Project Management Plan
Team Green - SchedulePRO
Author Justin Roberts
Last Updated 14 December 2011
Document Purpose Describe and reinforce the management
practices of SchedulePRO
Green Team SchedulePRO Management Plan
Page 2
Contents
Program Identification…………………………………………………………………………………………………………..3
Project Outlook …………….……………………………………………………………………………………………………...4
Corporative Management. ……………………………………………………………………………………………………4
Management Approach.…..……………………………………………………………………………………………………5
Tool Utilization …………………………………………………………………………………………………………………..…5
Team Organization ………………………………………………………………………………………………………………..6
Work Breakdown Structure …………………………………………………………………………………………………..11
Major Milestones ………………………………………………………………………………………………………………….12
Progress Reports …………………………………………………………………………………………………………………..13
Green Team SchedulePRO Management Plan
Page 3
1 Program Identification
This document is the Program Management Plan (PMP) for the CS 410 Green Team, also known as
SchedulePRO. This plan discusses the hardware, software, and documentation requirements as they
pertain to each team member. The SchedulePRO team will be responsible for integration, deployment,
testing, and training through this product’s life cycle.
1.1 Program Management Overview
Execution of the Program will be performed in accordance with the standards established by the
planning documents. The documents are the Project Management Plan, Staffing Plan, Marketing Plan,
Funding Plan, Resource Plan, and Risk Management Plan. These plans will outline how SchedulePRO will
be conducted.
Staffing
Plan
Marketing
Plan
Funding
Plan
Resource
Plan
Risk
Management
Plan
Management
Plan
This Program Management Plan describes the management philosophy, program organization,
schedule, and major milestones that serve as the guide for execution of the software development. The
PMP also provides the customer with the information needed to monitor and evaluate the progress of
SchedulePRO’s development.
The following topics will be covered in this plan:
Project outlook
Corporate organization
Tool utilization
Description of responsibilities of each team member by phase
Overview of the work breakdown structure (WBS) and major milestones
Progress reports
Figure 1. Project Plan Outline
Green Team SchedulePRO Management Plan
Page 4
2 Project Outlook
The goal of SchedulePRO is to provide an easy to use tool that efficiently allows a business or
organization to plan meetings while keeping personnel and resource availability in mind. SchedulePRO
will streamline current business practices by replacing the pen and paper and other time consuming
types of planning techniques. SchedulePRO wants to take the grunt work out of coordinating meetings,
allowing a business to focus on the real goal: an effective and well attended event.
The core of SchedulePRO is an optimization algorithm that works on the concepts of best fit, greatest
fitness, and resource and personnel priority. The concept of best fit and fitness is that the meeting
coordinator is given options to choose when the event should be scheduled and how the adjustment of
event parameters can resultantly give the best attendance. It is very hard for a human to efficiently plan
meetings when the number of attendees, resources, and their availabilities become large. The
combination of the previously mentioned concepts guarantees the coordinator has definite options with
adjustable parameters.
SchedulePRO users will interact with the system through a number of user interfaces that facilitate
successful meeting creation. SchedulePRO also includes a custom notification system that enables users
to be notified of events being created that affect them.
3 Corporate Organization
The CS 410 Green team members (the SchedulePRO team) are computer science students at Old
Dominion University. All team activities are under the guidance of Professor Janet Brunelle in support of
requirements for CS 410 Professional Workforce Development.
Green Team SchedulePRO Management Plan
Page 5
The SchedulePRO team has had the consultation of outside advisors through professional interviews as
noted in this document.
4 Management Approach
The success of the SchedulePRO project depends on the ability of the team to effectively solve a
problem inherent in most businesses that schedule meetings in a shared calendar environment. The
SchedulePRO team members are focused on delivering a product that meets the needs of its users.
Positions were selected to influence the professional experience of SchedulePRO team members as well
as their academic and personal interests. The Project Manager manages the day-to-day administration
of the project including the scheduling of meetings, team communication, and overall organization. All
SchedulePRO team members are encouraged to clinch their roles within the structure of their listed
responsibilities.
5 Tool Utilization
The team members of SchedulePRO will mostly use e-mail as the primary means of communication and
will be checked daily by every team member. Weekly meetings are conducted in person at regularly
scheduled intervals and in locations conducive to productivity. Documents will be created and handled
in Microsoft Office formats and posted onto the SchedulePRO website when appropriate.
[ This space intentionally left blank. ]
Green Team SchedulePRO Management Plan
Page 6
6 Team Organization
This section describes the necessary personnel and their various skills required to successfully complete
each phase of the project.
6.1 Phase 1- Implementation of Prototype
Figure 2 Phase 1 Staffing
During Phase 1 the SchedulePRO prototype will be designed and implemented. Phase 1 will require a
Software Lead, three Software Engineers, and GUI Design Expert.
Software Lead
The Software Lead will be needed for 160 hours. The hourly rate of the Project Manager is $15, which
will cost a total of $2,400. The main responsibilities of the Software Lead will be to prepare project
plans, organize team meetings, review project deliverables, and ensure the project stays on schedule.
[ This space intentionally left blank. ]
Green Team SchedulePRO Management Plan
Page 7
Software Engineer
Three Software Engineers will be needed for a total of 384 hours. The hourly rate of a Software
Engineer is $15, which will cost a total of $5,760. The main responsibilities of the Software Engineers
will be to develop, implement, and test the SchedulePRO algorithms and test harness interfaces.
GUI Design Expert
The GUI Design Expert will be needed for 168 hours. The hourly rate of a GUI Design Expert will be $15
for a total cost of $2,520. The main responsibilities of the GUI Design Expert will be to design and
implement our look and feel aesthetics for the coordinator and user interfaces.
6.2 Phase 2- Full Production
In phase 2, the team will complete all development and SchedulePRO and have a market-ready release.
Figure 3 Phase 2 Staffing
Green Team SchedulePRO Management Plan
Page 8
Software Lead
The Software Lead will be needed for 168 hours, at an hourly rate of $45. The total cost for the Project
Manager will be $7,560. The main responsibilities of the Software Lead will be to prepare project plans,
organize team meetings, review project deliverables, and ensure the project stays on schedule and
budget.
Software Engineer
Three Software Engineers will be needed for a total of 288 hours. The hourly rate of a Software
Engineer is $35, which will cost a total of $10,080. The main responsibilities of the Software Engineers
will be to develop and implement the SchedulePRO Engine, shared calendar system interfaces, and
associated algorithms.
Security Expert
A Security Expert will be needed for 112 hours, at an hourly rate of $100. The total cost of the Security
Expert will be $11,200. The Security Expert will be in charge of ensuring our product maintains user
confidentiality in all aspects of networks and communications.
GUI Design Expert
The GUI Design Expert will be needed for 240 hours. The hourly rate of a GUI Design Expert will be $35
for a total cost of $8,400. The main responsibilities of the GUI Design Expert will be to advance the
design and implementation of our look and feel aesthetics for the coordinator and user interfaces.
[ This space intentionally left blank. ]
Green Team SchedulePRO Management Plan
Page 9
Database Expert
The Database Expert will be needed for 112 hours. The hourly rate of the Database Expert will be $100
for a total cost of $11,200. The main duties of the Database Expert will be to finish designing and
implementing the prototype database. The Expert must ensure that database information is uploaded in
the correct format.
6.3 Phase 3- Post Production
In phase 3, the team will support SchedulePRO as it becomes a mature product, including
version and sub-version releases and bug fixes.
Figure 4 Phase 3 Staffing
Software Lead
Green Team SchedulePRO Management Plan
Page 10
The total cost for the Software Lead will be an annual salary of $84,000. The main responsibilities of the
Software Lead will be to prepare project plans, organize team meetings, review project deliverables, and
ensure project stays on schedule and budget.
Software Engineer
Two Software Engineers will be needed for this portion of the product life cycle. The total cost of the
Software Engineers will be $136,000 per year. The main responsibilities of the Software Engineer will be
to implement new features, update software, and testing.
Customer Support
Three Customer Support personnel will be brought on to play the vital role in product assistance to our
newly acquired and prospective customers. The combined annual salaries for these employees will be
$105,000 per year. Named as such, their main role will be telephone support, email support, and the
point of contact for all software issues that may arise.
Web Developer
A Web Developer will be kept on staff during the full life cycle of the product. The total cost for the Web
Developer will be $50,000 per year. The Webmaster will need to be proficient in scripting languages,
CSS, and SQL. The Webmaster will be in charge of maintaining the website.
Procurement Manager
A Procurement Manager will be brought on to be responsible for all aspects of legal documentation,
licensing, and contracting by creating contacts and overseeing the process of licensing. Procurement
Manager total cost will be $50,000 per year.
Green Team SchedulePRO Management Plan
Page 11
7 Work Breakdown Structure:
The Work Breakdown Structure (WBS) is a helpful chart that shows the team plan moving forward. The
chart breaks the project into components that cover a wide arrange of elements. It helps the project
manager secure a path for the project with the most logical steps and helps to determine what is
required. The SchedulePRO team is using Microsoft Project for the work breakdown structure.
Figure 6. Work Breakdown Structure
Green Team SchedulePRO Management Plan
Page 12
8 Major Milestones
The plan is split up among the phases for the development of the project. These phases are considered
milestones, or major improvements and changes, to the project.
8.1 Phase 1
The team enters into phase 1 with their business plans after their proposal for the project has been
approved. The business plan contains internal plans that include:
Requirements
Management
Resources
Staffing
Marketing
Funding
The team at this time has already developed a prototype which includes testing and demonstration of
the project.
8.2 Phase 2
Transitioning into phase 2 from phase 1, the team is getting ready for deployment of the project. The
deployment plans for the project include:
Final Business Plan
Developed product
Beta Testing
User manual for product
Obtaining customers
Proceed with Marketing Plan
Product Website
[ This space intentionally left blank. ]
Green Team SchedulePRO Management Plan
Page 13
8.3 Phase 3
The final phase for the project includes post-deployment. The team has a plan for maintenance,
training, and support of their product to their customers. New feature and bug fix releases will
occur and marketing and sales will continue.
9 Progress Reports
Several different reports will be required throughout the design and development of this project. These
include monthly progress reports, technical reports, budget reports, and reviews. All reports will be sent
to the Project Manager, who will measure the project and ensure the schedule is being maintained.
9.1 Monthly Progress Reports
During the development of our product, a series of reports will be written to keep the Project Manager
up to date with production rate of the team. Reports include progress of the project, peer reviews, self-
evaluation, budget reports, and technical reports.
9.2 Progress Reports
Each month team members will submit a brief report of the individual’s accomplishments. These
reports will be collected and verified by the Project Manager. This will help the manager gauge progress
of the project as a whole. A plan is established and if adjustments are necessary then the manager has
proper documents to make decisions.
[ This space intentionally left blank. ]
Green Team SchedulePRO Management Plan
Page 14
9.3 Peer & Self-Evaluation Reports
To ensure a stable and productive work environment, members will submit their monthly review of their
peers and themselves. They will be reviewed by the Project Manager and handled appropriately. These
reviews will help to keep members focused and goal-oriented.
9.4 Budget Report
The Financial Manager will submit bi-monthly budget reports to the Project Manager. Any budget
changes to the status of the financial plan have to be reported immediately. This will help the team
properly adjust to any changes and help mitigate future problems.
9.5 Technical Report
The software development team will submit reports on any technical issues, errors fixed, resolution
strategies, or any other possible needs for problems that hinder the project. These reports will be
collected and reviewed by the Project Manager.