anti termite

8
KOCHI-KOTTANAD-BANGALORE-MANGALORE PIPELINE PROJECT (PHASE-I) JOB PROCEDURE FOR ANTI TERMITE PROCEDURE NO: JPL/KKBMPL/CIVIL/03 REV 01 CLIENT : GAIL (INDIA) LIMITED CONSULTANT : MECON LIMITED CONTRACTOR : JAIHIND PROJECTS LIMITED JPL MECON MECON /GAIL PREPARED BY CHECKED BY REVIEWED BY APPROVED BY ANTI TERMITE DOCUMENT NO. REV Page 1 of 8 JPL/KKBMPL/CIVIL/03 01

Upload: sachein-anand

Post on 04-Dec-2015

2 views

Category:

Documents


0 download

DESCRIPTION

Anti Termite

TRANSCRIPT

Page 1: Anti Termite

KOCHI-KOTTANAD-BANGALORE-MANGALORE PIPELINE PROJECT(PHASE-I)

JOB PROCEDURE FOR

ANTI TERMITE

PROCEDURE NO: JPL/KKBMPL/CIVIL/03 REV 01

CLIENT : GAIL (INDIA) LIMITED

CONSULTANT : MECON LIMITED

CONTRACTOR : JAIHIND PROJECTS LIMITED

JPL MECON MECON /GAIL

PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

SIGNATURE

NAME

DATE

ANTI TERMITEDOCUMENT NO. REV

Page 1 of 6 JPL/KKBMPL/CIVIL/03 01

Page 2: Anti Termite

CONTENT

1.0 PURPOSE 3

2.0 SCOPE 3

3.0 REFERENCES 3

4.0 MACHINERIES AND EQUIPMENTS 3

5.0 RESPONSIBILITIES 3

6.0 PROCEDURE 4

7.0 HEALTH, SAFETY & ENVIRONMENT 5

8.0 QUALITY ASSURANCE & QUALITY CONTROL 5

9.0 APPENDIX / FORMAT 5

ANTI TERMITEDOCUMENT NO. REV

Page 2 of 6 JPL/KKBMPL/CIVIL/03 01

Page 3: Anti Termite

1.0 PURPOSE:

The purpose of this procedure is to prepare the execution sequence and work activity required for applying Anti Termite Treatment to Building Structures to be constructed in all Stations of KKBMPL Pipeline Project.

2.0 SCOPE:

This procedure establishes the material and method of accomplishing pre – constructional anti-termite treatment of soil for protection of buildings against attack by subterranean termites with the usages of chemical emulsions in accordance with the procedure laid down.

3.0 REFERENCES:

Following documents in totality or in part shall form the reference documents: Tender Specification-MEC/S/05/11/01 CLAUSE NO- 3.0 IS: 6313 Part-2.

4.0 MACHINERIES AND EQUIPMENTS

Spray gun with Container equipped with pumping facility

Chemicals Chlorophyrophos 1% or Lindance 1%.

Measuring Jars

Small containers (Bucket, tumblers etc.).

5.0 RESPONSIBILITIES

Construction/civil engineer Shall report to the Construction Manager and shall be responsible for :

Preparation of work schedule addressing specific issues and characteristics of each spread.

Overall control and safety management and for the implementation of procedure and supervise the activity.

Generation of reports during the activity.

Explaining all other persons involved in erection and installation of the operations to be done during the activity.

ANTI TERMITEDOCUMENT NO. REV

Page 3 of 6 JPL/KKBMPL/CIVIL/03 01

Page 4: Anti Termite

6.0 PROCEDUREThe treatment shall be carried out by an approved agency specialized in the field.

6.1 PREPARATION

Prior to start of chemical treatment, area(s), shall be made free from logs, stumps, timber off cuts, leveling pegs, roots of plants/trees etc. Soil treatment shall start when foundation trenches/pits are ready to take concrete masonry in foundations and plinth area ready for laying the subgrade. Treatment shall not be carried out when it is raining or the subsoil water level is at the same or higher than the level of treatment. In the event of water-logging of foundations, the water shall be pumped out and the chemical emulsion applied when the soil is absorbent. Treatment of the excavated pits/trenches and backfill for Foundations

(a) The bottom surface and the lower 300 mm side surfaces of the excavated pits/trenches for foundations of masonry works and RCC plinth beams supporting such masonry works, shall be treated with specified chemical emulsion @ 5 litres/m2 of the surface area. However, no such treatment shall be required in case of pits/trenches made for RCC foundations supporting RCC walls and/or columns.

(b) On completion of construction of masonry foundations, the backfill in immediate contact with the substructure shall be treated in layers of 300 mm with emulsion @ 7.5 litres/m2 of the vertical surface of the substructure (i.e. 7.5 x 0.300 = 2.25 liters/meter of perimeter) for each side. The treatment shall be given after ramming of each layer of soil, by roding the earth at 150 mm centers close to the wall surface and working the rod backward and forward (parallel to the wall surface) and then spraying the specified dosage of emulsion. The emulsion shall be directed towards the masonry surfaces so that the soil in contact with these surfaces is well treated with the chemical. After the treatment, the soil shall be tamped back into place. This shall be done for full depth of the fill.

(c) For RCC walls and columns, the treatment as specified in (b) shall start from a depth 500 mm below the finished ground level and shall be done up to the FGL.

6.2 TREATMENT OF PLINTH/BASEMENT AND APRON

The top surface of the consolidated earth below the non-suspended floor slabs and the peripheral aprons of width up to 750 mm, the bottom surface and side surfaces of the excavated pits for the basements shall be treated with chemical emulsion @ 5 litres/m2 of the surface area. Holes 50 to 75 mm deep at 150 mm centers, both ways, shall be made on the surface with 12mm diameter mild steel rod and then emulsion shall be sprayed uniformly over the area. At

ANTI TERMITEDOCUMENT NO. REV

Page 4 of 6 JPL/KKBMPL/CIVIL/03 01

Page 5: Anti Termite

expansion joint locations, anti-termite treatment shall be supplemented by treating through the expansion joint @ 2.0 liters per linear meter of joint after the subgrade has been laid. Treatment of Junctions of plinth filling and wall/column faces shall be done after making a small channel 30 mm x 30 mm, by making rod holes 150 mm apart (up to the ground level) in the channel and then by moving the rod backward and forward @7.5 litres/m2 of the vertical wall/column surface so as to soak the soil right to the bottom. The soil shall be tamped back into place after the treatment.

TREATMENT OF SOIL ALONG EXTERNAL PERIMETER OF BUILDING

After the building is complete, the earth along the external perimeter shall be rodded at intervals of 150 mm and to depth of 300 mm. The rod shall be moved backward and forward parallel to the wall to break up the earth and chemical emulsion poured along the wall @ 7.5 litres/m2 of vertical surface (i.e. 7.5 x 0.300 = 2.25 litres/metre of perimeter). After the treatment, the earth shall be tamped back into place.

7.0 HEALTH, SAFETY & ENVIRONMENT

Anti termite treatment shall be carried out under experienced & trained supervisor.

Only trained & experienced person shall be deployed in such activity. MSDS (Material Safety Data Sheet) shall be displayed at working site. Use of appropriate PPE’s like, eye protection, safety shoe, safety helmet,

respiratory protection (Nose Mask) etc. is mandatory during anti termite treatment.

First Aid kit with sufficient medicine easily available at site. Evacuation and cordoning the work location shall be done before starting the

activity and minimum person shall be deployed in anti termite treatment work.

8.0 QUALITY ASSURANCE & QUALITY CONTROL

QA/QC shall be as per Quality Plan and corresponding Inspection & Test Plan

9.0 APPENDIX / FORMAT

INSPECTION TEST PLAN FOR ANTI TERMITE TREATRMENT----------------JPL/KKBMPL/CIVIL/ITP/03

INSPECTION REPORT FOR ANTI TERMITE TREATRMENT --------------------JPL/KKBMPL/CIVIL/IR/03

ANTI TERMITEDOCUMENT NO. REV

Page 5 of 6 JPL/KKBMPL/CIVIL/03 01

Page 6: Anti Termite

NOTE: In case of any conflict between the requirements of this procedure and that of above referred specification then requirements of MECON specification shall govern.

ANTI TERMITEDOCUMENT NO. REV

Page 6 of 6 JPL/KKBMPL/CIVIL/03 01