approaches and associated costs of building demolition and...

151
Approaches and Associated Costs of Building Demolition and Deconstruction By: Shershah Zahir Professor Matt Syal A Plan B Report Submitted to Michigan State University in the partial fulfillment of the requirements for the degree of MASTERS OF SCIENCE Construction Management 04/07/2015

Upload: others

Post on 23-Aug-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

Approaches and Associated Costs of Building

Demolition and Deconstruction

By: Shershah Zahir

Professor Matt Syal

A Plan B Report

Submitted to

Michigan State University

in the partial fulfillment of the requirements

for the degree of

MASTERS OF SCIENCE

Construction Management

04/07/2015

Page 2: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

ii

ABSTRACT

Approaches and associated costs of building demolition and deconstruction

By: Shershah Zahir

Building demolition, deconstruction and preparing the environment for new construction is an

important aspect of urban development. As the built environment ages and plans for new

developments occur, the opportunities for deconstruction, demolition and renovation emerge. This

aspect has taken on great importance with the widespread residential, industrial and commercial

property abandonment in certain urban areas such as Detroit, Michigan. This research provides

technical, economic, and environmental inputs for the selection of building removal methods.

Demolition, using heavy equipment is the traditional process for building removal. Modern

demolition equipment removes structures quickly, destroying the materials within and creating

solid waste destined for landfills. On the other hand, deconstruction can work to offset the

environmental impacts of the building related waste. Deconstruction not only diverts wastes from

landfills, it also reduces greenhouse gas emissions by reducing the need to extract and ship new

materials and also gives rise to a new industry of skilled jobs. In order to transform the industry,

demolition should incorporate successful aspects of deconstruction, and future construction should

incorporate design for deconstruction. Deconstruction can be more cost effective than demolition

when considering the reduction in landfill disposal costs and the revenues from salvaged material.

On average, gross deconstruction costs are higher than demolition costs, but the net cost of

deconstruction with salvage is lower than demolition. For deconstruction to be more practicable

and profitable, it is important that attractive policies, incentives, and market/supply chain for

deconstructed material are available.

Page 3: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

iii

Dedicated to my country, Afghanistan.

Page 4: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

iv

AKNOWLEDGMENT

First of all, I am grateful to Allah for the good health and wellbeing that were necessary to complete

this research and my academics.

This research would not have been possible without the help and support of so many people. I

would like to express my most sincere thanks to Dr. Syal, my advisor, for his continuous and

tireless guidance and encouragement, not only for this research but throughout my academic career

at Michigan State University. His commitment to excellence and quality is inspiring. I would like

to express my gratitude to my committee members, Dr. Rex LaMore and Dr. Danial Duah, for

their guidance and support.

I take this opportunity to express gratitude to all of the Department faculty, graduate students

whom I have met while working on this research as colleagues, classmates and friends, for their

help and support. I would like to thank my family for the unceasing encouragement, support and

attention.

Page 5: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

v

CONTENTS

CHAPTER 1 ................................................................................................................................... 1

1.0 INTRODUCTION .................................................................................................................... 1

1.1. INTRODUCTION ................................................................................................................ 1

1.1.1. Demolition ................................................................................................................ 2

1.1.2. Deconstruction .......................................................................................................... 3

1.1.3. Design for Deconstruction ........................................................................................ 4

1.2. NEED STATEMENT ...................................................................................................... 4

1.2.1. Growth of demolition and deconstruction industry ....................................................... 5

1.2.2. Sustainability ................................................................................................................. 6

1.2.3. Abandoned private properties ........................................................................................ 7

1.3. RESEARCH GOALS AND OBJECTIVES .................................................................... 8

1.4. SCOPE ............................................................................................................................. 9

1.5. METHODOLOGY ........................................................................................................... 9

1.6. PROJECTED OUTPUTS ............................................................................................... 11

1.7. SUMMARY ....................................................................................................................... 12

Chapter 2 ....................................................................................................................................... 13

2.0. Literature Review................................................................................................................... 13

2.1. CHAPTER OVERVIEW ................................................................................................... 13

2.2. DEMOLITION ................................................................................................................... 14

2.2.1 Planning demolition projects ........................................................................................ 14

2.2.2. Analyzing the project................................................................................................... 15

2.2.2.1 Site survey .............................................................................................................. 15

2.2.2.2. Regulations and standards..................................................................................... 16

2.2.2.3. Safety requirements .............................................................................................. 17

2.2.2.4. Jobsite security ...................................................................................................... 18

2.2.2.5. Environmental regulations .................................................................................... 19

2.2.2.5.1. Water .......................................................................................................................... 19

2.2.2.5.2. Air pollution ................................................................................................................ 19

2.2.2.5.3. Noise ........................................................................................................................... 19

2.2.2.6. Hazardous material ............................................................................................... 20

2.2.2.7. Local authorities regulations ................................................................................. 22

Page 6: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

vi

2.2.2.8. Utilities and permits .............................................................................................. 22

2.2.2.9. Debris and waste handling .................................................................................... 23

2.2.2.9.1. Chutes ......................................................................................................................... 24

2.2.2.9.2 Dust .............................................................................................................................. 25

2.2.3. Demolition equipment and tools.................................................................................. 25

2.2.3.1. Excavators ............................................................................................................. 25

2.2.3.2. Specialized robotic demolition equipment............................................................ 27

2.2.3.3. Hand tools and specialized equipment .................................................................. 28

2.2.4. Approaches to demolition projects .............................................................................. 29

2.2.4.1. Mechanical demolition.......................................................................................... 29

2.2.4.2 Tripping and pulling the structures ........................................................................ 32

2.2.4.3. Selective demolition.............................................................................................. 34

2.2.4.4. Explosive demolition ............................................................................................ 35

2.3. DECONSTRUCTION ........................................................................................................ 36

2.3.1 Benefits of deconstruction ............................................................................................ 36

2.3.2. Planning deconstruction projects ................................................................................. 37

2.3.3. Analyzing the project................................................................................................... 38

2.3.3.1. Site survey ............................................................................................................. 38

2.3.3.2. Safety requirements .............................................................................................. 39

2.3.3.3. Environmental regulations .................................................................................... 40

2.3.3.4. Historic preservation ............................................................................................. 40

2.3.3.5. Permits and utilities............................................................................................... 41

2.3.3.6. Organizational plan ............................................................................................... 41

2.3.3.7. Site plan ................................................................................................................ 41

2.3.3.8. Site security ........................................................................................................... 42

2.3.3.9. Material management plan .................................................................................... 42

2.3.4. Deconstruction equipment and tools ........................................................................... 44

2.3.4.1. Deconstruction tools ............................................................................................. 44

2.3.5. Reusable and recyclable material ................................................................................ 46

2.3.5.1. Reuse ..................................................................................................................... 46

2.3.5.2. Recycle .................................................................................................................. 48

2.3.5.3. Disposed ................................................................................................................ 49

Page 7: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

vii

2.3.6. Various material handling ........................................................................................... 49

2.3.6.1. Steel....................................................................................................................... 50

2.3.6.2. Masonry ................................................................................................................ 50

2.3.6.3. Concrete ................................................................................................................ 51

2.3.6.4. Timber ................................................................................................................... 52

2.3.7. Approaches to deconstruction projects ........................................................................ 53

2.3.7.1. Full deconstruction................................................................................................ 53

2.3.7.2. Hybrid ................................................................................................................... 53

2.3.7.3. Partial demolition .................................................................................................. 54

2.4. DESIGN FOR DECONSTRUCTION (DFD).................................................................... 54

2.4.1. Materials ...................................................................................................................... 57

2.4.2. Assemblies ................................................................................................................... 57

2.4.3. Building systems.......................................................................................................... 58

2.4.4. Building Information ................................................................................................... 59

2.4.5. Case studies ................................................................................................................. 59

2.4.5.1. Boulevard House ................................................................................................... 60

2.4.5.1.1. Repositioning Interior Walls ....................................................................................... 61

2.4.5.1.2. Disentangled heating and cooling systems ................................................................. 62

2.4.5.1.3. Plumbing and electrical systems ................................................................................. 62

2.4.5.2. Chartwell School ................................................................................................... 64

2.4.5.2.1. Utilities ........................................................................................................................ 65

2.4.5.2.2. Modular framing ......................................................................................................... 66

2.4.5.2.3. Creativity with material and detailing ........................................................................ 66

2.4.5.2.4. Windows ..................................................................................................................... 69

2.4.5.2.5. Exterior siding ............................................................................................................. 69

2.4.5.2.6. Building information ................................................................................................... 71

2.5. Summary ......................................................................................................................... 71

chapter 3 ........................................................................................................................................ 73

3.0. comparison of demolition and deconstruction; cost and process ....................................... 73

3.1. INTRODUCTION .............................................................................................................. 73

3.2. COST ESTIMATION OF DEMOLITION PROJECTS .................................................... 73

3.2.1 Cost estimation factors ................................................................................................. 73

3.2.1.1 Preparatory estimating tasks .................................................................................. 74

Page 8: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

viii

3.2.1.2 Regulatory requirements ........................................................................................ 74

3.2.1.3 Project location ...................................................................................................... 75

3.2.1.4 Project size ............................................................................................................. 75

3.2.1.5 Available information ............................................................................................ 76

3.2.1.6 Available resources ................................................................................................ 77

3.2.1.7 Schedule ................................................................................................................. 78

3.2.1.8 Salvage ................................................................................................................... 78

3.2.1.9 Weather .................................................................................................................. 78

3.2.1.10 Quantity takeoff ................................................................................................... 78

3.2.2 Cost components of a demolition project ..................................................................... 79

3.2.3. Demolition case study ................................................................................................. 81

3.2.4. Sources for Cost estimation of demolition projects..................................................... 83

3.2.4.1 RSMeans building construction cost data (RSMeans, 2014) ................................. 83

3.2.4.2 Buildingjournal.com. (http://buildingjournal.com/estimating-demolition.html,

2014) .................................................................................................................................. 85

3.3. COST ESTIMATION OF DECONSTRUCTION PROJECTS ......................................... 88

3.3.1 Cost estimation steps for a deconstruction project ....................................................... 88

3.3.1.1 Survey .................................................................................................................... 89

3.3.1.2. Material management............................................................................................ 89

3.3.1.3. Hazardous material ............................................................................................... 89

3.3.1.4. Historic preservation ............................................................................................. 90

3.3.1.5. Demolition permits and utilities............................................................................ 90

3.3.1.6. Compliance with regulations ................................................................................ 91

3.3.2 Cost components of a deconstruction project ............................................................... 91

3.3.3. Deconstruction case study ........................................................................................... 92

3.4. INTERVIEWS AND ANALYSIS ..................................................................................... 95

3.4.1. Analysis and summary of the interviews ..................................................................... 96

3.4.1.1. Background of the contractors .............................................................................. 96

3.4.1.2. Demolition vs. deconstruction .............................................................................. 97

3.4.1.3. Approaches to project cost estimation, planning and implementation ................. 98

3.4.2. National Demolition Association (NDA) .................................................................... 99

3.5. COMPARISON OF DEMOLTION VS. DECONSTRUCTION .................................... 100

3.6. COST COMPARISON OF DEMOLTION AND DECONSTRUCTION ....................... 104

Page 9: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

ix

3.7. SUMMARY ..................................................................................................................... 111

chapter 4 ...................................................................................................................................... 113

4.0. removal of abandoned properties in michigan ..................................................................... 113

4.1. INTRODUCTION ............................................................................................................ 113

4.2. PRIVATE PROPERTY ABANDONMENT IN THE UNITED STATES ...................... 113

4.3. REMOVAL OF ABANDONED PRIVATE PROPERTIES IN MICHIGAN................. 115

4.4. REMOVAL OF ABANDONED PROPERTIES IN DETROIT ...................................... 117

4.4.1. Deconstruction in Detroit .......................................................................................... 118

4.4.2. Demolition in Detroit................................................................................................. 119

4.4.3 Recycling Detroit’s demolition waste ........................................................................ 120

4.4.4. Recommended demolition process by Detroit Blight Removal Task Force ............. 121

4.5. SUMMARY ..................................................................................................................... 124

chapter 5 ...................................................................................................................................... 125

5.0. summary, conclusions and areas of future research ............................................................. 125

5.1. INTRODUCTION ............................................................................................................ 125

5.2. RESEARCH LIMITATIONS .......................................................................................... 125

5.3. SUMMARY, OBSERVATIONS AND RECOMMENDATIONS ................................. 126

5.3.1. Understand various approaches for demolition, deconstruction and design for

deconstruction ...................................................................................................................... 126

5.3.2. Understand costs associated with various approaches and possible quantification

process for demolition and deconstruction .......................................................................... 127

5.3.3. Develop a comparison matrix for demolition and deconstruction ............................ 127

5.3.4. Identify approaches suitable for removal of abandoned properties in Michigan ...... 128

5.4. AREAS OF FUTURE RESEARCH ................................................................................ 129

References ................................................................................................................................... 131

Appendix A ................................................................................................................................. 135

SURVEY OF CONTRACTORS ............................................................................................ 135

Page 10: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

1

CHAPTER 1

1.0 INTRODUCTION

1.1. INTRODUCTION

Building demolition, deconstruction and preparing the environment for new construction is an

important aspect of urban development. As the built environment ages and plans for new

developments occur, the opportunities for deconstruction, demolition and renovation expand.

Throughout history, people have demolished structures to make room for new structures and to

rehabilitate existing ones.

When buildings need to be removed from a site, the typical and mostly economical option is to

demolish the building and haul the waste to landfills. Many quick and relatively inexpensive

methods can be used to demolish the building and clear the site. On the other hand, these methods

create substantial amounts of waste. The growing trend is to reuse materials in new or existing

structures. The material that are not suitable for reuse should be recycled and sending material to

a landfill should be the last resort. Hence, when the building contains large amounts of reusable

and recyclable materials it is important to incorporate deconstruction into demolition. Whoever

not all buildings are good candidates for deconstruction because they were not designed and built

to be deconstructed. Though in the experimental phase, the new trend in construction industry is

to design and build the buildings for deconstruction (Diven & Shaurette, 2010; EPA, 2008).

Deconstruction and demolition can be implemented using a number of approaches. These

approaches vary according to the type of structure, size, equipment required, availability of

resources, schedule requirements, regulatory requirements, disposal requirements, recycling

Page 11: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

2

requirements, etc. All the above noted factors will have significant impact on the cost of the

operation (Diven & Shaurette, 2010; Guy et al., 2003).

Projects can vary from low-rise residential and commercial buildings to high-rise residential and

commercial, industrial buildings and structures, underwater structures, bridges, roads, pavements,

railway lines, etc. Approaches to every project can be different considering the different

requirements of planning and resource allocation. While the demolition and deconstruction of low-

rise buildings are less complex and can be performed by most contractors, demolition and

deconstruction of high-rise buildings are more complex and are mostly performed by experienced

contractors equipped with necessary resources (Diven & Shaurette, 2010).

This document will discuss demolition, deconstruction and design for deconstruction based on the

available literature and the existing industry practices. Costs associated with demolition and

deconstruction projects will also be explored and compared. Finally, removal of abandoned

properties in urban areas of Michigan will be discussed.

1.1.1. Demolition

Demolition is an engineering project where a building or structure that needs to be removed from

a site, after reaching the end of its useful life, is knocked down with the help of heavy equipment

or manual tools and rendered into rubble and debris. In some cases, some of the material is recycled

such as concrete and steel and the rest of the material is hauled to landfills.

Many factors are considered in the planning of demolition projects. Major factors are the

construction type, safety issues, cost, site access, protection of adjacent structures, unforeseen

conditions, scheduling, sequence of work, and the disposal, recycling, reuse of material. A variety

Page 12: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

3

of regulations and standards apply to the demolition industry such as safety, environmental

requirements for site, environmental requirements for hazardous material, and community specific

regulations amongst other (Diven & Shaurette, 2010).

Modern demolition equipment remove the buildings and structures quickly, creating waste

destined for landfills. The environmental impacts of demolition are substantial, wasting large

amounts of energy and resources.

1.1.2. Deconstruction

Deconstruction is the disassembly of building in order to recover maximum amount of material

for reuse and recycle. Deconstruction is also known as green demolition, un-building or reverse

construction. It is often a part of the conventional demolition process as an initial salvage phase.

Most of the same regulations that apply to demolition such as safety, environmental and

community specific regulations apply to deconstruction as well (Guy, et al., 2003)

Deconstruction has many economic, environmental and social benefits. The benefits of reuse and

recycling of waste streams from building construction and demolition include diversion of waste

materials from landfill sites and reduced depletion of natural resources. Both of these benefits

contribute to the sustainable development practices within the building industry.

Not all buildings are good candidates for deconstruction. In general, buildings constructed before

1950 are better candidates for deconstruction because they may contain higher value of wood and

other structural and ornamental elements for recovery, and they have less complicated fasteners

and glues used for assembly (EPA, 2008)

Page 13: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

4

The new trend in construction industry is to design and build for deconstruction. The incorporation

of design for deconstruction or DfD is in its development stages and it will take time for it to be

adopted for all or most of the new construction (EPA, 2008).

1.1.3. Design for Deconstruction

Design for Deconstruction or Design for Disassembly is a technique that considers the entire

lifecycle of a building including design, manufacturing, construction, renovation, operation and

eventually deconstruction. It creates a closed loop building management option where the building

systems, components and materials are designed to be easily rearranged, dismantled, renovated,

recovered and reused (EPA, 2008).

Incorporating design for deconstruction in new construction offers great potential for reuse of

material and closing the loop of mining and use of new resources to a good extent. Though not

every building is a good candidate for design for deconstruction, a growing number of examples

are occurring in the field (EPA, 2008; EPA 2006).

1.2. NEED STATEMENT

Throughout history, demolition work has been imperative due to need for new construction and

rehabilitation of spaces. With growing economies, aging environment and increasing urbanization;

construction, renovation, demolition and deconstruction industries have substantial growth

projections.

Page 14: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

5

Demolition, deconstruction and design for deconstruction are major parts of the construction

industry and will continue to grow. While there is a large amount of varied popular literature and

industry practices available, there is a lack of common understanding of approaches, standard cost

databases or standardized cost quantification practices. This points to a need to understand these

activities based on the available literature and industry practices; leading to systematic

understanding of approaches that are used in practice and their associated costs.

1.2.1. Growth of demolition and deconstruction industry

With economic growth, increasing urbanization and ageing environment the construction and

demolition industry is set to grow.

Many cities with major urban growth in the United States and elsewhere are constantly renewed.

Old industrial sites are remodeled to accommodate new machinery and equipment, or they are

demolished and new offices and residencies are built. Dilapidated housing is demolished, to make

way for new and more efficient residences. In such cities, demolition is a sign of economic

activity, growth, expansion and renewal (Diven & Taylor, 2006).

“The scale of construction, renovation and demolition activities are expected to grow substantially.

According to one estimate, the built space in the United States will grow from 300 billion square

feet in year 2000 to 430 billion square feet by year 2030. In addition to the new construction of

130 billion square feet, one quarter of the construction that existed in 2000 will be replaced by

2030.” (EPA, 2008).

Page 15: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

6

While this growth can be viewed as challenging, it is an opportunity for the application of

sustainable practices in demolition through deconstruction and more efficient use of resources

through implementation of design for deconstruction.

1.2.2. Sustainability

Constructing buildings, renovation and taking them down all together have substantial

environmental impacts because of all the natural resources used for building construction and the

large amounts of construction and demolition waste that are directed to landfills. In order to

promote sustainability in the demolition industry, it is important to incorporate deconstruction into

the demolition, and possibly adaptation of design and build for deconstruction to recover all

systems and materials for reuse in future construction.

The facts below about construction, demolition and renovation waste in the United States compiled

by the Environmental Protection Agency (Guy. et al., 2003), highlights the need for incorporating

sustainable practices in the demolition industry:

U.S. companies generate 136 million tons of building- related construction and demolition

(C&D) waste per year.

92% of building-related C&D waste is from renovation and demolition.

C&D waste is approximately 30% of all solid waste produced in this country excluding

road and bridge debris.

It estimated that only 20-30% of C&D waste is presently recycled.

Excluding food and fuel, construction activities consume 60% of the total materials used

in the U.S. economy.

Page 16: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

7

About 245,000 residential structures and 44,000 commercial structures are demolished

each year in the US.

Many older buildings contain asbestos and lead-based paint both hazardous to human

health in renovation and demolition processes.

Heavily leaded paint was used in about 1/3 of homes constructed before 1940, about 1/2

of homes constructed between 1940 and 1960, and then to a lesser extent until it was limited

to 0.06% in any product in 1978.

Landfills and incinerators are increasingly more expensive and problematic to open,

operate and close.

In order to sustain human society into the next century, resource efficiency will have to

increase by a factor of 10.

Therefore, practicing reuse and recycling can strengthen our natural resources and decrease the

environmental impacts.

1.2.3. Abandoned private properties

Many cities in the United States which used to be the hubs of industrial activities are presently

facing economic and social decline with those industries reclining. This issue is well prevalent in

Michigan, where it has resulted in private property abandonment and blight in the cities of Detroit,

Flint, etc. LaMore & LeBlanc (2014) assert that many communities in Michigan have suffered

population and economic decline for decades, resulting in widespread residential, industrial and

commercial property abandonment. These property abandonment cause blight and leads to social

decline which threatens the public health and welfare of communities.

Page 17: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

8

These abandoned properties need to be removed and the sites need to be restored for future use.

Otherwise they turn into blight, triggering a spiral of social decline. Based on the understanding

of the policies that will lead to dismantling, removal, and restoration of these properties, there is a

need to identify most appropriate approaches for the removal of such structures with an

understanding of the associated costs of removal.

Based on the above discussions, it can be summarized that there is a need for the following:

1. Removal of abandoned properties.

2. Use of deconstruction over demolition for the removal of abandoned properties due to the

environmental, economic and social benefits of deconstruction.

3. Consideration of incorporation of design for deconstruction for all new construction due to

the potential benefits of deconstruction.

1.3. RESEARCH GOALS AND OBJECTIVES

As discussed earlier, various approaches used for demolition and deconstruction are selected based

on many factors. The goal of this research is to provide a systematic understanding of various

approaches for removal of buildings.

Following are the objectives of this research:

1. Understand various approaches for demolition, deconstruction and design for deconstruction

through literature review, case studies and interviews of contractors.

2. Analyze costs associated with approaches and possible quantification process.

3. Develop a comparison matrix for demolition and deconstruction.

Page 18: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

9

4. Identify and recommend approaches which are suitable for removal of abandoned properties

in Michigan.

1.4. SCOPE

The scope of this paper is limited to demolition and deconstruction of low-rise residential and mid-

rise residential and commercial buildings. In addition, even though the understanding of

approaches and associated costs are based on literature review, the identification of best practices

in Michigan are based on interviews, observations, site visits and surveys.

1.5. METHODOLOGY

The approach adopted for this research is a descriptive approach. Extensive amounts of popular

and some scholarly literature is available in these fields. The main aim is to identify and compile

literature and summarize them for the purpose of understanding various approaches in demolition,

deconstruction, and design for deconstruction and associated costs of these approaches.

Following is the methodology used for achieving each of the objectives:

1. Understand various approaches for demolition, deconstruction and design for deconstruction.

Literature review:

Various academic papers, thesis reports, case studies, industry reports and manuals are

available in these fields. This research aims to compile and analyze the best practices and key

lessons that can aid in the planning and implementation of demolition, deconstruction and

design for deconstruction projects.

Page 19: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

10

Site visits, survey and contractor interviews

A limited number of site visits and interviews will be carried out in order to understand the

practices prevalent in the demolition and deconstruction industry in Michigan. These site visits

and interviews will help compile and analyze the factors affecting the whole project planning

and implementation.

2. Understand cost associated with various approaches and possible quantification process for

demolition and deconstruction.

Analyze cost databases:

A limited amount of data is available for quantification of costs related to demolition and

specially deconstruction projects. The aim is to study available cost databases to be able to

understand major cost factors associated with various approaches.

Literature review:

A limited amount of literature is available regarding the cost of implementation of demolition

and deconstruction projects. Few case studies are also available discussing the major cost

factors in demolition and deconstruction projects. The aim is to compile and analyze the

available literature and case studies to understand the quantification of such projects.

Site visits, survey and contractor interviews:

Based on the site visits, surveys and contractor interviews carried out in the first objective,

major cost factors in these projects will be identified.

3. Develop a comparison matrix for demolition and deconstruction.

Self-analysis and observation:

Page 20: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

11

Based on objective one and two, a comparison matrix will be developed for demolition and

deconstruction. This will be a self-analysis work that will be based on the achieved objectives

mentioned above.

4. Identify approaches suitable for removal of abandoned properties in Michigan.

Site visits, survey and contractor interviews:

Based on the site visits, surveys and contractor interviews carried out in the first objective,

most suitable approaches will be identified for Michigan.

Self-analysis and observation:

Achieving the first, second and third objectives mentioned above will help in an understanding

of demolition and deconstruction projects in Michigan. Based on self-analysis best practices

will be identified.

1.6. PROJECTED OUTPUTS

This research will provide information regarding technical, management and cost issues related to

demolition and deconstruction projects. It will include modern practices, various approaches,

factors affecting decisions, equipment and resources needed, recycling and reuse of materials,

regulatory requirements, costs, etc.

The research will provide a reference for contractors and owners who hire demolition and

deconstruction contractors for projects. The comparative study approach will provide information

on associated costs for various approaches to select for different projects.

The following outputs are expected to be achieved from this paper:

Page 21: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

12

Various approaches in building demolition and deconstruction

Major cost factors associated with various approaches

Suitable approaches for removal of abandoned properties in Michigan.

1.7. SUMMARY

This chapter provides an overview of the need for studying building demolition and deconstruction

and associated costs, the goals and objectives, the scope, methodology and projected outputs of

this study. It is established that demolition and deconstruction are important parts of the

construction industry and are projected to grow. Finally, though not all buildings are suitable,

incorporating design for deconstruction in new construction is a very sustainable since it offers

great potential for material reuse and to a good extent, closing the loop of mining and use of new

resources. The following chapter will provide a literature review of demolition, deconstruction and

design for deconstruction.

Page 22: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

13

CHAPTER 2

2.0. LITERATURE REVIEW

2.1. CHAPTER OVERVIEW

This chapter provides an overview of the literature reviewed for the research. The literature review

is based on three broad topics of demolition, deconstruction and design for deconstruction.

Demolition and deconstruction are reviewed for planning, equipment and approaches used for

each. An introduction of design for deconstruction with case studies are provided. The following

chart provides an overall understanding of the structure of this chapter.

Literature review

Demolition

Planning

Equipment used

Approaches

Deconstruction

Planning

Equipment used

Approaches

Design for deconstruction

Introduction

Case studies

Page 23: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

14

2.2. DEMOLITION

Typically, when a building or structure needs to be removed from a site after reaching the end of

its useful life, it is knocked down with the help of heavy equipment or manual tools and rendered

into rubble and debris. In some cases some of the material is recycled like concrete and steel

buildings and the rest of the material is hauled to landfills.

"Demolition is an engineered project to reduce a building, structure, paved surface, or utility

infrastructure through manual and/or mechanized means, with or without the assistance of

explosive materials to piles of mixed rubble and debris. Demolition usually provides the quickest

method of removing a facility and segregates the debris or rubble into various components for

recycling where practicable" (Diven & Shaurette, 2010).

2.2.1 Planning demolition projects

Many factors are considered in planning demolition projects. Major factors are the construction

type, safety issues, cost, site access, protection of adjacent structures, unforeseen conditions,

scheduling, sequence of work, and the disposal, recycling, reuse of material. A variety of

regulations and standards apply to the demolition industry such as safety, environmental

requirements for site, environmental requirements for hazardous material, and community specific

regulations amongst other.

It is very important to pay attention to initial preparation and planning of a demolition project.

Some of the common planning practices for demolition projects are discussed in the following

sections.

Page 24: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

15

2.2.2. Analyzing the project

Before a demolition project is planned and executed, many factors are considered in determining

the methods used. Some the factors, which are discussed subsequently in details, are as follows

(Diven & Taylor, 2006; Diven & Shaurette, 2010; BDHK, 2004):

• Site survey

• Regulations and standards

• Safety requirements

• Job site security

• Environmental regulations

• Hazardous material

• Local authorities regulations

• Utilities and permits

• Debris and waste handling

2.2.2.1 Site survey

The first step in a potential demolition project is a site visit to examine the building. This consists

of surveying the building to evaluate the basic material types and the overall condition of the

structure. Based on the findings of these surveys, a demolition plan shall then be prepared.

It is important that during survey, the existing record plan, including layout plan showing adjoining

properties, pedestrian walkway, roads and street, etc. also be recorded and considered.

Page 25: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

16

The Building Survey shall cover the following (Diven & Shaurette, 2010; BDHK, 2004):

• The materials and methods of construction

• Original structural system

• The existing use and, if possible, the past uses of the building prior to demolition;

• The presence of hazardous materials.

• Adjoining properties and site conditions

• Utilities

• Shared facilities with adjoining building

• Adjoining pedestrian and vehicular traffic conditions;

• The sensitivity of neighborhood with respect to noise, dust, vibration and traffic impact

2.2.2.2. Regulations and standards

A variety of regulations and standards apply to demolition projects. These regulations are generally

provided to prevent contamination of the environment and to provide a safe and healthy working

environment. These regulations and standards contain federal, state and local standards that are

important in deciding the means and methods to execute a demolition project. Regulations

commonly associated with demolition projects can be classified in the following categories (Diven

& Taylor, 2006):

• Safety

• Environmental-site requirements

Page 26: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

17

• Environmental- hazardous materials requirements

• Community specific regulation

2.2.2.3. Safety requirements

Site safety features shall emphasize protection of the public, particularly, the pedestrian and

vehicular traffic and the adjacent properties. Proper safety features shall be designed to make sure

that the demolition can be carried out safely and the site personnel is protected. The Contractor

shall carry out the demolition works including precautionary measures in accordance with the

approved plans and other related documents, and provide continuous supervision to the works.

All mandated federal and local regulations should be identified. The OSHA regulations apply to

both construction and demolition projects. Demolition specific standards are set forth in CFR 1926,

Sub-part T of OSHA regulations. Some states have additional safety regulations such as the

MIOSHA regulations in Michigan, which should be strictly followed by the demolition contractors

(Diven &Taylor, 2006).

Some of the regulations particularly important for demolition projects are as follows (HUD-

NAHB, 2000; Diven & Shaurette, 2010):

• Integrating safety into the job

• Worker training

• Engineering survey for structures to be demolished

• Hazard communication standard compliance

• Medical services

Page 27: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

18

• Fire protection and prevention

• Site conditions and accessibility

• Public protection

• Personal protective equipment

• Fall prevention and protection

• Equipment safety

• Safe handling of Asbestos, PCBs and lead

• Safe use of cutting torches and arc welding

• Safe use of hand tools

• Safe blasting and explosive handling procedures

• Confined space safety practices

• Safe practice when demolishing stacks

2.2.2.4. Jobsite security

Security measures should be put in place to create a safe and secure demolition jobsite. These

measures are important not only to keep the workers safe but also the public from potential

dangers. There are a number of issues to be considered such as illegal entry to the site, vandalism

and theft. The measures may include fencing, signage, pedestrian walkways, scaffolding, screen

covers, enclosures, temporary lighting, etc. (Diven & Taylor, 2006; BDHK, 2004).

Page 28: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

19

2.2.2.5. Environmental regulations

The general requirements to minimize environmental impacts from construction sites can also be

applied to demolition processes. Some of the regulations are as follows:

2.2.2.5.1. Water

“The National Pollution Discharge Elimination System (NPDES) administered by EPA requires

that the owner of a demolition site over one acre obtain a permit and devise and implement a plan

to prevent pollutants conveyed by rainwater or snow melt from leaving the site” (Diven &

Shaurette, 2010).

2.2.2.5.2. Air pollution

Concrete breaking, handling of debris and hauling process are main sources of dust from building

demolition. Dust mitigation measures complying with the National Emission Standards for

Hazardous Air Pollutants (NESHAP) Regulations shall be adopted to minimize dust emissions.

Burning of waste shall not be allowed. Diesel fumes generated by mechanical plant or equipment

shall be subject to the control of the Air Pollution Control Regulations.

2.2.2.5.3. Noise

Noise pollution arise from the demolition works including, but not limited to, the use of specified

powered mechanical equipment such as pneumatic breakers, excavators and generators, etc.,

scaffolding, erection of temporary works, loading and transportation of debris, etc. The noise can

affect the workers, and the receivers in the vicinity of the demolition site. Silent type machines

and tools shall be used to reduce noise impact as much as practicable. Demolition activity shall

not be performed within the restricted hours as established by EPA or municipalities. OSHA

establishes some regulations regarding noise in the workplace (EPA, 2006).

Page 29: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

20

2.2.2.6. Hazardous material

If hazardous materials, such as asbestos containing materials, petroleum contamination and

radioactive contamination, exist in the building, further investigation and removal of such

hazardous material or contamination by specialists shall be provided. Many large contractors are

qualified to perform hazardous materials removal work with their own forces, whereas others may

use companies that specialize in handling hazardous material (BDHK, 2004).

Other materials such as LPG cylinders in domestic flats, toxic and corrosive chemicals for

industrial undertakings, and any other hazardous materials have to be identified and properly

handled and removed prior to the commencement of the demolition of the building.

OSHA has established extensive standards and regulations that must be followed during the

handling of hazardous materials. Some other regulations by states and other federal agencies are

also enacted to add to the requirements for handling hazardous material.

The removal process for hazardous materials requires careful planning process before commencing

the demolition work. These processes may include survey, notifications and permits, trainings,

personal protection equipment.

The following list includes some of the hazardous materials that may be found on a demolition

project taken from (EPA, 2004; Diven & Shaurette, 2010):

• Asbestos Containing Materials (ACM): friable ACM and Non-friable ACM

• Polychlorinated Biphenyls (PCBs): require special removal, transportation, and disposal

• Lead-Based Paints (LBPs) not all LBP is identified as hazardous, but testing is usually

required before using a landfill for disposal

Page 30: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

21

• Mercury: mostly from instrumentation, it is one of the most dangerous elements of humans

• Biological Hazards: bird and animal droppings, etc.

• Chemicals: from industrial to household, not all chemicals are identified hazardous

• Petroleum Oils Lubricants (POLs): most POLs are not hazardous however removal and

disposal is regulated

• Radiological Hazards: in some instrumentation and emergency lighting

• Dust: fugitive dust is usually non-hazardous, but may cause respiratory problems and

contain fine particles of silica

• Fluorocarbons: refrigerants, these require special removal techniques, and some types may

be recycled

• Mold: only some types of mold are hazardous

• Creosote: railroad ties and pilings

According to the regulations of (NESHAPS), the removal of hazardous material such as ACM

requires notification to EPA or its designated state agency of intent to remove ACM. Various states

have notice and permit requirements prior to beginning demolition activities (EPA, 2004; Diven

& Shaurette, 2010). The contractor must be aware of all the regulations and fees because it can

affect overall cost of the project tremendously.

Page 31: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

22

2.2.2.7. Local authorities regulations

Many states may implement regulations and standards that are more stringent than the federal

regulations in construction and demolition projects. All these requirements must be considered

while planning the demolition project. Some of the local regulations may apply to the following

points (Diven & Taylor, 2006; Diven & Shaurette, 2010):

• Permit requirements for specific building type

• Restrictions on use of certain methods like use of explosives

• Restrictions on work hours

• Permits to use municipal utilities like water lines and hydrants

• Haul restrictions

• Traffic regulations

2.2.2.8. Utilities and permits

The demolition plan shall ensure that during the course of demolition, no existing utilities in the

vicinity of the demolition sites are affected by the demolition operation. All utility companies and

relevant agencies shall be consulted prior to demolition of the structure.

Some of the common utilities that need to be disconnected from the structure include the following:

Electricity, Water, Gas, Telecommunication, Drainage, Overhead and Underground Cables,

Railway Tunnel and its accessories, such as vent shafts, Sewage Tunnel and its accessories and

Disused Tunnel. Some temporary utilities are required to provide a safe and healthy work

Page 32: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

23

environment (BDHK, 2004). Thus, it is necessary to acquire all the permits for demolition and

utility disconnection before any work can start on site.

2.2.2.9. Debris and waste handling

One of the major tasks and costs involved in demolition projects are sorting, recycling, hauling

and disposing of the demolition waste. Better site management and practice could facilitate and

allow on site sorting, and separation at source of demolition waste. It is better if the sequence of

demolition is planned to allow the separation and sorting of building materials.

Before the 1990s, most of the demolition debris was not sorted out and hauled and disposed to

landfills. As the public became aware of the environmental problems of disposing off waste to

landfills with diminishing capacity, recycling became more important (EPA, 2004).

The method of ‘selective demolition’ is highly encouraged for recycling purposes. It involves

demolition and removal of wastes of the same category one at a time. The goal is to facilitate

recycling of wastes for beneficial reuse, thus minimizing the burden on municipal landfills and

public filling areas. In general, domestic wastes such as furniture, household appliances, etc.,

metal components such as window frames, pipes, etc., timber components such as doors, wooden

floors, etc., other wastes such as tiles, asphaltic materials, ceramic products should be removed

first. Most of these materials may be recycled. The building demolition shall begin after all the

above non-structural materials have been stripped and removed (Diven & Shaurette, 2010).

The debris disposal and management system should clearly lay down the following details

(BDHK, 2004):

• method of handling demolished building debris

Page 33: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

24

• the routing and movement of debris from each floor to on grade holding area prior to

leaving the site

• means of transportation of debris off site

• time and frequency of debris disposal off site

• record scheme on the tonnage of each truck load, truck license plate, driver’s name, trip

tickets and location of dump site

Most demolition projects specify that the contractor will be responsible for the legal disposal of

all materials removed from the building. Particular client requirements, however, may be included

in the bid documents (e.g., required crushing of concrete rubble for use on the site). Since recycling

demolition materials has become an important part of nearly all demolition work, the demolition

planning process should identify both local recycling requirements and the wishes of the client.

Recycling can either increase or reduce demolition cost, depending on the circumstances of the

job and the market value of the products to be recycled.

2.2.2.9.1. Chutes

Debris waste and other materials shall not be thrown, tipped or shot down from a height where

they are liable to cause injury to any person on or near the site. Existing lift shaft, light well and

openings on floor may be used to convey debris down the building floors. Areas adjacent to the

openings of these features used as a chute shall be barricaded when they are not in use. Warning

signs shall be posted to prevent workers from entering the area. As an option, plastic chutes may

be used inside the floor openings and lift wells to minimize noise and confine the falling debris

(BDHK, 2004).

Page 34: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

25

2.2.2.9.2 Dust

To prevent dust generation during the debris hauling, water spraying is applied during the hauling

process. However, the Contractor shall ensure proper control of water supply and floor drainage

system in order to avoid flooding which is a nuisance and may cause overloading of floors (BDHK,

2004).

2.2.3. Demolition equipment and tools

Many different equipment and attachments have been developed by manufacturers for demolition

work. Some heavy equipment used in demolition projects are as follows: excavators, impact

hammers, cranes with wrecking balls, loaders with grapple bucket, concrete crackers, crawler

crusher, vacuum track, floor scraper, etc. There are also small hand tools and robotic demolition

tools and equipment that are mostly used for selective demolition work. Some of these equipment

are describe in the following sections.

2.2.3.1. Excavators

Excavators with different sizes, reach distances and various specialty attachments have been

developed for demolition work. The most common type used are crawler excavators equipped with

grapple or bucket and thumb and are shown in the figures below (Brook, 2000; Diven & Shaurette,

2010).

Page 35: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

26

Figure 2.1. Crawler Excavator with hydraulic hammer

attachment

(Source:http://www.centralpoolsandspas.com/cms/images/

stories/concrete_removal.jpg>)

Figure 2.2. Excavator with grapple attachment

(Source: http://excavatorgrapples.com/exgr/wp-

content/uploads/2012/10/HDG-Grapple-8-300x199.jpg)

Figure 2.3. Excavator with concrete pulverizer

attachment.

(Source:

http://img.directindustry.com/images_di/photo-

g/excavator-concrete-pulverizers-61578-4745351.jpg)

Figure 2.4. Excavator with pulverizer attachment.

(Source:

http://img.directindustry.com/images_di/photo-

g/excavator-concrete-pulverizers-56763-

3880565.jpg)

Page 36: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

27

2.2.3.2. Specialized robotic demolition equipment

Many small machines which resemble mini-excavators, can be operated by remote controls have

been developed for specialized work. They can be fitted with grapples, shears, concrete crackers,

hydraulic hammers, impact hammers, etc. (Brook, 2000; Diven & Shaurette, 2010).

These machines can be used in places where large equipment can’t reach, demolition of floors

where load restrictions can’t allow heavy equipment or places which are not safe for laborers to

work in. Figures 2.5 and 2.6 below show robotic demolition equipment.

Figure 2.5. Robotic concrete splitter being controlled by a

joystick. A lot of different attachments can be used with

these machines

(Source: http://i.ytimg.com/vi/jlaOUMqoe_8/0.jpg)

Figure 2.6. Robotic concrete cracker being controlled by a

joystick.

(Source:http://www.brokk.com/img/informupl/3Akershus_in

_Oslo.jpg)

Figure 7. Wheel loader loading debris.

(Source:http://www.recyclingproductnews.com/files/slides/lo

cale_image/listing/0012/2860_00000_rmt_intermercato_grap

ple_scale_mj2013p_junew_.jpg)

(Figure 8. Crawler excavator loading debris into trucks

used for hauling away the material to landfill

Source: http://utilitycontractoronline.com/pix/blog/11-

25-13/Bobcat.JPG)

Page 37: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

28

2.2.3.3. Hand tools and specialized equipment

There are various types of tools and specialized equipment used for selective demolition work

and places where the demolition work has to be done by hands and not heavy equipment. Figure

2.9 below shows a Jack hammer used for cracking concrete and figure 2.10 shows a cutting torch

that is used for cutting steel.

Figure 2.9. Jack hammer used for cracking concrete and paved surfaces.

(Source:http://us.123rf.com/450wm/americanspirit/americanspirit1307/americanspirit130704261/20801667-hispanic-male-breaking-concrete-with-yellow-jackhammer.jpg)

Figure 2.10. Steel cutting torches are used for selective demolition

of steel structures

(Source:http://graphics8.nytimes.com/images/2011/01/11/blogs/11C

RDeutsche2/11CRDeutsche2-blog480.jpg)

Page 38: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

29

2.2.4. Approaches to demolition projects

Building demolition is achieved by a variety of means and methods, using many kinds of

equipment and tools. Demolition experts can recommend which methods are appropriate for

particular projects. For simplicity, demolition methods can be grouped under the categories of

mechanical demolition, Explosive demolition, and Selective demolition (Diven & Shaurette, 2010;

BDHK, 2004).

2.2.4.1. Mechanical demolition

A large variety of specialized demolition equipment has been developed and most demolition

projects rely on heavy equipment to get the projects done. Though wrecking ball and cranes have

been used for large, high-rise demolition projects for a long time, a lot of high pressure hydraulics

tools with attachments such as shears, breakers, concrete pulverizers, and others tools have been

developed and are being used widely in demolition projects.

Some machines can operate in confined work areas and can separate the building materials as they

“chew” the building apart. This method is described as progressive wrecking. The work can be

done from a safe distance by machines such as excavators and front-loaders also.

Progressive wrecking of structures and buildings can be accomplished using one or a combination

of the three methods described below (Diven & Shaurette, 2010):

Page 39: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

30

1. Machines with high reach booms: this is a safe method that can be implemented in areas

of restricted access. Buildings and structures up to a height of 120 feet can be demolished

using this method. Large excavators are fitted with third member booms to allow safe work

at heights. Some attachments such as shears, grapples and concrete crackers are used.

Figure 2.11 shows a high reach excavator used for demolition.

2. Cranes and wrecking balls: for buildings and structures of up to twelve story or less can be

demolished using cranes and wrecking balls. The work is performed from a safe distance

with swinging the wrecking ball by cranes. The wrecking balls are made of cast steel and

weigh around 1500 to 10000 pounds.

3. Floor by floor: for buildings that are more than twelve stories and buildings and structures

that don’t have sufficient operation room, small excavators and skid steer loaders and can

be used to demolish the building one floor at a time. The loaders and mini excavators

demolish the concrete and masonry, and torches are used for cutting the steel (Brook, 2000;

Diven & Shaurette, 2010).

Figure 2.11. High Reach Excavator with

a boom reach of 21-32 meters.

(Source:http://r3.forconstructionpros.co

m/files/cygnus/image/FCP/2012/OCT/64

0x360/volvo-ec380dhr-

excavator_10819128.jpg)

Page 40: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

31

Figure 2.12-2.13. Crawler crane with wrecking ball, knocking down a structure from a safe distance.

(Source: http://upload.wikimedia.org/wikipedia/commons/5/59/Abrissbirne.jpg)

Figure 2.14. Excavators demolishing building floor by floor

(Source:http://cdn.theatlantic.com/static/infocus/china112012/s_c46_RTR2UY5Y.jpg)

Page 41: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

32

2.2.4.2 Tripping and pulling the structures

Large buildings and structures can be demolished by tripping or pulling. It is important to insure

that there is sufficient space for the structure to fall on without impacting any neighboring

buildings or underground structures.

Tripping buildings and structures is done by weakening the structure columns and shear walls

strategically. Next a crane is used with a wrecking ball to bring down the weakened building

(Diven & Shaurette, 2010).

Unlike tipping, pulling a building or structure is done by attaching heavy-duty cables to columns

at high points in the structure and; the lower floor columns and shear walls are weakened

strategically. Heavy machinery is then used to pull the cables and bring down the structure in the

desired direction (Diven & Shaurette, 2010). Figure 2.15 below shows an excavator pulling down

walls.

Figure 2.15. Crawler excavator pulling down walls.

(Source: http://www.3rdemolition.com/casestudy_images/warehouse3.jpg)

Page 42: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

33

Foundations and below grade structures: can be demolished using excavators and breaking

concrete with hydraulic hammers. Excavators are used with buckets, thumbs and grapples to wreck

the foundations and then remove the debris out (Brook, 2000). Figure 2.16 shows removal of

foundation concrete by excavators. Figure 2.17 shows a robotic excavator that can be used for

removal of floor concrete.

Figure 2.16. Excavators digging out

foundation concrete. The wheel excavator

is using the bucket to remove the material

where the crawler excavator is using the

concrete cracker attachment to break the

concrete

(Source:http://www.heavyequipmentguid

e.ca/files/slides/locale_image/listing/0046

/11481_00000_e05_doosan_dxb170h_hy

draulic_breaker.jpg)

Figure 2.17. Robotic excavator

breaking concrete in the basement

floor.

(http://www.aggregatetechnologies.co

m/wp-

content/uploads/2012/12/Photo-Dec-

17-5-35-04-PM.jpg)

Page 43: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

34

2.2.4.3. Selective demolition

Selective demolition uses combination of hand labor and small, specialized equipment and tools.

It is defined as careful demolition procedure where parts of a structure or building is removed

(Diven & Shaurette, 2010). Interior demolition and selective demolition are most often

accomplished with small, skid-steer loaders and small excavators equipped with a variety of

hydraulic attachments that include breakers for concrete, shears for cutting small steel, and

material-handling buckets and forks. In the last twenty years, effective remote-controlled machines

have been developed that can be used in hazardous environments, confined spaces, areas that have

been damaged or are structurally weakened, and areas that are sensitive to noise or vibration. These

machines are also being used in radioactive environments (Brook, 2000).

Figure 2.18. Robotic machine used for

selective demolition of concrete flooring

with a concrete cutter.

(Source:

http://www.nmldiamonddrilling.co.uk/upl

oads/Image/Robotic%20Demolition(1).jp

g)

Figure 2.19. Removing flooring sheets by

simple hand tools is an example of selective

demolition

(Source: http://www.mccullough-

construction.com/phpages/wp-

content/uploads/2009/07/03_6003ExecBlvd.j

pg)

Page 44: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

35

2.2.4.4. Explosive demolition

Explosion or Implosion methods are very effective for bringing down high structures that would

be difficult to reach with equipment or too expensive to demolish one floor at a time. These

methods use highly specialized explosives to undermine the supports of a structure so it collapses

either within its own footprint or in a predetermined path. The implosion process is especially

suited for high-rise buildings (usually more than twelve stories) and a variety of special structures

(e.g., cooling towers, nuclear reactor containments, space launch towers, smokestacks, boilers,

steel mill furnaces, and so on) (Diven & Taylor, 2006).

In this method the explosives are used to weaken the structural support system of a structure that

is columns and shear walls so the structure can no longer support the load of the structure and

comes down. Common explosives—usually various forms of dynamite and ammonium nitrate—

are frequently used to blast heavy concrete such as that in bridge piers and machinery foundations.

Figure 2.20 shows a demolition project where explosives are used.

Implosion demolition is usually done by very specialized contractors and most of them work as

subcontractors to conventional contractors performing demolition work.

Figure. 2.20. Controlled implosion of a

high-rise building.

The building is collapsing within its

foot print, thus ensuring the

neighboring buildings are not affected.

(Source:

http://www.gulfdemolition.com/image

s/ex1.jpg)

Page 45: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

36

2.3. DECONSTRUCTION

Deconstruction is basically the opposite of construction where the building is disassembled into

basic materials such as lumber, steel, widows, mechanical equipment, etc. while maintaining the

integrity of the material as much as possible for reuse. Reuse is the more desired outcome

compared to recycle as it provides low cost building material for the community and avoids debris

going to landfills.

"Deconstruction is a process of building disassembly in order to recover the maximum amount of

materials for their highest and best reuse. Re-use is the preferred outcome because it requires less

energy, raw materials, and pollution than recycling does in order to continue the life of the material.

As a consequence of deconstruction, there are also many opportunities for recycling other

materials along the way." (Guy, et al., 2003)

Deconstruction is also known as Green demolition, un-building, building disassembly or reverse

construction. Sometimes it is partly involved in the conventional demolition process, as an initial

salvage phase by recycling and reuse of material. It can be as simple as stripping out utilities,

appliances or cabinetry for reuse in another project, or it can involve taking apart the whole

building frame.

2.3.1 Benefits of deconstruction

Deconstruction has economic, environmental and social benefits. The benefits of reuse and

recycling of waste streams from building construction and demolition include diversion of waste

materials from landfill sites and reduced depletion of natural resources. Both of these benefits

contribute to sustainable development within building industry.

Page 46: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

37

The social benefits include creating more jobs for unskilled labor who can be easily trained to

perform deconstruction jobs. Additional benefits of deconstruction include the following (EPA,

2008):

• Reducing pollution, greenhouse gases emissions, and the need for landfilling

• Conserving energy and natural resources

• Creating job training and employment opportunities

• Providing materials for building construction and value adding manufacturing enterprise

• Lower building removing costs: because of the added value of material salvage and avoided

disposal costs

2.3.2. Planning deconstruction projects

Deconstruction in almost all cases requires more time than demolition — during the planning

phase as well as the building removal phase. The planning requires more time because the whole

sequence of dismantling different material has to be planned carefully as to make sure smooth flow

of work, safe environment, and structural integrity of building while laborers are working on

removing nonstructural elements, insuring integrity of salvaged material for reuse, etc.

Some of the common planning practices used for deconstruction projects are discussed in the

following sections.

Page 47: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

38

2.3.3. Analyzing the project

Before a deconstruction project is executed, many factors are considered in determining the

methods and sequence of work to be performed. The most important step is to survey the type of

material and identify them for reuse, recycle and disposal. Some of the factors are as follows (Guy,

et al. 2003; HUD-NAHB, 2000):

• Site survey

• Safety requirements

• Environmental regulations

• Historic preservation

• Permits and Utilities

• Organizational plan

• Site plan

• Site security

• Material management

2.3.3.1. Site survey

The first step in a deconstruction project is a site visit to examine the building. This consists of

surveying the type and condition of material in the building or structure. All the material has to be

identified for reuse, recycle and disposal to landfills. This called inventory of material. The

condition of material in the structure and the manner they are secured to the structure can have

Page 48: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

39

impact on the effectiveness of the salvage of material, especially for reuse as those material have

to be in good condition after salvage for reuse in new construction. The structural design of the

building or structure has to be completely understood and possible hazards need to be identified.

Some structural elements of the building may need temporary bracing while the deconstruction

work is being done till it reaches to the stage where the structural elements of the building can also

be removed safely. Basically this survey can be used to identify the tools, techniques, approaches

and schedule to be employed for this job (Guy, et al., 2003).

2.3.3.2. Safety requirements

The Safety Plan is an accident prevention plan. Safety is a daily activity, and should be

incorporated through daily safety talks at the beginning of the workday. (OSHA)

Maintaining a safe workplace for the employees and the general public that may be impacted by

the deconstruction project is an important aspect of a successful project. In general both public and

private clients are more likely to seek contractors with good safety records for their project.

Elements of the Safety includes worker orientation and training, hazard identification and training,

guidelines for the use of tools, personal protection equipment use, site conditions, accessibility,

first aide, fire protection , procedures for correcting unsafe behavior etc. (Guy, et al., 2003; IWMB,

2001).

Page 49: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

40

2.3.3.3. Environmental regulations

Proper management and removal of hazardous material is a highly regulated operation and it can

have heavy impact on the successful execution of a deconstruction or project.

Environmental surveys for lead and asbestos must be completed for any building built before 1978.

The US EPA, OSHA and HUD all have regulations for dealing with asbestos containing materials

(ACM) and lead-based paint materials (LBP). Although the EPA NESHAPS regulations exempt

demolitions from the removal of non-friable ACM, deconstruction and salvage necessitate the

removal of ALL asbestos before work begins. The deconstruction costs and processes will be

heavily influenced by the presence of ACM and LBP materials (Guy, et al., 2003; IWMB, 2001).

2.3.3.4. Historic preservation

Historic preservation or salvage is the careful removal of building components for their historic

value. Some features as special brick and terra-cotta, carved stone, carved stonework, cast iron

features, timber pieces, stained glass windows, etc. can be considered for salvage and reused later

in other buildings or may end up in museums (Diven & Taylor, 2006).

Government regulatory departments like municipalities or historic preservation organization

should be contacted to research any historic building or district designations and the local

deconstruction permits processes associated with historic buildings.

Page 50: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

41

2.3.3.5. Permits and utilities

Most local regulations require deconstruction permits or formal notification of intent to be obtained

in order to remove a building. In general the procedure required for obtaining the permit for

demolition are the same required for deconstruction permit (IWMB, 2001).

Disconnection of all utilities must take place before any work can begin on site like electricity,

natural gas, water, wastewater, telephone and cable. Some temporary services may still be needed

for safe and clean work environment like temporary electricity. The disconnection of the utilities

is sometimes included in the demolition permit approval process.

2.3.3.6. Organizational plan

A key element of a successful deconstruction project is development of a detailed and

comprehensive management plan. Planning comprehensively before execution of work can result

in successful completion of the project. Issues such as site supervision, schedules, labor

organization, tools and equipment, site safety and training are issues that has to be clearly defined

in the planning stage. Competent people should be responsible for specific operations (HUD-

NAHB, 2000; Guy, et al., 2003).

2.3.3.7. Site plan

The location of the site and the constraints of the building or structure in accordance to its foot

print and neighboring buildings is a very sensitive issue to be determined while planning a

deconstruction project. The location of all the operations happening on the site has to be identified

Page 51: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

42

in a site plan after the site survey has been done. More importantly the management of material on

site, there inventory, storage, hauling and removing them from site has to be issues paid attention

to while considering a site plan for the operation. This site plan also have a huge impact on the

issue of safety for workers and also general public and properties (Guy, et al., 2003).

2.3.3.8. Site security

Site security includes preventing the theft of equipment and tools, as well as the safety of anyone

trespassing onto the site. A partially dismantled house can be a temptation to vandals. Before any

work begins, the decision about whether salvaged materials will remain overnight will determine

the needs for fencing, and lockable containers for storage or the time that it will take each day to

remove materials from the site. Signage and warning tape should be used as due diligence to

protect the public from the hazards of a deconstruction site (IWMB, 2001).

2.3.3.9. Material management plan

Efficient management of material is an important part of the project. Recovered materials have

three places to go: Reuse, Recycle or Disposal. Efficiently managing the materials, allocation of

responsibilities for managing the materials, and the methods for planning and communicating

efficient materials “flow” on the site are very important for successful execution of project. The

major parts are removing material from structure, cleaning, sorting, stacking, recycling, hauling

and disposing material that can’t be reused or recycled. Deconstruction is creating materials for

reuse in the most cost-effective manner so, removing materials without damaging them and

keeping them in good condition when handling them will have to be insured. Increasing the amount

Page 52: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

43

of salvage on site and reducing the amount of disposed material are important to increase income

for contractors in deconstruction projects (Endicott, et al.; Guy, et al., 2003). Figures 2.21 and 2.22

below show different ways of creating stacks of material on site.

Figure 2.21. Sorting material by type

results in efficient flow of operations on

site. The pictures show different ways of

creating stacks for material.

(Source:

https://www.archsd.gov.hk/archsd/html/tea

chingkits/TK1/images/construction_waste

_management_clip_image004.jpg)

Figure 2.22. Using containers for sorting

material on site

(Source:

http://www.vivianmandaladesignstudio.com/

wp-content/uploads/2014/02/Sorting-

Construction-Waste2.jpg)

Page 53: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

44

2.3.4. Deconstruction equipment and tools

A wide variety of specialized demolition and deconstruction equipment have been developed.

Mostly demolition projects rely on heavy equipment and machinery while deconstruction rely on

smaller automatic and hand tools.

2.3.4.1. Deconstruction tools

Because in deconstruction most of the material has to be carefully salvaged for reuse and recycle,

smaller hand tools and equipment are used for the projects. Some of the tools and equipment used

for deconstruction are as follow, according to T. Reiff president of “The Reuse People” (as cited

in Endicott, et al., 2005):

• Axe (small and large)

• Pick axe

• Cats paw

• Chain saw

• Crow bars

• Short and long (prefer “Gorilla Bar” type crow bar)

• De-nailing gun and air compressor

• Drill

• Cordless with batteries and battery charger Hammers

• Ladders: 6 and 8 foot, 20’ extension ladders (fiberglass preferred)

Page 54: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

45

• Measuring tape

• Nails and screws

• Pliers Saws: bow saw, hand saw, hack saw rotary saw, Skil saw with grinder and wood

cutting blades Sawz-alls with bi-metal blades

• Screw drivers regular and phillips head

• Shovels: regular and specialty Snow shovels Roofing shovels

• Sledgehammers (small and large)

• Post-hole digger

• Pry bars

• Rakes Tamping bar or “Grizzly Bar”

• Tin snips

• Vise grips

• Wheelbarrows

• Wire and bolt cutters

• Wrenches adjustable

• 20 C.Y. to 40 C.Y. roll-off

• Covered truck to remove salvage

• Debris chutes

• Man-lift, Hi-lift, Fork Lift

Page 55: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

46

• Pneumatic or electric hammer with chisels

• Rolling scaffold

• Fall protection

• Safety equipment

• Respiratory protection safety suits and equipment

2.3.5. Reusable and recyclable material

Products of the deconstruction process fall into one of three broad categories: reused, recycled and

disposed. In current practice, reused and recycled materials can typically make up about 85% of a

building’s total weight, according to T. Reiff president of “The Reuse People” (as cited in Endicott,

et al., 2005).

2.3.5.1. Reuse

Instead of demolishing the whole building, this process tends to impact the least amount of change

to the existing building components by carefully dismantling each constituent. Ideally the best

situation in the end of the life cycle is the reuse of the whole building or the components in a new

combination. This practice does not change the material form and thus uses the least energy and

extra material when closing the loop of the component or building life cycle, according to Reiff

(as cited in Endicott, et al., 2005). After the deconstruction of a building, some parts of the salvaged

components and materials can be sold on-site, taken to the warehouse, or consigned to other

Page 56: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

47

resellers and sold to the public. Other materials may either be shipped to low-income markets or

donated to other nonprofit agencies.

According to “The Reuse People”, reused materials generally include, according to TRP

presentation (as cited in Endicott, et al., 2005):

• Appliances

• Architectural Pieces

• Bricks

• Cabinets & Vanities

• Doors

• Electrical

• Flooring

• Granite & Marble

• HVAC

• Lumber

• Plumbing

• Plywood & Oriented Strand Board

• Roofing Tiles

• Structural Steel

• Windows

Figure 2.23. Doors removed carefully from

structures for reuse.

(Source: The Reuse People (trp.org))

Figure 2.24. Windows removed carefully from

structures for reuse.

(Source: The Reuse People (trp.org))

Page 57: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

48

2.3.5.2. Recycle

This scenario is composed of three major processes. The first process group is deconstruction of

end-of-life buildings followed by the second, separation of used materials. Finally, in the third

process group, the used materials are reproduced and transformed to new products then

reintroduced into the life cycle of buildings (EPA, 2004).

Presently structures and components are not designed to be reused or recycled since the

components cannot be easily dismantled and separated once the building is demolished.

Contingent on the contamination, a considerable part of the recycled materials is limited to low

quality use or even landfilling (Endicott, et al., 2005). Figure 2.25 below shows the recycling of

concrete.

Typical recycled materials include, according to (TRP, 2005):

• Aluminum

• Asphalt

• Asphalt Shingles

• Carpet Padding

• Cast Iron

• Concrete

• Concrete Block

• Copper

Figure 2.25. Concrete being recycled by crushing

(Source: http://www.on-siterecycling.com/products/images/rm100-recycling-

concrete.jpg)

Page 58: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

49

• Glass

• Scrap Steel

• Stucco (when untreated)

• Wood (when untreated)

2.3.5.3. Disposed

The material that has very little or no recycle value like material mentioned below.

Typical disposed materials include (TRP, 2005):

• Ceramic Tile (because of glue)

• Drywall (because of paint)

• Plaster

• Stucco (when treated)

• Wood (when treated)

2.3.6. Various material handling

Corresponding to the various materials and components used in construction are the different

means, methods, tools, and techniques required to deconstruct the structures. The tools and

techniques used, as well as some difficulties associated with deconstruction, for steel, masonry,

concrete, and timber are described in this section.

Page 59: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

50

2.3.6.1. Steel

There are a number of different processes for removing steel from existing structures for reuse or

recycling. Crushers and pulverizes have been developed to remove reinforcing steel bars (rebar)

from reinforced concrete structures. Heavy-duty magnets can be used to remove reinforcing steel

during the process of crushing reinforced concrete.

Several opportunities for further development of tools and techniques exist in this area. For

example, a tool with an automated ability to remove bolts from connections could increase the

number of sections available for reuse instead of recycling. Currently, the ends of beams are

usually distorted in the removal process requiring that these damaged ends be cut off. The National

Federation of Demolition Contractors and the Institution of Demolition Engineers are two

organizations that can assist the industry in further development of such tools and techniques

(Endicott, et al., 2005).

2.3.6.2. Masonry

As is the case with all materials and structures, hand deconstruction results in the highest quality

of reclaimed materials. By using this meticulous method, contractor profits are maximized from

the sale of components to reclamation yards and recycling facilities (or the maximum tax benefits

are realized for the homeowner who donates the components to a not-for-profit organization). This

reality has been very evident in the case of masonry and brick.

In some cases, the contractor hand-cleans the bricks and in other cases the reclamation yards

remove the mortar themselves. However, the increased use of ordinary Portland cement (OPC) in

place of lime-based mortars has presented a problem for brick reuse. The lime-based mortars are

much easier to separate from the brick. Therefore, there exists a “need to investigate practical and

Page 60: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

51

cost-effective removal techniques for OPC mortars”. According to Hobbs (as cited in Endicott, et

al., 2005). Figure 2.26 below shows bricks that have been salvaged and cleaned for reuse.

2.3.6.3. Concrete

In most cases, concrete frames in concrete buildings are cast-in-place and cannot be deconstructed

for reuse in their original form. Pre-cast concrete components such as beams, columns, stairs, and

hollow-core floor slabs can be deconstructed provided the joints are simply supported.

Unfortunately, most joints are cast-in-place and that concrete is stronger than the precast

components it joins. New uniform jointing methods are being developed which hopefully will be

designed for deconstruction (EPA, 2006).

According to Hobbs (as cited in Endicott, et al., 2005) pre-cast concrete flooring systems are

commonly used in construction and are one of the simplest concrete components to deconstruct.

However, in some cases they are covered with a 50 mm cast-in-place concrete layer in order to

provide a monolithic slab, which prohibits deconstruction.

Figure 2.26. Bricks cleaned up after being

removed from building and ready for reuse.

(Source: The Reuse People (trp.org))

Page 61: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

52

One tool that is commonly used in repair applications holds promise in deconstruction. High

pressure water-jetting can cut concrete while leaving both the reinforcing steel and concrete clean

and reusable. Heating methods such as thermal lances may be used increasingly in the future

because they can cut through reinforced concrete while leaving the majority of the concrete

element intact.

2.3.6.4. Timber

Most existing timber components contain nails and screws. These must be removed for safe

handling before reuse or recycling. This is most often done by hand and generally is only

economically warranted for high value items like large section beams and old growth timber.

Lower value components such as studs and small section joists must be free of nails and screws

before they are chipped in recycling operations. Research and development is required in the area

of timber reuse and recycling. Although large amounts of timber are demanded and required in a

majority of residential construction projects, reclaimed lumber is not permitted for use in structural

applications because of the nailed and screwed connections. Furthermore, re-coding the wood is

expensive and not economically feasible at this point. The Scandinavians have developed one

method to remedy this problem. They reclaim defect free timber for reuse or recycling by

identifying ‘connector free zones’ within the timber cross section that can be easily removed using

a rip saw, according to Hobbs (as cited in Endicott, et al., 2005).

Page 62: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

53

2.3.7. Approaches to deconstruction projects

Three deconstruction models are currently being used across United States (DBRTF, 2014):

Full deconstruction

Hybrid deconstruction

Partial deconstruction (“skim” model)

2.3.7.1. Full deconstruction

Is removing a structure entirely through manual deconstruction intervention. This practice usually

takes anywhere from five to seven days or longer, depending on the size of the structure and costs

approximately 50 percent more than mechanical demolition (DBRTF, 2014).

2.3.7.2. Hybrid

The hybrid method combines the presence of human beings on the site, along with an excavator.

This variation of traditional deconstruction speeds up the work by using the excavator to carefully

assist the manpower on the ground by gently pulling down walls, porches, roofs, staircases, and

major elements. A crew of individuals can then get at these more easily, whether on site or for

transport to a warehouse to be taken apart manually. This practice usually takes anywhere from

one to three days, creates a lot of dust, and costs approximately 25 percent more than mechanical

demolition (DBRTF, 2014).

Page 63: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

54

2.3.7.3. Partial demolition

Sometimes referred to as the “skim” model, is a nuanced version of the full deconstruction model.

A “skim” model of deconstruction delicately balances the input (labor cost) with the throughput

(salvaged materials of value) over a much shorter period of time, one to three days versus five to

seven days or longer for full deconstruction. Typical materials manually removed from the

structure under a “skim” method of deconstruction are the higher-market resale items such as

hardwood floors, trim molding, stained glass windows, doors, and door jams. In addition the

estimated cost increase is only 10 to 12.5 percent more than mechanical demolition (DBRTF,

2014).

2.4. DESIGN FOR DECONSTRUCTION (DFD)

Deconstruction has emerged as an important practice for reducing the amount of demolition waste

that goes to landfills by reusing and recycling construction material. Reuse being a more favorable

outcome as it requires less resources for being used into a new construction thus causing less waste,

but in most cases it is not easy to deconstruct buildings and structures because they were not build

to be deconstructed. A new concept is being pioneered by construction professionals called Design

for Deconstruction.

Design for Deconstruction or Design for Disassembly is a technique that considers the entire

lifecycle of a building; design, manufacturing, construction, renovation, operation and eventually

deconstruction. It creates a closed loop building management option where the building systems,

components and materials are designed to be easily rearranged, dismantled, renovated, recovered

and reused (EPA, 2006).

Page 64: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

55

The traditional flow of resources in construction is a linear flow. The raw resources are mined

from earth and are processed into construction material, using a lot of energy and resources

needed for the process from mining to transportation to manufacturing and are simply disposed

of as waste to landfills.

The main benefit of Design for Deconstruction is to close the loop of resource use. This is done

by reducing the environmental impact of waste generated by renovation and deconstruction of

buildings because the material can economically recovered and reused, saving the material from

going to landfills and at the same time avoiding logging or mining of new virgin resources from

our ecosystem (Webster, et al., 2005; EPA, 2006).

Figure. 2.28. Closing the loop in material life cycle (EPA, 2008).

Page 65: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

56

Material salvaged from a deconstruction project is valued based on the function it can provide in

being used for new construction when assembled and therefor material are more valuable to be

reused than to be recycled. For example concrete can be recycled, but it can only be used as low

value aggregate, wood debris can be ground up but only used for wood fiber of mulch and therefor

losses its valuable properties to be used as construction material for new buildings. The challenge

is that these material were not put together to be recovered and reused and the goal of Design for

Deconstruction is to figure out how to put buildings together so that they can be economically

taken apart and reused in new construction (Webster, et al., 2005).

Efforts have always been made to create new construction systems that can encourage assembly

of buildings with standardized parts and connections, mass production and modular design but

they have not yet been able to come into the construction fields successfully. The Design for

Deconstruction is aiming to work with the current construction systems rather than working on

completely new construction systems (EPA, 2006).

Design for Deconstruction is not just concerned with the salvage of material at the end of the life-

cycle of a building but by making building components easier and faster to remove and reassemble

it meets the evolving functions of a building use over its lifetime. An important aspect of Design

for Deconstruction is to provide structural system with flexibility to reconfigure spaces. The

utilities and infrastructure of the buildings to be easily accessible for maintenance and upgrade.

According to (EPA, 2006) the principles of Design for Deconstruction are applied at three levels

of buildings and structures: materials, assemblies and building systems. In addition, building

information is an important aspect of Design for Deconstruction.

Page 66: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

57

2.4.1. Materials

Caution should be applied while selecting construction material. The material being used should

have the value to be recovered and reused in future. Hazardous material such as asbestos and lead

based paints should be avoided as much as possible. If for reasons of performance they still have

to be used, they should be tagged and identified properly so that they can be handled with caution

at the end of their useful life (EPA, 2006).

Using fewer material types simplifies deconstruction. Composites should be avoided where

possible. If the architectural aspects and performance allow, fewer material types with careful

interface should be considered (Webster, et al., 2005; EPA, 2008).

Using less material to realize a design makes a building design less complicated, require less labor

and reduce the waste of resource usage while construction and also requires less labor to

deconstruct (EPA, 2006).

It is encouraged to reuse salvaged material from existing buildings as this will minimize waste,

incorporate reused material and support the market for reuse of material.

2.4.2. Assemblies

Assemblies dictate how material come together to create fitted architectural blocks to complete

structures. Less adhesive and sealants should be used where possible and be replaced by simple

and stronger fittings and fasteners. Glues and chemicals damage materials and being removed,

instead the use of bolts, screws and mechanical connections are favored (EPA, 2006).

Assemblies should be readily accessible and where possible exposed to allow maintenance and

disassembly. It should be easy to repair assemblies when needed and other material should not be

Page 67: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

58

degraded for maintenance. For example to replace a window, there shouldn’t be a need to cut and

patch drywall and stucco (DfD, 2006).

Modularity and prefabrication of assemblies and components can promote reconfiguration, reuse

and recycle to a large extent. Fewer but larger components are favored. The assemblies should be

modularized only when it makes it easier to construct and deconstruct (EPA, 2006).

2.4.3. Building systems

Building systems are mostly modified to accommodate each other such as infill, substructure,

enclosure, mechanical, electrical, HVAC, etc. Disentangling all these systems from each other

makes it easier to maintain individual systems and facilitate adaptation and deconstruction of each

system (EPA, 2006).

Separating building systems and layers helps with flexibility and adaptability. Different utilities

such as HVAC, plumbing, electricity, etc need to be separated from structural components and

each other and should be readily accessible. Often in buildings, it is the utilities that require regular

maintenance and replacing. This will not only help during the life time of the building but during

the end of the lifecycle also, as it is much easy to recover and reuse if in good condition.

Separating or disentangling the utilities from the structure also is one of the main goals in Design

for Deconstruction. For example if the utilities are disentangled from the interior walls of the

building, the walls assemblies can be reconfigured as needed during the lifetime of the building to

create a flow of usefulness.

Page 68: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

59

2.4.4. Building Information

All the concepts of Design for Deconstruction implemented in building construction needs to be

clearly recorded with drawings and photographs of the utilities before they are concealed behind

walls and ceilings. This information should be maintained throughout the life time of the building.

These documents can be used to reconfigure assemblies, components and spaces as needed during

use and can also help with deconstruction at the end of the lifecycle of the building (EPA, 2006).

The concepts of Design for Deconstruction are in its conceptual stages in the United States. The

architect and engineers don’t build buildings with the consideration of the building to be taken

down when its useful lifetime ends. The issues and concepts of Design for Deconstruction are

addressed through education and research (DfD, 2006).

2.4.5. Case studies

In the following section, two case studies are provided that have implemented the concepts of

Design for Deconstruction in an effort to make these practices more widely accepted in

construction industry.

The first case study is a residential structure and the second case study is a school building. In both

the projects the United States Environmental Protection Agency (USEPA) had partnered with

others to implement these projects as pioneering projects of Design for Deconstruction.

Page 69: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

60

2.4.5.1. Boulevard House

This is a residential Design for Deconstruction project that has been referenced from Lifecycle

Construction Resource Guide (EPA, 2008). The project is a joint venture between the U.S

Environmental Protection Agency (EPA), Community Housing Resource Center (CHRC) and

Pennsylvania State University’s Hamer Center (EPA, Lifecycle construction resource guide,

2008).

This project is an effort to introduce best practices of DfD in residential design. Reducing the

Environmental impact of the project during construction phase, the flexibility of the design for

remodeling spaces in future and the ability to deconstruction the building are highlights of this

project presented in the following section. Figure 2.9 provides a description of the project.

Figure.29 Description of the project

Source: (EPA, 2008)

Page 70: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

61

2.4.5.1.1. Repositioning Interior Walls

The interior walls of this home can be moved and relocated without creating any waste or

compromising structural integrity of the structure. This is achieved by spanning the floors and

ceiling from exterior wall to exterior wall and making the interior walls non-structural. The utilities

have been disentangled from the interior walls so they are not a problem when moving the walls.

The flexibility of the plan is demonstrated in the figures 2.30 and 2.31 below.

Figure 2.30. Current plan

Source: (Korber, et. all, 2006)

Figure 2.31. Potential future plan

Source: (Korber, et. all, 2006)

Page 71: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

62

2.4.5.1.2. Disentangled heating and cooling systems

Instead of using on HVAC system for the whole house it was split into two parts, one for each

floor. Two smaller air-conditioning pumps were used instead one large pump. The unit for the first

floor is located in the basement crawl space and the second floor unit is placed in the attic. This

reduces the amount of duct work and the need for a core to run from basement to the top floor to

provide the duct work. This also allows the interior walls to be moved and relocated without having

to deal with reconfiguring the system (EPA, 2008).

2.4.5.1.3. Plumbing and electrical systems

The electrical and plumbing systems are bundled in a central location to avoid running them

through all the interior walls. These duct works were also placed in the attic and crawl spaces to

keep them untangled from the interior walls to be able to disassemble the interior walls without

having to deal with the utilities (EPA, 2008).

Figure 2.33. Photos showing Construction details of the

movable walls. Screws are used instead of glue or nails to

attach the parts. For ease of disassembly and

deconstruction the screws are left revealed.

Source: (Korber, et. all, 2006)

Page 72: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

63

Figure 2.34. Description of the Design for Deconstruction concepts implemented in the project.

Source: (Korber, et. all, 2006)

Page 73: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

64

2.4.5.2. Chartwell School

This project was partially funded by the United States Environmental Protection Agency’s Office

of Solid Waste and Emergency Response (OSWER) Resource Conservation Fund. The Chartwell

School was designed to help promote practices to readily disassemble building components and

material for reuse and replacement (EPA, 2008).

This school aims to be a development model in the region by implementing sustainable practices

to minimize the environmental impacts of the project throughout its lifecycle and at the same

provide a healthy environment for the occupants of the building. Certain unique approaches were

explored in this project by professionals. Some of the highlights of the project are as following

(EPA, 2008):

Figure 2.35. Description of the project

Source: (EPA, 2008)

Page 74: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

65

The school is designed for adaptability to accommodate changes in space organization, this is done

by making all the interior walls non-structural partitions that can be removed without

compromising the structural integrity of the building. The interior shear walls which are structural

are over designed to accommodate any opening cuts for windows and doors if needed in the future.

Figure 2.36 demonstrates the utility plan of the school.

2.4.5.2.1. Utilities

All the utilities in this building are exposed and placed in a raceway through the recessed shelf

along the corridor. This approach disentangles the utilities from the structure so the interior walls

can be disassembled and moved if needed without having to reconfigure the utilities. Maintenance

and recovery of utilities when needed is made easier. The wooden frame of the structure does not

Figure 2.36. Plan of the School showing utility raceway

Source: (EPA, 2006)

Page 75: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

66

accommodate the utilities, which results in fewer holes in the wood framing which increases its

value to be salvaged in the end of the lifecycle of the building.

2.4.5.2.2. Modular framing

The design of this school is a modular design, which allows for all the room sizes, doors, windows,

interior partitions land on a module layout. This allows for ease in disassembly and remodeling.

This building incorporates fewer high capacity fasteners for the structure which can be removed

easily in the future. The structure is based on 24” on-center module instead of a 16” on-center

wood frame, this approach saved up to 30 percent in lumber needs which decreased the labor also

(EPA, 2008). Figures below show the conventional framing method and the modular framing.

Figure 2.37. Conventional 16” o-c framing requires 2618

bf lumber

Source: (EPA, 2006)

Figure 2.38. 24” o-c framing requires 1908 bf lumber

Source: (EPA, 2006)

Page 76: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

67

2.4.5.2.3. Creativity with material and detailing

Some of the key principles followed in this project for Design for Deconstruction include: use of

fewer but larger components that require less labor and ease the process of deconstruction,

simplified connections by using fewer high capacity fasteners instead of nailing and use of

chemicals, keeping details and utilities exposed for ease of understanding the structure and ease of

deconstruction in the future (EPA, 2006).

For roof framing Structural Insulated Panels were selected in order to simplify connection and

reduce labor and waste. A single SIP unit combines the roof sheathing, insulation and ceiling finish

in one single component. They come in large unit sizes and are connected to the structure with

large screws. These units can be easily removed in the future and used for another building (EPA,

2006). Figures below provide structural, roofing and window details used in the project.

Figure. 2.39. Roof trusses spanning from exterior wall to exterior walls. Source: (EPA, 2006)

Page 77: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

68

Figure. 2.40. Structural Insulated Panels and Conventional roofing details. Source: (EPA, 2006)

Figure 2.41. Removable window details. Source: (EPA, 2006)

Page 78: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

69

2.4.5.2.4. Windows

Two alternate window details were developed to address the issues of providing the ability to

remove the windows without touching the cladding and components around the window frame.

This facilitates the removal of windows without damaging them for future use, or without

damaging the cladding around the windows.

2.4.5.2.5. Exterior siding

Some of the wood used for exterior siding in this project is salvaged wood from other projects.

The challenge was provide detailing for exterior paneling to be able to remove and salvage the

wood at the end of lifecycle of this building and reuse it. Normally the siding would be nailed to

the frame, but that creates holes in the wood and makes it difficult to remove the wood without

damaging it. Screws could have been used but if they are painted over during the building lifetime

and concealed, they become difficult to remove. And even the screws create holes in the wood and

make it defective.

Many alternate details were provided for this project that included: use of tongue and groove

method with the used of metal clips to hold the panels, use of channels for sliding the panels into

the frame, use of very strong double stick tape. Some of these detailing are shown in figures 2.42

through 2.45 below.

Page 79: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

70

Figure. 2.42. Siding attached with double stick tape.

Source: (EPA, 2006)

Figure. 2.43. Siding attached with C-channels.

Source: (EPA, 2006)

Figure. 2.44. Siding construction detail.

Source: (EPA, 2006)

Figure 2.45. Siding done with Tongue and Groove

method with clips.

Source: (EPA, 2006)

Page 80: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

71

2.4.5.2.6. Building information

One of the main objectives of Design for Deconstruction approach is to provide construction

drawings, specifications and instructions for deconstruction of the building in the future. Many

approaches were implemented in Chartwell School to provide and maintain this information (EPA,

2008):

A final record of drawings with a hard cover were provided and included information for

reproduction rather than removal of drawings from the bound.

Some building components and materials were directly labeled in the building, for example

the roof trusses are labelled for engineers to determine future use of the trusses.

Most of the utilities and construction details were left exposed to make the need for

drawings less critical.

Permanent signage were provided with the contact information about architect and

engineering design team for future reference when needed.

2.5. Summary

Demolition and deconstruction are rapidly growing parts of the construction industry. These are

complex businesses and require technical and managerial skills combined with experience.

Demolition using heavy equipment is the traditional process for building removal. Modern

demolition equipment removes structures quickly, destroying the materials within and creating

solid waste destined for landfills. Some recycling does occur during the demolition process, most

typically concrete, brick, metal, asphalt pavement, and wood. However, landfill costs in many

states are still low, enabling wasteful disposal practices.

Page 81: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

72

Environmental impacts from demolition activities are sizeable, both upstream and downstream.

Deconstruction can work to offset the environmental impacts of the building related waste.

Deconstruction not only diverts wastes from landfills, it also reduces greenhouse gas emissions by

reducing the need to extract and ship new materials and also gives rise to a new industry of skilled

jobs. In order to transform the industry, demolition should incorporate successful aspects of

deconstruction, and future construction should incorporate design for deconstruction for maximum

use of material.

This chapter reviewed the planning and management aspects of demolition and deconstruction.

Further, the various approaches used for demolition and deconstruction and equipment needed to

carry out the projects are reviewed. It is important to mention that both demolition and

deconstruction are complex businesses and various aspects of each can be studied separately in

more detailed manner. The scope of this study briefly covered aspects such as modern practices,

equipment, safety issues, regulations, material handling, etc.

The next chapter reviews the cost aspects of both demolition and deconstruction.

Page 82: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

73

CHAPTER 3

3.0. COMPARISON OF DEMOLITION AND DECONSTRUCTION;

COST AND PROCESS

3.1. INTRODUCTION

This chapter presents the approaches used in cost estimation of demolition and deconstruction

projects. All the pre-estimation tasks that are necessary for gathering information and planning for

the project are introduced with their impact on the cost. A breakdown of the major cost components

of a demolition and deconstruction project are presented through case studies. Interviews with

contractors are analyzed and a summary is presented. Finally, a comparison matrix of demolition

and deconstruction is presented followed by a cost comparison of both approaches.

3.2. COST ESTIMATION OF DEMOLITION PROJECTS

It is important to figure out the net cost of demolition. According to (Guy, 2001) the net cost for

demolition project is: (Demolition + Disposal) – (Salvage value). This section discusses various

factors that impact cost estimation and items covered in a demolition estimate; and provides a

sense of the cost of demolition through a case study and available literature and database sources.

3.2.1 Cost estimation factors

Many factors are determined while planning and executing a demolition project. These factors

determine the approach to be used and have impact on the cost of the project. Some of the factors

can be as following (Lui, et al., 2012; Diven & Shaurette, 2010):

• Preparatory estimating tasks

• Project location

• Available information

• Schedule

• Weather

• Regulatory requirements

Page 83: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

74

• Project size

• Available resources

• Salvage

• Quantity takeoff

3.2.1.1 Preparatory estimating tasks

This includes thorough understanding of the specifications of the project to be demolished.

Normally the specifications of the project might be provided by the clients’ architectural or

engineering firm. But the estimator needs to understand and list all the sections that will affect the

cost and also the information needed for cost estimation such as insurances, bonds, subcontractors

list, work plans, etc. This may also include a Rough Order of Magnitude (ROM) cost for a project

which can help the contractor determine if the project is suitable to match the available resources

of the company (Lui, et al., 2012; Diven & Shaurette, 2010).

3.2.1.2 Regulatory requirements

As discussed earlier, there are regulatory requirements at the federal, state, county, city and owner

level that can affect the cost of the work and the estimator needs to be completely familiar with

them and include them in the cost estimation. Compliance with some of these regulations might

be very costly but they help in creating safe and environmentally responsible projects if properly

applied. For example, the environmental regulations may require the contractor to comply with

Storm Water Pollution Prevention Plan (SWPPP) which can cost up to thousands of dollars to

install and maintain (Diven & Taylor, 2006).

Demolition permits and some other permits required for projects such as, the Asbestos Containing

Material removal, utility works, street use, etc. usually issued by local municipalities can also well

Page 84: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

75

exceed thousands of dollars. The estimator needs to be aware of them and include them in the cost

estimation.

3.2.1.3 Project location

The location factor must be taken into account by the estimator. Demolition of projects in

congested urban settings or in operating industrial plants is much higher because of the cost needed

for the protection of adjacent structures and utilities. The location of the project may restrict

accessibility or use of large equipment and instead may require small equipment and hand labor

which significantly affects the cost.

Remote sites on the other hand requires considerable planning and management to accomplish

mobilization and demobilization of equipment and personnel. Some location factors that can affect

the cost are as follows (Lui, et al., 2012; Diven & Shaurette, 2010).

Temporary living quarters

Personnel transportation

Security

Mobilization of equipment and tools

3.2.1.4 Project size

The size of the demolition project has a significant impact on the unit cost of the project. A larger

project may cost less per unit than a relatively smaller project, this is due to the spread of the cost

over a larger area. For example, if the cost of mobilization and demobilization is about $5,000

Page 85: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

76

each for two projects of 3,000sf and 20,000sf building demolition. The cost of mobilization and

demobilization per square footage is about $1.67/sf for the 3,000sf building, where it will cost

$0.25/sf for the 20,000 sf building (Diven & Shaurette, 2010).

Height of the building also impacts unit cost of the project. Higher buildings cost more per unit

than low rise buildings. This is due to the increased cost of safety measurements and material

handling amongst many other factors.

3.2.1.5 Available information

The estimator should attain information regarding the demolition projects from several sources

including (Diven & Taylor, 2006):

Company records: available data about previously implemented demolition projects by the

company are good resources for the estimator to cross check quantity take-offs and costs.

As-built drawings of the structure: access to as-built drawings of the structure will assist the

estimator in accurately quantifying building components. This can save time and increase accuracy

of takeoffs in comparison to the process of measuring on site and calculating quantities.

Utility locations: the owner will try to provide drawings for locating utilities in and around the

structure accurately but in some cases it is not possible. Therefore, the estimator should allow costs

in the estimation for locating utilities of should mentions that the utility survey is not included in

the cost if that is the case.

Page 86: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

77

Site inspection: enough time should be allowed for thorough inspection of the site. The site visit

is important for the estimator to determine the effects of added costs if any and verify the accuracy

of the drawings.

Disposal and recycling sites: the estimator should be fully aware of the location of businesses that

provide landfill and recycling yards in the work area.

Former use of property: it is necessary to understand previous use of the building for cost

estimation. The possibility of chemicals and contaminants presence on the site can impact the cost

significantly. Similarly if any previously demolished building material is buried under the site, it

will impact the cost of removal of the material significantly.

Hazardous material survey: the presence of Asbestos and other hazardous material on demolition

projects are a major cost factors. In some cases the removal of such material may cost more than

the project itself.

3.2.1.6 Available resources

The estimator should be fully aware of the availability of qualified personnel and equipment

necessary for a project. The estimator usually assumes that the company will have the necessary

equipment for a demolition project, the company may own some of these equipment. But if the

equipment is not available for a project the estimator should consider the rental cost of the

equipment for estimation.

Page 87: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

78

3.2.1.7 Schedule

Some projects may require unrealistic or very difficult schedule performance. The estimator should

take into account overtime costs, late completion penalties, additional personnel and equipment

costs that are required for completion of the project (Diven & Taylor, 2006).

3.2.1.8 Salvage

Net values of material and equipment that can be removed from a demolition project for salvage

purposes should be taken into account by the estimator. The ownership of such material should

also be well resolved before a project can start. Sometimes the owner may want to keep such

material or equipment and this issue can create a lot of financial and legal issues (Diven &

Shaurette, 2010).

3.2.1.9 Weather

Unusual weather conditions and time of the year can impact the cost of demolition. The estimator

should consider the weather and in most cases allow for some contingency in the estimation, this

allowance can cover the weather-related costs (Lui, et al., 2012).

3.2.1.10 Quantity takeoff

A site visit to the demolition project is one of the most important opportunities for the estimator to

determine the accuracy of information provided to her/him and verify drawings, measure building

Page 88: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

79

material, utilities, proximity of structure, ground conditions and any other information that will

affect the cost and schedule of the project. It is important for the estimator to calculate and

categorize the following items (Diven & Shaurette, 2010):

Hazardous Material: a thorough survey of presence of hazardous material on site will provide the

information regarding the quantities of such material on site. These surveys might be provided by

the owner along with specifications of the project. If not provided, then the contractor should

inform the owner of all the additional compensation needed for survey and removal of such

material.

Building material: material such as concrete, brick, CMU blocks, wood, steel, etc. should be

calculated by the estimator from the available drawings or by measurement on site.

Site restoration: the quantity and type of material needed for restoration of site such as backfill,

compaction, landscaping, fence, etc needed for the project after the completion of demolition work

should be estimated for cost considerations.

Salvage value: the estimator also needs to carefully quantify the negative cost item that is the

salvage material that can be retrieved from the project and will have impact on the overall cost of

the project.

3.2.2 Cost components of a demolition project

Accurate and reliable demolition budgets must account for the cost of a variety of items. These

include the demolition contractor’s requirements for personnel and equipment, as well as any costs

required by the client for a typical project (e.g., safety officer, fire watchman, pedestrian controller,

Page 89: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

80

traffic controller, and so on) (Lui, et al., 2012; Diven & Shaurette, 2010). Table 3.1 shows the

major cost components of a demolition project.

Table 3.1 Major cost components generally covered in an estimate of demolition projects.

Cost Components of a Demolition project

Permits

Mobilization and demobilization of equipment and personnel

Survey

Site protection and safety

Engineering services

Environmental surveys

Utility work

Supplies (e.g., scaffolding, lumber for protection, cutting gases, etc.)

Demolition labor and equipment

Security personnel

Material handling

Disposal fees

Earthwork

Cleanup

New construction

General and administrative expenses

Credit for salvage

Subcontractors

Page 90: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

81

3.2.3. Demolition case study

Over several decades, many techniques have been developed to analyze and estimate the

construction costs of buildings. On the other hand, the cost parameters of demolition, which can

be viewed as the reversed process of construction, have not been formulated (Lui, et al., 2012).

This section aims at understanding the major cost components used for estimating demolition

project cost. It uses residential building as a case study.

The state of Michigan recently awarded the contract for the demolition of about 1,700 blighted

publicly owned houses at a cost of $20.1 million for the Genesee County Land Bank Authority.

The aim of the project was to sell some of the vacant lots to interested adjacent owners and

maintain the remaining lots for up to 5 years after demolition (Genesee County Land bank, 2014).

The major cost components of the demolition work are presented below in Table 3.2. On an

average each residential structure costed $10,600 to demolish.

Table 3.2 Full cost of demolition of a house in Michigan (Genesee County Land Bank, 2014)

No. Cost Item Cost ($)

1 Property inspections and surveys 300 – 600

2 Abatement and disposal of hazardous material 0 – 15,000

3 Utility cuts 250 – 600

4 Demolition permit 75 – 350

5 Structure and basement removal 2,300 – 25,000

6 Backfill with clean soil and initial site grading 1,200 – 2,000

7 Final grade including seeding and mulching 500 – 750

8 Full Cost of Demolition Per House Average 10,600

Page 91: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

82

Since 2003, the Land Bank has managed the demolition of more than 3,000 structures in

cooperation with the City of Flint. Based on demolition activity under the recent federally funded

Neighborhood Stabilization Programs (NSP), the average cost of demolition was $10,600.

According to the Michigan State Housing Development Authority (MSHDA), the state-wide

average for single family demolition under NSP 2 was $12,000. The Land Bank’s average

demolition cost is in line with other similar efforts, e.g. that of Cuyahoga County Land Bank in

Ohio (Genesee County Land Bank, 2014).

The cost of demolition-related activities varies greatly based on the size and condition of the

structure. Costs can range anywhere from $3,000 to $25,000 (Genesee County Land Bank, 2014).

Abatement and demolition contractors develop their cost estimates based on the size and the

complexity of the job. The building material of the house also impacts the costs, e.g., brick

structures often cost more to demolish than wood structures. The amount of recyclable material in

the structure can also help to reduce the overall cost, e.g., as contractors may be able to salvage

any remaining metals in the structure.

The abatement of asbestos and hazardous materials greatly impacts the cost of a demolition. Some

structures are loaded with asbestos-containing materials and can cost as much as $15,000 to abate

while others have few or no abatement costs. Houses that are severely burned often do not have

inspection or abatement costs. However, all debris material must be treated as hazardous and

asbestos-containing and disposed of in special landfills with higher tipping fees. The complexity

of the project and the expertise required on the site also impacts the cost (Genesee County Land

Bank, 2014).

Page 92: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

83

Assuming that an average house is about 2,000 SF, including the garage, shed, etc. The cost of

demolition work is about $5/sq.ft. Many structures have fallen into a particular level of decay due

to neglect, the elements, or a previous fire, and there is little or no salvage value remaining. The

structures are on the city’s emergency demolition list and have to come down immediately.

It should be noted that two cost components are major cost items in this case; Abatement and

disposal of hazardous material and Structure & basement removal. The cost of these components

can highly impact the overall cost of demolition based on the type of construction and material

present in the structures.

3.2.4. Sources for Cost estimation of demolition projects

The estimator must have the knowledge of expected production rates each task to be performed in

a demolition project. This might be known from previous experiences or job records of the

company or the use of databases such as R.S. Means facilities construction cost data reference

book (RSMeans, 2014).

3.2.4.1 RSMeans building construction cost data (RSMeans, 2014)

Since 1942, RSMeans has been actively engaged in construction cost publishing and consulting

throughout North America. The primary objective is to provide construction industry professionals

with the current construction cost data. All the cost data has been divided into 50 divisions

according to the master format system of classification and numbering.

Division 2- Existing Conditions; provide cost data relating to various cost components of

demolition and deconstruction projects. Particularly the sub-divisions i.e. 02 40 00 Demolition and

Page 93: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

84

structure Moving, provide cost data for selective demolition. This subdivision does not include

rubbish handling and disposal, Hazardous material handling, etc. Each of these items should be

estimated using other sub-divisions in the data base.

In addition to subdivision 02 40 00, one can find selective demolition items in each division.

Example. Roofing demolition is in Division 7. Many unit costs from various subdivisions might

be used when estimating demolition projects such as:

Concrete superstructure

Concrete slab on grade

Concrete foundations

Concrete crushing

Wood frame building

Assemblies

Steel frame buildings and structures

Cost of handling, trucking, and disposal of building components

Subdivision 02 41 16 provides cost data for structure demolition based on the type and size of

structures. These costs do not include hauling and dumping of debris, removal of hazardous

material. Other subdivisions i.e. 02 50 00 Containment of hazardous waste, 02 80 00 Hazardous

material disposal should be used in conjunction with this subdivision to estimate the overall cost

of demolition projects. Some of the costs are provided below. Table 3.3 shows demolition cost of

residential structures based on area, type of construction and number of story of the building.

Page 94: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

85

Table 3.3 Demolition cost of various residential structures based on type, height and area of

structures (RSMeans, 2014).

Type of structure Area Total cost

Single family, wood

construction

1,600 s.f $5,725

Single family, wood

construction

3,200 s.f $11,500

Two family, wood

construction

2,400 s.f $8,575

Two family, wood

construction

4,200 s.f $15,300

Three family, 3 story, wood

construction

3,200 s.f $11,500

Three family, 3 story, wood

construction

5,400 s.f $19,100

3.2.4.2 Buildingjournal.com. (http://buildingjournal.com/estimating-demolition.html, 2014)

Another reference for achieving unit cost for demolition projects is “Buildingjournal.com”. It is

an online database which provides unit cost of demolition works based on project size, type, and

location. Examples from this online cost database have been presented below. It should be noted

that various cost items, that is, the presence of hazardous material removal and disposal, have not

been clearly defined in this cost database. Where these items can highly effect the overall cost of

the project. Figure 3.1-3.3 below show cost estimation of various projects based on their height.

Page 95: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

86

Figure. 3.1 Cost estimation of demolition for apartments which are 1 to 3 story high, using the

online source (http://buildingjournal.com/commercial-construction-estimating-demolition.html,

2014).

Figure. 3.2 Cost estimation of demolition for apartments which are 4 to 7 story high, using the

online source (http://buildingjournal.com/commercial-construction-estimating-demolition.html,

2014).

Page 96: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

87

Figure. 3.3 Cost estimation of demolition for apartments which are 8 to 24 story high, using the

online source (http://buildingjournal.com/commercial-construction-estimating-demolition.html,

2014).

It can be inferred from the above database that the cost of demolition for apartment buildings

increase as the number of story or height of the building increases. This is due to various factors,

that is, the increased cost of safety, increased cost of material handling and removal, etc.

The online cost database (buildingjournal.com) provides a quick estimation of a demolition project

without considering the details of the type of structure and material used among many other

important factors that highly affect the cost of demolition project. The RSMeans cost database

provides a more comprehensive estimation of demolition projects.

Estimating demolition projects are challenging because projects are different and contractors may

use various approaches based on their own experience.

Page 97: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

88

3.3. COST ESTIMATION OF DECONSTRUCTION PROJECTS

The estimate for deconstruction basically contains two major parts: the cost to deconstruct and the

value of the salvaged materials, a combination of which will provide the net cost of deconstruction.

Guy (2001) developed economic equation for deconstruction to estimate the net income for the

work. The net cost equation for deconstruction is:

(Price Paid by Owner + Salvage Value) - (Pre-Deconstruction + Deconstruction + Processing +

Transportation + Disposal).

According to (CCE, 2001) the major cost components are:

• Labor

• Tools and Equipment

• Handling and transportation of material

• Overhead

• Profit

The major salvage value is gained through:

• Reuse Material Value

• Recycle Material Value

• Tax Credits for Materials

3.3.1 Cost estimation steps for a deconstruction project

In order to properly identify the costs associated with any deconstruction project, the major process

involved must be established. The following indicates the major steps in the process for which the

cost component must be determined:

Page 98: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

89

• Survey

• Material management

• Hazardous material

• Historic preservation

• Demolition permits and utilities

• Compliance with regulations

3.3.1.1 Survey

There must be a site visit by the estimator to examine the building through a visual survey in order

to estimate the basic material type and overall condition of the building. This includes taking an

inventory of the materials (types and quantities) and measuring the building. Categories of

material are: reuse, recycle, hazardous disposal, C&D disposal, solid waste disposal (IWMB,

2001).

3.3.1.2. Material management

Material management on site and removal of material from site is a major cost component of the

deconstruction process. After a complete survey and inventory of material, the estimator must also

know where the reusable, recyclable, hazardous disposal, C&D disposal, and solid waste disposal

will go and the means to get it there. Understand and prepare specific outlets (contacts), general

markets (advertisement) and methods (equipment, labor, sub-contracts) for removal of all

materials from site (CCE, 2001).

3.3.1.3. Hazardous material

The estimator should be thorough with the cost of survey and removal of hazardous material which

can significantly impact the cost of the project. In some cases the client themselves provide

complete surveys and pay for removal of the hazardous material. If that is not the case the

Page 99: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

90

contractor must inform the client of all cost associated with it. Environmental surveys for lead and

asbestos has to be completed for any building completed before 1978. The process of

deconstruction is heavily influenced by the presence of asbestos containing materials (ACM) and

lead-based paint materials (LBP). Asbestos abatement involves the removal of all ACMs before

work begins. Proper notifications and permits must be obtained from the appropriate statutory

authorities (Guy et al., 2003).

3.3.1.4. Historic preservation

Buildings in older parts of a city or those appearing old may have a historic preservation oversight

by local municipality, thus, it is important to obtain the necessary permits. The estimator must

consider the cost of obtaining these permits, and the cost associated with the preservation process

(Divine & Taylor, 2006).

3.3.1.5. Demolition permits and utilities

The estimator must consider the cost of obtaining permits from local municipalities for the project.

And before the start of any work, all utilities must be disconnected. This includes electricity,

natural gas, water, wastewater, telephone, and cable. It is important to find out if the disconnection

of utilities is included in the demolition permit approval process or has to be obtained separately

(IWMB, 2001).

Page 100: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

91

3.3.1.6. Compliance with regulations

OSHA specifies the completion of a building engineering survey and dismantling plan before a

demolition work starts. This plan highlights known hazards at the time of inspection, the structural

fabric of the building, and the general schedule, tasks, techniques, and tasks to be employed in the

deconstruction work (Guy et al., 2003).. The estimator should include the costs of compliance with

these specifications, especially in the case of deconstruction projects, safety can be of high cost.

3.3.2 Cost components of a deconstruction project

Deconstruction projects require more time and labor hours as compared to demolition project.

Therefor it requires extensive planning and management. Table 3.4 below provides a summary of

the major costs components of a deconstruction project identified above.

Table 3.4 Major Cost Components for Deconstruction

Major Cost Components of a Deconstruction Project

Survey

Environmental Health and Compliance

Historic Preservation

Permits and utility work

Engineering Survey

Safety

Material management

Estimate: Costs (Labor, Tools/Equipment, Landfill, Oh & Profit)

Estimate: Salvage Value (Reuse, Recycle)

Page 101: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

92

3.3.3. Deconstruction case study

The Center for Construction and Environment (CCE, 2001) deconstructed six (6) houses during

1999-2000 to examine the cost effectiveness of deconstruction and salvage when compared to

traditional demolition. This research was funded through the Florida Department of Environmental

Protection (FDEP) Innovative Recycling Projects grant program. One of the six residential

structures has been presented here as a case study of the deconstruction cost estimation. The

selected building is identified as (2930 NW 6th Street), located in Gainesville, Florida, built in

1915.

This was a one-story house with a detached garage, the garage was approximately 500 SF of the

total 2014 SF. The house was wood raised on brick piers, the garage was a CMU wall construction

on concrete slab. This building had several additions and several layers of interior finishes, i.e. two

wood floors and two roof finishes, a metal roof laid over an asphalt roof. The interior walls were

predominantly plaster and lathe. The plaster was separated from the lathe to see if the lathe could

be recycled or used for fuel in pottery kilns. This project was affected by a summer heat wave and

several rain days. The site had ample room for the layout of de-nailing areas and roll-offs, and did

not require extensive site work to make space around the building.

Deconstruction costs were collected for labor, other costs, disposal costs, environmental

assessment and salvage costs. This case study represents a situation where there are no materials

storage, inventory, and sales personnel costs. Materials are given a retail value and deducted from

the deconstruction costs for a net deconstruction costs without the additional costs for overhead on

the materials themselves. Table 3.5 below shows a summary of the cost for the deconstruction of

the building.

Page 102: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

93

Table. 3.5 Economic summary for the building deconstruction (CCE, 2001).

No. Cost Item Cost ($)

1 Permit 50.00

2 Asbestos survey 1,200.00

3 Asbestos abatement 740.00

4 Disposal 1,334.00

5 Supplies 637.93

6 Labor and equipment cost 8,469.38

7 Toilet 63.00

Total Cost 12,504.32

8 Salvage value 9,415.00

9 Net Cost of Deconstruction 3,089.32

The cost of deconstruction before deducting the salvage value is 6.21 per SF. And after the

deduction of salvage value it is 1.53 per SF.

Labor productivity data was collected in the following task categories:

Supervision: directing and planning the flow of work on the job site.

Deconstruction: Labor involved in the initial removal of materials from the structure. Any manual

or mechanical procedure required to remove materials for salvage either the direct handling of a

material or removing other materials to gain access to the salvage material.

Demolition: The hand or mechanical removal of building materials for direct disposal.

Processing: Preparing materials for redistribution in reusable form. De-nailing is the most typical

processing activity.

Page 103: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

94

Non-production: non-production occurs when no work is being performed. This includes breaks

and lunch, and the unloading and clean-up of daily tools. Any work stoppage greater than five

minutes and not coordinated by the supervisor is considered non-production.

Clean-up / Disposal: sweeping and/or removing debris or demolition materials from a work area

and/or disposal into a roll-off container. Clean-up does not involve de-nailing, loading, stacking

or transporting processed materials.

Loading/unloading: loading or unloading materials from the site onto a truck for transport and at

the final storage area. Any efforts to move, stack or place the lumber is a loading activity.

Table 3.6 below shows the percentage and number of labor hours spent on each of the categories

of work explained above.

Table. 3.6 Labor time by work categories (CCE, 2001).

The “gross” deconstruction cost was $6.47/SF, which is approximately 26% higher than

demolition. Disposal costs for deconstruction were 15% of the total costs. Gross deconstruction

cost is the first cost of the deconstruction which includes all labor and disposal but does not include

any salvage revenues. Asbestos and lead surveys and remediation was an average of $0.97/SF or

15% of the costs for deconstruction.

The average salvage value was $3.28/SF. The “price” of salvaged lumber was estimated at between

25-50% of new lumber retail value in local stores. The price of other items were estimated as very

Page 104: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

95

low costs for used goods, based on the experience of an used building materials store

owner/operator in Gainesville, Florida.

3.4. INTERVIEWS AND ANALYSIS

Various academic papers, thesis reports, case studies, industry reports and manuals available in

the fields of demolition and deconstruction were reviewed for the purpose of literature review and

discussed in the previous chapters and sections. Based on the literature review the best practices

and key lessons were compiled and presented. In order to understand the practices prevalent in

the demolition and deconstruction industry in Michigan, a limited number of interviews were

carried out and their summary is discussed below.

The purpose of the interviews was to compile and analyze the factors affecting the entire project

planning and implementation, understand the major cost factors in demolition and deconstruction

projects, difference between demolition and deconstruction, from the contractor’s point of view.

The interviews were intended to gather project specific information from the contractors on the

following aspects:

Planning for a project

Difference between demolition and deconstruction

Cost estimation or quantification process for demolition and deconstruction projects

Major cost factors

Selecting an approach

Implementation

Page 105: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

96

The first part of the interview included questions regarding the background of the contractors and

their experience and area of practice. The second part were about project planning,

implementation, cost estimation, approaches and difference between building demolition and

deconstruction.

3.4.1. Analysis and summary of the interviews

A small number of contractors working in Detroit area and Lansing were interviewed. In addition

to interview summary, some information about the views of the National Demolition Association

(NDA) are also presented, because they represent more than 1,000 US and Canadian demolition

contractors.

3.4.1.1. Background of the contractors

The interviewees were both large and small sized contracting companies mainly involved in

demolition, and the contractors have membership of the National Demolition Association (NDA).

The interview questionnaire is provided in Appendix A. The large sized contracting companies are

involved in large scale residential demolition projects and also commercial and industrial

demolition in the Detroit area. The small sized contracting companies are mainly involved in small

number of residential demolitions in Michigan. All contractors claim to be involved in salvage and

recycling of materials in demolition projects at different scales when it is economically feasible. It

should be noted that due to time limitations, none of the interviewees were a specialized

deconstruction company, and this limits the scope of the summary of industry’s definition of

demolition and deconstruction, as it based on the views of the demolition contractors only.

Page 106: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

97

3.4.1.2. Demolition vs. deconstruction

Definition of both demolition and deconstruction varied according to various contractors and

projects. Demolition was defined by contractors mainly in two different ways; the first definition

was knocking down a building, changing it into rubble and clearing the site for future use. This

definition mainly related to demolition of large number of residential structures by large

contractors. The second definition was to dismantle the structure, salvage and recycle material and

send to landfills what is left of the rubble. This definition related to projects which were

economically feasible to salvage and recycle like commercial and industrial structures.

Deconstruction was defined as being able to disassemble building components and materials and

reassemble and use it somewhere else.

Deconstruction was defined as much more time consuming and labor intensive compared to

demolition. The safety costs are higher since more labor are working inside the buildings. So in

most cases economically not feasible. If the cost of recycle is much more than disposal of the

material to landfills, the contractors mostly decide to dispose the material. The tipping fees to

landfills in Michigan are lower than many states, but the main cost components are the hauling

and moving fees.

It was also pointed out that deconstruction is more favorable in the West coast because the labor

cost is cheaper compared to East coast and mid-west and also the landfill tipping fees are higher

in the west coast, therefore the contractors there favor deconstruction over demolition.

The decisions of whether to demolish or deconstruct a building are completely based on the

economics of the project. If the building consists of high value salvageable material it is

deconstructed and stripped off of all the material and then demolished as necessary. This approach

Page 107: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

98

is highly favorable in the case of commercial and industrial structures where structural wood, steel

frames, copper wires, insulation material and other high value material are salvaged. Most of the

components are favored for reuse if appropriate, if not, then are sold as scrap as in the case of steel

which is sold for $400/Ton. In the case of basement and foundation concrete, recycling the

concrete is a more economical option than transporting to landfills. Therefore, it is mostly recycled

on site and sold to others to be used as backfill material and aggregate.

In the case of residential demolition in the Detroit area, the large contractors mostly perform

complete demolition and send the rubble to landfills. As there are less valuable material to salvage

and it takes just few hours to completely demolish a residence and move on to the next. The small

sized contractors favored skim deconstruction where they would strip off salvageable material in

the residential projects and then demolish.

3.4.1.3. Approaches to project cost estimation, planning and implementation

The contractors based their approaches on experience of the company. The first step and mostly

costly component of the project was defined as the initial survey where building material and

components are inspected thoroughly to obtain a good understanding of the project, especially in

the case of commercial and industrial structures. The estimation department estimates the project

magnitude and cost. Other major components were defined as large equipment and machinery use,

hazardous material abatement and removal, structural demolition work like basements and slabs,

etc. The larger sized contracting companies own most of the heavy equipment and machines while

the smaller contractors preferred renting them. The machines are worn out much faster than when

used on construction sites.

Page 108: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

99

While deciding the method of demolition to be used, contractors mostly depend on their experience

and gut feeling. In the case of high-rise buildings high reach boom excavators are mostly used.

But the more experienced contractor proposed a different approach of weakening the supports at

the ground floors and using the pull down method to bring the down the building quickly.

Explosive demolition though the quickest method mostly is rarely used because they are

expensive. In the case of residential structures, excavators with hauling trucks are used with a very

limited number of labor on site.

The average cost of demolition of a residential structure was defined to be around $12,000 or less

by the large contractors. The small sized contractors stated the average about $15,000. The large

contractors mostly demolish many residences in a close proximity which automatically costs less

than a small sized contractor demolishing a single or couple residences.

3.4.2. National Demolition Association (NDA)

The National Demolition Association represents more than 1,000 U.S. and Canadian companies

that offer demolition services as well as a range of demolition-related services and products. It

provides education, advocacy, and industry updates to member companies and public as well as

increasing awareness of the economic and societal benefits of the demolition. The following

information is obtained from the official website of the National Demolition Association and a

summary is presented of their view towards the demolition and deconstruction industry (NDA,

2015).

Demolition is defined as “a complex set of tasks involving structural dismantlement, site clearance,

environmental remediation, salvage, recycling, and industrial recovery. Demolition is a highly

Page 109: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

100

sophisticated craft which involves the use of hydraulic equipment with specialized attachments,

cranes, loaders, wrecking balls and in some cases explosives”.

Deconstruction is defined as “the labor-intensive demolition of a structure in order to maximize

the amount of potentially recyclable materials from the building. It often involves a considerable

amount of hand demolition and sort separation in preparation for marketing the structure’s

components”.

The difference between demolition and deconstruction is defined as “considering that conventional

demolition contractors routinely recycle up to 90% of the material generated on a typical

demolition site, there is little difference between the two methods. Demolition saves the labor-

intensive nature of deconstruction”.

In author’s opinion, these statements are misleading and do not justify the environmental, social

and possibly economic benefits of deconstruction. It was found that very few of the demolition

projects recycle up to 90% of the material because not even a full deconstruction project can

achieve such a level of material recycle. Because demolition is a more established industry with

larger profits for contractors, it is pushed and recommended mostly and therefore it is implemented

at 90% of the projects for instance at the Detroit blight removal projects. It is absolutely necessary

to increase the public awareness of the benefits of deconstruction over demolition.

3.5. COMPARISON OF DEMOLITION VS. DECONSTRUCTION

This section presents a comparison of demolition and deconstruction after the understanding

reached through the literature review as well as the industry interviews. Table 3.7 outlines a

comparison matrix of demolition and deconstruction.

Page 110: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

101

Table 3.7 Comparison between building demolition and deconstruction (EPA, 2008; EPA 2006;

Diven & Shaurette, 2010; Guy, 2003; IWMB, 2001; CCE, 2000).

Attribute Demolition Deconstruction

Definition Change a building or structure to

a pile of debris and mixed rubble,

recycle where practicable by

segregating the debris and haul

the rubble to landfills

Disassemble components and material

from a building or structure for

maximum reuse and recycle

Impacts Heavy impact on the environment

due to disposal of material to

landfills and wastage of resources

Environmentally beneficial due to

reuse of material and preserving

maximum construction material.

Avoids depletion of energy and new

material. Conservation of natural

resources.

Socially does not benefit

communities as it is more

dependent on use of heavy

machinery

Creates new employment opportunities

for unskilled work force as it is

dependent largely on labor

Quickly executed, often more

economic for contractors and

owners who want the site clear

for investment

Operationally costs more but adds the

benefits of value from salvaged

material which may result in reduced

cost

Planning Intensive machine operation

planning

Intensive labor training and working

plans

Site survey Structure, Material, Method of

construction, Adjoining

properties, Utilities, Hazardous

material, Location,

Neighborhood, Access…

Requires more intensive survey of

Structure, Material Classification for

Reuse, Recycle and Disposal,

Components and connections,

Hazardous Material, Location, Access

Safety Workers on site, Pedestrian and

vehicular safety, adjoining

properties…

Many cases performed from a

safe distance by heavy machines

Workers safety, training, equipment

safety, site…

Personnel Safety more sensitive issue as

workers engaged inside the building

mostly

Tools and

Equipment

Heavy and large machines and

tools used for quick operations

Smaller hand tools and equipment used

to carefully remove material in an

integrated condition

Page 111: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

102

Schedule Requires less time Requires more time

Labor Less labor intensive, depend on

heavy machine operations

More labor intensive operation

Material

Handling

Heavy operations by machines:

Sorting for recycle, hauling and

disposal

All material separated as deconstructed

into different categories, De-nailed,

Cleaned for reuse and sorted for

recycle

Material

Disposal

Huge amount of waste produced

which is aimed at landfills.

Hauling and tipping costs are

higher

Reduces the amount of waste by up to

75% as most material aimed for reuse

and recycle

Approaches Many approaches are based on

heavy and specialized equipment

and tools and some cases use of

explosives for quick operations.

Based on the components to be

disassembled, approaches are lobar

intensive and time consuming.

Attention is paid to the components to

preserve their structural integrity while

deconstructed.

Structures All structures can be demolished

and changed into rubble

Not all buildings are good candidates

for deconstruction

Site Security Focus on workers safety and the

general public and adjoining

structures safety

Besides workers’ safety, material

security on site is important because

salvaged material is vulnerable to theft

Asbestos

Containing

Material

If asbestos containing material

present in the building, wet

demolition can be used without

having to remove the material

with great cost

Asbestos containing material, if present

in the buildings, require huge cost and

time investment to remove

Pollution

Creates more waste during site

clearance. More noise and dust

with the use of heavy machinery

and operations

Greater protection of the local site

including soil and vegetation. Creates

less dust and noise

Future As the environmental impacts of

demolition is widely discussed,

future construction goals will be

to avoid demolition where

possible

Building practices to encourage

deconstruction and Design for

Deconstruction to be incorporated into

construction industry

Page 112: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

103

Deconstruction is an idealized method from the perspective of perfecting material reuse and

recycling, by which the building is dismantled in terms of its valuable construction elements. As

compared to Demolition which is mostly about changing a building into rubble as fast as possible

and making the site ready for its future use. While demolition is mostly quick but is not an

environmentally responsible approach. And though deconstruction may be a socially,

environmentally and sometimes economically beneficial approach for removal of buildings, not

all the buildings are good candidates to be deconstructed.

Typically, when a building reaches the end of its useful life, heavy equipment is used to demolish

the structure. All parts of the structure are rendered into rubble which is a mix of wood, masonry,

metals, and other materials. In some cases, especially with large concrete and steel buildings, raw

material may be recycled, but for most light framed residential structures, the demolition waste

ends up in landfills. Deconstruction on the other hand, is the selective dismantling or removal of

materials from a building for reuse and recycle where possible and sending the least of the material

to landfills. Wood flooring, raised panel doors and windows, ornate exterior and interior trim,

electrical and plumbing fixtures, framing and bricks can have high salvage value. The goal of

deconstruction is to encourage maximum reuse and recycle of construction material.

Deconstruction is an environmentally responsible approach to removal of structures compared to

demolition as it prevents waste from going to landfills and resource depletion (IWMB, 2001; EPA,

2006).

Though the cost of operations in deconstruction is typically more than demolition, the real cost

savings in deconstruction depend on the market value of the salvaged material (CCE, 2000). Many

deconstruction operations are run by non-profit organizations. One reason for this is that a non-

Page 113: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

104

profit deconstruction firm can factor the tax-deductible donation benefit to the client into the bid.

This is an added benefit to the non-profit approach to deconstruction.

Deconstruction uses less machinery and more labor. It requires training for crew members to be

able to safely extract salvageable material without damaging them. This provides new employment

opportunities for minimally skilled work force (IWMB, 2001). Deconstruction in almost all cases

requires significantly more time than demolition. Developers are always under financial pressure

to clear the site as quickly as possible and this is a disincentive to deconstruction compared to

demolition.

Hazardous material regulation, safety and management can be more difficult or intensive for

deconstruction than demolition. In the case of deconstruction the workers should be well aware of

the existing and temporary supports inside the buildings and should follow strict safety rules to

avoid dangerous situations because they work inside the buildings in the case of deconstruction.

But in the case of demolition workers can operate machines from a safer distance from the

structure. If deconstruction is cost-competitive with demolition, it is a clear winner: It is better for

the environment (greater reuse and recycling, cleaner cleared lots, and less disposal) and for the

local economy (more jobs and availability of lower cost building materials).

3.6. COST COMPARISON OF DEMOLITION AND DECONSTRUCTION

Deconstruction can be more cost effective than demolition when considering the reduction in

landfill disposal costs and the revenues from salvage (CCE, 2001). For deconstruction to be

economically feasible, salvage value and revenue from resale of recovered materials is very

important and comprises large part of the income. Furthermore, a greater opportunity is savings in

Page 114: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

105

transportation and disposal costs. The net income from deconstruction can be increased by

carefully salvaging more material with the least damage, so amount of waste material is reduced

while increasing reuse and recycling potential of salvaged materials.

According to Macozoma (2002), in many cases, there are problems with the storage space for

salvaged materials, and with the location of end markets to avoid additional costs for

transportation. Therefore, there is a need for investment promoting the establishment of secondary

material businesses such as used building material stores, recycling companies that divert salvaged

waste into secondary materials, and product manufacturers that use secondary feedstock.

According to the CCE (2001), based on the study of deconstruction of 6 houses in Florida, which

was mainly done to compare the costs of deconstruction to traditional demolition work, the average

estimated demolition cost using all six (6) houses, was $5.36/SF and disposal was an average of

40% of the total costs. The average “gross” deconstruction cost was $6.47/SF, which is

approximately 26% higher average cost than demolition. Disposal costs for deconstruction were

on average 15% of the total costs. Gross deconstruction is the first cost of the deconstruction which

includes all labor and disposal but does not include any salvage revenues. Asbestos and lead

surveys and remediation was an average of $0.97/SF for both demolition and deconstruction. This

is 18% of the costs for demolition and 15% of the costs for deconstruction. Avoiding this cost on

a consistent basis for small scale demolitions makes deconstruction un-competitive with

demolition. Table 3.8 below provides a cost comparison of demolition vs. deconstruction for the

same project.

Page 115: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

106

Table. 3.8 Economic summary of demolition vs. deconstruction of a one story residential building

(CCE, 2001). (This building is presented in the case study for deconstruction estimation in the

previous section).

This was a one-story house with a detached garage, the garage was approximately 500 SF of the

total 2014 SF. The house was wood raised on brick piers, the garage was a CMU wall construction

on concrete slab. This building had several additions and several layers of interior finishes, i.e. two

wood floors and two roof finishes, a metal roof laid over an asphalt roof. The interior walls were

predominantly plaster and lathe. The plaster was separated from the lathe to see if the lathe could

be recycled or used for fuel in pottery kilns.

Table 3.9 below presents another comparison of cost between demolition and deconstruction for a

typical residential structure.

Cost items Total net demolition cost Total net deconstruction

Permit $50 $50

Asbestos survey $1,200 $1,200

Asbestos abatement $740 $740

Disposal $5,873 $1,344

Toilets $63 $63

Supplies $10 $637

Labor and equipment $3,504 $8,469

Total cost $11,441 $12,504

Salvage value $0.00 $9,415

Total net cost $11,441 $3,089

Total net cost per square

foot

$5.68 per SF $1.53 per SF

Page 116: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

107

Table. 3.9 Cost comparison of demolition and deconstruction of residential structures. (Guy, et

al., 2003).

The gross cost of deconstruction per square foot of area is higher than the gross cost of demolition

as seen in the table above. The real cost saving in deconstruction is dependent on the type and

quality of salvage material that is valued based on reuse and recycle.

Some private companies have also presented a cost comparison of demolition vs. deconstruction

projects as shown below. But according to the author these costs might have been inflated for

commercial purposes. Table 3.10 below is a cost comparison of a residential structure for

demolition and deconstruction presented on the official website of the Piece by Piece, who are one

company amongst many promoting deconstruction.

Cost Element Average Demolition

Costs

Average Deconstruction

Costs

Size (SF) 1,476 1,476

Labor/Equipment ($/SF) 1.74 3.64

Testing for Asbestos & Lead ($/SF) 0.97 0.97

Disposal ($/SF) 2.17 0.97

Other Costs: permit, etc. ($/SF) 0.48 0.89

Gross Cost ($/SF) 5.36 6.47

Salvage ($/SF) 0.00 3.28

Net Cost ($/SF) 5.36 3.19

Net Cost ($/SF) 50% Salvage 5.36 4.83

Page 117: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

108

Table. 3.10 Cost comparison of a 2500 sq.ft residential structure by piece by piece deconstruction

company (http://www.piecebypiecedecon.com/costs.html, 2014).

Cost items Deconstruction Demolition

Labor cost $16,875 $10,000

Disposal cost $1,667 $6,250

Total cost $18,542 $16,250

Salvage value $7,500 $0

Tax savings $2,625 $0

Final cost $15,917 $16,250

Salvage value is based on used building materials selling for 1/3 of their new price – the industry

average. Factors such as age, condition and design obviously affects the value of salvaged

materials. Tax savings are based on an owner tax bracket of 35%.

As presented in the table above, the gross cost of deconstruction is higher than gross cost of

demolition, but the net cost of deconstruction is less than demolition. Though a salvage value of

$7500 is stated but the details of the quality and type of material being salvaged is not presented.

The marketability of salvaged material has also not been detailed out. At the current situation the

market demand for salvaged material does not support deconstruction projects viability. That is if

a complete deconstruction of the project takes place where the maximum amount of material is

being reused and recycled.

Page 118: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

109

Table. 3.11. Cost comparison of demolition vs. deconstruction of a residential structure by The

Reuse People. (http://www.thereusepeople.org/deconstruction, 2014).

Cost items TRP deconstruction Demolition

Physical lowering of house $17,238 $6,000

Disposal $4,100 $4,100

Appraisal of salvaged material $3,000 $0

Cost $24,338 $10,100

Donation value $88,000 $0

Tax savings $24,640 $0

Total costs $24,338 $1,100

After tax benefits $302 $10,100

The after tax benefits between the two methods is $10,402; not only does the tax savings

completely cover the cost of deconstruction, but the homeowner also saves $10,100 in

demolition fees.

Total salvaged material would generally appraise for $77,000 to $112,000 in good reusable

condition. Assuming a tax bracket of 28% the after tax cash value, based on a typical value of

$88,000 is $24,640.

The Reuse People is another company that promotes deconstruction in the west coast. A cost

comparison of demolition vs. deconstruction is presented on their web page. This cost comparison

shows a big difference while calculating the gross cost of deconstruction as compared to

demolition. Estimating a value of $88,000 for salvaged material is also not detailed out. No other

paper has provided such a high value of savings in salvaged material. According to the author of

this report, it is highly impossible for a typical residential structure that is to be demolished to have

a salvaged value of material for reuse to be $112,000 as stated above.

Page 119: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

110

Deconstruction can be more cost effective than demolition when considering the cost reduction in

landfill disposal costs and the revenues gained from salvaged material. On average, the operational

deconstruction costs or gross deconstruction costs are higher than demolition costs, but the net cost

of deconstruction, after considering the income that is achieved from the resale and recycle of the

salvaged material, is lower than demolition. It should be noted that the salvage value is highly

based on the type, condition and value of the salvaged material. Material should be carefully

salvaged with least damage in order to be reused.

Waste transportation and disposal costs are one of the main cost components in a demolition

project. The distance and tipping fees of the landfills considerably affect this cost component. In a

deconstruction project, maximum amount of the material is targeted for resale and recycle which

reduces the waste disposal costs in the project. On the other hand, there are problems with salvaged

material such as storage, transportation and end markets availability. These cost factors should be

considered while estimating the salvage value of material. The current situation of the market

demand for salvaged material often does not support deconstruction projects feasibility.

Asbestos and lead survey and remediation is another important cost component. In smaller

demolition projects, based on the type of hazardous material, often the hazardous material

remediation cost is avoided and the material are disposed in a manner that would not require

abatement such as, use of wet demolition approach. In this approach the debris is kept wet from

start of the demolition project till they are safely disposed to landfills. The non-friable asbestos

and lead containing material are safely disposed. But this cost cannot be avoided in the case of

deconstruction projects, therefore making it un-competitive with demolition in many cases.

Page 120: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

111

Every project is different and therefore should be studied separately in order to figure out the

economic feasibility of the project to be deconstructed or demolished. Factors such as location,

material type and condition, marketability of the material, transportation and tipping fees of

landfills and labor wages in the area should all be studied in order to economically compare a

project for demolition and deconstruction. Hence, it can be said that deconstruction can be cost

effective compared to demolition in many projects, but it cannot be true in all projects and should

be studied separately on a case by case basis.

In the author’s opinion, demolition of a typical residential structure in Michigan should cost

between $10,000 to $11,000. If the same residence is to be deconstructed, it should cost between

$13,000 to $15,000. In the author’s opinion, a typical house that is due to be demolished or

deconstructed typically would not have a very large salvageable stock of material, but it will still

contain some amount of salvage value. The typical residence deconstruction should result in a

salvage value of about $4,000 to $5,000, depending on the quality and type of material and

availability of market. If the salvaged material has a marketable quality, it could be sold at a higher

retail price, but normally it might be sold at a lower price as a whole sale. It should be noted that

a lot of the cost factors that have been discussed in the earlier sections would be specific to projects

and would affect the cost of the project.

3.7. SUMMARY

This chapter provided an overview of cost estimation of demolition and deconstruction projects,

industry view of both methods and a comparison of demolition vs. deconstruction projects. The

comparison is done for planning, cost and execution of both approaches. Extensive planning is

required for both demolition and deconstruction cost estimation. Overall deconstruction can be

Page 121: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

112

more cost effective than demolition when considering the reduction in landfill disposal costs and

the revenues from salvage (CCE, 2001).

On average, according to the study done by (CCE, 2001), deconstruction costs for residential

buildings in Florida were 26% higher than demolition costs. On average, the net cost of

deconstruction with salvage was 37% lower costs than demolition using retail salvage values and

10% lower using “wholesale” prices.

Page 122: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

113

CHAPTER 4

4.0. REMOVAL OF ABANDONED PROPERTIES IN MICHIGAN

4.1. INTRODUCTION

America’s industrial decline in many urban communities has caused population and economic loss

for years. This has resulted in large amount of properties being abandoned and left to decay. Empty

neighborhoods are becoming an increasingly daunting problem across the country and these

buildings and structures need to be removed. The practices of demolition and deconstruction are

definitely related to decisions regarding removal of these structures. This chapter provides an

overview of the private property abandonment in the United States and specifically in Michigan.

It discusses the abandonment and removal topics in light of the approaches and costs of demolition

and deconstruction discussed in earlier chapters. The current practices in place for the removal of

the abandoned properties in Michigan are also discussed.

4.2. PRIVATE PROPERTY ABANDONMENT IN THE UNITED STATES

Industrial decline in America has left behind large amount of abandoned and decaying

neighborhoods. “Many cities in the United States which used to be the hubs of industrial activities

are presently facing economic and social decline and have suffered population loss. For the last 40

years these communities have experienced residential, industrial and commercial property

abandonment. The abandonment results in blight, resulting in large number of vacant properties in

communities which set in motion social and economic decline” (LaMore & LeBlanc, 2014). This

issue is well prevalent in Michigan, where it has resulted in private property abandonment and

blight in cities such as Detroit, Flint and many others.

Page 123: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

114

Detroit once the hub of American industry has been largely abandoned and left to rust. Las Vegas

edged Detroit for the title of America’s most abandoned city. Atlanta came in third, followed by

Greensboro, N.C., and Dayton, Ohio. Cities such as Detroit and Dayton are casualties of America’s

lengthy industrial decline, whereas others, including Las Vegas and Orlando, are mostly victims

of the recent housing bust (Greenburg, 2009).

The private property abandonment and blight creates social and economic problems for

communities and individuals and adds strain on public resources. It increases unemployment,

poverty and crime in communities. This is because the neighborhood becomes dominated by

joblessness, racial segregation and isolation from private economy (LaMore & LeBlanc, 2014).

Blighted and contaminated properties also create negative economic implications for the

surrounding properties. According to Paul (2008), property values for industrial and commercial

sites within 1.5 mile radius of a brownfield site are typically 10% lower than similar properties not

located within the 1.5 mile radius. Abandoned properties are not only a public safety hazard for

the community, but they are a clear economic threat to non-abandoned properties.

According to (LaMore & LeBlanc, 2014), the current pattern of abandonment of private properties

in many communities is largely due to the current land ownership policies that allow landowners

to abandon their privately held parcels and burden the public sector with the cost of blight removal.

It is necessary to put in place policies that will put an end to this practice of property abandonment

by owners. It is certain that all the abandoned properties need to be removed and the sites need to

be restored for future use. Otherwise they turn into blight, triggering a spiral of social decline.

Based on the understanding of the policies that will lead to dismantling, removal, and restoration

of these properties, there is a need to identify most appropriate approaches for the removal of such

structures.

Page 124: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

115

The current practice of removal of abandoned buildings typically includes complete demolition of

the building, changing it into rubble and hauling the waste into landfills. Salvage of material is

also incorporated into the demolition work when economically feasible. But these methods are

creating substantial amount of waste. Hence, when the building contains large amounts of reusable

and recyclable materials it is important to incorporate deconstruction into demolition. But because

not all the buildings are good candidates for deconstruction, the economic feasibility of

deconstruction of abandoned buildings need to be justified.

4.3. REMOVAL OF ABANDONED PRIVATE PROPERTIES IN MICHIGAN

Decline of the auto industry and the economic recession has caused widespread private commercial

and residential property abandonment in Michigan for many years. According to the Center for

Automotive Research, over half of the originally constructed automotive plants within the State of

Michigan have closed, leaving only 65 still in operation (Brugeman, et al., 2011). Many of the

abandoned commercial properties have become sights for crime and vandalism.

The State of Michigan has increased the efforts to slow down the increase of blight and alleviate

the effects of abandonment. The State Senate introduced a bill that causes property owners to face

a lawsuit if they fail to act on issued blight citations (State Senate, Michigan, 2013). Local and

statewide programs have also been enacted with goals of eliminating blight. The Department of

Human Services of the State of Michigan (DHS), the Michigan State Housing Authority

(MSHDA), and the Michigan Land Bank Fast Track Authority (MLB) enacted the Blight

Elimination program in 2012 which gives communities the opportunity to apply for funding that

fund the demolition of blighted properties. The Neighborhood Stabilization Program (NSP),

administered by the Department of Housing and Urban Development (HUD), focuses on

Page 125: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

116

residential abandoned properties and helps fund communities to stabilize. A variety of taxpayer

supported programs are also created to combat commercial and industrial abandonment ranging

from brownfield redevelopment tax credits to direct investments in failing industries (LaMore &

LeBlanc, 2014).

Private property abandonment places a substantial burden on limited public resources for the

removal of blighted properties. It is estimated that the removal of an abandoned single family home

costs approximately $10,600 (Genesee County Land bank, 2014). In some cities there are hundreds

of such abandoned properties which can amount to millions in blight removal cost.

The US Treasury Department allocated $498 million to Michigan in 2010 as part of the Hardest

Hit Fund program (Gallagher, L., 2009). In July of 2012 $25 million was allocated for blight

demolition with $15 million for the city of Detroit and remaining $10 million spread across

Michigan (Eggert, 2012). In 2013 $100 million was allocated for blight elimination in Detroit,

Flint, Saginaw, Grand Rapids and Pontiac (Behnan & Hinkle, 2009). In October of 2014 a total of

$75 million is allocated to eliminate blight in Michigan and it comes from the Hardest Hit Fund

program. $50 million is allocated for Detroit, $5.5 million for Jackson, $6 million for Lansing, $5

million for Highland Park, and remaining eight communities – Inkster, Encore, Muskegon Heights,

River Rouge, Port Huron, Hamtrack, Ironwood and Adrian - will receive between $375,000 to

$2.2 million. In the summer of 2015 it is expected that as many as 240 blighted houses in Lansing

could be demolished using the $6 million federal money (Behnan & Hinkle, 2009).

Page 126: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

117

4.4. REMOVAL OF ABANDONED PROPERTIES IN DETROIT

In particular, Detroit’s problems run much deeper. An industrial boomtown during the first half of

the 20th century, Detroit’s population increased from 285,000 in 1900 to 990,000 in 1920, reaching

a peak of 1.8 million in 1950. But starting in the 1960s, Detroit began a swift decline. Detroit’s

population is now 900,000 half of what it was in the middle of the century and many of its

neighborhoods languish in varying states of decay. Most scholars blame rapid suburbanization,

outsourcing of manufacturing jobs, and federal programs they say exacerbated the situation by

creating a culture of joblessness and dependency (Greenburg, 2009).

Detroit has internationally gained the reputation of urban ruin and is fighting to get rid of the

blighted properties for many years. At last it has started to show results, as of December 2014 the

city of Detroit is demolishing about 200 vacant houses a week and the city wants to reach a goal

of demolishing about 10,000 houses in one year. Much of the demolition work is concentrated in

about 20 neighborhoods where the blight removal can have immediate positive effects (Behnan &

Hinkle, 2009).

The Land Bank Authority in Detroit has filed close to 1,200 lawsuits in 2014 against owners of

nuisance properties and so far has won consent agreements in more than 500 cases. The Land Bank

then sells these properties to neighbors living adjacent or close by the property and have to keep

the property free of nuisance (Behnan & Hinkle, 2009).

Despite the progress in removing blighted properties in Michigan. There are a lot of challenges

that daunt the projects. Shortage of trained workers, trucks, bulldozers, and even clean dirt to fill

the basements of the demolished houses are some of the challenges. The demolition contractors in

most cases have had to buy sand and other fill from quarries at increased cost and inconvenience

(Gallagher, L., 2009).

Page 127: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

118

Several important efforts have helped the city of Detroit to keep pace with the need to remove

thousands of blighted properties quickly. The Detroit Blight Removal Task Force is an important

part of the administration, which has mapped out the city’s roughly 380,000 parcels, creating the

best digital database of the conditions of properties in the city. The Detroit Land Bank Authority

is another important administrative body through which municipalities can hold, improve and sell

tax foreclosed properties. For blight removal the Land Bank Authority readies the properties for

demolition by clearing up any legal issues and hands out lists of properties to Detroit Building

Authority, which works with private contractors to remove structures (Gallagher, L., 2009).

The Detroit Blight Removal Task Force has identified 78,506 blighted structures in Detroit in the

following (DBRTF, 2014):

Residential Structures Four Units or Less (legally defined as single-family): 72,328 units

Residential Structures over Four Units (legally defined as multi-family): 707 units

Commercial Structures with lot sizes smaller than 25,000 square feet: 3,904 units

Commercial Structures with lot sizes greater than 25,000 square feet: 220 units

Industrial Structures: 339 units

4.4.1. Deconstruction in Detroit

The absence of market demand for harvested materials, the increased costs and the impact of

deconstruction on schedules are presented as challenges in the Detroit city blight removal projects

(DBRTF, 2014). The Task Force has selected residential structures of four units or less as the best

deconstruction candidates in Detroit. The current resale and wholesale distribution market can

support deconstruction of only about 10 percent of Detroit’s present inventory of blighted

Page 128: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

119

structures in this category. That means that, under today’s conditions, about 7,000 buildings can

be cost- effectively deconstructed and recycled. The Task Force recommends starting with the

“skim” model of deconstruction, where the property is appropriate and a market exists. This would

result in an estimated 30- 35 new jobs in deconstruction and salvaging (DBRTF, 2014).

4.4.2. Demolition in Detroit

Mechanical demolition will likely address 90 percent of all removals necessary in Detroit.

Mechanical demolition typically includes a three-person crew and can occur in as little as three

hours once it has begun. The recommended approach for demolition of structures in Detroit is

wet/wet demolition. A “wet/wet” demolition is wetting down as much of the demolition site as

possible at all times, including the bucket and the debris pile and wetting down the load on the

truck as it‘s being hauled to the landfill (load stays wet the entire time). A typical candidate for

mechanical demolition is a structure with one or more of the following characteristics (DBRTF,

2014):

The structure is on the city’s emergency demolition list and has to come down immediately;

Structures that require significant asbestos abatement solutions which are typically too

cost-prohibitive to be good rehabilitation or deconstruction candidates;

The structure is in a defined geographic area with high levels of vacancy and blight, where

there is an opportunity to demolish at some level of scale;

The structure has fallen into a particular level of decay due to neglect, the elements, or a

previous fire, and there is little or no salvage value remaining.

Page 129: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

120

4.4.3 Recycling Detroit’s demolition waste

The landfills in Michigan are located at the southeast, which are generally about 30 miles from

Detroit city. Though the landfills have more capacity than required for the blight removal waste

from the city of Detroit, it also has low prices which even invites landfill from Canada. The goal

of city is to divert waste from landfills where possible (DBA, 2014).

The largest single cost factor for demolition in Detroit is the cost of trucking debris from the city

to these landfill locations. If recycling centers are provided within city limits, it would reduce the

average demolition cost dramatically, considering the offset from recycling versus the hauling,

fuel, tipping fees and limited hours of operation at the landfill. Recycling centers within the city

of Detroit would also keep revenue from this project in the city, creating jobs for Detroiters. A

recycling materials market must exist for recycling centers to make the investment in Detroit.

Funding sources for deconstruction and demolition must be defined to support the need for

recycling centers as well as contractor growth. The potential cost savings of two recycling centers

within city limits is approximately 10 percent of total demolition cost per structure. If the average

cost of demolition, including any deconstruction, is $10,000, this could save at least $1,000 per

demolition project. Assuming approximately 72,000 structural demolition candidates, this could

result in a cost savings of up to $72 million. Locating two recycling centers within the city would

cut the average trucking distance by one-half for demolition contractors. Contractors could also

pay lower tipping fees through large-scale, pre- negotiated contracts with the Detroit Land Bank

Authority. In addition, an anticipated 120 new jobs are possible through the creation of two

recycling centers (DBRTF, 2014).

Page 130: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

121

4.4.4. Recommended demolition process by Detroit Blight Removal Task Force

The Detroit Blight Removal Task Force has provided recommendations along with concerned

authorities in order to insure efficiency in the blight removal process from start to end. The Task

Force recommends that Detroit Land Bank Authority should ask demolition and deconstruction

companies to submit combined Request For Proposal (RFP) where deconstruction is viable. This

is to ensure increased coordination and decrease the hand-off time from deconstruction to

demolition. It is also recommended that the RFPs are based on the size of the job and size of

contractors. This method allows large contractors to secure large jobs, because the smaller

contractors do not have sufficient finances to handle larger demolition projects. The city always

gives priorities to Detroit based contractors. If firms outside of Detroit are needed to achieve

targeted volumes they should be required to hire qualified Detroit residents to perform the work

(DBRTF, 2014). The following illustrates the recommended demolition clearance process by

Detroit Blight Removal Task Force.

BEGIN NOTIFICATION PROCESS

Two weeks prior to

demolition,

notification of

demolition activity

posted on designated

properties by

DLBA/DBA

DLBA/DBA to notify

by mail all residents

near properties

designated for

demolition

Door to door

community

notification of

demolition activity by

DLBA/DBA

BEGIN UTILITY DISCONNECTION PROCESS

Page 131: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

122

BEGIN ASBISTOS ABATEMENT

DLBA issues RFP to

qualified Asbestos

Abatement

Contractors for

competitive bid

Contractor is

selected and

awarded work

by DBA on

behalf of

DLBA

Asbestos is abated

with 3rd party air

quality monitoring

firm

Contractor selected through

RFP process by DBA on

behalf of DLBA (Joint venture

between deconstruction and

demo contractors if

deconstruction candidate)

Contractor

obtains

Demolition/De

construction

Permit

If property is a

candidate for

deconstruction

the contractor

begins the

deconstruction

process

BEGIN DEMOLITION PROCESS

Contractor

uses wet/wet

demolition

method

Wood, debris

and basement/

footings are

removed by

contractor

Open Hole

inspection is

performed by

City

Clean soil is

delivered to backfill

the site; contractor

provides clean soil

certification

BEGIN PRE-DEMOLITION PROCESS

Page 132: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

123

Contractor

backfills,

compresses and

grades the fill

Lot is seeded

with low

growth grass

seed or clover

where

appropriate

Winter or

Final grade

inspection is

performed by

City

Waste is

maintained wet

up to and

during

transportation

Waste is transported

to the appropriate type

of landfill

Contractor transports

waste to recycling

center if recycling is

required

Non-recyclable

material is transported

to the appropriate type

of landfill

BEGIN CLOSEOUT PROCESS

Demolition permit

is closed out by

City and

Contractor submits

an invoice

DBA inspects

contractor’s

work and takes

photographs

Contractor is

paid by DLBA

Collect

community input

after demolition

is complete and

lot is maintained

Figure 4.1 Recommended building demolition process in Detroit (DBRTF, 2014)

Page 133: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

124

4.5. SUMMARY

This chapter reviewed the property abandonment issues related to various communities in the

United States and in particular Michigan. Due to the industrial decline in many communities in the

United States, there are a large number of abandoned buildings that are left to decay and the state

governments are responsible for removal of such blighted properties.

In the case of Michigan, even though large amounts of funds are dedicated currently for blight

removal and contractors are demolishing hundreds of buildings per week, deconstruction has been

implemented on a very small scale. This is creating large amounts of waste that are going to

landfills and are depriving the people of Michigan of potential job opportunities, environmental

benefits and efficient use of construction material.

Page 134: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

125

CHAPTER 5

5.0. SUMMARY, CONCLUSIONS AND AREAS OF FUTURE RESEARCH

5.1. INTRODUCTION

This research discussed demolition, deconstruction and design for deconstruction based on the

available literature and the existing industry practices. Costs associated with demolition and

deconstruction projects were discussed and compared. A comparison of demolition and

deconstruction was presented. Finally, removal of abandoned properties in urban areas of

Michigan were discussed. This chapter presents a summary, observation and conclusion of the

research based on the objectives that were initially identified. Finally, potential future areas of

research are presented.

5.2. RESEARCH LIMITATIONS

The research had some limitations and in the author’s opinion the following two were the main

limitations in this research:

1. Few interviews conducted: the research was primarily limited by the very few number of

interviews that were conducted with professionals in the industry. Especially in the case of

deconstruction, no specialized firm or contractor was interviewed. An increased number of

interviews with both demolition and deconstruction professionals would have provided a

more detailed understanding of the practices in the industry.

2. Cost recommendations are driven from case studies only: all the data and recommendations

provided for the cost of demolition and deconstruction are driven from case studies only.

Page 135: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

126

Site visits, contractor’s cost database details and in-depth study of the cost on the field

would have provided a more detailed and up to date cost recommendations for the study.

5.3. SUMMARY, OBSERVATIONS AND RECOMMENDATIONS

The goal of this research was to investigate and compile analysis regarding the various approaches

in demolition and deconstruction of buildings and the associated costs. Following is a discussion

of the work done under the objectives of the research:

5.3.1. Understand various approaches for demolition, deconstruction and design for

deconstruction

Various academic papers, thesis reports, case studies, industry reports and manuals available in

these fields were studied and the best practices and key lessons are compiled and analyzed. Steps

required for planning and implementation of demolition, deconstruction and design for

deconstruction projects were discussed. Further, the various approaches used for demolition and

deconstruction and equipment needed to carry out the projects were reviewed.

It is established that demolition using heavy equipment is the traditional process for building

removal. Modern demolition equipment removes structures quickly, destroying the materials

within and creating solid waste destined for landfills. Environmental impacts from demolition

activities are sizeable, both upstream and downstream. On the other hand, deconstruction can work

to offset the environmental impacts of the building related waste. Deconstruction not only diverts

wastes from landfills, it also reduces greenhouse gas emissions by reducing the need to extract and

ship new materials and also gives rise to a new industry of skilled jobs. In order to transform the

industry, demolition should incorporate successful aspects of deconstruction, and future

Page 136: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

127

construction should incorporate design for deconstruction for maximum use of low cost

construction material.

5.3.2. Understand costs associated with various approaches and possible quantification

process for demolition and deconstruction

Various academic papers, thesis reports, case studies, industry reports and manuals available in

the fields were studied and the best practices and key lessons were identified for approaches used

in cost estimation of demolition and deconstruction projects. All the pre-estimation tasks that are

necessary for gathering information and planning for the project were introduced with their impact

on the cost. A breakdown of the major cost components of a demolition and deconstruction projects

were presented through case studies. A limited number of interviews with contractors were also

conducted and a summary and analysis was presented. The interviews provided information

regarding the planning, estimation and implementation of the demolition and deconstruction

projects from the contractors’ point of view.

It is established that, overall deconstruction can be more cost effective than demolition when

considering the reduction in landfill disposal costs and the revenues from salvaged material. On

average, deconstruction costs are higher than demolition costs, but the net cost of deconstruction

with salvage is lower than demolition using retail salvage values or wholesale prices for the

salvaged material.

5.3.3. Develop a comparison matrix for demolition and deconstruction

Based on the lessons learned and information gained from the literature review, industry review

and interviews, a comparison matrix for demolition and deconstruction was presented. The

Page 137: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

128

comparison matrix mostly compared the requirements for planning and implementation of both

approaches. A cost comparison of demolition and deconstruction was also presented through

literature review and case studies.

Demolition is heavily mechanized operation with quick and sometimes economic solutions to

removal of buildings, but deconstruction is dependent on labor and small hand tools to operate.

Therefore, deconstruction is more time consuming, requires more stringent workers safety

measures and requires extensive site planning.

5.3.4. Identify approaches suitable for removal of abandoned properties in Michigan

Decline of the auto industry and the economic recession has caused widespread private commercial

and residential property abandonment in Michigan for many years. Available literature in the field

was reviewed, information of the current status of blight removal in Michigan was studied based

on the information available in state journals and government websites. In particular, the case of

Detroit was studied. Detroit has internationally gained the reputation of urban ruin and is fighting

to get rid of the blighted properties for many years. As of December 2014, the city of Detroit is

demolishing about 200 vacant houses a week and the city wants to reach a goal of demolishing

about 10,000 houses in one year. The absence of market demand for harvested materials, the

increased costs and the impact of deconstruction on schedules are presented as challenges in the

Detroit city blight removal projects. As a result, only 10% of the blighted structures in Detroit are

deconstructed presently and the rest are all demolished. Especially, in the case of residential

structures, the whole buildings are changed into rubble and sent to landfills. The basis of selection

of only 10% of the buildings for deconstruction are not very clear and justified in the case of

Detroit. It is absolutely necessary that the economic feasibility, environmental and social benefits

Page 138: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

129

of deconstruction in the case of Michigan are studied and analyzed. It is also recommended to

study the marketability of the salvaged material in Detroit at different levels, so that deconstruction

is more profitable to contractors.

For deconstruction to be more practicable and profitable for contractors, it is important that

incentives are provided for deconstruction process. Policies need to be put in place that give

deconstruction an edge over demolition. Increasing landfill tipping fees, and using volume-based

fees may be more important to encourage deconstruction. Enforcement of hazardous materials

regulations for asbestos surveying and handling will insure that small scale demolition projects do

not receive an economic advantage based upon avoiding hazardous materials management costs.

Permitting should be created for “deconstruction permits” that allows time for deconstruction with

a reduced time delay overall than would be allowed for a demolition permit. Permit fees for

deconstruction should be waived and demolition fees should be based not on the value of the work

or other arbitrary factors such as number of stories, but on the projected volume of wastes.

5.4. AREAS OF FUTURE RESEARCH

Demolition, deconstruction and design for deconstruction are major parts of the construction

industry and will continue to grow. These are complex business and require extensive planning,

and technical and managerial skills to be successfully implemented. There is a scope for further

research in these fields. Some of the important topics on which research can be done in future are

enlisted below.

1. Marketability of salvaged material: one of the main challenges facing deconstruction is the

absence of market demand for harvested material. The extra costs of handling, storing and

Page 139: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

130

transporting the harvested material reduces the cost competitiveness of reuse and recycle.

Hence, research can be based on supply chain management of harvested material from

deconstruction process.

2. Policies and incentives: State policies can highly be effective in promoting deconstruction

over demolition. Research can be based on studying policy changes at a State or Federal

level to encourage deconstruction and make it more profitable for contractors and owners.

This can be specifically studied in the case of Michigan, because demolition of blighted

structures is being implemented at a very high level and incentives that can promote

deconstruction need to be studied specifically in blight removal projects.

3. Incorporation of maximum deconstruction in demolition: Techniques, approaches and

policies that can insure maximum reuse and recycle of construction material from

demolition projects can be studied. Research can be conducted to study maximum

incorporation of deconstruction into demolition, which may have the potential benefits of

reduced schedules of demolition and environmental benefits of deconstruction.

This research provides information regarding technical, management and cost issues related to

demolition and deconstruction projects. It includes modern practices, various approaches, factors

affecting decisions, equipment and resources needed, recycling and reuse of materials, regulatory

requirements, and cost estimation process for demolition and deconstruction. The comparative

study of demolition and deconstruction provides a guide to choose the most suitable approach for

removal of an existing structure.

Page 140: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

131

REFERENCES

Brugeman, S., et al. (2011). “Repurposing Former Automotive Manufacturing”

<http://www.racertrust.org/files/CAR-Final-121211.pdf> (January, 20, 2015).

Buildings Department of Hong Kong. (2004). “Code of practice for demolition projects”,

<http://www.bd.gov.hk/english/documents/code/Demolition_e2004.pdf> (June, 1, 2014).

Brook AB, (2000). “Demolition with Brook”, <

http://www.anzeve.com/data/demolition_handbook_en.pdf>, (August, 15, 2014).

Behnan & Hinkley. (December, 14, 2009), Lansing gets $6M to fight blight woes “Lansing State

Journal” p.8A.

California Environmental Protection Agency, Integrated Waste Management Board (IWMB)

(2001). “Deconstruction training manual”.

<http://www.calrecycle.ca.gov/Publications/Documents/ConDemo%5C43301027.pdf > (

June, 10, 2014).

Diven, R., Taylor, M., (2006), “Demolition planning”, American Institute of Architects,

<http://www.aia.org/aiaucmp/groups/aia/documents/pdf/aiab089227.pdf > (May, 25,

2014).

Diven, R., Shaurette, M. (2010). “Demolition practices, technology and management”, Purdue

University press in association with National Demolition Association, West Lafayette,

Indiana.

Detroit Blight Removal Task Force (DBRTF). (2014), “What is the best way to remove blight”, <

http://report.timetoendblight.org/remove/ >, (February, 2, 2015).

Detroit Land Bank Authority (DLBA). (2014), < http://www.buildingdetroit.org/our-

programs/hardest-hit-funddemolition/>, (January, 15, 2015).

Eggert, D., (2012), “Michigan Legislature OKs plan to spend $97M from national foreclosure

settlement”,<http://www.mlive.com/news/index.ssf/2012/07/legislature_oks_plan_to_spe

nd.html#incart_river_default>, (December, 25, 2014).

Page 141: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

132

Endicott, B., et al. (2005). “Research on building deconstruction”, University of California,

<http://www.thereusepeople.org/sites/thereusepeople.org/files/images/Case_Studies/Dec

onstruction_Research_Paper-UCBerkeley-051305.pdf>, (June, 5, 2014).

Guy, B., et al. (2003). “A Guide to Deconstruction”, Deconstruction institute,

<http://www.deconstructioninstitute.com/files/learn_center/45762865_guidebook.pdf >

(May, 20, 2014).

Guy, B., et al. (2003). “Design for Deconstruction, Material reuse and constructability”,

USGBC, < http://www.usgbc.org/Docs/Archive/MediaArchive/204_Pulaski_PA466.pdf

> (May, 15, 2014).

Guy, B. (2003). “Green Demolition Certification”,

<http://www.deconstructioninstitute.com/files/learn_center/74145578_GreenDemoCert0

9-16.pdf>, (May, 25, 2014).

Guy, B. (CCE), (2001). “Building deconstruction: reuse and recycling of building materials”, <

http://www.lifecyclebuilding.org/docs/Six%20House%20Building%20Deconstruction.pd

f>, (June, 15, 2104).

Genesee County Land bank (2014), “The costs of demolition”, <

http://www.thelandbank.org/downloads/demo_costs_revised_with_graphic_final.pdf >,

(July, 20, 2014).

Greenburg, Z. (2009), “America’s emptiest cities”, <http://www.forbes.com/2009/02/12/cities-

ten-top-lifestyle-real-estate_0212_cities.html>, (January, 30, 2015).

Gallagher, L. (December, 14, 2009), Detroit revs up its campaign against blight “Lansing State

Journal” p.5A.

LaMore, R. and LeBlanc, M. (March, 2014), “Planning Policies and Regulations that can reduce

the Practice of Private Property Abandonment in the United States, The case for

Michigan”.

Michigan Department of Human Services, (2012). “Blight Elimination Program”, <

http://www.michigan.gov/dhs/0,4562,7-124-5453_7124_31804_62593-21285904--

,00.html>, (March, 02, 2015).

Page 142: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

133

Michigan Land Bank Fast Track Authority (MLBFTA), (2013). “Michigan Land Bank Fast Track

Authority”. <http://www.mcgi.state.mi.us/mlbfta/QueryResults.aspx>, (December, 25,

2014).

Macozoma, D.S., (2002). “Understanding the Concept of Flexibility in Design for

Deconstruction”. CIB Publications

Paul, E., (2008), “The Environmental and Economic Impacts of Brownfield Redevelopment, s.l.:

Northeast-Midwest Institute”.

<http://www.nemw.org/images/stories/documents/EnvironEconImpactsBFRedev.pdf>,

(January, 15, 2015).

RSMeans building construction cost data, (2014), 72 annual edition, The Gordian group,

RSMeans, Norwell, Massachusetts.

State Senate, Michigan, (2013). “Senate bill 0035”.

<http://legislature.mi.gov/(S(ij4oyn55yhwug155qagyt5jv))/mileg.aspx?page=getobject&

objectname=2013-SB-0035&query=on>, (February, 05, 2015).

Tara, S. (2007). “Integrating deconstruction and recycling into demolition process in Buffalo,

NY”, <http://www.ppgbuffalo.org/wp-content/uploads/2011/08/deconstruction.pdf>

(June, 1, 2014).

US Department of Housing and Urban Development, NAHB Research center, Inc. (2000), “A

guide to deconstruction”. < http://www.huduser.org/publications/pdf/decon.pdf > ( June,

05, 2010).

US Environmental Protection Agency (EPA). (2004), “RCRA in focus”. <http://

http://www.epa.gov/osw/inforesources/pubs/infocus/rif-cd.pdf >, (June, 15, 2014).

US Environmental Protection Agency (EPA). (2008), “Lifecycle Construction Resource Guide”.

<http://www.lifecyclebuilding.org/docs/Lifecycle%20Construction%20Resource%20Gui

de.pdf >, (June, 27, 2014).

US Environmental Protection Agency and Chartwell School (EPA). (2006), “Design for

Deconstruction”, < http://www.lifecyclebuilding.org/docs/DFD.pdf>, (June, 01, 2014).

Page 143: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

134

Webster et al., (2005), “Designing structural systems for Deconstruction”,

<http://www.lifecyclebuilding.org/docs/Designing%20Structural%20Systems%20for%2

0Deconstruction.pdf>, (June, 15, 2014).

Websites

Buildingjournal.com (2014), “building construction and demolition estimating online database”

<http://buildingjournal.com/commercial-construction-estimating-demolition.html>,

(August, 2014).

National Demolition Association (NDA), (2015), “Demolition F.A.Q”,

<http://www.demolitionassociation.com/demolition-faq>, (March, 10, 2015).

Piece by piece deconstruction, (2014), “Demolition vs. deconstruction- a cost comparison”,

<http://www.piecebypiecedecon.com/costs.html>, (August, 20, 2014).

The Reuse People of America, (2014), “Comparison between deconstruction and demolition”,

<http://www.thereusepeople.org/deconstruction>, (August, 20, 2014).

Page 144: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

135

APPENDIX A

SURVEY OF CONTRACTORS

What to produce

The objective of this survey is to understand the practices and associated costs prevalent in the

demolition and deconstruction industry in Michigan. Following is the information I need to

produce from this survey:

Major factors that affect the planning and implementation of demolition and

deconstruction projects from contractors’ point of view.

A range of costs for demolition and deconstruction projects.

Cost comparison matrix for demolition and deconstruction projects.

What information is needed

Based on the above mentioned objectives or information that needs to be produced, the survey

intends to gather information on the practical aspects of demolition and deconstruction from

contractor’s point of view. In order to achieve the above mentioned objectives the survey should

be able to gather project specific information from the contractors on the following aspects:

Information regarding the contractor

Planning for a project

Cost estimation or quantification process for demolition and deconstruction projects.

Major cost factors in demolition and deconstruction projects.

Selecting an approach

Implementation

Page 145: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

136

In order to gather the information needed, I have considered two typical buildings for demolition

and deconstruction. One is a two story single family residence of about 2500 square foot area.

Another is a multifamily residential building of five story. Each case will be considered separately

for demolition and deconstruction. Cost estimations will be provided based on the cost items with

a cost range for different scenarios.

1. Single family residence:

According to the National Home Builders Association an average home size in the United

States is about 2700 sq.ft. or less. I have chosen 2500 square feet area of the house with two

floors and a basement. The construction is considered typical wood frame structure with

gabled roof.

2. Multifamily apartment building:

A 5 story multi-family residential structure. The foot print of the building is 100x50 ft. The

building has a complete basement also. Total build-up area of the structure is about 30,000

sq.ft. The construction includes steel construction for the first 3 floors and two floors above

maybe of wood frame structure. The site is located at a down-town area surrounded by other

buildings.

What questions to ask:

The first part of the survey will include questions regarding the background of the contractor,

years of experience and area of specialty, etc. The contractor will be provided with questions

Page 146: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

137

based on two cases and will be asked to provide information regarding the planning and

implementation of demolition or deconstruction of the buildings. The questions will include the

following aspects:

Planning for the project

Equipment and personnel needed

Approach

Cost components

Cost estimation

Page 147: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

138

I. BACKGROUND OF THE COMPANY/CONTRACTOR

1. Which of the following building disassembly businesses does your firm engage in?

a. Demolition

b. Deconstruction

c. Demolition and deconstruction

d. Salvage

e. Other……………..

2. What role do you play in the firm?

a. Owner

b. Construction/Project Manager

c. Estimator

d. Other…………………….

3. What state or geographic region do you mainly operate in?

4. How many demolition/deconstruction projects have you worked on and over how many

years?

a. Demolition projects…………………………..

b. Deconstruction projects………………………

Page 148: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

139

II. BUILDING DEMOLITION/DECONSTRUCTION COST SPECIFIC QUESTIONS

1. What are the initial steps you take before deciding on a particular approach and

estimation for a project?

2. Based on which main factors do you decide whether to demolish a structure or deconstruct

it, if you were given option?

3. What in your opinion are the significant differences between deconstruction and

demolition of buildings?

4. What is the cost estimation process you go through once you have settled on an approach?

Page 149: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

140

5. What would you consider the main components of a building demolition/deconstruction

project for estimating the cost of the project?

a. Survey

b. Hazardous Material Abatement

c. Permit

d. Engineering Survey

e. Labor

f. Equipment

g. Overhead and Profit

h. Disposal Cost

i. Transport Cost

j. Others……………………………….

6. What are the overall cost range for different type of structures?

. Single family house . Multi-family

. Mid-rise office building . Industrial building

. High-rise building

Page 150: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

141

III. TYPICAL BUILDING SCENARIO

1. TWO STORY RESIDENCE, 2500 SQ.FT. DEMOLTION/DECONSTRUCTION

1) What will be your approach for this project?

2) How long will it take to execute the project?

3) Cost

MAJOR COST

COMPONENTS

COST RANGE COMMENTS

Page 151: Approaches and Associated Costs of Building Demolition and Deconstructiondomicology.msu.edu/Upload/Approaches-and-Associated... · 2016. 11. 3. · CONTENTS CHAPTER 1 ... deconstruction

142

2. FIVE STORY MULTI-FAMILY APARTMENT BUILDING, 100x40 FT. PER FLOOR,

TOTAL AREA OF 20,000 SQ.FT.

1) What will be your approach for this project?

2) How long will it take to execute the project?

3) Cost

ANY OTHER COMMENTS:

MAJOR COST

COMPONENTS

COST RANGE COMMENTS