2017-LUP-03 Date of Issue: July 14, 2017
(approximately 25 years) July 14, 2042
Garbage Hauling and Disposal
May 30, 2017
December 30, 2017
PCO Accreditation
September 29, 2017
September 29, 2020
Table 18. Safety Report as of December 2017
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
20
Previous This Period To Date
Average Manpower 385 300 372
CMC di Ravenna 96 97 98
Sub-contractor 289 203 263
Safe Man-hours 510,526 72,882 583,408
CMC di Ravenna 191,337 18,660 208,997
Sun-contractor 319,189 54,222 373,411
Major Incidents2 3 - 3
Minor Incidents3 7 - 7
Activity Previous This Period To Date
Incidents / Cases
Vehicle Incidents4 5 0 5
Near Misses5 9 2 11
First-Aid Cases6 9 0 9
Medical Treatment Cases7
261 84 345
Restricted Work Cases8
0 0 0
Lost-Time Cases9 0 0 0
Meeting/s
No. of Safety Meetings
19 3 22
No. of Toolbox Meetings
501 15 516
No. of People Inducted/Oriented
414 26 440
No. of Safety Observations
159 24 183
No. of Inspection Audits
168 12 180
Training Activity/ies and Number of
Participants
Hand and power tools
7 6 13
2 Major Incidents – defined as an acute incident such as major discharge/emission or a fire/explosion, which
immediately or subsequently causes several serious injuries and/or fatalities, serious harm to environment and/or loss of substantial material assets.
3 Minor Incidents – an accident that causes minor damage. 4 Vehicle Incidents – when a motor vehicle strikes or collides another vehicle, a stationary object, a pedestrian, or an
animal 5 Near Misses – unplanned event that has the potential to cause, but does not actually result in human injury,
environmental or equipment damage, or an interruption of normal operation. 6 First Aid Cases – worker’s injury cases administered immediately after the injury occurs at the location where it
occurred. 7 Medical Treatment Cases – recordable incident involving injury or illness that has required management and care of
the patient above and beyond first aid, but not severe enough to be a reportable fatality or lost work day case or restricted work day case.
8 Restricted Work Cases – when a person is so injured that they cannot perform their normal duties. Therefore, they
are transferred temporarily to some other jobs (light duties). 9 Lost-Time Cases – refer to the number of lost-time injuries within a given accounting period, relative to the total
number of hours worked in that period.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
21
Previous This Period To Date
Personal Protective Equipment (PPE)
37 5 42
Fire Prevention 30 11 41
Ladder Safety 21 6 27
Working at Heights 31 0 31
First Aid and CPR 0 0 0
Emergency and Evacuation Drill
3 0 3
Defensive Driving 15 0 15
Electrical Safety 30 5 35
Hazardous Materials Handling
2 0 2
Earthquake Drill 2017
An earthquake drill was conducted at CMC workers’ area on September 27,
2017. This was done as part of the implementation of Contingency
Emergency Response Plan. There were 30 participants in the drill, a
combination of CMC main staff, other contractors and soldiers from
Armed Forces of the Philippines. Emergency evacuation route was also
established and discussed to the staff.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
22
Figure 12. CMC staff during earthquake drill
Figure 13. Actual photo from the Earthquake Drill
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
23
Figure 14. Site Assembly Point Area (Holding Area/Muster Point)
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
24
3 Changes in project scope
No change in project scope.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
25
4 Summary of Environmental Mitigations and Compensation Measures Implemented
A full review of the CEMMP, IEE, EIA EMP and other obligations is presented in the compliance matrix in Appendix Section 8.1 of this report. Below is a summary
of prevailing issues on mitigation and compensation issues. Details can be found in Appendix Section 8.1.
Environmental Aspect
Potential Impact Possible Approach/ Mitigating Measures
Compliance Status
Remarks
Water
Impact on surface water quality due to/ from: · Contaminants from materials used and construction activities and processes · Siltation from soil erosion, spoil disposal area, dewatering excavations, etc · Water quality Deterioration of water quality in Ipo Dam and Bigte river Tributary during construction
· Implement hazardous waste management that minimizes, properly segregates and promptly and properly disposes of generated hazardous wastes. · Store hazardous construction materials in appropriately contained and elevated area and at least100 m away from surface water bodies. · Implement corrective action, when trigger thresholds of water quality are reached. · During construction, the contractor shall take corrective action to reduce concentration to below the standard.
Partial
High coliform was reported in segment of surface water where there are communities along the riverbanks prior to the start of construction activities. This trend was already noted during the collection of baseline information in 2013 -2014. Please note that Ipo Construction site was on stop work status since 2017 September. Portalets are provided and regularly collection is implemented in all construction sites - Ipo and Bigte. Waste onsite are segregated into biodegredable, non-biodegradable and residuals. There are designated bins for each type of waste, color coded and labeled. Waste are collected every Tuesday and Thursday by Brgy Bigte. CMC and Brgy Bigte has a service contract for garbage and hauling disposal from May 2017 to December 2017.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
26
Environmental Aspect
Potential Impact Possible Approach/ Mitigating Measures
Compliance Status
Remarks
The first water quality sampling was conducted by CMC last August 2017 with the following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS, ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See sampling location and results on the report). Weekly monitoring of water turbidity and other in-situ paramters using portable water meters started on October 2017. Testing is done weekly by CMC Envi, Health and Safety Officers (See sampling location and results on the report)
Air Quality and Noise
a) Deterioration of ambient air quality due to dust and gas emissions from: · Earthworks and other construction processes; tunneling (TBM) • stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas; • increased transport activities in the construction areas and along Ipo Road;
In active work sites: Use of dust curtains / nets to capture dust from the construction sites
Apply dust suppression techniques, e.g., watering with bowsers, sheeting particularly at Bigte area Require trucks, particularly those hauling aggregates, to have secure covers. · Limit engine idling to 5 minutes. · Prohibit open burning of vegetation and other waste in the project area
Partial
No dust curtains/net have been installed. Not yet necessary. This will be installed at the outlet portal area once excavation activities commence and measured air duality parameters such as total suspended particles and PM 10 are almost near the standard limits of air quality.
Dust suppression such as watering of road has been implemented already.
Open burning is not practiced onsite. ALL CMC drivers have defensive driving training. It is observed that speed limit along Ipo road was not followed mostly by the community.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
27
Environmental Aspect
Potential Impact Possible Approach/ Mitigating Measures
Compliance Status
Remarks
• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day • burning of vegetation and wastes; and • operation of mechanical equipment
· Ipo Road, main access road, other roads in the Project area, limit speed of all construction vehicles to maximum of 40 kph on the access road to, and maximum of 30 kph in the site · Control noise at source, e.g. low noise plant, muffling, acoustic screening, switch off campaigns · Restrict use of noisy and highly vibrating equipment from 8AM-5PM. Necessary overtime work should: a) not go beyond 9:00PM; b) observe regulated noise and vibration levels; c) not use noisy and highly vibrating equipment; and d) should be coordinated with the barangay and affected households. · Manage the ins and outs of hauling trucks. Spread out the schedule of material, waste and spoil transport in the day (off-peak hours). .· Enforce the rule of no blowing of horns. · Strictly enforce upon workers the compliance with wearing of ear mufflers, especially those who are operating equipment.
Agreement with CRL Laboratories for air quality monitoring is now in place (24 August 2017). The air quality sampling dates will be scheduled once the Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
February 6-8, 2018
May 8-10, 2018
August 7-9, 2018
November 6-8, 2018
February 5-7, 2019
Biological Environment
Loss of vegetation due to:
· Provide environmental training for workforce
Non-Compliant
No environmental training for workforce has been done yet The workforce has been made aware of the company’s policy against
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
28
Environmental Aspect
Potential Impact Possible Approach/ Mitigating Measures
Compliance Status
Remarks
• vegetation clearing and potential trampling of trucks/equipment beyond project footprints • Over-clearance and damage to vegetation around the construction sites
collection, transportation and selling of wildlife and endangered forest species.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
29
Table 19. Summary of Environmental Mitigations and Compensation Measures Implemented
EMP Requirement (list all mitigation
measures specified in the
EMP/CEMP/SEMP)
Compliance Attained
Location
Comment on Reasons for Partial or Non-Compliance
Required Action and Target Dates to Achieve Compliance
1. Water Quality Monitoring
Compliant Ipo and Bigte River
Visual monitoring through photograph and Video documentation. The first water quality sampling was conducted by CMC last August 2017 with the following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS, ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals. Water quality in the basin has also been collected and analyzed last December 2017 with the following parameters: temperature,TSS, electric conductivity, turbidity, color and TDS. Weekly monitoring of water turbidity using portable turbidimeter started on October 2017. Testing is done weekly by CMC Envi, Health and Safety Officers
2. Air quality monitoring
Partial Agreement with CRL Laboratories for air quality monitoring is now in place (24 August 2017). The air quality sampling dates will be scheduled once the Tunnel Excavation starts. A sound level meter was procured by CMC to monitor the noise level during construction period as one of the requirements of ADB and
Air quality monitoring will be done quarterly. Target date of air quality monitoring are as follows: -February 6-8,2018 -May 8-10, 2018 -August 7-9,2018 -November 6-8, 2018 -February 5-7, 2019
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
30
EMP Requirement (list all mitigation
measures specified in the
EMP/CEMP/SEMP)
Compliance Attained
Location
Comment on Reasons for Partial or Non-Compliance
Required Action and Target Dates to Achieve Compliance
DENR. Noise monitoring started on 28 October 2017.
3. Freshwater ecology monitoring
Partial Request for quotation for the conduct of the water quality has been sent to CRL Laboratories.
Target date of freshwater ecology monitoring is on April and August 2018-2019
4. Social and Economic Survey
Partial Socio-economic survey currently being discussed with an IP Specialist/ Anthropologist (Mr Joseph Lalo)
Target date of socio economic survey is on September 2018
5. Social and environmental awareness
Partial Residences near construction area and tunnel ROW
Bulletin boards for IEC purpose were installed in the barangay halls of Brgy Bigte and San Mateo on June 19-20, 2017. Third letter to NCIP in relation to FPIC application was sent on 15 June 2017.
IEC will be done to students and residents should there be major construction activities, deliveries of large goods, notice of employment requirement starting July 2017.
6. Public Health and safety
Compliant Health and safety staff are hired. Detailed grievance procedure was formulated on July 2017.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
31
4.1 Emission/Wastewater Discharge (Source) Monitoring Program (if
relevant or required in the EMP)
4.1.1 Summary of Monitoring No sampling has done yet.
4.1.2 Results No results are available yet.
4.1.3 Assessment10
4.2 Water Quality Monitoring Program
4.2.1 Summary of Water Quality Monitoring for Bigte and Ipo River (August, December
2017)
Fresh water quality sampling along Angat River and laboratory inspection
in CRL Laboratory in Clark, Pampanga was carried out 30 August 2017 by
Selam Tesfaye, Rusty Romero and Pam Constante. A total of 4 samples
were collected. Due to heavy rains, the samples in Bigte Creek and Sta
Maria River was collected in 5 September 2017.
The water quality sampling activity in Bigte area on 31 August 2017 was
aborted due to heavy rains. It was done in 5 September 2017.
A portable turbidimeter was purchased by CMC to conduct a daily turbidity
monitoring at the water bodies near the construction sites in December
2017.
Video and photo documentation along Ipo River (Angat River) is ongoing
while procurement of water quality instrument and laboratory analyses
service is in progress.
4.2.2 Results of Bigte and Ipo River (August, December 2017)
Below are sampling points and complete laboratory results of the water
quality samples collected in August and September.
Complete results were transmitted in October 2017. Measures in red are
parameters with exceedances according to DAO 2016-08. The results
presented were compared with the baseline (2013 wet season).
10 Discharge levels should be compared to the relevant discharge standards and/or performance indicators noted in
the EMP. Any exceedances should be highlighted for attention and follow-up. In addition, discharge levels could be compared to baseline conditions (if baseline data is available) and described in qualitative terms or be evaluated based on a ranking system, such as the following:
1. Very Good (overall conditions are generally improved) 2. Good (conditions are maintained or slightly improved) 3. Fair (conditions are unchanged) 4. Poor (conditions are moderately degraded) 5. Very Poor (conditions are significantly degraded)
Additional explanatory comments should be provided as necessary.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
32
Figure 15. The sampling locations (Bigte and Ipo Rivers)
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
33
Figure 16. Sampling points in Bigte River
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
34
Figure 17. Sampling points in Ipo River
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
35
4.2.3 Water Quality Results for Bigte River (August and December 2017)
Table 20. Water Quality Results for SWB1
Parameter Adopted Criteria (Class B DAO
2016-08) Reference
SW BIGTE1/SWB1
Bigte Creek near the basin 2 in Bigte Portal. This site is near the outlet.
N14° 51.538’ E121° 05.453’
Year/ quarter 2013 WET
(May to Oct.) 2014 DRY
(Nov. to Apr.) 2017 AUG.
2017 DEC.
Physical Characteristics
Temp (°C) 26-30 DAO 2016-08 27.4 27.5 25 25
Salinity (%) - parameter not included in DAO 2016-08 14.62 13.91 7
TSS (mg/L) 65 DAO 2016-08 130.5 130.5
Electric Cond. (mS/cm) - parameter not included in DAO 2016-08 228.5 217.3 270 -
Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC
5.66 5.26 13 0.25
Colour (Apparent, PCU) 50 DAO 2016-08, class B 15 15 20 8
TDS (mg/L) - parameter not included in DAO 2016-08 146.9 12 155 89
pH 6.50-8.50 DAO 2016-08 8.7 7.93 8
Inorganic and Non-metallic Constituents
Nitrogen (as NO₃¯) (mg/L) 7 DAO 2016-08 0.1 0.02 1
Oxidation Reduction Potential ORP (mV)
- parameter not included in DAO 2016-08 195 217.2 144
Phosphorus (as PO₄³¯) (mg/L) 0.5 DAO 2016-08 0.03 0.4 0
Organic and Biological Constituents
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
36
Parameter Adopted Criteria (Class B DAO
2016-08) Reference
SW BIGTE1/SWB1
Bigte Creek near the basin 2 in Bigte Portal. This site is near the outlet.
N14° 51.538’ E121° 05.453’
Year/ quarter 2013 WET
(May to Oct.) 2014 DRY
(Nov. to Apr.) 2017 AUG.
2017 DEC.
Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 14.4 4.21 8
BOD5 (mg/L) 5 DAO 2016-08 1 1 2
COD (mg/L) - parameter not included in DAO 2016-08 20 9.8 13
Fecal Coliform (MPN/100mL) 100 DAO 2016-08 92,000 1,700 16,000
Total Coliform (MPN/100mL) - parameter not included in DAO 2016-08 54,000 16,000 24,000
Oil and Grease (mg/L) 1 DAO 2016-08 0.5 0.4 0.4
Elements
Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.001
Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.01 <0.01
Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.006 <0.006
Chromium (hexavalent, Cr(VI)), (mg/L)
0.01 DAO 2016-08 <0.003 <0.003
Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.02 <0.02
Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05 <0.04
Manganese (Mn), (mg/L) 0.2 DAO 2016-08 0.01 0.1
Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0001
Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.03 <0.03 <0.03
Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 <1.0
Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.02 <0.007
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
37
Table 21. Water Quality Results for SWB2
Parameter Adopted Criteria
Reference
SW03/SWB2
Bigte Creek, within the Salonga Property. The site near Sitio Settling
N14° 51.526 E121° 05.330’
Year/ Quarter
2013 WET (May to Oct.)
2014 DRY (Nov. to Apr.)
2017 AUG.
2017 DEC.
Physical Characteristics
Temp (°C) 26-30 DAO 2016-08 27 27.1 25 26.1
Salinity (%) - parameter not included in DAO 90-34 14.06 12.16 8.2
TSS (mg/L) 65 DAO 2016-08 - 12
Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 219.7 190 497 426.6
Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 12.8 24.1 10.86 5.63
Colour (Apparent, PCU) 50 DAO 2016-08, class B 20 10 15
TDS (mg/L) - parameter not included inDAO 2016-08 141.1 120.4 306 278.7
pH 6.50-8.50 DAO 2016-08 8.33 8.12 7.5
Inorganic and Non-metallic Constituents
Nitrogen (as NO₃¯) (mg/L) 7 DAO 2016-08 0.02 0.02 0.4
Oxidation Reduction Potential ORP (mV)
- parameter not included in DAO 2016-08 82 82 141
Phosphorus (as PO₄³¯) (mg/L) 0.5 DAO 2016-08 0.01 0.01 0.09
Organic and Biological Constituents
Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 22.5 8.18 7.7
BOD5 (mg/L) 5 DAO 2016-08 1 1 3
COD (mg/L) - parameter not included in DAO 2016-08 9.8 9.8 7.3
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
38
Parameter Adopted Criteria
Reference
SW03/SWB2
Bigte Creek, within the Salonga Property. The site near Sitio Settling
N14° 51.526 E121° 05.330’
Year/ Quarter
2013 WET (May to Oct.)
2014 DRY (Nov. to Apr.)
2017 AUG.
2017 DEC.
Fecal Coliform (MPN/100mL) 100 DAO 2016-08 9,200 1,700 35,000
Total Coliform (MPN/100mL) - parameter not included in DAO 2016-08 92,000 16,000 92,000
Oil and Grease (mg/L) 1 DAO 2016-08 0.3 0.4 0.4
Elements
Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.001
Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.01 <0.01
Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.006 <0.006
Chromium (hexavalent, Cr(VI)), (mg/L)
0.01 DAO 2016-08 <0.003 <0.003
Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.02 <0.02
Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.05 <0.05 <0.05
Manganese (Mn), (mg/L) 0.2 DAO 2016-08 0.07 0.2
Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0001
Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.03 <0.03 <0.03
Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 <1.0
Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.02 <0.007
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
39
Table 22. Water Quality Results for SWB3
Parameter Adopted Criteria
Reference
SWB3
Baltazar bridge. This is the bridge pass the Barangay Bigte Hall
N14° 51.272’ E121° 05.144
Year/ quarter 2013 WET
(May to Oct.) 2014 DRY
(Nov. to Apr.) 2017 AUG.
2017 DEC.
Physical Characteristics Temp (°C) 26-30 DAO 2016-08 28.2 - 25 26.3
Salinity (%) - parameter not included in DAO 2016-08 - - 7.4
TSS (mg/L) 65 DAO 2016-08 - - -
Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 376 - 441 322.6
Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 25.4 - 10.44 6.96
Colour (Apparent, PCU) 50 DAO 2016-08, class B - 15
TDS (mg/L) - parameter not included in DAO 2016-08 244.8 - - 208.2
pH 6.50-8.50 DAO 2016-08 7.94 - 7.9
Inorganic and Non-metallic Constituents
Nitrogen (as NO₃¯) (mg/L) 7 DAO 2016-08 - - 0.5
Oxidation Reduction Potential ORP (mV)
- parameter not included in DAO 2016-08 251 - 140
Phosphorus (as PO₄³¯) (mg/L) 0.5 DAO 2016-08 - - 0.2
Organic and Biological Constituents - - -
Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 - - 8.3
BOD5 (mg/L) 5 DAO 2016-08 - - 1
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
40
Parameter Adopted Criteria
Reference
SWB3
Baltazar bridge. This is the bridge pass the Barangay Bigte Hall
N14° 51.272’ E121° 05.144
Year/ quarter 2013 WET
(May to Oct.) 2014 DRY
(Nov. to Apr.) 2017 AUG.
2017 DEC.
COD (mg/L) - parameter not included in DAO 2016-08 - - 12
Fecal Coliform (MPN/100mL) 100 DAO 2016-08 - - 24000
Total Coliform (MPN/100mL) - DAO 2016-08 - - 24000
Oil and Grease (mg/L) 1 DAO 2016-08 - - 0.5
Elements
Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 - -
Arsenic (As), (mg/L) 0.01 DAO 2016-08 - - <0.01
Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 - - <0.006
Chromium (hexavalent, Cr(VI)), (mg/L)
0.01 DAO 2016-08 - -
Copper (Cu), (mg/L) 0.02 DAO 2016-08 - - <0.02
Lead (Pb), (mg/L) 0.01 DAO 2016-08 - - <0.05
Manganese (Mn), (mg/L) 0.2 DAO 2016-08 - -
Mercury (Hg), (mg/L) 0.001 DAO 2016-08 - -
Nickel (Ni), (mg/L) 0.04 DAO 2016-08 - - <0.03
Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 - -
Zinc (Zn), (mg/L) 2 DAO 2016-08 - - <0.007
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
41
Table 23. Water Quality Results for SWSM1
Parameter Adopted Criteria
reference
STA MARIA 03/SWSM1 In Sta Maria River, within the vicinity of San Jose Bridge
N14° 50.123’ E121° 04.47’1’
Year/ quarter 2013 WET
(May to Oct.) 2014 DRY
(Nov. to Apr.) 2017 AUG.
2017 DEC.
Physical Characteristics Temp (°C) 26-30 DAO 2016-08 27.3 32.3 24.9 27.9
Salinity (%) - parameter not included in DAO 90-34 15.74 13
TSS (mg/L) 65 DAO 2016-08 657 32
Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 246 450.8 355 366.4
Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 51.4 12.1 19.33 4.23
Colour (Apparent, PCU) 50 DAO 2016-08, class B 500 20
TDS (mg/L) - parameter not included in DAO 2016-08 158 292.5 207 238.2
pH 6.50-8.50 DAO 2016-08 8.2 7.64 7.9
Inorganic and Non-metallic Constituents
Nitrogen (as NO₃¯), (mg/L) 7 DAO 2016-08 0.1 0.6 1
ORP (mV) - parameter not included in DAO 2016-08 187 156 138
Phosphorus (as PO₄³¯), (mg/L) 0.5 DAO 2016-08 0.7 0.3 0.2
Organic and Biological Constituents
Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 not measured 2.07 7.7
BOD5 (mg/L) 5 DAO 2016-08 14 1 2
COD (mg/L) - parameter not included in DAO 2016-08 49 49 9.3
Fecal Coliform (MPN/100mL) 100 DAO 2016-08 920,000 31,000 24,000
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
42
Parameter Adopted Criteria
reference
STA MARIA 03/SWSM1 In Sta Maria River, within the vicinity of San Jose Bridge
N14° 50.123’ E121° 04.47’1’
Year/ quarter 2013 WET
(May to Oct.) 2014 DRY
(Nov. to Apr.) 2017 AUG.
2017 DEC.
Total Coliform (MPN/100mL) - DAO 2016-08 920,000 31,000 24,000
Oil and Grease (mg/L) 1 DAO 2016-08 <0.3 0.7 0.4
Elements
Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.001
Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.01 <0.01
Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.006 <0.006
Chromium (hexavalent, Cr(VI)), (mg/L)
0.01 DAO 2016-08 <0.003 <0.003
Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.02 <0.02
Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.04 <0.05
Manganese (Mn), (mg/L) 0.2 DAO 2016-08 0.4 0.5
Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0001
Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.01 <0.01 <0.03
Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 <1.0
Zinc (Zn), (mg/L) 2 DAO 2016-08 0.1 <0.02 <0.007
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
43
4.2.4 Water Quality Results for IPO River (August 2017)
Water quality monitoring in Ipo was done only in 2017 August. Ipo Site is on ‘stop work status’ as of 7 August 2017.
Table 24. Water Quality Results for SW IPO1
Parameter
Adopted Criteria (Class B DAO
2016-08) Reference
IPO US2/IPO1
Near confluence of Sapang Anginan and Angat River
N14° 53’ 41.6” E121° 10’ 10.8”
Year/ quarter 2013 WET (Baseline)
2017 AUGUST
Physical Characteristics
Temp (°C) 26-30 DAO 2016-08 27.5 25
Salinity (%) - parameter not included in DAO 90-34 8.65 4
TSS (mg/L) 65 DAO 2016-08 - -
Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 135.2 155
Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 1.86 10
Colour (Apparent, PCU) 50 DAO 2016-08, class B - 8
TDS (mg/L) - parameter not included in DAO 2016-08 84.84 91
pH 6.50-8.50 DAO 2016-08 7.88 6.8
Inorganic and non-metallic constituents
Nitrogen (as NO₃¯) (mg/L) 7 DAO 2016-08 - 0.2
Oxidation Reduction Potential ORP (mV)
- parameter not included in DAO 2016-08 210 134
Phosphorus (as PO₄³¯) (mg/L)
0.5 DAO 2016-08 - 0.05
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
44
Parameter
Adopted Criteria (Class B DAO
2016-08) Reference
IPO US2/IPO1
Near confluence of Sapang Anginan and Angat River
N14° 53’ 41.6” E121° 10’ 10.8”
Year/ quarter 2013 WET (Baseline)
2017 AUGUST
Organic and Biological Constituents
Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 - 8.7
BOD5 (mg/L) 5 DAO 2016-08 210 1
COD (mg/L) - parameter not included in DAO 2016-08 - 3
Fecal Coliform (MPN/100mL)
100 DAO 2016-08 - 17
Total Coliform (MPN/100mL)
- parameter not included in DAO 2016-08 210 240
Oil and Grease (mg/L) 1 DAO 2016-08 - 0.05
Elements
Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.008
Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.01
Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.003
Chromium (hexavalent, Cr(VI)), (mg/L)
0.01 DAO 2016-08 not measured not measured
Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.01
Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05
Manganese (Mn), (mg/L) 0.2 DAO 2016-08 not measured not measured
Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0002
Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.01 <0.03
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
45
Parameter
Adopted Criteria (Class B DAO
2016-08) Reference
IPO US2/IPO1
Near confluence of Sapang Anginan and Angat River
N14° 53’ 41.6” E121° 10’ 10.8”
Year/ quarter 2013 WET (Baseline)
2017 AUGUST
Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 0.008
Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.007
Bromide (Br), (mg/L) - 4.1 not measured
Table 25. Water Quality Results for SW IPO2
Parameter Adopted Criteria (Class B DAO
2016-08) Reference
IPO 4/SW IPO2
Near confluence of Sapang Munti and Angat River
N14° 52’ 22.3” E121° 10’ 05.6”
Year/ quarter 2013 WET (Baseline) 2017
AUGUST
Physical Characteristics
Temp (°C) 26-30 DAO 2016-08 31.8 25
Salinity (%) - parameter not included in DAO 2016-08
9.76 2.4
TSS (mg/L) 65 DAO 2016-08 - -
Electric Cond. (mS/cm) b
- parameter not included in DAO 2016-08
152.5 151
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
46
Parameter Adopted Criteria (Class B DAO
2016-08) Reference
IPO 4/SW IPO2
Near confluence of Sapang Munti and Angat River
N14° 52’ 22.3” E121° 10’ 05.6”
Year/ quarter 2013 WET (Baseline) 2017
AUGUST
Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC
152.5 15
Colour (Apparent, PCU)
50 DAO 2016-08, class B - 10
TDS (mg/L) - parameter not included in DAO 2016-08
95.07 87
pH 6.50-8.50 DAO 2016-08 8.11 7.1
Inorganic and Non-metallic Constituents
Nitrogen (as NO₃¯) (mg/L)
7 DAO 2016-08 - 0.2
Oxidation Reduction Potential ORP (mV)
- parameter not included in DAO 2016-08
253 131
Phosphorus (as PO₄³¯) (mg/L)
0.5 DAO 2016-08 - 0.03
Organic and Biological Constituents
Dissolved Oxygen (mg/L)
5 (minimum) DAO 2016-08 - 8.3
BOD5 (mg/L) 5 DAO 2016-08 - 2
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
47
Parameter Adopted Criteria (Class B DAO
2016-08) Reference
IPO 4/SW IPO2
Near confluence of Sapang Munti and Angat River
N14° 52’ 22.3” E121° 10’ 05.6”
Year/ quarter 2013 WET (Baseline) 2017
AUGUST
COD (mg/L) - parameter not included in DAO 2016-08
- 6.4
Fecal Coliform (MPN/100mL)
100 DAO 2016-08 350 33
Total Coliform (MPN/100mL)
- parameter not included in DAO 2016-08
3500 110
Oil and Grease (mg/L)
1 DAO 2016-08 - 0.4
Elements
Antimony (Sb), (mg/L)
- parameter not included in DAO 2016-08
<0.001 <0.008
Arsenic (As), (mg/L)
0.01 DAO 2016-08 <0.01 <0.01
Cadmium (Cd), (mg/L)
0.003 DAO 2016-08 <0.006 <0.003
Chromium (hexavalent, Cr(VI)), (mg/L)
0.01 DAO 2016-08 not measured not
measured
Copper (Cu), (mg/L)
0.02 DAO 2016-08 <0.02 <0.01
Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05
Manganese (Mn), (mg/L)
0.2 DAO 2016-08 not measured not
measured
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
48
Parameter Adopted Criteria (Class B DAO
2016-08) Reference
IPO 4/SW IPO2
Near confluence of Sapang Munti and Angat River
N14° 52’ 22.3” E121° 10’ 05.6”
Year/ quarter 2013 WET (Baseline) 2017
AUGUST Mercury (Hg), (mg/L)
0.001 DAO 2016-08 <0.0001 <0.0002
Nickel (Ni), (mg/L)
0.04 DAO 2016-08 <0.01 <0.03
Vanadium (V), (mg/L)
- parameter not included in DAO 2016-08
<1.0 0.008
Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.007
Bromide (Br), (mg/L)
- 2.6 not
measured
Table 26. Water Quality Results for SW IPO3
Parameter
Adopted Criteria (Class B DAO 2016-
08)
Reference
IPO2/SW IPO3
Between the old Ipo Dam structure and intakes of existing tunnels 1,2,3
N14° 52’ 26.9” E121° 10’ 56.5”
Year/ quarter 2013 WET (Baseline)
2017 AUGUST
Physical Characteristics
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
49
Parameter
Adopted Criteria (Class B DAO 2016-
08)
Reference
IPO2/SW IPO3
Between the old Ipo Dam structure and intakes of existing tunnels 1,2,3
N14° 52’ 26.9” E121° 10’ 56.5”
Year/ quarter 2013 WET (Baseline)
2017 AUGUST
Temp (°C) 26-30 DAO 2016-08 31.7 25
Salinity (%) - parameter not included in DAO 2016-08 9.68 3.2
TSS (mg/L) 65 DAO 2016-08 - -
Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 151.3 159
Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 2.86 17
Colour (Apparent, PCU) 50 DAO 2016-08, class B - 10
TDS (mg/L) - parameter not included in DAO 2016-08 94.43 93
pH 6.50-8.50 DAO 2016-08 8 7.2
Inorganic and Non-metallic Constituents
Nitrogen (as NO₃¯) (mg/L)
7 DAO 2016-08 - 0.2
Oxidation Reduction Potential ORP (mV)
- parameter not included in DAO 2016-08 230 129
Phosphorus (as PO₄³¯) (mg/L)
0.5 DAO 2016-08 - 0.04
Organic and Biological Constituents
Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 - 8.1
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
50
Parameter
Adopted Criteria (Class B DAO 2016-
08)
Reference
IPO2/SW IPO3
Between the old Ipo Dam structure and intakes of existing tunnels 1,2,3
N14° 52’ 26.9” E121° 10’ 56.5”
Year/ quarter 2013 WET (Baseline)
2017 AUGUST
BOD5 (mg/L) 5 DAO 2016-08 - 1
COD (mg/L) - parameter not included in DAO 2016-08 - 9.4
Fecal Coliform (MPN/100mL)
100 DAO 2016-08 350 280
Total Coliform (MPN/100mL)
- parameter not included in DAO 2016-08 3500 280
Oil and Grease (mg/L) 1 DAO 2016-08 - 0.4
Elements
Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.008
Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.1
Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.003
Chromium (hexavalent, Cr(VI)), (mg/L)
0.01 DAO 2016-08 not measured not measured
Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.01
Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05
Manganese (Mn), (mg/L) 0.2 DAO 2016-08 not measured not measured
Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0002
Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.01 <0.03
Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 0.008
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
51
Parameter
Adopted Criteria (Class B DAO 2016-
08)
Reference
IPO2/SW IPO3
Between the old Ipo Dam structure and intakes of existing tunnels 1,2,3
N14° 52’ 26.9” E121° 10’ 56.5”
Year/ quarter 2013 WET (Baseline)
2017 AUGUST
Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.007
Bromide (Br), (mg/L) - 2.5 not measured
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
52
Table 27. Water Quality Results for SW IPO4
Parameter
Adopted Criteria (Class B DAO 2016-
08)
Reference
IPO DS2/SW IPO4
~ 350m downstream of Ipo Dam N14° 52’ 36.8” E121° 10’
42.3”
Year/ quarter 2013 WET 2017
AUGUST
Physical Characteristics
Temp (°C) 26-30 DAO 2016-08 31.3 25
Salinity (%) - parameter not included in DAO 2016-08
9.7 2.4
TSS (mg/L) 65 DAO 2016-08 - Electric Cond. (mS/cm) b
- parameter not included in DAO 2016-08
151.5 158
Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC
6.43 34
Colour (Apparent, PCU)
50 DAO 2016-08, class B - 15
TDS (mg/L) - parameter not included in DAO 2016-08
94.46 90
pH 6.50-8.50 DAO 2016-08 7.81 7.4
Inorganic and Non-metallic Constituents
Nitrogen (as NO₃¯) (mg/L)
7 DAO 2016-08 - 0.2
Oxidation Reduction Potential ORP (mV)
- parameter not included in DAO 2016-08
186 129
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
53
Parameter
Adopted Criteria (Class B DAO 2016-
08)
Reference
IPO DS2/SW IPO4
~ 350m downstream of Ipo Dam N14° 52’ 36.8” E121° 10’
42.3”
Year/ quarter 2013 WET 2017
AUGUST Phosphorus (as PO₄³¯) (mg/L)
0.5 DAO 2016-08 - 0.04
Organic and Biological Constituents
Dissolved Oxygen (mg/L)
5 (minimum) DAO 2016-08 - 9.5
BOD5 (mg/L) 5 DAO 2016-08 - 2
COD (mg/L) - parameter not included in DAO 2016-08
- 4
Fecal Coliform (MPN/100mL)
100 DAO 2016-08 350 5,400
Total Coliform (MPN/100mL)
- parameter not included in DAO 2016-08
9,200.00 5,400
Oil and Grease (mg/L)
1 DAO 2016-08 - 0.5
Elements
Antimony (Sb), (mg/L)
- parameter not included in DAO 2016-08
<0.001 <0.008
Arsenic (As), (mg/L)
0.01 DAO 2016-08 <0.01 <0.01
Cadmium (Cd), (mg/L)
0.003 DAO 2016-08 <0.006 <0.003
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
54
Parameter
Adopted Criteria (Class B DAO 2016-
08)
Reference
IPO DS2/SW IPO4
~ 350m downstream of Ipo Dam N14° 52’ 36.8” E121° 10’
42.3”
Year/ quarter 2013 WET 2017
AUGUST Chromium (hexavalent, Cr(VI)), (mg/L)
0.01 DAO 2016-08 not
measured not measured
Copper (Cu), (mg/L)
0.02 DAO 2016-08 <0.02 <0.01
Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05
Manganese (Mn), (mg/L)
0.2 DAO 2016-08 not
measured not measured
Mercury (Hg), (mg/L)
0.001 DAO 2016-08 <0.0001 <0.0002
Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.01 <0.03
Vanadium (V), (mg/L)
- parameter not included in DAO 2016-08
<1.0 0.008
Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.007
Bromide (Br), (mg/L)
- 1.6 not measured
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
55
4.2.5 Assessment11 of Bigte and Ipo River (August, December 2017)
For Bigte River, only fecal and total coliform were reported in all the
sampling locations (SWB1, SWB2, SWB3 and SWSM1) and exceeded the
DENR 2016-08 standards during the 2017 August-September sampling
period. SWB2 had the highest reported fecal and total coliform with 35,000
and 92,000 respectively. In comparison to the baseline data (2013 wet
season data), total and fecal coliform results have decreased in all the
sampling locations except from SWB3 and fecal coliform at SWB2.
All in-situ parameters measured in Bigte River during the 2017 December
sampling did not exceeded the DENR 2016-08 standard.
For Ipo River, all sampling locations had fecal and total coliform but only
SW IPO4 exceeded the DENR 2016-08 standard with 5,400 (both total and
fecal coliform). In comparison to the baseline data (2013 wet season data),
fecal coliform has increased while total coliform has decreased in SW IPO4.
4.2.6 Summary of Water Quality Assessment in Basin 1(October 2017)
A sample from Basin 1 was collected last October 2017 to establish baseline
data since these water will be used in the construction of the tunnel and
will be treated afterwards in the water treatment plant. Samples were
collected by Selamawit Tesfaye and a representative from CRL
Laboratories.
4.2.7 Results of Water Quality Assessment in Basin 1 (October 2017)
Table 28. Water Quality Results for Basin 1
Parameter Adopted
Criteria Reference Basin 1 Remarks
Physical Characteristics
Temp (°C) 26-30 DAO 2016-08 25
Salinity (%) b - parameter not included
in DAO 2016-08 3.3
TSS - DAO 2016-08 152
11 Ambient environmental conditions should be compared to the relevant ambient standards and/or performance
indicators noted in the EMP. Any exceedances should be highlighted for attention and follow-up. In addition, ambient environmental conditions could be compared to the baseline conditions (if baseline data is available) and described in qualitative terms or be evaluated based on a ranking system, such as the following:
1. Very Good (overall conditions are generally improved) 2. Good (conditions are maintained or slightly improved) 3. Fair (conditions are unchanged) 4. Poor (conditions are moderately degraded) 5. Very Poor (conditions are significantly degraded)
Additional explanatory comments should be provided as necessary.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
56
Electric Cond.
(mS/cm) b -
parameter not included
in DAO 2016-08 -
Turbidity (NTU) b 20 EP (Water Quality) Policy
2003, ANZECC 0.25
Colour (Apparent,
PCU) 50 DAO 2016-08, class B 8
TDS (mg/L) - parameter not included
in DAO 2016-08 89
pH 6.50-8.50 DAO 2016-08 -
Inorganic and non-metallic constituents
Nitrogen (as
NO₃¯) (mg/L) 7 DAO 2016-08 4.8
ORP (mV) - parameter not included
in DAO 2016-08 147
Phosphorus (as
PO₄³¯), (mg/L) 0.5 DAO 2016-08 0.03
organic and biological constituents
Dissolved Oxygen
(mg/L) 5 (minimum) DAO 2016-08 8
Higher value
than 5 mg/L is
preferred. This
value of DO is
very much
acceptable.
Higher DO
value, better
water quality
BOD5 3 DAO 2016-08 1
COD b - parameter not included
in DAO 2016-08 9
Faecal Coliform
(MPN/100mL) b 100 DAO 2016-08 49
Total Coliform
(MPN/100mL) 5000 DAO 2016-08 350
Oil and Grease
(mg/L) 1 DAO 2016-08 1
4.2.8 Assesment2 of Water Quality in Basin 1 (October 2017)
The water from Basin 1 will be the water source for the TBM water
requirement. All parameters in Basin 1 did not exceeded the DENR
2016-08 standard.
4.2.9 Turbidity Monitoring Summary (October to December 2017)
A portable turbidimeter was purchased by CMC to conduct a daily turbidity
monitoring at the water bodies near the construction sites.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
57
4.2.10 Results of Turbidity Monitoring (October – December 2017)
Below are the results of the turbidity monitoring from October –
December 2017. Results in red font indicate elevated turbidity values
compared to 20 NTU limit (EP (Water Quality) Policy 2003, ANZECC).
Table 29. Turbidity monitoring results from October to December 2017
Date Time Location Turbidity (NTU) Remarks
October 2017
28 Oct 2017 08:30 AM Portal Area
(0+300)
19.4 Heavy rain is noted
the night before
the collection of
water sample.
28 Oct 2017 08:42 AM Portal Area (0+
220)
33.23 Heavy rain is noted
the night before
the collection of
water sample.
28 Oct 2017 09:00 AM Industrial Area
(0+020)
28.45 Heavy rain is noted
the night before
the collection of
water sample.
28 Oct 2017 09:10 AM Industrial Area
(0+000)
31.7 Heavy rain is noted
the night before
the collection of
water sample.
November 2017
4 Nov 2017 7:30 AM Portal Area
(0+300)
8.17 Heavy rain is noted
the night before
the collection of
water sample.
4 Nov 2017 7:40 AM Portal Area
(0+20)
38.84 Heavy rain is noted
the night before
the collection of
water sample.
4 Nov 2017 08:10 AM Industrial Area
(0+020)
29.47 Heavy rain is noted
the night before
the collection of
water sample.
4 Nov 2017 08:15 Industrial Area
(0+000)
32.29 Heavy rain is noted
the night before
the collection of
water sample.
11 Nov 2017 7:30 AM Portal Area
(0+300)
18.57 Heavy rain is noted
the night before
the collection of
water sample
11 Nov 2017 7:40 AM Portal Area
(0+20)
18.18 Fine weather
during sampling
11 Nov 2017 08:10 AM Industrial Area
(0+020)
13.62 Fine weather
during sampling
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
58
11 Nov 2017 08:15 AM Industrial Area
(0+000)
12.18 Fine weather
during sampling
17 Nov 2017 07:45 AM Portal Area
(0+300)
10.37 Fine weather
during sampling
17 Nov 2017 07:55 AM Portal Area
(0+20)
11.11 Fine weather
during sampling
17 Nov 2017 08:30 AM Industrial Area
(0+020)
16.49 Fine weather
during sampling
17 Nov 2017 08:35 AM Industrial Area
(0+000)
17.06 Fine weather
during sampling
24 Nov 2017 08:00 AM Portal Area
(0+300)
17.62 Cloudy
24 Nov 2017 08:15 AM Portal Area
(0+20)
18.88 Cloudy
24 Nov 2017 08:35 AM Industrial Area
(0+020)
17.63 Cloudy
24 Nov 2017 08:50 AM Industrial Area
(0+000)
17.42 Cloudy
December 2017
1 Dec 2017 07:45 AM Portal Area
(0+300)
13.81 Sunny
1 Dec 2017 08:00 AM Portal Area
(0+20)
13.23 Sunny
1 Dec 2017 08:20 AM Industrial Area
(0+020)
12.69 Sunny
1 Dec 2017 08:30 AM Industrial Area
(0+000)
12.01 Sunny
8 Dec 2017 07:30 AM Portal Area
(0+300)
12.24 Cloudy
8 Dec 2017 07:35 AM Portal Area
(0+20)
13.85 Cloudy
8 Dec 2017 07:45 AM Industrial Area
(0+020)
10.22 Cloudy
8 Dec 2017 08:00 AM Industrial Area
(0+000)
112.4 Cloudy
4.3 Air and Noise Quality Monitoring Program
4.3.1 Summary of Air and Noise Quality Monitoring (July- December 2017)
Agreement with CRL Laboratories for air quality monitoring is now in
place (24 August 2017). The air quality sampling dates will be scheduled
once the Tunnel Excavation starts.
A sound level meter was procured by CMC to monitor the noise level
during construction period as one of the requirements of ADB and DENR.
Noise monitoring started on 28 October 2017.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
59
4.3.2 Result of Noise Level Monitoring (October-December 2017)
Below are the noise level measurement at the different locations onsite:
Table 30. Noise level monitoring results (October-December 2017)
Date Time Location Equipment Noise level
(db)
October 2017
28 Oct 2017 7:50 AM Industrial area Genset,
excavator,
grinding
78.1-83.8
28 Oct 2017 08:10 AM Industrial area,
near the gate
Genset,
excavator,
crane, forklift is
within the 20
meter radius
area
77.9-83.5
28 Oct 2017 08:33 AM RCBC/Reaction
Slab
Excavator,
drilling
machine, is
within the 30
meter radius
area
70.3-86.6
28 Oct 2017 08:50 AM In between Basin
1 and 2
Compressor for
drilling
machine, is
within the 30
meter radius
area.
71.3-79.9
28 Oct 2017 09:01 AM In front of clinic Concreting
work with
concrete mixer.
62.9-70.1
November 2017
11 Nov 2017
10:00 AM Portal Area Generator 76.4-79.9
Backhoe/Crane 78-93.8
Concrete Mixer 86.3-92
Residential Area 66.5-85.1
10:39 AM Industrial Area Genset 77.3-86.3
Grinder 79.6-89.3
10:50 AM Tippler Area Excavator 67.5-84
23 Nov 2017 Near Basin 1 58.9-63.2
Portal Rock Breaking 67.3-78.4
FA Station 56.9-69.5
Industrial Area Gen Set 73.1-74.9
Industrial Area
Gate
Road Vehicle 55.7-78.3
Along the Rail
Road
52.6-60.9
24 Nov 2017 7:54 AM Near MWSS
Office
Excavator 71.6-90.1
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
60
Portal Area Excavator 61.1-92.2
8:51 AM Warehouse Area Circular Saw 67-90.1
8:54 AM Water
Treatment Area
55.2-61.4
09:01 AM Segment Staging
Area
Forklift 64.3-73.8
09:04 AM Near Trippler Chainsaw 56.6-95.6
December 2017
1 Dec 2017 7:50 AM Portal Area Excavator 66.8-82.8
08:10 AM Warehouse/Fab
shop
Truck 66.8-68.5
08:25 AM Entrance Gate
(Industrial)
64.5-83
08:47 AM Sta 000 64.2-86.6
09:14 AM Fab Shop Grinder 68.2-93.7
10:00 AM Tippler/Commun
ity Area
63-68.4
13 Dec 2017 08:00 AM Office Area Backhoe/Loader 70.9-76.2
08:10 AM MWSS Breaker 65.1-87.8
08:17 AM Portal
Community
Houses
53.5-76.2
08:36 AM Railroad going to
Tippler
Welding
Machine
69.3-84.5
8:44 AM Box Culvert 62.4-67.4
09:00 AM Tippler Area 61.5-74.3
4.3.3 Assesment3 for Noise Quality Monitoring (October-December 2017)
The results are compared to WHO guidelines.
Table 31. WHO guidelines for noise quality
Reference / Jurisdiction Ambient Standard
Guidelines for Community Noise, WHO, 1999
International
Receptor: Residential; institutional; educational
Daytime (07:00-22:00): 55dBA
Nighttime (22:00-07:00): 45dBA
Receptor: Industrial; commercial
70dBA throughout the day
The sound level tests show high sound level at the construction site which
is expected due to machines, equipment and laborers at work. The
residential area near the outlet recorded sound reading between the range
of 53.5 -76.2 dB. The results show that noise level within the vicinity
exceeds noise guidelines. No complaints received from the areas.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
61
5 Key Environmental Issues
5.1 Key activities implemented
The following activities are currently implemented:
(i) The following monitoring is being established: Water quality monitoring
o Water quality monitoring started on August 2017. CMC also procured portable turbidimeter and multimeter to take in-situ measurements daily on the established sampling points and bodies of water near the construction sites.
Air and Noise quality monitoring
o Agreement with CRL Laboratories for air quality monitoring is
now in place (24 August 2017). The air quality sampling dates will
be scheduled once the Tunnel Excavation starts. It will be done
quarterly. Target dates of the air quality monitoring are as follows:
February 6-8, 2018
May 8-10, 2018
August 7-9, 2018
November 6-8, 2018
February 5-7, 2019 o A sound level meter was procured by CMC to monitor the noise
level during construction period as one of the requirements of ADB and DENR. Noise monitoring started on 28 October 2017 and will be continuously done weekly.
5.2 Key Issues Identified
Freshwater water ecology monitoring
o Target date of the freshwater monitoring are as follows:
April 2018
August 2018
Social and economic survey
o Target date of the socio-economic survey and monitoring are as
follows:
September 2018
Social and environmental awareness
o Bulletin boards for IEC purpose were installed in the barangay
halls of Brgy Bigte and San Mateo on June 19-20, 2017. Third
letter to NCIP in relation to FPIC application was sent on 15
June 2017. Target date of the social and environmental
awareness campaign for the residents and students will be done
on during:
Started in July 2017 and monthly updates thereafter or
in cases such as employment requirement of the
construction project; and major construction activities
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
62
and deliveries of largo goods that will have potential
impact to the environment as well as community health
and safety impact
Public Health and safety
o public health and safety campaign started in September 2017 and
should continue until the end of construction period. This activity
should be continued by MWSS during the operational phase.
Procurement of other laboratory services, consultancy services and surveys is on-
going.
(i) MWSS has no Construction Supervision Engineer Team where an
environment specialist is included. CMC provides environmental and
social technical inputs to the project.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
63
6 Complaints
6.1 Details of Complaint/s Table 32. List of grievances as of December 2017
Valid Grievance Cases 2
Invalid Grievance Cases 0
Unresolved Grievance Case from previous months
0
Pending Valid Grievance Cases 0
Resolved Grievance Cases to date 2
Two grievance cases have been reported as of December 2017.
1. Dumagats expressed their complaint during the FPIC meeting in July 4,
2017 on the turbidity of the water of Ipo River which is caused by the
runoff during heavy rain. The case was investigated by Rusty Romero and
Pamela Constante. There was no rain at the time of investigation.
Localized increase in turbidity is observed. Video / photo documentation
during heavy rain was requested from Danielle Scalaro and Alex Lim to
monitor water turbidity by visual inspection while waiting for the
instruments and water quality sampling. To date, video documents show
that the turbid water comes from Sapang Munti and upstream of Ipo
Dam.
2. A complaint was received on July 18, 2017 by CMC which was filed by
residents of Calle Onse (adjacent to the Industrial Area in Brgy Bigte
regarding the generation of dust and mud along the road. This case was
investigated by CMC H&S together with representative of Calle Onse.
CMC already made provision of a canal across the Industrial Area. The
problem is not attributed solely to CMC but residents addressed grievance
to CMC hoping to get some help. The case was closed and H&S has the
detailed documentation.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
64
7 Conclusion and Recommendation
7.1 Overall Progress of Implementation of Environmental Management
Measures12
The overall progress can be assessed as fair. The project construction
phase started in December 2016. Temporary and major facilities and work
areas have been established from July to December 2017. The TBM already
arrived onsite and will start operating on March 2018. In such construction
activities, potential environmental impacts associated to tunnel
construction per se is yet to be observed until the excavation work will
commence. Water quality monitoring has started on August 2017.
Portable water meters (turbidimeter and multi-meter) have arrived and in-
situ monitoring on established sampling points and water bodies onsite
started on October 2017. For air quality monitoring, agreement with CRL
Laboratories for air quality monitoring is now in place (24 August 2017).
The air quality sampling dates will be scheduled once the Tunnel
Excavation starts. A sound level meter was procured by CMC to monitor
the noise level during construction period Noise monitoring started on
October 2017 and will be continuously done weekly. Other monitoring and
survey services/ consultancy procurement are in progress.
12 Overall sector environmental management progress could be described in qualitative terms or be evaluated based
on a ranking system, such as the following: 1. Very Good 2. Good 3. Fair 4. Poor 5. Very Poor
Additional explanatory comments should be provided as necessary.
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
1
8 Appendices
8.1 AWTIP Monitoring Matrix
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
2
8.2 Tree Cutting Permits
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
3
8.3 Permits and Licenses
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
4
8.4 Water Quality Laboratory Results
Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1
2017 July – December
5
8.5 Grievance Case - Invalid
Potential Impact Responsible Responsible
Soil and Erosion due to:
· soil disturbance
· vegetation clearing
Location: Inlet structure and relevant work
sites
Confine soil disturbance and/or vegetation
clearing to pre-defined and planned area that
includes project footprint and needed
easements
Part of project development cost CMC OSP-AWTIP Compliant
Geocomposite steel mesh with anchor bolts has been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
MPR
Inspection Report
(c/o Jasper Cazenas
and Ricky Latunio)
Video documentation
by D Scolaro.
Environment
Inspection Checklist
and Inpection Report
(c/o Jasper Cazenas
and Ricky Latunio)
Soil and Erosion due to:
· soil disturbance
· vegetation clearing
Stabilize exposed soils with temporary
seeding, mulches, mats, non-chemical-based
soil binders.
Part of project development cost CMC OSP-AWTIP Compliant
Geocomposite steel mesh with anchor bolts has been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
MPR
Inspection Report
(c/o Jasper Cazenas
and Ricky Latunio)
Video documentation
by D Scolaro.
Environment
Inspection Checklist
and Inpection Report
(c/o Jasper Cazenas
and Ricky Latunio)
Soil and Erosion due to:
· soil disturbance
· vegetation clearing
Protect slopes with any one or combination of
bonded fiber matrices, erosion control
blankets, silt fence, fiber rolls, and keeping
stormwater off the slopes through diversion
channels and/or berms.
Part of project development cost CMC OSP-AWTIP Compliant
Geocomposite steel mesh with anchor bolts has been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
MPR
Inspection Report
(c/o Jasper Cazenas
and Ricky Latunio)
Video documentation
by D Scolaro.
Environment
Inspection Checklist
and Inpection Report
(c/o Jasper Cazenas
and Ricky Latunio)
Soil and Erosion due to:
· soil disturbance
· vegetation clearing
Re-vegetate disturbed soils/slopes as soon as
possible after completion of the construction
works.
Part of project development cost CMC OSP-AWTIP Not Applicable No vegetation survey has been done yet. To be checked AFTER
COMPLETION OF THE CONSTRUCTION WORKS
Geocomposite steel mesh with anchor bolts has been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Soil and Erosion due to:
· soil disturbance
· vegetation clearing
Replacing vegetation that died during the
defects liability period.
Part of project development cost CMC OSP-AWTIP Not Applicable TO BE MONITORED during the DEFECTS LIABILITY PERIOD.
No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Soil and Erosion due to:
· soil disturbance
· vegetation clearing
At the active work sites,
Provide temporary drainage with sedimentation
tank or filters such as block and gravel, prior to
discharge to watercourses
In Progress Water treatment plant is already under construction Work Site Plan
MPR
Inspection Report
(c/o Jasper Cazenas
and Ricky Latunio)
Environment
Inspection Checklist
and Inpection Report
(c/o Jasper Cazenas
and Ricky Latunio)
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
At the active work sites
Mitigating contaminants
· Provide adequate sanitation facilities and
water supply at work sites and workers’ camp. Enforce observance of good sanitation
practices by workers.
Part of project (construction) cost CMC OSP-AWTIP Compliant High coliform was reported in segment of surface water where there are
communities along the riverbanks prior to the start of construction activities.
Please note that Ipo Construction site was on stop work status since 2017
September.
Portalets are provided and regularly collection is implemented in all construction
sites - Ipo and Bigte.
Waste onsite are segregated into biodegredable, non-biodegradable and
residuals. There are designated bins for each type of waste, color coded and
labeled. Waste are collected every Tuesday and Thursday by Brgy Bigte. CMC
and Brgy Bigte has a service contract for garbage and hauling disposal from May
2017 to December 2017.
The first water quality sampling was conducted by CMC last August 2017 with the
following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,
ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ paramters using portable
water meters started on October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location and results on the report)
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· Implement solid waste management that
minimizes, re-uses, properly segregates and
promptly and properly disposes of generated
solid wastes.
Part of project (construction) cost CMC OSP-AWTIP Compliant Waste onsite are segregated into biodegredable, non-biodegradable and
residuals. There are designated bins for each type of waste, color coded and
labeled. Waste are collected every Tuesday and Thursday by Brgy Bigte. CMC
and Brgy Bigte has a service contract for garbage and hauling disposal from May
2017 to December 2017.
The first water quality sampling was conducted by CMC last August 2017 with the
following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,
ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ paramters using portable
water meters started on October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location and results on the report)
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· Implement hazardous waste management
that minimizes, properly segregates and
promptly and properly disposes of generated
hazardous wastes.
Part of project (construction) cost CMC OSP-AWTIP Compliant
Hazmat identified at this stage of construction is limited to oil, lubricants used by
heavy equipment and vehicles. Most vehicles used are brand new. Maintenance
is done off site.
Hazmat temporary storage included in the site plan
The first water quality sampling was conducted by CMC last August 2017 with the
following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,
ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ paramters using portable
water meters started on October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location and results on the report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
hazmat temporary
disposal included in
the Industrial Area
site plan (c/o Sergio
and Federico)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· Store hazardous construction materials in
appropriately contained and elevated area and
at least100 m away from surface water bodies.
Part of project (construction) cost CMC OSP-AWTIP Compliant
Hazmat identified at this stage of construction is limited to oil, lubricants used by
heavy equipment and vehicles. Most vehicles used are brand new. Maintenance
is done off site.
Hazmat temporary storage included in the site plan
The first water quality sampling was conducted by CMC last August 2017 with the
following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,
ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ paramters using portable
water meters started on October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location and results on the report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
hazmat temporary
disposal included in
the Industrial Area
site plan (c/o Sergio
and Federico)
Photo-documentation
Turbidity (c/o Jasper
Cazenas and Ricky
Latunio)Monitoring
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· Have equipment clearly leaking oil repaired
off-site immediately. No vehicle/equipment
maintenance, repair and refueling to be allowed
at the sites.
Part of project (construction) cost CMC OSP-AWTIP Compliant No equipment reported to have such case
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· Treat construction water before discharge.
Install settling pond/ water treatment facility
(see annex) for water generated during tunnel
boring. Allow water through grease trap or
oil/collector and/or filters such as rock filled
bags, block and gravel.
Part of project (construction) cost CMC OSP-AWTIP In Progress Please note that water quality parameter exceedances are noted in the baseline
data especially on coliform which was reported in segment of surface water
where there are communities are found along the riverbanks.
Hazmat identified at this stage of construction is limited to oil, lubricants used by
heavy equipment and vehicles. Most vehicles used are brand new. Maintenance
is done off site.
Construction of Waste Water Treatment Facility is on-going.
The first water quality sampling was conducted by CMC last August 2017 with the
following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,
ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Water quality in Basin 1 has also been collected and analyzed last October 2017
with the following parameters: temperature,TSS, electric conductivity, turbidity,
color and TDS (See sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ paramters using portable
water meters started on October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location and results on the report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· Implement corrective action, when trigger
thresholds of water quality are reached.
Part of project (construction) cost CMC OSP-AWTIP Compliant The first water quality sampling was conducted by CMC last August 2017 with the
following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,
ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Water quality in Basin 1 has also been collected and analyzed last October 2017
with the following parameters: temperature,TSS, electric conductivity, turbidity,
color and TDS (See sampling location and results on the report).
Weekly monitoring of water turbidity using portable turbidimeter started on
October 2017. Testing is done weekly by CMC Envi, Health and Safety Officers
(See sampling location and results on the report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· During construction, the contractor shall take
corrective action to reduce concentration to
below the standard.
Part of project (construction) cost CMC OSP-AWTIP Compliant The first water quality sampling was conducted by CMC last August 2017 with the
following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,
ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Water quality in Basin 1 has also been collected and analyzed last October 2017
with the following parameters: temperature,TSS, electric conductivity, turbidity,
color and TDS (See sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ paramters using portable
water meters started on October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location and results on the report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· Mitigating sedimentation
Build cofferdams when building inlet structure
Part of project (construction) cost CMC OSP-AWTIP Not Applicable inlet works not yet started
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
· Use any combination of perimeter controls
at spoil disposal areas or stockpiles of
aggregate materials, e.g., silt fences, sediment
basins, sandbags, earth bern/bund.
Part of project (construction) cost CMC OSP-AWTIP Compliant The first water quality sampling was conducted by CMC last August 2017 with the
following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,
ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Water quality in Basin 1 has also been collected and analyzed last October 2017
with the following parameters: temperature,TSS, electric conductivity, turbidity,
color and TDS (See sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ paramters using portable
water meters started on October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location and results on the report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Impact on surface water quality due to/
from:
· Contaminants from materials used and
construction activities and processes
· Siltation from soil erosion, spoil
disposal area, dewatering excavations, etc
· Water quality Deterioration of water
quality in Ipo Dam and Bigte river Tributary
during construction
• Minimize / control dewatering or extraction of tunnel water by storing and re-using pumped-
out water from the tunnel.
Part of project (construction) cost CMC OSP-AWTIP Not Applicable
Extraction of water from the dam site
(inlet) and creek (near the outlet) to be
used as coolant during construction
Use efficient tunnelling technology that recycles
tunnel drainage water to minimize extraction of
water.
Part of project (construction) cost CMC OSP-AWTIP In Progress Water treatment plant is already under construction
Water quality in Basin 1 has also been collected and analyzed last
October 2017 with the following parameters: temperature,TSS,
electric conductivity, turbidity, color and TDS (See sampling location
and results on the report).
MPR
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Impact on groundwater:
a) deteriorating water quality due to:
· Silt/sediments
· Hazardous materials and waste
In all active work sites
Site temporary stockpile of excavated soils in
flat areas, away from main surface drainage
routes, limit to maximum of 2 m high.
Part of project (construction) cost CMC OSP-AWTIP In ProgressTemporary stockpile areas are in flat or areas with localized depression. Spoil
disposal area, MAPOL quarry, was identified. It has an approximate land area of
4 hectares, located approximately 2 kilometers from the source of spoil.
Spoil management plan is in place and will be revised if needed.
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Impact on groundwater:
a) deteriorating water quality due to:
· Silt/sediments
· Hazardous materials and waste
Provide silt fences, silt traps, or sand bags, at
stockpiles of aggregate materials.
Part of project (construction) cost CMC OSP-AWTIP In Progress silt fences, traps, or sand bags are not yet necessary. stockpiles are on stable
areas or in areas with localized depression. No stockpile more than 2m high.
The stockpiles are and not causing deteriotion to water quality
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Impact on groundwater:
a) deteriorating water quality due to:
· Silt/sediments
· Hazardous materials and waste
Dispose of residual soil/spoil as soon as
possible, to the disposal areas, or as free
backfilling materials for LGU/barangay roads
Part of project (construction) cost CMC OSP-AWTIP In Progress spoils generated to date are needed in the construction activities.
Request for spoil from Ipo Elementary School has been received by CMC 2017
July. Please note that IPO construction site is on stop work status from August -
December 2017. No spoil delivered to Ipo Elementary School as of December
2017. The request is a priority once construction work at Ipo resumes.
Construction engineers made inspection and the following are some observation:
1. The materials are hauled from the construction sites using dump truck. This
size of vehicle cannot enter the school's premises due to small gate. Only small
vehicle can fit the gate of the school.
2. There is need to remove the a fence to enter to the school premise which the
head teacher indicated to dispose the spoil.
3. There is a need to remove the vegetation and cut some trees and do some
excavation works.
These observations are preliminary and will be discussed with th eschool
personnel. This concerns have to be dealth with by the school prior to te delivery
of the spoil.
Impact on groundwater:
a) deteriorating water quality due to:
· Silt/sediments
· Hazardous materials and waste
Avoid stockpiling more aggregates than
necessary.
Part of project (construction) cost CMC OSP-AWTIP In Progress Stockpile is at minimum especially in Ipo construction site (Intake).
Spoil management plan has been drafted and already submitted to MWSS. Spoil
disposal area, MAPOL quarry, was identified. It has an approximate land area of
4 hectares, located approximately 2 kilometers from the source of spoil.
b) lowering of water level of wells in
nearby communities due to tunnelling,
pumping/extracting of tunnel drainage
water
Monitor for potential groundwater depletion in
existing wells in the vicinity. Provide interim
measures to avoid disrupting water supply to
affected households. Investigate for proper
corrective action.
Part of project (construction) cost CMC OSP-AWTIP Non-CompliantNo groundwater monitoring has been done yet since excavation of tunnel had not
started.
a) Deterioration of ambient air quality due
to dust and gas emissions from:
· Earthworks and other construction
processes; tunnelling (TBM)
• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;
• increased transport activities in the construction areas and along Ipo Road;
• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day
• burning of vegetation and wastes; and
In active work sites:
Use of dust curtains / nets to capture dust from
the construction sites
Part of project (construction) cost CMC OSP-AWTIP In Progress No dust curtains/net has been installed. Not yet necessary.
Dust supression such as watering of road has been implemented already.
Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality Monitoring:
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
a) Deterioration of ambient air quality due
to dust and gas emissions from:
· Earthworks and other construction
processes; tunnelling (TBM)
• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;
• increased transport activities in the construction areas and along Ipo Road;
• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day
• burning of vegetation and wastes; and
• operation of mechanical equipment
Apply dust suppression techniques, e.g.,
watering with bowsers, sheeting particularly at
Bigte area
Part of project (construction) cost CMC OSP-AWTIP Compliant No dust curtains/net has been installed.
Dust supression has been implemented already.
Open burning is not practiced onsite
Speed limit within the construction site is implemented
Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
a) Deterioration of ambient air quality due
to dust and gas emissions from:
· Earthworks and other construction
processes; tunnelling (TBM)
• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;
• increased transport activities in the construction areas and along Ipo Road;
• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day
• burning of vegetation and wastes; and
• operation of mechanical equipment
Water dry unpaved/exposed surfaces,
stockpiles of sand and excavated materials, at
least twice daily, or as necessary.
Part of project (construction) cost CMC OSP-AWTIP In Progress watering of road not necessary during the wet season.
Dust supression has been implemented already.
Open burning is not practiced onsite
Speed limit has not yet implemented
Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
a) Deterioration of ambient air quality due
to dust and gas emissions from:
· Earthworks and other construction
processes; tunnelling (TBM)
• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;
• increased transport activities in the construction areas and along Ipo Road;
• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day
• burning of vegetation and wastes; and
• operation of mechanical equipment
Protect aggregate stockpiles with sheeting to
restrict the movement of dust.
Part of project (construction) cost CMC OSP-AWTIP In Progress
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
a) Deterioration of ambient air quality due
to dust and gas emissions from:
· Earthworks and other construction
processes; tunnelling (TBM)
• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;
• increased transport activities in the construction areas and along Ipo Road;
• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day
• burning of vegetation and wastes; and
• operation of mechanical equipment
Require trucks, particularly those hauling
aggregates, to have secure covers.
Part of project (construction) cost CMC OSP-AWTIP Compliant No dust curtains/net has been installed.
Dust supression has been implemented already.
Open burning is not practiced onsite
Speed limit has not yet implemented
Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
a) Deterioration of ambient air quality due
to dust and gas emissions from:
· Earthworks and other construction
processes; tunnelling (TBM)
• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;
• increased transport activities in the construction areas and along Ipo Road;
• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day
• burning of vegetation and wastes; and
• operation of mechanical equipment
Limit engine idling to 5 minutes. Part of project (construction) cost CMC OSP-AWTIP In Progress No dust curtains/net has been installed.
Dust supression has been implemented already.
Open burning is not practiced onsite
Speed limit has not yet implemented
Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
A sound level meter was procured by CMC to monitor the noise level during
construction period as one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
a) Deterioration of ambient air quality due
to dust and gas emissions from:
· Earthworks and other construction
processes; tunnelling (TBM)
• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;
• increased transport activities in the construction areas and along Ipo Road;
• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day
• burning of vegetation and wastes; and
• operation of mechanical equipment
Ipo Road, main access road, other roads in
the Project area area, limit speed of all
construction vehicles to max. of 40 kph on the
access road to, and max. 30 kph in, the site.
Part of project (construction) cost CMC OSP-AWTIP Compliant No dust curtains/net has been installed.
Dust supression has been implemented already.
Open burning is not practiced onsite
Speed limit has not yet implemented
Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
A sound level meter was procured by CMC to monitor the noise level during
construction period as one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas and
Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Where haulage traffic exceeds 200 heavy
goods vehicles (HGV) per dayIn Progress
Air quality in the tunnel In Progress TBM has a built-in air quality monitoring device to measure oxygen, methane and
carbon dioxide
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Noise and vibration in the project area
from excavation activities; genera
construction activities; and vehicle and
equipment operations
Use only equipment that emit least noise and
vibration and are well maintained.
Part of the project (construction) cost CMC OSP-AWTIP Compliant Trevi Foundations conducted inland drillinge for seismic test
Noise and vibration in the project area
from excavation activities; genera
construction activities; and vehicle and
equipment operations
Use facility layout to minimize noise
propagation e.g. using topography / existing
buildings as barriers, where possible locate
noisy activities away from local communities.
Part of the project (construction) cost CMC OSP-AWTIP In Progress Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
A sound level meter was procured by CMC to monitor the noise level during
construction period as one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Noise and vibration in the project area
from excavation activities; generated by
construction activities; and vehicle and
equipment operations
Control noise at source, e.g. low noise plant,
muffling, acoustic screening, switch off
campaigns.
Part of the project (construction) cost CMC OSP-AWTIP Compliant Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
A sound level meter was procured by CMC to monitor the noise level during
construction period as one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
PPEs (earplugs and earmuffs are used onsite)
Sound Level
Monitoring (c/o
Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Noise and vibration in the project area
from excavation activities; genera
construction activities; and vehicle and
equipment operations
Restrict use of noisy and highly vibrating
equipment from 8AM-5PM. Necessary
overtime work should: a) not go beyond
9:00PM; b) observe regulated noise and
vibration levels; c) not use noisy and highly
vibrating equipment; and d) should be
coordinated with the barangay and affected
households.
Part of the project (construction) cost CMC OSP-AWTIP In Progress Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
A sound level meter was procured by CMC to monitor the noise level during
construction period as one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Noise and vibration in the project area
from excavation activities; genera
construction activities; and vehicle and
equipment operations
Manage the ins and outs of hauling trucks.
Spread out the schedule of material, waste and
spoil transport in the day (off-peak hours).
Part of the project (construction) cost CMC OSP-AWTIP Compliant Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
A sound level meter was procured by CMC to monitor the noise level during
construction period as one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas and
Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Noise and vibration in the project area
from excavation activities; genera
construction activities; and vehicle and
equipment operations
Enforce the rule of no blowing of horns. Part of the project (construction) cost CMC OSP-AWTIP Compliant Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
A sound level meter was procured by CMC to monitor the noise level during
construction period as one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Noise and vibration in the project area
from excavation activities; genera
construction activities; and vehicle and
equipment operations
Strictly enforce upon workers the compliance
with wearing of ear mufflers, especially those
who are operating equipment.
Part of the project (construction) cost CMC OSP-AWTIP Compliant Agreement with CRL Laboratories for air quality monitoring is now in place (24
August 2017). The air quality sampling dates will be scheduled once the Tunnel
Excavation starts.
A sound level meter was procured by CMC to monitor the noise level during
construction period as one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
PPEs (earplugs and earmuffs are used onsite)
Sound Level
Monitoring (c/o
Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
Institute measures to avoid impacting on
habitats and wildlife, such as:
· minimize vegetation clearance at Bigte and
especially at the intake
Part of project (construction) cost CMC OSP-AWTIP In Progress
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
· fence off vegetation to be retained Part of project (construction) cost CMC OSP-AWTIP Compliant Vegetation survey has not been done yet.
Tree cutting pemit from DENR CENRO has been secured
Land use pemit from NPC has been secured
a. Permit: ECC
Permit #: EMB.ECC-
CO-1508-002
Date of Issue: Apr 7,
2017
Expiry Date: Apr 7,
2022
Agency: DENR-EMB
b. Permit: Land Use
Permit
Permit #: 2017-LUP-
03
Date of Issue: July
17, 2017
Expiry Date: July 14,
2042
Agency: National
Power Corporation
(NPC)
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
· Provide environmental training for workforce Part of project (construction) cost CMC OSP-AWTIP Non-Compliant No environmental training for workforce has been done yet
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
· enforce site rules and sanctions to
discourage workforce from hunting, fishing and
poaching.
Part of project (construction) cost CMC OSP-AWTIP Not Applicable
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
Confine all construction activities to previously
disturbed areas, to the extent practicable, e.g.,
workers’ quarters/camps.
Part of project (construction) cost CMC OSP-AWTIP In Progress
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
Use existing roads for project activities.
Minimize new road construction.
Part of project (construction) cost CMC OSP-AWTIP In Progress
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
To avoid unnecessary clearing, mark/delineate
areas to be cleared of vegetation, e.g. by
fencing.
Part of project (construction) cost CMC OSP-AWTIP Compliant fencing observed. Inspection Checklist
and Report (c/o
Jasper Cazenas and
Ricky Latunio)
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
Rehabilitate cleared areas to their pre-project
conditions, unless otherwise agreed with the
landowner.
Part of project (construction) cost CMC OSP-AWTIP Not Applicable vegetation of cleared areas will be done after the construction
activities. To be monitored in 2019.
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
Re-vegetate construction sites using local,
indigenous species.
Part of project (construction) cost CMC OSP-AWTIP Not Applicable vegetation of cleared areas will be done after the construction
activities. To be monitored in 2019.
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
Re-vegetate watershed target sites especially
in areas identified by the Watershed
Management Plan.
Part of project (construction) cost CMC OSP-AWTIP In Progress
Loss of vegetation due to:
• vegetation clearing and potential
trampling of trucks/equipment beyond
project footprints
• Over-clearance and damage to
vegetation around the construction sites
Limit any collection of wood for charcoal to
exotic i.e. non-native species.
Part of project (construction) cost CMC OSP-AWTIP Not Applicable vegetation of cleared areas will be done after the construction
activities. To be monitored in 2019.
Disturbance to wildlife due to
• Construction noise, vibration, dust,
lighting, presence/movement of people,
etc.
Implement measures to mitigate noise,
vibration and dust.
Part of project (construction) cost CMC Compliant A complaint was received on July 18,2017 by CMC which was filed by residents
of Calle Onse (adjacent to the Industrial Area in Brgy Bigte regarding the
generation of dust and mud along the road. This case was investigated by CMC
H&S together with representative of Calle Onse. CMC already made provision of
a canal across the Industrial Area. The problem is not attributed solely to CMC
but residents addressed grievance to CMC hoping to get some help. The case
was closed and H&S has the detailed documentation.
Grievance Report
(c/o Jasper Cazenas
and Ricky Latunio)
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Disturbance to wildlife due to
• Construction noise, vibration, dust,
lighting, presence/movement of people,
etc.
Strategically place nets at the tunnel portals to
prevent flying debris.
Part of project (construction) cost CMC In Progress
Disturbance to wildlife due to
• Construction noise, vibration, dust,
lighting, presence/movement of people,
etc.
Water to minimize dust accumulation and
spreading.
Part of project (construction) cost CMC Compliant
Traffic due to:
· inadequate capacity of Ipo Road
(access road)
· inadequate capacity of Ipo Road
(access road)
Institute prior coordination with the Barangay
and Municipality for the formulation of a traffic
management and safety plan and for clearing
of structures encroaching into access road
ROW.
Part of project (construction) cost CMC Compliant construction staff are assigned for traffic and transportation of goods
is assigned
Traffic due to:
· inadequate capacity of Ipo Road
(access road)
· inadequate capacity of Ipo Road
(access road)
Prior to construction, clear easement of
encroaching structures, most of them being
temporary.
Part of project (construction) cost CMC Compliant construction engineers confirm adequacy of the road for the transport
of heavy equipment and other large goods
heavy equipemnt
specification (c/c
Sergio and Federico)
Traffic due to:
· inadequate capacity of Ipo Road
(access road)
· inadequate capacity of Ipo Road
(access road)
Strategically post billboards informing the
public about the expected increase in volume of
traffic in the influence area due to Project
implementation. Post at least two weeks prior
to mobilization.
Part of project (construction) cost CMC Compliant Bulletin boards for IEC purpose were installed in the barangay halls of Brgy Bigte
and San Mateo.
CMC. Request for
Permission to Install
Bulletin Boad.
Barangay San Mateo,
Norzagaray, Bulacan.
June 6, 2017
CMC. Request for
Permission to Install
Bulletin Boad.
Barangay Bigte,
Norzagaray, Bulacan.
June 20, 2017
Traffic due to:
· inadequate capacity of Ipo Road
(access road)
· inadequate capacity of Ipo Road
(access road)
Coordinate with the Barangay for assistance in
traffic management.
Part of project (construction) cost CMC Compliant Hauling truck, heavy equipment and other construction related machines are
expected at the construction sites and associated road such as Ipo Road during
the construction
Traffic due to:
· inadequate capacity of Ipo Road
(access road)
· inadequate capacity of Ipo Road
(access road)
Strategically post traffic flagmen along Ipo
Road, equipped with two-way radio.
Part of project (construction) cost CMC Compliant construction staff are assigned for traffic and transportation of goods
is assigned
Traffic due to:
· inadequate capacity of Ipo Road
(access road)
· inadequate capacity of Ipo Road
(access road)
Post sufficiently legible (reflectorized) traffic
safety notice and signage at strategic locations
along the entire stretch of the access road.
Part of project (construction) cost CMC Compliant Traffic and safety signage were installed onsite
Traffic due to:
· inadequate capacity of Ipo Road
(access road)
· inadequate capacity of Ipo Road
(access road)
Limit speed to 40 kph along Ipo Road, 20 kph
at highly populated sections of Ipo Road, and
30 kph at construction sites and unpaved
haulage roads.
Part of project (construction) cost CMC Compliant road signs are provided. Traffic rules coordinated with Brgy Captain
Dadeng Cruz
Traffic due to:
· inadequate capacity of Ipo Road
(access road)
· inadequate capacity of Ipo Road
(access road)
Limit speed to 40 kph along Ipo Road, 20 kph
at highly populated sections of Ipo Road, and
30 kph at construction sites and unpaved
haulage roads.
Part of project (construction) cost CMC In Progress road signs are provided. Traffic rules coordinated with Brgy Captain
Dadeng Cruz. To further discuss implementation of speed limits
along Ipo Road
Coordinate with DPWH regarding the use of
Ipo Road.
Part of project (construction) cost CMC Not Applicable not yet applicable. No damage on road that is related to tunnel
construction has been recorded
Restore access roads within the MWSS
compound to the pre-construction condition or
better.
Part of project (construction) cost CMC PMO Not Applicable not yet applicable. No damage on road that is related to tunnel
construction has been recorded
Potential damage of existing roads used
as access roads due to movement of
heavy equipment and vehicles
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Restricted access to the existing fish
landing sites in Sitio Consultant (identified
area as the Contractor’s Work Area) and boat landing at Sitio Ipo
Inform affected communities living in Ipo
Watershed on the impact of construction works
on transportation and consult them for the best
alternative route. Have alternative route and
fish and boat landing sites ready for use prior
to commencement of construction activities.
Part of project (construction) cost CMC PMO Compliant dumagat communities has been informed of the impacts consultations
annexed in EIA
MMT formation-
MWSS. Angat Water
Improvement
Project(Tunnel 4)-
MOA between MWSS
and DENR on the
Formation of Multi-
partite Monitoring
Team, Manual of
Operation,
Environmental
Monitoring Fund,
Environmental
Guarnatee Fund, and
Work and Financial
Plan. September 19,
2017
Restricted access to the existing fish
landing sites in Sitio Consultant (identified
area as the Contractor’s Work Area) and boat landing at Sitio Ipo
Provide alternative access to school for school
children and residents
Part of project (construction) cost CMC Compliant boat service has been provided for free to communities in Ipo
Restricted access to the existing fish
landing sites in Sitio Consultant (identified
area as the Contractor’s Work Area) and boat landing at Sitio Ipo
Establish alternate boat landing at the mouth of
Sapang Munti River
Part of project (construction) cost CMC Compliant boat service has been provided for free to communities in Ipo
Restricted access to the existing fish
landing sites in Sitio Consultant (identified
area as the Contractor’s Work Area) and boat landing at Sitio Ipo
Install soil entrapment nets and coffer dams to
contain soil erosion at dam site
Part of project (construction) cost CMC Not Applicable construction at Ipo is on road improvement and slope stabilization
Restricted access to the existing fish
landing sites in Sitio Consultant (identified
area as the Contractor’s Work Area) and boat landing at Sitio Ipo
Provide clear signage of alternative routes Part of project (construction) cost CMC Compliant Signage has been posted already
Community health and safety hazards Inform local residents of the project phase and
prohibit entry of local residents into the
construction area.
Part of project (construction) cost CMC In Progress a bulletin board has been installed in Ipo Dam for IEC CMC. Request for
Permission to Install
Bulletin Boad. Ipo
Elementary School,
Norzagaray, Bulacan.
August 7, 2017
Community health and safety hazards Secure project area, including associated
facilities particularly the storage for explosives,
from unauthorized entry
Part of project (construction) cost CMC CompliantUnauthorized entry signage have been installed onsite
Grievance procedure and scheme to be formulated
UXO survey and clearing have been done by hired demining company, Vourvon
Electronica Marketing. UXO were retrieved and surrendered to the Philippine
Army.
Clearance
Certification
Issued by: Vourvon
Electronica Marketing
Issued on: May 29,
2017
Certification of
Receipt of
Unexploded
Explosives
Issued by: Alpha
Aggressor Company
Issued on: July 17,
2017
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Community health and safety hazards Implement measures to mitigate impacts on air
and water quality, noise, traffic
Part of project (construction) cost CMC Compliant
Community health and safety hazards Provide mechanism to reduce dust /other
pollutants (ie. water spraying on the road,
speed limit of vehicles, etc.)
Part of project (construction) cost CMC In Progress
Community health and safety hazards People with impaired health/risks wear masks
and other protective device
Part of project (construction) cost CMC Compliant
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Workers’ health and safety hazard Mitigating impacts from tunnel excavation
(TBM method):
Include H&S protocols in the C-EMP on the
safe construction procedures during
construction.
Compliant Health and Safety Officers have been hired.
Workers’ health and safety hazard Evacuation procedures in tunnel prior to setting
charges. Compliant
Workers’ health and safety hazard Set up a sufficiently equipped emergency first-
response and health care team, linked to an
ultimate response team.
Compliant Health and safety staff have been hired by CMC
Health and safety plan has been formulated
Standby doctor and nurse are present onsite
Ambulance, first aid kits, and fire extinguishers have been provided
Personal Protective Equipment (PPE) are given to the staff. Contractors’ staff are REQUIRED to use PPE onsite at all times.
CMC Health and
Safety Plan
Workers’ health and safety hazard Provide safe housing with adequate basic
services. Compliant Housing was provided for CMC employees
Workers’ health and safety hazard Enforce use of protective wears when at work. Compliant
Workers’ health and safety hazard Conduct pre-mobilization orientation workshop
on health and safety and emergency response
and evacuation procedures.
Compliant
Generation of spoil and spoil disposal.
More than 150,000m3 is expected to be
generated due to tunnelling works, which is
about 190,000 m3 loose volume.
Contamination of spoil with oil from the
operation of the TBM
Prepare and implement a plan for the
preparation of the spoil disposal areas.
Part of project construction cost MWSS
DED consultants
CMC
Compliant Spoil management plan to be formulated. Spoil disposal area, MAPOL quarry,
was identified. It has an approximate land area of 4 hectares, located
approximately 2 kilometers from the source of spoil.
Generation of spoil and spoil disposal.
More than 150,000m3 is expected to be
generated due to tunnelling works, which is
about 190,000 m3 loose volume.
Contamination of spoil with oil from the
operation of the TBM
Characterization of the spoil. Spoil
characterization in terms of oil contamination.
Oil content should be determined by grab
sampling and sending samples to laboratory
partner for analysis.
DED Consultants Compliant
Generation of spoil and spoil disposal.
More than 150,000m3 is expected to be
generated due to tunnelling works, which is
about 190,000 m3 loose volume.
Contamination of spoil with oil from the
operation of the TBM
Minimise the volume of spoil to be disposed of
by re-use in backfilling of roads, and by offering
as free filling materials to government projects
needing backfill materials.
CMC Compliant
Generation of spoil and spoil disposal.
More than 150,000m3 is expected to be
generated due to tunnelling works, which is
about 190,000 m3 loose volume.
Contamination of spoil with oil from the
operation of the TBM
Disposal area must be confined to solid
ground, of low ecological and agricultural value.In Progress Spoil management plan to be formulated. Spoil disposal area, MAPOL quarry,
was identified. It has an approximate land area of 4 hectares, located
approximately 2 kilometers from the source of spoil.
Generation of spoil and spoil disposal.
More than 150,000m3 is expected to be
generated due to tunnelling works, which is
about 190,000 m3 loose volume.
Contamination of spoil with oil from the
operation of the TBM
Disposal area must not occupy drainage lines
and streams, and create an obstacle to
streams or induced flooding.
In Progress Geocomposite steel mesh with anchor bolts has been installed upon portal
Soil from intake slope has been removed
Installation of threaded rock bolts have been done
Generation of spoil and spoil disposal.
More than 150,000m3 is expected to be
generated due to tunnelling works, which is
about 190,000 m3 loose volume.
Contamination of spoil with oil from the
operation of the TBM
Spoil heaps must be designed and shaped with
stable side slopes and suitable drainage.In Progress
AWTIP Monitoring Matrix - CEMMP
Potential Impact Responsible Responsible
Implement Monitor
Relevant
documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)
Generation of spoil and spoil disposal.
More than 150,000m3 is expected to be
generated due to tunnelling works, which is
about 190,000 m3 loose volume.
Contamination of spoil with oil from the
operation of the TBM
Spoils heaps must be compacted during the
earthworks.In Progress
Generation of spoil and spoil disposal.
More than 150,000m3 is expected to be
generated due to tunnelling works, which is
about 190,000 m3 loose volume.
Contamination of spoil with oil from the
operation of the TBM
On complete, the spoil heaps must be covered
with the original top soil from the site and re-
vegetated
In Progress
Solid waste Implement an eco-friendly solid waste
management at work sites and workers’ camp/s, which minimizes, re-uses, segregates
and promptly disposes of generated solid
waste.
Part of project (construction) cost MWSS
CMC
Compliant • Spoil disposal areas will be identified.
• Garbage are segregated into biodegradable, non-biodegradable and residuals
• Contract for waste collection is between Brgy Bigte and CMC
• No ecological solid waste management plan has been formulated yet
Service Contract of
Brgy Bigte and CMC
for Garbage hauling
and disposal
Date of Issue: May
30, 2017
Expiry Date: Dec 31,
2017
Site inspection report
(c/o Jasper Cazenas
and Ricky Latunio)
Hazardous waste Locate stationary ground storage for
hazardous waste at least 100 m away from
water bodies, raised to min 1 ft above high
flood level. Or, use mobile storage but should
not be parked near water bodies.
Secure storage areas appropriately. Storage
facilities must be able to contain spillage.
Dispose of waste promptly and appropriately.
The contractor shall be required to implement
an appropriate hazardous waste management
program.
Part of project (construction) cost CMC In Progress hazmat temporary disposal area included in the industrial area site map hazmat temporary
disposal included in
the Industrial Area
site plan (c/o Sergio
and Federico)
Storage of oil and grease used for the
maintenance and operation of heavy equipment
shall be properly built and maintained, to
include bunded storage for the capacity of the
containers plus 10%, and oil traps on drainage
outfalls.
Part of project (construction) cost CMC In Progress • No hazardous materials facility was built yet.
• No accredited hazardous waste disposal hauler has been contacted yet
• hazmat temporary disposal is included in the site plan.
Industrial area site
plan (c/o Sergio
Daipra and Federico
Mezzetti)
AWTIP Monitoring Matrix - CEMMP
I. Conditions
Environmental Management
ConditionsResponsible
Agencies
Compliance
StatusRemarks Relevant Documents
1. Continuously conduct an effective Information, Education and
Communication (IEC) program to inform and educate all
stakeholders especially its contractors, workers, and local
residents about the:
a. mitigating measures embodied in its EIS;
b. the condition herein stipulated and the environmental;
c. disastar risk reduction management measures and climate
change related issues/concerns
d. human safety features for greater awareness, understanding
and sustained acceptance of the project*The report of program implementation shall be submitted to EMB Central
Office on an annual basis
In Progress
Bulletin boards for IEC purpose were installed
in the barangay halls of Brgy Bigte and San
Mateo.
Socio-economic survey currently being
discussed with an IP Specialist/ Anthropologist
(Mr. Joseph Lalo). The survey is scheduled on
September 2018.
transmittal/ acceptance record of bulletin
board
2. Implement a Comprehensive Social Development Program
(SDP) and submit a separate report together with the
Compliance Monitoring Report (CMR) to the EMB CO and copy
furnished EMB-III on a semi-annual basis
In ProgressSocial Development Program of CMC is
draftedCMC Social Development Plan
3. Submission of EMB CO details, impacts and measure for
repair/rehabilitation of the three tunnels, with public IEC and
consultation, prior to activity funding approval and detailed
design
Compliant
4. Submission to EMB CO details, impacts and measure to
Right-of-Way (ROW) fencing activities, with public IEC and
consultation, including those residents within the ROW and
fence-side neighbors, prior to funding approval and detailed
design
Compliant
All commitments, appropriate mitgating/enhancement measures and monitoring requirements contained in final EIS, including the following shall be instituted and strictly implemented throughout its
project implementation
AWTIP Monitoring Matrix - ECC
5. Submission of a detailed full year water supply and utilization
analysis shall be undertaken within (2) years from receipt of this
Certificate to include history of the water releases from Umiray
River, Angat Dam, irrigation thru the Angat Tailrace tunnel, Ipo
River upstream of Ipo Dam, Angat River downstream of Ipo
Dam, and water diverted thru the existing tunnels. This shall
address any existing impact on NIA Angat-Maasim River
Irrigation System (AMRIS) water supply and potential to
increase water allocation to Water Right or optimize the
60.6m3/s capacity of the four tunnels. The premise is the priority
domestic/municipal water supply (advantage side) over irrigation
water supply. Scenarios include the normal water flow, excess
water flow (La Niña events) and extremely low flows (El Niño).
The study shall be coordinated with NWRB, NIA, AMRIS
federation of farmers. The goals is to provide the farmers, LGUs
and decision-makers awareness of the actual situation and
preparedness for extreme condition.
Not Applicable to be submitted on April 2019 by MWSS
General conditions
6. The project operations shall conform with the provisions of
environmental laws regulations and their Implementing Rules
and Regulations namely: RA 6969 (Toxic Substances and
Hazardous and Nuclear Waste Control Act of 1990), RA 8749
(Philippine Clean Air Act of 1999), RA 9003 (Act providing for an
Ecological Solid Waste Management Program), and RA 9275
(Philippine Clean Water Act of 2004)
In Progress
SMR
MPR
7. The proponent shall set up the following:
a. A readily available and replenishable Environmental
Guarantee Fund (EGF) to cover the following expenses:
• for further environmental assessments, compensations/ identification for whatever damages to life and property that may
be caused by the project;
• rehabilitation and/or restoration of areas affected by the project’s implementation;• abandonment/decommissioning of the project facilities related to the prevention of possible negative impacts and as a source
of fund for contingency and clean-up activities;
In Progress
the MOA between DENR and MWSS has been
forwarded by MWSS to DENR for their
comments (see MWSS letter to EMB Central
Office dated 26 July 2017; MWSS letter to
Chief EIA Div Central Office dated 16 June
2017; MWSS Letter to EMB Central dated 11
September 2017). DENR Region 3 Regional
director realeased memo dated 26
September 2017 to Regional Director of EMB
Region 3 to review the proforma MOA
between MWSS and DENR). CMC also
forwarded the proforma MOA to MWSS for
their review. CMC is ready to release fund for
the EGF after MOA has been signed by
parties.
AWTIP Monitoring Matrix - ECC
b. A Multi-Partite Monitoring Team (MMT) composed of
representative(s) from the proponent, EMB Region III, a local
environmental Non-Government Organization (NGO), NIA and
the LGUs concerned shall be organized. The MMT shall
primarily oversee the compliance of the proponent with the
Environmental Monitoring Plan (EMP) as well as the condition of
its ECC.
In Progress
The MMT has been formed and initiated by
CMC and MWSS. To date, the MMT is
headed by Mr Thiongpe Lee, the MENRO of
Municipality of Norzagaray. Meeting has
been held for the formation of MMT in 2017
July 27; August 23; Septmeber 5 at the MWSS
compound. The activities were supported by
CMC.
c. A replenishable Environmental Monitoring Fund (EMF) to
cover all costs attendant to the operation of the MMT such as
training, sampling and analysis, the hiring of technical experts,
accommodations and transportations.
The amount and mechanics of the EGF, EMF, and the establishments of the
MMT shall be determined by EMB CO and the proponent in coordination with
EMB Region III through a Memorandum of Agreement (MOA) which shall be
submitted within sixty (60) days upon receipt of the Certificate
In Progress
The meetings of MMT members resulted to
formulation of Manual of Operation and
Financial Work Plan. This has been submitted
to MWSS for their review. This has to be
attached to the MOA between MWSS and
DENR for the establishment of the MMT, EGF
and EMF. The EMF is estimated at
2,500,000.00 PhP.
8. Creation of Environmental Unit within sixty (60) days from
receipt of this Certificate that shall competently handle the
environmental-related aspects of the project. In addition to the
monitoring requirements as specified in the Environmental Plan/
Environmental Monitoring Plan, the EU shall have the following
responsibilities:
• Monitor actual projects impacts vis-à-vis the predicted impacts and management measures in the EIS
• Recommended revisions to the EMP/EMoP, whenever necessary subject to the approval of EMB CO. Revisions should
also consider the result of the validation of air dispersion and
thermal plume modeling
• Ensure that data gathered during monitoring activities are properly documented, assessed, evaluated and reported to
EMB CO and Region III in accordance with the standard
formats; and
• Ensure that monitoring and submissions of reports to EMB
In Progress
9. The proponent shall ensure that its contractors and
subcontractors strictly comply with relevant condition of this
certificate as well as the Environmental Management Plan in the
EIS
In Progress
MWSS and CMC conducts weekly meeting
and regular site inspection. MWSS has field
office based in MWSS Compound in Brgy
Bigte. The project staff are reporting to this
office and at the main office in Balara,
Quezon City
AWTIP Monitoring Matrix - ECC
Restrictions
10. No other activities shall be undertaken other than what were
stipulated in the EIS. Any expansion or modification of the
Project beyond the project description or any change in the
activity shall be subject to new EIA study
Compliant No modification or alteration on the project.
11. Transfer the ownership of this project carries these same
conditions and restrictions for which written notification must be
made by herein grantee to EMB within fifteen (15) days from
such transfer
Not Applicable
II. Project Assessment Planning Tool
By the way of recommendation, the following have been taken notice of by this Office, and are forwarding these recommendations to the parties and authorities concerned for proper actions
RecommedationsResponsible
Agencies
Compliance
StatusRemarks Relevant Documents
1. Compliance with the following:
a. Sanitation Code of the PhilippinesDOH Compliant
portalets have been provided in constrcution
site where toilet is not available. MPRs.
b. Labor code of the Philippines including health and safety
standardsDOLE Compliant
employment contracts
SSS, Pag-ibig and Phil Health remitances for
regular employees.
c. National Building Code of the Philippines LGU Compliant Excavation permit
2. Ensure conformance with the Ecological Solid Waste
Management ActLGU Compliant
Service Contract with Brgy Bigte for Hauling
and disposal of solid waste dated 2017 May-
December
3. Inform constituents about the proposed project especially
those that are located downstream of Ipo Dam like Barangays
Baraca and Pinagtulayan for any potential increase in the total
suspended solids of Angat River during dry season.
LGU of Norzagaray Compliant
installation of project bulletin boards in Brgy
Halls of Brgy Bigte and San Mateo, Ipo
Elementary School
4. Maintain records of both print and digital versions on the daily
water supply allocation, schedule and actual water extraction of
Bustos Dam, including often affected rice farms during El Niño
events
NIA Cannot Document CNIA should have data on this
5. Monitor of water flow downstream of Bustos Dam NIA Cannot Document CMWSS measures water intake to all its
transmission system
For the assistance of proponent and government agencies concerned in the management of the project and for the better coordination and mitigating on the project on its surrounding areas and to the
environment
AWTIP Monitoring Matrix - ECC
6. Secure tree cutting permit (if any) DENR-FMB Compliant tree cutting permit secured
Tree cutting Permits issued by Community
Environment and Natural Resources (DENR-
CENRO)
a. Date of Issue: July 10, 2017
Expiry Date: July 25, 2017
b. Date of Issue: July 25, 2017
Expiry Date: July 30, 2017
c. Date of Issue: August 16, 2017
Expiry Date: August 31, 2017
d. Date of Issue: August 24, 2017
Expiry Date: August 31, 2017
e. Date of Issue: September 11, 2017
Expiry Date: September 18, 2017
f. Date of Issue: September 23, 2017
Expiry Date: October 8, 2017
7. Secure PAMB clearance DENR Not Applicablenot applicable as the watershed has no
management board
8. Secure FPIC NCIP In Progress
NCIP conducted field based investigation.
MWSS/CMC is waiting for the work financial
plan of NCIP for the FPIC process
III. Environmental Plainning and Recommendations for the
Proponent
RecommedationsResponsible
Agencies
Compliance
StatusRemarks Relevant Documents
1. Give priority employment to qualified local residents.
Adequate public information for jobs available to local residents
in the affected areas needs to be provided.
Compliant
employement record
MPR
2. Strictly conduct rigid/periodic monitoring of related
health/sickness during project’s operation Compliant H and S record. Medical Record
3. The proponent shall be provide adequate safety gadgets to its
employees/workers to prevent health and occupational hazards
posed by project implementation
Compliant
H and S record on PPEs
MPR H&S section
The proponent shall conduct regular structural monitoring that
will detect potential problems and trigger remedial responses to
avoid possible tunnel failure/breakdown.
In Progress
MWSS is conducting site inspection. CMC is
submitting monthly progress reports that
covers all aspect of the construction project
AWTIP Monitoring Matrix - ECC
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Pre-construction B. the People Required clearances and permits Obtain the following prior to
Notice of Award:
(a) ECC
(b) MOA among DENR RO 3,
NPC and MWSS
(c) Permit to cut tree
(d) Permit to operate
(a) MWSS
(b) MWSS
(c) D&B
Contractor
(d) D&B
Contractor
(a) PhP 500,000.00
(b) none
(c) part of
construction cost
(d) part of
construction cost
Permits/clearances
obtained prior to Notice
of Award
Compliant a. ECC was issued on April 7, 2017
b. Land use permit from NPC is secured on July 17,
2017.
c. Tree Cutting Permit – from Community Environment and Natural Resources (DENR-
CENRO) have been secured.
d. Permit to operate has been secured on October
20, 2017
a. Permit: ECC
Permit #: EMB.ECC-
CO-1508-002
Date of Issue: Apr 7,
2017
Expiry Date: Apr 7,
2022
Agency: DENR-EMB
b. Permit: Land Use
Permit
Permit #: 2017-LUP-
03
Date of Issue: July
17, 2017
Expiry Date: July 14,
2042
Agency: National
Power Corporation
(NPC)
c. Tree cutting
Permits issued by
Community
Environment and
Natural Resources
(DENR-CENRO)
a. Date of Issue: July
10, 2017
Expiry Date: July 25,
2017
Pre-construction B. the People Preparing relevant communities Conduct intensive social and
environmental awareness
program at least one month prior
to Notice of Award, covering (i)
communicable/ transmittable
diseases that may be brought
with the entry of workers; (ii)
potential social conflicts between
communities and workers; (iii)
other health and safety hazards
and impacts during construction
and during maintenance and
repair of completed works; (iv)
potential impact on passageway
of school children, boat landing at
Ipo dam site and Angat River
downstream due to water
turbidity as a result of diggings at
inlet ;and (iv) the grievance
redress mechanism.
OSP-AWTIP
Affected
barangays
In Progress Bulletin boards for IEC purpose were installed in the
barangay halls of Brgy Bigte and San Mateo.CMC. Request for
Permission to Install
Bulletin Boad.
Barangay San
Mateo, Norzagaray,
Bulacan. June 6,
2017
CMC. Request for
Permission to Install
Bulletin Boad.
Barangay Bigte,
Norzagaray, Bulacan.
June 20, 2017
CMC. Request for
Permission to Install
Bulletin Boad. Ipo
Elementary School,
Norzagaray, Bulacan.
August 7, 2017
Performance Indicator
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Pre-construction B. the People Ensuring environmentally
responsible procurement
Include an SPS-compliant EMP in
the bidding documents.
OSP-AWTIP Not applicable SPS-compliant EMP
included in eth bidding
documents
Compliant
Pre-construction B. the People Append EMP to the Contract for
basis in the preparation of the C-
EMP.
OSP-AWTIP SPS-compliant EMP
included in eth bidding
documents
Compliant see General Conditons of the Contract (Section 6
and Employer's Requirment (Section 7)
AWTIP Contract
Agreement signed
2016 May 25G.
Esquivel (MWSS) Pre-construction B. the People In Contract, require D&B
Contractor to submit monthly and
semi-annual environmental
monitoring report.
OSP-AWTIP SPS-compliant EMP
included in eth bidding
documents
Compliant see General Conditons of the Contract (Section 6
and Employer's Requirment (Section 7)
AWTIP Contract
Agreement signed
2016 May 25G.
Esquivel (MWSS)
and A Ciamei (CMC) Pre-construction B. the People Stipulate in Contract the tie up of
progress payment and collection
of performance bond with the
performance in C-EMP
implementation.
OSP-AWTIP SPS-compliant EMP
included in eth bidding
documents
Compliant see General Conditons of the Contract (Section 6
and Employer's Requirment (Section 7)
AWTIP Contract
Agreement signed
2016 May 25G.
Esquivel (MWSS)
and A Ciamei (CMC)
Pre-construction B. the People Prepare C-EMP that addresses
as minimum the requirements of
the EMP.
D & B Contractor SPS-compliant EMP
included in eth bidding
documents
Compliant CEMMP has been submitted by CMC to MWSS on
2017 July 7. CEMMP, June 2017
Pre-construction B. the People Evaluate C-EMP quantitatively
and qualitatively againts the EMP
OSP-AWTIP SPS-compliant EMP
included in eth bidding
documents
In Progress CEMMP has been approved by MWSS. Please see
letter of MWSS to CMC dated 15 August 2017
CEMMP:
Contractor's
Environmental
Management and Pre-construction B. the People Clear the C-EMP before the start
of any activity/work onsite or
establish of any construction
related facility on site by D&B
Contractor
ADB SPS-compliant EMP
included in eth bidding
documents
Compliant CEMMP has been approved by MWSS. Please see
letter of MWSS to CMC dated 15 August 2017
CEMMP:
Contractor's
Environmental
Management and
Construction Phase A. Land Soil and Erosion due to:
(a) soil disturbance
(b) vegetation clearing
Location: Inlet structure and
relevant work sites
Confine soil disturbance and/or
vegetation clearing to pre-defined
and planned area that includes
project footprint and needed
easements
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
development cost
CEMP Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Soil and Erosion due to:
(a) soil disturbance
(b) vegetation clearing
Stabilize exposed soils with
temporary seeding, mulches,
mats, non-chemical-based soil
binders.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
development cost
CEMP Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Construction Phase A. Land Soil and Erosion due to:
(a) soil disturbance
(b) vegetation clearing
Protect slopes with any one or
combination of bonded fiber
matrices, erosion control
blankets, silt fence, fiber rolls,
and keeping stormwater off the
slopes through diversion
channels and/or berms.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
development cost
CEMP In Progress No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase A. Land Soil and Erosion due to:
(a) soil disturbance
(b) vegetation clearing
Re-vegetate disturbed
soils/slopes as soon as possible
after completion of the
construction works.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
development cost
CEMP In Progress No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removedConstruction Phase A. Land Soil and Erosion due to:
(a) soil disturbance
(b) vegetation clearing
Replacing vegetation that died
during the defects liability period.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
development cost
CEMP In Progress No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been doneConstruction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
Institute measures to avoid
impacting on habitats and
wildlife, such as:
a. minimize vegetation clearance
at Bigte and especially at the
intake
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
b. fence of vegetation to be
retained
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
c. provide environmental training
workforce
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit In Progress staff orientation conducted training and
orientation record
Toolbox meeting
attendances (c/o
Jasper Cazenas and
Ricky Latunio) Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
d. enforce site rules and sactions
to discourage workforce from
hunting, fishing and poaching
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
Confine all construction activities
to previously disturbed areas, to
the extent practicable, e.g.,
workers’ quarters/camps.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
Use existing roads for project
activities. Minimize new road
construction.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Minimal number of trees
applied for tree cutting permit
from DENR
Minimal number of trees
applied for tree cutting permit
from DENR
Minimal number of trees
applied for tree cutting permit
from DENR
Minimal number of trees
applied for tree cutting permit
from DENR
Minimal number of trees
applied for tree cutting permit
from DENR
Minimal number of trees
applied for tree cutting permit
from DENR
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
To avoid unnecessary clearing,
mark/delineate areas to be
cleared of vegetation, e.g. by
fencing.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
Rehabilitate cleared areas to their
pre-project conditions, unless
otherwise agreed with the
landowner.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
Re-vegetate construction sites
using local, indigenous species.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit In Progress No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Loss of vegetation due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
Re-vegetate watershed target
sites especially in areas identified
by the Watershed Management
Plan.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit In Progress No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Loss of vegetatio due to:
a. vegetation clearing and
potential trampling of
trucks/equipments beyong project
footprints
Limit any collection of wood for
charcoal to exotic i.e. non-native
species.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
Tree cutting permit In Progress No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Disturbance to wildlife due to:
(a) Construction noise, vibration,
dust, lighting, presence/
movement of people, etc.
(b) flying debris from blasting
Implement measures to mitigate
noise vibration and dust
Implement:
D&B Contractor
Monitor:
PMO
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Disturbance to wildlife due to:
(a) Construction noise, vibration,
dust, lighting, presence/
movement of people, etc.
(b) flying debris from blasting
Implement measures to mitigate
noise vibration and dust
Implement:
D&B Contractor
Monitor:
PMO
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Minimal number of trees
applied for tree cutting permit
from DENR
Record of number of poaching
and illegal trading of wildlife
by workers
Record of number of poaching
and illegal trading of wildlife
by workers
Minimal number of trees
applied for tree cutting permit
from DENR
Minimal number of trees
applied for tree cutting permit
from DENR
Minimal number of trees
applied for tree cutting permit
from DENR
Minimal number of trees
applied for tree cutting permit
from DENR
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase A. Land Disturbance to wildlife due to:
(a) Construction noise, vibration,
dust, lighting, presence/
movement of people, etc.
(b) flying debris from blasting
Implement measures to mitigate
noise vibration and dust
Implement:
D&B Contractor
Monitor:
PMO
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Generationof spoil and spoil
disposal
More than 150,000m3 is expected
to be generated due to tunnelling
works, which is about 190,000 m3
loose volume.
Prepare and implement a plan for
the preparation of the spoil
disposal areas.
Implement:
DED Consultants
D&B Contractor
Monitor:
MWSS
Part of project
(construction) cost
Detailed Engineering
Design (DED) scope of
work
Detailed Engineering
Design Plans
In Progress Spoil disposal, MAPOL quarry, was identified. It has
an approximate land area of 4 hectares, located
approximately 2 kilometers from the source of spoil.
No vegetation survey has been done yet
Geocomposite steel mesh with anchor bolts has
been installed upon portals
Spoil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Generationof spoil and spoil
disposal
More than 150,000m3 is expected
to be generated due to tunnelling
works, which is about 190,000 m3
loose volume.
Minimise the volume of spoil to
be disposed of by re-use in
backfilling of roads, and by
offering as free filling materials to
government projects needing
backfill materials.
Implement:
DED Consultants
D&B Contractor
Monitor:
MWSS
Part of project
(construction) cost
Detailed Engineering
Design (DED) scope of
work
Detailed Engineering
Design Plans
In Progress Spoil disposal, MAPOL quarry, was identified. It has
an approximate land area of 4 hectares, located
approximately 2 kilometers from the source of spoil.
Construction Phase A. Land Generationof spoil and spoil
disposal
More than 150,000m3 is expected
to be generated due to tunnelling
works, which is about 190,000 m3
loose volume.
Disposal area must be confined
to solid ground, of ecological and
agricultural value
Implement:
DED Consultants
D&B Contractor
Monitor:
MWSS
Part of project
(construction) cost
Detailed Engineering
Design (DED) scope of
work
Detailed Engineering
Design Plans
In Progress Spoil disposal, MAPOL quarry, was identified. It has
an approximate land area of 4 hectares, located
approximately 2 kilometers from the source of spoil.
Construction Phase A. Land Generationof spoil and spoil
disposal
More than 150,000m3 is expected
to be generated due to tunnelling
works, which is about 190,000 m3
loose volume.
Disposal area must not occupy
drainage lines and streams, and
create an obstacle to streams or
induced flooding.
Implement:
DED Consultants
D&B Contractor
Monitor:
MWSS
Part of project
(construction) cost
Detailed Engineering
Design (DED) scope of
work
Detailed Engineering
Design Plans
In Progress Geocomposite steel mesh with anchor bolts has
been installed upon portal
Soil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Generationof spoil and spoil
disposal
More than 150,000m3 is expected
to be generated due to tunnelling
works, which is about 190,000 m3
loose volume.
Spoil heaps must be designed
and shaped with stable side
slopes and suitable drainage
Implement:
DED Consultants
D&B Contractor
Monitor:
MWSS
Part of project
(construction) cost
Detailed Engineering
Design (DED) scope of
work
Detailed Engineering
Design Plans
In Progress Geocomposite steel mesh with anchor bolts has
been installed upon portal
Soil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Generationof spoil and spoil
disposal
More than 150,000m3 is expected
to be generated due to tunnelling
works, which is about 190,000 m3
loose volume.
Spoils heaps must be compacted
during the earthworks.
Implement:
DED Consultants
D&B Contractor
Monitor:
MWSS
Part of project
(construction) cost
Detailed Engineering
Design (DED) scope of
work
Detailed Engineering
Design Plans
In Progress Geocomposite steel mesh with anchor bolts has
been installed upon portal
Soil from intake slope has been removed
Installation of threaded rock bolts have been done
Record of number of poaching
and illegal trading of wildlife
by workers
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase A. Land Generationof spoil and spoil
disposal
More than 150,000m3 is expected
to be generated due to tunnelling
works, which is about 190,000 m3
loose volume.
On complete, the spoil heaps
must be covered with the original
top soil from the site and re-
vegetated
Implement:
DED Consultants
D&B Contractor
Monitor:
MWSS
Part of project
(construction) cost
Detailed Engineering
Design (DED) scope of
work
Detailed Engineering
Design Plans
In Progress Geocomposite steel mesh with anchor bolts has
been installed upon portal
Soil from intake slope has been removed
Installation of threaded rock bolts have been done
Construction Phase A. Land Solid Waste Implement an eco-friendly solid
waste management at work sites
and workers’ camp/s, which minimizes, re-uses, segregates
and promptly disposes of
generated solid waste.
MWSS
D&B Contractor
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress Waste onsite are segregated into biodegredable,
non-biodegradable and residuals. There are
designated bins for each type of waste, color coded
and labeled. Waste are collected every Tuesday and
Thursday by Brgy Bigte. CMC and Brgy Bigte has a
service contract for garbage and hauling disposal
from May 2017 to December 2017.
Service Contract of
Brgy Bigte and CMC
for Garbage hauling
and disposal
Date of Issue: May
30, 2017
Expiry Date: Dec 31,
2017
Construction Phase A. Land Hazardous Waste Locate stationary ground storage
for hazardous waste at least 100
m away from water bodies,
raised to min 1 ft above high
flood level. Or, use mobile
storage but should not be parked
near water bodies..
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress Construction of HAZMAT facility is already on
planning stage.
No accredited hazardous waste disposal hauler has
been contacted yet
hazmat temporary
disposal included in
the Industrial Area
site plan (c/o Sergio
and Federico)
Construction Phase A. Land Hazardous Waste Secure storage areas
appropriately. Storage facilities
must be able to contain spillage.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Construction of HAZMAT facility is already on
planning stagehazmat temporary
disposal included in
the Industrial Area
site plan (c/o Sergio
and Federico)
Construction Phase A. Land Hazardous Waste Dispose of waste promptly and
appropriately.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of WorkIn Progress Construction of HAZMAT facility is already on
planning stagehazmat temporary
disposal included in
the Industrial Area Construction Phase A. Land Hazardous Waste The contractor shall be required
to implement an appropriate
hazardous waste management
program.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress no large volume hazmat waste has been generated
yet. Hazmat temporary disposal included in the site
plan. To be constructed
hazmat temporary
disposal included in
the Industrial Area
site plan (c/o Sergio
and Federico)
Construction Phase A. Land Hazardous Waste Storage of oil and grease used
for the maintenance and
operation of heavy equipment
shall be properly built and
maintained, to include bunded
storage for the capacity of the
containers plus 10%, and oil
traps on drainage outfalls.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress no large volume hazmat waste has been generated
yet. Hazmat temporary disposal included in the site
plan. To be constructed
hazmat temporary
disposal included in
the Industrial Area
site plan (c/o Sergio
and Federico)
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
At the active work site:
Mitigating contaminants
Provide adequate sanitation
facilities and water supply at work
sites and workers’ camp. Enforce observance of good
sanitation practices by workers.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant High coliform was reported in segment of surface
water where there are communities alongt the
riverbanks. The construction camp is near the
riverbank and might be a potential contributor to
poor surface water quality.
Construction area at the inlet is a steep slope. Any
accidental chemical spillage can be flushed to Angat
River. Intakes of the 3 existing tunnels in adjacent to
the Tunnel 4 intake site.
Waste onsite are segregated into biodegredable,
non-biodegradable and residuals. There are
designated bins for each type of waste, color coded
and labeled. Waste are collected every Tuesday and
Thursday by Brgy Bigte. CMC and Brgy Bigte has a
service contract for garbage and hauling disposal
from May 2017 to December 2017.
The first water quality sampling was conducted by
CMC last August 2017 with the following
parameters: Temperature, pH, electric conductivity,
tubidity, color, TDS, ORP, dissolved oxygen, BOD,
coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ
paramters using portable water meters started on
October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Implement solid waste
management that minimizes, re-
uses, properly segregates and
promptly and properly disposes
of generated solid wastes.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant High coliform was reported in segment of surface
water where there are communities alongt the
riverbanks. The construction camp is near the
riverbank and might be a potential contributor to
poor surface water quality.
Construction area at the inlet is a steep slope. Any
accidental chemical spillage can be flushed to Angat
River. Intakes of the 3 existing tunnels in adjacent to
the Tunnel 4 intake site.
Waste onsite are segregated into biodegredable,
non-biodegradable and residuals. There are
designated bins for each type of waste, color coded
and labeled. Waste are collected every Tuesday and
Thursday by Brgy Bigte. CMC and Brgy Bigte has a
service contract for garbage and hauling disposal
from May 2017 to December 2017.
The first water quality sampling was conducted by
CMC last August 2017 with the following
parameters: Temperature, pH, electric conductivity,
tubidity, color, TDS, ORP, dissolved oxygen, BOD,
coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ
paramters using portable water meters started on
October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Implement hazardous waste
management that minimizes,
properly segregates and
promptly and properly disposes
of generated hazardous wastes.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Hazmat identified at this stage of construction is
limited to oil, lubricants used by heavy equipment
and vehicles. Most vehicles used are brand new.
Maintenance is done off site.
Hazmat temporary storage included in the site plan
The first water quality sampling was conducted by
CMC last August 2017 with the following
parameters: Temperature, pH, electric conductivity,
tubidity, color, TDS, ORP, dissolved oxygen, BOD,
coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ
paramters using portable water meters started on
October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location
and results on the report).
MPR
Self Monitoring Report
(SMR)
Site Inspection Report
(c/o Jasper Cazenas and
Ricky Latunio)
hazmat temporary disposal
included in the Industrial
Area site plan (c/o Sergio
and Federico)
Photo-documentation
Turbidity Monitoring (c/o
Jasper Cazenas and Ricky
Latunio) dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results from
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Store hazardous construction
materials in appropriately
contained and elevated area and
at least100 m away from surface
water bodies.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Hazmat identified at this stage of construction is
limited to oil, lubricants used by heavy equipment
and vehicles. Most vehicles used are brand new.
Maintenance is done off site.
Hazmat temporary storage included in the site plan
The first water quality sampling was conducted by
CMC last August 2017 with the following
parameters: Temperature, pH, electric conductivity,
tubidity, color, TDS, ORP, dissolved oxygen, BOD,
coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Weekly monitoring of water turbidity and other in-situ
paramters using portable water meters started on
October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location
and results on the report).
MPR
Self Monitoring Report
(SMR)
Site Inspection Report
(c/o Jasper Cazenas and
Ricky Latunio)
hazmat temporary disposal
included in the Industrial
Area site plan (c/o Sergio
and Federico)
Photo-documentation
Turbidity Monitoring (c/o
Jasper Cazenas and Ricky
Latunio) dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results from
CRL - P00075686-01
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Have equipment clearly leaking
oil repaired off-site immediately.
No vehicle/equipment
maintenance, repair and refueling
to be allowed at the sites.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant No equipment reported to have such case
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Treat construction water before
discharge. Install settling pond for
water generated during tunnel
boring. Allow water through
grease trap or oil/collector and/or
filters such as rock filled bags,
block and gravel.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In ProgressHigh coliform was reported in segment of surface
water where there are communities along the
riverbanks. The construction camp is near the
riverbank and might be a potential contributor to
poor surface water quality.
Hazmat identified at this stage of construction is
limited to oil, lubricants used by heavy equipment
and vehicles. Most vehicles used are brand new.
Maintenance is done off site.
Construction of Waste Water Treatment Facility is
on-going.
The first water quality sampling was conducted by
CMC last August 2017 with the following
parameters: Temperature, pH, electric conductivity,
tubidity, color, TDS, ORP, dissolved oxygen, BOD,
coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Water quality in Basin 1 has also been collected and
analyzed last October 2017 with the following
parameters: temperature,TSS, electric conductivity,
turbidity, color and TDS (See sampling location and
results on the report).
Weekly monitoring of water turbidity and other in-situ
paramters using portable water meters started on
October 2017. Testing is done weekly by CMC Envi,
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Implement corrective action,
when trigger thresholds of water
quality are reached.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
CompliantThe first water quality sampling was conducted by
CMC last August 2017 with the following
parameters: Temperature, pH, electric conductivity,
tubidity, color, TDS, ORP, dissolved oxygen, BOD,
coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Water quality in Basin 1 has also been collected and
analyzed last October 2017 with the following
parameters: temperature,TSS, electric conductivity,
turbidity, color and TDS (See sampling location and
results on the report).
Weekly monitoring of water turbidity and other in-situ
paramters using portable water meters started on
October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location
and results on the report)
visual inspection done through photo and video
documentation
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
During construction, the
contractor shall take corrective
action to reduce concentration to
below the standard.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
CompliantThe first water quality sampling was conducted by
CMC last August 2017 with the following
parameters: Temperature, pH, electric conductivity,
tubidity, color, TDS, ORP, dissolved oxygen, BOD,
coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Water quality in Basin 1 has also been collected and
analyzed last October 2017 with the following
parameters: temperature,TSS, electric conductivity,
turbidity, color and TDS (See sampling location and
results on the report).
Weekly monitoring of water turbidity and other in-situ
paramters using portable water meters started on
October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location
and results on the report)
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Mitigating sedimentation
Build cofferdams when
constructing inlet structure
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Not Applicable inlet works not yet started
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Use any combination of perimeter
controls at spoil disposal areas or
stockpiles of aggregate
materials, e.g., silt fences,
sediment basins, sandbags,
earth bern/bund.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
CompliantThe first water quality sampling was conducted by
CMC last August 2017 with the following
parameters: Temperature, pH, electric conductivity,
tubidity, color, TDS, ORP, dissolved oxygen, BOD,
coliform (Total and Fecal) and heavy metals (See
sampling location and results on the report).
Water quality in Basin 1 has also been collected and
analyzed last October 2017 with the following
parameters: temperature,TSS, electric conductivity,
turbidity, color and TDS (See sampling location and
results on the report).
Weekly monitoring of water turbidity and other in-situ
paramters using portable water meters started on
October 2017. Testing is done weekly by CMC Envi,
Health and Safety Officers (See sampling location
and results on the report)
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o Jasper
Cazenas and Ricky
Latunio)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase B. Water Impact on surface water quality
due to/ from:
(a) Contaminants from materials
used and construction activities
and processes
(b) Siltation from soil erosion,
spoil disposal area, drill and
blasting, dewatering excavations,
etc
Minimize / control dewatering or
extraction of tunnel water by
storing and re-using pumped-out
water from the tunnel.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress Water treatment plant is already under construction
Water quality in Basin 1 has also been collected and
analyzed last October 2017 with the following
parameters: temperature,TSS, electric conductivity,
turbidity, color and TDS (See sampling location and
results on the report).
Construction Phase B. Water Extraction of water from the dam
site (inlet) and creek (near the
outlet) to be used as coolant
during construction
Use efficient tunneling technology
that recycles tunnel drainage
water to minimize extraction of
water.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress Water treatment plant is already under construction
Water quality in Basin 1 has also been collected and
analyzed last October 2017 with the following
parameters: temperature,TSS, electric conductivity,
turbidity, color and TDS (See sampling location and
results on the report).
Construction Phase B. Water Impact on groundwater:
(a) deteriorating water quality due
to:
• Silt/sediments• Solid waste• Hazardous materials and waste
In all active work sites:
Site temporary stockpile of
excavated soils in flat areas,
away from main surface drainage
routes, limit to maximum of 2 m
high.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress Stockpile is at minimum especially in Ipo
construction site (Intake).
Spoil management plan has been drafted and
already submitted to MWSS. Spoil disposal area,
MAPOL quarry, was identified. It has an approximate
land area of 4 hectares, located approximately 2
kilometers from the source of spoil.
Construction Phase B. Water Impact on groundwater:
(a) deteriorating water quality due
to:
• Silt/sediments• Solid waste• Hazardous materials and waste
Provide silt fences, silt traps, or
sand bags, at stockpiles of
aggregate materials.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress No silt fences, traps, or sand bags have been
provided yet.
Stockpile is at minimum especially in Ipo
construction site (Intake).
Spoil management plan has been drafted and
already submitted to MWSS. Spoil disposal area,
MAPOL quarry, was identified. It has an approximate
land area of 4 hectares, located approximately 2
kilometers from the source of spoil.
No groundwater monitoring has been done yet
since excavation of tunnel had not started.
Construction Phase B. Water Impact on groundwater:
(a) deteriorating water quality due
to:
• Silt/sediments• Solid waste• Hazardous materials and waste
Dispose of residual soil/spoil as
soon as possible, to the disposal
areas, or as free backfilling
materials for LGU/barangay
roads.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress No silt fences, traps, or sand bags have been
provided yet.
Stockpile is at minimum especially in Ipo
construction site (Intake).
Spoil management plan has been drafted and
already submitted to MWSS. Spoil disposal area,
MAPOL quarry, was identified. It has an approximate
land area of 4 hectares, located approximately 2
kilometers from the source of spoil.
No groundwater monitoring has been done yet
since excavation of tunnel had not started.
DAO 1994- 26A for Philippine
drinking water quality
standards
DAO 1994- 26A for Philippine
drinking water quality
standards
DAO 1994- 26A for Philippine
drinking water quality
standards
Water Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standardsWater Column. Parameters to
characterize the physico-
chemical and biological status
of the water column to include
but not limited to: temperature,
salinity, total suspended
solids, turbidity, dissolved
oxygen and bacteriological
parameters.
Refer to DAO 34 and 35 for
water quality standards
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase B. Water Impact on groundwater:
(a) deteriorating water quality due
to:
• Silt/sediments• Solid waste• Hazardous materials and waste
Avoid stockpiling more
aggregates than necessary
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress No silt fences, traps, or sand bags have been
provided yet.
Spoil management plan to be formulated. Spoil
disposal area, MAPOL quarry, was identified. It has
an approximate land area of 4 hectares, located
approximately 2 kilometers from the source of spoil.
No groundwater monitoring has been done yet
since excavation of tunnel had not started.
Construction Phase B. Water Lowering of water level of wells
nearby communities due to
tunneling, pumping/extracting of
tunnel drainage water
Monitor for potential groundwater
depletion in existing wells in the
vicinity. Provide interim measures
to avoid disrupting water supply
to affected households.
Investigate for proper corrective
action.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Non-Compliant No groundwater monitoring has been done yet
since excavation of tunnel had not started.
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
At the project area, locate
emission sources away from
sensitive receptors, e.g., concrete
batching and rock crushing
plants at least 500m upwind of
sensitive receptors.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress No dust curtains/net has been installed.
Dust supression has been implemented already.
Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level
Monitoring(c/o Jasper
Cazenas and Ricky
Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
In active work sites:
Use of blast curtains / nets to
capture dust from blasting
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Not ApplicableMaintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
suhc as WHO Air Quality
Guidelines Global Update,
2005
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
such as WHO Air Quality
Guidelines Global Update,
2005
DAO 1994- 26A for Philippine
drinking water quality
standards
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
Apply dust suppression
techniques, e.g., watering with
bowsers, sheeting particularly at
Bigte area
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant No dust curtains/net has been installed.
Dust supression has been implemented already.
Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
Water dry unpaved/exposed
surfaces, stockpiles of sand and
excavated materials, at least
twice daily, or as necessary.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress No dust curtains/net has been installed.
Dust supression has been implemented already.
Open burning is not practiced onsite
Speed limit has not yet implemented
Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
Protect aggregate stockpiles with
sheeting to restrict the movement
of dust.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
suhc as WHO Air Quality
Guidelines Global Update,
2005
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
suhc as WHO Air Quality
Guidelines Global Update,
2005
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
suhc as WHO Air Quality
Guidelines Global Update,
2005
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
Throughout the tunnelling
construction period
Continuous monitoring of oxygen
with equipment conforming to BS
EN 50104
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
NC-Time TBM has a built-in air quality monitoring device to
measure oxygen, methane and carbon dioxide
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
Require trucks, particularly those
hauling aggregates, to have
secure covers.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
Limit engine idling to 5 minutes. Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress No dust curtains/net has been installed.
Dust supression has been implemented already.
Open burning is not practiced onsite
Speed limit has not yet implemented
Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level Monitoring
(c/o Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
suhc as WHO Air Quality
Guidelines Global Update,
2005
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
suhc as WHO Air Quality
Guidelines Global Update,
2005
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
suhc as WHO Air Quality
Guidelines Global Update,
2005
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
Prohibit open burning of
vegetation and other waste in the
project area
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Open burning is not practiced onsite
Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
Construction Phase C. Air Deterioration of ambient air
quality due to dust and gas
emissions from:
Earthworks and other construction
processes; tunneling
Stockpiling of aggregates and
spoils, and conveyance of spoils
to disposal areas;
Increased transport activities in
the construction areas and along
Ipo Road;
urning of vegetation and wastes;
and
Operation of mechanical
equipment
Ipo Road, main access road,
other roads in the Project area,
llimit speed of all construction
vehicles to maximum of 40 kph
on the access road to, and
maximum of 30 kph in the site.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level Monitoring
(c/o Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Phase C. Air Noise and vibration in the project
area from excavation activities;
general construction activities;
and vehicle and equipment
operations
Use only equipment that emit
least noise and vibration and are
well maintained.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Trevi Foundations conducted inland drilling for
seismic test
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
such as WHO Air Quality
Guidelines Global Update,
2005
Adopt national standards for
construction sites and
residential areas if available.
Alternatively use internationally
accepted standards such as
WHO.
Maintain national air quality
standards or if these are not
available, internationally
accepted air quality standards
suhc as WHO Air Quality
Guidelines Global Update,
2005
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase C. Air Noise and vibration in the project
area from excavation activities;
general construction activities;
and vehicle and equipment
operations
Use facility layout to minimize
noise propagation e.g. using
topography / existing buildings as
barriers, where possible locate
noisy activities away from local
communities.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress
Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level Monitoring
(c/o Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Phase C. Air Noise and vibration in the project
area from excavation activities;
general construction activities;
and vehicle and equipment
operations
Control noise at source, e.g. low
noise plant, muffling, acoustic
screening, switch off campaigns
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
PPEs (earplugs and earmuffs are used onsite)
Sound Level Monitoring
(c/o Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Phase C. Air Noise and vibration in the project
area from excavation activities;
general construction activities;
and vehicle and equipment
operations
Restrict use of noisy and highly
vibrating equipment from 8AM-
5PM. Necessary overtime work
should: a) not go beyond 9:00PM;
b) observe regulated noise and
vibration levels; c) not use noisy
and highly vibrating equipment;
and d) should be coordinated
with the barangay and affected
households.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level Monitoring
(c/o Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Adopt national standards for
construction sites and
residential areas if available.
Alternatively use internationally
accepted standards such as
WHO.
Adopt national standards for
construction sites and
residential areas if available.
Alternatively use internationally
accepted standards such as
WHO.
Adopt national standards for
construction sites and
residential areas if available.
Alternatively use internationally
accepted standards such as
WHO.
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase C. Air Noise and vibration in the project
area from excavation activities;
general construction activities;
and vehicle and equipment
operations
Manage the ins and outs of
hauling trucks. Spread out the
schedule of material, waste and
spoil transport in the day (off-
peak hours).
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level Monitoring
(c/o Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Phase C. Air Noise and vibration in the project
area from excavation activities;
general construction activities;
and vehicle and equipment
operations
Enforce the rule of no blowing of
horns.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
Sound Level Monitoring
(c/o Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Phase C. Air Noise and vibration in the project
area from excavation activities;
general construction activities;
and vehicle and equipment
operations
Strictly enforce upon workers the
compliance with wearing of ear
mufflers, especially those who
are operating equipment.
Implement: D&B
Contractor
Monitor: OSP-
AWTIP
Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Agreement with CRL Laboratories for air quality
monitoring is now in place (24 August 2017). The air
quality sampling dates will be scheduled once the
Tunnel Excavation starts.
Schedule of Air Quality Monitoring:
A sound level meter was procured by CMC to
monitor the noise level during construction period as
one of the requirements of ADB and DENR. Noise
monitoring started on 28 October 2017.
PPEs (earplugs and earmuffs are used onsite)
Sound Level Monitoring
(c/o Jasper Cazenas and
Ricky Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Phase D. The People Traffic due to:
(a) inadequate capacity of Ipo
Road (access road)
(b) expected volume of truck
movement
Institute prior coordination with
the Barangay and Municipality for
the formulation of a traffic
management and safety plan and
for clearing of structures
encroaching into access road
ROW.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Adopt national standards for
construction sites and
residential areas if available.
Alternatively use internationally
accepted standards such as
WHO.
Adopt national standards for
construction sites and
residential areas if available.
Alternatively use internationally
accepted standards such as
WHO.
Zero road accident and related
incidents
Adopt national standards for
construction sites and
residential areas if available.
Alternatively use internationally
accepted standards such as
WHO.
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase D. The People Traffic due to:
(a) inadequate capacity of Ipo
Road (access road)
(b) expected volume of truck
movement
Prior to construction, clear
easement of encroaching
structures, most of them being
temporary.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Construction Phase D. The People Traffic due to:
(a) inadequate capacity of Ipo
Road (access road)
(b) expected volume of truck
movement
Strategically post billboards
informing the public about the
expected increase in volume of
traffic in the influence area due to
Project implementation. Post at
least two weeks prior to
mobilization.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Bulletin boards for IEC purpose were installed in the
barangay halls of Brgy Bigte and San Mateo.CMC. Request for
Permission to Install
Bulletin Boad.
Barangay San
Mateo, Norzagaray,
Bulacan. June 6,
2017
CMC. Request for
Permission to Install
Bulletin Boad.
Barangay Bigte,
Norzagaray, Bulacan.
June 20, 2017
Construction Phase D. The People Traffic due to:
(a) inadequate capacity of Ipo
Road (access road)
(b) expected volume of truck
movement
Coordinate with the Barangay for
assistance in traffic management.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Hauling truck, heavy equipment and other
construction related machines are expected at the
construction sites and associated road such as Ipo
Road during the construction
Construction Phase D. The People Traffic due to:
(a) inadequate capacity of Ipo
Road (access road)
(b) expected volume of truck
movement
Strategically post traffic flagmen
along Ipo Road, equipped with
two-way radio.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Construction Phase D. The People Traffic due to:
(a) inadequate capacity of Ipo
Road (access road)
(b) expected volume of truck
movement
Post sufficiently legible
(reflectorized) traffic safety notice
and signage at strategic locations
along the entire stretch of the
access road.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Traffic and safety signage were installed onsite
Construction Phase D. The People Traffic due to:
(a) inadequate capacity of Ipo
Road (access road)
(b) expected volume of truck
movement
Limit speed to 40 kph along Ipo
Road, 20 kph at highly populated
sections of Ipo Road, and 30 kph
at construction sites and unpaved
haulage roads.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Speed limit is not implemented yet.
Construction Phase D. The People Potential damage of existing
roads used as access roads due
to movement of heavy equipment
and vehicles
Coordinate with DPWH
regarding the use of Ipo Road.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Construction Phase D. The People Potential damage of existing
roads used as access roads due
to movement of heavy equipment
and vehicles
Restore access roads within the
MWSS compound to the pre-
construction condition or better.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant
Zero road accident and related
incidents
Zero road accident and related
incidents
Zero road accident and related
incidents
Zero road accident and related
incidents
Zero road accident and related
incidents
Zero road accident and related
incidents
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase D. The People Restricted access to the existing
fish landing sites in Sitio
Consultant (identified area as the
Contractor’s Work Area) and boat landing at Sitio Ipo
Inform affected communities
living in Ipo Watershed on the
impact of construction works on
transportation and consult them
for the best alternative route.
Have alternative route and fish
and boat landing sites ready for
use prior to commencement of
construction activities.
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Wire mesh has been installed for slope protection
Safety signage has been installed
Construction Phase D. The People Restricted access to the existing
fish landing sites in Sitio
Consultant (identified area as the
Contractor’s Work Area) and boat landing at Sitio Ipo
Provide alternative access to
school for school children and
residents
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress
Construction Phase D. The People Restricted access to the existing
fish landing sites in Sitio
Consultant (identified area as the
Contractor’s Work Area) and boat landing at Sitio Ipo
Establish alternate boat landing
at the mouth of Sapang Munti
River
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Alternate boat have been provided for the affected
residents
Construction Phase D. The People Restricted access to the existing
fish landing sites in Sitio
Consultant (identified area as the
Contractor’s Work Area) and boat landing at Sitio Ipo
Install soil entrapment nets and
coffer dams to contain soil
erosion at dam site
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
In Progress
Construction Phase D. The People Restricted access to the existing
fish landing sites in Sitio
Consultant (identified area as the
Contractor’s Work Area) and boat landing at Sitio Ipo
Provide clear signage of
alternative routes
D&B Contractor Part of project
(construction) cost
D&B Contractor Scope
of Work
D&B Contractor’s C-EMP
Compliant Signage has been posted already
Construction Phase D. The People Community health and safety
hazards - Potential health risks for
persons with chronic disease
such as asthma, and other
respiratory diseases due dust
pollution within the vicinity of the
construction site and along road
side
Secure project area, including
Associated facilities particularly
the storage for explosives, from
unauthorized entry.
CompliantUnauthorized entry signage have been installed
onsite
Grievance procedure and scheme to be formulated
UXO survey and clearing have been done by hired
demining company, Vourvon Electronica Marketing.
UXO were retrieved and surrendered to the
Philippine Army.
Clearance
Certification
Issued by: Vourvon
Electronica
Marketing
Issued on: May 29,
2017
Certification of
Receipt of
Unexploded
Explosives
Issued by: Alpha
Aggressor Company
Issued on: July 17,
2017
Construction Phase D. The People Community health and safety
hazards - Potential health risks for
persons with chronic disease
such as asthma, and other
respiratory diseases due dust
pollution within the vicinity of the
construction site and along road
side
Implement measures to mitigate
impacts on air and water quality,
noise, traffic.
In Progress A complaint was received on July 18,2017 by CMC
which was filed by residents of Calle Onse (adjacent
to the Industrial Area in Brgy Bigte regarding the
generation of dust and mud along the road. This
case was investigated by CMC H&S together with
representative of Calle Onse. CMC already made
provision of a canal across the Industrial Area. The
problem is not attributed solely to CMC but residents
addressed grievance to CMC hoping to get some
help. The case was closed and H&S has the detailed
documentation.
Grievance report (c/o
Jasper Cazenas and
Ricky Latunio)
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase D. The People Community health and safety
hazards - Potential health risks for
persons with chronic disease
such as asthma, and other
respiratory diseases due dust
pollution within the vicinity of the
construction site and along road
side
Provide mechanism to reduce
dust /other pollutants (ie. water
spraying on the road, timing of
blasting during day time, etc.)
In Progress no grievance case recorded on this regard from
July to December 2017
Construction Phase D. The People Community health and safety
hazards - Potential health risks for
persons with chronic disease
such as asthma, and other
respiratory diseases due dust
pollution within the vicinity of the
construction site and along road
side
People with impaired health/risks
wear masks and other protective
device
Cannot Document Compliance
Construction Phase D. The People Workers’ health and safety hazard Mitigating impacts from blasting:
(a) Include H&S protocols in the
C-EMP on the safe procedures in
the storage, handling and use of
explosives during construction.
Compliant Health and Safety Officers have been hired.
Construction Phase D. The People Workers’ health and safety hazard (b) Control the blasting by using
small charges. Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (c) Evacuation procedures in
tunnel prior to setting charges. NC-Time
Construction Phase D. The People Workers’ health and safety hazard (d) Set up a sufficiently equipped
emergency first-response and
health care team, linked to an
ultimate response team.
Compliant Health and safety staff have been hired by CMC
Health and safety plan has been formulated
Standby doctor and nurse are present onsite
Ambulance, first aid kits, and fire extinguishers have
been provided
Personal Protective Equipment (PPE) are given to
the staff. Contractors’ staff are REQUIRED to use PPE onsite at all times.
CMC Health and
Safety Plan
Construction Phase D. The People Workers’ health and safety hazard (e) Provide safe housing with
adequate basic services. Compliant Housing was provided for CMC employees
Construction Phase D. The People Workers’ health and safety hazard (f) Enforce use of protective
wears when at work. Compliant
Construction Phase D. The People Workers’ health and safety hazard (g) Conduct pre-mobilization
orientation workshop on health
and safety and emergency
response and evacuation
procedures
Compliant
Construction Phase D. The People Workers’ health and safety hazard Handling and storage of
explosives:
(a) Magazine storage should be
far from residential areas, roads,
transmission lines, dams and
their appurtenant works.
Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (b) Site should be well-drained
and sloping, accessible by road.
At least 100 m from overhead
power transmission lines.
Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (c) Detonators should not be
stored together with explosives.Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (d) Maintenance should follow the
prescribed instructions for the
explosives.
Not Applicable
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Construction Phase D. The People Workers’ health and safety hazard (e) Inside of all magazines should
be kept thoroughly clean.Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (f) Cigarettes and matches
should not be taken into
Explosives should be used
according to date of manufacture
magazines. Its keeper should
ensure this.
Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (g) Explosive boxes should be of
wood or soft non-ferrous metal,
e.g., brass, copper.
Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (h) Magazine should be securely
locked, when not attended.Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (i) Detailed records of outgoing
and incoming stocks should be
kept
Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (j) Magazines should be kept free
from bushes and vegetation.Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (k) Empty boxes, loose packing
material or cotton waste should
not be kept on the magazine
premises.
Not Applicable
Construction Phase D. The People Workers’ health and safety hazard (l) Do not open magazines during
or on the approach of a
thunderstorm. No person should
remain in the vicinity of the
magazine during such storm
Not Applicable
Construction Phase D. The People Public safety related to future
development and activities along
the ROW
MWSS must secure the ROW.
Existing above ground
infrastructure along ROW should
be limited. The public must not
be allowed to encroach onto the
ROW by constructing any
buildings or farming the land.
MWSS Not Applicable
Operation Phase B. The Water Changes in hydrology along
Angat River during dry season
During the operation phase, flows
shall be monitored downstream
of Ipo dam.
Concession agrrement In Progress flows at the Ipo Reservoir is being measured on a
daily basis
flowrate of water to
Ipo (c/c MWSS)
Operation Phase B. The Water Changes in hydrology along
Angat River during dry season
As practice in the Philippines, Ipo
dam should maintain 10%
riparian flow downstream of Ipo
dam. This flow aims to allow
migration of fish species and to
maintain natural characteristics of
the river downstream of Ipo dam.
Concession agrrement Compliant
Operation Phase B. The Water Public safety related to future
development and activities along
the ROW
MWSS must secure the ROW.
Existing above ground
infrastructure along ROW should
be limited. The public must not
be allowed to encroach onto the
ROW by constructing any
buildings or farming the land.
MWSS
CPF (represented
by 2 water
concessionaires -
MWCI and MWSI)
Part of project
maintenance cost
LGU/ MWSS/
Concessionaires ‘ responsibility
Concession Agreement
Compliant
Operation Phase B. The Water Security of tunnel 4
Potential encroachment of
informal settlers along the 8
ROW, 6.4 Km alignment
Conduct IEC on how to ensure
security of tunnel 4
Concessionaires
/MWSS/
barangay
LGU/ MWSS/
Concessionaires ‘ responsibility
Concession Agreement
In Progress MWSS has priliminary discussion with CPF on the
securing of Tunnel ROW.
AWTIP Monitoring Matrix - EIA
No. Project Phase Environmental
Component likely to be
affected
Potential Impact Options for prevention or
mitigation or enhancement
Responsible
entity
Cost Guarantee/ financial
arrangements
Compliance Status Remarks
Relevant
Documents
Performance Indicator
Operation Phase B. The Water Security of tunnel 4
Potential encroachment of
informal settlers along the 8
ROW, 6.4 Km alignment
Continuous monitoring of the
ROW alignment for potential
encroachers
Concessionaires
/MWSS/
barangay
LGU/ MWSS/
Concessionaires ‘ responsibility
Concession Agreement
In Progress
Operation Phase B. The Water Security of tunnel 4
Potential encroachment of
informal settlers along the 8
ROW, 6.4 Km alignment
Fencing of the 60m ROW where
aqueduct 4 is located
Incentives /imposition of penalty
for encroachers
Concessionaires
/MWSS/
barangay
LGU/ MWSS/
Concessionaires ‘ responsibility
Concession Agreement
Compliant
AWTIP Monitoring Matrix - EIA
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
Documents
Implement Monitor
Pre-construction Required
permits/clearance
Obtain the following prior to
Notice of Award:
a. ECC
Php 500,000.00 MWSS Permits/clearances
obtained prior to
Notice of Award
Employer's
requirement
documents
Compliant ECC was issued on April 7,
2017
Permit:
Environmental
Compliance
Certifcate (ECC)
Permit #:
EMB.ECC-CO-
1508-002
Date of Issue: Apr
7, 2017
Expiry Date: Apr
7, 2022
Pre-construction Required
permits/clearance
b. MOA between DENR RO3,
NPC and MWSS
None MWSS Permits/clearances
obtained prior to
Notice of Award
Employer's
requirement
documents
Compliant Land use permit from NPC is
secured on July 17,2017.
Permit: Land Use
Permit
Permit #: 2017-
LUP-03
Date of Issue: July
17, 2017
Expiry Date: July
14, 2042
Agency: National
Power Corporation
(NPC)
Pre-construction Required
permits/clearance
c. Permit to cut tree Part of construction cost Part of
construction
cost
Permits/clearances
obtained prior to
Notice of Award
Compliant Tree Cutting Permit – from Community Environment and
Natural Resources (DENR-
CENRO) have been secured.
Tree cutting
Permits issued by
Community
Environment and
Natural Resources
(DENR-CENRO)
a. Date of Issue:
July 10, 2017
Expiry Date: July
25, 2017
b. Date of Issue:
July 25, 2017
Expiry Date: July
30, 2017
c. Date of Issue:
August 16, 2017
Expiry Date:
August 31, 2017
d. Date of Issue:
August 24, 2017
Expiry Date:
August 31, 2017
e. Date of Issue:
September 11,
2017
Expiry Date:
September 18,
2017
f. Date of Issue:
September 23,
2017
Responsible
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Pre-construction Required
permits/clearance
c. Permit to Operate Part of construction cost Part of
construction
cost
Permits/clearances
obtained prior to
Notice of Award
Employer's
requirement
documents
Compliant Permit to operate has been
secured on October 20, 2017
Permit: Permit to
Operate
Permit #: FLA-17J-
03BU-550 (1 Unit
20 KW) Standby
Genset
Permit #:
17J03BU-549 (1
unit 40KW
Standby GenSet)
Date of Issue:
October 20, 2017
Expiry Date:
October 28, 2017Pre-construction Required
permits/clearance
d. Permit to use explosives for
construction
Part of construction cost Part of
construction
cost
Permits/clearances
obtained prior to
Notice of Award
Employer's
requirement
documents
Not Applicable Not applicable. Tunnel boring
machine will be used.
Pre-construction Prepare relevant
communities
Conduct intensive social and
environmental awareness
program at least one month
prior to Notice of Award,
covering: (i) communicable/
transmittable diseases that may
be brought with the entry of
workers; (ii) potential social
conflicts between communities
and workers; (iii) other health
and safety hazards and
impacts during construction and
during maintenance and repair
of completed works;
and (iv) the grievance redress
mechanism.
Included in OSP-AWTIP'a
budget
OSP-AWTIP
Affected
barangays
In Progress Bulletin boards for IEC purpose
were installed in the barangay
halls of Brgy Bigte and San
Mateo.
CMC. Request for
Permission to
Install Bulletin
Boad. Barangay
San Mateo,
Norzagaray,
Bulacan. June 6,
2017
CMC. Request for
Permission to
Install Bulletin
Boad. Barangay
Bigte, Norzagaray,
Bulacan. June 20,
2017
CMC. Request for
Permission to
Install Bulletin
Boad. Ipo
Elementary
School,
Norzagaray,
Bulacan. August
7, 2017
Pre-construction Ensure
environmentally
responsible
procurement
Include an SPS-compliant EMP
in the bidding documents.
Not applicable OSP-AWTIP SPS-compliant EMP
included in the bidding
documents
Compliant see Bidding Document General
Conditons of the Contract
(Section 6 and Employer's
Requirment (Section 7)
General
Conditions of the
Contract (AWTIP-
ICB-CW001)
Section 6
Employers
Requirement and
Section 7 General
Conditions of the
Contract
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Pre-construction Append EMP to the Contract for
basis in the preparation of the C-
EMP
OSP-AWTIP EMP appended in the
Contract
Compliant see General Conditons of the
Contract (Section 6 and
Employer's Requirment
(Section 7)
General
Conditions of the
Contract (AWTIP-
ICB-CW001)
Section 6
Employers
Requirement and
Section 7 General
Conditions of the
Contract
Pre-construction In Contract, require D&B
Contractor to submit monthly
and semi-annual environmental
monitoring report
OSP-AWTIP Requirement stated in
the contract
Compliant see General Conditons of the
Contract (Section 6 and
Employer's Requirment
(Section 7)
General
Conditions of the
Contract (AWTIP-
ICB-CW001)
Section 6
Employers
Requirement and
Section 7 General
Conditions of the
Contract
Pre-construction Stipulate in the Contract the tie-
up of progress payment and
collection of performance bond
with the performance in C-EMP
implementation
OSP-AWTIP Stipulation in the
contract
Compliant see General Conditons of the
Contract (Section 6 and
Employer's Requirment
(Section 7)
AWTIP Contract
Agreement signed
2016 May 25G.
Esquivel (MWSS)
and A Ciamei
(CMC)
General
Conditions of the
Contract (AWTIP-
ICB-CW001)
Section 6
Employers
Requirement and
Section 7 General
Conditions of the
Contract
Pre-construction Prepare C-EMP that addresses
as minimum the requirements of
the EMP. A final construction
spoil management plan will be
prepared by Contractor for
endorsement / approval by both
MWSS and ADB. The plan
should be included in the C-
EMP to be prepared by D&B
Contractor.
D&B
Contractor
Presence of a C-EMP
based on EMP
Compliant CEMMP has been submitted by
CMC to MWSS on 2017 July 7.
CEMMP, June
2017
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Pre-construction Evaluate the C-EMP
quantitatively and qualitatively
against the EMP
OSP-AWTIP Evaluation undertaken
quantitatively and
qualitatively
Compliant CEMMP has been approved by
MWSS. Please see letter of
MWSS to CMC dated 15
August 2017
CEMMP:
Contractor's
Environmental
Management and
Monitoring Plan.
MWSS letter to
CMC dated 15
August 2017
Pre-construction Clear the C-EMP before the
start of any activity/work on site
or establishment of any
construction-related facility
onsite by D&B Contractor
ADB C-EMP cleared prior to
start of any
mobilization activity on
site by D&B Contractor
Compliant CEMMP has been approved by
MWSS. Please see letter of
MWSS to CMC dated 15
August 2017
CEMMP:
Contractor's
Environmental
Management and
Monitoring Plan.
MWSS letter to
CMC dated 15
August 2017
Pre-construction Endorsement/ approval of the
final construction spoil
management plan, which is part
of CEMP
ADB C-EMP cleared prior to
start of any
mobilization activity on
site by D&B Contractor
In Progress Spoil disposal management is
included in the CEMMP. A
separate document on Spoil
Disposal Procedure is in place.
Copy may be obtained from
CMC
CMC. Spoil
Disposal
Procedure
Construction Physical (Land)
Environment
Soil and erosion
due to:‐ soil disturbance‐ vegetation
clearing
Location: Inlet structure and
relevant work sites
Confine soil disturbance and/or
vegetation clearing to pre-
defined and planned area that
includes project footprint and
needed easements
Part of construction cost D&B
Contractor
OSP-AWTIP Compliant No vegetation survey has been
done yet
Geocomposite steel mesh with
anchor bolts has been installed
upon portals
Spoil from intake slope has
been removed
Installation of threaded rock
bolts have been doneConstruction Physical (Land)
Environment
Soil and erosion
due to:‐ soil disturbance‐ vegetation
clearing
Stabilize exposed soils with
temporary seeding, mulches,
mats, non chemical-based soil
binders.
Part of construction cost D&B
Contractor
OSP-AWTIP CEMP Compliant No vegetation survey has been
done yet
Geocomposite steel mesh with
anchor bolts has been installed
upon portals
Spoil from intake slope has
been removed
Installation of threaded rock
bolts have been doneConstruction Physical (Land)
Environment
Soil and erosion
due to:‐ soil disturbance‐ vegetation
clearing
Protect slopes with any one or
combination of bonded fiber
matrices, erosion control
blankets, silt fence, fiber rolls,
and keeping stormwater off the
slopes through diversion
channels and/or berms.
Part of construction cost D&B
Contractor
OSP-AWTIP CEMP Compliant No vegetation survey has been
done yet
Geocomposite steel mesh with
anchor bolts has been installed
upon portals
Spoil from intake slope has
been removed
Installation of threaded rock
bolts have been done
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Physical (Land)
Environment
Soil and erosion
due to:‐ soil disturbance‐ vegetation
clearing
Re-vegetate disturbed
soils/slopes as soon as possible
after completion of the
construction works.
Part of construction cost D&B
Contractor
OSP-AWTIP CEMP Compliant No vegetation survey has been
done yet
Geocomposite steel mesh with
anchor bolts has been installed
upon portals
Spoil from intake slope has
been removed
Installation of threaded rock
bolts have been doneConstruction Physical (Land)
Environment
Soil and erosion
due to:‐ soil disturbance‐ vegetation
clearing
Replacing vegetation that died
during the defects liability
period.
Part of construction cost D&B
Contractor
OSP-AWTIP CEMP Compliant No vegetation survey has been
done yet
Geocomposite steel mesh with
anchor bolts has been installed
upon portals
Spoil from intake slope has
been removed
Installation of threaded rock
bolts have been doneConstruction Physical (Land)
Environment
Soil and erosion
due to:‐ soil disturbance‐ vegetation
clearing
At the active work sites,
Provide temporary drainage with
sedimentation tank or filters
such as block and gravel, prior
to discharge to watercourses
Part of construction cost D&B
Contractor
OSP-AWTIP CEMP Compliant No vegetation survey has been
done yet
Geocomposite steel mesh with
anchor bolts has been installed
upon portals
Spoil from intake slope has
been removed
Installation of threaded rock
bolts have been doneConstruction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
At the active work sites
Mitigating contaminants
Provide adequate sanitation
facilities and water supply at
work sites and workers’ camp. Enforce observance of good
sanitation practices by workers.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Compliant The first water quality sampling
was conducted by CMC last
August 2017 with the following
parameters: Temperature, pH,
electric conductivity, tubidity,
color, TDS, ORP, dissolved
oxygen, BOD, coliform (Total
and Fecal) and heavy metals
(See sampling location and
results on the report).
Water quality in Basin 1 has
also been collected and
analyzed last October 2017
with the following parameters:
temperature,TSS, electric
conductivity, turbidity, color and
TDS (See sampling location
and results on the report).
Weekly monitoring of water
turbidity and other in-situ
paramters using portable water
meters started on October
2017. Testing is done weekly
by CMC Envi, Health and
Safety Officers (See sampling
location and results on the
report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o
Jasper Cazenas
and Ricky Latunio)
Photo-
documentation
Turbidity
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Implement solid waste
management that minimizes, re-
uses, properly segregates and
promptly and properly disposes
of generated solid wastes.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Compliant High coliform was reported in
segment of surface water where
there are communities alongt
the riverbanks. The
construction camp is near the
riverbank and might be a
potential contributor to poor
surface water quality.
Construction area at the inlet is
a steep slope. Any accidental
chemical spillage can be
flushed to Angat River. Intakes
of the 3 existing tunnels in
adjacent to the Tunnel 4 intake
site.
Waste onsite are segregated
into biodegredable, non-
biodegradable and residuals.
There are designated bins for
each type of waste, color coded
and labeled. Waste are
collected every Tuesday and
Thursday by Brgy Bigte. CMC
and Brgy Bigte has a service
contract for garbage and
hauling disposal from May 2017
to December 2017.
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o
Jasper Cazenas
and Ricky Latunio)
Photo-
documentation
Turbidity
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Implement hazardous waste
management that minimizes,
properly segregates and
promptly and properly disposes
of generated hazardous wastes.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Compliant
Hazmat identified at this stage
of construction is limited to oil,
lubricants used by heavy
equipment and vehicles. Most
vehicles used are brand new.
Maintenance is done off site.
Hazmat temporary storage
included in the site plan
The first water quality sampling
was conducted by CMC last
August 2017 with the following
parameters: Temperature, pH,
electric conductivity, tubidity,
color, TDS, ORP, dissolved
oxygen, BOD, coliform (Total
and Fecal) and heavy metals
(See sampling location and
results on the report).
Weekly monitoring of water
turbidity and other in-situ
paramters using portable water
meters started on October
2017. Testing is done weekly
by CMC Envi, Health and
Safety Officers (See sampling
location and results on the
MPR
Self Monitoring Report
(SMR)
Site Inspection Report
(c/o Jasper Cazenas
and Ricky Latunio)
hazmat temporary
disposal included in the
Industrial Area site
plan (c/o Sergio and
Federico)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Store hazardous construction
materials in appropriately
contained and elevated area
and at least100 m away from
surface water bodies.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Compliant
Hazmat identified at this stage
of construction is limited to oil,
lubricants used by heavy
equipment and vehicles. Most
vehicles used are brand new.
Maintenance is done off site.
Hazmat temporary storage
included in the site plan
The first water quality sampling
was conducted by CMC last
August 2017 with the following
parameters: Temperature, pH,
electric conductivity, tubidity,
color, TDS, ORP, dissolved
oxygen, BOD, coliform (Total
and Fecal) and heavy metals
(See sampling location and
results on the report).
Weekly monitoring of water
turbidity and other in-situ
paramters using portable water
meters started on October
2017. Testing is done weekly
by CMC Envi, Health and
Safety Officers (See sampling
location and results on the
MPR
Self Monitoring Report
(SMR)
Site Inspection Report
(c/o Jasper Cazenas
and Ricky Latunio)
hazmat temporary
disposal included in the
Industrial Area site
plan (c/o Sergio and
Federico)
Photo-documentation
Turbidity Monitoring
(c/o Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Have equipment clearly leaking
oil repaired off-site immediately.
No vehicle/equipment
maintenance, repair and
refuelling to be allowed at the
sites.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Compliant No equipment reported to have
such case
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Treat construction water before
discharge. Install settling pond
for water generated during
tunnel boring. Allow water
through grease trap or
oil/collector and/or filters such as
rock filled bags, block and
gravel.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
In ProgressHigh coliform was reported in
segment of surface water where
there are communities along
the riverbanks. The
construction camp is near the
riverbank and might be a
potential contributor to poor
surface water quality.
Hazmat identified at this stage
of construction is limited to oil,
lubricants used by heavy
equipment and vehicles. Most
vehicles used are brand new.
Maintenance is done off site.
Construction of Waste Water
Treatment Facility is on-going.
The first water quality sampling
was conducted by CMC last
August 2017 with the following
parameters: Temperature, pH,
electric conductivity, tubidity,
color, TDS, ORP, dissolved
oxygen, BOD, coliform (Total
and Fecal) and heavy metals
(See sampling location and
results on the report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o
Jasper Cazenas
and Ricky Latunio)
Photo-
documentation
Turbidity
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Implement corrective action,
when trigger thresholds of water
quality are reached.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Compliant The first water quality sampling
was conducted by CMC last
August 2017 with the following
parameters: Temperature, pH,
electric conductivity, tubidity,
color, TDS, ORP, dissolved
oxygen, BOD, coliform (Total
and Fecal) and heavy metals
(See sampling location and
results on the report).
Water quality in Basin 1 has
also been collected and
analyzed last October 2017
with the following parameters:
temperature,TSS, electric
conductivity, turbidity, color and
TDS (See sampling location
and results on the report).
Weekly monitoring of water
turbidity and other in-situ
paramters using portable water
meters started on October
2017. Testing is done weekly
by CMC Envi, Health and
Safety Officers (See sampling
location and results on the
report).
visual inspection done through
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o
Jasper Cazenas
and Ricky Latunio)
Photo-
documentation
Turbidity
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
During construction, the
contractor shall take corrective
action to reduce concentration
to below the standard.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Compliant The first water quality sampling
was conducted by CMC last
August 2017 with the following
parameters: Temperature, pH,
electric conductivity, tubidity,
color, TDS, ORP, dissolved
oxygen, BOD, coliform (Total
and Fecal) and heavy metals
(See sampling location and
results on the report).
Water quality in Basin 1 has
also been collected and
analyzed last October 2017
with the following parameters:
temperature,TSS, electric
conductivity, turbidity, color and
TDS (See sampling location
and results on the report).
Weekly monitoring of water
turbidity and other in-situ
paramters using portable water
meters started on October
2017. Testing is done weekly
by CMC Envi, Health and
Safety Officers (See sampling
location and results on the
report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o
Jasper Cazenas
and Ricky Latunio)
Photo-
documentation
Turbidity
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL - Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Mitigating sedimentation
Build cofferdams when
constructing inlet structure
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Not Applicable inlet works not yet started
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Use any combination of
perimeter controls at spoil
disposal areas or stockpiles of
aggregate materials, e.g., silt
fences, sediment basins,
sandbags, earth bern/bund.
Part of project
development cost
D&B
Contractor
OSPAWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
Compliant The first water quality sampling
was conducted by CMC last
August 2017 with the following
parameters: Temperature, pH,
electric conductivity, tubidity,
color, TDS, ORP, dissolved
oxygen, BOD, coliform (Total
and Fecal) and heavy metals
(See sampling location and
results on the report).
Water quality in Basin 1 has
also been collected and
analyzed last October 2017
with the following parameters:
temperature,TSS, electric
conductivity, turbidity, color and
TDS (See sampling location
and results on the report).
Weekly monitoring of water
turbidity and other in-situ
paramters using portable water
meters started on October
2017. Testing is done weekly
by CMC Envi, Health and
Safety Officers (See sampling
location and results on the
report).
MPR
Self Monitoring
Report (SMR)
Site Inspection
Report (c/o
Jasper Cazenas
and Ricky Latunio)
Photo-
documentation
Turbidity
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
dated:
- Oct 28, 2017
- Nov 4, 2017
- Nov 11, 2017
- Nov 17, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 8, 2017
Laboratory results
from CRL -
P00075686-01
Construction Water Impact on surface water
quality due to/ from:‐ Contaminants
from materials
used and
construction
activities and
processes
- Siltation from soil
erosion, spoil
disposal area,
drill and blasting,
dewatering
excavations, etc
Minimize / control dewatering or
extraction of tunnel water by
storing and re-using pumped
out water from the tunnel.
Part of project
development cost
D&B
Contractor
OSP-AWTIP Water column.
Parameters to
characterize the
physicochemical and
biological status of the
water column to include
but not limited to:
temperature, salinity,
total suspended solids,
turbidity, dissolved
oxygen and
bacteriological
parameters.
Refer to DAO 34 and 35
for water quality
standards
In Progress Water treatment plant is already
under construction
Water quality in Basin 1 has
also been collected and
analyzed last October 2017
with the following parameters:
temperature,TSS, electric
conductivity, turbidity, color and
TDS (See sampling location
and results on the report).
Construction Water Extraction of water from
dam site (inlet) and creek
(near the outlet) to be used
as coolant during
construction
Use efficient tunnelling
technology that recycles tunnel
drainage water to minimize
extraction of water
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP If significant amount of
water is to be used, a
permit from the National
Water Resources
Board may be necessary
DAO 34 and 35 for water
quality standards
In Progress Water treatment plant is already
under construction
Water quality in Basin 1 has
also been collected and
analyzed last October 2017
with the following parameters:
temperature,TSS, electric
conductivity, turbidity, color and
TDS (See sampling location
and results on the report).
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Water Impact on groundwater
a) Deteriorating
water quality due
to:
- Silt/ sediments
- Solid waste
- Hazardous
materials
In all active work sites:
Site temporary stockpile of
excavated soils in flat areas,
away from main surface
drainage routes, limit to
maximum of 2m high
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP DAO 1994- 26A for
Philippine drinking water
quality standards
In Progress No silt fences, traps, or sand
bags have been provided yet.
Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
2 kilometers from the source of
spoil.
No groundwater monitoring has
been done yet since excavation
of tunnel had not started.
Construction Water Impact on groundwater
a) Deteriorating
water quality due
to:
- Silt/ sediments
- Solid waste
- Hazardous
materials
Provide silt fences, silt traps, or
sand bags, at stockpiles of
aggregate materials
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP DAO 1994- 26A for
Philippine drinking water
quality standards
In Progress No silt fences, traps, or sand
bags have been provided yet.
Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
2 kilometers from the source of
spoil.
No groundwater monitoring has
been done yet since excavation
of tunnel had not started.
Construction Water Impact on groundwater
a) Deteriorating
water quality due
to:
- Silt/ sediments
- Solid waste
- Hazardous
materials
Dispose residual soil/spoil as
soon as possible to the disposal
areas or as free
backfilling materials for
LGU/barangay roads
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP DAO 1994- 26A for
Philippine drinking water
quality standards
In Progress No silt fences, traps, or sand
bags have been provided yet.
Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
2 kilometers from the source of
spoil.
No groundwater monitoring has
been done yet since excavation
of tunnel had not started.
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Water Impact on groundwater
a) Deteriorating
water quality due
to:
- Silt/ sediments
- Solid waste
- Hazardous
materials
Avoid stockpiling more
aggregates than necessary
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP DAO 1994- 26A for
Philippine drinking water
quality standards
In Progress No silt fences, traps, or sand
bags have been provided yet.
Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
2 kilometers from the source of
spoil.
No groundwater monitoring has
been done yet since excavation
of tunnel had not started.
Construction Water b. lowering of water
level of wells in nearby
communities due to
tunnelling,
pumping/extracting
of tunnel drainage water
Monitor for potential
groundwater depletion in
existing wells in the vicinity.
Provide interim measures to
avoid disrupting water supply to
affected households. Investigate
for proper
corrective action.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Non-Compliant No groundwater monitoring
has been done yet since
excavation of tunnel had not
started.
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
At the project area, locate
emission sources away from
sensitive receptors, e.g.
concrete batching and rock
crushing plants at least 500m
upwind of sensitive receptors.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2005
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress No dust curtains/net has been
installed.
Dust supression has been
implemented already.
Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
In active work sites:
Use of blast curtains / nets to
capture dust from blasting
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2006
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Not Applicable
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
Apply dust suppression
techniques, e.g., watering with
bowsers, sheeting particularly at
Bigte area
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2007
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant No dust curtains/net has been
installed.
Dust supression has been
implemented already.
Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
Water dry unpaved/exposed
surfaces, stockpiles of sand and
excavated materials, at least
twice daily, or as necessary.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2008
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant No dust curtains/net has been
installed.
Dust supression has been
implemented already.
Open burning is not practiced
onsite
Speed limit has not yet
implemented
Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
Protect aggregate stockpiles
with sheeting to restrict the
movement of dust.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2009
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
Use of blast curtains / nets to
capture dust from blasting.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2010
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Not Applicable
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
Limit engine idling to 5 minutes. Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2012
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress
Speed limit has not yet
implemented
Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky
Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
Prohibit open burning of
vegetation and other waste in
the project area
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2013
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Open burning is not practiced
onsite
Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
Construction Air Quality and Noise Deterioration of
ambient air quality
due to dust and
gas emissions
from:
a. Earthworks and
other construction
processes; tunnelling (drill
and blast)
b. Stockpiling of
aggregates and spoils, and
conveyance of
spoils to disposal areas
c. Increased transport
activities in the
construction areas and
along Ipo Road
d. Burning of vegetation
and wastes
e. Operation of
mechanical equipment
Ipo Road, main access road,
other roads in the Project area
area,
Limit speed of all construction
vehicles to max of 40kph on the
access road and max 30kph
onsite
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Maintain air quality
within national air quality
standards, or if these are
not available,
internationally accepted
air quality standards,
such as WHO Air
Quality Guidelines
Global Update, 2014
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Air Quality and Noise Noise and vibration in the
project area from
excavation activities;
general construction
activities; and vehicle and
equipment operations
Use only equipment that emit
least noise and vibration and are
well maintained.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Adopt national
standards for
construction sites and
residential areas if
available. Alternatively
use internationally
accepted standards
such as WHO
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant No dust curtains/net has been
installed.
Dust supression has been
implemented already.
Open burning is not practiced
onsite
Speed limit has not yet
implemented
Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky
Latunio) Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Air Quality and Noise Noise and vibration in the
project area from
excavation activities;
general construction
activities; and vehicle and
equipment operations
Use facility layout to minimize
noise propagation e.g. using
topography / existing buildings
as barriers, where possible
locate noisy activities
away from local communities.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Adopt national
standards for
construction sites and
residential areas if
available. Alternatively
use internationally
accepted standards
such as WHO
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Air Quality and Noise Noise and vibration in the
project area from
excavation activities;
general construction
activities; and vehicle and
equipment operations
Control noise at source, e.g. low
noise plant, muffling, acoustic
screening, switch off
campaigns.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Adopt national
standards for
construction sites and
residential areas if
available. Alternatively
use internationally
accepted standards
such as WHO
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Air Quality and Noise Noise and vibration in the
project area from
excavation activities;
general construction
activities; and vehicle and
equipment operations
Restrict use of noisy and highly
vibrating equipment from 8AM-
5PM. Necessary overtime work
should: a) not go beyond
9:00PM; b)
observe regulated noise and
vibration levels;
c) not use noisy and highly
vibrating equipment; and
d) should be coordinated with
the barangay and affected
households.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Adopt national
standards for
construction sites and
residential areas if
available. Alternatively
use internationally
accepted standards
such as WHO
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Air Quality and Noise Noise and vibration in the
project area from
excavation activities;
general construction
activities; and vehicle and
equipment operations
Manage the ins and outs of
hauling trucks. Spread out the
schedule of material, waste and
spoil transport in the day (off-
peak hours).
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Adopt national
standards for
construction sites and
residential areas if
available. Alternatively
use internationally
accepted standards
such as WHO
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Air Quality and Noise Noise and vibration in the
project area from
excavation activities;
general construction
activities; and vehicle and
equipment operations
Enforce the rule of no blowing of
horns.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Adopt national
standards for
construction sites and
residential areas if
available. Alternatively
use internationally
accepted standards
such as WHO
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Air Quality and Noise Noise and vibration in the
project area from
excavation activities;
general construction
activities; and vehicle and
equipment operations
Strictly enforce upon workers
the compliance with wearing of
ear mufflers, especially those
who are operating equipment.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Adopt national
standards for
construction sites and
residential areas if
available. Alternatively
use internationally
accepted standards
such as WHO
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Agreement with CRL
Laboratories for air quality
monitoring is now in place (24
August 2017). The air quality
sampling dates will be
scheduled once the Tunnel
Excavation starts.
Schedule of Air Quality
Monitoring:
A sound level meter was
procured by CMC to monitor
the noise level during
construction period as one of
the requirements of ADB and
DENR. Noise monitoring
started on 28 October 2017.
Sound Level
Monitoring (c/o
Jasper Cazenas
and Ricky Latunio)
Dated:
- Oct 28, 2017
-Nov 11, 2017
- Nov 24, 2017
- Dec 1, 2017
- Dec 13, 2017
Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
trucks/ equipment beyond
project footprints
Institute measures to avoid
impacting on habitats and
wildlife, such as:
1. minimize vegetation
clearance at Bigte
and especially at the intake;
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permit from DENR.
Tree cutting
permit
Compliant
Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
2. fence off vegetation to be
retained
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permitfrom DENR.
Tree cutting
permit
Compliant
Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
trucks/ equipment beyond
project footprints
3. provide environmental
training for workforce enforce
site rules and sanctions to
discourage workforce from
hunting, fishing and poaching.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permit from DENR.
Tree cutting
permit
In Progress staff orientation and training
provided
training and
orientation record
Toolbox meeting
attendances (c/o
Jasper Cazenas
and Ricky Latunio)
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
trucks/ equipment beyond
project footprints
Confine all construction activities
to previously disturbed areas, to
the extent practicable, e.g.,
workers’ quarters/camps.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permit from DENR.
Tree cutting
permit
Compliant Tree cutting
Permits issued by
Community
Environment and
Natural Resources
(DENR-CENRO)
a. Date of Issue:
July 10, 2017
Expiry Date: July
25, 2017
b. Date of Issue:
July 25, 2017
Expiry Date: July
30, 2017
c. Date of Issue:
August 16, 2017
Expiry Date:
August 31, 2017
d. Date of Issue:
August 24, 2017
Expiry Date:
August 31, 2017
e. Date of Issue:
September 11,
2017
Expiry Date:
September 18,
2017
f. Date of Issue:
September 23,
2017Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
trucks/ equipment beyond
project footprints
To avoid unnecessary clearing,
mark/delineate areas to be
cleared of vegetation, e.g. by
fencing.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permit
from DENR.
Tree cutting
permit
Compliant c. Tree cutting
Permits issued by
Community
Environment and
Natural Resources
(DENR-CENRO)
a. Date of Issue:
July 10, 2017
Expiry Date: July
25, 2017
b. Date of Issue:
July 25, 2017
Expiry Date: July
30, 2017
c. Date of Issue:
August 16, 2017
Expiry Date:
August 31, 2017
d. Date of Issue:
August 24, 2017
Expiry Date:
August 31, 2017
e. Date of Issue:
September 11,
2017
Expiry Date:
September 18,
2017
f. Date of Issue:
September 23,
2017
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
trucks/ equipment beyond
project footprints
Rehabilitate cleared areas to
their pre-project conditions,
unless otherwise agreed with
the landowner.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permit from DENR.
Tree cutting
permit
Not Applicable
Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
trucks/ equipment beyond
project footprints
Re-vegetate construction sites
using local, indigenous species.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permit from DENR.
Tree cutting
permit
Not Applicable
Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
trucks/ equipment beyond
project footprints
Re-vegetate watershed target
sites especially in areas
identified by the Watershed
Management Plan.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permit from DENR.
Tree cutting
permit
Not Applicable
Construction Biological Loss of vegetation
due to:
- Vegetation clearing and
potential trampling of
trucks/ equipment beyond
project footprints
Limit any collection of wood for
charcoal to exotic i.e. non-native
species.
Part of project
(construction) cost
D&B
Contractor
OSP-AWTIP Minimal number of trees
applied for tree cutting
permit from DENR.
Tree cutting
permit
In Progress
Construction Biological Disturbance to wildlife due
to construction noise,
vibration, dust, lighting,
presence/ movement of
people, etc. flying debris
from blasting
Implement measures to mitigate
noise,
vibration and dust
Part of project
(construction) cost
D&B
Contractor
PMO Record number of
poaching and illegal
trading of wildlife
by workers
N/A In Progress
Construction Biological Disturbance to wildlife due
to construction noise,
vibration, dust, lighting,
presence/ movement of
people, etc. flying debris
from blasting
Strategically place nets at the
tunnel portals to
prevent flying debris
Part of project
(construction) cost
D&B
Contractor
PMO Record number of
poaching and illegal
trading of wildlife
by workers
N/A In Progress
Construction Biological Disturbance to wildlife due
to construction noise,
vibration, dust, lighting,
presence/ movement of
people, etc. flying debris
from blasting
Water to minimize dust
accumulation and spreading
Part of project
(construction) cost
D&B
Contractor
PMO Record number of
poaching and illegal
trading of wildlife
by workers
N/A In Progress
Construction Socio-economic Traffic due to:
- Inadequate capacity of
Ipo Road (access road)
- Expected volume of truck
movement
Institute prior coordination with
the Barangay and Municipality
for the formulation of a traffic
management and safety plan
and for clearing of structures
encroaching into access road
ROW.
Part of project
(construction) cost
D&B
Contractor
Zero accident and
related incidents
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress
Construction Socio-economic Traffic due to:
- Inadequate capacity of
Ipo Road (access road)
- Expected volume of truck
movement
Prior to construction, clear
easement of encroaching
structures, most of them being
temporary.
Part of project
(construction) cost
D&B
Contractor
Zero accident and
related incidents
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress
Construction Socio-economic Traffic due to:
- Inadequate capacity of
Ipo Road (access road)
- Expected volume of truck
movement
Strategically post billboards
informing the public about the
expected increase in volume of
traffic in the influence area due
to Project implementation. Post
at least two weeks prior to
mobilization.
Part of project
(construction) cost
D&B
Contractor
Zero accident and
related incidents
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Socio-economic Traffic due to:
- Inadequate capacity of
Ipo Road (access road)
- Expected volume of truck
movement
Coordinate with the Barangay
for assistance in traffic
management.
Part of project
(construction) cost
D&B
Contractor
Zero accident and
related incidents
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant
Construction Socio-economic Traffic due to:
- Inadequate capacity of
Ipo Road (access road)
- Expected volume of truck
movement
Strategically post traffic flagmen
along Ipo Road, equipped with
two-way radio.
Part of project
(construction) cost
D&B
Contractor
Zero accident and
related incidents
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant
Construction Socio-economic Traffic due to:
- Inadequate capacity of
Ipo Road (access road)
- Expected volume of truck
movement
Post sufficiently legible
(reflectorized) traffic safety
notice and signage at strategic
locations along the entire stretch
of the access road.
Part of project
(construction) cost
D&B
Contractor
Zero accident and
related incidents
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant
Construction Socio-economic Traffic due to:
- Inadequate capacity of
Ipo Road (access road)
- Expected volume of truck
movement
Limit speed to 40 kph along Ipo
Road, and 30 kph at
construction sites and unpaved
haulage roads.
Part of project
(construction) cost
D&B
Contractor
Zero accident and
related incidents
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant
Construction Socio-economic Potential damage of
existing roads used
as access roads due
to movement of
heavy equipment
and vehicles
Coordinate with DPWH
regarding the use of Ipo Road.
Part of project
(construction) cost
D&B
Contractor
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant
Construction Socio-economic Potential damage of
existing roads used
as access roads due
to movement of
heavy equipment
and vehicles
Restore access roads within the
MWSS compound to the pre-
construction condition or better.
Part of project
(construction) cost
D&B
Contractor
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant
Construction Socio-economic Restricted access to the
existing fish landing
sites in Sitio Consultant
(identified area as the
Contractor’s Work Area)and boat landing at Sitio
Ipo
Inform affected communities
living in Ipo Watershed on the
impact of construction works on
transportation and consult them
for the best alternative route.
Have alternative route and fish
and boat landing sites ready for
use prior to commencement of
construction activities.
Part of project (construction)
cost
D&B
Contractor
Compliant
Construction Socio-economic Community health and
safety hazards
Inform local residents of the
timing of blasting and prohibit
entry of local residents into the
construction area
Part of project (construction)
cost
D&B
Contractor
Compliant
Construction Socio-economic Community health and
safety hazards
Secure project area, including
associated facilities particularly
the storage for explosives,
from unauthorized entry
Part of project (construction)
cost
D&B
Contractor
Compliant
Construction Socio-economic Community health and
safety hazards
Implement measures to mitigate
impacts on air and water quality,
noise, and traffic
Part of project (construction)
cost
D&B
Contractor
In Progress proper PPEs provided to
workers and staff
Construction Socio-economic Workers’ health andsafety hazard
Mitigating impacts from blasting:
- Include H&S protocols in the C-
EMP on the safe procedures in
the storage, handling and use of
explosives during construction
Compliant
Construction Socio-economic Workers’ health andsafety hazard
Provide safe housing with
adequate basic services
Compliant
Construction Socio-economic Workers’ health andsafety hazard
Enforce use of protective wears
when at work
Compliant
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Construction Socio-economic Workers’ health andsafety hazard
Conduct premobilization
orientation workshop on
health and safety and
emergency response and
evacuation procedures
Compliant
Construction Socio-economic Workers’ health andsafety hazard
Handling and storage of
explosives
- Magazine storage should be
far from residential areas, roads,
transmission lines, dams and
their appurtenant works
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Site should be well-drained and
sloping, accessible by road at
least 100m from
overhead power transmission
lines
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Detonators should not be stored
together with explosives
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Maintenance should follow the
prescribed instructions for the
explosivess
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Inside of all magazines should
be kept thoroughly clean
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Cigarettes and matches should
not be taken into explosives
should be used according to
date of manufactured
magazines. Its keeper should
ensure this
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Explosive boxes should be of
wood or soft non-ferrous metal,
e.g. brass and copper.
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Magazine should be securely
locked, when not attended
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Detailed records of outgoing and
incoming stocks should be kept
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Magazines should be kept free
from bushes and vegetation
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Empty boxes, loose packing
material or cotton waste should
not be kept on the magazine
premises
Not Applicable
Construction Socio-economic Workers’ health andsafety hazard
Do not open magazines during
or in the approach of a
thunderstorm. No person should
remain in the vicinity of the
magazine during such storm
Not Applicable
Generation of spoil and
spoil disposal. More than
150,000m3 is expected to
be generated due to
tunnelling works, which is
about 190,000 m3 loose
volume.
Prepare and implement a plan
for the preparation of the spoil
disposal areas.
Part of project
development cost
MWSS
DED
Consultants
D&B
Contractor
Detailed
Engineering
Design (DED)
Scope of Work
Detailed
Engineering and
Design Plans
In Progress Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Generation of spoil and
spoil disposal. More than
150,000m3 is expected to
be generated due to
tunnelling works, which is
about 190,000 m3 loose
volume.
Minimise the volume of spoil to
be disposed of by re-use in
backfilling of roads, and by
offering as free filling materials
to government projects needing
backfill materials.
Part of project
development cost
MWSS
DED
Consultants
D&B
Contractor
Detailed
Engineering
Design (DED)
Scope of Work
Detailed
Engineering and
Design Plans
In Progress Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
2 kilometers from the source of
spoil. Generation of spoil and
spoil disposal. More than
150,000m3 is expected to
be generated due to
tunnelling works, which is
about 190,000 m3 loose
volume.
Disposal area must be confined
to solid ground, of low ecological
and agricultural value.
Part of project
development cost
MWSS
DED
Consultants
D&B
Contractor
Detailed
Engineering
Design (DED)
Scope of Work
Detailed
Engineering and
Design Plans
In Progress Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
2 kilometers from the source of
spoil. Generation of spoil and
spoil disposal. More than
150,000m3 is expected to
be generated due to
tunnelling works, which is
about 190,000 m3 loose
volume.
Disposal area must not occupy
drainage lines and streams, and
create an obstacle to streams or
induced flooding.
Part of project
development cost
MWSS
DED
Consultants
D&B
Contractor
Detailed
Engineering
Design (DED)
Scope of Work
Detailed
Engineering and
Design Plans
In Progress Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
2 kilometers from the source of
spoil. Generation of spoil and
spoil disposal. More than
150,000m3 is expected to
be generated due to
tunnelling works, which is
about 190,000 m3 loose
volume.
Spoil heaps must be designed
and shaped with stable side
slopes and suitable drainage.
Part of project
development cost
MWSS
DED
Consultants
D&B
Contractor
Detailed
Engineering
Design (DED)
Scope of Work
Detailed
Engineering and
Design Plans
In Progress Stockpile is at minimum
especially in Ipo construction
site (Intake).
Spoil management plan has
been drafted and already
submitted to MWSS. Spoil
disposal area, MAPOL quarry,
was identified. It has an
approximate land area of 4
hectares, located approximately
2 kilometers from the source of
spoil. Generation of spoil and
spoil disposal. More than
150,000m3 is expected to
be generated due to
tunnelling works, which is
about 190,000 m3 loose
volume.
Spoils heaps must be
compacted during the
earthworks.
Part of project
development cost
MWSS
DED
Consultants
D&B
Contractor
Detailed
Engineering
Design (DED)
Scope of Work
Detailed
Engineering and
Design Plans
In Progress
Generation of spoil and
spoil disposal. More than
150,000m3 is expected to
be generated due to
tunnelling works, which is
about 190,000 m3 loose
volume.
When completed, the spoil
heaps must be covered with the
original top soil from the site and
revegetated
Part of project
development cost
MWSS
DED
Consultants
D&B
Contractor
Detailed
Engineering
Design (DED)
Scope of Work
Detailed
Engineering and
Design Plans
In Progress
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Solid waste Implement an eco-friendly solid
waste management at work
sites and workers’ camp/s,which minimize, re-use,
segregate and promptly
dispose generated solid waste
Part of project
development cost
MWSS
D&B
contractor
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Waste onsite are segregated
into biodegredable, non-
biodegradable and residuals.
There are designated bins for
each type of waste, color coded
and labeled. Waste are
collected every Tuesday and
Thursday by Brgy Bigte. CMC
and Brgy Bigte has a service
contract for garbage and
hauling disposal from May 2017
to December 2017.
Service Contract
of Brgy Bigte and
CMC for Garbage
hauling and
disposal
Date of Issue:
May 30, 2017
Expiry Date: Dec
31, 2017
Site inspection
report Jasper
Cazenas and
Ricky Latunio)Hazardous waste Locate stationary ground
storage for hazardous waste at
least 100m away from water
bodies, raised to min 1ft above
high flood level. Or use mobile
storage but should not be
parked near water bodies
Part of project
(construction) cost
D&B
contractor
Construction
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress hazmat temporary disposal
area included in the industrial
area site map
hazmat temporary
disposal included
in the Industrial
Area site plan (c/o
Sergio and
Federico)
Hazardous waste Secure storage areas
appropriately. Storage
facilities must contain spillage
Part of project
(construction) cost
D&B
contractor
Construction
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant
Hazardous waste Dispose of waste promptly and
appropriately
Part of project
(construction) cost
D&B
contractor
Construction
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
Compliant Waste onsite are segregated
into biodegredable, non-
biodegradable and residuals.
There are designated bins for
each type of waste, color coded
and labeled. Waste are
collected every Tuesday and
Thursday by Brgy Bigte. CMC
and Brgy Bigte has a service
contract for garbage and
hauling disposal from May 2017
to December 2017.
Service Contract
of Brgy Bigte and
CMC for Garbage
hauling and
disposal
Date of Issue:
May 30, 2017
Expiry Date: Dec
31, 2017
Site inspection
report (c/o Jasper
Cazenas and
Ricky Latunio)
Hazardous waste The Contractor shall be required
to implement an appropriate
hazardous waste management
program
Part of project
(construction) cost
D&B
contractor
Construction
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress hazmat temporary disposal
area included in the industrial
area site map
hazmat temporary
disposal included
in the Industrial
Area site plan (c/o
Sergio and
Federico)
Hazardous waste Storage of oil and grease used
for the maintenance and
operation of heavy equipment
shall be properly built and
maintained to include bunded
storage for the capacity of the
containers plus 10%, and oil
Part of project
(construction) cost
D&B
contractor
Construction
D&B Contractor
Scope of Work
D&B Contractor’sC-EMP
In Progress hazmat temporary disposal
area included in the industrial
area site map
hazmat temporary
disposal included
in the Industrial
Area site plan (c/o
Sergio and
Federico)
Public safety as
related to future
development and
activities along the
ROW
MWSS must secure the ROW.
Existing above ground
infrastructure along ROW
should be limited. The public
must not be allowed to encroach
onto the ROW by constructing
any buildings or farming the
Part of maintenance cost MWSS
CPF
(represented
by 2
water
concessionair
Compliant
Changes in hydrology
along Angat river during
dry season
During the operation phase,
flows shall be monitored
downstream of Ipo dam.
Not Applicable to be monitored during the
operation phase
AWTIP Monitoring Matrix - IEE
No Project Phase
Environmental
Aspect Potential Impact
Possible approach/mitigating
measures
Mitigation
cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks
Relevant
DocumentsResponsible
Changes in hydrology
along Angat river during
dry season
As practice in the Philippines,
Ipo dam should maintain 10%
riparian flow downstream. This
flow aims to allow migration of
fish species and maintain
natural characteristics of the
river downstream of the dam.
Not Applicable to be monitored during the
operation phase
AWTIP Monitoring Matrix - IEE