appendix 33

3
   APPENDIX 33 Rev. 01 December 2012 Page 1of 2 Excerpt from Trakhees / Ports. Customs & Free Zone Corporation - Fire Protection, Fire Prevention & Fire/Emergency Control Regulations (2012 Edition) Requirements For Design Of Water Tank Fire Water Pump Room 1.0 Fire Water Tank ( FWT ) 1.1 The Water Tank shall be designed in accordance with NFPA  22 in all respects. 1.2 The FWT shall be constructed in two equal compartments with isolation facilities to allow perio  dic cleaning and maintenance works of each compartment. 1.3 FWT shall be constructed of steel or concrete 1.4 FWT pre-engineered/prefabricated is also accepted provided it is listed (FM or LPCB) for service application. 1.5 FWT located within 6.1m from the building shall be protected externally with either fire proof material or protected with open sprinklers. 1.6 A minimum of two automatic fill valves is required for the water tank. Each fill valve, when operating independently, is required to refill the system at a rate equal to or greater than the fire protection demand rate. 1.7 Underground water tank & Fire Pump installation where permitted shall be installed i n accordance with Appendix  33A 2.0 Fire Water Pump Room 2.1 The Pump room shall be designed in accordance with NFPA- 20. Access to fire pump rooms is required directly through an exterior door or through a 2-hr rated enclosed passageway connected to an exterior door or an enclosed door or an enclosed stairway. The Pump room shall be provided with proper ventilation system and allow sufficient intake air for the diesel engine ensuring satisfactory performance. 2.2 The Fuel Oil Tank (FOT) shall be fitted with a Level Indicator and a Level Switch. 2.3 The f ollowing signa ls shall be annunciated on the FACP and BMS Panel : a) Low Level Alarm in FWT for FWP. b) Low Level Alarm in FWT for domestic wate r pumps (if installed). c) Low Level Alarm in FOT. d) FWP ‘ fails to start ‘ (all pumps ) e) Normal Source Power Failure 2.4 All Flow and instrument parameters shall be specified. Pump Start Up / Operati onal logic notes shall be submitted. 2.5 Pump Room Equipment layout  Plan & Section ( 1: 20 Scale ) , Water Tank with water levels and suction pipe arrangement shall be submitted. 2.6 Fire Water Pump sets Fire P rotection The Pump Room shall be protected by sprinkler system in accordance with NFPA-20 and designed as per NFPA  13. 2.7 Generator Set Fire Protection The Generator Set Room shall be protected by sprinklers designed in accordance with NFPA  13.

Upload: kadiri-olanrewaju

Post on 07-Oct-2015

215 views

Category:

Documents


0 download

DESCRIPTION

standards

TRANSCRIPT

  • APPENDIX 33

    Rev. 01 December 2012 Page 1of 2 Excerpt from Trakhees / Ports. Customs & Free Zone Corporation - Fire Protection, Fire Prevention & Fire/Emergency Control Regulations (2012 Edition)

    Requirements For Design Of Water Tank Fire Water Pump Room

    1.0 Fire Water Tank ( FWT )

    1.1 The Water Tank shall be designed in accordance with NFPA 22 in all respects.

    1.2 The FWT shall be constructed in two equal compartments with isolation facilities to allow periodic cleaning and maintenance works of each compartment.

    1.3 FWT shall be constructed of steel or concrete

    1.4 FWT pre-engineered/prefabricated is also accepted provided it is listed (FM or LPCB) for service application.

    1.5 FWT located within 6.1m from the building shall be protected externally with either fire proof material or protected with open sprinklers.

    1.6 A minimum of two automatic fill valves is required for the water tank. Each fill valve, when operating independently, is required to refill the system at a rate equal to or greater than the fire protection demand rate.

    1.7 Underground water tank & Fire Pump installation where permitted shall be installed in accordance with Appendix 33A

    2.0 Fire Water Pump Room

    2.1 The Pump room shall be designed in accordance with NFPA- 20.

    Access to fire pump rooms is required directly through an exterior door or through a 2-hr rated enclosed passageway connected to an exterior door or an enclosed door or an enclosed stairway.

    The Pump room shall be provided with proper ventilation system and allow sufficient intake air for the diesel engine ensuring satisfactory performance.

    2.2 The Fuel Oil Tank (FOT) shall be fitted with a Level Indicator and a Level Switch.

    2.3 The following signals shall be annunciated on the FACP and BMS Panel : a) Low Level Alarm in FWT for FWP. b) Low Level Alarm in FWT for domestic water pumps (if installed). c) Low Level Alarm in FOT. d) FWP fails to start (all pumps )

    e) Normal Source Power Failure

    2.4 All Flow and instrument parameters shall be specified. Pump Start Up / Operational logic notes shall be submitted.

    2.5 Pump Room Equipment layout Plan & Section ( 1: 20 Scale ) , Water Tank with water levels and suction pipe arrangement shall be submitted.

    2.6 Fire Water Pump sets Fire Protection

    The Pump Room shall be protected by sprinkler system in accordance with NFPA-20 and designed as per NFPA 13.

    2.7 Generator Set Fire Protection

    The Generator Set Room shall be protected by sprinklers designed in accordance with NFPA 13.

  • APPENDIX 33

    Rev. 01 December 2012 Page 2of 2 Excerpt from Trakhees / Ports. Customs & Free Zone Corporation - Fire Protection, Fire Prevention & Fire/Emergency Control Regulations (2012 Edition)

    3.0 Equivalencies

    Equivalencies to any established prescriptive criteria of NFPA and its companion codes, standards and publications may be approved by the EHS-Fire Department / AHJ, if the alternative fire protection engineering design provides an equivalent level of fire protection and life safety. Written requests for approval shall include justification demonstrating equivalencies on the basis of pertinent data. Approved equivalencies and alternatives shall only apply to the specific building, facility or structure involved in extraordinary case where no technical alternatives exist; and shall not constitute blanket approval for similar cases.

    NB (a) 1 to 3 as above (i) provide only an outline of the specific requirement(s) of EHS-Fire Department for the

    guidance of qualified & approved consultants/users & (ii) serves as ready reckoner for maintaining consistency in approach. However, the consultants/users are cautioned and advised that they meet all requirements/recommendations as specified / cited in drawing review report(s) issued by EHS-Fire Department.

    (b) Consultant shall submit design drawings meeting the above requirements and obtain approval of EHS Fire Department, before procurement of materials.

    (c) Refer to Fire Department and relevant codes & standards for additional information/details.