Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.1

Reactors & Services

Jean-Paul Bombail

AREVA NP IBOF

IAEA Vienna October 2015

Outage performanceSupport by OEM andService providers

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.3

AREVA Our expertise

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.4

AREVA Installed Base Business Division

Reactors in operationDelivering services, solutions and products formaintenance, modernization and lifetimeextension

New buildsSupplying equipment and commissioning

Servicing 250+ all designs reactors worldwide

Scope of Work

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.5

Global presence and local delivery

Around 4,600 professionals in 9 countries on more than 20* sites

*major sites only

South Africa

Canada

USA

Brazil

China

Angra

Cape Town

Benicia/CASan Jose/CA

Forth Worth/TX

ParisLyon

RungisVal de Reuil

Chalon-sur-SaôneSully-sur-Loire

Cadarache

ErlangenOffenbachKarlstein

HelsingborgKarlskrona

GermanyFrance

Sweden

SpainBeijing

Shanghai

Shenzhen

ZaragozaTarragona

Toronto

Global Expertise for Local CustomersInstalled Base Locations

Cranberry Township, PALynchburg/VACharlotte/ NC

Marlborough/CTAlpharetta/GA

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.6

Safety Quality

CostOn timedelivery

Operationnal excellence

Maintenance and outage projects / tasks

Our fundamentals

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.7

Outage Optimization vs. Outage Shortening

Utility Goal: safe, reliable and cost effective plant operation.

PRINCIPLES:

Duration is not the sole measure of outage success

Outage work must be performed safely from all perspectives: Nuclear, Industrial,and Radiological

Scope selection must focus on improving plant material condition to improvereliability

All approved outage work must be completed

Work must be done cost effectively

Post-outage plant reliability is a key measure of outage success

Outage Lessons Learned must be effectively implemented to achieve continuousimprovement

Maintenance and Outage environment

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.8

OEM and Service providersupport to Utilities

OEM and service providers can support the utilities by performingmaintenance activities:

With dedicated trained and qualified manpower

By using specific and adapted tools (and identified spare parts)

With the relevant working documentation

Optimized tasks and pre-defined schedule in a outage maintenance window

All the activities are managed through a Quality HealthSafety and Environmental (QHSE) Manual which describesall the requirements and processes to be applied to insurethe compliance of the supplied products and services

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.9

OEM and Service providersupport to Utilities

Trained and qualified manpower:

Professional (field of competencies)

Nuclear industry specificities

• Industrial safety and Radioprotection

• Nuclear Safety

• Quality assurance and traceability

• Transparency, curiosity

Specific certification and qualification

• NDE

• Welding

• QC

• ….

Specific training

• Specialized maintenance activities

Aditionnal requirement:

• Human performance toolbox (pre job, 3 way communication, …)

• Outage knowledge: 30’ rule, critical path,….

OEM service provider/OEM manpower is usually involved in many outages worldwide which

increase their own experience and offer to Utilities some feedback or goodpractices

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.10

OEM and Service providersupport to Utilities

Using specific and adapted tools:

Limited risks for the operator (industrial safety: weight, electrization free,ergonomics,…) and dose exposure reduction.

Easy transportation and rigging

Easy decontamination

Foreign object policy considered in the design

Efficient (potential impact on the outage critical path)

Using the right spare part:

Secured by the quality assurance process and the relevant certificates

Physically checked prior to the work

Knowledge of the systems and equipments by the OEM

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.11

OEM and Service providersupport to Utilities

Working documentation

Procedure adherence during the work performance

Traceability fo the safety related equipment

Non conformance treatment if any

Technical support (HO) to the site operator

« I do what it is written and I write what I have done »

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.12

OEM and Service providersupport to Utilities

Optimized tasks and pre-defined schedule in a outage maintenancewindow

The maintenance task performed by the OEM or the service provider has to betotally integrated in the utility Outage Process:

• In accordance with the Outage preparation milestones:

- Planning

- Resource levelling

- Working file issuance

- Work permit and specific authorizations

- Logistis needs (rigging,scafolding,thermal insulation removal, standard tools,…)

- Post maintenance testing and requalification has to be considered

- Lessons learned integration

- Kick off meeting

- Prerequisite meeting

The lessons learned and wash up sessions have to be organized after the workperformance or included in the post outage milestones

Deep Implication of OEM and contractors in the outage preparation

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.13

AREVA Outage Optimization support

The first principle: Outage optimization has to be owned by the Utility, our mission

is to support the utility in achieving outage excellence

AREVA is organized to provide extensive support to utilities with its worldwide

experience and capabilities:

AREVA is involved with many utilities in outage optimization processes giving us a unique opportunity togather best practices.

AREVA has in place a multiregional team and hired utility Outage Management experts to compliment ourcore competencies.

Every plant is different and we work with you to address your specific needs

We understand that Quality, Safety, Production and Costs must be driven

simultaneously.

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.14

D: Modification and upgradingC: System Engineering

improvement

A: Outage management

support / Soft skills

B: Specific Task Improvements

Outage performance & tooling

AREVA Support

AREVA

Experience

and

support

AREVA

Experience

and

support

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.15

AREVA Outage Optimization support

Four Areas of Outage Optimization

A - Outage management programs - soft skills

Management issues such as planning scheduling, communications, ownership, scope control, task

management.

B - Specific task improvements - outage execution and tooling

Innovations for work on or near the critical path that typically been the domain of the service supplier tobring advanced tooling, robotics, skilled personnel to perform specific tasks:

C - Engineering improvements

Innovations applied to shorten outages windows or eliminate outage tasks such as TechnicalSpecification (license) changes, water management plans, reliability centered maintenance, maintenanceprograms

D - Modifications to plant systems, structure or components

Typically involve critical or near critical path equipment

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.16

AREVA outage optimization support

Soft skills (A)

Specific task improvements

and tooling (B)

System Engineering (C)

Mods (D)

Days

Saved

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.17

AREVA Outage optimization support

A - Outage management support - soft skills

All items that are human behavior driven but are present in everysuccessful outage organization in the world such as planning scheduling,communications, ownership, scope control, task management.

Practical examples:

• Area coordinators

• Re-qualification coordinators

• Detailed schedule on intranet

• Replace versus repair philosophy

• Single point of accountability

• High Impact Team (HIT)

• Pre Outage milestones adherence

• On line maintenance increase

• ….

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.18

AREVA Outage optimization support

B - Specific task improvements - outage performance and tooling

Typical areas that have always been the domain of service supplier tobring advanced tooling, robotics, skilled personnel to perform outagespecific tasks :

Typical examples:

• Integrated services package such asrefueling, S.G., valve and pumps, RCPs,…

• SG inspection: remote data analysis

• R V threaded hole inspection cleaningautomatic and remote controlled tools

• Reactor vessel threaded hole plug

• RV inspection tool

• ….

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.19

AREVA Outage optimization support

C - System Engineering

Engineered changes to the PlantsTechnical Specifications, programsand procedures

Examples:

• Reliability focused maintenancepractices

• Increased on line maintenance

• Periodical tests optimization (periodicity,criteria,required plant status, ....)

• Faster cooldown rates

• Water management plans

• Chemistry licence changes

• Corrosion prevention: Film FormingAmine

• ….

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.20

AREVA Outage optimization support

D - Major modification to plant systems,

structure or components

Typical examples:

• Refueling equipment (containment, transfer andfuel building) revamping.

• Integrated Head Assembly (I.H.A.)

• Thermocouple column quick connector.

• Humid dummy head

• Additional Emergency Diesel Generators

• Equipment Monitoring systems

• Purification flowrate increase

• …..

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.21

Major modification to plant systems

Safety Post-Fukushima

NPP Life Extension and Long-Term Operation

NPP Cost of Operation and Doses ReductionDeploying solutions for Utilities CAPEX and OPEX optimization

also addressing new Flexible Operation approach in NorthAmerica

2011

2013

2015

Confidential AREVAReactors & Services

IAEA – VIENNA 2015– J.P. BOMBAIL - p.22

Conclusion

Outage performance: support by OEM and Service provider

Engineering support (OEM)

On site support

• Technical support

• On site maintenance, inspection, requalification tasks

• Plant modification work performance

• I§C revamping

• Engineering justification (if possible)

Increased support and efficiency if the OEM is deeply involvedin the preparation phase and close up phase (lesson learned)