annex 2 - info.gov.hk
TRANSCRIPT
Section 16 Planning Application for Proposed Temporary Transitional Housing Development for a Period of 3 Years at Lot 2160 RP (Part) in D.D. 106 and Adjoining Government Land in Kam Tin, Yuen Long, New Territories Planning Statement
Ref.: PPC-PLG-10071 Report: Version 2.0
Annex 2
Landscape Master Plan
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long
Landscape Master Plan
14th June 2021
Prepared By:
SCENIC Landscape Studio Limited
Project Title
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long
Report Title Landscape Master Plan
Revision Date Complied by: Checked by: Approved by: Description G 20210607 Benny Kwok John Charters Chris Foot Draft to Client H 20210608 Benny Kwok John Charters Chris Foot Draft to Client I 20210629 Benny Kwok John Charters Chris Foot Final to Client J 20210714 Benny Kwok John Charters Chris Foot Final to Client
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long Landscape Master Plan
20210714 HLDP048 LMP SCENIC Landscape Studio Limited 1
Table of Contents 1.0 Introduction
2.0 Existing Site Description
3.0 Description of the Proposed Scheme
4.0 Landscape Design Proposal
5.0 Landscape Design Objectives
6.0 Open Space Proposals
7.0 Green Coverage
8.0 Landscape Design Components
9.0 Landscape Design Elements
10.0 Landscape Management and Maintenance
Tables Table 9.1 Tree and Plant Species Table 10.1 Landscape Maintenance Schedule Figures Figure 4.1 Landscape Master Plan – All Levels Figure 5.1 Landscape Section A-A’ Figure 5.2 Landscape Section B-B’ Figure 6.1 Open Space – All Levels Figure 7.1 Green Coverage – All Levels Figure 9.1 Typical Section showing Planter Soil Depth and Drainage Arrangement
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long Landscape Master Plan
20210714 HLDP048 LMP SCENIC Landscape Studio Limited 1
1.0 Introduction 1.1 SCENIC Landscape Studio Limited have been commissioned on behalf of the Applicant, New
Territories Association of Societies (Community Services) Foundation, to prepare a Landscape Master Plan under Section 16 of the Town Planning Ordinance for a Proposed Temporary Transitional Housing Development (“the Proposed Development”) for a period of three years in Kam Tin, Yuen Long, New Territories (“the Application Site”). The Application Site is zoned “Comprehensive Development Area” (“CDA”) on the Approved Kam Tin South Outline Zoning Plan No. S/YL-KTS/15.
1.2 This report seeks to present the landscape design proposal. It will outline the landscape
design objectives and landscape treatment for each component of the Application Site. This report has been prepared in accordance with Buildings Department, Lands Department and Planning Department Joint Practice Note No. 3 concerning the Re-engineering of Approval Process for Land and Building Developments and adheres to the requirements of Buildings Department Practice Notes PNAP APP-152 Sustainable Building Design Guidelines for the calculation of the green coverage.
1.3 The Landscape Master Plan is presented as Figure 4.1 and sections through the landscape
as Figures 5.1 and 5.2. 2.0 Existing Site Description 2.1 The Application Site covers a total land area of 16,680 m2, adjacent to Kam Sheung Road
MTR Station in Kam Tin, Yuen Long and abuts Tung Wui Road to its southeast and Kam Wui Road to its east, while to its north and southwest are Kam Tin River and a nullah. Access to the site is currently via a gated entrance on Kam Wui Road.
2.2 The central portion of the Application Site is disturbed with existing hardstanding for the storage of construction equipment including cranes. The other portion of the site would appear to have been vacant for some time and is currently overgrown with a combination of pioneer species of shrubs and coarse grassland together with extensive new tree growth. There is also an area of maintained amenity landscape in the north east corner of the site, between Tung Wui Road and Kam Po Road.
3.0 Description of the Proposed Scheme 3.1 The temporary housing units are for families and individuals in need are provided by the
Proposed Development in the form of a low-rise development with a maximum building height of 4 storeys (not more than 15m). The Proposed Development provides about 1,020 nos. transitional housing units. The blocks containing the units are arranged in three rows on an east – west axis across the Application Site separated by internal access roads with the southernmost row having a t-shaped extension south towards Tung Wui Road. The proposed transitional housing development consists of 6 residential compounds and 3 ancillary blocks for amenity, E&M and the Sewage Treatment Plant. Vehicular access will be located in the north eastern corner of the Application Site where it meets Kam Wui Road. The Proposed Development will be landscaped including a landscape buffer along the periphery of the development. The landscape buffer will be formed by bamboo planting which will be established at an early stage during the construction phase to form an effective screen.
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long Landscape Master Plan
20210714 HLDP048 LMP SCENIC Landscape Studio Limited 2
4.0 Landscape Design Proposal 4.1 The concept underpinning the Landscape Master Plan for the Proposed Scheme, presented
as Figure 4.1 is to provide a tranquil and visually attractive setting for the proposed housing blocks. As this is a relatively temporary use of the land the proposals have sought to enhance the landscape environment whilst also being sustainable.
4.2 The landscape design proposal is described in terms of the main design objectives, followed
by a description of the key landscape components, and finally the landscape elements including the proposed hard and soft landscape, which form the palette of materials.
5.0 Landscape Design Objectives 5.1 The design objectives for the Master Landscape Plan are to:
• Create a distinctive landscape which responds to the existing context, the architectural scheme proposals and the future needs of the residents;
• Integrate the Proposed Scheme from a landscape and visual perspective with the existing and planned landscape context;
• Provide visual integration in elevated views of the Proposed Scheme, and screening and softening of the built-form in low- level views adjacent to public realm;
• Create a quality, sustainable environment for the enjoyment of the future users; and • Provide a comfortable and relaxing landscape for communal passive recreation areas.
6.0 Open Space Proposals 6.1 The design of the open space is based on the objective of providing high quality passive
recreational facilities and features with adequate open space (1 m2 per person) for the future residents in accordance with Chapters 4 and 5 of the Hong Kong Planning Standard and Guidelines (“HKPSG”).
6.2 The Proposed Scheme includes not less than 2,751 m2 of Private Open Space for the future
residents. 6.3 All of the open space within the Application Site would be constructed, managed and
maintained by the developer after the completion of Defect Liability Period and Establishment Period.
6.4 The provision of publically accessible open space for the future tenants of the development
is illustrated on Figure 6.1. 7.0 Green Coverage
7.1 The green coverage for the Application Site will not be less than 25% in accordance with the Buildings Department Practice Notes PNAP APP-152 Sustainable Building Design Guidelines. Given that this is a low-rise development all of the greening will be located within the Primary Zone (15 m above mean street level). The calculation of area is based on the uncovered areas of bamboo, shrub and lawn planting.
7.2 With a total land area of 16,680m2 the site coverage of greening shall be 4,170 m2 (25%) within the Application Site.
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long Landscape Master Plan
20210714 HLDP048 LMP SCENIC Landscape Studio Limited 3
7.3 Figure 7.1 shows the location and extent of the green coverage.
8.0 Landscape Design Components
8.1 The following description seeks to establish some general principles that are important in realising the landscape design as part of the general mitigation for the development and ensure its feasibility. Figure 4.1 shows the Landscape Master Plan for the Proposed Scheme.
8.2 The proposed landscape concept has a number of key components which include the
creation of spaces designed to reinforce the sense of community and social interaction both on a residential and communal level.
Main Entrance
8.3 The main vehicular and pedestrian entrance at the north eastern corner of the Application Site is framed to the north by bamboo planting directing views towards the internal access road. The landscape of this area is designed to establish the character of the development at the point of entry. It will form an attractive entry threshold experience with the positioning of planting being designed as a means of directing pedestrian flow. Use of a distinct paving pattern starting from the main entrance area further enhances the sense of place in terms of entry experience.
Internal Access Road
8.4 The internal access roads are likely to be relatively lightly trafficked on a day-to-day basis and as such can be considered a shared surface. The pedestrian footpath lining these access roads will be paved in decorative pavers to enhance their appearance.
Community Gathering Space
8.5 Located in the courtyard formed between Block 1 and the amenity / E&M building the design of the Community Gathering Space has sought to provide a focal point for the Proposed Scheme. This area is formed by a relatively large, multi-functional paved surface enclosed to the south and south east by a planter.
Pocket Gardens
8.6 Located at the confluence of the Kam Tin River nullahs at the western corner of the Application Site and along the southern western periphery of the site there are a series of Pocket Gardens. These areas provide shaded seating area with views along the river channel.
Landscape Buffer
8.7 The landscape buffer is designed to soften views of the Proposed Scheme from surrounding locations including the pedestrian pavements on the surrounding road network and the Kam Sheung MTR station and the open area to the east of the station. The buffer is formed using new tree planting and clumps of bamboo.
9.0 Landscape Design Elements Soft Landscape Design Approach 9.1 The basis for the proposed planting scheme would be to provide a green and comfortable
environment for the future residents. The planting design will contribute to the overall character of the Proposed Scheme.
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long Landscape Master Plan
20210714 HLDP048 LMP SCENIC Landscape Studio Limited 4
9.2 The species listed in Table 9.1 will form the basis of the planting design proposals. Table 9.1: Tree and Plant Species
Botanical Name
Chinese Name Native / Exotic
Tree Size Spacing / Planting Centres
Tree Species
Bauhinia x blakeana 洋紫荊 Native Heavy Standard 5000
Bischofia javanica 秋楓 Native Heavy Standard 5000
Cinnamomum burmannii 陰香 Native Heavy Standard 5000
Jacaranda mimosifolia 藍花楹 Exotic Heavy Standard 5000
Liquidambar formosana 楓香 Native Heavy Standard 5000
Michelia x alba 白蘭 Exotic Heavy Standard 5000
Sapium discolor 山烏桕 Native Heavy Standard 5000
Terminalia mantaly 小葉欖仁 Exotic Heavy Standard 5000
Botanical Name Stock Size Spacing / Planting
Centres Bamboo Bambusa textilis 2000-3000 Ht.
(3 culms per clump) 250
Pseudosasa japonica 1000-2000 Ht. (3 culms per clump)
250
Lawn Axonopus compressus Sown grass seeds
Note: The plant species listed above provide an indication of the future character of the proposed landscape areas however the design will be subject to further review during the detailed design stage of the project.
Soil Depth for Planting Areas 9.3 In order to ensure that the planting areas are feasible, it is proposed that an adequate
planting medium be incorporated into the design of the soft landscape areas. All trees, bamboo, lawn and green roof planting shall be provided with minimum clear soil depths of 1200mm, 600mm, 300mm and 300mm respectively, exclusive of drainage layers. The configuration of typical planters are shown on Figure 9.1.
Irrigation and Drainage
9.4 The proposed irrigation system will utilise a manual system with lockable water points at 40m centres throughout the entire site. The proposed source of water supply will be subject to final approval from the Water Supplies Department. For the most part all of the planters are at-grade and open bottomed and so no additional drainage is required. The green roof on the Amenity / E&M and Sewage Treatment Plant roof will utilise a cellular drainage system such as “Mira-drain” or an approved equivalent.
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long Landscape Master Plan
20210714 HLDP048 LMP SCENIC Landscape Studio Limited 5
Feature Paving 9.5 The paving will be an important element of the landscape design both in terms of its
aesthetic appearance and in producing a hardwearing landscape for usage by the future users. Non-slip paving materials will be utilised throughout the site and the proposed finishes and materials are summarized below:
• External pedestrian pathways and open spaces: Subtle shades of natural granite and
concrete pavers designed to create visual continuity whilst also creating a distinct identity at the threshold of the development.
• Outdoor decks and open spaces; Combination of natural granite and concrete block
paving to create attractive garden scale paving features.
9.6 Wherever possible all landscape areas will cater for multiple use needs including people with impaired ability and access for the disabled in accordance with Building Department’s Design Manual on ‘Barrier Free Access (DMBFA), 2008’.
9.7 The landscape design considers the requirements of Chapter 6 of the DMBFA for the use of
elderly residents whereby the landscape has been designed without steps, thresholds, small ramps or kerbs, wherever possible. Where changes in level are unavoidable handrails or grab bars will be provided. Steps and staircases should be designed with wider treads and lower risers. Floor surfaces will comply with Division 4. Slip-resistant floor finishes and avoids the use of shiny and reflective floors such as marble, glazed tiles and the like. Open jointed pavers or aeration paver blocks with uneven or very rough surface will be avoided at external open spaces.
Lighting
9.8 The lighting design concept for the landscaped areas should be designed to contribute to the quality of the development in nocturnal views providing an aesthetically pleasing atmosphere through the highlighting of landscape elements. All of the landscape areas will be provided with sufficient illumination to meet the required lighting safety standards, particularly for the entrance areas and pedestrian access paths. The lighting concept will include three types of lighting which are as follows:
• Amenity lighting highlighting planting through the use of spotlights and up-lighting
which are of suitable direction and intensity so that they enhance the night-time landscape ambience without affecting external areas;
• Area lighting involving the use of low-level lighting sources such as lighting bollards
and recessed wall lights for sitting areas and main landscape spaces designed to avoid glare / light spillage to adjacent properties; and
• General safety lighting with the minimum lux level which will last between midnight
and early morning.
Site Furniture 9.9 The landscape design would include the provision of site furniture including seating, which
in addition to its functional attributes would also contribute to the perceived quality of the landscape.
Safety Requirements 9.10 All outdoor facilities will be designed, constructed and operated in full compliance with
relevant safety standards and guidelines.
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long Landscape Master Plan
20210714 HLDP048 LMP SCENIC Landscape Studio Limited 6
10.0 Landscape Management and Maintenance 10.1 Upon completion of the construction works, a 12-month Defects Liability Period (DLP) will
be implemented applying to the hard landscape whereby the specialist contractor will be responsible for the maintenance during this first year. Similarly the softworks contractor will be responsible for a 12-month Establishment Period (EP) for the planting after practical completion. This allows a period of time for proper establishment of the plants and the replacement of any losses.
10.2 At the end of the 12-month DLP / EP, the property owner will be responsible for
arrangements to take care of all landscape areas within the development. This includes general tree care and proper tree maintenance for the retained trees in accordance with relevant guidelines promulgated by DEVB.
10.3 Table 10.1 (overleaf) provides the maintenance schedule for the soft landscape.
Tree Risk Assessment
10.4 A tree risk assessment for the target area retained trees shall be conducted annually in accordance with the ‘Handbook on Tree Management’ promulgated by the GLTM Section of DEVB.
Prop
osed
Tem
pora
ry T
rans
ition
al H
ousi
ng
Dev
elop
men
t at K
am T
in, Y
uen
Long
Lan
dsca
pe M
aste
r Pla
n
2021
0714
HLD
P048
LM
P SC
ENIC
Lan
dsca
pe S
tudi
o Li
mite
d
11
Tabl
e 10
.1
Land
scap
e M
aint
enan
ce S
ched
ule
Item
M
aint
enan
ce O
pera
tion
Fr
eque
ncy
J F
M
A
M
J J
A
S O
N
D
1.1
Wat
erin
g 28
0 da
ys
1.2
Litt
er C
olle
ctio
n D
aily
1.3
Wee
d C
ontr
ol
16/ y
ear
1.4
Prun
ing
of tr
ees
and
shru
bs
As
requ
ired
1.5
Fert
ilise
r Ap
plic
atio
n Tw
ice/
year
1.6
Top-
up M
ulch
Tw
ice/
year
1.7
Pest
Con
trol
A
s re
quire
d
1.8
Repl
acem
ent p
lant
ing
As
requ
ired
1.9
Chec
king
aft
er e
xcep
tiona
l wea
ther
A
s re
quire
d
1.10
G
rass
Cut
ting
14 ti
mes
1.
11
Perio
dic
Insp
ectio
n by
Use
r and
H
ortic
ultu
ral M
aint
enan
ce C
ontr
acto
r is
reco
mm
ende
d
Four
/yea
r
1
1
1
1
1.12
Tr
ee R
isk
Ass
essm
ent f
or re
tain
ed tr
ees
in
acc
orda
nce
with
DEV
B m
etho
dolo
gy
at a
n ap
prop
riate
tim
e of
the
year
Onc
e/ye
ar
1
Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long Landscape Master Plan
20210714 HLDP048 LMP SCENIC Landscape Studio Limited
Landscape Figures
SCALE
CHECKED
FIGURE NO.
DATE
DRAWN
REV
JBC
A.S.
CL
FIGURE TITLE Jun 2021Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long
DFigure 4.1
LEGEND
Proposed Architectural Scheme
Existing Tree
Proposed Buffer Tree /Bamboo Planting
Proposed Levels
Existing Levels
Proposed Lawn
Proposed Green Roof
Proposed Paving
Proposed Seating
Proposed Bicycle Parking Area
xx.xx
xx.xx
Application Site Boundary
North
Landscape Master Plan - All Levels
0 10 20 30 40 50M
Block 4 Block 5
Block 2
Block 1
Amenity & E/M
Sewage Treatment Plant
Block 6
Block 3
LANDSCAPE COMPONENTSMain Entrance Internal Circulation RoadCommunity Gathering SpacePocket GardenBuffer Tree PlantingBicycle Parking Area
1 2 3 4 5 6
Note: It is assumed that the Government will provide landscaping / tree plantation as much as possible as shown in this layout, if needed during implementa-tion. However, the proposed compensatory trees might be removed at the end of temporary use and the replaced by the future landscape master plan.
It should be noted that the majority of the existing trees are the invasive exotic species (Leucaena leuco-cephala) which do not contribute to the landscape quality of the site and that the priority of this proposal is to provide housing stock.
9.80 20.10
12.00
20.10
20.10
20.10
11.30
17.80
20.10
5.807.44 7.605.80
5.80
5.80
20.10 20.10
21.50
+8.30
+7.70
+6.30
+7.10
4
2
4
4
1
3
2
4
6
Telephone: 2 4 6 8 2422 Fa c s i m i l e : 3016 2422Website: [email protected]
S C E N I C L a n d s c a p e S t u d i o L i m i t e d L A N D S C A P E A R C H I T E C T U R E , L A N D S C A P E P L A N N I N G & A S S E S S M E N T
12 /F So Hong Commercial Bui lding, 41- 47
Jer vois Street , Sheung Wan, Hong Kong
SCALE
CHECKED
FIGURE NO.
DATE
DRAWN
REV
JBC
A.S.
CL
FIGURE TITLE Jun 2021Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long
BFigure 5.1Landscape Section A-A’
5.80mPD
20.10mPD 20.10mPD
7.40mPD
Application Site Boundary Application Site Boundary
Ramp atRun-in/out
Nullah Kam Wui Road
Block 3Block 1
Landscape Area EVA
0 5 10 15m
New tree and bamboo planting as landscape buffer
New tree and bamboo planting as landscape buffer
Proposed Buffer Tree / Bamboo Planting
LEGEND
Section Line
Application Site Boundary
Typical Levels xx.xx
Proposed Vehicular Access
Proposed Lawn Areas
North
Section A-A’
A
A’
Telephone: 2 4 6 8 2422 Fa c s i m i l e : 3016 2422Website: [email protected]
S C E N I C L a n d s c a p e S t u d i o L i m i t e d L A N D S C A P E A R C H I T E C T U R E , L A N D S C A P E P L A N N I N G & A S S E S S M E N T
12 /F So Hong Commercial Bui lding, 41- 47
Jer vois Street , Sheung Wan, Hong Kong
SCALE
CHECKED
FIGURE NO.
DATE
DRAWN
REV
JBC
A.S.
CL
FIGURE TITLE Jun 2021Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long
Figure 5.2Landscape Section B-B’C
5.80mPD5.80mPD
20.10mPD 20.10mPD 20.10mPD17.80mPD
21.50mPD
8.5mPD5.80mPD
Application Site Boundary Application Site Boundary
Proposed Extentive Roof Green
Nullah Tung Wui Road
Block 5 Block 2 Block 1
Amenity & E/MBuilding
EVAEVAMulti-purpose
open
0 5 10 15m
Landscape buffer formed by a combination of retained trees and bamboo
New tree and bamboo planting as landscape
buffer
Proposed Buffer Tree / Bamboo Planting
LEGEND
Section Line
Application Site Boundary
Typical Levels xx.xx
North
B’
B
SectionB-B’
Proposed Vehicular Access
Proposed Lawn Areas
Telephone: 2 4 6 8 2422 Fa c s i m i l e : 3016 2422Website: [email protected]
S C E N I C L a n d s c a p e S t u d i o L i m i t e d L A N D S C A P E A R C H I T E C T U R E , L A N D S C A P E P L A N N I N G & A S S E S S M E N T
12 /F So Hong Commercial Bui lding, 41- 47
Jer vois Street , Sheung Wan, Hong Kong
SCALE
CHECKED
FIGURE NO.
DATE
DRAWN
REV
JBC
A.S.
CL
FIGURE TITLE Jun 2021Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long
CFigure 6.1
Private Open Space(Passive Use)
Application Site Boundary
LEGEND
Open Space - All Levels
North
0 10 20 30 40 50M
G/F Landscape Area
OS01 Open Space (Passive Use) 2,751 m2
Private Open Space
OS01 OS01
OS01N
orth
Telephone: 2 4 6 8 2422 Fa c s i m i l e : 3016 2422Website: [email protected]
S C E N I C L a n d s c a p e S t u d i o L i m i t e d L A N D S C A P E A R C H I T E C T U R E , L A N D S C A P E P L A N N I N G & A S S E S S M E N T
12 /F So Hong Commercial Bui lding, 41- 47
Jer vois Street , Sheung Wan, Hong Kong
SCALE
CHECKED
FIGURE NO.
DATE
DRAWN
REV
JBC
A.S.
CL
FIGURE TITLE Jun 2021Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long
CFigure 7.1
Uncovered Greening at G/F Landscape area
UncoveredExtensive Roof Green
LEGEND
Application Site Boundary
Green Coverage - All Levels
North
Green Coverage
Greenery Types without CAPG/F Landscape Area
GA01 Soft Landscape (tree and shrub planting)
2,770 m2 Uncovered Primary Zone
Roof Green
GA02 Soft Landscape (Roof Green)
1,400 m2 Uncovered Non-Primary
Zone
Total Green Coverage: 4,170 m2 (25%)
GA01
GA01
GA02
GA02
GA01
GA01
GA01GA01
GA01
GA01
GA01
GA01
GA01
0 10 20 30 40 50M
North
Telephone: 2 4 6 8 2422 Fa c s i m i l e : 3016 2422Website: [email protected]
S C E N I C L a n d s c a p e S t u d i o L i m i t e d L A N D S C A P E A R C H I T E C T U R E , L A N D S C A P E P L A N N I N G & A S S E S S M E N T
12 /F So Hong Commercial Bui lding, 41- 47
Jer vois Street , Sheung Wan, Hong Kong
SCALE
CHECKED
FIGURE NO.
DATE
DRAWN
REV
JBC
A.S.
CL
FIGURE TITLE Jun 2021Proposed Temporary Transitional Housing Development at Kam Tin, Yuen Long
CFigure 9.1Typical Section showing Planter Soil Depth and Drainage Arrangement
B. Section showing the proposed grass planting (at-grade) and roof green (on-structure).
300mm minimum soil depth for grass/lawn planting
300mm minimum soil depth for grass / groundcover planting
300mm minimum soil depth for grass planting
A. Section showing proposed tree, bamboo and grass / lawn planting (at-grade).
1200mm minimum soil depth for tree and bamboo planting
Planter Drainage Outlet to Engineering’s Details
LEGEND
Section Line
Typical Levels xx.xx
Section Line
Typical Levels xx.xx
Soil Mix
Gravel Covered with Geotextile at Drain Outlet
Drainage Cell / Screed Laid to Falls
Note:
- All soil depths stated exclude drainage layer.- With exception of green roof all planters at-grade with open bottoms and so no drainage system required
Diagram showing the drainage outlet detail for green roof
soil depth excluding drainage layers (min. 300mm for low shrubs and groundcover for roof greening
North
B’
B
A
A’
Telephone: 2 4 6 8 2422 Fa c s i m i l e : 3016 2422Website: [email protected]
S C E N I C L a n d s c a p e S t u d i o L i m i t e d L A N D S C A P E A R C H I T E C T U R E , L A N D S C A P E P L A N N I N G & A S S E S S M E N T
12 /F So Hong Commercial Bui lding, 41- 47
Jer vois Street , Sheung Wan, Hong Kong