appendix a district 4 high band voted system contract ... · the fdot will witness commissioning...

12
APPENDIX A District 4 High Band Voted System Contract Plans Package 39 of 50

Upload: lemien

Post on 21-May-2018

213 views

Category:

Documents


1 download

TRANSCRIPT

APPENDIX A

District 4 High Band Voted System

Contract Plans Package

39 of 50

STATE OF FLORIDA

DEPARTMENT OF TRANSPORTATION

PENSACOLA

TALLAHASSEEJACKSONVILLE

TAMPA

NAPLESFT LAUDERDALE

MIAMI

KEY WEST

ORLANDO

LAKECITY

Contract plans

BROWARD COUNTY

DISTRICT 4 HIGH BAND VOTED SYSTEM

Intelligent transportation systems plans

NOTE: THE SCALE OF THESE PLANS MAY

HAVE CHANGED DUE TO REPRODUCTION.

INDEX OF PLANS

SHEET NO. SHEET DESCRIPTION

IT-1 KEY SHEET

IT-2 GENERAL NOTES AND INSPECTION NOTES

IT-3 INSTALLATION NOTES

IT-4 NETWORK DESIGN

IT-5 DISTRICT 4 HEADQUARTERS ROOF APPURTENANCES

IT-6 DISTRICT 4 HQ EQUIPMENT ROOM AND CABINET DETAILS

IT-7 MCARTHUR TOWER LOADING DETAILS

IT-8 MCARTHUR COMMUNICATIONS SHELTER DETAILS

IT-9 BROWARD OPS EQUIPMENT ROOM AND TOWER

IT-10 MAJOR EQUIPMENT LIST

FDOT PROJECT MANAGER: RANDY PIERCE

N

TOWER SITE ADDRESS(ES):

DISTRICT 4 HEADQUARTERS

3400 WEST COMMERCIAL BOULEVARDFT. LAUDERDALE, FL 33309-3421

MCARTHUR

5100 WEST SUNRISE BOULEVARDFT. LAUDERDALE, FL 33313

BROWARD OPS

5548 NW 9TH AVENUEFT. LAUDERDALE, FL 33309-2804

TOWER SITE LOCATION(S):

DISTRICT 4 HEADQUARTERS

LATITUDE: 26-11-8.03 N (NAD 83)LONGITUDE: 80-11-39.40 W

MCARTHUR

LATITUDE: 26-08-15.08 N (NAD 83)LONGITUDE: 80-13-3.52 W

BROWARD OPS

LATITUDE: 26-11-40.47 N (NAD 83)LONGITUDE: 80-09-14.64 W

IT-1

SHEET NO.District 4 high band

key sheet

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

DISTRICT 4

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

LOCATION OF PROJECT

GOVERNING STANDARDS AND SPECIFICATIONS:

FLORIDA DEPARTMENT OF TRANSPORTATION,

DESIGN STANDARDS DATED 2015,

AND STANDARD SPECIFICATIONS FOR ROAD AND

BRIDGE CONSTRUCTION DATED 2015,

AS AMENDED BY CONTRACT DOCUMENTS.

0 2.5 miles 5 miles

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

0 30 60miles

40 of 50

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

IT-2

SHEET NO.bayshore

GENERAL NOTES AND

INSTALLATION

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

DISTRICT 4

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

GENERAL NOTES:

1. THE VENDOR SHALL BE RESPONSIBLE FOR VERIFYING ALL CONDITIONS AND MEASUREMENTS RELATING TO THE WORK IN THE FIELD PRIOR

TO PROCEEDING WITH INSTALLATION, REMOVAL, AND DISPOSAL ACTIVITIES. THE VENDOR SHALL COORDINATE ANY MODIFICATIONS

REQUIRED WITH FDOT.

2. THE VENDOR IS RESPONSIBLE FOR ALL EQUIPMENT, MATERIALS, AND SERVICES REQUIRED TO COMPLETE THIS PROJECT. THE VENDOR IS

RESPONSIBLE FOR VERIFYING THE COMPLETENESS OF MATERIALS REQUIRED AND SUITABILITY OF DEVICES TO MEET THESE PLANS. THE

VENDOR SHALL PROVIDE AND INSTALL, WITHOUT CLAIM, ANY ADDITIONAL EQUIPMENT AND SERVICES REQUIRED FOR OPERATION PER THESE

PLANS.

3. THE VENDOR SHALL BE RESPONSIBLE FOR DETERMINING LOCAL FACILITIES FOR DELIVERING, STORING, AND LEGALLY DISPOSING OF POST-

INSTALLATION MATERIALS.

4. THE VENDOR IS RESPONSIBLE FOR OBTAINING ANY PERMITS AND MEETING BUILDING OFFICIAL REQUIREMENTS, INCLUDING ASSOCIATED

FEES. THE VENDOR IS RESPONSIBLE FOR CONTACTING APPLICABLE BUILDING OFFICIALS FOR PERMIT APPLICATIONS AND SUBMITTING TO

THE FDOT FOR SIGNATURE.

5. THE VENDOR IS RESPONSIBLE FOR COORDINATING ALL NECESSARY NOTIFICATIONS OF WORK AND CONSTRUCTION WITH THE FEDERAL

AVIATION ADMINISTRATION (FAA) AND FEDERAL COMMUNICATIONS COMMISSION (FCC) WITH THE FDOT PROJECT MANAGER. ALL FAA AND

FCC FILINGS WILL BE HANDLED BY THE VENDOR BASED ON THIS COORDINATION.

6. THE VENDOR SHALL SUBMIT AN INSTALLATION SCHEDULE TO FDOT FOR REVIEW AND APPROVAL. THE PLAN SHALL INCLUDE A DETAILED

SCHEDULE OF EVENTS DETAILING EACH PHASE OF INSTALLATION, INCLUDING A PROJECTED TIMELINE.

7. THE VENDOR MUST COORDINATE ALL SITE WORK WITH FDOT. THE CONTACT PERSON IS RANDY PIERCE, 850-410-5608.

8. ALL ANTENNA REMOVAL AND INSTALLATION WORK SHALL BE DONE BY TOWER CLIMBERS CERTIFIED BY COMTRAIN, OR APPROVED

EQUIVALENT. CERTIFICATION DOCUMENTATION IS REQUIRED, STATING THE NAME OF THE VENDOR AND THE INDIVIDUAL NAME FOR EACH

EMPLOYEE ON THE SITE. THE COMTRAIN ID CARD CAN BE USED FOR THIS DOCUMENTATION AND MUST BE CARRIED ON A PERSON ON SITE

WHILE WORKING.

THE VENDOR SHALL BE AN AUTHORIZED MIDLAND SYSTEMS DEALER, AND A 4RF DEALER APPROVED TO SELL, DESIGN, AND INSTALL PUBLIC

SAFETY GRADE MIDLAND LAND MOBILE RADIO AND 4RF PRODUCTS.

9. THE VENDOR SHALL COORDINATE EACH ELEMENT ON THE SCHEDULE WITH OTHER INSTALLATION ACTIVITIES AND SHOW EACH ACTIVITY IN

PROPER SEQUENCE.

10. THE VENDOR SHALL RESTRICT PERSONNEL, THE USE OF EQUIPMENT, AND THE STORAGE OF MATERIALS TO AREAS WITHIN THE LIMITS OF

INSTALLATION. ANY OFF-SITE STORAGE AREA IS THE RESPONSIBILITY OF THE VENDOR.

11. THE VENDOR SHALL PROVIDE SECURITY FOR HIS/HER EQUIPMENT AND SHALL CONDUCT HIS/HER OPERATIONS SO AS TO AVOID

INTERFERENCE WITH FDOT'S NORMAL OPERATIONS.

12. THE VENDOR SHALL PROVIDE AND MAINTAIN IN A NEAT AND SANITARY CONDITION SUCH ACCOMMODATIONS FOR THE USE OF HIS/HER

EMPLOYEES AS MAY BE NECESSARY TO COMPLY WITH REGULATIONS OF THE COUNTY OR THE DEPARTMENT OF HEALTH AND

REHABILITATIVE SERVICES. NO NUISANCE WILL BE PERMITTED.

13. THE VENDOR SHALL BE RESPONSIBLE FOR REMOVING AND LEGALLY DISPOSING OF TRASH IN A TIMELY MANNER.

14. ALL EQUIPMENT AND SERVICES FURNISHED BY THE VENDOR AS PART OF THIS PROJECT SHALL BE WARRANTED TO BE FREE FROM DEFECTS

IN MATERIAL AND WORKMANSHIP. IN THE EVENT ANY SUCH DEFECTS IN EQUIPMENT OR SERVICES BECOME EVIDENT WITHIN THE WARRANTY

PERIOD, THE VENDOR SHALL CORRECT THE DEFECT BY REPAIRING OR REPLACING THE DEFECTIVE COMPONENT OR EQUIPMENT AT NO COST

TO FDOT DURING THE WARRANTY PERIOD. THE WARRANTY PERIOD SHALL BE A MINIMUM OF 12 MONTHS FROM DATE OF FINAL ACCEPTANCE.

CLAIMS UNDER ANY OF THE WARRANTIES HEREIN ARE VALID IF MADE WITHIN 30 DAYS AFTER TERMINATION OF THE WARRANTY PERIOD.

15. THE VENDOR SHALL PROVIDE PHOTOGRAPHIC DOCUMENTATION OF ALL WORK PERFORMED AT EACH SITE CLEARLY SHOWING THE NEW

ANTENNAS AND ASSOCIATED HARDWARE AND CABLING, AND THE NEW RADIOS.

THE VENDOR SHALL SUBMIT A SET OF HARD COPY AS-BUILT DOCUMENTATION DEPICTING THE TOWER LOADING DETAILS AND RACK

DIAGRAMS, AND A SOFT COPY OF THE AS-BUILT DOCUMENTATION.

THE VENDOR SHALL COMPLETE THE ITS FACILITY MANAGEMENT SYSTEM FORMS (ITSFM038, ITSFM053, AND ITSFM055). THE VENDOR SHALL

DOWNLOAD THE ACTUAL FORM FROM THE FOLLOWING ITS FACILITY MANAGEMENT SYSTEM WEB SITE ADDRESS:

http://www.dot.state.fl.us/trafficoperations/its/Projects_Telecom/ITSFM/ITSFM-datacollection.shtm

IT IS IMPORTANT THAT THE VENDOR DOWNLOAD AND USE THE MOST CURRENT FILE VERSION PRIOR TO STARTING WORK BECAUSE OF THE

FREQUENCY OF UPDATES.

16. THE VENDOR SHALL BE RESPONSIBLE FOR THE COAXIAL CABLE AND RESPECTIVE HARDWARE. ANY BENDS, KINKS, OR DEFORMATION WILL

RENDER THE COAXIAL CABLES UNUSABLE. SPLICING OF THE COAXIAL CABLE IS NOT PERMITTED. ANY EXISTING ELLIPTICAL WAVEGUIDES

AND NEW AND EXISTING COAXIAL CABLES DAMAGED BY THE VENDOR SHALL BE REPLACED WITH NEW FULL-LENGTH WAVEGUIDES AND

COAXIAL CABLES, WITHOUT CLAIM, AND AT THE VENDOR’S COST.

17. ALL COAXIAL TRANSMISSION LINES SHALL BE INSTALLED IN SUCH A MANNER THAT DOES NOT VIOLATE THE MANUFACTURER’S MINIMUM BEND

RADIUS.

18. THE VENDOR IS RESPONSIBLE FOR VERIFYING CORRECT SIZE, GENDER, AND SUITABILITY OF ALL COAXIAL TRANSMISSION LINE CONNECTORS

AND SPDS. THE VENDOR SHALL SUBMIT A DETAILED LIST OF CONNECTORS AND SPDS TO THE FDOT PROJECT MANAGER FOR REVIEW AND

APPROVAL.

DISTRICT 4 HIGH BAND

general NOTES

GENERAL NOTES (CONT’D):

19. ALL ANTENNA SYSTEMS SHALL BE FREQUENCY DOMAIN SWEEP TESTED AND TIME DOMAIN TESTED PRIOR TO OPERATION.

THE ANTENNA AND COAXIAL TRANSMISSION LINES THAT ARE SPECIFIED TO BE REUSED SHALL BE FREQUENCY AND TIME DOMAIN SWEEP

TESTED TO DETERMINE IF IT IS OPERATIONAL. IF THE TEST INDICATES THAT THE ANTENNA OR COAXIAL TRANSMISSION LINES NEED TO BE

REPLACED, THE VENDOR SHALL REPLACE THE ANTENNA AND/OR COAXIAL TRANSMISSION LINES WITH A CHANGE ORDER APPROVED BY

THE FDOT.

NEW ANTENNAS AND TRANSMISSION LINES THAT DO NOT PASS THE SWEEP TESTS SHALL BE REPLACED BY THE VENDOR AT NO

ADDITIONAL COST TO THE FDOT. THE VENDOR SHALL CORRECT THE PROBLEM AND PERFORM SWEEP TESTS UNTIL THE PROBLEM IS

RESOLVED.

20. ALL COAXIAL TRANSMISSION LINES SHALL BE MARKED WITH COLORED TAPE AT THE TOP AND BOTTOM (NEAR THE ANTENNA AND NEAR THE

GROUND BUS BAR/BULKHEAD). THE COLORED TAPE SHALL BE APPLIED IN RINGS (BANDS) AROUND THE COAXIAL TRANSMISSION LINES FOR

EASY IDENTIFICATION.

21. THE FDOT WILL WITNESS COMMISSIONING AND TESTING OF THE HIGH-BAND REPEATER, MICROWAVE LINK AND NETWORK CONNECTION(S)

AT EACH OF THE THREE (3) DISTRICT 4 TRANSMISSION SITES, AND NOTIFY THE VENDOR OF FINAL ACCEPTANCE.

22. THE VENDOR SHALL COLLECT PRODUCT DATA INTO A SINGLE SUBMITTAL FOR EACH ELEMENT OF INSTALLATION OR SYSTEM. PRODUCT

DATA SHALL INCLUDE PRINTED INFORMATION SUCH AS MANUFACTURER’S INSTALALTION INSTRUCTIONS AND PERFORMANCE

SPECIFICATIONS.

23. THE VENDOR SHALL SUBMIT TWO (2) SETS OF AS-BUILT DRAWINGS DEPICTING THE LOCATION OF COMPONENTS OF THE COMMUNICATIONS

FACILITIES WITH RESPECT TO LOCAL FEATURES AND BENCHMARKS. AS-BILT DRAWINGS DEPICTING ANY FIELD CHANGES TO THE FACILITIES

SHALL ALSO BE SUBMITTED. AS-BUILT DOCUMENTATION SHALL BE SUBMITTED IN ELECTRONIC FORMAT, AS WELL AS PRINTED.

INSPECTION NOTES:

1. THE INSPECTION SHALL BE PERFORMED BY THE VENDOR AND WITNESSED BY FDOT. THE VENDOR SHALL NOTIFY FDOT AT LEAST

3 DAYS PRIOR TO COMPLETION OF INSTALLATION. THE VENDOR AND FDOT SHALL VERIFY JOINTLY THAT ALL INSTALLATION WORK

IS CORRECTLY INSTALLED AND FUNCTIONAL.

2. GROUNDING SHALL BE INSPECTED FOR PROPER CONNECTION TYPES, TIGHTNESS, WORKMANSHIP, AND CONFORMANCE WITH THE

APPROVED DESIGN.

3. THE SITES SHALL BE INSPECTED TO BE FREE OF DEBRIS AND COMPOUND RESTORED.

4. FOLLOWING THE COMPLETION OF INSPECTIONS, THE INSTALLED EQUIPMENT AND FACILITIES SHALL BE SUBJECTED TO A MINIMUM

20-DAY PERFORMANCE PERIOD. FOR THE PURPOSE OF THE SUCCESSFUL PERFORMANCE PERIOD, FAILURE OF OPERATION IS

DEFINED AS THE FAILURE OF A MAJOR COMPONENT OF THE SITE (COAXIAL TRANSMISSION LINE, ANTENNAS, ETC.). DEGRADATION OF

MICROWAVE LINK PERFORMANCE IS A FAILURE. THE PERFORMANCE VERIFICATION SHALL BE ACCOMPLISHED WITH THE FDOT. UPON

ACCEPTANCE OF THE PERFORMANCE AND TEST CRITERIA BY FDOT, THE 20-DAY PERFORMANCE PERIOD SHALL BEGIN.

APPLICABLE PUBLICATIONS AND STANDARDS:1. ANSI/TIA-222-G-2, STRUCTURAL STANDARD FOR ANTENNA SUPPORTING STRUCTURES AND ANTENNAS, STRUCTURE CLASSIFICATION-III.

2. APPLICABLE MANUFACTURER’S INSTRUCTIONS AND STANDARD PRACTICES.

3. APPLICABLE OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (O.S.H.A.) PRACTICES.

4. ASTM A123: STANDARD SPECIFICATION FOR: ZINC (HOT GALVANIZED) COATINGS ON PRODUCTS FABRICATED FROM ROLLED, PRESSED,

AND FORGED STEEL SHAPES, PLATES, BARS, AND STRIP.

5. ASTM A153: STANDARD SPECIFICATION FOR: ZINC COATING (HOT-DIP) ON IRON AND STEEL HARDWARE.

6. EIA-81: MEASURING GROUND RESISTANCE AND POTENTIAL GRADIENTS IN THE EARTH.

7. FLORIDA BUILDING CODE, 2015 EDITION.

8. FDOT 2015 STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE DESIGN.

9. FDOT 2015 DESIGN STANDARDS.

10. FEDERAL AVIATION ADMINISTRATION REGULATIONS.

11. IEEE 837: STANDARD FOR QUALIFYING PERMANENT CONNECTIONS USED IN SUBSTATION GROUNDING.

12. NATIONAL ELECTRICAL CODE (NEC) (NFPA 70), CURRENT EDITION.

13. NIST: NATIONAL INSTITUTE OF STANDARDS AND TECHNOLIGY.

14. UL 467: STANDARDS FOR GROUNDING AND BONDING EQUIPMENT.

15. NATIONAL FIRE PROTECTION ASSOCIATION (NFPA 780), CURRENT EDITION

41 of 50

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

SHEET NO.bayshore

GENERAL NOTES AND

INSTALLATION

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

DISTRICT 4

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

DISTRICT 4 HIGH BAND

INSTALLATION NOTESIT-3

DISTRICT 4 HEADQUARTERS NOTES:

1. THE VENDOR SHALL REMOVE AND PROPERLY DISPOSE OF THE DB201 ANTENNA. THE VENDOR SHALL LEAVE THE 1/2-INCH COAXIAL

TRANSMISSION LINE AND MOUNTING HARDWARE IN PLACE TO BE REUSED FOR THE 960 MHZ LINK TO THE FDOT MCARTHUR SITE.

2. THE VENDOR SHALL REMOVE TWO (2) MIDLAND BASETECH BASE STATION RADIOS FROM AN EXISTING CABINET LOCATED IN THE DISTRICT 4

HEADQUARTERS EQUIPMENT ROOM. THE VENDOR SHALL RETURN THE RADIOS TO DISTRICT 4 HEADQUARTERS PERSONNEL.

3. THE VENDOR SHALL FURNISH AND INSTALL A KATHREIN-SCALA PR-950 GRID ANTENNA ON A 10-FOOT PIPE TO BE MOUNTED WHERE THE DB201

ANTENNA WAS REMOVED. THE GRID ANTENNA SHALL BE CONFIGURED FOR HORIZONTAL POLARIZATION AND ALIGNED WITH THE FDOT

MCARTHUR TOWER SITE (AZIMUTH: APPROXIMATELY 203.9 DEGREES). SEE SHEETS IT-4 AND IT-5.

THE VENDOR SHALL REUSE THE DB224 ANTENNA AND ASSOCIATED TRANSMISSION LINE FOR THE VHF HIGH BAND TRANSMISSION SYSTEM.

4. THE VENDOR SHALL REMOVE THE EXISTING IN-LINE SURGE PROTECTIVE DEVICES (SPDS) MOUNTED TO THE GROUND BUS BAR INSIDE THE

DISTRICT 4 HEADQUARTERS EQUIPMENT ROOM AND RETURN TO DISTRICT 4 HEADQUARTERS PERSONNEL.

THE VENDOR SHALL FURNISH AND INSTALL NEW SPDS FOR THE TRANSMISSION LINES. THE VENDOR INSTALL A POLYPHASER TSX-DFM-BF

FOR THE 960 MHZ LINK ASSOCIATED WITH THE NEW GRID ANTENNA. THE VENDOR SHALL INSTALL A POLYPHASER VHF50HD-MA FOR THE VHF

HIGH BAND ASSOCIATED WITH THE EXISTING DB224 ANTENNA. THE VENDOR SHALL PROVIDE SUITABLE HARDWARE FOR THE PROPER

MOUNTING OF THE SPDS TO THE GROUND BUS BAR.

5. THE VENDOR SHALL INSTALL A FDOT PROVIDED BIRD/TX-RX DUPLEXER AND A FDOT PROVIDED MIDLAND BASETECH III REPEATER IN THE

EXISTING CABINET LOCATED IN THE DISTRICT 4 HEADQUARTERS EQUIPMENT ROOM. THE VENDOR SHALL CONNECT THE TRANSMISSION LINE

ASSOCIATED WITH THE DB224 ANTENNA TO THE DUPLEXER. THE VENDOR SHALL CONNECT THE DUPLEXER TO THE REPEATER AND

CONFIGURE, VERIFY, AND/OR OPTIMIZE THE DUPLEXER AND REPEATER FOR THE FOLLOWING FREQUENCIES: TX: 154.68 MHZ, RX: 156.24 MHZ.

THE FDOT IS LICENSED TO OPERATE ON THIS FREQUENCY UNDER CALL SIGN WQXV737. THE VENDOR SHALL CONFIGURE THE RECEIVE AND

TRANSMIT CTCSS TONES TO BE 151.4 HZ.

THE VENDOR SHALL CONFIGURE AND PROGRAM THE BASETECH III 2020 BOARD IN ACCORDANCE WITH FDOT SPECIFICATIONS THAT WILL BE

PROVIDED TO THE VENDOR.

6. THE VENDOR SHALL FURNISH AND INSTALL A 12VDC 4RF APRISA XE MICROWAVE RADIO IN THE SAME CABINET AS THE REPEATER. THE

VENDOR SHALL CONNECT THE APRISA XE MICROWAVE RADIO TO THE TRANSMISSION LINE ASSOCIATED WITH THE GRID ANTENNA. THE

VENDOR SHALL CONFIGURE THE APRISA XE MICROWAVE RADIO FOR THE FOLLOWING FREQUENCIES: TX: 933.375 MHZ, RX: 942.375 MHZ. THE

FDOT IS LICENSED TO OPERATE ON THIS FREQUENCY UNDER CALL SIGN WQYG790.

THE VENDOR SHALL CONFIGURE THE APRISA XE WITH THE FOLLOWING NETWORK ADDRESS:

IP ADDRESS: 172.16.17.21

SUBNET MASK: 255.255.254.0

DEFAULT GATEWAY: 172.16.17.19

7. THE VENDOR SHALL WIRE A 4-WIRE E&M CONNECTION BETWEEN THE APRISA XE AND THE BASETECH III 2020 BOARD. THE VENDOR SHALL

INSTALL TWO (2) FDOT PROVIDED 4-WIRE VF SPDS FOR THIS CONNECTION BETWEEN THE APRISA XE AND THE BASETECH III 2020 BOARD. THE

VENDOR SHALL FURNISH AND INSTALL AN APPROPRIATELY SIZED DIN RAIL TO BE INSTALLED IN THE EQUIPMENT CABINET WHERE THE SPDS

WILL BE MOUNTED TO. THE DIN RAIL SHALL BE DR24500 OR APPROVED EQUIVALENT AND SHALL BE SECURELY BONDED TO THE EQUIPMENT

CABINET.

MCARTHUR NOTES:

2. THE VENDOR SHALL INSTALL TWO (2) KATHREIN-SCALA PR-950 GRID ANTENNAS WITH 7/8-INCH COAXIAL TRANSMISSION LINE FOR EACH

ANTENNA. SEE SHEET IT-7 FOR TOWER LOADING DETAILS.

3. THE COAXIAL TRANSMISSION LINE SHALL BE HOISTED UP THE TOWER USING APPROPRIATELY SIZED HOISTING GRIPS. USING THE FLANGES

AND CONNECTORS TO LIFT THE TRANSMISSION LINE IS PROHIBITED. THE HOISTING GRIPS SHALL BE SECURED TO THE TOWER AND PROVIDE

SUPPORT FOR THE COAXIAL TRANSMISSION LINE.

4. ALL COAXIAL TRANSMISSION LINES SHALL BE MOUNTED AND SECURED TO THE TOWER, VERTICAL TRANSMISSION LINE LADDER, AND

HORIZONTAL TRANSMISSION LINE BRIDGE WITH APPROPRIATELY SIZED STAINLESS STEEL BOLT-ON HANGERS AND HARDWARE. SNAP-ON AND

‘TWIST-TIE’ HANGERS WILL NOT BE PERMITTED. THE HANGERS SHALL BE SPACED WITH A MAXIMUM SEPERATION OF 36 IN. ON CENTER.

5. ALL COAXIAL TRANSMISSION LINES SHALL BE GROUNDED TO THE TOWER AND BULKHEAD AT A MINIMUM OF FOUR (4) LOCATIONS PER THESE

SPECIFICATIONS: 1.) TOP OF TRANSMISSION LINE SYSTEM, 2.) MIDDLE OF TRANSMISSION LINE SPAN 3.) BASE OF THE TOWER WHERE

TRANSITION IS MADE TO THE HORIZONTAL TRANSMISSION LINE BRIDGE (TOWER BASE GROUND BUS BAR), AND 4.) AT THE TRANSMISSION

LINE BULKHEAD PRIOR TO ENTERING THE COMMUNICATIONS BUILDING.

6. THE VENDOR SHALL INSTALL THE COAXIAL TRANSMISSION LINES IN THE SPECIFIED ENTRY PORTS ON SHEET IT-8. ALL COAXIAL

TRANSMISSION LINES SHALL BE EQUIPPED WITH SPDS PER THESE SPECIFICATIONS. ALL SPDS SHALL BE CONNECTED DIRECTLY TO THE

BULKHEAD UPON ENTERING THE COMMUNICATIONS BUILDING. THE SPDS SHALL BE POLYPHASER MODEL TSX-DFM-BF.

7. THE COAXIAL TRANSMISSION LINES SHALL BE SECURED TO THE OVERHEAD CABLE TRAYS INSIDE THE COMMUNICATIONS BUILDING IN

ACCORDANCE WITH THE MCARTHUR COMMUNICATIONS BUILDING PLANS. SEE SHEET IT-8.

8. THE VENDOR SHALL FURNISH AND INSTALL TWO (2) NEW JPS INTEROPERABILITY SOLUTIONS SVM-2 CARDS IN PORTS 7 & 8 OF THE JPS SNV-12

(VOTER) CHASSIS LOCATED IN THE CHANNEL BANK RACK. PORT 7 SHALL BE USED FOR THE LINK TO DISTRICT 4 HEADQUARTERS, AND PORT 8

SHALL BE USED FOR THE LINK TO BROWARD OPS.

MCARTHUR NOTES (CONT’D):

9. THE VENDOR SHALL INSTALL TWO (2) NEW -48VDC 4RF APRISA XE MICROWAVE RADIOS IN THE CHANNEL BANK RACK. SEE SHEET IT-8. THE

MAINTENANCE CONTRACTOR, TRANSCORE, WILL BE RESPONSIBLE FOR CONNECTING EACH APRISA XE TO THE -48VDC FUSE PANEL IN THE

CHANNEL BANK RACK. THE FDOT IS LICENSED TO OPERATE ON THE FOLLOWING FREQUENCIES UNDER CALL SIGN WQYG789.

THE VENDOR SHALL CONFIGURE THE APRISA XE MICROWAVE RADIO FOR THE LINK TO DISTRICT 4 HEADQUARTERS FOR THE FOLLOWING

FREQUENCIES: TX: 942.375 MHZ, RX: 933.375 MHZ, HORIZONTAL POLARIZATION. THE VENDOR SHALL CONFIGURE THE APRISA XE MICROWAVE

RADIO WITH THE FOLLOWING NETWORK ADDRESS:

IP ADDRESS: 172.16.17.20

SUBNET MASK: 255.255.254.0

DEFAULT GATEWAY: 172.16.17.19

THE VENDOR SHALL CONFIGURE THE APRISA XE MICROWAVE RADIO FOR THE LINK TO BROWARD OPS FOR THE FOLLOWING FREQUENCIES:

TX: 943.375 MHZ, RX: 934.375 MHZ, VERTICAL POLARIZATION. THE VENDOR SHALL CONFIGURE THE APRISA XE MICROWAVE RADIO WITH THE

FOLLOWING NETWORK ADDRESS:

IP ADDRESS: 172.16.17.30

SUBNET MASK: 255.255.254.0

DEFAULT GATEWAY: 172.16.17.19

10. THE VENDOR SHALL WIRE A 4-WIRE E&M CIRCUIT FROM THE 4-WIRE E&M PORT 1 ON THE APRISA XE FOR THE DISTRICT 4 HEADQUARTERS

LINK TO A VENDOR PROVIDED AND INSTALLED EDCO MI-50 PUNCHBLOCK EQUIPPED WITH A EDCO MGB GROUND RAIL. THE VENDOR SHALL

INSTALL TWO (2) EDCO HDE SPDS ON THE PUNCHBLOCK, AND WIRE TO PORT 7 OF THE VOTER. THE VENDOR SHALL APPROPRIATELY LABEL

THE CIRCUIT.

THE VENDOR SHALL WIRE A 4-WIRE E&M CIRCUIT FROM THE 4-WIRE E&M PORT 1 ON APRISA XE FOR THE BROWARD OPS LINK TO A VENDOR

PROVIDED AND INSTALLED EDCO MI-50 PUNCHBLOCK EQUIPPED WITH A EDCO MGB GROUND RAIL. THE VENDOR SHALL INSTALL TWO (2)

EDCO HDE SPDS ON THE PUNCHBLOCK, AND WIRE TO PORT 8 OF THE VOTER. THE VENDOR SHALL APPROPRIATELY LABEL THE CIRCUIT.

11. THE VENDOR SHALL WIRE A ETHERNET CIRCUIT FROM THE ETHERNET PORT 1 ON THE APRISA XE FOR THE DISTRICT 4 HEADQUARTERS LINK

TO PORT 7 OF THE BPS 2000 LOCATED IN THE PASSPORT 15K RACK, WITH ETHERNET SPDS IN EACH RACK. THE SPDS SHALL BE MODEL

ZB24596. THE VENDOR SHALL WIRE A ETHERNET CIRCUIT FROM THE ETHERNET PORT 1 ON THE APRISA XE FOR THE BROWARD OPS LINK TO

PORT 8 OF THE BPS 2000 LOCATED IN THE PASSPORT 15K RACK, WITH ETHERNET SPDS IN EACH RACK. THE SPDS SHALL BE MODEL ZB24596.

BROWARD OPS NOTES:

1. THE VENDOR SHALL REMOVE AND PROPERLY DISPOSE OF THE TWO (2) DB201 ANTENNAS. THE VENDOR SHALL LEAVE COAXIAL

TRANSMISSION LINES IN PLACE TO BE REUSED. THE VENDOR SHALL RETURN THE DB201 ANTENNA TO BROWARD OPS PERSONNEL. SEE

SHEET IT-9.

2. THE VENDOR SHALL REMOVE TWO (2) MIDLAND BASETECH RADIOS FROM THE CABINET LOCATED IN THE RADIO EQUIPMENT ROOM, AND

RETURN TO BROWARD OPS PERSONNEL. SEE SHEET IT-9.

3. THE VENDOR SHALL FURNISH AND INSTALL A NEW COMTELCO VHF HIGH BAND ANTENNA MODEL BS150XL3-B TO BE INSTALLED AT THE TOP OF

THE TOWER AFFIXED TO THE WEST SIDE OF THE WAREHOUSE BUILDING. THE VENDOR SHALL REUSE THE 1/2-INCH COAXIAL TRANSMISSION

LINE THAT WAS ASSOCIATED WITH THE DB201 ANTENNA MOUNTED TO THE TOP OF THE TOWER.

4. THE VENDOR SHALL FURNISH AND INSTALL A NEW KATHREIN-SCALA PR-950 GRID ANTENNA ON THE TOWER, NOT MORE THAN 10-FEET ABOVE

THE ROOF LINE. THE GRID ANTENNA SHALL BE CONFIGURED FOR VERTICAL POLARIZATION AND ALIGNED WITH THE GRID DISH AT THE FDOT

MCARTHUR SITE (AZMIUTH: APPROXIMATELY 225 DEGREES).

THE VENDOR SHALL RELOCATE THE COAXIAL TRANSMISSION LINE ASSOCIATED WITH THE DB201 ANTENNA REMOVED FROM THE WALL

MOUNT TO THE NEW GRID ANTENNA ON THE TOWER. SEE SHEET IT-9.

5. THE VENDOR SHALL INSTALL A FDOT PROVIDED BASETECH III VHF HIGH BAND TRANSMITTER IN THE EXISTING CABINET. THE VENDOR SHALL

CONNECT THE BASETECH III TO THE TRANSMISSION LINE ASSOCIATED WITH THE NEW COMTELCO ANTENNA. THE VENDOR SHALL

CONFIGURE THE BASETECH III AS A SIMPLEX STATION, AND CONFIGURE THE BASETECH III FOR THE FOLLOWING FREQUENCIES:

TX: 154.92 MHZ, RX: 154.92 MHZ. THE FDOT IS LICENSED TO OPERATE ON THIS FREQUENCY UNDER CALL SIGN KIB482.

THE VENDOR SHALL CONFIGURE AND PROGRAM THE BASETECH III 2020 BOARD IN ACCORDANCE WITH FDOT SPECIFICATIONS THAT WILL BE

PROVIDED TO THE VENDOR.

6. THE VENDOR SHALL FURNISH AND INSTALL A 4RF APRISA XE MICROWAVE RADIO IN THE EXISTING CABINET. THE VENDOR SHALL CONNECT

THE APRISA XE MICROWAVE RADIO TO THE TRANSMISSION LINE ASSOCIATED WITH THE GRID ANTENNA. THE VENDOR SHALL CONFIGURE THE

APRISA XE MICROWAVE RADIO FOR THE FOLLOWING FREQUENCIES: TX: 934.375 MHZ, RX: 943.375 MHZ. THE FDOT IS LICENSED TO OPERATE

ON THIS FREQUENCY UNDER CALL SIGN WQYG788.

THE VENDOR SHALL CONFIGURE THE APRISA XE WITH THE FOLLOWING NETWORK ADDRESS:

IP ADDRESS: 172.16.17.31

SUBNET MASK: 255.255.254.0

DEFAULT GATEWAY: 172.16.17.19

7. THE VENDOR SHALL WIRE A 4-WIRE E&M CONNECTION BETWEEN THE APRISA XE AND THE BASETECH III 2020 BOARD. THE VENDOR SHALL

INSTALL TWO (2) FDOT PROVIDED 4-WIRE VF SPDS FOR THIS CONNECTION BETWEEN THE APRISA XE AND THE BASETECH III 2020 BOARD. THE

VENDOR SHALL FURNISH AND INSTALL AN APPROPRIATELY SIZED DIN RAIL TO BE INSTALLED IN THE EQUIPMENT CABINET WHERE THE SPDS

WILL BE MOUNTED TO. THE DIN RAIL SHALL BE DR24500 OR APPROVED EQUIVALENT AND SHALL BE SECURELY BONDED TO THE EQUIPMENT

CABINET.

42 of 50

IT-4

SHEET NO.District 4 high band

voter network

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

DISTRICT 4

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

4RF Aprisa XE

4RF Aprisa XE172.16.17.30

4RF Aprisa XE

PR-950 Paraflector

PolyPhaserTSX-DFM-BF

PolyPhaserTSX-DFM-BF

DIN-F

DIN-M

DIN-F

DIN-M

N-M

N-MN-M

1/2” Superflex1/2” Superflex

7/8" Foam-Filled7/8" Foam-Filled

District 4 HQ McArthur

DIN-MDIN-F

DIN-MDIN-F

1/2” Superflex

4-Wire E&M Port 1

4-Wire E&M Port 1

N-M

PR-950 Paraflector

Four (4) 4-Wire VF SPD Edco HDE

To Voter Port 8

4RF Aprisa XE

DIN-F

N-M

N-M

4-WireAudio

1/2” Superflex

DIN-M

(2) 4-Wire VF SPDASC90976

4-Wire E&MPort 1

1/2” Superflex

DB-224

N-M

1/2” Plenum-Rated Foam (Equipment Room to Roof)

VHF High Band Basetech 3(repeater configuration)

1/2” Superflex

N-F

1/2” Superflex

VF

PR-950 Paraflector

1/2” Plenum-Rated Foam

Duplexer

1/2” Superflex

172.16.17.21

172.16.17.20

172.16.17.31

Call Sign: WQYG789Tx: 943.375 MHzRx: 934.375 MHzVertical Polarization

Call Sign: WQYG790Tx: 933.375 MHzRx: 942.375 MHzHorizontal Polarization

Call Sign: WQYG789Tx: 942.375 MHzRx: 933.375 MHzHorizontal Polarization

PolyPhaserVHF50HD-MA

DIN-MDIN-F

DIN-F

DIN-M

1/2” Superflex

N-M

N-M

1/2” Superflex

(2) 4-Wire VF SPDASC90976

4-Wire E&M Port 1

4-WireAudio

1/2” Superflex

BS150XL3-B

N-M

1/2" Foam

VHF High Band Basetech 3

(simplex configuration)

Broward OPS

1/2” Superflex

PR-950 Paraflector

DIN-MDIN-F

N-M

Call Sign: WQYG788Tx: 934.375 MHzRx: 943.375 MHzVertical Polarization

DIN-F

DIN-M

DIN-MDIN-F

1/2" Foam

PolyPhaserVHF50HD-MA

PolyPhaserTSX-DFM-BF

DIN-M

DIN-F

PolyPhaserTSX-DFM-BF

Ethernet Port 1

Ethernet Port 1

BPS 2000(Passport 15k Rack)

Ethernet SPDZB24596

Ethernet SPDZB24596

Call Sign: KIB482Tx: 154.92 MHzRx: 154.92 MHz

Call Sign: WQXV737Tx: 154.68 MHzRx: 156.24 MHz

TO BE FURNISHED AND INSTALLED

FDOT PROVIDED &VENDOR INSTALLED

EXISTING TO BE REUSED

LEGEND

N-M

N-M

N-M

N-M

BPS 2000 Port 7 BPS 2000 Port 8

12VDC Power

-48VDC Power -48VDC Power

12VDC Power

To Voter Port 7

Punchblock

43 of 50

Approximate EquipmentRoom Location (on 3rd Floor)

X

Existing 1/2” transmission

lines protrude roof here

Roof Appurtenances and Dimensions

3400 Commercial Boulevard

District 4 Headquarters

Removals and Additions

IT-5

SHEET NO.District 4

headquarters ROOF

appurtenances

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BROWARD OPS

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

Approximate EquipmentRoom Location (on 3rd Floor)

X

Inner parapet wall(+ 15' above roof line)

DB-224

300'

DB-224

48'

29'

PR-950(Azimuth: 203.9 degrees to McArthur Tower)

73'

73'

48'

Outer Parapet Wall/Edge of Building

Outer Parapet Wall/Edge of Building

DB-201

Inner parapet wall(+ 15' above roof line)

PARKING LOT

COMMERCIAL BOULEVARD

NOTES:

1. THE VENDOR SHALL GROUND THE NEW 1/2-INCH SUPERFLEX COAXIAL CABLE TO THE DISTRICT

4 HEADQUARTERS EXISTING GROUNDING SYSTEM.

2. THE VENDOR SHALL USE BEST PRACTICES AND SECURE THE TRANSMISSION LINE SO THAT IT

IS NOT LOOSELY HANGING. SNAP ON HANGERS AND ‘TWIST TIES’ ARE NOT PERMITTED.

44 of 50

IT-6

SHEET NO.DISTRICT 4 HQ

EQUIPMENT ROOM AND

cabinet details

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

DISTRICT 4 HQ

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

ELECTRICALROOM

EQUIPMENTROOMAND

STORAGE

MIDLANDCABINET

Ground/Bus Bar

*IS-PLDO-120US15A

MIDLANDCABINET

(Remove/Return to Spares)

MIDLANDCABINET

(Add/Install) (FDOT Provided)

IS-PLDO-120US15A*

NOTES:

1. REMOVE AND RETURN TO SPARES INVENTORY TWO (2) MIDLAND BASETECH TRANSMITTERS.

2. INSTALL AND CONFIGURE ONE (1) FDOT PROVIDED MIDLAND BASETECH III. THE VENDOR SHALL

PROGRAM AND CONFIGURE THE BASETECH III 2020 BOARD IN ACCORDANCE WITH FDOT

SPECIFICATIONS WHICH SHALL BE PROVIDED TO THE VENDOR. THE VENDOR SHALL COORDINATE WITH

THE FDOT PROJECT MANAGER FOR THIS PROCEDURE.

3. INSTALL AND CONFIGURE ONE (1) FDOT PROVIDED DUPLEXER.

4. REMOVE AND RETURN TO SPARES INVENTORY TWO (2) POLYPHASER LIGHTNING ARRESTORS.

5. INSTALL TWO (2) NEW LIGHTNING ARRESTORS IN PLACE OF THE OLD PARTS. THE VENDOR INSTALL A

POLYPHASER TSX-DFM-BF FOR THE 960 MHZ TRANSMISSION LINE ASSOCIATED WITH THE NEW GRID

ANTENNA. THE VENDOR SHALL INSTALL A POLYPHASER VHF50HD-MA FOR THE VHF HIGH BAND

TRANSMISSION LINE ASSOCIATED WITH THE EXISTING DB224 ANTENNA.

6. FURNISH, INSTALL AND CONFIGURE A NEW 900 MHZ 4RF APRISA XE.

7. INSTALL TWO (2) FDOT PROVIDED VOICE FREQUENCY SPDS TO PROTECT THE AUDIO CIRCUIT BETWEEN

THE NEW BASETECH III 2020 BOARD AND THE 4-WIRE E&M PORT OF THE APRISA XE ON A VENDOR

FURNISHED AND INSTALLED DIN RAIL.

* POLYPHASER 120 VAC/15A SURGE PROTECTION BETWEEN HOUSE POWER/UPS AND MIDLAND POWER

SUPPLY – REMAINS IN-PLACE.

71-2020AX-1 SPL Tone Remote Termination 71-2020AX-1 SPL Tone Remote Termination

4RF Aprisa XE

Duplexer

EQUIPMENT REMOVAL PLANS EQUIPMENT INSTALLATION PLANS

MIDLANDCABINET

MIDLANDCABINET

45 of 50

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

IT-7

SHEET NO.MCARTHUR

TOWER Loading

Details

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

MCARTHUR

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

MCARTHUR - PROPOSED TOWER LOADING DETAIL

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

S

T

LEG B

130º

LEG C

250º

LEG A

10º

R

A

R

B

C

DE

FG

H

IJ

K

M

N

O

P

Q

R

L

20'

40'

60'

80'

100'

120'

140'

160'

180'

200'

0'

220'

233'

LEG A

10º

ID MODELMTG.

HGT.

LEG/

FACE

APIPE W/

LIGHTNING ROD

240'

(BASE)B

B DB-201234'

(BASE)C

CRED/WHITE

BEACON

230'

(BASE)C

D ASP705K228'

(BASE)A

E ASP705K223'

(BASE)B

F DB-225-2207', 206'

(C.L.)A, B

GCOMPROD

531-70

211'

(BASE)C

H DA8-65193'

(C.L.)C

I ASP705185'

(BASE)B

J ASP705K183'

(BASE)A

K PA8-65180'

(C.L.)C

L DB-225-2177', 176'

(C.L.)A,B

AZIM.

-

-

-

-

-

-

-

212.2°

-

-

272.0°

-

NOTES

-

-

-

-

-

-

-

-

-

-

-

-

M PA8-65158'

(C.L.)A

N DB-420154'

(BASE)C

O DA8-65144'

(C.L.)C

P PA8-65131'

(C.L.)C

Q SIDE MARKERS (2)116'

(C.L.)A,C

22.9°

-

212.2°

-

-

-

-

-

-

-

TX LINE

-

7/8"

-

1-1/4"

7/8"

7/8"

7/8"

WE65

1-1/4"

1-1/4"

EW63

7/8"

WE65

7/8"

WE65

EW63

-

R CAMERA114'

(C.L.)C - -

VIDEO

CABLE

SKATHREIN-SCALA

PR-950

110'

(C.L.)A 23.9° 1,2,37/8"

TKATHREIN-SCALA

PR-950

100'

(C.L.)A 45° 1,2,47/8"

120° TYP

10º

LEG B

LEG C

LEG A

TOWER AXIS

N

NOTES:

1. THE VENDOR SHALL FURNISH AND INSTALL TWO (2) NEW KATHREIN-SCALA PR-950 GRID

ANTENNAS. THE VENDOR IS RESPONSIBLE FOR ALL MOUNTING AND GROUNDING

HARDWARE.

2. NEW 7/8-INCH COAXIAL TRANSMISSION LINE SHALL BE RFS LCF78-50J

3. ANTENNA TO DISTRICT 4 HEADQUARTERS CONFIGURED FOR HORIZONTAL

POLARIZATION.

4. ANTENNA TO BROWARD OPS CONFIGURED FOR VERTICAL POLARIZATION.

TO BE FURNISHED AND INSTALLED

LEGEND

46 of 50

NM

S/

DA

CC

s R

ack

47 MH

zR

epeater R

ack

Channel B

ank R

ack

-48 VD

CR

ectifier R

ack

Passport15KR

ack

IT-8

SHEET NO.MCARTHUR

COMMUNICATIONS

SHELTER DETAILS

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

MCARTHUR

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

-48 VDCBattery Bank

ITS W

AN

R

ack

GENERATOR

ROOM

MCARTHUR – SHELTER FLOORPLAN

Harris

Constellation

Rack

MCARTHUR – ENTRY PORT DETAIL EXTERIOR VIEW

NOTES:

1. THE APPROXIMATE LOCATION OF THE EQUIPMENT IS FOR DIAGRAMMATICAL PURPOSES ONLY. THE VENDOR IS RESPONSIBLE FOR

DETERMINING THE BEST LOCATIONS FOR ALL ASSOCIATED CONDUITS AND MOUNTING AND GROUNDING HARDWARE.

2. THE VENDOR SHALL INSTALL THE NEW COAXIAL TRANSMISSION LINES IN THE SPECIFIED ENTRY PORTS WITH NEW BOOT ASSEMBLIES.

THE COAXIAL TRANSMISSION LINES SHALL BE GROUNDED TO THE TRANSMISSION LINE BULKHEAD UPON ENTERING THE SHELTER.

3. THE VENDOR SHALL INSTALL THE NEW SURGE PROTECTIVE DEVICES (SPD) FOR THE COAXIAL TRANSMISSION LINES DIRECTLY ON THE

INTERIOR TRANSMISSION LINE BULKHEAD. THE SPDS SHALL BE POLYPHASER MODEL TSX-DFM-BF.

4. THE VENDOR SHALL ROUTE THE NEW COAXIAL TRANSMISSION LINES ALONG THE OVERHEAD CABLE TRAYS, PARALLEL TO THE

EXISTING UHF COAXIAL TRANSMISSION LINES TO THE CHANNEL BANK RACK. THE VENDOR SHALL SECURE THE TRANSMISSION LINES

TO THE OVERHEAD CABLE TRAYS WITH ZIP TIES, AT 36 IN. INTERVALS, MAXIMUM.

5. THE VENDOR SHALL FURNISH AND INSTALL TWO (2) NEW 4RF APRISA XE MICROWAVE RADIOS IN THE CHANNEL BANK RACK.

6. THE VENDOR SHALL FURNISH AND INSTALL ONE (1) 66MI-50 PUNCHBLOCK ON THE EXISTING TELCO BOARD ON THE WEST WALL. THE

VENDOR SHALL FURNISH AND INSTALL ONE (1) EDCO MGB GROUND RAIL ON THE PUNCHBLOCK, AND MECHANICALLY GROUND THE

PUNCHBLOCK TO THE INTERIOR GROUND RING USING MANUFACTURER’S RECOMMENDATIONS.

7. FIRST, THE VENDOR SHALL CONFIGURE THE SNV-12 VOTER IN ACCORDANCE WITH FDOT SPECIFICATIONS. THE VENDOR SHALL

COORDINATE WITH THE FDOT PROJECT MANAGER FOR THIS PROCEDURE. THEN, THE VENDOR SHALL FURNISH AND INSTALL TWO (2)

NEW SVM-2 VOTER CARDS IN PORTS 7 & 8 OF THE SNV-12 VOTER CHASSIS LOCATED IN THE CHANNEL BANK RACK. PORT 7 SHALL BE

FOR THE DISTRICT 4 HEADQUARTERS SITE, AND PORT 8 SHALL BE FOR THE BROWARD OPS SITE. THE VENDOR SHALL CONFIGURE THE

SVM-2 CARDS IN ACCORDANCE WITH FDOT SPECIFICATIONS WHICH WILL BE PROVIDED TO THE VENDOR. THE VENDOR SHALL

COORDINATE WITH THE FDOT PROJECT MANAGER FOR THIS PROCEDURE.

8. THE VENDOR SHALL WIRE A 4-WIRE E&M CIRCUIT FROM THE 4-WIRE E&M PORT 1 ON THE APRISA XE FOR THE DISTRICT 4

HEADQUARTERS LINK TO THE NEW PUNCHBLOCK. THE VENDOR SHALL INSTALL TWO (2) EDCO HDE SPDS ON THE PUNCHBLOCK, AND

WIRE TO PORT 7 OF THE VOTER. THE VENDOR SHALL WIRE A 4-WIRE E&M CIRCUIT FROM THE 4-WIRE E&M PORT 1 ON APRISA XE FOR

THE BROWARD OPS LINK TO THE NEW PUNCHBLOCK. THE VENDOR SHALL INSTALL TWO (2) EDCO HDE SPDS ON THE PUNCHBLOCK, AND

WIRE TO PORT 8 OF THE VOTER. THE VENDOR SHALL APPROPRIATELY LABEL EACH CIRCUIT.

9. THE VENDOR SHALL INSTALL FOUR (4) ETHERNET SPDS TO PROTECT THE ETHERNET CIRCUIT BETWEEN EACH APRISA XE MICROWAVE

RADIO AND THEIR RESPECTIVE PORTS ON THE BPS 2000. THE ETHERNET SPDS SHALL BE MODEL ZB24596. TWO (2) SPDS SHALL BE

MOUNTED TO THE EXISTING DIN RAIL LOCATED IN THE CHANNEL BANK RACK TO PROTECT THE APRISA XE MICROWAVE RADIOS. THE

OTHER TWO (2) SPDS SHALL BE MOUNTED TO THE EXISTING DIN RAIL LOCATED IN THE PASSPORT 15K RACK TO PROTECT THE BPS

2000.

10. THE VENDOR SHALL FURNISH AND INSTALL CAT5 ETHERNET CABLE BETWEEN EACH APRISA XE AND THE BPS 2000. THE CAT5

ETHERNET CABLE SHALL BE CUSTOM LENGTH AND ROUTED ALONG THE OVERHEAD CABLE TRAYS, PARALLEL TO EXISTING CAT5

ETHERNET CABLES. THE VENDOR SHALL SECURE THE CAT5 ETHERNET CABLES TO THE OVERHEAD CABLE TRAYS WITH ZIP TIES, AT 36

IN. INTERVALS, MAXIMUM.

MCARTHUR – CHANNEL BANK RACK DETAIL

1/2-INCH SUPERFLEX

TO APRISA XE RADIO

CAT5 ETHERNET

CABLE

ETHERNET SPDS

ETHERNET SPDS

EXISTING EQUIPMENT

LOCATED IN RACK TO

BE USED AS PART OF

THIS PROJECT

SEE CHANNEL BANK

RACK DETAIL

POLYPHASOR

TXS-DFM-BF

FURINISH AND INSTALL 7/8-INCH COAXIAL

TRANSMISSION LINE RFS LCF78-50J IN THE

SPECIFIED PORTS WITH NEW BOOT ASSEMBLY

TO BE FURNISHED AND INSTALLED

LEGEND

NXU-2A

Omnitronics

4RF Aprisa XE

4RF Aprisa XE

SVM-2 CARDS

IN PORT 7 & 8

TWO (2) ETHERNET SPDS

47 of 50

IT-9

SHEET NO.BROWARD OPS

EQUIPMENT ROOM AND

ROOFTOP ANTENNAS

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

BROWARD OPS

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501

T:\Public\ITS\Telecommunications\47_MHz\D4 HQ VHF High Band Project\Spec\D4 High Band Linkage Spec 20160929.vsd

WAREHOUSE BUILDING AT BROWARD OPS5548 NW 9TH AVENUE FT. LAUDERDALE, FL 33309-2804

TWO (2) DB-201s

(one on a foldover mast – see below)

BS150XL3-B

PR-950

Removals and Additions

Remove two (2) DB-201s

Radio Equipment

Room (9' x 12')

MIDLAND

CABINET

(Remove/Return to Spares)

Aprisa XE

MIDLAND

CABINET

(Add/Install) (FDOT Provided)

Roof of 5548 NW 9th Avenue – Ft. Lauderdale

Radio Equipment

Room (9' x 12')

Roof of 5548 NW 9th Avenue – Ft. Lauderdale

New PR-950 and BS150XL3-B(both on ‘fold over’ mast)

Radio Equipment Room

(9' x 12')

Radio Equipment Room

(9' x 12')

Relocate 1/2” transmission

line to mast for new

microwave antenna

45'

62'

45'

62'50'

Nominal height for microwave

antenna: 50' (C.L.) AGL

or 5' above roof line

NOTES:

1. THE VENDOR SHALL REMOVE AND PROPERLY DISPOSE OF THE TWO (2) DB201 ANTENNAS.

2. REMOVE AND RETURN TO SPARES INVENTORY TWO (2) MIDLAND BASETECH TRANSMITTERS.

3. INSTALL AND CONFIGURE ONE (1) FDOT PROVIDED MIDLAND BASETECH III. THE VENDOR

SHALL PROGRAM AND CONFIGURE THE BASETECH III 2020 BOARD IN ACCORDANCE WITH

FDOT SPECIFICATIONS WHICH SHALL BE PROVIDED TO THE VENDOR. THE VENDOR SHALL

COORDINATE WITH THE FDOT PROJECT MANAGER FOR THIS PROCEDURE.

4. REMOVE AND RETURN TO SPARES INVENTORY THE TWO (2) TRANSMISSION LINE LIGHTNING

ARRESTORS.

5. INSTALL TWO (2) NEW LIGHTNING ARRESTORS IN PLACE OF THE OLD PARTS. THE VENDOR

INSTALL A POLYPHASER TSX-DFM-BF FOR THE 960 MHZ TRANSMISSION LINE ASSOCIATED

WITH THE NEW GRID ANTENNA. THE VENDOR SHALL INSTALL A POLYPHASER VHF50HD-MA

FOR THE VHF HIGH BAND TRANSMISSION LINE ASSOCIATED WITH THE NEW COMTELCO

BS115XL3-B.

6. FURNISH, INSTALL AND CONFIGURE A NEW 900 MHZ 4RF APRISA XE.

7. INSTALL TWO (2) FDOT PROVIDED VOICE FREQUENCY SPDS TO PROTECT THE AUDIO

CIRCUIT BETWEEN THE NEW BASETECH III 2020 BOARD AND THE 4-WIRE E&M PORT OF THE

APRISA XE ON A VENDOR FURNISHED AND INSTALLED DIN RAIL.

48 of 50

SHEET NO.

MAJOR EQUIPMENT LIST

STATE OF FLORIDADEPARTMENT OF TRANSPORTATION

DISTRICT 4

SITE NAME FINANCIAL PROJECT IDCOUNTY

BROWARD

CONTRACT PLANS RECORDREV.DATE DESCRIPTION REV.DATE DESCRIPTION

FLORIDA DEPARTMENT OF TRANSPORTATION605 SUWANNEE STREET, MS 90TALLAHASSEE, FL 32399-0450PH.(850)-410-5600FAX.(850)-410-5501 IT-10

MAJOR EQUIPMENT LIST TO BE FURNISHED BY THE VENDOR:

MANUFACTURER

4RF

4RF

4RF

PLOYPHASER

POLYPHASER

KATHREIN-SCALA

COMTELCO

VENDOR SPECIFY

EDCO

EDCO

MTL SURGE TECH

JPS INTEROPERABILITY

RFS

RFS

RFS

RFS

RFS

RFS

DESCRIPTION

APRISA XE 900 MHZ MICROWAVE RADIO -48VDC POWER SUPPLY

APRISA XE 900 MHZ MICROWAVE RADIO 12VDC POWER SUPPLY

APRISA XE 4-WIRE E&M INTERFACE CARD

900 MHZ TX LINE SPD

VHF HIGH BANK TX LINE SPD

900 MHZ GRID ANTENNA

VHF HIGH BAND ANTENNA

66MI-50 PUNCHBLOCK

66MI-50 PUNCHBLOCK GROUND RAIL

4-WIRE VF SPD FOR PUNCHBLOCK

ETHERNET SPD

SITE VOTER MODULE CARDS

7/8-INCH COAXIAL TRANSMISSION LINE

1/2-INCH SUPERFLEXIBLE COAXIAL JUMPER CABLE

7/16 DIN FEMALE CONNECTOR FOR 7/8-INCH COAXIAL CABLE

7/16 DIN MALE CONNECTOR FOR 1/2-INCH SUPERFLEX COAXIAL CABLE

7/16 DIN FEMALE CONNECTOR FOR 1/2-INCH FOAM COAXIAL CABLE

N MALE CONNECTOR FOR 1/2-INCH SUPERFLEX COAXIAL CABLE

MODEL

APXE-N900-200-G2-48-FC

APXE-N900-200-G2-12-FC

APXI-Q4EM

TSX-DFM-BF

VHF50HD-MA

PR-950

BS150XL3-B

VENDOR SPECIFY

MGB

HDE

ZB24596

SVM-2

LCF78-50J

SCF12-50J

VENDOR SPECIFY

VENDOR SPECIFY

VENDOR SPECIFY

VENDOR SPECIFY

QUANTITY

2

2

4

4

2

4

1

1

1

4

4

2

AS NEEDED

AS NEEDED

4

11

7

15

NOTES:

1. THE VENDOR SHALL PROVIDE AND INSTALL THE SPECIFIED ANTENNAS, SPECIFIED COAXIAL CABLES,

MOUNTING APPARATUS, AND INSTALLATION HARDWARE FOR ALL RADIO SYSTEMS. THE VENDOR SHALL BE

RESPONSIBLE FOR FURNISHING ALL OF THE NECESSARY EQUIPMENT, HARDWARE, LABOR, AND INSTALLATION

PROCEDURES TO EFFECT PROPER INSTALLATION OF THE RADIO ANTENNA SYSTEMS.

49 of 50

BID CHECKLIST

(DOES NOT NEED TO BE RETURNED WITH YOUR BID RESPONSE)

This Checklist is provided as a guideline, only, to assist bidders in the preparation of their bid response. Included are some important matters that the bidder should check. This checklist is just a guideline, and is not intended to include all matters required by the ITB. Bidders are responsible to read and comply with the ITB in its entirety.

Check off each the following:

____ 1. The “Bid Sheet” has been filled out completely, signed, and enclosed in the bid response.

____ 2. The Federal Employers Identification Number or Social Security Number has been entered in the space provided.

____ 3. “Drug-Free Workplace Program Certification” form has been read, signed, and enclosed in the bid response, if applicable.

____ 4. “Scrutinized Companies Lists” certification form has been read, signed, and enclosed in the bid response, if applicable (bids of $1 million or more).

____ 5. The Technical Specifications section has been thoroughly reviewed for compliance to the bid requirements.

____ 6. The prices bid have been reviewed for accuracy and all price corrections have been initialed in ink.

____ 7. The www.myflorida.com website has been checked and any Addendums posted have been completed, signed, and included in the bid response.

____ 8. The bid response must be received, at the location specified, on or before the Bid Due Date and Time designated in the ITB.

____ 9. The Scope of Services, Exhibit “A”, has been thoroughly reviewed for compliance to the ITN requirements.

____ 10. On the Lower Left Hand Corner of the Envelope transmitting your bid response, write inthe following information:

Bid No.: ITB-DOT-16/17-9032-CA

Title: Furnish & Install Connection of High Band Radios to the Voted Radio System in District 4

Opening Date & Time: See “TIMELINE” in INTRODUCTION SECTION

50 of 50