appendix 7.03 high pressure (hp) … report sha tin cavern sewage treatment works appendix 7.03...

24
EIA Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION PIPELINES 1 INTRODUCTION ................................................................................................................. 2 1.1 Background.......................................................................................................................... 2 1.2 Hazard to Life Assessment Objectives and Risk Criteria .................................................... 3 1.3 Study Approach ................................................................................................................... 6 2 DESCRIPTION OF SURROUNDINGS ............................................................................... 7 2.1 Surrounding Population ....................................................................................................... 7 2.2 Meteorology ....................................................................................................................... 12 3 HAZARD IDENTIFICATION AND ANALYSIS ................................................................. 14 3.1 Introduction ........................................................................................................................ 14 3.2 Pipeline Design Parameters .............................................................................................. 14 3.3 Behaviour of Town Gas Releases ..................................................................................... 14 3.4 Domino Effects .................................................................................................................. 15 3.5 Hazard Analysis for the HP Gas Pipeline .......................................................................... 15 3.6 Frequency Estimation ........................................................................................................ 17 4 FREQUENCY ANALYSIS ................................................................................................. 20 4.1 Introduction ........................................................................................................................ 20 4.2 Frequency of Occurrence .................................................................................................. 20 5 CONSEQUENCES AND IMPACT ANALYSIS ................................................................. 21 5.1 Introduction ........................................................................................................................ 21 5.2 Source Term ...................................................................................................................... 21 5.3 Scenarios Following Gas Release .................................................................................... 21 5.4 Effect Modelling of the HP Gas Pipeline ........................................................................... 22 5.5 Ignition Probability ............................................................................................................. 24 6 RISK EVALUATION .......................................................................................................... 26 6.1 Introduction ........................................................................................................................ 26 6.2 Individual Risk.................................................................................................................... 26 6.3 Societal Risk ...................................................................................................................... 27 7 CONCLUSIONS AND RECOMMENDATIONS ................................................................ 33 8 REFERENCES .................................................................................................................. 34 List of Annex Annex 1 Population Data Annex 2 Aircraft Crash Frequency Calculation Annex 3 Fault Tree Analysis Annex 4 Event Tree Analysis EIA Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-2 August 2016 1.1.1.1 The High Pressure (HP) underground town gas transmission pipeline to Sha Tin originates at the Tai Po Gas Production Plant, runs subsea along Tolo Harbour and Shing Mun River to the offtake and pigging station in City One, Sha Tin. The HP underground town gas transmission pipel Highway and Sai Sha Road, and arrives the downstream Sai O pigging station. According to the information provided by the Hong Kong and China Gas Company (HKCG), the length of HP underground town gas transmission pipeline between the 2 pigging stations is approximately 7.8km, of which 1.9km lies in the vicinity of the proposed transport route of explosives between A Kung Kok Shan Road and the Project Site. Figure 1.1 shows the location plan of the study. 1.1.1.2 Along this section, there is also a pair of 750mm diameter twin HP submarine town gas transmission pipelines running along Shing Mun River, which is more than 150m away from the proposed transport route of explosives as well as the Project Site. The Project also proposed to install 2,000mm diameter emergency outfall by pipe jacking method across Shing Mun River Channel, HKCG has been consulted on the potential impact to the gas pipelines during construction and operation of the sewerage pipes. Advice from HKCG including to provide a minimum vertical separation of 10m between the gas pipelines and the sewerage pipes, and to control the vibration acting on the gas pipelines to less than 25mm/sec peak particle velocity and the peak magnitude over the gas pipelines to less than 0.2mm will be incorporated to the design of the sewerage pipes during detailed design stage. Taking into consideration the separation distance and the design of the sewerage pipes, the HP submarine town gas transmission pipelines will not be further considered in this study. Figure 1.2 shows the alignment of the proposed emergency outfall. Figure 1.1 Location Plan of the Study

Upload: dangthuy

Post on 11-Jul-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-1 August 2016

APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSIONPIPELINES

1 INTRODUCTION ................................................................................................................. 2

1.1 Background.......................................................................................................................... 21.2 Hazard to Life Assessment Objectives and Risk Criteria .................................................... 31.3 Study Approach ................................................................................................................... 6

2 DESCRIPTION OF SURROUNDINGS ............................................................................... 7

2.1 Surrounding Population ....................................................................................................... 72.2 Meteorology ....................................................................................................................... 12

3 HAZARD IDENTIFICATION AND ANALYSIS ................................................................. 14

3.1 Introduction ........................................................................................................................ 143.2 Pipeline Design Parameters .............................................................................................. 143.3 Behaviour of Town Gas Releases ..................................................................................... 143.4 Domino Effects .................................................................................................................. 153.5 Hazard Analysis for the HP Gas Pipeline .......................................................................... 153.6 Frequency Estimation ........................................................................................................ 17

4 FREQUENCY ANALYSIS ................................................................................................. 20

4.1 Introduction ........................................................................................................................ 204.2 Frequency of Occurrence .................................................................................................. 20

5 CONSEQUENCES AND IMPACT ANALYSIS ................................................................. 21

5.1 Introduction ........................................................................................................................ 215.2 Source Term ...................................................................................................................... 215.3 Scenarios Following Gas Release .................................................................................... 215.4 Effect Modelling of the HP Gas Pipeline ........................................................................... 225.5 Ignition Probability ............................................................................................................. 24

6 RISK EVALUATION .......................................................................................................... 26

6.1 Introduction ........................................................................................................................ 266.2 Individual Risk.................................................................................................................... 266.3 Societal Risk ...................................................................................................................... 27

7 CONCLUSIONS AND RECOMMENDATIONS ................................................................ 33

8 REFERENCES .................................................................................................................. 34

List of Annex

Annex 1 Population Data

Annex 2 Aircraft Crash Frequency Calculation

Annex 3 Fault Tree Analysis

Annex 4 Event Tree Analysis

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-2 August 2016

1.1.1.1 The High Pressure (HP) underground town gas transmission pipeline to Sha Tinoriginates at the Tai Po Gas Production Plant, runs subsea along Tolo Harbour and ShingMun River to the offtake and pigging station in City One, Sha Tin. The HP undergroundtown gas transmission pipelHighway and Sai Sha Road, and arrives the downstream Sai O pigging station. Accordingto the information provided by the Hong Kong and China Gas Company (HKCG), thelength of HP underground town gas transmission pipeline between the 2 pigging stationsis approximately 7.8km, of which 1.9km lies in the vicinity of the proposed transport routeof explosives between A Kung Kok Shan Road and the Project Site. Figure 1.1 showsthe location plan of the study.

1.1.1.2 Along this section, there is also a pair of 750mm diameter twin HP submarine town gastransmission pipelines running along Shing Mun River, which is more than 150m awayfrom the proposed transport route of explosives as well as the Project Site. The Projectalso proposed to install 2,000mm diameter emergency outfall by pipe jacking methodacross Shing Mun River Channel, HKCG has been consulted on the potential impact tothe gas pipelines during construction and operation of the sewerage pipes. Advice fromHKCG including to provide a minimum vertical separation of 10m between the gaspipelines and the sewerage pipes, and to control the vibration acting on the gas pipelinesto less than 25mm/sec peak particle velocity and the peak magnitude over the gaspipelines to less than 0.2mm will be incorporated to the design of the sewerage pipesduring detailed design stage. Taking into consideration the separation distance and thedesign of the sewerage pipes, the HP submarine town gas transmission pipelines will notbe further considered in this study. Figure 1.2 shows the alignment of the proposedemergency outfall.

Figure 1.1 Location Plan of the Study

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 2: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-3 August 2016

Figure 1.2 Alignment of the Proposed Emergency Outfall of Relocated STSTW

1.2.1 Objectives

1.2.1.1 The Hazard to Life Assessment requirements as detailed in Appendix G of the EIA StudyBrief are shown below:

(a) Identify hazardous scenarios associated with the operation of HP undergroundtown gas transmission pipelines and then determine a set of relevant scenarios tobe included in a Quantitative Risk Assessment (QRA);

(b) Execute a QRA of the set of hazardous scenarios determined in (a), expressingpopulation risks in both individual and societal terms;

(c) Compare individual and societal risks with the criteria for evaluating Hazard to Lifestipulated in Annex 4 of the TM; and

(d) Identify and assess practicable and cost-effective risk mitigations.

1.2.2 EIAO-TM Risk Criteria

1.2.2.1 Annex 4 of the EIAO-TM specifies the Individual and Societal Risk Guidelines. The HongKong Government Risk Guidelines (HKRG) per the EIAO TM Annex 4 states that theindividual risk is the predicted increase in the chance of fatality per year to an individualdue to a potential hazard. The individual risk guidelines require that the maximum level ofindividual risk should not exceed 1 in 100,000 per year i.e. 1 x10-5 per year. Societal riskexpresses the risks to the whole population. It is expressed in terms of lines plotting thecumulative frequency (F) of N or more deaths in the population from incidents at theinstallation. Three F-

To avoid major disasters, there is a vertical cut-off line atthe 1000 fatality level extending down to a frequency of 1 in a billion years. The

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-4 August 2016

intermediate region indicates the acceptability of societal risk is borderline and should bereduced to a leveensure that all practicable and cost effective measures that can reduce risk will beconsidered. The HKRG is presented graphically in Figure 1.3 below.

Figure 1.3 Societal Risk Guidelines for Acceptable Risk Levels

1.2.3 Institution of Gas Engineers and Managers (IGEM) Risk Guidelines

1.2.3.1 Criteria for individual risk levels and societal risk levels for gas pipelines recommended bythe IGEM have also been considered in this study.

1.2.3.2 The criteria for individual risk levels have been determined by HSE based on historic riskof death. The framework for the tolerability of individual risk is shown in Figure 1.4. Theframework specifies ranges of risk

-6/year isconsidered broadly acceptable for general public.

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 3: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-5 August 2016

Figure 1.4 Framework for the Tolerability of Individual Risk in IGEM

1.2.3.3 For societal risk, the IGEM/TD/1 criterion envelope relates to a 1.6km length of pipelinesand is shown in Figure 1.5limits, mitigation measures should be required to reduce risks to acceptable.

Figure 1.5 IGEM F-N Criterion Envelope

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-6 August 2016

1.3.1.1 The QRA consists of the following 6 main tasks:

(a) Data / Information Collection and Update: Collect relevant data / informationwhich is necessary for the hazard assessment.

(b) Hazard Identification: Identify hazardous scenarios associated with the HPunderground town gas transmission pipelines.

(c) Frequency Estimation: Estimate the frequencies of each hazardous event leadingto fatalities with full justification by reviewing historical accident data and previoussimilar projects.

(d) Consequence Analysis: Analyse the consequences of the identified hazardousscenarios.

(e) Risk Integration and Evaluation: Evaluate the risks associated with the identifiedhazardous scenarios. The evaluated risks will be compared with the HKRG todetermine their acceptability. Where necessary, risk mitigation measures will beidentif(ALARP) principle used in the HKRG.

(f) Identification of Mitigation Measures: Review the recommended risk mitigationmeasures from previous studies, practicable and cost-effective risk mitigationmeasures will be identified and assessed as necessary. Risk outcomes of themitigated case will then be reassessed to determine the level of risk reduction.

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 4: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-7 August 2016

2.1.1 Introduction

2.1.1.1 Societal risk is a measure of the consequence magnitude and the frequency of thehazardous events. In order to establish the impact of any release (the number of peoplelikely to be affected) in the future, it is necessary to have a good knowledge of thesurrounding population levels. It includes residential population, government andinstitutional population and transport population. The main population groups in thevicinity of the 1.9km section of the proposed transport route of explosives interfacing withthe HP underground town gas transmission pipeline are shown in Figure 2.1.

Figure 2.1 Population Groups

2.1.2 Land and Building Population

2.1.2.1 Construction of the Project is tentatively scheduled to substantially commence in 2017 forcompletion in 2027, and the peak cavern construction year is Year 2022. Assessmentyears for construction stage and operational stage of the Project would thus be Year 2022and Year 2027 respectively. The populations in each area are listed in Table 2.1.

2.1.2.2 Population estimations are based on site surveys, Centamap, and data from theenhanced 2011-based Territorial Population and Employment Data Matrix (TPEDM)provided by the Planning Department. Planning Department, Lands Department, CivilEngineering and Development Department, and Home Affairs Department have beenconsulted on the population assumptions.

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-8 August 2016

Table 2.1 Land and Building Population Data

PopulationID Description

Population inConstruction

Stage (Year 2022)[Note 1][Note 2]

Population inOperational

Stage (Year 2027)[Note 1][Note 2]

14 Garden Vista 1662 161514a Block D 562 54514b Block E 562 54514c Block F 432 41914d Car park under podium of

Block D, Block E & Block F30 30

14e Podium of Block D, BlockE & Block F

76 76

15 Pictorial Garden (Stage 1) 1958 190415a Abbey Court 605 58715b Belleve Court 605 58715c Capilano Court 605 58715d Car park under podium 40 4015e Podium 103 103

16 Pictorial Garden (Stage 2) 1831 177916a Delite Court 281 27216b Elegant Court 281 27216c Forum Court 562 54516d Galaxy Court 562 54516e Car park under podium 40 4016f Podium 105 105

17 Pictorial Garden (Stage 3) 1212 117617a Hillview Court 373 36117b Iris Court 373 36117c Juniper Court 373 36117d Car park under podium 30 3017e Podium 63 63

18 On King Street Park 100 10019 Open Car Park (near Jockey

Club Shek Mun RowingCentre)

10 10

20 Jockey Club Shek MunRowing Centre

50 50

21 Hong Kong China DragonBoat Association Shatin ShekMun Training Centre

50 50

22 Hong Kong Canoe UnionShatin Training Centre

50 50

23 Site Offices (DSD / LandsD) 60 6024 Petrol Station 10 1025 Shek Mun Fresh Water

Booster Pumping Station0 0

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 5: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-9 August 2016

PopulationID Description

Population inConstruction

Stage (Year 2022)[Note 1][Note 2]

Population inOperational

Stage (Year 2027)[Note 1][Note 2]

26 On Sum Street Substation 0 027 Sha Tin Community Green

Station60 60

28 Open Car Park (nearPumping House on PingStreet)

20 20

29 Shatin Hospital 1296 129229a Shatin Hospital 975 97529b Open Car Park 10 1029c Transport Terminus 30 3029d Football Field 22 2229e Basketball Court 16 1629f Jockey Club Centre for

Positive Ageing25 25

29g A Kung Kok GovernmentQuarters Block B

104 102

29h A Kung Kok GovernmentQuarters Block C

104 102

29i Tennis Court 10 1030 A Kung Kok Sewage

Pumping Station10 10

31 Ah Kung Kok Fishermen'sVillage

1061 1045

31a Ah Kung Kok FishermenVillage (a)

374 368

31b Ah Kung Kok FishermenVillage (b)

639 629

31c Basketball Court 16 1631d Football Field 22 2231e A Kung Kok Sitting-out

Area10 10

32 Hong Kong MountaineeringUnion

0 0

33 Evangelical Lutheran Churchof Hong Kong Shatin YouthCentre Recreational Campand Training Centre

0 0

34 Custom and ExciseDepartment Shatin VehicleDetention Centre [Note 4]

0 800

35 A Kung Kok Street Garden 10 1036 Ma On Shan Tsung Tsin

Secondary School1406 1406

37 Kowloon City Baptist ChurchHay Nien Primary School

1124 1124

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-10 August 2016

PopulationID Description

Population inConstruction

Stage (Year 2022)[Note 1][Note 2]

Population inOperational

Stage (Year 2027)[Note 1][Note 2]

38 Chevalier Garden 1136 112038a Chevalier Garden Block 6 568 56038b Chevalier Garden Block 5 568 560

39 Kam Tai Court 1436 141439a Kam Ying House Block H 718 70739b Kam Tin House Block J 718 707

40 S.K.H. Ma On Shan HolySpirit Primary School

1318 1318

41 Shing Mun River Promenade 36 36P1 Proposed Project Site [Note 3] 500 300P2 Proposed Project Site Office

and Works Area500 0

Note 1: Populations for residential are estimated based on domestic household size in enhanced 2011-based TPEDM.

Note 2: School populations estimated based on the school information from the Education Bureau.Note 3: It is assumed that there will be a maximum of 500 construction workers in construction stage and a

maximum of 300 staff and visitors in operational stage in the project site.Note 4: The centre will be changed to site office during cavern construction stage. The land use after

completion of construction works is not known at the moment. In view that with the constraintimposed by Tate's Cairn Highway, it is unlikely to have high density population there. Therefore it isassumed that it will be an educational institution.

2.1.3 Road & Train Population

2.1.3.1 Traffic data is based on the latest Annual Traffic Census (ATC) [12] and Based District

Cairn Highway ad Ma On Shan Road are assumed to be 80km/hr and 70km/hrrespectively, and the speed limit on other roads is assumed to be 50km/hr. The roadpopulation is predicted based on the following equation:

Population Density (persons/km) = No. of person/vehicle * No. of vehicles/hr / Speed

2.1.3.2 The occupancies for each vehicle type and vehicle mix are taken as the average at the 4core stations which are considered representative of the road traffic in the study area.Details please refer to Section 4.2.3 of Appendix 7.01. The average occupancy isestimated to be 4.34 persons/vehicle.

2.1.3.3is in parallel to the HP underground town gas transmission pipelines. The maximumcarrying capacity of Ma On Shan Line is currently 30,500 people per hour per directionwith the use of 4 train compartments per train [3]. With the commissioning of the sectionbetween Tai Wan and Hung Hom stations of SCL in 2018, the number of traincompartments of Ma On Shan Line will be increased to 8 [3]. It is assumed that themaximum carrying capacity will then be increased to 61,000 per hour per direction. Themaximum train population density is calculated by the following formula:

Population Density (persons/km) = Passenger per hour / Train Speed

2.1.3.4 Maximum speed of the Ma On Shan Line is 110km/hr, assuming that the train isoperating with average speed of around 80km/hr, the population density is calculated tobe 1,525 persons/km.

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 6: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-11 August 2016

Table 2.2 Road and Train Population to be Considered in Year 2022

Note: * This figure presents the total number of passengers travelled on the Ma On Shan Lineper hour in both directions. It is calculated based on maximum carrying capacity of Ma OnShan Line and assumed that passenger flow reaches the maximum carrying capacity forboth directions as conservative approach.

Table 2.3 Road and Train Population to be Considered in Year 2027

Note: * This figure presents the total number of passengers travelled on the Ma On Shan Lineper hour in both directions. It is calculated based on maximum carrying capacity of Ma OnShan Line and assumed that passenger flow reaches the maximum carrying capacity forboth directions as conservative approach.

2.1.4 Time Modes

2.1.4.1 To be consistent with the hazard assessment for the storage, transport and use ofexplosives methodology, 3 day categories (Weekdays, Saturdays and Sundays) with 4time periods (AM Peak, Daytime, PM Peak and Night) for population have beenconsidered in this study. A total of 6 time modes are being considered and aresummarised in Table 2.4.

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-12 August 2016

Table 2.4 Definitions of Time ModesTime Mode Definition Proportion of Time

Night All days 8:00pm to 7:00am 0.4583AM Peak All days 7:00am to 9:00am 0.0833PM Peak All days 6:00pm to 8:00pm 0.0833Weekday Daytime Weekdays 9:00am to 6:00pm 0.2679Saturday Daytime Saturdays 9:00am to 6:00pm 0.0536Sunday Daytime Sundays 9:00am to 6:00pm 0.0536

2.2.1.1 Meteorological data is required for consequence modelling and risk calculation.Consequence modelling (dispersion modelling) requires wind speed and stability class todetermine the degree of turbulent mixing potential whereas risk calculation requires wind-rose frequencies for each combination of wind speed and stability class.

2.2.1.2 Meteorological data is obtained from Sha Tin Weather Station (2014) where wind speed,stability class, weather class and wind direction are available. This data represents theweather conditions for the whole year in 2014 and has already taken into account ofseasonal variations, and is therefore considered applicable for the assessment. Table 2.5shows the wind speed-stability frequencies.

Table 2.5 Stability Category-Wind Speed Frequencies at Sha Tin StationDay-time

Wind Speed (m/s) A B C D E F Total (%)0.0-1.9 10.60 7.74 0.00 9.25 0.00 14.47 42.062.0-3.9 8.66 19.07 8.20 8.66 4.88 0.89 50.364.0-5.9 0.00 3.57 1.95 1.67 0.05 0.00 7.246.0-7.9 0.00 0.00 0.09 0.25 0.00 0.00 0.34

Over 8.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00All (%) 19.26 30.38 10.24 19.83 4.93 15.36 100.00

Night-timeWind Speed (m/s) A B C D E F Total (%)

0.0-1.9 0.0 0.0 0.0 0.8 0.0 70.1 70.912.0-3.9 0.0 0.0 0.0 6.9 15.5 3.2 25.594.0-5.9 0.0 0.0 0.0 2.8 0.4 0.0 3.236.0-7.9 0.0 0.0 0.0 0.3 0.0 0.0 0.25

Over 8.0 0.0 0.0 0.0 0.0 0.0 0.0 0.02All (%) 0.00 0.00 0.00 10.80 15.91 73.29 100.00

2.2.1.3 According to Table 2.5, 6 combinations (2B, 1D, 3D, 6D, 2E and 1F) and 5 combinations(1D, 4D, 6D, 2E and 1F) of wind speed and stability class are chosen for daytime andnight-time meteorological conditions respectively. These combinations are consideredadequate to reflect the full range of observed variations in these quantities. It is notnecessary and efficient to consider every combination observed. The principle is to groupthese combinations into representative weather classes which together cover allconditions observed.

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 7: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-13 August 2016

2.2.1.4 Once the weather classes have been selected, frequencies for each wind direction foreach weather class can then be determined. Table 2.6 listed out separately thesefrequency distributions for the daytime and night-time meteorological conditions.

Table 2.6 Weather Class-Wind Direction Frequencies at Sha Tin StationDaytime

Direction 2B 1D 3D 6D 2E 1F Total(%)

0 30 6.25 1.01 2.80 0.00 2.27 1.82 14.1530 60 12.11 1.05 4.43 0.05 2.03 1.27 20.9460 90 5.75 0.89 2.42 0.02 1.24 1.72 12.0490 120 7.52 0.91 3.69 0.05 1.63 1.13 14.93120 150 5.34 0.62 2.87 0.05 1.03 0.65 10.56150 180 1.53 0.22 0.65 0.05 0.19 0.31 2.95180 210 1.77 0.38 0.50 0.05 0.36 0.31 3.37210 240 8.33 0.31 4.57 0.57 0.69 0.34 14.81240 270 1.08 0.07 0.81 0.07 0.12 0.34 2.49270 300 0.26 0.10 0.02 0.00 0.05 0.24 0.67300 330 0.10 0.07 0.02 0.00 0.02 0.14 0.35330 360 0.77 0.22 0.79 0.00 0.41 0.55 2.74All (%) 50.81 5.85 23.57 0.91 10.04 8.82 100.00

Night-timeDirection 1D 4D 6D 2E 1F Total (%)0 30 0.10 1.00 0.00 6.15 8.15 15.4030 60 0.13 1.62 0.10 5.48 6.69 14.0260 90 0.03 1.11 0.15 4.43 9.20 14.9290 120 0.05 1.34 0.00 5.20 6.91 13.50120 150 0.03 0.39 0.05 1.83 4.86 7.16150 180 0.03 0.28 0.13 0.82 3.83 5.09180 210 0.03 0.64 0.03 1.03 3.09 4.82210 240 0.00 2.96 0.08 4.76 2.11 9.91240 270 0.00 1.03 0.00 1.36 2.32 4.71270 300 0.00 0.00 0.00 0.05 1.98 2.03300 330 0.00 0.00 0.00 0.03 1.80 1.83330 360 0.15 0.41 0.00 1.93 4.12 6.61All (%) 0.55 10.78 0.54 33.07 55.06 100.00

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-14 August 2016

3.1.1.1 A hazard is an undesired event which may cause harm to people or to the environment ordamage to property.

3.1.1.2 Potential hazards related to transmission of town gas are identified and discussed. TheHong Kong and China Gas Company Limited (HKCG) are consulted for operationinformation and parameters. This section outlined the hazards identification of thepipeline transport of gas including a review of historical accident database, Major HazardIncident Data Services (MHIDAS).

3.1.1.3 The initiating events resulting in a release of town gas could occur due to various reasons,including spontaneous failure and leakage of pipeline. The main hazard from the HP GasPipeline is loss of containment leading to a gas leak, fire, explosion and toxicity. Towngas is flammable and explosive due to the presence of methane, hydrogen and carbondioxide. It is also toxic due to presence of carbon dioxide and carbon monoxide.

3.2.1.1 The HP pipeline is constructed of steel with specification API X52. The nominal wallthickness for the pipe is 12.7mm and the maximum operating pressure is 35 bar. Thepipeline is provided with internal epoxy coating, external fusion bonded epoxy coating,sacrificial anodes cathodic protection system, and a minimum earth cover of 1.1m. Theleak detection system uses low pressure sensors at above ground installations (AGIs),the operator can initiate remote shutdown of valves at AGIs if needed. In addition ofremote isolation at AGIs, manual isolation of intermediate sections in the HP network canalso be achieved through manual ball valves located in underground chambers.

3.3.1.1 Town gas, produced from naphtha and natural gas, is the final product of the gas works.It is a clean, safe and reliable gaseous fuel. With about half the density of air, it rises andwill dissipate in the air if leakages occur. It has neither colour nor odour; thereforeodouriser has been added to the gas such that it can easily be detected.

3.3.1.2 Town gas is a mixture of hydrogen, methane, carbon dioxide and carbon monoxide. It isboth flammable and toxic while carbon monoxide, components of the town gas, ischemical asphyxiant. Table 3.1 lists the composition and physical properties of town gas.

Table 3.1 Compositions and Properties of Town GasComposition % (By Volume) Physical Properties Values

Hydrogen 48.1% Calorific Value 17.27 MJ/m3

Methane 29.4% Specific Gravity 0.52

Carbon Dioxide 19.5% Wobbe Index 24

Carbon Monoxide 3% Weaver Flame Speed 35

3.3.1.3 Release in large quantity, if ignited immediately, will produce a fireball. Initially the gasconcentration in the mixture will be above the Upper Flammability Limit (UFL). As burningoccurs around the edges of the release, this will entrain more air into the mixture andmore combustion will take place. The process accelerates until the mixture rises abovethe ground as a ball of fire.

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 8: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-15 August 2016

3.3.1.4 If not ignited immediately, the gas will disperse and dilute. When the gas concentration isbetween lower Flammability Limit (LFL) and Upper Flammability Limit (UFL), presence ofan ignition source in entire length of the gas cloud movement path may result in a flashfire. In case of continuous release, fire is flashed back to the release source and leads toa jet fire.

3.3.1.5 For continuous releases, immediate ignition will produce a long vigorous jet flame fromthe point of release.

3.3.1.6 For all sizes of release, town gas will have a toxic effect on nearby population sites ifthere is no source of ignition and allowed to disperse.

3.3.1.7 Possible hazardous scenarios associated with the operation of the HP underground towngas transmission pipelines are the loss of containment leading to a gas leak, fireexplosion and toxicity.

3.4.1.1 The transport route of explosives is in close vicinity of a section of the HP undergroundtown gas transmission pipelines from the Sha Tin Hospital to Mui Tsz Lam Road.Separation distance between the transport route of explosives and the pipelines is around50m. For the HP underground town gas transmission pipelines, a minimum earth cover of1.1m is provided, with consideration of the separation distance from the transport route ofexplosives and the protection from the earth cover, it is presumed that probability of thefailure of the transport of explosives triggering failure of HP underground town gastransmission pipelines is very unlikely and thus will not be further considered in the HA.

3.5.1 General

3.5.1.1 The hazards from the pipeline transport of gas are well understood based on historicalexperience world-wide relating to pipeline transportation of oil and gas. From the incidentreview by HSE (1995) [6], some common causes of failure gas pipelines are identifiedbelow:

(a) External events;

(b) Pipe corrosion;

(c) Defective pipe and welds Vehicle impact;

(d) Equipment malfunction and improper operations; and

(e) Spontaneous & partial failure.

3.5.2 External Events

Earthquake

3.5.2.1 An earthquake has the potential to cause damage to HP underground town gastransmission pipelines. The damage could occur due to ground movement/ vibration, withspontaneous failure of pipelines possibly resulting. Though Hong Kong is not particularlyprone to earthquake, the probability 1.0×10-5 per year of earthquake MMI VIII occurrenceis adopted for conservative approach. The failure rate of pipeline due to earthquake isassumed to be 0.01 [4]. Failure due to earthquake is in the order of 10-7 which isconsidered 1 to 2 orders of magnitude lower than base failure rate and/or other causes.

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-16 August 2016

Aircraft Crash

3.5.2.2 Aircrafts crashing into the HP underground town gas transmission pipelines due to airwayaccidents from arrival/departure flight paths are taken into account in this study. Themethod given in HSE (1997) [5] for the calculation of aircraft frequency is adopted.Further details are included in Annex 2. Since the calculated failure rates are muchsmaller than order of 10-9, failure caused by aircraft crash is not further considered in theassessment.

Landslide

3.5.2.3 The 1.9km pipeline segment is not located close to hillside or slope and loss ofcontainment due to landslide is not possible. Therefore, landslide is not further assessedand this factor is not added to the fault tree analysis separately.

Severe Environmental Event

3.5.2.4 Loss of containment due to severe environmental event such as typhoon or tsunami(large scale tidal wave) is considered to be insignificant as the installation of the HPunderground town gas transmission pipelines is situated underground and away fromseashore. Subsidence is usually slow in movement and such movement can be observedand remedial action can be taken in time. Besides, the pipeline was built for many years.Soil condition is rather stable. Failure caused by subsidence is not considered further inthis assessment.

Lightning

3.5.2.5 The HP underground town gas transmission pipelines is buried at 1.1m undergroundalong . Besides, nearby buildings also provide shielding effect toprevent the pipeline being struck by lightning. With sufficient protection system, no furtherconsideration is given for effect of lightning strike in this assessment.

Third Party Damage

3.5.2.6 Third party damage includes activities causing incidents such as work on otherunderground utilities, drilling for ground sampling, construction work on adjoining areas,etc. These excavation works are well controlled in Hong Kong, and there are guidelinesissued by EMSD and also the gas company for construction in the vicinity of gas pipelines.Accurate alignment records of the HP underground town gas transmission pipelines willbe provided by HKCG for works in the vicinity of the pipelines. Nevertheless, failures maystill occur due to inadequate site control and supervision, and the failure rates adopted inSection 3.6 have already included this cause of gas pipeline failure.

External Fire

3.5.2.7 The HP underground town gas transmission pipelines is buried at 1.1m underneath thepaved . Loss of containment due to external fire is considered notpossible. Therefore, external fire is not further assessed and this factor is not added tothe fault tree analysis separately.

3.5.3 Pipeline Corrosion

3.5.3.1 HKCG put particular emphasis on the importance of close inspection and surveillance of

ensure the integrity of the strategic high pressure pipelines. It is effectively a magneticflux pig, ran through the pipelines to record data on electronic devices. Anomalies suchas internal or external corrosion, reduction in pipe wall thickness, dents, attachments etc.were reflected by the strength, change or orientation of magnetic flux signal as the pig ranthrough the pipeline. The data was sent to the On-line Inspection Centre of British Gas fordetail analysis [9].

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 9: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-17 August 2016

3.5.3.2 It is noted though that the HP underground town gas transmission pipelines underconsideration in this study is approximately 10-30 years old. However, given that the wallthickness is 12.7mm, and that recent inspection found no significant loss of thickness dueto corrosion, the high pressure system of HKCG in general is still in an excellent condition.It appears unnecessary to consider failure caused by ageing of pipeline.

3.5.4 Defective Pipe and Welds

3.5.4.1 HKCG have not experienced any loss of containment failure in their high pressuretransmission network (35bar) due to material or construction defect since commencementof operation in 1983.

3.5.5 Equipment Malfunction and Improper Operations

3.5.5.1 From time to time, HKCG receives voluminous notifications from other utility companiesor contractor regarding their construction work. HKCG replies expediently to each enquirywith clear marking of the existing pipeline alignment. For work which may jeopardise thesafety of the gas system, engineers with closely liaise with the party concerned and atrench inspector will monitor the progress of the work. The trench inspector are well-trained and can provide valuable advice to the roadwork contractors on the safetyprecaution required to avoid damage of pipelines and proper site equipmentmaintenances work.

3.5.6 Spontaneous & Partial Failure

3.5.6.1 Offtake stations control and regulate pressures of gas inflow from high tointermediate/medium pressure network and are sensitive to interferences. In case ofminor accident, interferences would disturb inflow of gas in the transmission system. Incase of overpressure, pipeline would be overloaded and lead to full bore rupture follow byan instantaneous gas release. In cold partial failure, it results in continuous gas release tothe atmosphere through a pipe crack or leak.

3.6.1 General

3.6.1.1 Subsequent to the Hazard Identification and Analysis in previous section, the next stepwill be to estimate the likelihoods of various release scenarios. There are combinations ofhazard initiating events, as identified in previous section, which would lead to releasescenarios.

3.6.1.2frequency to be estimated from a logical model of the failure mechanisms of a system.The model is based on the combinations of failures of more basic components, safetysystems and human errors.

3.6.1.3

frequency is calculated from failure data of more simple events.

3.6.1.4 A basic assumption in FTA is that all failures in a system are binary in nature, acomponent or operator either performs successfully or fails completely. In addition, thesystem is assumed to be functioning if all sub-components are operating properly.

3.6.1.5 The stepwise procedure for undertaking FTA is presented below:

(a) Hazard identificat

(b) Construction of fault tree

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-18 August 2016

(c) Quantitative evaluation of the fault tree

3.6.2 Gas Pipeline Failure Frequency

3.6.2.1Association (UKOPA) [1] will be adopted in this study. The UKOPA Database representsa source of pipeline fault data which is specific to UK pipelines and based on exposure ofincident during over 810,000km pipeline operating years between 1952 and 2012. Thedata are contributed to by ten organisations, including Shell. It may be preferable to uselocal data to estimate failure frequencies; however, such data are not sufficient to providestatistically significant results.

3.6.2.2 The approach is to examine UKOPA databases and derive an appropriate failurefrequency for the HKCG pipeline taking into account specific pipeline and environmentfeatures. The total failure rate for onshore gas transmission and distribution in the UK,derived based on data for the period 1992 to 2012 is 1.0×10-5 per km per year [1]. Thisfailure rate will be adopted for the HP underground town gas transmission pipelinerunning along the Highway.

3.6.3 Hole Size Distribution

3.6.3.1 The hole size distribution is given in Table 3.2. In this study, possible releases from holesand ruptures are included. The distribution of the overall frequency into different failuresizes are selected based on UKOPA data. Although the probability of a full bore rupture isextremely low due to the design factor of 0.3 and wall thickness of 12.7mm, it isconsidered in this study for completeness. When modelling pipeline ruptures, the releaserate from both sides of the ruptured pipeline was addressed. Table 3.3 summarises thefailure rates for all identified failure scenarios.

Table 3.2 Hole Size DistributionCategory Hole Size (inch) % ContributionRupture Full bore 1Puncture 19

Hole 30Leak 30Leak 10mm 20

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 10: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-19 August 2016

Table 3.3 Summary of Identified Failure Scenarios and Their Associated Failure Rates for theHP underground town gas transmission pipeline

Failure Scenarios Failure Rates Reference SourceSpontaneous Failure of HP Underground Town Gas Transmission PipelineFull bore rupture 1.00 × 10-7 per km per year Reference [1]Partial Failure of HP Underground Town Gas Transmission Pipeline

1.90 × 10-6 per km per year Reference [1]3.00 × 10-6 per km per year Reference [1]3.00 × 10-6 per km per year Reference [1]

Leak (10mm) 2.00 × 10-6 per km per year Reference [1]Total Failure Rate 1.00 × 10-5 per km per yearExternal EventEarthquake (MMI VIII) 1.00×10-5 per year Reference [4]

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-20 August 2016

4.1.1.1 Subsequent to the Hazard Identification and Analysis in previous section, the next stepwill be to estimate the likelihoods of various releases of town gas. There are combinationsof hazard initiating events, as identified in previous section, which would lead to thereleases.

4.1.1.2frequency to be estimated from a logical model of the failure mechanisms of a system.The model is based on the combinations of failures of more basic components, safetysystems and human errors.

4.1.1.3synthesize a failufrequency is calculated from failure data of more simple events.

4.1.1.4 A basic assumption in FTA is that all failures in a system are binary in nature, acomponent or operator either performs successfully or fails completely. In addition, thesystem is assumed to be functioning if all sub-components are operating properly.

4.1.1.5 The stepwise procedure for undertaking FTA is presented below:

(a)

(b) Construction of fault tree; and

(c) Quantitative evaluation of the fault tree.

4.2.1.1 Fault tree analysis was used to provide models for the calculation of failure rates or theprobabilities of the hazardous scenarios as identifies in Section 3.

4.2.1.2 The estimated likelihoods of various releases of town gas at the HP Gas Pipeline aresummarized in Table 4.1. Set of fault tree diagrams are attached in Annex 3.

Table 4.1 Estimated Occurrence Frequencies of Significant Town Gas Releases at the HPUnderground Town Gas Transmission Pipelines

Release CaseFrequency ofOccurrence/

YearSpontaneous Failure of HP Gas Pipeline (Full Bore Rupture) 2.90E-07

3.71E-065.80E-065.80E-06

Partial Failure of HP Gas Pipeline (10mm Hole Leak) 3.90E-06

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 11: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-21 August 2016

5.1.1.1 Consequence and impact analysis is conducted to provide a quantitative estimate of thelikelihood and number of deaths associated with the range of possible outcomes (i.e.fireball, jet fire, flash fire etc.) which are resulted from failure cases identified in previoussections for the HP Underground Town Gas Transmission Pipeline. In this study, PhastRisk 6.7, upgraded version of DNV SAFETI, is used.

5.2.1.1 All the releases will be modeled assuming 7.8km pipeline section (which has an inventoryof about 50 tonnes), i.e. the section between the offtake station at City One and thedownstream Sai O pigging station.

5.3.1.1 This section gives a brief description of the physical effects models used in the study toassess the effects zones for the following hazardous outcomes,

Fireball;

Jet fire;

Flash fire;

VCE;

Unignited toxic release; and

Safe dispersion

5.3.2 Fireball

5.3.2.1 The release rate following a rupture, if ignition was immediate, would be too high to give a

The fireball is limited to a maximum duration of 30s. The combustion would develop into astable jet fire once the instantaneous release has been burnt and the release rate hasbecome sufficiently steady for a flame to stabilise as stated by Bilo and Kinsman [10]. Arelease from a hole, if ignited, gives a stable flame close to the hole and produces a jetfire.

5.3.2.2 Adopting a conservative approach, the gas mixture for the fatality calculation is assumed100% CO. The following probit equation for CO, from the built-in material database ofPhast Risk, is applied to the risk model,

5.3.2.3 Due to the large size and intensity of a fireball, its effects are not significantly influencedby weather or wind direction. The thermal radiation from a fireball at given distances fromthe fireball centre are estimated using the Phast -in fireball modelling suite inwhich TNO model and HSE model are adopted. The modelling suite is set such that itdecides the most appropriate one in the effect modelling.

5.3.3 Jet Fire

5.3.3.1 A jet fire occurs following the ignition and combustion of a flammable fluid issuingcontinuously from a pipeline, which burns close to the release source. The jet fire which

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-22 August 2016

follows the fire ball is assumed to be directed vertically upwards out of the crater. The jetfire shape is the frustum of a cone and the location and orientation of the frustum aredependent on a number of factors such as release rate and wind speed.

5.3.3.2 Combustion in a jet fire occurs in the form of a strong turbulent diffusion flame that isstrongly influenced by the initial momentum of the release. The principal hazards from ajet fire are thermal radiation and the potential for knock-on effects. Jet fires also dissipatethermal radiation and causes casualty and damage to the population and property nearby.

5.3.4 Gas Dispersion and Flash Fire

5.3.4.1 As town gas is pressurized in the transmission network, it is heavier than air at the initialrelease stage. While the gas expands, it rises rapidly due to the buoyancy nature of thegas under atmospheric conditions. It will propagate and be diluted as a result of airentrainment with the influence of wind.

5.3.4.2 The principal hazard arising from a cloud of dispersing town gas is the delayed ignition ofthe flammable cloud that cause a flame to flash back to the release location and developinto a stable jet or crater fire. The potential for vapour cloud explosion is not consideredsignificant for a buoyant gas plume and thus will not be further considered in this study.

5.3.4.3 Large scale experiments on the dispersion and ignition of flammable gas clouds showthat ignition is unlikely when the average concentration is below the Lower FlammableLimit (LFL) or above the Upper Flammable Limit (UFL). The hazard distance is calculatedby the Unified Dispersion Model (UDM) in the Phast Risk. It estimates the profile of adispersing cloud in segments according to properties of propagating cloud. For simplicityof presenting the hazardous extent of the clouds, the cloud dispersion segment isdescribed as a half/ full ellipse by the following parameters,

Downwind distance to the LFL of the cloud - major semi-axis of the ellipse;

Crosswind distance to the LFL of the cloud - minor semi-axis of the ellipse;

Downwind displacement downwind distance to centre of ellipse.

5.3.4.4 It is considered that there is no scope for escape within the LFL of a flammable cloud in aflash fire. Therefore, a fatality probability of 100% of persons present within the flammablecloud is assumed for flash fires.

5.4.1 Probit Equations

5.4.1.1 The estimation of the fatality/ injury caused by a physical effect such as thermal radiationor overpressure requires the use of probit equations, which describe the probability offatality as a function of some physical effect. The probit equations take the followinggeneral form

Y = a + b ln(V)

where Y is the probit;a and b are constants determined from experiments; andV is a measure of the physical effect such as thermal dose, peak overpressure

etc.

5.4.1.2 The probit is an alternative way of expressing the probability of fatality and is derived froma statistical transformation of the probability of fatality. The relationship between fatalityprobabilities and probits is given in [7].

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 12: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-23 August 2016

5.4.2 Probit Equations For Thermal Impact

5.4.2.1 Fatality rates due to exposure to thermal radiation from a fire were determined by thefollowing probit function which is set as the default in the Phast Risk,

a = -36.38

b = 2.56

V = t x I4/3

where I = thermal radiation intensity at the target (W/m2); and t = duration of exposure (s).

5.4.2.2 For jet fires, the exposure duration is estimated to be 20s, which is considered to be thetime taken for people to take evasive action such as seeking refuge etc.

5.4.3 Probit Equations For Toxic Impact

5.4.3.1 As shown previously in Table 3.1, the composition of town gas contains by volume 19.5%CO2 and 3% CO. Both gases have the potential to cause adverse health effects atpopulation centres if allowed to disperse without ignition.

5.4.3.2 Carbon dioxide (CO2) is not classified as a toxic or harmful gas, but is considered anasphyxiant gas. It is a potent stimulus to respiration and both a depressant and excitant ofthe central nervous system. Carbon dioxide content in fresh air varies around 0.037%.Concentrations of 20% to 30% can result in unconsciousness and convulsions within 1minute of exposure [11].

5.4.3.3 Carbon monoxide (CO) is a highly toxic gas capable of causing harm at very lowconcentrations. It combines with haemoglobin in the blood, thus displacing oxygen. TheIDLH (Immediately Dangerous to Life and Health) value for CO is 1200ppm (0.12%) [11],but concentrations at 0.0035% are enough to cause headache and dizziness.

5.4.3.4 While both gases are odourless, town gas has been odourised with THT. As such,populations under the exposure of town gas are warned olfactorily, allowing the affectedindividuals to react and escape exposure. It is expected that there is a significant intervalbetween the start of the exposure and the onset of incapacitation which would preventescape action. Therefore, escaping from the affected area is a practicable action and hasa high success rate.

5.4.3.5 Since town gas is lighter than air, the release will disperse upwards under normal windconditions until its concentration equilibrates with the surrounding air, where it is then freeto move in any direction. Assuming no immediate ignition has occurred, the surroundingpopulation of the HP underground town gas transmission pipelines is unlikely to be fullyexposed to the emerging gas cloud. As the gas cloud continues to disperse, its CO2 andCO concentration will begin to dilute, significantly reducing its toxicity over time.

5.4.3.6 Adopting a conservative approach, the gas mixture for the fatality calculation is assumed100% CO. The following probit equation for CO, from the built-in material database ofPhast Risk, is applied to the risk model,

Pr = -7.21 + ln(Ct)

where C is gas concentration in ppm and t is the exposure time in minute.

5.4.3.7 Toxic effect is not considered for rail traffic since the gas is likely to be ignited by the trainmotion. Even if the gas cloud is not ignited, the duration of exposure for a passenger in a

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-24 August 2016

moving train provided with mechanical ventilation is limited and therefore it is consideredunlikely to have any significant effects.

5.5.1 General

5.5.1.1 In order to calculate the risk from flammable materials, information on ignition sourcespresent in the study area needs to be identified. Such data is included in the risk modelfor each type of ignition source (i.e. point sources, line sources and area sources). Therisk calculation program (MPACT) built into Phast Risk then predicts the probability of aflammable cloud being ignited as the cloud moves downwind over ignition sources.

5.5.1.2 In general, the probability of immediate or delayed ignitions depends on the scale ofrelease, the presence and location of ignition sources, and the weather conditions.

5.5.1.3 For town gas release analysis, ignition probabilities for pipelines were taken from the Cox,Lees and Ang model [8], which is summarized in Table 5.1. To be conservative, theprobability of immediately ignition is taken as 100% of the listed probability. These ignitionprobabilities are applied to event trees as shown in Annex 4, which are entered in PhastRisk.

Table 5.1 Ignition Probabilities from Cox, Lees and Ang ModelLeak Size Ignition Probability (Gas Release)

Minor (<< 1kg/s) 0.01Major (1-50 kg/s) 0.07

Massive (>50kg/s) 0.3

5.5.2 Point Sources

5.5.2.1 No major point source is identified in vicinity of the HP underground town gastransmission pipelines.

5.5.3 Line Sources

5.5.3.1 Roads are defined as line sources in Phast Risk. The following assumptions are appliedto estimate the presence factor of the line source and the ignition probability:

(a) Probability of ignition for a vehicle is taken as 0.4 in 60 seconds.

(b) Traffic density is based on the projected traffic flow as shown Table 5.2 andTable 5.3.

5.5.3.2 In addition, the Ma On Shan Line is also defined as line sources in Phast Risk. Thefollowing assumptions are applied to estimate the presence factor of the line source andthe ignition probability:

(a) Probability of ignition is taken as 0.75 in 60 seconds.

(b) Presence factor of the ignition source is assumed to be 1.

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 13: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-25 August 2016

Table 5.2 Summary of Road Ignition Source for Construction Stage (Year 2022)

Line SourcePeak Traffic

Flow(veh/hr)

DaytimeTraffic Flow

(veh/hr)

Night-timeTraffic Flow

(veh/hr)

TrafficSpeed(km/hr)

Tai Chung Kiu Road 2,917 2,179 937 50On King Street 583 436 187 50On Ping Street 729 545 234 50On Sum Street 729 545 234 50Tate's Cairn Highway 8,677 6,481 2,787 80A Kung Kok ShanRoad 111 83 36 50

A Kung Kok Street 966 722 310 50Ma On Shan Road 2,173 1,623 698 70Mui Tsz Lam Road 97 72 31 50Hang Tai Road 435 325 140 50Shek Mun Interchange 1,742 1,301 559 50

Table 5.3 Summary of Road Ignition Source for Operational Stage (Year 2027)

Line SourcePeak Traffic

Flow(veh/hr)

DaytimeTraffic Flow

(veh/hr)

Night-timeTraffic Flow

(veh/hr)

TrafficSpeed(km/hr)

Tai Chung Kiu Road 3,066 2,290 985 50On King Street 613 458 197 50On Ping Street 767 573 246 50On Sum Street 767 573 246 50Tate's Cairn Highway 9,492 7,090 3,049 80A Kung Kok ShanRoad 111 83 36 50

A Kung Kok Street 583 435 187 50Ma On Shan Road 2,284 1,706 734 70Mui Tsz Lam Road 58 44 19 50Hang Tai Road 457 341 147 50Shek Mun Interchange 1,586 1,185 510 50

5.5.4 Area Source

5.5.4.1 Phast Risk considers residential population as an ignition source (such as cooking,smoking, heating appliances etc.). The ignition probability is derived from populationdensities in the concerned area by the software.

5.5.5 Population Input

5.5.5.1 With reference to previous practice with SAFETI in Hong Kong, population at locationslisted in Table 2.1, Table 2.2, Table 2.3 and Annex 1 are applied to the risk model.Shielding factors are applied in fireball events according to recommendations in [2].Shielding factors are determined by considering the location of a building and the fireballsize. For a building shielded by other buildings and not in the direct line of sight of thefireball or with a blank wall facing towards the fireball, population in the building isconsidered protected. For buildings in the direct line of the fireball, population in unitsdirectly in front is affected.

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-26 August 2016

6.1.1.1 In this section, the risks arising from the HP underground town gas transmission pipelineare evaluated in terms of both individual and societal risks separately.

6.1.1.2 Individual risk is a measure of the risk to a chosen individual at a particular location. Assuch, this is evaluated by summing the contributions to that risk across a spectrum ofincidents which could occur at a particular location.

6.1.1.3 Societal risk is a measure of the overall impact of an activity upon the surroundingcommunity. As such, the likelihoods and consequences of the range of incidentspostulated for that particular activity are combined to create a cumulative picture of thespectrum of the possible consequences and their frequencies. This is usually presentedas a fN curve and the acceptability of the results can be judged against the societal riskcriterion under the risk guidelines.

6.2.1.1 The associated individual risk levels are shown in Figure 6.1. The risk level is based on100% occupancy with no allowance made for shelter or escape, which can be referredfrom the user manual of Phast Risk.

6.2.1.2 criterion for individual risk is that no person off-site shallbe subject to an additional risk of 1×10-5/year; while the tolerability of individual risk in theIGEM Risk Guidelines is less than 1×10-6/year for general public.

6.2.1.3 The maximum individual risk is less than 1×10-7 per year. On this basis, it would appearthat the level of individual risk associated with the HP underground town gas transmissionpipeline should be acceptable since it meets both the Hong Kong Risk Guidelines and theIGEM Risk Guidelines.

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 14: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-27 August 2016

Figure 6.1 Individual Risk Contours for the HP Underground Town Gas Transmission Pipeline

6.3.1 Societal Risk for the HP Gas Pipeline According to Hong Kong Risk Guidelines

6.3.1.1 The societal risks are evaluated for the range of incidents with the potential for fatalities inthe vicinity and are shown in Table 6.1 and Table 6.2. The societal risk is more complexthan that for individual risk but, in essence, comprises three regions:

(a) - a region within which the risks may be regarded as unacceptable;

(b) - a region within which the risks may be regarded as acceptable; and

(c) - a region between the two in which measures should be taken todemonstrate the riskwords, consideration is given not only to the level of risk but also the cost andpracticality of reducing it.

6.3.1.2 Numerically, the upper bound of the ALARP region (and hence the borderline of

(a) 1 chance in 1,000 per year of an incident resulting in 1 or more fatalities;

(b) 1 chance in 10,000 per year of an incident resulting in 10 or more fatalities;

(c) 1 chance in 100,000 per year of an incident resulting in 100 or more fatalities; and

(d) not more than 1,000 fatalities at a frequency of greater than 1 chance in a billion(1,000,000,000) per year.

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-28 August 2016

6.3.1.3 As shown in Figure 6.2 and Figure 6.3, majority of the societal risks associated with theoperation of the HP underground town gas transmission pipeline for both constructionand operational stages , with number of fatality between 200

.

6.3.1.4 truction and operational stages,it is found that the ALARP is due to the background population instead of the populationinduced by the Project. Data points for the Construction Stage Scenario and OperationalStage Scenario are tabulated in Table 6.1 and Table 6.2 respectively.

Table 6.1 Societal Risk Data for Construction Stage ScenarioNo.

FatalitiesFrequency

(/year)No.

FatalitiesFrequency/

yearNo.

FatalitiesFrequency/

year1 1.91E-06 15 1.41E-07 120 5.60E-08

2 3.90E-07 20 1.31E-07 150 5.23E-083 3.21E-07 25 1.21E-07 200 5.12E-084 2.96E-07 30 1.11E-08 250 5.00E-085 2.71E-07 40 9.49E-08 300 4.67E-086 2.44E-07 50 8.93E-08 400 2.96E-088 1.98E-07 60 8.63E-08 500 8.36E-0910 1.68E-07 80 7.58E-08 600 3.87E-0912 1.55E-07 100 6.51E-08

Table 6.2 Societal Risk Data for Operational Stage ScenarioNo.

FatalitiesFrequency

(/year)No.

FatalitiesFrequency/

yearNo.

FatalitiesFrequency/

year1 1.82E-06 15 1.42E-07 120 5.37E-082 3.93E-07 20 1.32E-07 150 5.22E-083 3.17E-07 25 1.22E-07 200 5.07E-084 2.93E-07 30 1.12E-07 250 4.97E-085 2.69E-07 40 9.56E-08 300 4.53E-086 2.49E-07 50 8.75E-08 400 2.58E-088 2.06E-07 60 8.34E-08 500 7.18E-0910 1.70E-07 80 7.48E-08 600 1.55E-0912 1.57E-07 100 6.24E-08

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 15: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-29 August 2016

Figure 6.2 Societal Risk Curve for Construction Stage

1.00E-09

1.00E-08

1.00E-07

1.00E-06

1.00E-05

1.00E-04

1.00E-03

1.00E-02

1 10 100 1000 10000

Freq

uenc

y(f)

ofAc

cide

nts

with

Nor

Mor

eFa

talit

ies

PerY

ear

No. of Fatalities (N)

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-30 August 2016

Figure 6.3 Societal Risk Curve For Operational Stage

6.3.2 Societal Risk for the HP Gas Pipeline According to IGEM Risk Guidelines

6.3.2.1 The societal risks are evaluated for the range of incidents with the potential for fatalities inthe vicinity and are shown in Figure 6.4 and Figure 6.5 for construction stage andoperational stage respectively. The societal risk criterion envelope of IGEM comprisestwo regions:

(a) - a region within which the risks may be regarded asacceptable; and

(b) - a region in which measures

(ALARP). In other words, consideration is given not only to the level of risk butalso the cost and practicality of reducing it.

6.3.2.2 As a conservative approach, the entire pipeline section of 1.9km instead of scaling to1.6km pipeline length is considered in the risk assessment. The fN curves are shown inFigure 6.4 and Figure 6.5 along with the criteria for comparison with the IGEM riskguidelines. As shown in the figures, the societal risks associated with the operation of theHP underground town gas transmission pipeline for both Construction Stage Scenario

1.00E-09

1.00E-08

1.00E-07

1.00E-06

1.00E-05

1.00E-04

1.00E-03

1.00E-02

1 10 100 1000 10000

Freq

uenc

y(f)

ofAc

cide

nts

with

Nor

Mor

eFa

talit

ies

PerY

ear

No. of Fatalities (N)

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 16: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-31 August 2016

and Operational Stage Scenario Tolerable Risk based upon ALARPConsiderationsand operational stages, it is found that the tolerable risk is mainly due to the backgroundpopulation instead of the population induced by the Project.

Figure 6.4 Societal Risk Curve With IGEM F-N Criterion Envelope For Construction Stage

1.00E-10

1.00E-09

1.00E-08

1.00E-07

1.00E-06

1.00E-05

1.00E-04

1.00E-03

1.00E-02

1 10 100 1000 10000

Freq

uenc

y(f)

ofAc

cide

nts

with

Nor

Mor

eFa

talit

ies

PerY

ear

No. of Fatalities (N)

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-32 August 2016

Figure 6.5 Societal Risk Curve With IGEM F-N Criterion Envelope For Operational Stage

6.3.3 Potential Loss of Life (PLL)

6.3.3.1 The total PLL for construction stage and operational stage are found to be 2.95×10-5 peryear and 2.84×10-5 per year respectively. Fireball events from town gas releasecontribute to most of the proportion (~85%) of the overall PLL.

1.00E-10

1.00E-09

1.00E-08

1.00E-07

1.00E-06

1.00E-05

1.00E-04

1.00E-03

1.00E-02

1 10 100 1000 10000

Freq

uenc

y(f)

ofAc

cide

nts

with

Nor

Mor

eFa

talit

ies

PerY

ear

No. of Fatalities (N)

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 17: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-33 August 2016

7.1.1.1 A Hazard to Life Assessment of the risks associated with operation of the HPunderground town gas transmission pipeline has been conducted for both constructionand operational stages of the Project.

7.1.1.2 The individual risk complies with both the Hong Kong Risk Guidelines and the IGEM RiskGuidelines.

7.1.1.3the Hong Kong Risk Guidelines for both construction stage and operational stage

operational stages, it is found that the ALARP is due to the background populationinstead of the population induced by the Project.

7.1.1.4 It is recommended that adequate emergency response / evacuation plans for the projectworks areas and the future sewage treatment works staff are established and emergencytraining / drills for all relevant personnel conducted at regular intervals.

EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM App 7.3-34 August 2016

[1] RA McConnell & Dr J V Haswell (2012). UKOPA Pipeline Product Loss Incidentsand Faults Report (1962-2012).

[2]nference on Risk & Safety

Management in the Gas Industry, EMSD & HKIE, Hong Kong

[3] Legislative Council Panel on Transport Subcommittee on Matters Relating toRailways Capacity and Loading of MTR Trains CB(1)980/13-14(03).

[4] Ling Chan & Partners Limited (2001). Environmental Impact Assessment forProposed Headquarters and Bus Maintenance Depot in Chai Wan (BDEIA).

[5] Health and Safety Executives (1997). The Calculation of Aircraft Crash Risk in theUK. J P Byrne.

[6] Health & Safety Executive, UK (1995). Risk from Hazards Pipelines in the UnitedKingdom, Arthur D Little, HSE Contract Research Report No. 82/1994, HMSO

[7] TNO, Guideline for Quantitative Risk Assessment (Purple Book), CPR 18E, 2005

[8] Assessmentand Control, 3rd edition, 2005

[9] ERM (1998) Proposed High Pressure Steel Gas Pipeline from Tai Po Tsai toTseung Kwan O (ETPE), HKCG.

[10] Bilo and Kinsman PR (1997). MISHAP -methodology. Pipes and Pipelines International.

[11] Nick H. Proctor, James P. Hughes and Michael L. Fischman (1988), ChemicalHazards of the Workplace

[12] Transport Department (June 2014). The Annual Traffic Census 2013.

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03
leekhk1
Typewriter
App7.03
Page 18: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

Study Brief No. ESB - 273/2014 EIA Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A1 May 2016

Annex 1

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
August 2016
leekhk1
Text Box
leekhk1
Typewriter
App7.03-A1-
Page 19: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

Study Brief No. ESB - 273/2014 EIA Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A2 May 2016

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
August 2016
leekhk1
Text Box
leekhk1
Typewriter
App7.03-A1-
Page 20: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A3 May 2016

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A4 May 2016

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
August 2016
leekhk1
Typewriter
August 2016
leekhk1
Text Box
leekhk1
Typewriter
App7.03-A2-1
leekhk1
Text Box
leekhk1
Typewriter
App7.03-A2-2
Page 21: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A5 May 2016

Annex 3

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A6 May 2016

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
August 2016
leekhk1
Typewriter
August 2016
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03-A3-1
leekhk1
Typewriter
App7.03-A3-2
Page 22: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A7 May 2016

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A8 May 2016

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
August 2016
leekhk1
Typewriter
August 2016
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03-A3-3
leekhk1
Typewriter
App7.03-A3-4
Page 23: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A9 May 2016

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A10 May 2016

Annex 4

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
August 2016
leekhk1
Typewriter
August 2016
leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
App7.03-A3-5
leekhk1
Typewriter
App7.03-A4-1
Page 24: APPENDIX 7.03 HIGH PRESSURE (HP) … Report Sha Tin Cavern Sewage Treatment Works Appendix 7.03 AECOM App 7.3-1 August 2016 APPENDIX 7.03 HIGH PRESSURE (HP) UNDERGROUND TOWN GAS TRANSMISSION

Study Brief No. ESB - 273/2014 EIA ReportSha Tin Cavern Sewage Treatment Works Appendix 7.03

AECOM 7C-A11 May 2016

leekhk1
Text Box
leekhk1
Text Box
leekhk1
Typewriter
August 2016
leekhk1
Text Box
leekhk1
Typewriter
App7.03-A4-2