Dam Safety/Floodplain Management Staff
Trevor Timberlake, PE, CFM Engineer SupervisorMichael Borengasser, CFM, NFIP CoordinatorDonna Ryles, Floodplain Management – TrainingTim Dreher, Floodplain Management – CRSVeronica Villalobos-Pogue, Floodplain Management
Flood Mitigation Grants
•Ryan Brooks, Dam Safety Engineer
2
Your ExpectationsWhat do you hope to come away with at the
end of this course?
3
Importance of Post-Disaster Preparation
How many of you have been through disasters?
What were your experiences?
4
Course Objectives Describe elements of pre-disaster
preparation and planningIdentify contents of a post-disaster SOPOutline post-disaster actionsDescribe compliance methodsList funding sources for post-disaster
assistance
5
Course Topics Pre-disaster preparation: what to know/doSOP (Standard Operating Procedures)Post-Disaster Operations: ActivitiesFunding Sources
Risk Map
6
Importance of Planning
7
Why are pre- and post-disaster planning important?
Potential Post-Disaster DutiesCritical needs duties
Life/safety and urgent needsServing as a resource to other divisions
Floodplain management dutiesSubstantial damage/repetitive lossCoordinate collection of high water marksPromote higher standardsPermit repair/reconstruction Provide flood insurance/ICC information
8
Standard Operating Procedure(SOP)
Established procedure to be followed in carrying out a given operation or in a given situation.
A Post Disaster SOP is a tool for assessment teams following a disaster.
It may also be comprehensive in outreach to all stakeholders and in extending beyond the immediate end of the disaster. Once the disaster has subsided, the rebuilding process continues.
9
Pre-Flood PreparationsKnow your communityReview your community’s flood mapsKnow which areas and structures are most
vulnerable to floodingReview your community’s floodplain
management regulationsIdentify staff responsible for various
aspects of floodplain management in your community
10
Pre-Flood Preparations (cont.)
11
List some…
What additional preparations should be included in prior to a flood?
Element of an SOP
12
• Identify key players• Staffing needs for building damage assessment• Establish a chain-of-command• Identify procedures to coordinate with
emergency operations • Develop a procedure for damage inspections• Provide for safety of inspection teams• Secure access to communication equipment,
transportation and supplies• Implement MOAs if necessary• Provide for public outreach• Set up procedures to report inspections and
other actions
SOP Activation: Examples May be triggered by:
NOAA alerts (tropical storm warnings, etc.)
River stagesEOC notificationDecision by the CEOSkip
13
14
Who are the key players in planning post-disaster operations?
Identify Key Players
Return to Elements
Staffing Needs for Building Damage Assessment
Qualified building officialsPersonnel with construction expertiseWhat are the possible staffing sources?
15
Return to Elements
Disaster Command SystemLocations
Local Emergency Operations Center (EOC) State EOC
Use of Incident Command System (ICS)
16
Return to Elements
Initial Damage Assessment and Building Safety Survey
When should initial sweeps be done?What information should be collected?How will the information be used?What safety precautions should workers follow
in the affected areas?
17
Return to Elements
• Deploy into the local EOC• Implement the SOP: Conduct
initial sweeps• Disseminate information• Conduct detailed Substantial
Damage Inspection• Issue Substantial Damage
Declarations
18
• Post red/yellow/green tags on structures• Conduct permitting and documentation
activities• Ensure compliance/resolve cases• Activate any mutual aid agreements
19