applicability of alara lessons learned from

37
Applicability of ALARA Lessons Learned from Decommissioning Projects to Operating Plants 2009 ISOE North American ALARA Symposium/ EPRI Radiation Protection Conference January 12-14, 2009 Rich McGrath EPRI

Upload: others

Post on 12-Nov-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Applicability of ALARA Lessons Learned from

Applicability of ALARA Lessons Learned from Decommissioning Projects to Operating Plants 2009 ISOE North American ALARA Symposium/ EPRI Radiation Protection ConferenceJanuary 12-14, 2009Rich McGrath EPRI

Page 2: Applicability of ALARA Lessons Learned from

2© 2009 Electric Power Research Institute, Inc. All rights reserved.

Discussion Topics

•Decommissioning Projects Compared to Operating Projects

•Decommissioning Chemical Decontamination Experience

•Typical Uses of Robotics in Decommissioning

•The Benefits of Benchmarking Previous Experience

Page 3: Applicability of ALARA Lessons Learned from

3© 2009 Electric Power Research Institute, Inc. All rights reserved.

10 US Decommissioning Plant Statusfuel in dry storage at most sites

Yankee Rowe

180MW PWR complete

Trojan

1100MW PWR, complete

Maine Yankee

900MW PWR, complete

Connecticut Yankee

600MW PWR complete

Rancho Seco

900MW PWR, ~90% complete

San Onofre 1

450MW PWR, Remediation complete, FSS at a later date

Big Rock Point

65MW BWR complete

Saxton

23MW PWR, complete

Zion

2, 1040MW PWRs, 2017

Humboldt Bay

63MW BWR 2015

Page 4: Applicability of ALARA Lessons Learned from

4© 2009 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning vs. Operating ALARA

• Operating Plant Projects (High Dose):– In Service Inspection (incl. S/G Inspections)– Piping Modifications– Occasional Large Projects (i.e., S/G Replacements)

• Decommissioning Projects (High Dose):– Movement of Fuel to Dry Storage– Removal of All Contaminated Systems

• Primary Systems Components (Includes Reactors, S/G)

• Other Piping Systems and Components– Decontamination of Highly Contaminated Structures

• Decommissioning Involves a Huge Number of RWP Hours

Page 5: Applicability of ALARA Lessons Learned from

5© 2009 Electric Power Research Institute, Inc. All rights reserved.

Scope of Typical Full System Decon (FSD) –PWR (Connecticut Yankee)

Page 6: Applicability of ALARA Lessons Learned from

6© 2009 Electric Power Research Institute, Inc. All rights reserved.

Temporary Equipment for FSD

Page 7: Applicability of ALARA Lessons Learned from

7

Reactor Coolant System Exposure Rate Reduction

0

200

400

600mr/hr

800

1000

7/24 7/25 7/26 7/27 7/28 7/29 7/30 7/31 8/1 8/2

PZR SPRAY LI(Loc#2)

1 BYPASS*(Loc#7)

CVCS LD 1 IN(Loc#8)

2 BYPASS*(Loc#14)

2 BYPASS*(Loc#14)

4 BYPASS *(Loc#26)

DRAIN 4*(Loc#28)

Rgn Hx Ret.(Loc#30)

Page 8: Applicability of ALARA Lessons Learned from

8© 2009 Electric Power Research Institute, Inc. All rights reserved.

Comparison FSD at PWRs

Surface Area (m2)

Metal Removed

Activity (Ci)

Resin Waste DFs

SS Inconel (Kg) Co-60 (ft3) RCS Aux Sys.

Indian Point-2 (1995) 6000 14,000 128 3906 1770 7.9 5.8

Connecticut Yankee (1998) 1,997 929 182 129 115* 17.6 9.8

Maine Yankee (1998) 465 139 307 99 537 8.7 44.8

Stade - Germany (2007) 5,000 12,000 231 630

(total) 540 47.8 17.9

Zorita - Spain (2007) 894 2,313 234 714 462 29.4 33.1

Plants

*Volume required by the process. Additional volume created to avoid GTCC waste due to high alpha levels in oxide film.

Page 9: Applicability of ALARA Lessons Learned from

9© 2009 Electric Power Research Institute, Inc. All rights reserved.

Improvements in Full System Decons

• Improvement from Indian Point 2 Decon– Average Radwaste Volumes Reduced by 77 %– Average Decontamination Factors Have

Increased by 3.4 Times (7.8 to 26.1)•Estimated Dose Savings:

– Indian Point-2: 3,500 Rem (Over 5 cycles)– Connecticut Yankee: 1,197 Rem (For

Decommissioning)•Typical FSD Duration: 10 days•Could be performed During 10 year ISI•Performed at European Operating Plants

Page 10: Applicability of ALARA Lessons Learned from

10© 2009 Electric Power Research Institute, Inc. All rights reserved.

Many Robots from Non-Nuclear Applications Can Be Adapted to Radiological Work

Page 11: Applicability of ALARA Lessons Learned from

11© 2009 Electric Power Research Institute, Inc. All rights reserved.

Robot Designed to Survey and Map Chernobyl

Page 12: Applicability of ALARA Lessons Learned from

12© 2009 Electric Power Research Institute, Inc. All rights reserved.

ROV Technologies Scarab I and II (Camera and Survey Equipment)

Page 13: Applicability of ALARA Lessons Learned from

13© 2009 Electric Power Research Institute, Inc. All rights reserved.

Pipe Crawler for Hydrolyzing/Survey of CY Fuel Transfer Tube (Bottom Right Photo is Mock-up)

Page 14: Applicability of ALARA Lessons Learned from

14© 2009 Electric Power Research Institute, Inc. All rights reserved.

Mock-up Testing for Grasping and Placement of Highly Radioactive Thermal Sleeves

Page 15: Applicability of ALARA Lessons Learned from

15© 2009 Electric Power Research Institute, Inc. All rights reserved.

Robug III Serpentine Robot Crawls into Nuclear Work Area

Page 16: Applicability of ALARA Lessons Learned from

16© 2009 Electric Power Research Institute, Inc. All rights reserved.

ROV Technologies Mini-Sub and Sub with Gripper (Underwater Survey and Inspection)

Page 17: Applicability of ALARA Lessons Learned from

17© 2009 Electric Power Research Institute, Inc. All rights reserved.

Track-Mounted Remote Cutting and Welding Equipment Welding Reactor Vessel Canister at CY

Page 18: Applicability of ALARA Lessons Learned from

18© 2009 Electric Power Research Institute, Inc. All rights reserved.

Partitioning of CY Steam Generator Performed with a Track-Mounted Cutter

Page 19: Applicability of ALARA Lessons Learned from

19© 2009 Electric Power Research Institute, Inc. All rights reserved.

Magnetic Crawler Removing Paint from Ship Hull

Page 20: Applicability of ALARA Lessons Learned from

20© 2009 Electric Power Research Institute, Inc. All rights reserved.

Small and Large Hydrolyzer Systems

Page 21: Applicability of ALARA Lessons Learned from

21© 2009 Electric Power Research Institute, Inc. All rights reserved.

Example on A Multi-Use Robot at CY

Page 22: Applicability of ALARA Lessons Learned from

22© 2009 Electric Power Research Institute, Inc. All rights reserved.

L.A. Grant Model GMM-1400 Robotic Arm Used at CY with Saw and Electromagnet

Page 23: Applicability of ALARA Lessons Learned from

23© 2009 Electric Power Research Institute, Inc. All rights reserved.

Mock-up Testing and Work Location for Cutting of CY Neutron Shield Tank

Page 24: Applicability of ALARA Lessons Learned from

24© 2009 Electric Power Research Institute, Inc. All rights reserved.

Refueling Cavity at End of CY Reactor Internals Segmentation Project: Cleanup with Robotic Arm

Page 25: Applicability of ALARA Lessons Learned from

25© 2009 Electric Power Research Institute, Inc. All rights reserved.

Grant Robotic Arm Vacuuming Reactor Cavity Floor and as Used to Perform Underwater Cutting

Page 26: Applicability of ALARA Lessons Learned from

26© 2009 Electric Power Research Institute, Inc. All rights reserved.

Grant Machine Hydrolyzer Head and Remote Control Station

Page 27: Applicability of ALARA Lessons Learned from

27© 2009 Electric Power Research Institute, Inc. All rights reserved.

Benefits Derived From the Use of Multi-Purpose Robots in Decommissioning

•Efficiently Dismantle Systems, Structures, and Components

•Minimize Proximity and Duration of Exposure to Radioactive and Hazardous Materials

•Minimizes the Risk and Consequences of Personnel Error in Hazardous Environments

•Potentially Same Benefits for Operating Plants

Page 28: Applicability of ALARA Lessons Learned from

28© 2009 Electric Power Research Institute, Inc. All rights reserved.

– Upper Guide Structure, Upper Core Barrel and Core Support Structure packaged with Reactor Vessel

• Package Limits – 1000 Tons

– Mid-core region segmented and packaged:

• Land disposal of Class A• Class B/C Stored on Site

Until Disposal Available• ISFSI for GTCC

– Contact Dose Rate Up to 1.0E04 R/hr

Overview of Reactor Internals Segmentation

Page 29: Applicability of ALARA Lessons Learned from

29© 2009 Electric Power Research Institute, Inc. All rights reserved.

Core Baffle Assembly at CY

Page 30: Applicability of ALARA Lessons Learned from

30© 2009 Electric Power Research Institute, Inc. All rights reserved.

Cutting Technologies

Abrasive Water Jet

Metal Disintegration Machining

Page 31: Applicability of ALARA Lessons Learned from

31© 2009 Electric Power Research Institute, Inc. All rights reserved.

Benefits of Benchmarking Previous Experience

Comparison of Reactor Internal Segmentation Projects

050

100150200250

Con

nect

icut

Yan

kee

(200

0)

Mai

neY

anke

e(2

001)

San

Ono

freU

nit 1

(200

1)

Ran

cho

Sec

o(2

005)

Rem Project Dose Rem

Page 32: Applicability of ALARA Lessons Learned from

32© 2009 Electric Power Research Institute, Inc. All rights reserved.

Rancho Seco Reactor Vessel Segmentation

Page 33: Applicability of ALARA Lessons Learned from

33© 2009 Electric Power Research Institute, Inc. All rights reserved.

Page 34: Applicability of ALARA Lessons Learned from

34© 2009 Electric Power Research Institute, Inc. All rights reserved.

Waterjet Manipulator

Page 35: Applicability of ALARA Lessons Learned from

35© 2009 Electric Power Research Institute, Inc. All rights reserved.

Segmenting Rancho Seco Reactor Vessel

Page 36: Applicability of ALARA Lessons Learned from

36© 2009 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning Lessons Learned with Operating Plant Applicability

•Full System Chemical Decontaminations Can Result in Very Large Exposure Savings with Small Impact on Refueling Outage

•Robotics and Remote Controlled Equipment can Greatly Reduce Cost, Help Avoid Overexposures

•Mutli-Use Machines Can Increase the Cost-Benefit Ratios for Remote Controlled Equipment

•Fully Test Remote Equipment Prior to RCA Use•Benchmarking Previous Experience Can Greatly Save Exposure

Page 37: Applicability of ALARA Lessons Learned from

37© 2009 Electric Power Research Institute, Inc. All rights reserved.

EPRI Reports with Additional Information

•Application of Non-Nuclear Robotics to Nuclear Industry Decommissioning (EPRI Report # 1009571, 2004)

•Evaluation of the Decontamination of the Reactor Coolant Systems at Maine Yankee and Connecticut Yankee (EPRI Report # TR-112092, 1999)

•Connecticut Yankee Decommissioning Experience Report (EPRI Report # 1013511, 2006)

•Reactor Pressure Vessel Internals Segmentation Experience Report (EPRI Report #1003029, 2007)

•Rancho Seco Reactor Vessel Segmentation Experience Report (EPRI Report #1015501, 2008)