application (f orm-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 ·...

36
APPLICATION (FORM-1) FOR SUBMISSION TO MOEF FOR EXTENSION OF VALIDITY OF ENVIRONMENTAL CLEARENCE ( REF.NO-J-13012/240/2007-IAII(T) DATED 30 TH OCTOBER 2009 OF 2X660 THERMAL POWER PROJECT at Devirikala , Gadhva , Karchhana Tehsil, Allahabad district, Uttar Pradesh Project Proponent: Karchhana Power Generation Company Limited Noida, UP September 2014

Upload: others

Post on 12-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

APPLICATION (FORM-1)FOR

SUBMISSION TO MOEF FOR EXTENSION OF VALIDITY OF

ENVIRONMENTAL CLEARENCE

( REF.NO-J-13012/240/2007-IAII(T) DATED 30TH OCTOBER 2009

OF

2X660 THERMAL POWER PROJECT

at

Devirikala , Gadhva , Karchhana Tehsil, Allahabad district, Uttar Pradesh

Project Proponent:

Karchhana Power Generation Company Limited

Noida, UP

September 2014

Page 2: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

APPENDIX –I

FORM-1

(I) Basic Information

S.No. Item Details1 Name of the project/s 2X660 MW Thermal Power Project at Karchhana of

Sangam Power Generation Company Limited2 S.No. in the schedule Activity 1 (d)3 Proposed capacity/

area/length/tonnage to be handled/ command area/leasearea/number of wells to be drilled

2X660 MW Super Thermal Power Project usingSuper Critical Technology

4 New/Expansion/Modernization Project under implementation ( EnvironmentalClearance granted vide letter No.J-13012/240/2007-IAII(T) DATED 30TH OCTOBER 2009

5 Existing capacity/Area ETC Not Applicable as project is under implementation6 Category of Project i.e. “’A” or “B” Category “A”7 Does it attract the general

conditions? If Yes, please specify.Not Applicable

8 Does it attract the specificcondition? If yes, please specify.

Not Applicable

9 Location Village-Dehli Phagesar, Kachra, Karchhana Tehsil,Allahabad district, Uttar Pradesh

Latitude : 250 11’ 26”’ NorthLongitude : 820 01’ 11” East

The index map and location is presented inAnnexure – 1

Plot/Survey/Khasra No.Village Dehli Phagesar, KachraTehsil KarchhanaDistrict AllahabadState Uttar Pradesh

10 Nearest railway station/airportalong with distance in kms

Nearest railway station- Bheerpur , 3 kmNearest airport – Bamruali , Allahabad , 33 km , NW

11 Nearest town, city, DistrictHeadquarters along with distancein kms

Nearest Town – Allahabad 33 km , NWNearest city – Allahabad , 33 km, NWDistrict Headquarters – Allahabad 33 km, NW

12 Village Panchyats, Zila Parishad,Municipal Corporation, Local Body( Complete postal addresses withtelephone nos .to be given)

Village-Dehli Phagesar, Kachra, Karchhana Tehsil,Allahabad district, Uttar Pradesh

13 Name of applicant Sangam Power Generation Company Limited( SPGCL)

Page 3: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

14 Registered address Sector – 128 , Noida -201304, Uttar Pradesh

15 Address for correspondence Sector – 128 , Noida -201304, Uttar PradeshName Manoj GaurDesignation owner/Partner / CEO) Executive ChairmanAddress Sector – 128 , Noida -201304, Uttar PradeshPin Code 201304E-mail [email protected] No. 0120-4609000Fax No. 0120-4609464

16. Details of Alternative sitesexamined, if any. Location of thesesites should be shown on a toposheet.

Since it is implementation.

17 Interlinked Projects Nil18 Whether separate application of

inter liked project has beensubmitted

Not applicable

19 If yes, date of submission Not applicable20 If no, reason Not applicable21 Whether the proposal involves

approval/clearance under:(a) The Forest ( Conservation)

Act 1980(b) The wildlife ( Protection)

Act, 1972(c) The C.R.Z. Notification,

1991

Not applicable

22 Whether there is any Governmentorder/Policy relevant/relating tothe site.

No

23 Forest Land involved ( hectares) Nil24 Whether there is any litigation

pending against the project and /orland in which the project ispropose to be setup

(a) Name of the court(b) Case no(c) Orders/direction of the

court, if any and itsrelevance with theproposed project.

No

Page 4: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

(ii) Activity

Construction, operation or decommissioning of the Project involving actions, which willcause physical changes in the locality ( topography, land use, changes in water bodiesetc)

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof ( with approximatequantities/rates, wherever possible)with source of information data

1.1 Permanent or temporary change inland use, land cover or topographyincluding increase in intensity ofland use ( with respect to localland use plan)

Yes Change of nature of land use from barrenland to industrial

1.2 Clearance of existing land,vegetation and building?

No The land is barren, dusty, loose, devoid ofvegetation and in habited.

1.3 Creation of new land uses Yes Industrial use

1.4 Pre-construction investigations e.g.bore houses, soil testing?

Yes Soil testing etc will be done as perrequirement

1.5 Construction works? Yes Construction work will be taken up forproposed Power Plant

1.6 Demolition works? No -

1.7 Temporary sites used forconstruction works or housing ofconstruction workers?

Yes Temporary accommodation would beprovided for contract labour duringconstruction phase

1.8 Above ground buildings, structuresor earthworks including linearstructures, cut and fill orexcavations.

Yes Installation of proposed Power Plant

1.9 Underground works includingmining or tunnelling?

Yes May be minor

1.10 Reclamation works? No Not applicable1.11 Dredging? No Not applicable1.12 Offshore structures? No Not applicable1.13 Production manufacturing

process?Yes Coal based thermal Power Plant-

Electricity Generation. The brief processdescription along with process flowdiagram is enclosed as Annexure- 2

1.14 Facilities for storage of goods ormaterials?

Yes

1.15 Facilities for treatment or disposalof solid waste or liquid effluents?

Yes Ash ponds and Effluent Treatment Plantwill be provided

1.16 Facilities for long term housing ofoperational workers?

Yes Colony is proposed to be developed

Page 5: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

1.17 New road, rail or sea traffic duringconstruction and operation?

Yes Strengthening of existing roads, railwaysystem as per requirement

1.18 New road, rail, air water borne orother transport infrastructureincluding new or altered routesand stations, ports, airports etc?

Yes The proposed site is located about 2-3 kmfrom the nearest railway station. Therailway line falls on main broad gaugeHowrah- Allahabad line. Strengthening ofexisting roads, railway system would bemade as per requirement.

1.19 Closure or division of existingtransport routes or infrastructureleading to changes in trafficmovements?

No

1.20 New or diverted transmission linesor pipelines?

Yes Existing 132 KV of Transmission line ofRailways and 132 KV transmission line ofUPPCL need to be diverted

1.21 Impoundment, damming,culverting, realignment or otherchanges to the hydrology of watercourses or aquifers?

Yes Minor in nature

1.22 Stream crossings? No

1.23 Abstraction or transfers of waterfrom ground or surface waters?

Yes Abstraction of water (~ 5000 m3 / Hr)from surface ( Yamuna river)

1.24 Changes in water bodies or theland surface affecting drainage orrun off.

No

1.25 Transport of personnel ormaterials for construction,operation or de-commissioning?

Yes With the help of existing road systemthrough its strengthening

1.26 Long- term dismantling ordecommissioning or restorationworks?

No

1.27 Ongoing activity duringdecommissioning which couldhave an impact on theenvironment?

No

1.28 Influx of people to an area in eithertemporarily of permanently?

Yes Temporarily influx of construction labour

1.29 Introduction of alien species? No

1.30 Loss of native species or geneticdiversity?

No

1.31 Any other No

2.0 Use of Natural resources for construction or operation of Project ( Such as land, water,materials or energy, especially any resources which are non-renewable or in shortsupply)

Page 6: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

2.1 Land specially undeveloped oragricultural land (ha)

Yes Approximate 401 hectares fromDevrikala, Gadhva, Bhitar, Kachra, Kachrivillages

2.2 Water ( expected source &competing users) unit KLD

Yes Water (~ 4600m3/hr) will be used fromYamuna river. Water allocation byIrrigation Dept. U.P. Govt. Consideringsufficient quantity of water available forthe downstream competent users.

2.3 Minerals( MT) Yes Coal (~ 16560 MT/Day)

2.4 Construction materials stone,aggregates and / soil ( expectedsources=-MT)

Yes Stone blast as construction materials willbe coming from stone quarries andcement will be coming from nearbycement factory.

2.5 Forests and timber( source-MT) No

2.6 Energy including electricity andfuels etc.( source, competingusers) unit: fuel ( MT), energy (MW)

Yes Coal (~ 16560 MT/Day) will be used forelectricity generation as allocated byMinistry of Coal.

2.7 Any other natural resources ( useappropriate standard units)

No

3.0 Use, storage, transport, handling or production of substances or materials , whichcould be harmful to human health or the environment or raise concerns about actualor perceived risks to human health

3.1 Use of substances or materialswhich are hazardous ( as perMSIHC rules) to human health orthe environment ( flora, fauna ,and water supplies)

No

3.2 Changes in occurrence of diseaseor affect diseases vectors ( e.g.insect or water borne diseases)

No

3.3 Affect the welfare of people e.g. bychanging living conditions?

Yes Positive impact on people. Moreemployment ( direct and indirect)opportunities will be created andlivelihood of local people will beimproved through improvement ofexisting infrastructure viz. Schools,hospital/medical facilities, toad, drinkingwater , electricity etc.

3.4 Vulnerable groups of people whocould be affected by the projecte.g. hospital patients, children , theelderly etc

No

Page 7: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

3.5 Any other causes No4. Production of solid wastes during construction or operation or decommissioning (

MT/Month)4.1 Spoil, overburden or mine wastes No4.2 Municipal waste( domestic and or

commercial wastes)Yes There will be some addition due to

construction and operation of theproposed units in the power plant.

4.3 Hazardous wastes ( as perhazardous waste managementrules)

No

4.4 Other industrial process wastes Yes Ash generation (~5630 MT/Day)4.5 Surplus product No4.6 Sewage sludge or other sludge

from effluent treatmentYes Sewage treatment plant is proposed for

colony4.7 Construction or demolition wastes No4.8 Redundant machinery or

equipmentNo

4.9 Contaminated soils or othermaterials

No

4.10 Agricultural wastes No4.11 Other solid wastes No

5.0 Release of pollutants or any hazardous , toxic or noxious substances to air ( kg/hr)5.1 Emission from combustion of fossil

fuels from stationary or mobilesources

Yes Particulate Matter, SO2 & NOX will beemitted through 275 m tall stackconnected to boilers. Efficient pollutioncontrol devices such as high collectionefficiency ESP will be installed to controlemission from boilers. Dust suppressionsystem/ water sprinkles will be installedto control fugitive emission in coalhandling area.

5.2 Emission from productionprocesses

Yes Emission from boiler will be controlledthrough high collection efficiency ESP andwill be discharged through tall stack forbetter dispersion of gaseous pollutants.

5.3 Emission from materials handlingsincluding storage or transport

Yes Dust extraction system will be installed incoal handling area.

5.4 Emissions from constructionactivities including plant andequipment

No

5.5 Dust or odours from handling ofmaterials including constructionmaterials , sewage and waste

No Water sprinklers shall be used. Sewageand waste water shall be treated.

5.6 Emission from incineration ofwaste

No

Page 8: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

5.7 Emission from burning of waste inopen air ( e.g. slash materials,construction debris)

No

5.8 Emission from any other sources No6.0 Generation of Noise and Vibration and emission of Light and heat6.1 From operation of equipment e.g.

engines, ventilation plant, crushersYes It is expected during operation of power

plant. Effort will be made to meetstatutory noise level while selectingequipments.

6.2 From industrial or similarprocesses

No

6.3 From construction or demolition No6.4 From blasting or piling No6.5 From construction or operational

trafficNo

6.6 From lighting or cooling systems No6.7 From any other sources No7.0 Risks of contamination of land or water from releases of pollutants into the ground or

into sewers, surface waters, groundwater, coastal waters or the sea.7.1 From handling storage, use or

spillage of hazardous materials.No

7.2 From discharge of sewage or othereffluents to water or the land (expected mode and place ofdischarge)

No Treated effluent from the plant will berecycled/ reused for ash slurrypreparation and green belt development.Sewage from colony will be treated in theproposed STP and will be used for GreenBelt Development

7.3 By deposition of pollutantsemitted to air into the land or intowater

No

7.4 Form any other sources No7.5 Is there a risk of long term build up

of pollutants in the environmentfrom these sources?

No

8.0 Risk of accidents during or operation of the project which could affect human health orthe environment

8.1 From explosions, spillages, fires etcfrom storage, handling, use orproduction of hazardoussubstances.

No Adequate safety measures shall be takento eliminate risk of explosion /fire/accident.

8.2 From any other causes No8.3 Could the project be affected by

natural disasters causingenvironmental damage ( e.g.floods, earthquakes, landslides,cloud burst etc)?

No

Page 9: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

9.0 Factors which should be considered ( such as consequential development) which couldlead to environmental effect or the potential for cumulative impacts with otherexisting or planned activities in the locality

9.1 Lead to development of supporting,facilities, ancillary development ordevelopment stimulated theproject which could have impacton the environment e.g.: Supporting infrastructure(

roads, power supply, wasteor waste or waste watertreatment etc)

Housing development Extractive industries Supply industries

No

9.2 Lead to after use of the site, whichcould have an impact on theenvironment

No

9.3 Set a precedent for laterdevelopments

No

9.4 Have cumulative effects due toproximity to other existing orplanned projects with similareffects.

No

(III) Environmental Sensitivity

Sr.No

Areas Name/Identity

Aerial distance ( within 15 km) Proposedproject location boundary

1 Areas protected underinternational conventions, nationalor local legislation for theirecological, landscape, cultural orother related value.

No

2 Areas which are important orsensitive of ecological reasons,wetlands , water courses or otherwater bodies, coastal zone,biospheres, mountains , forests

No

3 Areas used by protected,important or sensitive species offlora or fauna for breeding,nesting, foraging, resting, overwintering, migration

No

4 In land, coastal , marine orunderground waters

No

Page 10: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,
Page 11: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

NOTE:

1. The projects involving clearance under coastal Regulation zone Notification, 1991shall submit with the application C.R.Z. map duly demarcated by one of theauthorized agencies, showing the project activities, w.e.t. C.R.Z. ( at stage of ToR)and the recommendations of the State Coastal Zone Management Authority ( at thestage of EC). Simultaneous action shall also be taken to obtain the requisiteclearance under the provisions of the C.R.Z. Notification, 1991 for the activities to belocated in the CRZ.

2. The projects to be located within 10 km or the National Parks , Sanctuaries,Biosphere Reserves, Migratory Corridors of Wild Animals, the project proponentshall submit the map duly authenticated by Chief Wildlife Warden showing thesefeatures vis-s-vis the project location and recommendations or comments of theChief Wildlife Warden thereon ( at the stage of EC)

3. All Corressponace with the Ministry of Environment & Forests including submissionof application for TOR/Environmental clearance, subsequent clarifications, as may berequired from time to time, participation in the EAC Meeting on behalf of the projectproponent shall be made by the authorized signatory only. The authorized signatoryshould also submit a document in support of his claim of being an authorizedsignatory for the specific project.

Page 12: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,
Page 13: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,
Page 14: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,
Page 15: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

ANNEXURE –2

PROCESS DESCRIPTION

Thermodynamic Cycle:

The thermodynamic cycle for 660 MW super critical unit comprising the Steam Generator,The steam turbine generator, the condenser, the condensate extraction and boiler feedsystems along with all other necessary equipment for single reheat regenerative cycle.Steam parameters at the outlet of the steam generator have been considered to be 255 kgKg / Cm2 (abs), 5680 C with steaming capacity of about 2092 TPH

Corresponding steam parameters at the turbine inlet would be 247 Kg / Cm2 (abs), 5650 Creheated steam temperature would be about 5930. The HP/LP casing design as permanufacturers’ standard.

The exhaust steam from the LP turbine will be cooled in main steam condenser bycirculation of required quantity of cooling water and its vacuum will be maintained by oneof the two (2) 100% capacity vacuum pumps maintaining a backpressure of 76 mmHg ( abs).The condenser would be single pass, horizontal, surface type cooled by circulation of coolingwater (inlet water temp. 33 0 C max.) in a circulating cooling water circuit using wet typecooling tower.

The regenerative feed heating system consist of four stages of low pressure heaters, onegland steam condenser, one separate drain cooler, one spray –cum –tray type deaerator,two parallel chains of high pressure heaters each having 50% capacity and two 50% turbinedriven boiler feed water pumps and two 25% capacity motor driven pumps. The condensatedrawn from condenser hot well by 3x50% (2W+1S) capacity condensate extraction pumpswill be pumped to the deaerator through the LP heaters.

Steam Generator Set:

The steam generators are semi-outdoor, two-pass, drum less, once through, single reheat,balanced draft type with direct pulverised coal firing burners, dry bottom units designed forfiring coal. The steam parameters have been selected as per manufacturers design andburning of high ash coal.

The steam generator is conservatively designed for high ash coal and high efficiency. Theunits are with coal preparation and firing system, fuel oil pumping and firing system, draftsystem comprising of FD,ID and PA fans, electrostatic precipitators and a twin-flue 275 mhigh chimney ( for tow units).

Page 16: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

Light Diesel Oil ( Calorific value around 10,000 Kcal/kg), Heavy Fuel Oil ( Calorific value about10280 Kcal/kg and kinematic viscosity above 170 centistokes at 500 C) would be used asstart-up and stabilization fuels. As per GOI norms, provision for FGD unit is there.

To limit the dust load at the inlet to the chimney to a value prescribed by Ministry ofEnvironment & Forests, Govt Of India, adequate sized electrostatic precipitators have beenprovided.

Turbine Generators Set :

The steam turbines are multi-stage, 3000 rpm, tandem compound, single reheat,regenerative, condensing, multi-cylinder unit capable of operating with super critical steamparameters and with six (6) uncontrolled extractions for regenerative feed water heating.The LP turbine will exhaust against a condenser pressure of 76 mm Hg (abs) and maximumcooling water temperature of 330 C. A quick acting “HP and LP Turbine Bypass Station”provided as a part of steam generator / turbine package. The unit equipped with allauxiliaries.

The team turbines are directly coupled to the horizontally mounted, three phase, two –pole,cylindrical rotor type electric generators and will have a nominal rating of 660 MW atgenerator terminal after meeting power requirement for excitation system. The generationwould be at 0.85 power factor and thus the MVA rating works out to be about 776.5 MVA.The generators will deliver power at the standard voltage between 21 kv , 3 phase, 50 Hz.The generators have class-F insulation rated for class –B temperature rise. The TG sets arecapable of delivering continuously the rated power at rated power factor when the voltagevariation is within ± 5% of rated value and also when frequency variation is with 47.5 Hz and51.5 Hz.

The unis are with 2 x 100% vacuum pumps, horizontal shell and tube type high pressurefeed water heaters with group bypass arrangement, 4 stage horizontal U-tube type lowpressure heaters, drain cooler, bland steam condenser, horizontal spray – cum-tray typedeaerator with integral vent condenser etc.

Plant Water System:

Water requirement for the project will be met from river Yamuna. With the water qualityavailable, water treatment plant would comprise clariflocculation; sand bed filtration anddeminineralization. 100% condensate polishers are installed for TPP. Recirculating coolingwater system using Natural draft cooling towers are deployed. As per water quality, a cycleof concentration of five to six is considered attainable in the CW circuit.

Page 17: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

Coal Handling System

Single coal handling plant (CHP) will be constructed having dedicated coal unloadingterminal. The coal handling plant is the parallel double stream ( one working and onestandby) of belt conveyors along with facilities for receiving, unloading, crushing andconveying the crushed coal to boiler bunkers and reversible stacking/ reclaiming the coalto/from crushed coal stockyard. Rail mounted, stacker-reclaimers, bucket wheel type will beinstalled for coal stock yard management.

Ash Handling System

The bottom ash will be extracted and disposed off in wet form. The fly ash will be extractedin dry form from the electrostatic precipitator hoppers. This dry ash will be taken to bufferhopper for its onward transportation in dry form or can be slurrified in wetting units for itsdisposal in wet form to ash disposal area.

Auxiliary System:

Other auxiliaries viz. Liquid fuel HFO/LDO system, adequately sized compressed air system,Ventilation and Air Conditioning System, Fire Fighting system, piping, valves, fittings &specialties, insulation, painting etc will be provided compatible for the station requirement.Other miscellaneous auxiliaries’ viz. Turbine ol purification plant, chemical feed system,elevators, cranes and hoisting equipment, pollution monitoring equipment etc will beprovided. For other associated facilities viz. Workshop, stores, chemical laboratory etcadequate facilities will be developed to cater the requirement of the station.

Electrical System:

Power evacuation will be done at 400 kv level. Hence one 400 kv switchyard will be installedin the plant. The 400 kv besides serving evacuation of power will also feed the start uppower of the plant.

Page 18: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,
Page 19: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

PRE-FEASIBILTY REPORTFOR

2X660 MW SUPER THERMAL POWER PLANT

AT

Dehli Phagesar, Kachra Village, Karchhana Tehsil,

Allahabad district, Uttar Pradesh

Project Proponent

Karchhana Power Generation Company Limited

Noida, U.P.

September 2014

Page 20: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

TABLE OF CONTENTS

S.No. Contents

1 Executives Summary

2 Introduction of the Project

3 Project Description

4 Site Analysis

5 Project Brief

6 Proposed Infrastructure

7 Rehabilitation and Resettlement ( R&R) Plan

8 Project Schedule & cost estimates

9 Analysis of Proposal

Figures

Figures-1 Index Map

Figures-2 Plant layout

Figures-3 Process Flow Sheet

Page 21: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

1.0 Executives Summary

Table : 1

Brief description of the proposed project

Sr.No. Description Details

1 Name of the project Karchhana / 2X660 MW Sangam PowerGeneration Co Ltd. Karchhana

2 Location of the project Village-Dehli Phagesar, Kachra, KarchhanaTehsil, Allahabad district, Uttar Pradesh

Latitude : 250 11’ 26”’ NorthLongitude : 820 01’ 11” EAST

3 Production 2X660 MW Power generation

4 Total land requirement for theproject

555.63 Acres

5 Total water requirement &source

3508 m3/hr , Yamuna river ( allocation fromirrigation dept for 54 cusec)

6 Rehabilitation & Resettlement Already proposed

7 Manpower ( Operation Phase) Approx 1000 no’s8 Estimated cost of the project Rs 6500 crores

2.0 Introduction of the project / background information

(i) Company Profile

Sangam Power Generation Company Limited ( SPGCL) previously 100% subsidiary ofU.P.Power Corporation Ltd, it was a special purpose company formed and registered inUttar Pradesh.

SPGCL was incorporated by Uttar Pradesh Power Corporation Limited as a StateGovernment Company. JAIPRAKASH Associates Limited ( JAL) was declared as successfulbidder for the project of the company vide LOI dated 20.05.2009 and Jaiprakash PowerVentures Limited( JPVL), an affiliate of JAL, had executed the Share Purpose Agreement(SPA) amongst Uttar Pradesh Power Corporation Ltd( UPPCL), the company, JPVL and JAL,as confirming party for acquiring / purpose of 100% equity share capital of the companyon 23.07.2009.

Page 22: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

Now Sangam Power Generation Company Limited ( SPGCL) a subsidiary of JaiprakashPower Ventures Limited ( JPVL), A Jaypee Group Company is setting up a 2X660 MW coalbased thermal power plant with super critical technology, which is under project stageat Dehli Phagesar, Kachra village, Karchhana Tehsil, Allahabad District, Uttar Pradesh.

Jaypee group is a well-diversified industrial conglomerate in India with a turnover of Rs18000 crores commenced its operation in mid sixties in the businesses of Engineering &Construction, Cement, Private Hydropower, development of Expressways, Real Estateand Hospitality. With a professional management team and a competent technicalcadre, the group employs a total workforce of over 30000.

It is 3rd largest cement producer in India with an operational capacity of 35.9 MTPA. Itshas computerized process control cement plants at various location of central andNorthern region of India.

(ii) Brief description of nature of the project

2X660 MW coal based super thermal power plant is located near Dehli Phagesar, Kachrain Karchhana Tehsil of Allahabad district. The district headquarter Allahabad is around33 kms in NW direction from the project site. The project site is surrounded by NationalHighways No 76 E ( Allahabad – Mirzapur road) on side and Delhi – Hawrah railway lineon other side. Nearest Railway station is Bheerpur around 3 kms from project site. Coalrequirement of the project will be met through coal mines of Northern Coalfield Ltd.Necessary coal linkage has been confirmed by Ministry of Coal for thermal Power projectfrom coal mines of Northern Coalfield Ltd, in Singrrauli region. Mode of coaltransportation from the coal mines to the power plant is through India Railway System.

The water sanction is available from Yamuna River which Is approximately 47kms in westdirection from the project site. The water will be pumped to project site throughunderground pipeline.

An area 555.63 acres is allotted for the project which was mostly barren (waste) andarea around the project site is very thinly populated also there is no major humansettlement exists in the region.

Effluent treatment plant will be installed for effluent generated during operationalphase and it will be treated by primary, secondary and tertiary process. Entire treatedwill be recycled back in process, dust suppression and for green belt development a “Zero Discharge Concept” is adopted.

Page 23: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

(iii) Need of the project

Uttar Pradesh is India’s most populous state with a population of over 186 million.Promoting opportunity is at the center of strategy for development of the state. Powerto all therefore is not only integral but the primary component of the developmentprogram of the state. Uttar Pradesh has been severely constrained in its economicdevelopment and quality of life by the appalling power situation in the State.

Quality power at optimum cost is a catalyst for industrial development of any state. Thestate of Uttar Pradesh has ambitious plans for rapid industrialization. Therefore powergeneration in the state of Uttar Pradesh requires urgent augmentation of generationcapacity.

The present installed capacity in the state of U.P. is insufficient to meet the demand forpower. It is estimated that Peak Power demand in U.P. will rise from current level of10193 MW to 13947 MW by 2011-12. As there is an acute shortage of power in UttarPradesh and this has become the main hindrance in the development of industries andthe State, installation of more thermal power plant on urgent basis in this State becomesimportant.

The project is one of the projects planned to be developed for long term capacityaddition project. The project will help in bridging the gap between supply and demandof power in the State of U.P. and Northern region

(iv) Demand – Supply Gap

The project is one of the projects planned under 10th and 11th plan developed for longterm capacity addition project. The project will help in bridging the gap between supplyand demand of power in the State of U.P. and Northern region.

(v) Export Possibility

There is no possibility of export

(vi) Employment generation

Any production process requires human resources involving both skilled and semi-skilledworkers and thus is same for the Thermal Power Plant. Employment potential createdby this project will be met by takIng the people from the region and thus scope forimproving the socio economic life of the region and contributes to increase in GDP as awhole.

Besides , unskilled workforces mostly from the nearby area are required for cleaning &other day to day jobs will be hired through contractor.

Page 24: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

Due to the installation of the project direct or indirect employment generation will bethere. The project is under implementation man power engaged during construction isaround 5000 to 7000 and during operation phase around1000 skilled persons arerequired other than unskilled personnel.

3.0 Project Description

(i) Project Site

2X660 MW caol based thermal power plant is located near Dehli Phagesar, Kachravillages in Karchhana Tehsil of Allahabad district. The project site is surrounded byNational Highway No 76 E on one side and Delhi- Howrah railway line on other side. Theindex map and the location of the proposed project site in the district map are enclosedin Figure 1.

(ii) Location and Accessibility

The project is located adjacent to the National Highway No 76 E on Allahabad toMirzapur section. Nearest Railway Station is a Bheerpur on Delhi – Howrah railway linewhich passes through Allahabad. Bheerpur railway station is around 3 kms from site andAllahabad airport is around 35 km from the site. The project site is well connected withmajor towns and cities in the region. The district head quarter Allahabad is around 33kms in NW direction from project site.

(iii) Alternate sites

Not applicable

Page 25: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,
Page 26: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

v

Page 27: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

(iv) Project Technical Concept

˃ Infrastructure

Power

Proposed one is coal based thermal power plant based on super critical technologywill be generating around 1320 MW of power.

Water

Water requirement for TPP is around 3508 m3/Hrs which will be met from YamunaRiver. Water allocation of 96 cusecs is in place from Central water Commission,Irrigation Planning (North) DTE Including Bara Power Plant.

Environmental Aspects

Thermal power plants invariably have potential environmental effects during boththe construction and operational phases including effects on air, water, noise & landenvironments as well as socio-economic conditions during construction phase.During construction phase, significance of construction impacts are limited asmeasures will be taken for traffic management, appropriate timing and routing ofmaterials, delivery, maintenance of sanitary facilities etc.

During operation of thermal power plant environmental effects on air quality will beminimized through implementation of mitigation measures viz. installation of highefficiency ( 99.89% ) ESP’s for collection of fly ash from the boilers, ESP designed for50 mg/NM3 in operation and installation of tall stacks of 275 meters for betterdispersion of flues gases.

A comprehensive Environmental Impact Assessment ( EIA) study had been carriedout by BHEL Haridwar and requisite Environment Management Plan ( EMP) isprepared , based on EIA study. Based on EIA study MoEF has granted EnvironmentalClearance to the project in year 2009

The technical concept of Thermal Power Plant

Page 28: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

Table – 2

TECHNICAL DETAILS OF THERMAL POWER PLANT

Sr. No. Details of Equipment/ Configuration 2X660MWA BOILER

Type Pulverised fuel fired boilersNos of Boiler 2Maximum Continuous RATING 2095 TPHSuperheated Steam Pressure 242 bar (a)Superheated steam Temperature 565o C/5930CFuel Indian Coal

B STEAM TURBINENo of Turbine 2Type Condensing multistageInlet Steam Pressure 242 bar(a)Inlet steam Temperature 565o C/5930CCondenser Vacuum 0.22 kg/cm2 (a)Generated Power ( MCR) 1320 MW at 400 kvNos of Bleed 4

C GENERATORType Once through semi outdoorRated capacity 660MWRated power Factor 0.85Voltage 21 KVFrequency 50HzNo of phase 3Insulation class F ( Temperature rise limit to class B)Winding connection WyeGrounding Resistance groundingSpeed 3000 rpm

D WATER COOLED CONDENSERNos of condenser 2Type Natural DraftSteam inlet quantitySteam inlet pressure 0.22 kg/cm2 (a)

E COAL REQUIREMENTINDIAN COAL)

16560 MT/DAY

Note : The GCV of coal have been selected as 4400 Kcal/Kg

Page 29: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

F ASH GENERATIONa) Fly ash 1.64 MTPAb) Bottom ash 0.41 MTPA

G MAKE –UP WATERREQUIREMENT

3508 m3 / hr

Cooling tower 2836 m3 / hrDM Water 54.42 m3 / hr

H EFFLUENT GENERATION 688 m3 / day

I MANPOWER REQUIRED Approx.1000 during Operation phase

APPROX. COST OF PROJECT 6500 CRORES

COAL CHARACTERISTICS

S.No. Parameter Range of CoalJayant Project Dudhichua

ProjectMean

1 Total Moisture Content 4.8-10.4% 2.9-8.8% 6.6%

2 Volatile Matters 18.0-31.6% 18.9-31.6% 25.9%

3 Ash 20.8-46.8% 20.0-53.2% 34.1%

4 Carbon 79.5-81.7% 78.7-81.5% 80.2%

5 Hydrogen 4.8-5.2% 4.8-5.0% 4.9%

6 Nitrogen 1.6-1.8% 1.8-2.0% 1.8%

7 Sulphur 0.3-0.5% 0.3-0.5% 0.4%

8 Oxygen 11.2-12.6% 11.1-14.1% 12.3%

9 Gross calorific Value (Kcal/Kg)

2890-5230 1070-5390 4175

Page 30: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,
Page 31: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

4. Site Analysis

Infrastructure

For successful operation of power plant, it is imperative to ensure availability of thefollowing infrastructure:

Away from CRZ area No structure of archaeological importance No R&R issues No wild life sanctuaries / protected sensitive zones Coal from Northern coal field

(i) Connectivity

The project site is well connected with major towns and cities in the region. The projectis located adjacent to the National Highway No 76 E on Allahabad – Mirzapur section.Nearest Railway Station is at Bheerpur on Delhi-Howrah rail line which passes throughAllahabad. Bheerpur railway station is around 3 kms from site and Allahabad air port isaround 35 kms from the site.

(ii) Land Form

555.63 acres of land will be utilised for thermal power project. It is mostly barren (waste) land the area around the proposed project site is very thin populated also thereis no major human settlement exits in the region.

(iii) Topography

The elevation of the project site about 91.6 m above mean sea level.

(iv)Soil Classification

The project falls under Karchhana block of karchhana tehsil which is under Yamunaaparregion. The proposed site falls in Vindhya Hills and plateau with hard rock strata. Northof Karchhana is crowned with light sandy soil.

(v) Climatic data from secondary sources

The area has wet bulb and dry bulb temperatures are 12 0c and 450c respectively. Themonsoon starts in early July and continues up to September. The temperature observedin summer 43 to 300 C and in winter 25 to 3 0 C. The average annual rainfall is 907.3 mmwith a monthly maximum of 274.8 mm in August.

Page 32: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

(vi) Environmental setting

The detail of environmental setting of project is presented in Table 3

TABLE-3

DETAILS OF ENVIRONMENTAL SETTING

Sr. No. Particulars Proposed Captive Power Plant

1 Longitude/Latitude Latitude : 250 11’ 26”’ NorthLongitude : 820 01’ 11” East

2 Nearest highway Allahabad-Mirzapur highway No 76 E

3 Nearest Railway line Nearest railway station- Bheerpur , 3km on Delhi – Harwah main rail line

4 Nearest Airport along with distancein kms

Nearest airport – Bamruali , Allahabad, 35 km , NW

5 Nearest town/city, districtHeadquarters along with distance inkms

Nearest Town – Allahabad 33 km , NWNearest city – Allahabad , 33 km, NWDistrict Headquarters – Allahabad 33km, NW

6 Forest land involved ( hectares) No forest land involved

7 Reserved / Protected Forests Nil

8 National Parks / Wildlife Sanctuaries There is no National park and wildlifesanctuary is within 10 km radius fromthe plant site

9 Nearest Rivers Tons River – 500 m from project siteYamuna River- 47 km from project site

4.0 Planning Brief

(i) Land use Planning

The Power Plant is under implementation which is already under industrial use.

Page 33: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

(ii) Assessment of infrastructure demand ( Physical & Social)

The nearest town and city is Allahabad located a distance of 33 KMS from the projectsite. Allahabad is a District Headquarter. The facilities like education; social amenities areavailable in the region. The influx of the people will not have any impact on the existinginfrastructure.

(iii) Amenities/ Facilities

The following facilities will be developed at the project site for-

- Main building- Transformer Yard- Switch Yard- Main stack & By pass stack- Control/Electrical building- Cooling towers , CW pump house- Coal Yard- Railway siding- Administration Building- DM Plant Building- Security and time office- First aid & Fire Station- Ash & water pipelines- Green belt area- Ash disposal- Township

Service Buildings

Office building, statutory building such as first aid centre, rest shelter, canteen etc provided.

Roads

The site is adjacent to National highway, well connected to road and railway. No new roador diversion is proposed. Existing road will be adequate for additional load oftransportations and for movement of heavy plant and machinery. Railway siding will beinstalled within plant premises.

5.0 PROPOSED INFRASTRUCTURE

(I) Industrial area ( processing area)

No any industries are situated with 10 km radius of project site.

Page 34: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

For power plant the coal will be used as fuel. For bringing the coal to the through rail, apermanent railway siding is constructed. Coal transportation from coal mines to the powerplant is through Indian Railway System / Road. The rakes shall be unloaded at the wagontippler /track hopper terminal.

Coal Handling Plant (CHP) with dedicated coal unloading terminal will be installed. For coalstorage coal stockyard will have crushed coal storage equivalent to 30 days coalconsumption for 2X660 MW units. Stacker reclaimers installed thus creating a capacity of5,20,000 tons, which will be enough for 30 days. Raw material details are given in table 4 asfollows:

Table: 4

Material Quantity Source Storage Capacity (tonnes)

Coal Indian 16,560 tpd Coal linage with NCL 5,20,000

(II)Residential Area

Full fledged township in 30 hectare of land for employees. Permanent township comprising1000 dwelling units, with all necessary infrastructural facilities, to cater to the requirementof operation & maintenance personnel and other supporting staff of the project.

(iii)Green belt

33% green belt will be developed in the plant area following CPCB/MoEF guidelines, whichwould not only act as lung space in the area but also would improve the aesthetics. Greenbelt will be developed and maintained in all available free space.

Municipal solid waste generated during construction period & during operation period, aswell as from STP will be, will be vermin-composted and used as manure for green beltdevelopment.

(iv) Social Infrastructure

Site facilities for construction such as offices, stores, sheds etc, for SPGCL as well as forcontractor’s use will be provided.

(v) Connectivity

Site is well connected with road and rail network and good infrastructure is available withinareas, which will be adequate for additional load of transportation and for movement ofheavy plant and machinery.

Page 35: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

(vi) Drinking Water Management ( Source & Supply of Water)

Total water requirement for project is 3508 m3/Hr. Water allocation of 96 cusec fromYamuna including Bara thermal power plant will be treated in water treatment plant fordrinking purpose.

(vii) Sewerage System

Domestic sewage will be treated in Sewage Treatment plant and treated water will be usedfor green belt development.

(viii) Industrial Waste Management

a) Industrial effluent

The effluent treatment will be installed through primary, secondary & tertiary treatmentand treated water will be re-used back in system.

b) Domestic effluent

The sewage treatment plant will be treated in a sewage treatment plant. The treatedsewage confirming to prescribe standards will be utilized for plantation purpose.

(viii)Solid waste Management

The maximum ash generation from power plant is about 2.05 MTPA 1.64 MTPA ) is fly ash 0.41 MTPA) is generated as bottom ash

Entire fly ash generate will be pozzolonic material. It will be sold to surroundingcement manufacturers including Jaypee group cement units for PPC Production.

Waste generated from the temporary and workers houses will be suitably disposed.Used oil and grease, discarded batteries, used barrels or container will be disposedthough approved agencies of CPCB. The plant will be developed with “Zero EffluentDischarge” philosophy.

7. REHABILITATION AND RESETTLEMENT ( R&R) PLAN

No R&R issue at this issue.

8. COST ESTIMATES

The project cost for 2X660 MW units works out to Rs 6500 crores.

Page 36: APPLICATION (F ORM-1)environmentclearance.nic.in/writereaddata/modification/... · 2014-10-16 · Nearest city – Allahabad , 33 km, NW District Headquarters ... 128 , Noida -201304,

Analysis of proposal

Proposed thermal power plant based on super critical technology will result inconsiderable growth of service sector.

During construction & operational phase proposed unit require man power, apartfrom contract labour for auxiliary services. This will increase the employmentopportunities in the region.

However, no environmental effects are envisaged due to ancillary development.

No major impacts are envisaged.