areview of bot for developing project

155

Upload: arman1496

Post on 12-Dec-2015

19 views

Category:

Documents


2 download

DESCRIPTION

BOT Concept

TRANSCRIPT

Page 1: Areview of BOT for Developing Project
Page 2: Areview of BOT for Developing Project

Copyright 2010Philippine Institute for Development Studies

Printed in the Philippines. All rights reserved.

The views expressed in this paper are those of the author and do notnecessarily reflect the views of any individual or organization. Please donot quote without permission from the author or PIDS.

Please address all inquiries to:

Philippine Institute for Development StudiesNEDA sa Makati Building, 106 Amorsolo StreetLegaspi Village, 1229 Makati City, PhilippinesTel: (63-2) 893-5705 / 894-2584Fax: (63-2) 893-9589 / 894-2584E-mail: [email protected]: http://www.pids.gov.ph

ISBN 978-971-564-058-9RP 06-10-600

Copyeditor: Joel C. LozareProduction coordinator: Ma. Aileen A. GarciaLayout: Jane C. AlcantaraCover design: Ma. Gizelle G. ManuelPrinting: Bencel Z Press

Page 3: Areview of BOT for Developing Project

Table of Contents

List of Tables, Figures, and Boxes vi

Foreword ix

Preface xi

1 Introduction 1

2 An Overview of Infrastructure in the Philippines 17Overall situation 17Subsectoral dimension 26Subnational dimension 57Comparison with other countries 65

3 The Build-operate-transfer Approach for Infrastructure 71ProvisionEconomics of BOT and anatomy of BOT contracts 72Description of a typical BOT project 78Major participants in the BOT process 79

4 Some Key Lessons from the Philippine Experience 83Overview of the BOT Law and proposed amendment 83to the LawStages in the BOT process: the project cycle 92Goals and typical contractual agreements of the major 111participantsRisk in BOT projects 117Risk mitigation instruments 119Institutional framework 122Contracts and regulation 124Third party evaluation of projects 124

5 Conclusion and Policy Recommendations 125

Annex A. A Proposal for an Amended BOT Law 129

References 143

The Author 149

Page 4: Areview of BOT for Developing Project

List of Tables, Figures, and Boxes

Table1 Installed generating capacity in megawatts, 1992–2007 142 Philippine toll road network, 2008 283 Philippine registered airports, 2005 374 Issues on the ports sector and action taken 445 Restructuring of the power industry 466 Telecommunications industry structure, 2002–2006 527 Distribution of subscribers per local exchange carriers, 2006 548 Gross regional domestic product, 2005–2006 58

(at constant 1985 prices)9 Regional financing, 2006 5910 Infrastructure expenditure (in thousand pesos), 2005 6011 Public roads by region, 2007 6512 Regional telephone statistics, 2006 6613 Barangay electrification program, 2006 6714 Cost of exporting a container (20-footer) 6815 Infrastructure ranking in the Global Competitiveness Report 6916 Unsolicited projects presented to BOT Center and ICC 101

Secretariat, 1994–2006 (operational and awarded)17 Breakdown of cost increases 111

Figure1 World Competitiveness Yearbook infrastructure rankings, 5

2006–20072 Cost of awarded projects, 1999–2003 (in US$ million) 153 CIIP investment requirement by sector 194 CIIP investment requirement by financing source 205 CIIP transport investment requirement, 2006–2010 206 Geographical distribution of infrastructure investments 217 Comparative road network of selected ASEAN countries, 27

2000–20048 Strong Republic Transit System 349 Air transport passengers carried 3610 Philippine ports as of 2005 39

vi

Page 5: Areview of BOT for Developing Project

11 Total passenger traffic, 2005 3912 Total cargo throughput in MT, 2000–2006 4013 Roll-on roll-off terminal system 4014 Teledensity 5315 Cellular mobile technology subscribers 5416 Mobile phone subscribers, 2005 5517 Number of cellular mobile telephone subscribers 56

per provider, 200618 Typical BOT project structure 8019 Stages in the BOT process 93

Box1 Key issues and challenges in urbanization, Philippines 82 Selected macroeconomic indicators, 1986–1998 133 BOT projects in the Medium-Term Infrastructure Program 16

(2005–2010)4 Reasons for private participation in infrastructure 725 The Casecnan Transbasin Multipurpose Project 986 Ninoy Aquino International Airport (NAIA) Terminal III 1037 Competitive tender of unsolicited proposals 1068 Manila North Tollways-North Luzon Expressway 1089 Bottlenecks to efficient implementation of ODA-funded 112

projects10 Manila Water concession: key lessons and challenges 11411 Risk sharing in Philippine BOT projects 119

vii

Page 6: Areview of BOT for Developing Project

ix

Foreword

The private sector has been a prime mover in Philippine public infrastructuredevelopment in the past two decades. Through contractual arrangements suchas the build-operate-transfer (BOT), services in utilities, transportation,property development, and information technology are provided to the generalpublic. The Philippines is not very new to BOT and similar types ofarrangements with the private sector. In fact, a number of developmentprojects have been implemented under the BOT.

Implementation of such arrangements, however, has not been withoutproblems. In fact, several projects under the BOT and other similar types ofarrangements have been marred with irregularities and controversies thathave caught national attention. But beyond the noise of such controversies,steps to “diagnose and cure” problem areas and find rooms for improvementare in order. These are what this volume is attempting to achieve.

In this regard, this volume is a welcome addition to the literature onthe topic over and above the other studies that have been made based onpreviously implemented and ongoing projects to improve the implementationof the BOT as a strategic instrument for the provision of public services.

In this volume, the author, Dr. Gilberto Llanto, himself not a strangerto the review of BOT projects in his former capacity as deputy director-generalof the National Economic and Development Authority (NEDA), gives a reviewof the Philippine experience in utilizing BOT as an approach to infrastructuredevelopment and recommends policy reforms for its improvement. Animportant feature of this volume is the presentation of case studies whichhighlight the lessons drawn from failed and successful projects.

It is hoped that the recommendations outlined in this volume wouldserve as input for policymakers in crafting the needed reforms to realizeoptimum benefits from partnerships that could contribute significantly to theexpansion of infrastructure, which in turn leads to substantial economic growthand development.

JOSEF T. YAP President, PIDS

June 2010

Page 7: Areview of BOT for Developing Project

xi

Preface

The Philippines has used the Build-operate-transfer (BOT) Law, as amended,to motivate private sector provision of infrastructure. During the early yearsof its implementation, the private sector showed an enthusiastic response tothis avenue for public-private partnership as indicated by the size of theinvestments in several BOT projects. The World Bank (2005) observed thatthe “the landmark BOT Law has been successful in paving the way for majorinfrastructure projects in the Philippines.” However, the enthusiasm seemsto have been muted in recent years due to problems with government’sinfrastructure policy, vagueness over the application of unsolicited bids anddefinition of guarantees, and weaknesses in the implementation frameworkgoverning BOT projects, among other reasons.

This book is an attempt to understand the recent experience with theimplementation of the BOT Law as well as to point out various areas or issuesneeding the attention of policymakers, starting from the legal framework tothe level of responsibilities of the government institutions that are involvedin the project cycle, i.e., from entry level to implementation and completion.

Using examples from selected BOT projects in the country, the volumepoints out key issues constraining the successful implementation of the BOTapproach to infrastructure provision. It indicates several factors that wereinstrumental in forging an effective public-private partnership in BOT projectsand presents the areas where improvements may be done at the level of boththe legal and institutional frameworks, with the latter referring to the role ofthe oversight agencies and the implementing agencies.

I must acknowledge my indebtedness to the following individuals whoshared with me their knowledge of and insights on infrastructure policy andthe BOT Law: former colleagues at the National Economic and DevelopmentAuthority—Dante Canlas, Ruben Reinoso, Margarita Songco, Erick Planta,Rowena Cham, Lawrence Nelson Guevara, Adora Navarro, Ruzette Mariano,and members of NEDA’s Infrastructure Staff. The paper with Dante Canlas(senior author), Rhean Botha, and Domingo Pallarca, which was prepared forConsuelo Perez, former governor of the Board of Investments, was a source ofcritical analysis and insight.

GILBERTO M. LLANTO Senior Research Fellow, PIDS

June 2010

Page 8: Areview of BOT for Developing Project

1Introduction

This paper has a twofold objective: (a) to review the experience of thePhilippines with the utilization of the build-operate-transfer (BOT)approach for infrastructure development; and (b) to draw key lessons andrecommend policy reforms on how to improve the use of this strategicinstrument for infrastructure provision. The paper is organized into fivesections. After a brief introduction, section 2 gives an overview ofinfrastructure in the Philippines. Section 3 provides an analyticalframework of BOT as an approach for providing infrastructure and howBOT is used by developing countries such as the Philippines to providemuch needed infrastructure. Section 4 analyzes the main issues and lessonsin BOT implementation and uses case studies of BOT projects in thePhilippines to illustrate key points. The lessons are traced through adiscussion of the project cycle or the different stages of the BOT process.The case studies presented highlight the differential experience with BOTas an approach to infrastructure provision. Both failed and successfulprojects are used to illustrate key points in the Philippine experience withthe BOT approach. Time and data limitation forced the paper to simplysketch in broad strokes, so to speak, the various policy issues that thegovernment has to address in order to improve public-private sectorparticipation (PPP) in infrastructure in general and BOT implementationin particular. A more extensive and in-depth study of BOT projects, whichcan overcome the limitations of drawing lessons from a few simple casestudies, should perhaps be done in the near future by other researchers.The last section provides concluding remarks and some policyrecommendations.

The globalization of production and distribution has compelledcountries to have efficient infrastructure in order to be able to havesubstantial participation in global trading and production networks.Fabella (1996) tells the compelling story of Taiwan, which followed a two-

Page 9: Areview of BOT for Developing Project

pronged strategy; improving macroeconomic stability and the provisionof a competitive infrastructure. Once these conditions were met, firms onthe technological frontier came and operated. Inefficient infrastructurecreates a serious bottleneck and impediment to trade and growth andthus there is a drive to meet the infrastructure gap or to make moreefficient existing infrastructure in many countries in East Asia. On theother hand, efficient infrastructure reduces transaction costs and createsvalue-added for producers and consumers. It links producers to the globalsupply chains and distribution system thereby creating access todiscriminating global markets for goods and services. The rapidly developingcountries in East Asia that have made substantial investments in power,telecommunication, transport, and production technology have surged aheadof other noninvesting, developing countries (Llanto 2004 and 2007a).

Recent research shows the substantial impact of infrastructure ongrowth and that with higher infrastructure quantity and quality, incomeinequality declines (Calderon and Serven 2004). Thus, they matter foreconomic growth (Calderon and Serven 2005). Bougheas and others (1999)note that infrastructure can promote specialization and long-run growth.The findings of Calderon and Serven (2005) suggest that infrastructuredevelopment can be a highly effective instrument to combat poverty. Theirsimulation for Latin American countries indicate that increasedavailability and quality of infrastructure can highlight the growthacceleration and inequality reduction.

The growth of international trade and rapid urbanization underscoresthe need to cut costs, increase efficiency and competitiveness wherein thequality of infrastructure matters a lot. The limited coverage and qualityof some Asian countries’ infrastructures are hindering their efforts toachieve international competitiveness (Malhotra 1997).

The key role of infrastructure in economic growth cannot be ignored.A recent study done by a consortium of researchers under the World Bank(WB), the Asian Development Bank (ADB), and the Japan Bank forInternational Cooperation (JBIC) (2005) substantiates the decisive rolethat infrastructure has played in growth and poverty reduction in EastAsia and the Pacific.

Empirical studies testing the public capital hypothesis indicated thatinfrastructure has a positive and significant impact on growth andproductivity.1 Canning and Pedroni (2004) investigated the long-run__________________1Tatom (1991) finds a contrary result: the hypothesis that public capital (infrastructure) has apositive marginal private sector product cannot be supported.

2 A Review of Build-operate-transfer for Infrastructure Development

Page 10: Areview of BOT for Developing Project

consequences of infrastructure provision on per capita income in a panelof countries over the period 1950–1992. Their results provide clear evidencethat in the vast majority of cases, infrastructure does induce long-rungrowth effects although there is a great deal of variation in the resultsacross individual countries. Summarizing the results of various estimates,Gramlich (1994) and Sturm and De Haan (1995) found output elasticitieswith respect to public capital of around 0.3. Wang’s (2002) estimates forseven East Asian countries for the period 1979–1998 indicated an averageelasticity of 0.2 percent of private production to a 1 percent increase inpublic capital. Shepherd and Wilson (2006) find that better roads arestrongly associated with larger trade flows among 138 cities in 27 countriesof Eastern Europe and Central Asia.

On the other hand, there still is debate “about whether infrastructureprovision actually fosters economic development or whether it is providedas a product of the economic development process (Button 2002).2 Adifferent view is that while there is a definite link between infrastructureinvestment and economic growth, the causality in either direction has notbeen established. Thus, physical infrastructure can be regarded as a formof “complementary capital” that requires the existence of availableproductive capital (whether physical or human) for investment (andinnovation) in order to realize the economic growth potential.Infrastructure in itself can only develop, not create, economic potentialbut only where appropriate conditions exist (O’Fallon 2003).

Notwithstanding the lively debate among different researchers onthe link between infrastructure and growth, the preponderance ofempirical evidence shows that inadequate supply of infrastructure or theunreliability of infrastructure services may constrain investments ofproductive capital and lead to a restriction or reduction of output. Thereare too many pieces of evidence supporting the significant impacts ofinfrastructure on productivity and growth that are difficult to ignore(Rodriguez 2006). The majority of studies trying to establish a linkagebetween (public) investments or capital and economic growth indicate that(a) public capital is complementary and promotes private capital formation;(b) core infrastructure, such as roads and railways, tend to have the mostimpact on productivity; and (c) the direction of causation is from public

__________________2 Button (2002) notes the inconclusiveness of empirical evidence on this matter citing problemswith data and techniques that are used to provide empirical estimation on the relationship betweeninfrastructure and economic growth.

Llanto 3

Page 11: Areview of BOT for Developing Project

capital to productivity and not the other way around (InfrastructureCanada 2007).

A recent empirical paper pointed out that infrastructure acts as amajor driver for growth and poverty reduction in the Philippines and thatinfrastructure is a significant determinant of economic growth on anaggregative basis and also at the subnational level (Llanto 2008). Thepaper has found evidence that infrastructure could be an importantconditioning variable in regional convergence. Llanto’s results indicatedthe importance of investment in human capital (education) andinfrastructure in promoting regional growth consistent with the findingsof other researchers (Lamberte et al. 2003; Basilio and Gundaya 1997).Infrastructure development is critical at the subnational level as shownby the results showing that local government infrastructure expenditureis a significant determinant of local growth. The implication is thatunderinvestment in infrastructure will have serious consequences forthe country’s capacity to grow and reduce poverty. A more recent study(Llanto 2009) finds that electricity, roads, irrigation, and telephonesare positive determinants of agricultural productivity.

However, the Philippines amid globalization is failing to make sub-stantial investments in transport, ports and shipping, and communica-tions thereby weakening its ability to compete on a global basis (Llanto2004). A recent survey by the Japan External Trade Office (JETRO) of asample of Japanese international investors about what they consideredas a deterrent to increasing their investments in Asia cited underdevel-oped infrastructure as a major disincentive to Japanese foreign invest-ment in the Philippines (JETRO 2007).

The lack of adequate transportation, telecommunication, and energyfacilities can adversely affect the development of existing industries andmay likewise preclude new entrants from coming in. An efficienttransportation and communication infrastructure provides overall mobilityfor goods and people alike, contributes to a reduction of input andtransactions costs, and enhances the efficiency of markets. Localinfrastructure, which may have significant spillover effects spurs localeconomic activities while the network characteristics of infrastructureenhances connectivity of regions and promotes domestic integration. Aninteresting observation is that infrastructure investments may also bedefended on equity grounds because interregional infrastructure increasesthe accessibility of peripheral regions and raises their level ofcompetitiveness. This could help stop the process of regional divergence(Rosik 2006).

4 A Review of Build-operate-transfer for Infrastructure Development

Page 12: Areview of BOT for Developing Project

Infrastructure in the country has not kept pace with the requirementsof a growing economy, the increase in population, and urbanization. Thepoor state of infrastructure in the country and the lack of infrastructureinvestment have constrained growth (Llanto 2004). At the regional level,empirical estimates showed that the regions with the lowest gross regionaldomestic product are also those suffering from the most severe lack ofbasic infrastructure (Llanto 2007a). The Philippines has not providedinfrastructure that is sufficient in quantity and quality to meet competitivechallenges in the global economy as well as poverty reduction goals undersuch international commitments as the Millennium Development Goals.Both the Asian Development Bank and the World Bank have noted thenegative impact of low-quality infrastructure on the Philippines’ globalcompetitiveness. The state of infrastructure in a given country is one keydeterminant of its competitiveness ranking. The 2007 InfrastructureRanking by the World Competitiveness Yearbook (Figure 1) shows thatamong the ASEAN countries, the Philippines (51st) is not far behindThailand (48th) and slightly ahead of Indonesia (54th).

The low level of investment in and poor condition of infrastructurein the Philippines have increased the cost of doing business in the countryand had significant adverse impact on the perceived competitiveness ofthe Philippines as an investment destination. As indicated in Llanto (2008):

The World Economic Forum (WEF) in 2003–2004 ranked thePhilippines 66th of 102 countries in its growth competitiveness

Figure 1. World Competitiveness Yearbook infrastructure rankings, 2006–2007

Llanto 5

Page 13: Areview of BOT for Developing Project

index partly because of the poor state of Philippine infrastructure(WEF 2004).In terms of overall infrastructure quality, the Philippines ranked88th of 125 countries in the 2006 Global Competitiveness Indexof the WEF.In terms of adequacy of infrastructure, the Philippines slid to51st in 2007 of 61 countries from 49th in 2006 according to the2007 World Competitiveness Yearbook (IMD 2007).

With respect to the increased cost of doing business in the countrythat is brought about by the inadequate and poor condition ofinfrastructure, the following have been observed:

More than half of the country’s road network was in poor andbad condition, leading to vehicle operating and intercity freightcosts that are more than 50 percent higher than in regionalneighbors such as Indonesia and Thailand. Thus, the high levelof congestion on the main roads is costing the Philippines as muchas PhP185 billion a year in 2006 prices (World Bank 2005).Power tariffs for businesses in Manila were 20 to 80 percent higherthan tariffs in nine other Southeast Asian cities (Leung et al.2003).About 18 percent of firms participating in the 2005 InvestmentClimate Survey reported that the inadequate transport networkwas a major constraint to investment (ADB-WB 2005).The Philippines has the highest cost in the ASEAN for exportinga container partly because of inefficiencies in port handling. TheWorld Bank’s recent Doing Business Indicators noted that thecost of exporting a 20-foot container from the Philippines is 16 to51 percent higher than from the People’s Republic of China,Singapore, or Thailand (WB-IFC 2007).

Rapid urbanization has swelled the ranks of the urban poor and hascreated a tremendous demand for housing and social services, securedland tenure and serviced land, which to a great extent has remainedunsatisfied. Access to social services such as water supply and sanitationand solid waste management is on a decline both in terms of coverage andquality. The deteriorating coverage and lack of quality of infrastructureand service delivery have been widely considered as an impediment togrowth and poverty reduction. The projected growth of the populationand the rapid urbanization rate in the Philippines will put even greater

6 A Review of Build-operate-transfer for Infrastructure Development

Page 14: Areview of BOT for Developing Project

pressure on the government to address the lack of infrastructure. TheHousing and Urban Development Coordinating Council has estimatedthat Philippine population will increase from 80 million in 2002 to 98.2million by 2015. The country has one of the highest urbanization growthrates in the world with an average urbanization growth rate of 5.1 percentbetween 1960 and 1995. More than half of the population is in urbanareas and this proportion is expected to reach 60 percent by 2010 if currenttrends continue. While official data indicate that only about 20 percent ofthe 7.5 million urban households fall below the poverty income line(PhP13,915 per capita per year as of 2001), the poverty income line alonedoes not capture the dire situation of informal settlers (Llanto 2007).

The key issues and challenges in urbanization are summarized inBox 1.

Since the 1997 Asian financial crisis, infrastructure investment hasdropped from a peak of 8.5 percent of gross domestic product in 1998 toonly 2.8 percent of GDP in 2002. In this regard, the donor community hasadvised the Philippine government to increase infrastructure investmentsto at least 5 percent of GDP, the average infrastructure investment normof its neighboring countries in the past decade. To do this, the governmenthas to expand its fiscal space through a vigorous tax reform program. TheWorld Bank (2005) recommends the need to pursue a “credible andsustained period of fiscal reforms—in particular, increasing tax revenues.. .contingent liabilities from infrastructure programs should be carefullyaccounted for and managed; guarantees should be used judiciously, basedon a clear rationale and appropriate risk allocation” (Executive summary,pages xxiv to xxv).

The government has recognized the constraining effect of poorinfrastructure on economic growth and development and has prioritizedthe removal of this serious bottleneck. The Medium-Term PhilippineDevelopment Plan (MTPDP) (2004–2010) provided broad strategies andidentified critical infrastructure that have to be completed or provided bythe end of the Plan period. The MTPDP 2004–2010 also recognizes privatesector participation as key to infrastructure development in the country.In a workshop organized by the Philippine Development Forum, it wasclaimed that “public-private partnership (PPP) would be the only viableoption for key infrastructure development in the short-term, given thefiscal conditions of the Philippine Government.3

__________________3 Report of the Philippine Infrastructure Workshop, Philippine Infrastructure and Business ClimateWorkshop, Makati Shangri-la Hotel, Makati City, 1 March 2006.

Llanto 7

Page 15: Areview of BOT for Developing Project

The MTPDP 2004–2010 stressed the importance of connectivity ofan archipelagic economy by good transport and communications network.The connectivity provided by good infrastructure facilities is expected to

8 A Review of Build-operate-transfer for Infrastructure Development

The World Bank, after a series of consultations and workshops with stake-holders, summarized the key issues and challenges in urban development.

Already, most people (40 million) live in urban areas; urban incomes are2.3 times rural incomes; they already account for the vast majority (70%) ofeconomic output. The contribution of urban areas to economic growth is evengreater. For example, in 2000, the largely urbanized Philippine heartland(NCR + Regions IIIand IV) aloneaccounted for 60 per-cent of economicgrowth. The Philip-pines has one of thehighest urbanizationrates in the develop-ing world. Thoughexpected to slowdown, urban pop-ulation will continueto increase muchfaster than averagepopulation growthand will account for75 percent of thetotal population by2030.

What are the main issues and challenges?creating enough jobs, especially in urban areas where population isgrowing fastest;rising share of urban poverty in national poverty;crisis in governance of larger urban-regional scale infrastructurenetworks, which contributes to the cost of doing business investmentas well as housing;integrated urban infrastructure development.

Source: World Bank 2005

Box 1. Key issues and challenges in urbanization, Philippines

Source: UN Population Division (2002)

Figure 1. Urban and rural population, 1950–2030

Page 16: Areview of BOT for Developing Project

open new economic opportunities, reduce transportation and transactioncosts of business, and increase access to social services. The interconnectionwill also strengthen the socioeconomic, cultural, and political linkagesbetween and among regions. Eventually, connectivity will decentralizeprogress and bring development to the countryside.

Efficient infrastructure is important for economic integration in theASEAN and East Asia and for narrowing development gaps. The neweconomic geography considers two forces that work on economic integrationamong countries as well as domestic regions within a country: (a)agglomeration forces, and (b) dispersion forces. While agglomeration forceswiden disparities among countries and within country, countervailingdispersion forces motivate the relocation of economic activities, e.g.,manufacturing to lagging countries or regions as congestion in the moredeveloped countries or regions within country starts to constrain furthergrowth.

The interim report of the Economic Research Institute of Asia (ERIA)on “Developing a roadmap toward East Asian economic integration” drawsattention to a sign of congestion in economic agglomeration in East Asia,and the dispersion forces that start working to influence industrial location(ERIA 2007). Congestion and increases in production costs (e.g., highwages, difficulty in securing land) suggest that dispersion forces come into address these constraints. The report notes that firms have to find laborfrom far distance and some of them eventually set up a new factory in amiddle-size city or in a rural area. The report cites fragmentation theoryto explain that differences in location advantages such as factor pricesmotivate fragmentation of production processes. Differences in wage levelsbetween ASEAN forerunner countries and Cambodia, Laos, Myanmar,and Vietnam (CLMV) are still substantial and thus CLMV may ratherhave strengths, particularly for labor-intensive or natural-resource-intensive production processes. The development of economicinfrastructure including logistics is crucially important for economicdevelopment through effectively utilizing globalizing forces. Economicinfrastructure is vital to the efficient formation of agglomeration as wellas the extension of production networks. Gill and Kharas (2007) point outthat “ports and other transport modes have served as the foundation forcities and, once established, these cities tended to grow. Transport costscontinue to be important in determining the size and nature of cities”(page 16).

Proper project design and prioritization are extremely important.Effective use of regional resources for infrastructure development,

Llanto 9

Page 17: Areview of BOT for Developing Project

including public-private partnership, is also required. In this regard,among the many important issues facing CLMV is the need to reducenetwork setup cost and service link cost. Their geographical proximity togrowth centers in forerunner ASEAN countries would be a strong pointand thus, efforts for deeper integration such as adopting the appropriateinfrastructure policies are essential for economic integration. ThePhilippines, being an archipelago, faces a different set of challenges inestablishing connectivity among its numerous islands and integrating withthe Asian region and the global markets although the commondenominator among these countries is the critical role that goodinfrastructure has played in market integration. Because of the potentialhigh economic and financial returns of linking with major Asian and globalmarkets, investments in air and sea infrastructure in fast growing regionssuch as those in Central Luzon, Southern Luzon, and the Davao regionmay be feasible. Those putative investments may even attract privatesector participation given proper incentives. It is the infrastructureinvestment to connect many smaller islands of the archipelago, many ofwhich are in lagging regions that poise formidable investment andfinancing challenges.

In recent years, many developing country governments have triedto solicit investment for public projects from the private sector. Privatesector capital and management expertise were looked upon as helping toquickly and cheaply solve the infrastructure lack through variousprivatization approaches such as corporatization, sell-off of state-ownedenterprises and management contracts (Menheere and Pollalis 1996;Handley 1997). The World Bank (2005) has advised the Philippinegovernment about the advantages of a private sector-led infrastructuredevelopment strategy, calling it “a pillar of infrastructure development.”

Public-private partnership can play a significant role in infrastructureprovision and development. Several countries have successfully used theBOT approach, a particular form of public sector-private sector partnershipto address the infrastructure needs of the economy (UNIDO 1996).4 WithBOT, the private sector takes care of the design, financing, construction,operation, and management of the infrastructural facility and after aspecified concession period, the government assumes ownership of thefacility. The private sector takes on long-term risks of financing andmanaging an infrastructural facility in exchange for commercial returns

__________________4 UNIDO cites BOT as an approach for medium- and large-scale infrastructure in several countries.

10 A Review of Build-operate-transfer for Infrastructure Development

Page 18: Areview of BOT for Developing Project

to the investment under the ‘user-pays’ principle (Menheere and Pollalis1986; Handley 1997, among others).

The development of the Suez Canal was done through a BOTapproach (Levy 1996). The first official private facility development underthe name “Build-Operate-Transfer” was used in Turkey in 1984 to developinfrastructure. Private financing was used to develop railways and roadsin the western world in the second half of the nineteenth century(Menheere and Pollalis 1996). The BOT approach has been applied topower generation, telecommunication, sewerage and water, bridges andtoll roads, and other facilities in the United States of America, England,and Latin America. The Eurotunnel built in the early 1990s was probablythe largest ever BOT project (Handley 1997). Some other BOT projectsare as follows: China’s Shajiao B Power Plant Project, Pakistan’s HubPower Project, Thailand’s Mass Transit System Project, Thailand’s SecondStage Expressway Project, among others.

The Philippines faced a severe power crisis as the 1990s came to aclose. Economic output plummeted as debilitating power outages crippledmanufacturing and industry and the entire economy. The narrow fiscalspace and lead time it would take to commission new power plants forcedthe government to seek legislation for a BOT approach that could be usedto entice the private sector to help solve the power crisis.

The Philippines was reported as the first country in Southeast Asiato enact a BOT Law. In 1990, the Philippine Congress enacted a hallmarklaw, Republic Act (RA) 6957, which was later amended by RA 7718 in1994, to provide the legal framework governing financing, construction,and operation of an infrastructure project by a private entity called aconcessionaire. The contract with the government specifies a cooperationperiod, that is, a period of time during which the government delegates tothe concessionaire the authority to finance, build, and operate a facility,and to impose charges or fees on users of the facility for a profit. At theend of the cooperation period, the private investor turns over or transfersthe facility to the government.

The Philippine BOT Law has been studied and used as a model forother BOT laws in neighboring countries. The BOT and its variant schemeshave been widely used to apply private sector management and technicalexpertise and financing on infrastructure provision that would otherwisehave not been provided because of the country’s capital shortage andinability to finance the provision of much needed infrastructure and thenotorious inefficiency of government operation of infrastructure. ThePhilippine government entered into BOT contracts with the private sector

Llanto 11

Page 19: Areview of BOT for Developing Project

in water supply, urban rail transit, international airport terminal services,and toll roads.

During the latter part of the Aquino administration, the power crisisadversely affected the performance of the manufacturing sector as reflectedby the decline in manufacturing growth rate. For 1990–1992, averageannual growth rate of the manufacturing sector was 0.16 percent. Installedgenerating capacity in 1992 was 6,949 megawatts at the close of theadministration of Corazon Aquino.

The Ramos administration used the BOT approach to solve the criticalpower problem of the 1990s without having to provide for an immediatecash outlay, which the narrow fiscal space effectively prevented.5 The powerproblem has brought the economy to a tailspin as manufacturing practicallyground to a halt (Box 2).

The government’s efforts to provide power through private sectorparticipation, basically through BOT projects, contributed to reviving theeconomy. Through the BOT, the private sector constructed andrehabilitated about 5,627-megawatt (MW) generation capacity or 47percent of the country’s total generation capacity (Llanto 2004). Amongthe private energy companies that accepted the challenge laid down bythe government to invest in the Philippines, Hopewell was the largestindependent power producer (IPP) with 1,280 megawatts of installedcapacity.6 As of December 2007, the Department of Energy reported thatthe Philippines had a total installed generation capacity of 15,937megawatts, slightly increasing from previous year’s 15,803 megawatts(Table 1).7

The early harvest of relatively successful BOT projects has raisedexpectations among donors, the government, and the private sector inusing BOT schemes to solve the infrastructure lack, which investors haveidentified as a principal barrier to investments.

However, the role of the BOT approach in addressing theinfrastructure lack in Asian developing countries seems to have diminishedfollowing the aftermath of the Asian financial crisis as private investorsfocused their attention elsewhere. There seems to be a retreat of attentionand investment resolve on the part of the private sector even as

__________________5 Handley (1997) commented that the country has had the most successful independent power-producing BOT programs in the region as a result of its BOT approach.6 http://www.converger.com/eiacab/philippi.htm7 http://www.doe.gov.ph

12 A Review of Build-operate-transfer for Infrastructure Development

Page 20: Areview of BOT for Developing Project

governments and the multilateral lending institutions look up to it as asolution to a severe infrastructure lack in developing countries.

The decline in private sector interest is widely observed in the world.The Public-Private Infrastructure Advisory Facility of the World Bankreported that the decline is an international trend and is brought aboutby several underlying factors: the more developed middle-income countrieshad reached the end of the private participation cycle; the financial crisesduring the 1990s brought about a climate of uncertainty; and controversialtransactions brought to the limelight the complex political economy ofprivate involvement in infrastructure.8

In particular, for the Philippines, the BOT approach has stalled as amechanism for private participation in infrastructure provision even asthe government, which cannot adequately meet the infrastructure lack,continuously tries to woo private capital to invest in infrastructure. Thisis worrisome because the infrastructure lack has been described as a

Year GDP Manufacturing Employment Export Import Interest Exchange (Real) Rate Rate I% % per PhP/US$Growth Annum Rates

1986 3.42 -15.29 2.95 4.60 -1.31 -38.65 9.561987 4.31 5.57 -0.63 18.13 33.56 -23.12 0.891988 6.75 9.52 3.38 23.67 21.11 20.30 2.561989 6.21 5.81 1.64 10.56 27.70 21.88 3.041990 3.04 2.66 3.13 4.67 17.15 24.62 11.841991 -0.58 -0.44 1.98 7.99 -1.27 -3.29 13.031992 0.34 -1.73 3.12 11.13 20.48 -17.45 -7.161993 2.12 0.75 2.90 15.79 21.20 -24.74 6.301994 4.39 5.01 2.67 18.53 21.23 2.74 -2.591995 4.68 6.77 2.57 29.40 23.71 -2.67 -2.661996 5.85 5.58 5.88 17.75 20.82 1.37 1.951997 5.19 4.22 1.95 22.81 14.02 9.46 12.421998 -0.58 -1.13 -3.91 16.92 -18.79 13.58 38.76

Source: NSCB

Box 2. Selected macroeconomic indicators, 1986–1998

__________________8 2003 Public-Private Infrastructure Advisory Facility (PPIAF) Annual Report.

Llanto 13

Page 21: Areview of BOT for Developing Project

bottleneck to growth and failure to address it will surely undermine thecountry’s competitiveness in the global markets and its attractiveness asa destination of foreign direct investment.

Figure 2 shows the cost of awarded projects under the Philippineprogram of public-private sector partnerships during the period 1999–2003. A declining trend in terms of new investments committed by theprivate sector every year can be seen.9

What explains this adverse turn of events in Philippine BOTimplementation? Why has there been a retreat of interest and resolve touse it as a mechanism for infrastructure provision?

Popular discourse points to the need to improve the implementationof BOT by amending certain provisions of the Implementing Rules andRegulations (IRR) and/or amending the law itself in order to remove factorsthat have seemed to stymie a more extensive use of BOT in infrastructureprovision. Still others view the retreat of interest as part of an overallcautious stance taken by private investors to reduce their exposure to thePhilippines. The World Bank (2005) noted that the business environment

__________________9 Source: Build-Operate-Transfer (BOT) Center.

14 A Review of Build-operate-transfer for Infrastructure Development

Table 1. Installed generating capacity in megawatts,1992–2007

Total Hydro Coal Geothermal Diesel/Oil

1992 6,949 2,257 405 888 3,3991993 7,959 2,259 441 963 4,2961994 9,212 2,254 550 1,074 5,3351995 9,732 2,303 850 1,154 5,4251996 11,193 2,303 1,600 1,446 5,8441997 11,722 2,303 1,600 1,886 5,9731998 12,067 2,304 2,200 1,856 5,5681999 12,431 2,304 3,355 1,931 4,8392000 13,185 2,301 3,963 1,931 4,9872001 13,380 2,518 3,963 1,931 3,9052002 14,702 2,518 3,963 1,931 3,5272003 15,124 2,867 3,958 1,932 3,6042004 15,548 3,217 3,967 1,932 3,6692005 15,619 3,222 3,967 1,978 3,6632006 15,803 3,257 4,177 1,978 3,6022007 15,937 3,269 4,213 1,958 3,616

Page 22: Areview of BOT for Developing Project

for infrastructure “has been undermined by a number of majorimpediments” such as “inadequate cost recovery, corruption, insufficientcompetition, and low credibility of regulatory and judicial institutions”. . .that are “affecting both public and private sector performance.”

It is submitted that a review of the Philippine experience with thismode of private sector participation in infrastructure provision will becritical and useful in identifying critical barriers to effectiveimplementation. Private investors and the government alike continue tolook up to BOT as an important mechanism for public-private partnershipin infrastructure provision. The MTPDP has identified BOT arrangementsor schemes as a major instrument for infrastructure development (Box 3).

The next section provides a brief overview of the infrastructuresituation in the country, which shows many opportunities for BOT typearrangements and for private participation. The discussion in Section 2sets the stage for an analysis of the Philippine experience with BOT, whichwill point to a number of issues or concerns that have to be resolved bypolicymakers.

Llanto 15

Figure 2. Cost of awarded projects, 1999–2003 (in US$ million)

Page 23: Areview of BOT for Developing Project

Box 3. BOT projects in the Medium-Term Infrastructure Program (2005–2010)

Northern Intermodal Transport Terminal Complex (build-operate-own)EDSA/MRT/LRT loop project (solicited build-operate-transfer)MRT 3 CAPEX project (build-lease-transfer/official developmentassistance [ODA])MRT 4 (build-transfer/build-operate-transfer)MRT 7 (build, gradual transfer, operation, and maintenance)MRT 8 (build-transfer/build-operate-transfer)La Mesa Parkway – 21-kilometer tollway, 5-MW hydro power plant,12-MCD water treatment plant, stage 1 (build-operate-transfer)Expanded MVIS project (build-operate-transfer)Carmen bulk water supply project (build-operate-own)Alien certificate of registration card extensible automated fingerprint(build-operate-transfer)

Source: Medium-Term Philippine Development Plan (2004–2010).

16 A Review of Build-operate-transfer for Infrastructure Development

Page 24: Areview of BOT for Developing Project

Overall situationThe importance of infrastructure for developing countries cannot beunderstated as it is considered a major driver for growth and povertyreduction. The lack of adequate transportation, water and energy facilities,for instance, can adversely affect the development of existing industriesand may likewise preclude new entrants from coming in. An efficienttransportation and communication infrastructure provides overall mobilityfor goods and people as well, contributes to a reduction of input andtransactions costs, and enhances the efficiency of markets. Localinfrastructure, which may have significant spillover effects spurs localeconomic activities while the network characteristics of infrastructureenhances connectivity of regions and promotes domestic integration.

Multilateral donors such as the Asian Development Bank and theWorld Bank have noted the negative impact on the Philippines’ globalcompetitiveness of low quality infrastructure, notwithstanding recent gainsof the country in providing households and firms alike with better accessto water, sanitation, and electricity. As stated earlier, in terms of overallinfrastructure quality, the Philippines ranked 88th (out of 125 countries)in the 2006 Global Competitiveness Index, slightly improving from 89th

rank in 2004.11 On the other hand, in terms of adequacy of infrastructure,the Philippines slid to 51st in 2007 (out of 61 countries) from 49th in 2006according to the 2007 World Competitiveness Yearbook (IMD 2007). Thestate of infrastructure in a given country is one key determinant of itscompetitiveness ranking. Unfortunately, the Philippines has not providedinfrastructure that is sufficient in quantity and quality to meet global

2An Overview of Infrastructurein the Philippines10

__________________10 This largely draws from Llanto (2008b).11 Global Competitiveness Report (2006).

Page 25: Areview of BOT for Developing Project

economic challenges as well as poverty reduction goals under suchinternational commitments as the Millennium Development Goals.

Notwithstanding the low global ranking in infrastructure adequacyand competitiveness, the Philippines has some notable achievements inthe infrastructure sector during the past few years. The enactment of theBuild-Operate-Transfer Law (Republic Act 6957 as amended by RepublicAct 7718) paved the way for private sector involvement in the finance,construction, and operation of vital public infrastructure facilities andservices. Completed BOT projects included toll roads, mass rail transit(MRT) systems, and power plants, which averted an impending energycrisis in the 1990s. The present government has recognized the criticalstate of Philippine infrastructure and has given it high priority in the2004–2010 MTPDP. In the priority list is the development of roll-on roll-off (RORO) shipping as an important component of the “Strong RepublicNautical Highway,” which links major islands, the provision of power toall barangays, and the development of a reliable and integrated mass railtransit system for populous urban areas such as Metro Manila, amongothers.

Planned investments in infrastructureIn particular for infrastructure, the MTPDP 2004–2010 lays down thefollowing goals to be attained by the end of the planning period in relationto the promotion of decentralized development:

the network of transport and digital infrastructure, which thegovernment launched in 2002 shall have linked the entire country;power and water services shall have been regularly provided tothe entire country;Metro Manila will have been decongested with economic activitygrowing and spreading to new centers of government, business,and community in Luzon, Visayas, and Mindanao; and,the Subic-Clark (in Luzon) corridor will have become the mostcompetitive international service and logistics center in theSoutheast Asian region.

The government has mapped out its medium-term investmentprogram in a document called the “Comprehensive and IntegratedInfrastructure Program (CIIP).” The CIIP contains the list of infrastructureprojects, which would be implemented to meet the goals and objectives ofinfrastructure development under the MTPDP 2004–2010. It includesprojects that will be financed and implemented by private sector

18 A Review of Build-operate-transfer for Infrastructure Development

Page 26: Areview of BOT for Developing Project

participation, that is, under BOT arrangements, joint venture, and otherpublic-private partnership schemes, and those that will be purely publicinvestment, which are either; (a) funded by budgetary appropriation, (b)ODA loans, (c) local government units, (d) government financialinstitutions, or (e) government-owned and -controlled corporations.12

Please see Figure 3.The CIIP has identified priority infrastructure projects estimated at

PhP2,016.8 billion for the period 2006–2010 and beyond. Almost half, oraround PhP952 billion, represents transportation-related projects whilePhP456 billion would fund power and electrification programs. Theremaining investments are related to water resources, socialinfrastructure, support to agrarian reform communities (ARCs), andcommunications.

In terms of financing source, almost half of the total proposedinvestments (PhP881 billion, 43.7%) would be sourced from the nationalgovernment, one-third (PhP663.2 billion, 33%) from the private sector,and almost one-fifth (PhP341 billion, 16.9%) from government-owned and-controlled corporations (GOCCs) and government financial institutions(GFIs). Local government units (LGUs), through GFI financing schemes,would bear only 2 percent of the total proposed infrastructure investmentprogram (Figure 4).

__________________12 National Economic and Development Authority, Comprehensive and Integrated InfrastructureProgram (CIIP), presentation to NEDA Board, 22 May 2007.

Figure 3. CIIP investment requirement by sector

Source: National Economic Development Authority [NEDA] (2007).

Llanto 19

Page 27: Areview of BOT for Developing Project

To augment the funds sourced from budgetary appropriation, thegovernment would continue to tap ODA from multilateral (e.g., ADB) andbilateral sources (e.g., JBIC, China Export-Import Bank, etc.) and thecapital markets.

For transportation, most of the investments will be allocated to roadsand bridges (43%) and urban rail (41%) while the remaining will beallocated to air transport (12%) and water transport (4%) (Figure 5).

Geographically, half of the total proposed investments will benefitthe Luzon Urban beltway super region while proposed investments for

Figure 4. CIIP investment requirement by financing source

Source: NEDA (2007).

20 A Review of Build-operate-transfer for Infrastructure Development

Figure 5. CIIP transport investment requirement, 2006–2010

Source: NEDA (2006).

Page 28: Areview of BOT for Developing Project

the Central Philippines, Agribusiness Mindanao, and North Luzon superregions would each have around 15 percent of total proposed infrastructureinvestments (Figure 6). The proposed investments for the development ofthe Cyber Corridor represent 3 percent of the total investments.

The overall situation shows the inadequate state of infrastructurein the country and the limited ability of the government to provide it. It isnow recognized that the serious lack of good infrastructure is the result ofyears of neglect of proper maintenance and underinvestment in the sector.To address this problem the Plan presented what appears to beoverambitious targets for new infrastructure that could fail to materializebecause of the Philippine (national) government’s narrow fiscal space.However, it seems that the government is silent on the aspect ofmaintenance of infrastructure facilities. The relatively low tax effort andsubstantial leakages arising from inefficiencies and reported corruptionin both the executive and the legislative branches of government areserious challenges that have to be faced squarely by the government. Thenarrow fiscal space constrains the provision not only of infrastructure butalso of vital services to the population while corruption andmismanagement of projects erode the image of the country as a good placeto make investments. The irony is the misallocation that visitsgovernment’s expenditure policy when politicians insert ill-conceived andself-serving projects during the annual budgetary appropriation process.Political pork barrel, which represents a substantial amount of funds, hasnever been associated with efficient allocation and utilization of publicmonies.

Figure 6. Geographical distribution of infrastructure investments

Llanto 21

Page 29: Areview of BOT for Developing Project

The MTPDP rightly identified the private sector and LGUs aspartners in addressing the infrastructure lack. Through BOTarrangements and other modes of private sector participation, e.g.,concession agreement, management contract, the government would beable to harness private sector financing, technical, and managementexpertise for infrastructure development. However, the government wouldhave to address a number of issues in order to give the private sector astrong motivation to participate in infrastructure development.13 Sufficeit to say at this juncture that there is a large scope for potential privatesector participation in infrastructure provision and development and thecountry has a good basic legal framework to support it. Past experienceshows how this strategy was used to solve the energy crisis problem of the1990s but the BOT approach has since faltered for reasons to be explainedlater in this paper. In this regard, the government should pursue certainreforms for a meaningful public-private partnership. It cannot afford tolose private sector expertise and resources in its quest to improve thestate of infrastructure in the country.

Role of LGUs and GOCCsThe local government units (LGUs) should provide much-needed localinfrastructure such as critical road links to the national arterial highwayand port terminals for the government’s RORO terminal system forefficient transport of goods and people across the archipelago. For this tohappen, government authorities have to address several issues thatconstrain the efficient participation of LGUs in infrastructure provision:(a) inadequacy of local revenues and inefficient fiscal transfer system; (b)inefficient investment programming and implementation; and (c) lack ofintegration of local infrastructure with national infrastructure plans.

Local government units do not generally raise substantial own-sourcerevenues. Many LGUs are dependent on the fiscal transfer from thenational government called the internal revenue allotment (IRA). Theshare of the IRA in total LGU income net of borrowings rose from 38percent in 1985–1991 to as high as 65 percent in 1992–2003 for all LGUscombined. The IRA, thus, effectively substitutes for own-source revenuegeneration by the lower income LGUs. Only a few big cities and towns areable to raise substantial local revenues but ironically, these LGUs receivea bigger share of the IRA than the lower income government units. The

__________________13 This is a point discussed in Section 4 of this paper.

22 A Review of Build-operate-transfer for Infrastructure Development

Page 30: Areview of BOT for Developing Project

latter, which have smaller tax bases owing to weak local economies, cannotraise the necessary revenues and thus, become more and more dependenton the fiscal transfer. A more effective own-source revenue generationwill provide substantial funds for local development, including theprovision of local infrastructure.

A recent study (Brillantes et al. 2009) suggests that consolidation ofsome local governments should be seriously considered. The consolidationmay well expand local tax bases, provide the potential for more substantialrevenue collection, and improve service delivery, including the provisionof local infrastructure. This could be the right track instead of the penchantof politicians to cut up current local governments into smaller politicalunits that only serve their selfish interests such as expanding a politicaldynasty and ensuring the political elite’s hold to power. Consolidationcould lead to improving administrative capacity and prevent overlappingresponsibilities and functions.

There is also the problem of local infrastructure projects as tendingto be ‘governor-centric or ‘mayor-centric’ meaning that local infrastructureprojects are typically pursued for the furtherance of the parochial politicalobjectives of the local chief executive. Worse, there is also a reportedsyndrome of “dividing by N” the local infrastructure budget appropriatedby the local sanggunian (local legislative councils). This is a system bywhich local legislators apportion a share of the local infrastructure budgetamong themselves for implementation purposes. The local infrastructurebudget is divided among as many members of the ruling administrationin the sanggunian for implementing their respective pet projects. Thisapproach, an imitation of the much-maligned ‘pork barrel’ funds given tocongressmen and senators who help themselves to funds supposedlyappropriated for the country’s development, fragments already scarce localresources and results in uncoordinated and unrelated “infrastructureprojects.”14 The lack of integration of those infrastructure projects withregional and national development plans has resulted into a waste of localresources and the sorry state of subnational infrastructure (Llanto 2007a).Thus, the expectation that LGUs could fill the gap in infrastructuredevelopment should be tempered by (a) the fact that LGUs themselvesface fiscal constraints unless they become really serious about local revenuemobilization and (b) the experience on the ground showing that local

__________________14 Some examples are cemented basketball courts that are used for drying rice and corn, waitingsheds for pedestrians, street lighting, farm-to-market roads, etc., which form part of an incoherentlocal investment plan.

Llanto 23

Page 31: Areview of BOT for Developing Project

infrastructure development projects may not be integrated with overallregional or national development plans and worse, fragmentation of theinfrastructure budget to support tiny projects that are intended to meetthe political objectives of locally elected officials. These are critical issuesthat the national government and the LGUs should address.

The case for using GOCCs has to be assessed relative to their capacityto undertake infrastructure projects and readiness to take on the task inview of fiscal problems hounding a good number of those corporations.Lenders would typically demand sovereign guarantees for loans to be takenby those GOCCs. The issue of the increasing size of contingent liabilitiesarising from those guarantees has to be closely examined by thegovernment because of the fiscal risk they will create once they becomeactual liabilities. Total estimated contingent liabilities of the governmentas of 2003 were PhP1,672 million. The contingent liabilities of theinfrastructure sector comprised 54 percent of total contingent liabilitiesas estimated by the Department of Finance. Of the total contingentliabilities of the infrastructure sector, BOT projects had a share of 18.5percent while buyout costs of IPPs made up 35 percent. Guarantees onprojects and activities of GOCCs and GFIs were 43 percent of the totalestimate. Guarantee institutions had 3 percent of the total estimate (Llanto2007b).

This is not to say that GOCCs should not be part of the strategy toaddress the infrastructure lack because they may be able to play asignificant role in infrastructure development in view of the fiscalconstraints faced by the government. However, while a few of those GOCCsmay have the resources to engage in infrastructure development,infrastructure provision should be in the mandate of those corporations.Many of the GOCCs depend on government subsidies for continuingoperation and thus, they are contributory to the consolidated public sectordeficit. For those GOCCs that have the resources to engage ininfrastructure development and can borrow from the capital markets, thegovernment should ensure good corporate governance, transparency, andabove-board procurement procedures apart from effectively dealing withpotential contingent liabilities arising from sovereign guarantees that maybe demanded by lenders. A line of thinking currently going amonggovernment bureaucrats is that a joint venture between a governmentcorporation or agency and the private sector in the development, provision,and financing of infrastructure facilities, e.g., transport facilities, may bean alternative approach. There are no clear policy and operational

24 A Review of Build-operate-transfer for Infrastructure Development

Page 32: Areview of BOT for Developing Project

guidelines on the formation of joint venture with the private sector and itseems that each agency is left to define and implement joint ventureapproaches. A joint venture is inferior to transparent and competitiveprocurement processes and should be carefully scrutinized by the oversightagencies and policymakers (elected officials) with the end in view ofproviding clear guidelines to government agencies intending to adopt thisparticular approach to infrastructure provision.

The decision to invest in infrastructure is an endogenous variablethat is influenced by both technocratic and political forces. Governmentsometimes make the myopic decision of making across-the-board cuts incapital expenditures, which include infrastructure investments withoutdue regard for the productivity loss implications of severe cutbacks. Thisis usually done during times of fiscal stress when adjustment policies woulddictate cuts in government spending. The most expedient spending itemfor a cutback is capital expenditures since governments usually succumbto political pressure to avoid layoff of personnel. The risk posed byindiscriminate cutbacks in capital expenditures is that the cutback mayhave deleterious impact on the economy’s productivity, especially privatesector productivity, in the long run. The other complicating factor is notjust the efficiency impact of cutbacks in capital expenditures but also theequity aspect of the exercise. Should the reduction in the budget for roadsbe applied equally or differentially across regions? Should poorer regionsbe made to suffer the same proportionate cutback in road expenditures?Should the richer region be spared because infrastructure spending hasto be supported in those areas in view of agglomeration and dispersionforces, which to a large extent determine the spatial distribution ofeconomic activity? What parameters are used to make the decision tocutback in particular locations?

In this regard, the government has the following immediate tasks,among others: (a) expand its narrow fiscal space by improving the taxeffort, eliminating inefficiencies in government procurement proceduresand implementation, and combating graft and corruption; (b) reducepolitical risks and uncertainties which either avert potential private sectorinvestments or delay the implementation of vital infrastructure projects;and (c) establish a policy environment that promotes and upholdscompetition as the rule in infrastructure provision, with the possibility ofadopting alternative approaches but subject to public scrutiny; and (d)provide a regulatory framework that safeguards both consumer welfareand investor interest.

Llanto 25

Page 33: Areview of BOT for Developing Project

Subsectoral dimension

Transport subsectorConsidering the archipelagic geography of the Philippines, a fullyintegrated transport system plays a very important role in facilitatingeconomic activities and integrating local economies. The Philippinetransportation network includes roads, bridges, airports, ports, and rail,with the Department of Public Works and Highways (DPWH) for nationalroads and bridges and the Department of Transportation andCommunications (DOTC) for airports, ports, and rail as implementingagencies.

The Philippines’ transport system relies heavily on the road network,which handles about 90 percent of the country’s passenger movement andabout 50 percent of freight movement (MTPDP 2004–2010). The existingroad network provides the most common means of transporting passengersand economic goods within the islands as well as interisland using therecently inaugurated RORO shipping facilities under the Strong RepublicNautical Highway. Water transport links the numerous islands of thearchipelago. The government has recently promoted the RORO transportbetween major islands. A light rail transport system is presentlyconcentrated in the Metro Manila area while a partially functioning heavyrail system operates a few kilometers outside Metro Manila. A string ofdomestic ports and airports forms the remaining components of thenetwork of transportation infrastructure to major economic centers in thecountry.

Under the MTPDP 2004–2010, transport infrastructure is envisionedto provide easier access to local and international markets, enhance peaceand order in conflict-affected areas, strengthen national unity, familybonds, and tourism, and facilitate the decongestion of Metro Manila.

RoadsPhilippine roads are categorized into public roads, toll roads, and privateroads. Private roads comprise an undetermined length of roads. Theseare roads commonly constructed and financed by large private propertydevelopers. Public roads, as the name implies, are roads that areadministered, rehabilitated, and maintained by the government. As of2004, the total length of the Philippine nontoll road network, regardlessof condition, was reported at 202,860 kilometers.15 Compared to other__________________15 World Bank website. Transport in the Philippines. http://go.worldbank.org/7T9R5GE2Q0.

26 A Review of Build-operate-transfer for Infrastructure Development

Page 34: Areview of BOT for Developing Project

ASEAN countries, the Philippine road network is relatively extensive(World Development Indicators 2006). Density is relatively higher thanIndonesia’s 0.19 kilometer and Malaysia’s 0.28 kilometer but lower thanSingapore’s 4.72 kilometer for the year 200316 (Figure 7).

Public roads are categorized into national roads, provincial roads,city or municipal roads, and barangay roads. As of July 2007, there is atotal of 29,288 kilometers of national roads nationwide.17 Of this nationalroad network, 70 percent are paved (13,023 km concrete and 7,525 kmasphalt) although only 49 percent are in good condition. National roadsaccount for 12 percent of the total public road network while barangayroads cover more than half.18

Toll roads, also known locally as “tollways” are roads where a userpays a fixed fare or toll fee in exchange for passage or use of the road. Asof 2008, the Philippines has a total of six toll road networks measuring atotal of 261.67 kilometers (Table 2).

__________________16 International Road Federation. 2006. World Road Statistics.17 DPWH website. Infrastructure Statistics. July 2007.18 Infrastructure chapter of the Medium-Term Philippine Development Plan, 2004–2010, NEDA.

Source: World Development Indicators 2006.

Figure 7. Comparative road network of selected ASEAN countries, 2000–2004

Llanto 27

Page 35: Areview of BOT for Developing Project

For public roads, the construction and maintenance of national roadsand bridges rest with the DPWH.19 Local roads, i.e., provincial, city/municipal, and barangay roads, are administered by the respective LGUs.20

A small number of farm-to-market roads falling under the category ofbarangay roads, which are mostly foreign ODA-funded roads areadministered by the Department of Agrarian Reform (DAR) and theDepartment of Agriculture (DA). The Toll Regulatory Board (TRB)regulates and supervises toll roads. Private owners, i.e., subdivisions andother residential villages, maintain private roads.

The major policies on the Philippine road sector are found in thefollowing laws:

Republic Act 917 or the Philippine Highway Act of 1953 providesthe framework for effective highway administration and theclassification of roads into national, provinces, cities, andmunicipalities for administration and funding purposes. Thebarangay classification was added through Executive Order 113(1955) as modified by Presidential Decree 702 in 1975.

__________________19 Pursuant to Executive Order No. 124 dated January 30, 1987, the DPWH is mandated toundertake (a) the planning of infrastructure such as roads and bridges, flood control, waterresources projects, and other public works and (b) the design, construction, and maintenanceof national roads and bridges and major flood control systems.20 Pursuant to RA 7160 or the Philippine Local Government Act of 1991.

Table 2. Philippine toll road network, 2008

Name Length (km) Coverage

North Luzon Expressway (NLE) 83.2 Metro Manila and the provinces of Pampanga andBulacan

South Luzon Expressway (SLE) 42.9 Metro Manila and the provinces of Batangas,Laguna, and Cavite

Metro Manila Skyway (MMS) 13.5 Elevated portion of the SLE from Buendia to Stage 1 BicutanRadial Road 1 (R-1) Expressway, 6.2 Cavite and Manila Manila-Cavite (Coastal Road)Southern Tagalog Arterial Road 22.1 Sto. Tomas, Batangas to Batangas City (STAR) expresswaySubic-Clark-Tarlac Expresswaya 93.77 Zambales, Pampanga, and Tarlac

a The Subic-Clark-Tarlac expressway was inaugurated on March 19, 2008 and was opened on April 18, 2008.

28 A Review of Build-operate-transfer for Infrastructure Development

Page 36: Areview of BOT for Developing Project

Land Transportation and Traffic Code of 1964 (RA 4136) providesfor the rules on road use.Republic Act 8794 imposes a motor vehicle user’s charge onowners of all types of motor vehicles, creates a Road Fund thatwill fund road maintenance including maintenance of local roadsand control of air pollution from motor vehicles.

There are several outstanding issues in the road sector. While thePhilippine road network is extensive, a large portion continues to be inpoor condition. As stated above, only 70 percent of the national roadnetwork is paved.21 The national road network is a mere 12 percent of thetotal public road network, with barangay roads mostly unpaved and inpoor condition covering almost more than half of the network. The bulk ofthe road network consists of roads that are devolved to LGUs. Segmentsof the road network have deteriorated over time because of the centralgovernment’s and LGUs’ neglect of basic road maintenance andunderinvestment in new roads. A major reason for rapid deterioration isthe poor construction of those roads. This is ironic because the budgetaryappropriation for roads is usually a sizeable amount. It seems that theproblem does not lie with insufficiency of funds for road maintenance. RA8794 created the Road Fund, a fund earmarked for the maintenance ofnational and local roads and the control of air pollution from motor vehicles.The Road Fund has accumulated to a substantial amount since thecollection of a motor vehicle user charge (MVUC) from motor vehicleowners started on May 2001. Available data from the Road Board showMVUC collections from May 2001 to April 2005 of around PhP22.6 billionon a cumulative basis. The Land Transportation Office forecasts that totalvehicle registration will grow at an average rate of 3 percent per annumand, thus, around PhP44.5 billion of MVUC collections are expected fromthe period 2005–2010. The principal problem lies with the administrationand efficient utilization of the Road Fund.

The uncoordinated road works, e.g., excavation, digging, paving,reblocking done by LGUs and various utilities in the urban centerscontribute to the deterioration of already poor road conditions. Thus, poorroad maintenance, poor traffic management, and uncoordinated andwasteful road works produce the daily road congestion in many urbanroads especially in Metro Manila. Notwithstanding the so-called Unified__________________21 Paved roads refer to the length of all roads that are surfaced with crushed stone (macadam)and hydrocarbon binder or bituminized agents with concrete or with cobblestones.

Llanto 29

Page 37: Areview of BOT for Developing Project

Vehicular Volume Reduction Program (UVVRP) being implemented bythe Metro Manila Development Authority (MMDA), Metro Manilanscontinue to suffer from terrible road congestion and air pollution.22 A studyconducted by the Japan International Cooperation Agency (JICA) revealedthat the average bus travel speed along Epifanio delos Santos Avenue(EDSA) is only 15 kilometers per hour. One bus trip averaged two hoursand five minutes along a 12-kilometer stretch from Magallanes Village inPasay City to East Avenue in Quezon City at an average speed of 14 to 15kilometers per hour (JICA 1999).

RailRail transport systems provide land-based alternatives to road transportand are also expected to cut down road traffic congestion and air pollution,reduce travel times, and ultimately spur economic growth. The Philippinerailway system can be divided into two; heavy rail and light rail. Theheavy rail system is operated by the Philippine National Railways (PNR).23

The PNR network consists of two main rail lines; the North Main Line(Northrail) and the South Main Line (Southrail). Northrail is a 266-kilometer line stretching from Manila to San Fernando City in La Unionwith a 55-kilometer branch line from Tarlac City to San Jose, Nueva Ecijaand various nonoperational branch lines. On the other hand, Southrail isa 479-kilometer line from Manila to Legazpi City in Albay, with a 5-kilometer branch line from San Pedro, Laguna to Carmona, Cavite andtwo other branch lines connecting Calamba to Batangas City and SantaCruz, Laguna. A commuter service line (about 46 kilometers) also runsfrom Caloocan to Carmona. The total rail network consists of 1,060kilometers but only the 479-kilometer Southrail is operational. Northboundrail services ended in the late 1980s and no direct connection currentlyexists between Northrail and Southrail. At present, the Northrail is beingrehabilitated through a loan from the Chinese government.

Light rails move large numbers of people efficiently and reduce roadcongestion, air pollution, and travel cost. The development of a light rail

__________________22 The MMDA was created by virtue of RA No. 7924 dated March 1, 1995 to complement theefforts of the Metro Manila LGUs in providing metro-wide services within Metro Manila including(1) development planning; (2) transportation and traffic management; (3) solid waste disposaland management; (4) flood control and sewerage management; (5) urban renewal, zoning,land use planning, and shelter services; and (6) health sanitation, urban protection and pollutioncontrol, and public safety.23 PNR is a government corporation created by virtue of Congressional RA No. 4156 dated June20, 1964.

30 A Review of Build-operate-transfer for Infrastructure Development

Page 38: Areview of BOT for Developing Project

system in Metro Manila was envisioned to provide two main benefits: (a)it will make available an alternative and efficient means of transportationto the already traffic-stricken metropolitan area and (b) to some extent, itwill help address rapid urban migration and decongestion problem in MetroManila by encouraging people to reside outside of the metropolitan areain places such as Laguna, Batangas, and Cavite with the assurance of anefficient, reliable, and accessible light rail system that they can use in thedaily commute from residence to the workplace and vice versa. ThePhilippine light rail system is administered by the Light Rail TransitAuthority (LRTA).24 Metro Manila has three light rail transit (LRT) lines,LRT line 1, LRT line 2, and the Mass Rail Transit (MRT3) along EDSA,the main road connecting the cities of Manila, Makati, Mandaluyong, Pasig,and Quezon in the metro area.25 An ongoing construction will link QuezonCity to Caloocan City, thereby, connecting these last two segments of thelight rail system and completing the loop (running from the cities of Pasay,Manila, Caloocan, Quezon, Mandaluyong, Pasig, Makati back to Pasay).

The Light Rail Transit line 1, “LRT 1” or simply “LRT,” is a 15-kilometer elevated rail system running from Baclaran, Parañaque City toMonumento, Caloocan City through 18 stations or strategic transport hubs.The LRT has been in operation since 1984 and is considered to be the firstLRT system in Southeast Asia. Average daily ridership is estimated at300,000 passengers. LRT line 2, also known as the “Megatren” or “LRT 2,”is a 13.8-kilometer mass transit line from Santolan, Marikina City to Recto,Manila traversing five cities in Metro Manila (Pasig, Marikina, QuezonCity, San Juan, and Manila) through 11 stations along the majorthoroughfares of Marcos Highway, Aurora Boulevard, Ramon MagsaysayBoulevard, Legarda, and Recto Avenue. The Megatren has been inoperation since 2004. Average daily ridership is estimated at 130,000passengers. Mass Rail Transit (LRT 3, “Manila Metro Rail Transit System,”“Metrostar Express,” “Metrostar,” or simply “MRT”) is a 16.8-kilometerrail line along EDSA. The 13-station line commences at Taft Avenue andends at North Avenue serving the cities of Makati, Mandaluyong, Pasay,Pasig, Quezon, and San Juan. The line is mostly elevated with some

__________________24 LRTA is a wholly owned government corporation created on July 12, 1980 under ExecutiveOrder No. 603, as amended by EO No. 830, dated September 1982 and EO No. 210 dated July7, 1987. The LRTA is primarily responsible for the construction, operation, maintenance, and/orlease of light rail transit systems in the Philippines.25 Sources of information in this section: Light Rail Transit Authority, Metro Rail Transit Corporation,and the Department of Transportation and Communication.

Llanto 31

Page 39: Areview of BOT for Developing Project

sections at grade or underground level. The Metro Rail system is designedto carry in excess of 600,000 passengers per day and 200 million passengersa year initially and is expandable to accommodate over 900,000 passengersper day and 300 million passengers per year. Average daily ridership isestimated at 400,000 passengers. With the high fare for bus and jeepneyride that has been brought about by the high cost of petroleum products,train utilization is becoming intensive notwithstanding the rundown andunsafe facilities of the heavy rail system. The light rail system offers amodern and efficient transport system for metro commuters and it isexperiencing increasing utilization due to the shift to mass rail transportbecause of the high cost of petroleum products. However, maintenanceproblems have begun to appear in the different line segments of the lighttransit system because of lack of funds for maintenance, inefficientmaintenance, and simple bureaucratic neglect.

The MRT is privately owned and operated by Metro Rail TransitCorporation (MRTC) and was constructed under a build-lease-transfercontract. Under the arrangement, the DOTC operates the MRT directlyand pays an annual lease fee to MRTC. Commencing operation in 1999,the MRT is part of government’s strategy to alleviate the chronic trafficcongestion along the EDSA corridor.

Various interchange links are also established among the LRT Line1, LRT Line 2, and MRT Line 3. Moreover, food and drink stalls are locatedin the concourse of most LRT/MRT stations with some stations providingrentable spaces for shopping (clothes, shoes, bags, cellular phones,electronic load, phone accessories, magazines, jewelry, etc.) and popularservices (internet, automatic teller machines, etc.). Some stations, suchas EDSA Taft, Central Terminal, Araneta Center-Cubao, and Ayala Makatiare directly connected to or are near shopping malls and other largeshopping areas, which have generated various business activities forcommuters and shoppers alike.

Strong Republic Transit SystemIn 2003, the Strong Republic Transit System (SRTS) was launched by thegovernment with the objective of providing a reliable, seamless, andintegrated mass transit system that would be at par with very good transitsystems in the world. In a nutshell, the program involves the following:

construction of seven interconnection facilities or links tophysically integrate the existing LRT/MRT lines and provideconvenience to the LRT/MRT riding public;

32 A Review of Build-operate-transfer for Infrastructure Development

Page 40: Areview of BOT for Developing Project

rehabilitation and extension of the LRT Line 1 to Cavite (southend);extension of MRT from North Avenue, Quezon City toMonumento, Caloocan City;26

rehabilitation of the Philippine National Railways; anddevelopment of a unified fare system using “ContactlessSmartCard Technology” to facilitate easy transfer of passengersbetween the existing lines.

Under the SRTS, the existing lines have been color-coded for purposesof uniformity and ease of recall (similar to rail systems of Japan, SouthKorea, etc.) as shown in Figure 8.

In support of the SRTS and to enhance the delivery of train services,the institutional framework of the sector is presently under review. Theobjective is to separate the policy, planning, and regulation functions fromthe delivery of train services.27 In particular, the plan is to merge thePNR and LRTA into a Track Authority that will own the right-of-way andinfrastructure facilities. The private sector can operate and maintain thedifferent lines under this model. A Strategic Rail Authority/Office in DOTCis envisioned to carry out policy/strategy and regulatory functions.However, it seems that there is no progress in the envisaged reforms,which have remained as plans. Meanwhile, only the extension of MRT3(Metrostar) from North Avenue to Monumento is making real, albeit slow,progress.

A number of issues impacts on the sector’s efficiency. PNR suffersfrom chronic operating deficit and has depended on government subsidiesfor its operations. The proposed PNR privatization plan has not yet beenimplemented. The routes for the heavy rail system are single-track (exceptin Metro Manila) and were built to the “Cape Gauge” of 1067 mm (3 feet 6inches), which is a narrow gauge standard resulting in lateral instabilityand poses problems for high-speed operation. Thus, the maximumallowable speed is 50 kilometers per hour.28 The rolling stocks, stations,and systems (including signaling and ticketing systems) are antiquated,

__________________26 As mentioned earlier, there is an ongoing construction for this segment of the light rail transitsystem.27 National Economic and Development Authority, Medium Term Philippine Development Plan,2004–2010.28 Wikipedia.org, Philippine National Railways.

Llanto 33

Page 41: Areview of BOT for Developing Project

inefficient, and substandard in comparison to international benchmarkswith consequent safety and security risks. The perennial problem ofinformal settlements along the rail tracks has remained unsolved.29

For the light rail sector, security and safety though controlled shouldbe continuously monitored. Thus far, since its operation in 2004, therehas been only one casualty reported at the MRT Line 3 while four isolatedcasualties were reported for LRT Line 1. The main issues here are (a)slow progress made in linking North Avenue, Quezon City to Monumento,Caloocan City, a mere five-kilometer stretch;30 (b) insufficient capacityand number of coaches which is felt especially during rush or peak hours,causing stress on many passengers; and (c) interruption of operations due__________________29 With the exception of a few kilometers running along Makati City and some portions of theNorthrail line where informal settlers have been moved to government housing projects.30 The link was inaugurated on February 2010 but is not yet operational.

34 A Review of Build-operate-transfer for Infrastructure Development

Figure 8. Strong Republic transit system

Notes:Old Name New NameLRT Line 1 / Metrorail Yellow LineMRT Line 2 / Megatren Purple LineMRT Line 3 / Metrostar Blue LinePNR Northrail Green LinePNR Southrail Orange Line

Page 42: Areview of BOT for Developing Project

to mechanical and or electrical failure especially during adverse weatherconditions since there is no dedicated power source for the light rail system.

AirportsThe liberalization and deregulation of the Philippine civil aviation industryin 1995 was envisioned to be a catalyst for economic growth bytransforming the Philippines into a major transport and logistics hub inthe Asia-Pacific region. Since then, however, the industry has onlyresponded with gradual and few significant developments. Domestically,it has accomplished the following:

Promotion of competition which resulted in an increase in thenumber of domestic airline operators, decrease in airfares, andimprovement in the quality of service and efficiency in theindustry in general.Development of niche markets and segmentation of the marketinto (1) major routes where traffic demand is heavier (more than20,000 passengers annually) and serviced by the relatively biggerairlines (Philippine Airlines [PAL], Cebu Pacific, and AirPhilippines) and (2) minor, short-distance routes (also referredto as secondary, tertiary, or missionary routes) where trafficdemand is lighter and serviced by smaller airlines and aircrafts(Asian Spirit and South East Asian Airlines or “SEAir”) [Manuela2005].Increase in passenger and freight volume and attraction of newinternational carriers with the opening of international gatewaysin Cebu (Visayas), Davao (Mindanao), and Clark, Pampanga(Luzon) as well as the servicing of otherwise “missionary routes”by smaller airlines.Execution of Air Service Agreements (ASAs) with Taiwan andHong Kong in 1996, which allowed the sixth freedom rights—the right to carry passengers between two foreign countries bystopping or connecting in the home country.

The Philippine domestic airline industry is currently dominated byPAL. In terms of traffic, the number of passengers carried indicates anincreasing trend from the period 2001–2005 (Figure 9) [World Bank 2006].

Compared to other countries, the Philippines ranks 34th in terms ofnumber of passengers carried following Singapore (23rd), Thailand (22nd),Hong Kong (21st), Malaysia (20th), Indonesia (16th), and Korea (14th) [IMD2007].

Llanto 35

Page 43: Areview of BOT for Developing Project

As of 2005, the Philippines has a total of 203 registered airportsbroken down into private airports (118) and national airports (85) (Table3) [NSCB 2006]. National airports are classified by the Air TransportationOffice (ATO) into (a) primary (regular) and secondary (alternate)international airports; (b) major commercial domestic airports (“trunkline”airports); (c) minor commercial domestic airports (secondary airports);and (d) feeder airports. At present, there are a total of eight internationalairports and 77 domestic and feeder airports strategically located in themajor economic hubs nationwide.

The birth of Philippine civil aeronautics began in 1931 with thepassage of Legislative Act No. 3909 providing for the creation of an officeunder the Department of Commerce and Communications to handle theenforcement of rules and regulations governing commercial and privateaviation. This was followed by the passage of Commonwealth Act No. 168(the Civil Aviation Law of the Philippines) in 1936, which created theBureau of Aeronautics to promulgate Civil Aviation Regulations, and ofRepublic Act No. 776 (Civil Aeronautics Act of the Philippines) in 1952,which reorganized the Civil Aeronautics Board (CAB) and the CivilAeronautics Administration (predecessor of the Air Transportation Office).

In the 1990s, the government liberalized the airline industry underExecutive Order (EO) 219. In particular, the EO provided for the removal

Source: World Development Indicators (2006).

Figure 9. Air transport passengers carried

36 A Review of Build-operate-transfer for Infrastructure Development

Page 44: Areview of BOT for Developing Project

of restrictions on routes, fares, and flight frequencies as well as governmentcontrol on routes, flight frequency, fares, and charges.

At present, there are two key agencies involved in the administrationof the Philippine air transportation sector. These are the ATO and theCAB. The ATO is mandated pursuant to EO 125/125A to implement policieson civil aviation to assure safe, economic, and efficient air travel. On theother hand, the CAB administers the economic regulation of the industry,in particular, regulating capacity, flight frequency, and airfare in theinternational air transport sector and is also in charge of the issuance ofoperating permits, airline service route approvals, and review/approvalof airfares in single-airline markets. There is a proposed legislative billconverting the ATO into a corporate body while an independent oversightunit to handle economic regulation and safety concerns and an independentaccident investigation group will be established within the DOTC.31

Table 3. Philippine registered airports, 2005

Classification Description Number Location

Regular Utilized for the operation of 4 Ninoy Aquino International Airportinternational aircrafts engaged in international (NAIA)

air navigation Subic International AirportClark International Airport(Diosdado Macapagal InternationalAirport)Mactan-Cebu International Airport

Alternate Utilized for the operation of 4 Laoaginternational aircrafts engaged in international Zamboanga

air navigation in lieu of the regular Davaointernational airports General Santos

Trunkline Utilized for the operation of 12 Nationwideaircrafts engaged in internationalair navigation in lieu of the regularinternational airports

Secondary Serving principal towns and cities 36 Nationwidewith regular traffic densities

Feeder Serving towns with limited 29 Nationwidepassenger traffic and are intendedfor use by piston aircrafts

Total 85

__________________31 National Economic and Development Authority, Medium Term Philippine Development Plan2004–2010.

Llanto 37

Page 45: Areview of BOT for Developing Project

Some outstanding issues impact on the efficiency of the airportinfrastructure sector. The biggest outstanding issue is the unresolvedsituation of NAIA International Passenger Terminal 3 whose finalresolution is awaited by the public and private investors alike. Theuncertainty over this issue has somewhat dampened investor interestbased on various accounts in the popular media.32

Another issue is the lack of adequate funds which delays thenecessary upgrading and improvement of existing airport facilitiesincluding the provision of the necessary lighting and navigationalequipment to allow 24-hour operations (Carlos 2007). Inadequatemaintenance and the lack of investments in facilities, lighting, andnavigational equipment have contributed to the failure to meetinternational standards on safety, passenger comfort, and ease oftransaction and maximize the full potential of the airports.

PortsPorts handle a wide variety of goods that are critical to the economyincluding petroleum, food, pharmaceuticals, machineries, and many others.An efficient and effective port system is therefore essential to thePhilippines, an archipelagic country. As of 2005, there are 414 registeredports nationwide, more than half of which (222) are privately owned. Theremaining 192 public ports are classified as base ports, terminal ports,and other national or municipal ports (Figure 10) [NSCB 2006].

In terms of cargo traffic, the consistent upsurge of foreign cargoesfrom 2004–2006 was not able to raise overall cargo output due to slowdownin domestic cargo shipments (Figure 11).33 Port passenger traffic likewisedeteriorated during the same period due to port inefficiencies, concernsabout safety, and competition by other means of transportation (Figure12). The port of Manila ranked 31st among the top 50 worldwide in the2005 World Port Rankings in terms of container traffic with a total of2,665 TEUs.34 The Philippines is way behind other ASEAN ports in thetop 50 list: Singapore (1st), Hong Kong (2nd), Busan, South Korea (5th),Port Klang, Malaysia (14th), Tanjung Pelepas, Indonesia (19th), LaemChabang, Thailand (20th), and Tanjung Priok, Indonesia (24th).

__________________32 This issue is discussed in section 4.33 Philippine Ports Authority, Port Performance 2006.33 World Container Port League 2005 (Top 50), Containerisation International Yearbook, 2005.

38 A Review of Build-operate-transfer for Infrastructure Development

Page 46: Areview of BOT for Developing Project

Philippine Nautical Highway System/Strong Republic NauticalHighwayIn 2003, the Philippine government launched the Strong Republic NauticalHighway (SRNH) program. This involves the upgrading of existing portsto facilitate a road roll-on roll-off (RORO) terminal system (RRTS). TheSRNH intends to connect the islands of Luzon, Visayas, and Mindanaoand induce more economic activities through the improved connectivityof local markets. Executive Order 170 and subsequent issuancesestablished the policy that the RRTS should be integrated into the nationalhighway system (Figure 13).

Figure 10. Philippine ports as of 2005

Figure 11. Total passenger traffic, 2005

Llanto 39

Page 47: Areview of BOT for Developing Project

Figure 12. Total cargo throughput in MT, 2000–2006

Figure 13. Roll-on roll-off terminal system

Source: Philippine Ports Authority

Specifically, the SRNH aims to:reduce the cost of interisland transportation through the use of asafe, efficient, and cost-effective roll-on roll-off system;

40 A Review of Build-operate-transfer for Infrastructure Development

Page 48: Areview of BOT for Developing Project

support the agriculture and fisheries modernization and foodsecurity programs of the government;enhance tourism, transportation, and commerce throughout thecountry; andencourage private sector participation in the establishment,construction, and operation of RRTS facilities.

With RORO facilities, offloading and reloading of cargoes andshipments would no longer be necessary. Handling time and stevedoringcosts are reduced and goods reach markets sooner, with better qualityand at a lower cost of transportation.

To date, the nautical highway has already connected Luzon todifferent islands such as Mindoro, Panay, Guimaras, Negros, andMindanao. However, recent study has pointed out a current problem inRRTS operation. Various parties view the RORO vessel operation andRORO terminal operation in the Philippines as separate and distinctactivities with the government through the Philippine Ports Authority(PPA) or the local governments providing port services while the privatesector supplies the vessels and transport services. From the efficiencystandpoint, however, these seemingly separate operations are really partof an integrated system, which requires coordination and consistentoperation. For any defined route, the two operations are actuallyinterdependent and complementary investments (one cannot operatewithout the other) and there is merit in “bundling” both into a singlebusiness if integration proves to be viable. A study of the Bicol Mainland-Masbate-Cebu connections finds that an integrated operation is financiallyviable offering sufficient returns to attract private sector interest not justin vessel but in port operations as well (Alonzo et al. 2007).

There are also significant policy and institutional issues that haveto be addressed to improve RRTS (Alonzo et al. 2007). The governmenthas to consider the separation of the RRTS from the regular ports operatedby either the Philippine Ports Authority or the Cebu Ports Authority (CPA).Most of the existing RRTS connections today have terminals within thejurisdiction of PPA (CPA in the case of Cebu province) with the contractsbetween PPA and the arrastre companies still in force. This is why despiteEO 170, the PPA has to share with the arrastre companies a part of theterminal fees. There is a need to view RRTS differently from the regularshipping and port operations. There should be no cargo handing in theRRTS; only the terminal fee and the passage fee have to be paid for sothat the seamless travel for vehicles and passengers can be achieved.

Llanto 41

Page 49: Areview of BOT for Developing Project

Because the RRTS is rightly part of the highway system, anotherimportant issue is to resolve which government body should regulateRRTS. At present, this is an institutional gap, which both the MaritimeIndustry Authority (MARINA) and the PPA are trying to fill. MARINA’srole is to assure the safety and seaworthiness of RORO vessels while thePPA is in charge of either leasing out the port terminals to private operatorsor managing the ports.

The PPA regulates the port industry. Pursuant to EO 159 issued in1987, the PPA is mandated to establish, develop, regulate, manage, andoperate a rationalized national port system in support of trade and nationaldevelopment. PPA is also tasked to undertake all port construction projectsunder its port system.

The PPA operates the biggest common-user ports in the Philippines/Manila through long-term private concessions. These ports are the SouthHarbor (for international cargo), the Manila International ContainerTerminal (MICT), and the North Harbor (for domestic traffic). Themanagement of fishing ports and wharves is handled by anothergovernment entity, the Philippine Fisheries Development Authority(PFDA) while other public ports are municipal/city ports, which areoperated and owned by the respective LGUs.35

Four other independent port authorities operate within the PhilippinePort System. These are:

Cebu Port Authority for the operation of the Cebu Port;Subic Bay Metropolitan Authority (SBMA) for the operation ofthe Subic freeport;Bases Conversion Development Authority (BCDA) for theoperation of the San Fernando Port in La Union; andCagayan Economic Zone Authority (CEZA) for the operation ofthe Port Irene freeport.

The Medium-Term Philippine Development Plan (MTPDP) 2004–2010 has identified some key policy issues for the port sector as follows:36

restructuring of the port institutions to improve port service__________________35 PFDA is a government-owned and -controlled corporation attached to the Department ofAgriculture and mandated to promote the development of the fishing industry through the provisionof postharvest infrastructure facilities and essential services that improve efficiency in the handlingand distribution of fish and fishery products and enhance their quality. This mandate is pursuantto EO 772 dated February 8, 1982 amending PD 977.36 National Economic and Development Authority, Medium-Term Philippine Development Plan(MTPDP) 2004–2010.

42 A Review of Build-operate-transfer for Infrastructure Development

Page 50: Areview of BOT for Developing Project

amendment of EO 170 to facilitate further expansion of the RRTScoverageprivatization of the remaining government-owned SRNH ROROports/terminalsderegulation of routes and rates to attract new players and tomake the maritime transport more cost-efficienta comprehensive review of the present port tariff system to pavethe way for a cost-based tariff systemmodernization of vessels through incentives pursuant to RA 9295,An Act Promoting the Development of the Philippine DomesticShipping, Shipbuilding and Ship Repair, and Ship Breaking,Ordaining Reforms in Government Policies Toward Shipping inthe Philippines and for Other Purposesthe establishment of a Maritime Equity Corporation of thePhilippines which will acquire modern RORO vessels that canbe leased to qualified operators under a lease purchase agreementtransfer of regulatory functions to an independent regulator (orregulators), which shall have jurisdiction over all portsamendment of the PPA Charter to address, among other things,the dual role of PPA as port regulator and operator

In addition to these are several outstanding issues in the port sector.37

These are summarized in Table 4.

PowerAgainst the backdrop of complaints by the business sector about the highcost of electricity which undermines competitiveness and the fiscal cost ofa deficit-ridden National Power Corporation (NPC), the Philippine powerindustry was restructured in 2001 by virtue of RA 9136 or the ElectricPower Reform Industry Act (EPIRA).

Broadly, the EPIRA was envisioned to: ensure a high quality, reliable,secure, and affordable electric power supply; encourage free and faircompetition; enhance the inflow of private capital into the sector; andbroaden the ownership base of power generation, transmission, anddistribution by:

__________________37 This section draws from Llanto, Basilio, and Basilio (2005) and Basilio, Llanto, and Rodolfo(2007).

Llanto 43

Page 51: Areview of BOT for Developing Project

Table 4. Issues on the ports sector and action taken

Issues in the ports sector Action taken by the government

PPA is the main port authority. Port EO 212 (s. 1994) was an attempt to liberalize andadministration is highly centralized. deregulate the ports sector through the privatization ofThere are inefficiencies in port public ports. However, the threat of labor (port workers)administration and operation. displacement paved the way for the nonimplementation ofPort dues, cargo handling rates are the EO. In 1997, EO 410 was issued rescinding EO 212.regulated by PPA. However, its EO 59 (s. 1998) was an attempt to transfer thecharter allows it to share 10–20 government monopoly of the port system to a privatepercent from cargo handling consortium without public bidding. This time, the businessrevenues. community opposed its implementation. In 2000, EO 308Port development and operation is was issued rescinding EO 59 and mandating competitiona government monopoly. Very few in the privatization of the Manila North Harbor.private ports are allowed to operate Emergence of other independent port authorities (asidecommercially. from the Philippine Ports Authority.) These include theRORO service was introduced. SBMA (Subic Freeport), CEZA (Port Irene), BCDA (PoroHowever, cargo handling charges Point), CPA (Cebu Ports), RPMA (ARMM ports), andwere levied even when no service Phividec (Mindanao Container Port Terminal). However,was provided. these IPAs offer little competition to PPA. In many cases,Cargo handling is a virtual monopoly they simply follow/adopt PPA rates and policies.in every port. Emergence of more private commercial ports like

BREDCO, Harbour Centre, etc.EO 170 (s. 2003) promotes private sector investment inthe operation of RORO ships as well as development ofRORO terminals (ports) as part of the Road-ROROTerminal System. In a span of only three years, moreports (private and public) have been established to formthe RORO links. Initial economic impact assessment ofRORO indicates that it has increased transport efficiency,reduced transport cost, promoted tourism and regionaltrade, enhanced agricultural productivity, and RORO portdevelopment served as a catalyst for area development.Port facilities and ships are required to undergo securityassessments in compliance with the provisions of theIMO-ISPS Code. The Office of Transport Security (OTS)was established to oversee.

separating the competitive from the monopolistic components ofthe industry such as generation versus transmission, distributionversus supply of electricity;unbundling the cost components of power rates to ensuretransparency and to distinguish the efficient utilities from theinefficient ones; and

44 A Review of Build-operate-transfer for Infrastructure Development

Page 52: Areview of BOT for Developing Project

promoting efficiency and providing reliable and competitivelypriced electricity while giving customers a full range of choices.

Thus far, a few reforms have already been achieved under the EPIRA:creation of the National Transmission Corporation (TransCo)creation of the Power Sector Assets and Liabilities ManagementCorporation (PSALM)establishment of a wholesale spot electricity market (WESM)unbundling of power ratesreview and renegotiation of the independent power purchasecontracts of NPC.

The Department of Energy (DOE) remains as the central energyplanning and policymaking body in the energy sector. The DOE ismandated to prepare, integrate, coordinate, supervise, and control allplans, programs, projects, and activities of the government relative toenergy exploration, development, utilization, distribution, andconservation.38

Aside from DOE, the Philippine National Oil Company and itsattached agencies as well as the National Electrification Administration(NEA) have remained as key institutions in the sector.39 Table 5 showshow the industry has been restructured.

The supply sector, which will be composed of wholesale and retailsuppliers, is still being established. The supply sector is regulated andparticipants would have to secure a license from ERC. Because theprerequisites for open access and retail competition have not yet been firmedup, the supply sector participants have not yet been formally identified.40

GenerationDespite the sector reforms, generation remains a regulated industry withNPC plants (and its IPPs) continuing to dominate the generation sector

__________________38 Pursuant to RA 7638 or the Department of Energy Act of 1992.39 RA 6038 dated August 04, 1969 provided for the creation of NEA. At present, NEA is mandatedto implement the government’s rural electrification program and to prepare the electriccooperatives to operate in a competitive electricity market by strengthening their technical,financial, and institutional viability.40 A NEDA source said that ERC is presently processing some of the applications.

Llanto 45

Page 53: Areview of BOT for Developing Project

(71%).41 NPC ownership is expected to give way to private ownership asthe privatization of generation assets picks up.

NPC, through its Small Power Utilities Group, also supplies 41electric cooperatives that are either not connected to the main grid islandsor located in remote areas.

TransmissionPower transmission in the Philippines is a regulated industry administeredby the Transmission Corporation (TransCo), a GOCC that assumed NPC’selectrical transmission functions (including planning, construction,centralized system operation, and maintenance of high-voltagetransmission facilities, grid interconnections, and ancillary services)beginning 2003 pursuant to the EPIRA. At present, the country has threehigh-voltage grids in Luzon, Visayas, and Mindanao but only two of which,Luzon and Visayas, are interconnected.

TransCo is mandated to link power plants to the country’s distributionutilities and electric cooperatives, which in turn deliver electricity to end-

__________________41 NPC was first established under Commonwealth Act No. 120 approved by Pres. Manuel L.Quezon on November 3, 1936 and reorganized pursuant to RA 6395 as amended. The Corporationhas evolved through the years responding to the mainstream needs of the economy and will continueto maintain its mandated functions until its gradual privatization as stipulated under the EPIRA.

Table 5. Restructuring of the power industry

Sector Activities Regulation Participants

Generation Production or generation Deregulated, open, NPC, IPPs, other private-of electricity and competitive owned plants

Transmission Transmission of electricity Monopoly but regulated. Transmission companyfrom the point of Rates subject to Energygeneration to the point of Regulatory Commissiondistribution (ERC) approval

Distribution Distribution of electricity Regulated. Requires Manila Electric Companythrough transmission national franchise. (MERALCO) and severalfacilities to end-users Rates subject to ERC distribution utilities (electric

approval cooperatives, privatecorporations, government-owned utility, or existing LGU)

Supply Sale, brokering, marketing Require ERC license.aggregate electricity to the Rates not subject toend-users ERC approval

46 A Review of Build-operate-transfer for Infrastructure Development

Page 54: Areview of BOT for Developing Project

users ensuring the reliability, adequacy, security, stability, and integrityof the grid. TransCo has approximately 21,319 circuit-kilometers oftransmission lines including a submarine cable system; considered thefirst of its kind in Asia; and 93 substations with approximately 24,310million volt amperes substation capacity.42

Due to imminent domain and right-of-way issues, the transmissionassets cannot be auctioned completely. Instead, the assets (gridinterconnections) and ancillary services are being offered through open,competitive bidding in the form of a 25-year concession with the possibilityof renewal for another 25 years. Under this arrangement, the governmentthrough PSALM, will retain the ownership of TransCo’s assets. Thewinning bidder will be responsible for improving, expanding, operating,and maintaining these assets, and operating any related business.

Because transmission is a regulated business the winning bidderwill be governed by the Grid Code and the Transmission DevelopmentPlan as approved by the DOE.43

DistributionThe distribution and sale of electricity to end-users is carried out by atotal of 142 distribution utilities. This is broken down into 119 electriccooperatives, 17 private investor-owned companies (including Meralco),and six local government-owned utilities.

The Luzon franchise area is dominated by the Manila ElectricCompany (MERALCO), a listed company traded on the Philippine StockExchange, which was established in 1903. At present, it has a franchisearea covering 9,337 square kilometers, 25 cities, and 86 municipalitieswhere the prime business districts and industrial estates are situated. Asof 2006, it has sold 25.1 billion kilowatt hours (kwh) of electricity to its 4.3million customers in the commercial, industrial, and residential sectors.44

The Visayas and Mindanao franchise area is largely made up ofelectric cooperatives, private investor-owned companies, and local

__________________42 Source: National Transmission Corporation.43 The National Grid Corporation of the Philippines (a consortium composed of Monte Oro,Calaca High-Power Corporation, and the State Grid of China) won as the concession for Transcoat US$3.95 billion on December 12, 2008. The required 25 percent upfront payment was alreadyreceived by PSALM last January 9 and 12, 2009. The National Grid Corporation will manageand control the transmission business with PSALM retaining ownership of the assets (Source:NEDA).44 Source: Manila Electric Company.

Llanto 47

Page 55: Areview of BOT for Developing Project

government-owned utilities connected to TransCo’s transmission (138–500 kV) or subtransmission (mostly 69 kV) systems.

Wholesale electricity spot market (WESM)Section 30 of the EPIRA provides for the establishment of a wholesaleelectricity spot market, which will provide the mechanism for determiningthe price of electricity not covered by bilateral contracts between sellersand purchasers of electricity. Since it is a spot market, electricity is tradedin real time. At the same time, as a wholesale market, it is open todistributors, directly connected customers, large users, and supplyaggregators.

The WESM aims to:provide incentives for the cost-efficient dispatch of power plantsthrough an economic merit order;create reliable price signals to assist participants in weighinginvestment options; andensure a fair and level playing field for suppliers and buyers ofelectricity wherein prices are driven by market forces.

The WESM, which was established in November 2003, is governedby an independent board of the Philippine Electricity Market Corporationand is jointly owned by the WESM participants. The Luzon marketoperations started in June 2006 while the Visayas market is still undertrial operation. The Luzon WESM began its operations at a time whenthe generation market (supply side) was dominated by government whilethe buyer side is dominated by MERALCO.

The vision is for WESM to evolve into a mature market, able to ensurethat there is adequate investment and security of supply, manage pricevolatility risks by avoiding excessive market power, and ensure that thereare adequate means of managing the exposures to price risks.

PrivatizationTo reduce the dominance of government in the generation as well as inthe transmission sectors, the EPIRA provided for the privatization of thetransmission and generation assets of NPC by the PSALM. Thus, PSALMis mandated to take ownership, manage, privatize, and dispose of allexisting generation assets, liabilities, real estate, and other disposableresources of NPC including its contracts with independent powerproducers. PSALM also administers the collection of the universal charge.

48 A Review of Build-operate-transfer for Infrastructure Development

Page 56: Areview of BOT for Developing Project

The proceeds from the sale of the generation and transmission assetsare expected to reduce consolidated debt to a more sustainable level andat the same time attract new private investments which otherwise possessgreater operational efficiency.

Thus far, PSALM has succeeded in privatizing a total of eight plantswith a combined capacity of 1,080 megawatts since 2003 despite somedifficulties.45 Five more plants are being firmed up for privatization byend of 2007: Calaca Coal-Fired Power Plant (600 MW), PalinpinonGeothermal Power Plant (192.5 MW), Panay (Dingle) Diesel Power Plant(146.5 MW), Tiwi Geothermal Power Plant (275 MW), and Mak-BanGeothermal Power Plant (410 MW).

As of 2006, the Philippines had a total installed generation capacityof 15,803 MW, slightly increasing from previous year’s 15,619 MW.46

The generation mix is fairly distributed among the various sourcesin terms of installed generating capacity with coal and diesel accountingfor the largest shares contributing 4,177 MW and 3,602 MW, respectively.This is followed by hydro plants, natural gas, and geothermal plants.Nonconventional plants (solar, wind, etc.) are slowly being developed toaugment the power requirements of the country.

In terms of actual generation, the Philippines generated a total of56.7 billion kilowatt hours of electricity in 2006. Renewable energy sourcesaccounted for 65 percent of the total generation with natural gas (alsobecause of its take-or-pay arrangements) contributing 16 billion kilowatthours or almost 29 percent, geothermal plants at 10.5 billion kilowatthours (18%), and hydro plants at 10 billion kilowatt hours (17%). Coalcontinues to be an important source of power generating 15 billion kilowatthours or 27 percent in 2006.

For missionary electrification, the Rural Electrification Program ofthe DOE envisaged to achieve 100 percent barangay electrification by2008 and 90 percent household electrification by 2017. As of 2006, thenational electrification level stood at 94.6 percent (39,671 out of the 41,945barangays).47

__________________45 Masinloc Power plant was bid out in December 2003 and was awarded to YNN Consortiumfor the purchase price of US$561 million. YNN Consortium, however, defaulted on its obligationto pay the 40 percent and Masinloc was bid anew and awarded recently to AES Corporation.Privatization of TransCo concession was also unsuccessful.46 Source: Department of Energy.47 Source: Department of Energy.

Llanto 49

Page 57: Areview of BOT for Developing Project

Despite the reforms set out under the EPIRA, several challengesstill remain. These are as follows:

Ensure the sustained financial viability of both NPC and PSALMhave to be put in place;Attract new investments in the power sector, especially newgeneration plants in view of a projected supply shortage in thenear future;Manage the WESM more efficiently;Fast track privatization, IPP administration to establishcompetitive atmosphere to reflect true cost of electricity; andReview and streamline the ERC process.

TelecommunicationsThe telecommunications industry in the Philippines began in 1905 withthe birth of the first telephone company in Manila. This was followed bythe establishment of the Philippine Long Distance Telephone (PLDT)Company in 1928, then under the ownership of the American investors. Itwas eventually bought out by Filipino investors in 1967. PLDT hasdominated the Philippine telecommunications services market until theliberalization of the sector in the 1990s, which provided for the entry ofcompetition, an increase in telephone service areas, and a wide range ofservice providers including cellular services. The latter eventuallyimprinted a remarkable growth throughout the country since itsintroduction in the late 1990s. Due to high maintenance and capitalinvestment requirements that the government cannot afford and consistentwith Philippine telecommunication policies, the private sector has takenthe lead in the provision of telecommunication services and in makingsubstantial investments in new technology.

The responsibility of maintenance and expansion of viable, efficient,and dependable communications systems as effective instruments foreconomic growth and development rests with the Department ofTransportation and Communication (DOTC).48 In particular fortelecommunications, the DOTC is supported by its attached agencies, theNational Telecommunications Commission (NTC) and theTelecommunications Office (TELOF).

In January 2004 the Commission on Information andCommunications Technology (CICT) was created as the “primary ICT

__________________48 As reorganized in March 1987 pursuant to EO 125, and 125-A.

50 A Review of Build-operate-transfer for Infrastructure Development

Page 58: Areview of BOT for Developing Project

policy, planning, coordinating and implementing, regulating, andadministrative entity” of the executive branch of the Philippine governmentrelieving the DOTC of this mandate.49 Accordingly, both NTC and TELOFreport to CICT.50

NTC remains as the sole body that exercises jurisdiction over thesupervision, adjudication, and control over all telecommunications servicesthroughout the country through the adoption and promulgation ofguidelines, rules, and regulations relative to the establishment, operation,and maintenance of various telecommunications facilities and servicesnationwide.51 The NTC is also responsible for radio spectrum managementand regulation of the activities of the broadcasting sector and is mandatedto collect regulatory fees for its supervisory and licensing activities. Onthe other hand, TELOF is tasked with providing telecoms services inmissionary areas or those areas that are not served by private sectoroperators.

There is also a proposed bill creating a Department for ICT to facilitatethe convergence of information technology and telecommunicationstechnologies with infrastructure development, education, health care, etc.

The major laws covering the industry are as follows:Republic Act 6849 dated December 21, 1989 provided for theinstallation, operation, and maintenance of public telephones ineach and every municipality in the Philippines.RA 7925, or the Public Telecommunications Policy Act of 1995,provided for the promotion of the development of Philippinetelecommunications and the delivery of public telecommunicationsservices. In particular, RA 7925 aims to promote universal access,competition, liberalization, and consumer welfare byinterconnecting all public telecommunications networks andallowing greater private sector participation.RA 8792, Electronic Commerce Act of 2000 covering all electronicdata message and electronic document used in the context ofcommercial and noncommercial activities to include domestic andinternational dealings, transactions, arrangements, agreements,contracts and exchanges, and storage of information.

__________________49 Pursuant to EO 269.50 The current administration later assigned NTC to be under the supervision of DOTC.51 Pursuant to EO 125-A of 1997.

Llanto 51

Page 59: Areview of BOT for Developing Project

EO 264 provided for the merger of the National IT Council andthe Electronic-Commerce Promotion Council into the InformationTechnology and Electronic-Commerce Council in 2000.

Service providers can be categorized into local exchange orinterexchange carrier services, international gateway facility services, longdistance services, and mobile services (Table 6).

The removal of monopoly and promotion of competition has resultedin an impressive improvement in teledensity (Figure 14). The number oftelephone subscribers has increased dramatically from the period 1992–1999 with the implementation of RA 7925. The advent of mobile technology,however, has slowed down the rate of subscription to fixed telephone linesbecause it provided the much-awaited access to telecommunication servicesat affordable levels.

Despite the promotion of competition, PLDT continues to dominatethe local (domestic) exchange carrier market, the interexchange (domesticlong-distance) carrier market, as well as the international gateway facility(international long-distance). For the domestic market, for instance,PLDT’s installed lines accounted for 41 percent of the total installed linesnationwide while its subscribed lines represent 55 percent of the totalsubscribed lines nationwide as of 2006.52 The remainder is divided amonga company called Innove (21% market share on installed, but only 9%

__________________52 National Telecommunications Commission, 2006.

Table 6. Telecommunications industry structure, 2002–2005

Service Providers 2002 2003 2004 2005

Local exchange carriers 74 73 73 73Interexchange carrier service 14 14 14 14International gateway facility 11 11 11 11Radio mobile

Cellular mobile telephone systems 7 7 7 7Public trunk repeater services 11 11 10 10

Value-added servicesCoastal 12 13 18 18Broadband 19 19 19 19With networks 186 249 292 351

Source: National Telecommunications Commission. Annual Report 2006.

52 A Review of Build-operate-transfer for Infrastructure Development

Page 60: Areview of BOT for Developing Project

subscribed) and other small, private, or municipal companies providingservices in various areas (Table 7).

The Service Area Scheme (SAS) policy obligated new entrants toinstall their own local exchange service infrastructure. In particular, underthe SAS, each operator was required to deliver within three to five years300,000 lines in various regions of the country to increase access to basicservices. This imposed capital costs, which were not fully recovered bythe telecommunications companies through the expected increase insubscription. The entry of the more accessible and affordable cellularmobile technology services and other product and service innovations hasgiven stiff competition to the traditional, fixed-line domestic and long-distance services.

The low cost of mobile handsets and the relatively cheap cost of shortmessaging service (SMS) have made mobile telecommunications morepopular than fixed-line in the Philippines. As of 2006, there are 42 millioncellular phone subscribers nationwide. The number of cellular phonesubscribers has been significantly increasing and the trend is expected tocontinue as incomes grow and as phone companies establish a wider andmore efficient cell network (Figure 15).

Compared to other ASEAN countries, the Philippine mobile marketis quickly catching up with the Indonesian and Korean markets. In 2005,Indonesia and Korea registered a total of 47 million and 38 millionsubscribers, respectively, while the Philippines registered a total of 35million subscribers (Figure 16) [World Bank 2006].

Figure 14. Teledensity

Llanto 53

Page 61: Areview of BOT for Developing Project

Due to mergers in the past ten years, the Philippine mobile marketis currently dominated by two players, namely, the PLDT-owned SmartCommunications (and Pilipino Telephone Corporation), which controls56 percent of the market and Ayala Group’s Globe Telecom (and IslaCommunications or Innove Communications) with 38 percent (Figure 17).53

Table 7. Distribution of subscribers per local exchange carriers, 2006

Operator Installed Subscribed Market Share Lines Lines Installed Subscribed

Bayantel 443,910 227,057 6.17 6.25Bell Telecom 489,000 271,000 6.79 7.46Digitel 653,616 431,366 9.08 11.87ETPI/TTPI 91,446 22,467 1.27 0.62Innove 1,507,197 329,908 20.94 9.08Philcom 213,236 53,098 2.96 1.46Piltel 236,561 46,202 3.29 1.27PLDT 3,009,791 2,006,773 41.81 55.23PT&T 129,000 14,193 1.79 0.39Other Operators 425,165 231,124 5.91 6.36Total 7,198,922 3,633,188 100.00 100.00

Source: National Telecommunications Commission 2006.

Figure 15. Cellular mobile technology subscribers

__________________53 National Telecommunications Commission, 2006.

54 A Review of Build-operate-transfer for Infrastructure Development

Page 62: Areview of BOT for Developing Project

Philippine mobile communications employ global system, a second-generation (2G) digital technology used by the majority of the worldmarket. The recent introduction of third-generation (3G) digital technologywill enable high-speed, high-bandwidth video applications in mobile phoneand is expected to spur further growth of the industry.

The liberalization of the sector in the 1990s and the subsequentmarket-oriented stance taken by NTC has yielded dividends in terms of agreater accessibility of telecommunications services by a growing numberof the population and a declining trend in telecommunications costs. Arecent report states that telecommunications reforms in the Philippineshas laid the foundations for a competitive market, which has improvedaccess of the public to an efficient means of communication and other IT-enabled services (EMERGE Quarterly Report 2007). An example of thedesire of NTC for a competitive market is a ruling that voice over internetprotocol (VOIP) is a value-added service and not a franchise. The dominanttelecommunications firms took the opposite side, that is, VOIP as afranchise. This ruling, which was first subjected to public hearings wherethe views of the different stakeholders were presented, has resulted to anincrease in VOIP providers and a decline in telecommunications costs.Telecommunications carriers are offering as low as five centavos perminute for overseas calls made using VOIP technology, an 87.5 percentdrop from the usual 40 centavos per minute. At least 17 firms have beengiven licenses to provide VOIP services.

Figure 16. Mobile phone subscribers, 2005

Llanto 55

Page 63: Areview of BOT for Developing Project

The same report indicated that the NTC has issued on December2005 a consultative document on the development of a competition policyframework for the information and communications technology sector.The NTC document cites the inequality in market power in the Philippinetelecommunications sector where the largest two among 73 local exchangecarriers account for 75 percent of the subscribers base while the biggesttwo cellular operators control 96 percent of the mobile service market.54

In 2004, the two largest carriers showed a net income of PhP39.2 billionagainst the net loss of PhP2.3 billion of the next two largest carriers. Whilethis extreme inequality in market shares and profit performance is notnecessarily caused by a lack of fair competition, the NTC points out thatit provides opportunities for anticompetitive behavior and, hence, groundsfor regulatory attention. For example, a large supplier who owns andcontrols essential facilities, i.e., so-called bottleneck facilities that are costlyto duplicate, can eliminate competition by constraining access of its rivalsto those facilities. Rivals need access in order to provide telecommunicationsservices to clients. The NTC further recognizes the advantages ofincumbents who are first movers in the market. Incumbents controlessential facilities and network standards and have vertically integratedfacilities that may be used to cross-subsidize services and engage inpredatory practices to ruin its competitors.

Figure 17. Number of cellular mobile telephone subscribers per provider, 2006

Source: National Telecommunications Commission 2006.

__________________54 Based on 2004 NTC Annual Report figures on subscription base.

56 A Review of Build-operate-transfer for Infrastructure Development

Page 64: Areview of BOT for Developing Project

Realizing the lack of effective competition in the market, the NTCconsultative document considered the introduction of four pro-competitionpolicies, namely: (a) imposing obligations on carriers with significantmarket power (SMP); (b) mandating local loop unbundling; (c) requiringcarriers to allow for resale of their services; and (d) changing the basis ofprice regulation from ex ante to ex post. An important component of SMPsis the development of an instrument that will address the problem ofinterconnection agreements between access provider and access seekerand the desire of public for relevant information on the subject. Thisinstrument is the set of guidelines on reference access offers (RAO).

The guidelines will require all authorized public telecommunicationsentities to submit to the NTC a RAO for certain access services. The RAOwill contain the terms and conditions for which an access provider isprepared to provide access to its telecommunications network or facilityto any requesting service provider. The end goal is to introduce morecompetition in the telecommunications market, which will further drivedown communication costs for the consumer and business sector.

Subnational dimensionBeing the second largest archipelagic nation in the world, the Philippineshas more than 7,107 islands with a total land area of 340,574.7 sqkilometers.55 Physically, three major islands divide the country into Luzonin the north, the Visayan Islands in the middle, and Mindanao in thesouth. Administratively, however, the country is subdivided into numerousregions, provinces, cities, and municipalities.

In terms of gross regional domestic product (GRDP), total GRDPincreased by 5.45 percent from the period 2005 to 2006.56 This increase isbrought about by the parallel growth across all the regions ranging from2.06 percent (Region IX) to as high as 7.25 percent (Region II) (Table 8).

__________________55 Based on 2005 estimated land area certified by the Philippine Lands Management Bureau.56 Similar to GDP, conceptually, there are three approaches for measuring Gross RegionalDomestic Product, namely, production approach, expenditure approach, and income approach.Production approach expresses GRDP as the total value of final goods and services producedby all production units in a region within a certain period (usually one year period.) Expenditureapproach expresses GRDP as the total of final demand components covering the consumptionexpenditure of households and private nonprofit institutions, government consumption, grossdomestic fixed capital formation, increase in stock and net export within a certain period. Incomeapproach expresses GRDP as the total income by production factors engaged in the productionprocess in a region. The income components of the production factors may take the form ofwages or salaries, land rent, capital interest, and profit margin. The profits include income taxand other direct taxes.

Llanto 57

Page 65: Areview of BOT for Developing Project

For 2006, the National Capital Region (NCR) continued to top theregional share to GRDP contributing PhP414 million (32%), followed byRegion IV-A Calabarzon (PhP157 million, 12%), and Region III CentralLuzon (PhP107 million, 8%). Meanwhile, the Autonomous Region ofMuslim Mindanao (ARMM), Caraga (Region XIII), and Cagayan Valley(Region II) contributed the least to total GRDP with 0.9 percent, 1.3 percentand 2.0 percent share, respectively.

With regard to financing, Table 9 shows the distribution of totalfinancial resources and internal revenue allotment in 2006 across regions.It is notable that NCR, CALABARZON (IV-A), and Central Luzon (III)have a larger share of total financial resources in the regions (Table 9).57

Expenditure-wise, the Commission on Audit (COA) reported thattotal expenditures for infrastructure amounted to PhP19.8 billion in 2005.58

__________________57 Pursuant to Section 285 of RA 7160 or the Local Government Code of 1991, LGUs shall havea share in the national internal revenue taxes.58 Source: COA 2005 Annual Financial Report for National and Local Government.

Table 8. Gross regional domestic product, 2005–2006 (at constant 1985 prices)

Region/Year 2005 2006 2005–2006 Per Capita% Growth rate GRDP 2006

Philippines 1,210,497,421 1,276,435,452 5.45 14,676NCR 387,751,888 414,292,958 6.84 37,855CAR 27,390,829 28,338,279 3.46 18,171I 35,927,006 38,136,691 6.15 7,982II 23,701,925 25,419,614 7.25 8,098III 102,428,717 107,385,259 4.84 11,442IVA 150,502,498 157,406,451 4.59 14,437IVB 33,740,765 34,526,488 2.33 12,690V 34,453,986 35,358,229 2.62 6,685VI 87,498,594 91,806,935 4.92 13,092VII 86,112,111 90,379,775 4.96 13,931VIII 26,663,453 27,979,058 4.93 6,819IX 31,971,822 32,631,502 2.06 10,136X 58,555,017 62,558,765 6.84 15,628XI 55,425,093 57,844,052 4.36 14,152XII 41,934,851 44,729,136 6.66 11,983ARMM 10,865,931 11,311,801 4.10 3,486XIII 15,572,937 16,330,459 4.86 6,912

Source: National Statistical Coordination Board (2007).

58 A Review of Build-operate-transfer for Infrastructure Development

Page 66: Areview of BOT for Developing Project

Almost half of the total amount (48%) was sourced from the LGUs. Forthe national government share, infrastructure expenditures were observedhighest in NCR (29.06%), Regions IV (15.56%), and III (11.00%), while itwas observed lowest for ARMM (1.73%).

Against total expenditures, however, expenditures in infrastructureare generally low, 6.5 percent for LGUs and 1.5 percent for nationalgovernment, which may explain the inadequate provision of localinfrastructure services in some regions (Table 10).

The lack of access to adequate infrastructure services can beattributed to the uneven pace of growth among regions in the Philippines,which is reflected in their respective contribution to GRDP and, to someextent, the relative size of financial resources available to the regions.ARMM, for instance, registered the lowest GRDP and ranked lowest interms of electricity, telephone connectivity, and road density as shownbelow. On the other hand, the NCR and the CALABARZON area in RegionIV, the fastest growing regions in the country, consistently top the rankingsfor access to basic infrastructure. However, it should also be noted that

Table 9. Regional financing, 2006

Region Total Financial IRA (PhP m) IRA per Capita Other SourcesResources (PhP m) (PhP m) (PhP m)

Philippines 103,548.70 48,204.70 554.25 2,222.00NCR 49,374.90 8,795.50 803.68 1,470.00CAR 2,170.20 1,717.60 1,101.03 9.00I 3,078.70 2,305.90 482.51 1.60II 3,333.50 2,400.40 764.95 -III 5,593.20 4,055.80 432.11 272.80IVA 7,043.00 4,096.70 375.71 301.00IVB 2,670.80 2,251.90 827.60 -V 3,493.90 2,817.60 532.63 -VI 4,270.40 3,187.00 454.44 -VII 4,314.60 2,542.50 391.94 16.50VIII 3,048.20 2,650.20 645.76 -IX 2,324.50 1,546.10 493.02 -X 3,398.80 2,081.40 519.96 151.20XI 2,502.00 1,813.30 443.57 -XII 2,509.10 1,971.80 528.21 -ARMM 2,409.00 2,232.60 688.01 -Caraga 2,014.10 1,738.60 736.07 -

Source: National Statistical Coordination Board (2006).

Llanto 59

Page 67: Areview of BOT for Developing Project

infrastructure capital would also have significant effects on regional orlocal productivity. Network infrastructure may have both positive andnegative spillover effects. The benefits of good infrastructure may be feltin areas or regions outside the region where it is located (positiveexternality) but the same infrastructure may also lead to negativeexternality when, due to mobile factors, a region with a good infrastructureendowment grows faster than its neighboring regions. It is able to attractmore investments and to stimulate more economic activity due tocentripetal or agglomeration forces.

The underprovision of local infrastructure services in some regionssuch as ARMM can also be attributed to underinvestment in infrastructurein the regions not only by government but also by the private sector. Notall LGUs have access to or have the capability to secure other means of

Table 10. Infrastructure expenditure (in thousand pesos), 2005

Source Infrastructure* Other Expenses Total Expenses % of Infrastructure (PS and other Expenditures MOOE) to Total

LGU 9,461,757.00 136,370,640.90 145,832,397.90 6.49Provinces 2,310,236.80 29,050,991.70 31,361,228.50 7.37Cities 2,453,942.00 55,314,421.90 57,768,363.90 4.25Municipalities 4,697,578.20 52,005,227.30 56,702,805.50 8.28NG 10,347,595.20 695,473,483.20 705,821,078.40 1.47NCR 3,007,366.20 517,207,675.60 520,215,041.80 0.58CAR 332,700.90 11,639,734.20 11,972,435.10 2.78I 355,785.60 6,007,453.60 6,363,239.20 5.59II 333,999.90 9,859,871.90 10,193,871.80 3.28III 1,138,812.60 20,444,121.50 21,582,934.10 5.28IV 1,610,178.50 24,701,786.30 26,311,964.80 6.12V 385,185.60 13,097,568.60 13,482,754.20 2.86VI 623,002.00 15,188,987.60 15,811,989.60 3.94VII 511,923.20 11,945,963.50 12,457,886.70 4.11VIII 355,235.90 11,829,921.90 12,185,157.80 2.92IX 298,510.90 10,745,693.00 11,044,203.90 2.70X 323,573.70 11,466,728.10 11,790,301.80 2.74XI 316,470.90 9,180,713.70 9,497,184.60 3.33XII 285,077.10 9,707,307.00 9,992,384.10 2.85Caraga 290,057.90 5,804,089.30 6,094,147.20 4.76ARMM 179,714.30 6,645,867.40 6,825,581.70 2.63

* Derived from the Total “Repair and Maintenance” expense items.Source: Commission on Audit (2005).

60 A Review of Build-operate-transfer for Infrastructure Development

Page 68: Areview of BOT for Developing Project

financing such as BOT, ODA, and other financing instruments (bondsissuance, credit guarantees, etc.). They would have to rely on local taxrevenues and the IRA for making infrastructure investments. To promotethe development of regional infrastructure, the financial and technicalcapability of the local governments should also be improved. A review ofthe allocation formula for the IRA is timely considering the great need ofLGUs to have substantial resources for delivery of local public servicesand infrastructure development. Another area for improvement would bethe access of LGUs to other financing sources so that they may not be toodependent on IRA transfers. Many LGUs use the IRA for financing localadministrative services as well as capital expenditures. The nationalgovernment can also provide not only financial support but also technicalsupport in the planning, development, and implementation of localinfrastructure projects.

Framework for subnational infrastructure developmentTwo major strategies for economic growth and development have a bearingon infrastructure development at the subnational level. These are (a)decentralization and (b) the creation of so-called “super regions.” Thegovernment has clustered certain regions into different “super regions,”each with a unique development strategy.

Under the first strategy, local infrastructure development is theresponsibility of subnational governments, that is, “local government units”comprised of provinces, cities, municipalities, and barangays. Localgovernments would be better able to identify and finance localinfrastructure requirements, which will contribute to the creation of anenvironment for more investments and economic activity in the local areas.Under the second strategy, major contiguous areas in the country havebeen identified and clustered as platforms for growth and developmenton the basis of the areas’ resource endowments, competitive advantages,and business activities. The development of efficient transportation,communication, and power infrastructure in the super regions willcomplement those regions’ perceived advantages for certain economicactivities, e.g., information and communications technology developmentin the Luzon Urban Beltway.

DecentralizationThe Philippine administrative system is comprised of a central or nationalgovernment and local territorial/political subdivisions called collectivelyas local government units, which are composed of provinces, cities,

Llanto 61

Page 69: Areview of BOT for Developing Project

municipalities, and barangays (smallest administrative and political unit).For administrative convenience, all provinces are grouped into regions.National government agencies, e.g., Department of Agriculture, maintainregional offices to serve the constituent provinces. The regions do notpossess a separate local government with the exception of the AutonomousRegion of Muslim Mindanao and the Cordillera Administrative Region,which are comprised of provinces, cities, and municipalities sharing, amongother things, common and distinctive historical and cultural heritage andeconomic and social structures. Unlike the other regions, the autonomousregions are provided legislative powers within their territorial jurisdictionover matters pertaining to, among other things, ancestral domain andnatural resources; regional, urban, and rural planning development; andeconomic, social, and tourism development.

At present, the Philippines has 17 regions, 82 provinces, 1,510municipalities, and 41,995 barangays.59

This administrative and political structure, coupled with thegeographical attributes of the Philippines, is meant to facilitateadministration and governance especially of people in remote areas. Withthe intention of bringing the government closer to the people throughadministrative deconcentration and political devolution, RA 7160 or theLocal Government Code (LGC) was enacted in 1991. Under the LGC, thebasic services that were previously the responsibility of the nationalgovernment were transferred to the LGUs, to wit, health (field healthand hospital services and other tertiary services), social services (socialwelfare services), environment (community-based forestry projects),agriculture (agricultural extension and onsite research), public works(funded by local funds), education (school building program), tourism(facilities, promotion, and development), telecommunications services andhousing projects (for provinces and cities), and other services such asinvestment support. The decentralization and consequent devolution ofthe delivery of basic goods and services follow the thinking that localdevelopment could be more effectively fostered by providing local areaswith the necessary autonomy, power, and authority.

Super regionsIn her State of the Nation Address in 2006, President Gloria Macapagal-Arroyo unveiled the administration’s regional development program

__________________59 National Statistical Coordination Board. 2006. Philippine countryside in figures.

62 A Review of Build-operate-transfer for Infrastructure Development

Page 70: Areview of BOT for Developing Project

through the enhancement of regional clusters or super regions inMindanao, Central Philippines, North Luzon Agribusiness Quadrangle,and Luzon Urban Beltway.60 In addition, a Cyber Corridor, traversingBaguio City to Zamboanga, would focus on information and communicationstechnology (ICT)-related investment such as business process outsourcing.By grouping selected regions and provinces according to their economicstrengths, the super regions are intended to stimulate economic growthand development and harness the natural competitive advantage/s of majorareas of the country as well as that of knowledge and technology andextend urban development outside of Metro Manila.

Specifically, the Mindanao super region will take advantage of theregion’s competitive edge in agribusiness. Efforts will likewise beundertaken to address and accelerate the development of Mindanao.

The Central Philippines super region is envisioned to be a premiertourist hub due to its long white beaches, rich coastal and marine resources,vast forest reserves and diverse ecosystems, varied provincial culturesand historical landmarks, and warm and friendly people.

The North Luzon Agribusiness Quadrangle is envisioned to spur thecountry’s drive toward agricultural productivity and increased foodproduction to supply the major population centers of Luzon as well asNorth Asia’s. This proximity to the major markets of North Asia has thepotential to increase food and agricultural exports as well as exploitopportunities in cultural and ecotourism.

Finally, the Cyber Corridor will be an information, communications,and technology channel across the country stretching from the northerncity of Baguio down to Zamboanga in the south. The Cyber Corridor isintended to enhance the country’s high-bandwidth optic fiber backboneand digital network to provide a globally competitive environment forbusiness process outsourcing (BPO), contact centers, animation, medicaland legal transcription, software development, e-learning, e-entertainmentand gaming, and other back office operations (e.g., finance and accounting,human resource development, etc.).

Regional infrastructureIn general, the more rapidly growing regions are endowed with betterand more infrastructure facilities with the NCR producing around 40percent of GDP and thus, it leads the pack, so to say.

__________________60 www.gov.ph, State of the Nation Address.

Llanto 63

Page 71: Areview of BOT for Developing Project

As of July 2007, there are a total of 29,288 kilometers of nationalroads nationwide (excluding ARMM) representing 15 percent of the totalroad network.61 On the other hand, local roads, which are administeredby the local governments, accounted for the remaining 85 percent. As of2006, Region IV has most of public roads (11% of the total public roadnetwork) while NCR registered the lowest (2.35%).

For road density, measured in terms of kilometer of roads per 1,000persons, the NCR ranked lowest as against other regions such as CAR(5.79), Region II (4.71), and Region XI (4.22), which have higher roaddensities, respectively.

Disparity in the development of public roads road is also evident inthe proportion of roads to total land area. In 2006, NCR registered thehighest proportion of roads vis-à-vis its land area (7.67%) as against ARMMwith the lowest (0.23%) followed by Caraga (0.34%) (Table 11).

With regard to telephone connections, the most number ofinstallations and subscriptions were observed in NCR and Region IV(Calabarzon) with 1.8 million and 583,234 subscribers, respectively.Installations and subscriptions were seen lowest in ARMM with only 8,108subscribers. Teledensity, measured as the number of telephone subscribersover the total population in the area under consideration, was observedhighest in the fastest growing regions of the country, e.g., NCR, RegionsIII, IV, VII, and XI (Table 12).

Teledensity figures show that there is great disparity in the provisionof telephone facilities among the regions, which can be attributed to theconcentration of demand for such facilities in the more urbanized centers.The users of those facilities, higher-income households and firms, areclustered around major urban areas. On the other hand, the entry ofcellular mobile technology has provided residents even in remote areasthat have no access to fixed-line facilities with access to the latestcommunications technology. The rising number of overseas Filipinoworkers in global markets, who come from regions outside the urban areassuch as Metro Manila, Cebu, and other urban centers, has also fueleddemand for mobile telephony.

With respect to access to electricity, all Philippine cities are already100 percent energized as of 2006.62 For the barangays, however, only thebarangays in NCR have been reported to be 100 percent energized. All

__________________61 Department of Public Works and Highways.62 Source: Department of Energy.

64 A Review of Build-operate-transfer for Infrastructure Development

Page 72: Areview of BOT for Developing Project

Table 11. Public roads by region, 2007

Region National (km) Local (km) Total (km) Road Density % of Land Area

NCR 1,031 3,723 4,754 0.43 7.67CAR 1,844 7,183 9,027 5.79 0.46I 1,610 13,166 14,776 3.09 1.14II 1,765 13,035 14,800 4.71 0.52III 1,992 13,481 15,473 1.65 0.71IV 4,589 17,763 22,352 1.64 0.48V 2,196 7,000 9,196 1.74 0.51VI 2,880 14,816 17,696 2.52 0.85VII 2,034 13,694 15,728 2.42 0.97VIII 2,370 7,342 9,712 2.37 0.42IX 1,218 9,603 10,821 3.36 0.59X 1,651 13,671 15,322 3.83 0.71XI 1,447 15,805 17,252 4.22 0.75XII 1,304 8,527 9,831 2.63 0.43Caraga 1,357 6,276 7,633 3.23 0.34ARMM 914 6,588 7,502 2.31 0.23Total 30,202 171,673 201,875 45.96 0.59

Source: National Roads, Department of Public Works and Highways (2007); Local Roads, NationalStatistical Coordination Board (2004).

other regions in Luzon are within 95–99 percent level of barangayelectrification except for Regions V (Bicol) and IV-B (MIMAROPA), whichincludes the island provinces of Mindoro, Marinduque, Romblon, andPalawan. In the Visayas, the level of barangay electrification is withinthe range of 89–98 percent. In Mindanao, the range is slightly lower at83–95 percent with the exception of the ARMM, which is only 69 percentenergized. The barangay electrification program is expected to becompleted by the end of 2008 (Table 13).

Comparison with other countriesA general observation is that countries in East Asia that have madesubstantial infrastructure investments have realized rapid economicgrowth. Infrastructure has given such countries tremendous opportunitiesto integrate their domestic markets with the global trading system andinternational capital markets resulting in greater exports of goods andservices, the advent of new technologies, including financial innovationsand higher outputs and levels of employment. Rapid economic growthhas translated into higher standards of living and significant reductions

Llanto 65

Page 73: Areview of BOT for Developing Project

in poverty in those countries.63 The opposite is also commonly observed—inadequate infrastructure discourages investment—and leads to a generalclimate of economic decline. Poverty levels are deeper in countries that donot have sufficient infrastructure. Efficient infrastructure reducestransaction costs and creates value added for producers and consumers.It links producers to global supply chains and distribution systems therebycreating access to discriminating global markets for goods and services.The rapidly developing countries in East Asia that have made substantialinvestments in efficient power, telecommunications, transport, andproduction technology have surged ahead of other noninvesting, devel-oping countries.64

Table 12. Regional telephone statistics, 2006

Region Population Lines TeledensityInstalled Subscribed Installed Subscribed

NCR 10,944,300 3,405,627 1,837,718 31.12 16.79CAR 1,559,500 85,476 34,327 5.48 2.20I 4,777,900 180,912 120,004 3.79 2.51II 3,139,000 44,505 29,515 1.42 0.94III 9,385,300 422,802 289,142 4.50 3.08IV 10,903,200 1,110,997 583,234 10.19 5.35V 5,289,500 121,525 71,637 2.30 1.35VI 7,012,300 442,217 139,222 6.31 1.99VII 6,487,800 481,344 224,252 7.42 3.46VIII 4,103,200 151,652 27,766 3.70 0.68IX 3,219,300 36,671 29,353 1.14 0.91X 4,003,100 150,901 57,893 3.77 1.45XI 4,087,200 324,663 107,799 7.94 2.64XII 3,732,600 79,014 38,699 2.12 1.04XIII 2,362,700 127,272 34,519 5.39 1.46ARMM 3,244,800 33,344 8,108 1.03 0.25Total 86,972,500 7,198,922 3,633,188 8.28 4.18

Source: National Telecommunications Commission

__________________63 A commonly cited success story for a country breaking into the ranks of the developed countriesin a relatively short period of time is that of Korea. This country had a per capita GNP of US$100in the 1960s and by the early 2000s, it has reported a per capita GNP of around US$25,000(Source: presentation of the Korea Institute of Economic Policy during the launch of the Korea-Philippines cooperation program, Makati Shangri-la Hotel, June 24, 2009.) Korea had effectivepublic governance, received substantial foreign investments, and successfully exploited thepotential of the export market. Good infrastructure helped in linking with foreign markets.64 Llanto (2007a).

66 A Review of Build-operate-transfer for Infrastructure Development

Page 74: Areview of BOT for Developing Project

Data from the Asian Development Outlook, which is published bythe Asian Development Bank, show a lower per capita GDP of thePhilippines in comparison with a sample of economies in East andSoutheast Asia that includes the four newly industrializing economies(NIEs) of Hong Kong, Singapore, South Korea, and Taiwan. The averageannual growth rate of Philippine GNP taken from the World DevelopmentReport published by the World Bank is also lower than those of itscomparators. The Philippines is ahead only of Indonesia in per capitaGDP in the sample of economies shown.

Recent studies indicate that electricity generation costs in thePhilippines are among the highest in the region and intercity freight ratesare up to 50 percent higher than those of other Southeast Asian countries.Inefficient port infrastructure explains around 40 percent of predictedmaritime transport costs for coastal countries while cargo handlingaccounts for 46 percent of sea transport costs in the Philippines (Limaoand Venables 1999; Clark et al. 2004).65 These inefficiencies get reflected

Table 13. Barangay electrification program, 2006

Region Municipality Cities BarangaysCoverage Energized % Potential Energized %

NCR 17 17 100.00 1,693 1,693 100.00CAR 73 73 100.00 1,108 1,067 96.30I 116 116 100.00 3,027 3,018 99.70II 97 97 100.00 2,375 2,260 95.16III 99 99 100.00 2,231 2,216 99.33IVA 71 71 100.00 1,946 1,942 99.79IVB 69 69 100.00 1,414 1,297 91.73V 113 113 100.00 3,410 3,199 93.81VI 132 132 100.00 3,870 3,782 97.73VII 121 121 100.00 2,713 2,670 98.42VIII 142 142 100.00 4,372 3,924 89.75IX 72 72 100.00 1,864 1,548 83.05X 85 85 100.00 1,841 1,720 93.43XI 43 43 100.00 894 834 93.29XII 46 46 100.00 1,024 927 90.53Caraga 73 73 100.00 1,308 1,255 95.95ARMM 99 99 100.00 2,606 1,811 69.49Total 1,468 1,468 100.00 37,696 35,163 93.28

Source: Department of Energy.

__________________65 Cited in Llanto et al. (2005).

Llanto 67

Page 75: Areview of BOT for Developing Project

in the cost of transport. A recent survey of the World Bank (Cross-BorderTrading 2006) indicates that the Philippines has the highest cost ofexporting a container among ASEAN countries (Basilio et al. 2007).66

According to the World Bank’s Doing Business Indicators, it costs 60–300percent more to export a 20-foot container from the Philippines than fromChina, Singapore, or Thailand.

Table 14 shows a comparison of the cost of exporting a containerfrom several Asian countries.

The World Bank (2007) reports that compared with other Asianneighbors, the Philippines is in the bottom in most of different categoriesof infrastructure—railroads, port, and air transport. Philippine ports arenow rated as the least competitive among those in eight major Asiancountries (Table15).

On the other hand, access to social services such as water supplyand sanitation and solid waste management is also on decline both interms of coverage and quality. Consider the following situation: more thanone third of urban families live in makeshift dwellings. Rental housingmarkets are almost nonexistent because of strict rent-control laws, whichhave discouraged private investments in this segment of the market.Access to land is a key constraint on housing for the urban poor. Only 48.5percent of households in urban areas have access to the community watersystem and at least 13 percent of urban households lack potable watersource near their homes. One of five poor households has no toilet facility(Llanto 2007c). This deteriorating coverage and the lack of quality of

__________________66 H. Basilio, 2007. Trade in maritime transport services, unpublished paper.

Table 14. Cost of exporting a container (20-footer)*

Country In US Dollars

Philippines 1,336Thailand 848China 335Singapore 382

Source: World Bank 2006.*Note: The cost cited above consists of several items/charges—documentation, inland transportation, customs clearance andtechnical control, and ports and terminal handling. The cost doesnot include ocean freight.

68 A Review of Build-operate-transfer for Infrastructure Development

Page 76: Areview of BOT for Developing Project

infrastructure and service delivery, including the lack of infrastructurein the poorer communities have been widely considered as an impedimentto growth and poverty reduction.

Recently, the Japan External Trade Office (JETRO) conducted asurvey among a sample of Japanese international investors about whatthey would consider as a deterrent to increasing their investments in Asia.Underdeveloped infrastructure was cited as a major disincentive toJapanese foreign investment in the Philippines. In the ranking done inthat survey, the Philippines was third with India and Vietnam in the toptwo slots (JETRO 2007). In the Philippines, local and foreign companiesblame the high costs of doing business on the poor state of the country’sinfrastructure. Bad roads and poor rural transport infrastructure add tothe costs of doing business, as does the price of electricity, which is thehighest in the region (ADB 2005). In 2003–2004, the World EconomicForum ranked the Philippines 66th out of 102 countries on its growthcompetitiveness index partly because of the poor state of Philippineinfrastructure (World Economic Forum 2004). A World Bank investmentclimate assessment also found that infrastructure was a major concernamong the 650 or so private firms surveyed (World Bank 2005).67

__________________67 Llanto (2007a).

Llanto 69

Table 15. Infrastructure ranking in the Global Competitiveness Report

Country Overall Railroad Port Air Electricity TelecomsInfrastructure

China 3.5 3.7 3.7 3.9 4.2 5.4India 2.9 4.7 3.2 4.8 3.0 6.0Indonesia 3.7 3.2 3.7 4.1 3.6 3.9Korea 5.2 5.4 5.3 5.7 6.1 6.5Malaysia 6.1 4.9 6.1 6.2 5.9 6.0Thailand 4.9 3.7 4.5 5.6 5.3 6.1Vietnam 2.7 2.8 3.1 3.9 3.4 4.9Philippines 2.3 1.5 2.4 3.9 3.6 4.8Ranking 8 of 8 8 of 8 8 of 8 6 of 8 5 of 8 7 of 8

Source: World Economic Forum “The Global Competitiveness Report, 2003–2004”Legend: 1 = poorly developed and inefficient; 7 = among the best in the world.

Page 77: Areview of BOT for Developing Project

Governments have traditionally been in charge of providing and financinginfrastructure based on the conviction that infrastructure partakes thenature of a public good that the public sector is obligated to provide. Infact, many countries in East Asia report that it is still government or thepublic sector that provides most of the infrastructure in the region.68 Thisis understandable because generally that is indeed the character of publicgoods. However, as earlier discussed, pure public sector provision hasyielded to private participation in infrastructure as a mechanism for theprovision of infrastructure. Several factors have driven many countries touse private participation as an important instrument to provideinfrastructure (Box 4).

The BOT approach is part of a range of methods for private sectorparticipation in infrastructure provision. It has been widely viewed as apragmatic approach in infrastructure provision in countries where severebudgetary constraints limit government’s capacity to provide it. Othermodes of private participation in infrastructure are management contracts,leasing, divestiture by state-owned enterprises, concessions, and jointventure. A good example of a joint venture is the Manila North Toll Ways,a large toll road project in the country, which is discussed below. Whatmay be emphasized here is that the clarity of the roles of government andthe private sector and the close cooperation between the contracting partiesled to a successful public-private partnership in this toll way project.

3The Build-operate-transfer Approachfor Infrastructure Provision

__________________68 Country representatives’ comments made during the Workshop of Economic Research Instituteof Asia Infrastructure Project (final meeting), JETRO-IDE Research Center, Bangkok, Thailand,20–21 January 2008. The countries represented in the workshop are the following: People’sRepublic of China, Indonesia, Myanmar, Thailand, Cambodia, Malaysia, Philippines, Singapore,Lao PDR, Vietnam, Japan, and India.

Page 78: Areview of BOT for Developing Project

72 A Review of Build-operate-transfer for Infrastructure Development

Economics of BOT and anatomy of BOT contracts69

The economic argument for BOTGenerally, people would expect that the service from a given infrastructurefacility should be freely given by the government as part of the service itis mandated to provide the citizenry. In reality, the service is not freebecause general taxation finances this type of expenditure as well as otherexpenditures done in the pursuit of development objectives.

An argument for government provision of infrastructure facilitiesrelies on a case of market failure. Canlas and Llanto (2006) point out that,for a variety of reasons, even if people value a service from a giveninfrastructure project (say, from a road or a bridge), they will hesitate toreveal the price that they are willing to pay for the service. If users canfree ride, they will. Thus, it may not be possible technologically and atreasonable cost to exclude potential users from nonusers of the service.Once the service is provided to one it must be provided to all. In other

Box 4. Reasons for private participation in infrastructure

Investment requirements exceed the capacities of national utilities andgovernments;The performance of the infrastructure sector, in general, has not metinternational standards;The managerial and technical resources available to the government areinadequate;Innovations in technology (for example, small but economic combined-cycle power plants fueled by gas) permit the unbundling—vertical andhorizontal—of the power sector);Demonstration effects arising from the success of privatization andunbundling efforts, (for example, in the United Kingdom) and thepossibility of using regulation to protect the public interest (for example,the incentive regulation and yardstick regulation used in Spain) aremaking new approaches to upgrading infrastructure viable); andThe limited coverage and quality of some countries’ infrastructures arehindering their efforts to achieve international competitiveness.

Source: Malhotra (1997).

__________________69 This was prepared by Prof. Dante Canlas as part of a technical memorandum on a review ofthe (Philippine) BOT Law conducted by Dante Canlas and Gilberto Llanto on 14 May 2006.

Page 79: Areview of BOT for Developing Project

words, that service partakes of the nature of a public good, which thegovernment is forced to provide.

Pricing of the service is not possible and so if one were to rely onmarkets guided by a price system, the project will never be built. No marketwill emerge to exclude those who are not willing to pay for the cost of theservice. As a result, a need is not met and in the overall, society’s welfaresuffers. And so the government steps in to provide the service through atax-and-subsidy scheme.

However, in some cases—such as toll roads and bridges—pricing ispossible. The services from these infrastructure projects can be extendedonly to those willing to pay the charges. Unlike some pure public goodswherein markets fail, it is possible to exclude nonpayers in a relativelyinexpensive way. User charges can be imposed allowing project investorsto recover operating costs plus normal profits. In this setting, private sectorprovision of infrastructural facilities is an option.

This works to the advantage of the government. As pointed outearlier, the provision and financing of some infrastructural facilities bythe private sector (technically, a concessionaire) presents government anoption to focus its scarce resources elsewhere. A narrow fiscal space, thatis, severe budgetary constraints, can lead to drastic cuts in discretionaryspending of the national government wherein infrastructure spending cutsare first resorted to before cuts on social expenditure are introduced.70

In this context, a BOT approach as a particular form of private sectorprovision of infrastructural facilities may be used. The prospects ofcommercial returns arising from a ‘user-pays’ principle motivate privaterisk capital to consider investing in long-lived, lumpy infrastructurefacilities. To be able to realize a mutually agreed-upon rate of return toinvestment, the concessionaire relies mainly on a user charge that isregulated. However, achieving the rate of return that would satisfy privateinvestors will depend on, among others, the openness of the regulator onthe matter of allowing cost-recovering user charges. People who pay theadministered fee can avail of the service provided by the project. Thosenot willing to pay are excluded. Thus, since pricing is possible, users,instead of taxpayers, pay for the operating cost. Much-needed infrastructureservice is provided and the concessionaire profits from the investment.

Setting the user fee at entry level and its predicted time path duringthe cooperation period are vital to achieving the desired financial stability__________________70 The national budget may also be maintained in current peso terms during times of fiscalstress.

Llanto 73

Page 80: Areview of BOT for Developing Project

74 A Review of Build-operate-transfer for Infrastructure Development

and profitability of the project. A highly regulated fee structure thatdisallows cost recovery and the generation of normal profits may createdisincentives on the part of the concessionaire. Project financiers carefullyassess the financial viability of the BOT project and its vulnerability toregulatory and political risks. In this regard, project financiers may viewa tightly regulated fee-setting procedure as putting loan servicingexcessively at risk. Evidently, it is important to pay close attention to thecreditors’ preference; otherwise, financial closure will be very difficult toobtain, which endangers the BOT project.

Administering the user fee rests on a number of factors. One factorto consider is the price elasticity of demand for the infrastructure service.Very high user charges may discourage many potential users from availingof the service. If target revenues are not realized, the project may loseand eventually fail. In this regard, the two parties negotiate at the startfor possible monetary and nonmonetary incentives to the project, whichare then built into the contract.

On the institutional arrangement, there is a need for a strongpartnership between the concessionaire and the government grantingauthority throughout the period of cooperation, which is a long period oftime since long-lived investment assets are involved. The strength anddurability of the partnership depend to a great extent on the presence oftechnical, legal, and financial expertise at the level of the grantingauthority. Such expertise, if present, enables the government agencyconcerned to engage the concessionaire in meaningful discussions ordialogue on a wide range of relevant issues at project-entry level, duringproject construction, and during project implementation or operation.

An implicit requirement is continuing commitment of the contractingparties during the cooperation period to operate the infrastructure facilityaccording to the terms and conditions spelled out in the BOT contract.That commitment is bolstered by the presence of a mutually agreeableconcession agreement or contract governing the BOT project.

BOT contract as an incomplete contract71

Several factors impact the production of a concession agreement that ismutually acceptable to the government and the private concessionaire.An example of such factors is the allocation of risk between the private

__________________71 The author is indebted to Adora Navarro for a good review of the literature on incompletecontracts theory, which is partly incorporated in this section. The paper was written under thesupervision of the author.

Page 81: Areview of BOT for Developing Project

investor and the government. Risk allocation and contingent claims ofthe concessionaire in case a particular state of nature occurs are spelledout in the concession agreement or contract between the private investorand the government.

The contract is a comprehensive document that spells out privateproperty rights, decision rights, risk-sharing arrangements, and third-party intervention if contractual disputes arise and, in general, the dutiesand responsibilities of the private concessionaire and the governmentgranting authority. In view, however, of imperfect information and limitedability of the parties to anticipate all possible states of nature at the timeof contract writing, all such contracts are essentially incomplete.

What makes BOT contracts incomplete? Infrastructure investmentsare long-term contracts involving the production and operation of long-lived assets financed by long-term financial instruments. In BOT contracts,long-term obligations are committed ex ante while the benefits arerealizable ex post. This creates a potential ‘hold-up’ problem. Williamson(1975 and 1985) identified the possibility of “hold up” situation thatbasically predicts this: after the long-term investment, e.g., aninfrastructure facility, has been made ex ante by one party to a transaction,the other party may behave opportunistically ex post (Williamson 1975,1985). The latter party can do this by reneging on the agreement to usethe contracted facility or threatening not to use it if the price for the servicegiven by the infrastructure facility is not lowered. Because of the sunkcost already made, the first party loses. Because of the difficulty ofprotecting such long-term investments made ex ante by an investor, thereis a need to properly align incentives as much as possible. Underinvestmentin such infrastructure facilities may occur because the potential investorfears the possibility of a ‘hold-up,’ that is, future exploitation. Williamsonassumes that high transaction costs prevent some aspects of the futuretrade from being contracted ex ante. The contracting parties have to leavecontingencies open to future renegotiation and, thus, contracts becomenecessarily incomplete.

Grossman and Hart (1986) formalized the “hold-up” problem incontracts by distinguishing between ex ante transaction costs (writing costs)and ex post transaction costs (nonverifiability by a third party, say, thejudicial system, of valuation of trade variables). The former assumes thatcontractual contingencies are costly to specify whereas the latter assumesobservable but nonverifiable information on the parties’ valuation of futuretrade exchange or contractual obligations. Grossman and Hart explainthat incompleteness of contracts results from a combination of investment

Llanto 75

Page 82: Areview of BOT for Developing Project

76 A Review of Build-operate-transfer for Infrastructure Development

specificity and the cognitive and informational boundaries of the judicialsystem which decides on the enforceability of contracts. Hart and Moore(1988) carried on this nonverifiability and enforceability assumptionfurther by pointing out the judges’ inability to verify whether a relevantstate of nature had occurred. Moreover, they postulated that long-termcontracts reflect the incapacity of parties to prevent ex post renegotiation.This renegotiation framework introduces another phase—the ex interimperiod—when the realization of a state of nature that calls for therenegotiation option is occurring or has just occurred.

Overall, four possible reasons explain the presence of incompletecontracts: (i) unforeseen contingencies; (ii) existence of writing costs; (iii)the nonverifiability of valuations and states of nature which createsenforcement problems; and (iv) the lack of commitment not to renegotiate.72

These constrain the production of an efficient contract that canaddress information, risk, and uncertainty arising from BOT contracts.Thus, bounded rationality is a major explanation for the inability to designoptimal long-term BOT contracts.73 Brousseau and Fares (1998) explainsthat “bounded rationality of all agents” and “radical uncertainty” are thekey reasons agents cannot write complete contingent contracts andprecisely state ex ante each party’s behavior.

However, notwithstanding bounded rationality, in reality thecontracting parties (that is, the government granting authority and theprivate proponent/investor) do try to envisage and assess all possible futurestates of nature. Then, they try to devise and agree on mutually agreeablemeasures that will be utilized upon the occurrence of future states tominimize adverse impact on commitment. Although, in practice, not eachand every future state of nature may be addressed in contingent contracts,the contracting parties can design contracts that provide approximatesolutions, including compromises to alternative states of nature in thefuture.

In the context of BOT, examples of such alternative future statesare unexpected, prolonged delays in construction, glitches during

__________________72 Tirole’s 1994 and 1999 papers reject the nonverifiability assumption since contracting partiescan always implement a “revelation mechanism.” In Tirole’s view if parties are risk-averse, amechanism may be devised to induce parties to reveal information that may be used to designan optimal contract.73 The New Palgrave–A Dictionary of Economics (1987) uses the term ‘bounded rationality’ todesignate “rational choice that takes into account the cognitive limitations of the decisionmaker—limitations of both knowledge and computational capacity.”

Page 83: Areview of BOT for Developing Project

operation, changes in the political environment, and many others. Thus,the contracting parties labor to design contracts that identify measure fordealing with every imaginable future state such as provisions forperformance bonds, operation bonds, liquidated damages, buyouts, earlytermination, step-in rights, and others. However, notwithstanding thebest efforts of the contracting parties, bounded rationality imposes anatural limit to the design of optimal contracts. It is difficult to write exante into the contract the range of all possible contingencies and theappropriate interventions, which are seen only ex post during actual projectimplementation and operation. As is commonly asserted, hindsight is 20/20 vision! Given real world complexities, contracting parties must recognizethe limits imposed by bounded rationality and the need to maintain openand transparent lines of communication and some degree of flexibilityand to make relevant project-related information accessible to either partyon a timely basis.

Some aspects of the future states of the world, e.g., a change in thelegal environment or drastic market movements, may be unforeseen orcould not be anticipated by the contracting parties in advance. Theuncertainty of future events, some of which are exogenous, drives thecontracting parties to agree on revisiting the contract in some future timeto be able to deal with contingent events. A mutually agreed upon schedulefor a review of contract implementation is a good option!

Thus, BOT contracts have to provide for contract renegotiation whensome unanticipated states of nature occur. Contracting parties, especiallythe government, have to provide some form of assurance or guarantee totake care of risk and uncertainty that may weaken long-term commitment.

Even if these states of nature may be described or appreciated, writingthem into the contract can be costly. Transaction costs may be highespecially if there is lack of financial, economic, and legal expertise toprepare optimal or near-optimal contracts. Furthermore, whoever isresponsible for enforcing the contract (e.g., the court) may not be able toverify whether or not a particular state of the world has occurred, orwhether or not a party’s representation is true. It is also possible that theprevailing legal system does not allow parties to prevent renegotiation(i.e., renegotiation is always an option). In this regard, the contractingparties must ensure that renegotiation does not happen upon the instanceof a trivial event or state of the world. It is always the rule of stable long-term partnerships to avoid having to enter into a renegotiation because oftrivial reasons or political whim or caprice. The Philippine legal frameworkfor BOT actually confirms this—there is a provision on contract reopening

Llanto 77

Page 84: Areview of BOT for Developing Project

78 A Review of Build-operate-transfer for Infrastructure Development

for renegotiation purposed under the BOT Law’s Implementing Rules andRegulations (BOT-IRR).

Thus, if contracting parties are often unable to legally bind themselvesnot to renegotiate, the possibility of renegotiation constrains the set offeasible contracts. The contracting parties want a stable contract and along-term commitment to mutually agreeable contract provisions. It isindeed desirable to have stable contracts but the nature of BOT-typearrangements results in incomplete contracts, which makes BOT projectimplementation a difficult and complex exercise.

The problem with incomplete contracts is that moral hazard problemsand strategic behavior may arise during implementation of BOT-typearrangements. The main objective, therefore, of the parties is to producea contract that addresses information asymmetry, contingent events inthe future, risk-sharing arrangement, and settlement of disputes betweenthe parties, among others. Ambiguity of language is bound to occur in awritten contract, which can give rise to a contractual dispute. Thecontracting parties have to agree on the venue for arbitration as well as atrusted, impartial third-party arbitrator in case of contractual dispute.Third-party arbitration may involve lower transaction cost than courtarbitration but the third party arbitrator must have integrity andcredibility in order to avoid the risk of decisions being assailed by a losingparty. Hence, both parties choose to provide explicitly for the approach toarbitration in the contract, the mode of dispute settlement and acommitment to abide by the decision of a third-party arbitrator agreedupon by the contracting parties.

Description of a typical BOT project74

BOT is an approach where:“…a private party or concessionaire retains a concession for afixed period from a public party, called principal (client), for thedevelopment and operation of a public facility. The developmentconsists of the financing, design, and construction of the facility,managing and maintaining the facility adequately, and makingit sufficiently profitable. The concessionaire secures a return ofinvestment by operating the facility and, during the concessionperiod, the concessionaire acts as owner. At the end of the

__________________74 The discussion of BOT approach in subsections (B and C) draws heavily from two majorreferences: Menheere and Pollais (1996) and M. Augenblick and B. Custer Jr. (1990). Theauthor is indebted to Karl Jandoc, research associate, for summarizing the work of these authors.

Page 85: Areview of BOT for Developing Project

concession period, the concessionaire transfers the ownership ofthe facility free of liens to the principal at no cost” [Menheereand Polais, 1996 quoting Verhoeven].

The degree of success of a project delegated by the government tothe private sector rests on several factors. Apart from the problem withfinding an efficient contract as discussed above, several factors that impacton the successful implementation of a BOT project are indicated in variousstages of development of a BOT project. These factors affect project qualityat entry level, during contract writing and implementation, and in thecourse of regulating user fees.

Understanding the whole BOT approach starts from an appreciationof the interplay of various actors in the project structure, the timing of theBOT process, the goals and incentives that each participant/actor in theBOT process aspires for, the risks the participants face in attaining thosegoals, and the ways they mitigate those risks through various contractualarrangements and the risk-reducing measures adopted by the concernedparties.

Although BOT may be a popular alternative, it is a complex approachbecause of the presence of different actors with particular goals, objectivefunctions and interests, the need to reconcile or harmonize these varyingobjectives to meet a particular infrastructure goal, the presence of manyrisks affecting BOT projects, and the need for the different actors to agreeon risk-sharing allocation and the use of risk management techniques tominimize those risks. Figure 18 shows the complex relationship amongdifferent actors in a BOT project.

Major participants in the BOT processThere are several variations of the BOT approach depending on projectspecifications that attempt to address particular infrastructure problems.The Philippine BOT Law allows several variations: (a) build-operate-transfer; (b) build-operate-own; (c) build-transfer and operate; (d) buildand transfer; (e) build-lease and transfer; (f) contract-add and operate; (g)develop-operate and transfer; (h) rehabilitate-operate and transfer; and(i) rehabilitate-own-operate. These various approaches have a genericstructure. The principal (usually the government) will grant the concessionto the concessionaire, which is typically a consortium of private companies.The role of the concessionaire is to develop, finance, and construct theinfrastructure project. The concessionaire sources funds from both sponsorsand lenders. Finally, the contractor builds the facility, which is

Llanto 79

Page 86: Areview of BOT for Developing Project

80 A Review of Build-operate-transfer for Infrastructure Development

subsequently managed by the operator. The concessionaire, sponsors,lenders, contractor, and infrastructure facility operator belong to theprivate sector.

PrincipalIn general, a host government draws up a list of infrastructure investmentsin accordance to the country’s overall economic and development plan. Ifthe government is constrained to fully financially support theinfrastructure investments, it may start soliciting proposals from privatecompanies to implement those infrastructure investment projects. Acompetitive tender of infrastructure projects defines the mode ofprocurement.

However, depending on the BOT Law of a country, privateparticipants may submit unsolicited proposals to undertake a specificinfrastructure project. Philippine BOT law allows the submission ofunsolicited proposals which “refer to project proposals submitted by theprivate sector, not in response to a formal solicitation or request issued by

Source: Menheere and Pollalis (1996).

Figure 18. Typical BOT project structure

Page 87: Areview of BOT for Developing Project

an Agency/LGU, to undertake Infrastructure or Development Projects,which may be entered into by Agency/LGU subject to the requirements/conditions” (Section 1.3) given as follows under Section 10.1 (Implementingrules and regulations of the Republic Act 6967, as amended by RepublicAct 7718, “The BOT Law”):

“the project involves a new concept or technology and/or is notpart of the List of Priority Projects;no Direct Government Guarantee, subsidy, or equity is required;andthe Agency/LGU concerned has invited by publication, for threeconsecutive weeks, in a newspaper of general circulation,comparative or competitive proposals and no other proposal isreceived for a period of 60 working days.”

The host government either approves or disapproves the unsolicitedproject proposal. Upon approval of a solicited or unsolicited project, thehost government typically grants the private company a concession thatmay last anywhere from 10 to 25 years (or more). The principal (that is,the government) takes ownership of the facility and the assets after theconcession period.

It is well known that developing country governments rarely adopta laissez-faire approach to these projects. Sometimes they provide a portionof the required financing or provide guarantees, subsidies, or similarsupport to make the project more attractive and viable to privateinvestors.75

ConcessionaireOnce all the relevant review and approval processes are followed, theconcession is granted to the concessionaire, which is usually a group ofcompanies interested in undertaking the design, finance, construction,and operation and maintenance of the infrastructure project or facility.The property rights of the facility (or the assets) rest with theconcessionaire during the specified concession period wherein the privateinvestors/owners try to recover their investments and earn profits.

Investors (shareholders and lenders)An integral part of the undertaking of the BOT project is the presence of__________________75 Philippine BOT Law is clear about not providing “direct government guarantee, subsidy, orequity” to unsolicited projects.

Llanto 81

Page 88: Areview of BOT for Developing Project

credible and capable investors to provide the required financing. Theseinvestors include shareholders and lenders. Shareholders infuse moneyin exchange for equity and lenders provide credit financing to theconsortium, which negotiates with the principal for certain guarantees orcredit enhancements to make the project attractive to lenders and funders.There are two broad categories of equity providers: (a) those that have adirect interest in the operation of the project such as contractors, operators,or the host government itself; and (b) those that are solely involved asequity investors such as public shareholders and other institutionalinvestors. Lenders are oftentimes commercial banks, insurance companies,multilateral lending institutions, and other large private lending entities.

ContractorBOT projects involve large-scale building and construction of a facility. Inpractice, the concessionaire taps the services of a contractor to constructthe facility under the project. In some instances, the contractor is part ofthe consortium for reasons, which will be discussed later. The contractoralso hires subcontractors, suppliers, consultants, and advisors.

OperatorAfter completing the construction of the infrastructure facility, theconcessionaire then secures the services of the operator to manage andoperate the facility. The operator is oftentimes one of the entities in theconsortium which has an intimate knowledge of the business and the localenvironment.

82 A Review of Build-operate-transfer for Infrastructure Development

Page 89: Areview of BOT for Developing Project

The Philippine BOT Center reports that as of June 2006, there are a totalof 90 private sector participation (PSP) projects with an aggregateestimated cost of US$23 billion, which are either completed/terminated,operational, awarded, or under construction or in the pre-award stage.76

Seventy-four out of the 90 PSP projects amounting to about US$ 20 billionrepresent those which are already completed, in operation, awarded, andunder construction.

After comments on the legal framework, this section discusses keylessons from the Philippine experience by using as frame the differentstages of the BOT process. The following discussion looks at the projectcycle and examines the experience of three BOT projects: the first twoprojects indicate flaws in BOT implementation while the third highlightsa successful experience.

Overview of the BOT Law and proposed amendment to the law77

The Philippine Congress enacted RA 6957 in 1990 and later amended itthrough RA 7718 in 1994 to develop a comprehensive legislative framework

4Some Key Lessons from the PhilippineExperience

__________________76 Pursuant to Section 12 of RA 7718, the Coordinating Council of the Philippine AssistanceProgram (CCPAP) was identified as the agency responsible for the coordination and monitoringof projects implemented under the BOT Law. CCPAP was later reorganized and converted intothe Coordinating Council for Private Sector Participation (CCPSP) by virtue of AO No. 67,series of 1999, as amended by AO No. 103, series of 2000. EO 144 dated November 2002provided for the conversion of the CCPSP to the current BOT Center and transferred as anattached unit from the Office of the President to the Department of Trade and Industry. The BOTCenter is mandated to provide project development assistance and monitoring functions inaddition to promotion and marketing of the BOT/PSP program to prospective investors/developersand government agencies.77 This is taken from the Technical Memorandum entitled “A proposed BOT Bill to EnhancePublic-Private Partnership in Infrastructure Development” prepared by Dante B. Canlas andGilberto M. Llanto, with inputs from Rhean Botha and Rowena Cham for the DTI-BOI under theEMERGE Project, June 10, 2006.

Page 90: Areview of BOT for Developing Project

84 A Review of Build-operate-transfer for Infrastructure Development

for public-private partnership in infrastructure projects. Subsequently,many other countries have emulated its approach and adopted theirrespective legislation for private sector participation in infrastructureprojects. Today, BOT is a familiar approach to infrastructure provision inmany developing countries worldwide.

As earlier recounted, the Philippine government has taken a keeninterest in harnessing private sector expertise and financing to provideservices that have traditionally been undertaken by the government. Thepossibility of pricing infrastructure services and the availability oftechnologies capable of excluding nonpayers or free riders from availingof the service have made these arrangements possible. This is theexperience in the Philippines in projects such as the Bureau ofImmigration’s information technology project, the MRT-3 (the light railtransport along the main highway of Metro Manila, the Epifanio delosSantos Avenue), and others. In BOT projects, the government has alsoallowed the commercial exploitation of state-owned land through theconstruction of facilities such as shopping centers and government centralheadquarters with office accommodation. At the local level, projectproposals received by LGUs include public markets, bus terminals, andshopping centers.

The BOT Law comprises 13 sections. It was amended in 1994 throughprovisions that: (a) expanded the range of contracts that governmentauthorities may conclude; (b) specified a procedure for the approval ofprojects falling within a given cost range; and (c) stipulated a procedurefor the treatment of unsolicited proposals. The detailed rules andprocedures for project preparation, approval, evaluation, bidding, andimplementation are contained in the Implementing Rules and Regulationsof the law (BOT-IRR). The members of the committee in charge of theIRR are from key government oversight and implementing agencies, e.g.,National Economic and Development Authority (NEDA), Department ofFinance (DOF), Department of Public Works and Highways (DPWH),Department of Transportation and Communication (DOTC), Departmentof Energy (DOE), Department of Agriculture (DA), and the BOT Center,which is attached to the Department of Trade and Industry (DTI). TheIRR has been updated twice since the first BOT Law was adopted in July1990.

There is a recent attempt to amend the IRR in order to make it moreresponsive to private sector demand for speedier review and approval ofproject proposals. A proposed amendment to the IRR wants to change theinstitutional framework from the traditional assignment of project

Page 91: Areview of BOT for Developing Project

identification to the line agencies and the review and approval by theNEDA-Investment Coordinating Committee (ICC) to assigning to lineagencies the responsibility of identifying, selecting, and approving projects.The proposed amendment removes the review and approval process fromthe NEDA-ICC. This has not been unchallenged (Llanto 2007a). Whilethe intent of the government was to facilitate the project approval process,what it did not realize was the conflict of interest situation to which theproposed change will cast line agencies. This is bad public policy. There isa conflict of interest situation because line agencies will now do the job ofidentifying, reviewing, and approving projects that they themselves haveidentified!

Under the proposed change, the line agencies will prepare and submittheir list of priority projects for approval by NEDA-ICC. This reducesNEDA-ICC, an oversight body into some sort of ‘clearing house’ for projectsearlier identified as priority by line agencies. A better approach is tomaintain the traditional process of giving the oversight agencies theresponsibility for project review and approval and assigning line agenciesthe role of identifying and preparing project proposals. Under thetraditional approach, an arm’s length relationship is maintained betweenthe submitting agency and the oversight body. On the other hand, theproposed change, that is, giving line agencies the authority to identify,prepare, review, and approve projects, poses a tremendous conflict-of-interest situation which may harm public interest. The lack of transparencyand objectivity in the review and approval process may result to strategicand opportunistic behavior on the part of the bureaucrats and officialstasked with providing infrastructure projects. The intention ofstreamlining the project identification, preparation, review, and approvalprocess is laudable. If successfully done, the streamlining will result inlower transaction cost and faster provision of much-needed infrastructure.However, the solution that the government seeks to provide to the problemof delays and inefficiencies in the BOT process is unfortunately flawed.

To shorten the approval process, which is the objective of the proposedIRR amendment, the endorsement by the line or implementing agency ofa BOT project should already constitute a “first pass” approval. The NEDA-ICC approval will be the “second pass,” which will then mean the elevationof the project to the NEDA Board, chaired by the President of the Republic,for final approval (Llanto 2007d). It is often convenient to lay the blameabout delays and inefficiencies in the BOT process to the oversight body(NEDA-ICC) but as will be explained below, the greater part of the delayand inefficiencies lie in weak project identification and preparation.

Llanto 85

Page 92: Areview of BOT for Developing Project

86 A Review of Build-operate-transfer for Infrastructure Development

Experience shows that a poorly prepared proposal for an infrastructureproject would not be able to pass muster the review and approval stagebecause to do otherwise would cast on the public the burdens of a flawedproject such as high cost, inadequate maintenance, heavy debt service,and others.

The BOT Law starts with a declaration of policy that confirms theprivate sector’s role as the main engine for growth and development ofthe Philippine economy (Section 1). It also provides for the granting ofappropriate incentives aimed at encouraging the private sector to financethe construction, operation, and maintenance of infrastructure anddevelopment projects that would otherwise be financed by the government.Incentives proposed in the law include (a) financial incentives; (b) minimumgovernment regulation; and (c) specific government undertakings.

Section 2 is a list of definitions. A prominent feature is the variety ofcontractual arrangements for public-private partnership in infrastructurethat are individually defined. In its original version, the law mentionedonly two contractual forms, namely, BOT and build-and-transfer (BT). In1994, additional BOT variants were added and defined, namely, BOO,BLT, BTO, CAO, DOT, and ROT.78

Section 2 contains additional definitions. “Private-sectorinfrastructure and development projects” are defined listing the areas inwhich private investment may be sought.79 The definition confirms thatproject finance may be sourced domestically or internationally. In view ofrestrictions on the operation of public utilities provided for by theConstitution of the Philippines, the law confirms the requirement thatthe facility operator of a public-utility franchise must be a Filipino or acorporation that is at least 60 percent Filipino owned. A final condition isthat no more than 50 percent of the project cost may be provided throughdirect government funding or official development assistance.

Finally, Section 2 also contains separate definitions for: “projectproponent,” “contractor,” “facility operator,” “direct government

__________________78 These abbreviations refer to build-own-operate, build-lease-transfer, build-transfer-operate,contract-add-operate, develop-operate-transfer, and rehabilitate-operate-transfer, respectively.79 Power plants, highways, ports, airports, canals, dams, hydropower projects, water supply,irrigation, telecommunications, railroads and railways, transport systems, land reclamationprojects, industrial estates or townships, housing, government buildings, tourism projects,markets, slaughterhouses, warehouses, solid waste management, information technology,networks and database infrastructure, education and health facilities, sewerage, drainage, anddredging.

Page 93: Areview of BOT for Developing Project

guarantee,” “reasonable rate of return on investments and operating costs,”and “construction.”

Section 3 provides the basic authority for government agencies tocontract with private sector entities. The government agencies withcontracting authority are listed as: government infrastructure agencies,government-owned and controlled corporations (GOCCs), and localgovernment units (LGUs). This authority is qualified by the requirementthat projects should be “financially viable” and that the contractors shouldhave “extensive experience” in projects of this nature.

Section 4 lays down the procedure for initiating projects for biddingunder the law. Government agencies, GOCCs, and LGUs are required toprepare “priority” projects that are included in their respectivedevelopment programs. These are then advertised as eligible for privatefinancing every six months.

Section 4 also specifies nominal peso limits for the approval of projectsunder a particular mode. A distinction is made between national projectsand projects initiated by LGUs. The NEDA Board is the final approvingauthority for national projects. Depending on the value of the project,either the NEDA Board or the ICC is responsible for approving a project.The NEDA Board approves a project which amounts to PhP300 millionand above. The ICC approves projects whose estimated cost is belowPhP300 million. In the latter situation, the NEDA Board merely notesthe action taken by the NEDA-ICC.

A different approval process applies to projects of LGUs that haveconstitutionally enshrined autonomy. The law, however, requires localgovernment projects to be confirmed by various local authorities dependingon the total cost of the project. Confirmation is required from municipalgovernment councils (for projects costing up to PhP20 million), provincialdevelopment councils (for projects costing between PhP20 and 50 million),city development councils (for all projects up to PhP50 million), regionaldevelopment councils (for projects costing between PhP50 and 200 million),and the NEDA-ICC (for projects costing above PhP200 million). While notexplicitly stipulated in the BOT Law, final approval of local governmentprojects is vested in the local government council called the Sanggunianas provided for in the Local Government Code.

Section 5 describes the treatment of unsolicited proposals. It is amajor addition to the amended BOT Law. It allows national and localgovernment agencies to accept unsolicited proposals subject to certainconditions, namely: (a) the project should involve a “new concept ortechnology;” (b) may not be part of the list of “priority” projects identified

Llanto 87

Page 94: Areview of BOT for Developing Project

88 A Review of Build-operate-transfer for Infrastructure Development

by the agency under Section 4; and (c) no direct government guarantee,subsidy, or equity is required. Section 5 also requires the agency to solicita comparative proposal or what is commonly termed as “Swiss challenge.”The agency receiving an unsolicited proposal after verifying compliancewith these conditions must advertise comparative or competitive proposalsfor three consecutive weeks and may accept the original proposal if noother proposal is forthcoming after a period of 60 working days. The lawgives the original proponent the right to match the competing proposalwithin 30 working days.

Section 6 outlines the procedure to be followed in project bidding. Itdirects the head of an infrastructure agency or LGU to advertise approvedprojects at least once a week in newspapers of general and local circulationfor three consecutive weeks. A two-stage/two-envelope bidding proceduremust be followed. Consortium bidders are required to present proof thatthey are jointly and severally liable for the project completion. Withdrawalof a consortium member before project completion may be a ground forcontact cancellation.

The section also prescribes the method for evaluating winning bidsin the case of BOT, BT, and BLT contracts. For a BOT contract, the lawrequires the bid to be awarded to the bidder whose bid is the lowest basedon the present value of its proposed tolls, fees, etc. over the fixed term ofthe project. In the case of a BT and BLT contract, the bid must be awardedto the lowest complying bidder based on the present value of its proposedschedule of amortization payments. There is a proviso, however, thatpreference must be given to a Filipino “contractor if its bid is equallyadvantageous to the bid of a foreign “contractor.”

Section 7 outlines the circumstances under which a contract may beawarded through direct negotiation. This is permitted in four situations:

if only one bidder applies for prequalification;if there is only one prequalified bidder;if more than one bidder is prequalified, but only one submits acompliant bid; orif more than one bid is received, but only one is compliant.

Prospective bidders can appeal their disqualification. Appeals mustbe directed to the head of the agency in the case of a national project andto the Department of Interior and Local Government for a local project.The law also specifies time limits within which appeals must be lodgedand acted upon.

Section 8 describes the “Repayment Scheme.” This section is wide-ranging and deals not only with the manner in which a project proponent

Page 95: Areview of BOT for Developing Project

recovers its investment but also with the regulation of tolls, fees, andother charges that a proponent may levy, its maintenance obligations,and various other issues.

The section confirms that a BOT proponent can recover its investmentby levying tolls, fees, and other charges that are “reasonable” and shouldnot exceed those specified in the contract. Repayment can also be done bygranting the proponent a revenue share or some nonmonetary paymentsuch as granting of a share in “reclaimed land.” In the case of a BT contract,the proponent is repaid through amortization payments that follow thescheme proposed in the bid and incorporated in the contract.

Negotiated contracts granting a natural monopoly or contracts wherethe public has no access to alternative facilities, tolls, fees, and othercharges are subject to government regulation based on a reasonable rateof return. The section contains various provisos:

the term for which tolls, fees, and other charges may be collectedmust be fixed in the bid and may not exceed 50 years;tolls, fees, and other charges may be adjusted during the lifetimeof the contract using a predetermined formula based on officialprice indices and included in the instructions to bidders and thecontract;tolls, fees, and other charges and adjustments must take intoaccount the reasonableness of the rates to end-users; andthe proponent must undertake the necessary maintenance andrepair of the facility during the lifetime of the contract.

Section 9 provides for “contract termination.” It stipulates that if acontract is terminated through no fault of the proponent or by mutualagreement, the government must compensate the proponent the actualexpenses incurred plus a reasonable rate of return that may not exceedthe rate stipulated in the contract. The government is required to insurethis interest with the Government Service Insurance System or an insureraccredited with the Insurance Commission. The bidding terms are requiredto allow for costs of such insurance.

The section further allows a proponent to terminate a contract ifgovernment defaults on “certain major obligations” and the default cannotbe remedied or it can be remedied but the government fails to do so for anunreasonable length of time. Termination must be preceded by prior noticespecifying the effective date of termination. The proponent must becompensated a reasonable equivalent or proportionate cost.

Section 11 confirms that each project must be undertaken inaccordance with the approved plans, specifications, standards, and costs

Llanto 89

Page 96: Areview of BOT for Developing Project

90 A Review of Build-operate-transfer for Infrastructure Development

and that it is subject to the supervision of the agency or LGU concerned.This should be read along with Section 14, which stipulates that all projectsare coordinated and monitored by the Coordinating Council of thePhilippine Assistance Program (CCPAP). In 2002, the CCPAP wasrenamed the BOT Center under EO 144.

Section 13 mandates the issuing of the IRR by a committee. The IRRsets out the criteria and guidelines for the evaluation of bid proposals andlists the financial incentives and arrangements that the government mayextend to projects. The committee is also mandated to amend the IRRfrom time to time after undertaking public hearings and publication.

Sections 10, 12, and 15 to 18 contain various miscellaneous provisions.These include Regulatory Boards, Investment Incentives, Coordinationand Monitoring of Projects, Repealing Clause, Separability Clause, andEffectivity Clause.

An assessmentOn the whole, the BOT Law is a good basic law but together with someamendments to its IRR, it can stand improvement. An indispensablecondition for the successful implementation of the BOT Law is a legalenvironment where property rights and contractual agreements areprotected and enforced. The present BOT Law’s framework for privatesector investment in infrastructure has to be clarified by a clear allocationof roles, functions, and duties across the spectrum of participants in theBOT project.

A primary consideration is to be able to distinguish between the rolesof the enabling legal framework (the BOT Law itself) and the IRR.80 TheBOT Law should provide the enabling framework and clearly allocateroles, functions, powers, duties, and rights among government agencies,namely, the oversight agencies and the implementing agencies involvedin the project cycle. It is, after all, a primary statute that establishesgovernment policy and the institutional framework for implementing thatpolicy.

On the other hand, the IRR are normally technical or operational innature. Thus, they should never be a verbatim copy of the enabling law.What the Philippines has now, however, is a BOT Law that contains both

__________________80 The following paragraphs were from a report prepared by Dante Canlas, Gilberto Llanto, andRhean Botha for Governor Consuelo Perez, Board of Investment, Department of Trade andIndustry in 2007.

Page 97: Areview of BOT for Developing Project

the enabling policy framework and too many details that are technical oroperational in nature. Ideally, the details should be in the IRR so that thegovernment may have the flexibility to change any of them in view ofrapid changes in technology, financial markets, and other factors thatimpact a BOT project. Because it is hard to anticipate such future changes,having a detailed BOT Law may therefore not work in favor of the countryinasmuch as the task of amending the law to respond to changes andinnovations could be a complicated and time-consuming process. There isalso the risk that parallel to the effort to improve the policy and regulatoryframework for the BOT approach are attempts by vested interests tocapture the legislative process by introducing amendments that will befavorable to those interests.

Nevertheless, it is submitted that it will be much more efficient tohave (a) a primary statute that clearly specifies state policy and assignsroles and functions to government institutions and the private proponent;and (b) an administrative procedure based on the IRR that may be amendedfrom time to time as the need arises. The primary statute must affirmgovernment’s binding commitment to honor and defend contractual rightsand obligations. The law must counter ruinous attacks on contracts,especially after a relatively long period of time has elapsed since thecontract was signed, by limiting options to annul or void contracts onprocedural grounds. This includes providing for greater transparency withregard to the content of contracts. The IRR should stipulate the operationaldetails for smooth and transparent implementation of the BOT process toavoid potential disputes that may require tedious court intervention at alater stage of the process.

At the same time, the past experience with BOT implementationindicates the need to provide a clear legal and regulatory framework notonly for BOT projects but also for public-private partnerships in generalin government infrastructure projects. Such framework must give enoughflexibility to the implementing agencies and the oversight body to adjustthe rules and regulations governing public-private partnership (PPP) asmay be required by the passage of time and specific circumstances. Insum, the idea is to have a good and solid basic law for PPP and detailedIRR that is flexible and transparent, which could be changed in atransparent manner in consideration of a change in the legal, financial,technological, and economic environment for infrastructure investments.For instance, there may be a need for contract renegotiation and rules onhow to do this should be provided for very clearly in the IRR. As statedearlier, the IRR can usually be amended more easily by way of an

Llanto 91

Page 98: Areview of BOT for Developing Project

92 A Review of Build-operate-transfer for Infrastructure Development

administrative procedure thereby avoiding delays that may arise from ausually lengthy and ponderous legislative process.

A specific provision that needs a clear and unambiguousinterpretation is the provision on unsolicited proposals and the grant ofsubsidies to BOT projects. The BOT Law grants subsidies and guaranteesonly to solicited BOT projects but the provision speaks of direct subsidies.As shown in the Casecnan case (Box 5), the Department of Agriculturewas able to get a legal opinion that this unsolicited project deserved aperformance undertaking from the government, that is, a subsidy becausethe farmers are the direct beneficiaries of Casecnan project, not NIA, whichwill only get an indirect subsidy. On the other hand, there could be in thehorizon critical projects requiring some form of subsidy, which may notsee the light of day in the absence of such subsidies because they would besubmitted under the unsolicited mode.

At the minimum, an effective implementation of BOT projects hingeson the following: (a) legal and economic environment that is conducive toa mutually beneficial partnership between the private sector and the publicsector; (b) clarity in articulating the duties and responsibilities of theparties to the contract; (c) certainty of recovering investments andavailability of mechanisms for dealing with risks and unforeseen events;and (d) transparency and credibility of the government’s processes forreview and approval of proposed BOT projects and the associated contractsfor implementation. A draft bill amending the current BOT Law, whichadheres to these tenets prepared by a team composed of Dante Canlas,Gilberto Llanto, Rhean Botha, and Domingo Pallarca (2006) is hereinprovided as Annex A.

Stages in the BOT process: the project cycle81

Most BOT projects undergo six identified stages: preliminary study,selection, project implementation, construction, operation, and transfer.Figure 19 shows these stages and the principal activities contained ineach stage. The whole process can be roughly divided into two parts: (a)review and approval of the project and contracting process before thecooperation or concession period; and (b) implementation during theconcession period. During the first part of the process a feasibility studyis done; the proposed project is approved; and is then awarded to theconcessionaire who builds, finances, and operates the facility. In the second

__________________81 The new framework in this section relied on Menheere and Pollalis (1996).

Page 99: Areview of BOT for Developing Project

part, the concessionaire starts to implement the project by obtaining thenecessary requirements, designing the facility, and constructing it. Thefacility is then used to generate revenues for the concessionaire and aftera specified period, transfers the ownership of the facility and its assets tothe host government.

Review, approval, and contracting processIn the case of the Philippines, the government identifies the infrastructurepriorities and the facilities that have to be built. The basic documentsthat justify the infrastructure projects are the Medium-Term PhilippineDevelopment Plan and its companion document, the Medium-Term PublicInvestment Program that lists the priority infrastructure projects thatthe public sector and the private sector, respectively, are expected to design,finance, and construct. Some of those projects are identified as projectsthat may be implemented through the BOT approach. The concernedgovernment agency prepares a feasibility study on a project identified tobe implemented under the BOT approach, e.g., the DOTC prepares afeasibility study on a toll road project or it may contract independentparties to conduct a feasibility study to determine the economic viabilityand desirability of the project. The preliminary study equips thegovernment agency with a feasible project idea to start the competitivetendering process as provided by the procurement law.

Figure 19. Stages in the BOT process

Adapted from Menheere and Pollalis (1996).

Llanto 93

Page 100: Areview of BOT for Developing Project

94 A Review of Build-operate-transfer for Infrastructure Development

Under Republic Act 9184 or The Government Procurement ReformAct of 2003 competitive bidding procedures remain to be the central tenetof government procurement policy. Philippine procurement law requirescompetitive bidding for infrastructure projects. Section 5 of Republic Act9184 defines competitive bidding as a “method of procurement which isopen to participation by any interested party and which consists of thefollowing processes: advertisement, prebid conference, eligibility screeningof prospective bidders, receipt and opening of bids, evaluation of bids,postqualification, and award of contract.” The governing principles ongovernment procurement are well laid out in Section 3 of Republic Act9184—all procurement of the national government, its departments,bureaus, offices, and agencies, including state universities and colleges,government-owned and/or -controlled corporations, government financialinstitutions, and local government units shall in all cases be governed bythese principles:

Transparency in the procurement process and in theimplementation of procurement contracts.Competitiveness by extending equal opportunity to enable privatecontracting parties who are eligible and qualified to participatein public bidding.Streamlined procurement process that will uniformly apply toall government procurement. The procurement process shall besimple and made adaptable to advances in modern technology inorder to ensure an effective and efficient method.System of accountability where both the public officials directlyor indirectly involved in the procurement process as well as inthe implementation of procurement contracts and the privateparties that deal with government are, when warranted bycircumstances, investigated and held liable for their actionsrelative thereto.Public monitoring of the procurement process and theimplementation of awarded contracts with the end in view ofguaranteeing that these contracts are awarded pursuant to theprovisions of this Act and its implementing rules and regulationsand that all these contracts are performed strictly according tospecifications.

The government must expedite the drafting of the ImplementingRules and Regulations that will govern the procurement of foreign-assistedprojects. It was reported (16th ODA Portfolio Review 2007) that during

Page 101: Areview of BOT for Developing Project

the Philippines Development Forum in March 2008, both the governmentand development partners (donors) agreed to work together in the draftingof those rules. Both committed to finalize the rules by end 2008.

Reviewing the Philippine experience, it seems that governmentagencies have found it difficult to move BOT projects from the identificationto approval stage because of weak technical capacity and insufficient legaland financial expertise, especially among proponent/implementingagencies. The problem starts with the inability to prepare a good feasibilitystudy because of weak technical capacity in the agency. The lack of projectidentification and preparation capacity has resulted to the inconsistentapplication of Section 4 (Priority Projects) in the BOT Law and has openedup opportunities to crowd out projects in the priority list.

The poor quality of project proposals submitted for review by theNEDA-ICC often results in a lengthy and tedious review process, whichunfortunately is blamed on the reviewing agencies (the NEDA- ICC). It isnot uncommon for infrastructure project proposals in general to be sentback to the implementing agencies because of failure to address particularissues, e.g., right-of-way problem, lack of realistic plans for the relocationof informal settlers, environmental concerns, questionable project viabilitybecause of faulty or untenable assumptions used in the financial model,unclear institutional arrangements, inefficient risk-sharing agreementsbetween the government and the private investor, and other reasons.

This is a clear area for policy and institutional reform. Implementinggovernment agencies should be ready with clear bid documents, technicalspecifications, and terms of reference but to have bid-ready projects thoseagencies will need time, expertise, and sufficient funds. Also, the concernedgovernment agency should be provided with sufficient budget to solveright-of-way problems, address environmental concerns, and musterenough resources for the relocation of informal settlers in the areas wherethe infrastructure facility, e.g., road, will be constructed.

While the Philippine government takes the initiative with respect tosolicited projects on the one hand, private sector proponents may alsotake the first step in the case of unsolicited proposals, on the other hand.A government agency may also agree with a private proponent about thesubmission of an unsolicited proposal by the private party. An amendmentto the basic BOT Law in 1994 opened the way for private sector proponentsto directly submit to a government agency unsolicited project proposalsthat they think could address some infrastructure lack.

The BOT Law provides certain conditions that have to be met byunsolicited proposals. More specifically, Section 4-A (BOT Law, as

Llanto 95

Page 102: Areview of BOT for Developing Project

96 A Review of Build-operate-transfer for Infrastructure Development

amended) provides the following: “Unsolicited proposals for projects maybe accepted by any government agency or local government unit on anegotiated basis provided that all the following conditions are met: (a)such projects involve a new concept or technology and/or are not part ofthe list of priority projects; (b) no direct government guarantee, subsidy,or equity is required; and (c) the government agency or local governmentunit has invited by publication, for three consecutive weeks, in a newspaperof general circulation, comparative or competitive proposals and no otherproposal is received for a period of sixty (60) working days; provided furtherthat in the event another proponent submits a lower price proposal, theoriginal proponent shall have the right to match that price within thirty(30) working days.”

A government agency may go for the unsolicited mode for thefollowing reasons:82

lack of good feasibility studies on a given project arising fromlack of expertise of the implementing agencies in preparing themand funding constraints for hiring consultants to help in thepreparation of those studies;private proponent doing the feasibility study, which frees thegovernment agency from having to source the initial investmentcost of feasibility studies from the implementing agency’s already-constrained annual budget covers; andbelief that the unsolicited proposal is about a new technology orconcept, which will address some public need, if successfullyimplemented.

Acceptance by the government agency of an unsolicited projectproposal does not end its problem. Reviewing the unsolicited proposalmay burden the ill-equipped government agency, which in the first placeis not capable of identifying projects for competitive bidding. A governmentagency’s inability to effectively evaluate unsolicited bids is the source offrustration on the part of private investors.

The amendment in the BOT Law that inserted the provision onunsolicited proposal has been hailed by congressional sponsors as a goodopportunity for stimulating private sector interest in infrastructureprovision in the country considering the huge financing requirement ofestablishing an efficient infrastructure facility, e.g., modern internationalairport, toll roads, and others, and the willingness of the private proponent__________________82 This is discussed in detail in Llanto (2007d).

Page 103: Areview of BOT for Developing Project

to shoulder the construction and financing burden of the (unsolicited)project. However, unsolicited proposals also create an incentive fornontransparent, backroom negotiations for ill-prepared but politicallyvested projects that are submitted to the implementing agency for approvaland subsequent endorsement or recommendation to the NEDA-ICC.83

It should be stressed that the BOT Law allows the submission ofunsolicited projects under certain conditions. The implicit assumption isthat unsolicited projects will be the exception to general rule ofinfrastructure projects, that is, solicited BOT projects that will be subjectto competition. However, the amendment has created the incentive forthe submission of unsolicited proposals, which are the exceptional casesunder the BOT Law since there is state policy preference for solicitedproposals. Ironically the exceptional case seems to have become thepreferred mode for BOT projects by the private sector and somegovernment agencies. The lack of competition and transparency inunsolicited proposals may lead to flawed design and unwarranted risksfor the public sector. Typically, during project negotiation, it is possiblefor private proponents to get the assent of their public sector counterpartsin covering certain risks that should appropriately be covered by the privateproponents. Please see Box 5 for an example of an unsolicited project andof what the World Bank (2005) termed as ‘how not to do a BOT project.’

On balance, the lack of competition and transparency in an unsolicitedmode of procuring infrastructure creates risks that the project foisted onthe public may not be the most efficient project among alternative options.Solicited projects that would be competitively procured offers the bestpossible option to uphold public interest.

The NEDA proposed the establishment of a project preparationfacility in the late 1990s. Although the Department of Budget andManagement has been quite sympathetic to the idea and appears__________________83 The huge controversy generated by the failed unsolicited proposal known as the NBN-ZTEbroadband proposal where accusations of impropriety, shady negotiation, and alleged corruptionwere traded by proponents, government agencies, and legislators demonstrates the peril oftreading the path of unsolicited projects.

The Philippine National Broadband Network controversy (also referred to as the NBN-ZTEdeal or NBN-ZTE mess) involved allegations of corruption in the awarding of a US$329 millionconstruction contract to Chinese telecommunications firm ZTE for the proposed government-managed National Broadband Network (NBN). The contract with ZTE was signed on April 20,2007 in Hainan, China. Following the emergence of irregularities, President Gloria Macapagal-Arroyo cancelled the National Broadband Network project in October 2007. On July 14, 2008,the Supreme Court dismissed all three petitions questioning the constitutionality of the nationalbroadband deal, saying the petitions became moot when the project was cancelled. (Source:http://en.wikipedia.org/wiki/Philippine_National_Broadband_Network_controversy.)

Llanto 97

Page 104: Areview of BOT for Developing Project

98 A Review of Build-operate-transfer for Infrastructure Development

supportive, the lack of fiscal space (in other words, severe budgetaryconstraints) has hampered the allocation of such funds to the implementingagencies. However, in the light of the adverse impact on project quality atentry of weak capacities of implementing agencies, it is now timely toconsider the provision of funding for a project development facility frombudgetary resources and/or to solicit grant assistance from donor-partners

Box 5.The Casecnan Transbasin Multipurpose Project

In 1983, the National Irrigation Administration (NIA) commissioned afeasibility study of the Casecnan Transbasin Project to provide irrigationand electricity services. Several factors hindered the contemplated project;huge capital requirement, uncertain energy production of the project, complexdesign, environmental issues, and the long construction period estimated at12 years. In May 1993, the government decided to use the BOT scheme tofinance and build the project. The Casecnan Water and Energy Consortium(CWEC) submitted an unsolicited proposal in May 1994. The NIA soughtNEDA-ICC clearance in 1995. The ICC identified serious flaws in theproposed project: environmental concerns and uncertain cash flow whichweakens project viability and significant hydrologic risks. After lengthydeliberations, the ICC finally approved the project in principle subject tofulfillment of several conditions, e.g., issuance of Department of Justiceopinion on the legality of the contract between NIA and CWEC, compliancewith environmental requirements, etc. The government went ahead withthis BOT project but only after agreeing to provide a guarantee for thehydrologic risk. The identified hydrologic risk put in question the viabilityof the power component of the project.

Among others, there are at least three important lessons to be derivedfrom a review of the experience of the Casecnan Transbasin Project:

Project identification and approval processThere should be prior approval of the project proposal by the NEDA-ICCbefore a government agency enters into an agreement with a privatesector proponent. Apparently, NIA had some form of agreement prior tosecuring NEDA-ICC approval.Transparent risk-sharing arrangement with the private proponentIn particular, the following should be thoroughly observed: riskidentification, determination of project viability given certain assumptionsand appreciation of risks involved, and efficient allocation (risk-sharing)between the government and the proponent.Clear rule or regulation on the nonapplicability of subsidy, in whateverform, to unsolicited projects

Page 105: Areview of BOT for Developing Project

Box 5 (cont’d.)

Section 10.1b of the IRR of RA 7718 states that no direct governmentguarantee, subsidy, or equity could be given to an unsolicited project. Therewas a view by the reviewers that the Casecnan project did not involve a newconcept or technology. Neither could the technology being proposed by theproponent be considered new. However, in the case of Casecnan, NIA askedthe DOF to issue a performance undertaking for its obligation to CWEC.The DOF expressed its reservation to the request given that the NIA BOTobligation would require an annual subsidy of PhP1.2 billion for 20 years.Under the BOT Law, the government cannot provide a subsidy to unsolicitedproposals. However, the Department of Agriculture (DA) produced a legalopinion stating that the subsidies to the Casecnan project are indirect (theBOT Law prohibits the grant of direct guarantee or subsidy). According tothe DA, the farmers would be the actual beneficiaries of the subsidies becauseof improved irrigation services and that the NIA would only act as acontractor. The Department of Budget and Management expressed theopinion that the PhP1.2 billion annual requirement of NIA is a direct subsidyand that the government would effectively subsidize NIA, which in turnwould use it to pay for the water delivered by CWEC. NIA has earlier agreedto pay CWEC for the annual delivery of water estimated at 809.1 million m3

regardless of whether the water was actually delivered or not.

Source: World Bank 2005; NEDA.

to jumpstart the process. The weak capacities of government agenciesresult in poor project quality at entry and the basic reason for this is theinability of those agencies to procure the best talent to help with projectidentification and review. The implementing government agencies maynot be able to hire and retain high quality financial, management, andlegal expertise in view of the very real problem of low government salaries.Those experts may not have the incentive to stay long with the implementinggovernment agencies. However, access to a project development facility thatprovides resources to implementing agencies to procure domestic expertiseor even foreign expertise to give advice on BOT projects may be an alternativeroute to strengthen capacities in those agencies.

Procurement processThere are two basic avenues for the BOT approach; solicited and unsolicitedproject proposals. The former refers to the general public selection or publicbidding process. The standard procurement process is through a

Llanto 99

Page 106: Areview of BOT for Developing Project

100 A Review of Build-operate-transfer for Infrastructure Development

competitive bidding process. The implementing agency disseminates arequest for submission of expression of interest to provide a particularinfrastructure facility and upon receiving applications it requests someprequalified consortia to submit their proposals. This presumes that theimplementing agency has done some basic feasibility study of the proposedinfrastructure facility. The proposals are then subject to competitiveevaluation. The Philippine government uses the “two-envelope system”to evaluate the proposal. Under this system, the evaluation based ontechnical merits is followed by financial evaluation that considers thefinancial viability and economic benefits of the project. The concession isthen awarded to the proponent, which has successfully passed the technicaland financial evaluation.

As mentioned earlier, the Philippine BOT Law allows the submissionof unsolicited proposals. Table 16 shows a list of unsolicited projectsawarded between 1994 and 2006.

Under the unsolicited mode, a private proponent directly submits aproposal to the government. In contrast to the solicited mode wheregovernment takes the initiative in asking private parties to submit a projectproposal, the private party makes the first move under the unsolicitedmode as illustrated in Box 5. If deemed acceptable, the proposal is openedup to some form of competition. The Philippines uses an approach called“Swiss challenge” to determine who will undertake the project. After thenecessary evaluation process, the project is granted to a concessionaire.

Under Section 5, the implementing agency may accept the originalunsolicited proposal if no ‘competing’ proposal is submitted after a periodof 60 working days. The original proponent is allowed to match thecompeting proposal within 30 working days. The main critique againstthe Swiss challenge procedure is the limited time that is allowed forpotential competitors to mount a credible challenge, which discouragesother potential private participants. It seems that, so far, only oneunsolicited proposal submitted under the Swiss challenge has won overthe original proponents of unsolicited proposals. The World Bank (2000)indicated the ineffectiveness of the Swiss challenge in actual practicealthough in theory it seems to overcome the lack of competition associatedwith unsolicited projects. Box 6 summarizes the experience with the onlyunsolicited proposal that a competitor won over an original proponentunder the Swiss challenge. While that competitor was able to mount asuccessful challenge, that is, the unsolicited BOT contract was awardedto it, legal infirmities weighed down the concerned project, which led to aprotracted and yet unresolved arbitration process.

Page 107: Areview of BOT for Developing Project

Table 16. Unsolicited projects presented to BOT Center and ICC Secretariat,1994–2006 (operational and awarded)

Project Title Sponsor Sector Type/ Estimated Year Status Winner Wasand Status Agency Variant Project Approved “Right

Cost to($ million) Match”

aFactor?

Under concession/OperationalAlien Certificate EI information BOT 2.80 2003 ongoing original noof Registration technology proponentI-Card ProjectCaliraya- NPC power/ BROT 450.00 n.a. operational original yesBotocan- water proponentKalayaan PowerPlant ProjectCasecnan NPC power/ BOT 650.00 1994 operational original noMultipurpose water proponentBOT ProjectComputerization NSO information BTO 65.00 1996 operational original noof the Civil technology proponentRegistry SystemSan Roque NPC, NIA power/ BOT 1,141.00 1996 operational original noMultipurpose DENR, water proponentProject DPWHSubtotal: 5 projects 2,308.80

Awarded/Under constructionLand Titling LRA information BOO 82.00 1998 ongoing original noComputerization technology proponentProjectMachine- DFA information BOT 50.30 1995 terminated original noReadable technology by DFA proponentPassports andVisa ProjectSan Pascual NPC power BOO 400.00 1995 operational original noCogeneration proponentPower PlantProjectPampanga Pampanga information BTO 0.96 n.a. ongoing original noGIS Center Province technology proponent

LGUTarlac Public Tarlac City property BOT 3.88 n.a. ongoing original noMarket LGU development proponentRoxas Roxas, property BOT 1.00 n.a. ongoing original noCommercial Isabela development proponentCenter LGUSubtotal: 6 projects 538.14

Llanto 101

Page 108: Areview of BOT for Developing Project

102 A Review of Build-operate-transfer for Infrastructure Development

The lack of effective competition in unsolicited proposals hasencouraged suggestions to constrain or restrict the usage of this mode ofinfrastructure provision. One step is to follow a strict application of theconditions allowed by the BOT Law to the submission of unsolicitedproposals, namely, that the proposed project be a new concept or technologyand that no direct government guarantee, subsidy, or equity can be givento the unsolicited project. To further constrain the space of unsolicitedproposal, it can be added that Section 5 of the BOT Law should be amended(a) to lengthen the time period for laying a Swiss challenge; and (b) toprohibit the grant of direct and indirect guarantee, subsidy, performanceundertaking, or equity to the unsolicited BOT project (underscoringsupplied).

There is a need to review whether or not it is really useful to have aprovision in the BOT Law on unsolicited proposals. These have been thesource of controversy in several projects because experience has indicatedthat the unsolicited mode leads to a situation where the element ofcompetition becomes missing notwithstanding the so-called Swisschallenge that has been devised by legislators as a “cure” to the lack ofcompetition. Building capacities in the implementing agencies foridentifying projects for competitive bidding will minimize, if not eliminate,the need for a provision on unsolicited proposals. On the other hand, theremay be merit in allowing private proponents to submit unsolicited

Project Title Sponsor Sector Type/ Estimated Year Status Winner Wasand Status Agency Variant Project Approved “Right

Cost to($ million) Match”

aFactor?

CancelledNinoy Aquino DOTC transport BOT 369.15 1995 Partially third party yesInternational completedAirport Terminal but not inIII Development operationProject Contract

nullifiedSubtotal: 1 project 369.15

Source: BOT Center, NEDA-ICC.Note: n.a. = not availableSponsor agency: BI = Bureau of Immigration; DENR = Department of Environment and Natural Resources

DFA = Department of Foreign Affairs; DOTC = Department of Transportation and Communication

Table 16 (cont’d.)

Page 109: Areview of BOT for Developing Project

Box 6. Ninoy Aquino International Airport (NAIA) Terminal III*

Terminal III is a 189,000-square meter facility, which started constructionin 1997 and was intended to start operations in 2002. The modern US$640million facility was designed by Skidmore, Owings, and Merril to have acapacity of 13 million passengers per year or 33,000 passengers daily atpeak or 6,000 passengers per hour. Based on the design, it has the followingfeatures: a four-level shopping mall connecting the terminal and parkingbuildings; a parking building with 2,000 car capacity and outdoor parkingfacility which can accommodate 1,200 cars; 34 air bridges and 20 contactgates with ability to service 28 planes at any given time; 70 flight informationterminals; 314 display monitors with 300 kilometers of fiber optic IT cabling;29 restroom blocks; five entrances in the departure area equipped with X-ray machines; and seven large baggage carousels each with individual flightdisplay monitors.

The original proposal for the construction of a third terminal in MetroManila was submitted by Asia’s Emerging Dragon Corporation (AEDP). Theunsolicited proposal was subjected to a Swiss challenge by other interestedparties. The AEDP lost the bid to PairCargo and its partner Fraport AG ofGermany. Fraport AG and PairCargo then contracted the PhilippineInternational Air Terminals Corporation (PIATCO) to undertake theconstruction and subsequent operation of the terminal. PIATCO is whollyowned by Fraport AG (Operator of Frankfurt airport in Germany), SecurityBank and Trust Co., Equitable Banking Corporation, Chuah Hup HoldingsCo., and Philippine Airport Ground services (PAGS). Construction of theterminal was begun under the administration of Joseph Estrada.

The BOT contract included: (a) the Concession Agreement signed onJuly 12, 1997; (b) the Amended and Restated Concession Agreement datedNovember 26, 1999; (c) the First Supplement to the Amended and RestatedConcession Agreement dated August 27, 1999; (d) the Second Supplementto the Amended and Restated Concession Agreement dated September 4,2000; and (e) the Third Supplement to the Amended and Restated ConcessionAgreement dated June 22, 2001.

The original agreement required PairCargo and Fraport AG to constructand subsequently operate the international airport within a 25-yearcooperation period. After 25 years of operation, NAIA Terminal III will behanded over to the Philippine Government. The government offered to buyout Fraport AG for $400 million, to which Fraport agreed. Before the terminalcould be fully completed, current president Gloria Macapagal-Arroyo formeda committee to evaluate the agreement to buy out Fraport AG. The Arroyoadministration eventually abrogated PIATCO’s BOT contract for allegedly

Llanto 103

Page 110: Areview of BOT for Developing Project

104 A Review of Build-operate-transfer for Infrastructure Development

Box 6 (cont’d.)

having been anomalous in certain important respects. In a subsequentdecision, the Philippine Supreme Court upheld the Philippine Government’sposition on the matter and declared the BOT contract “null and void” for,among other things, having violated certain provisions of the BOT Law. Inparticular, the decision was based on (a) the absence of the requisite financialcapacity of the PairCargo Consortium (predecessor of PIATCO), which isrequired under the BOT Law; (b) material and substantial amendments tothe 1997 Concession Agreement which deviated from the original contractbid upon, which is contrary to public policy; and (c) the amendments in the1997 Concession Agreement provided for a direct government guaranteewhich is expressly prohibited by the BOT Law and its Implementing Rulesand Regulations. The Supreme Court found that the original contract wasrevised to allow for a Philippine Government guarantee of PIATCO’sobligations to its creditors, contractors, and suppliers. The BOT Law disallowsthe granting of such sovereign guarantees. The project in question is anunsolicited project and thus, it does not qualify to receive governmentguarantees. PIATCO maintains that the provisions cited by the SupremeCourt do not amount to a prohibited sovereign guarantee by the PhilippineGovernment.

On December 2004, the NAIA Terminal III was expropriated by thePhilippine Government through an order of the Pasay City Regional TrialCourt subject to payment of an initial amount of PhP3 billion (US$66 millionat PhP45:US$1) to PIATCO. The Philippine Government paid PIATCO thesaid amount on the second week of September 2006. PIATCO and FraportAG also filed compensation claims before international parties, particularly:(a) the Singapore-based International Chamber of Commerce (ICC) Court ofArbitration for PIATCO’s US$565 million claim against the PhilippineGovernment; and (b) the World Bank’s International Center for theSettlement of Investment Disputes (ICSID) in Washington, D.C. for FraportAG’s US$425 million counterpart claim. In August 2007, the ICSID dismissedFraport AG’s claim of compensation for NAIA Terminal III saying it had nojurisdiction over the matter. On the other hand, PIATCO indicated that itremains open to reaching an amicable settlement with the PhilippineGovernment.

According to the Philippine Government, NAIA-III is 98 percent completeand will require at least an additional US$6 million to complete. Thegovernment is in the process of negotiating a contract with the builder of theterminal, Takenaka of Japan. Another factor that has delayed the terminal’sopening was the investigation on the collapse of a 100-square meter area of

Page 111: Areview of BOT for Developing Project

Box 6 (cont’d.)

the terminal’s ceiling. It seems that concerns over safety and other proposedtest runs for Terminal III have been postponed indefinitely pending theresults of the investigation and the inspection of the airport terminal.**

* References for Terminal III issues:(a) Lala Rimando, Government wins one of its biggest international arbitration cases, NewsBreak[online], Public Trust Media Group, Inc., 17 August 2007.

(b) Rafael S. Santos, Businessmen remind government to keep policy on course, Manila Times,September 14, 2006.

(c) Supreme Court Jurisprudence, En Banc Decision, Agan Jr. vs. Piatco, G.R. No. 155001,155547, and 155661, May 5, 2003.

(d) Roel Landingin, A commercial compromise: a less than perfect solution may be the onlyway to open NAIA-3, Newsbreak, February 11, 2007 [online]. http://www.newsbreak.com.ph/index.php?option=com_content&task. [Accessed January 14, 2008.]

(e) http://en.wikipedia.org/wiki/Ninoy_Aquino_International_Airport.** News sources recently reported another portion of the ceiling collapsing after a strong typhoonvisited Metro Manila.

proposals because of their access and familiarity to cutting edge technologyand innovations that could inform BOT projects. The country may benefitfrom having efficient, cost-effective, and innovative infrastructure facilitiesthat may be provided by those unsolicited projects. In this regard, it wouldbe useful to improve the mechanism for allowing challenges to theunsolicited project. The selection process could be made contestable bygiving potential challengers sufficient time to match the unsolicited projectwith their own proposals. Constraining the space for unsolicited projectsas earlier argued could be a workable alternative to the complete scrappingof this mode of procurement. Nevertheless, it is emphasized thattransparency and integrity of the selection process would be indispensable.Appropriate disclosure to the public of details of the unsolicited proposaland open discussion of its advantages and disadvantages should be adoptedas policy.

Hodges and Dellacha (2007) point out that channeling unsolicitedproposals into a transparent, competitive process gives other companiesa fair chance of winning the tender. This can reduce the risks whilepreserving the potential for innovative solutions. They describe a two-stage process followed by most countries: Stage 1 consisting of severalprocedures for approving the unsolicited proposal and Stage 2 whencompetitive tender is made. Stage 1 is the approval stage. During this

Llanto 105

Page 112: Areview of BOT for Developing Project

106 A Review of Build-operate-transfer for Infrastructure Development

stage, the unsolicited proposal is submitted and reviewed by the responsiblegovernment body. Preliminary acceptance of the proposal leads to thesubmission of a full detailed proposal, which is reviewed and may beapproved for a competitive process or rejected. If accepted, an opencompetitive tender follows (Stage 2). Rejection does not necessarily meanthe end of the proposal. In some countries, a proponent may submit amodified version. In Chile, the government may use the unsolicited projectconcept in a public bid after a period of three years. In the second stage,the project is competitively bid under any one of three systems; bonus, Swisschallenge, or best and final offer. The three systems are shown in Box 7.

Project implementation and constructionAfter satisfaction of the necessary legal, environmental, and socialrequirements and the availability of the necessary financing, theconstruction of the infrastructure facility begins. This is usuallyundertaken by the contractor who has hired the construction crew,suppliers, and technical and project management consultants, and has

Box 7. Competitive tender of unsolicited proposals

Bonus system. Chile and Korea use a system to promote unsolicitedproposals that awards a bonus in the tendering procedure to the originalproject proponent. This bonus can take many forms but most commonly it isan additional theoretical value applied to the original proponent’s technicalor financial offer for bidding purposes only.

Swiss challenge system. Used in Guam, Philippines, India, Italy, andTaiwan, it gives the original proponent the right to countermatch any betteroffers. If the original proponent does not match the better price, the projectis awarded to the third party. In Guam, if the original proponent matchesthe better price, the government awards the project on the basis of technicalmerit.

Best and final offer system. Here, the key element is multiple rounds oftendering, in which the original proponent is given the advantage ofautomatically participating in the final round. In South Africa, the two mostadvantageous bids are selected for a final bidding round. If the originalproponent is not one of these two, it will still automatically be allowed to competein the final round. In all cases, the final round is an open competition duringwhich the preferred bid will be selected with no bonuses or advantages given.

Source: Hodges and Dellacha (2007).

Page 113: Areview of BOT for Developing Project

done the project design and detailed engineering for the infrastructurefacility. It is important to ensure that the private proponents includingthe contractor will have not only the management and technical expertisebut also the financial muscle to move the infrastructure project tocompletion and subsequent operation. A supportive policy environmentwill be a fundamental requirement for private risk-capital to be channeledtoward lumpy, long-gestating infrastructure projects. Adoptingtransparency as a policy in developing the joint venture helped in firmingup the partnership between government and the private sector. Box 8shows a good example of a successful public-private sector partnership ininfrastructure provision.

A review of Philippine experience with infrastructure projects, notjust BOT projects, shows that delays in project implementation wouldusually arise due to a rise in project costs, construction problems, right-of-way problems, and others. Implementing government agencies wouldthen make representation with the oversight NEDA-ICC body for contractvariation to support the requested increase in project funding sought bycontractors. The proposed increase in project funding may arise from anexpansion in the scope of a project, alteration of design, and other factors.However, poor project quality at entry is a common denominator. Poor orcomplex project designs and inefficient project management andconstruction are common causes of the escalation of project costs.Sometimes, implementing government agencies cite inflation and currencymovements as a reason for cost escalation. However, it cannot be deniedthat poor project planning, identification, and preparation together withinefficient project implementation are the real reasons for the reportedcost overruns.84

The 16th ODA Portfolio Review (2007) reported the following as topthree causes of cost increases of projects that underwent NEDA-ICC reviewin 2007: (a) increase in unit cost of labor, materials, and equipment/priceadjustment/price escalation with 29 percent of the total causes of costincreases of projects; (b) changes in scope which accounts for 25 percent;and (c) high bids with 22 percent (Table 17).

In this regard, the 16th ODA Portfolio Review submitted by NEDA toCongress has called attention to: (a) greater and more serious attentionby the implementing and oversight agencies on project preparation andplanning, risk assessment, review of feasibility studies, among others, to__________________84 Per the ODA Act of 1996, cost overrun is defined as additional costs over and above the ICC-approved project cost.

Llanto 107

Page 114: Areview of BOT for Developing Project

108 A Review of Build-operate-transfer for Infrastructure Development

Box 8. Manila North Tollways-North Luzon Expressway1

The North Luzon Expressway (NLE or NLEx), also called North DiversionRoad, is a limited-access toll expressway that connects Metro Manila to theprovinces of the Central Luzon region in the Philippines. It is one of the twobranches of the Road 8 major radial road of Metro Manila (Quirino Highwayis the other).

The expressway begins in Quezon City at a cloverleaf interchange withEpifanio delos Santos Avenue; a logical continuation of Andres BonifacioAvenue. It then passes through Quezon City, Caloocan City, and ValenzuelaCity in Metro Manila; Meycauayan, Marilao, Bocaue, Balagtas, Guiguinto,Plaridel, and Pulilan in Bulacan; and San Simon, San Fernando City, Mexico,and Angeles City in Pampanga. The expressway currently ends at Mabalacatand merges with the MacArthur Highway, which continues northward intothe rest of Central and Northern Luzon.

The expressway, including Andres Bonifacio Avenue, has a total lengthof 88 kilometers. The expressway segment has a length of 84 kilometers. Itis currently being extended by 44 kilometers starting from its current end inMabalacat, Pampanga up to Tarlac City in Tarlac. Its extension is part ofthe Subic-Clark-Tarlac Expressway Project. It may be extented up to LaoagCity in Ilocos Norte and there are plans to have a spur route going to BaguioCity to provide motorists going to the summer capital a fast and safe journey.The extension passes through (in the future) the rest of Tarlac City, Gerona,Paniqui, and Camiling in Tarlac; Bayambang, Basista, Malasiqui, Villasis,Urdaneta City, Binalonan, Pozzorubio, and Sison in Pangasinan; Rosario inLa Union; and Tuba and Baguio City in Benguet.

Originally controlled by the Philippine National ConstructionCorporation (PNCC), operation and maintenance of the NLEx in 2005 wastransferred to the Manila North Tollways Corporation, a subsidiary of theLopez Group of Companies. A major upgrade and rehabilitation has beencompleted in February 2005 and the road has now similar qualities as amodern French tollway. The main contractor of the rehabilitation work wasLeighton Contractors Pty. Ltd. (Australia) with Egis Projects, a companybelonging to the French Groupe Egis as the main subcontractor for the toll,telecommunication, and traffic management systems. To help maintain thesafety and quality of the expressway, various rules are in effect such asrestricting the left lane to passing vehicles only and banning overloadedtrucks.

The tollway has two sections: an open section and a closed section. Theopen section (within Metro Manila) charges a flat toll based on vehicle classand is employed to reduce the number of toll barriers (and associatedbottlenecks) within the metropolis. The closed section is distance based,

Page 115: Areview of BOT for Developing Project

Box 8 (cont’d.)

charging based on the class of vehicle and distance traveled. Class 1 vehiclescan use an electronic toll collection system (called EC Tag) to reduce waitingtimes and congestion at toll barriers. A prepaid magnetic card (the NLEBadge) is provided as an alternative payment for class 2 and 3 vehicles.Both systems connect to accounts that can be replenished in various ways.Travelers not using EC Tag or the NLE Badge on the closed system willinstead be issued tickets describing tolls for the various exits. In order tosave costs concerning toll barriers at exits, many exits on the NLEx haveexit and entrance ramps running alongside each other so that both may beserviced with a single toll barrier.

The Lopez Group took on the challenge of providing an efficient transportfacility north of Manila and ventured into road infrastructure to improveand upgrade the NLEx. Through First Philippine InfrastructureDevelopment Corporation (FPIDC), the Group partnered with the Philippinegovernment through the PNCC, whose franchise allows it to enter into jointventure schemes and to choose its partners without the need for a publicbidding. The resulting joint venture created the Manila North TollwaysCorporation (MNTC) which was mandated to finance, rehabilitate, operate,and maintain the NLEx until 2030. MNTC also invited Egis Projects S.A. ofFrance, Leighton Asia Limited of Australia, and PNCC to partner with itthrough equity funding and construction activity.2

The rehabilitation of the NLEx is a joint venture between the governmentand the private sector, for which the MNTC was granted the concession tofinance, redesign, rehabilitate, expand, operate, and maintain the NLExunder a Supplemental Toll Operation Agreement (STOA). The STOA wassigned in April 1998 by the MNTC, PNCC, and the Republic of thePhilippines acting through the Toll Regulatory Board (TRB). It wassubsequently approved by former President Fidel V. Ramos in June 1998.

Under the STOA, all usufructuary rights, interests, and privileges ofPNCC were transferred to MNTC. This gives MNTC the right to collect tollfees during the concession period of 30 years so that it may continue tomaintain the expressway, recover its investment, and settle the long-termloans used to finance the project. The new NLEx uses a reasonable andinternationally accepted direct road-user fee principle for revenue collection.Unlike government infrastructure projects that are subsidized by taxes(which, in effect, makes nonusers of the infrastructure pay for its servicesthrough the taxes they pay), the toll fees will only be paid by those whodirectly use the NLEx. Investments for the NLEx project may only berecovered through toll fees and not through tax revenues. This ensures thatpeople who do not use the NLEX will not be burdened with the cost of the

Llanto 109

Page 116: Areview of BOT for Developing Project

110 A Review of Build-operate-transfer for Infrastructure Development

Box 8 (cont’d.)

project. After the concession period, the project roads—plus alldevelopments—will revert to the government at no cost.3 Those who do notwant to use NLEx have the option of using the parallel (nontoll) road calledthe MacArthur Highway to reach destinations north of Manila.

Because of the benefits reaped by the country through the rehabilitationof the NLEx, other developing countries are actually using the project as themodel for government and private sector partnership. The private sector’sinvesting in infrastructure development projects is essential since it enablesthe government to use its limited resources for other vital services likeeducation, housing, agriculture, and health. The project financing for theproject, acknowledged by Project Finance Magazine in its February 2003issue as a “considerable benchmark for transport financing in Asia,” wasobtained despite the country’s low credit rating. The project was named the“Asia Pacific Transport Deal of the Year” in 2001 by the same publication.

1 Source: http://en.wikipedia.org/wiki/North_Luzon_Expressway (date accessed January 14,2008.)2 This paragraph and subsequent paragraphs are from http://www.mntc.com/nlex/overview2.htm(accessed 14 January 2008.)3 Ibid.

come up with better project proposals; (b) implementation readiness of aproject including the availability of counterpart funds before loan andcontract negotiation; and (c) adequate or accurate estimation ofcontingencies during project design. The specific bottlenecks to the efficientimplementation of ODA-funded projects, which also hold true for BOTprojects are summarized in Box 9.

OperationAfter the facility is built, the concessionaire designates an operator tooperate and maintain the facility. The operation lasts until the terminationof the concession period. Critical at this stage is the efficient operationand maintenance of the infrastructure facility. Clear assignment of rolesand responsibilities helps a great deal in ensuring that the service to beprovided through the infrastructure facility will meet certain performancestandards. The best Philippine experience with this stage of infrastructureproject operation and maintenance is the globally renowned waterconcession operated by Manila Water Company. Box 10 summarizes theexperience.

Page 117: Areview of BOT for Developing Project

TransferUpon completion of the cooperation or concession period, the ownershipof facility and all its assets are then transferred to the host government.Transfer can also be done prior to the expiration of the concession periodbut the concessionaire has to be compensated properly for the investmentsmade in the project. The government may then operate the facility itselfor decide to hire an independent operator. There is yet no experience inthis area because at present the BOT/concession agreements are stilloperating within the contract or concession period.

Goals and typical contractual agreements of the majorparticipants85

The presence of several actors and the different stages of a BOT projectgive rise to a complex relationship, which makes imperative closecooperation and collaboration to ensure that the project will lead tocompletion and efficient operation with minimal problems. Theparticipants in the BOT project may have different objectives and goals,which may conflict directly with each other. For instance, the hostgovernment may want to provide the public with as wide an access aspossible to the infrastructure facility and this may involve controlling fees

Table 17. Breakdown of cost increases

Reason for Cost Increase Amount in Pesos % to Total (million)

Total (21 projects) 33,499.92 100.00Increase in unit cost of labor, materials, equipment/

Price adjustment/price escalation 9,705.39 28.97Changes in scope, variation orders, supplemental

agreements 8,267.84 24.68High bids (bids above ABC/AAE) 7,241.18 21.62IDC, VAT, and other taxes 3,372.63 10.07Foreign exchange movements 2,003.92 5.98Increase in cost of consulting services 1,522.34 4.54Increase in administrative costs 1,260.57 3.76Increase in cost of right-of-way, land acquisition,

resettlement costs, price adjustment of land 106.06 0.32

__________________85 Part of the discussion in this section and the next two sections draws from Meenhere andPollalis (1996).

Llanto 111

Page 118: Areview of BOT for Developing Project

112 A Review of Build-operate-transfer for Infrastructure Development

Box 9. Bottlenecks to efficient implementation of ODA-funded projects

Cost overrunsThese are caused by: (a) additional civil works (changes in scope/variationorders/supplemental agreements); (b) increase in right-of-way/landacquisition/resettlement costs; (c) increase in unit cost of labor, materials,and equipment; (d) high bids (bids above Approved Budget for the Contract/Approved Agency Estimate); (e) currency exchange rate movement; (f)increase in consultancy services; (g) increase in administrative cost; and (h)claims for price escalation.

Budget/financing issuesThe reenactment by Philippine Congress of the budget for 2006 limited thefinancing cover for ongoing projects to its 2005 levels. This also meant thatno new appropriation was allocated for newly approved projects.

ProcurementDelays in procurement were brought about by (a) lengthy review process; (b)restraining orders filed by losing bidders; (c) suspended bidding proceedingsdue to contested procedures by one of the bidders or delay in approval by thefinancing institution; and (d) failure in bidding/rebidding of contracts.

Right-of-way (ROW)/land acquisitionROW and land acquisition bottlenecks remain to be a major bottleneck dueto: (a) delayed judicial action on the titling of acquired properties; (b)unresolved issues on land ownership; (c) relocation site no longer available;(d) new batch of informal settlers reoccupied the previously cleared areas;and (e) change in local government leadership, priorities, and commitments.

LGU issuesLGUs’ capacity to put up the required counterpart for projects continues tobe a problem. Other LGU issues include the limited technical capability ofsome LGUs particularly those in the lower income class and changes inLGU leadership, priorities, and commitments.

Contractor performancePoor performance of the contractors were noted in terms of weakmanagement, late mobilization and/or insufficient equipment and materialson site, insufficient technical manpower, technical problems, i.e., frequentbreakdown of equipment, and changes in design concept and uncertainty inthe financial capability of the contractor.

Page 119: Areview of BOT for Developing Project

or regulating fee increases in order to make the facility affordable tomembers of the community.

On the other hand, the concessionaire and the investors who wantto make profits or have a high return on their investments may considercharging higher user fees for the facility. Lenders aim to make their long-term loans safe and profitable. Equity investors want to have a high returnon investment in proportion to the risks they face. The contractor wantsto increase the price of their contract for the construction of the facility.The users aim to use the facility at the least cost to them. In certain cases,there could even be expectations that the government should provide thefacility for free. Therefore, there must be some mechanism that will providethe incentives to balance these diverse and oftentimes conflicting goals.The contract is the principal means by which parties align their individualgoals to make the project operational. As argued above, a BOT contractmay partake of the nature of incomplete contracts and thus, the challengeto participants, including the policymakers who craft the so-called “rulesof the game,” is to find incentive-compatible contracts.

There will naturally be a great number of contracts among all theinvolved parties in the BOT project. The following are the main contractsthat are inherently present in all these projects.

Concession agreementThis is the agreement between the host government and the concessionaire.It is the main contract in a BOT project. Under the concession agreementthe following are specified:

the concession period, the starting date, and the terminal date;the structure of the concessionaire;the financial scheme;the construction duration and process;

Box 9 (cont’d.)

SustainabilityThere were also instances of weak postcompletion performance monitoring,operation, and maintenance for some completed projects which raisedconcerns on the sustainability of the projects.

Source: ODA Portfolio Review 2006.

Llanto 113

Page 120: Areview of BOT for Developing Project

114 A Review of Build-operate-transfer for Infrastructure Development

Box 10. Manila Water concession: key lessons and challenges

The privatization objectives were as follows:expand service coverageimprove delivery of serviceincrease operating efficiency

The Metropolitan Waterworks and Sewerage System (MWSS) wasresponsible for delivering water service and to do this, it employed 7,000people. After August 1, 1997, through the concession agreement, the twoselected operators or concessionaires, namely, Manila Water Company andMaynilad Company, were required to deliver the service in behalf of MWSSand in return for investment they will get reimbursed.

Delivery of water is done through an infrastructure that is very expensiveto maintain such as aqueducts, treatment plants, pump stations, meters,branch offices, and leased water facilities. These facilities are owned by theMWSS but the concessionaires are allowed to use these facilities under theprivatization arrangement. Under the Asset Management Obligation, theconcessionaires are required to operate, maintain, refurbish, expand, etc.This involves a very challenging service obligation such as provision of watersupply; sewerage and sanitation; and customer service.

The service obligation drives the tariffs. Labor and power accounts for70 percent of operating costs. The Manila Water Company, Inc. (MWCI) hasinvested US$70–80 million on an annual basis over the next 10–15 years.Full cost recovery is very important for the private sector to sustain capitalinvestment. The regulator reviews the concessionaires’ business plans andrate rebasing every five years. During the interim period they get inflationadjustment. This is because 100 percent of the debts are in hard foreigncurrency. Adjustments are given to cushion the concessionaire from foreigncurrency differential as well as unlikely events such as the El Niñophenomenon.

Manila Water is also one of the organizations that can claim to servicethe needs of the poor. It has provided interconnections or piped water supplyto over 850,000 people in informal settlements or low-income areas such asthe Manggahan floodway with 60,000 households. It has also invested morethan US$200 million to make interconnection possible for hundreds ofthousands of households. Sewerage is one of the neglected areas of the watersector. It has very small coverage and this will drive MWCI’s expenditureplan over the next 15 years. World Bank will help provide US$64 million toexpand the coverage.

Page 121: Areview of BOT for Developing Project

Box 10 (cont’d.)

Lessons learnedThe concession approach may be appropriate in Metro Manila but maynot be in some other areas. It depends on the reform objectives.There are investible resources. Competitive bidding is important butthe windfall gain accruing to the government might send the wrong signalto the customers that the resource is cheap and abundant. Using thelowest priced service as a rule to select a concessionaire might limit theflexibility of the players in terms of addressing shocks such as the majordevaluation that was experienced in 1997.Trust and confidence of employees are necessary.Key determinants of success are good timing and political will of thenPres. Ramos. He had a dedicated team that oversaw the transaction tobe completed in less than 24 months; there were clear objectivessupported by the private sector.It takes time to establish credibility of winning concessionaire.There is a need for appropriate arbitration mechanisms; review ofcontract considering the changing operating environment; the concessionrequires full asset recovery.It is important to have a good cash flow and to maintain affordable tariffs.

Source: Presentation made by Mr. Virgilio Rivera, Business Development Group Headof Manila Water Company, during the Roundtable Discussion with the Business Sectoron the Amendments to the BOT Law, February 21, 2006, Holiday Inn, Pasig City,conducted by the Economic Policy Reform and Advocacy.

tariff structure with tariff revision provisions;rights and obligations of both parties, that is, the governmentand private party; andguarantees (financial and material).

Loan agreementThe loan agreement is made between the lenders and the concessionaireand specifies the amount to be lent with the specific repayment periodand mode, the different guarantees, and the agreed terms and conditionsof the loan. The limited recourse nature of BOT projects may promptlenders to demand adequate security. The contract may include theprovision that project revenues be stored in one or more special debt-reserve escrow account to ensure payment of senior debt before any

Llanto 115

Page 122: Areview of BOT for Developing Project

116 A Review of Build-operate-transfer for Infrastructure Development

distributions can be made to equity investors (Augenblick and Custer1990). Other guarantees may include the right for the lenders to takeover the operation of the facility in the event that the concessionaire isnot able to meet financial obligations. In other instances, theconcessionaire negotiates with the host government for guarantee of theloans made with creditors.

Shareholder agreementThe shareholder agreement is between equity investors and theconcessionaire. Equity financing is oftentimes raised by the consortium’sown capital funds although other external equity investors may infusefunds. The contract specifies the detailed agreement on the mode ofpayment and the distribution of revenues and dividends to the investorand the prescribed debt-to-equity ratio.

Construction contractThe contract between the construction contractor and the concessionaireis usually a fixed price turnkey contract. There also may be a single overallcontract which encompasses both design and construction. The fixed priceturnkey contract may be the most efficient contract to reduce the risksrelated to project time, quantity, and costs. The penalties for late deliveryof the contractor are stipulated in this contract.

Operation and maintenance contractThis contract plays a very vital role since this has serious implications onthe revenue-generating capability of the project and the longevity of theasset. Specifics may include the level of rates or user charges for the facility,the formula or procedure for rate adjustment, details of the use of thefacility, reimbursement for maintenance costs, and others.

To be successful, a BOT project should be able to harmonize andreconcile all these contracts to meet a common end: an efficientinfrastructure that provides good service to the public and satisfactoryrates of return to investors, shareholders, the operator, and lenders.Harmonization is not an easy task as indicated by the earlier discussionof incomplete contracts. It should be borne in mind that these contractsreflect the risk-bearing ability of the parties concerned and the tendencyfor any party is always to minimize the risks it faces and transfer these asmuch as possible to parties most able to bear them. This requires a verygood understanding of the nature of the risks faced by all actors, e.g., thelikely events that would trigger the occurrence of the risk and the

Page 123: Areview of BOT for Developing Project

appropriate risk mitigation instrument. Transparency in contracting whichspecifies who is responsible in bearing a particular risk will help to ensurethat opportunistic behavior and confusion will be minimized. The nextsection presents some of the most common risks that a typical BOT projectwill face and of the risk management and mitigation responses that canbe incorporated in the contract.

Risks in BOT projectsExposure to risks is oftentimes greater in the earlier stages of the projectand so monitoring must be more intense during the early stages. Themost common risks in a typical BOT project are listed below.

Completion riskIn any typical BOT project, there is a risk that the construction may notbe completed on time and in the agreed price. The solution to this risk isfor the concessionaire to offer a fixed price, firm date, and turnkeyconstruction contract with concomitant penalties stipulated by liquidateddamages. This clause states the monetary damages payable by thecontractor for each unit of time delay in the completion of the project orthe completed project’s inability to meet specifications. Thus, cost overruns,hidden defects, and other related problems become the responsibility ofthe construction contractor. The price of the turnkey contract then reflectsthe risk that the construction contractors have to bear. Another way toobviate completion risk is for the consortium to include the constructioncontractor as a partner or participant in the consortium. In this way, theinformation asymmetry between the concessionaire and the constructioncontractor, which may give rise to moral hazard problem, will beeliminated.

Performance and operating riskThere is also a risk that a project will not perform according to what isexpected from it. These failures may include technical failures,interruption, and management or labor incompetence. This may bemitigated by warranties from the construction contractors and equipmentsuppliers and also by performance guarantees in the operating andmaintenance contract.

Cash flow risksDisruptions of cash flow may jeopardize the repayment of debt to theproject’s lenders. These disruptions are usually precipitated by a change

Llanto 117

Page 124: Areview of BOT for Developing Project

118 A Review of Build-operate-transfer for Infrastructure Development

in market demand conditions, for instance, sudden disruption of tariffrevenue brought about by a downturn in purchasing power of theconsumers. The usual response is to specify in the contract the opening ofan escrow account as what was discussed earlier. Another is for the hostgovernment to guarantee a portion of the revenues generated by thefacility, for instance, a minimum off-take agreement.

Inflation and foreign exchange risksRapid inflation and exchange rate spikes may alter the returns to bothlenders and equity investors. These risks are deemed to be beyond thecontrol of lenders and equity investors but may be addressed bygovernment policy action. This is the reason host governments are almostalways asked to provide cover for these risks. For instance, indexation ofuser fees and revenues from off-take contracts are used to cover for therisk of inflation. Governments are also asked to provide sufficient foreigncurrency in case of supply disruptions or index the tariff rates to the rateof inflation to preserve the real value of profits.

Insurable risksInsurable risks, e.g., manpower casualty, can be sufficiently covered byvarious form of insurance. The insurance may come from commercialsources or from government guarantees.

Force majeureThese risks are sometimes uninsurable or can be insured at a veryprohibitive cost. The government may be asked to cover or seek cover forforce majeure risks that are uninsurable. Force majeure risks are ofteninsured by entities such as the Overseas Private Investment Corporationand the Multilateral Investment Guarantee Agency.

Political risksThese risks may, in general, include any deviation by the host governmentfrom any specific undertakings or agreement provided for in the project.It also includes risks such as those precipitated by political violence—war, insurrections, or sabotage—that may disrupt the operation of a BOTfacility. This also includes problems of law and order, the threat ofexpropriation or nationalization by the host government, or even a changein political leadership, which questions the legality or appropriateness ofa BOT project approved by the predecessor government. Foreigncommercial lenders and equity investors want to seek political risk

Page 125: Areview of BOT for Developing Project

insurance from sources such as the government itself (through sovereignguarantees), export credit agencies, or other multilateral agencies.

Regulatory risksThe regulatory regime also posts some risk with regard to tariff rates,volume, or quality of services. Rules may be hazy or easily subjected topolitical intervention, which puts at risk the viability of the BOT project,e.g., fixing or controlling charges/fees, unclear formulas for rate or feeadjustment, among others. The creation of credible and independentregulatory agencies is seen as the first step to mitigate such regulatory risks.

Risk mitigation instrumentsOne of the means for a BOT project to succeed is to mitigate the risk thatcan be identified. Risks are often within the control of one or more of theparticipants but some are out of the participants’ hands. A basic principleis that the party who is in the best position to manage the risk shouldbear that particular risk and should be duly compensated for it. However,Philippine experience shows that in some cases commercial risk that moreproperly belongs to the private sector has been assumed by the government(Box 11). The government should be more careful in the future with the

Box 11. Risk sharing in Philippine BOT projects

Risk Casecnan MRT 3 San Mateo NAIA 3 StarLandfill

Construction private private private private privateproponent proponent proponent proponent proponent

Exchange rate government government government government governmentInterest rate private private private private private

proponent proponent proponent proponent proponentPerformance private private private private private

proponent proponent proponent proponent proponentRaw water/ government n.a. n.a. n.a. n.a. hydroOperating cost private private private private private

proponent proponent proponent proponent proponentDemand government government government private private

proponent proponent

Source: National Economic and Development Authority (NEDA).

Llanto 119

Page 126: Areview of BOT for Developing Project

120 A Review of Build-operate-transfer for Infrastructure Development

assumption of risks that should properly be absorbed by the private sector.The earlier case study of Casecnan is a very vivid picture of what thegovernment should not have done in the first place because the burdenwas unnecessarily put on the shoulder of the unsuspecting taxpayer.

There may be some risks that cannot be insured or that are tooprohibitively costly to insure. To encourage private investors, thegovernment usually intervenes by providing guarantees, subsidies, andsimilar support. It seems that BOT projects in developing countries are inreality rarely a 100 percent private undertaking with purely private risktaking and without any form of commitment or support from the hostgovernments. There are several factors such as underdeveloped capitalmarkets, political instability, regulatory uncertainty, and others that maydeter private investments in infrastructure and thus, the government stepsin to eliminate or minimize such risks to the project. The following aresome of the common support given by governments for the developmentand implementation of BOT projects.

Political and bureaucratic supportStrong political support by the highest leadership of the country is aneffective way to facilitate the acceptance of any project. A president, primeminister, or key legislators championing the cause of private participationin infrastructure can thwart bureaucratic resistance from entrenchedpublic sector entities, which could have an interest to build and operatethe facility itself instead of the private sector. Political leadership canlikewise convince the doubting citizenry about the importance of the BOTfacility through effective communication of its advantages to thecommunity and transparent procedures for review and approval of theproject, among others. The successful experience with the privatization ofwater supply distribution in Metro Manila showed what a determinedpresident could do for the welfare of the people.

Assured suppliesThe government may provide some logistical support such as land, right-of-way, raw materials, or steady supply of energy required during the lifeof the BOT project.

Assured revenuesIn instances when the government is a major purchaser of a BOT output,it commits to a steady revenue stream to make the project viable therebyattracting both lenders and equity investors to provide funding for the

Page 127: Areview of BOT for Developing Project

project. For instance, the government could pledge a “minimum off take”or “take-or-pay” guarantee for the power generated from BOT-built powerplants or guarantee ridership in a rail project in order for the concessionaireto be able to pay off both debts to lenders and dividends to equity investors.This is precisely what the government did to encourage private sectorinvestments in generation plants as a solution to the severe power crisisin the early 1990s.

Loans/equity contributionsIn some instances, government may provide loans or infuse capital toBOT projects. This helps the concessionaire to be more independent fromlenders and sponsors and gives it more bargaining power to negotiate forconstruction contracts and equipment supplies. Transparency is also thereason governments provide loans and equity. The government candemand transparency of the project’s financial structure in return for thesupport

Earning assetsThe government can also allow public sector assets to be used by theconcessionaire to pay capital costs, debt service, and operating expense.Some examples are public toll roads, which are made available to theconcessionaire after the award of the operation and maintenance of thetoll road. In the case of Metro Manila rail projects, private proponentshave been allowed to exploit the commercial opportunities in certainstations by renting space to various establishments.

Regulatory, fiscal, and other supportThere may be legislation needed to help the private company push throughwith the project. Legislator can enact laws to make conducive the legaland regulatory environment to long-term private investments. Some formof tax incentives such as tax holidays, exemption from stamp, and customstaxes may also be given to BOT concessionaires. Salaries of foreignexpatriates may also be exempt from local taxes. In the case of thePhilippines, the BOT, as earlier stated, is a good basic law but it standssome improvement. The same may be said of the IRR, which should providea transparent and facilitative process to get BOT projects competed andsubsequently implemented.

Project risk supportIn case of project failure or interruption in the cash flow of the facility, the

Llanto 121

Page 128: Areview of BOT for Developing Project

122 A Review of Build-operate-transfer for Infrastructure Development

government can intervene to provide loans on a standby basis over a fixedperiod of time to provide for debt service.

Inflation and foreign exchange coverThese covers may come in the form of price escalation clauses initiated bythe government. Indexation of user fees or tariffs to inflation is the mostcommon form of support although the form and timing may be politicallycostly and time consuming to develop or organize. In the case of rapidforeign exchange fluctuation, the government must be able to assureforeign investors of the convertibility of local currency earnings into foreigncurrency and that it will provide sufficient foreign currency to meet thedemand of these investors.

Sovereign guaranteesSovereign guarantees are called upon in the event that the concessionairedefaults in the payment of a loan to its lenders.

Protection from competitionThe government can influence the environment to make the BOT projectmore viable. For instance, it can stop the development of parallel nontollroutes to make the toll routes more profitable during the concession period.

Institutional frameworkUnder the current IRR of the BOT Law, implementing agencies prepareBOT projects for competitive bidding or undertake the feasibility studiesand submit the necessary documents for review and approval by the NEDA-ICC. Unsolicited project proposals, including the draft contract, are alsoreviewed by the oversight agencies composing the ICC upon endorsementby the implementing agencies. In the case of unsolicited projects, theNEDA-ICC gives approval upon finding merit and the implementingagencies are then asked to hold a Swiss challenge and make an award.

However, as explained earlier, there have been recent attempts toamend the BOT Law IRR with the end in view of facilitating the projectapproval and award process. The proposed amendments to the BOT LawIRR have two main parts: (a) assigning implementing agencies to reviewand approve specific BOT projects and contracts while confining the NEDA-ICC role to merely checking whether the BOT project concerned is in thepriority list; and (b) shortening the processing time for BOT projects. BOOprojects would still need approval by the President of the Philippines afterrecommendation by the NEDA-ICC. Under the proposed amendments to

Page 129: Areview of BOT for Developing Project

the BOT Law IRR, implementing agencies will prepare a list of priorityprojects and submit this to the NEDA-ICC for approval. This will effectivelymake the NEDA-ICC a mere “clearing house” for preferred BOT projects.As formulated in the draft rules, government agencies will prepare their“list of priority projects.”

There must be a transparent institutional framework for projectidentification, review, and approval. The Philippine experience shows theimportance of having oversight agencies that have the responsibility forproject review and approval while line departments or ministries (agencies)are responsible for identifying and preparing terms of reference and scopeof work for BOT projects to be tendered. Line ministries should not beinvolved in project review and approval because this will conflict withtheir role in identifying projects that may be financed and constructedunder the BOT approach.

An effective implementation of the BOT approach and, in general,public-private partnership requires more accountability on the part ofthe implementing agencies. Their officials should be accountable for theprocurement contract as well as monitoring of the BOT project. Monitoringrequires vigilance over delivery by the private proponent of its contractualobligations. The implementing agencies and the oversight agencies shouldobserve transparency from project identification to procurement to contractimplementation. A copy of the signed contract should be available to theimplementing agencies and the oversight agencies. Moreover, BOTcontracts are imbued with public interest and should likewise be accessibleto the public.86

The government should also allow the private proponent to levy usercharges that provide a return commensurate to the opportunity cost of itsinvested funds and ensure appropriate maintenance of the infrastructurefacility. This will ensure project viability. The proper allocation of costand risk sharing is likewise vital. Some risks are uninsurable. In thiscase, the partnership must allow for some form of co-insurance thatprovides for sharing of the identified risks.

__________________86 It is very difficult to get information on approved contracts notwithstanding the public interestaspect of such contracts, which imply that they should be opened to public scrutiny. This writerwas told by government agencies that there is no official government agency that has beendesignated as repository of BOT contracts. Such contracts are lodged in agencies that aredirectly responsible for projects implemented under a BOT approach, e.g., DOTC will havecopies of BOT projects on transport, etc. Not one agency has a complete file of all those contracts.

Llanto 123

Page 130: Areview of BOT for Developing Project

Contracts and regulationAnother difficult area is contract writing where implementing agenciesmust have a good understanding of the obligations of each party in aproject; financial terms and conditions for the financing provided byexternal creditors, including guarantees, subsidies, or equity to be providedif the project is eligible; and contractual provisions on risk allocationincluding assisting the project secure financing and ensuring its financialviability and sustainability. Implementing agencies do not necessarily havethe skills for contract writing.

The result is that during negotiations, the implementing agenciesmay not be adequately informed about the implications of the contractualprovisions they have committed to the private partner. Obviously, theimplementing agencies must develop capacity not only for contract writingbut also for monitoring of contract implementation.

An example of a complex area is the provision on ContractTermination, a standard provision in contracts here and abroad. Thelanguage for the said provision should be thoroughly understood by thegovernment agency concerned, reviewed, and tailored to ensure that thegovernment’s (that is, public) interest is protected. The private investorinterest will almost surely be protected given their access to the best legaladvice that money can buy. On the other hand, creditors normally demandprovisions on contract termination as a protection. They do not lend to projectsunless such provisions are expressed with clarity and could be enforceable.

Third party evaluation of projectsIt will also be good to introduce as a norm, the evaluation of projects duringactual implementation and also after a period of time following theirimplementation. The idea is to assess whether or not actual projectimplementation delivers the development outputs envisaged during theproposal and approval stages. The evaluation should be done byindependent organizations such as reputable research and academicinstitutions. Implementing ministries or agencies and the privateproponent/operator of the BOT project should make available to third partyevaluators such data as may be necessary for proper evaluation. Theestablishment of benchmarking indicators or information will beindispensable for an effective evaluation of project impacts.

124 A Review of Build-operate-transfer for Infrastructure Development

Page 131: Areview of BOT for Developing Project

The energy crisis in the late 1980s and the weak fiscal position of thegovernment forced the Philippine government to seek private sectorsupport in carrying out infrastructure priority projects. In December 1990,the Philippine Congress enacted the Build-Operate-and-Transfer Law,otherwise known as RA No. 6957, “An Act Authorizing the Financing,Construction, Operation, and Maintenance of Infrastructure Projects bythe Private Sector and for other purposes.” Said law was subsequentlyamended by RA No. 7718 in April 1994 to increase private investment inother infrastructure sector among other features. The first wave of BOTprojects involved the execution of power purchase agreements betweenthe National Power Corporation and independent power producers. OtherBOT projects such as mass rail transit, toll ways, etc., followed.

Using examples from selected BOT projects in the country, the paperpointed out key issues constraining the successful implementation of theBOT approach to infrastructure provision. It also indicated from thoseexamples several factors that were instrumental in forging an effectivepublic-private partnership in infrastructure projects. At the minimum,an effective implementation of BOT projects hinges on the following: (a) alegal and economic environment that is conducive to a mutually beneficialpartnership between the government and private participants; (b) clarityin articulating the duties and responsibilities of the parties to the contract;(c) certainty of recovering investments and availability of mechanisms fordealing with risks and unforeseen events and for arbitration in case ofdispute between the contracting parties; and (d) transparency andcredibility of the government’s processes for review and approval ofproposed BOT projects and the associated contracts for implementation.

Recent experience with the implementation of the BOT Law indicatesthe need to address various issues, starting from the legal framework tothe level of responsibilities of the government institutions that are involved

5Conclusion and Policy Recommendations

Page 132: Areview of BOT for Developing Project

126 A Review of Build-operate-transfer for Infrastructure Development

in the project cycle, i.e., from project entry level to implementation andcompletion. Improvements should be introduced at the policy, legal, andinstitutional frameworks in order to improve the usefulness of thisapproach to infrastructure development. Because of the complexity of theBOT process for infrastructure development, it will be useful to considerthe following policy recommendations arising from lessons culled fromthe Philippine experience with the implementation of this approach. It issubmitted that pursuing reforms along the following policyrecommendations will serve to strengthen public-private partnership andthe use of BOT as a particular approach to infrastructure provision:

The government should provide an enabling framework for privateparticipation in infrastructure provision that clearly allocate roles,functions, powers, duties, and rights of the government and theprivate sector. A specific instrument for private participation ininfrastructure provision is the BOT approach.A clear policy framework on the BOT approach should be stated in alaw or official policy pronouncement, e.g., Executive Order,Memorandum Circular, Administrative Order, or any such officialinstrument to announce policy. Such a law or official policy statementshould have a clear statement of the role, responsibilities, andfunctions of the parties to the BOT contract. The implementing rulesand regulations (IRR) should be transparent and unambiguous ininterpretation over such matters as contractual obligations, risk-sharing arrangement, tariff setting, recovery of investments, contractvariation, contract termination, dispute settlement, arbitration, andother concerns of the parties involved in the BOT contract.The BOT Law should be considered the primary statute thatestablishes government policy and the institutional framework forimplementing BOT. There should be accompanying IRR of the BOTLaw that specify the administrative procedure for implementation.The IRR may be amended from time to time as the need arises. Thiswill provide the government both the legal basis for the BOT approach(that is, a primary statute) as well as the flexibility (through theIRR) to respond to changing needs and circumstances of the economy,the financial markets, private investors, and other stakeholders thatmay impact on the efficient implementation of the BOT approach.Competitive bidding procedures remain the central tenet ofgovernment procurement policy. Competitive bidding provides thebest prospects for efficient provision and implementation of theinfrastructure project at the least possible cost to the economy. The

Page 133: Areview of BOT for Developing Project

BOT Law should thus forthrightly express the government’spreference for competitive bidding and affirm that direct negotiationand unsolicited proposals remain the exception. Ideally, unsolicitedproposals should not be part of the approach to infrastructureprovision because they create incentives for nontransparent anddubious “back-of-the-room” negotiations and cutting deals betweenthe proponent and potential implementing agency.There should be a clear institutional framework for identification ofprojects, preparation of project proposals, and review and approvalof BOT projects and contracts. Both implementing agencies andoversight agencies should be accountable to the public over theirdecisions. It is the oversight agencies composed of the Department ofFinance, the Department of Budget and Management, and theNational Economic and Development Authority, principal membersof the NEDA-Investment Coordination Committee, that should bechiefly responsible for the review and approval of BOT projects andcontracts. The Department of Justice should provide the necessarylegal advice and review BOT contracts while the Bangko Sentral ngPilipinas joins this group to take care of potential impact on thefinancial system and balance of payments of foreign-fundedinfrastructure projects. Implementing agencies, which are theproponent agencies in charge of identifying and packaging projectproposals should not be allowed to be members of the InvestmentCoordination Committee that reviews and approves those projects.Other agencies, e.g., the Department of the Environment and NaturalResources, may be tapped when needed to give information or advicethat oversight agencies will need to make a good decision.The BOT Law should affirm the government’s binding commitmentto honor and defend contractual rights and obligations. This includesproviding for greater transparency with regard to the content ofcontracts.The government should build capacity for project design, technicalanalysis, contract review, and monitoring the implementation of BOTinfrastructure projects. It is also important to give implementingagencies the responsibility of monitoring BOT projects at differentstages of development, that is, from project entry, construction toimplementation, and of reporting these to the oversight agencies andthe Office of the President.The government, with initial assistance from donors, should establisha project preparation or development facility that could be tapped by

Llanto 127

Page 134: Areview of BOT for Developing Project

government agencies for BOT project identification and thedevelopment of BOT proposals for tender or competitive bidding. Theproject development facility should be given the appropriate amountof budgetary support once institutionalized.The independent ex post evaluation of the BOT project should bemade a regular activity of the government in order to assess whetheror not it is delivering the envisaged development outputs. Third partyevaluators from the academe, civil society, and professionalassociations could be tapped for this task.

The BOT Law or official policy pronouncement should allow theprivate proponent to levy user charges that provide a return commensurateto the opportunity cost of invested funds. This will ensure project viabilityand will reduce or minimize the amount of subsidy that the governmentprovides. It seems unfair to use revenues from general taxation to financeor provide subsidy or support to a BOT project, which is availed of byparticular segments of the population, that is, the users.

128 A Review of Build-operate-transfer for Infrastructure Development

Page 135: Areview of BOT for Developing Project

We propose that RA 7718 be amended in pursuit of the goal of thegovernment to enhance public-private partnership (PPP) in infrastructuredevelopment, in general, and promote the use of build-operate-transfer(BOT) scheme and its variants, in particular. The legal framework we areproposing must be conducive to the protection and enforcement of propertyand contractual rights, backed by a substantive Implementing Rules andRegulations (IRR) of maximum clarity. To make the IRR operationallyefficient, some institutional reforms are indicated.

Implementing Agencies (IAs) must be empowered to render a first-pass approval in line with the desire to make them assume projectownership. Capacity building aimed at raising the technical, financial,and legal expertise of the IAs is crucial. Meanwhile, the oversight functionthe Investment Coordinating Committee (ICC) exercises over BOT projectsmay de delegated to a subcommittee whose membership may be stipulatedin the IRR. The requirements for a second-pass approval to be retained bythe ICC should be focused on aligning any form of government supportbeing contemplated with the existing policies on government procurementand special fiscal and investment incentives.

The table below shows the sections of the existing law that can berelegated to the IRR. This is followed by a proposed bill amending thecurrent BOT Law.

Annex A. A Proposal for an Amended BOT Law

by Dante B. Canlas, Gilberto M. Llanto, Rhean Botha, and DomingoPallarca

Sec 1: Declaration of Policy Retain in law with amplification.Sec 2: Definition of Terms Replace with a new section (Scope of PPP

Contractual Arrangement).Sec 3: Private Initiative in Infrastructure Retain in law.Sec 4: Priority Projects Retain in law with amendment.

Relegate approval limits to IRR.Sec 5: Unsolicited Proposals Subsume under Section on public bidding; unsolicited

mode can be undertaken under exceptional cases.Sec 6: Public Bidding of Projects Reaffirm in the law the principle of competitive

bidding as the principal means of procuring privateinvestment. Law also needs to confirm the principleof publication of contract terms and notification toCongress.

Llanto 129

Page 136: Areview of BOT for Developing Project

130 A Review of Build-operate-transfer for Infrastructure Development

A Bill Seeking to Amend Republic Act no. 7718

Section 1. Declaration of policy

1. It is the policy of the State to:a. recognize the indispensable role of the private sector as the main

engine for national growth and development;b. create an enabling environment for public-private partnership

projects, that is, private sector investment in public infrastructurefor efficient provision of public services;

c. recognize the long-term nature of private investment ininfrastructure and services and to mitigate the associated risksby ensuring that the validity and enforceability of contracts arerespected through the due process of law;

d. encourage private investment in public infrastructure and/orpublic services that:(i) yields value for money for the State by allocating risks to the

party best able to manage them;(ii) is affordable in light of overall budgetary sustainability,

forward commitment in relation to public expenditure, andthe potential returns on private sector investment;

Relegate provisions dealing with: (a) advertisementof project opportunities; (b) financial criteria foridentifying winning bids; (c) liability of bidders; and (d)bidding procedures to IRR.

Sec 7: Direct Negotiation of Contract Subsume under section on public bidding of projects,reaffirm principle that direct negotiation may beentered into only in exceptional circumstances(subject to appeal and safeguards) in law. Relegateprovisions dealing with the circumstances underwhich direct negotiations may be entered into to IRR.

Sec 8: Repayment Scheme Relegate to IRR.Sec 9: Contract Termination Reaffirm in the law the principle of government

liability for no-fault contract termination.Sec 10: Regulatory Boards For deletion.Sec 11: Project Supervision Subsume/incorporate in the Section on monitoring.Sec 12: Investment Incentives Retain in law but should be made consistent with

Omnibus Investment Code/Investment Priorities Act.Sec 13: Implementing Rules and Regulations Retain in law with streamlined membership.Sec 14: Co-ordination and Monitoring Retain in law to include auditing.

Page 137: Areview of BOT for Developing Project

(iii) maximizes the benefits of private sector efficiency, expertise,flexibility, and innovation;

(iv) is financially viable; and(v) is desired in light of economic and social benefits and costs.

e. ensure a clear and transparent allocation of roles and functionsbetween the oversight and implementing agencies at the nationallevel to ensure the effective implementation of this Act and toencourage the same at local government level;

f. secure private investment through open and competitive biddingprocedures and to permit noncompetitive procedures only inexceptional circumstances as allowed by this Act, its ImplementingRules and Regulations, and consistent with the provision of RA9184;

g. ensure a consistent approach among government agencies at bothnational and local levels in the identification, design, assessment,solicitation, and management of projects;

h. build the capacity of government agencies and local governmentunits (LGUs) to avail themselves of investment opportunitiesunder this Act;

i. review regularly the progress of the achievement of this policyand to report to Congress on the same.

2. The NEDA Board shall oversee the implementation of this state policyby all agencies of government at the national and local levels and shallsubmit an annual report to Congress on the progress achieved. To thisend, the National Economic and Development Authority (NEDA) Board,through the Investment Coordination Committee, shall request nationalagencies and LGUs to submit progress reports of PPP projects.3. The NEDA Board shall issue the IRR consistent with the provisionsof this Act and on any matter it deems appropriate to assist with theimplementation of policy. The IRR shall be published in the OfficialGovernment Gazette and Congress shall likewise be notified of the samewithin one month of the IRR’s publication.4. For the purpose of this section and subsequent reference in thefollowing sections, “government agency” refers to implementing agenciesof the national government, including, government-owned and controlledcorporations.

Llanto 131

Page 138: Areview of BOT for Developing Project

132 A Review of Build-operate-transfer for Infrastructure Development

Section 2. Scope of Contractual Arrangements

Government agencies and LGUs may select from the list of contractualarrangements provided below. Each agency, however, may adopt othercontractual arrangements that may be decided upon during contractnegotiations. New contractual arrangements not listed under this Act maybe adopted but shall be approved by the ICC.

a. Build-operate-and-transfer (BOT): A contractual arrangementwhereby the project proponent undertakes the construction,including financing, of a given infrastructure facility, and theoperation and maintenance thereof. The project proponentoperates the facility over the fixed term during which it is allowedto charge facility users appropriate tools, fees, rentals, and chargesnot exceeding those proposed in its bid or as negotiated andincorporated in the contract to enable the project proponent torecover its investment and operating and maintenance expensesin the project. The project proponent transfers the facility to thegovernment agency or LGU concerned at the end of the fixed termwhich shall not exceed fifty (50) years, provided that, in case of aninfrastructure or development facility the operation of whichrequires a public-utility franchise, the proponent must be Filipinoor, if a corporation, must be duly registered with the Securitiesand Exchange Commission (SEC) and owned up to at least sixtypercent (60%) by Filipinos.

The build-operate-and-transfer shall include a supply-and-operate situation, which is a contractual arrangement wherebythe supplier of equipment and machinery for a given infrastructurefacility, if the interest of the Government so requires, operatesthe facility providing in the process technology transfer andtraining to Filipino nationals.

b. Build-and-transfer (BT): A contractual arrangement whereby theproject proponent undertakes the financing and construction of agiven infrastructure or development facility and after itscompletion turns it over to the government agency or LGUconcerned, which shall pay the proponent on an agreed scheduleits total investments expended on the project, plus a reasonablerate of return thereon. This project, including critical facilities

Page 139: Areview of BOT for Developing Project

which, for security or strategic reasons, must be operated directlyby the government.

c. Build-own-and-operate (BOO): A contractual arrangementwhereby a project proponent is authorized to finance, construct,own, operate, and maintain an infrastructure or developmentfacility from which the proponent is allowed to recover its totalinvestment, operating and maintenance costs plus a reasonablereturn thereon by collecting tolls, fees, rentals, or other chargesfrom facility users; provided, that all such projects, uponrecommendation of the ICC, shall be approved by the President ofthe Philippines as chair of the NEDA Board. Under this project,the proponent that owns the assets of the facility may assign itsoperation and maintenance to a facility operator.

d. Build-lease-and-transfer (BLT): A contractual arrangementwhereby a project proponent is authorized to finance and constructan infrastructure or development facility and upon its completionturns it over to the government agency or LGU concerned on alease arrangement for a fixed period after which ownership of thefacility is automatically transferred to the government agency orLGU concerned.

e. Build-transfer-and-operate (BTO): A contractual arrangementwhereby the public sector contracts out the building of aninfrastructure facility to a private entity such that the contractorbuilds the facility on a turn-key basis, assuming cost overrun,delay, and specified performance risks.

Once the facility is commissioned satisfactorily, title istransferred to the implementing agency. The private entity,however, operates the facility on behalf of the implementing agencyunder an arrangement.

f. Contract-add-and-operate (CAO): A contractual arrangementwhereby the project proponent adds to an existing infrastructurefacility which it is renting from the government. It operates theexpanded project over an agreed franchise period. There may ormay not be a transfer arrangement in regard to the facility.

g. Develop-operate-and-transfer (DOT): A contractual arrangementwhereby favorable conditions external to a new infrastructureproject, which is to be built by a private project proponent, areintegrated into the arrangement by giving that entity the right todevelop adjoining property, and thus, enjoy some of the benefitsthe investment creates such as higher property or rent values.

Llanto 133

Page 140: Areview of BOT for Developing Project

134 A Review of Build-operate-transfer for Infrastructure Development

h. Rehabilitate-operate-and-transfer (ROT): A contractualarrangement whereby an existing facility is turned over to theprivate sector to refurbish, operate, and maintain for a franchiseperiod, at the expiry of which the legal title to the facility is turnedover to the government. The term is also used to describe thepurchase of an existing facility from abroad, importing,refurbishing, erecting, and consuming it within the host country.

i. Rehabilitate-own-and-operate (ROO): A contractual arrangementwhereby an existing facility is turned over to the private sector torefurbish and operate with no time limitation imposed onownership. As long as the operator is not in violation of itsfranchise, it can continue to operate the facility in perpetuity.

Section 3. Private Delivery of Public Infrastructure and/or Services

1. A government agency or LGU may contract with the private sectorfor the delivery of public infrastructure and/or services in any of thefollowing areas:

a. energy, including oil and gas;b. transport, including railways, roads, tunnels, bridges, ports, canals,

channels, airports, pipelines;c. water, including water storage and wastewater;d. communications;e. information technology;f. education;g. health;h. tourism;i. culture, sports, and leisure facilities;j. government buildings, industrial estates and townships, and

housing;k. markets, warehouses, and slaughterhouses;l. any other area as may be prescribed.

2. Contractual arrangements that may be utilized for the purposes ofprojects contemplated in Section 2 shall be determined during thenegotiations between the government agency or LGU, on one hand, andthe private sector, on the other.3. For the purpose of this section and subsequent reference in thefollowing sections, “prescribed” means prescribed in the IRR issued interms of this Act except as otherwise indicated.

Page 141: Areview of BOT for Developing Project

Section 4. Project Preparation

a. Each government agency or LGU shall within its area ofresponsibility prepare a project for approval by the approvingauthority contemplated in Section 5 in the manner as prescribed.

b. Prior to preparing a project for approval, the head of theresponsible government agency or LGU shall review or assess:i. the risks associated with the proposed project taking into

account the various methods for sharing these risks; andii. the economic and financial feasibility of the proposed project

including a comparison of the costs and benefits ofimplementing the project in terms of this Act with the costsof implementation in another form.

c. A government agency or LGU that lacks the capacity to prepare aproject in the manner as prescribed (including the prebidding,bidding, and contract management stages of the project) can tap theProject Development Facility (PDF). The PDF will be a fund whosestart-up money will come from the national government budget or,where feasible, grants from donors of official development assistance(ODA). In the case of a government agency, the PDF shall beappropriated within its budget ceiling to enable the governmentagency to solicit assistance or expert advice as necessary. In theinterest of sustainability, the winning bidder for a PPP project shallbe required to compensate the cost the government agency expendedin developing the proposal. In the case of LGUs, the DOF shall actas custodian of the PDF and the winning bidder for a LGU-initiatedPPP project shall likewise compensate the cost expended indeveloping the proposal. In the event that resources from the PDFare unavailable to render the required assistance within theprescribed period, the government agency or LGU shall report thesame to the ICC and NEDA Board, respectively.

d. The NEDA Board, upon receiving such report, shall:i. request the Department of Budget and Management (DBM)

to allocate alternative resources from within government toassist the government agency;

ii. seek such additional resources as may be available togovernment to assist the government agency or LGU; or

iii. based on the overall priorities of the Medium-Term PhilippineDevelopment Plan (MTPDP) and the government agency’s

Llanto 135

Page 142: Areview of BOT for Developing Project

136 A Review of Build-operate-transfer for Infrastructure Development

prioritized projects appearing in the Medium-Term PublicInvestment Program (MTPIP) or in the LGU’s localdevelopment plan direct the government agency or requestthe LGU to reprioritize its programs and project or delay theproject until the budget required for the proposed project canbe accommodated.

e. The NEDA Board shall communicate its decision under subsection(4) to the government agency within 30 days and shall reportthereon in its Annual Report contemplated in Section 1.

f. The NEDA Board may, in writing, delegate its powers under thissection to the ICC.

Section 5. Approving Authority

1. A national government agency that has identified and prepared aproject in the manner specified in Section 4 shall:

a. be required to endorse, through the head of the governmentagency, the project proposal and contract to the ICC. Thisendorsement shall serve as the first-pass approval for the projectand draft contract. All government agencies are required to reviewthe technical, legal, financial, economic, and social implications ofthe project and approve the same prior to endorsement to the ICC.

b. submit projects of major national importance with a contract valueabove an amount as may be prescribed to the NEDA Board forapproval; all other projects to the ICC for approval.

2. All local government PPP projects shall be approved following theprovisions of the Local Government Code.

Section 6. Implementing, Monitoring, and Auditing Functions

1. A government agency or LGU that has secured approval for a projectin the manner contemplated in Section 5 shall be responsible for theimplementation, management, and supervision of the project. Regularmonitoring reports shall be submitted to the ICC for its information.2. Regular auditing shall likewise be conducted following Commissionon Audit (COA) guidelines. Reports may be requested from the respectivegovernment agency, LGU, or COA as deemed necessary.

Page 143: Areview of BOT for Developing Project

Section 7. Competitive Bidding Procedures

1. Competitive bidding procedures shall apply to all projects for whichprivate investment is solicited in terms of this Act.2. Under exceptional cases, government agencies may resort to directnegotiations under such conditions prescribed in Section 53 of RA 9184.LGUs may resort to direct negotiations under conditions prescribed inthe Local Government Code and/or RA 9184 as applicable. Such conditionsshall include a requirement that the government agency or LGU mustgive public notice in the prescribed manner of:

a. the intention to enter into direct negotiations;b. the conclusion of negotiations to enter into a contract through

direct negotiation; andc. the salient terms of the contract to be concluded.

3. A government agency may only entertain an unsolicited proposalprovided that such proposal is not contained in its prioritized projects inthe MTPIP. In the case of LGUs, an unsolicited proposal may beentertained provided it does not appear in the local development plan ofthe LGU concerned.

The other conditions for considering an unsolicited proposal are asfollows:

a. the government agency or LGU has notified in writing theapproving authority within seven working days of the receipt ofthe proposal;

b. the head of the government agency or head of the LGU hasconducted an assessment as contemplated in Section 4(2) and hascertified in writing to the approving authority that it is capable ofconducting all proceedings relating to the proposal;

c. the head of the government agency or LGU certified in writingthat the proposed project serves the public interest;

d. the proposal does not entail the provision of any form ofgovernment guarantee, subsidy, or undertakings as may beprescribed;

e. the proposal complies with such requirements for unsolicitedproposals as may be prescribed; and

f. the proponent has indicated its costs for developing the proposalin the prescribed manner.

4. Notwithstanding compliance by any government agency or LGU withthe provisions of subsection 3, the ICC may direct a government agency

Llanto 137

Page 144: Areview of BOT for Developing Project

138 A Review of Build-operate-transfer for Infrastructure Development

or LGU not to proceed with its consideration of an unsolicited proposaluntil such time as the latter satisfies the approving authority that:

a. it has access to adequate resources to properly assess the proposal,to conduct the evaluation of comparative proposals, to conductnegotiations, and to oversee implementation; and

b. the proposal meets such requirements related to the public interestas may be prescribed.

5. All unsolicited proposals shall be subject to comparative proposals,after approval by the approving authority, in the manner as may beprescribed.6. A government agency or LGU during its negotiations and beforeissuing a request for comparative proposals, negotiate with the proponentthat it be compensated for the cost of developing the proposal and to submitthe proposal to competitive bidding procedures. The government agencyor LGU shall introduce, as part of the bidding conditions, a requirementthat the winning bidder (if not the original proponent) be reimbursed forits costs in developing the proposal or for such amount as the governmentagency or LGU and the proponent may agree beforehand in writing.

Noncompliance with the provisions of subsection 3 shall be a groundfor declaring a contract null and void.

Section 8. Contracts and Public Disclosure

1. Copies of all contracts concluded in terms of this Act shall be theresponsibility of the government agency or LGU. The said governmentagency or LGU is required to forward a copy of the signed agreement tothe ICC for records purposes.2. The grant of access to the signed agreements by the public shall bethe responsibility of the government agency or LGU.

Section 9. Validity of Contracts

1. No party may, in proceedings before any court, allege the invalidity ofany contract concluded under this Act on the grounds of noncompliancewith the provisions of this Act or its IRR after a period of 90 days haselapsed from the date of publication of the approval of the government-procured project in the Official Gazette.

Page 145: Areview of BOT for Developing Project

Section 10. Contract Termination

1. In the event that a project is revoked, cancelled, or terminated by theGovernment, through no fault of the project proponent or by mutualagreement, the project proponent shall be compensated by the governmentas provided for in the contractual agreement.2. In cases where the government defaults on certain major obligationsin the contract and such failure is not remediable, or if remediable shallremain unremedied for an unreasonable length of time, the projectproponent may, by prior notice to the concerned government agency orLGU, specifying the turnover date, terminate the contract. The privateproponent shall likewise be compensated by the Government according tothe provisions of the contractual agreement.

Section 11. Investment Promotion

1. The status of the BOT Center as a unit attached to the Department ofTrade and Industry (DTI) is hereby confirmed. The Center shall,henceforth, be known as the Public-Private Partnership Center (PPPC).2. The main responsibilities of PPPC include:

a. promote and market the government’s private sector investmentprogram, including the formulation and implementation of apromotion and marketing plan, providing service as an informationcenter for investors/developers as well as for government agencies;

b. participate in the technical working group (TWG) that may beestablished by the IRR Committee;

c. perform business development and investment-related activitiesin support of the other functions and mandate of the DTI; and

d. perform such other functions as may be prescribed under the IRR.

Section 12. Liability

In accordance with Section 38 Chapter 9 of the Administrative Code, thehead of the government agency shall not be held liable for any bona fide actor omission undertaken for the purposes of implementing this Act or its IRRunless there is a clear showing of bad faith, malice, or gross negligence.

Llanto 139

Page 146: Areview of BOT for Developing Project

140 A Review of Build-operate-transfer for Infrastructure Development

Section 13. Implementing Rules and Regulations

1. The IRR issued in terms of RA No. 6957 as amended by RA No. 7718remain in force until repealed in terms of this Act.2. The IRR committee may, subject to the approval of the NEDA Boardand after conducting public consultations and publication as required bylaw, issue the IRR to provide for the implementation of this Act in themost expeditious manner. The committee may, as needed, update suchIRR from time to time.3. Without limiting the generality of the foregoing, the IRR may providefor:

a. contractual arrangements and repayment schemes that may beentered into under this Act;

b. areas in which private investment may be solicited;c. institutional arrangements for bid management;d. manner of preparation and content of documents including

clarifications and prebid conferences;e. qualification of proponents, contractors, bidders, and facility

operators;f. procedures for competitive bidding;g. procedures for direct negotiation;h. procedures for unsolicited proposals;i. contract negotiation and award;j. contract approval and implementation;k. investment incentives, government guarantees, support, and

undertakings;l. contract management, coordination, monitoring, and auditing;m. the powers, functions, and duties of concerned agencies; andn. any other matter required for the expeditious implementation of

the Act.4. For the purposes of this section, “committee” means a committeeappointed by the President comprising one representative from each ofthe following:

a. the Department of Public Works and Highways;b. the Department of Transportation and Communications;c. the Department of Energy;d. the Department of Trade and Industry;e. the Department of Finance;f. the Department of Interior and Local Government;g. the National Economic and Development Authority;

Page 147: Areview of BOT for Developing Project

h. the Department of Budget and Management; andi. the Office of the President.

Section 14. Repeal Clause

All laws or parts of any law inconsistent with the provisions of this Actare hereby repealed or modified accordingly.

Section 15. Separability Clause

If any provision of this Act is held invalid, the other provisions not affectedthereby shall continue in operation.

Section 16. Effectivity Clause

This Act shall take effect fifteen (15) days following its publication in theOfficial Gazette and in at least two newspapers of general circulation.

Llanto 141

Page 148: Areview of BOT for Developing Project

Asian Development Bank and World Bank (ADB and WB). 2005. Improvingthe investment climate in the Philippines. Manila.

Abrenica, M.J. and G.M. Llanto. 2003. Services. In The Philippine economy:development policies and challenges edited by A. Balisacan and H.Hill. Quezon City: Ateneo de Manila University Press.

Alonzo, R., G. Rognstad, A. Ashar, and A. Navarro. 2007. The road-ROROterminal system: Bicol mainland-Masbate-Cebu connection. A reportsubmitted to the Development Bank of the Philippines and theEMERGE Project. Unpublished paper.

Augenblick, M. and B. Custer, Jr. 1990. The build, operate, and transfer(BOT) approach to infrastructure projects in developing countries.World Bank Working Paper No. 498. Washington, D.C.: The WorldBank.

Basilio, E., G.M. Llanto, and C.L. Rodolfo. 2007. Transport infrastructurepolicy paper. Unpublished.

Basilio, L. and D. Gundaya. 1997. The impact of collective publicinfrastructure on regional income disparities. Unpublishedundergraduate thesis, School of Economics, University of thePhilippines.

Bougheas, S., P. Demetriades, and T. Mamuneas. 1999. Infrastructure,specialization, and economic growth. Discussion Paper 99-01.Department of Economics, University of Cyprus.

Brillantes, A., G.M. Llanto, J. Alm, and D. Sosmena. 2009. Decentralizationand devolution in the Philippines: status, triumphs, tests, andchallenges, an in-depth study of decentralization in the Philippines.A study submitted to the Department of the Interior and LocalGovernment and TA 4778 Asian Development Bank.

Brousseau, E. and M. Fares. 1998. Incomplete contracts and governancestructures. Centre d’ Analyse Théorique des Organisations et desMarchés, Université de Paris.

Button, K. 2002. Effective infrastructure policies to foster integratedeconomic development [online]. Third African Development Forum,Addis Ababa. http://www.uneca.org/adfiii/docs/Effective_infrastructure_Policies. [Accessed 13 July 2007.]

Calderon, C.A. and L. Serven. 2004. Effects of infrastructure developmenton growth and income distribution. Central Bank of Chile WorkingPaper No. 270.

References

Llanto 143

Page 149: Areview of BOT for Developing Project

______. 2005. The effects of infrastructure development on growth andincome distribution. Washington, D.C.: The World Bank.

Canlas, D. and G.M. Llanto. 2006. A proposed BOT bill to enhance public-private partnership in infrastructure development. A technicalmemorandum. Unpublished paper.

Canlas, D., G.M. Llanto, R. Botha, and D. Pallarca. 2006. A proposed BOTbill to enhance public-private partnership in infrastructuredevelopment. A report submitted to EMERGE Project and theDepartment of Trade and Industry.

Canning, D. and P. Pedroni. 2004. The effect of infrastructure on long-run economic growth. Unpublished paper.

Carlos, M.J., Jr. 2007. Seamless infrastructure network. Presented at theState of Philippine Competitiveness National Conference, NationalCompetitiveness Council, 18 July.

Clark, X, D. Dollar, and A. Micco. 2004. Port efficiency, maritime transportcosts, and bilateral trade. NBER Working Paper 10353. Cambridge:National Bureau of Economic Research.

EMERGE Quarterly Report. 2007. Unpublished report submitted to theNational Economic and Development Authority.

Economic Research Institute of Asia (ERIA). 2007. Developing a roadmaptoward East Asian economic integration. Interim Report.

Fabella, R. 1996. Features of the emerging world economic order:implications on growth policy. Chapter 14 in The Philippines in theemerging world environment, edited by C. Paderanga, Jr. Quezon City:U.P. Press.

Gill, I. and H. Kharas. 2007. An East Asian renaissance: ideas for economicgrowth [online]. Washington, DC: The World Bank. http://www.williams.edu/Economics/wp/pedroniinfrastructure.pdf. [Accessed15 December 2007.]

Gramlich, E.M. 1994. Infrastructure investment: a review essay. Journalof Economic Literature 32(3):1176–96.

Grossman, S. and O. Hart. 1986. The costs and benefits of ownership: atheory of vertical and lateral integration. Journal of Political Economy94:691–719.

Hart, O. and J. Moore. 1988. Incomplete contracts and renegotiation.Econometrica 56:755–786.

Handley, P. 1997. A critical view of the BOT privatization process in Asia.Asia Journal of Public Administration 19(2):203–243.

Hodges, J. and G. Dellacha. 2007. Unsolicited infrastructure proposals:how some countries introduce competition and transparency, aninternational experience review. Washington, D.C.: The World Bank.

144 A Review of Build-operate-transfer for Infrastructure Development

Page 150: Areview of BOT for Developing Project

International Institute for Management Development (IMD). 2007. WorldCompetitiveness Yearbook [online]. Switzerland. http//www.imd.ch/research/ publications/wey/index/cfm.

Infrastructure Canada. 2007. Infrastructure and productivity. Researchand Analysis Division. Unpublished.

Japan External Trade Office (JETRO). 2007. FY 2006 Survey of JapaneseFirms’ International Operations. Tokyo: JETRO.

Japan International Cooperation Agency (JICA). 1999. Metro Manila urbantransportation integrated study. Final report. Unpublished paper.

Lamberte, M., F. Alburo, and E. Patalinghug. 2003. Private sectorassessment study: the Philippines. Report for the Asian DevelopmentBank. Unpublished.

Levy, S.M. 1996. Build-operate-transfer, paving the way for tomorrow’sinfrastructure. New York: John Wiley and Sons.

Limao, N., and A.J. Venables. 1999. Infrastructure, geographicaldisadvantage, and transport costs. Policy Research Working PaperNo. 2257. Washington, D.C.: The World Bank.

Llanto, G.M. 2004. Infrastructure development: the experience and policyoptions for the future. Perspective Paper Series No. 7. Makati City:Philippine Institute for Development Studies.

______. 2007a. Infrastructure and regional growth. Chapter 10 in Thedynamics of regional development: the Philippines in East Asia, editedby A. Balisacan and H. Hill. Quezon City: Ateneo de Manila UniversityPress.

______. 2007b. Dealing with contingent liabilities: the Philippines. Chapter8 in Fiscal policy and management in East Asia, edited by T. Ito andA. Rose. National Bureau of Economic Research East Asia Seminaron Economics Vol. 16. Chicago: University of Chicago Press.

______. 2007c. Shelter finance strategies for the poor: Philippines.Environment and Urbanization 19(2): 409–423.

______. 2007d. Reforming the BOT Law: a call of the times. PIDS PolicyNotes No. 2007-01. Makati City: Philippine Institute for DevelopmentStudies.

______. 2008a. Build-operate-transfer for infrastructure development: somelessons from the Philippine experience. Paper submitted to theEconomic Research Institute of Asia (ERIA) research project onInternational Infrastructure Development in East Asia: TowardEffective and Balanced Regional Integration.

______. 2008b. Overcoming infrastructure constraints to economic growthin the Philippines. Draft report submitted to the Asian DevelopmentBank.

Llanto 145

Page 151: Areview of BOT for Developing Project

______. 2009. The impact of rural infrastructure on agriculturalproductivity. Paper presented at the Final Workshop: ProductivityGrowth of Philippine Agriculture Project, SEARCA, Los Baños,Laguna, June 2–3.

______, H. Basilio, and L. Basilio. 2005. Competition policy and regulationin ports and shipping. PIDS Discussion Paper No. 2005-02. MakatiCity: Philippine Institute for Development Studies.

Leung, S., V.T. Thanh, and K.R. Visith. 2003. Integration and transition—Vietnam, Cambodia, and Lao PDR. International and DevelopmentEconomics Working Paper 05-1. Canberra: Asia Pacific School ofEconomics and Government, Australian National University.

Levy, S.M. 1996. Build-operate-transfer, paving the way for tomorrow’sinfrastructure. New York: John Wiley and Sons.

Malhotra, A. 1997. Private participation in infrastructure: lessons fromAsia’s power sector. Finance and Development.

Manuela, W.S., Jr. 2005. The evolution of the Philippine airline industry.Aerlines E-zine Edition, Issue No. 36.

Menheere, S. and S. Pollalis. 1996. Case studies on build-operate-transfer.Netherlands: Delft University of Technology.

National Economic and Development Authority (NEDA). 2007. 16th ODAPortfolio Review. Pasig City: NEDA.

National Statistical Coordination Board (NSCB). 2006. PhilippineStatistical Yearbook. Makati City: NSCB.

Navarro, A. 2005. Build-operate-transfer arrangements: the experienceand policy changes. Paper submitted to the Philippine Institute forDevelopment Studies. Unpublished.

O’Fallon, C. 2003. Linkages between infrastructure and economic growth.Report submitted to the New Zealand Ministry of Economic Development.

Rodriguez, J.F.P. 2006. Public investment in infrastructure andproductivity growth: evidence from the Venezuelan manufacturingsector [online]. http://frrodriguez.web.wesleyan.edu/docs/working_papers/Infrastructure.

Rosik, P. 2006. Transport infrastructure, public capital, and regional policy:review of studies. Paper presented at the International Conferenceon Shaping EU Regional Policy: Economic Social and PoliticalPressures, Leuven, Belgium.

Shepherd, B. and J. Wilson. 2006. Road infrastructure in Europe andCentral Asia: does network quality affect trade? World Bank PolicyResearch Working Paper 4104. Washington, D.C.: The World Bank.

146 A Review of Build-operate-transfer for Infrastructure Development

Page 152: Areview of BOT for Developing Project

Sturm, J., G. Kuper, and J. de Haan. 1996. Modeling governmentinvestment and economic growth on a macro level: a review. CCSOSeries No. 9. Department of Economics, University of Groningen.

Tatom, J. 1991. Public capital and private sector performance. FederalBank of St. Louis Review. May–June.

United Nations Industrial Development Organization (UNIDO). 1996.Guidelines for infrastructure development through build-operate-transfer (BOT) projects.

Wang, E. 2002. Public infrastructure and economic growth: a new approachapplied to East Asian economies. Journal of Public Policy Modeling24(5):411–35.

Williamson, O.E. 1975. Markets and hierarchies: analysis and antitrustimplications. New York: The Free Press.

______. 1985. The economic institutions of capitalism. New York: The FreePress.

World Bank (WB). 2005. Philippines: meeting infrastructure challenges.Washington, D.C.: WB.

______. 2006. World Development Indicators, 2006. Washington, D.C.: WB.______. 2007a. Philippines: invigorating growth, enhancing its impact.

Report No. 39226-PH. Washington, D.C.: WB.______. 2007b. Investment climate survey [online]. Washington, D.C. http:/

/iresearch.worldbank.org/Investment Climate/.______ and International Finance Corporation. 2007c. Doing business, how

to reform [online]. Washington, D.C. http://www.doingbusiness.org.World Economic Forum. 2004, 2005, 2006, and various years. Global

competitiveness report [online]. http://www.gcr.weforum.org.

Llanto 147

Page 153: Areview of BOT for Developing Project

The Author

Gilberto M. Llanto is Senior Research Fellow of the Philippine Institutefor Development Studies (PIDS). He was formerly Deputy-DirectorGeneral of the National Economic and Development Authority (NEDA),Vice-President of the PIDS, and Executive Director of the AgriculturalCredit Policy Council (ACPC). His chairmanship of the Technical Boardof the Investment Coordination Committee during his stint at NEDA gavehim first-hand insights into factors constraining infrastructuredevelopment in the country.

He is a Professorial Lecturer at the National College of PublicAdministration and Governance, University of the Philippines and memberof the Strategic Studies Council of the Local Government DevelopmentFoundation. He was President of the Philippine Economics Society from2003–2004.

He obtained his Ph.D. in Economics from the University of thePhilippines School of Economics (UPSE) and has written and publishedon financial markets, public economics, local governance, institutionaleconomics, and infrastructure regulation.

Page 154: Areview of BOT for Developing Project

Erratum

The following should be included under Preface:

This paper partly draws from Gilberto M. Llanto, “Build-operate-transferfor infrastructure development: some lessons from the Philippineexperience,” paper submitted to the ERIA Research Project onInternational Infrastructure Development in East Asia: Toward Effectiveand Balanced Regional Integration, 31 March 2008 and also from DanteCanlas, Gilberto M. Llanto, Rhean Botha, and Domingo Pallarca, “ProposedBOT Bill to Enhance Public-private Partnership in InfrastructureDevelopment,” a report submitted to the EMERGE Project and theDepartment of Trade and Industry, 1 June 2006.

Page 155: Areview of BOT for Developing Project