angat water transmission improvement project

147
Environmental Monitoring Report Semestral Report January 2018 Philippines: Angat Water Transmission Improvement Project Prepared by the Metropolitan Waterworks and Sewerage System for the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area

Upload: others

Post on 13-Jan-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Angat Water Transmission Improvement Project

Environmental Monitoring Report

Semestral Report January 2018

Philippines: Angat Water Transmission Improvement

Project

Prepared by the Metropolitan Waterworks and Sewerage System for the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein

do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may

be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation

of or reference to a particular territory or geographic area in this document, the Asian

Development Bank does not intend to make any judgments as to the legal or other status of any

territory or area

Page 2: Angat Water Transmission Improvement Project

AWTIP Tunnel 4 Semi Annual Environmental Monitoring Report 2

2017 July - December

Contents

Executive Summary 1

General 1

Assessment of compliance 1

1 Introduction 2

1.1 Background 2

1.2 Project Implementation Progress 4

2 Compliance with ADB loan covenants and applicable

government laws, regulations and requirements 18

2.1 Status of compliance with government environmental requirements: 18

3 Changes in project scope 24

4 Summary of Environmental Mitigations and

Compensation Measures Implemented 25

4.1 Emission/Wastewater Discharge (Source) Monitoring Program (if

relevant or required in the EMP) 31

4.2 Water Quality Monitoring Program 31

4.3 Air and Noise Quality Monitoring Program 58

5 Key Environmental Issues 61

5.1 Key activities implemented 61

5.2 Key Issues Identified 61

6 Complaints 63

6.1 Details of Complaint/s 63

7 Conclusion and Recommendation 64

7.1 Overall Progress of Implementation of Environmental Management

Measures 64

8 Appendices 1

8.1 AWTIP Monitoring Matrix 1

8.2 Tree Cutting Permits 2

Page 3: Angat Water Transmission Improvement Project

AWTIP Tunnel 4 Semi Annual Environmental Monitoring Report 2

2017 July - December

8.3 Permits and Licenses 3

8.4 Water Quality Laboratory Results 4

8.5 Grievance Case - Invalid 5

Page 4: Angat Water Transmission Improvement Project

List of Tables

Table 1. Contract Price for design and construction service ....................................................... 3

Table 2. Key information about the project .............................................................................. 3

Table 3. Key project progress .................................................................................................... 4

Table 4. Overall Progress of the project as of June 2016 ........................................................... 5

Table 5. Total Length to be concreted from STA 0+000 to STA 0+863.95 = 863.95 m ..... 6

Table 6. Workforce as of December 31, 2017 ........................................................................ 13

Table 7. Filipino Workforce as of December 31, 2017 – by geographic location ...................... 14

Table 8. Workforce as of December 31, 2017 – by Gender .................................................... 14

Table 9.. Workforce as of December 31, 2017 – Dumagats ................................................... 14

Table 10. Workforce as of December 31, 2017 – by Age Groups .......................................... 15

Table 11. Staff requirement in the next 3 months ................................................................... 15

Table 12. Contractor: CMC di Ravenna ................................................................................ 16

Table 13. Sub-contractor: First Balfour .................................................................................. 16

Table 14. Sub-contractor: Don Vic Construction .................................................................... 16

Table 15. Sub-contractor: White Moon Inc. ............................................................................ 17

Table 16. Permits ................................................................................................................. 18

Table 17. Other Permits....................................................................................................... 19

Table 18. Safety Report as of December 2017 ...................................................................... 19

Page 5: Angat Water Transmission Improvement Project

AWTIP Tunnel 4 Semi Annual Monitoring Report 1

2017 January - June

Table 19. Summary of Environmental Mitigations and Compensation Measures Implemented

............................................................................................................................................... 29

Table 20. Water Quality Results for SWB1 .......................................................................... 35

Table 21. Water Quality Results for SWB2 .......................................................................... 37

Table 22. Water Quality Results for SWB3 .......................................................................... 39

Table 23. Water Quality Results for SWSM1 ....................................................................... 41

Table 24. Water Quality Results for SW IPO1 ..................................................................... 43

Table 25. Water Quality Results for SW IPO2 ..................................................................... 45

Table 26. Water Quality Results for SW IPO3 ..................................................................... 48

Table 27. Water Quality Results for SW IPO4 ..................................................................... 52

Table 28. Water Quality Results for Basin 1 ......................................................................... 55

Table 29. Turbidity monitoring results from October to December 2017 .................................. 57

Table 30. Noise level monitoring results (October-December 2017) ......................................... 59

Table 31. WHO guidelines for noise quality ........................................................................... 60

Table 32. List of grievances as of December 2017 ................................................................ 63

Page 6: Angat Water Transmission Improvement Project

List of Figures

Figure 1. Project Site .............................................................................................................. 3

Figure 2. Conveyance channel area ............................................................................................ 7

Figure 3. Substation of outlet portal area .................................................................................. 7

Figure 4. Lifting of Back-up Cars for TBM Assembly ............................................................. 8

Figure 5. Probe Drilling Investigation at Launching Chamber .................................................. 8

Figure 6. Probe Drilling at Launching Chamber....................................................................... 9

Figure 7. Construction of Water Treatment Tank ..................................................................... 9

Figure 8. Construction of Tippler ............................................................................................ 10

Figure 9. Railway at Industrial Area (Sta. 0-140 onwards) ................................................... 10

Figure 10. Delivered Precast Segments .................................................................................... 11

Figure 11. Delivered Precast Segments .................................................................................... 11

Figure 12. CMC staff during earthquake drill ........................................................................ 22

Figure 13. Actual photo from the Earthquake Drill ............................................................... 22

Figure 14. Site Assembly Point Area (Holding Area/Muster Point) ..................................... 23

Figure 15. The sampling locations (Bigte and Ipo Rivers) ........................................................ 32

Figure 16. Sampling points in Bigte River ............................................................................... 33

Figure 17. Sampling points in Ipo River ................................................................................. 34

Page 7: Angat Water Transmission Improvement Project

Acronyms1

AWTIP Angat Water Transmission Improvement Project

ADB Asian Development Bank

CCO Chemical Control Orders

CEMMP Contractor’s Environmental Management And Monitoring Plan

CENRO City Environment and Natural Resources Office

CMC Cooperativa Muratori Cementisti di Ravenna

DENR Department of Environment and Natural Resources

ECC Environmental Compliance Certificate

EIA Environmental Impact Assessment

EMP Environmental Management Plan

IEC Information, Education and Communication

IEE Initial Environmental Examination

IP Indigenous People

km Kilometer

L Length

MENRO Municipal Environment and Natural Resources Office

MMT Multi-partite monitoring team

MWSS Metropolitan Waterworks and Sewerage System

NA Not applicable

NCIP National Commission on Indigenous Peoples

NPC National Power Corporation

ORP Oxidation Reduction Potential

PD Presidential Decree

PO Permit to Operate

RCBC Reinforced Concrete Box Culvert

RCPC Reinforced Concrete Pipe Culvert.

ROW Right of way

SEMP Self-Environmental Management Plan

TBM Tunnel Boring Machine

1 This is a standard acronym list for all monitoring reports. The acronym may not appear in all

reports

Page 8: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

1

Executive Summary

General

The Contractor, CMC di Ravenna, monitors its performance against the CEMMP obligations.

Because of this, it will record non-compliance where performance does not meet the original

obligations. In many cases this should not be taken to mean that the outcomes are bad and

where alternative courses of action have been adopted CMC and MWSS has recorded this.

This report highlights prevailing issues about the project. Only obligations which are assessed

as in progress, non-compliant (in specification and time schedule), and not applicable are

presented in the body of the report. A full review of the CEMMP obligations is presented in

the CA matrix in excel format.

The layout of this report followed recommended ADB monitoring report structure.

Assessment of compliance The following are the definition of remarks used to assess the CEMMP, EMP of IEE and EIA and other environment related project documents.

(a) COMPLIANT – completed according to schedule and specifications in the

CEMMP and other relevant ADB policies;

(b) NON-COMPLIANT – not completed according to schedule and specification

and/or not according to specification;

(c) NC time – completed beyond the date of completion stated in the CEMMP

(d) IN PROGRESS – partly compliant and pending for completion

(e) NOT APPLICABLE – obligations not applicable to AWTIP project

(f) CANNOT DOCUMENT COMPLIANCE – insufficient document or no

document provided to support assessment of compliance

A full review of the CEMMP and other relevant project documents on environment is

presented in Appendix Section 8.1.

Two grievance cases reported in the period July to December 2017.

Water quality monitoring started on August 2017. Portable turbidimeter and multimeter were

procured for in-situ measurements and monitoring of water. Monitoring using the

instruments started on October 2017.

A sound level meter was also procured to monitor sound levels onsite. Monitoring started on

October 2017.

Other monitoring and survey services/ consultancy procurement are in progress.

Page 9: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

2

1 Introduction

1.1 Background

The Angat Water Transmission Improvement Project (AWTIP) is part of a bigger scheme of

modernization and improvement of the Metro Manila Water Distribution Network. The

water of the Angat basin, which is fed through the Umiray tunnel, provides around 35% of

the water for domestic use to the city of Manila. Currently the transportation of water from

Ipo dam basin to the Bigte sedimentation plant happens through 4 tunnels, 2 of which are

very obsolete. The progressive deterioration of the existing tunnels (2 of which were built

more than 75 years ago), or the occurrence of an earthquake (which is very likely since the

area is close to two active faults), may seriously compromise the provision of water to millions

of people.

The project is located in the province of Bulacan, at around 50 km north of Manila, close to

Norzagaray City, of 150,000 inhabitants which hosts several important cement industries and

which is easily accessible via highway or normal roads.

More than 95% of the water supply for Metro Manila comes from a single source: The

Umiray–Angat– Ipo, or Angat system. Water from the Angat reservoir is conveyed through

three parallel tunnels followed by six parallel aqueducts, to water treatment plants in Metro

Manila. The treated water is then distributed to households, businesses, and industries in

Metro Manila, and parts of Cavite and Rizal provinces. The transmission’s tunnel system

which is about 75 years old, has not been assessed ever since. The earlier tunnels, tunnels 1

and 2 are not in compliance with current structural and seismic requirements. These factors

could lead to serious interruptions of Metro Manila’s water supply. The proposed project will

construct the urgently required fourth parallel tunnel. This new tunnel will not increase system

capacity, but it will enable the rehabilitation or decommissioning of the upstream tunnels and

downstream aqueducts.

The proposed project aims to (i) help restore the full design capacity of the Angat systems

and thus ensure the sustainable provision of the water supply distribution system, and (ii)

mitigate the risk of a total loss of water supply to Metro Manila and portions of Cavite and

Rizal provinces. Both objectives are essential for the stable economic growth of Metro Manila

and the Philippines. The government has asked the Asian Development Bank (ADB) to

finance this investment. The figure below shows the general location of the project.

Page 10: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

3

Figure 1. Project Site

The Angat Water Transmission Project (AWTIP) is a design and build project consists of

Design and Construction activities:

Table 1. Contract Price for design and construction service

ITEM GRAND SUMMARY CONTRACT PRICE

1 Designs Services 93,516,701.06

2 Construction Devices 3,198,038,168.46

Grand Total for Design Services and Construction Service

(1) + (2)

Php

3,291,554,869.52

1.1.1 Project Data

Table 2. Key information about the project

Project Name Angat Water Transmission Improvement Project

(AWTIP)

Components 6.4 km Tunnel Construction, Intake/Outlet

Structure, and Interconnection to Basin of

Aqueduct No. 5

Location Norzagaray, Ipo Dam to Bigte Basin

Duration 52 months (4 years and 4 months) Design Period

= 6 months Construction Period = 46 months

Source of Fund Asian Development Bank (Loan 3377 PHI-AWTIP)

Contractor Cooperativa Muratori Cementisti di Ravenna (Italy)

Contractor’s Project Manager Mr. Salvatore La Valle

Page 11: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

4

Project Manager/ CO for MWSS Jose D. Dorado Jr.

Consultant’s Project Manager MWSS’s Consultant is not yet in place. MWSS,

the principal will do direct supervision

Notice to Proceed (NTP) May 31, 2016

Actual Date of Start June 01, 2016

Target Completion September 07, 2020

1.2 Project Implementation Progress

1.2.1 Overall Progress as of 31 December 2017

Table 3. Key project progress

PERIOD ENDING 31 December 2017

Project Phase Construction Phase

Target Accomplishment to Date (31

December 2017)

26.541%

Actual Accomplishment to Date 23.02%

Scheduled Accomplishment for the Month 2.855%

Actual Accomplishment for the Month 0.61%

% Variance to Date 3.523 % (-)

% Variance last Month

(Ahead/Slippage)+/-

1.275 % (-)

Contract Time Elapsed 579 c.d. or 37.12%

Delayed Activities:

1. No. 136: Slope Stabilization (Inlet) – The delay in the Slope Stabilization along inlet area

is primarily due to CMC’s claim to Redesign the Intake Structure and Slope Stabilization at Ipo dam area. Technically, the Variation on Design was approved last May 2017. MWSS Board of Directors declined the Variation on Cost. Thus, since CPF have an on-going project negotiation regarding Slope Stabilization within the area, the additional scope of work being claimed by CMC to AWTIP scope of work will be covered to Ipo Dam Slope Stabilization Project (IDSSP) being implemented by CPF.

2. Permanent Access Road – the works at the remaining areas of the Access road at IPO dam area, was on hold since 07 August 2017. The stoppage of work was CMC’s prerogative while waiting for the approval of Variation Order No.1

a. No. 123: Clearing and Grubbing b. No. 124: Subgrade Preparation c. No. 125: Road Excavation

3. Tunnel Excavation by TBM – The delay is caused mainly by the unforeseeable site

condition such as the ever- changing site condition and unforeseeable geologic feature such as transported materials, Karst-cavities and artesian aquifers discovered during the rock excavation. Due to the updated geological findings, the design of the outlet portal was revised with the introduction of the micropiles retaining wall, and extension of shotcrete area on both sides of the outlet portal. The position of the portal has been moved 10 m ahead from the original design because of this transported slope wash material and rock soil debris. Moreover, grout injection works was necessary to stabilize

Page 12: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

5

the areas around the tunnel portal to avoid possible collapse or cave-ins during excavation. The rock excavation of the launching chamber prevented the TBM to be completely assembled and mobilized to the portal area. These works caused delay on the activities below:

a. No. 187 – Preparatory Works b. No. 188 – TBM Mobilization c. No. 190 – TBM Assembly

4. No. 196 – Production of Precast Segments – The delay in the precast production was due to the quality of cement used for the mix that cause slow curing time for demoulding. CMC utilized another cement supplier who is able to provide high early strength concrete, thereby producing increase in production of segments due to faster demoulding time. CMC also hired a specialist in precast rings/segment production, Mauro Spelozzi, to undertake the precasting process. His technical know-how, skills and experience will be optimized to mitigate the problem of low production rate.

1.2.2 Physical Progress

Table 4. Overall Progress of the project as of June 2016

Contract Amount Relative Weight

(%)

Accomplishment (Php Millions)

Weighted (%) % Target

Previous

This Period

To date Previous This Period

To date

1. Designs Services

P93,516,701.06 2.84% 93.517 93.517 2.84% 2.84% 2.84%

2. Construction Services

P 3,198,038,168.46 97.16% 644.141 19.996 664.137 19.57% 0.61% 20.18% 23.70%

TOTAL

P 3,291,554,869.52 100% 737.658 19.996 757.654 22.41% 0.61% 23.02% 26.54%

Note: This report shows the physical accomplishments of the Contractor’s work for items 1 and 2

Progress Status (Ahead/Slippage; +/-)

23.02 % (+)

1.2.3 On-going Site Works (as of December 2017)

(a) Facilities for the client’s office – All site facilities were completed on July 2017.

(b) Permanent Access Road (5m – width and 865m – length) All works on access road are still on hold as per Letter to MWSS Ref. No.

AWTIP_2017_OUT_0216-07/08/2017, dated 7 August 2017, except those related to security and safety due to the absence of formal response from MWSS on the formal issuance of its instruction for the redesign and relocation of Intake Structure and for CPF to award the Slope Stabilisation Design and Works.

(i) Earthworks – on hold

(ii) Basecourse Preparation – on hold

(iii) Concreting of Pavement – on hold

Page 13: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

6

Table 5. Total Length to be concreted from STA 0+000 to STA 0+863.95 = 863.95 m

(iv) Slope protection – on hold

(c) Outlet

(i) Conveyance channel – Activities in progress

(ii) Rock breaking for conveyance channel

(d) TBM preparatory works (Tunnels and Portals)

(i) Railway from Sta 0-000 to Sta 0-285 - Activity in Progress

(ii) Concrete Cradle for TBM Sliding – Not yet started

(iii) Excavation and Fortifications for Launching Chamber - Completed on 12-

Dec-17

(iv) Installation of 34.5 KV Poles, Main Switch and Cables - Activity in

Progress

(v) Preparation for Rotodump assembly - Activity in Progress

(vi) Ventilation system - Activity in Progress

(vii) Water Treatment Tank - Activity in Progress

(viii) Construction of Tippler - Activity in Progress

(e) Production of Precast Segment

(i) Production of Precast Segments (3,889 out of 19,940) - Activity in Progress

Page 14: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

7

1.2.4 Progress Photos (as of December 2017)

(a) Outlet Portal Area

Figure 2. Conveyance channel area

(b) TBM Excavation Works (Preparatory Works)

Figure 3. Substation of outlet portal area

Page 15: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

8

Figure 4. Lifting of Back-up Cars for TBM Assembly

Figure 5. Probe Drilling Investigation at Launching Chamber

Page 16: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

9

Figure 6. Probe Drilling at Launching Chamber

Figure 7. Construction of Water Treatment Tank

Page 17: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

10

Figure 8. Construction of Tippler

Figure 9. Railway at Industrial Area (Sta. 0-140 onwards)

Page 18: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

11

(c) Production of Precast Segments

Figure 10. Delivered Precast Segments

Figure 11. Delivered Precast Segments

Page 19: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

12

1.2.5 Previous Site Works (July to November 2017)

Activities 2017

July Aug. Sept. Oct. Nov.

i. Facilities for the Client’s Office

· Living quarters ●

· All site facilities ●

ii. Outlet Portal Area General Site Facilities

· Industrial Area/Precast Segments Storage Platform

Formation ●

· Workshop and Warehouse ●

· Fuel station and tank ●

iii. Permanent Access Road (Inlet)

· Earthworks → Ø Ø Ø Ø

· Basecourse Preparation → Ø Ø Ø Ø

· Concreting of pavement → Ø Ø Ø Ø

- On-hold (Total length to be concreted from STA

0+000 to STA 863.95 = 863.95 m)

· Slope protection → Ø Ø Ø Ø

· Slope protection works from Sta 0+600 to Sta 0+620 ●

· Concreting of Access Road Pavement from Sta 0+462

to Sta 0+474 ●

· Concreting of Access Road Pavement from Sta 0+336

to Sta 0+364 ●

iv. Slope upon the Portal (Outlet)

· Installation of Geocomposite Steel Mesh with Anchor

Bolts → → → ? ?

· Installation of 28mmØ threaded rock bolts, 5 meters → → → ? ?

· Rock breaking for conveyance channel → → → → ?

· Micro piling works → → → ●

· Anchoring and Fore poling works at the Portal → ●

· Shotcrete works at Level 101 to 92 ●

v. Outlet Structure

· Excavation for Outlet Structure ●

vi. Conveyance Channel

· Earthworks (Area for Segments 2. 3 & 4) →

· Earthworks (Area for Segments 5 & 6) →

vii. Railway for TBM preparatory Works (Tunnels and

Portals)

· Large RCBC, (Sta 0+010, 4.00x1.80, L=9.50m) → → ? →

· Large RCBC (Sta 0+010, 2x 4.00x1.80 L=6.00m) → → → ●

Page 20: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

13

Activities 2017

July Aug. Sept. Oct. Nov.

· Bridge overpass Aqueduct 1 (Span 3.65m, Length

33.35m) → → ? →

· Delivery of TBM “Veronica” at Site → ●

· Large RCBC (Sta 0+259.47) → ●

· Railway from Sta 0+240 to Sta 0 + 260 → ?

· Railway from Sta 0+260 to Sta 0+_?__ → ?

· Railway from Sta 0+000 to Sta 0+285 →

· Concrete Cradle for TBM Assembly ●

· Concrete Cradle for TBM Sliding -

· Excavation and Fortifications for Launching Chamber →

- (CMC conduct operations at night time for the

excavation of Launching Chamber for 3 consecutive

weeks from Nov. 20 to Dec. 9, 2017)

· Installation of 34.5 KV Poles, Main Switch and Cables →

· Preparation for Rotodump assembly →

· Ventilation system →

· Water Treatment Tank →

viii. Production of Pre-Cast Segment →

- Activity in Progress (2,725

out of

19,940)

ix. Inland Drilling by TREVI FOUNDATIONS at IPO (For

Seismic Test)

· Drilling of Core Holes ●

· Installation of PVC Pipes at Core Holes ●

· Grouting of Core Holes ●

Notes:

● - Completed

→ - Activity in progress

Ø - On-hold

- - Not yet started

1.2.6 Contractors Resources

(a) List of Production Construction Staff

Table 6. Workforce as of December 31, 2017

Entity Filipino Foreigner

TOTAL # % # %

CMC permanent staff

42 41 15 15 57

CMC contract workers / utilities

42 41 0 0 42

CMC consultants 1 1 2 3

Page 21: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

14

First Balfour 77 100 0 0 77

White Moon Inc. 14 100 0 0 14

Don Vic Construction

41 100 0 0 41

TOTAL 217 93 17 7 234

Table 7. Filipino Workforce as of December 31, 2017 – by geographic location

Entity

Personnel employed from Brgy San Mateo

Personnel employed from Bgry Bigte

Personnel employed from other Bgrys in Norzagaray

Personnel employed from other municipalities/ cities in Bulacan

Personnel employed from other provinces TOTAL

# % # % # % # % # %

CMC permanent staff

4 4 7 7 3 3 15 15 28 27 57

CMC contract workers / utilities

1 1 3 3 6 6 15 15 17 17 42

CMC consultants 0 0 0 0 0 0 0 0 3 3 3

First Balfour 5 6 11 14 1 1 7 9 53 69 77

Don Vic Construction

15 37 25 61 0 0 0 0 1 2 41

White Moon Inc 0 0 8 57 0 0 0 0 6 43 14

TOTAL 25 11 54 23 10 4 37 16 108 46 234

Table 8. Workforce as of December 31, 2017 – by Gender

Entity Male Female

TOTAL # % # %

CMC permanent staff 41 40 16 16 57

CMC contract workers / utilities

37 36 5 5 42

CMC consultants 2 2 1 1 3

First Balfour 69 90 8 10 77

Don Vic Construction 37 90 4 10 41

White Moon Inc. 14 100 0 0 14

TOTAL 200 85 34 15 234

Table 9.. Workforce as of December 31, 2017 – Dumagats

Entity Male Female

TOTAL # % # %

CMC permanent staff 0 0 0 0 0

Page 22: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

15

CMC contract workers / utilities

0 0 0 0 0

CMC consultants 0 0 0 0 0

First Balfour 2 100 0 0 2

Don Vic Construction 15 88 2 12 17

White Moon Inc. 0 0 3 0 21

TOTAL 17 89 2 11 19

Table 10. Workforce as of December 31, 2017 – by Age Groups

Entity 18-25 26-35 36-45 46-60 Over 60

TOTAL # % # % # % # % # %

CMC permanent staff

5 5 11 11 21 21 20 20 0 0 57

CMC contract workers / utilities

4 4 14 14 10 10 10 10 4 4 42

CMC consultants 0 0 0 0 1 1 2 2 0 0 3

First Balfour 16 21 31 40 16 21 14 18 0 0 77

Don Vic Construction

9 22 32 78 0 0 0 0 0 0 41

White Moon Inc. 4 29 4 29 4 29 2 14 0 0 14

TOTAL 38 16 92 39 52 22 48 21 4 2 234

(b) Recruitment Table 11. Staff requirement in the next 3 months

Position No. of Required

1. Health, Safety and Environment Officer 1

2. Driver 4WD 1

3. TBM/Hydraulic Mechanic 1

4. Forklift Operator 1

5. Chief Mechanic 1

6. Chief Electricians 1

7. Electronic Technicians 1

8. Helper 1

9. Tunnel Line Extension 2 1

10. Tunnel Line Extension 3 1

11. Tunnel Line Extension 4 1

12. TBM Operator 1

13. Laborers 5

14. Erector Operator/Probe Drill 2

15. Shift Boss 1

16. Driver Lorry Crane 1

17. Locomotive Operator 1

18. Driver (Mini Van) 2

19. Tippler Operator 2

20. Tippler Operator Helpper 2

21. Rail/Switch Cleaner 6

Page 23: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

16

22. Surveyor 2

23. Loco Driver 4

24. Erector Operator 2

25. Grouting Supervisor 2

26. Grouting Pump Operator 4

27. Grouting Injection Operator 4

28. Pea Gravel Pump Operator 2

29. Pea Gravel Injection Operator 4

30. Segment Crane Operator 2

31. Nurse 1

TOTAL 62

(c) List of Equipment

Table 12. Contractor: CMC di Ravenna

Item Quantity (as of 31 Dec 2017)

Stand-by (as of 31 Dec 2017)

Remarks

Welding Machine 3

Generator Set 4

Tower Light 1

Air Compressor 2

Dropside Truck 1

Forklift 1

Telescopic Handler 1

60 Ton Crane (Rental) 1

Table 13. Sub-contractor: First Balfour

Item Quantity (as of 31 Dec 2017)

Stand-by (as of 31 Dec 2017)

Remarks

Backhoe(20Tons Capacity)

2

Backhoe (7Tons Capacity)

1

BHI Hydraulic Breaker 1

Service Vehicles 3

Mini Dump Truck 2

Dump Truck (15 cu.m capacity)

1

Komatsu Breaker 1

Skid Steer Loader 1

Wheel Loader 1

Shotcrete Machine 1

Compressor 1

Grout pump 1

Grout mixer 1

Bagger Mixer 1

Table 14. Sub-contractor: Don Vic Construction

Page 24: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

17

Item Quantity (as of 31 Dec 2017)

Stand-by (as of 31 Dec 2017)

Remarks

Backhoe 1

Dropside Truck 1

Table 15. Sub-contractor: White Moon Inc.

Item Quantity (as of 31 Dec 2017)

Stand-by (as of 31 Dec 2017)

Remarks

Circular Saw 1

Electric Drill 2

Oxygen Acetylene Tank

1

1.2.7 Specific dates (day/month/year) site visits/inspections conducted by the supervision consultant to monitor

compliance of the contractors (and subcontractors) with the mitigation measures specified in the EMP.

The construction supervision consultants have not yet been commissioned by MWSS. MWSS

staff were the ones monitoring the compliance of CMC with the mitigating measures specified

in the Contractor’s Environmental Management and Monitoring Plan (CEMMP) Issues and

concerns were discussed in their weekly project management meeting with CMC.

Page 25: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

18

2 Compliance with ADB loan covenants and applicable government laws, regulations and requirements

2.1 Status of compliance with government environmental requirements:

The following table presents the permits acquired for the project. Copies

of the permits are in Appendix Section 8.2 and 8.3 of this report.

Table 16. Permits

Environmental Laws

Permits Date of Issue/ remarks Expiry Date

PD 1586 (Establishing EIS System)

ECC1 (Environmental Compliance Certificate)

ECC-CO-1508-0022

7 April 2017.

The certificate shall cover the following:

1. construction of water tunnel #4 with 6.4 kilometer length and 4 m diameter from Ipo Dam, Barangay San Mateo to Barangay Bigte, with associated facilities such as Contractor’s Work areas, Spoil Disposal Sites as enumerated in the EIS

2. Repair and rehabilitation works of Tunnel Nos 1,2,3

3. Water transmission operations of Tunnels No 1,2,3 and 4 for an aggregate water flow of up to 43 m3/sec

4. Fencing of the Right-of- way

-

RA 6969 (Toxic Substances and Hazardous and Nuclear Waste)

DENR Registry ID

No major construction activity as of this time. Only used oil

from vehicle is generated and all maintenance services of vehicles are done offsite. Permit application will be

processed when temporary Hazmat disposal area is 50%

filled.

CCO Registry (Chemical Control Order Registry)

N/A

Importer Clearance No

N/A

Permit to Transport

N/A. no major construction activity as of this time. Only

Page 26: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

19

used oil from vehicle is generated and all

maintenance services of vehicles are done offsite. Permit application will be

processed when temporary Hazmat disposal area is 50%

filled.

RA 8749 (Phil Clean Air Act)

PO No.1 (permit to Operate)

FLA-17J-03BU-550 (1 unit 20KW Standby GenSet)

20 October 2017 October 30, 2018

PO No.2 (permit to Operate)

FLA- 17J03BU-549 (1 unit 40KW Standby GenSet)

20 October 2017 October 30, 2018

PD 705 (The Forestry Reform Code Of The Philippines)

Tree Cutting Permit

- Tree cutting permit dated July 10, 2017 (10 fruit bearing trees) issued by CENRO Tabang

July 25, 2017

- Tree cutting permit dated July 25, 2017 (2 Acacia Trees) issued by MENRO Norzagaray

July 30, 2017

- Tree cutting permit dated August 16, 2017 (20 assorted fruit tree species) issued by CENRO Tabang

August 31, 2017

- Tree cutting permit dated August 24, 2017 (4 Acacia trees) issued by CENRO Tabang

August 31, 2017

- Tree cutting permit dated September 11, 2017 (5 Acacia Trees) issued by CENRO Tabang

September 18, 2017

- Tree cutting permit dated September 23, 2017 (10 assorted tree species) issued by CENRO Tabang

October 8, 2017

Table 17. Other Permits

Permits Date of Issue/ remarks Expiry Date

Mayor’s Permit Permit number: 2017-0722 Date of Issue: June 5, 2017

December 31, 2017 (For renewal)

Excavation/Slope Stabilization Permit

Permit number: 2017-11-0090 Date of Issue: November 29, 2017

-

Storage Building Permit

BP #2017-11-0091 November 29, 2017

Land use Permit issued by NPC

Permit number: 2017-LUP-03 Date of Issue: July 14, 2017

(approximately 25 years) July 14, 2042

Garbage Hauling and Disposal

May 30, 2017

December 30, 2017

PCO Accreditation

September 29, 2017

September 29, 2020

Table 18. Safety Report as of December 2017

Page 27: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

20

Previous This Period To Date

Average Manpower 385 300 372

CMC di Ravenna 96 97 98

Sub-contractor 289 203 263

Safe Man-hours 510,526 72,882 583,408

CMC di Ravenna 191,337 18,660 208,997

Sun-contractor 319,189 54,222 373,411

Major Incidents2 3 - 3

Minor Incidents3 7 - 7

Activity Previous This Period To Date

Incidents / Cases

Vehicle Incidents4 5 0 5

Near Misses5 9 2 11

First-Aid Cases6 9 0 9

Medical Treatment Cases7

261 84 345

Restricted Work Cases8

0 0 0

Lost-Time Cases9 0 0 0

Meeting/s

No. of Safety Meetings

19 3 22

No. of Toolbox Meetings

501 15 516

No. of People Inducted/Oriented

414 26 440

No. of Safety Observations

159 24 183

No. of Inspection Audits

168 12 180

Training Activity/ies and Number of

Participants

Hand and power tools

7 6 13

2 Major Incidents – defined as an acute incident such as major discharge/emission or a fire/explosion, which

immediately or subsequently causes several serious injuries and/or fatalities, serious harm to environment and/or loss of substantial material assets.

3 Minor Incidents – an accident that causes minor damage. 4 Vehicle Incidents – when a motor vehicle strikes or collides another vehicle, a stationary object, a pedestrian, or an

animal 5 Near Misses – unplanned event that has the potential to cause, but does not actually result in human injury,

environmental or equipment damage, or an interruption of normal operation. 6 First Aid Cases – worker’s injury cases administered immediately after the injury occurs at the location where it

occurred. 7 Medical Treatment Cases – recordable incident involving injury or illness that has required management and care of

the patient above and beyond first aid, but not severe enough to be a reportable fatality or lost work day case or restricted work day case.

8 Restricted Work Cases – when a person is so injured that they cannot perform their normal duties. Therefore, they

are transferred temporarily to some other jobs (light duties). 9 Lost-Time Cases – refer to the number of lost-time injuries within a given accounting period, relative to the total

number of hours worked in that period.

Page 28: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

21

Previous This Period To Date

Personal Protective Equipment (PPE)

37 5 42

Fire Prevention 30 11 41

Ladder Safety 21 6 27

Working at Heights 31 0 31

First Aid and CPR 0 0 0

Emergency and Evacuation Drill

3 0 3

Defensive Driving 15 0 15

Electrical Safety 30 5 35

Hazardous Materials Handling

2 0 2

Earthquake Drill 2017

An earthquake drill was conducted at CMC workers’ area on September 27,

2017. This was done as part of the implementation of Contingency

Emergency Response Plan. There were 30 participants in the drill, a

combination of CMC main staff, other contractors and soldiers from

Armed Forces of the Philippines. Emergency evacuation route was also

established and discussed to the staff.

Page 29: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

22

Figure 12. CMC staff during earthquake drill

Figure 13. Actual photo from the Earthquake Drill

Page 30: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

23

Figure 14. Site Assembly Point Area (Holding Area/Muster Point)

Page 31: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

24

3 Changes in project scope

No change in project scope.

Page 32: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

25

4 Summary of Environmental Mitigations and Compensation Measures Implemented

A full review of the CEMMP, IEE, EIA EMP and other obligations is presented in the compliance matrix in Appendix Section 8.1 of this report. Below is a summary

of prevailing issues on mitigation and compensation issues. Details can be found in Appendix Section 8.1.

Environmental Aspect

Potential Impact Possible Approach/ Mitigating Measures

Compliance Status

Remarks

Water

Impact on surface water quality due to/ from: · Contaminants from materials used and construction activities and processes · Siltation from soil erosion, spoil disposal area, dewatering excavations, etc · Water quality Deterioration of water quality in Ipo Dam and Bigte river Tributary during construction

· Implement hazardous waste management that minimizes, properly segregates and promptly and properly disposes of generated hazardous wastes. · Store hazardous construction materials in appropriately contained and elevated area and at least100 m away from surface water bodies. · Implement corrective action, when trigger thresholds of water quality are reached. · During construction, the contractor shall take corrective action to reduce concentration to below the standard.

Partial

High coliform was reported in segment of surface water where there are communities along the riverbanks prior to the start of construction activities. This trend was already noted during the collection of baseline information in 2013 -2014. Please note that Ipo Construction site was on stop work status since 2017 September. Portalets are provided and regularly collection is implemented in all construction sites - Ipo and Bigte. Waste onsite are segregated into biodegredable, non-biodegradable and residuals. There are designated bins for each type of waste, color coded and labeled. Waste are collected every Tuesday and Thursday by Brgy Bigte. CMC and Brgy Bigte has a service contract for garbage and hauling disposal from May 2017 to December 2017.

Page 33: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

26

Environmental Aspect

Potential Impact Possible Approach/ Mitigating Measures

Compliance Status

Remarks

The first water quality sampling was conducted by CMC last August 2017 with the following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS, ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See sampling location and results on the report). Weekly monitoring of water turbidity and other in-situ paramters using portable water meters started on October 2017. Testing is done weekly by CMC Envi, Health and Safety Officers (See sampling location and results on the report)

Air Quality and Noise

a) Deterioration of ambient air quality due to dust and gas emissions from: · Earthworks and other construction processes; tunneling (TBM) • stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas; • increased transport activities in the construction areas and along Ipo Road;

In active work sites: Use of dust curtains / nets to capture dust from the construction sites

Apply dust suppression techniques, e.g., watering with bowsers, sheeting particularly at Bigte area Require trucks, particularly those hauling aggregates, to have secure covers. · Limit engine idling to 5 minutes. · Prohibit open burning of vegetation and other waste in the project area

Partial

No dust curtains/net have been installed. Not yet necessary. This will be installed at the outlet portal area once excavation activities commence and measured air duality parameters such as total suspended particles and PM 10 are almost near the standard limits of air quality.

Dust suppression such as watering of road has been implemented already.

Open burning is not practiced onsite. ALL CMC drivers have defensive driving training. It is observed that speed limit along Ipo road was not followed mostly by the community.

Page 34: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

27

Environmental Aspect

Potential Impact Possible Approach/ Mitigating Measures

Compliance Status

Remarks

• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day • burning of vegetation and wastes; and • operation of mechanical equipment

· Ipo Road, main access road, other roads in the Project area, limit speed of all construction vehicles to maximum of 40 kph on the access road to, and maximum of 30 kph in the site · Control noise at source, e.g. low noise plant, muffling, acoustic screening, switch off campaigns · Restrict use of noisy and highly vibrating equipment from 8AM-5PM. Necessary overtime work should: a) not go beyond 9:00PM; b) observe regulated noise and vibration levels; c) not use noisy and highly vibrating equipment; and d) should be coordinated with the barangay and affected households. · Manage the ins and outs of hauling trucks. Spread out the schedule of material, waste and spoil transport in the day (off-peak hours). .· Enforce the rule of no blowing of horns. · Strictly enforce upon workers the compliance with wearing of ear mufflers, especially those who are operating equipment.

Agreement with CRL Laboratories for air quality monitoring is now in place (24 August 2017). The air quality sampling dates will be scheduled once the Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

February 6-8, 2018

May 8-10, 2018

August 7-9, 2018

November 6-8, 2018

February 5-7, 2019

Biological Environment

Loss of vegetation due to:

· Provide environmental training for workforce

Non-Compliant

No environmental training for workforce has been done yet The workforce has been made aware of the company’s policy against

Page 35: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

28

Environmental Aspect

Potential Impact Possible Approach/ Mitigating Measures

Compliance Status

Remarks

• vegetation clearing and potential trampling of trucks/equipment beyond project footprints • Over-clearance and damage to vegetation around the construction sites

collection, transportation and selling of wildlife and endangered forest species.

Page 36: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

29

Table 19. Summary of Environmental Mitigations and Compensation Measures Implemented

EMP Requirement (list all mitigation

measures specified in the

EMP/CEMP/SEMP)

Compliance Attained

Location

Comment on Reasons for Partial or Non-Compliance

Required Action and Target Dates to Achieve Compliance

1. Water Quality Monitoring

Compliant Ipo and Bigte River

Visual monitoring through photograph and Video documentation. The first water quality sampling was conducted by CMC last August 2017 with the following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS, ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals. Water quality in the basin has also been collected and analyzed last December 2017 with the following parameters: temperature,TSS, electric conductivity, turbidity, color and TDS. Weekly monitoring of water turbidity using portable turbidimeter started on October 2017. Testing is done weekly by CMC Envi, Health and Safety Officers

2. Air quality monitoring

Partial Agreement with CRL Laboratories for air quality monitoring is now in place (24 August 2017). The air quality sampling dates will be scheduled once the Tunnel Excavation starts. A sound level meter was procured by CMC to monitor the noise level during construction period as one of the requirements of ADB and

Air quality monitoring will be done quarterly. Target date of air quality monitoring are as follows: -February 6-8,2018 -May 8-10, 2018 -August 7-9,2018 -November 6-8, 2018 -February 5-7, 2019

Page 37: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

30

EMP Requirement (list all mitigation

measures specified in the

EMP/CEMP/SEMP)

Compliance Attained

Location

Comment on Reasons for Partial or Non-Compliance

Required Action and Target Dates to Achieve Compliance

DENR. Noise monitoring started on 28 October 2017.

3. Freshwater ecology monitoring

Partial Request for quotation for the conduct of the water quality has been sent to CRL Laboratories.

Target date of freshwater ecology monitoring is on April and August 2018-2019

4. Social and Economic Survey

Partial Socio-economic survey currently being discussed with an IP Specialist/ Anthropologist (Mr Joseph Lalo)

Target date of socio economic survey is on September 2018

5. Social and environmental awareness

Partial Residences near construction area and tunnel ROW

Bulletin boards for IEC purpose were installed in the barangay halls of Brgy Bigte and San Mateo on June 19-20, 2017. Third letter to NCIP in relation to FPIC application was sent on 15 June 2017.

IEC will be done to students and residents should there be major construction activities, deliveries of large goods, notice of employment requirement starting July 2017.

6. Public Health and safety

Compliant Health and safety staff are hired. Detailed grievance procedure was formulated on July 2017.

Page 38: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

31

4.1 Emission/Wastewater Discharge (Source) Monitoring Program (if

relevant or required in the EMP)

4.1.1 Summary of Monitoring No sampling has done yet.

4.1.2 Results No results are available yet.

4.1.3 Assessment10

4.2 Water Quality Monitoring Program

4.2.1 Summary of Water Quality Monitoring for Bigte and Ipo River (August, December

2017)

Fresh water quality sampling along Angat River and laboratory inspection

in CRL Laboratory in Clark, Pampanga was carried out 30 August 2017 by

Selam Tesfaye, Rusty Romero and Pam Constante. A total of 4 samples

were collected. Due to heavy rains, the samples in Bigte Creek and Sta

Maria River was collected in 5 September 2017.

The water quality sampling activity in Bigte area on 31 August 2017 was

aborted due to heavy rains. It was done in 5 September 2017.

A portable turbidimeter was purchased by CMC to conduct a daily turbidity

monitoring at the water bodies near the construction sites in December

2017.

Video and photo documentation along Ipo River (Angat River) is ongoing

while procurement of water quality instrument and laboratory analyses

service is in progress.

4.2.2 Results of Bigte and Ipo River (August, December 2017)

Below are sampling points and complete laboratory results of the water

quality samples collected in August and September.

Complete results were transmitted in October 2017. Measures in red are

parameters with exceedances according to DAO 2016-08. The results

presented were compared with the baseline (2013 wet season).

10 Discharge levels should be compared to the relevant discharge standards and/or performance indicators noted in

the EMP. Any exceedances should be highlighted for attention and follow-up. In addition, discharge levels could be compared to baseline conditions (if baseline data is available) and described in qualitative terms or be evaluated based on a ranking system, such as the following:

1. Very Good (overall conditions are generally improved) 2. Good (conditions are maintained or slightly improved) 3. Fair (conditions are unchanged) 4. Poor (conditions are moderately degraded) 5. Very Poor (conditions are significantly degraded)

Additional explanatory comments should be provided as necessary.

Page 39: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

32

Figure 15. The sampling locations (Bigte and Ipo Rivers)

Page 40: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

33

Figure 16. Sampling points in Bigte River

Page 41: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

34

Figure 17. Sampling points in Ipo River

Page 42: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

35

4.2.3 Water Quality Results for Bigte River (August and December 2017)

Table 20. Water Quality Results for SWB1

Parameter Adopted Criteria (Class B DAO

2016-08) Reference

SW BIGTE1/SWB1

Bigte Creek near the basin 2 in Bigte Portal. This site is near the outlet.

N14° 51.538’ E121° 05.453’

Year/ quarter 2013 WET

(May to Oct.) 2014 DRY

(Nov. to Apr.) 2017 AUG.

2017 DEC.

Physical Characteristics

Temp (°C) 26-30 DAO 2016-08 27.4 27.5 25 25

Salinity (%) - parameter not included in DAO 2016-08 14.62 13.91 7

TSS (mg/L) 65 DAO 2016-08 130.5 130.5

Electric Cond. (mS/cm) - parameter not included in DAO 2016-08 228.5 217.3 270 -

Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC

5.66 5.26 13 0.25

Colour (Apparent, PCU) 50 DAO 2016-08, class B 15 15 20 8

TDS (mg/L) - parameter not included in DAO 2016-08 146.9 12 155 89

pH 6.50-8.50 DAO 2016-08 8.7 7.93 8

Inorganic and Non-metallic Constituents

Nitrogen (as NO₃¯) (mg/L) 7 DAO 2016-08 0.1 0.02 1

Oxidation Reduction Potential ORP (mV)

- parameter not included in DAO 2016-08 195 217.2 144

Phosphorus (as PO₄³¯) (mg/L) 0.5 DAO 2016-08 0.03 0.4 0

Organic and Biological Constituents

Page 43: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

36

Parameter Adopted Criteria (Class B DAO

2016-08) Reference

SW BIGTE1/SWB1

Bigte Creek near the basin 2 in Bigte Portal. This site is near the outlet.

N14° 51.538’ E121° 05.453’

Year/ quarter 2013 WET

(May to Oct.) 2014 DRY

(Nov. to Apr.) 2017 AUG.

2017 DEC.

Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 14.4 4.21 8

BOD5 (mg/L) 5 DAO 2016-08 1 1 2

COD (mg/L) - parameter not included in DAO 2016-08 20 9.8 13

Fecal Coliform (MPN/100mL) 100 DAO 2016-08 92,000 1,700 16,000

Total Coliform (MPN/100mL) - parameter not included in DAO 2016-08 54,000 16,000 24,000

Oil and Grease (mg/L) 1 DAO 2016-08 0.5 0.4 0.4

Elements

Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.001

Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.01 <0.01

Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.006 <0.006

Chromium (hexavalent, Cr(VI)), (mg/L)

0.01 DAO 2016-08 <0.003 <0.003

Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.02 <0.02

Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05 <0.04

Manganese (Mn), (mg/L) 0.2 DAO 2016-08 0.01 0.1

Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0001

Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.03 <0.03 <0.03

Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 <1.0

Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.02 <0.007

Page 44: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

37

Table 21. Water Quality Results for SWB2

Parameter Adopted Criteria

Reference

SW03/SWB2

Bigte Creek, within the Salonga Property. The site near Sitio Settling

N14° 51.526 E121° 05.330’

Year/ Quarter

2013 WET (May to Oct.)

2014 DRY (Nov. to Apr.)

2017 AUG.

2017 DEC.

Physical Characteristics

Temp (°C) 26-30 DAO 2016-08 27 27.1 25 26.1

Salinity (%) - parameter not included in DAO 90-34 14.06 12.16 8.2

TSS (mg/L) 65 DAO 2016-08 - 12

Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 219.7 190 497 426.6

Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 12.8 24.1 10.86 5.63

Colour (Apparent, PCU) 50 DAO 2016-08, class B 20 10 15

TDS (mg/L) - parameter not included inDAO 2016-08 141.1 120.4 306 278.7

pH 6.50-8.50 DAO 2016-08 8.33 8.12 7.5

Inorganic and Non-metallic Constituents

Nitrogen (as NO₃¯) (mg/L) 7 DAO 2016-08 0.02 0.02 0.4

Oxidation Reduction Potential ORP (mV)

- parameter not included in DAO 2016-08 82 82 141

Phosphorus (as PO₄³¯) (mg/L) 0.5 DAO 2016-08 0.01 0.01 0.09

Organic and Biological Constituents

Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 22.5 8.18 7.7

BOD5 (mg/L) 5 DAO 2016-08 1 1 3

COD (mg/L) - parameter not included in DAO 2016-08 9.8 9.8 7.3

Page 45: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

38

Parameter Adopted Criteria

Reference

SW03/SWB2

Bigte Creek, within the Salonga Property. The site near Sitio Settling

N14° 51.526 E121° 05.330’

Year/ Quarter

2013 WET (May to Oct.)

2014 DRY (Nov. to Apr.)

2017 AUG.

2017 DEC.

Fecal Coliform (MPN/100mL) 100 DAO 2016-08 9,200 1,700 35,000

Total Coliform (MPN/100mL) - parameter not included in DAO 2016-08 92,000 16,000 92,000

Oil and Grease (mg/L) 1 DAO 2016-08 0.3 0.4 0.4

Elements

Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.001

Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.01 <0.01

Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.006 <0.006

Chromium (hexavalent, Cr(VI)), (mg/L)

0.01 DAO 2016-08 <0.003 <0.003

Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.02 <0.02

Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.05 <0.05 <0.05

Manganese (Mn), (mg/L) 0.2 DAO 2016-08 0.07 0.2

Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0001

Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.03 <0.03 <0.03

Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 <1.0

Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.02 <0.007

Page 46: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

39

Table 22. Water Quality Results for SWB3

Parameter Adopted Criteria

Reference

SWB3

Baltazar bridge. This is the bridge pass the Barangay Bigte Hall

N14° 51.272’ E121° 05.144

Year/ quarter 2013 WET

(May to Oct.) 2014 DRY

(Nov. to Apr.) 2017 AUG.

2017 DEC.

Physical Characteristics Temp (°C) 26-30 DAO 2016-08 28.2 - 25 26.3

Salinity (%) - parameter not included in DAO 2016-08 - - 7.4

TSS (mg/L) 65 DAO 2016-08 - - -

Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 376 - 441 322.6

Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 25.4 - 10.44 6.96

Colour (Apparent, PCU) 50 DAO 2016-08, class B - 15

TDS (mg/L) - parameter not included in DAO 2016-08 244.8 - - 208.2

pH 6.50-8.50 DAO 2016-08 7.94 - 7.9

Inorganic and Non-metallic Constituents

Nitrogen (as NO₃¯) (mg/L) 7 DAO 2016-08 - - 0.5

Oxidation Reduction Potential ORP (mV)

- parameter not included in DAO 2016-08 251 - 140

Phosphorus (as PO₄³¯) (mg/L) 0.5 DAO 2016-08 - - 0.2

Organic and Biological Constituents - - -

Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 - - 8.3

BOD5 (mg/L) 5 DAO 2016-08 - - 1

Page 47: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

40

Parameter Adopted Criteria

Reference

SWB3

Baltazar bridge. This is the bridge pass the Barangay Bigte Hall

N14° 51.272’ E121° 05.144

Year/ quarter 2013 WET

(May to Oct.) 2014 DRY

(Nov. to Apr.) 2017 AUG.

2017 DEC.

COD (mg/L) - parameter not included in DAO 2016-08 - - 12

Fecal Coliform (MPN/100mL) 100 DAO 2016-08 - - 24000

Total Coliform (MPN/100mL) - DAO 2016-08 - - 24000

Oil and Grease (mg/L) 1 DAO 2016-08 - - 0.5

Elements

Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 - -

Arsenic (As), (mg/L) 0.01 DAO 2016-08 - - <0.01

Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 - - <0.006

Chromium (hexavalent, Cr(VI)), (mg/L)

0.01 DAO 2016-08 - -

Copper (Cu), (mg/L) 0.02 DAO 2016-08 - - <0.02

Lead (Pb), (mg/L) 0.01 DAO 2016-08 - - <0.05

Manganese (Mn), (mg/L) 0.2 DAO 2016-08 - -

Mercury (Hg), (mg/L) 0.001 DAO 2016-08 - -

Nickel (Ni), (mg/L) 0.04 DAO 2016-08 - - <0.03

Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 - -

Zinc (Zn), (mg/L) 2 DAO 2016-08 - - <0.007

Page 48: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

41

Table 23. Water Quality Results for SWSM1

Parameter Adopted Criteria

reference

STA MARIA 03/SWSM1 In Sta Maria River, within the vicinity of San Jose Bridge

N14° 50.123’ E121° 04.47’1’

Year/ quarter 2013 WET

(May to Oct.) 2014 DRY

(Nov. to Apr.) 2017 AUG.

2017 DEC.

Physical Characteristics Temp (°C) 26-30 DAO 2016-08 27.3 32.3 24.9 27.9

Salinity (%) - parameter not included in DAO 90-34 15.74 13

TSS (mg/L) 65 DAO 2016-08 657 32

Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 246 450.8 355 366.4

Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 51.4 12.1 19.33 4.23

Colour (Apparent, PCU) 50 DAO 2016-08, class B 500 20

TDS (mg/L) - parameter not included in DAO 2016-08 158 292.5 207 238.2

pH 6.50-8.50 DAO 2016-08 8.2 7.64 7.9

Inorganic and Non-metallic Constituents

Nitrogen (as NO₃¯), (mg/L) 7 DAO 2016-08 0.1 0.6 1

ORP (mV) - parameter not included in DAO 2016-08 187 156 138

Phosphorus (as PO₄³¯), (mg/L) 0.5 DAO 2016-08 0.7 0.3 0.2

Organic and Biological Constituents

Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 not measured 2.07 7.7

BOD5 (mg/L) 5 DAO 2016-08 14 1 2

COD (mg/L) - parameter not included in DAO 2016-08 49 49 9.3

Fecal Coliform (MPN/100mL) 100 DAO 2016-08 920,000 31,000 24,000

Page 49: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

42

Parameter Adopted Criteria

reference

STA MARIA 03/SWSM1 In Sta Maria River, within the vicinity of San Jose Bridge

N14° 50.123’ E121° 04.47’1’

Year/ quarter 2013 WET

(May to Oct.) 2014 DRY

(Nov. to Apr.) 2017 AUG.

2017 DEC.

Total Coliform (MPN/100mL) - DAO 2016-08 920,000 31,000 24,000

Oil and Grease (mg/L) 1 DAO 2016-08 <0.3 0.7 0.4

Elements

Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.001

Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.01 <0.01

Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.006 <0.006

Chromium (hexavalent, Cr(VI)), (mg/L)

0.01 DAO 2016-08 <0.003 <0.003

Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.02 <0.02

Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.04 <0.05

Manganese (Mn), (mg/L) 0.2 DAO 2016-08 0.4 0.5

Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0001

Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.01 <0.01 <0.03

Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 <1.0

Zinc (Zn), (mg/L) 2 DAO 2016-08 0.1 <0.02 <0.007

Page 50: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

43

4.2.4 Water Quality Results for IPO River (August 2017)

Water quality monitoring in Ipo was done only in 2017 August. Ipo Site is on ‘stop work status’ as of 7 August 2017.

Table 24. Water Quality Results for SW IPO1

Parameter

Adopted Criteria (Class B DAO

2016-08) Reference

IPO US2/IPO1

Near confluence of Sapang Anginan and Angat River

N14° 53’ 41.6” E121° 10’ 10.8”

Year/ quarter 2013 WET (Baseline)

2017 AUGUST

Physical Characteristics

Temp (°C) 26-30 DAO 2016-08 27.5 25

Salinity (%) - parameter not included in DAO 90-34 8.65 4

TSS (mg/L) 65 DAO 2016-08 - -

Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 135.2 155

Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 1.86 10

Colour (Apparent, PCU) 50 DAO 2016-08, class B - 8

TDS (mg/L) - parameter not included in DAO 2016-08 84.84 91

pH 6.50-8.50 DAO 2016-08 7.88 6.8

Inorganic and non-metallic constituents

Nitrogen (as NO₃¯) (mg/L) 7 DAO 2016-08 - 0.2

Oxidation Reduction Potential ORP (mV)

- parameter not included in DAO 2016-08 210 134

Phosphorus (as PO₄³¯) (mg/L)

0.5 DAO 2016-08 - 0.05

Page 51: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

44

Parameter

Adopted Criteria (Class B DAO

2016-08) Reference

IPO US2/IPO1

Near confluence of Sapang Anginan and Angat River

N14° 53’ 41.6” E121° 10’ 10.8”

Year/ quarter 2013 WET (Baseline)

2017 AUGUST

Organic and Biological Constituents

Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 - 8.7

BOD5 (mg/L) 5 DAO 2016-08 210 1

COD (mg/L) - parameter not included in DAO 2016-08 - 3

Fecal Coliform (MPN/100mL)

100 DAO 2016-08 - 17

Total Coliform (MPN/100mL)

- parameter not included in DAO 2016-08 210 240

Oil and Grease (mg/L) 1 DAO 2016-08 - 0.05

Elements

Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.008

Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.01

Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.003

Chromium (hexavalent, Cr(VI)), (mg/L)

0.01 DAO 2016-08 not measured not measured

Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.01

Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05

Manganese (Mn), (mg/L) 0.2 DAO 2016-08 not measured not measured

Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0002

Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.01 <0.03

Page 52: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

45

Parameter

Adopted Criteria (Class B DAO

2016-08) Reference

IPO US2/IPO1

Near confluence of Sapang Anginan and Angat River

N14° 53’ 41.6” E121° 10’ 10.8”

Year/ quarter 2013 WET (Baseline)

2017 AUGUST

Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 0.008

Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.007

Bromide (Br), (mg/L) - 4.1 not measured

Table 25. Water Quality Results for SW IPO2

Parameter Adopted Criteria (Class B DAO

2016-08) Reference

IPO 4/SW IPO2

Near confluence of Sapang Munti and Angat River

N14° 52’ 22.3” E121° 10’ 05.6”

Year/ quarter 2013 WET (Baseline) 2017

AUGUST

Physical Characteristics

Temp (°C) 26-30 DAO 2016-08 31.8 25

Salinity (%) - parameter not included in DAO 2016-08

9.76 2.4

TSS (mg/L) 65 DAO 2016-08 - -

Electric Cond. (mS/cm) b

- parameter not included in DAO 2016-08

152.5 151

Page 53: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

46

Parameter Adopted Criteria (Class B DAO

2016-08) Reference

IPO 4/SW IPO2

Near confluence of Sapang Munti and Angat River

N14° 52’ 22.3” E121° 10’ 05.6”

Year/ quarter 2013 WET (Baseline) 2017

AUGUST

Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC

152.5 15

Colour (Apparent, PCU)

50 DAO 2016-08, class B - 10

TDS (mg/L) - parameter not included in DAO 2016-08

95.07 87

pH 6.50-8.50 DAO 2016-08 8.11 7.1

Inorganic and Non-metallic Constituents

Nitrogen (as NO₃¯) (mg/L)

7 DAO 2016-08 - 0.2

Oxidation Reduction Potential ORP (mV)

- parameter not included in DAO 2016-08

253 131

Phosphorus (as PO₄³¯) (mg/L)

0.5 DAO 2016-08 - 0.03

Organic and Biological Constituents

Dissolved Oxygen (mg/L)

5 (minimum) DAO 2016-08 - 8.3

BOD5 (mg/L) 5 DAO 2016-08 - 2

Page 54: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

47

Parameter Adopted Criteria (Class B DAO

2016-08) Reference

IPO 4/SW IPO2

Near confluence of Sapang Munti and Angat River

N14° 52’ 22.3” E121° 10’ 05.6”

Year/ quarter 2013 WET (Baseline) 2017

AUGUST

COD (mg/L) - parameter not included in DAO 2016-08

- 6.4

Fecal Coliform (MPN/100mL)

100 DAO 2016-08 350 33

Total Coliform (MPN/100mL)

- parameter not included in DAO 2016-08

3500 110

Oil and Grease (mg/L)

1 DAO 2016-08 - 0.4

Elements

Antimony (Sb), (mg/L)

- parameter not included in DAO 2016-08

<0.001 <0.008

Arsenic (As), (mg/L)

0.01 DAO 2016-08 <0.01 <0.01

Cadmium (Cd), (mg/L)

0.003 DAO 2016-08 <0.006 <0.003

Chromium (hexavalent, Cr(VI)), (mg/L)

0.01 DAO 2016-08 not measured not

measured

Copper (Cu), (mg/L)

0.02 DAO 2016-08 <0.02 <0.01

Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05

Manganese (Mn), (mg/L)

0.2 DAO 2016-08 not measured not

measured

Page 55: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

48

Parameter Adopted Criteria (Class B DAO

2016-08) Reference

IPO 4/SW IPO2

Near confluence of Sapang Munti and Angat River

N14° 52’ 22.3” E121° 10’ 05.6”

Year/ quarter 2013 WET (Baseline) 2017

AUGUST Mercury (Hg), (mg/L)

0.001 DAO 2016-08 <0.0001 <0.0002

Nickel (Ni), (mg/L)

0.04 DAO 2016-08 <0.01 <0.03

Vanadium (V), (mg/L)

- parameter not included in DAO 2016-08

<1.0 0.008

Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.007

Bromide (Br), (mg/L)

- 2.6 not

measured

Table 26. Water Quality Results for SW IPO3

Parameter

Adopted Criteria (Class B DAO 2016-

08)

Reference

IPO2/SW IPO3

Between the old Ipo Dam structure and intakes of existing tunnels 1,2,3

N14° 52’ 26.9” E121° 10’ 56.5”

Year/ quarter 2013 WET (Baseline)

2017 AUGUST

Physical Characteristics

Page 56: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

49

Parameter

Adopted Criteria (Class B DAO 2016-

08)

Reference

IPO2/SW IPO3

Between the old Ipo Dam structure and intakes of existing tunnels 1,2,3

N14° 52’ 26.9” E121° 10’ 56.5”

Year/ quarter 2013 WET (Baseline)

2017 AUGUST

Temp (°C) 26-30 DAO 2016-08 31.7 25

Salinity (%) - parameter not included in DAO 2016-08 9.68 3.2

TSS (mg/L) 65 DAO 2016-08 - -

Electric Cond. (mS/cm) b - parameter not included in DAO 2016-08 151.3 159

Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC 2.86 17

Colour (Apparent, PCU) 50 DAO 2016-08, class B - 10

TDS (mg/L) - parameter not included in DAO 2016-08 94.43 93

pH 6.50-8.50 DAO 2016-08 8 7.2

Inorganic and Non-metallic Constituents

Nitrogen (as NO₃¯) (mg/L)

7 DAO 2016-08 - 0.2

Oxidation Reduction Potential ORP (mV)

- parameter not included in DAO 2016-08 230 129

Phosphorus (as PO₄³¯) (mg/L)

0.5 DAO 2016-08 - 0.04

Organic and Biological Constituents

Dissolved Oxygen (mg/L) 5 (minimum) DAO 2016-08 - 8.1

Page 57: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

50

Parameter

Adopted Criteria (Class B DAO 2016-

08)

Reference

IPO2/SW IPO3

Between the old Ipo Dam structure and intakes of existing tunnels 1,2,3

N14° 52’ 26.9” E121° 10’ 56.5”

Year/ quarter 2013 WET (Baseline)

2017 AUGUST

BOD5 (mg/L) 5 DAO 2016-08 - 1

COD (mg/L) - parameter not included in DAO 2016-08 - 9.4

Fecal Coliform (MPN/100mL)

100 DAO 2016-08 350 280

Total Coliform (MPN/100mL)

- parameter not included in DAO 2016-08 3500 280

Oil and Grease (mg/L) 1 DAO 2016-08 - 0.4

Elements

Antimony (Sb), (mg/L) - parameter not included in DAO 2016-08 <0.001 <0.008

Arsenic (As), (mg/L) 0.01 DAO 2016-08 <0.01 <0.1

Cadmium (Cd), (mg/L) 0.003 DAO 2016-08 <0.006 <0.003

Chromium (hexavalent, Cr(VI)), (mg/L)

0.01 DAO 2016-08 not measured not measured

Copper (Cu), (mg/L) 0.02 DAO 2016-08 <0.02 <0.01

Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05

Manganese (Mn), (mg/L) 0.2 DAO 2016-08 not measured not measured

Mercury (Hg), (mg/L) 0.001 DAO 2016-08 <0.0001 <0.0002

Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.01 <0.03

Vanadium (V), (mg/L) - parameter not included in DAO 2016-08 <1.0 0.008

Page 58: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

51

Parameter

Adopted Criteria (Class B DAO 2016-

08)

Reference

IPO2/SW IPO3

Between the old Ipo Dam structure and intakes of existing tunnels 1,2,3

N14° 52’ 26.9” E121° 10’ 56.5”

Year/ quarter 2013 WET (Baseline)

2017 AUGUST

Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.007

Bromide (Br), (mg/L) - 2.5 not measured

Page 59: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

52

Table 27. Water Quality Results for SW IPO4

Parameter

Adopted Criteria (Class B DAO 2016-

08)

Reference

IPO DS2/SW IPO4

~ 350m downstream of Ipo Dam N14° 52’ 36.8” E121° 10’

42.3”

Year/ quarter 2013 WET 2017

AUGUST

Physical Characteristics

Temp (°C) 26-30 DAO 2016-08 31.3 25

Salinity (%) - parameter not included in DAO 2016-08

9.7 2.4

TSS (mg/L) 65 DAO 2016-08 - Electric Cond. (mS/cm) b

- parameter not included in DAO 2016-08

151.5 158

Turbidity (NTU) 20 EP (Water Quality) Policy 2003, ANZECC

6.43 34

Colour (Apparent, PCU)

50 DAO 2016-08, class B - 15

TDS (mg/L) - parameter not included in DAO 2016-08

94.46 90

pH 6.50-8.50 DAO 2016-08 7.81 7.4

Inorganic and Non-metallic Constituents

Nitrogen (as NO₃¯) (mg/L)

7 DAO 2016-08 - 0.2

Oxidation Reduction Potential ORP (mV)

- parameter not included in DAO 2016-08

186 129

Page 60: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

53

Parameter

Adopted Criteria (Class B DAO 2016-

08)

Reference

IPO DS2/SW IPO4

~ 350m downstream of Ipo Dam N14° 52’ 36.8” E121° 10’

42.3”

Year/ quarter 2013 WET 2017

AUGUST Phosphorus (as PO₄³¯) (mg/L)

0.5 DAO 2016-08 - 0.04

Organic and Biological Constituents

Dissolved Oxygen (mg/L)

5 (minimum) DAO 2016-08 - 9.5

BOD5 (mg/L) 5 DAO 2016-08 - 2

COD (mg/L) - parameter not included in DAO 2016-08

- 4

Fecal Coliform (MPN/100mL)

100 DAO 2016-08 350 5,400

Total Coliform (MPN/100mL)

- parameter not included in DAO 2016-08

9,200.00 5,400

Oil and Grease (mg/L)

1 DAO 2016-08 - 0.5

Elements

Antimony (Sb), (mg/L)

- parameter not included in DAO 2016-08

<0.001 <0.008

Arsenic (As), (mg/L)

0.01 DAO 2016-08 <0.01 <0.01

Cadmium (Cd), (mg/L)

0.003 DAO 2016-08 <0.006 <0.003

Page 61: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

54

Parameter

Adopted Criteria (Class B DAO 2016-

08)

Reference

IPO DS2/SW IPO4

~ 350m downstream of Ipo Dam N14° 52’ 36.8” E121° 10’

42.3”

Year/ quarter 2013 WET 2017

AUGUST Chromium (hexavalent, Cr(VI)), (mg/L)

0.01 DAO 2016-08 not

measured not measured

Copper (Cu), (mg/L)

0.02 DAO 2016-08 <0.02 <0.01

Lead (Pb), (mg/L) 0.01 DAO 2016-08 <0.04 <0.05

Manganese (Mn), (mg/L)

0.2 DAO 2016-08 not

measured not measured

Mercury (Hg), (mg/L)

0.001 DAO 2016-08 <0.0001 <0.0002

Nickel (Ni), (mg/L) 0.04 DAO 2016-08 <0.01 <0.03

Vanadium (V), (mg/L)

- parameter not included in DAO 2016-08

<1.0 0.008

Zinc (Zn), (mg/L) 2 DAO 2016-08 <0.02 <0.007

Bromide (Br), (mg/L)

- 1.6 not measured

Page 62: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

55

4.2.5 Assessment11 of Bigte and Ipo River (August, December 2017)

For Bigte River, only fecal and total coliform were reported in all the

sampling locations (SWB1, SWB2, SWB3 and SWSM1) and exceeded the

DENR 2016-08 standards during the 2017 August-September sampling

period. SWB2 had the highest reported fecal and total coliform with 35,000

and 92,000 respectively. In comparison to the baseline data (2013 wet

season data), total and fecal coliform results have decreased in all the

sampling locations except from SWB3 and fecal coliform at SWB2.

All in-situ parameters measured in Bigte River during the 2017 December

sampling did not exceeded the DENR 2016-08 standard.

For Ipo River, all sampling locations had fecal and total coliform but only

SW IPO4 exceeded the DENR 2016-08 standard with 5,400 (both total and

fecal coliform). In comparison to the baseline data (2013 wet season data),

fecal coliform has increased while total coliform has decreased in SW IPO4.

4.2.6 Summary of Water Quality Assessment in Basin 1(October 2017)

A sample from Basin 1 was collected last October 2017 to establish baseline

data since these water will be used in the construction of the tunnel and

will be treated afterwards in the water treatment plant. Samples were

collected by Selamawit Tesfaye and a representative from CRL

Laboratories.

4.2.7 Results of Water Quality Assessment in Basin 1 (October 2017)

Table 28. Water Quality Results for Basin 1

Parameter Adopted

Criteria Reference Basin 1 Remarks

Physical Characteristics

Temp (°C) 26-30 DAO 2016-08 25

Salinity (%) b - parameter not included

in DAO 2016-08 3.3

TSS - DAO 2016-08 152

11 Ambient environmental conditions should be compared to the relevant ambient standards and/or performance

indicators noted in the EMP. Any exceedances should be highlighted for attention and follow-up. In addition, ambient environmental conditions could be compared to the baseline conditions (if baseline data is available) and described in qualitative terms or be evaluated based on a ranking system, such as the following:

1. Very Good (overall conditions are generally improved) 2. Good (conditions are maintained or slightly improved) 3. Fair (conditions are unchanged) 4. Poor (conditions are moderately degraded) 5. Very Poor (conditions are significantly degraded)

Additional explanatory comments should be provided as necessary.

Page 63: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

56

Electric Cond.

(mS/cm) b -

parameter not included

in DAO 2016-08 -

Turbidity (NTU) b 20 EP (Water Quality) Policy

2003, ANZECC 0.25

Colour (Apparent,

PCU) 50 DAO 2016-08, class B 8

TDS (mg/L) - parameter not included

in DAO 2016-08 89

pH 6.50-8.50 DAO 2016-08 -

Inorganic and non-metallic constituents

Nitrogen (as

NO₃¯) (mg/L) 7 DAO 2016-08 4.8

ORP (mV) - parameter not included

in DAO 2016-08 147

Phosphorus (as

PO₄³¯), (mg/L) 0.5 DAO 2016-08 0.03

organic and biological constituents

Dissolved Oxygen

(mg/L) 5 (minimum) DAO 2016-08 8

Higher value

than 5 mg/L is

preferred. This

value of DO is

very much

acceptable.

Higher DO

value, better

water quality

BOD5 3 DAO 2016-08 1

COD b - parameter not included

in DAO 2016-08 9

Faecal Coliform

(MPN/100mL) b 100 DAO 2016-08 49

Total Coliform

(MPN/100mL) 5000 DAO 2016-08 350

Oil and Grease

(mg/L) 1 DAO 2016-08 1

4.2.8 Assesment2 of Water Quality in Basin 1 (October 2017)

The water from Basin 1 will be the water source for the TBM water

requirement. All parameters in Basin 1 did not exceeded the DENR

2016-08 standard.

4.2.9 Turbidity Monitoring Summary (October to December 2017)

A portable turbidimeter was purchased by CMC to conduct a daily turbidity

monitoring at the water bodies near the construction sites.

Page 64: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

57

4.2.10 Results of Turbidity Monitoring (October – December 2017)

Below are the results of the turbidity monitoring from October –

December 2017. Results in red font indicate elevated turbidity values

compared to 20 NTU limit (EP (Water Quality) Policy 2003, ANZECC).

Table 29. Turbidity monitoring results from October to December 2017

Date Time Location Turbidity (NTU) Remarks

October 2017

28 Oct 2017 08:30 AM Portal Area

(0+300)

19.4 Heavy rain is noted

the night before

the collection of

water sample.

28 Oct 2017 08:42 AM Portal Area (0+

220)

33.23 Heavy rain is noted

the night before

the collection of

water sample.

28 Oct 2017 09:00 AM Industrial Area

(0+020)

28.45 Heavy rain is noted

the night before

the collection of

water sample.

28 Oct 2017 09:10 AM Industrial Area

(0+000)

31.7 Heavy rain is noted

the night before

the collection of

water sample.

November 2017

4 Nov 2017 7:30 AM Portal Area

(0+300)

8.17 Heavy rain is noted

the night before

the collection of

water sample.

4 Nov 2017 7:40 AM Portal Area

(0+20)

38.84 Heavy rain is noted

the night before

the collection of

water sample.

4 Nov 2017 08:10 AM Industrial Area

(0+020)

29.47 Heavy rain is noted

the night before

the collection of

water sample.

4 Nov 2017 08:15 Industrial Area

(0+000)

32.29 Heavy rain is noted

the night before

the collection of

water sample.

11 Nov 2017 7:30 AM Portal Area

(0+300)

18.57 Heavy rain is noted

the night before

the collection of

water sample

11 Nov 2017 7:40 AM Portal Area

(0+20)

18.18 Fine weather

during sampling

11 Nov 2017 08:10 AM Industrial Area

(0+020)

13.62 Fine weather

during sampling

Page 65: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

58

11 Nov 2017 08:15 AM Industrial Area

(0+000)

12.18 Fine weather

during sampling

17 Nov 2017 07:45 AM Portal Area

(0+300)

10.37 Fine weather

during sampling

17 Nov 2017 07:55 AM Portal Area

(0+20)

11.11 Fine weather

during sampling

17 Nov 2017 08:30 AM Industrial Area

(0+020)

16.49 Fine weather

during sampling

17 Nov 2017 08:35 AM Industrial Area

(0+000)

17.06 Fine weather

during sampling

24 Nov 2017 08:00 AM Portal Area

(0+300)

17.62 Cloudy

24 Nov 2017 08:15 AM Portal Area

(0+20)

18.88 Cloudy

24 Nov 2017 08:35 AM Industrial Area

(0+020)

17.63 Cloudy

24 Nov 2017 08:50 AM Industrial Area

(0+000)

17.42 Cloudy

December 2017

1 Dec 2017 07:45 AM Portal Area

(0+300)

13.81 Sunny

1 Dec 2017 08:00 AM Portal Area

(0+20)

13.23 Sunny

1 Dec 2017 08:20 AM Industrial Area

(0+020)

12.69 Sunny

1 Dec 2017 08:30 AM Industrial Area

(0+000)

12.01 Sunny

8 Dec 2017 07:30 AM Portal Area

(0+300)

12.24 Cloudy

8 Dec 2017 07:35 AM Portal Area

(0+20)

13.85 Cloudy

8 Dec 2017 07:45 AM Industrial Area

(0+020)

10.22 Cloudy

8 Dec 2017 08:00 AM Industrial Area

(0+000)

112.4 Cloudy

4.3 Air and Noise Quality Monitoring Program

4.3.1 Summary of Air and Noise Quality Monitoring (July- December 2017)

Agreement with CRL Laboratories for air quality monitoring is now in

place (24 August 2017). The air quality sampling dates will be scheduled

once the Tunnel Excavation starts.

A sound level meter was procured by CMC to monitor the noise level

during construction period as one of the requirements of ADB and DENR.

Noise monitoring started on 28 October 2017.

Page 66: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

59

4.3.2 Result of Noise Level Monitoring (October-December 2017)

Below are the noise level measurement at the different locations onsite:

Table 30. Noise level monitoring results (October-December 2017)

Date Time Location Equipment Noise level

(db)

October 2017

28 Oct 2017 7:50 AM Industrial area Genset,

excavator,

grinding

78.1-83.8

28 Oct 2017 08:10 AM Industrial area,

near the gate

Genset,

excavator,

crane, forklift is

within the 20

meter radius

area

77.9-83.5

28 Oct 2017 08:33 AM RCBC/Reaction

Slab

Excavator,

drilling

machine, is

within the 30

meter radius

area

70.3-86.6

28 Oct 2017 08:50 AM In between Basin

1 and 2

Compressor for

drilling

machine, is

within the 30

meter radius

area.

71.3-79.9

28 Oct 2017 09:01 AM In front of clinic Concreting

work with

concrete mixer.

62.9-70.1

November 2017

11 Nov 2017

10:00 AM Portal Area Generator 76.4-79.9

Backhoe/Crane 78-93.8

Concrete Mixer 86.3-92

Residential Area 66.5-85.1

10:39 AM Industrial Area Genset 77.3-86.3

Grinder 79.6-89.3

10:50 AM Tippler Area Excavator 67.5-84

23 Nov 2017 Near Basin 1 58.9-63.2

Portal Rock Breaking 67.3-78.4

FA Station 56.9-69.5

Industrial Area Gen Set 73.1-74.9

Industrial Area

Gate

Road Vehicle 55.7-78.3

Along the Rail

Road

52.6-60.9

24 Nov 2017 7:54 AM Near MWSS

Office

Excavator 71.6-90.1

Page 67: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

60

Portal Area Excavator 61.1-92.2

8:51 AM Warehouse Area Circular Saw 67-90.1

8:54 AM Water

Treatment Area

55.2-61.4

09:01 AM Segment Staging

Area

Forklift 64.3-73.8

09:04 AM Near Trippler Chainsaw 56.6-95.6

December 2017

1 Dec 2017 7:50 AM Portal Area Excavator 66.8-82.8

08:10 AM Warehouse/Fab

shop

Truck 66.8-68.5

08:25 AM Entrance Gate

(Industrial)

64.5-83

08:47 AM Sta 000 64.2-86.6

09:14 AM Fab Shop Grinder 68.2-93.7

10:00 AM Tippler/Commun

ity Area

63-68.4

13 Dec 2017 08:00 AM Office Area Backhoe/Loader 70.9-76.2

08:10 AM MWSS Breaker 65.1-87.8

08:17 AM Portal

Community

Houses

53.5-76.2

08:36 AM Railroad going to

Tippler

Welding

Machine

69.3-84.5

8:44 AM Box Culvert 62.4-67.4

09:00 AM Tippler Area 61.5-74.3

4.3.3 Assesment3 for Noise Quality Monitoring (October-December 2017)

The results are compared to WHO guidelines.

Table 31. WHO guidelines for noise quality

Reference / Jurisdiction Ambient Standard

Guidelines for Community Noise, WHO, 1999

International

Receptor: Residential; institutional; educational

Daytime (07:00-22:00): 55dBA

Nighttime (22:00-07:00): 45dBA

Receptor: Industrial; commercial

70dBA throughout the day

The sound level tests show high sound level at the construction site which

is expected due to machines, equipment and laborers at work. The

residential area near the outlet recorded sound reading between the range

of 53.5 -76.2 dB. The results show that noise level within the vicinity

exceeds noise guidelines. No complaints received from the areas.

Page 68: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

61

5 Key Environmental Issues

5.1 Key activities implemented

The following activities are currently implemented:

(i) The following monitoring is being established: Water quality monitoring

o Water quality monitoring started on August 2017. CMC also procured portable turbidimeter and multimeter to take in-situ measurements daily on the established sampling points and bodies of water near the construction sites.

Air and Noise quality monitoring

o Agreement with CRL Laboratories for air quality monitoring is

now in place (24 August 2017). The air quality sampling dates will

be scheduled once the Tunnel Excavation starts. It will be done

quarterly. Target dates of the air quality monitoring are as follows:

February 6-8, 2018

May 8-10, 2018

August 7-9, 2018

November 6-8, 2018

February 5-7, 2019 o A sound level meter was procured by CMC to monitor the noise

level during construction period as one of the requirements of ADB and DENR. Noise monitoring started on 28 October 2017 and will be continuously done weekly.

5.2 Key Issues Identified

Freshwater water ecology monitoring

o Target date of the freshwater monitoring are as follows:

April 2018

August 2018

Social and economic survey

o Target date of the socio-economic survey and monitoring are as

follows:

September 2018

Social and environmental awareness

o Bulletin boards for IEC purpose were installed in the barangay

halls of Brgy Bigte and San Mateo on June 19-20, 2017. Third

letter to NCIP in relation to FPIC application was sent on 15

June 2017. Target date of the social and environmental

awareness campaign for the residents and students will be done

on during:

Started in July 2017 and monthly updates thereafter or

in cases such as employment requirement of the

construction project; and major construction activities

Page 69: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

62

and deliveries of largo goods that will have potential

impact to the environment as well as community health

and safety impact

Public Health and safety

o public health and safety campaign started in September 2017 and

should continue until the end of construction period. This activity

should be continued by MWSS during the operational phase.

Procurement of other laboratory services, consultancy services and surveys is on-

going.

(i) MWSS has no Construction Supervision Engineer Team where an

environment specialist is included. CMC provides environmental and

social technical inputs to the project.

Page 70: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

63

6 Complaints

6.1 Details of Complaint/s Table 32. List of grievances as of December 2017

Valid Grievance Cases 2

Invalid Grievance Cases 0

Unresolved Grievance Case from previous months

0

Pending Valid Grievance Cases 0

Resolved Grievance Cases to date 2

Two grievance cases have been reported as of December 2017.

1. Dumagats expressed their complaint during the FPIC meeting in July 4,

2017 on the turbidity of the water of Ipo River which is caused by the

runoff during heavy rain. The case was investigated by Rusty Romero and

Pamela Constante. There was no rain at the time of investigation.

Localized increase in turbidity is observed. Video / photo documentation

during heavy rain was requested from Danielle Scalaro and Alex Lim to

monitor water turbidity by visual inspection while waiting for the

instruments and water quality sampling. To date, video documents show

that the turbid water comes from Sapang Munti and upstream of Ipo

Dam.

2. A complaint was received on July 18, 2017 by CMC which was filed by

residents of Calle Onse (adjacent to the Industrial Area in Brgy Bigte

regarding the generation of dust and mud along the road. This case was

investigated by CMC H&S together with representative of Calle Onse.

CMC already made provision of a canal across the Industrial Area. The

problem is not attributed solely to CMC but residents addressed grievance

to CMC hoping to get some help. The case was closed and H&S has the

detailed documentation.

Page 71: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

64

7 Conclusion and Recommendation

7.1 Overall Progress of Implementation of Environmental Management

Measures12

The overall progress can be assessed as fair. The project construction

phase started in December 2016. Temporary and major facilities and work

areas have been established from July to December 2017. The TBM already

arrived onsite and will start operating on March 2018. In such construction

activities, potential environmental impacts associated to tunnel

construction per se is yet to be observed until the excavation work will

commence. Water quality monitoring has started on August 2017.

Portable water meters (turbidimeter and multi-meter) have arrived and in-

situ monitoring on established sampling points and water bodies onsite

started on October 2017. For air quality monitoring, agreement with CRL

Laboratories for air quality monitoring is now in place (24 August 2017).

The air quality sampling dates will be scheduled once the Tunnel

Excavation starts. A sound level meter was procured by CMC to monitor

the noise level during construction period Noise monitoring started on

October 2017 and will be continuously done weekly. Other monitoring and

survey services/ consultancy procurement are in progress.

12 Overall sector environmental management progress could be described in qualitative terms or be evaluated based

on a ranking system, such as the following: 1. Very Good 2. Good 3. Fair 4. Poor 5. Very Poor

Additional explanatory comments should be provided as necessary.

Page 72: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

1

8 Appendices

8.1 AWTIP Monitoring Matrix

Page 73: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

2

8.2 Tree Cutting Permits

Page 74: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

3

8.3 Permits and Licenses

Page 75: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

4

8.4 Water Quality Laboratory Results

Page 76: Angat Water Transmission Improvement Project

Angat Water Transmission Improvement Project – Tunnel 4 Semi-annual Environmental Monitoring Report 1

2017 July – December

5

8.5 Grievance Case - Invalid

Page 77: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Soil and Erosion due to:

·   soil disturbance

·   vegetation clearing

Location: Inlet structure and relevant work

sites

Confine soil disturbance and/or vegetation

clearing to pre-defined and planned area that

includes project footprint and needed

easements

Part of project development cost CMC OSP-AWTIP Compliant

Geocomposite steel mesh with anchor bolts has been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

MPR

Inspection Report

(c/o Jasper Cazenas

and Ricky Latunio)

Video documentation

by D Scolaro.

Environment

Inspection Checklist

and Inpection Report

(c/o Jasper Cazenas

and Ricky Latunio)

Soil and Erosion due to:

·   soil disturbance

·   vegetation clearing

Stabilize exposed soils with temporary

seeding, mulches, mats, non-chemical-based

soil binders.

Part of project development cost CMC OSP-AWTIP Compliant

Geocomposite steel mesh with anchor bolts has been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

MPR

Inspection Report

(c/o Jasper Cazenas

and Ricky Latunio)

Video documentation

by D Scolaro.

Environment

Inspection Checklist

and Inpection Report

(c/o Jasper Cazenas

and Ricky Latunio)

Soil and Erosion due to:

·   soil disturbance

·   vegetation clearing

Protect slopes with any one or combination of

bonded fiber matrices, erosion control

blankets, silt fence, fiber rolls, and keeping

stormwater off the slopes through diversion

channels and/or berms.

Part of project development cost CMC OSP-AWTIP Compliant

Geocomposite steel mesh with anchor bolts has been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

MPR

Inspection Report

(c/o Jasper Cazenas

and Ricky Latunio)

Video documentation

by D Scolaro.

Environment

Inspection Checklist

and Inpection Report

(c/o Jasper Cazenas

and Ricky Latunio)

Soil and Erosion due to:

·   soil disturbance

·   vegetation clearing

Re-vegetate disturbed soils/slopes as soon as

possible after completion of the construction

works.

Part of project development cost CMC OSP-AWTIP Not Applicable No vegetation survey has been done yet. To be checked AFTER

COMPLETION OF THE CONSTRUCTION WORKS

Geocomposite steel mesh with anchor bolts has been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Soil and Erosion due to:

·   soil disturbance

·   vegetation clearing

Replacing vegetation that died during the

defects liability period.

Part of project development cost CMC OSP-AWTIP Not Applicable TO BE MONITORED during the DEFECTS LIABILITY PERIOD.

No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

AWTIP Monitoring Matrix - CEMMP

Page 78: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Soil and Erosion due to:

·   soil disturbance

·   vegetation clearing

At the active work sites,

Provide temporary drainage with sedimentation

tank or filters such as block and gravel, prior to

discharge to watercourses

In Progress Water treatment plant is already under construction Work Site Plan

MPR

Inspection Report

(c/o Jasper Cazenas

and Ricky Latunio)

Environment

Inspection Checklist

and Inpection Report

(c/o Jasper Cazenas

and Ricky Latunio)

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

At the active work sites

Mitigating contaminants

·   Provide adequate sanitation facilities and

water supply at work sites and workers’ camp. Enforce observance of good sanitation

practices by workers.

Part of project (construction) cost CMC OSP-AWTIP Compliant High coliform was reported in segment of surface water where there are

communities along the riverbanks prior to the start of construction activities.

Please note that Ipo Construction site was on stop work status since 2017

September.

Portalets are provided and regularly collection is implemented in all construction

sites - Ipo and Bigte.

Waste onsite are segregated into biodegredable, non-biodegradable and

residuals. There are designated bins for each type of waste, color coded and

labeled. Waste are collected every Tuesday and Thursday by Brgy Bigte. CMC

and Brgy Bigte has a service contract for garbage and hauling disposal from May

2017 to December 2017.

The first water quality sampling was conducted by CMC last August 2017 with the

following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,

ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ paramters using portable

water meters started on October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location and results on the report)

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

·   Implement solid waste management that

minimizes, re-uses, properly segregates and

promptly and properly disposes of generated

solid wastes.

Part of project (construction) cost CMC OSP-AWTIP Compliant Waste onsite are segregated into biodegredable, non-biodegradable and

residuals. There are designated bins for each type of waste, color coded and

labeled. Waste are collected every Tuesday and Thursday by Brgy Bigte. CMC

and Brgy Bigte has a service contract for garbage and hauling disposal from May

2017 to December 2017.

The first water quality sampling was conducted by CMC last August 2017 with the

following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,

ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ paramters using portable

water meters started on October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location and results on the report)

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

AWTIP Monitoring Matrix - CEMMP

Page 79: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

·   Implement hazardous waste management

that minimizes, properly segregates and

promptly and properly disposes of generated

hazardous wastes.

Part of project (construction) cost CMC OSP-AWTIP Compliant

Hazmat identified at this stage of construction is limited to oil, lubricants used by

heavy equipment and vehicles. Most vehicles used are brand new. Maintenance

is done off site.

Hazmat temporary storage included in the site plan

The first water quality sampling was conducted by CMC last August 2017 with the

following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,

ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ paramters using portable

water meters started on October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location and results on the report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

hazmat temporary

disposal included in

the Industrial Area

site plan (c/o Sergio

and Federico)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

·   Store hazardous construction materials in

appropriately contained and elevated area and

at least100 m away from surface water bodies.

Part of project (construction) cost CMC OSP-AWTIP Compliant

Hazmat identified at this stage of construction is limited to oil, lubricants used by

heavy equipment and vehicles. Most vehicles used are brand new. Maintenance

is done off site.

Hazmat temporary storage included in the site plan

The first water quality sampling was conducted by CMC last August 2017 with the

following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,

ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ paramters using portable

water meters started on October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location and results on the report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

hazmat temporary

disposal included in

the Industrial Area

site plan (c/o Sergio

and Federico)

Photo-documentation

Turbidity (c/o Jasper

Cazenas and Ricky

Latunio)Monitoring

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

·   Have equipment clearly leaking oil repaired

off-site immediately. No vehicle/equipment

maintenance, repair and refueling to be allowed

at the sites.

Part of project (construction) cost CMC OSP-AWTIP Compliant No equipment reported to have such case

AWTIP Monitoring Matrix - CEMMP

Page 80: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

·   Treat construction water before discharge.

Install settling pond/ water treatment facility

(see annex) for water generated during tunnel

boring. Allow water through grease trap or

oil/collector and/or filters such as rock filled

bags, block and gravel.

Part of project (construction) cost CMC OSP-AWTIP In Progress Please note that water quality parameter exceedances are noted in the baseline

data especially on coliform which was reported in segment of surface water

where there are communities are found along the riverbanks.

Hazmat identified at this stage of construction is limited to oil, lubricants used by

heavy equipment and vehicles. Most vehicles used are brand new. Maintenance

is done off site.

Construction of Waste Water Treatment Facility is on-going.

The first water quality sampling was conducted by CMC last August 2017 with the

following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,

ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Water quality in Basin 1 has also been collected and analyzed last October 2017

with the following parameters: temperature,TSS, electric conductivity, turbidity,

color and TDS (See sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ paramters using portable

water meters started on October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location and results on the report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

·   Implement corrective action, when trigger

thresholds of water quality are reached.

Part of project (construction) cost CMC OSP-AWTIP Compliant The first water quality sampling was conducted by CMC last August 2017 with the

following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,

ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Water quality in Basin 1 has also been collected and analyzed last October 2017

with the following parameters: temperature,TSS, electric conductivity, turbidity,

color and TDS (See sampling location and results on the report).

Weekly monitoring of water turbidity using portable turbidimeter started on

October 2017. Testing is done weekly by CMC Envi, Health and Safety Officers

(See sampling location and results on the report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

·   During construction, the contractor shall take

corrective action to reduce concentration to

below the standard.

Part of project (construction) cost CMC OSP-AWTIP Compliant The first water quality sampling was conducted by CMC last August 2017 with the

following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,

ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Water quality in Basin 1 has also been collected and analyzed last October 2017

with the following parameters: temperature,TSS, electric conductivity, turbidity,

color and TDS (See sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ paramters using portable

water meters started on October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location and results on the report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

AWTIP Monitoring Matrix - CEMMP

Page 81: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

· Mitigating sedimentation

Build cofferdams when building inlet structure

Part of project (construction) cost CMC OSP-AWTIP Not Applicable inlet works not yet started

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

·   Use any combination of perimeter controls

at spoil disposal areas or stockpiles of

aggregate materials, e.g., silt fences, sediment

basins, sandbags, earth bern/bund.

Part of project (construction) cost CMC OSP-AWTIP Compliant The first water quality sampling was conducted by CMC last August 2017 with the

following parameters: Temperature, pH, electric conductivity, tubidity, color, TDS,

ORP, dissolved oxygen, BOD, coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Water quality in Basin 1 has also been collected and analyzed last October 2017

with the following parameters: temperature,TSS, electric conductivity, turbidity,

color and TDS (See sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ paramters using portable

water meters started on October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location and results on the report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Impact on surface water quality due to/

from:

·   Contaminants from materials used and

construction activities and processes

·   Siltation from soil erosion, spoil

disposal area, dewatering excavations, etc

·   Water quality Deterioration of water

quality in Ipo Dam and Bigte river Tributary

during construction

• Minimize / control dewatering or extraction of tunnel water by storing and re-using pumped-

out water from the tunnel.

Part of project (construction) cost CMC OSP-AWTIP Not Applicable

Extraction of water from the dam site

(inlet) and creek (near the outlet) to be

used as coolant during construction

Use efficient tunnelling technology that recycles

tunnel drainage water to minimize extraction of

water.

Part of project (construction) cost CMC OSP-AWTIP In Progress Water treatment plant is already under construction

Water quality in Basin 1 has also been collected and analyzed last

October 2017 with the following parameters: temperature,TSS,

electric conductivity, turbidity, color and TDS (See sampling location

and results on the report).

MPR

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

AWTIP Monitoring Matrix - CEMMP

Page 82: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Impact on groundwater:

a)   deteriorating water quality due to:

·    Silt/sediments

·    Hazardous materials and waste

In all active work sites

Site temporary stockpile of excavated soils in

flat areas, away from main surface drainage

routes, limit to maximum of 2 m high.

Part of project (construction) cost CMC OSP-AWTIP In ProgressTemporary stockpile areas are in flat or areas with localized depression. Spoil

disposal area, MAPOL quarry, was identified. It has an approximate land area of

4 hectares, located approximately 2 kilometers from the source of spoil.

Spoil management plan is in place and will be revised if needed.

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Impact on groundwater:

a)   deteriorating water quality due to:

·    Silt/sediments

·    Hazardous materials and waste

Provide silt fences, silt traps, or sand bags, at

stockpiles of aggregate materials.

Part of project (construction) cost CMC OSP-AWTIP In Progress silt fences, traps, or sand bags are not yet necessary. stockpiles are on stable

areas or in areas with localized depression. No stockpile more than 2m high.

The stockpiles are and not causing deteriotion to water quality

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Impact on groundwater:

a)   deteriorating water quality due to:

·    Silt/sediments

·    Hazardous materials and waste

Dispose of residual soil/spoil as soon as

possible, to the disposal areas, or as free

backfilling materials for LGU/barangay roads

Part of project (construction) cost CMC OSP-AWTIP In Progress spoils generated to date are needed in the construction activities.

Request for spoil from Ipo Elementary School has been received by CMC 2017

July. Please note that IPO construction site is on stop work status from August -

December 2017. No spoil delivered to Ipo Elementary School as of December

2017. The request is a priority once construction work at Ipo resumes.

Construction engineers made inspection and the following are some observation:

1. The materials are hauled from the construction sites using dump truck. This

size of vehicle cannot enter the school's premises due to small gate. Only small

vehicle can fit the gate of the school.

2. There is need to remove the a fence to enter to the school premise which the

head teacher indicated to dispose the spoil.

3. There is a need to remove the vegetation and cut some trees and do some

excavation works.

These observations are preliminary and will be discussed with th eschool

personnel. This concerns have to be dealth with by the school prior to te delivery

of the spoil.

Impact on groundwater:

a)   deteriorating water quality due to:

·    Silt/sediments

·    Hazardous materials and waste

Avoid stockpiling more aggregates than

necessary.

Part of project (construction) cost CMC OSP-AWTIP In Progress Stockpile is at minimum especially in Ipo construction site (Intake).

Spoil management plan has been drafted and already submitted to MWSS. Spoil

disposal area, MAPOL quarry, was identified. It has an approximate land area of

4 hectares, located approximately 2 kilometers from the source of spoil.

b)  lowering of water level of wells in

nearby communities due to tunnelling,

pumping/extracting of tunnel drainage

water

Monitor for potential groundwater depletion in

existing wells in the vicinity. Provide interim

measures to avoid disrupting water supply to

affected households. Investigate for proper

corrective action.

Part of project (construction) cost CMC OSP-AWTIP Non-CompliantNo groundwater monitoring has been done yet since excavation of tunnel had not

started.

a)   Deterioration of ambient air quality due

to dust and gas emissions from:

·    Earthworks and other construction

processes; tunnelling (TBM)

• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;

• increased transport activities in the construction areas and along Ipo Road;

• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day

• burning of vegetation and wastes; and

In active work sites:

Use of dust curtains / nets to capture dust from

the construction sites

Part of project (construction) cost CMC OSP-AWTIP In Progress No dust curtains/net has been installed. Not yet necessary.

Dust supression such as watering of road has been implemented already.

Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality Monitoring:

AWTIP Monitoring Matrix - CEMMP

Page 83: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

a)   Deterioration of ambient air quality due

to dust and gas emissions from:

·    Earthworks and other construction

processes; tunnelling (TBM)

• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;

• increased transport activities in the construction areas and along Ipo Road;

• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day

• burning of vegetation and wastes; and

• operation of mechanical equipment

Apply dust suppression techniques, e.g.,

watering with bowsers, sheeting particularly at

Bigte area

Part of project (construction) cost CMC OSP-AWTIP Compliant No dust curtains/net has been installed.

Dust supression has been implemented already.

Open burning is not practiced onsite

Speed limit within the construction site is implemented

Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

a)   Deterioration of ambient air quality due

to dust and gas emissions from:

·    Earthworks and other construction

processes; tunnelling (TBM)

• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;

• increased transport activities in the construction areas and along Ipo Road;

• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day

• burning of vegetation and wastes; and

• operation of mechanical equipment

Water dry unpaved/exposed surfaces,

stockpiles of sand and excavated materials, at

least twice daily, or as necessary.

Part of project (construction) cost CMC OSP-AWTIP In Progress watering of road not necessary during the wet season.

Dust supression has been implemented already.

Open burning is not practiced onsite

Speed limit has not yet implemented

Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

a)   Deterioration of ambient air quality due

to dust and gas emissions from:

·    Earthworks and other construction

processes; tunnelling (TBM)

• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;

• increased transport activities in the construction areas and along Ipo Road;

• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day

• burning of vegetation and wastes; and

• operation of mechanical equipment

Protect aggregate stockpiles with sheeting to

restrict the movement of dust.

Part of project (construction) cost CMC OSP-AWTIP In Progress

AWTIP Monitoring Matrix - CEMMP

Page 84: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

a)   Deterioration of ambient air quality due

to dust and gas emissions from:

·    Earthworks and other construction

processes; tunnelling (TBM)

• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;

• increased transport activities in the construction areas and along Ipo Road;

• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day

• burning of vegetation and wastes; and

• operation of mechanical equipment

Require trucks, particularly those hauling

aggregates, to have secure covers.

Part of project (construction) cost CMC OSP-AWTIP Compliant No dust curtains/net has been installed.

Dust supression has been implemented already.

Open burning is not practiced onsite

Speed limit has not yet implemented

Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

a)   Deterioration of ambient air quality due

to dust and gas emissions from:

·    Earthworks and other construction

processes; tunnelling (TBM)

• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;

• increased transport activities in the construction areas and along Ipo Road;

• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day

• burning of vegetation and wastes; and

• operation of mechanical equipment

Limit engine idling to 5 minutes. Part of project (construction) cost CMC OSP-AWTIP In Progress No dust curtains/net has been installed.

Dust supression has been implemented already.

Open burning is not practiced onsite

Speed limit has not yet implemented

Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

A sound level meter was procured by CMC to monitor the noise level during

construction period as one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

a)   Deterioration of ambient air quality due

to dust and gas emissions from:

·    Earthworks and other construction

processes; tunnelling (TBM)

• stockpiling of aggregates and spoils, and conveyance of spoils to disposal areas;

• increased transport activities in the construction areas and along Ipo Road;

• Where haulage traffic exceeds 200 heavy goods vehicles (HGV) per day

• burning of vegetation and wastes; and

• operation of mechanical equipment

Ipo Road, main access road, other roads in

the Project area area, limit speed of all

construction vehicles to max. of 40 kph on the

access road to, and max. 30 kph in, the site.

Part of project (construction) cost CMC OSP-AWTIP Compliant No dust curtains/net has been installed.

Dust supression has been implemented already.

Open burning is not practiced onsite

Speed limit has not yet implemented

Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

A sound level meter was procured by CMC to monitor the noise level during

construction period as one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas and

Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Where haulage traffic exceeds 200 heavy

goods vehicles (HGV) per dayIn Progress

Air quality in the tunnel In Progress TBM has a built-in air quality monitoring device to measure oxygen, methane and

carbon dioxide

AWTIP Monitoring Matrix - CEMMP

Page 85: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Noise and vibration in the project area

from excavation activities; genera

construction activities; and vehicle and

equipment operations

Use only equipment that emit least noise and

vibration and are well maintained.

Part of the project (construction) cost CMC OSP-AWTIP Compliant Trevi Foundations conducted inland drillinge for seismic test

Noise and vibration in the project area

from excavation activities; genera

construction activities; and vehicle and

equipment operations

Use facility layout to minimize noise

propagation e.g. using topography / existing

buildings as barriers, where possible locate

noisy activities away from local communities.

Part of the project (construction) cost CMC OSP-AWTIP In Progress Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

A sound level meter was procured by CMC to monitor the noise level during

construction period as one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Noise and vibration in the project area

from excavation activities; generated by

construction activities; and vehicle and

equipment operations

Control noise at source, e.g. low noise plant,

muffling, acoustic screening, switch off

campaigns.

Part of the project (construction) cost CMC OSP-AWTIP Compliant Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

A sound level meter was procured by CMC to monitor the noise level during

construction period as one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

PPEs (earplugs and earmuffs are used onsite)

Sound Level

Monitoring (c/o

Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

AWTIP Monitoring Matrix - CEMMP

Page 86: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Noise and vibration in the project area

from excavation activities; genera

construction activities; and vehicle and

equipment operations

Restrict use of noisy and highly vibrating

equipment from 8AM-5PM. Necessary

overtime work should: a) not go beyond

9:00PM; b) observe regulated noise and

vibration levels; c) not use noisy and highly

vibrating equipment; and d) should be

coordinated with the barangay and affected

households.

Part of the project (construction) cost CMC OSP-AWTIP In Progress Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

A sound level meter was procured by CMC to monitor the noise level during

construction period as one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Noise and vibration in the project area

from excavation activities; genera

construction activities; and vehicle and

equipment operations

Manage the ins and outs of hauling trucks.

Spread out the schedule of material, waste and

spoil transport in the day (off-peak hours).

Part of the project (construction) cost CMC OSP-AWTIP Compliant Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

A sound level meter was procured by CMC to monitor the noise level during

construction period as one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas and

Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Noise and vibration in the project area

from excavation activities; genera

construction activities; and vehicle and

equipment operations

Enforce the rule of no blowing of horns. Part of the project (construction) cost CMC OSP-AWTIP Compliant Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

A sound level meter was procured by CMC to monitor the noise level during

construction period as one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Noise and vibration in the project area

from excavation activities; genera

construction activities; and vehicle and

equipment operations

Strictly enforce upon workers the compliance

with wearing of ear mufflers, especially those

who are operating equipment.

Part of the project (construction) cost CMC OSP-AWTIP Compliant Agreement with CRL Laboratories for air quality monitoring is now in place (24

August 2017). The air quality sampling dates will be scheduled once the Tunnel

Excavation starts.

A sound level meter was procured by CMC to monitor the noise level during

construction period as one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

PPEs (earplugs and earmuffs are used onsite)

Sound Level

Monitoring (c/o

Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

AWTIP Monitoring Matrix - CEMMP

Page 87: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

Institute measures to avoid impacting on

habitats and wildlife, such as:

·   minimize vegetation clearance at Bigte and

especially at the intake

Part of project (construction) cost CMC OSP-AWTIP In Progress

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

·   fence off vegetation to be retained Part of project (construction) cost CMC OSP-AWTIP Compliant Vegetation survey has not been done yet.

Tree cutting pemit from DENR CENRO has been secured

Land use pemit from NPC has been secured

a. Permit: ECC

Permit #: EMB.ECC-

CO-1508-002

Date of Issue: Apr 7,

2017

Expiry Date: Apr 7,

2022

Agency: DENR-EMB

b. Permit: Land Use

Permit

Permit #: 2017-LUP-

03

Date of Issue: July

17, 2017

Expiry Date: July 14,

2042

Agency: National

Power Corporation

(NPC)

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

·   Provide environmental training for workforce Part of project (construction) cost CMC OSP-AWTIP Non-Compliant No environmental training for workforce has been done yet

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

·   enforce site rules and sanctions to

discourage workforce from hunting, fishing and

poaching.

Part of project (construction) cost CMC OSP-AWTIP Not Applicable

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

Confine all construction activities to previously

disturbed areas, to the extent practicable, e.g.,

workers’ quarters/camps.

Part of project (construction) cost CMC OSP-AWTIP In Progress

AWTIP Monitoring Matrix - CEMMP

Page 88: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

Use existing roads for project activities.

Minimize new road construction.

Part of project (construction) cost CMC OSP-AWTIP In Progress

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

To avoid unnecessary clearing, mark/delineate

areas to be cleared of vegetation, e.g. by

fencing.

Part of project (construction) cost CMC OSP-AWTIP Compliant fencing observed. Inspection Checklist

and Report (c/o

Jasper Cazenas and

Ricky Latunio)

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

Rehabilitate cleared areas to their pre-project

conditions, unless otherwise agreed with the

landowner.

Part of project (construction) cost CMC OSP-AWTIP Not Applicable vegetation of cleared areas will be done after the construction

activities. To be monitored in 2019.

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

Re-vegetate construction sites using local,

indigenous species.

Part of project (construction) cost CMC OSP-AWTIP Not Applicable vegetation of cleared areas will be done after the construction

activities. To be monitored in 2019.

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

Re-vegetate watershed target sites especially

in areas identified by the Watershed

Management Plan.

Part of project (construction) cost CMC OSP-AWTIP In Progress

Loss of vegetation due to:

• vegetation clearing and potential

trampling of trucks/equipment beyond

project footprints

• Over-clearance and damage to

vegetation around the construction sites

Limit any collection of wood for charcoal to

exotic i.e. non-native species.

Part of project (construction) cost CMC OSP-AWTIP Not Applicable vegetation of cleared areas will be done after the construction

activities. To be monitored in 2019.

Disturbance to wildlife due to

• Construction noise, vibration, dust,

lighting, presence/movement of people,

etc.

Implement measures to mitigate noise,

vibration and dust.

Part of project (construction) cost CMC Compliant A complaint was received on July 18,2017 by CMC which was filed by residents

of Calle Onse (adjacent to the Industrial Area in Brgy Bigte regarding the

generation of dust and mud along the road. This case was investigated by CMC

H&S together with representative of Calle Onse. CMC already made provision of

a canal across the Industrial Area. The problem is not attributed solely to CMC

but residents addressed grievance to CMC hoping to get some help. The case

was closed and H&S has the detailed documentation.

Grievance Report

(c/o Jasper Cazenas

and Ricky Latunio)

AWTIP Monitoring Matrix - CEMMP

Page 89: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Disturbance to wildlife due to

• Construction noise, vibration, dust,

lighting, presence/movement of people,

etc.

Strategically place nets at the tunnel portals to

prevent flying debris.

Part of project (construction) cost CMC In Progress

Disturbance to wildlife due to

• Construction noise, vibration, dust,

lighting, presence/movement of people,

etc.

Water to minimize dust accumulation and

spreading.

Part of project (construction) cost CMC Compliant

Traffic due to:

·   inadequate capacity of Ipo Road

(access road)

·   inadequate capacity of Ipo Road

(access road)

Institute prior coordination with the Barangay

and Municipality for the formulation of a traffic

management and safety plan and for clearing

of structures encroaching into access road

ROW.

Part of project (construction) cost CMC Compliant construction staff are assigned for traffic and transportation of goods

is assigned

Traffic due to:

·   inadequate capacity of Ipo Road

(access road)

·   inadequate capacity of Ipo Road

(access road)

Prior to construction, clear easement of

encroaching structures, most of them being

temporary.

Part of project (construction) cost CMC Compliant construction engineers confirm adequacy of the road for the transport

of heavy equipment and other large goods

heavy equipemnt

specification (c/c

Sergio and Federico)

Traffic due to:

·   inadequate capacity of Ipo Road

(access road)

·   inadequate capacity of Ipo Road

(access road)

Strategically post billboards informing the

public about the expected increase in volume of

traffic in the influence area due to Project

implementation. Post at least two weeks prior

to mobilization.

Part of project (construction) cost CMC Compliant Bulletin boards for IEC purpose were installed in the barangay halls of Brgy Bigte

and San Mateo.

CMC. Request for

Permission to Install

Bulletin Boad.

Barangay San Mateo,

Norzagaray, Bulacan.

June 6, 2017

CMC. Request for

Permission to Install

Bulletin Boad.

Barangay Bigte,

Norzagaray, Bulacan.

June 20, 2017

Traffic due to:

·   inadequate capacity of Ipo Road

(access road)

·   inadequate capacity of Ipo Road

(access road)

Coordinate with the Barangay for assistance in

traffic management.

Part of project (construction) cost CMC Compliant Hauling truck, heavy equipment and other construction related machines are

expected at the construction sites and associated road such as Ipo Road during

the construction

Traffic due to:

·   inadequate capacity of Ipo Road

(access road)

·   inadequate capacity of Ipo Road

(access road)

Strategically post traffic  flagmen along Ipo

Road, equipped with two-way radio.

Part of project (construction) cost CMC Compliant construction staff are assigned for traffic and transportation of goods

is assigned

Traffic due to:

·   inadequate capacity of Ipo Road

(access road)

·   inadequate capacity of Ipo Road

(access road)

Post sufficiently legible (reflectorized) traffic

safety notice and signage at strategic locations

along the entire stretch of the access road.

Part of project (construction) cost CMC Compliant Traffic and safety signage were installed onsite

Traffic due to:

·   inadequate capacity of Ipo Road

(access road)

·   inadequate capacity of Ipo Road

(access road)

Limit speed to 40 kph along Ipo Road, 20 kph

at highly populated sections of Ipo Road, and

30 kph at construction sites and unpaved

haulage roads.

Part of project (construction) cost CMC Compliant road signs are provided. Traffic rules coordinated with Brgy Captain

Dadeng Cruz

Traffic due to:

·   inadequate capacity of Ipo Road

(access road)

·   inadequate capacity of Ipo Road

(access road)

Limit speed to 40 kph along Ipo Road, 20 kph

at highly populated sections of Ipo Road, and

30 kph at construction sites and unpaved

haulage roads.

Part of project (construction) cost CMC In Progress road signs are provided. Traffic rules coordinated with Brgy Captain

Dadeng Cruz. To further discuss implementation of speed limits

along Ipo Road

Coordinate with DPWH regarding the use of

Ipo Road.

Part of project (construction) cost CMC Not Applicable not yet applicable. No damage on road that is related to tunnel

construction has been recorded

Restore access roads within the MWSS

compound to the pre-construction condition or

better.

Part of project (construction) cost CMC PMO Not Applicable not yet applicable. No damage on road that is related to tunnel

construction has been recorded

Potential damage of existing roads used

as access roads due to movement of

heavy equipment and vehicles

AWTIP Monitoring Matrix - CEMMP

Page 90: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Restricted access to the existing fish

landing sites  in Sitio Consultant (identified

area as the Contractor’s Work Area) and boat landing at Sitio Ipo

Inform affected communities living in Ipo

Watershed on the impact of construction works

on transportation and consult them for the best

alternative route. Have alternative route and

fish and boat landing sites ready for use prior

to commencement of construction activities.

Part of project (construction) cost CMC PMO Compliant dumagat communities has been informed of the impacts consultations

annexed in EIA

MMT formation-

MWSS. Angat Water

Improvement

Project(Tunnel 4)-

MOA between MWSS

and DENR on the

Formation of Multi-

partite Monitoring

Team, Manual of

Operation,

Environmental

Monitoring Fund,

Environmental

Guarnatee Fund, and

Work and Financial

Plan. September 19,

2017

Restricted access to the existing fish

landing sites  in Sitio Consultant (identified

area as the Contractor’s Work Area) and boat landing at Sitio Ipo

Provide alternative access to school for school

children and residents

Part of project (construction) cost CMC Compliant boat service has been provided for free to communities in Ipo

Restricted access to the existing fish

landing sites  in Sitio Consultant (identified

area as the Contractor’s Work Area) and boat landing at Sitio Ipo

Establish alternate boat landing at the mouth of

Sapang Munti River

Part of project (construction) cost CMC Compliant boat service has been provided for free to communities in Ipo

Restricted access to the existing fish

landing sites  in Sitio Consultant (identified

area as the Contractor’s Work Area) and boat landing at Sitio Ipo

Install soil entrapment nets and coffer dams to

contain soil erosion at dam site

Part of project (construction) cost CMC Not Applicable construction at Ipo is on road improvement and slope stabilization

Restricted access to the existing fish

landing sites  in Sitio Consultant (identified

area as the Contractor’s Work Area) and boat landing at Sitio Ipo

Provide clear signage of alternative routes Part of project (construction) cost CMC Compliant Signage has been posted already

Community health and safety hazards Inform local residents of the project phase and

prohibit entry of local residents into the

construction area.

Part of project (construction) cost CMC In Progress a bulletin board has been installed in Ipo Dam for IEC CMC. Request for

Permission to Install

Bulletin Boad. Ipo

Elementary School,

Norzagaray, Bulacan.

August 7, 2017

Community health and safety hazards Secure project area, including associated

facilities particularly the storage for explosives,

from unauthorized entry

Part of project (construction) cost CMC CompliantUnauthorized entry signage have been installed onsite

Grievance procedure and scheme to be formulated

UXO survey and clearing have been done by hired demining company, Vourvon

Electronica Marketing. UXO were retrieved and surrendered to the Philippine

Army.

Clearance

Certification

Issued by: Vourvon

Electronica Marketing

Issued on: May 29,

2017

Certification of

Receipt of

Unexploded

Explosives

Issued by: Alpha

Aggressor Company

Issued on: July 17,

2017

AWTIP Monitoring Matrix - CEMMP

Page 91: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Community health and safety hazards Implement measures to mitigate impacts on air

and water quality, noise, traffic

Part of project (construction) cost CMC Compliant

Community health and safety hazards Provide mechanism to reduce dust /other

pollutants (ie. water spraying on the road,

speed limit of vehicles, etc.)

Part of project (construction) cost CMC In Progress

Community health and safety hazards People with impaired health/risks wear masks

and other protective device

Part of project (construction) cost CMC Compliant

AWTIP Monitoring Matrix - CEMMP

Page 92: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Workers’ health and safety hazard Mitigating impacts from tunnel excavation

(TBM method):

Include H&S protocols in the C-EMP on the

safe construction procedures during

construction.

Compliant Health and Safety Officers have been hired.

Workers’ health and safety hazard Evacuation procedures in tunnel prior to setting

charges. Compliant

Workers’ health and safety hazard Set up a sufficiently equipped emergency first-

response and health care team, linked to an

ultimate response team.

Compliant Health and safety staff have been hired by CMC

Health and safety plan has been formulated

Standby doctor and nurse are present onsite

Ambulance, first aid kits, and fire extinguishers have been provided

Personal Protective Equipment (PPE) are given to the staff. Contractors’ staff are REQUIRED to use PPE onsite at all times.

CMC Health and

Safety Plan

Workers’ health and safety hazard Provide safe housing with adequate basic

services. Compliant Housing was provided for CMC employees

Workers’ health and safety hazard Enforce use of protective wears when at work. Compliant

Workers’ health and safety hazard Conduct pre-mobilization orientation workshop

on health and safety and emergency response

and evacuation procedures.

Compliant

Generation of spoil and spoil disposal.

More than 150,000m3 is expected to be

generated due to tunnelling works, which is

about 190,000 m3 loose volume.

Contamination of spoil with oil from the

operation of the TBM

Prepare and implement a plan for the

preparation of the spoil disposal areas.

Part of project construction cost MWSS

DED consultants

CMC

Compliant Spoil management plan to be formulated. Spoil disposal area, MAPOL quarry,

was identified. It has an approximate land area of 4 hectares, located

approximately 2 kilometers from the source of spoil.

Generation of spoil and spoil disposal.

More than 150,000m3 is expected to be

generated due to tunnelling works, which is

about 190,000 m3 loose volume.

Contamination of spoil with oil from the

operation of the TBM

Characterization of the spoil. Spoil

characterization in terms of oil contamination.

Oil content should be determined by grab

sampling and sending samples to laboratory

partner for analysis.

DED Consultants Compliant

Generation of spoil and spoil disposal.

More than 150,000m3 is expected to be

generated due to tunnelling works, which is

about 190,000 m3 loose volume.

Contamination of spoil with oil from the

operation of the TBM

Minimise the volume of spoil to be disposed of

by re-use in backfilling of roads, and by offering

as free filling materials to government projects

needing backfill materials.

CMC Compliant

Generation of spoil and spoil disposal.

More than 150,000m3 is expected to be

generated due to tunnelling works, which is

about 190,000 m3 loose volume.

Contamination of spoil with oil from the

operation of the TBM

Disposal area must be confined to solid

ground, of low ecological and agricultural value.In Progress Spoil management plan to be formulated. Spoil disposal area, MAPOL quarry,

was identified. It has an approximate land area of 4 hectares, located

approximately 2 kilometers from the source of spoil.

Generation of spoil and spoil disposal.

More than 150,000m3 is expected to be

generated due to tunnelling works, which is

about 190,000 m3 loose volume.

Contamination of spoil with oil from the

operation of the TBM

Disposal area must not occupy drainage lines

and streams, and create an obstacle to

streams or induced flooding.

In Progress Geocomposite steel mesh with anchor bolts has been installed upon portal

Soil from intake slope has been removed

Installation of threaded rock bolts have been done

Generation of spoil and spoil disposal.

More than 150,000m3 is expected to be

generated due to tunnelling works, which is

about 190,000 m3 loose volume.

Contamination of spoil with oil from the

operation of the TBM

Spoil heaps must be designed and shaped with

stable side slopes and suitable drainage.In Progress

AWTIP Monitoring Matrix - CEMMP

Page 93: Angat Water Transmission Improvement Project

Potential Impact Responsible Responsible

Implement Monitor

Relevant

documentsPossible Approach/ Mitigating Measures Cost of Mitigation/ Enhancement Compliance Status Remarks (2017 Jul to Dec)

Generation of spoil and spoil disposal.

More than 150,000m3 is expected to be

generated due to tunnelling works, which is

about 190,000 m3 loose volume.

Contamination of spoil with oil from the

operation of the TBM

Spoils heaps must be compacted during the

earthworks.In Progress

Generation of spoil and spoil disposal.

More than 150,000m3 is expected to be

generated due to tunnelling works, which is

about 190,000 m3 loose volume.

Contamination of spoil with oil from the

operation of the TBM

On complete, the spoil heaps must be covered

with the original top soil from the site and re-

vegetated

In Progress

Solid waste Implement an eco-friendly solid waste

management at work sites and workers’ camp/s, which minimizes, re-uses, segregates

and promptly disposes of generated solid

waste.

Part of project (construction) cost MWSS

CMC

Compliant • Spoil disposal areas will be identified.

• Garbage are segregated into biodegradable, non-biodegradable and residuals

• Contract for waste collection is between Brgy Bigte and CMC

• No ecological solid waste management plan has been formulated yet

Service Contract of

Brgy Bigte and CMC

for Garbage hauling

and disposal

Date of Issue: May

30, 2017

Expiry Date: Dec 31,

2017

Site inspection report

(c/o Jasper Cazenas

and Ricky Latunio)

Hazardous waste Locate stationary ground storage for

hazardous waste at least 100 m away from

water bodies, raised to min 1 ft above high

flood level. Or, use mobile storage but should

not be parked near water bodies.

Secure storage areas appropriately. Storage

facilities must be able to contain spillage.

Dispose of waste promptly and appropriately.

The contractor shall be required to implement

an appropriate hazardous waste management

program.

Part of project (construction) cost CMC In Progress hazmat temporary disposal area included in the industrial area site map hazmat temporary

disposal included in

the Industrial Area

site plan (c/o Sergio

and Federico)

Storage of oil and grease used for the

maintenance and operation of heavy equipment

shall be properly built and maintained, to

include bunded storage for the capacity of the

containers plus 10%, and oil traps on drainage

outfalls.

Part of project (construction) cost CMC In Progress • No hazardous materials facility was built yet.

• No accredited hazardous waste disposal hauler has been contacted yet

• hazmat temporary disposal is included in the site plan.

Industrial area site

plan (c/o Sergio

Daipra and Federico

Mezzetti)

AWTIP Monitoring Matrix - CEMMP

Page 94: Angat Water Transmission Improvement Project

I. Conditions

Environmental Management

ConditionsResponsible

Agencies

Compliance

StatusRemarks Relevant Documents

1. Continuously conduct an effective Information, Education and

Communication (IEC) program to inform and educate all

stakeholders especially its contractors, workers, and local

residents about the:

a. mitigating measures embodied in its EIS;

b. the condition herein stipulated and the environmental;

c. disastar risk reduction management measures and climate

change related issues/concerns

d. human safety features for greater awareness, understanding

and sustained acceptance of the project*The report of program implementation shall be submitted to EMB Central

Office on an annual basis

In Progress

Bulletin boards for IEC purpose were installed

in the barangay halls of Brgy Bigte and San

Mateo.

Socio-economic survey currently being

discussed with an IP Specialist/ Anthropologist

(Mr. Joseph Lalo). The survey is scheduled on

September 2018.

transmittal/ acceptance record of bulletin

board

2. Implement a Comprehensive Social Development Program

(SDP) and submit a separate report together with the

Compliance Monitoring Report (CMR) to the EMB CO and copy

furnished EMB-III on a semi-annual basis

In ProgressSocial Development Program of CMC is

draftedCMC Social Development Plan

3. Submission of EMB CO details, impacts and measure for

repair/rehabilitation of the three tunnels, with public IEC and

consultation, prior to activity funding approval and detailed

design

Compliant

4. Submission to EMB CO details, impacts and measure to

Right-of-Way (ROW) fencing activities, with public IEC and

consultation, including those residents within the ROW and

fence-side neighbors, prior to funding approval and detailed

design

Compliant

All commitments, appropriate mitgating/enhancement measures and monitoring requirements contained in final EIS, including the following shall be instituted and strictly implemented throughout its

project implementation

AWTIP Monitoring Matrix - ECC

Page 95: Angat Water Transmission Improvement Project

5. Submission of a detailed full year water supply and utilization

analysis shall be undertaken within (2) years from receipt of this

Certificate to include history of the water releases from Umiray

River, Angat Dam, irrigation thru the Angat Tailrace tunnel, Ipo

River upstream of Ipo Dam, Angat River downstream of Ipo

Dam, and water diverted thru the existing tunnels. This shall

address any existing impact on NIA Angat-Maasim River

Irrigation System (AMRIS) water supply and potential to

increase water allocation to Water Right or optimize the

60.6m3/s capacity of the four tunnels. The premise is the priority

domestic/municipal water supply (advantage side) over irrigation

water supply. Scenarios include the normal water flow, excess

water flow (La Niña events) and extremely low flows (El Niño).

The study shall be coordinated with NWRB, NIA, AMRIS

federation of farmers. The goals is to provide the farmers, LGUs

and decision-makers awareness of the actual situation and

preparedness for extreme condition.

Not Applicable to be submitted on April 2019 by MWSS

General conditions

6. The project operations shall conform with the provisions of

environmental laws regulations and their Implementing Rules

and Regulations namely: RA 6969 (Toxic Substances and

Hazardous and Nuclear Waste Control Act of 1990), RA 8749

(Philippine Clean Air Act of 1999), RA 9003 (Act providing for an

Ecological Solid Waste Management Program), and RA 9275

(Philippine Clean Water Act of 2004)

In Progress

SMR

MPR

7. The proponent shall set up the following:

a. A readily available and replenishable Environmental

Guarantee Fund (EGF) to cover the following expenses:

• for further environmental assessments, compensations/ identification for whatever damages to life and property that may

be caused by the project;

• rehabilitation and/or restoration of areas affected by the project’s implementation;• abandonment/decommissioning of the project facilities related to the prevention of possible negative impacts and as a source

of fund for contingency and clean-up activities;

In Progress

the MOA between DENR and MWSS has been

forwarded by MWSS to DENR for their

comments (see MWSS letter to EMB Central

Office dated 26 July 2017; MWSS letter to

Chief EIA Div Central Office dated 16 June

2017; MWSS Letter to EMB Central dated 11

September 2017). DENR Region 3 Regional

director realeased memo dated 26

September 2017 to Regional Director of EMB

Region 3 to review the proforma MOA

between MWSS and DENR). CMC also

forwarded the proforma MOA to MWSS for

their review. CMC is ready to release fund for

the EGF after MOA has been signed by

parties.

AWTIP Monitoring Matrix - ECC

Page 96: Angat Water Transmission Improvement Project

b. A Multi-Partite Monitoring Team (MMT) composed of

representative(s) from the proponent, EMB Region III, a local

environmental Non-Government Organization (NGO), NIA and

the LGUs concerned shall be organized. The MMT shall

primarily oversee the compliance of the proponent with the

Environmental Monitoring Plan (EMP) as well as the condition of

its ECC.

In Progress

The MMT has been formed and initiated by

CMC and MWSS. To date, the MMT is

headed by Mr Thiongpe Lee, the MENRO of

Municipality of Norzagaray. Meeting has

been held for the formation of MMT in 2017

July 27; August 23; Septmeber 5 at the MWSS

compound. The activities were supported by

CMC.

c. A replenishable Environmental Monitoring Fund (EMF) to

cover all costs attendant to the operation of the MMT such as

training, sampling and analysis, the hiring of technical experts,

accommodations and transportations.

The amount and mechanics of the EGF, EMF, and the establishments of the

MMT shall be determined by EMB CO and the proponent in coordination with

EMB Region III through a Memorandum of Agreement (MOA) which shall be

submitted within sixty (60) days upon receipt of the Certificate

In Progress

The meetings of MMT members resulted to

formulation of Manual of Operation and

Financial Work Plan. This has been submitted

to MWSS for their review. This has to be

attached to the MOA between MWSS and

DENR for the establishment of the MMT, EGF

and EMF. The EMF is estimated at

2,500,000.00 PhP.

8. Creation of Environmental Unit within sixty (60) days from

receipt of this Certificate that shall competently handle the

environmental-related aspects of the project. In addition to the

monitoring requirements as specified in the Environmental Plan/

Environmental Monitoring Plan, the EU shall have the following

responsibilities:

• Monitor actual projects impacts vis-à-vis the predicted impacts and management measures in the EIS

• Recommended revisions to the EMP/EMoP, whenever necessary subject to the approval of EMB CO. Revisions should

also consider the result of the validation of air dispersion and

thermal plume modeling

• Ensure that data gathered during monitoring activities are properly documented, assessed, evaluated and reported to

EMB CO and Region III in accordance with the standard

formats; and

• Ensure that monitoring and submissions of reports to EMB

In Progress

9. The proponent shall ensure that its contractors and

subcontractors strictly comply with relevant condition of this

certificate as well as the Environmental Management Plan in the

EIS

In Progress

MWSS and CMC conducts weekly meeting

and regular site inspection. MWSS has field

office based in MWSS Compound in Brgy

Bigte. The project staff are reporting to this

office and at the main office in Balara,

Quezon City

AWTIP Monitoring Matrix - ECC

Page 97: Angat Water Transmission Improvement Project

Restrictions

10. No other activities shall be undertaken other than what were

stipulated in the EIS. Any expansion or modification of the

Project beyond the project description or any change in the

activity shall be subject to new EIA study

Compliant No modification or alteration on the project.

11. Transfer the ownership of this project carries these same

conditions and restrictions for which written notification must be

made by herein grantee to EMB within fifteen (15) days from

such transfer

Not Applicable

II. Project Assessment Planning Tool

By the way of recommendation, the following have been taken notice of by this Office, and are forwarding these recommendations to the parties and authorities concerned for proper actions

RecommedationsResponsible

Agencies

Compliance

StatusRemarks Relevant Documents

1. Compliance with the following:

a. Sanitation Code of the PhilippinesDOH Compliant

portalets have been provided in constrcution

site where toilet is not available. MPRs.

b. Labor code of the Philippines including health and safety

standardsDOLE Compliant

employment contracts

SSS, Pag-ibig and Phil Health remitances for

regular employees.

c. National Building Code of the Philippines LGU Compliant Excavation permit

2. Ensure conformance with the Ecological Solid Waste

Management ActLGU Compliant

Service Contract with Brgy Bigte for Hauling

and disposal of solid waste dated 2017 May-

December

3. Inform constituents about the proposed project especially

those that are located downstream of Ipo Dam like Barangays

Baraca and Pinagtulayan for any potential increase in the total

suspended solids of Angat River during dry season.

LGU of Norzagaray Compliant

installation of project bulletin boards in Brgy

Halls of Brgy Bigte and San Mateo, Ipo

Elementary School

4. Maintain records of both print and digital versions on the daily

water supply allocation, schedule and actual water extraction of

Bustos Dam, including often affected rice farms during El Niño

events

NIA Cannot Document CNIA should have data on this

5. Monitor of water flow downstream of Bustos Dam NIA Cannot Document CMWSS measures water intake to all its

transmission system

For the assistance of proponent and government agencies concerned in the management of the project and for the better coordination and mitigating on the project on its surrounding areas and to the

environment

AWTIP Monitoring Matrix - ECC

Page 98: Angat Water Transmission Improvement Project

6. Secure tree cutting permit (if any) DENR-FMB Compliant tree cutting permit secured

Tree cutting Permits issued by Community

Environment and Natural Resources (DENR-

CENRO)

a. Date of Issue: July 10, 2017

Expiry Date: July 25, 2017

b. Date of Issue: July 25, 2017

Expiry Date: July 30, 2017

c. Date of Issue: August 16, 2017

Expiry Date: August 31, 2017

d. Date of Issue: August 24, 2017

Expiry Date: August 31, 2017

e. Date of Issue: September 11, 2017

Expiry Date: September 18, 2017

f. Date of Issue: September 23, 2017

Expiry Date: October 8, 2017

7. Secure PAMB clearance DENR Not Applicablenot applicable as the watershed has no

management board

8. Secure FPIC NCIP In Progress

NCIP conducted field based investigation.

MWSS/CMC is waiting for the work financial

plan of NCIP for the FPIC process

III. Environmental Plainning and Recommendations for the

Proponent

RecommedationsResponsible

Agencies

Compliance

StatusRemarks Relevant Documents

1. Give priority employment to qualified local residents.

Adequate public information for jobs available to local residents

in the affected areas needs to be provided.

Compliant

employement record

MPR

2. Strictly conduct rigid/periodic monitoring of related

health/sickness during project’s operation Compliant H and S record. Medical Record

3. The proponent shall be provide adequate safety gadgets to its

employees/workers to prevent health and occupational hazards

posed by project implementation

Compliant

H and S record on PPEs

MPR H&S section

The proponent shall conduct regular structural monitoring that

will detect potential problems and trigger remedial responses to

avoid possible tunnel failure/breakdown.

In Progress

MWSS is conducting site inspection. CMC is

submitting monthly progress reports that

covers all aspect of the construction project

AWTIP Monitoring Matrix - ECC

Page 99: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Pre-construction B. the People Required clearances and permits Obtain the following prior to

Notice of Award:

(a) ECC

(b) MOA among DENR RO 3,

NPC and MWSS

(c) Permit to cut tree

(d) Permit to operate

(a) MWSS

(b) MWSS

(c) D&B

Contractor

(d) D&B

Contractor

(a) PhP 500,000.00

(b) none

(c) part of

construction cost

(d) part of

construction cost

Permits/clearances

obtained prior to Notice

of Award

Compliant a. ECC was issued on April 7, 2017

b. Land use permit from NPC is secured on July 17,

2017.

c. Tree Cutting Permit – from Community Environment and Natural Resources (DENR-

CENRO) have been secured.

d. Permit to operate has been secured on October

20, 2017

a. Permit: ECC

Permit #: EMB.ECC-

CO-1508-002

Date of Issue: Apr 7,

2017

Expiry Date: Apr 7,

2022

Agency: DENR-EMB

b. Permit: Land Use

Permit

Permit #: 2017-LUP-

03

Date of Issue: July

17, 2017

Expiry Date: July 14,

2042

Agency: National

Power Corporation

(NPC)

c. Tree cutting

Permits issued by

Community

Environment and

Natural Resources

(DENR-CENRO)

a. Date of Issue: July

10, 2017

Expiry Date: July 25,

2017

Pre-construction B. the People Preparing relevant communities Conduct intensive social and

environmental awareness

program at least one month prior

to Notice of Award, covering (i)

communicable/ transmittable

diseases that may be brought

with the entry of workers; (ii)

potential social conflicts between

communities and workers; (iii)

other health and safety hazards

and impacts during construction

and during maintenance and

repair of completed works; (iv)

potential impact on passageway

of school children, boat landing at

Ipo dam site and Angat River

downstream due to water

turbidity as a result of diggings at

inlet ;and (iv) the grievance

redress mechanism.

OSP-AWTIP

Affected

barangays

In Progress Bulletin boards for IEC purpose were installed in the

barangay halls of Brgy Bigte and San Mateo.CMC. Request for

Permission to Install

Bulletin Boad.

Barangay San

Mateo, Norzagaray,

Bulacan. June 6,

2017

CMC. Request for

Permission to Install

Bulletin Boad.

Barangay Bigte,

Norzagaray, Bulacan.

June 20, 2017

CMC. Request for

Permission to Install

Bulletin Boad. Ipo

Elementary School,

Norzagaray, Bulacan.

August 7, 2017

Performance Indicator

AWTIP Monitoring Matrix - EIA

Page 100: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Pre-construction B. the People Ensuring environmentally

responsible procurement

Include an SPS-compliant EMP in

the bidding documents.

OSP-AWTIP Not applicable SPS-compliant EMP

included in eth bidding

documents

Compliant

Pre-construction B. the People Append EMP to the Contract for

basis in the preparation of the C-

EMP.

OSP-AWTIP SPS-compliant EMP

included in eth bidding

documents

Compliant see General Conditons of the Contract (Section 6

and Employer's Requirment (Section 7)

AWTIP Contract

Agreement signed

2016 May 25G.

Esquivel (MWSS) Pre-construction B. the People In Contract, require D&B

Contractor to submit monthly and

semi-annual environmental

monitoring report.

OSP-AWTIP SPS-compliant EMP

included in eth bidding

documents

Compliant see General Conditons of the Contract (Section 6

and Employer's Requirment (Section 7)

AWTIP Contract

Agreement signed

2016 May 25G.

Esquivel (MWSS)

and A Ciamei (CMC) Pre-construction B. the People Stipulate in Contract the tie up of

progress payment and collection

of performance bond with the

performance in C-EMP

implementation.

OSP-AWTIP SPS-compliant EMP

included in eth bidding

documents

Compliant see General Conditons of the Contract (Section 6

and Employer's Requirment (Section 7)

AWTIP Contract

Agreement signed

2016 May 25G.

Esquivel (MWSS)

and A Ciamei (CMC)

Pre-construction B. the People Prepare C-EMP that addresses

as minimum the requirements of

the EMP.

D & B Contractor SPS-compliant EMP

included in eth bidding

documents

Compliant CEMMP has been submitted by CMC to MWSS on

2017 July 7. CEMMP, June 2017

Pre-construction B. the People Evaluate C-EMP quantitatively

and qualitatively againts the EMP

OSP-AWTIP SPS-compliant EMP

included in eth bidding

documents

In Progress CEMMP has been approved by MWSS. Please see

letter of MWSS to CMC dated 15 August 2017

CEMMP:

Contractor's

Environmental

Management and Pre-construction B. the People Clear the C-EMP before the start

of any activity/work onsite or

establish of any construction

related facility on site by D&B

Contractor

ADB SPS-compliant EMP

included in eth bidding

documents

Compliant CEMMP has been approved by MWSS. Please see

letter of MWSS to CMC dated 15 August 2017

CEMMP:

Contractor's

Environmental

Management and

Construction Phase A. Land Soil and Erosion due to:

(a) soil disturbance

(b) vegetation clearing

Location: Inlet structure and

relevant work sites

Confine soil disturbance and/or

vegetation clearing to pre-defined

and planned area that includes

project footprint and needed

easements

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

development cost

CEMP Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Soil and Erosion due to:

(a) soil disturbance

(b) vegetation clearing

Stabilize exposed soils with

temporary seeding, mulches,

mats, non-chemical-based soil

binders.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

development cost

CEMP Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Construction Phase A. Land Soil and Erosion due to:

(a) soil disturbance

(b) vegetation clearing

Protect slopes with any one or

combination of bonded fiber

matrices, erosion control

blankets, silt fence, fiber rolls,

and keeping stormwater off the

slopes through diversion

channels and/or berms.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

development cost

CEMP In Progress No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

AWTIP Monitoring Matrix - EIA

Page 101: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase A. Land Soil and Erosion due to:

(a) soil disturbance

(b) vegetation clearing

Re-vegetate disturbed

soils/slopes as soon as possible

after completion of the

construction works.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

development cost

CEMP In Progress No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removedConstruction Phase A. Land Soil and Erosion due to:

(a) soil disturbance

(b) vegetation clearing

Replacing vegetation that died

during the defects liability period.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

development cost

CEMP In Progress No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been doneConstruction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

Institute measures to avoid

impacting on habitats and

wildlife, such as:

a. minimize vegetation clearance

at Bigte and especially at the

intake

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

b. fence of vegetation to be

retained

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

c. provide environmental training

workforce

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit In Progress staff orientation conducted training and

orientation record

Toolbox meeting

attendances (c/o

Jasper Cazenas and

Ricky Latunio) Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

d. enforce site rules and sactions

to discourage workforce from

hunting, fishing and poaching

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

Confine all construction activities

to previously disturbed areas, to

the extent practicable, e.g.,

workers’ quarters/camps.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

Use existing roads for project

activities. Minimize new road

construction.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Minimal number of trees

applied for tree cutting permit

from DENR

Minimal number of trees

applied for tree cutting permit

from DENR

Minimal number of trees

applied for tree cutting permit

from DENR

Minimal number of trees

applied for tree cutting permit

from DENR

Minimal number of trees

applied for tree cutting permit

from DENR

Minimal number of trees

applied for tree cutting permit

from DENR

AWTIP Monitoring Matrix - EIA

Page 102: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

To avoid unnecessary clearing,

mark/delineate areas to be

cleared of vegetation, e.g. by

fencing.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

Rehabilitate cleared areas to their

pre-project conditions, unless

otherwise agreed with the

landowner.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

Re-vegetate construction sites

using local, indigenous species.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit In Progress No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Loss of vegetation due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

Re-vegetate watershed target

sites especially in areas identified

by the Watershed Management

Plan.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit In Progress No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Loss of vegetatio due to:

a. vegetation clearing and

potential trampling of

trucks/equipments beyong project

footprints

Limit any collection of wood for

charcoal to exotic i.e. non-native

species.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

Tree cutting permit In Progress No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Disturbance to wildlife due to:

(a) Construction noise, vibration,

dust, lighting, presence/

movement of people, etc.

(b) flying debris from blasting

Implement measures to mitigate

noise vibration and dust

Implement:

D&B Contractor

Monitor:

PMO

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Disturbance to wildlife due to:

(a) Construction noise, vibration,

dust, lighting, presence/

movement of people, etc.

(b) flying debris from blasting

Implement measures to mitigate

noise vibration and dust

Implement:

D&B Contractor

Monitor:

PMO

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Minimal number of trees

applied for tree cutting permit

from DENR

Record of number of poaching

and illegal trading of wildlife

by workers

Record of number of poaching

and illegal trading of wildlife

by workers

Minimal number of trees

applied for tree cutting permit

from DENR

Minimal number of trees

applied for tree cutting permit

from DENR

Minimal number of trees

applied for tree cutting permit

from DENR

Minimal number of trees

applied for tree cutting permit

from DENR

AWTIP Monitoring Matrix - EIA

Page 103: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase A. Land Disturbance to wildlife due to:

(a) Construction noise, vibration,

dust, lighting, presence/

movement of people, etc.

(b) flying debris from blasting

Implement measures to mitigate

noise vibration and dust

Implement:

D&B Contractor

Monitor:

PMO

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Generationof spoil and spoil

disposal

More than 150,000m3 is expected

to be generated due to tunnelling

works, which is about 190,000 m3

loose volume.

Prepare and implement a plan for

the preparation of the spoil

disposal areas.

Implement:

DED Consultants

D&B Contractor

Monitor:

MWSS

Part of project

(construction) cost

Detailed Engineering

Design (DED) scope of

work

Detailed Engineering

Design Plans

In Progress Spoil disposal, MAPOL quarry, was identified. It has

an approximate land area of 4 hectares, located

approximately 2 kilometers from the source of spoil.

No vegetation survey has been done yet

Geocomposite steel mesh with anchor bolts has

been installed upon portals

Spoil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Generationof spoil and spoil

disposal

More than 150,000m3 is expected

to be generated due to tunnelling

works, which is about 190,000 m3

loose volume.

Minimise the volume of spoil to

be disposed of by re-use in

backfilling of roads, and by

offering as free filling materials to

government projects needing

backfill materials.

Implement:

DED Consultants

D&B Contractor

Monitor:

MWSS

Part of project

(construction) cost

Detailed Engineering

Design (DED) scope of

work

Detailed Engineering

Design Plans

In Progress Spoil disposal, MAPOL quarry, was identified. It has

an approximate land area of 4 hectares, located

approximately 2 kilometers from the source of spoil.

Construction Phase A. Land Generationof spoil and spoil

disposal

More than 150,000m3 is expected

to be generated due to tunnelling

works, which is about 190,000 m3

loose volume.

Disposal area must be confined

to solid ground, of ecological and

agricultural value

Implement:

DED Consultants

D&B Contractor

Monitor:

MWSS

Part of project

(construction) cost

Detailed Engineering

Design (DED) scope of

work

Detailed Engineering

Design Plans

In Progress Spoil disposal, MAPOL quarry, was identified. It has

an approximate land area of 4 hectares, located

approximately 2 kilometers from the source of spoil.

Construction Phase A. Land Generationof spoil and spoil

disposal

More than 150,000m3 is expected

to be generated due to tunnelling

works, which is about 190,000 m3

loose volume.

Disposal area must not occupy

drainage lines and streams, and

create an obstacle to streams or

induced flooding.

Implement:

DED Consultants

D&B Contractor

Monitor:

MWSS

Part of project

(construction) cost

Detailed Engineering

Design (DED) scope of

work

Detailed Engineering

Design Plans

In Progress Geocomposite steel mesh with anchor bolts has

been installed upon portal

Soil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Generationof spoil and spoil

disposal

More than 150,000m3 is expected

to be generated due to tunnelling

works, which is about 190,000 m3

loose volume.

Spoil heaps must be designed

and shaped with stable side

slopes and suitable drainage

Implement:

DED Consultants

D&B Contractor

Monitor:

MWSS

Part of project

(construction) cost

Detailed Engineering

Design (DED) scope of

work

Detailed Engineering

Design Plans

In Progress Geocomposite steel mesh with anchor bolts has

been installed upon portal

Soil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Generationof spoil and spoil

disposal

More than 150,000m3 is expected

to be generated due to tunnelling

works, which is about 190,000 m3

loose volume.

Spoils heaps must be compacted

during the earthworks.

Implement:

DED Consultants

D&B Contractor

Monitor:

MWSS

Part of project

(construction) cost

Detailed Engineering

Design (DED) scope of

work

Detailed Engineering

Design Plans

In Progress Geocomposite steel mesh with anchor bolts has

been installed upon portal

Soil from intake slope has been removed

Installation of threaded rock bolts have been done

Record of number of poaching

and illegal trading of wildlife

by workers

AWTIP Monitoring Matrix - EIA

Page 104: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase A. Land Generationof spoil and spoil

disposal

More than 150,000m3 is expected

to be generated due to tunnelling

works, which is about 190,000 m3

loose volume.

On complete, the spoil heaps

must be covered with the original

top soil from the site and re-

vegetated

Implement:

DED Consultants

D&B Contractor

Monitor:

MWSS

Part of project

(construction) cost

Detailed Engineering

Design (DED) scope of

work

Detailed Engineering

Design Plans

In Progress Geocomposite steel mesh with anchor bolts has

been installed upon portal

Soil from intake slope has been removed

Installation of threaded rock bolts have been done

Construction Phase A. Land Solid Waste Implement an eco-friendly solid

waste management at work sites

and workers’ camp/s, which minimizes, re-uses, segregates

and promptly disposes of

generated solid waste.

MWSS

D&B Contractor

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress Waste onsite are segregated into biodegredable,

non-biodegradable and residuals. There are

designated bins for each type of waste, color coded

and labeled. Waste are collected every Tuesday and

Thursday by Brgy Bigte. CMC and Brgy Bigte has a

service contract for garbage and hauling disposal

from May 2017 to December 2017.

Service Contract of

Brgy Bigte and CMC

for Garbage hauling

and disposal

Date of Issue: May

30, 2017

Expiry Date: Dec 31,

2017

Construction Phase A. Land Hazardous Waste Locate stationary ground storage

for hazardous waste at least 100

m away from water bodies,

raised to min 1 ft above high

flood level. Or, use mobile

storage but should not be parked

near water bodies..

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress Construction of HAZMAT facility is already on

planning stage.

No accredited hazardous waste disposal hauler has

been contacted yet

hazmat temporary

disposal included in

the Industrial Area

site plan (c/o Sergio

and Federico)

Construction Phase A. Land Hazardous Waste Secure storage areas

appropriately. Storage facilities

must be able to contain spillage.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Construction of HAZMAT facility is already on

planning stagehazmat temporary

disposal included in

the Industrial Area

site plan (c/o Sergio

and Federico)

Construction Phase A. Land Hazardous Waste Dispose of waste promptly and

appropriately.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of WorkIn Progress Construction of HAZMAT facility is already on

planning stagehazmat temporary

disposal included in

the Industrial Area Construction Phase A. Land Hazardous Waste The contractor shall be required

to implement an appropriate

hazardous waste management

program.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress no large volume hazmat waste has been generated

yet. Hazmat temporary disposal included in the site

plan. To be constructed

hazmat temporary

disposal included in

the Industrial Area

site plan (c/o Sergio

and Federico)

Construction Phase A. Land Hazardous Waste Storage of oil and grease used

for the maintenance and

operation of heavy equipment

shall be properly built and

maintained, to include bunded

storage for the capacity of the

containers plus 10%, and oil

traps on drainage outfalls.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress no large volume hazmat waste has been generated

yet. Hazmat temporary disposal included in the site

plan. To be constructed

hazmat temporary

disposal included in

the Industrial Area

site plan (c/o Sergio

and Federico)

AWTIP Monitoring Matrix - EIA

Page 105: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

At the active work site:

Mitigating contaminants

Provide adequate sanitation

facilities and water supply at work

sites and workers’ camp. Enforce observance of good

sanitation practices by workers.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant High coliform was reported in segment of surface

water where there are communities alongt the

riverbanks. The construction camp is near the

riverbank and might be a potential contributor to

poor surface water quality.

Construction area at the inlet is a steep slope. Any

accidental chemical spillage can be flushed to Angat

River. Intakes of the 3 existing tunnels in adjacent to

the Tunnel 4 intake site.

Waste onsite are segregated into biodegredable,

non-biodegradable and residuals. There are

designated bins for each type of waste, color coded

and labeled. Waste are collected every Tuesday and

Thursday by Brgy Bigte. CMC and Brgy Bigte has a

service contract for garbage and hauling disposal

from May 2017 to December 2017.

The first water quality sampling was conducted by

CMC last August 2017 with the following

parameters: Temperature, pH, electric conductivity,

tubidity, color, TDS, ORP, dissolved oxygen, BOD,

coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ

paramters using portable water meters started on

October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Implement solid waste

management that minimizes, re-

uses, properly segregates and

promptly and properly disposes

of generated solid wastes.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant High coliform was reported in segment of surface

water where there are communities alongt the

riverbanks. The construction camp is near the

riverbank and might be a potential contributor to

poor surface water quality.

Construction area at the inlet is a steep slope. Any

accidental chemical spillage can be flushed to Angat

River. Intakes of the 3 existing tunnels in adjacent to

the Tunnel 4 intake site.

Waste onsite are segregated into biodegredable,

non-biodegradable and residuals. There are

designated bins for each type of waste, color coded

and labeled. Waste are collected every Tuesday and

Thursday by Brgy Bigte. CMC and Brgy Bigte has a

service contract for garbage and hauling disposal

from May 2017 to December 2017.

The first water quality sampling was conducted by

CMC last August 2017 with the following

parameters: Temperature, pH, electric conductivity,

tubidity, color, TDS, ORP, dissolved oxygen, BOD,

coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ

paramters using portable water meters started on

October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

AWTIP Monitoring Matrix - EIA

Page 106: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Implement hazardous waste

management that minimizes,

properly segregates and

promptly and properly disposes

of generated hazardous wastes.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Hazmat identified at this stage of construction is

limited to oil, lubricants used by heavy equipment

and vehicles. Most vehicles used are brand new.

Maintenance is done off site.

Hazmat temporary storage included in the site plan

The first water quality sampling was conducted by

CMC last August 2017 with the following

parameters: Temperature, pH, electric conductivity,

tubidity, color, TDS, ORP, dissolved oxygen, BOD,

coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ

paramters using portable water meters started on

October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location

and results on the report).

MPR

Self Monitoring Report

(SMR)

Site Inspection Report

(c/o Jasper Cazenas and

Ricky Latunio)

hazmat temporary disposal

included in the Industrial

Area site plan (c/o Sergio

and Federico)

Photo-documentation

Turbidity Monitoring (c/o

Jasper Cazenas and Ricky

Latunio) dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results from

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Store hazardous construction

materials in appropriately

contained and elevated area and

at least100 m away from surface

water bodies.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Hazmat identified at this stage of construction is

limited to oil, lubricants used by heavy equipment

and vehicles. Most vehicles used are brand new.

Maintenance is done off site.

Hazmat temporary storage included in the site plan

The first water quality sampling was conducted by

CMC last August 2017 with the following

parameters: Temperature, pH, electric conductivity,

tubidity, color, TDS, ORP, dissolved oxygen, BOD,

coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Weekly monitoring of water turbidity and other in-situ

paramters using portable water meters started on

October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location

and results on the report).

MPR

Self Monitoring Report

(SMR)

Site Inspection Report

(c/o Jasper Cazenas and

Ricky Latunio)

hazmat temporary disposal

included in the Industrial

Area site plan (c/o Sergio

and Federico)

Photo-documentation

Turbidity Monitoring (c/o

Jasper Cazenas and Ricky

Latunio) dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results from

CRL - P00075686-01

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Have equipment clearly leaking

oil repaired off-site immediately.

No vehicle/equipment

maintenance, repair and refueling

to be allowed at the sites.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant No equipment reported to have such case

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

AWTIP Monitoring Matrix - EIA

Page 107: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Treat construction water before

discharge. Install settling pond for

water generated during tunnel

boring. Allow water through

grease trap or oil/collector and/or

filters such as rock filled bags,

block and gravel.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In ProgressHigh coliform was reported in segment of surface

water where there are communities along the

riverbanks. The construction camp is near the

riverbank and might be a potential contributor to

poor surface water quality.

Hazmat identified at this stage of construction is

limited to oil, lubricants used by heavy equipment

and vehicles. Most vehicles used are brand new.

Maintenance is done off site.

Construction of Waste Water Treatment Facility is

on-going.

The first water quality sampling was conducted by

CMC last August 2017 with the following

parameters: Temperature, pH, electric conductivity,

tubidity, color, TDS, ORP, dissolved oxygen, BOD,

coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Water quality in Basin 1 has also been collected and

analyzed last October 2017 with the following

parameters: temperature,TSS, electric conductivity,

turbidity, color and TDS (See sampling location and

results on the report).

Weekly monitoring of water turbidity and other in-situ

paramters using portable water meters started on

October 2017. Testing is done weekly by CMC Envi,

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Implement corrective action,

when trigger thresholds of water

quality are reached.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

CompliantThe first water quality sampling was conducted by

CMC last August 2017 with the following

parameters: Temperature, pH, electric conductivity,

tubidity, color, TDS, ORP, dissolved oxygen, BOD,

coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Water quality in Basin 1 has also been collected and

analyzed last October 2017 with the following

parameters: temperature,TSS, electric conductivity,

turbidity, color and TDS (See sampling location and

results on the report).

Weekly monitoring of water turbidity and other in-situ

paramters using portable water meters started on

October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location

and results on the report)

visual inspection done through photo and video

documentation

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

AWTIP Monitoring Matrix - EIA

Page 108: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

During construction, the

contractor shall take corrective

action to reduce concentration to

below the standard.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

CompliantThe first water quality sampling was conducted by

CMC last August 2017 with the following

parameters: Temperature, pH, electric conductivity,

tubidity, color, TDS, ORP, dissolved oxygen, BOD,

coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Water quality in Basin 1 has also been collected and

analyzed last October 2017 with the following

parameters: temperature,TSS, electric conductivity,

turbidity, color and TDS (See sampling location and

results on the report).

Weekly monitoring of water turbidity and other in-situ

paramters using portable water meters started on

October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location

and results on the report)

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Mitigating sedimentation

Build cofferdams when

constructing inlet structure

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Not Applicable inlet works not yet started

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Use any combination of perimeter

controls at spoil disposal areas or

stockpiles of aggregate

materials, e.g., silt fences,

sediment basins, sandbags,

earth bern/bund.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

CompliantThe first water quality sampling was conducted by

CMC last August 2017 with the following

parameters: Temperature, pH, electric conductivity,

tubidity, color, TDS, ORP, dissolved oxygen, BOD,

coliform (Total and Fecal) and heavy metals (See

sampling location and results on the report).

Water quality in Basin 1 has also been collected and

analyzed last October 2017 with the following

parameters: temperature,TSS, electric conductivity,

turbidity, color and TDS (See sampling location and

results on the report).

Weekly monitoring of water turbidity and other in-situ

paramters using portable water meters started on

October 2017. Testing is done weekly by CMC Envi,

Health and Safety Officers (See sampling location

and results on the report)

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o Jasper

Cazenas and Ricky

Latunio)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

AWTIP Monitoring Matrix - EIA

Page 109: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase B. Water Impact on surface water quality

due to/ from:

(a) Contaminants from materials

used and construction activities

and processes

(b) Siltation from soil erosion,

spoil disposal area, drill and

blasting, dewatering excavations,

etc

Minimize / control dewatering or

extraction of tunnel water by

storing and re-using pumped-out

water from the tunnel.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress Water treatment plant is already under construction

Water quality in Basin 1 has also been collected and

analyzed last October 2017 with the following

parameters: temperature,TSS, electric conductivity,

turbidity, color and TDS (See sampling location and

results on the report).

Construction Phase B. Water Extraction of water from the dam

site (inlet) and creek (near the

outlet) to be used as coolant

during construction

Use efficient tunneling technology

that recycles tunnel drainage

water to minimize extraction of

water.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress Water treatment plant is already under construction

Water quality in Basin 1 has also been collected and

analyzed last October 2017 with the following

parameters: temperature,TSS, electric conductivity,

turbidity, color and TDS (See sampling location and

results on the report).

Construction Phase B. Water Impact on groundwater:

(a) deteriorating water quality due

to:

• Silt/sediments• Solid waste• Hazardous materials and waste

In all active work sites:

Site temporary stockpile of

excavated soils in flat areas,

away from main surface drainage

routes, limit to maximum of 2 m

high.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress Stockpile is at minimum especially in Ipo

construction site (Intake).

Spoil management plan has been drafted and

already submitted to MWSS. Spoil disposal area,

MAPOL quarry, was identified. It has an approximate

land area of 4 hectares, located approximately 2

kilometers from the source of spoil.

Construction Phase B. Water Impact on groundwater:

(a) deteriorating water quality due

to:

• Silt/sediments• Solid waste• Hazardous materials and waste

Provide silt fences, silt traps, or

sand bags, at stockpiles of

aggregate materials.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress No silt fences, traps, or sand bags have been

provided yet.

Stockpile is at minimum especially in Ipo

construction site (Intake).

Spoil management plan has been drafted and

already submitted to MWSS. Spoil disposal area,

MAPOL quarry, was identified. It has an approximate

land area of 4 hectares, located approximately 2

kilometers from the source of spoil.

No groundwater monitoring has been done yet

since excavation of tunnel had not started.

Construction Phase B. Water Impact on groundwater:

(a) deteriorating water quality due

to:

• Silt/sediments• Solid waste• Hazardous materials and waste

Dispose of residual soil/spoil as

soon as possible, to the disposal

areas, or as free backfilling

materials for LGU/barangay

roads.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress No silt fences, traps, or sand bags have been

provided yet.

Stockpile is at minimum especially in Ipo

construction site (Intake).

Spoil management plan has been drafted and

already submitted to MWSS. Spoil disposal area,

MAPOL quarry, was identified. It has an approximate

land area of 4 hectares, located approximately 2

kilometers from the source of spoil.

No groundwater monitoring has been done yet

since excavation of tunnel had not started.

DAO 1994- 26A for Philippine

drinking water quality

standards

DAO 1994- 26A for Philippine

drinking water quality

standards

DAO 1994- 26A for Philippine

drinking water quality

standards

Water Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standardsWater Column. Parameters to

characterize the physico-

chemical and biological status

of the water column to include

but not limited to: temperature,

salinity, total suspended

solids, turbidity, dissolved

oxygen and bacteriological

parameters.

Refer to DAO 34 and 35 for

water quality standards

AWTIP Monitoring Matrix - EIA

Page 110: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase B. Water Impact on groundwater:

(a) deteriorating water quality due

to:

• Silt/sediments• Solid waste• Hazardous materials and waste

Avoid stockpiling more

aggregates than necessary

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress No silt fences, traps, or sand bags have been

provided yet.

Spoil management plan to be formulated. Spoil

disposal area, MAPOL quarry, was identified. It has

an approximate land area of 4 hectares, located

approximately 2 kilometers from the source of spoil.

No groundwater monitoring has been done yet

since excavation of tunnel had not started.

Construction Phase B. Water Lowering of water level of wells

nearby communities due to

tunneling, pumping/extracting of

tunnel drainage water

Monitor for potential groundwater

depletion in existing wells in the

vicinity. Provide interim measures

to avoid disrupting water supply

to affected households.

Investigate for proper corrective

action.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Non-Compliant No groundwater monitoring has been done yet

since excavation of tunnel had not started.

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

At the project area, locate

emission sources away from

sensitive receptors, e.g., concrete

batching and rock crushing

plants at least 500m upwind of

sensitive receptors.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress No dust curtains/net has been installed.

Dust supression has been implemented already.

Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level

Monitoring(c/o Jasper

Cazenas and Ricky

Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

In active work sites:

Use of blast curtains / nets to

capture dust from blasting

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Not ApplicableMaintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

suhc as WHO Air Quality

Guidelines Global Update,

2005

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

such as WHO Air Quality

Guidelines Global Update,

2005

DAO 1994- 26A for Philippine

drinking water quality

standards

AWTIP Monitoring Matrix - EIA

Page 111: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

Apply dust suppression

techniques, e.g., watering with

bowsers, sheeting particularly at

Bigte area

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant No dust curtains/net has been installed.

Dust supression has been implemented already.

Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

Water dry unpaved/exposed

surfaces, stockpiles of sand and

excavated materials, at least

twice daily, or as necessary.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress No dust curtains/net has been installed.

Dust supression has been implemented already.

Open burning is not practiced onsite

Speed limit has not yet implemented

Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

Protect aggregate stockpiles with

sheeting to restrict the movement

of dust.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

suhc as WHO Air Quality

Guidelines Global Update,

2005

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

suhc as WHO Air Quality

Guidelines Global Update,

2005

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

suhc as WHO Air Quality

Guidelines Global Update,

2005

AWTIP Monitoring Matrix - EIA

Page 112: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

Throughout the tunnelling

construction period

Continuous monitoring of oxygen

with equipment conforming to BS

EN 50104

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

NC-Time TBM has a built-in air quality monitoring device to

measure oxygen, methane and carbon dioxide

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

Require trucks, particularly those

hauling aggregates, to have

secure covers.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

Limit engine idling to 5 minutes. Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress No dust curtains/net has been installed.

Dust supression has been implemented already.

Open burning is not practiced onsite

Speed limit has not yet implemented

Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level Monitoring

(c/o Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

suhc as WHO Air Quality

Guidelines Global Update,

2005

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

suhc as WHO Air Quality

Guidelines Global Update,

2005

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

suhc as WHO Air Quality

Guidelines Global Update,

2005

AWTIP Monitoring Matrix - EIA

Page 113: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

Prohibit open burning of

vegetation and other waste in the

project area

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Open burning is not practiced onsite

Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

Construction Phase C. Air Deterioration of ambient air

quality due to dust and gas

emissions from:

Earthworks and other construction

processes; tunneling

Stockpiling of aggregates and

spoils, and conveyance of spoils

to disposal areas;

Increased transport activities in

the construction areas and along

Ipo Road;

urning of vegetation and wastes;

and

Operation of mechanical

equipment

Ipo Road, main access road,

other roads in the Project area,

llimit speed of all construction

vehicles to maximum of 40 kph

on the access road to, and

maximum of 30 kph in the site.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level Monitoring

(c/o Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Phase C. Air Noise and vibration in the project

area from excavation activities;

general construction activities;

and vehicle and equipment

operations

Use only equipment that emit

least noise and vibration and are

well maintained.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Trevi Foundations conducted inland drilling for

seismic test

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

such as WHO Air Quality

Guidelines Global Update,

2005

Adopt national standards for

construction sites and

residential areas if available.

Alternatively use internationally

accepted standards such as

WHO.

Maintain national air quality

standards or if these are not

available, internationally

accepted air quality standards

suhc as WHO Air Quality

Guidelines Global Update,

2005

AWTIP Monitoring Matrix - EIA

Page 114: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase C. Air Noise and vibration in the project

area from excavation activities;

general construction activities;

and vehicle and equipment

operations

Use facility layout to minimize

noise propagation e.g. using

topography / existing buildings as

barriers, where possible locate

noisy activities away from local

communities.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress

Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level Monitoring

(c/o Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Phase C. Air Noise and vibration in the project

area from excavation activities;

general construction activities;

and vehicle and equipment

operations

Control noise at source, e.g. low

noise plant, muffling, acoustic

screening, switch off campaigns

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

PPEs (earplugs and earmuffs are used onsite)

Sound Level Monitoring

(c/o Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Phase C. Air Noise and vibration in the project

area from excavation activities;

general construction activities;

and vehicle and equipment

operations

Restrict use of noisy and highly

vibrating equipment from 8AM-

5PM. Necessary overtime work

should: a) not go beyond 9:00PM;

b) observe regulated noise and

vibration levels; c) not use noisy

and highly vibrating equipment;

and d) should be coordinated

with the barangay and affected

households.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level Monitoring

(c/o Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Adopt national standards for

construction sites and

residential areas if available.

Alternatively use internationally

accepted standards such as

WHO.

Adopt national standards for

construction sites and

residential areas if available.

Alternatively use internationally

accepted standards such as

WHO.

Adopt national standards for

construction sites and

residential areas if available.

Alternatively use internationally

accepted standards such as

WHO.

AWTIP Monitoring Matrix - EIA

Page 115: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase C. Air Noise and vibration in the project

area from excavation activities;

general construction activities;

and vehicle and equipment

operations

Manage the ins and outs of

hauling trucks. Spread out the

schedule of material, waste and

spoil transport in the day (off-

peak hours).

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level Monitoring

(c/o Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Phase C. Air Noise and vibration in the project

area from excavation activities;

general construction activities;

and vehicle and equipment

operations

Enforce the rule of no blowing of

horns.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

Sound Level Monitoring

(c/o Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Phase C. Air Noise and vibration in the project

area from excavation activities;

general construction activities;

and vehicle and equipment

operations

Strictly enforce upon workers the

compliance with wearing of ear

mufflers, especially those who

are operating equipment.

Implement: D&B

Contractor

Monitor: OSP-

AWTIP

Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Agreement with CRL Laboratories for air quality

monitoring is now in place (24 August 2017). The air

quality sampling dates will be scheduled once the

Tunnel Excavation starts.

Schedule of Air Quality Monitoring:

A sound level meter was procured by CMC to

monitor the noise level during construction period as

one of the requirements of ADB and DENR. Noise

monitoring started on 28 October 2017.

PPEs (earplugs and earmuffs are used onsite)

Sound Level Monitoring

(c/o Jasper Cazenas and

Ricky Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Phase D. The People Traffic due to:

(a) inadequate capacity of Ipo

Road (access road)

(b) expected volume of truck

movement

Institute prior coordination with

the Barangay and Municipality for

the formulation of a traffic

management and safety plan and

for clearing of structures

encroaching into access road

ROW.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Adopt national standards for

construction sites and

residential areas if available.

Alternatively use internationally

accepted standards such as

WHO.

Adopt national standards for

construction sites and

residential areas if available.

Alternatively use internationally

accepted standards such as

WHO.

Zero road accident and related

incidents

Adopt national standards for

construction sites and

residential areas if available.

Alternatively use internationally

accepted standards such as

WHO.

AWTIP Monitoring Matrix - EIA

Page 116: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase D. The People Traffic due to:

(a) inadequate capacity of Ipo

Road (access road)

(b) expected volume of truck

movement

Prior to construction, clear

easement of encroaching

structures, most of them being

temporary.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Construction Phase D. The People Traffic due to:

(a) inadequate capacity of Ipo

Road (access road)

(b) expected volume of truck

movement

Strategically post billboards

informing the public about the

expected increase in volume of

traffic in the influence area due to

Project implementation. Post at

least two weeks prior to

mobilization.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Bulletin boards for IEC purpose were installed in the

barangay halls of Brgy Bigte and San Mateo.CMC. Request for

Permission to Install

Bulletin Boad.

Barangay San

Mateo, Norzagaray,

Bulacan. June 6,

2017

CMC. Request for

Permission to Install

Bulletin Boad.

Barangay Bigte,

Norzagaray, Bulacan.

June 20, 2017

Construction Phase D. The People Traffic due to:

(a) inadequate capacity of Ipo

Road (access road)

(b) expected volume of truck

movement

Coordinate with the Barangay for

assistance in traffic management.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Hauling truck, heavy equipment and other

construction related machines are expected at the

construction sites and associated road such as Ipo

Road during the construction

Construction Phase D. The People Traffic due to:

(a) inadequate capacity of Ipo

Road (access road)

(b) expected volume of truck

movement

Strategically post traffic flagmen

along Ipo Road, equipped with

two-way radio.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Construction Phase D. The People Traffic due to:

(a) inadequate capacity of Ipo

Road (access road)

(b) expected volume of truck

movement

Post sufficiently legible

(reflectorized) traffic safety notice

and signage at strategic locations

along the entire stretch of the

access road.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Traffic and safety signage were installed onsite

Construction Phase D. The People Traffic due to:

(a) inadequate capacity of Ipo

Road (access road)

(b) expected volume of truck

movement

Limit speed to 40 kph along Ipo

Road, 20 kph at highly populated

sections of Ipo Road, and 30 kph

at construction sites and unpaved

haulage roads.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Speed limit is not implemented yet.

Construction Phase D. The People Potential damage of existing

roads used as access roads due

to movement of heavy equipment

and vehicles

Coordinate with DPWH

regarding the use of Ipo Road.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Construction Phase D. The People Potential damage of existing

roads used as access roads due

to movement of heavy equipment

and vehicles

Restore access roads within the

MWSS compound to the pre-

construction condition or better.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant

Zero road accident and related

incidents

Zero road accident and related

incidents

Zero road accident and related

incidents

Zero road accident and related

incidents

Zero road accident and related

incidents

Zero road accident and related

incidents

AWTIP Monitoring Matrix - EIA

Page 117: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase D. The People Restricted access to the existing

fish landing sites in Sitio

Consultant (identified area as the

Contractor’s Work Area) and boat landing at Sitio Ipo

Inform affected communities

living in Ipo Watershed on the

impact of construction works on

transportation and consult them

for the best alternative route.

Have alternative route and fish

and boat landing sites ready for

use prior to commencement of

construction activities.

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Wire mesh has been installed for slope protection

Safety signage has been installed

Construction Phase D. The People Restricted access to the existing

fish landing sites in Sitio

Consultant (identified area as the

Contractor’s Work Area) and boat landing at Sitio Ipo

Provide alternative access to

school for school children and

residents

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress

Construction Phase D. The People Restricted access to the existing

fish landing sites in Sitio

Consultant (identified area as the

Contractor’s Work Area) and boat landing at Sitio Ipo

Establish alternate boat landing

at the mouth of Sapang Munti

River

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Alternate boat have been provided for the affected

residents

Construction Phase D. The People Restricted access to the existing

fish landing sites in Sitio

Consultant (identified area as the

Contractor’s Work Area) and boat landing at Sitio Ipo

Install soil entrapment nets and

coffer dams to contain soil

erosion at dam site

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

In Progress

Construction Phase D. The People Restricted access to the existing

fish landing sites in Sitio

Consultant (identified area as the

Contractor’s Work Area) and boat landing at Sitio Ipo

Provide clear signage of

alternative routes

D&B Contractor Part of project

(construction) cost

D&B Contractor Scope

of Work

D&B Contractor’s C-EMP

Compliant Signage has been posted already

Construction Phase D. The People Community health and safety

hazards - Potential health risks for

persons with chronic disease

such as asthma, and other

respiratory diseases due dust

pollution within the vicinity of the

construction site and along road

side

Secure project area, including

Associated facilities particularly

the storage for explosives, from

unauthorized entry.

CompliantUnauthorized entry signage have been installed

onsite

Grievance procedure and scheme to be formulated

UXO survey and clearing have been done by hired

demining company, Vourvon Electronica Marketing.

UXO were retrieved and surrendered to the

Philippine Army.

Clearance

Certification

Issued by: Vourvon

Electronica

Marketing

Issued on: May 29,

2017

Certification of

Receipt of

Unexploded

Explosives

Issued by: Alpha

Aggressor Company

Issued on: July 17,

2017

Construction Phase D. The People Community health and safety

hazards - Potential health risks for

persons with chronic disease

such as asthma, and other

respiratory diseases due dust

pollution within the vicinity of the

construction site and along road

side

Implement measures to mitigate

impacts on air and water quality,

noise, traffic.

In Progress A complaint was received on July 18,2017 by CMC

which was filed by residents of Calle Onse (adjacent

to the Industrial Area in Brgy Bigte regarding the

generation of dust and mud along the road. This

case was investigated by CMC H&S together with

representative of Calle Onse. CMC already made

provision of a canal across the Industrial Area. The

problem is not attributed solely to CMC but residents

addressed grievance to CMC hoping to get some

help. The case was closed and H&S has the detailed

documentation.

Grievance report (c/o

Jasper Cazenas and

Ricky Latunio)

AWTIP Monitoring Matrix - EIA

Page 118: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase D. The People Community health and safety

hazards - Potential health risks for

persons with chronic disease

such as asthma, and other

respiratory diseases due dust

pollution within the vicinity of the

construction site and along road

side

Provide mechanism to reduce

dust /other pollutants (ie. water

spraying on the road, timing of

blasting during day time, etc.)

In Progress no grievance case recorded on this regard from

July to December 2017

Construction Phase D. The People Community health and safety

hazards - Potential health risks for

persons with chronic disease

such as asthma, and other

respiratory diseases due dust

pollution within the vicinity of the

construction site and along road

side

People with impaired health/risks

wear masks and other protective

device

Cannot Document Compliance

Construction Phase D. The People Workers’ health and safety hazard Mitigating impacts from blasting:

(a) Include H&S protocols in the

C-EMP on the safe procedures in

the storage, handling and use of

explosives during construction.

Compliant Health and Safety Officers have been hired.

Construction Phase D. The People Workers’ health and safety hazard (b) Control the blasting by using

small charges. Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (c) Evacuation procedures in

tunnel prior to setting charges. NC-Time

Construction Phase D. The People Workers’ health and safety hazard (d) Set up a sufficiently equipped

emergency first-response and

health care team, linked to an

ultimate response team.

Compliant Health and safety staff have been hired by CMC

Health and safety plan has been formulated

Standby doctor and nurse are present onsite

Ambulance, first aid kits, and fire extinguishers have

been provided

Personal Protective Equipment (PPE) are given to

the staff. Contractors’ staff are REQUIRED to use PPE onsite at all times.

CMC Health and

Safety Plan

Construction Phase D. The People Workers’ health and safety hazard (e) Provide safe housing with

adequate basic services. Compliant Housing was provided for CMC employees

Construction Phase D. The People Workers’ health and safety hazard (f) Enforce use of protective

wears when at work. Compliant

Construction Phase D. The People Workers’ health and safety hazard (g) Conduct pre-mobilization

orientation workshop on health

and safety and emergency

response and evacuation

procedures

Compliant

Construction Phase D. The People Workers’ health and safety hazard Handling and storage of

explosives:

(a) Magazine storage should be

far from residential areas, roads,

transmission lines, dams and

their appurtenant works.

Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (b) Site should be well-drained

and sloping, accessible by road.

At least 100 m from overhead

power transmission lines.

Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (c) Detonators should not be

stored together with explosives.Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (d) Maintenance should follow the

prescribed instructions for the

explosives.

Not Applicable

AWTIP Monitoring Matrix - EIA

Page 119: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Construction Phase D. The People Workers’ health and safety hazard (e) Inside of all magazines should

be kept thoroughly clean.Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (f) Cigarettes and matches

should not be taken into

Explosives should be used

according to date of manufacture

magazines. Its keeper should

ensure this.

Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (g) Explosive boxes should be of

wood or soft non-ferrous metal,

e.g., brass, copper.

Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (h) Magazine should be securely

locked, when not attended.Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (i) Detailed records of outgoing

and incoming stocks should be

kept

Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (j) Magazines should be kept free

from bushes and vegetation.Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (k) Empty boxes, loose packing

material or cotton waste should

not be kept on the magazine

premises.

Not Applicable

Construction Phase D. The People Workers’ health and safety hazard (l) Do not open magazines during

or on the approach of a

thunderstorm. No person should

remain in the vicinity of the

magazine during such storm

Not Applicable

Construction Phase D. The People Public safety related to future

development and activities along

the ROW

MWSS must secure the ROW.

Existing above ground

infrastructure along ROW should

be limited. The public must not

be allowed to encroach onto the

ROW by constructing any

buildings or farming the land.

MWSS Not Applicable

Operation Phase B. The Water Changes in hydrology along

Angat River during dry season

During the operation phase, flows

shall be monitored downstream

of Ipo dam.

Concession agrrement In Progress flows at the Ipo Reservoir is being measured on a

daily basis

flowrate of water to

Ipo (c/c MWSS)

Operation Phase B. The Water Changes in hydrology along

Angat River during dry season

As practice in the Philippines, Ipo

dam should maintain 10%

riparian flow downstream of Ipo

dam. This flow aims to allow

migration of fish species and to

maintain natural characteristics of

the river downstream of Ipo dam.

Concession agrrement Compliant

Operation Phase B. The Water Public safety related to future

development and activities along

the ROW

MWSS must secure the ROW.

Existing above ground

infrastructure along ROW should

be limited. The public must not

be allowed to encroach onto the

ROW by constructing any

buildings or farming the land.

MWSS

CPF (represented

by 2 water

concessionaires -

MWCI and MWSI)

Part of project

maintenance cost

LGU/ MWSS/

Concessionaires ‘ responsibility

Concession Agreement

Compliant

Operation Phase B. The Water Security of tunnel 4

Potential encroachment of

informal settlers along the 8

ROW, 6.4 Km alignment

Conduct IEC on how to ensure

security of tunnel 4

Concessionaires

/MWSS/

barangay

LGU/ MWSS/

Concessionaires ‘ responsibility

Concession Agreement

In Progress MWSS has priliminary discussion with CPF on the

securing of Tunnel ROW.

AWTIP Monitoring Matrix - EIA

Page 120: Angat Water Transmission Improvement Project

No. Project Phase Environmental

Component likely to be

affected

Potential Impact Options for prevention or

mitigation or enhancement

Responsible

entity

Cost Guarantee/ financial

arrangements

Compliance Status Remarks

Relevant

Documents

Performance Indicator

Operation Phase B. The Water Security of tunnel 4

Potential encroachment of

informal settlers along the 8

ROW, 6.4 Km alignment

Continuous monitoring of the

ROW alignment for potential

encroachers

Concessionaires

/MWSS/

barangay

LGU/ MWSS/

Concessionaires ‘ responsibility

Concession Agreement

In Progress

Operation Phase B. The Water Security of tunnel 4

Potential encroachment of

informal settlers along the 8

ROW, 6.4 Km alignment

Fencing of the 60m ROW where

aqueduct 4 is located

Incentives /imposition of penalty

for encroachers

Concessionaires

/MWSS/

barangay

LGU/ MWSS/

Concessionaires ‘ responsibility

Concession Agreement

Compliant

AWTIP Monitoring Matrix - EIA

Page 121: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

Documents

Implement Monitor

Pre-construction Required

permits/clearance

Obtain the following prior to

Notice of Award:

a. ECC

Php 500,000.00 MWSS Permits/clearances

obtained prior to

Notice of Award

Employer's

requirement

documents

Compliant ECC was issued on April 7,

2017

Permit:

Environmental

Compliance

Certifcate (ECC)

Permit #:

EMB.ECC-CO-

1508-002

Date of Issue: Apr

7, 2017

Expiry Date: Apr

7, 2022

Pre-construction Required

permits/clearance

b. MOA between DENR RO3,

NPC and MWSS

None MWSS Permits/clearances

obtained prior to

Notice of Award

Employer's

requirement

documents

Compliant Land use permit from NPC is

secured on July 17,2017.

Permit: Land Use

Permit

Permit #: 2017-

LUP-03

Date of Issue: July

17, 2017

Expiry Date: July

14, 2042

Agency: National

Power Corporation

(NPC)

Pre-construction Required

permits/clearance

c. Permit to cut tree Part of construction cost Part of

construction

cost

Permits/clearances

obtained prior to

Notice of Award

Compliant Tree Cutting Permit – from Community Environment and

Natural Resources (DENR-

CENRO) have been secured.

Tree cutting

Permits issued by

Community

Environment and

Natural Resources

(DENR-CENRO)

a. Date of Issue:

July 10, 2017

Expiry Date: July

25, 2017

b. Date of Issue:

July 25, 2017

Expiry Date: July

30, 2017

c. Date of Issue:

August 16, 2017

Expiry Date:

August 31, 2017

d. Date of Issue:

August 24, 2017

Expiry Date:

August 31, 2017

e. Date of Issue:

September 11,

2017

Expiry Date:

September 18,

2017

f. Date of Issue:

September 23,

2017

Responsible

AWTIP Monitoring Matrix - IEE

Page 122: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Pre-construction Required

permits/clearance

c. Permit to Operate Part of construction cost Part of

construction

cost

Permits/clearances

obtained prior to

Notice of Award

Employer's

requirement

documents

Compliant Permit to operate has been

secured on October 20, 2017

Permit: Permit to

Operate

Permit #: FLA-17J-

03BU-550 (1 Unit

20 KW) Standby

Genset

Permit #:

17J03BU-549 (1

unit 40KW

Standby GenSet)

Date of Issue:

October 20, 2017

Expiry Date:

October 28, 2017Pre-construction Required

permits/clearance

d. Permit to use explosives for

construction

Part of construction cost Part of

construction

cost

Permits/clearances

obtained prior to

Notice of Award

Employer's

requirement

documents

Not Applicable Not applicable. Tunnel boring

machine will be used.

Pre-construction Prepare relevant

communities

Conduct intensive social and

environmental awareness

program at least one month

prior to Notice of Award,

covering: (i) communicable/

transmittable diseases that may

be brought with the entry of

workers; (ii) potential social

conflicts between communities

and workers; (iii) other health

and safety hazards and

impacts during construction and

during maintenance and repair

of completed works;

and (iv) the grievance redress

mechanism.

Included in OSP-AWTIP'a

budget

OSP-AWTIP

Affected

barangays

In Progress Bulletin boards for IEC purpose

were installed in the barangay

halls of Brgy Bigte and San

Mateo.

CMC. Request for

Permission to

Install Bulletin

Boad. Barangay

San Mateo,

Norzagaray,

Bulacan. June 6,

2017

CMC. Request for

Permission to

Install Bulletin

Boad. Barangay

Bigte, Norzagaray,

Bulacan. June 20,

2017

CMC. Request for

Permission to

Install Bulletin

Boad. Ipo

Elementary

School,

Norzagaray,

Bulacan. August

7, 2017

Pre-construction Ensure

environmentally

responsible

procurement

Include an SPS-compliant EMP

in the bidding documents.

Not applicable OSP-AWTIP SPS-compliant EMP

included in the bidding

documents

Compliant see Bidding Document General

Conditons of the Contract

(Section 6 and Employer's

Requirment (Section 7)

General

Conditions of the

Contract (AWTIP-

ICB-CW001)

Section 6

Employers

Requirement and

Section 7 General

Conditions of the

Contract

AWTIP Monitoring Matrix - IEE

Page 123: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Pre-construction Append EMP to the Contract for

basis in the preparation of the C-

EMP

OSP-AWTIP EMP appended in the

Contract

Compliant see General Conditons of the

Contract (Section 6 and

Employer's Requirment

(Section 7)

General

Conditions of the

Contract (AWTIP-

ICB-CW001)

Section 6

Employers

Requirement and

Section 7 General

Conditions of the

Contract

Pre-construction In Contract, require D&B

Contractor to submit monthly

and semi-annual environmental

monitoring report

OSP-AWTIP Requirement stated in

the contract

Compliant see General Conditons of the

Contract (Section 6 and

Employer's Requirment

(Section 7)

General

Conditions of the

Contract (AWTIP-

ICB-CW001)

Section 6

Employers

Requirement and

Section 7 General

Conditions of the

Contract

Pre-construction Stipulate in the Contract the tie-

up of progress payment and

collection of performance bond

with the performance in C-EMP

implementation

OSP-AWTIP Stipulation in the

contract

Compliant see General Conditons of the

Contract (Section 6 and

Employer's Requirment

(Section 7)

AWTIP Contract

Agreement signed

2016 May 25G.

Esquivel (MWSS)

and A Ciamei

(CMC)

General

Conditions of the

Contract (AWTIP-

ICB-CW001)

Section 6

Employers

Requirement and

Section 7 General

Conditions of the

Contract

Pre-construction Prepare C-EMP that addresses

as minimum the requirements of

the EMP. A final construction

spoil management plan will be

prepared by Contractor for

endorsement / approval by both

MWSS and ADB. The plan

should be included in the C-

EMP to be prepared by D&B

Contractor.

D&B

Contractor

Presence of a C-EMP

based on EMP

Compliant CEMMP has been submitted by

CMC to MWSS on 2017 July 7.

CEMMP, June

2017

AWTIP Monitoring Matrix - IEE

Page 124: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Pre-construction Evaluate the C-EMP

quantitatively and qualitatively

against the EMP

OSP-AWTIP Evaluation undertaken

quantitatively and

qualitatively

Compliant CEMMP has been approved by

MWSS. Please see letter of

MWSS to CMC dated 15

August 2017

CEMMP:

Contractor's

Environmental

Management and

Monitoring Plan.

MWSS letter to

CMC dated 15

August 2017

Pre-construction Clear the C-EMP before the

start of any activity/work on site

or establishment of any

construction-related facility

onsite by D&B Contractor

ADB C-EMP cleared prior to

start of any

mobilization activity on

site by D&B Contractor

Compliant CEMMP has been approved by

MWSS. Please see letter of

MWSS to CMC dated 15

August 2017

CEMMP:

Contractor's

Environmental

Management and

Monitoring Plan.

MWSS letter to

CMC dated 15

August 2017

Pre-construction Endorsement/ approval of the

final construction spoil

management plan, which is part

of CEMP

ADB C-EMP cleared prior to

start of any

mobilization activity on

site by D&B Contractor

In Progress Spoil disposal management is

included in the CEMMP. A

separate document on Spoil

Disposal Procedure is in place.

Copy may be obtained from

CMC

CMC. Spoil

Disposal

Procedure

Construction Physical (Land)

Environment

Soil and erosion

due to:‐ soil disturbance‐ vegetation

clearing

Location: Inlet structure and

relevant work sites

Confine soil disturbance and/or

vegetation clearing to pre-

defined and planned area that

includes project footprint and

needed easements

Part of construction cost D&B

Contractor

OSP-AWTIP Compliant No vegetation survey has been

done yet

Geocomposite steel mesh with

anchor bolts has been installed

upon portals

Spoil from intake slope has

been removed

Installation of threaded rock

bolts have been doneConstruction Physical (Land)

Environment

Soil and erosion

due to:‐ soil disturbance‐ vegetation

clearing

Stabilize exposed soils with

temporary seeding, mulches,

mats, non chemical-based soil

binders.

Part of construction cost D&B

Contractor

OSP-AWTIP CEMP Compliant No vegetation survey has been

done yet

Geocomposite steel mesh with

anchor bolts has been installed

upon portals

Spoil from intake slope has

been removed

Installation of threaded rock

bolts have been doneConstruction Physical (Land)

Environment

Soil and erosion

due to:‐ soil disturbance‐ vegetation

clearing

Protect slopes with any one or

combination of bonded fiber

matrices, erosion control

blankets, silt fence, fiber rolls,

and keeping stormwater off the

slopes through diversion

channels and/or berms.

Part of construction cost D&B

Contractor

OSP-AWTIP CEMP Compliant No vegetation survey has been

done yet

Geocomposite steel mesh with

anchor bolts has been installed

upon portals

Spoil from intake slope has

been removed

Installation of threaded rock

bolts have been done

AWTIP Monitoring Matrix - IEE

Page 125: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Physical (Land)

Environment

Soil and erosion

due to:‐ soil disturbance‐ vegetation

clearing

Re-vegetate disturbed

soils/slopes as soon as possible

after completion of the

construction works.

Part of construction cost D&B

Contractor

OSP-AWTIP CEMP Compliant No vegetation survey has been

done yet

Geocomposite steel mesh with

anchor bolts has been installed

upon portals

Spoil from intake slope has

been removed

Installation of threaded rock

bolts have been doneConstruction Physical (Land)

Environment

Soil and erosion

due to:‐ soil disturbance‐ vegetation

clearing

Replacing vegetation that died

during the defects liability

period.

Part of construction cost D&B

Contractor

OSP-AWTIP CEMP Compliant No vegetation survey has been

done yet

Geocomposite steel mesh with

anchor bolts has been installed

upon portals

Spoil from intake slope has

been removed

Installation of threaded rock

bolts have been doneConstruction Physical (Land)

Environment

Soil and erosion

due to:‐ soil disturbance‐ vegetation

clearing

At the active work sites,

Provide temporary drainage with

sedimentation tank or filters

such as block and gravel, prior

to discharge to watercourses

Part of construction cost D&B

Contractor

OSP-AWTIP CEMP Compliant No vegetation survey has been

done yet

Geocomposite steel mesh with

anchor bolts has been installed

upon portals

Spoil from intake slope has

been removed

Installation of threaded rock

bolts have been doneConstruction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

At the active work sites

Mitigating contaminants

Provide adequate sanitation

facilities and water supply at

work sites and workers’ camp. Enforce observance of good

sanitation practices by workers.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Compliant The first water quality sampling

was conducted by CMC last

August 2017 with the following

parameters: Temperature, pH,

electric conductivity, tubidity,

color, TDS, ORP, dissolved

oxygen, BOD, coliform (Total

and Fecal) and heavy metals

(See sampling location and

results on the report).

Water quality in Basin 1 has

also been collected and

analyzed last October 2017

with the following parameters:

temperature,TSS, electric

conductivity, turbidity, color and

TDS (See sampling location

and results on the report).

Weekly monitoring of water

turbidity and other in-situ

paramters using portable water

meters started on October

2017. Testing is done weekly

by CMC Envi, Health and

Safety Officers (See sampling

location and results on the

report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o

Jasper Cazenas

and Ricky Latunio)

Photo-

documentation

Turbidity

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

AWTIP Monitoring Matrix - IEE

Page 126: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Implement solid waste

management that minimizes, re-

uses, properly segregates and

promptly and properly disposes

of generated solid wastes.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Compliant High coliform was reported in

segment of surface water where

there are communities alongt

the riverbanks. The

construction camp is near the

riverbank and might be a

potential contributor to poor

surface water quality.

Construction area at the inlet is

a steep slope. Any accidental

chemical spillage can be

flushed to Angat River. Intakes

of the 3 existing tunnels in

adjacent to the Tunnel 4 intake

site.

Waste onsite are segregated

into biodegredable, non-

biodegradable and residuals.

There are designated bins for

each type of waste, color coded

and labeled. Waste are

collected every Tuesday and

Thursday by Brgy Bigte. CMC

and Brgy Bigte has a service

contract for garbage and

hauling disposal from May 2017

to December 2017.

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o

Jasper Cazenas

and Ricky Latunio)

Photo-

documentation

Turbidity

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Implement hazardous waste

management that minimizes,

properly segregates and

promptly and properly disposes

of generated hazardous wastes.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Compliant

Hazmat identified at this stage

of construction is limited to oil,

lubricants used by heavy

equipment and vehicles. Most

vehicles used are brand new.

Maintenance is done off site.

Hazmat temporary storage

included in the site plan

The first water quality sampling

was conducted by CMC last

August 2017 with the following

parameters: Temperature, pH,

electric conductivity, tubidity,

color, TDS, ORP, dissolved

oxygen, BOD, coliform (Total

and Fecal) and heavy metals

(See sampling location and

results on the report).

Weekly monitoring of water

turbidity and other in-situ

paramters using portable water

meters started on October

2017. Testing is done weekly

by CMC Envi, Health and

Safety Officers (See sampling

location and results on the

MPR

Self Monitoring Report

(SMR)

Site Inspection Report

(c/o Jasper Cazenas

and Ricky Latunio)

hazmat temporary

disposal included in the

Industrial Area site

plan (c/o Sergio and

Federico)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

AWTIP Monitoring Matrix - IEE

Page 127: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Store hazardous construction

materials in appropriately

contained and elevated area

and at least100 m away from

surface water bodies.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Compliant

Hazmat identified at this stage

of construction is limited to oil,

lubricants used by heavy

equipment and vehicles. Most

vehicles used are brand new.

Maintenance is done off site.

Hazmat temporary storage

included in the site plan

The first water quality sampling

was conducted by CMC last

August 2017 with the following

parameters: Temperature, pH,

electric conductivity, tubidity,

color, TDS, ORP, dissolved

oxygen, BOD, coliform (Total

and Fecal) and heavy metals

(See sampling location and

results on the report).

Weekly monitoring of water

turbidity and other in-situ

paramters using portable water

meters started on October

2017. Testing is done weekly

by CMC Envi, Health and

Safety Officers (See sampling

location and results on the

MPR

Self Monitoring Report

(SMR)

Site Inspection Report

(c/o Jasper Cazenas

and Ricky Latunio)

hazmat temporary

disposal included in the

Industrial Area site

plan (c/o Sergio and

Federico)

Photo-documentation

Turbidity Monitoring

(c/o Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Have equipment clearly leaking

oil repaired off-site immediately.

No vehicle/equipment

maintenance, repair and

refuelling to be allowed at the

sites.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Compliant No equipment reported to have

such case

AWTIP Monitoring Matrix - IEE

Page 128: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Treat construction water before

discharge. Install settling pond

for water generated during

tunnel boring. Allow water

through grease trap or

oil/collector and/or filters such as

rock filled bags, block and

gravel.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

In ProgressHigh coliform was reported in

segment of surface water where

there are communities along

the riverbanks. The

construction camp is near the

riverbank and might be a

potential contributor to poor

surface water quality.

Hazmat identified at this stage

of construction is limited to oil,

lubricants used by heavy

equipment and vehicles. Most

vehicles used are brand new.

Maintenance is done off site.

Construction of Waste Water

Treatment Facility is on-going.

The first water quality sampling

was conducted by CMC last

August 2017 with the following

parameters: Temperature, pH,

electric conductivity, tubidity,

color, TDS, ORP, dissolved

oxygen, BOD, coliform (Total

and Fecal) and heavy metals

(See sampling location and

results on the report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o

Jasper Cazenas

and Ricky Latunio)

Photo-

documentation

Turbidity

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Implement corrective action,

when trigger thresholds of water

quality are reached.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Compliant The first water quality sampling

was conducted by CMC last

August 2017 with the following

parameters: Temperature, pH,

electric conductivity, tubidity,

color, TDS, ORP, dissolved

oxygen, BOD, coliform (Total

and Fecal) and heavy metals

(See sampling location and

results on the report).

Water quality in Basin 1 has

also been collected and

analyzed last October 2017

with the following parameters:

temperature,TSS, electric

conductivity, turbidity, color and

TDS (See sampling location

and results on the report).

Weekly monitoring of water

turbidity and other in-situ

paramters using portable water

meters started on October

2017. Testing is done weekly

by CMC Envi, Health and

Safety Officers (See sampling

location and results on the

report).

visual inspection done through

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o

Jasper Cazenas

and Ricky Latunio)

Photo-

documentation

Turbidity

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

AWTIP Monitoring Matrix - IEE

Page 129: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

During construction, the

contractor shall take corrective

action to reduce concentration

to below the standard.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Compliant The first water quality sampling

was conducted by CMC last

August 2017 with the following

parameters: Temperature, pH,

electric conductivity, tubidity,

color, TDS, ORP, dissolved

oxygen, BOD, coliform (Total

and Fecal) and heavy metals

(See sampling location and

results on the report).

Water quality in Basin 1 has

also been collected and

analyzed last October 2017

with the following parameters:

temperature,TSS, electric

conductivity, turbidity, color and

TDS (See sampling location

and results on the report).

Weekly monitoring of water

turbidity and other in-situ

paramters using portable water

meters started on October

2017. Testing is done weekly

by CMC Envi, Health and

Safety Officers (See sampling

location and results on the

report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o

Jasper Cazenas

and Ricky Latunio)

Photo-

documentation

Turbidity

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL - Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Mitigating sedimentation

Build cofferdams when

constructing inlet structure

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Not Applicable inlet works not yet started

AWTIP Monitoring Matrix - IEE

Page 130: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Use any combination of

perimeter controls at spoil

disposal areas or stockpiles of

aggregate materials, e.g., silt

fences, sediment basins,

sandbags, earth bern/bund.

Part of project

development cost

D&B

Contractor

OSPAWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

Compliant The first water quality sampling

was conducted by CMC last

August 2017 with the following

parameters: Temperature, pH,

electric conductivity, tubidity,

color, TDS, ORP, dissolved

oxygen, BOD, coliform (Total

and Fecal) and heavy metals

(See sampling location and

results on the report).

Water quality in Basin 1 has

also been collected and

analyzed last October 2017

with the following parameters:

temperature,TSS, electric

conductivity, turbidity, color and

TDS (See sampling location

and results on the report).

Weekly monitoring of water

turbidity and other in-situ

paramters using portable water

meters started on October

2017. Testing is done weekly

by CMC Envi, Health and

Safety Officers (See sampling

location and results on the

report).

MPR

Self Monitoring

Report (SMR)

Site Inspection

Report (c/o

Jasper Cazenas

and Ricky Latunio)

Photo-

documentation

Turbidity

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

dated:

- Oct 28, 2017

- Nov 4, 2017

- Nov 11, 2017

- Nov 17, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 8, 2017

Laboratory results

from CRL -

P00075686-01

Construction Water Impact on surface water

quality due to/ from:‐ Contaminants

from materials

used and

construction

activities and

processes

- Siltation from soil

erosion, spoil

disposal area,

drill and blasting,

dewatering

excavations, etc

Minimize / control dewatering or

extraction of tunnel water by

storing and re-using pumped

out water from the tunnel.

Part of project

development cost

D&B

Contractor

OSP-AWTIP Water column.

Parameters to

characterize the

physicochemical and

biological status of the

water column to include

but not limited to:

temperature, salinity,

total suspended solids,

turbidity, dissolved

oxygen and

bacteriological

parameters.

Refer to DAO 34 and 35

for water quality

standards

In Progress Water treatment plant is already

under construction

Water quality in Basin 1 has

also been collected and

analyzed last October 2017

with the following parameters:

temperature,TSS, electric

conductivity, turbidity, color and

TDS (See sampling location

and results on the report).

Construction Water Extraction of water from

dam site (inlet) and creek

(near the outlet) to be used

as coolant during

construction

Use efficient tunnelling

technology that recycles tunnel

drainage water to minimize

extraction of water

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP If significant amount of

water is to be used, a

permit from the National

Water Resources

Board may be necessary

DAO 34 and 35 for water

quality standards

In Progress Water treatment plant is already

under construction

Water quality in Basin 1 has

also been collected and

analyzed last October 2017

with the following parameters:

temperature,TSS, electric

conductivity, turbidity, color and

TDS (See sampling location

and results on the report).

AWTIP Monitoring Matrix - IEE

Page 131: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Water Impact on groundwater

a) Deteriorating

water quality due

to:

- Silt/ sediments

- Solid waste

- Hazardous

materials

In all active work sites:

Site temporary stockpile of

excavated soils in flat areas,

away from main surface

drainage routes, limit to

maximum of 2m high

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP DAO 1994- 26A for

Philippine drinking water

quality standards

In Progress No silt fences, traps, or sand

bags have been provided yet.

Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

2 kilometers from the source of

spoil.

No groundwater monitoring has

been done yet since excavation

of tunnel had not started.

Construction Water Impact on groundwater

a) Deteriorating

water quality due

to:

- Silt/ sediments

- Solid waste

- Hazardous

materials

Provide silt fences, silt traps, or

sand bags, at stockpiles of

aggregate materials

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP DAO 1994- 26A for

Philippine drinking water

quality standards

In Progress No silt fences, traps, or sand

bags have been provided yet.

Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

2 kilometers from the source of

spoil.

No groundwater monitoring has

been done yet since excavation

of tunnel had not started.

Construction Water Impact on groundwater

a) Deteriorating

water quality due

to:

- Silt/ sediments

- Solid waste

- Hazardous

materials

Dispose residual soil/spoil as

soon as possible to the disposal

areas or as free

backfilling materials for

LGU/barangay roads

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP DAO 1994- 26A for

Philippine drinking water

quality standards

In Progress No silt fences, traps, or sand

bags have been provided yet.

Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

2 kilometers from the source of

spoil.

No groundwater monitoring has

been done yet since excavation

of tunnel had not started.

AWTIP Monitoring Matrix - IEE

Page 132: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Water Impact on groundwater

a) Deteriorating

water quality due

to:

- Silt/ sediments

- Solid waste

- Hazardous

materials

Avoid stockpiling more

aggregates than necessary

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP DAO 1994- 26A for

Philippine drinking water

quality standards

In Progress No silt fences, traps, or sand

bags have been provided yet.

Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

2 kilometers from the source of

spoil.

No groundwater monitoring has

been done yet since excavation

of tunnel had not started.

Construction Water b. lowering of water

level of wells in nearby

communities due to

tunnelling,

pumping/extracting

of tunnel drainage water

Monitor for potential

groundwater depletion in

existing wells in the vicinity.

Provide interim measures to

avoid disrupting water supply to

affected households. Investigate

for proper

corrective action.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Non-Compliant No groundwater monitoring

has been done yet since

excavation of tunnel had not

started.

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

At the project area, locate

emission sources away from

sensitive receptors, e.g.

concrete batching and rock

crushing plants at least 500m

upwind of sensitive receptors.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2005

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress No dust curtains/net has been

installed.

Dust supression has been

implemented already.

Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

AWTIP Monitoring Matrix - IEE

Page 133: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

In active work sites:

Use of blast curtains / nets to

capture dust from blasting

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2006

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Not Applicable

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

Apply dust suppression

techniques, e.g., watering with

bowsers, sheeting particularly at

Bigte area

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2007

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant No dust curtains/net has been

installed.

Dust supression has been

implemented already.

Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

AWTIP Monitoring Matrix - IEE

Page 134: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

Water dry unpaved/exposed

surfaces, stockpiles of sand and

excavated materials, at least

twice daily, or as necessary.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2008

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant No dust curtains/net has been

installed.

Dust supression has been

implemented already.

Open burning is not practiced

onsite

Speed limit has not yet

implemented

Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

Protect aggregate stockpiles

with sheeting to restrict the

movement of dust.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2009

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress

AWTIP Monitoring Matrix - IEE

Page 135: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

Use of blast curtains / nets to

capture dust from blasting.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2010

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Not Applicable

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

Limit engine idling to 5 minutes. Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2012

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress

Speed limit has not yet

implemented

Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky

Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

AWTIP Monitoring Matrix - IEE

Page 136: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

Prohibit open burning of

vegetation and other waste in

the project area

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2013

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Open burning is not practiced

onsite

Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

Construction Air Quality and Noise Deterioration of

ambient air quality

due to dust and

gas emissions

from:

a. Earthworks and

other construction

processes; tunnelling (drill

and blast)

b. Stockpiling of

aggregates and spoils, and

conveyance of

spoils to disposal areas

c. Increased transport

activities in the

construction areas and

along Ipo Road

d. Burning of vegetation

and wastes

e. Operation of

mechanical equipment

Ipo Road, main access road,

other roads in the Project area

area,

Limit speed of all construction

vehicles to max of 40kph on the

access road and max 30kph

onsite

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Maintain air quality

within national air quality

standards, or if these are

not available,

internationally accepted

air quality standards,

such as WHO Air

Quality Guidelines

Global Update, 2014

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

AWTIP Monitoring Matrix - IEE

Page 137: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Air Quality and Noise Noise and vibration in the

project area from

excavation activities;

general construction

activities; and vehicle and

equipment operations

Use only equipment that emit

least noise and vibration and are

well maintained.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Adopt national

standards for

construction sites and

residential areas if

available. Alternatively

use internationally

accepted standards

such as WHO

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant No dust curtains/net has been

installed.

Dust supression has been

implemented already.

Open burning is not practiced

onsite

Speed limit has not yet

implemented

Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky

Latunio) Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Air Quality and Noise Noise and vibration in the

project area from

excavation activities;

general construction

activities; and vehicle and

equipment operations

Use facility layout to minimize

noise propagation e.g. using

topography / existing buildings

as barriers, where possible

locate noisy activities

away from local communities.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Adopt national

standards for

construction sites and

residential areas if

available. Alternatively

use internationally

accepted standards

such as WHO

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

AWTIP Monitoring Matrix - IEE

Page 138: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Air Quality and Noise Noise and vibration in the

project area from

excavation activities;

general construction

activities; and vehicle and

equipment operations

Control noise at source, e.g. low

noise plant, muffling, acoustic

screening, switch off

campaigns.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Adopt national

standards for

construction sites and

residential areas if

available. Alternatively

use internationally

accepted standards

such as WHO

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Air Quality and Noise Noise and vibration in the

project area from

excavation activities;

general construction

activities; and vehicle and

equipment operations

Restrict use of noisy and highly

vibrating equipment from 8AM-

5PM. Necessary overtime work

should: a) not go beyond

9:00PM; b)

observe regulated noise and

vibration levels;

c) not use noisy and highly

vibrating equipment; and

d) should be coordinated with

the barangay and affected

households.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Adopt national

standards for

construction sites and

residential areas if

available. Alternatively

use internationally

accepted standards

such as WHO

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

AWTIP Monitoring Matrix - IEE

Page 139: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Air Quality and Noise Noise and vibration in the

project area from

excavation activities;

general construction

activities; and vehicle and

equipment operations

Manage the ins and outs of

hauling trucks. Spread out the

schedule of material, waste and

spoil transport in the day (off-

peak hours).

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Adopt national

standards for

construction sites and

residential areas if

available. Alternatively

use internationally

accepted standards

such as WHO

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Air Quality and Noise Noise and vibration in the

project area from

excavation activities;

general construction

activities; and vehicle and

equipment operations

Enforce the rule of no blowing of

horns.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Adopt national

standards for

construction sites and

residential areas if

available. Alternatively

use internationally

accepted standards

such as WHO

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

AWTIP Monitoring Matrix - IEE

Page 140: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Air Quality and Noise Noise and vibration in the

project area from

excavation activities;

general construction

activities; and vehicle and

equipment operations

Strictly enforce upon workers

the compliance with wearing of

ear mufflers, especially those

who are operating equipment.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Adopt national

standards for

construction sites and

residential areas if

available. Alternatively

use internationally

accepted standards

such as WHO

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Agreement with CRL

Laboratories for air quality

monitoring is now in place (24

August 2017). The air quality

sampling dates will be

scheduled once the Tunnel

Excavation starts.

Schedule of Air Quality

Monitoring:

A sound level meter was

procured by CMC to monitor

the noise level during

construction period as one of

the requirements of ADB and

DENR. Noise monitoring

started on 28 October 2017.

Sound Level

Monitoring (c/o

Jasper Cazenas

and Ricky Latunio)

Dated:

- Oct 28, 2017

-Nov 11, 2017

- Nov 24, 2017

- Dec 1, 2017

- Dec 13, 2017

Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

trucks/ equipment beyond

project footprints

Institute measures to avoid

impacting on habitats and

wildlife, such as:

1. minimize vegetation

clearance at Bigte

and especially at the intake;

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permit from DENR.

Tree cutting

permit

Compliant

Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

2. fence off vegetation to be

retained

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permitfrom DENR.

Tree cutting

permit

Compliant

Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

trucks/ equipment beyond

project footprints

3. provide environmental

training for workforce enforce

site rules and sanctions to

discourage workforce from

hunting, fishing and poaching.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permit from DENR.

Tree cutting

permit

In Progress staff orientation and training

provided

training and

orientation record

Toolbox meeting

attendances (c/o

Jasper Cazenas

and Ricky Latunio)

AWTIP Monitoring Matrix - IEE

Page 141: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

trucks/ equipment beyond

project footprints

Confine all construction activities

to previously disturbed areas, to

the extent practicable, e.g.,

workers’ quarters/camps.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permit from DENR.

Tree cutting

permit

Compliant Tree cutting

Permits issued by

Community

Environment and

Natural Resources

(DENR-CENRO)

a. Date of Issue:

July 10, 2017

Expiry Date: July

25, 2017

b. Date of Issue:

July 25, 2017

Expiry Date: July

30, 2017

c. Date of Issue:

August 16, 2017

Expiry Date:

August 31, 2017

d. Date of Issue:

August 24, 2017

Expiry Date:

August 31, 2017

e. Date of Issue:

September 11,

2017

Expiry Date:

September 18,

2017

f. Date of Issue:

September 23,

2017Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

trucks/ equipment beyond

project footprints

To avoid unnecessary clearing,

mark/delineate areas to be

cleared of vegetation, e.g. by

fencing.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permit

from DENR.

Tree cutting

permit

Compliant c. Tree cutting

Permits issued by

Community

Environment and

Natural Resources

(DENR-CENRO)

a. Date of Issue:

July 10, 2017

Expiry Date: July

25, 2017

b. Date of Issue:

July 25, 2017

Expiry Date: July

30, 2017

c. Date of Issue:

August 16, 2017

Expiry Date:

August 31, 2017

d. Date of Issue:

August 24, 2017

Expiry Date:

August 31, 2017

e. Date of Issue:

September 11,

2017

Expiry Date:

September 18,

2017

f. Date of Issue:

September 23,

2017

AWTIP Monitoring Matrix - IEE

Page 142: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

trucks/ equipment beyond

project footprints

Rehabilitate cleared areas to

their pre-project conditions,

unless otherwise agreed with

the landowner.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permit from DENR.

Tree cutting

permit

Not Applicable

Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

trucks/ equipment beyond

project footprints

Re-vegetate construction sites

using local, indigenous species.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permit from DENR.

Tree cutting

permit

Not Applicable

Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

trucks/ equipment beyond

project footprints

Re-vegetate watershed target

sites especially in areas

identified by the Watershed

Management Plan.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permit from DENR.

Tree cutting

permit

Not Applicable

Construction Biological Loss of vegetation

due to:

- Vegetation clearing and

potential trampling of

trucks/ equipment beyond

project footprints

Limit any collection of wood for

charcoal to exotic i.e. non-native

species.

Part of project

(construction) cost

D&B

Contractor

OSP-AWTIP Minimal number of trees

applied for tree cutting

permit from DENR.

Tree cutting

permit

In Progress

Construction Biological Disturbance to wildlife due

to construction noise,

vibration, dust, lighting,

presence/ movement of

people, etc. flying debris

from blasting

Implement measures to mitigate

noise,

vibration and dust

Part of project

(construction) cost

D&B

Contractor

PMO Record number of

poaching and illegal

trading of wildlife

by workers

N/A In Progress

Construction Biological Disturbance to wildlife due

to construction noise,

vibration, dust, lighting,

presence/ movement of

people, etc. flying debris

from blasting

Strategically place nets at the

tunnel portals to

prevent flying debris

Part of project

(construction) cost

D&B

Contractor

PMO Record number of

poaching and illegal

trading of wildlife

by workers

N/A In Progress

Construction Biological Disturbance to wildlife due

to construction noise,

vibration, dust, lighting,

presence/ movement of

people, etc. flying debris

from blasting

Water to minimize dust

accumulation and spreading

Part of project

(construction) cost

D&B

Contractor

PMO Record number of

poaching and illegal

trading of wildlife

by workers

N/A In Progress

Construction Socio-economic Traffic due to:

- Inadequate capacity of

Ipo Road (access road)

- Expected volume of truck

movement

Institute prior coordination with

the Barangay and Municipality

for the formulation of a traffic

management and safety plan

and for clearing of structures

encroaching into access road

ROW.

Part of project

(construction) cost

D&B

Contractor

Zero accident and

related incidents

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress

Construction Socio-economic Traffic due to:

- Inadequate capacity of

Ipo Road (access road)

- Expected volume of truck

movement

Prior to construction, clear

easement of encroaching

structures, most of them being

temporary.

Part of project

(construction) cost

D&B

Contractor

Zero accident and

related incidents

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress

Construction Socio-economic Traffic due to:

- Inadequate capacity of

Ipo Road (access road)

- Expected volume of truck

movement

Strategically post billboards

informing the public about the

expected increase in volume of

traffic in the influence area due

to Project implementation. Post

at least two weeks prior to

mobilization.

Part of project

(construction) cost

D&B

Contractor

Zero accident and

related incidents

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant

AWTIP Monitoring Matrix - IEE

Page 143: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Socio-economic Traffic due to:

- Inadequate capacity of

Ipo Road (access road)

- Expected volume of truck

movement

Coordinate with the Barangay

for assistance in traffic

management.

Part of project

(construction) cost

D&B

Contractor

Zero accident and

related incidents

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant

Construction Socio-economic Traffic due to:

- Inadequate capacity of

Ipo Road (access road)

- Expected volume of truck

movement

Strategically post traffic flagmen

along Ipo Road, equipped with

two-way radio.

Part of project

(construction) cost

D&B

Contractor

Zero accident and

related incidents

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant

Construction Socio-economic Traffic due to:

- Inadequate capacity of

Ipo Road (access road)

- Expected volume of truck

movement

Post sufficiently legible

(reflectorized) traffic safety

notice and signage at strategic

locations along the entire stretch

of the access road.

Part of project

(construction) cost

D&B

Contractor

Zero accident and

related incidents

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant

Construction Socio-economic Traffic due to:

- Inadequate capacity of

Ipo Road (access road)

- Expected volume of truck

movement

Limit speed to 40 kph along Ipo

Road, and 30 kph at

construction sites and unpaved

haulage roads.

Part of project

(construction) cost

D&B

Contractor

Zero accident and

related incidents

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant

Construction Socio-economic Potential damage of

existing roads used

as access roads due

to movement of

heavy equipment

and vehicles

Coordinate with DPWH

regarding the use of Ipo Road.

Part of project

(construction) cost

D&B

Contractor

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant

Construction Socio-economic Potential damage of

existing roads used

as access roads due

to movement of

heavy equipment

and vehicles

Restore access roads within the

MWSS compound to the pre-

construction condition or better.

Part of project

(construction) cost

D&B

Contractor

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant

Construction Socio-economic Restricted access to the

existing fish landing

sites in Sitio Consultant

(identified area as the

Contractor’s Work Area)and boat landing at Sitio

Ipo

Inform affected communities

living in Ipo Watershed on the

impact of construction works on

transportation and consult them

for the best alternative route.

Have alternative route and fish

and boat landing sites ready for

use prior to commencement of

construction activities.

Part of project (construction)

cost

D&B

Contractor

Compliant

Construction Socio-economic Community health and

safety hazards

Inform local residents of the

timing of blasting and prohibit

entry of local residents into the

construction area

Part of project (construction)

cost

D&B

Contractor

Compliant

Construction Socio-economic Community health and

safety hazards

Secure project area, including

associated facilities particularly

the storage for explosives,

from unauthorized entry

Part of project (construction)

cost

D&B

Contractor

Compliant

Construction Socio-economic Community health and

safety hazards

Implement measures to mitigate

impacts on air and water quality,

noise, and traffic

Part of project (construction)

cost

D&B

Contractor

In Progress proper PPEs provided to

workers and staff

Construction Socio-economic Workers’ health andsafety hazard

Mitigating impacts from blasting:

- Include H&S protocols in the C-

EMP on the safe procedures in

the storage, handling and use of

explosives during construction

Compliant

Construction Socio-economic Workers’ health andsafety hazard

Provide safe housing with

adequate basic services

Compliant

Construction Socio-economic Workers’ health andsafety hazard

Enforce use of protective wears

when at work

Compliant

AWTIP Monitoring Matrix - IEE

Page 144: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Construction Socio-economic Workers’ health andsafety hazard

Conduct premobilization

orientation workshop on

health and safety and

emergency response and

evacuation procedures

Compliant

Construction Socio-economic Workers’ health andsafety hazard

Handling and storage of

explosives

- Magazine storage should be

far from residential areas, roads,

transmission lines, dams and

their appurtenant works

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Site should be well-drained and

sloping, accessible by road at

least 100m from

overhead power transmission

lines

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Detonators should not be stored

together with explosives

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Maintenance should follow the

prescribed instructions for the

explosivess

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Inside of all magazines should

be kept thoroughly clean

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Cigarettes and matches should

not be taken into explosives

should be used according to

date of manufactured

magazines. Its keeper should

ensure this

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Explosive boxes should be of

wood or soft non-ferrous metal,

e.g. brass and copper.

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Magazine should be securely

locked, when not attended

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Detailed records of outgoing and

incoming stocks should be kept

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Magazines should be kept free

from bushes and vegetation

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Empty boxes, loose packing

material or cotton waste should

not be kept on the magazine

premises

Not Applicable

Construction Socio-economic Workers’ health andsafety hazard

Do not open magazines during

or in the approach of a

thunderstorm. No person should

remain in the vicinity of the

magazine during such storm

Not Applicable

Generation of spoil and

spoil disposal. More than

150,000m3 is expected to

be generated due to

tunnelling works, which is

about 190,000 m3 loose

volume.

Prepare and implement a plan

for the preparation of the spoil

disposal areas.

Part of project

development cost

MWSS

DED

Consultants

D&B

Contractor

Detailed

Engineering

Design (DED)

Scope of Work

Detailed

Engineering and

Design Plans

In Progress Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

AWTIP Monitoring Matrix - IEE

Page 145: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Generation of spoil and

spoil disposal. More than

150,000m3 is expected to

be generated due to

tunnelling works, which is

about 190,000 m3 loose

volume.

Minimise the volume of spoil to

be disposed of by re-use in

backfilling of roads, and by

offering as free filling materials

to government projects needing

backfill materials.

Part of project

development cost

MWSS

DED

Consultants

D&B

Contractor

Detailed

Engineering

Design (DED)

Scope of Work

Detailed

Engineering and

Design Plans

In Progress Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

2 kilometers from the source of

spoil. Generation of spoil and

spoil disposal. More than

150,000m3 is expected to

be generated due to

tunnelling works, which is

about 190,000 m3 loose

volume.

Disposal area must be confined

to solid ground, of low ecological

and agricultural value.

Part of project

development cost

MWSS

DED

Consultants

D&B

Contractor

Detailed

Engineering

Design (DED)

Scope of Work

Detailed

Engineering and

Design Plans

In Progress Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

2 kilometers from the source of

spoil. Generation of spoil and

spoil disposal. More than

150,000m3 is expected to

be generated due to

tunnelling works, which is

about 190,000 m3 loose

volume.

Disposal area must not occupy

drainage lines and streams, and

create an obstacle to streams or

induced flooding.

Part of project

development cost

MWSS

DED

Consultants

D&B

Contractor

Detailed

Engineering

Design (DED)

Scope of Work

Detailed

Engineering and

Design Plans

In Progress Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

2 kilometers from the source of

spoil. Generation of spoil and

spoil disposal. More than

150,000m3 is expected to

be generated due to

tunnelling works, which is

about 190,000 m3 loose

volume.

Spoil heaps must be designed

and shaped with stable side

slopes and suitable drainage.

Part of project

development cost

MWSS

DED

Consultants

D&B

Contractor

Detailed

Engineering

Design (DED)

Scope of Work

Detailed

Engineering and

Design Plans

In Progress Stockpile is at minimum

especially in Ipo construction

site (Intake).

Spoil management plan has

been drafted and already

submitted to MWSS. Spoil

disposal area, MAPOL quarry,

was identified. It has an

approximate land area of 4

hectares, located approximately

2 kilometers from the source of

spoil. Generation of spoil and

spoil disposal. More than

150,000m3 is expected to

be generated due to

tunnelling works, which is

about 190,000 m3 loose

volume.

Spoils heaps must be

compacted during the

earthworks.

Part of project

development cost

MWSS

DED

Consultants

D&B

Contractor

Detailed

Engineering

Design (DED)

Scope of Work

Detailed

Engineering and

Design Plans

In Progress

Generation of spoil and

spoil disposal. More than

150,000m3 is expected to

be generated due to

tunnelling works, which is

about 190,000 m3 loose

volume.

When completed, the spoil

heaps must be covered with the

original top soil from the site and

revegetated

Part of project

development cost

MWSS

DED

Consultants

D&B

Contractor

Detailed

Engineering

Design (DED)

Scope of Work

Detailed

Engineering and

Design Plans

In Progress

AWTIP Monitoring Matrix - IEE

Page 146: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Solid waste Implement an eco-friendly solid

waste management at work

sites and workers’ camp/s,which minimize, re-use,

segregate and promptly

dispose generated solid waste

Part of project

development cost

MWSS

D&B

contractor

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Waste onsite are segregated

into biodegredable, non-

biodegradable and residuals.

There are designated bins for

each type of waste, color coded

and labeled. Waste are

collected every Tuesday and

Thursday by Brgy Bigte. CMC

and Brgy Bigte has a service

contract for garbage and

hauling disposal from May 2017

to December 2017.

Service Contract

of Brgy Bigte and

CMC for Garbage

hauling and

disposal

Date of Issue:

May 30, 2017

Expiry Date: Dec

31, 2017

Site inspection

report Jasper

Cazenas and

Ricky Latunio)Hazardous waste Locate stationary ground

storage for hazardous waste at

least 100m away from water

bodies, raised to min 1ft above

high flood level. Or use mobile

storage but should not be

parked near water bodies

Part of project

(construction) cost

D&B

contractor

Construction

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress hazmat temporary disposal

area included in the industrial

area site map

hazmat temporary

disposal included

in the Industrial

Area site plan (c/o

Sergio and

Federico)

Hazardous waste Secure storage areas

appropriately. Storage

facilities must contain spillage

Part of project

(construction) cost

D&B

contractor

Construction

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant

Hazardous waste Dispose of waste promptly and

appropriately

Part of project

(construction) cost

D&B

contractor

Construction

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

Compliant Waste onsite are segregated

into biodegredable, non-

biodegradable and residuals.

There are designated bins for

each type of waste, color coded

and labeled. Waste are

collected every Tuesday and

Thursday by Brgy Bigte. CMC

and Brgy Bigte has a service

contract for garbage and

hauling disposal from May 2017

to December 2017.

Service Contract

of Brgy Bigte and

CMC for Garbage

hauling and

disposal

Date of Issue:

May 30, 2017

Expiry Date: Dec

31, 2017

Site inspection

report (c/o Jasper

Cazenas and

Ricky Latunio)

Hazardous waste The Contractor shall be required

to implement an appropriate

hazardous waste management

program

Part of project

(construction) cost

D&B

contractor

Construction

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress hazmat temporary disposal

area included in the industrial

area site map

hazmat temporary

disposal included

in the Industrial

Area site plan (c/o

Sergio and

Federico)

Hazardous waste Storage of oil and grease used

for the maintenance and

operation of heavy equipment

shall be properly built and

maintained to include bunded

storage for the capacity of the

containers plus 10%, and oil

Part of project

(construction) cost

D&B

contractor

Construction

D&B Contractor

Scope of Work

D&B Contractor’sC-EMP

In Progress hazmat temporary disposal

area included in the industrial

area site map

hazmat temporary

disposal included

in the Industrial

Area site plan (c/o

Sergio and

Federico)

Public safety as

related to future

development and

activities along the

ROW

MWSS must secure the ROW.

Existing above ground

infrastructure along ROW

should be limited. The public

must not be allowed to encroach

onto the ROW by constructing

any buildings or farming the

Part of maintenance cost MWSS

CPF

(represented

by 2

water

concessionair

Compliant

Changes in hydrology

along Angat river during

dry season

During the operation phase,

flows shall be monitored

downstream of Ipo dam.

Not Applicable to be monitored during the

operation phase

AWTIP Monitoring Matrix - IEE

Page 147: Angat Water Transmission Improvement Project

No Project Phase

Environmental

Aspect Potential Impact

Possible approach/mitigating

measures

Mitigation

cost/Enhnancement Performance Standard Guarantee Compliance Status Remarks

Relevant

DocumentsResponsible

Changes in hydrology

along Angat river during

dry season

As practice in the Philippines,

Ipo dam should maintain 10%

riparian flow downstream. This

flow aims to allow migration of

fish species and maintain

natural characteristics of the

river downstream of the dam.

Not Applicable to be monitored during the

operation phase

AWTIP Monitoring Matrix - IEE