arts & humanities instructional building

35
Arts & Humanities Instructional Building Noah J. Ashbaugh Construction Management 2006

Upload: branxton

Post on 21-Jan-2016

68 views

Category:

Documents


0 download

DESCRIPTION

Arts & Humanities Instructional Building. Noah J. Ashbaugh. Construction Management 2006. Senior Thesis Presentation. Noah J. Ashbaugh. Construction Management 2006. Agenda. Arts and Humanities Instructional Building Project Background Analysis Areas Roof System Analysis - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Arts & Humanities Instructional Building

Arts & Humanities Instructional Building

Noah J. AshbaughConstruction Management 2006

Page 2: Arts & Humanities Instructional Building

Agenda

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

• Arts and Humanities Instructional Building Project Background

• Analysis Areas

• Roof System Analysis

• Façade Sequencing

• Waste Management

• Final Conclusions and Recommendations

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Page 3: Arts & Humanities Instructional Building

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

• Arts and Humanities Instructional Building Project Background

• Analysis Areas

• Roof System Analysis

• Façade Sequencing

• Waste Management

• Final Conclusions and Recommendations

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Agenda

Page 4: Arts & Humanities Instructional Building

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Project Background

• Project Name:

• Location:

• Delivered Method :

•Construction Manager :

• GMP :

• Construction Schedule:

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Arts & Humanities Instructional Building

Columbia, Maryland

CM at risk

Riparius Construction, Inc.

$20 M

22 months

Page 5: Arts & Humanities Instructional Building

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

• Project Size : 77,000 sq.ft.

• Building Use: Classrooms, offices, musical and theatrical theaters

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Project Background

Page 6: Arts & Humanities Instructional Building

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

• Arts and Humanities Instructional Building Project Background

• Analysis Areas

• Roof System Analysis

• Façade Sequencing

• Waste Management

• Final Conclusions and Recommendations

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Agenda

Page 7: Arts & Humanities Instructional Building

Roof System Analysis

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Objective:

Compare 4-ply built-up roof system vs. green roof system

Considerations:

• Cost

• Schedule

• Structural

• Mechanical

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Page 8: Arts & Humanities Instructional Building

Green Roofs Green roof systems

Two main categories:

• Extensive: 15 psf – 80 psf, typically 4-6 inches deep•Less Maintenance and smaller plants

• Intensive: 80 psf – 150 psf, typically 12 inches deep

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Benefits:

• Reduce heat gain in summer

• Reduce rainfall runoff impacts

• Reduce sound reflection and transmission

Page 9: Arts & Humanities Instructional Building

Roof Systems

Green roof system

Extensive roof designed to be 24 psf4 inches of growing mediumPlant selection: sedums

Built-up roof system

4-ply roof 4 inches of rigid insulationMinimum dead load design 5.5 psf, table C3-1, ASCE7-05

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 10: Arts & Humanities Instructional Building

Costs & Scheduling

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

AHIB

Green roof

Page 11: Arts & Humanities Instructional Building

Costs & SchedulingMaterial and Installation Summary:

• Built-up roof @ $1.98 / sf = $ 7,223

• Green roof @ $14.43 / sf = $52,640

Cost Difference: $45,417

Installation Productivity:

• Built-up roof @ 2,000 sq.ft installed per day = 13 days

• Green roof @ 1,800 sq.ft installed per day = 14 days

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 12: Arts & Humanities Instructional Building

Structural ImpactArea Analyzed

Area over musical theater. Typical bay

W10x12 beams, 17 ftW27x84 girders, 40 ft

Resizing of structural members is not required

W10x12 typ

W27

x84

typ

Live load: 30 psfSnow load: 19.3 psfDead load: 49 psfGreen roof load: 24 psf

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

1.2D + 1.6L + .5S = 145 psf

• ΦVn ≥ Vu • ΦMn ≥ Mu • L/240

Page 13: Arts & Humanities Instructional Building

Mechanical Impact

• Green roof expected heat flow reduction is 20% in summer months

• Greatest thermal savings of a green roof is in summer months

Heat flow calculations Built-up roof: cooling qx = (91-68) * 3,648 / 15.89 = 5,280 btu/hr Green roof savings = 5,280 btu/hr * 20% = 1,560 btu/hr

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 14: Arts & Humanities Instructional Building

Roof System Analysis

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Built-up roof system

Considerations:

• Cost

• Schedule

• Structural

• Mechanical

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Results:

• Built-up roof ($45,417)

• Faster installation

• No impact

• No impact

Page 15: Arts & Humanities Instructional Building

Agenda

• Arts and Humanities Instructional Building Project Background

• Analysis Areas

• Roof System Analysis

• Façade Sequencing

• Waste Management

• Final Conclusions and Recommendations

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 16: Arts & Humanities Instructional Building

Façade SequencingObjective:

Analyze alternative methods for the construction of the facade

Considerations:

• Productivity

• Cost

• Schedule

• Practicality

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 17: Arts & Humanities Instructional Building

Why Re-Sequencing?Façade materials

• Curtain wall

• Pre-finished aluminum panels

• Brick veneer

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 18: Arts & Humanities Instructional Building

Façade SequencingOriginal Sequence

• 37 week duration

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 19: Arts & Humanities Instructional Building

Façade SequencingFour alternatives identified

• Alternative A – compress schedule by adding additional crews• Alternative B – compress schedule by adding additional masonry crews• Alternative C – phase sequence of north facade• Alternative D – change aluminum panels to masonry veneer

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 20: Arts & Humanities Instructional Building

Façade SequencingAlternative C

• Alternative C phases construction of north façade• Later curtain wall activities occur sequentially• 36 week duration

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 21: Arts & Humanities Instructional Building

Façade SequencingAlternative C

Considerations:

• Productivity

• Cost

• Schedule

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Results:

• No loss of productivity

• ($13,544)

• One week faster

Page 22: Arts & Humanities Instructional Building

Agenda

• Arts and Humanities Instructional Building Project Background

• Analysis Areas

• Roof System Analysis

• Façade Sequencing

• Waste Management

• Final Conclusions and Recommendations

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 23: Arts & Humanities Instructional Building

Waste ManagementObjective:

Develop a waste management plan for the AHIB

Considerations:

• Cost

• Accessibility

• Practicality

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 24: Arts & Humanities Instructional Building

Waste ManagementMaterials

• Wood

• Concrete

• Gypsum board

Anticipated recycling

• Concrete: 37 tons

• Wood: 18 tons

• Gypsum board: 7 tons

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 25: Arts & Humanities Instructional Building

Waste Management

Costs

• Tipping fee

• Rental fee

• Hauling fee

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Source separated

• Construction debris separated at jobsite into different recycling bins

Page 26: Arts & Humanities Instructional Building

Waste Management

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 27: Arts & Humanities Instructional Building

Waste Management

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Waste Management

• Site Utilization Plan

Page 28: Arts & Humanities Instructional Building

Waste ManagementWaste management plan

Considerations:

• Cost

• Accessibility

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Results:

• ($2,500)

• Recycling centers are available

Page 29: Arts & Humanities Instructional Building

Agenda

• Arts and Humanities Instructional Building Project Background

• Analysis Areas

• Roof System Analysis

• Façade Sequencing

• Waste Management

• Final Conclusions and Recommendations

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 30: Arts & Humanities Instructional Building

ConclusionRecommendations

• Construct 4-ply built-up roof

• Re-sequence façade construction

• ($13,544)

• One week faster

• Implement waste management plan

• ($2,500)

• 65 tons diverted from landfill

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 31: Arts & Humanities Instructional Building

Questions

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 32: Arts & Humanities Instructional Building

Acknowledgements

Howard Community College

Riparius Construction, Inc

Penn State AE Faculty

Family and Friends

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 33: Arts & Humanities Instructional Building

Façade Sequencing

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 34: Arts & Humanities Instructional Building

Façade Sequencing

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

Page 35: Arts & Humanities Instructional Building

Sound Attenuation

Construction Management 2006

Noah J. AshbaughSenior Thesis Presentation

Roof System Analysis

Project Background

Façade Sequencing

Waste Management

Conclusion

• Expected sound transmission reduction: 5 decibels

• 55 decibels reduced to 50 decibels

• Road traffic to office activities