applicability of alara lessons learned from
TRANSCRIPT
Applicability of ALARA Lessons Learned from Decommissioning Projects to Operating Plants 2009 ISOE North American ALARA Symposium/ EPRI Radiation Protection ConferenceJanuary 12-14, 2009Rich McGrath EPRI
2© 2009 Electric Power Research Institute, Inc. All rights reserved.
Discussion Topics
•Decommissioning Projects Compared to Operating Projects
•Decommissioning Chemical Decontamination Experience
•Typical Uses of Robotics in Decommissioning
•The Benefits of Benchmarking Previous Experience
3© 2009 Electric Power Research Institute, Inc. All rights reserved.
10 US Decommissioning Plant Statusfuel in dry storage at most sites
Yankee Rowe
180MW PWR complete
Trojan
1100MW PWR, complete
Maine Yankee
900MW PWR, complete
Connecticut Yankee
600MW PWR complete
Rancho Seco
900MW PWR, ~90% complete
San Onofre 1
450MW PWR, Remediation complete, FSS at a later date
Big Rock Point
65MW BWR complete
Saxton
23MW PWR, complete
Zion
2, 1040MW PWRs, 2017
Humboldt Bay
63MW BWR 2015
4© 2009 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning vs. Operating ALARA
• Operating Plant Projects (High Dose):– In Service Inspection (incl. S/G Inspections)– Piping Modifications– Occasional Large Projects (i.e., S/G Replacements)
• Decommissioning Projects (High Dose):– Movement of Fuel to Dry Storage– Removal of All Contaminated Systems
• Primary Systems Components (Includes Reactors, S/G)
• Other Piping Systems and Components– Decontamination of Highly Contaminated Structures
• Decommissioning Involves a Huge Number of RWP Hours
5© 2009 Electric Power Research Institute, Inc. All rights reserved.
Scope of Typical Full System Decon (FSD) –PWR (Connecticut Yankee)
6© 2009 Electric Power Research Institute, Inc. All rights reserved.
Temporary Equipment for FSD
7
Reactor Coolant System Exposure Rate Reduction
0
200
400
600mr/hr
800
1000
7/24 7/25 7/26 7/27 7/28 7/29 7/30 7/31 8/1 8/2
PZR SPRAY LI(Loc#2)
1 BYPASS*(Loc#7)
CVCS LD 1 IN(Loc#8)
2 BYPASS*(Loc#14)
2 BYPASS*(Loc#14)
4 BYPASS *(Loc#26)
DRAIN 4*(Loc#28)
Rgn Hx Ret.(Loc#30)
8© 2009 Electric Power Research Institute, Inc. All rights reserved.
Comparison FSD at PWRs
Surface Area (m2)
Metal Removed
Activity (Ci)
Resin Waste DFs
SS Inconel (Kg) Co-60 (ft3) RCS Aux Sys.
Indian Point-2 (1995) 6000 14,000 128 3906 1770 7.9 5.8
Connecticut Yankee (1998) 1,997 929 182 129 115* 17.6 9.8
Maine Yankee (1998) 465 139 307 99 537 8.7 44.8
Stade - Germany (2007) 5,000 12,000 231 630
(total) 540 47.8 17.9
Zorita - Spain (2007) 894 2,313 234 714 462 29.4 33.1
Plants
*Volume required by the process. Additional volume created to avoid GTCC waste due to high alpha levels in oxide film.
9© 2009 Electric Power Research Institute, Inc. All rights reserved.
Improvements in Full System Decons
• Improvement from Indian Point 2 Decon– Average Radwaste Volumes Reduced by 77 %– Average Decontamination Factors Have
Increased by 3.4 Times (7.8 to 26.1)•Estimated Dose Savings:
– Indian Point-2: 3,500 Rem (Over 5 cycles)– Connecticut Yankee: 1,197 Rem (For
Decommissioning)•Typical FSD Duration: 10 days•Could be performed During 10 year ISI•Performed at European Operating Plants
10© 2009 Electric Power Research Institute, Inc. All rights reserved.
Many Robots from Non-Nuclear Applications Can Be Adapted to Radiological Work
11© 2009 Electric Power Research Institute, Inc. All rights reserved.
Robot Designed to Survey and Map Chernobyl
12© 2009 Electric Power Research Institute, Inc. All rights reserved.
ROV Technologies Scarab I and II (Camera and Survey Equipment)
13© 2009 Electric Power Research Institute, Inc. All rights reserved.
Pipe Crawler for Hydrolyzing/Survey of CY Fuel Transfer Tube (Bottom Right Photo is Mock-up)
14© 2009 Electric Power Research Institute, Inc. All rights reserved.
Mock-up Testing for Grasping and Placement of Highly Radioactive Thermal Sleeves
15© 2009 Electric Power Research Institute, Inc. All rights reserved.
Robug III Serpentine Robot Crawls into Nuclear Work Area
16© 2009 Electric Power Research Institute, Inc. All rights reserved.
ROV Technologies Mini-Sub and Sub with Gripper (Underwater Survey and Inspection)
17© 2009 Electric Power Research Institute, Inc. All rights reserved.
Track-Mounted Remote Cutting and Welding Equipment Welding Reactor Vessel Canister at CY
18© 2009 Electric Power Research Institute, Inc. All rights reserved.
Partitioning of CY Steam Generator Performed with a Track-Mounted Cutter
19© 2009 Electric Power Research Institute, Inc. All rights reserved.
Magnetic Crawler Removing Paint from Ship Hull
20© 2009 Electric Power Research Institute, Inc. All rights reserved.
Small and Large Hydrolyzer Systems
21© 2009 Electric Power Research Institute, Inc. All rights reserved.
Example on A Multi-Use Robot at CY
22© 2009 Electric Power Research Institute, Inc. All rights reserved.
L.A. Grant Model GMM-1400 Robotic Arm Used at CY with Saw and Electromagnet
23© 2009 Electric Power Research Institute, Inc. All rights reserved.
Mock-up Testing and Work Location for Cutting of CY Neutron Shield Tank
24© 2009 Electric Power Research Institute, Inc. All rights reserved.
Refueling Cavity at End of CY Reactor Internals Segmentation Project: Cleanup with Robotic Arm
25© 2009 Electric Power Research Institute, Inc. All rights reserved.
Grant Robotic Arm Vacuuming Reactor Cavity Floor and as Used to Perform Underwater Cutting
26© 2009 Electric Power Research Institute, Inc. All rights reserved.
Grant Machine Hydrolyzer Head and Remote Control Station
27© 2009 Electric Power Research Institute, Inc. All rights reserved.
Benefits Derived From the Use of Multi-Purpose Robots in Decommissioning
•Efficiently Dismantle Systems, Structures, and Components
•Minimize Proximity and Duration of Exposure to Radioactive and Hazardous Materials
•Minimizes the Risk and Consequences of Personnel Error in Hazardous Environments
•Potentially Same Benefits for Operating Plants
28© 2009 Electric Power Research Institute, Inc. All rights reserved.
– Upper Guide Structure, Upper Core Barrel and Core Support Structure packaged with Reactor Vessel
• Package Limits – 1000 Tons
– Mid-core region segmented and packaged:
• Land disposal of Class A• Class B/C Stored on Site
Until Disposal Available• ISFSI for GTCC
– Contact Dose Rate Up to 1.0E04 R/hr
Overview of Reactor Internals Segmentation
29© 2009 Electric Power Research Institute, Inc. All rights reserved.
Core Baffle Assembly at CY
30© 2009 Electric Power Research Institute, Inc. All rights reserved.
Cutting Technologies
Abrasive Water Jet
Metal Disintegration Machining
31© 2009 Electric Power Research Institute, Inc. All rights reserved.
Benefits of Benchmarking Previous Experience
Comparison of Reactor Internal Segmentation Projects
050
100150200250
Con
nect
icut
Yan
kee
(200
0)
Mai
neY
anke
e(2
001)
San
Ono
freU
nit 1
(200
1)
Ran
cho
Sec
o(2
005)
Rem Project Dose Rem
32© 2009 Electric Power Research Institute, Inc. All rights reserved.
Rancho Seco Reactor Vessel Segmentation
33© 2009 Electric Power Research Institute, Inc. All rights reserved.
34© 2009 Electric Power Research Institute, Inc. All rights reserved.
Waterjet Manipulator
35© 2009 Electric Power Research Institute, Inc. All rights reserved.
Segmenting Rancho Seco Reactor Vessel
36© 2009 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning Lessons Learned with Operating Plant Applicability
•Full System Chemical Decontaminations Can Result in Very Large Exposure Savings with Small Impact on Refueling Outage
•Robotics and Remote Controlled Equipment can Greatly Reduce Cost, Help Avoid Overexposures
•Mutli-Use Machines Can Increase the Cost-Benefit Ratios for Remote Controlled Equipment
•Fully Test Remote Equipment Prior to RCA Use•Benchmarking Previous Experience Can Greatly Save Exposure
37© 2009 Electric Power Research Institute, Inc. All rights reserved.
EPRI Reports with Additional Information
•Application of Non-Nuclear Robotics to Nuclear Industry Decommissioning (EPRI Report # 1009571, 2004)
•Evaluation of the Decontamination of the Reactor Coolant Systems at Maine Yankee and Connecticut Yankee (EPRI Report # TR-112092, 1999)
•Connecticut Yankee Decommissioning Experience Report (EPRI Report # 1013511, 2006)
•Reactor Pressure Vessel Internals Segmentation Experience Report (EPRI Report #1003029, 2007)
•Rancho Seco Reactor Vessel Segmentation Experience Report (EPRI Report #1015501, 2008)