appendix g - department of city planningplanning.lacity.org/eir/mccadden/deir/files/app_g.pdf ·...
TRANSCRIPT
Appendix G
Utility Technical Report
McCadden Project Utility Technical Report: Water and Energy
January 29, 2016
PREPARED BY:
KPFF Consulting Engineers
6080 Center Drive, Suite 750
Los Angeles, CA 90045
(310) 665-2800
McCadden Project Utility Technical Report
Page i
January 29, 2016
Table of Contents
1. INTRODUCTION ..................................................................................................................... 1
1.1. PROJECT DESCRIPTION ......................................................................................................... 1
1.2. SCOPE OF WORK.................................................................................................................. 2
2. EXISTING CONDITIONS .......................................................................................................... 2
2.1. WATER SERVICE .................................................................................................................. 2
2.1.1. DOMESTIC ................................................................................................................... 2
2.1.2. FIRE ............................................................................................................................ 2
2.2. ENERGY .............................................................................................................................. 2
3. METHODOLOGY ..................................................................................................................... 2
3.1. WATER ............................................................................................................................... 2
3.2. ENERGY .............................................................................................................................. 3
4. INFRASTRUCTURE CAPACITY ................................................................................................ 3
4.1. CONSTRUCTION ................................................................................................................... 3
4.1.1. WATER ........................................................................................................................ 3
4.1.2. ENERGY ....................................................................................................................... 4
4.2. OPERATION ......................................................................................................................... 5
4.2.1. WATER ........................................................................................................................ 5
4.2.1.1. WATER CONSUMPTION ............................................................................................. 5
4.2.1.2. FIRE WATER DEMAND ............................................................................................... 5
4.2.1.3. DOMESTIC WATER DEMAND ...................................................................................... 6
4.2.2. ENERGY ....................................................................................................................... 6
Appendix
Exhibit 1- SAR Reports (3)
Exhibit 2- Los Angeles Department of Water and Power Will Serve Letter
Exhibit 3- Southern California Gas Will Serve Letter
McCadden Project Utility Technical Report
Page 1
January 29, 2016
1. INTRODUCTION
1.1. PROJECT DESCRIPTION
The proposed McCadden Project (Project) consists of the construction of three new
buildings and a new two-level, below-grade parking structure on a project site located at
1118-1139 N. McCadden Place and 6719-6733 Santa Monica Boulevard (the Project Site)
in the Hollywood community of the City of Los Angeles (City). The Project Site includes
approximately 2.67 acres of land bisected by N. McCadden Place. The portion of the
Project Site on the west side of N. McCadden Place is located at 1119-1139 N.
McCadden Place (the West Site) and the portion of the Project Site on the east side of N.
McCadden Place is located at 1118-1136 N. McCadden Place and 6719–6733 Santa
Monica Boulevard (the East Site).
The proposed Project includes a six-story senior housing building, a five-story youth
housing building and a 1-4-story LGBT facility that includes a senior center, the youth
center, administrative offices, accessory recreational space, and transitional living and
emergency guestrooms. The senior housing building, the LGBT facility and the below-
grade parking would be developed on the East Site, while the youth housing building
would be developed on the southern portion of the West Site located at 1119 N.
McCadden Place (the Youth Housing Parcel), just south of the existing Village at Ed
Gould Plaza (the Village), which is located on the northern portion of the West Site.
The East Site is bound to the north by parking lots with commercial property beyond; to
the east by N. Las Palmas Ave with commercial property (film/camera shops,
laundromat, 7-11) beyond; to the south by Santa Monica Boulevard with commercial
property beyond; and to the west by N. McCadden Place with commercial property
beyond. The West Site is bound to the north by commercial property; to the east by
N. McCadden Place; to the south by commercial property; and to the west by
commercial property.
The southern portion of the East Site is currently developed with one-story, brick office
building that was constructed around 1952 and is currently utilized as office space by
the Los Angeles LGBT Center. The Youth Housing Parcel is currently an asphalt-paved
parking lot utilized by the LGBT Center. The north portion of the East Site is developed
with asphalt-paved parking that extends from N. Las Palmas Ave to the east to
N. McCadden Place to the west. Access to the East Site is via Santa Monica Boulevard to
the south, N. Las Palmas Avenue to the east, and N. McCadden Place to the west. Access
to the Youth Housing Parcel on the West Site is via N. McCadden Place to the east.
McCadden Project Utility Technical Report
Page 2
January 29, 2016
1.2. SCOPE OF WORK
This report evaluates the capacity of the existing water and energy (electricity and
natural gas) infrastructure serving the Project Site and determines whether the existing
infrastructure can accommodate the Project.
2. EXISTING CONDITIONS
2.1. WATER SERVICE
2.1.1. DOMESTIC
Based on available record data provided by the City, there is a 12-inch water main in
Santa Monica Boulevard, an 8-inch water main in Las Palmas Avenue, and a 4-inch water
main in N. McCadden Place. Based on conversations with Los Angeles Department of
Water and Power (LADWP), the domestic water for the existing office building on the
East Site and the Village on the West Site are served off N. McCadden Place.
2.1.2. FIRE
Fire sprinklers for the existing office building on the East Site are served off of Santa
Monica Boulevard, while fire sprinklers for the Village are served off of N. McCadden
Place. There are also existing fire hydrants in front of the property on Las Palmas
Avenue, on the southwest corner of N. McCadden Place and Santa Monica Boulevard
and the northwest corner of Las Palmas Avenue and Santa Monica Boulevard.
2.2. ENERGY
Electrical service to the Project Site is provided by the LADWP. Based on conversations
with the LADWP, the site receives power from power poles in Santa Monica Boulevard.
Gas service to the Project Site is provided by Southern California Gas Company. Based
on available record drawings, the gas company operates gas lines in N. McCadden Place
and Santa Monica Boulevard.
3. METHODOLOGY
3.1. WATER
To determine the capacity of the existing water infrastructure to serve the Project, this
report compares the estimated Project water demand with the calculated available
capacity of the existing water infrastructure.
LADWP was also consulted in preparation of this report. Specifically, LADWP performed
a flow test to determine if available water conveyance exists for future development.
LADWP's approach consists of data ranging from available static pressure (meaning how
McCadden Project Utility Technical Report
Page 3
January 29, 2016
much pressure is available at the source before applying a project's demand), to the
available pressure at the maximum demand needed for a project. Based on the results
of the flow test, LADWP then determines whether or not it can meet the project's need
based on the existing water infrastructure.
The following has been considered as part of this analysis:
Environmental Setting
• Description of major water infrastructure serving the Project Site, including
the type of facilities, location and sizes, and any planned improvements
• Description of the water conditions for the project area and known
improvement plans
Project Infrastructure Impacts
• Review the project description and the information obtained from a review
of the Environmental Setting (above) and Evaluation of Screening Criteria.
• Determine what improvements would be needed, if any, to adequately
serve the Project.
• Describe the degree to which presently scheduled off-site improvements
offset infrastructure needs.
3.2. ENERGY
The Project Site will require an upgrade in the electrical service. The Project demands
include the number of feeds, the overall estimated connected load, the need for a
transformer, and placement of the transformer. The electrical engineer in coordination
with the will serve letters from the gas company and LADWP will determine if sufficient
capacity is available to serve the Project.
4. INFRASTRUCTURE CAPACITY
4.1. CONSTRUCTION
4.1.1. WATER
A water supply would be required during the construction of the Project for dust
control, cleaning of equipment, excavation/export, removal and re-compaction, etc.
However, this water use during construction would be limited and temporary. The
water demand during construction of the Project would also be offset from removal of
the existing office building on the East Site, which is currently operational and has
associated water consumption. Therefore, it is anticipated that the existing water
McCadden Project Utility Technical Report
Page 4
January 29, 2016
infrastructure would meet the limited and temporary water demand associated with
construction of the Project.
The Project will require construction of new, onsite water distribution lines that would
connect to the public main lines to serve the new buildings. Construction activities
associated with the installation of water distribution lines would primarily involve
trenching in order to place the water distribution lines below the surface and would be
limited to onsite water distribution, together with minor offsite work associated with
connections to the public main. No upgrades to public water mains are anticipated.
Prior to ground disturbance, The project contractor would coordinate with LADWP to
identify the locations and depth of all lines. Further, LADWP would be notified in
advance of proposed ground disturbance activities to avoid water lines and disruption of
water service.
4.1.2. ENERGY
Electrical power would be consumed to construct the new buildings and facilities that
comprise the Project. Electrical power would be supplied from existing electrical
services within the Project Site or from a power pole in the adjacent streets and would
not affect other services. Overall, demolition and construction activities would require
minimal electricity consumption and it is anticipated that available electricity supplies
and infrastructure, whether onsite or offsite, would meet the limited electricity
consumption associated with construction of the Project.
Construction of the Project would not involve the consumption of natural gas. Natural
gas would not be supplied to support project construction activities, so there would be
no demand for natural gas generated by construction.
The Project would require construction of new onsite electrical and gas distribution
facilities that would connect to existing main lines to serve the new buildings.
Construction activities associated with the installation of the electrical and gas
distribution facilities would primarily be confined to trenching and would be limited to
onsite electrical and natural gas distribution, together with minor offsite work
associated with connections to the main lines. No upgrades to the existing electrical and
natural gas mains are anticipated. Prior to ground disturbance, the project contractor
would coordinate with LADWP and the Southern California Gas Company to identify the
locations and depth of all lines. LADWP and the Southern California Gas Company would
also be notified in advance of proposed ground disturbance activities to avoid disruption
of electrical and natural gas service.
McCadden Project Utility Technical Report
Page 5
January 29, 2016
4.2. OPERATION
4.2.1. WATER
4.2.1.1. WATER CONSUMPTION
When analyzing the Project for infrastructure capacity, the projected demands for both
fire suppression and domestic water are considered. Although domestic water demand
is the Project’s main contributor to water consumption, fire flow demands have a much
greater instantaneous impact on infrastructure, and therefore are the primary means
for analyzing infrastructure capacity. Nevertheless, conservative analysis for both fire
suppression and domestic water flows has been completed by LADWP for the Project.
See Exhibit 1 of this report for the results of the service advisory request (SAR) with
respect to fire service pressure flow.
4.2.1.2. FIRE WATER DEMAND
Based on fire flow standards set forth in Section 57.507.3.1 of the LAMC for High
Density Residential and Neighborhood Commercial, the Project would require fire flow
of 4,000 gallons per minute (gpm) for four hydrants flowing simultaneously with a
residual pressure of 20 pounds per square inch. This translates to a required flow of
1,000 gpm for each hydrant. A Service Advisory Request (SAR) was submitted to LADWP
in order to determine if the existing public infrastructure could meet the demands of
the Project. Exhibit 1 shows a static pressure of 129-130 pounds per square inch in the
area and that flows up to 1,400 gpm can be delivered to the Project Site with a residual
pressure of up to 89 pounds per square inch, which far exceeds the 20 pounds per
square inch requirement for the surrounding public hydrants.
Furthermore, Section 57.513.1 of the LAMC permits the use of supplemental fire
protection equipment or systems, including the installation of an automatic fire
extinguishing system, in lieu of the requirements of the Fire Code, in which case the
project developer shall either conform to the requirements of the Fire Code or install
such supplemental equipment or systems. In accordance with these provisions, the
Project will incorporate seperate fire sprinkler suppression systems for each site to
reduce or eliminate the public hydrant demands, which will be subject to fire
department review and approval during the design and permitting of the Project. The
plumbing engineer has estimated the fire sprinkler demand to be approximately 1,000
gpm for the East Site and 750 gpm for the West Site. Based on pressure flow reports
obtained from LADWP (see Exhibit 1), the existing public infrastructure can deliver flows
up to 1,400 gpm with a residual pressure of up to 89 psi. Therefore, LADWP would be
able to supply sufficient flow and pressure to satisfy the needs of the fire suppression
McCadden Project Utility Technical Report
Page 6
January 29, 2016
for the Project. As stated above, Exhibit 1 shows that LADWP can supply sufficient flow
and pressure to satisfy that demand.
4.2.1.3. DOMESTIC WATER DEMAND
Based on fixture units and type of use, the domestic demand for the Project has been
estimated by the plumbing engineer to be a total of 320 gpm spread for all of the
buildings. The approved SARs for the three adjacent streets confirm that sufficient
capacity is available for the Project, regardless of where the connections are made. The
Project includes a 3” domestic water connection to the existing water main in N.
McCadden Place, a 4” domestic water connection to the existing water main in Santa
Monica Boulevard and a 3” domestic water connection to the existing water min in N.
Las Palmas Avenue. The service laterals will be adequately sized to accommodate the
fire demand and domestic demand flowing simultaneously. In addition, the services will
include backflows and be metered separately per City requirements.
4.2.2. ENERGY
The Project would result in an increase in electrical demand in comparison with existing
conditions on the Project Site. Will serve request letter were sent to LADWP to
determine if there is sufficient capacity to serve the Project. The responses from LADWP
(see Exhibit 2) state that electric service will be available for the Project and that the
estimated power requirement for the Project is part of the total load growth forecast of
the City and has been taken into account in the planned growth of the power system.
The Project will also increase the demand for natural gas in comparison with existing
conditions on the Project Site. A will serve request letter was sent to the Southern
California Gas Company (SGC)to determine if there is sufficient capacity to serve the
Project. The response from SCG (see Exhibit 3) states that there are currently gas
facilities in the area available for the Project.
McCadden Project Utility Technical Report
Page 7
January 29, 2016
EXHIBIT 1
SAR
Residual Flow/Pressure Table for water system street mainat this location
Press.(psi)
Press.(psi)
Flow(gpm)
Press.(psi)
Flow(gpm)
Flow(gpm)
0 75 885 5793 610
130 74 900 5692 630
185 73 915 5591 645
230 72 925 5490 665
270 71 940 5389 680
305 70 950 5288 695
335 69 965 5187 710
365 68 975 5086 730
395 67 990 4985 745
420 66 1000 4884 760
445 6583 775
465 6482 790
490 6381 805
510 6280 820
530 6179 830
555 6078 845
570 5977 860
590 5876 875
Meter AssemblyCapacities
Domestic Meters
=1 inch 56 gpm
=1-1/2 inch 96 gpm
=2 inch 160 gpm
=3 inch 220 gpm
=4 inch 400 gpm
=6 inch 700 gpm
=8 inch 1500 gpm
=10 inch 2500 gpm
Fire Service
=2 inch 250 gpm
=4 inch 600 gpm
=6 inch 1400 gpm
=8 inch 2500 gpm
=10 inch 5000 gpm
FM Services
=8 inch 2500 gpm
=10 inch 5000 gpm
For:
System maximum pressure should be used only for determining class of piping and fittings.
These values are subject to change due to changes in system facilities or demands.
This information will be sent to the Department of Building and Safety for plan checking.
Notes: It is approved up to 1000 gpm which is the maximum available flow.
This SAR is valid for one year from 11-02-15. Once the SAR expires, the applicant needs to re-apply and pay applicable processing fee.
WESTERN (213) 367-1225For additional information contact the Water Distribution Services Section
Prepared by Water Service Map
144-183ELIA SUN ELIA SUN
Approved by
1119 N MCCADDEN PL
130 302
Approved Date:
psi based on street curb elevation of feet above sea level at this location.
off of the 6 INCH
The distance from the DWP street main to the property line is feet
4 inch main in MCCADDEN PL on the WEST side approximately
231 feet NORTH of NORTH of SANTA MONICA BLVD The System maximum pressure is
28
52533SAR NUMBER 618198SERVICE NUMBERFire Service Pressure Flow Report
11-2-2015
Los Angeles Department of Water and Power - Water SystemCity of Los Angeles
Proposed Service
McCadden Project Utility Technical Report
Page 8
January 29, 2016
EXHIBIT 2
LOS ANGELES DEPARTMENT OF WATER AND POWER WILL SERVE LETTER
McCadden Project Utility Technical Report
Page 9
January 29, 2016
EXHIBIT 3
SOUTHERN CALIFORNIA GAS WILL SERVE LETTER
November 20, 2015
Attn: Dustin James
KPFF Consulting Engineers
6080 Center Dr., Suite 700
Los Angeles, CA. 90045
RE: Will Serve Letter Request for – Job ID# 43-2015-06-00062: 1119 McCadden Pl.
Los Angeles, CA. 90038
Dear Sir/Madam:
Thank you for inquiring about the availability of natural gas service for your project. We are pleased to
inform you that Southern California Gas Company (SoCalGas) has facilities in the area where the above
named project is being proposed. The service would be in accordance with SoCalGas’ policies and
extension rules on file with the California Public Utilities Commission (Commission) at the time
contractual arrangements are made.
This letter should not be considered a contractual commitment to serve the proposed project, and is only
provided for informational purposes only. The availability of natural gas service is based upon natural
gas supply conditions and is subject to changes in law or regulation. As a public utility, SoCalGas is
under the jurisdiction of the Commission and certain federal regulatory agencies, and gas service will be
provided in accordance with the rules and regulations in effect at the time service is provided. Natural
gas service is also subject to environmental regulations, which could affect the construction of a main or
service line extension (for example, if hazardous wastes were encountered in the process of installing the
line). Applicable regulations will be determined once a contract with SoCalGas is executed.
If you need assistance choosing the appropriate gas equipment for your project, or would like to discuss
the most effective applications of energy efficiency techniques, please contact our area Service Center at
800-427-2200.
Thank you again for choosing clean, reliable, and safe natural gas, your best energy value.
Sincerely,
Pedro Reyes
Pipeline Planning Associate
Compton Headquarters