appendix d - parkland county€¦ · investigation to support the design and construction of the...

70
Acheson Zone 4 Reservoir Expansion – Geotechnical Investigation Parkland County Acheson, AB Project number: 60586018 (433) November 21, 2018 APPENDIX D

Upload: others

Post on 19-Oct-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

  • Acheson Zone 4 Reservoir Expansion – Geotechnical Investigation

    Parkland County Acheson, AB

    Project number: 60586018 (433)

    November 21, 2018

    APPENDIX D

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    Statement of Qualifications and Limitations

    The attached Report (the “Report”) has been prepared by AECOM Canada Ltd. (“AECOM”) for the benefit of the Client (“Client”) in

    accordance with the agreement between AECOM and Client, including the scope of work detailed therein (the “Agreement”).

    The information, data, recommendations and conclusions contained in the Report (collectively, the “Information”):

    is subject to the scope, schedule, and other constraints and limitations in the Agreement and the qualifications contained

    in the Report (the “Limitations”);

    represents AECOM’s professional judgement in light of the Limitations and industry standards for the preparation of

    similar reports;

    may be based on information provided to AECOM which has not been independently verified;

    has not been updated since the date of issuance of the Report and its accuracy is limited to the time period and

    circumstances in which it was collected, processed, made or issued;

    must be read as a whole and sections thereof should not be read out of such context;

    was prepared for the specific purposes described in the Report and the Agreement; and

    in the case of subsurface, environmental or geotechnical conditions, may be based on limited testing and on the

    assumption that such conditions are uniform and not variable either geographically or over time..

    AECOM shall be entitled to rely upon the accuracy and completeness of information that was provided to it and has no obligation to

    update such information. AECOM accepts no responsibility for any events or circumstances that may have occurred since the date

    on which the Report was prepared and, in the case of subsurface, environmental or geotechnical conditions, is not responsible for

    any variability in such conditions, geographically or over time.

    AECOM agrees that the Report represents its professional judgement as described above and that the Information has been

    prepared for the specific purpose and use described in the Report and the Agreement, but AECOM makes no other representations,

    or any guarantees or warranties whatsoever, whether express or implied, with respect to the Report, the Information or any part

    thereof.

    Without in any way limiting the generality of the foregoing, any estimates or opinions regarding probable construction costs or

    construction schedule provided by AECOM represent AECOM’s professional judgement in light of its experience and the knowledge

    and information available to it at the time of preparation. Since AECOM has no control over market or economic conditions, prices

    for construction labour, equipment or materials or bidding procedures, AECOM, its directors, officers and employees are not able to,

    nor do they, make any representations, warranties or guarantees whatsoever, whether express or implied, with respect to such

    estimates or opinions, or their variance from actual construction costs or schedules, and accept no responsibility for any loss or

    damage arising therefrom or in any way related thereto. Persons relying on such estimates or opinions do so at their own risk.

    Except (1) as agreed to in writing by AECOM and Client; (2) as required by-law; or (3) to the extent used by governmental reviewing

    agencies for the purpose of obtaining permits or approvals, the Report and the Information may be used and relied upon only by

    Client.

    AECOM accepts no responsibility, and denies any liability whatsoever, to parties other than Client who may obtain access to the

    Report or the Information for any injury, loss or damage suffered by such parties arising from their use of, reliance upon, or

    decisions or actions based on the Report or any of the Information (“improper use of the Report”), except to the extent those parties

    have obtained the prior written consent of AECOM to use and rely upon the Report and the Information. Any injury, loss or damages

    arising from improper use of the Report shall be borne by the party making such use.

    This Statement of Qualifications and Limitations is attached to and forms part of the Report and any use of the Report is subject to

    the terms hereof.

    AECOM: 2015-04-13

    © 2009-2015 AECOM Canada Ltd. All Rights Reserved.

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    Prepared for:

    Parkland County

    Prepared by:

    Brian Nguyen, P.Eng.

    Geotechnical Engineer

    T: 780-486-7616

    E: [email protected]

    Alex Tam, E.I.T

    Geotechnical Engineer-in-Training

    T: 780-486-7616

    E: [email protected]

    AECOM Canada Ltd.

    101-18817 Stony Plain Road NW

    Edmonton, AB T5S 0C2

    Canada

    T: 780.486.7000

    F: 780.486.7070

    aecom.com

    © 2018 AECOM Canada Ltd.. All Rights Reserved.

    This document has been prepared by AECOM Canada Ltd. (“AECOM”) for sole use of our client (the “Client”) in

    accordance with generally accepted consultancy principles, the budget for fees and the terms of reference agreed

    between AECOM and the Client. Any information provided by third parties and referred to herein has not been

    checked or verified by AECOM, unless otherwise expressly stated in the document. No third party may rely upon this

    document without the prior and express written agreement of AECOM.

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    Table of Contents

    1. Introduction ......................................................................................................................................................... 1

    1.1 General .................................................................................................................................................... 1

    1.2 Scope of work .......................................................................................................................................... 1

    2. Methodology ....................................................................................................................................................... 2

    2.1 Planning and Coordination ...................................................................................................................... 2

    2.2 Geotechnical Desktop Study ................................................................................................................... 2

    2.2.1 Quaternary Geology ................................................................................................................................ 2

    2.2.2 Surficial Geological .................................................................................................................................. 2

    2.2.3 Bedrock Geology ..................................................................................................................................... 2

    2.3 Field investigation .................................................................................................................................... 2

    2.4 Laboratory testing program ...................................................................................................................... 3

    3. Subsurface Condition .......................................................................................................................................... 4

    3.1 General Profiles ....................................................................................................................................... 4

    3.1.1 Topsoil ..................................................................................................................................................... 4

    3.1.2 Silt............................................................................................................................................................ 4

    3.2 Soil Chemistry ......................................................................................................................................... 5

    3.3 Groundwater Conditions .......................................................................................................................... 5

    3.4 Frost Susceptibility................................................................................................................................... 5

    3.5 Frost Penetration ..................................................................................................................................... 6

    3.6 Seismic Considerations ........................................................................................................................... 6

    4. General Site Recommendations ......................................................................................................................... 7

    4.1 General Site Assessment ........................................................................................................................ 7

    4.2 Site Preparation ....................................................................................................................................... 7

    4.3 Excavations and Backfill .......................................................................................................................... 7

    4.4 General Engineered Fill ........................................................................................................................... 8

    4.5 Structural Fill ............................................................................................................................................ 8

    4.6 Bedding ................................................................................................................................................... 8

    5. Reservoir and Pumphouse Building Recommendations ................................................................................... 10

    5.1 General .................................................................................................................................................. 10

    5.2 Shallow Foundations ............................................................................................................................. 10

    5.3 Deep Foundations ................................................................................................................................. 11

    5.3.1 Driven Steel Piles .................................................................................................................................. 11

    5.3.2 Lateral Load Capacity for Piles .............................................................................................................. 12

    5.4 Subsurface Drainage ............................................................................................................................. 13

    5.5 Lateral Earth Pressures ......................................................................................................................... 13

    5.6 Buoyant Uplift ........................................................................................................................................ 14

    5.7 Grading and Drainage ........................................................................................................................... 15

    5.8 Geochemistry Attack on Foundations .................................................................................................... 15

    6. References ....................................................................................................................................................... 16

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    Tables

    Table 2-1: Summary of Field Investigation ..................................................................................................................... 3 Table 2-2: Summary of Field Investigation ..................................................................................................................... 3 Table 3-1: Atterberg Limits of Silt.................................................................................................................................... 4 Table 3-2: Grain Size Analysis of Silt .............................................................................................................................. 4 Table 3-3: Soil Chemistry Summary ............................................................................................................................... 5 Table 3-4: Summary of Groundwater Measurements ..................................................................................................... 5 Table 3-5: Frost Susceptibility ........................................................................................................................................ 6 Table 3-6: Frost Penetration Depth ................................................................................................................................ 6 Table 4-1: Recommended Gradation for Crushed Gravel (Parkland County Engineering Design Standards, Section

    7.4.3) .............................................................................................................................................................................. 8 Table 4-2: Recommended Gradation for Bedding (Parkland County Engineering Design Standards, Section 4.5.7) .... 9 Table 5-1: Design Parameters for Driven Steel Piles ................................................................................................... 11 Table 5-2: Values of nh for Cohesionless Soils

    1 ............................................................................................................ 12

    Appendices

    Appendix A. Testhole Location Plan, Surficial Geology of Alberta, Bedrock Geology of Alberta

    Appendix B. Modified Unified Soil Classification Chart, Explanation of Field and Laboratory Test Data, General

    Statement; Normal Variability of Subsurface Conditions, Testhole Logs

    Appendix C. Laboratory Test Results

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    1

    1. Introduction

    1.1 General

    AECOM Canada Ltd. (AECOM) was contracted by Parkland County to conduct a geotechnical

    investigation to support the design and construction of the Zone 4 reservoir expansion in Acheson, AB.

    The capacity of the reservoir expansion is expected to between 4,000 and 5,000 cubic metres (m3). The

    purpose of this geotechnical investigation was to assess the suitability of the ground conditions of the site

    for the proposed reservoir expansion, and to provide soil parameters for the design and construction of

    the foundations of the proposed water reservoir and pump house. The recommendations provided in this

    report are preliminary, and will need to be reviewed and revised, if warranted. A testhole location plan

    showing the proposed testholes in relation to the proposed reservoir site is included on Figure 1 in

    Appendix A. Testholes logs are included in Appendix B.

    1.2 Scope of work

    The scope of work for this intrusive geotechnical investigation includes the following:

    Planning and co-ordination of the field drilling program, which included site reconnaissance, safety

    planning, utility co-ordination and clearances, logistics planning, and coordination with AECOM

    subcontractors

    Performing a geotechnical desktop study which included a review of available geological maps and

    review of previous geotechnical reports and literature

    Executing the geotechnical field investigation, which included drilling testholes within the footprint of

    the proposed water reservoir expansion area

    Installation of standpipe piezometers in select testholes to monitor groundwater conditions

    Measuring groundwater levels in the standpipes after completion of the field drilling program

    Performing laboratory testing on soil samples for soil classification and to determine engineering

    properties of select soil samples collected during the field investigation

    Completing a geotechnical investigation report, which includes a discussion of the regional geology,

    subsurface conditions, design and construction recommendations, geotechnical risks associated with

    the site, and general site suitability for the proposed reservoir expansion

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    2

    2. Methodology

    2.1 Planning and Coordination

    Drilling operations were executed in accordance with AECOM’s drilling standard operating procedures

    (SOP) to ensure that all work was being completed safely. A job safety analysis (JSA) and task hazard

    analysis (THA) was prepared to identify all hazards during drilling operations.

    Alberta One Call, DigShaw, third party private locators, and Parkland Country were contacted to

    determine the locations of nearby utilities at the proposed site. Additionally, a site reconnaissance was

    completed prior to completing drilling activities to access site access to the proposed reservoir site.

    2.2 Geotechnical Desktop Study

    Prior to the execution of the intrusive geotechnical investigation, a geological desktop study was

    conducted to determine the expected ground conditions at the proposed site. The study area is located in

    Acheson, AB. The following documents were reviewed to determine subsurface geology:

    Quaternary Geology, Central Alberta Map (Shetsen, 1990)

    Surficial Geology of Alberta. (Alberta Geological Survey. Fenton M.M., et. al. 2013.)

    Bedrock Geology of Alberta. Alberta, Geological Survey (Prior G.J., et. al. 2013)

    2.2.1 Quaternary Geology

    Near-surface geology of the project area was compiled from the Quaternary Geology, Central Alberta map

    (Shetsen, 1990). The Acheson area consists of fine sediments lacustrine deposits of silt and clay, up to

    80 m thick; deposited mainly in proglacial lakes. Deposits also include undifferentiated recent clay

    sediments. Quaternary geology of the project area as mapped by Shetsen (1990) is shown on Figure 2

    in Appendix A.

    2.2.2 Surficial Geological

    The surficial geology in the study area is expected to include primarily glaciolacustrine deposits.

    Glaciolacustrine deposits include either deposited sediments consisting of rhythmically fine sand, silt,

    clay, and till, or littoral sediments consisting of well-sorted silty sand, pebbly sand, and minor gravel.

    2.2.3 Bedrock Geology

    Bedrock geology of the project area was compiled from the “Bedrock Geology Map of Alberta” (Prior G.J.,

    et al. (2013)). The bedrock in the project area generally belongs to the non-marine to locally marginal

    marine Horseshoe Canyon Formation, consisting of grey feldspathic clayey sandstone, grey bentonitic

    mudstone and carbonaceous mudstone, concretionary sideritic layers and laterally continuous coal

    seams. This includes white, pedogenically altered sandstone and mudstone. Bedrock geology of the

    project area as mapped by Prior G.J., et al. (2013) is shown on Figure 3 in Appendix A.

    2.3 Field investigation

    The intrusive geotechnical investigation was started on September 14, 2018 and completed on

    September 15, 2018. The investigation included drilling four testholes to depths of 10.3 m below ground

    surface (mBGS) and one testhole drilled to a depth of 29.8 mBGS. Five 50 millimetre (mm) diameter PVC

    standpipe piezometers were installed in all of the testholes. Testhole details are summarized in Table 2-1

    below.

    The soil types were assessed visually in the field and were classified according to the modified unified

    classification system (MUCS) for soils. Standard penetration tests (SPT) were performed in all testholes

    and split spoon and grab samples were retrieved from the testholes at select intervals.

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    3

    Table 2-1: Summary of Field Investigation

    Testhole Number

    Coordinates

    (Northing, Easting)

    Elevation (m)

    Depth

    (mBGS)

    Well Installed

    (Y/N)

    TH18-01 5936736 N, 317738 E 717.5 10.3 Y

    TH18-02 5936729 N, 317711 E 716.9 10.3 Y

    TH18-03 5936711 N, 317740 E 717.2 10.3 Y

    TH18-04 5936704 N, 317717 E 717.0 29.8 Y

    TH18-05 5936690 N, 317692 E 716.6 10.3 Y

    2.4 Laboratory testing program

    Soil samples collected during the site investigation were tested in AECOM’s materials testing laboratory in

    Calgary, Alberta. The laboratory testing included the determination of moisture contents, Atterberg Limits,

    grain size distributions, and soil chemical properties. Soil chemical analysis included tests for pH, soluble

    sulphates, resistivity, and chloride content. The test results are shown on the testhole logs, and are

    presented separately in Appendix C. Laboratory testing consists of the following:

    Table 2-2: Summary of Field Investigation

    Laboratory Test Number of Tests

    Data Location

    Moisture content determination 96 Testhole Locations, Appendix C

    Atterberg limits determination on selected soil samples 5 Testhole Locations, Appendix C

    Grain Size Analysis on selected samples 5 Testhole Locations, Appendix C

    Soil Chemical Testing 3 Testhole Locations, Appendix C

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    4

    3. Subsurface Condition

    3.1 General Profiles

    3.1.1 Topsoil

    Topsoil was encountered at the ground surface in all testholes. The thickness of the topsoil layer was

    50 mm. The topsoil contained some silt and some rootlets. The topsoil was organic, fibrous, moist, and

    was black in color.

    3.1.2 Silt

    Silt was encountered below the topsoil layer in all testholes at this site. The silt was encountered at

    depths ranging from 0.05 to 29.8 mBGS. The thickness of the silt layer ranged from 10.3 to greater than

    29.8 metres (m). The silt layer extended to the termination depths of all testholes during this investigation.

    The silt contained trace to some fine grained sand, and trace to some clay. The silt was occasionally

    oxidized, and brown to light brown in colour.

    Standard Penetration Test (SPT) N-values for the silt ranged from 4 to 37 blows per 300 mm of

    penetration, indicating that the silt was very loose to dense. The average SPT N-value for the silt was 15.

    Moisture content of all silt samples tested varied from 6.9% to 30.9%. Five Atterberg Limits and five grain

    size analyses were completed on the silt. The test results are summarized in Table 3-1 and Table 3-2.

    Table 3-1: Atterberg Limits of Silt

    Testhole Sample

    Number

    Depth

    (mBGS) MUSC

    Liquid

    Limit (%)

    Plastic

    Limit (%)

    Plasticity

    Index (%)

    TH18-01 12 8.35 ML 21.8 19.8 2.0

    TH18-02 10 6.85 ML 24.9 21.8 3.0

    TH18-03 10 6.85 ML 23.8 21.7 2.1

    TH18-04 18 12.85 ML 20.7 19.2 1.6

    TH18-05 6 3.85 ML 31.3 24.0 7.3

    Table 3-2: Grain Size Analysis of Silt

    Testhole Sample

    Number

    Depth

    (mBGS)

    Gravel

    (%)

    Sand

    (%)

    Silt

    (%)

    Clay

    (%)

    TH18-01 12 8.35 0.0 32.0 54.6 13.4

    TH18-02 10 6.85 0.0 17.8 67.8 14.4

    TH18-03 10 6.85 0.0 26.4 61.7 11.9

    TH18-04 18 12.85 0.0 45.0 44.1 10.9

    TH18-05 6 3.85 0.0 2.2 76.0 21.8

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    5

    3.2 Soil Chemistry

    Chemical testing was conducted on select samples to determine pH, resistivity, chlorides content, and

    water soluble sulphate content. The degree of corrosiveness and corrosion potential for sulphate attack

    are provided in Table 3-3 below in accordance to the Handbook of Corrosion Engineering and the

    Canadian Standards Association Guidelines.

    Table 3-3: Soil Chemistry Summary

    Testhole Depth

    (mBGS)

    Soil

    Layer

    Resistivity

    (ohm-cm)

    Chlorides

    Content

    (mg/L)

    Water Soluble

    Sulphate

    Content (%)

    pH Corrosion Potential Sulphate

    Attack

    TH18-01 6.85 Silt 5100

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    6

    Table 3-5: Frost Susceptibility

    Soil Unit USC Finer than 0.02

    mm (%)

    Plasticity Index (%) Frost Group

    Silt ML - - F4

    Generally, the surficial soils at this site were classified in the F4 frost group, which indicates the surficial

    soils are highly susceptible to frost.

    3.5 Frost Penetration

    The surficial soil deposits in the Acheson, AB area are highly susceptible to frost action. The depth of

    frost penetration for soils can be determined using the Canadian Foundation Engineering Manual

    guidelines. The depth of frost penetration for the surficial silt is summarized in Table 3-6.

    Table 3-6: Frost Penetration Depth

    Soil Unit Frost Penetration Depth

    (m)

    Silt 2.8

    The frost penetration depths provided above are based on a uniform soil type with no insulation cover. In

    areas covered with turf or snow cover, the depth of frost penetration will be less. Conversely, if well

    graded granular backfill is used, the depth of frost penetration will be greater. The depth of frost

    penetration is dependent on the in situ moisture content, relative density, grain and pore sizes, and

    permeability of the soil. As a result, frost penetration is expected to vary across the site as the subsurface

    materials and temperatures vary.

    3.6 Seismic Considerations

    The Canadian Foundation Engineering Manual (CFEM 2006) requires that loading due to earthquake

    shaking should be considered as an external load in the design of civil engineering structures. The

    earthquake loading at any given site is related to factors such as subsoil conditions and behaviour,

    magnitude, duration, and frequency content of strong ground motion and the probable intensity and

    likelihood of occurrence of an earthquake (i.e. seismic loads).

    The site soil classification was determined from the energy-corrected average standard penetration test

    value N60 of 16.2 in testhole TH18-04 drilled to a depth of 29.8 mBGS. The site is classified as Class D

    based on the SPT results and according to Table 6.1A in the Canadian Foundation Engineering Manual

    (CFEM, 2006).

    The typical soil profile for a Class D site consists of generally stiff soils with an average standard

    penetration resistance (N60) between 4 and 34 blows.

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    7

    4. General Site Recommendations

    4.1 General Site Assessment

    The proposed reservoir structure will be a reinforced concrete underground structure with the base at an

    approximate depth of 7 m to 8 m below the existing ground surface (EL.710 mASL to 709 mASL). Based

    on the findings of the testholes, the base of the reservoir is expected to be situated within the slightly

    plastic to non-plastic silt.

    Groundwater levels recorded in standpipe piezometers installed at the site ranged from Dry to 16.2

    mBGS after completion of drilling, and ranged from Dry to 17.6 mBGS and Dry to 17.9 mBGS on October

    17, 2018 and November 14, 2018, respectively. However, it is recommended a groundwater depth of

    between 3.0 mBGS (EL.714 mASL) and 6.4 mBGS (EL.710.6 mASL) be used for preliminary design

    purposes as the measured groundwater levels are short term readings only. Additionally, it is

    recommended further groundwater monitoring events be carried out in the upcoming spring season and

    prior to the start of construction.

    The proposed reservoir and pumphouse development is considered feasible at the site, based on

    conditions encountered within the testholes. Geotechnical recommendations for preliminary design of the

    proposed development are included in the sections below.

    4.2 Site Preparation

    The site should be stripped of all topsoil and other deleterious materials from beneath the footprint of the

    proposed reservoir and pumphouse structure. Fill required in establishing design grade elevations should

    consist of imported general engineered fill as discussed in Section 4.4. The soils encountered at this site

    were generally considered not suitable for use as backfill, site grading, or subgrade preparation, as the

    silty soils are unstable when wet, difficult to compact, and highly susceptible to frost heaving.

    4.3 Excavations and Backfill

    Excavations are expected to be required for reservoir and pumphouse foundations and underground

    utility trenches. All excavations should be carried out in accordance with applicable Occupational Health

    and Safety regulations.

    Temporary cut slopes, less than 3.0 m high in silt should have side slopes cut no steeper than 2H:1V.

    Temporary cut slopes exceeding 3.0 m in silt should have side slopes cut no steeper than 3H:1V. Flatter

    short-term cut slopes may be required in localized zones where groundwater seepage is encountered.

    Permanent cut slopes in silt should be set at an inclination no steeper than 4H:1V. If cut slopes were to

    extend below the groundwater table flowing silts and unstable conditions would likely be encountered. In

    such cases, relatively flat excavations of 5H:1V in combination with free-draining gravel buttresses placed

    over a geotextile separator would be required in the seepage zones. The thickness of the free-draining

    material should be at least 500 mm. Based on the subsurface conditions in the testholes, appreciable

    groundwater seepage flow from the sides and the base of the excavation may not be expected. If

    seepage is encountered in the excavation extending through the silt, a new work perimeter drainage ditch

    or another dewatering method will be required. The contractor will be responsible for designing and

    implementing a dewatering system that maintains a dry subgrade.

    Grading should be undertaken so that surface water is not allowed to pond adjacent to the excavation.

    Temporary surcharge loads, such as construction materials and equipment, should not be allowed within

    1.5 m (or the depth of the excavation, whichever is greater) of an unsupported excavated face. Vehicles

    delivering materials should be kept back from the edge of the excavation by at least one-half of the depth

    of excavation. All excavations should be checked regularly for signs of sloughing, especially after periods

    of rain. Small earth or rock falls from the side slopes are a potential source of danger to workers and

    must be guarded against. The base of the excavation should be protected from frost during construction

    of the foundation.

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    8

    4.4 General Engineered Fill

    Unless recommended otherwise, backfill should consist of general engineered fill consisting of low to

    medium plastic clay or clay till. The native silt encountered at site is primarily low plastic, and therefore

    considered not suitable for use as backfill at this site. The general engineered fill should be compacted to

    95% Standard Proctor Maximum Dry Density (SPMDD), and within ± 2% of the Optimum Moisture

    Content (OMC), with the exception of below foundations or floor slabs. All fill placed below foundations,

    floor slabs or other settlement sensitive structures should be compacted to 100% of the SPMDD, and

    within ± 2% of the OMC. Placement of backfill material should not exceed 150 mm in compacted

    thickness. Organic material and frozen soil should not be used as backfill.

    4.5 Structural Fill

    Structural fill should be used under foundations, floor slabs, or any other settlement sensitive structures.

    Structural fill should consist of well graded, crushed gravel with less than 10% fines (silt and clay), and a

    maximum particle size of 20 mm.

    The structural fill should be compacted to 100% of the SPMDD, and within ± 2% of the OMC and placed

    in lifts not exceeding 150 mm in compacted thickness. The structural fill should extend on each side of

    the foundation or floor slab a minimum distance of 500 mm.

    Recommended gradation for crushed gravel is provided in Table 4-1. The supplied material should

    comply with Parkland County Engineering Design Standards.

    Table 4-1: Recommended Gradation for Crushed Gravel (Parkland County Engineering Design Standards,

    Section 7.4.3)

    Metric Sieve (mm)

    Percentage Passing by Mass

    20 100

    16 84 to 95

    12.5 60 to 90

    10 50 to 84

    5 37 to 62

    2 26 to 50

    1.25 19 to 43

    0.630 10 to 25

    0.160 6 to 18

    0.080 2 to 10

    4.6 Bedding

    Bedding should be used under buried pipes, utility services, and insulation. The minimum thickness of the

    bedding material should be 100 mm below and around the pipe, and 300 mm above the pipe. A non-

    woven geotextile fabric should be placed between the foundation soils and the bedding material. The

    bedding layer should be placed as uniformly as possible to the required density, except that loose,

    uncompacted material should be placed under the middle third of the pipe, prior to placement of the pipe.

    Bedding should be compacted to 95% of the SPMDD, and within ± 2% of the OMC, and placed in lifts not

    exceeding 150 mm in compacted thickness, unless otherwise recommended by the manufacturer.

    Typical gradation for bedding is provided in Table 4-2.

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    9

    Table 4-2: Recommended Gradation for Bedding (Parkland County Engineering Design Standards, Section

    4.5.7)

    Metric Sieve (mm)

    Percentage Passing by Mass

    10 100

    5 95 to 100

    2.5 80 to 100

    1.25 50 to 85

    0.63 30 to 65

    0.315 10 to 30

    0.160 2 to 10

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    10

    5. Reservoir and Pumphouse Building Recommendations

    5.1 General

    It is understood that the development will consist of a reservoir structure and a pumphouse. The

    reservoir will be founded at a depth of approximately 7 m to 8 m below grade (EL. 710 mASL to 709

    mASL). Several foundation alternatives are suitable for these structures, including both shallow and deep

    foundations. The foundation type selected depends on foundation depths, expected loads, allowable soil

    bearing capacity, and the groundwater table level.

    5.2 Shallow Foundations

    Shallow foundations are considered feasible for this development, provided these foundation types are

    founded below the frost zone. Raft foundations may be considered suitable for the reservoir structure. It

    is recommended that raft foundations be founded within one soil type to minimize the potential for

    differential settlements.

    Raft foundations may be designed using an allowable net bearing capacity value of 125 KPa and a

    modulus of subgrade reaction, ks, of 13,500 kN/m3 at depths below ground surface of approximately 7 to 8

    mBGS (EL. 710 mASL to 709 mASL).

    Friction between the subgrade and foundation of reservoir structure can be calculated as follows:

    F = σv tan (0.66 φ')

    where:

    F = Friction between base of reservoir and subgrade

    σv = Vertical effective stress on the subgrade

    φ' = Internal friction angle (use 27° for silt)

    The reservoir will be constructed at a depth below the existing grade such that the weight of the

    excavated soil will approach or even be greater than the weight of the structure. Hence a major portion of

    the settlement of the reservoir would be due to the recompression of the base heave which would occur

    during the excavation. For preliminary design purposes, assuming a reservoir depth of about 7 to 8 m

    below grade (EL. 710 mASL to 709 mASL), the total settlement is not expected to exceed 30 mm. This

    settlement will mostly occur through loading during construction rather than long term settlement.

    Differential settlements are typically half to three quarters of the total settlement noted above if rafts are

    supported with relatively uniform subgrade soil. Differential settlements could be highly variable if the

    reservoir structure is supported on different subgrade soils.

    The base of raft excavations should be thoroughly cleaned of all loosened or disturbed soil prior to

    pouring concrete. A lean concrete pad about 75 mm to 100 mm thick may be used to protect the bearing

    surface from disturbance during the period between completion of excavation and casting of the raft

    foundation.

    If a satisfactory bearing surface cannot be attained, a 150 mm thick layer of well graded 20 mm minus

    crushed gravel should be placed and compacted to a minimum of 100% of SPMDD, as discussed in

    Section 4.5.

    Rafts should be adequately reinforced to allow the structure to settle uniformly and maintain structural

    integrity. Flexible connections should be provided from the structure to all connected piping to

    accommodate differential settlements.

    It is anticipated that where pipe connections enter the reservoir or the pumphouse building, additional

    settlement will occur due to the greater thickness of overlying backfill. It is recommended that lean mix

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    11

    concrete be placed beneath the piping within the trench zone at the entrance into the reservoir

    excavation.

    5.3 Deep Foundations

    Based on the subsurface conditions at this location, driven steel “H” piles or closed – end steel pipe piles

    are considered suitable pile types to support the reservoir and pumphouse building foundation loads.

    Drilled cast-in-place concrete piles are not considered at this time due to the presence of slightly plastic to

    non-plastic soils at this site (silt). A temporary casing will be required for the installation of such piles.

    Should drilled cast-in-place concrete piles be considered, recommendations for this foundation type can

    be provided upon request.

    5.3.1 Driven Steel Piles

    If closed – end pipe piles are used, some densification of the silt may be achieved due to displacement

    during driving, resulting in more favourable skin friction values. Driven steel piles may be designed to

    carry compressive loading on the basis of the allowable skin friction and end bearing resistance given in

    Table 5-1 below.

    Table 5-1: Design Parameters for Driven Steel Piles

    Depth

    (m) Soil

    End Bearing Pressure (kPa) Skin Friction (kPa)

    Ultimate Factored Ultimate Factored

    0 to 1.5 Topsoil / Silt - - - -

    1.5 to 16.0 Silt - - 37.5 15

    Below 16.0 Silt 1,000 400 50 20

    The following is recommended for driven steel pile installation:

    For pipe piles, only the exterior surface area of the pile in contact with the soil should be used in the

    calculation of the frictional resistance. For steel H-piles, the surface area should include the exterior

    sides of the two flanges plus twice the depth of the web.

    In calculating frictional resistance for a steel H section, the gross area at the tip may be taken as the

    cross-section of a rectangle bounded by the flanges. For a pipe pile, the gross area may be taken as

    that enclosed by the outer diameter of the pile section.

    The vertical load capacity of steel piles, determined using the recommended shaft friction and end

    bearing parameters, should be limited to no more than cross-sectional area of steel multiplied by

    0.35 fy, where fy is the yield strength of the steel.

    Steel piles should be driven with a piling hammer of appropriate size and rated energy, depending on

    the pile design load requirements. As a guideline, a minimum energy of 300 J per blow per square

    centimetre of steel pile cross sectional area is recommended for lightly loaded piles and 500 J per

    blow per square centimetre of steel pile cross sectional area for heavily loaded piles. The maximum

    driving energy should not exceed 630 J per blow per square centimetre of steel cross-sectional area

    to avoid damage of the pile section.

    To limit structural damage to the pile, piles should not be driven beyond practical refusal, which may

    be taken as 10 to 12 blows per 25 mm penetration for the last 250 mm of penetration for the

    recommended hammer energies. This criterion is a preliminary guide to estimate the size of pile

    driving hammer that may be required for construction.

    The ability of a pile driving hammer to drive the proposed piles to the required capacity should be

    confirmed using wave equation analysis (GRLWEAP software) once the details regarding the

    proposed hammer configuration and the pile size is known. The required termination criteria should

    also be determined using wave equation analysis once the hammer energies, hammer type and pile

    details are known.

    A minimum centre-to-centre pile spacing should be three pile diameters or three pile flange widths.

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    12

    Heave of adjacent piles is a concern where groups of piles are installed at about 3D spacing or less

    and should be monitored throughout the driving. All piles indicating heave should be re-driven.

    When piles are re-driven, they should achieve additional penetration approximately equal to the

    amount of heave originally recorded.

    Prior to the pile installation, the piles should be inspected to confirm that the material specifications

    are satisfied. The piles should be free from protrusions, including protruding welds which could

    create voids in the soil around the pile during driving. If a driving shoe is used, it must not protrude

    beyond the outside diameter of the pile.

    Monitoring of the pile installation by qualified personnel is recommended to verify that the piles are

    installed in accordance with design assumptions. For each pile, a complete pile driving record in

    terms of the number of blows per 250 mm of penetration and the final set of the pile should be

    recorded by inspector and reviewed by the geotechnical engineer.

    The minimum, embedment depth of the piles into the silt to resist frost jacking forces should be

    determined based on the adfreeze stresses and the pile diameter. The ultimate average adfreeze

    stresses acting along the pile shafts and on the sides of the pile caps and grade beams may be taken

    as 65 kPa for the frost penetration depth, which for design purposes may be taken as 2.8 m from

    finished grade. Frost adfreeze stresses exert upward forces on the pile shaft, which are counteracted

    by the dead weight of the structure plus the skin friction below the frost penetration depth.

    5.3.2 Lateral Load Capacity for Piles

    Lateral load capacity will depend on pile stiffness and the geotechnical engineering properties of the

    native or backfill soil within the upper few metres of the pile. Detailed lateral pile capacities can be

    provided once the design grades, pile types, pile layout and nature of the backfill have been determined.

    Lateral pile capacity can be calculated using spring constants called the coefficient of horizontal subgrade

    reaction (ks).

    The following methods of estimating ks have been used successfully where full-scale pile load test data is

    not available. If lateral deflections are the limiting factor in the overall pile design, it is recommended to

    conduct full-scale lateral pile load tests to verify the coefficient of subgrade reaction values for this site.

    For cohesionless soils (sand, silt, and sand and gravel), ks can be estimated using the following equation:

    ks = nh z/d (MN/m3)

    where:

    z = Pile embedment depth (m)

    d = Pile diameter (m)

    The values for the factor nh for cohesionless soils are summarized in the table below.

    Table 5-2: Values of nh for Cohesionless Soils1

    Soil Condition nh (MN/M

    1)

    Above Groundwater Table Below Groundwater Table

    Loose 2.5 1.5

    Compact 7.0 4.5

    Dense 18.0 11.0

    1Values excerpted from Evaluation of Coefficient of Subgrade Reaction (Terzaghi, 1955).

    The soil stratigraphy was generally consistent across the site. Calculations for the coefficient of

    horizontal subgrade reaction along the length of the pile, used in determining lateral pile deformations will

    likely only include the cohesionless soil parameters described above.

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    13

    5.4 Subsurface Drainage

    If foundations or sumps are founded below the groundwater table, placement of a sub-drain (weeping tile

    system) below the base of foundation will be required to provide drainage and reduce potential adfreeze

    forces. The drainage system must maintain the groundwater level at or below the base of the foundation.

    Permanent structures founded below the groundwater table should either be designed to resist the

    potential hydraulic uplift pressures, or alternatively should have a subsurface drainage system below the

    foundation or around the perimeter walls to drain water away from the foundations.

    A higher groundwater table would be expected during spring and upon melting of snow. A subsurface

    drainage system may be provided to prevent buildup of hydrostatic uplift pressures on the base of the

    foundation during periods of high groundwater. The recommended approach for permanent subsurface

    drainage where required is to provide a gravel drainage layer around the perimeter walls and below the

    base of foundation to collect water. The subgrade should be sloped to drain subsurface water towards

    permanent drains and sumps. The collected water should be directed to the site drainage system or to a

    sump for collection and discharge. A minimum thickness of between 300 mm and 1000 mm of free

    draining gravel with less than 5% passing sieve No. 200 should be used under the base of foundations

    and behind the walls. It is recommended that a non-woven geotextile be placed directly over the

    prepared subgrade and at the interface around perimeter wall drainage layer to provide separation

    between the subgrade and drainage gravel layer and to prevent clogging of the gravel. It is

    recommended that further monitoring of groundwater levels to be carried out after completion of the site

    grading works to measure the depth of groundwater below the finished grade.

    5.5 Lateral Earth Pressures

    The reservoir walls should be designed to resist lateral earth pressures in an "at-rest" condition. This

    condition assumes a triangular pressure distribution with no hydrostatic pressure and may be calculated

    using the following equation:

    Backfill around concrete reservoir walls should not commence before the concrete has reached adequate

    strength and/or the walls are laterally braced. Only hand operated compaction equipment should be used

    within 600 mm of the concrete walls. When backfill is compacted, caution should be used to avoid high

    lateral loads caused by excessive compaction. To avoid differential wall pressures, the backfill should be

    brought up evenly around the reservoir walls. The upper 0.4 m of backfill should consist of compacted

    cohesive soil to prevent infiltration of surficial water into foundation soils and backfilled material.

    Final grades should be established to accommodate settlements in the order of 2% to 5% of the height of

    backfill around the reservoir walls. Positive drainage away from the structure should be maintained.

    A geotechnical engineer should be present during excavation and backfilling to confirm soil conditions,

    and to confirm that the backfill is placed according to the specification.

    Po = ko (𝛾H + q)

    Po = Lateral earth pressure "at-rest" condition

    (no wall movement occurs at a given depth)

    ko = Coefficient of earth pressure "at-rest" condition

    (use 0.55 for silt and 0.5 for sand and gravel backfill)

    𝛾o = Bulk unit weight of backfill soil (use 19 kN/m

    3 for cohesive fill and 20 kN/m

    3 for granular fill above the groundwater

    table, and use unit weights of 9 and 10 kN/m3 for cohesive and granular fill,

    respectively, below the groundwater table)

    H = Depth below final grade (m)

    q = Surcharge pressure at ground level (kPa)

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    14

    5.6 Buoyant Uplift

    Based on groundwater observations completed on October 17, 2018 and November 14, 2018, the depth

    of the groundwater table ranged from dry to 16.2 to 17.9 mBGS. However, it is possible that higher short-

    term water levels will be encountered after periods of increased precipitation.

    The magnitude of hydrostatic uplift forces applied to below grade structures should be calculated,

    assuming that the groundwater table is at an elevation of 3.0 mBGS (EL.714 mASL) to 6.4 mBGS (EL.

    710.6 mASL).

    The hydrostatic pressure may be calculated using the following equation:

    Given that the reservoir will be relatively large and constructed of concrete, buoyancy forces will likely not

    have much of an effect on the structure when it is full. However, when empty, the magnitude of the

    buoyancy forces will impact the structure. Buoyancy forces should be determined using the following

    equation:

    Buoyant uplift forces may be resisted by the mass of the structure, or by extending the base of the slab

    beyond the walls of the structure, such that the mass of the soils above the projection are used to resist

    uplift forces.

    If an extended base is considered, uplift resistance due to the weight of the soil above the projected slab

    may be determined as follows:

    Pw = wHw

    where:

    Pw = Hydrostatic pressure (kPa)

    𝛾w = Unit weight of water (9.8 kN/m3)

    Hw = Depth below top of water table (m)

    U = wVs

    where:

    U = Hydrostatic uplift force (kN)

    w = Unit weight of water (9.8 kN/m3)

    Vs = Volume of structure below the groundwater table (m³)

    Rss = AWH'

    where:

    Rss = Total allowable resistance due to weight of soil (kN)

    A = Perimeter of reservoir walls (m)

    W = Width of projected base slab beyond reservoir walls (m)

    H = Height between top-of-slab and ground surface (m)

    ' = Submerged unit weight of soil (kN/m3)

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    15

    Uplift resistance due to shearing through the soil may be assumed to have a triangular distribution as

    determined by the following equation:

    5.7 Grading and Drainage

    Excess water should be drained from the site as quickly as possible both during and after construction.

    The finished grade should be laid out so that surface waters are drained away from buildings and other

    structures.

    Landscaping should be designed such that surface water is prevented from ponding beside buildings. In

    the development area, the landscaping should maintain a minimum grade of 2%, while around the

    building area the minimum grade should be 5%. Within 2 m of the building and of other structure

    perimeters, the hard surfacing should be graded to slope away from the building at a gradient of at least

    2%.

    Asphalt pavement areas should be provided with a minimum grade of 1% and gravel pavements should

    be provided with a minimum grade of 2% to promote runoff and minimize ponding.

    5.8 Geochemistry Attack on Foundations

    Selected samples of the near-surface soils encountered at the site were subjected to chemical analysis

    for the purpose of corrosion assessment. The samples were tested for pH, resistivity, soluble sulphates,

    and soluble chlorides. The water soluble sulphate contents were determined in the laboratory to be less

    than 0.05%. Based on CSA A23.1-04, the potential for sulphate exposure is classified as negligible.

    Since sulphate content may vary across the site, it is recommended to use Type HS sulphate resistant

    Portland cement for foundation concrete and concrete exposed to soil and groundwater. All concrete

    work should be performed in accordance with applicable specifications. Higher strength and lower water

    to cement ratios may be required due to structural considerations or for exposure to de-icing chemicals.

    A water soluble chloride content of less than 20 ppm is generally considered non-corrosive to reinforced

    concrete.

    The pH and conductivity were determined on the same soil samples submitted for sulphate content

    determination.

    Analytical pH results indicate that the soils are of neutral to moderate corrosivity to buried ferrous metals.

    Resistivity results also show that the on-site soils have the potential to be moderately corrosive to

    corrosive towards ferrous metals. This should be considered in the design.

    Rs = (ko'dtanφ')/FS

    where:

    Rs = Allowable shearing resistance (kPa)

    ko = Coefficient of earth pressure at rest (0.5)

    ' = Submerged unit weight of soil (kN/m3)

    d = Depth below final ground level (m)

    φ' = Friction angle of backfill (assume 20° for cohesive fill and 30° for granular fill)

    FS = Factor of Safety (minimum of 2.0)

  • Acheson Zone 4 Reservoir Expansion Geotechnical Investigation

    Parkland County

    RPT-2018-11-21-Acheson Water Reservoir Expansion-60586018 AECOM

    16

    6. References

    Airforce Manual (1987) Concrete Floor Slabs on Grade Subjected to Heavy Loads. U.S. Departments of

    the Army and the Air Force.

    Andriashek, L.D., Quaternary Stratigraphy of the Edmonton Map Area, NTS 83H, Alberta Research

    Council, 1988.

    Bowles, J., Foundation Analysis and Design, Third Edition, 1982.

    Canadian Foundation Engineering Manual (CFEM), 4th Edition, 2006.

    Casagrande, A. (1932). A new Theory on Frost Heaving, Highway Research Board, (HRB). Proceedings,

    No.11, pp.168-172.

    Ceroici, W., Hydrogeology of the Southwest Segment, Edmonton Area, Alberta, Earth Sciences Report

    78-5, 1979.

    Prior G.J., et. al. (2013). Bedrock Geology of Alberta. Alberta. Geological Survey.

    Roberge, P. R. (2000). Handbook of Corrosion Engineering. New York: McGraw-Hill.

    Terzaghi, K., Evaluation of Coefficient of Subgrade Reaction, Geotechnique Vol. 5, No. 4, 1955.

    aecom.com

  • Appendix ATesthole Location Plan

  • © 2018 Microsoft Corporation © 2018 DigitalGlobe ©CNES (2018) Distribution Airbus DS

    TOWNSHIP RD. 530

    TH18-01

    TH18-02

    TH18-03

    TH18-04

    TH18-05

    X X X X X

    XX

    XX

    X

    X

    XX

    XX

    XX

    X

    X

    X

    X

    X

    X

    XX

    X

    P P P

    P

    P P

    FO

    FO

    FOFO

    FO

    UG

    UG

    UG

    UG

    UG

    UG

    UG

    UG

    UG

    UG

    UGUGUGUG

    PPPP

    N

    RANGE RD. 262

    © 2018 Microsoft Corporation © 2018 DigitalGlobe ©CNES (2018) Distribution Airbus DS

    HIGHWAY 16A

    HIG

    HW

    AY 6

    0

    SITE LOCATIONACHESONN

    0m

    1:15000

    375 750

    LOCATION PLAN

    0 25 50

    1:1000m

    SITE PLAN

    LEGEND:TESTHOLE LOCATION

    Acheson Zone 4 Reservoir ExpansionGeotechnical InvestigationParkland CountyProject No.: 60586018

    ANSI

    B 2

    79.4

    mm

    x 4

    31.8

    mm

    Last

    sav

    ed b

    y: E

    RO

    SC(2

    018-

    11-1

    5)

    Last

    Plo

    tted:

    201

    8-11

    -15

    Proj

    ect M

    anag

    emen

    t Ini

    tials

    :D

    esig

    ner:

    Che

    cked

    :Ap

    prov

    ed:

    File

    nam

    e: P

    :\605

    8601

    8\90

    0-C

    AD_G

    IS\9

    10-C

    AD\3

    0-FI

    GU

    RES

    \B\0

    0\60

    5860

    18-F

    IG-0

    0-00

    00-B

    -000

    1.D

    WG

    TESTHOLE LOCATION PLAN

    Figure 1Date: 2018-11-15

    ____

    ___

    ___

    ____

    _

  • N

    SITE LOCATION

    0m

    1:250000

    6250 12500

    ANSI

    A 2

    15.9

    mm

    x 2

    79.4

    mm

    Last

    sav

    ed b

    y: E

    RO

    SC(2

    018-

    11-1

    5)

    Las

    t Plo

    tted:

    201

    8-11

    -15

    Proj

    ect M

    anag

    emen

    t Ini

    tials

    :D

    esig

    ner:

    Che

    cked

    :Ap

    prov

    ed:

    File

    nam

    e: P

    :\605

    8601

    8\90

    0-C

    AD_G

    IS\9

    10-C

    AD\3

    0-FI

    GU

    RES

    \B\0

    0\60

    5860

    18-F

    IG-0

    0-00

    00-B

    -000

    2.D

    WG

    QUATERNARY GEOLOGY(Central Alberta Map)

    Figure 2Date: 2018-11-15

    ____

    ___

    ___

    ____

    _

    Fine sediment: silt and clay; flat to gently undulating surface.

    ICE-CONTACT LACUSTRINE AND FLUVIAL DEPOSITS, UNDIVIDED: gravel, sand, silt and clay, local till; upto 25 m thick; deposited in intermittent supraglacial lakes and streams, or at margins of ice-floored proglaciallakes; undulating to hummocky topography.

    Acheson Zone 4 Reservoir ExpansionGeotechnical InvestigationParkland CountyProject No.: 60586018

    Coarse sediment: sand and silt; undulating surface in places modified by wind.

    LACUSTRINE DEPOSIT: sand, silt and clay, with local ice-rafted stones; up to 80 m thick; deposited mainly inproglacial lakes, but includes also undifferentiated recent lake sediment; flat to gently undulating topography.

    GLACIAL DEPOSIT (Units 9 through 12a): till consisting of unsorted mixture of clay, silt, sand and gravel, withlocal water-sorted material and bedrock; the thickness is generally less than 25 m on uplands, but may reachas much as 100 m in buried valleys; flat, undulating, hummocky or ridged topography.

  • N

    SITE LOCATION

    0m

    1:750000

    18750 37500

    ANSI

    A 2

    15.9

    mm

    x 2

    79.4

    mm

    Last

    sav

    ed b

    y: E

    RO

    SC(2

    018-

    11-1

    5)

    Las

    t Plo

    tted:

    201

    8-11

    -15

    Proj

    ect M

    anag

    emen

    t Ini

    tials

    :D

    esig

    ner:

    Che

    cked

    :Ap

    prov

    ed:

    File

    nam

    e: P

    :\605

    8601

    8\90

    0-C

    AD_G

    IS\9

    10-C

    AD\3

    0-FI

    GU

    RES

    \B\0

    0\60

    5860

    18-F

    IG-0

    0-00

    00-B

    -000

    3.D

    WG

    BEDROCK GEOLOGY(Bedrock Geology of Alberta,Alberta Geological Survey)

    Figure 3Date: 2018-11-15

    ____

    ___

    ___

    ____

    _

    UPPER CRETACEOUS and PALEOGENE

    Edmonton Group

    SCOLLARD FORMATION: generally fine-grained, commonly cross-stratified, light grey to buff sandstoneand pale to dark grey, sandy to silty mudstone; thick coal seams and carbonaceous mudstone intervals inupper part; nonmarine

    UPPER CRETACEOUS

    BATTLE FORMATION: dark grey to purplish-black silty mudstone with thin, pale grey, siliceous beds inupper part; discontinuous due to erosion; nonmarine

    HORSESHOE CANYON FORMATION: pale grey, fine- to very fine grained, feldspathic sandstoneinterbedded with siltstone, bentonitic mudstone, carbonaceous mudstone, concretionary sideritic layers,and laterally continuous coal seams; includes white, pedogenically altered sandstone and mudstoneinterval at top (formerly assigned to the Whitemud Formation); nonmarine to locally marginal marine

    BEARPAW FORMATION: dominantly dark grey to brown-grey mudstone with concretionary sideritic andbentonite concretionary layers; concretions locally yield ammonities; marine to marginal marine

    Belly River Group

    BELLY RIVER GROUP (undivided): fine- to coarse-grained sandstone; grey to brown carbonaceoussiltstone; coal; marginal marine to nonmarine

    Acheson Zone 4 Reservoir ExpansionGeotechnical InvestigationParkland CountyProject No.: 60586018

  • Appendix BTesthole Logs

  • efltd-aecom 1

    Explanation of Field and Laboratory Test Data

    January 2009

    1. Explanation of Field and Laboratory Test Data

    The field and laboratory test results, as shown on the logs, are briefly described below.

    1.1 Natural Moisture Content and Atterberg Limits

    The relationship between the natural moisture content and depth is significant in determining the subsurface

    moisture conditions. The Atterberg Limits for a sample should be compared to the natural moisture content

    and should be on the Plasticity Chart in order to determine their classification.

    1.2 Soil Profile and Description

    Each soil stratum is classified and described noting any special conditions. The Modified Unified Soils

    Classification System (MUSCS) is used. The soil profile refers to the existing ground level. When available,

    the existing ground elevation is shown. The soil symbols used are shown in detail on the soil classification

    chart.

    1.3 Tests on Soil Samples

    Laboratory and field tests on the logs are identified by the following:

    N (Standard Penetration Test (SPT) Blow Count) - The SPT is conducted in the field to assess the in situ

    consistency of cohesive soils and the relative density of non-cohesive soils. The N value recorded is

    the number of blows from a 63.5 kg hammer dropped 760 mm which is required to drive a 51 mm split

    spoon sampler 300 mm into the soil.

    SO4 (Water Soluble Sulphate Content) - Conducted primarily to determine requirements for the use of

    sulphate resistant cement. Further details on the water soluble sulphate content are given in

    Section 1.6.

    D (Dry Unit Weight) kN/m3 and T (Total Unit Weight) kN/m

    3.

    QU (Unconfined Compressive Strength) kPa - May be used in determining allowable bearing capacity of

    the soil.

    CU (Undrained Shear Strength) kPa - This value is determined by an unconfined compression test and

    may also be used in determining the allowable bearing capacity of the soil.

    CPEN (Pocket Penetrometer Reading) kPa - Estimate of the undrained shear strength as determined by a

    pocket penetrometer.

    The following tests may also be performed on selected soil samples and the results are given on the borehole

    logs: Grain Size Analysis; Standard or Modified Proctor Compaction Test; California Bearing Ratio; Unconfined

    Compression Test; Permeability Test; Consolidation Test; Triaxial Test

  • efltd-aecom 2

    Explanation of Field and Laboratory Test Data

    January 2009

    1.4 Soil Density and Consistency

    The SPT test described above may be used to estimate the consistency of cohesive soils and the density of

    cohesionless soils. These approximate relationships are summarized in the following tables:

    Table 1.1

    Cohesive Soils

    N Consistency CU (kPa) (approx.)

    0 - 1 Very Soft 60 Very Hard >300

    Table 1.2

    Cohesionless Soils

    N Density

    0 - 5 Very Loose

    5 - 10 Loose

    10 - 30 Compact

    30 - 50 Dense

    >50 Very Dense

    1.5 Sample Condition and Type

    The depth, type, and condition of samples are indicated on the borehole logs by the following symbols:

    Grab Sample A-Casing

    Shelby Tube No Recovery

    SPT Sample Core Sample

  • efltd-aecom 3

    Explanation of Field and Laboratory Test Data

    January 2009

    1.6 Water Soluble Sulphate Concentration

    The following table from CSA Standard A23.1-94 indicates the requirements for concrete subjected to sulphate

    attack based upon the percentage of water soluble sulphate as presented on the borehole logs. CSA

    Standard A23.1-94 should be read in conjunction with the table.

    Table 1.3

    Requirements for Concrete Subjected to Sulphate Attack

    Class of

    Exposure

    Degree of

    Exposure

    Water-Soluble

    Sulphate (SO4)

    in Soil Sample

    %

    Sulphate (SO4)

    in Groundwater

    Samples

    mg/L

    Minimum

    Specified 28 d

    Compressive

    Strength

    MPa†

    Maximum

    Water/

    Cementing

    Materials

    Ratio†

    Portland

    Cement

    to be

    Used‡

    S-1 Very severe over 2.0 over 10,000 35 0.40 50

    S-2 Severe 0.20 - 2.0 1,500 - 10,000 32 0.45 50

    S-3 Moderate 0.10 - 0.20 150 - 1,500 30 0.50 20§,40, or 50

    * For sea water exposure see Clause 15.4

    † See Clause 15.1.4

    ‡ See Clause 15.1.5

    § Type 20 cement with moderate sulphate resistance (see Clause 3.1.2)

    1.7 Groundwater Table

    The groundwater table is indicated by the equilibrium level of standing water in a standpipe installed in a

    borehole. This level is generally taken at least 24 hours after installation of the standpipe. The groundwater

    level is subject to seasonal variations and its highest level usually occurs in spring. The symbol on the

    borehole logs indicating the groundwater level is an inverted solid triangle ().

  • AECOM Canada Ltd. General Statement; Normal Variability Of Subsurface Conditions

    The scope of the investigation presented herein is limited to an investigation of the subsurface conditions as to suitability of the site for the proposed project. This report has been prepared to aid in the general evaluation of the site and to assist the design engineer in the conceptual design for the area. The description of the project presented in this report represents the understanding by the geotechnical engineer of the significant aspects of the project relevant to the design and construction of the subdivision, infrastructure and similar. In the event of any changes in the basic design or location of the structures, as outlined in this report or plan, AECOM should be given the opportunity to review the changes and to modify or reaffirm in writing the conclusions and recommendations of this report. The analysis and recommendations represented in this report are based on the data obtained from the test holes drilled at the locations indicated on the site plans and from other information discussed herein. This report is based on the assumption that the subsurface conditions everywhere on the site are not significantly different from those encountered at the test locations. However, variations in soil conditions may exist between the test holes and, also, general groundwater levels and condition may fluctuate from time to time. The nature and extent of the variations may not become evident until construction. If subsurface conditions, different from those encountered in the test holes are observed or encountered during construction or appear to be present beneath or beyond the excavation, AECOM should be advised at once so that the conditions can be observed and reviewed and the recommendations reconsidered where necessary. Since it is possible for conditions to vary from those identified at the test locations and from those assumed in the analysis and preparation of recommendations, a contingency fund should be included in the construction budget to allow for the possibility of variations which may result in modifications of the design and construction procedures.

  • Sample 10:Chlorides -

  • 25

    END OF TESTHOLE AT 10.3 mBGS- no groundwater or sloughing encountered upon drilling completion- 50 mm diameter monitoring well installed to 9.8 mBGS- no groundwater encontered on October 17, 2018- no groundwater encontered on November 14, 2018

    ML 14

    11

    12

    13

    14

    15

    16

    17

    18

    19

    COMMENTS

    20

    Page 2 of 2

    SOIL DESCRIPTION

    707

    706

    705

    704

    703

    702

    701

    700

    699

    698

    COMPLETION DEPTH: 10.30 mCOMPLETION DATE: 9/14/2018

    DEP

    TH (m

    )

    10

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)

    25 50 75

    SPT

    (N)

    SOIL

    SYM

    BOL

    USC

    TESTHOLE NO.: TH18-01

    PROJECT NO.: 60586018

    ELEVATION (m): 717.5GRAB BULK NO RECOVERYSAMPLE TYPE SHELBY TUBE CORESPLIT SPOON

    PROJECT: Acheson Zone 4 Reservoir Expansion

    LOCATION: Township Road 530 A / Range Road 262A

    CONTRACTOR: Canadian Geological Drilling Ltd.

    CLIENT: Parkland County

    COORDINATES: UTM N 5936736 E 317738

    METHOD: Solid Stem Augers

    GROUT SANDGRAVEL SLOUGHBENTONITE CUTTINGSBACKFILL TYPE

    SAM

    PLE

    #

    SAM

    PLE

    TYPE

    9.6

  • Sample 10:Liquid Limit - 24.9%Plastic Limit - 21.8%Plasticity Index - 3.0%

    Gravel - 0.0%Sand - 17.8%Silt - 67.8%Clay - 14.4%

    4

    6

    7

    7

    13

    17

    TOPSOIL (50 mm) - some silt, organic, fibrous, some rootlets, moist, blackSILT - some clay, trace to some fine-grained sand, very loose, oxidized, damp,brown

    - some clay, low plasticity, moist

    - loose

    - some sand, some clay, compact

    OR

    ML

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    1

    2

    3

    4

    5

    6

    7

    8

    9

    COMMENTS

    10

    Page 1 of 2

    SOIL DESCRIPTION

    716

    715

    714

    713

    712

    711

    710

    709

    708

    707

    COMPLETION DEPTH: 10.30 mCOMPLETION DATE: 9/14/2018

    DEP

    TH (m

    )

    0

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)

    25 50 75

    SPT

    (N)

    SOIL

    SYM

    BOL

    USC

    TESTHOLE NO.: TH18-02

    PROJECT NO.: 60586018

    ELEVATION (m): 716.9GRAB BULK NO RECOVERYSAMPLE TYPE SHELBY TUBE CORESPLIT SPOON

    PROJECT: Acheson Zone 4 Reservoir Expansion

    LOCATION: Township Road 530 A / Range Road 262A

    CONTRACTOR: Canadian Geological Drilling Ltd.

    CLIENT: Parkland County

    COORDINATES: UTM N 5936729 E 317711

    METHOD: Solid Stem Augers

    GROUT SANDGRAVEL SLOUGHBENTONITE CUTTINGSBACKFILL TYPE

    SAM

    PLE

    #

    SAM

    PLE

    TYPE

    16.5

    12.7

    26.3

    13.5

    21

    16.2

    18.5

    18.1

    9.1

    12

    12.8

    10.7

    9.7

  • 16

    END OF TESTHOLE AT 10.3 mBGS- no groundwater or sloughing encountered upon drilling completion- 50 mm diameter monitoring well installed to 9.8 mBGS- trace groundwater encontered at the bottom of well on October 17, 2018- trace groundwater encontered at the bottom of well on November 14, 2018

    ML 14

    11

    12

    13

    14

    15

    16

    17

    18

    19

    COMMENTS

    20

    Page 2 of 2

    SOIL DESCRIPTION

    706

    705

    704

    703

    702

    701

    700

    699

    698

    697

    COMPLETION DEPTH: 10.30 mCOMPLETION DATE: 9/14/2018

    DEP

    TH (m

    )

    10

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)

    25 50 75

    SPT

    (N)

    SOIL

    SYM

    BOL

    USC

    TESTHOLE NO.: TH18-02

    PROJECT NO.: 60586018

    ELEVATION (m): 716.9GRAB BULK NO RECOVERYSAMPLE TYPE SHELBY TUBE CORESPLIT SPOON

    PROJECT: Acheson Zone 4 Reservoir Expansion

    LOCATION: Township Road 530 A / Range Road 262A

    CONTRACTOR: Canadian Geological Drilling Ltd.

    CLIENT: Parkland County

    COORDINATES: UTM N 5936729 E 317711

    METHOD: Solid Stem Augers

    GROUT SANDGRAVEL SLOUGHBENTONITE CUTTINGSBACKFILL TYPE

    SAM

    PLE

    #

    SAM

    PLE

    TYPE

    9.8

  • Sample 10:Liquid Limit - 23.8%Plastic Limit - 21.7%Plasticity Index - 2.1%

    Gravel - 0.0%Sand - 26.4%Silt - 61.7%Clay - 11.9%

    4

    8

    7

    6

    8

    15

    TOPSOIL (50 mm) - some silt, organic, fibrous, some rootlets, moist, blackSILT - trace to some fine sand, trace clay, very loose, damp, some oxidizedlaminations, light brown

    - loose

    - sandy, some clay, loose

    - trace clay layering, increasing clay content

    - compact

    - some sand laminations, increasing sand content

    OR

    ML

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    1

    2

    3

    4

    5

    6

    7

    8

    9

    COMMENTS

    10

    Page 1 of 2

    SOIL DESCRIPTION

    717

    716

    715

    714

    713

    712

    711

    710

    709

    708

    COMPLETION DEPTH: 10.30 mCOMPLETION DATE: 9/14/2018

    DEP

    TH (m

    )

    0

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)

    25 50 75

    SPT

    (N)

    SOIL

    SYM

    BOL

    USC

    TESTHOLE NO.: TH18-03

    PROJECT NO.: 60586018

    ELEVATION (m): 717.2GRAB BULK NO RECOVERYSAMPLE TYPE SHELBY TUBE CORESPLIT SPOON

    PROJECT: Acheson Zone 4 Reservoir Expansion

    LOCATION: Township Road 530 A / Range Road 262A

    CONTRACTOR: Canadian Geological Drilling Ltd.

    CLIENT: Parkland County

    COORDINATES: UTM N 5936711 E 317740

    METHOD: Solid Stem Augers

    GROUT SANDGRAVEL SLOUGHBENTONITE CUTTINGSBACKFILL TYPE

    SAM

    PLE

    #

    SAM

    PLE

    TYPE

    10

    20.5

    15

    25.9

    18.8

    20.3

    24.5

    29.2

    23

    11.1

    24.1

    16.1

    12.6

  • 34

    END OF TESTHOLE AT 10.3 mBGS- no groundwater or sloughing upon drilling completion- 50 mm diameter monitoring well installed to 9.8 mBGS- no groundwater encontered on October 17, 2018- no groundwater encontered on November 14, 2018

    ML 14

    11

    12

    13

    14

    15

    16

    17

    18

    19

    COMMENTS

    20

    Page 2 of 2

    SOIL DESCRIPTION

    707

    706

    705

    704

    703

    702

    701

    700

    699

    698

    COMPLETION DEPTH: 10.30 mCOMPLETION DATE: 9/14/2018

    DEP

    TH (m

    )

    10

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)

    25 50 75

    SPT

    (N)

    SOIL

    SYM

    BOL

    USC

    TESTHOLE NO.: TH18-03

    PROJECT NO.: 60586018

    ELEVATION (m): 717.2GRAB BULK NO RECOVERYSAMPLE TYPE SHELBY TUBE CORESPLIT SPOON

    PROJECT: Acheson Zone 4 Reservoir Expansion

    LOCATION: Township Road 530 A / Range Road 262A

    CONTRACTOR: Canadian Geological Drilling Ltd.

    CLIENT: Parkland County

    COORDINATES: UTM N 5936711 E 317740

    METHOD: Solid Stem Augers

    GROUT SANDGRAVEL SLOUGHBENTONITE CUTTINGSBACKFILL TYPE

    SAM

    PLE

    #

    SAM

    PLE

    TYPE

    11.8

  • Sample 14:

    4

    7

    8

    9

    10

    10

    TOPSOIL (50 mm) - some silt, organic, fibrous, some rootlets, moist, blackSILT - trace to some fine-grained sand, trace clay, very loose, damp, someoxidized laminations, light brown

    - loose

    - moist

    - increasing sand content

    - compact

    OR

    ML

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    1

    2

    3

    4

    5

    6

    7

    8

    9

    COMMENTS

    10

    Page 1 of 4

    SOIL DESCRIPTION

    716

    715

    714

    713

    712

    711

    710

    709

    708

    COMPLETION DEPTH: 29.80 mCOMPLETION DATE: 9/15/2018

    DEP

    TH (m

    )

    0

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)

    25 50 75

    SPT

    (N)

    SOIL

    SYM

    BOL

    USC

    TESTHOLE NO.: TH18-04

    PROJECT NO.: 60586018

    ELEVATION (m): 717GRAB BULK NO RECOVERYSAMPLE TYPE SHELBY TUBE CORESPLIT SPOON

    PROJECT: Acheson Zone 4 Reservoir Expansion

    LOCATION: Township Road 530 A / Range Road 262A

    CONTRACTOR: Canadian Geological Drilling Ltd.

    CLIENT: Parkland County

    COORDINATES: UTM N 5936704 E 317717

    METHOD: Solid Stem Augers

    GROUT SANDGRAVEL SLOUGHBENTONITE CUTTINGSBACKFILL TYPE

    SAM

    PLE

    #

    SAM

    PLE

    TYPE

    13

    24.5

    17.2

    17

    12

    17.1

    24.4

    17.9

    22.5

    21

    14

    14.5

    12.7

  • Chlorides -

  • 14

    19

    21

    21

    21

    26

    23

    - some fine-grained sand, saturated, some groundwater

    - grey

    END OF TESTHOLE AT 29.8 mBGS

    ML

    28

    29

    30

    31

    32

    33

    34

    35

    36

    37

    38

    39

    40

    21

    22

    23

    24

    25

    26

    27

    28

    29

    COMMENTS

    30

    Page 3 of 4

    SOIL DESCRIPTION

    696

    695

    694

    693

    692

    691

    690

    689

    688

    COMPLETION DEPTH: 29.80 mCOMPLETION DATE: 9/15/2018

    DEP

    TH (m

    )

    20

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)

    25 50 75

    SPT

    (N)

    SOIL

    SYM

    BOL

    USC

    TESTHOLE NO.: TH18-04

    PROJECT NO.: 60586018

    ELEVATION (m): 717GRAB BULK NO RECOVERYSAMPLE TYPE SHELBY TUBE CORESPLIT SPOON

    PROJECT: Acheson Zone 4 Reservoir Expansion

    LOCATION: Township Road 530 A / Range Road 262A

    CONTRACTOR: Canadian Geological Drilling Ltd.

    CLIENT: Parkland County

    COORDINATES: UTM N 5936704 E 317717

    METHOD: Solid Stem Augers

    GROUT SANDGRAVEL SLOUGHBENTONITE CUTTINGSBACKFILL TYPE

    SAM

    PLE

    #

    SAM

    PLE

    TYPE

    23.4

    22.2

    27

    25.6

    23.5

    29.9

    30.9

    29.9

    23.8

    26.3

    22.6

    21.2

    24.5

  • - groundwater and sloughing at 16.2 mBGS upon drilling completion- 50 mm diameter monitoring well installed to 22.9 mBGS- groundwater encountered at 17.6 mBGS on October 17, 2018- groundwater encountered at 17.9 mBGS on November 14, 2018

    31

    32

    33

    34

    35

    36

    37

    38

    39

    COMMENTS

    40

    Page 4 of 4

    SOIL DESCRIPTION

    686

    685

    684

    683

    682

    681

    680

    679

    678

    COMPLETION DEPTH: 29.80 mCOMPLETION DATE: 9/15/2018

    DEP

    TH (m

    )

    30

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)

    25 50 75

    SPT

    (N)

    SOIL

    SYM

    BOL

    USC

    TESTHOLE NO.: TH18-04

    PROJECT NO.: 60586018

    ELEVATION (m): 717GRAB BULK NO RECOVERYSAMPLE TYPE SHELBY TUBE CORESPLIT SPOON

    PROJECT: Acheson Zone 4 Reservoir Expansion

    LOCATION: Township Road 530 A / Range Road 262A

    CONTRACTOR: Canadian Geological Drilling Ltd.

    CLIENT: Parkland County

    COORDINATES: UTM N 5936704 E 317717

    METHOD: Solid Stem Augers

    GROUT SANDGRAVEL SLOUGHBENTONITE CUTTINGSBACKFILL TYPE

    SAM

    PLE

    #

    SAM

    PLE

    TYPE

  • Sample 6:Liquid Limit - 31.3%Plastic Limit - 24.0%Plasticity Index - 7.3%

    Gravel - 0.0%Sand - 2.2%Silt - 76.0%Clay - 21.8%

    14

    11

    11

    14

    19

    15

    TOPSOIL (50 mm) - some silt, organic, fibrous, some rootlets, moist, blackSILT - trace fine-grained sand, trace clay, non-plastic, compact, oxidized, humid,brown

    - some clay - increasing fine-grained sand

    - some clay layers to 6.9 mBGS

    - compact

    OR

    ML

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    1

    2

    3

    4

    5

    6

    7

    8

    9

    COMMENTS

    10

    Page 1 of 2

    SOIL DESCRIPTION

    716

    715

    714

    713

    712

    711

    710

    709

    708

    707

    COMPLETION DEPTH: 10.30 mCOMPLETION DATE: 9/14/2018

    DEP

    TH (m

    )

    0

    ELEV

    ATIO

    N (m

    )

    LOGGED BY: Pat EckelREVIEWED BY: Brian NguyenPROJECT MANAGER: Jason CasaultLO

    G O

    F T

    ES

    TH

    OLE

    605

    8601

    8 -

    AC

    HE

    SO

    N R

    ES

    IVO

    IR.G

    PJ

    UM

    A_C

    OC

    .GD

    T P

    RIN

    T: 1

    1/20

    /18

    By:

    LIQUIDPLASTIC M.C.

    12.5 25.0 37.5

    SPT (Standard Pen Test) (Blows/300mm)