asbestos abatement project design · c. “report of findings of partial inspection for asbestos...

167
Asbestos Abatement Project Design for the Cuyahoga Community College-Metro Campus Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects Recreation Center, Arts & Music Auditorium, Media Center & Theater 2900 Community College Avenue Cleveland, Ohio 44115 Prepared for Cuyahoga Community College 700 Carnegie Avenue Cleveland, Ohio 44115 Prepared by Professional Service Industries, Inc. 5555 Canal Road Cleveland, Ohio 44125 Draft Issued: May 10, 2019 PSI Project Number: 01372563

Upload: others

Post on 18-Apr-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design

for the

Cuyahoga Community College-Metro Campus Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects

Recreation Center, Arts & Music Auditorium, Media Center & Theater

2900 Community College Avenue Cleveland, Ohio 44115

Prepared for

Cuyahoga Community College 700 Carnegie Avenue Cleveland, Ohio 44115

Prepared by

Professional Service Industries, Inc. 5555 Canal Road

Cleveland, Ohio 44125

Draft Issued: May 10, 2019

PSI Project Number: 01372563

Page 2: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design

Cuyahoga Community College-Metro Campus

Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects Recreation Center, Arts & Music Auditorium,

Media Center & Theater

Prepared on: PSI Project Number: Draft Issued: 10/19/18 01372563

Prepared by: Prepared for: Professional Service Industries, Inc. Cuyahoga Community College 5555 Canal Road 700 Carnegie Avenue Cleveland, Ohio 44125 Cleveland, Ohio 44115

Project Designer: Reviewed by: DRAFT

DRAFT

Jennifer Rogowski Asbestos Hazard Abatement Project Designer

Page 3: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

TOC - 1

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS Section 01013 Summary of Work Section 01043 Project Coordination Section 01091 Definitions and Standards Section 01092 Codes, Regulation and Standards Section 01220 Project Meetings Section 01301 Submittals Section 01410 Air Monitoring by the Owner Section 01503 Temporary Facilities Section 01513 Temporary Negative Pressure and Air Circulation System Section 01526 Temporary Enclosures Section 01527 Regulated Areas Section 01529 Mini-Enclosures and Glovebags Section 01560 Worker Protection Section 01562 Respiratory Protection Section 01562 Decontamination Units Section 01632 Substitutions Section 01701 Contract Closeout Section 01711 Project Decontamination Section 01714 Work Area Clearance DIVISION 2 SITE WORK Section 02046 Cutting and Patching of Asbestos-Containing Materials Section 02081 Removal of Asbestos-Containing Materials, OSHA Class I Section 02083 Removal of Asbestos-Containing Materials, OSHA Class II Section 02084 Disposal of Asbestos-Containing Waste Material Section 02086 Hazardous Waste Management DIVISION 9 FINISHES Section 09805 Encapsulation of Asbestos-Containing Materials LIST OF APPENDICES Appendix A Asbestos Abatement Drawings Appendix B Worker Acknowledgement Form Appendix C Pre-Abatement Inspection Form Appendix D Visual Inspection Form Appendix E Certificate of Reoccupancy Appendix F Asbestos Survey Report

Page 4: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

SECTION 01013 - SUMMARY OF THE WORK PART 1 - GENERAL 1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division Specification Sections, apply to this Section.

B. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga Community College-Metro Campus-Recreation Center, 2900 Community College Avenue, Cleveland, Ohio”, a Limited Asbestos Survey, laboratory testing results, drawings and other referenced documents issued under separate cover by Gandee & Associates dated March 2019 for the use of Cuyahoga Community College/ConstructAbility, Inc. These documents were relied upon for the development and completion of this specification.

C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga Community College-Metro Campus-Art & Music Auditorium, 2900 Community College Avenue, Cleveland, Ohio”, a Limited Asbestos Survey, laboratory testing results, drawings and other referenced documents issued under separate cover by Gandee & Associates dated March 2019 for the use of Cuyahoga Community College/ConstructAbility, Inc. These documents were relied upon for the development and completion of this specification.

D. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga Community College-Metro Campus-Media Center & Theater, 2900 Community College Avenue, Cleveland, Ohio”, a Limited Asbestos Survey, laboratory testing results, drawings and other referenced documents issued under separate cover by Gandee & Associates dated March 2019 for the use of Cuyahoga Community College/ConstructAbility, Inc. These documents were relied upon for the development and completion of this specification.

Project identification and directory

Site Address: Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects Recreation Center, Arts & Music Auditorium, Media Center & Theater 2900 Community College Avenue Cleveland, Ohio 44115

Project Owner: Cuyahoga Community College District Office

700 Carnegie Avenue Cleveland, Ohio 44115

Contact: Judi Cooper, Capital and Construction 216-987-3474

Page 5: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Environmental Consultant:

Professional Services Industries, Inc. 5555 Canal Road Cleveland, Ohio 44125

Contact: Jennifer D. Rogowski – SR. Project Manager/Designer 216-447-1335

Construction Manager:

ConstructAbility, Inc. 24600 Center Ridge Road, Suite 295 Westlake, Ohio 44145

Contact: Mike Finucan – Construction Manager 440-391-5475

Scope of Work consists of:

Removal and disposal of select ACM in areas scheduled for renovation as listed in this section and the project drawings, including (but not limited to):

Recreation Center:

• Removal of ACM fireproofing from North Penthouse ceilings, stairwell and adjacent substrate; and non-ACM fireproofing over remnant ACM fireproofing from the South Penthouse ceiling.

• Removal of ACM pipe fitting insulation systems on pipes insulted with

fiberglass located within the North Penthouse, South Penthouse, and Basement Room 23J.

• Removal of ACM hard plaster wall systems (perimeter walls) in the North

Penthouse and South Penthouse.

• Removal of ACM duct connectors on air handling units within the North Penthouse, South Penthouse, Basement G1-Room 28 and Basement Room 23J. Duct connectors may have to be abated in conjunction with the removal of the air handling units.

• Removal of ACM seam sealant (mastic) on air handling units within

Basement Room 23J.

• Assumed ACM Fire Doors to remain within the facility.

• ACM debris on floor within the North Penthouse is to be abated prior to the beginning of this project.

Arts & Music Auditorium:

• Removal of ACM fireproofing from Room 91C (South Concourse) and Room

Page 6: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

107 ceilings; and non-ACM fireproofing over remnant ACM fireproofing from the Room 115, the North Penthouse and South Penthouse ceilings.

• Removal of ACM mastic (yellow) and associated asbestos contaminated

fiberglass insulation installed over hard plaster walls in the North Penthouse and South Penthouse.

• Assumed ACM Fire Doors to remain within the facility. • ACM debris on the floors within the Room 115 and Room 91C is to be

abated prior to the beginning of this project.

Media Center & Theater:

• Removal of non-ACM fireproofing over remnant ACM fireproofing from the Room 304, Room 300 and Room 21B.

• Removal of ACM pipe fitting insulation systems on pipes insulted with

fiberglass located within the Room 304, Room 300 and Room 21B.

• Removal of ACM hard plaster wall systems over steel beams/columns in Room 304 and Room 300.

• Removal of ACM duct connectors on air handling units within the North

Penthouse, South Penthouse, Basement G1-Room 28 and Basement Room 23J. Duct connectors may have to be abated in conjunction with the removal of the air handling units.

• Removal of ACM seam sealant (mastic) on air handling units within

Basement Room 23J.

• Assumed ACM Fire Doors to remain within the facility. • ACM debris on the floors within the Room 304 and Room 300 is to be abated

prior to the beginning of this project. 1.02 WORK COVERED BY CONTRACT DOCUMENTS

The Project consists of removal of regulated and selected non-regulated asbestos containing materials before renovation activities at:

1. Project Location & Owner: Cuyahoga Community College-Metro Campus Recreation Center, Arts & Music Auditorium, Media Center & Theater 2900 Community College Avenue Cleveland, OH 44115

Page 7: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

A. Contract Documents, forms of agreement, and related contractual documents were

prepared under separate cover for the work listed in this specification.

B. The Work consists of;

1. Removal of all Regulated Asbestos Containing Materials (RACM) in areas that Cuyahoga Community College is planning the removal and replacement of several air handling units, water pumps and pneumatic controls (on HVAC equipment to DDC controls) located within various penthouses/mechanical rooms of the Recreation Center Building, Media Center & Theater Building and Art & Music Auditorium (on the Tri-C Metro Campus) as listed in this section and the project drawings.

2. Removal, decontamination and disposal of asbestos contaminated Non-ACM in all areas.

3. Patch, repair and labeling of any exposed remaining ACM in areas not affected by the project.

C. The Work will be constructed under a single prime contract.

1.03 WORK UNDER OTHER CONTRACTS

A. Separate Contract: The Owner has awarded a separate contract for performance of certain construction operations at the site. Those operations will be conducted simultaneously with work under this Contract in areas of new construction or areas of no ACM. That Contract requires the successful completion of all abatement activities prior to entry of non abatement personnel in affected areas. It is anticipated that the phasing in of construction activities will be coordinated with the abatement contractor as areas are released by the Construction Manager.

B. Cooperate fully with separate contractors so that work under those contracts may be carried out smoothly, without interfering with or delaying work under this Contract.

1.04 FUTURE WORK

A. It is anticipated that after substantial completion of the work of this contract, additional discovery and abatement of various materials may become necessary. The contractor must be prepared to provide additional services if needed at the unit rates listed in the bid form for a period of one year after substantial completion of work.

1.05 WORK SEQUENCE

A. The Work will be completed with each penthouse/mechanical room as a separate unit.

1. Cuyahoga Community College plans to contract with an abatement contractor to remove identified ACM prior to the removal and replacement of the air handling units, water pumps and pneumatic controls.

Page 8: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

1.06 ASBESTOS-CONTAINING MATERIALS:

A. The Work of this contract involves activities that will disturb asbestos-containing materials (ACM) or regulated asbestos-containing materials (RACM). The location and type of ACM known to be present at the worksite is set forth in the drawings. If any other ACM or RACM is found, notify the owner, other employers and employees about the location and quantity of the ACM or RACM immediately upon discovery.

B. The Bid for Work of this contract is to be on a lump sum basis for the quantities listed and on an add/deduct unit rate basis for discovered or changed quantities. The contractor agrees not to seek payment for quantities in excess of up to 10% of the bid amount. Likewise, the Owner will not seek deductions in the contract amounts for reduced quantities down to 90% of the bid amount. Unit rates will be used for all other work.

C. Trace Materials (asbestos plaster and drywall/joint compound) means the material was

tested and at least one sample from that material type contained between trace and 1% asbestos. These materials are regulated by the OSHA Construction Standard (29 CFR 1926.1101) and require employers of employees who disturb these materials to comply with basic work practices and be monitored for exposure and protected if they are expected to exceed the OSHA’s Permissible Exposure Limits (PEL’s). If exposure readings are below the PEL, only basic material handling requirements need to be followed.

1.07 ASBESTOS HEALTH RISK:

A. The disturbance or dislocation of ACM may cause asbestos fibers to be released into the building’s atmosphere, thereby creating a potential health risk to workers and building occupants. Apprise all workers, supervisory personnel, subcontractors and consultants who will be at the job site of the seriousness of the risk and of proper work procedures which must be followed.

B. Where in the performance of the work, workers, supervisory personnel, subcontractors,

or consultants may encounter, disturb, or otherwise function in the immediate vicinity of any identified ACM, take appropriate continuous measures as necessary to protect all building occupants from the risk of exposure to airborne asbestos. Such measures shall include the procedures and methods described herein, and compliance with regulations of applicable federal, state and local agencies.

1.08 TRACE AMOUNTS OF ASBESTOS IN MATERIALS:

A. PSI recommends the following work practices accordance with the OSHA Construction Industry Standard:

B. Incidental cutting, drilling, nailing, etc. of the original plaster areas must follow the OSHA modified handling work practices by all trades. (See attached OSHA Interpretation letter dated 8/7/98)

Page 9: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

C. All debris can be treated as unregulated construction waste but must be handled and disposed of wet.

D. High-speed abrasive disk saws, dry sweeping, dry shoveling or use of compressed air is prohibited on the identified materials.

1.08 LEAD BASED PAINT HEALTH RISK: E.

F. The disturbance or dislocation of lead based paints (LBP) may cause lead particles to be released into the building`s atmosphere, thereby creating a potential health risk to workers and building occupants. Apprise all workers, supervisory personnel, subcontractors and consultants who will be at the job site of the seriousness of the risk and of proper work procedures which must be followed.

G. Where in the performance of the work, workers, supervisory personnel, subcontractors, or consultants may encounter, disturb, or otherwise function in the immediate vicinity of any identified LBP, take appropriate continuous measures as necessary to protect all building occupants from the risk of exposure to airborne lead. Such measures shall include the procedures and methods described herein, and compliance with regulations of applicable federal, state and local agencies.

H. All sandblasting work must be performed within the negative pressure enclosures after asbestos final clearances have been achieved. Final clearance of sandblasting operations will consist of washing all surfaces with a TSP solution by the contractor, visual clearance inspection and performance of lead air sampling to achieve values less than the OSHA PEL for lead in construction by the Construction Manager.

1.09 CONTRACTOR USE OF PREMISES

A. Use of the Site: Limit use of the premises to work in areas indicated. Confine operations

to areas within contract limits indicated. Do not disturb portions of the site beyond the areas in which the Work is indicated.

1. Owner Occupancy: Allow for Owner occupancy and use by the public per

drawings. 2. Driveways and Entrances: Keep driveways and entrances serving the premises

clear and available to the Owner, the Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

B. Use of the Existing Building: Maintain the existing building in a weather tight condition

throughout the construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building and its occupants during the construction period.

Page 10: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

1. Use of Existing Elevators: use of elevators by the Contractor will be permitted. The Contractor will be permitted to use the freight elevators for temporary freight service and the transportation of construction personnel during the construction period. This elevator may also be made available to the Owner at specific times; coordinate freight elevator usage with The Construction Manager. Provide protective pads for the elevator car and other appropriate protective measures for the car and entrance doors and frames. During asbestos abatement activities the car is to be protected as set forth in the Division 1 Section on Temporary Enclosures.

2. Smoking: Smoking or open fires will not be permitted within the building enclosure

or on the premises. 3. Toilet Rooms: Use of existing toilets within the construction area, by the

Contractor’s personnel, will be permitted. 1.10 OCCUPANCY REQUIREMENTS

A. Partial Owner Occupancy: The Owner reserves the right to occupy and to place and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placing of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. The Construction Manager will prepare a Certificate of Substantial Completion for

each specific portion of the Work to be occupied prior to Owner occupancy. 1.11 AIR MONITORING BY THE OWNER:

A. The Owner has contracted for air monitoring. Air monitoring may be conducted both outside and inside of the work area during the work, and for clearance sampling at the end of the project

1. Outside of the Work Area: The Owner's air monitoring firm may sample air outside

of the work area to detect faults in the work area isolation such as:

a. Contamination of the building outside of the work area with airborne asbestos fibers,

b. Failure of filtration or rupture in the differential pressure system, c. Contamination of air outside the building envelop with airborne asbestos

fibers. d. Contamination outside of the work areas by airborne lead particulate.

2. Inside the Work Area: The Owner’s air monitoring firm may monitor airborne fiber counts in the Work Area. The purpose of this air monitoring is to detect airborne asbestos concentrations which may challenge the ability of the Work Area isolation procedures to protect the balance of the building or outside of the building from contamination by airborne fibers.

Page 11: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

B. Work area clearance: Clearance air sampling by the Owner’s air monitor at the completion of asbestos abatement work is described in Section 01711 Project Decontamination.

C. Air monitoring required by OSHA is work of the Contractor and is not covered in this

section. 1.12 SCHEDULE OF AIR SAMPLES BY OWNER:

A. Sample cassettes: Samples will be collected on 25 mm. cassettes as follows:

1. PCM: 0.8 micrometer mixed cellulose ester.

B. Number and Volume of Samples: The number and volume of air samples given in the schedules is approximate. The exact number and volume of samples collected by the Owner may vary depending upon job conditions and the analytical method used.

C. Sample Volume and Sensitivity:

1. PCM: The sample volumes collected by the Owner’s air monitor will be determined

based upon the work conditions, location and material type on a daily basis. a. For purposes of this specification, the sample volume calculated above will

be considered to be of sufficient size so that there is a 95% level of confidence that the value measured by each individual sample at the limit of detection (LOD) is less than or equal to the limit values specified below.

b. For purposes of this specification, the Limit of Detection (LOD) is defined as 7 fibers/mm2 on the filter or 5 fibers/100 fields.

c. For purposes of this specification overloaded samples will be considered as exceeding the applicable limit value.

D. Base Line:

1. Before Start of Work: The Owner will secure air samples to establish a base line. 2. PCM Samples

Location Number Limit Approx. Rate Sampled of Value Volume (Liters/

Samples (Fibers/cc) (Liters) Minute) Each Work Area 5 0.01 <2,000> 1-10

Outside Each 5 0.01 <2,000> 1-10 Work Area

Outside Building 5 0.01 <2,000> 1-10

Page 12: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

3. Base Line: a level expressed in fibers per cubic centimeter which is twenty-five percent greater than the largest of the following:

a. Average of the PCM samples collected outside each Work Area b. Average of the PCM samples collected outside the building c. 0.01 fibers per cubic centimeter

E. Daily:

1. From start of work of Section 01526 Temporary Enclosures through the work of

Section 01711 Project Decontamination, the Owner may take samples. 2. Sample volume and sensitivity: inside the work area may vary depending upon

conditions in the work area. If samples are overloaded at the sample volume required for a limit value equal to the Stop Action Levels or Immediate Stop Action Levels given later in this section, the level is considered to have been exceeded.

3. PCM Samples:

Location Number Limit Approx. Rate Sampled of Value Volume (LPM)

Samples (Fibers/cc) (Liters) Each Work Area 2 <0.1> <100> 1-10 Outside Each 1 0.01 <1,000> 1-10 Work Area at Critical Barrier

Clean Room 1 0.01 <1,000> 1-10

Equipment Decon 1 0.01 <1,000> 1-10

Outside Building 1 0.01 <1,000> 1-10

Output of Pressure 1 0.01 <1,000> 1-10 Differential System

F. Additional samples may be taken at Owner's or The Construction Manager’s discretion. If

airborne fiber counts exceed allowed limits additional samples may be taken as necessary to monitor fiber levels.

1.13 ANALYTICAL METHODS USED BY THE OWNER:

A. The following methods will be used by The Owner in analyzing filters used to collect air

Page 13: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

samples. Sampling rates may be varied from printed standards to allow for high volume sampling.

1. Phase Contrast Microscopy (PCM) will be performed using the NIOSH 7400

method. 1.14 LABORATORY TESTING BY OWNER:

A. The services of a testing laboratory will be employed by the Owner to perform laboratory analyses of the air samples. A microscope and technician will be set up at the job site, or samples will be sent overnight on a daily basis, so that verbal reports on air samples can be obtained within 24 hours. The Contractor will have access to all air monitoring tests and results.

B. The Contractor will have access to all air monitoring tests and results upon request.

C. Written Reports: of all air monitoring tests will be posted at the job site on a daily basis.

1.15 FIBERS AND STRUCTURES

A. Fibers Counted: The following procedure will be used to resolve any disputes regarding fiber types when a project has been stopped due to excessive airborne fiber counts.

1. Large Fibers: "Airborne Fibers" referred to above include all fibers regardless of

composition as counted by phase contrast microscopy (PCM), unless additional analysis by transmission or scanning electron microscopy demonstrates to the satisfaction of The Construction Manager that non-asbestos fibers are being counted. "Airborne Fibers" counted in samples analyzed by transmission electron microscopy shall be asbestos fibers, greater than 5 microns in length. For purposes of stop action levels, subsequent to analysis by electron microscopy, the number of "Airborne Fibers" shall be determined by multiplying the number of fibers, regardless of composition, counted by PCM by the proportion of fibers that are asbestos as determined by TEM (a number equal to, asbestos fibers counted, divided by all fibers counted in the electron microscopy analysis).

2. Small Structures: "Airborne Fibers" referred to above include asbestos structures

(fibers, bundles, clusters or matrices) of any diameter and any length greater than 0.5 microns.

1.16 ADDITIONAL TESTING:

A. The Contractor may conduct air monitoring and laboratory testing. If he elects to do this the cost of such air monitoring and laboratory testing shall be at no additional cost to the Owner. Additionally, only the Owner’s Air Monitoring results will be considered controlling in the event of a dispute.

Page 14: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

1.17 PERSONAL MONITORING:

A. Owner will not perform air monitoring for the Contractor to meet Contractor's OSHA requirements for personal sampling or any other purpose.

PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.01 STOP ACTION LEVELS:

A. Inside Work Area: Maintain an average airborne count in the Work Area of less than 0.5 fibers per cubic centimeter. If the fiber counts rise above this figure for any sample taken, revise work procedures to lower fiber counts. If the Time Weighted Average (TWA) fiber count for any work shift or 8 hour period exceeds 0.5 fibers per cubic centimeter, stop all work, leave Pressure Differential System in operation and notify The Construction Manager. After correcting cause of high fiber levels, do not recommence work for 24 hours unless otherwise authorized, in writing, by the Construction Manager.

1. If airborne fiber counts exceed 2.5 fibers per cubic centimeter for any period of time

cease all work except corrective action until fiber counts fall below 0.5 fibers per cubic centimeter and notify The Construction Manager. After correcting cause of high fiber levels, do not recommence work for 24 hours unless otherwise authorized, in writing, by The Construction Manager.

B. Inside Work Area: Maintain an average airborne count in the work area of less than the

Stop Action Level given below for the type of respiratory protection in use. If the fiber counts rise above this figure for any sample taken, revise work procedures to lower fiber counts. If the Time Weighted Average (TWA) fiber count for any work shift or 8 hour period exceeds the Stop Action Level, stop all work except corrective action, leave pressure differential and air circulation system in operation and notify The Construction Manager. After correcting cause of high fiber levels, do not recommence work for 24 hours unless otherwise authorized, in writing, by The Construction Manager. STOP IMMEDIATELY MINIMUM ACTION STOP RESPIRATOR PROTECTION LEVEL LEVEL REQUIRED FACTOR (f/cc) (f/cc)

0.1 0.5 Half face 10 0.5 2.5 PAPR 50

1.0 5.0 Supplied Air 100 Pressure Demand

Page 15: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

1. If airborne fiber counts exceed Immediate Stop Level given above for type of

respiratory protection in use for any period of time cease all work except corrective action. Notify the Construction Manager. Do not recommence work until fiber counts fall below Stop Action Level given above for the type of respiratory protection in use. After correcting cause of high fiber levels, do not recommence work for 24 hours unless otherwise authorized, in writing, by The Construction Manager.

C. Outside Work Area: If any air sample taken outside of the Work Area exceeds the base

line established in Part 1 of this section, immediately and automatically stop all work except corrective action. The Construction Manager will determine the source of the high reading and so notify the Contractor in writing.

1. If the high reading was the result of a failure of Work Area isolation measures

initiate the following actions:

a. Immediately erect new critical barriers as set forth in Section 01526 Temporary Enclosures to isolate the affected area from the balance of the building. Erect Critical Barriers at the next existing structural isolation of the involved space (e.g. wall, ceiling, floor).

b. Decontaminate the affected area in accordance with Section 01712 Cleaning & Decontamination Procedures.

c. Require that respiratory protection as set forth in Section 01562 Respiratory Protection be worn in affected area until area is cleared for re-occupancy in accordance with Section 01711 Project Decontamination.

d. Leave Critical Barriers in place until completion of work and insure that the operation of the pressure differential system in the Work Area results in a flow of air from the balance of the building into the affected area.

e. If the exit from the clean room of the personnel decontamination unit enters the affected area, establish a decontamination facility consisting of a Shower Room and Changing Room as set forth in Section 01563 Decontamination Units at entry point to affected area.

f. After Certification of Visual Inspection in the Work Area remove critical barriers separating the work area from the affected area. Final air samples will be taken within the entire area as set forth in Section 01711 Project Decontamination.

2. If the high reading was the result of other causes initiate corrective action as

determined by the The Construction Manager.

D. Effect on Contract Sum: Complete corrective work with no change in the Contract Sum if high airborne fiber counts were caused by Contractor's activities. The Contract Sum and schedule will be adjusted for additional work caused by high airborne fiber counts beyond the Contractor's control.

Page 16: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

3.02 STOP WORK:

A. If the Owner or the Project Administrator presents a written stop work order, immediately and automatically conform to that stop work order, while maintaining temporary enclosures and pressure differential. Do not recommence abatement work until authorized in writing by Owner or Project Administrator.

B. Immediately initiate the following actions: After being presented with a stop work order

immediately:

1. Cease all asbestos removal activities, or any other activities that disturbs ACM. 2. Repair any fallen, ripped or otherwise failed work area isolation measures. 3. Maintain in operation all work area isolation measures including those required by

Sections 01526 Temporary Enclosures, 01513 Temporary Pressure Differential & Air Circulation System, 01563 Decontamination Units.

4. Maintain all worker protections including those required by Sections 01560 Worker

Protection - Asbestos Abatement, and 01562 Respiratory Protection. 5. Fog the air in the work area with a mist of amended water to reduce airborne fiber

levels.

C. Do not recommence work until authorized in writing by the Owner or The Construction Manager.

Page 17: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

3.03 SCHEDULE OF ASBESTOS-CONTAINING MATERIALS BY BUILDING AREA: The following quantities are estimations of exposed or observed ACM only and need to be field verified by the Contractor. Recreation Center-North Penthouse-Removal of 2 Air Handling Units Material Description General Location Estimated

Quantity Fireproofing Ceilings in Penthouse,

stairwell and adjacent substrates

1,450 sf

Pipe Fitting Insulation Systems Penthouse 38 Hard Plaster Wall Systems Penthouse, Stairwell 1,500 sf Duct Connectors Air Handling Units 6 Recreation Center-South Penthouse-Removal of 6 Air Handling Units Material Description General Location Estimated

Quantity Fireproofing Ceilings 3,125 sf Pipe Fitting Insulation Systems Penthouse 75 Hard Plaster Wall Systems Penthouse-Stairwell 2,000 sf Duct Connectors Air Handling Units 12 Mastic and Acoustical Wall Panels Penthouse 150 sf Recreation Center-Basement G1-Room 28-Removal of 1 Air Handling Unit Material Description General Location Estimated

Quantity Duct Connectors Air Handling Units 3 Recreation Center-Basement Room 23J-Removal of 1 Air Handling Unit Material Description General Location Estimated

Quantity Pipe Fitting Insulation Systems 16 Duct Connectors Air Handling Units 2 Duct Seam Sealant (Mastic) Air Handling Units 2 sf

Page 18: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Art & Music Auditorium-Room 91C (South Concourse)-Removal of Vertical Pumps Material Description General Location Estimated

Quantity Fireproofing Ceilings 150 sf Art & Music Auditorium-Room 115-Removal of 1 Air Handling Unit Material Description General Location Estimated

Quantity Non-ACM Fireproofing over remnant ACM Fireproofing

Ceilings 625 sf

Art & Music Auditorium-Room 107-Removal of 1 Air Handling Unit Material Description General Location Estimated

Quantity Fireproofing Ceilings 750 sf Art & Music Auditorium-Room North Penthouse-Removal of 1 Air Handling Unit Material Description General Location Estimated

Quantity Yellow Mastic-associated asbestos contaminated glass fiber batt insulation installed over hard wall plaster systems

Plaster walls 900 sf

Non-ACM Fireproofing over remnant ACM Fireproofing

Ceilings 500 sf

Art & Music Auditorium-Room South Penthouse-Removal of 1 Air Handling Unit Material Description General Location Estimated

Quantity Yellow Mastic-associated asbestos contaminated glass fiber batt insulation installed over hard wall plaster systems

Plaster walls 900 sf

Non-ACM Fireproofing over remnant ACM Fireproofing

Ceilings 500 sf

Media Center & Theater-Room 304-Removal of 2 Air Handling Units Material Description General Location Estimated

Quantity Pipe Fitting Insulation Systems Room 304 26 Hard Plaster Systems Steel Beams/Columns 550 sf Non-ACM Fireproofing over remnant ACM Fireproofing

Ceilings 1,275 sf

Page 19: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Media Center & Theater-Room 300-Removal of 2 Air Handling Units Material Description General Location Estimated

Quantity Pipe Fitting Insulation Systems Room 300 26 Hard Plaster Systems Steel Beams/Columns 550 sf Non-ACM Fireproofing over remnant ACM Fireproofing

Ceilings 1,400 sf

Media Center & Theater-Room 84-Pump Replacement Material Description General Location Estimated

Quantity No ACM identified Room 84 NA Media Center & Theater-Room 21B-Removal of 2 Air Handling Units Material Description General Location Estimated

Quantity Pipe Fitting Insulation Systems Room 21B 28 END OF SECTION – 01013

Page 20: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01043 01043 - 1 Project Coordination

SECTION 01043 – PROJECT COORDINATION PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of the Contract and other Asbestos Abatement Project Design sections, apply to this section.

1.2 SUMMARY

1.2.1 This section includes administrative and supervisory requirements necessary for coordinating construction operation including, but not limited to, the following:

1.3 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

1.3.1 Provide a full-time Asbestos Abatement Supervisor who is experiences in administration and supervision of asbestos abatement projects including work practices, protective measures for building and personnel, and disposal procedures. This person is the Contractor’s Representative and will function as the OSHA competent person at the work site. The Asbestos Abatement Supervisor is responsible for compliance with all applicable federal, state and local laws and regulations.

1.3.2 The Asbestos Abatement Supervisor is to be accredited by the US EPA as an Asbestos

Abatement Contractor Supervisor and licensed as an Ohio Department of Health (ODH) Asbestos Hazard Abatement Specialist

1.3.3 The Asbestos Abatement Supervisor must have demonstrable experience in the

successful management of asbestos abatement projects that are similar to the work of this contract. The Asbestos Abatement Supervisor must have a minimum of two years’ experience in the onsite management of asbestos abatement projects and must have had responsible charge of a minimum of ten asbestos abatement projects similar in size and type of the work in this contract.

1.3.4 The Asbestos Abatement Supervisor is to be a Competent Person as required by OSHA

in 29 CFR 1926.1101 and must be present at all times when response actions are being performed. In the absence of the Asbestos Abatement Supervisor, the Contractor shall designate a similarly qualified individual who will perform all required project Asbestos Abatement Supervisor duties.

1.4 PROGRESS MEETINGS

1.4.1 General: In addition to specific coordination and pre-installation meetings for each element of work, and other regular project meetings held for other purposes, Construction Manger will hold general progress meetings as required. See Section 01220 – Project Meetings.

1.5 PRE-CONSTRUCTION CONFERENCE

1.5.1 An initial progress meeting, recognized as "Pre-Construction Conference" will be convened by the Construction Manager prior to start of any work. See Section 01220 – Project Meetings.

1.6 RECORD KEEPING

Page 21: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01043 01043 - 2 Project Coordination

1.6.1 Daily Log: Maintain a daily log within an accessible area as a bound, sequential, hand-written record carefully prepared daily that documents, but is not limited, to the following items:

A. Meetings (purpose, attendees, brief discussion)

B. Visitation (authorized and unauthorized)

C. Personnel (by name)

D. Special or unusual events (barrier breeching, equipment failures, accidents)

E. Inspection of work area preparation prior to start of removal and daily thereafter

F. Removal of any sheet plastic barriers

G. Contractor’s inspections prior to spray back, lock back, encapsulation, enclosure or

any other operation that will conceal the condition of ACM or the substrate from which such materials have been removed

H. Removal of waste materials from work area

I. Decontamination of equipment (list items)

J. Contractor’s final inspection and air clearance analysis

1.6.2 Entry/Exit Log: Maintain within the Decontamination Unit a daily log documenting the

dates and time of, but not limited to, the following items

A. Visitors (name, organization, entry time, exit time, respiratory protection)

B. Personnel (printed name, license number, entry time, exit time, respiratory protection)

1.6.3 Air Monitoring Results: Post personnel and work area air monitoring results in Decontamination Unit within 24 hours of sample collection. Post the respiratory protection requirements for the work in progress

1.6.4 Other Records: Maintain the following documentation in a location accessible to

Contractor workers, Owner, Construction Manager and Consultant:

A. Documentation of inspection by federal, state, or local agencies

B. Respiratory protection program

C. Waste manifests and shipping records

D. Landfill receipts

E. Accident report

1.6.5 Provide a copy of records to the Construction Manager and Consultant on a daily basis. 1.7 SPECIAL REPORTS

1.7.1 General: Except as otherwise indicated, submit special reports directly to the Construction within one day of occurrence requiring special report, with copy to the

Page 22: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01043 01043 - 3 Project Coordination

Consultant and others affected by occurrence. This requirement is separate from any change order procedures. Compliance with change order procedures is required regardless of any reports proposed pursuant to this section.

1.7.2 Reporting Unusual Events: When an event of unusual and significant nature occurs at site (examples: failure of negative pressure system, rupture of temporary enclosures), prepare and submit a special report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. When such events are known or predictable in advance, advise Construction Manager in advance at earliest possible date.

1.7.3 Reporting Accidents: Prepare and submit special reports of significant accidents, at site and anywhere else work is in progress. Record and document data and actions; comply with industry standards. For this purpose, a significant accident is defined to include events where personal injury is sustained, property loss of substance is sustained, where the event posed a significant threat of loss or personal injury, or where work was stopped for over four hours during a scheduled shirt.

1.7.4 Report Discovered Conditions:

A. When an unusual condition of the building is discovered during the work (e.g. leaks,

termites, corrosion) prepare and submit a special report indication condition discovered.

B. Where suspect ACM not otherwise described in the Asbestos Abatement Project

Design are discovered, prepare, and submit a Special Report. 1.8 CONTINGENCY PLAN

1.8.1 Contingency Plan: Prepare a contingency plan for emergencies or any other event that may require breaching of work area, containment modification, abridgement of decontamination, or work area isolation procedures. Include in this plan procedures for performing electrical and mechanical repairs inside containment after abatement work has begun. Include in plan specific procedures for decontamination or work area isolation. Note that nothing in this asbestos abatement project design should impede safe exiting or providing of adequate medical attention in the event of an emergency. Items to be addressed in the plan include, but are not limited to:

A. Fire B. Accident C. Life threatening injury D. Non-life threatening injury E. Rescue F. Power failure G. Pressure differential system failure H. Breach of containment I. Electrical faults or shock J. Excessive heat/cold K. Supplied air system failure L. Water leaks M. Waste spills N. Unauthorized entry into work area O. Elevated air samples outside of containment P. Repairs inside containment Q. Toxic releases

Page 23: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01043 01043 - 4 Project Coordination

1.8.2 Submit the Contingency Plan to the Construction Manager and provide a copy to the Consultant prior to the start of work.

1.9 CONTRACTOR’S CONSTRUCTION SCHEDULE

1.9.1 Prepare a construction schedule and submit within 10 days after the date established for commencement of the work. Schedule should include the following information, at a minimum, for each phase:

A. Planned start date of non-asbestos demolitions B. Planned start date of preparation of the work area C. Planned start date of asbestos removal D. Planned date of final visual inspection and clearance air monitoring E. Planned date of substantial completion

1.9.2 Submit the construction schedule to the Construction Manager, provide a copy to the

Consultant, and post copies in the temporary field office.

1.9.3 Revise schedule after each meeting, event, or activities where revisions have been recognized or made. Issue the updated schedule concurrently with the report of each meeting.

1.10 PLAN OF ACTION

1.10.1 Prepare a detailed plan of the procedures proposed for use in complying with the requirements of this project design. Include in the plan: A. Location and layout of decontamination areas B. Sequencing of asbestos work C. Interface of trades involved in the performance of work D. Methods to be used to assure the safety of building occupants and visitors to the site E. Disposal plan including location of approved site F. Detailed description of the methods to be employed to control pollution G. Use of HEPA ventilation systems H. Closing out of the building’s HVAC system I. Method of removal to prohibit visible emissions in work area J. Packaging of removed asbestos debris

1.10.2 Submit the Plan of Action to the General Manager and provide a copy to the Consultant

prior to the start of work. 1.11 PROJECT DIRECTORY

1.11.1 Develop a directory of all entities involved in the project. Include the Contractor’s principal staff assignments, including the Superintendent and other personnel in attendance at the site. Identify individuals, their duties and responsibilities. List business name, contact person, normal business and emergency telephone and address of:

A. Owner, Construction Manager and Consultant B. Contractor’s Asbestos Abatement Supervisor, supervisory personnel and

Contractor’s home office C. Emergency services including, but not limited to, fire, ambulance, doctor, hospital,

police, power company and telephone company D. Local, state and federal agencies with jurisdiction over the project

Page 24: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01043 01043 - 5 Project Coordination

1.11.2 Post copies of the Project Directory in the project meeting room, the temporary field office, and at entrance to clean room of personnel decontamination unit.

1.12 BUILDING OCCUPANT NOTIFICATIONS

1.12.1 Notify other entities at the job site of the nature of the asbestos abatement activities, locations of asbestos-containing materials, requirements relative to asbestos set forth in this asbestos abatement project design, and applicable regulations. Advance notification will be made to:

A. Owner of the building and their representative B. Employees who will perform asbestos abatement work or related activities, or who

will be in the work area during the course of the work of this contract C. Employers of employees who work and/or will be working in adjacent areas during

the course of the work of this contract.

1.12.2 Notify emergency service agencies, including fire, ambulance, police or other agency that may service the abatement work site in case of an emergency. Notification is to include methods of entering work area, emergency entry and exit locations, modification to fire notification or firefighting equipment, and other information needed by agencies providing emergency services.

1.12.3 Any individual at the job site may notify emergency service agencies, if necessary,

without effect on this contract. 1.13 PRE-CONSTRUCTION INSPECTION

1.13.1 Prior to commencement of work, inspect areas in which work will be performed. Prepare a listing of damage to structure, surfaces and finishes, equipment or of surrounding properties which could be misconstrued as damage resulting from the work. Photograph or videotape existing conditions, as necessary, to document conditions. Submit to Construction Manager prior to starting work.

1.14 SUBMITTALS RELATIVE TO PROJECT COORDINATION

1.14.1 Before the Start of Work: Submit the following to the Construction Manager and provide a copy to the Consultant for review. No work shall begin until these submittals are returned with Construction Manager’s approval indicating that all submittals have been received-not reviewed.

A. Plan of Action B. Contingency Plans C. Project Directory D. Building Occupant Notification E. Pre-Construction Inspection F. Contractor’s Construction Schedule G. Accreditation: Submit copies of required training course certificates and ODH

licenses for the Asbestos Abatement Supervisor and abatement workers. H. Resume: Submit resume of Asbestos Abatement Supervisor

PART 2 – PRODUCTS (NOT APPLICABLE) PART 3 – EXECUTION (NOT APPLICABLE) END OF SECTION 01043

Page 25: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 1 Definitions and Standards

SECTION 01091 – DEFINITIONS AND STANDARDS PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of the Contract and other sections of the Asbestos Abatement Project Design apply to this section.

1.2 SUMMARY

1.2.1 General Explanation: A substantial amount of specification language constitutes

definitions for terms found in other contract documents, including the drawings. (Drawings must be recognized as diagrammatic in nature and not completely descriptive of the requirements indicated thereon.) Certain terms used in Contract Documents are defined in this article.

1.3 GENERAL DEFINITIONS

1.3.1 General: Definitions contained in this section are not necessarily complete, but are general to the extent that they are not defined more explicitly elsewhere in the Contract documents.

1.3.2 Indicated: This term refers to graphic representations, notes or schedules on the

drawings, or other paragraphs or schedules in the Asbestos Abatement Project Design, and similar requirements in Contract documents. Where terms such as "shown," "noted," "scheduled," and "specified" are used, it is to help locate the reference; no limitation on location is intended except as specifically noted.

1.3.3 Directed: Terms such as "directed", "requested", "authorized", "selected", "approved",

"required", and "permitted" mean "directed by the Owner’s Representative”, "requested by the Owner’s Representative", and similar phrases. However, no implied meaning shall be interpreted to extend the Owner’s Representative’s responsibility into the Contractor's area of construction supervision.

1.3.4 Approved: The term "approved," where used in conjunction with the Construction

Manager’s action on the Contractor's submittals, applications, and requests is limited to the responsibilities and duties of the Construction Manager. Such approval shall not release the Contractor from responsibility to fulfill Contract Document requirements, unless otherwise provided in the Contract Documents.

1.3.5 Regulations: The term "Regulations" includes laws, statutes, ordinances, patents,

royalties and lawful orders issued by authorities having jurisdiction, as well as rules, conventions and agreements within the construction industry that control performance of the Work, whether they are lawfully imposed by authorities having jurisdiction or not.

1.3.6 Furnish: The term "furnish" is used to mean "supply and deliver to the project site, ready

for unloading, unpacking, assembly, installation, and similar operations."

1.3.7 Install: The term "install" is used to describe operations at project site including the actual "unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations."

Page 26: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 2 Definitions and Standards

1.3.8 Provide: The term "provide" means "to furnish and install, complete and ready for the

intended use."

1.3.9 Installer: An "Installer" is an entity engaged by the Contractor, either as an employee, subcontractor or sub-subcontractor for performance of a particular construction activity, including installation, erection, application and similar operations. Installers are required to be experienced in the operations they are engaged to perform.

1.3.10 Project Site is the space available to the Contractor for performance of the work, either exclusively or in conjunction with others performing other construction as part of the project.

1.3.11 Testing Laboratories: A "testing laboratory" is an independent entity engaged to perform

specific inspections or tests, either at the Project Site or elsewhere, to report on and, if required, to interpret results of those inspections or tests.

1.3.12 Owner's Representative: The Owner's Representative will represent the Owner during

construction and until final payment is due. The Owner's Representative will advise and consult with the Owner. The Owner's instructions to the Contractor will be forwarded through the Owner's Representative.

1.3.13 Project Administrator: The Project Administrator is a full time representative of the Owner at the job site with authority to stop the work upon verbal order if requirements of the Contract Documents are not met, or if in the sole judgment of the Project Administrator, Owner's Representative, Owner, the interests of the Owner, safety of any person or the Owner's property are jeopardized by the work. The Project Administrator is different from the position of Owner's Representative as used in these documents, the latter having more limited authority in general and specifically not having authority to stop the work.

1.3.14 General Superintendent: This is the Contractor's Asbestos Abatement Supervisor at the work site. This person will generally be the Competent Person required by OSHA in 29 CFR 1926.

1.3.15 Stop Work Order: is a written order to cease asbestos removal, encapsulation or

enclosure activities. The Contractor must maintain work area enclosure, pressure differential isolation and ventilation of the work area, and decontamination units during the period that a Stop Work Order is in effect.

1.4 DEFINITIONS RELATIVE TO ASBESTOS ABATEMENT

1.4.1 Accredited or Accreditation (when referring to a person or laboratory): A person or laboratory accredited in accordance with section 206 of Title II of the Toxic Substances Control Act (TSCA).

1.4.2 Adequately Wet: means to sufficiently mix or penetrate with liquid to prevent the release

of particulates. If visible emissions are observed coming from the asbestos-containing material (ACM), then that material has not been adequately wetted. The absence of visible emissions is not sufficient evidence of being adequately wetted.

1.4.3 Air Monitoring: The process of measuring the fiber concentration of a specific volume of

air.

1.4.4 Amended Water: Water to which a surfactant has been added to increase the ability of the liquid to penetrate ACM.

Page 27: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 3 Definitions and Standards

1.4.5 Approved Training Course: means an asbestos hazard abatement specialist training course, an asbestos hazard evaluation specialist training course, an asbestos abatement worker training course, an asbestos hazard abatement project designer training course, an asbestos hazard abatement air-monitoring technician training course, or any renewal training course meeting the requirements of Chapter 3710 of the Ohio Revised Code and approved by the director pursuant to rule 3701-34-07 of the Ohio Administrative Code.

1.4.6 Asbestos: The asbestiform varieties of chrysotile (serpentine), amosite (cummingtonite-

grunerite), crocidolite (riebeckite), tremolite, anthophyllite, actinolite, and any of these minerals that has been chemically treated and/or altered.

1.4.7 Asbestos-Containing Material (ACM): Any material containing more than one percent

asbestos.

1.4.8 Asbestos-Containing Waste Material: Any waste that contains asbestos. This term includes filters or other materials contaminated with asbestos. This term also includes regulated asbestos-containing material waste and material contaminated with asbestos including disposable equipment and clothing.

1.4.9 Asbestos Debris: Pieces of asbestos-containing material that can be identified by color,

texture, or composition, or dust if the dust is determined by an accredited inspector to be ACM.

1.4.10 Asbestos Hazard Abatement Activity: means any activity involving the removal,

renovation, enclosure, repair, or encapsulation of reasonably related friable asbestos-containing materials in an amount greater than 50 linear feet or 50 square feet. Asbestos hazard abatement activity also includes any such activity involving such asbestos-containing materials in an amount of 50 linear of 50 square feet or less if, when combined with any other reasonably related activity in terms of time and location of the activity, the total amount is in an amount greater than 50 linear of 50 square feet.

1.4.11 Asbestos Hazard Abatement Air-Monitoring Technician: means the person who is

responsible for environmental monitoring or work area clearance air sampling, including air monitoring performed to determine completion of response actions under the rules set forth in 40 CFR 763 Subpart E, adopted by the United State Environmental Protection Agency (EPA) pursuant to the “Asbestos Hazard Emergency Response Act of 1986”. An industrial hygienist or industrial hygienist in training certified by the American Board of Industrial Hygiene is exempt from certification as an asbestos hazard abatement air-monitoring technician.

1.4.12 Asbestos Hazard Abatement Contractor: means a business entity or public entity that

engages in or intends to engage in asbestos hazard abatement activities and that employs or supervises one or more asbestos hazard abatement specialists for asbestos hazard abatement activities. Asbestos hazard abatement contractor does not mean an employee of an asbestos hazard abatement contractor, a general contractor who subcontracts to an asbestos hazard abatement contractor an asbestos hazard abatement activity, or any individual who engages in asbestos hazard abatement activity in their own home. Asbestos hazard abatement contractor shall not mean a business entity which engages in asbestos hazard abatement activities solely at its own place of business provided that the business entity is required to and does comply with all applicable standards of the United State Environmental Protection Agency (EPA) and the United State Occupational Safety and Health Administration (OSHA).

Page 28: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 4 Definitions and Standards

1.4.13 Asbestos Hazard Abatement Project: means one or more asbestos hazard abatement activities that are conducted by one asbestos hazard abatement contractor and that are reasonably related to each other.

1.4.14 Asbestos Hazard Abatement Project Design: means the person responsible for the

determination of work scope, work sequence, or performance standards for an asbestos hazard abatement activity, including preparation of asbestos abatement project designs, plans, and contract documents.

1.4.15 Asbestos Hazard Abatement Specialist: means a person with responsibility for the

oversight or supervision of asbestos hazard abatement activities including asbestos hazard abatement project managers, hazard abatement project supervisors and foremen, and employees of school districts or other governmental or public entities who coordinate or directly supervise or oversee asbestos hazard abatement activities performed by school district, governmental, or other public employees in school district, governmental, or other public building.

1.4.16 Asbestos Hazard Abatement Worker: means the person responsible in a nonsupervisory

capacity for the performance of an asbestos hazard abatement activity.

1.4.17 Asbestos Hazard Evaluation Specialist: means a person responsible for the identification, detection, and assessment of asbestos-containing materials, the determination of appropriate response actions, or the preparation of asbestos management plans for the purpose of protecting the public health from the hazards associated with exposure to asbestos, including the performance of air and bulk sampling. This category of specialists includes management planners, health professionals, industrial hygienists, private consultants, or other individuals involved in asbestos risk identification or assessment of regulatory activities.

1.4.18 Authorized Visitor: The Owner, the Owner's Representative, testing lab personnel, the

Architect/Engineer, emergency personnel or a representative of any federal, state and local regulatory or other agency having authority over the project.

1.4.19 Breathing Zone: A hemisphere forward of the shoulders with a radius of approximately 6

to 9 inches.

1.4.20 Business Entity: means a partnership, firm, association, corporation, sole proprietorship, or other business concern.

1.4.21 Certified Industrial Hygienist (CIH): An industrial hygienist certified in Comprehensive

Practice by the American Board of Industrial Hygiene.

1.4.22 Class I Asbestos Work: Activities involving the removal of asbestos-containing thermal system insulation and surfacing materials.

1.4.23 Class II Asbestos Work: Activities involving the removal of asbestos-containing materials

which are not thermal system insulation or surfacing materials. This include, but are not limited to, the removal of asbestos-containing wallboard, floor tile and sheeting, roofing and siding shingles, and construction mastics.

1.4.24 Clearance Air Sampling: means air-sampling performed after the completion of any

asbestos hazard abatement activity and prior to the reoccupation of the contained work area by the public and conducted for the purpose of protecting the public from the health hazards associated with exposure to friable asbestos-containing material.

Page 29: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 5 Definitions and Standards

1.4.25 Competent Person: One who meets the definition in 29 CFR 1926.32(f) and is capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the authority to take prompt corrective measures to eliminate them, and is specially trained in a training course which meets the criteria of the United States Environmental Protection Agency’s Model Accreditation Plan for project designer or supervisor.

1.4.26 Contained Work Area: means designated rooms, spaces, or other areas where asbestos

hazard abatement activities are being performed, including decontamination structure. The contained work area is separated from the uncontaminated environmental by polyethylene sheeting or other materials used in conjunction with existing floors, ceiling, and walls of the structure.

1.4.27 Critical Barriers: One or more layers of plastic sealed over all openings into a work area

or any other similarly placed physical barrier sufficient to prevent airborne asbestos in a work area from migrating to an adjacent area.

1.4.28 Decontamination Area: An enclosed area adjacent and connected to the regulated area

and consisting of an equipment room, shower area, and clean room, which is used for decontamination of workers, materials and equipment that are contaminated with asbestos.

1.4.29 Disposal Bag: A 6 mil thick leak-tight plastic bag, properly marked with the OSHA

Asbestos DANGER legend, used for transporting asbestos waste from work and to disposal site.

1.4.30 Encapsulant: A material that surrounds or embeds asbestos fibers in an adhesive matrix,

to prevent release of fibers.

1.4.31 Encapsulation: Treatment of asbestos-containing materials, with an encapsulant.

1.4.32 Enclosure: The construction of an air-tight, impermeable, permanent barrier around asbestos-containing material to control the release of asbestos fibers into the air.

1.4.33 Filter: A media component used in respirators to remove solid or liquid particles from the

inspired air.

1.4.34 Friable Asbestos: any asbestos-containing material that, when dry, can be crumbled, pulverized, or reduced to powder by hand pressure.

1.4.35 Glovebag: An impervious plastic bag-like enclosure affixed around the asbestos-

containing material with glove-like appendages through which materials and tools may be handled.

1.4.36 Grinding: to reduce to powder or small fragments and includes manual or mechanical

chipping or drilling

1.4.37 HEPA Vacuum: A high efficiency particulate air (HEPA) filtered vacuum collection equipment with a filter system capable of collecting and retaining asbestos fibers. Filters should be of 99.97% efficiency for retaining fibers of 0.3 microns or larger.

1.4.38 HEPA Filter: refers to a high efficiency particulate air (HEPA) filtering system capable of

trapping and retaining 99.97 percent of all monodispersed particles 0.3 um in diameter or larger.

Page 30: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 6 Definitions and Standards

1.4.39 Intact: means that the asbestos-containing material has not crumbled, been pulverized, or other deteriorated so that the asbestos is no longer likely to be bound within its matrix

1.4.40 Leak-Tight: means that the solids or liquids cannot escape or spill out. It also means

dust-tight.

1.4.41 Negative Initial Exposure Assessment: A demonstration by the contractor which complies with the criteria specified in 29 CFR 1926.1101 that employee exposure during an operation is expected to be consistently below the permissible exposure limit (PEL).

1.4.42 Negative Pressure Enclosure (NPE): A pressure differential and ventilation system,

consisting of a local exhaust system, utilizing HEPA filtration capable of maintaining a pressure differential with the inside of the Work Area at a lower pressure than any adjacent area, and which cleans recirculated air or generates a constant air flow from adjacent areas into the Work Area.

1.4.43 Negative Pressure Respirator: A respirator in which the air pressure inside the

respiratory-inlet covering is positive during exhalation in relation to the air pressure of the outside atmosphere and negative during inhalation in relation to the air pressure of the outside atmosphere.

1.4.44 Nonfriable Material: means any material that, when dry, cannot be crumbled, pulverized,

or reduced to powder by hand pressure and has not been rendered friable.

1.4.45 Oversight: means to directly observe an asbestos abatement project for the purpose of determining compliance with contractual, performance or regulatory standards affecting the safety of the asbestos abatement activity.

1.4.46 Personal Monitoring: Sampling of the asbestos fiber concentrations within the breathing

zone of an employee.

1.4.47 Permissible Exposure Limits (PEL): Not in excess of 0.1 f/cc airborne asbestos fiber concentration as a 8-hour time weighted average (TWA) or 1.0 f/cc over a sampling period of 30 minutes as measured by NIOSH method 7400.

1.4.48 Protection Factor: The ratio of the ambient concentration of an airborne substance to the

concentration of the substance inside the respirator at the breathing zone of the wearer. The protection factor is a measure of the degree of protection provided by a respirator to the wearer.

1.4.49 Removal: means the stripping of friable asbestos containing materials from a building

component or the taking out of any friable asbestos-containing material from any facility.

1.4.50 Repair: Returning damaged asbestos-containing materials to an undamaged condition or to an intact state so as to prevent fiber release.

1.4.51 Regulated Work Area: An area established to demarcate areas where OSHA Class I, II,

and III asbestos work is conducted, and any adjoining area where debris and waste from such asbestos work accumulate; and a work area within which airborne concentrations of asbestos exceed or there is a reasonable possibility they may exceed the permissible exposure limit.

1.4.52 Respirator: A device designed to protect the wearer from the inhalation of harmful

atmospheres.

Page 31: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 7 Definitions and Standards

1.4.53 Surfacing Material: A material that is sprayed, troweled-on or otherwise applied to surfaces (such as acoustical plaster and fireproofing)

1.4.54 Surfactant: A chemical wetting agent added to water to improve penetration, thus

reducing the quantity of water required for a given operation or area.

1.4.55 Thermal System Insulation (TSI): asbestos-containing insulation applied to pipes, fittings, boilers, breeching, tanks, ducts or other structural components to prevent heat loss or gain.

1.4.56 Time Weighted Average (TWA): The average concentration of a contaminant in air

during a specific time period as determined by the method prescribed in Appendix A of 29 CFR 1926.1101.

1.4.57 Visible Emissions: Any emissions containing particulate asbestos material that are

visually detectable without the aid of instruments. This does not include condensed uncombined water vapor.

1.4.58 Wet Cleaning: The process of eliminating asbestos contamination from building surfaces

and objects by using cloths, mops, or other cleaning utensils which have been dampened with amended water or diluted removal encapsulant and afterwards thoroughly decontaminated or disposed of as asbestos-contaminated waste.

1.4.59 Work Area: The area where asbestos-related work or removal operations are performed

which is defined and/or isolated to prevent the spread of asbestos dust, fibers or debris, and entry by unauthorized personnel. Work area is a Regulated Area as defined by 29 CFR 1926.

1.4.60 Working Day: Monday through Friday and includes holidays that fall on any of the days

Monday through Friday as indicated in the notification requirements. 1.5 PROJECY MANUAL FORMAT AND CONTENT EXPLANATION

1.5.1 This article is provided to help the user of this Asbestos Abatement Project Design understand the format, language, implied requirements, and similar conventions. None of the explanations shall be interpreted to modify the substance of Contract requirements.

1.5.2 Project Manual Format: This Asbestos Abatement Project Design is organized into

Divisions, Sections or Trade Headings based on the Construction Specifications Institute's 16-Division format and the MASTERFORMAT numbering system. This organization conforms generally to recognized construction industry practice.

1.5.3 Project Manual Content: This Asbestos Abatement Project Design has been produced

employing conventions in the use of language and the intended meaning of certain terms, words, and phrases when used in particular situations or circumstances. These conventions are explained as follows:

A. Abbreviated Language: Language used in the Asbestos Abatement Project Design is

the abbreviated type. Implied words and meanings will be appropriately interpreted. Singular words will be interpreted as plural and plural words interpreted as singular where applicable and where the full context of the Contract Documents so indicates.

B. Streamlined Language: Imperative language is used generally in the Asbestos

Abatement Project Design. Requirements expressed imperatively are to be performed by the Contractor. At certain locations in the text, for clarity, subjective language is

Page 32: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 8 Definitions and Standards

used to describe responsibilities which must be fulfilled indirectly by the Contractor, or by others when so noted.

1.5.4 Assignment of Specialists: The Asbestos Abatement Project Design requires that certain

specific construction activities shall be performed by specialists who are recognized experts in the operations to be performed. The specialists must be engaged for those activities, and the assignments are requirements over which the Contractor has no choice or option. Nevertheless, the ultimate responsibility for fulfilling Contract requirements remains with the Contractor.

A. This requirement should not be interpreted to conflict with enforcement of building

codes or regulations governing the work. It is also not intended to interfere with local trade union jurisdictional settlements and similar conventions.

B. Trades: Use of titles such as "carpentry" is not intended to imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespersons of the corresponding generic name.

1.6 INDUSTRY STANDARDS

1.6.1 Applicability of Standards: Except where Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into Contract Documents. Such standards are made a part of the Contract Documents by reference.

A. Referenced industry standards take precedence over standards that are not referenced

but recognized in the construction industry as applicable.

B. Unreferenced industry standards are not directly applicable to the work, except as a general requirement of whether the work complies with recognized construction industry standards.

1.6.2 Publication Dates: Where compliance with an industry standard is required, comply with

standard in effect as of date of execution of the work.

A. Updated Standards: At the request of the Owner's Representative, Contractor may submit a Change Order proposal where applicable code or standard has been revised and reissued after the date of the Contract Documents and before performance of Work affected. The Owner's Representative will decide whether to issue a Change Order to proceed with the updated standard.

1.6.3 Conflicting Requirements: Where compliance with two or more standards is specified,

and they establish different or conflicting requirements for minimum quantities or quality levels, the most stringent requirement will be enforced, unless the Contract Documents indicate otherwise. Refer requirements that are different, but apparently equal, and uncertainties as to which quality level is more stringent to the Owner's Representative for a decision before proceeding.

A. Minimum Quantities or Quality Levels: In every instance the quantity or quality level

shown or specified shall be the minimum to be provided or performed. The actual installation may comply exactly, within specified tolerances, with the minimum quantity or quality specified, or it may exceed that minimum within reasonable limits. In complying with these requirements, indicated numeric values are minimum or maximum values, as noted, as appropriate for the context of the requirements. Refer

Page 33: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 9 Definitions and Standards

instances of uncertainty to the Owner's Representative for decision before proceeding.

1.6.4 Copies of Standards: Each entity engaged in construction on the Project is required to

be familiar with industry standards applicable to that entities' construction activity. Copies of applicable standards are not bound with the Contract Documents.

A. Where copies of standards are needed for performance of a required construction

activity, the Contractor shall obtain copies directly from the publication source.

B. Although copies of standards needed for enforcement of requirements may be part of required submittals, the Owner's Representative reserves the right to require the Contractor to submit additional copies as necessary for enforcement of requirements.

1.6.5 Standard: which apply to asbestos abatement work or hauling and disposal of asbestos

waste materials include, but are not limited, to the following:

A. American National Standards Institute (ANSI) 1430 Broadway New York, NY 10018 a. Fundamental Governing the Design and Operation of Local Exhaust Systems

Publication Z9.2 b. Practices for Respiratory Protection Publication Z88.2

B. American Society for Testing and Materials (ASTM)

100 Bar Harbor Drive West Conshocken, PA 19428 a. Safety and Health Requirements Relating to Occupational Exposure to Asbestos

E849 b. ASTM Standard Practice for Encapsulants for Spray-or-Trowel Applied Friable

Asbestos-Containing Building Materials E1494 c. ASTM Standard Practice for Visual Inspection of Asbestos Abatement Project

E1368

1.6.6 Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. Where acronyms or abbreviations are used in the Asbestos Abatement Project Manual or other Contract Documents they mean the recognized name of the trade association, standards generating organization, authority having jurisdiction or other entity applicable to the context of the text provision. Refer to the "Encyclopedia of Associations," published by Gale Research Co., available in most libraries. The following acronyms or abbreviations, as reference in the Contract Documents, are defined to mean the associated name.

1.6.7 Trade Union Jurisdictions: The Contractor shall maintain, and require subcontractors to

maintain, complete current information on jurisdictional matters, regulations and pending actions, as applicable to construction activities. The manner in which Contract Documents have been organized and subdivided is not intended to be indicative of trade union or jurisdictional agreements. A. Discuss new developments at project meetings at the earliest feasible dates. Record

relevant information and actions agreed upon.

Page 34: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01091 01091 - 10 Definitions and Standards

B. Assign and subcontract construction activities, and employ tradesmen and laborers in a manner that will not unduly risk jurisdictional disputes that could result in conflicts, delays, claims and losses.

1.7 SUBMITTALS REQUIRED BY STANDARDS

1.7.1 Permits, Licenses and Certificates: For the Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, and similar documents, correspondence and records established in conjunction with compliance with standards and regulations bearing upon performance of the work.

PART 2 – PRODUCTS (NOT APPLICABLE) PART 3 – EXECUTION (NOT APPLICABLE) END OF SECTION 01091

Page 35: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01092 01092 - 1 Codes, Regulations, and Standards

SECTION 01092 – CODES, REGULATIONS, AND STANDARDS PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to this section.

1.2 SUMMARY

1.2.1 This section sets forth governmental regulations and industry standards which are included and incorporated herein by reference and made a part of the Asbestos Abatement Project Design. This section also sets forth those notices and permits which are known to the Owner and which either must be applied for and received, or which must be given to governmental agencies before start of work.

A. Requirements include adherence to work practices and procedures set forth in

applicable codes, regulations and standards.

B. Requirements include obtaining permits, licenses, inspections, releases and similar documentation, as well as payments, statements and similar requirements associated with codes, regulations, and standards.

1.3 CODES AND REGULATIONS

1.3.1 General Applicability of Codes and Regulations, and Standards: Except to the extent that more explicit or more stringent requirements are written directly into the contract documents, all applicable codes, regulations, and standards have the same force and effect (and are made a part of the contract documents by reference) as if copied directly into the contract documents, or as if published copies are bound herewith.

1.3.2 Contractor Responsibility: The Contractor shall assume full responsibility and liability for

the compliance with all applicable Federal, State, and local regulations pertaining to work practices, hauling, disposal, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site. The Contractor is responsible for providing medical examinations and maintaining medical records of personnel as required by the applicable Federal, State, and local regulations. The Contractor shall hold the Owner and Owner's Representative harmless for failure to comply with any applicable work, hauling, disposal, safety, health or other regulation on the part of himself, his employees, or his subcontractors.

1.3.3 Federal Requirements: Which govern asbestos abatement work or hauling and disposal

of asbestos waste materials include but are not limited to the following:

A. OSHA: U.S. Department of Labor, Occupational Safety and Health Administration, (OSHA) including but not limited to:

a. Asbestos

29 CFR 1910.1001 29 CFR 1926.1101

b. Respiratory Protection

29 CFR 1910.134 29 CFR 1926.103

Page 36: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01092 01092 - 2 Codes, Regulations, and Standards

c. Personal Protective Equipment for General Industry 29 CFR 1910.132 29 CFR 1926.95-107

d. Access to Employee Exposure and Medical Records 29 CFR 1926.33

e. Hazard Communication 29 CFR 1926.33

f. Specifications for Accident Prevention Signs and Tags 29 CFR 1910.145

g. Permit Required Confined Space 29 CFR 1910.146

h. Construction Industry 20 CFR 1910.1001 20 CFR 1926.1101

i. Construction Industry – General Duty Standards 29 FR 1926.20-35

B. DOT: United State Department of Transportation (DOT) including, but not limited to:

a. Hazardous Substances 49 CFR 171 and 172

b. Hazardous Material Regulations – General Awareness and Training Requirements for Handlers, Loaders and Drivers 49 CFR 171-180

c. Hazardous Material Regulations – Editorial and Technical Revisions 49 FR 171-180

C. EPA: United States Environmental Protection Agency (EPA) including, but not limited

to:

a. Asbestos Abatement Projects; Worker Protection Rule 40 CFR 763, Sup-part G

b. Asbestos Hazard Emergency Response Act (AHERA) Regulation 40 CFR 763, Sub-part E

c. EPA Model Accreditation Plan – Asbestos Containing Materials Final Rule and Notice 40 CFR 763, Sub-part E, Appendix C

d. National Emission Standard for Hazardous Air Pollutants (NESHAP) Nation Emission Standard for Asbestos 40 CFR 61, Sub-parts A and M

1.3.4 State Requirements: Which govern asbestos abatement work or hauling and disposal of asbestos waste materials include but are not limited to the following:

Page 37: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01092 01092 - 3 Codes, Regulations, and Standards

A. ODH: Ohio Department of Health (ODH) including, but not limited to:

a. Ohio Administrative Code, Final Rule 3701-34

B. OEPA: Ohio Environmental Protection Agency (OEPA) including, but not limited to:

a. Ohio Administrative Code, Final Rule 3745-20

1.3.5 Local Requirements: Abide by all local requirements which govern asbestos abatement work or hauling and disposal of asbestos waste materials.

1.4 STANDARDS

1.4.1 General Applicability of Standards: Except to the extent that more explicit or more stringent requirements are written directly into the Contract Documents, all applicable standards have the same force and effect (and are made a part of the Contract Documents by reference) as if copied directly into the Contract Documents, or as if published copies are bound herewith.

1.4.2 Contractor Responsibility: The Contractor shall assume full responsibility and liability for

the compliance with all standards pertaining to work practices, hauling, disposal, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site. The Contractor shall hold the Owner and Owner's Representative harmless for failure to comply with any applicable standard on the part of himself, his employees, or his subcontractors.

1.4.3 Standards: Which apply to asbestos abatement work or hauling and disposal of asbestos

waste materials include but are not limited to the following:

A. American National Standards Institute (ANSI) 1430 Broadway New York, NY 10018

a. Fundamentals Governing the Design and Operation of Local Exhaust Systems,

Publication Z9.2-79

b. Practices for Respiratory Protection, Publication Z88.2-80

B. American Society for Testing and Materials (ASTM) 1916 Race Street Philadelphia, PA 19103 a. Safety and Health Requirements Relating to Occupational Exposure to Asbestos,

E 849-82

b. Standard Practice for Visual Inspection of Asbestos Abatement Projects, E 1368-90

c. Specification for Encapsulants for Friable Asbestos Containing Building

Materials, Proposal P-189 1.5 EPA GUIDANCE DOCUMENTS

Page 38: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01092 01092 - 4 Codes, Regulations, and Standards

1.5.1 EPA Guidance Documents: Discuss asbestos abatement work or hauling and disposal of asbestos waste materials listed below for the Contractor's information only. These documents do not describe the work and are not a part of the work of this contract.

A. Guidance for Controlling Asbestos-Containing Materials in Buildings (Purple Book)

EPA 560/5-85-024

B. Evaluation of the EPA Asbestos-in-Schools Identification and Notification Rule. EPA 560/5-84-005.

C. Asbestos in Buildings: Guidance for Service and Maintenance Personnel. EPA

560/5-85-018.

D. Asbestos Waste Management Guidance. EPA 530-SW-85-007.

E. Managing Asbestos In Place. A Building Owner's Guide to Operations and Maintenance Programs for Asbestos-Containing Materials. EPA 2OT-2003

F. A Guide to Respiratory Protection for the Asbestos Abatement Industry. EPA-560-

OPTS-86-001 1.6 NOTICES

1.6.1 United States Environmental Protection Agency

A. Postmark or deliver notification as required by US EPA National Emission Standards for Hazardous Air Pollutants (NESHAP) Asbestos Regulations (40 CFR 61, Subpart M) to the regional Asbestos NESHAP Contact at least 10 days prior to beginning any work on asbestos-containing materials. Send notification to the following address:

Demo/Reno Notifications US EPA Region 5 Office 77 West Jackson Boulevard Chicago, Illinois 60604

1.6.2 Ohio Environmental Protection Agency

A. Submit written notification in accordance with 40 CFR Part 61 to Ohio Environmental

Protection Agency (OEPA), who are also the Local Air Authority. Cleveland Department of Public Health Division of Air Quality Penton Media Building Fourth Floor 1300 East 9th Street Cleveland, Ohio 44114

B. A copy of the OEPA notification form can be found in the Appendices.

1.6.3 Ohio Department of Health

A. Submit written notification and fee in accordance with Ohio Revised Code 3710 to the

Ohio Department of Health (ODH). Ohio Department of Health 246 North High Street

Page 39: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01092 01092 - 5 Codes, Regulations, and Standards

PO Box 118 Columbus, Ohio 43266-0118

B. A copy of the ODH notification can be found in the Appendices.

1.7 PERMITS

1.7.1 All asbestos-containing waste is to be transported by an entity maintaining a current “Industrial waste hauler permit” specifically for asbestos-containing materials, as required for transporting of asbestos-containing waste to an approved disposal site.

1.7.2 Contractor is responsible for obtaining any demolition, building, renovation or other

permits, and for paying application fees, if any, where required by State or Local jurisdictions.

1.8 LICNESES

1.8.1 Maintain current licenses as required by applicable State or Local jurisdictions for the removal, transporting, disposal or other regulated activity relative to the work of the Contract.

1.9 POSTING AND FILING OF REGULATIONS

1.9.1 Post all notices required by applicable federal, state and local regulations. Maintain at least once copy of applicable federal, state and local regulations and standards at Project Site and on file in Contractor’s office.

1.10 SUBMITTALS RELATED TO REGULATORY REQUIREMENTS

1.10.1 Before Start of Work: Submit the following to the Consultant for review. No work shall begin until these submittals are returned with Consultant’s approval indicating that the submittal is returned for unrestricted use or final-but-restricted use.

A. Permits, Licenses, and Certificates: For the Owner's records, submit copies of

permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, and similar documents, correspondence and records established in conjunction with compliance with standards and regulations bearing upon performance of the Work including:

B. Notices: Submit notices required by federal, state and local regulations together with proof of timely transmittal to agency requiring the notice.

C. Permits: Submit copies of current valid permits required by state and local

regulations.

D. Licenses: Submit copies of all State and local licenses and permits necessary to carry out the work of this contract.

PART 2 – PRODUCTS (NOT APPLICABLE) PART 3 – EXECUTION (NOT APPLICABLE) END OF SECTION 01092

Page 40: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01220 01220 - 1 Project Meetings

SECTION 01220 – PROJECT MEETINGS PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of the Contract and other Asbestos Abatement Project Design Sections apply to work of this Section.

1.2 DESCRIPTION

1.2.1 This section describes procedures for scheduling and administration of project progress meetings, including the preconstruction conference.

1.3 RELATED SECTIONS

1.3.1 Agreement between the Owner and Contractor Section 01043 - Project Coordination Section 01301 - Submittals 1.4 PRECONSTRUCTION CONFERENCE

1.4.1 The Preconstruction Conference covers assignment of responsibilities and personnel, location of contained work areas and temporary facilities for electric and water services.

1.4.2 The Preconstruction Conference will be held at a time and place selected by the Owner

or Owner's Representative prior to commencing project work.

1.4.3 At minimum the following personnel shall attend: A. Contractor and Contractor's superintendent and assistants

B. Owner's Representative

C. Construction Manager

D. Environmental Consultant

E. Other personnel as indicated by the Owner

1.4.4 Pre-work submittals are to be presented at the Preconstruction Conference. No work shall commence prior to approval of required pre-work submittals.

1.4.5 The Contractor shall present for approval the Contractor's Schedule and Building

Coordination Plan.

1.4.6 The Preconstruction Conference will be chaired by the Construction Manager or other owner designee.

1.5 PROGRESS MEETINGS

1.5.1 The Contractor shall attend progress meetings and other called meetings throughout the duration of the project.

Page 41: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01220 01220 - 2 Project Meetings

1.5.2 The Contractor shall provide and present materials as required for each progress meeting as delineated herein.

1.5.3 Progress meetings shall be held at the time and place as delineated by the Construction

Manager.

1.5.4 The following personnel shall attend the weekly progress meetings:

A. Contractor and Contractor's superintendent and assistants

B. Owner's Representative

C. Construction Manager

D. Environmental Consultant

E. Other personnel as indicated by the Owner

1.5.5 Agenda shall consist of the review of the following at minimum:

A. Minutes of previous meeting

B. Work progress, field observations of operations, problems, etc.

C. Identified problems which will delay project schedule or adversely affect coordination with other parts of the project

D. Methods employed to comply with project schedule

E. Submittal schedule and status of submittals and resubmittals

F. Means of expediting work to comply with project schedule

G. Revised schedule for next work period, if necessary

H. Coordination of scheduled work progress

I. Issues related to quality of work

J. Proposed changes in work and their effect on schedule and coordination

K. Unsettled Contractor claims

L. Unresolved items and discussion of means of settling them; adoption of such means if

possible

M. Other items of discussion as approved by the Owner or Owner's Representative

1.5.6 Weekly progress meetings will be chaired by the Construction Manager or other owner designee.

PART 2 – PRODUCTS (NOT APPLICABLE) PART 3 – EXECUTION (NOT APPLICABLE)

Page 42: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01220 01220 - 3 Project Meetings

END OF SECTION 01220

Page 43: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01301 01301 - 1 Submittals

SECTION 01301 – SUBMITTALS PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of the Contract and other Asbestos Abatement Project Design sections apply to this Section.

1.2 SUMMARY

1.2.1 This Section specifies administrative and procedural requirements for submittals required for performance of the Work.

1.3 SUBMITTAL PROCEDURES

1.3.1 Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.

A. Coordinate transmittal of different types of submittals for related elements of the Work

so processing will not be delayed by the need to review submittals concurrently for coordination.

B. The Construction Manager reserves the right to withhold action on a submittal requiring coordination with other submittals until all related submittals are received.

1.3.2 Processing: Allow sufficient review time so that installation will not be delayed as a

result of the time required to process submittals, including time for resubmittals.

A. Allow two weeks for initial review. Allow additional time if the Construction Manager must delay processing to permit coordination with subsequent submittals.

B. No extension of Contract Time will be authorized because of failure to transmit submittals to the Construction Manager sufficiently in advance of the work to permit processing.

1.3.3 Submittal Preparation: Place a permanent label or title block on each submittal for

identification. Indicate the name of the entity that prepared each submittal on the label or title block.

1.3.4 Submittal Transmittal: Package each submittal appropriately for transmittal and handling.

Transmit each submittal from the Contractor to the Construction Manager using a transmittal form. Provide a copy of the submittal package to the Consultant. The Construction Manager will not accept submittal received from sources other than the Contractor.

A. On the transmittal, record relevant information and requests for data. On the form, or

separate sheet, record deviations from Contract Document requirements, including variations and limitations. Include Contractor’s certification that information complies with Contract Document requirements.

1.4 CONTRACTOR'S CONSTRUCTION SCHEDULE

Page 44: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01301 01301 - 2 Submittals

1.4.1 Bar-Chart Schedule: Prepare a fully developed, horizontal bar-chart type Contractor's construction schedule. Submit within ten days of the date established for "Commencement of the Work."

A. Provide a separate time bar for each significant construction activity. Provide a

continuous vertical line to identify the first working day of each week. Use the same breakdown of units of the work as indicated in the "Schedule of Values."

B. Within each time bar indicate estimated completion percentage in 10 percent increments. As work progresses, place a contrasting mark in each bar to indicate Actual Completion.

C. Prepare the schedule on a sheet, or series of sheets, of stable transparency, or other

reproducible media, of sufficient width to show data for the entire construction period.

D. Secure time commitments for performing critical elements of the work from parties involved. Coordinate each element on the schedule with other construction activities; include minor elements involved in the sequence of the work. Show each activity in proper sequence. Indicate graphically sequences necessary for completion of related portions of the work.

E. Coordinate the Contractor's construction schedule with the schedule of values, list of

subcontracts, submittal schedule, progress reports, payment requests and other schedules.

F. Indicate Clearance of each Work Area in advance of the dates established for

Clearance. Allow time for testing and other procedures necessary for certification of Clearance.

G. Indicate completion in advance of the date established for Substantial Completion.

Indicate Substantial Completion on the schedule to allow time for the procedures necessary for certification of Substantial Completion.

1.4.2 Phasing: Provide notations on the schedule to show how the sequence of the work is affected by requirements for phased completion to permit work by separate Contractors and partial occupancy by the Owner prior to Substantial Completion.

1.4.3 Work Stages: Indicate important stages of construction for each major portion of the

work, including testing and installation. Include indication of start and finish times for the following:

A. Non-asbestos demolitions

B. Preparation of the Work Area

C. Asbestos removal

D. Clearance testing

E. Substantial Completion

1.4.4 Area Separations: Provide a separate time bar to identify each Work Area or major

construction area for each major portion of the work. Indicate where each element in an area must be sequenced or integrated with other activities.

Page 45: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01301 01301 - 3 Submittals

1.4.5 Distribution: Following response to the initial submittal, print and distribute copies to the Owner's Representative, Owner, Construction Manager, Consultant, subcontractors, and other parties required to comply with scheduled dates. Post copies in the Construction Manager’s field office, project meeting room and temporary field office.

1.4.6 When revisions are made, distribute to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.

1.4.7 Schedule Updating: Revise the schedule after each meeting or activity, where revisions have been recognized or made. Issue the updated schedule concurrently with report of each meeting.

1.5 SUBMITTAL SCHEDULE

1.5.1 Listing: At the end of this section is a listing of the principal submittals required for the work. This listing is not necessarily complete, nor does the listing reflect the significance of each submittal requirement. The listing is included only for the convenience of users of the Contract Documents.

1.5.2 Distribution: Following response to initial submittal, print and distribute copies to the

Consultant, subcontractors, and other parties required to comply with submittal dates indicated. Post copies in the project meeting room and field office.

1.5.3 Revisions: When revisions are made, distribute to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the work and are no longer involved in construction activities.

1.5.4 Schedule Updating: Revise the schedule after each meeting or activity, where revisions

have been recognized or made. Issue the updated schedule concurrently with report of each meeting.

1.6 PRODUCT DATA

1.6.1 Collect Product Data into a single submittal. Product Data includes printed information such as manufacturer's installation instructions, catalog cuts, standard wiring diagrams and performance curves. Where Product Data must be specially prepared because standard printed data is not suitable for use, submit as "Shop Drawings."

1.6.2 Mark each copy to show applicable choices and options. Where printed Product Data

includes information on several products, some of which are not required, mark copies to indicate the applicable information. Include the following information:

A. Manufacturer's printed recommendations.

B. Compliance with recognized trade association standards.

C. Compliance with recognized testing agency standards.

D. Application of testing agency labels and seals.

E. Notation of dimensions verified by field measurement.

F. Notation of coordination requirements.

Page 46: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01301 01301 - 4 Submittals

1.6.3 Submittals: Submit 3 copies of each required submittal. The Construction Manager will retain two, and will return one marked with action taken and corrections or modifications if required.

1.6.4 Unless noncompliance with Contract Document provisions is observed, the submittal may

serve as the final submittal. 1.7 MISCELLANEOUS SUBMITTALS

1.7.1 Material Safety Data Sheets: Process material safety and data sheets as "product data."

1.7.2 Closeout Submittals: Refer to section "Project Closeout" and to individual sections of this Asbestos Abatement Project Manual for specific submittal requirements of project closeout information.

1.7.3 Record Documents: Furnish set of original documents as maintained on the project site.

1.8 CONSTRUCTION MANAGER’S ACTION

1.8.1 Except for submittals for record, information or similar purposes, where action and return is required or requested, the Construction Manager will review submittals, mark to indicate action taken, and return.

1.8.2 Compliance with specified characteristics is the Contractor's responsibility.

1.8.3 Approval: The Construction Manager will mark each submittal to indicate the action taken.

A. Final Unrestricted Release: Where submittals are marked "Approved," that part of the

work covered by the submittal may proceed provided it complies with requirements of the Contract Documents; final acceptance will depend upon that compliance.

B. Final-But-Restricted Release: When submittals are marked "Approved as Noted," that part of the work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Documents; final acceptance will depend on that compliance.

C. Returned for Resubmittal: When submittal is marked "Not Approved, Revise, and

Resubmit," do not proceed with that part of the work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal in accordance with the notations; resubmit without delay. Repeat if necessary to obtain a different action mark.

a. Do not permit submittals marked "Not Approved, Revise, and Resubmit," to be

used at the Project Site, or elsewhere where work is in progress.

D. Received-Not Reviewed: When the Construction Manager marks a submittal “Received-Not Reviewed” this acknowledges that the submittal has been received. This action applies to materials that are to be submitted for information purposes only, and where no review or action by the Construction Manager is required.

E. Other Action: Where a submittal is for information or record purposes or special

processing or other activity, the Construction Manager will return the submittal marked “Action Not Required”.

Page 47: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01301 01301 - 5 Submittals

1.8.4 Unsolicited Submittals: The Construction Manager will return unsolicited submittals to the sender without action.

1.9 SUBMITTAL CHECKLIST

1.9.1 The submittals required from the Contractor include, but are not limited, to the following. Refer to each section for information regarding required submittal.

1.9.2 Before Start of Work:

A. Contractor’s Construction Schedule B. Plan of Action C. Contingency Plan D. Project Directory E. Building Occupant Notifications F. Pre-Construction Inspection G. Contractor’s Asbestos Abatement ODH license H. Resume of Asbestos Abatement Supervisor I. Asbestos Abatement Supervisor and Workers EPA accreditation J. Asbestos Abatement Supervisor and Workers ODH license K. Asbestos Abatement Supervisor and Worker Fit Tests L. Asbestos Abatement Supervisor and Worker Statement of Physician’s Opinion M. Certificate of Worker Acknowledgement N. Permits O. Licenses P. Notification Q. Respiratory Protection Plan R. Temporary Facilities Plan S. Product Data T. Pre-Abatement Inspection

1.9.3 Daily:

A. Daily Logs B. Entry/Exit Logs C. Contactor Air Monitoring Results

1.9.4 Periodic:

A. Unusual Event Report B. Accident Report C. Discovered Conditions Report D. Update to Contractor’s Construction Schedule E. Update Asbestos Abatement Worker’s Information F. Certification of Visual Inspection G. Waste Manifest and Shipment Records H. Landfill Receipts

PART 2 – PRODUCTS (NOT APPLICABLE) PART 3 – EXECUTION (NOT APPLICABLE) END OF SECTION 01301

Page 48: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01410 01410 - 1 Air Monitoring By The Owner

SECTION 01410 – AIR MONITORING BY THE OWNER PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.1.2 Work area clearance air monitoring is described in Section 01714 – Work Area

Clearance. 1.2 DESCRIPTION OF THE WORK

1.2.1 The Owner has contracted the Consultant for air monitoring services. Air monitoring may be conducted both outside and inside of the work area during abatement activities, and for clearance sampling at the end of abatement activities for each work area.

1.2.2 This section describes air monitoring carried out by the Owner to verify that the building

beyond the work area and the outside environment remains uncontaminated. This section also sets forth airborne fiber levels both inside and outside the work area as action levels, and describes the action required by the Contractor if an action level is met or exceeded.

1.2.3 Air monitoring required by OSHA is work of the Contractor and is not covered in this

section. 1.3 AIR MONITORING

1.3.1 Background; The Consultant may sample air in the anticipated Work Area to establish a baseline before the start of work.

1.3.2 Work Area Isolation; The Consultant may sample air outside the work area to detect faults in the Work Area isolation, such as:

A. Contamination of the building outside of the work area with airborne fibers

B. Failure of filtration or rupture in the differential pressure system

C. Contamination of air outside the building envelop with airborne fibers

1.3.3 Inside the Work Area; The Consultant may monitor airborne fiber counts inside the Work

Area. The purpose of this air monitoring will be to detect airborne asbestos concentrations which may challenge the ability of the Work Area isolation procedures to protect the balance of the building or outside of the building from contamination by airborne fibers.

1.3.4 Work Area Clearance: To determine if the elevated airborne fiber counts encountered during abatement operations have been reduced to an acceptable level, the Consultant will sample and analyze air per Section 01714 – Work Area Clearance.

1.3.5 Air monitoring required by OSHA is work of the Contractor and is not covered in this

section. 1.4 SCHEDULE OF AIR SAMPLES

Page 49: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01410 01410 - 2 Air Monitoring By The Owner

1.4.1 Sample Cassettes; Samples will be collected on 25 millimeter cassettes with a 50 millimeter extension cowl as follows:

A. PCM: 0.8 micrometer mixed cellulose ester

B. TEM: 0.45 micrometer mixed cellulose ester

1.4.2 Number and Volume of Samples: The number and volume of air samples given in this

schedule is approximate. The exact number and volume of samples collected by the Consultant may vary depending upon job conditions and the analytical method used.

1.4.3 The samples volumes collected by the Consultant will be determined based upon the

work conditions, location and material type on a daily basis.

A. For purposes of this asbestos abatement project design, the sample volume calculated above will be considered to be of sufficient size so that there is a 95% level of confidence that the value measured by each individual sample at the limit of detection (LOD) is less than or equal to the limit values specified below.

B. For purposes of this asbestos abatement project design, the LOD is defined as 7 fibers per cubic centimeter (f/cc) on the filter.

C. For purposes of this asbestos abatement project design, overloaded samples will be

considered as exceeding the applicable limit value. 1.5 BACKGROUND MONITORING

1.5.1 The Consultant will secure the following air samples to establish a baseline before the start of work for each work area.

Location Sampled

Approximate Number of Samples

Limit Value (f/cc)

Approximate Volume (L)

Rate (Lpm)

Inside each work area

5 0.01 2,000 1-12

Outside each work area 3

0.01 2,000 1-12

1.6 DAILY MONITORING

1.6.1 From start of work of Section 01503 – Temporary Enclosures through the work of Section 01711 – Project Decontamination, the Consultant may collect the following samples on a daily basis.

Location Sampled

Approximate Number of Samples

Limit Value (f/cc)

Approximate Volume (L)

Rate (Lpm)

Inside each work area

2 0.10 100 1-12

Outside each work area 3

0.01 1,000 1-12

Output of Negative Pressure System

1 0.01 1,000 1-12

Page 50: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01410 01410 - 3 Air Monitoring By The Owner

1.6.2 Additional samples may be collected at Consultant’s discretion. If airborne fiber counts exceed allowed limits, additional samples will be taken as necessary to monitor fiber levels.

1.7 ANALYTICAL METHODS

1.7.1 The following methods will be used by the Consultant in analyzing filters used to collect air samples. Sampling rates may be varied from printed standards to allow for high volume sampling.

A. Phase Contrast Microscopy (PCM) will be performed using the NIOSH 7400 Method.

B. Transmission Electron Microscopy (TEM) will be performed using the method set

forth in the AHERA Regulations, 40 CFR 763, Appendix A. 1.8 LABORATORY TESTING

1.8.1 Samples will either be analyzed on site at a suitable location as provided by the Owner or will be sent overnight on a daily basis so that verbal reports on air samples can be obtained within 24 hours of receipt by the laboratory.

1.8.2 The Contractor will have access to all air monitoring tests and results upon request.

1.8.3 A complete record of all air monitoring and results will be furnished to the Owner by the

Consultant.

1.8.4 Written reports of all air monitoring tests will be posted at the job site on a daily basis. 1.9 ADDITIONAL TESTING

1.9.1 The Contractor may conduct air monitoring and laboratory testing. If the Contractor elects to do this, the cost of such air monitoring and laboratory testing shall be at no additional cost to the Owner. Additionally, only the Consultant’s air monitoring results will be considered controlling in the event of a dispute.

1.10 STOP ACTION LEVELS

1.10.1 Inside Work Area: Maintain an airborne fiber count in the work area of less than the Stop Action Level given below for the type of respiratory protection in use. If the fiber counts rise above this figure for any sample collected, revise work procedures to lower fiber counts. If a fiber count for any work shirt or eight-hour period exceeds the Stop Action Level, stop all work except correction actions, leave negative pressure and air circulation system in operation and notify Owner’s Representative. After correcting cause of high fiber levels, do not recommence work for 24 hours unless otherwise authorized in writing by Owner’s Representative.

Stop Action Level (f/cc) Respirator Required OSHA Protection

Factor 0.1

Half face APR 10

0.5

Full face PAPR 50

1.0

Supplied air pressure demand 100

Page 51: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01410 01410 - 4 Air Monitoring By The Owner

1.10.2 Outside Work Area: If any air sample taken outside the work area exceeds the baseline established prior to start of work, immediately and automatically stop all work, except corrective actions. The Owner’s Representative will determine the source of the high reading and so notify the Contractor in writing.

A. If the high reading was the results of failure of work area isolation measures, initiate

the following actions: a. Immediately erect new critical barriers as set forth in Section 01526 - Temporary

Enclosures to isolate the affected area from the balance of the building. Erect Critical Barriers at the next existing structural isolation of the involved space (eg. wall, ceiling, floor).

b. Decontaminate the affected area in accordance with Section 01712 - Cleaning and Decontamination Procedures.

c. Require that respiratory protection as set forth in Section 01562 Respiratory Protection be worn in affected area until area is cleared for reoccupancy in accordance with Section 01714 - Work Area Clearance.

d. Leave Critical Barriers in place until completion of work and insure that the operation of the negative pressure system in the Work Area results in a flow of air from the balance of the building into the affected area.

e. If the exit from the clean room of the personnel decontamination unit enters the affected area, establish a decontamination facility consisting of a Shower Room and Clean Room as set forth in Section 01563 - Decontamination Units at entry point to affected area.

f. After Certification of Visual Inspection in the Work Area, remove critical barriers separating the work area from the affected area. Final air samples will be taken within the entire area as set forth in Section 01714 - Work Area Clearance.

B. If the high reading was the result of other causes, initiate corrective action as determined by the Owner's Representative.

C. TEM analysis will be used to resolve any disputes regarding fiber types when a project has been stopped due to excessive airborne fiber counts.

D. Effect on Contract Sum: Complete corrective work with no change in the Contract Sum

if high airborne fiber counts were caused by Contractor's activities; TEM charges will be borne by Contractor. The Contract Sum and schedule will be adjusted for additional work caused by high airborne fiber counts beyond the Contractor's control.

1.11 STOP WORK

1.11.1 If the Owner or the Owner’s Representative presents a written stop work order, immediately and automatically conform to that stop work order, while maintaining temporary enclosures and pressure differential.

1.11.2 After being presented with a stop work order, immediately initiate the following actions:

A. Cease all asbestos removal activities or any other activities that disturb ACM

B. Repair any fallen, ripped, or otherwise failed work areas isolation measures

C. Maintain in operation all work area isolation measures including those required by

Sections 01526 - Temporary Enclosures, 01513 - Temporary Negative Pressure and Air Circulation System, and 01563 - Decontamination Units.

Page 52: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01410 01410 - 5 Air Monitoring By The Owner

D. Maintain all worker protections including those required by Sections 01560 - Worker Protection and 01562 - Respiratory Protection.

E. Fog the air in the work area with a mist of amended water to reduce airborne fiber

levels

1.11.3 Do not recommence work until authorized in writing by the Owner or Owner’s Representative.

PART 2 – PRODUCTS (NOT APPLICABLE) PART 3 – EXECUTION 3.1 PERSONAL EXPOSURE MONITORING

3.1.1 The Owner will not be performing air monitoring to meet Contractor’s OSHA requirements for personnel sampling or any other purpose.

END OF SECTION 01410

Page 53: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 1 Temporary Facilities

SECTION 01503 – TEMPORARY FACILITIES PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of the Contract and other Asbestos Abatement Project Design Sections apply to work of this section.

1.2 SUMMARY

1.2.1 General: This section includes requirements for construction facilities and temporary controls, including temporary utilities, support facilities, and security and protection.

1.2.2 Temporary utilities include, but are not limited to, the following:

A. Water service and distribution B. Temporary electric power and lighting C. Temporary heat D. Temporary cooling E. Ventilation F. Sanitary facilities, including drinking water G. Storm and sanitary sewer

1.2.3 Support facilities include, but are not limited to, the following:

A. Field offices, storage sheds B. Temporary enclosures C. Hoists and temporary elevator use

1.2.4 Security and protection facilities include, but are not limited to, the following:

A. Temporary fire protection B. Barricades, warning signs and lights

1.3 DESCRIPTION OF REQUIREMENTS

1.3.1 General: Provide temporary connection to existing building utilities or provide temporary

facilities as required herein or as necessary to carry out the work.

1.4 SUBMITTALS

1.4.1 Before the Start of Work: Submit the following to the Construction Manager for review. Begin no work until these submittals are returned with Construction Manager’s approval indicating that the submittal is returned for unrestricted use or final-but-restricted use.

A. Hot water heater: Submit manufacturers name, model number, size in gallons, heating

capacity, power requirements B. Decontamination Unit Sub-panel: Product data C. Ground Fault Circuit Interrupters (GFCI): Product data D. Lamps and Light Fixtures: Product data E. Temporary Heating Units: Product data F. Temporary Cooling Units: Product data and installation instructions G. Self-Contained Toilet Units: Product data and name of sub-contractor to be used for

servicing self-contained toilets. Submit method to be used for servicing H. First Aid Supplies: List of contents of first aid kit. Submit in form of check list

Page 54: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 2 Temporary Facilities

I. Fire Extinguishers: Product data. Submit schedule indicating location at job site. J. Temporary Utilities: Submit reports of tests, inspections, meter readings, and similar

procedures performed on temporary utilities. K. Implementation and Termination Schedule: Within 15 days of the date established for

commencement of the work, submit a schedule indicating implementation and termination of each temporary utility.

1.5 QUALITY ASSURANCE

1.5.1 Regulations: Comply with industry standards and applicable laws and regulations of authorities having jurisdiction including, but not limited to, the following:

A. Building code requirements B. Health and safety regulations C. Utility company regulations D. Police, fire department, and rescue squad rules E. Environmental protection regulations

1.5.2 Standards: Comply with NFPA241 “Standard for Safeguarding Construction, Alterations,

and Demolition Operations”, ANSI A10 Series standards for “Safety Requirements for Construction and Demolition”, and NECA Electrical Design Library “Temporary Electrical Facilities”.

1.5.3 Electrical Service: Comply with NEMA, NECA, and UL standards and regulations for

temporary electric service. Install service in compliance with NFPA 70 “National Electric Code”.

1.5.4 Inspections: Arrange for authorities having jurisdiction to inspect and test each

temporary utility before use. Obtain required certifications and permits. 1.6 PROJECT CONDITIONS

1.6.1 Temporary Utilities: Prepare a schedule in coordination with the general contractor and Construction Manager indicating dates for implementation and termination of each temporary utility. At the earliest feasible time, when acceptable to the Owner, change over from use of temporary service to use of permanent service.

1.6.2 Conditions of Use: Keep temporary services and facilities clean and neat in appearance.

Operate in a safe and efficient manner. Relocate temporary services and facilities as the work progresses. Do not overload facilities or permit them to interfere with progress. Take necessary fire-prevention measures. Do not allow hazardous, dangerous, or unsanitary conditions, or public nuisances to develop or persist onsite.

PART 2 – PRODUCTS 2.1 MATERIALS AND EQUIPMENT

2.1.1 General: Provide new or used materials and equipment that are undamaged and in serviceable condition. Provide only materials and equipment that are recognized as being suitable for the intended use, by compliance with appropriate standards.

2.1.2 Lumber and Plywood:

A. For job-built temporary offices, shops and sheds within the construction area, provide

UL-labeled, fire-treated lumber and plywood for framing, sheathing and siding

Page 55: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 3 Temporary Facilities

B. For fences and vision barriers, provide minimum 3/8 inch (9.5 mm) thick exterior plywood.

2.2 SCAFFOLDING

2.2.1 Provide all scaffolding, ladders and/or staging, etc., as necessary to accomplish the work of this contract. Scaffolding may be of suspension type or standing type such as metal tube and coupler, tubular welded frame, pole or outrigger type or cantilever type and must be implemented by a professional scaffolding company. The type, erection and use of all scaffolding shall comply with all applicable OSHA regulations. The contractor shall be responsible for any damage which occurs as a result from improper scaffolding use.

2.2.2 Equip rungs of all metal ladders, etc., with an abrasive non-slip surface.

2.2.3 Provide a non-skid surface on all scaffold surfaces subject to foot traffic.

2.3 WATER SERVICE

2.3.1 Use of water service are specified in the Contract Documents of the Construction Manager

2.4 ELECTRICAL SERVICE

2.4.1 Use of electrical service are specified in the Contract Documents of the Construction Manager.

2.5 TEMPORARY HEAT

2.5.1 Heating Units: Temporary heating units must have been tested and labeled by UL, FM or another recognized trade association related to the fuel being consumed. Use steam or hot water radiant heat where available, and where not available use electric resistant fin radiation supplied from a branch circuit with ground fault circuit interrupter.

2.6 TEMPORARY COOLING

2.6.1 Cooling Units: Temporary cooling units must consist of a fan coil unit inside the work area with a compressor and heat rejection coil outside.

2.7 SANITARY FACILITIES

2.7.1 Use of sanitary facilities are specified in the Contract Documents of the Construction Manager.

2.8 FIRST AID

2.8.1 First Aid Supplies: Comply with governing regulations and recognized recommendations within the construction industry.

2.9 FIRE EXTINGUISHERS

2.9.1 Fire Extinguishers: Provide hand-carried, portable, UL-rated Class A fire extinguishers for temporary offices and similar spaces where there is minimal danger of electrical or grease-oil-flammable liquid fires. In other locations provide hand-carried, portable, UL-rated Class ABC dry chemical extinguishers, or a combination of several extinguishers of NFPA recommended types for the exposures in each case.

Page 56: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 4 Temporary Facilities

PART 3 – EXECUTION 3.1 INSTALLATION, GENERAL

3.1.1 General: Use qualified tradesmen for installation of temporary services and facilities. Locate temporary services and facilities where they will serve the entire project adequately and result in minimum interference with the performance of the Work.

3.1.2 Provide each facility ready for use when needed to avoid delay. Maintain and modify as

required. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.1.3 Require that tradesmen accomplishing this work be licensed as required by local

authority for the work performed.

3.1.4 Relocate, modify and extend services and facilities as required during the course of work so as to accommodate the entire work of the project.

3.2 SCAFFOLDING

3.2.1 During the erection and/or moving of scaffolding, care must be exercised so that the polyethylene floor covering is not damaged.

3.2.2 Clean as necessary debris from non-slip surfaces.

3.2.3 At the completion of abatement work clean all construction aids within the work area.

Either wrap in one layer of 6 mil (0.15 mm) polyethylene sheet and seal before removal from the Work Area or decontaminate thoroughly through the equipment decontamination unit.

3.3 TEMPORARY UTILITY INSTALLATION

3.3.1 General: Engage the appropriate local utility company to install temporary service or connect to existing service. Where company provides only part of the service, provide the remainder with matching, compatible materials and equipment. Comply with company recommendations.

A. Arrange with company and existing users for a time when service can be interrupted,

if necessary, to make connections for temporary services.

B. Provide adequate capacity at each stage of construction. Prior to temporary utility availability, provide trucked-in services.

C. Use Charges: Cost or use charges for temporary facilities are not chargeable to the

Owner. The Owner will accept cost or use charges as a basis of claims for change orders.

3.4 WATER SERVICES

3.4.1 General: Water connection (without charge) to Owner's existing potable water system is limited to one 3/4" pipe-size connection, and a maximum flow of 10 gpm each to hot and cold water supply. Install using vacuum breakers or other backflow preventer as required by local authority. Hot water shall be supplied at a minimum temperature of 100 F. Supply hot and cold water to the Decontamination Unit in accordance with Section 01563. In addition, water shall be supplied for the following uses:

Page 57: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 5 Temporary Facilities

A. Maintain hose connections and outlet valves in leak-proof condition. Where finish work below an outlet might be damaged by spillage or leakage, provide a drip pan of suitable size to minimize the possibility of water damage. Drain water promptly from pans as it accumulates.

3.5 ELECTRICAL SERVICE

3.5.1 General: Provide a weatherproof, grounded temporary electric power service and

distribution system of sufficient size, capacity, and power characteristics to accommodate performance of work during the construction period. Install temporary lighting adequate to provide sufficient illumination for safe work and traffic conditions in every area of work.

3.5.2 Lockout: Lockout all existing power to or through the work area as described below.

Unless specifically noted otherwise existing power and lighting circuits to the Work Area are not to be used. All power and lighting to the Work Area and Decontamination facilities are to be provided from temporary electrical panel described below.

A. Comply with requirements to OSHA 19 CRF 1910.147 for control of hazardous

energy lockout/tag out.

B. Lockout power to Work Area by switching off all breakers serving power or lighting circuits in work area. Label breakers with tape over breaker with notation "DANGER circuit being worked on." Lock panel and have all keys under control of Contractor's Superintendent or Owner's designated Representative.

C. Lockout power to circuits running through Work Area wherever possible by switching

off all breakers serving these circuits. Label breakers with tape over breaker with notation "DANGER circuit being worked on." Sign and date danger tag. Lock panel and supply keys to Contractor, Owner and Owner's Representative. If circuits cannot be shut down for any reason, label at intervals 4'-0" on center with tags reading, "DANGER live electric circuit. Electrocution hazard."

D. All asbestos abatement work in the vicinity of the live circuit is to be performed dry.

All necessary notifications and procedures for dry removal are to be followed.

3.5.3 Temporary Electrical Panel: Provide temporary electrical panel sized and equipped to accommodate all electrical equipment and lighting required by the work. Connect temporary panel to existing building electrical system. Protect with circuit breaker or fused disconnect. Locate temporary panel as directed by Construction Manager. Panel is to be installed by a licensed electrician.

3.5.4 Power Distribution System: Provide circuits of adequate size and proper characteristics

for each use. In general run wiring overhead, and rise vertically where wiring will be at least exposed to damage from construction operations.

3.5.5 Circuit Protection: Protect each circuit with a ground fault circuit interrupter (GFCI) of

proper size located in the temporary panel. Do not use outlet type GFCI devices.

3.5.6 Temporary Wiring: in the Work Area shall be type UF non-metallic sheathed cable located overhead and exposed for surveillance. Do not wire temporary lighting with plain, exposed (insulated) electrical conductors. Provide liquid tight enclosures or boxes for wiring devices.

Page 58: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 6 Temporary Facilities

3.5.7 Number of Branch Circuits: Provide sufficient branch circuits as required by the work. All branch circuits are to originate at temporary electrical panel. At minimum provide the following:

A. One Circuit for each HEPA filtered fan unit

B. For power tools and task lighting, provide one temporary 4-gang outlet in the following

locations. Provide a separate 110-120 Volt, 20 Amp circuit for each 4-gang outlet (4 outlets per circuit).

C. One outlet in the work area for each 2500 square feet of work area

D. One outlet at each decontamination unit, located in equipment room

3.5.8 Provide 110-120 volt 20-amp branch circuits with 4-gang outlet for Consultant’s exclusive

use while conducting air sampling during the work as follows:

A. One in each work area

B. One at clean side of each Decontamination Unit.

C. One at each exhaust location for HEPA filtered fan units

3.5.9 Provide 110-120 volt 20-amp branch circuits with 4-gang outlet for Consultant’s exclusive use for conducting final air sampling as set forth in Section 01714 - Work Area Clearance as follows:

A. Five inside work area B. Two outside work area in location designated by Consultant

3.6 TEMPORARY LIGHTING

3.6.1 Lockout: Lock out all existing power to lighting circuits in Work Area as described in section 01526 - Temporary Enclosures. Unless specifically noted otherwise existing lighting circuits to the Work Area are not to be used. All lighting to the Work Area and Decontamination facilities is to be provided from temporary electrical panel described above.

3.6.2 Provide the following or equivalent where natural lighting or existing building lighting does

not meet the required light level:

A. One 200-watt incandescent lamp per 1000 square feet of floor area, uniformly distributed, for general construction lighting, or equivalent illumination of a similar nature. In corridors and similar traffic areas provide one 100-watt incandescent lamp every 50 feet. In stair ways and at ladder runs, provide one lamp minimum per story, located to illuminate each landing and flight. Provide sufficient temporary lighting to ensure proper workmanship everywhere; by combined use of daylight, general lighting, and portable plug-in task lighting.

B. Provide lighting in areas where work is being performed as required to supply a 100-foot candle minimum light level.

C. Provide lighting in any area being subjected to a visual inspection as required to supply

a 100-foot candle minimum light level.

Page 59: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 7 Temporary Facilities

D. Provide lighting in the Decontamination Unit as required to supply a 50-foot candle minimum light level.

3.6.3 Number of Lighting Circuits: Provide sufficient lighting circuits as required by the work.

All lighting circuits are to originate at temporary electrical panel.

3.6.4 Circuit Protection: Protect each circuit with a ground fault circuit interrupter (GFCI) of proper size located in the temporary panel.

3.7 TEMPORARY HEAT

3.7.1 General: Provide temporary heat where indicated or needed for performance of the Work.

3.7.2 Heating Facilities: Except where the Owner authorizes use of the permanent system,

provide vented, self-contained, LP-gas or fuel-oil heaters with individual space thermostatic control.

A. Use of gasoline-burning space heaters, open flame, or salamander heating units is

prohibited.

3.7.3 Maintain a minimum temperature of 70 degrees F where finished work has been installed.

3.7.4 Maintain a minimum temperature of 75 degrees F in the shower of the decontamination

unit.

3.7.5 Maintain a minimum temperature of 66 degrees F in the work area at all times when work activities are being performed. At all other times and at completion of removal work, maintain a minimum temperature of 50 degrees F.

3.8 SANITARY FACILITIES

3.8.1 Sanitary facilities include temporary toilets, wash facilities, and drinking-water fixtures. Comply with regulations and health codes for the type, number, location, operation and maintenance of fixtures and facilities. Install where facilities will be serve the project needs.

A. Provide toilet tissue, paper towels, paper cups, and similar disposable materials for

each facility. Provide covered waste containers for used material.

3.8.2 Toilets: Use of the Owner's existing toilet facilities, as indicated, will be permitted, so long as these facilities are properly cleaned and maintained in a condition acceptable to the Owner. At substantial completion, restore these facilities to the condition prevalent at the time of initial use.

3.8.3 Toilets: If necessary, provide one self-contained chemical toilet unit in the Work Area for

each 30 workers. Facilities shall be maintained throughout the Work. At the end of the job, facilities shall be decontaminated in accordance with these specifications.

A. Provide separate facilities for male and female personnel.

Page 60: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 8 Temporary Facilities

3.8.4 Wash Facilities: If necessary, install wash facilities supplied with potable water at convenient locations for personnel involved in handling materials that require wash-up for a healthy and sanitary condition. Dispose of drainage properly. Supply cleaning compounds appropriate for each condition.

3.8.5 Drinking Water Facilities: Provide containerized, tap-dispenser, bottled-water drinking–

water units, including paper supply. 3.9 FIRE PROTECTION FACILITIES INSTALLATION

3.9.1 Fire Extinguishers: Comply with the applicable recommendations of NFPA Standard 10 "Standard for Portable Fire Extinguishers" and local fire regulations. A. Locate fire extinguishers where they are most convenient and effective for their

intended purpose, but provide not less than one extinguisher in each Work Area in Equipment Room and One outside Work Area in Clean Room.

B. Store combustible materials in containers in fire-safe locations.

C. Maintain unobstructed access to fire extinguishers, fire hydrants, temporary fire-

protection facilities, stairways, and other access routes for fighting fires.

D. Prohibit smoking within any building, structure, and other enclosures or in hazardous fire-exposure areas.

E. Provide supervision of welding operations, combustion-type temporary heating units,

and similar sources of fire ignition.

3.9.2 Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erection of structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and the public of the hazard being protected against. Where appropriate and needed, provide lighting, including flashing red or amber lights.

3.9.3 Environmental Protection: Provide protection, operate temporary facilities, and conduct

construction in ways and by methods that comply with environmental regulations, and minimize the possibility that air, waterways and subsoil might be contaminated or polluted or that other undesirable effects might results. Avoid use of tools and equipment that produce harmful noise.

3.10 OPERATION, TERMINATION AND REMOVAL

3.10.1 Supervision: Enforce strict discipline in use of temporary facilities. Limit availability of temporary facilities to essential and intended uses to minimize waste and abuse.

3.10.2 Maintenance: Maintain facilities in good operating condition until removal. Protect from

damage by freezing temperatures and similar elements.

A. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

B. Protection: Prevent water-filled piping from freezing. Maintain markers for

underground lines. Protect from damage during excavation operations.

Page 61: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01503 01503 - 9 Temporary Facilities

3.10.3 Termination and Removal: Unless the Owner’s Representative requests that it be maintained longer, remove each temporary facility when the need has ended, when replaced by authorized use of a permanent facility, or not later than substantial completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with the temporary facility. Repair damaged items, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

A. Materials and facilities that constitute temporary facilities are the Contractor’s

property

B. At substantial completion, clean and renovate permanent facilities used during the construction period including, but not limited to, the following:

a. Replace air filters and clean inside of ductwork and housing b. Replace significantly worn parts and parts subject to unusual operating

conditions c. Replace lamps burned out or noticeably dimmed by use

END OF SECTION 01503

Page 62: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01513 01513 - 1 Temporary Negative Pressure and Air Circulation System

SECTION 01513 – TEMPORARY NEGATIVE PRESSURE AND AIR CIRCULATION SYSTEM PART 1 – GENERAL 1.1 PATENT RIGHTS

1.1.1 Negative pressure machines and the process of setting up a negative pressure space may be subject to patent rights (e.g. Patent No. 4,604,111). Contractor shall pay all license fees and royalties and assume all costs incidental to the use, in the performance of the work or the incorporation into the work of any invention, design, process, product or device which is the subject of any rights, including but not limited to patents or copyrights, held by others. Contractor shall defend, indemnify and hold harmless the Owner and Owner’s Representative and anyone directly or indirectly employed by either of them from and against any and all claims, damages, losses and expenses (including attorney's fees and court and arbitration expenses) arising out of any alleged infringement of such rights of others.

1.2 RELATED DOCUMENTS

1.2.1 Drawings and general provisions of Contract and Asbestos Abatement Project Design Sections apply to work of this section

1.3 RELATED SECTIONS

1.3.1 Heating and cooling requirements are set forth in Section 01503 – Temporary Facilities. 1.4 MONITORING

1.4.1 Continuously monitor and record the pressure differential between the work area and the outside of the work area with a monitoring device incorporating a continuous recorder. For containments greater than 20,000 square feet, two monitoring devices, with recorder, shall be required. Meters shall be equipped with a warning buzzer which will sound if pressure differential drops below 0.02 inches of water.

1.4.2 The monitoring device(s) shall produce a continuous print out of the pressure differential

between the work area and the outside of the work area. The Contractor shall date, initial and indicate the beginning and the end of each shift on the printout. Maintain records of pressure differential in the project data binder.

1.5 SUBMITTALS

1.5.1 Before Start of Work: Submit design of negative pressure system to the Construction Manager for review. Do not begin work until submittal is returned with the Construction Manager’s approval indicating that the submittal is returned for unrestricted use. Include in the submittal at a minimum:

A. Number of HEPA filtered fan units required and the calculations necessary to

determine the number of machines

B. Description of projected air flow within Work Area and methods required to provide adequate air flow in all portions of the work area

C. Anticipated pressure differential across Work Area enclosures

Page 63: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01513 01513 - 2 Temporary Negative Pressure and Air Circulation System

D. Description of methods of testing for correct air flow and pressure differentials

E. Manufacturer's product data on the HEPA filtered fan units to be used

F. Location of the machines in the Work Area

G. Method of supplying adequate power to the machines and designation of building electrical panel(s) which will be supplying the power

H. Description of work practices to insure that airborne fibers travel away from workers

I. Manufacturer's product data on equipment used to monitor pressure differential

between inside and outside of Work Area

J. Manufacturer's product data on auxiliary generator to be used

K. Schematic diagram of power and auxiliary power supply to HEPA filtered fan units.

1.5.2 On a weekly basis: Submit printout from pressure differential monitoring equipment. Mark printout with date and start of time for each day. Use printout paper that indicates elapsed time in intervals no greater than hours. Indicate on each day's record times of starting and stopping abatement work, type of work in progress, breaks for lunch or other purposes, periods of stop work, and filter changes. Cut printout into segments by day, attach to 8 1/2" by 11" paper. Label with project name, contractor's name and date.

1.6 QUALITY ASSURANCE

1.6.1 Monitor pressure differential at Personnel and Equipment Decontamination Units with a differential pressure meter equipped with a continuous recorder. Meter shall be equipped with a warning buzzer which will sound if pressure differential drops below 0.02" of water.

PART 2 – PRODUCTS 2.1 HEPA FILTERED FAN UNITS

2.1.1 General: Supply the required number of HEPA filtered fan units to the site in accordance with this Asbestos Abatement Project Manual. Use units that meet the following requirements.

2.1.2 Cabinet: Constructed of durable materials able to withstand damage from rough handling

and transportation. The width of the cabinet should be less than 30 inches to fit through standard-size doorways. Provide units whose cabinets are:

A. Factory-sealed to prevent asbestos-containing dust from being released during use,

transport, or maintenance

B. Arranged to provide access to and replacement of all air filters from intake end

C. Mounted on casters or wheels

2.1.3 Fans: Rate capacity of fan according to usable air-moving capacity under actual operating conditions.

Page 64: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01513 01513 - 3 Temporary Negative Pressure and Air Circulation System

2.1.4 HEPA Filters: Provide units whose final filter is the HEPA type with the filter media (folded into closely pleated panels) completely sealed on all edges with a structurally rigid frame.

A. Provide units with a continuous rubber gasket located between the filter and the filter

housing to form a tight seal.

B. Provide HEPA filters that are individually tested and certified by the manufacturer to have an efficiency of not less than 99.97 percent when challenged with 0.3 m dioctylphthalate (DOP) particles when tested in accordance with Military Standard Number 282 and Army Instruction Manual 136-300-175A. Provide filters that bear a UL586 label to indicate ability to perform under specified conditions.

C. Provide filters that are marked with: the name of the manufacturer, serial number, air

flow rating, efficiency and resistance, and the direction of test air flow.

D. Pre-filters, which protect the final filter by removing the larger particles, are required to prolong the operating life of the HEPA filter. Two stages of pre-filtration are required. Provide units with the following pre-filters: a. First-stage pre-filter: low-efficiency type (e.g., for particles 100 m and larger) b. Second-stage (or intermediate) filter: medium efficiency (eg., effective for particles

down to 5 m) c. Provide units with pre-filters and intermediate filters installed either on or in the

intake grid of the unit and held in place with special housings or clamps.

E. Instrumentation: Provide units equipped with: a. Magnehelic gauge or manometer to measure the pressure drop across filters and

indicate when filters have become loaded and need to be changed b. A table indicating the usable air-handling capacity for various static pressure

readings on the Magnehelic gauge affixed near the gauge for reference, or the Magnehelic reading indicating at what point the filters should be changed, noting Cubic Feet per Minute (CFM) air delivery at that point

c. Elapsed time meter to show the total accumulated hours of operation

F. Safety and Warning Devices: Provide units with the following safety and warning devices:

a. Electrical (or mechanical) lockout to prevent fan from operating without a HEPA

filter b. Automatic shutdown system to stop fan in the event of a rupture in the HEPA filter

or blocked air discharge c. Warning lights to indicate normal operation (green), too high a pressure drop

across the filters (i.e., filter overloading) (yellow), and too low of a pressure drop (i.e., rupture in HEPA filter or obstructed discharge) (red)

d. Audible alarm if unit shuts down due to operation of safety systems

G. Electrical components: Provide units with electrical components approved by the National Electrical Manufacturers Association (NEMA) and Underwriter's Laboratories (UL). Each unit is to be equipped with overload protection sized for the equipment. The motor, fan, fan housing, and cabinet are to be grounded.

2.2 AUXILIARY GENERATOR

Page 65: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01513 01513 - 4 Temporary Negative Pressure and Air Circulation System

2.2.1 Provide auxiliary gasoline powered generator located outside of the building in a location protected from the weather. Arrange so that if a power failure occurs the generator automatically starts and supplies power to a minimum of 50% of the negative air machines in operation.

2.3 AUXILIARY POWER SWITCH

2.3.1 Auxiliary Power Switch: Provide a switching relay which will automatically start auxiliary generator and switch over power supplied to HEPA filtered fan units to auxiliary generator.

PART 3 – EXECUTION 3.1 NEGATIVE PRESSURE SYSTEM ISOLATION

3.1.1 Isolate the Work Area from all adjacent areas or systems of the building with a pressure differential that will cause a movement of air from outside to inside at any breach in the physical isolation of the Work Area ("Negative Air").

3.1.2 Relative Pressure in Work Area: Continuously maintain the Work Area at an air pressure

that is lower than that in any surrounding space in the building, or at any location in the immediate proximity outside of the building envelope. This pressure differential when measured across any physical or critical barrier must equal or exceed a static pressure of 0.02 inches of water.

3.1.3 Accomplish the pressure differential by exhausting a sufficient number of HEPA filtered

fan units from the Work Area. The number of units required will depend on machine characteristics, the seal at barriers, and required air circulation. The number of units will increase with increased make-up air or leaks into the Work Area. Determine the number of units required for pressure isolation by the following procedure:

A. Establish required air circulation in work area, personnel and equipment

decontamination units.

B. Exhaust a sufficient number of units from the work area to develop the required pressure differential.

C. The required number of units is the number determined above plus one additional unit.

D. Vent HEPA filtered fan units to outside of building unless authorized in writing by

Owner's Representative.

E. Where not feasible to exhaust outside the building and where written authorization is given from the Construction Manager, vent each HEPA filtered fan to inlet of second unit. Vent second unit to a controlled area in building. Insure that controlled area is isolated from balance of building by critical barriers at all times that units are in operation.

F. Mount units to exhaust directly or through disposable ductwork

G. Use only new ductwork except for sheet metal connections and elbows

H. Use ductwork and fittings of same diameter or larger than discharge connection on fan

unit

I. Use inflatable, disposable plastic ductwork in lengths not greater than 100 feet

Page 66: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01513 01513 - 5 Temporary Negative Pressure and Air Circulation System

J. Use spiral wire-reinforced flex duct in lengths not greater than 50 feet

K. Arrange exhaust as required to inflate duct to a rigidity sufficient to prevent flapping

L. If direction of discharge from fan unit is not aligned with duct use sheet metal elbow to

change direction. Use six feet of spiral wire reinforced flex duct after direction change

3.1.4 Isolation of elevators, stair towers, and return air intakes: Erect seals with an air space at doors to elevators and stair towers.

A. Fabricate seal by first sealing door with duct tape and 6 mil polyethylene. Construct a

barrier from ½" CDX plywood or ½" gypsum board supported by wood studs at 16" on centers. Space face of barrier a minimum of 3" from face of door. Seal barrier with 6 mil sheet plastic and duct tape.

B. Use plywood and framing lumber that is treated to be fire resistant

3.1.5 Isolation of return air ductwork: Return air duct work which must be kept operating is to be isolated from the Work Area.

A. Wrap the duct with 2 layers of 6 mil polyethylene. Seal all polyethylene seams with

spray glue and duct tape. 3.2 AIR CIRCULATION IN THE WORK AREA

3.2.1 Air Circulation: For purposes of this section air circulation refers to either the introduction of outside air to the Work Area or the circulation and cleaning of air within the Work Area.

3.2.2 Air circulation in the work area is a minimum requirement intended to help maintain

airborne fiber counts at a level that does not significantly challenge the work area isolation measures. The Contractor may also use this air circulation as part of the engineering controls in the work protection program.

3.2.3 Determining the Air Circulation Requirements: Provide a fully operational air circulation

system supplying a minimum of four (4) air changes per hour.

3.2.4 Determine Number of Units needed to achieve required air circulation according to the following procedure:

A. Determine the volume in cubic feet of the work area by multiplying floor area by ceiling

height. Determine total air circulation requirement in cubic feet per minute (CFM) for the work area by multiplying this volume by the air change rate and dividing by 60.

B. Air Circulation Required in Cubic Feet of Air per Minute (CFM) = Volume of work area (cubic feet) X Number of air changes per hour 60 (minutes per hour)

C. Divide the air circulation requirement (CFM) above by capacity of HEPA filtered fan

unit(s) used. Capacity of a unit for purposes of this section is the capacity in cubic feet per minute with fully loaded filters (pressure differential which causes loaded filter warning light to come on) in the machine's labeled operating characteristics.

Number of Units Needed = Air Circulation Requirement (CFM)

Capacity of Unit with Loaded Filters (CFM)

Page 67: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01513 01513 - 6 Temporary Negative Pressure and Air Circulation System

D. Add one (1) additional unit as a backup in case of equipment failure or machine

shutdown for filter changing. 3.3 EXHAUST SYSTEM

3.3.1 Negative pressure isolation and air circulation in the Work Area are to be accomplished by an exhaust system as described below.

A. Exhaust all units from the Work Area to meet air circulation requirement of this section.

B. Location of HEPA Filtered Fan Units: Locate fan unit(s) so that makeup air enters

work area primarily through decontamination facilities and traverses Work Area as much as possible. This may be accomplished by positioning the HEPA filtered fan unit(s) at a maximum distance from the worker access opening or other makeup air sources.

C. Vent to Outside of Building, unless authorized in writing by the Construction Manager.

D. Air Handling Unit Exhaust: The exhaust plume from air handling units should be

located away from adjacent personnel and intakes for HVAC systems.

E. The end of the unit or its exhaust duct should be placed through an opening in the plastic barrier or wall covering. Seal plastic around the unit or duct with tape.

F. Window Openings: Window panes which have to be removed temporarily shall be

reinstalled by a qualified tradesman at the completion of the work.

G. Decontamination Units: Arrange Work Area and decontamination units so that the majority of make-up air comes through the Decontamination Units. Use only personnel or equipment Decontamination Unit at any time and seal the other so that make up air passes through unit in use.

H. Supplemental Makeup Air Inlets: Provide where required for proper air flow through

the Work Area in location approved by the Construction Manager by making openings in the plastic sheeting that allow air from outside the building into the Work Area. Locate auxiliary makeup air inlets as far as possible from the fan unit(s) (e.g., on an opposite wall), off the floor (preferably near the ceiling), and away from barriers that separate the Work Area from occupied clean areas. Cover with flaps to reseal automatically if the negative pressure system should shut down for any reason. Spray flap and around opening with spray adhesive so that if flap closes meeting surfaces are both covered with adhesive. Use adhesive that forms contact bond when dry. If makeup air is coming from an asbestos-fiber-contaminated source or potentially contaminated then it should pass through a HEPA filter before entering work area. If air is contaminated with other materials it may also require filtering. If this is done, supply air fans will be necessary to overcome the resistance of the filters. A HEPA filtered fan unit may be used to accomplish this. Caution must be used to insure that work area remains under negative pressure.

3.4 RECIRCULATION SYSTEM

3.4.1 Pressure differential isolation and air circulation in the Work Area are to be accomplished by a recirculation system as described below.

Page 68: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01513 01513 - 7 Temporary Negative Pressure and Air Circulation System

3.4.2 Recirculate air in the Work Area through HEPA filtered fan units to accomplish air circulation requirements of this section.

3.4.3 Location of Fan Units: Locate HEPA filtered fan units so that air is circulated through all

parts of the Work Area, and so that required pressure is maintained at all parts of Work Area geometry. Move units as necessary so that in any location where asbestos-containing materials are being disturbed the discharge from one HEPA filtered fan unit is blowing contamination away from workers. Direct air flow in these locations so that it is predominantly toward workers' backs at the breathing zone elevation.

3.5 AIR CIRCULATION IN DECONTAMINATION UNITS

3.5.1 Pressure Differential Isolation: Continuously maintain the pressure differential required for the work area in the:

A. Personnel Decontamination Unit: across the Shower Room with the Equipment

Room at a lower pressure than the Clean room.

B. Equipment Decontamination Unit: Across the Holding Room with the Wash Room at a lower pressure than the Clean Room.

3.5.2 Air Circulation: Continuously maintain air circulation in Decontamination Units at same

level as required for Work Area.

3.5.3 Air Movement: Arrange air circulation through the Personnel Decontamination Unit so that it produces a movement of air from the Clean Room through the Shower Room into the Equipment Room. At each opening, the air flow velocity must be sufficient to provide visible indications of air movement into the work area. The velocity of air flow within the enclosure must be adequate to remove airborne contamination from each worker’s breathing one without disturbing the asbestos-containing material on surfaces.

3.6 USE OF THE NEGATIVE AIR SYSTEM

3.6.1 General: Each unit shall be serviced by dedicated circuits with overload device. If an existing building electrical panel is being used it must have sufficient spare capacity to accommodate the load of all negative pressure units connected. Dedication of existing circuits may be accomplished by shutting down existing loads on the circuits.

3.6.2 Testing the System: Test negative pressure system before any asbestos-containing

material is wetted or removed. After the Work Area has been prepared, the decontamination facility set up, and the fan unit(s) installed, start the unit(s) (one at a time). Demonstrate operation and testing of negative pressure system to Consultant.

3.6.3 Demonstrate Condition of Equipment for each HEPA filtered fan unit and negative

pressure monitoring equipment including proper operation of the following:

A. Squareness of HEPA Filter

B. Condition of Seals

C. Proper operation of all lights

D. Proper operation of automatic shut down if exhaust is blocked

E. Proper operation of alarms

Page 69: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01513 01513 - 8 Temporary Negative Pressure and Air Circulation System

F. Proper operation of magnehelic gauge

G. Proper operation and calibration on pressure monitoring equipment

3.6.4 Demonstrate Operation of the negative pressure system to the Consultant to include, but not be limited to, the following:

A. Plastic barriers and sheeting move lightly in toward Work Area B. Curtain of decontamination units move lightly in toward Work Area

C. There is a noticeable movement of air through the Decontamination Unit

D. Use smoke tube to demonstrate air movement from Clean Room through Shower

Room to Equipment Room

E. Use smoke tubes to demonstrate a definite motion of air across all areas in which work is to be performed

F. Modify the Negative Pressure System as necessary to demonstrate successfully the

above.

3.6.5 Use of System during Abatement Operations

A. Start fan units before beginning work (before any asbestos-containing material is disturbed). After abatement work has begun, run units continuously to maintain constant negative pressure and air circulation until decontamination of the work area is complete. Do not turn off units at the end of the work shift or when abatement operations temporarily stop.

B. Do not shut down negative pressure system during encapsulating procedures, unless

authorized by the Construction Manager in writing. Supply sufficient pre-filters to allow frequent changes.

C. Start abatement work at a location farthest from the fan units and proceed toward

them. If an electric power failure occurs, immediately stop all abatement work and do not resume until power is restored and fan units are operating again.

D. At completion of abatement work, allow fan units to run as specified under Section

01711 – Project Decontamination, to remove airborne fibers that may have been generated during abatement work and cleanup and to purge the Work Area with clean makeup air. The units may be required to run for a longer time after decontamination, if dry or only partially wetted asbestos material was encountered during any abatement work.

3.6.6 Dismantling the System

A. When a final inspection and the results of final air tests indicate that the area has been

decontaminated, fan units may be removed from the Work Area. Before removal from the Work Area, remove and properly dispose of pre-filter, decontaminate exterior of machine and seal intake to the machine with 6 mil polyethylene to prevent environmental contamination from the filters.

END OF SECTION 01513

Page 70: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 1 Temporary Enclosures

SECTION 01526 – TEMPORARY ENCLOSURES PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design Sections apply to work of this section.

1.2 SUBMITTALS

1.2.1 Before Start of Work submit the following to the Construction Manager for review. Provide a copy of the submittals to the Consultant. Do not begin work until these submittals are returned with the Construction Manager’s approval indicating that the submittal is returned for unrestricted use.

1.2.2 Strippable Coatings: Submit following:

A. Product description including major components and solvents.

B. Test report on ASTM E84 test of surface burning characteristics.

C. Manufacturer's installation instructions. Indicate portions applicable to the project and

selected assemblies where the manufacturer offers alternatives.

D. Material Safety Data Sheet: Submit the Material Safety Data Sheet, or equivalent, in accordance with the OSHA Hazard Communication Standard (29 CFR 1910.1200) for strippable coating material proposed for use on the work. Include a separate attachment for each sheet indicating the specific worker protective equipment proposed for use with the material indicated.

1.2.3 Spray Cement: Submit following:

A. Product description including major components and solvents. B. Manufacturer's installation instructions. Indicate portions applicable to the project.

C. Material Safety Data Sheet: Submit the Material Safety Data Sheet, or equivalent, in

accordance with the OSHA Hazard Communication Standard (29 CFR 1910.1200) for spray cement material proposed for use on the work. Include a separate attachment for each sheet indicating the specific worker protective equipment proposed for use with the material indicated.

1.2.4 Sheet Plastic: For fire retardant plastic submit test reports on NFPA 701 test.

1.2.5 Signs: Submit samples of signs to be used.

PART 2 – PRODUCTS 2.1 SHEET PLASTIC

2.1.1 Polyethylene Sheet: A single polyethylene film in the largest sheet size possible to minimize seams 6 mils thick, clear, frosted, or black as indicated.

2.1.2 Polyethylene Sheet: Provide flame-resistant polyethylene film that conforms to

requirements set forth by the National Fire Protection Association Standard 701, Small

Page 71: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 2 Temporary Enclosures

Scale Fire Test for Flame-Resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mils thick as indicated, frosted or black as indicated.

2.1.3 Reinforced Polyethylene Sheet: Where plastic sheet constitutes the only barrier between

the work area and the building exterior, provide translucent, nylon reinforced or woven polyethylene, laminated, flame resistant, polyethylene film that conforms to requirements set forth by the National Fire Protection Association Standard 701, Small Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mil thick as indicated, frosted or black as indicated.

2.2 STRIPPABLE COATINGS

2.2.1 Provide strippable coatings in aerosol cans or premixed for spray application formulated to adhere gently to surfaces and remove cleanly by peeling off at the completion of the work.

A. Provide only water-based latex materials.

B. Provide materials manufactured for the specific application required.

2.2.2 Wall coating: designed to be easy to remove

2.2.3 Floor coating: designed to provide a tough film which resists spread of water beneath

plastic layer

2.2.4 Window coating: recommended by the manufacturer for use on windows. Supply materials that are designed to be stable on glass in sunlight and resist the transmission of ultraviolet radiation

2.2.5 Fire Safety: Provide materials that meet the following requirements:

A. When wet or while being installed:

a. Do not create combustible vapors b. Have no flash point c. Are not noxious d. Department of Transportation category of non-flammable

B. When dry, material must have a Class A rating as a building material and meet the

following requirements when tested in accordance with ASTM E-84: a. Flame Spread no greater than 20 b. Fuel Contributed 0 c. Smoke Developed no more than 110

2.2.6 Deliver materials to the job site in unopened, factory-labeled containers.

2.3 MISCELLANEOUS MATERIALS

2.3.1 Duct Tape: Provide duct tape in 2" or 3" widths as indicated, with an adhesive which is formulated to stick aggressively to sheet polyethylene.

2.3.2 Spray Cement: Provide spray adhesive in aerosol cans which is specifically formulated

to stick tenaciously to sheet polyethylene. PART 3 – EXECUTION

Page 72: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 3 Temporary Enclosures

3.1 SEQUENCE OF WORK

3.1.1 Carry out work of this section sequentially. Complete each activity before proceeding to the next.

3.1.2 Work Area: One contiguous work location. A "Work Area" is considered contaminated

during the work, and must be isolated from the balance of the building, and decontaminated at the completion of the asbestos-control work.

3.1.3 Completely isolate the Work Area from other parts of the building so as to prevent

asbestos-containing dust or debris from passing beyond the isolated area. Should the area beyond the Work Area(s) become contaminated with asbestos-containing dust or debris as a consequence of the work, clean those areas in accordance with the procedures indicated in Section 01711 – Project Decontamination. Perform all such required cleaning or decontamination at no additional cost to owner.

3.1.4 Construct enclosures to provide an air-tight seal around ducts and openings into existing

ventilation systems and around penetrations for electrical conduits, telephone wires, water lines, drain pipes, etc. Construct enclosures to be both airtight and watertight except for those openings designed to provide entry and/or air flow control.

3.1.5 Size: Construct enclosure with sufficient volume to encompass all of the working surfaces

yet allow unencumbered movement by the workers, provide unrestricted air flow past the workers, and ensure walking surfaces can be kept free of tripping hazards.

3.1.6 Structural Integrity: The walls, ceilings and floors must be supported in such a manner

that portions of the enclosure will not fall down during normal use.

3.1.7 Barrier Supports: Provide frames as necessary to support all unsupported spans of sheeting.

3.1.8 Openings: It is not necessary that the structure be airtight: openings may be designed to

direct air flow. Such openings are to be located at a distance from active removal operations. They are to be designed to draw air into the enclosure under all anticipated circumstances. In the event that negative pressure is lost, they are to be fitted with either HEPA filters to trap dust or automatic trap doors that prevent dust from escaping the enclosure. Openings for exits are to be controlled by an airlock or a vestibule.

3.1.9 Place all tools, scaffolding, staging, etc. necessary for the work in the area to be isolated

prior to completion of Work Area isolation.

3.1.10 Areas within an Enclosure: Each enclosure consists of a work area, a decontamination area, and a waste storage area. The work area where the asbestos removal operations occur are to be separated both from the waste storage area and the contamination control area by physical curtains, doors, and/or airflow patterns that force any airborne contamination back into the work area.

3.1.11 Removing Mobile Objects: Remove all removable furniture that has not been designated

as contaminated by the Consultant. Also remove uncontaminated equipment, and/or supplies from the Work Area before commencing work, or completely cover with two (2) layers of polyethylene sheeting, at least 6 mil in thickness, securely taped in place with duct tape. Such furniture and equipment shall be considered outside the work area unless covering plastic or seal is breached.

Page 73: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 4 Temporary Enclosures

3.1.12 Disabling HVAC System: Disable ventilating systems or any other system bringing air into or out of the Work Area. Disable system by disconnecting wires, removing circuit breakers, by lockable switch or other positive means that will prevent accidental premature restarting of equipment.

3.1.13 Operating HVAC Systems in the Regulation Area: If components of a HVAC system

located in the regulated area are connected to a system that will service another zone during the project, the portion of the duct in the regulated area must be sealed and pressurized. Necessary precautions include caulking the duct joints, covering all cracks and openings with two layers of sheeting, and pressurizing the duct throughout the duration of the project by restricting the return of air flow. The power to the fan supplying the positive pressure should be locked on to prevent pressure loss.

A. If fan providing positive pressure fails for any reason, immediately stop asbestos

removal work, mist the area to reduce airborne fiber levels and notify the Construction Manager. Do not resume asbestos removal work until authorized by the Construction Manager.

3.1.14 Lockout power to Work Area by switching off all breakers serving power or lighting

circuits in work area. Label breakers with tape over breaker with notation "DANGER circuit being worked on". Lock panel and have all keys under control of Contractor's Asbestos Abatement Supervisor or Construction Manager.

3.1.15 Lockout power to circuits running through work area wherever possible by switching off

all breakers or removing fuses serving these circuits. Label breakers with tape over breaker with notation "DANGER circuit being worked on". Lock panel and have all keys under control of Contractor's Asbestos Abatement Supervisor or Construction Manager. If circuits cannot be shut down for any reason, label at intervals 4'-0" on center with tags reading, "DANGER live electric circuit. Electrocution hazard." Label circuits in hidden locations but which may be affected by the work in a similar manner.

3.1.16 Inspection Windows: Install inspection windows in locations as directed by the

Construction Manager. Each inspection window is to have a 24" X 24" viewing area fabricated from 1/4" acrylic or polycarbonate sheet. Install window with top at 6'-6" above floor height in a manner that provides unobstructed vision from outside to inside of the Work Area. Protect window from damage from scratching, dirt or any coatings used during the work. A sufficient number of windows are to be installed to provide observation of all portions of the Work Area that can be made visible from adjacent areas. Inspection windows that open into uncontrolled area are to be covered with a removable plywood hatch secured by lock and key. Provide keys to Construction Manager for all such locks.

3.2 EMERGENCY EXITS

3.2.1 Provide emergency exits and emergency lighting as set forth below:

3.2.2 Emergency Exits: At each existing exit door from the Work Area provide the following means for emergency exiting:

A. Arrange exit door so that it is secure from outside the Work area but permits exiting

from the Work Area.

B. Mark outline of door on Primary and Critical Barriers with luminescent paint at least 1" wide. Hang a razor knife on a string beside outline. Arrange Critical and Primary barriers so that they can be easily cut with one pass of razor knife. Paint words

Page 74: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 5 Temporary Enclosures

"EMERGENCY EXIT" inside outline with luminescent paint in letters at least one foot high and 2" thick.

C. Provide EXIT sign at each exit.

D. Provide battery-operated emergency lighting that switches on automatically in the

event of a power failure. 3.3 CONTROL ACCESS

3.3.1 Isolate the Work Area to prevent entry by building occupants into Work Area or surrounding controlled areas. Accomplish isolation by the following:

A. Submit a list of doors and other openings that must be secured to isolate the Work

Area to the Construction manager.

B. After receiving written authorization from the Construction manager, lock all doors into the Work Area, or if doors cannot be locked, chain shut. Notify the local fire department of the list of doors or other openings which must be chained or otherwise secured shut. Cover any signs that direct emergency exiting, either outside or inside the Work Area, to locked doors. Do not obstruct doors required for emergency exits from the Work Area of from the building.

C. Fabricate partitions from 2 inch by 4 inch wood studs with 3/8 inch plywood on both

faces. Brace at intervals of 4 feet on center.

D. Modify elevator controls to prevent elevators from stopping at doors in Work Areas. This work is to be performed by a qualified elevator technician.

E. Replace passage sets on doors required for exiting from the Work Area with temporary

locksets for duration of the project. Use entry type locksets that are key lockable from one side and always operable from the inside. Install locksets with key side in stair tower and escape side on the Work Area side. Provide one key to the Construction Manager and maintain on key in the clean room of the decontamination unit. After meeting Contractor release criteria set forth in Section 01711 – Project Decontamination, reinstall original passage sets and adjust for proper operation.

3.3.2 Locked Access: Arrange Work Area so that the only access into Work Area is through

lockable doors to personnel and equipment decontamination units.

A. Install temporary doors with entrance type lockset that are key lockable from the outside and always unlocked and operable from the inside. Do not use deadbolts or padlocks.

B. Replace locksets or passage sets on doors leading to decontamination units with temporary locksets for duration of the project. Remove any deadbolts or padlocks. Use entry type locksets that are key lockable from the outside and always unlocked and operable from the inside. After meeting contractor release criteria set forth in Section 01711 - Project Decontamination, reinstall original locks, passage sets and locksets and adjust for proper operation.

C. Provide one key for each door to the Owner and Construction Manager, and maintain

one key in the clean room of the decontamination unit.

3.3.3 Visual Barrier: Where the Work Area is immediately adjacent to or within view of occupied areas, provide a visual barrier of opaque polyethylene sheeting at least 6 mil in

Page 75: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 6 Temporary Enclosures

thickness so that the work procedures are not visible to building occupants. Where this visual barrier would block natural light, substitute frosted or woven rip-stop sheet plastic in locations approved by the Construction Manager.

3.3.4 Demarcation: Demarcate the regulated area in any manner that minimizes the number of

persons within the area and protect persons outside the area from exposure to airborne concentrations of asbestos. Where critical barriers or negative pressure enclosures are used, they may demarcate the regulated area.

3.3.5 Access: Limit access to regulated areas to authorized persons as defined by OSHA and

to the Owner, Construction Manager, Consultant or a representative authorized by one of these entities.

3.3.6 Provide Warning Signs in English and Spanish at each locked door leading to Work Area

reading as follows:

A. At each locked door leading to Work Area, provide warning sign as follows:

KEEP OUT - 3 inch Sans Serif Gothic or Block BEYOND THIS POINT - 1 inch Sans Serif Gothic or Block ASBESTOS ABATEMENT WORK - 1 inch Sans Serif Gothic or Block IN PROGRESS - 1 inch Sans Serif Gothic or Block BREATING ASBESTOS DUST MAY BE HAZARDOUS TO YOUR HEALTH – 14 point Gothic KEEP OUT - 3 inch Sans Serif Gothic or Block CONSTRUCTION - 1 inch Sans Serif Gothic or Block WORK AREA - 1 inch Sans Serif Gothic or Block PROTECTIVE CLOTHING REQUIRED BEYOND THIS POINT – 14 point Gothic

B. Immediately inside door and outside critical barriers post an approximately 20 inch by 14 inch manufactured caution sign displaying the following legend with letter sizes and styles of a visibility required by 29 CFR 1926.1101:

DANGER ASBESTOS CANCER AND LUNG DISEASE HAZARD AUTHORIZED PERSONNEL ONLY RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED IN THIS AREA

C. Provide spacing between respective lines at least equal to the height of the respective

upper line.

3.3.7 Alternate Methods of Enclosure: Alternate methods of containing the Work Area may be submitted to the Construction Manager for approval. Before Class I work which involves the removal of more than 25 linear or 10 square feet of thermal system insulation or surfacing material is begun using an alternate method to those specified in 29 CFR 1926.1101, a copy of the required evaluation and certification must be submitted to the national office of OSHA. Do not proceed with any such method(s) without prior written approval of the Construction Manager.

3.4 RESPIRATORY AND WORKER PROTECTION

3.4.1 Before proceeding beyond this point in providing Temporary Enclosures:

A. Provide Worker Protection per Section 01560

Page 76: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 7 Temporary Enclosures

B. Provide Respiratory Protection per Section 01562

C. Provide Personnel Decontamination Unit per Section 01563

3.5 CRITICAL BARRIERS

3.5.1 Completely Separate the Work Area from other portions of the building and the outside by closing all openings with sheet plastic barriers at least 6 mil in thickness, or by sealing cracks leading out of Work Area with duct tape.

3.5.2 Individually seal all ventilation openings (supply and exhaust), lighting fixtures, clocks,

doorways, windows, convectors and speakers, and other openings into the Work Area with duct tape alone or with polyethylene sheeting at least 6 mil in thickness, taped securely in place with duct tape. Maintain seal until all work including Project Decontamination is completed. Take care in sealing of lighting fixtures to avoid melting or burning of sheeting.

3.5.3 Provide Sheet Plastic barriers at least 6 mil in thickness as required to seal openings

completely from the Work Area into adjacent areas. Seal the perimeter of all sheet plastic barriers with duct tape or spray cement.

3.5.4 Mechanically Support sheet plastic independently of duct tape or spray cement seals so

that seals do not support the weight of the plastic. Following are acceptable methods of supporting sheet plastic barriers. Alternative support methods may be used if approved in writing by the Construction Manager.

A. Plywood squares 6 inches by 6 inches by 3/8 inch held in place with one 6d smooth

masonry nail or electro-galvanized common nail driven through the center of the plywood and duct tape on plastic so that plywood clamps plastic to the wall. Locate plywood squares at each end, corner and at a maximum 4 feet on centers.

B. Nylon or polypropylene rope or wire with a maximum unsupported span of 10 feet, minimum ¼ inch in diameter suspended between supports securely fastened on either side of opening at a maximum 1 foot below ceiling. Tighten rope so that is has 2 inches maximum dip. Drape plastic over rope from outside Work Area so that a two foot long flap of plastic extends over rope into Work Area. Staple or wire plastic to itself 1 inch below rope at maximum 6 inches on centers to form a sheath over rope. Lift flap and seal to ceiling with duct tape or spray cement. Seal loop at bottom of flap with duct tape. Erect entire assembly so that it hangs vertically without a “shelf” upon which debris could collect.

3.5.5 Provide Negative Pressure System per Section 01513.

3.5.6 Clean housings and ducts of all overspray materials prior to erection of any Critical

Barrier that will restrict access. 3.6 PREPARE AREA

3.6.1 Scaffolding: If fixed scaffolding is to be used to provide access, HEPA vacuum and wet clean area prior to scaffolding installation.

3.6.2 Remove all electrical and mechanical items, such as lighting fixtures, clocks, diffusers,

registers, escutcheon plates, etc. which cover any part of the surface to be worked on with the work.

Page 77: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 8 Temporary Enclosures

3.6.3 Remove all general construction items such as cabinets, casework, door and window trim, moldings, ceilings, and trim which cover the surface of the work as required to prevent interference with the work.

3.6.4 Clean all contaminated furniture, equipment, and or supplies with a HEPA filtered

vacuum cleaner or by wet cleaning, as specified in Section 01712 - Cleaning and Decontamination Procedures, prior to being moved or covered. All equipment and furniture is to be deemed contaminated unless specifically declared as uncontaminated on the drawings or in writing by the Owner's Representative.

3.6.5 Clean all surfaces in Work Area with a HEPA filtered vacuum or by wet wiping prior to the

installation of primary barrier.

3.6.6 Cleaning and Sealing Surfaces: After cleaning with water and a HEPA vacuum, surfaces of stationary objects should be covered with two layers of plastic sheeting. The sheeting should be secured with duct tape or an equivalent method to provide a tight seal around the object.

3.7 PRIMARY BARRIER

3.7.1 Protect building and other surfaces in the Work Area from damage from water and high humidity or from contamination from asbestos-containing debris, slurry or high airborne fiber levels by covering with a primary barrier as described below.

3.7.2 Sealing Elevators: If an elevator shaft is located in the regulated area, it should be either

shut down or isolated by sealing with two layers of plastic sheeting. The sheeting should provide enough slack to accommodate the pressure changes in the shaft without breaking the air-tight seal.

3.7.3 Sheet Plastic: Protect surfaces in the Work Area with two (2) layers of plastic sheeting

on floor and walls, or as otherwise directed on the Contract Drawings or in writing by the Construction Manager. Perform work in the following sequence.

A. All seams in the sheeting should overlap, be staggered and not be located at corners

or wall-to-floor joints.

B. Floors: Cover floor of Work Area with 2 individual layers of clear polyethylene sheeting, each at least 6 mil in thickness, turned up walls at least 12 inches. Form a sharp right angle bend at junction of floor and wall so that there is no radius which could be stepped on causing the wall attachment to be pulled loose. Both spray-glue and duct tape all seams in floor covering. Locate seams in top layer six feet from, or at right angles to, seams in bottom layer. Install sheeting so that top layer can be removed independently of bottom layer.

C. Removal all carpeting before abatement.

D. Walls: Cover all walls in Work Area including "Critical Barrier" sheet plastic barriers with

one layer of polyethylene sheeting, at least 6 mil in thickness, mechanically supported and sealed with duct tape or spray-glue in the same manner as "Critical Barrier" sheet plastic barriers. Tape all joints including the joining with the floor covering with duct tape or as otherwise indicated on the Contract Documents or in writing by the Construction Manager. Install sheeting so that inner layer can be removed independently of bottom layer.

E. Elevator: Cover walls, floor and ceiling of elevator with two layers of 6 mil

polyethylene sheeting. Arrange entry to Work Area so that elevator door is in a

Page 78: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01526 01526 - 9 Temporary Enclosures

positively pressurized space outside the clean room of the decontamination unit. At completion of work, clean elevator as set forth in Section 01711 – Project Decontamination. Refer to Section 01013 - Summary of Work for additional requirement for protection of elevator.

F. Stairs and Ramps: Do not cover stairs or ramps with unsecured sheet plastic. Where

stairs or ramps are covered with plastic, provide 3/4" exterior grade plywood treads securely held in place, over plastic. Do not cover rungs or rails with any type of protective materials.

G. Repair of Damaged Polyethylene Sheeting: Remove and replace plastic sheeting

which has been damaged by removal operations or where seal has failed allowing water to seep between layers. Remove affected sheeting and wipe down entire area. Install new sheet plastic only when area is completely dry.

3.8 STOP WORK

3.8.1 If the Critical or Primary barrier falls or is breached in any manner stop work immediately and comply with Stop Work requirements of Section 01013 - Summary of Work. Do not start work until authorized in writing by the Construction Manager.

3.9 EXTENSION OF WORK AREA

3.9.1 Extension of Work Area: If the Critical Barrier is breached in any manner that could allow the passage of asbestos debris or airborne fibers, then add affected area to the Work Area, enclose it as required by this Section of the Asbestos Abatement Project Manual and decontaminate the affected as described in Section 01711 - Project Decontamination.

3.10 SECONDARY BARRIER

3.10.1 Secondary layer of plastic as a drop cloth to protect the primary layer from debris generated by the asbestos abatement work is specified in the appropriate work sections.

3.11 EXTERIOR ENCLOSURES

3.11.1 Construct exterior enclosures as a Critical Barrier as necessary to completely enclose the work. Fabricate from reinforced polyethylene sheeting and wood framing with appropriate sized lumber. Attach to existing building components or brace as necessary for lateral stability. Construct walls to meet all state and local regulations for construction of temporary buildings. Construct to resist a wind of 30 MPH, slope ceiling to permit drainage of rain water.

END OF SECTION 01526

Page 79: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01527 01527 - 1 Regulated Areas

SECTION 01527 – REGULATED AREAS PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design Sections apply to work of this section.

1.2 RELATED WORK SPECIFICED ELSEWHERE

1.2.1 Worker Protection: Is specified in Section 01560 - Worker Protection

1.2.2 Respiratory Protection: Is specified in Section 01562 – Respiratory Protection

1.2.3 Decontamination Facilities: Are described in Section 01563 – Decontamination Units 1.3 DESCRIPTION OF WORK

1.3.1 Work of this section consists of preparing a Regulated Area for work of the following sections only. Do not use procedures set forth in this section in connection with any other work.

A. Section 01529 – Mini Enclosures and Glovebags

B. Section 01712 – Cleaning and Decontamination Procedures

1.4 SUBMITTALS

1.4.1 Before the Start of Work: Submit the following to the Construction Manager for review. Provide a copy of the submittals to the Consultant. Begin no work until these submittals are returned with Construction Manager’s action stamp indicating that the submittal is returned for unrestricted use or final-but-restricted use.

A. HEPA Filtered Vacuum Cleaners: Submit product data

B. Signs: Submit samples of each type of sign to be used

C. Warning Tape: Submit samples

PART 2 – PRODUCTS 2.1 HEPA FILTER VACUUM CLEANERS

2.1.1 Available Manufactures: Subject to compliance with requirements, manufacturers offering products which may be incorporated in the Work include, but are not limited to, the following:

2.1.2 Manufacturer: Subject to compliance with requirements, provide products of or equivalent

to one of the Following:

Nilfisk of America, Inc. Minuteman International Pullman-Hold (White) Corp.

Page 80: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01527 01527 - 2 Regulated Areas

2.2 PLASTIC SHEET

2.2.1 Plastic Sheet: A single polyethylene film in the largest sheet size possible to minimize seams, 6.0 mil (0.15 mm) thick, clear, frosted or black as indicated.

PART 3 – EXECUTION 3.1 SECURING WORK AREA

3.1.1 Secure Work Area from access by occupants, staff or users of the building. Accomplish this where possible by locking doors, windows, or other means of access to the area, by scheduling work for periods of time that the building is unoccupied or by constructing temporary wood stud and plywood barriers.

3.2 DEMARCATION OF REGULATED AREA

3.2.1 Demarcate the Regulated Area with a sheet plastic drop cloth, signs and barrier tape. Configure the regulated area in a manner that minimizes the number of persons within the area and protects person outside the area from exposure to airborne concentrations of asbestos.

A. Drop Cloth: Cover floor in vicinity of Work Area and six feet beyond with 6 mil

polyethylene drop sheet. Where work is adjacent to wall, extend drop sheet up wall and secure at ceiling with duct tape. This drop sheet demarcates the boundary of the Regulated Area.

B. Signs: Post warning signs that carry the following legends in both English and Spanish: a. First Sign: Provide warning signs at each locked door leading to the controlled

area reading as follows: KEEP OUT 3 inch Block

b. Second Sign: Immediately inside the locked door and outside the controlled

area, post an approximately 20 inch by 14 inch manufactured caution sign displaying the following legend with letter sizes and styles of a visibility required by 29 CFR 1926: Asbestos Cancer and Lung Disease Hazard Authorized Personnel Only Respirators and Protective Clothing are required in this Area

c. Barrier Tape: Where the controlled area is in a large area, such as on part of a

boiler room or open office area, delineate area with 3 inch wide polyethylene ribbon with the printed warning “CAUTION ASBESTOS REMOVAL”. Install this ribbon between 3 and 4 feet above the floor.

3.3 SCHEDULING

3.3.1 Work may be carried out during normal working hours in those areas which can be completely secured by lockable doors from access by building occupants and staff, and which have HVAC equipment that can be shut down and locked off. Otherwise, work is to be carried out after building occupants have left.

Page 81: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01527 01527 - 3 Regulated Areas

3.4 GENERAL PROCEDURES

3.4.1 The following precautions and procedures have application to work of this section. Workers must exercise caution to avoid release of asbestos fibers into the air:

A. Setup and management of the controlled area is to be under the supervision of an

OSHA Competent Person as described in Section 01043 – Project Coordination.

B. Before start of work, comply with requirements for Section 01560 – Worker Protection and Section 01562 – Respiratory Protection.

C. Do not allow eating, drinking, smoking, chewing tobacco or gym or applying

cosmetics in the Regulated Area.

D. Shut down any air handling equipment bringing air into or out of the Regulated Area.

E. Clean any existing dust or debris from the floor and walls, and other surface in the immediate location of the work prior to commencing work by damp-mopping or by use of a High Efficiency Particulate Air (HEPA) filtered vacuum.

F. Cover floor in vicinity of Work Area and six feet beyond with 6 mil polyethylene drop

sheet. Where work is adjacent to wall, extend drop sheet up wall and secure at ceiling with duct tape. This drop sheet demarcates the boundary of the Regulated Area.

G. Seal all openings, supply and exhaust vents, and convectors within ten feet of the

Work Area with 6 mil polyethylene sheeting secured and completely sealed with duct tape.

H. Perform the work per the appropriate Asbestos Abatement Project Manual section

while on plastic drop sheet.

I. Immediately remove any asbestos-containing debris which collects on the drop sheet either by using a HEPA vacuum or by spraying with amended water or removal encapsulant, collecting with wet paper towels, placing in a disposal bag while still wet, and cleaning surface of plastic sheet with wet paper towels.

J. Complete the following at completion of work in an area before stepping off drop

sheet:

a. While standing on plaster sheet, thoroughly HEPA vacuum ladder and any tools used and pass to worker standing off sheet.

b. Worker standing off the sheet HEPA vacuum thoroughly the worker standing on the sheet.

c. Worker on the sheet thoroughly HEPA vacuum all surfaces of the plastic sheet, bags and any other items on the sheet, including the worker’s feet.

K. If moving to the next Work Area in the same secured area, worker on the drop sheet is to don clean foot covers, placing each foot, in turn, off the sheet as the foot cover is put on. Remove clean foot covers at the next Work Area while standing on the sheet. Dispose of the used foot covers along with the plastic sheet at completion of work in that area. Do not reuse foot covers to move off the sheet.

L. If work day is complete or if next Work Area is in another secured area: all workers remove protective suits turning them inside out while doing so. The person on the sheet steps with each foot off the sheet as the foot covers are removed.

Page 82: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01527 01527 - 4 Regulated Areas

M. Fold sheet and all its contents towards the center

N. Place the sheet in a properly labeled disposal bag.

O. Neck down the bag and collapse it with the HEPA vacuum.

P. Twist the bag shut, bend over and seal with duct tape by wrapping around bag neck

at least 3 times.

Q. Clean all surfaces of the Work Area by use of a HEPA filter vacuum until no visible residue remains.

R. At completion of work, require all workers to complete decontamination procedures in

accordance with Section 01560 – Worker Protection.

S. Remove respirators using the procedure in Section 01560 – Worker Protection

T. At completion of work, require all workers to complete wet decontamination procedures in accordance with Section 01560 – Worker Protection.

END OF SECTION 01527

Page 83: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 1 Mini Enclosures and Glovebags

SECTION 10529 – MINI-ENCLOSURES AND GLOVEBAGS PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design Sections apply to work of this section.

1.2 DESCRIPTION OF THE WORK

1.2.1 Work of this section consists of preparing a regulated area for work for which there is no negative exposure assessment or that involves drilling, cutting, abrading, sanding, chipping, breaking, or sawing of thermal system insulation or surfacing material. This is OSHA Class III work and is limited in size to operations that generate small amounts of ACM, i.e. no more than can be contained in one standard (60 inch by 60 inch) glove or waste bag filled no more than half full.

1.3 SUBMITTALS

1.3.1 Before start of work, submit the following to the Construction Manager for review. Provide a copy of the submittals to the Consultant. Do not begin work until these submittals are returned with the Construction Manager’s action tamp indicating that the submittal is returned for unrestricted use.

A. Surfactant: Submit product data, use instruction and recommendations from

manufacturer of surfactant intended for use. Include data substantiating that material complies with requirements.

B. Removal Encapsulant: Submit product data, use instructions and recommendations from manufacturer of removal encapsulant intended for use. Include data substantiating that material complies with requirements.

C. NESHAP Certification: Submit certification from manufacturer of surfactant or

removal encapsulant that, to the extent required by this project manual, the material, if used in accordance with manufacturer’s instructions, will wet ACM to which it is applied as required by NESHAP Asbestos Regulation (40 CFR 61, Subpart M).

D. Material Safety Data Sheet: Submit Material Safety Data Sheet, or equivalent, in

accordance with the OSHA Hazard Communications Standard (29 CFR 1910.1200) for each surfactant and encapsulating material proposed for use. Submit in the same manner as product data. Submittal is for information purposes only. Submittal will not be reviewed by Construction Manager.

E. Spray Cement: Submit the following:

a. Product description including major components and solvents b. Manufacturer’s installation instructions. Indicate portions applicable to the

project.

F. Sheet Plaster: For fire retardant plastic, submit test reports on NFPA 701 test.

G. Glovebags: Submit product data.

H. HEPA Vacuums: Submit product data

Page 84: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 2 Mini Enclosures and Glovebags

I. Signs: Submit samples of signs to be used

J. Mini-Enclosure: Provide shop drawing of mini-enclosure arrangement to be used 1.3.2 Before start of work, submit the following to the Construction Manager for review.

Provide a copy of submittals to the Consultant. Do not begin work until these submittals are returned with the Construction Manager’s action stamp indicating that the submittal has been Received – Not Reviewed:

A. Material Safety Data Sheet: Submit Material Safety Data Sheets, or equivalent, in

accordance with the OSHA Hazard Communication Standard (29 CFR 1910.1200) for the following:

a. Surfactants b. Spray Cement c. Encapsulants

PART 2 – PRODUCTS 2.1 GLOVE BAGS

2.1.1 Glovebags: Provide minimum 6 mil (0.15 mm) thick polyethylene, polyvinyl chloride or equivalent plastic sack with a seamless bottom and two sealed inward projecting long sleeved gloves or mittens, preprinted with same warning notice as disposal bag, equipped with a pouch for storage of tools, with designated location for wand or HEPA vacuum wand. Glove bag is to be not more than 60 inches by 60 inches in size.

2.1.2 Negative Pressure Glove Bag System: Provide glovebags as specified above that are

equipped for attachment to a HEPA vacuum, and that has a device to prevent the bag from collapsing during use.

2.1.3 Negative Pressure Glove Box System: Provide glove boxes constructed with rigid sides

and made from metal or other material, equipped for attachment to a HEAP vacuum, which will not collapse during use, and which can withstand the weight of the ACM and water used during removal. Provide system equipped with:

A. An air filtration unit attached to the box

B. The box fitted with gloved apertures

C. An aperture at the base of the box to serve as a bagging outlet for waste ACM and

water

D. Provide waste bags made of 6 mil (0.15 mm) thick plastic labeled as set forth in Section 02084 – Disposal of Asbestos-Containing Materials

E. A HEPA filtration system (or HEPA vacuum) to maintain pressure barrier in box.

2.2 SHEET PLASTIC

2.2.1 Polyethylene Sheet: A single polyethylene sheet in the largest sheet size possible to minimize seams, 6.0 mil (0.15 mm) thick, clear, frosted, or black as indicated.

2.2.2 Polyethylene Sheet: Where surface temperatures of building components are expected

to exceed 150⁰ F, provide flame resistant polyethylene sheet that conforms to requirements set forth by the National Fire Protection Association Standard 701, Small

Page 85: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 3 Mini Enclosures and Glovebags

Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mil (0.15 mm) thick, frost or black as indicated.

2.2.3 Reinforced Polyethylene Sheet: Where plastic sheet constitutes the only barrier between

the work area and the building exterior, provide translucent, nylon reinforced or woven polyethylene, laminated, flame resistant, polyethylene film that conforms to requirements set forth by the Nation Fire Protection Association Standard 701, Small Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mil (0.15 mm) thick, frosted or black as indicated.

2.3 MISCELLANEOUS MATERIALS

2.3.1 Duct Tape: Provide duct tape in 2 inch or 3 inch widths as indicated, with an adhesive which is formulated to stick aggressively to sheet polyethylene.

2.3.2 Spray Cement: Provide spray adhesive in aerosol cans which is specifically formulated

to stick tenaciously to sheet polyethylene.

2.3.3 Wetting Materials: For wetting prior to disturbance of ACM use either amended water or a removal encapsulant:

A. Amended Water: Provide water to which a surfactant has been added. Use a

mixture of surfactant and water which results in wetting of the ACM and retardation of fiber release during disturbance of the material equal to or greater than that provided by water amended with a surfactant consisting of one ounce of a solution of 50% polyoxyethylene ester and 50% polyoxyethylene ether mixed with five gallons of water.

B. Removal Encapsulant: Provide a penetrating type encapsulant designed specifically for removal of ACM. Use a material which results in wetting of the ACM and retardation of fiber release during disturbance of the material equal to or greater than that provided by water amended with a surfactant consisting of one ounce of a solution of 50% polyoxyethylene ester and 50% polyoxyethylene ether mixed with five gallons of water.

2.3.4 Encapsulants are specified in Section 09805 – Encapsulation of Asbestos-Containing

Materials

2.3.5 Garden Sprayer: Provide a hand pump type pressure-can garden sprayer fabricated out of either metal or plastic, equipped with a metal wand at the end of a hose that can deliver a stream or spray of liquid under pressure.

PART 3 – EXECUTION 3.1 GENERAL

3.1.1 Before Start of Work: Complete the following before start of work of this Section:

A. Section 01527 – Regulated Areas 3.2 WORKER PROTECTION

3.2.1 Before beginning work with any material for which a Material Safety Data Sheet has been submitted, provide workers with the required protective equipment. Required that appropriate protective equipment be used at all times.

Page 86: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 4 Mini Enclosures and Glovebags

3.3 GLOVE BAGS AND BOXES

3.3.1 Complete requirements of the following:

A. Section 01562 – Respiratory Protection

3.3.2 Glovebag: Remove ACM inside a glovebag according to the following procedure:

A. Use at least two persons to perform glovebag removal operations

B. Use each glovebag only once

C. Do not move glovebag once it has been mounted in place

D. Do not use glovebag on surface whose temperatures exceed 150⁰ F

E. Check materials adjacent to locations where glovebag will be installed. Wrap damaged, loose or friable material in 2 layers of 6 mil plastic and “candy-stripe” with duct tape, or render material intact by some other method. Place one layer of duct tape around undamaged pipe at each location where the glove bag will be attached.

F. Slit top of the glove bag open (if necessary) and cut down the sides to accommodate

the size of the pipe (about two inches longer than the pipe diameter) and allow additional so that the top of the glovebag will be clear of the pipe after installation.

G. Place necessary tools into pouch located inside glove bag. This will usually include:

bone saw, utility knife, rags, scrub brush, wire cutters, tin snips, and pre-wetted cloth.

H. Place a strip of duct tape along both edges of the open top slit of glovebag for reinforcement

I. Place the glovebag around section of pipe to be worked on and staple top together

through reinforcing duct tape. Staple down sides approximately 6 inches so that top of the glovebag is clear of pipe. Seal top and sides with duct tape. Next, duct tape the ends of the glovebag to the pipe itself, where previously covered with plastic or duct tape

J. Install glovebag so that it completely covers the circumference of pipe or other

structures where the work is to be done.

K. Use smoke tube and aspirator bulb to test seal. Place tube into water sleeve (two-inch opening to glovebag) squeezing bulb and filling bag with visible smoke. Remove smoke tube and twist water sleeve closed. While holding the water sleeve tightly, gently squeeze glovebag and look for smoke leaking out (especially at the top and ends of the glove bag). If leaks are found, tape closed using duct tape and re-test.

L. Insert wand from garden sprayer through water sleeve. Duct tape water sleeve

tightly around the wand to prevent leakage.

M. Thoroughly wet material to be worked on with amended water or removal encapsulant and allow to soak in. Wet adequately to penetrate and soak material through to substrate

N. One person places their hands into the long-sleeved gloves while the second person

directs garden sprayer at the work.

Page 87: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 5 Mini Enclosures and Glovebags

O. Use bone saw, if required, to cut insulation at each end of the section to be removed.

A bone saw is a serrated heavy gauge wire with ring-type handles at each end. Throughout this process, spray amended water or removal encapsulant on the cutting area to keep dust to a minimum.

P. Remove insulation using putty knives or other tools. Place pieces in bottom of bag

without dropping.

Q. Rinse all tools with water inside the bag and place back into pouch.

R. Using scrub brush, rags and water, scrub and wipe down the exposed pipe.

S. Thoroughly wash and wipe down interior of glovebag to a point below the location where the bag will be twisted and taped to seal waste in bottom of bag

T. Remove water wand from water sleeve and attach the small nozzle from HEPA

filtered vacuum. Turn on the vacuum only briefly to collapse the bag.

U. Remove the vacuum nozzle, twist water sleeve closed and seal with duct tape

V. From outside the bag, pull the tool pouch away from the bag. Place duct tape over twisted portion and then cut the tool bag from the glovebag, cutting through the twisted/taped section. Contaminated tools may then be placed directly into next glove bag without cleaning. Alternatively, tool pouch with the tools can be placed in a bucket of water, opened underwater, and tools cleaned and dried. Discard rags and scrub brush with asbestos waste.

W. With removed insulation in the bottom of the glovebag, twist the bag several times

and tape it to seal material in the bottom during removal of the glovebag from the pipe.

X. Slip a 6 mil disposal bag over the glovebag (still attached to the pipe). Remove tape

or cut bag and open the top of the glove bag and fold it down into disposal bag.

Y. Clean all surfaces in the work area using disposable clothes wetted with water with surfactant or removal encapsulant added. When these surfaces have dried, clean with a HEPA filtered vacuum. Material adhered to a surface with removal encapsulant may require the application of additional removal encapsulant to facilitate cleaning.

Z. Remove disposable suits and place them into bag with waste.

AA. Collapse the bag with a HEPA vacuum, twist top of bag, seal with at least 3 wraps of

duct tape, bend over and seal again with at least 3 wraps of duct tape. 3.3.3 Negative Pressure Glove Bag System: Remove ACM inside a negative pressure glove

bag system according to the following procedure:

A. Use at least two persons to perform glovebag removal operations

B. Use each glovebag only once

C. Do not move glovebag once it has been mounted in place

D. Do not use glovebag on surface whose temperatures exceed 150⁰ F

Page 88: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 6 Mini Enclosures and Glovebags

E. Check materials adjacent to locations where glovebag will be installed. Wrap

damaged, loose or friable material in 2 layers of 6 mil plastic and “candy-stripe” with duct tape, or render material intact by some other method. Place one layer of duct tape around undamaged pipe at each location where the glove bag will be attached.

F. Install glovebag so that it completely covers the circumference of pipe or other

structure where the work is to be done.

G. Install device used to prevent collapse of bag by negative pressure.

H. Smoke test glovebag for leaks and seal any leaks prior to use

I. Run HEPA vacuum cleaner or other device used to create a negative pressure in the bag continuously during the operation.

J. Prior to disposal, collapse glovebag by removing air within it using a HEPA vacuum.

K. Where system uses attached waste bag, connect waste bag to collection bag using

hose or other material which will withstand pressure of ACM waste and water without losing its integrity. Use sliding value or other device to separate waste bag from hose to ensure no exposure when waste bag is disconnected.

L. Where a separate waste bag is used along with a collection bag and waste bag is

discarded after one use, the collection bag may be reused if rinsed clean with amended water before reuse.

3.3.4 Negative Pressure Glove Box Systems: Remove ACM inside a negative glove box

system according to the following procedure:

A. Use at least two persons to perform the work

B. Check materials adjacent to location where glove box will be installed. Wrap damaged, loose or friable material in 2 layers of 6 mil plastic and “candy-stripe” with duct tape, or render material intact by some other method. Place one layer of duct tape around undamaged pipe at each location where the glove box will be attached.

C. Use system in accordance with manufacturer’s instructions.

D. Smoke test box prior to each use

E. Use a HEPA Vacuum or other negative pressure generator with HEPA filtration to

create a negative pressure in system

F. Provide a back-up HEPA vacuum on site at all times during operation of the system

G. Use waste bags made of 6 mil thick plastic, double-bag before filling

3.4 MINI-ENCLOSURES

3.4.1 A mini-enclosure is a small walk-in enclosure which accommodates no more than two person. Provide a fabricated or job-made enclosure constructed of 6 mil plastic or equivalent. Place the enclosure under negative pressure by means of a HEPA filter vacuum or similar HEPA filter ventilation unit.

Page 89: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 7 Mini Enclosures and Glovebags

3.4.2 Provide a remote personnel decontamination unit meeting requirements of Section 01563 – Decontamination Units for worker decontamination.

3.4.3 Sequence of Work: Before beginning work of this sub-section, complete the following:

A. Isolation of area in accordance with Section 01527 – Regulated Areas.

B. Construction of a personnel decontamination unit in accordance with Section 01563

– Decontamination Unit.

3.4.4 Work Room: Construct work room in the same manner as a primary barrier fabricated from 6 mil sheet plastic. Arrange so that primary barrier provides both a crucial and primary barrier. Line walls and floor or work room with a continuous secondary barrier.

3.4.5 Change room: Provide an approximately 3 feet by 3 feet change room with additional

space as required for storage attached to each work room. Fabricate change room from 6 mil sheet plastic in the same manner as a primary barrier. Locate so that access to work area is through change room.

3.4.6 Step Off Area: Cover floor in front of entry to change room with one layer of 6 mil sheet

plastic. Securely anchor sheet plastic to prevent slipping.

3.4.7 Flapped Door Construction: Provide flapped door as entry to change room and entry from change room to work room. Fabricate each flapped door from overlapping contacting layers of sheet plastic. Fasten each layer on the top and one side. Each flap is to be 3 inches longer than door opening. Reinforce free side and bottom of each sheet with duct tape. Alternate sides that are fastened on each layer. Form arrows pointing to entry side from duct tape on inside and outside door.

3.4.8 Signage: At entry to change room, post an approximately 20 inch by 14 inch

manufactured caution sign displaying the following legend with letter sizes and styles of a visibility required by 29 CFR 1926:

DANGER

ASBESTOS CANCER AND LUNG DISEASE HAZARD

AUTHORIZED PERSONNEL ONLY RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED IN THIS AREA

A. Provide spacing between respective lines at least equal to the height of the

respective upper line.

3.4.9 Complete requirements of the following:

A. Section 01560 – Worker Protection

B. Section 01562 – Respiratory Protection

C. Section 01513 – Temporary Negative Pressure and Air Circulation System: HEPA filtered vacuum cleaner with vacuum in space outside mini-enclosure may be used for compliance in this section. Provide a minimum of 8 air changes per hour in the work room.

3.4.10 Testing: The mini-enclosure shall be inspected for leaks and smoke tested to detect

breaches and breaches sealed.

Page 90: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 8 Mini Enclosures and Glovebags

3.4.11 Entry to Work Room: Require that any time a worker enter the work room the following procedure is followed:

A. Outside of change room, remove all street clothes and don clean coveralls and

respirator. A swimsuit and second disposal suit may be worn beneath outer coveralls.

B. Enter change room, be sure that entry is completely closed.

C. Enter work room, be sure that entry is completely closed. 3.4.12 Work Procedures: Arrange work area within the mini-enclosure so that during use, air

movement is directed away from the worker’s breathing zone.

3.4.13 Worker Decontamination: Require that any time a worker leaves the mini-enclosure the following procedure be followed:

A. Maintain a bucket of clean potable water in the work area. Do not amend with a

wetting agent.

B. Remove contaminated suit inside the work area. Leave respirator in place.

C. Wash hands, face, and surface of respirator with water and wet paper towels. Use caution to avoid breaking seal between respirator face-piece and face.

D. Proceed with respirator in place to change room.

E. Be sure that entry to work area is completely closed

F. In change room, don clean disposable suit leaving respirator in place.

G. Exit change room. Be sure that entry to change room is completely closed. Proceed

to next mini-enclosure of a remote shower.

H. At end of work day, decontaminate fully in accordance with procedures in Section 01560 – Worker Protection.

3.4.14 Material Decontamination: Require that the following procedure by used in removing

equipment and bagged debris from the work room:

A. Three workers are required. One in the work room, one in the change room, and one on the step off area.

B. Equipment and bagged debris are to be removed from the mini-enclosure in separate operations

C. Worker in work room cleans equipment and bagged debris and hands one piece of

equipment or one bag of debris at a time to worker in change room.

D. Worker in change room wet cleans each piece of equipment or bag and stores them in change room. Equipment is sealed completely in 6 mil sheet plastic in change room.

E. When the amount of stored materials in the change room becomes large enough that

the worker cannot clean incoming material without contacting previously cleaned material, the door between the work and clean room is closed.

Page 91: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01529 01529 - 9 Mini Enclosures and Glovebags

F. The worker in the change room then passes each item into a new disposal bag held

open in the doorway between the changing room and step off area by the worker on the step off area. The worker on the step off area places each bag in a sealed cart for transport to the load out area. No bags are to be stored outside of the mini-enclosure.

3.4.15 Mini-Enclosure Decontamination: At completion of all work decontaminate the work and

changing rooms as set forth in Section 01711 – Project Decontamination for non-friable materials.

END OF SECTION 01529

Page 92: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01560 01560 - 1 Worker Protection

SECTION 01560 – WORKER PROTECTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.2 DESCRIPTION OF WORK

1.2.1 This section describes the equipment and procedures required for protecting workers against asbestos contamination and other workplace hazards except for respiratory protection.

1.3 RELATED WORK SPECIFIED ELSEWHERE

1.3.1 Respiratory Protection is specified in Section 01562. 1.4 WORKER TRAINING

1.4.1 AHERA Accreditation: All workers are to be accredited as Abatement Workers or Abatement Supervisors as required by the Asbestos Model Accreditation Plan, 40 CFR 763 Appendix C to Subpart E.

1.4.2 State and Local License: All workers are to be licensed as Asbestos Hazard Abatement

Workers or Asbestos Hazard Abatement Specialists as required by the Ohio Department of Health (ODH) regulations regarding asbestos, found in the Ohio Administration Code, Final rule 3701-34.

1.4.3 Training: In accordance with OSHA 29 CFR 1926.1101 and any applicable state and

local regulations, all workers shall be trained in the dangers inherent in handling asbestos and breathing asbestos dust and in proper work procedures and personal and area protective measures.

1.5 MEDICAL SURVEILLANCE

1.5.1 Provide medical surveillance for all workers who may encounter an airborne fiber level of 0.1 f/cc or greater for an 8 hour Time Weighted Average. In the absence of specific airborne fiber data provide medical examinations for all workers who will enter the Work Area for any reason. Examination shall as a minimum meet OSHA requirements as set forth in 29 CFR 1926.1101. In addition, provide an evaluation of the individual's ability to work in environments capable of producing heat stress in the worker.

1.5.2 Provide a medical surveillance program and physician’s written opinion before a

respirator is assigned as required by OSH 29 CFR 1910.134 and 29 CFR 1926.103(e)(10).

1.6 SUBMITTALS

1.6.1 Before Start of Work: Submit the following to the Construction Manager for review. Provide a copy of submittals to the Consultant. Do not start work until these submittals are returned with Construction Manager’s approval indicating that the submittal is returned for unrestricted use.

Page 93: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01560 01560 - 2 Worker Protection

1.6.2 AHERA Accreditation: Submit copies of certificates from an EPA-approved Asbestos Abatement Worker or Asbestos Abatement Supervisor course for each worker as evidence that each asbestos abatement worker is accredited as required by EPA 40 CFR 763 Appendix C to Subpart E.

1.6.3 State and Local License: Submit evidence that all workers have been licensed by the

Ohio Department of Health as an Asbestos Hazard Abatement Worker of Asbestos Hazard Abatement Specialist.

1.6.4 Certificate Worker Acknowledgement: Submit an original signed copy of the Certificate of

Worker's Acknowledgement found in Appendix C, for each worker who is to be at the job site or enter the Work Area.

1.6.5 Report from Medical Examination: conducted within last 12 months as part of

compliance with OSHA medical surveillance requirements for each worker who is to enter the Work Area. Submit, at a minimum, for each worker the following:

A. Name and Social Security Number

B. Physician's Written Opinion from examining physician including at a minimum the

following:

a. Whether worker has any detected medical conditions that would place the worker at an increased risk of material health impairment from exposure to asbestos.

b. Any recommended limitations on the worker or on the use of personal protective equipment such as respirators.

c. Statement that the worker has been informed by the physician of the results of the medical examination and of any medical conditions that may result from asbestos exposure.

C. Statement that worker is able to wear and use the type of respiratory protection

proposed for the project, and is able to work safely in an environment capable of producing heat stress in the worker.

1.6.6 Notarized Certifications: Submit certification signed by an officer of the abatement

contracting firm and notarized that exposure measurements, medical surveillance, and worker training records are being kept in conformance with OSHA 29 CFR 1926.1101.

PART 2 - EQUIPMENT 2.1 PROTECTIVE CLOTHING

2.1.1 General: Provide and require the use of protective clothing, such as coveralls or similar whole-body clothing, head coverings, gloves, and foot coverings for any employee exposed to airborne concentrations of asbestos that exceed the TSA and/or excursion limit prescribed in OSHA 29 CFR 1926.1101 or for which a required negative exposure assessment is not produced, and for any employee performing OSHA Class I operations which involve the removal of over 25 linear or 10 square feet of TSI or surfacing ACM.

2.1.2 Coveralls: Provide disposable full-body coveralls and disposable head covers, and

require that they be worn by all workers in the Work Area. Provide a sufficient number for all required changes, for all workers in the Work Area.

2.1.3 Cold Weather Gear: Provide each worker with an insulated jacket, pants, gloves, and

hat. Require that cold weather gear be removed in Equipment Room of Personnel

Page 94: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01560 01560 - 3 Worker Protection

Decontamination Unit. Dispose of cold weather gear as asbestos waste at completion of all work.

2.1.4 Boots: Provide work boots with non-skid soles and, where required by OSHA, foot

protection for all workers. Provide boots at no cost to workers. Do not allow boots to be removed from the Work Area for any reason, after being contaminated with asbestos-containing material. Dispose of boots which have not been decontaminated as asbestos-contaminated waste at the end of the work.

2.1.5 Hard Hats: Provide head protection (hard hats) as required by OSHA for all workers, and

provide four spares for use by authorized visitors. Label hats with same warning labels as used on disposal bags. Require hard hats to be worn at all times that work is in progress that may potentially cause head injury. Provide hard hats of type with plastic strap type suspension. Require hats to remain in the Work Area throughout the work. Thoroughly clean, decontaminate and bag hats before removing them from Work Area at the end of the work.

2.1.6 Goggles: Provide eye protection (goggles) as required by OSHA for all workers involved

in scraping, spraying, or any other activity which may potentially cause eye injury. Thoroughly clean, decontaminate and bag goggles before removing them from Work Area at the end of the work.

2.1.7 Gloves: Provide work gloves to all workers and require that they be worn at all times in

the Work Area. Do not remove gloves from Work Area and dispose of as asbestos-contaminated waste at the end of the work.

2.2 ADDITIONAL PROTECTIVE EQUIPMENT

2.2.1 Disposable coveralls, head covers, and footwear covers shall be provided by the Contractor for authorized visitors who may inspect the job site.

PART 3 - EXECUTION 3.1 GENERAL

3.1.1 Provide worker protection as required by the most stringent OSHA and EPA standards applicable to the work. The following procedures are minimums to be adhered to regardless of fiber count in the Work Area.

3.1.2 Each time Work Area is entered remove all street clothes in the Clean Room of the

Personnel Decontamination Unit and put on new disposable coverall, or reusable coverall (to be donned in Equipment Room), new head cover, and a clean respirator. Proceed through shower room to equipment room and put on work boots.

3.2 DECONTAMINATION PROCEDURES

3.2.1 Require all workers to adhere to the following personal decontamination procedures whenever they leave the Work Area:

3.2.2 When using Type C Supplied Air or Powered Air-Purifying Respirators: Require that all

workers use the following decontamination procedure as a minimum requirement whenever leaving the Work Area:

A. When exiting area, remove coveralls, disposable head covers, and disposable

footwear covers or boots in the Equipment Room.

Page 95: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01560 01560 - 4 Worker Protection

B. Still wearing respirators, proceed to showers. Showering is mandatory. Care must be taken to follow reasonable procedures in removing the respirator to avoid asbestos fibers while showering. The following procedure is required as a minimum:

C. Thoroughly wet body including hair and face. If using a Powered Air-Purifying

Respirator (PAPR) hold blower unit above head to keep canisters dry.

D. With respirator still in place thoroughly wash body, hair, respirator face piece, and all parts of the respirator except the blower unit and battery pack on a PAPR. Pay particular attention to seal between face and respirator and under straps.

E. Take a deep breath, hold it and/or exhale slowly, completely wet hair, face, and

respirator. While still holding breath, remove respirator and hold it away from face before starting to breath.

F. Carefully wash facepiece of respirator inside and out.

3.2.3 If using PAPR, shut down in the following sequence: first cap inlets to filter cartridges and

turn off blower unit (this sequence will help keep debris which has collected on the inlet side of filter from dislodging and contaminating the outside of the unit). Thoroughly wash blower unit and hoses. Carefully wash battery pack with wet rag. Be extremely cautious of getting water in battery pack as this will short out and destroy battery.

A. Shower completely with soap and water.

B. Rinse thoroughly.

C. Rinse shower room walls and floor prior to exit.

D. Proceed from shower to Clean Room and change into street clothes or into new

disposable work items.

3.2.4 When using Air Purifying-Negative Pressure Respirators: Require that all workers use the following decontamination procedure as a minimum requirement whenever leaving the Work Area with a half or full face cartridge type respirator:

A. When exiting area, remove coveralls, disposable headcovers, and disposable

footwear covers or boots in the Equipment Room.

B. Still wearing respirators, proceed to showers. Showering is mandatory. Care must be taken to follow reasonable procedures in removing the respirator and filters to avoid asbestos fibers while showering. The following procedure is required as a minimum:

C. Thoroughly wet body from neck down.

D. Wet hair as thoroughly as possible without wetting the respirator filter if using an air

purifying type respirator.

E. Take a deep breath, hold it and/or exhale slowly, complete wetting of hair, thoroughly wetting face, respirator and filter (air purifying respirator). While still holding breath, remove respirator and hold it away from face before starting to breath.

F. Dispose of wet filters from air purifying respirator.

G. Carefully wash facepiece of respirator inside and out.

Page 96: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01560 01560 - 5 Worker Protection

H. Shower completely with soap and water.

I. Rinse thoroughly.

J. Rinse shower room walls and floor prior to exit.

K. Proceed from shower to Clean Room and change into street clothes or into new

disposable work items. 3.2.5 Remote Shower: If the decontamination facility is used as a remote shower, the

procedures above are to be used. If a worker cannot gain direct access to the Equipment Room, require that he enter Decontamination Unit and proceed directly through Shower Room to Equipment Room. Decontamination procedure is then completed as required above.

3.2.6 Within Work Area

A. Require that workers NOT eat, drink, smoke, chew tobacco or gum, or apply

cosmetics in the Work Area. To eat, chew, drink or smoke, workers shall follow the procedure described above, then dress in street clothes before entering the non-Work Areas of the building.

3.3 CERTIFICATE OF WORKER'S ACKNOWLEDGEMENT

3.3.1 Certificate of Worker Training form can be found in Appendices. After each worker has been included in the Contractor's Respiratory Protection Program, completed the training program and medical examination, secure a fully executed copy of this form.

END OF SECTION - 01560

Page 97: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01562 01562 - 1 Respiratory Protection

SECTION 01562 – RESPIRATORY PROTECTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.2 DESCRIPTION OF WORK

1.2.1 Instruct and train each worker involved in asbestos abatement or maintenance and repair of friable ACM in proper respiratory use and require that each worker always wear a respirator, properly fitted on the face, in the Work Area from the start of any operation which may cause airborne asbestos fibers until the Work Area is completely decontaminated. Use respiratory protection appropriate for the fiber level encountered in the work place or as required for other toxic or oxygen-deficient situations encountered.

1.3 DEFINITIONS

1.3.1 Negative Pressure Respirator: A respirator in which the air pressure inside the respiratory-inlet covering is positive during exhalation in relation to the air pressure of the outside atmosphere and negative during inhalation in relation to the air pressure of the outside atmosphere.

1.3.2 Protection Factor: The ratio of the ambient concentration of an airborne substance to the

concentration of the substance inside the respirator at the breathing zone of the wearer. The protection factor is a measure of the degree of protection provided b y a respirator to the wearer.

1.3.3 Respirator: A device designed to protect the wearer from the inhalation of harmful

atmospheres. 1.4 STANDARDS

1.4.1 Except to the extent that more stringent requirements are written directly into the Contract Documents, the following regulations and standards have the same force and effect (and are made a part of the Contract Documents by reference) as if copied directly into the Contract Documents, or as if published copies were bound herewith. Where there is a conflict in requirements set forth in these regulations and standards, meet the more stringent requirement.

A. OSHA - U.S. Department of Labor Occupational Safety and Health Administration,

Safety and Health Standards 29 CFR 1910.1001, 1910.134. and 1926.1101.

B. CGA - Compressed Gas Association, Inc., New York, Pamphlet G-7, "Compressed Air for Human Respiration", and Specification G-7.1 "Commodity Specification for Air"

C. ANSI - American National Standard Practices for Respiratory Protection, ANSI Z88.2-

1980

D. NIOSH - National Institute for Occupational Safety and Health

E. MSHA - Mine Safety and Health Administration

Page 98: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01562 01562 - 2 Respiratory Protection

1.5 SUBMITTALS

1.5.1 Before Start of Work submit the following to the Construction Manager for review. Provide a copy of submittals to the Consultant. Do not begin work until these submittals are returned with the Construction Manager’s approval indicating that the submittal is returned for unrestricted use.

A. Product Data: Submit manufacturer's product information for each component used,

including NIOSH and/or MSHA Certifications for each component in an assembly and/or for entire assembly.

B. System Diagram: When a Type "C" supplied air respiratory system is required by the

work, submit drawing showing assembly of components into a complete supplied air respiratory system. Include diagram showing location of compressor, filter banks, backup air supply tanks, hose line connections in Work Area(s), routing of air lines to Work Area(s) from compressor.

C. Operating Instruction: Submit complete operating and maintenance instructions for all

components and systems as a whole. Submittal is to be in bound manual form suitable for field use.

D. Respiratory Protection Program: Submit Contractor's written respiratory protection

program manual as required by OSHA 1926.1101.

E. Initial Exposure Assessment: Submit level of respiratory protection intended for each operation required by the project. Base this selection on an initial Exposure Assessment as required by OSHA 29 CFR 1926.1101. Submit information to support this Initial Exposure Assessment on the form included in Appendix D.

a. Submit data from exposure monitoring for the PEL and EL from prior asbestos

abatement projects within the last 12 months b. Submit monitoring and analysis that were performed in compliance with the OSHA

asbestos standard in effect c. Submit data that was obtained under workplace conditions closely resembling

those that will exist during the Work d. Submit data from previous asbestos abatement projects where the type of

asbestos abatement and other work, material, control methods, work practices, and environmental conditions closely resemble those that will exist during the Work

e. Submit exposure data from prior asbestos abatement projects where the work that was conducted by employees whose training and experience are not more extensive than that of employees performing the current job

f. Based on the exposure data from the previous asbestos abatement projects, select respiratory protection for the Work that will, to a high degree of certainty, prevent worker exposures (inside the respirator) that exceed the PEL set forth in this Section of the Asbestos Abatement Project Manual.

F. Resume information: Submit resume and information on training for individual

monitoring the operation of supplied air respiratory systems. Submit training certifications where applicable.

1.6 AIR QUALITY FOR SUPPLIED AIR RESPIRATORY SYSTEMS

1.6.1 Provide air used for breathing in Type "C" supplied air respiratory systems that meets or exceeds standards set for C.G.A. type 1 (Gaseous Air) Grade D.

Page 99: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01562 01562 - 3 Respiratory Protection

1.7 DELIVERY

1.7.1 Deliver replacement parts not otherwise labeled by NIOSH and/or MSHA to job site in manufacturer's containers.

PART 2 - EQUIPMENT 2.1 AIR PURIFYING RESPIRATORS

2.1.1 Respirator Bodies: Provide half face or full face type respirators. Equip full face respirators with a nose cup or other anti-fogging device as would be appropriate for use in air temperatures less than 32 degrees Fahrenheit.

2.1.2 Filter Cartridges: Provide, at a minimum, HEPA type filters labeled with NIOSH and

MSHA Certification for "Radionuclides, Radon Daughters, Dust, Fumes, Mists including Asbestos-Containing Dusts and Mists" and color coded in accordance with ANSI Z228.2 (1980). In addition, a chemical cartridge section may be added, if required, for solvents, etc., in use. In this case, provide cartridges that have each section of the combination canister labeled with the appropriate color code and NIOSH and/or MSHA Certification.

2.1.3 Non-permitted respirators: Do not use single use, disposable or quarter face respirators.

2.2 SUPPLIED AIR RESPIRATOR SYSTEMS

2.2.1 Provide equipment capable of producing air of the quality and volume required by the above referenced standards applied to the job site conditions and crew size. Comply with provisions of this section if more stringent than the governing standard.

2.2.2 Face Piece and Hose: Provide full face piece and hose by same manufacturer that has

been certified by NIOSH and/or MSHA as an approved Type "C" respirator assembly operating in pressure demand mode with a positive pressure face-piece.

2.2.3 Auxiliary backup system: In atmospheres which contain sufficient oxygen (greater than

or equal to 19.5% oxygen) provide a pressure-demand full face piece supplied air respirator equipped with an emergency backup HEPA filter.

2.2.4 Escape air supply: In atmospheres which are oxygen deficient (less than 19.5% oxygen)

provide a pressure-demand full face piece supplied air respirator incorporating an auxiliary self-contained breathing apparatus (SCBA) which automatically maintains an uninterrupted air supply in pressure demand mode with a positive pressure face piece.

2.2.5 Backup air supply: Provide a reservoir of compressed air located outside the Work Area which will automatically maintain a continuous uninterruptable source of air automatically available to each connected face piece and hose assembly in the event of compressor shut-down, contamination of air delivered by compressor, power loss or other failure. Provide sufficient capacity in the back-up air supply to allow a minimum escape time of one-half hour times the number of connections available to the Work Area. Air requirement at each connection is the air requirement of the respirators in use plus the air requirement of an average-sized adult male engaged in moderately strenuous activity.

2.2.6 Warning device: Provide a warning device that will operate independently of the

building's power supply. Locate so that alarm is clearly audible above the noise level produced by equipment and work procedures in use in all parts of the Work Area and at the compressor. Connect alarm to warn of:

A. Compressor shut down or other fault requiring use of backup air supply

Page 100: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01562 01562 - 4 Respiratory Protection

B. Carbon Monoxide (CO) levels in excess of 5 PPM

2.2.7 Carbon Monoxide (CO) Monitor: Continuously monitor and record on a strip chart

recorder Carbon Monoxide (CO) levels. Place monitors in the airline between compressor and back-up air supply and between backup air supply and workers. Connect monitors so that they also sound an alarm as specified under "Warning Devices".

2.2.8 Compressor Shut Down: Interconnect monitors, alarms and compressor so that

compressor is automatically shut down and the alarms sounded if any of the following occur:

A. Carbon Monoxide (CO) concentrations exceed 5 PPM in the air line between the filter

bank and backup air supply

B. Compressor temperature exceeds normal operating range

2.2.9 Compressor Motor - Provide a compressor driven by an electric motor. Do not use a gas or diesel engines to drive compressor. Insure that electrical supply available at the work site is adequate to energize motor.

2.2.10 Compressor Location: Locate compressor outside of building in location that will not

impede access to the building, and that will not cause a nuisance by virtue of noise or fumes to occupied portions of the building.

2.2.11 Air Intake: Locate air intake remotely from any source of automobile exhaust or any

exhaust from engines, motors, auxiliary generator or buildings.

2.2.12 After-Cooler: Provide an after-cooler at entry to filter system which is capable of reducing temperatures to outside ambient air temperatures.

2.2.13 Self Contained Breathing Apparatus (SCBA): Configure system to permit the recharging

of 1/2 hour 2260 PSI SCBA cylinders. PART 3 - EXECUTION 3.1 GENERAL

3.1.1 Respiratory Protection Program: Comply with ANSI Z88.2 - 1980 "Practices for Respiratory Protection" and OSHA 29 CFR 1910 and 1926.

3.1.2 Require that respiratory protection be used at all times that there is any possibility of

disturbance of asbestos-containing materials whether intentional or accidental.

3.1.3 Require that a respirator be worn by anyone in a Work Area at all times, regardless of activity, during a period that starts with any operation which could cause airborne fibers until the area has been cleared for re-occupancy in accordance with Section 01714.

3.1.4 Regardless of Airborne Fiber Levels: Require that the minimum level of respiratory

protection used be half-face air-purifying respirators with high efficiency filters.

3.1.5 Do not allow the use of single-use, disposable, or quarter-face respirators for any purpose.

Page 101: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01562 01562 - 5 Respiratory Protection

3.2 FIT TESTING

3.2.1 Initial Fitting: Provide initial fitting of respiratory protection during a respiratory protection course of training. Fit types of respirator to be actually worn by each individual. Allow an individual to use only those respirators for which training and fit testing have been provided.

3.2.2 On a Weekly Basis, check the fit of each worker's respirator by having irritant smoke

blown onto the respirator from a smoke tube.

3.2.3 Upon Each Wearing: Require that each time an air-purifying respirator is put on it be checked for fit with a positive and negative pressure fit test in accordance with the manufacturer's instructions or ANSI Z88.2 (1980).

3.3 TYPE OF RESPIRATORY PROTECTION REQUIRED

3.3.1 Provide Respiratory Protection as indicated in paragraph below. Higher levels of protection may be provided as desired by Contractor, or as directed by Construction Manager. Where paragraph below does not apply, determine the proper level of protection by dividing the expected or actual airborne fiber count in the Work Area by the "protection factors" given below. The level of respiratory protection which supplies an airborne fiber level inside the respirator, at the breathing zone of the wearer, at or below 0.01 f/cc is the minimum level of protection allowed.

3.3.2 Use the following unless air monitoring results indicate greater protection is necessary.

Refer to Protection Factors table for choice of respirators.

A. Loose equipment cleaning prior to removal in uncontaminated area: Half-face dual cartridge-type respirator.

B. Plastic installation which does not disturb asbestos-containing material: Half-face dual cartridge-type respirator.

C. Removing or cleaning items or plastic installation when such operation may disturb

asbestos-containing material: Powered air purifying respirator (PAPR).

D. Asbestos-containing material removal: Powered air purifying respirator

E. Gross cleanup of removal area(s): Powered air purifying respirator (PAPR).

F. Installation of encapsulant after air sampling results indicate 0.01 or less f/cc and before plastic removal: powered air purifying respirators.

G. Final wet-cleaning of walls until final air tests show exposure in work areas to be below

0.01 f/cc: powered air purifying respirators.

H. Loading and unloading drums on truck (outside work area): Half-face cartridge respirators.

I. Glove bag and modified glove bag removal: Powered air purifying respirator (PAPR).

J. Vinyl-asbestos floor tile, floor tile mastic, ceiling tile, cement-asbestos board removal:

Powered air purifying respirator (PAPR).

K. Built-up roofing and roof flashing removal: Half-face dual cartridge respirators.

Page 102: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01562 01562 - 6 Respiratory Protection

L. Disposal at landfill: Half-face dual cartridge respirator.

3.3.3 Fibers: For purposes of this section fibers are defined as all fibers regardless of composition as counted in the OSHA Reference Method (ORM), NIOSH Method 7400 procedure, or asbestos fibers of any size as counted using either a scanning or transmission electron microscope.

PROTECTION FACTORS

RESPIRATOR TYPE PROTECTION FACTOR

Air purifying respirator Negative pressure respirator High efficiency filter Half facepiece

10

Air purifying respirator Negative pressure respirator High efficiency filter Full facepiece

50

Powered-air purifying respirator (PAPR) Positive pressure respirator High efficiency filter Half facepiece

50

Powered air-purifying respirator (PAPR) Continuous flow High efficiency filter Full facepiece

100

Type C supplied air: Positive pressure respirator Pressure demand Full facepiece

1,000

Type C supplied air: Positive pressure respirator, pressure demand Full facepiece Equipped with an auxiliary positive pressure Self-Contained Breathing Apparatus (SCBA)

1,000

3.4 AIR PURIFYING RESPIRATORS

3.4.1 Negative pressure - half or full face mask: Supply a sufficient quantity of respirator filters approved for asbestos, so that workers can change filters during the work day. Require that respirators be wet-rinsed, and filters discarded, each time a worker leaves the Work Area. Require that new filters be installed each time a worker re-enters the Work Area. Store respirators and filters at the job site in the changing room and protect totally from exposure to asbestos prior to their use.

3.4.2 Powered air purifying - half or full face mask: Supply a sufficient quantity of high

efficiency respirator filters approved for asbestos so that workers can change filters at any time that flow through the face piece decreases to the level at which the manufacturer recommends filter replacement. Require that regardless of flow, filter cartridges be replaced after 40 hours of use. Require that HEPA elements in filter cartridges be protected from wetting during showering. Require entire exterior housing of respirator, including blower unit, filter cartridges, hoses, battery pack, face mask, belt, and cords, be washed each time a worker leaves the Work Area. Caution should be

Page 103: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01562 01562 - 7 Respiratory Protection

used to avoid shorting battery pack during washing. Provide an extra battery pack for each respirator so that one can be charging while one is in use.

3.5 TYPE "C" SUPPLIED AIR RESPIRATOR

3.5.1 Air Systems Monitor: Continuously monitor the air system operation including compressor operation, filter system operation, backup air capacity and all warning and monitoring devices at all times that system is in operation. Assign an individual, trained by manufacturer of the equipment in use or by a Certified Industrial Hygienist, in the operation and maintenance of the system to provide this monitoring. Assign no other duties to this individual which will take him away from monitoring the air system.

END OF SECTION - 01562

Page 104: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 1 Decontamination Units

SECTION 01563 - DECONTAMINATION UNITS PART 1 - GENERAL 1.1 DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.2 DESCRIPTION OF WORK

1.2.1 Provide separate Personnel and Equipment Decontamination facilities. Require that the Personnel Decontamination Unit be the only means of ingress and egress for the Work Area. Require that all materials exit the Work Area through the Equipment Decontamination Unit.

1.3 RELATED WORK SPECIFIED ELSEWHERE

1.3.1 Section 01503 Temporary Facilities - Asbestos Abatement for electrical requirements and requirements relative to connection of decontamination facilities to building systems such as water, sewer, and electrical.

1.3.2 Section 01526 Temporary Enclosures - Isolation of the Work Area

1.3.3 Section 01092 Codes and Regulations - Warning Signs

1.3.4 Section 01301 Submittals - Submittals

1.4 SUBMITTALS

1.4.1 Before the Start of Work: Submit the following to the Construction Manager for review. Provide a copy of submittals to the Consultant. Do not begin work until these submittals are returned with Construction Manager’s approval indicating that the submittal is returned for unrestricted use or final-but-restricted use.

A. Personnel Decontamination Unit: Provide sketch showing location.

B. Equipment Decontamination Unit: Provide sketch showing location

C. Filters: Provide product data.

PART 2 - PRODUCTS 2.1 POLYETHYLENE SHEET

2.1.1 Provide a single polyethylene film in the largest sheet size possible to minimize seams, 6

mils thick as indicated, clear, frosted, or black as indicated.

2.1.2 Provide flame resistant polyethylene film that conforms to requirements set forth by the National Fire Protection Association Standard 701, Small Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mils thick as indicated, frosted or black as indicated.

2.2 REINFORCED POLYETHYLENE SHEET

Page 105: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 2 Decontamination Units

2.2.1 Where plastic sheet is the only separation between the Work Area and building exterior, provide translucent, nylon reinforced, laminated, flame resistant, polyethylene film that conforms to requirements set forth by the National Fire Protection Association Standard 701, Small Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mil thick as indicated, frosted or black as indicated.

2.3 DUCT TAPE

2.3.1 Provide duct tape in 2" or 3" widths as indicated, with an adhesive which is formulated to stick aggressively to sheet polyethylene.

2.4 SPRAY ADHESIVE

2.4.1 Provide spray adhesive in aerosol cans which is specifically formulated to stick tenaciously to sheet polyethylene.

2.5 SHOWER PAN

2.5.1 Provide one piece waterproof shower pan of appropriate size. Fabricate from seamless fiberglass minimum 1/16" thick reinforced with wood, 18 ga. stainless or galvanized steel with welded seems, copper or lead with soldered seams, or a seamless liner of minimum 60 mil thick elastomeric membrane.

2.6 SHOWER WALLS

2.6.1 Provide 8' long by approximately 7' high walls fabricated from rigid, impervious, waterproof material, either corrugated fiberglass roofing or equivalent. Structurally support as necessary for stability.

2.7 SHOWER HEAD AND CONTROLS

2.7.1 Provide a factory-made shower head producing a spray of water which can be adjusted for spray size and intensity. Feed shower with water mixed from hot and cold supply lines. Arrange so that control of water temperature, flow rate, and shut off is from inside shower without outside aid.

2.8 FILTERS

2.8.1 Provide cascaded filter units on drain lines from showers or any other water source carrying asbestos-contaminated water from the Work Area. Provide units with disposable filter elements as indicated below. Connect so that discharged water passes primary filter and output of primary filter passes through secondary filter.

2.8.2 Primary Filter - Passes particles 20 microns and smaller

2.8.3 Secondary Filter - Passes particles 5 microns and smaller

2.8.4 Provide spare filters for both personnel and equipment decontamination unit water filters.

2.9 HOSE BIB

2.9.1 Provide heavy bronze angle type with wheel handle, vacuum breaker, and 3/4" National Standard male hose outlet.

2.10 SHOWER STALL

Page 106: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 3 Decontamination Units

2.10.1 For Wash Down Station provide leak tight shower enclosure with integrated drain pan fabricated from fiberglass or other durable waterproof material, approximately 3' x 3' square with minimum 6' high sides and back. Structurally support as necessary for stability. Equip with hose bib, as specified in this section, mounted at approximately 4'-0" above drain pan. Connect drain to a reservoir, pump water from reservoir through filters to a drain. Mount filters inside shower stall on back wall beneath hose bib.

2.11 ELASTOMERIC MEMBRANE

2.11.1 Provide uniform flat sheets of flexible sheet roofing material fabricated from EPDM (ethylene propylene diene monomers) or Neoprene (polychloroprene), in a nominal 45 mil thickness.

2.12 LUMBER

2.12.1 Provide kiln dried lumber of any grade or species. 2.13 SUMP PUMP

2.13.1 Provide totally submersible waterproof sump pump with integral float switch. Provide unit sized to pump 2 times the flow capacity of all showers or hoses supplying water to the sump, through the filters specified herein when they are loaded to the extent that replacement is required. Provide unit capable of pumping debris, sand, plaster or other materials washed off during decontamination procedures without damage to mechanism of pump. Adjust float switch so that a minimum of 3" remains between top of liquid and top of sump pan.

2.14 HOLDING TANK

2.14.1 Provide holding tank for waste water to prevent water from backing up in shower or wash room.

2.15 GROUND FAULT CIRCUIT INTERRUPTER

2.15.1 To be installed on all electrical equipment, including cords, used in the decontamination units.

PART 3 - EXECUTION 3.1 PERSONNEL DECONTAMINATION UNIT

3.1.1 Provide a Personnel Decontamination Unit outside the work area consisting of a serial arrangement of connected rooms or spaces, Clean Room, Shower Room, Equipment Room. Require all persons without exception to pass through this Decontamination Unit for entry into and exiting from the Work Area for any purpose. Do not allow parallel routes for entry or exit. Do not remove equipment or materials through Personnel Decontamination Unit. Provide adequate temporary lighting and heat within Decontamination Units.

3.1.2 Clean Room (changing room): Provide a room that is physically and visually separated

from the rest of the building for the purpose of changing into protective clothing.

A. Construct using polyethylene sheeting, at least 6 mil in thickness, to provide an airtight seal between the Clean Room and the rest of the building.

B. Locate so that access to Work Area from Clean Room is through Shower Room.

Page 107: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 4 Decontamination Units

C. Separate Clean Room from the building by a sheet plastic flapped doorway.

D. Require workers to remove all street clothes in this room, dress in protective coveralls,

and don respiratory protection equipment. Do not allow asbestos-contaminated items to enter this room. Require Workers to enter this room either from outside the structure dressed in street clothes, or naked from the showers.

E. An existing room may be utilized as the Clean Room if it is suitably located and of a

configuration whereby workers may enter the Clean Room directly from the Shower Room. Protect all surfaces of room with sheet plastic as set forth in Section 01526 - Temporary Enclosures. Authorization for this must be obtained from the Owner's Representative in writing prior to start of construction. Submit written request in accordance with Section 01632 - Product Substitutions detailing layout and protective measures proposed.

F. Maintain floor of changing room dry and clean at all times. Do not allow overflow water

from shower to wet floor in changing room.

G. Damp wipe all surfaces twice after each shift change with a disinfectant solution.

H. Provide posted information for all emergency phone numbers and procedures.

I. Provide a continuously adequate supply of disposable bath towels.

J. Provide 1 storage locker per employee. Equip room with benches and shelves and clean protective clothing, replacement filters for respirators, towels and other required protective equipment.

K. Provide a lockable door which may be secured during non-work hours.

L. Provide all other components indicated on the contract drawings.

3.1.3 Shower Room: Provide a completely watertight operational shower to be used for transit

by cleanly dressed workers heading for the Work Area from the Clean Room, or for showering by workers headed out of the Work Area after undressing in the Equipment Room.

A. Construct room by providing a shower pan and 2 shower walls in a configuration that

will cause water running down walls to drip into pan. Install a freely draining wooden floor in shower pan at elevation of top of pan.

B. Separate this room from the rest of the building with airtight walls fabricated of 6 mil polyethylene.

C. Separate this room from the Clean Room and Equipment Room with airtight walls

fabricated of 6 mil polyethylene.

D. Provide splashproof entrances.

E. Provide shower head and controls.

F. Provide temporary extensions of existing hot and cold water and drainage, as necessary for a complete and operable shower.

Page 108: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 5 Decontamination Units

G. Provide a soap dish and a continuously adequate supply of soap and maintain in sanitary condition. Provide liquid shampoo.

H. Arrange so that water from showering does not splash into the Clean or Equipment

Rooms.

I. Arrange water shut off and drain pump operation controls so that a single individual can shower without assistance from either inside or outside of the Work Area.

J. Pump waste water to drain. Provide 20 micron and 5 micron waste water filters in line

to drain or waste water storage. Change filters daily or more often if necessary. Locate filters inside shower unit so that water lost during filter changes is caught by shower pan.

K. Provide hose bib.

3.1.4 Equipment Room (contaminated area): Require work equipment, footwear and additional

contaminated work clothing to be left here. This is a change and transit area for workers.

A. Separate this room from the Work Area by a 6 mil polyethylene flapped doorway.

B. Separate this room from the rest of the building with airtight walls fabricated of 6 mil polyethylene.

C. Separate this room from the Shower Room and Work Area with airtight walls fabricated

of 6 mil polyethylene.

D. Provide a container for collection of used protective clothing.

3.1.5 Work Area: Separate Work Area from the Equipment Room by polyethylene barriers. If the airborne asbestos level in the Work Area is expected to be high, as in dry removal, add an intermediate cleaning space between the Equipment Room and the Work Area. Damp wipe clean all surfaces after each shift change.

3.1.6 Decontamination Sequence: Require that all workers adhere to the following sequence

when entering or leaving the Work Area.

A. Entering Work Area: Worker enters Clean Room and removes street clothing, puts on protective overalls and respirator, and passes through the Shower Room into the Equipment Room. a. Any additional clothing and equipment left in Equipment Room needed by the

worker are put on in the Equipment Room.

b. Worker proceeds to Work Area.

B. Exiting Work Area

a. Before leaving the Work Area, require the worker to remove all gross contamination and debris from overalls and feet.

b. The worker then proceeds to the Equipment Room and removes all clothing except respiratory protection equipment.

c. Extra work clothing such as boots, hard hats, goggles, gloves are to be stored in contaminated end of the Equipment Room.

d. Disposable coveralls are placed in a bag for disposal with other material.

Page 109: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 6 Decontamination Units

e. Require that Decontamination procedures found in Section 01560 be followed by all individuals leaving the Work Area.

f. After showering, the worker moves to the Clean Room and dresses in either new coveralls for another entry or street clothes if leaving.

3.2 EQUIPMENT DECONTAMINATION UNIT

3.2.1 Provide an Equipment Decontamination Unit consisting of a serial arrangement of rooms, Clean Room, Holding Room, Wash Room for removal of equipment and material from Work Area. Do not allow personnel to enter or exit Work Area through Equipment Decontamination Unit.

3.2.2 Wash Down Station: Provide an enclosed Shower Unit located in Work Area just outside

Wash Room as an equipment, bag and container cleaning station.

3.2.3 Wash Room: Provide wash room for cleaning of bagged or containerized asbestos-containing waste materials passed from the Work Area.

A. Construct wash room of wood framing of appropriate sized lumber and polyethylene

sheeting, at least 6 mil in thickness and located so that packaged materials, after being wiped clean, can be passed to the Holding Room.

B. Separate this room from the Work Area by a single flapped door of 6 mil polyethylene sheeting.

C. Provide a drop cloth layer of plastic on floor in the Wash Room for every load-out

operation. Roll this drop cloth layer of plastic from Wash Room into Work Area after each load-out. Provide a minimum of two (2) layers of plastic at all times. Use only clear plastic to cover floors.

D. Pump waste water to drain. Provide 20 micron and 5 micron waste water filters in line

to drain or waste water storage. Change filters daily or more often if necessary. Locate filters inside shower unit so that water lost during filter changes is caught by shower pan.

3.2.4 Clean Room: Provide Clean Room to isolate the Holding Room from the building

exterior. If possible locate to provide direct access to the Holding Room from the building exterior.

A. Erect Critical and Primary Barriers as described in Section 01526 "Temporary

Enclosures" in an existing space. If no space exists construct Clean Room of wood framing of appropriate size and polyethylene sheeting, at least 6 mil in thickness.

B. Separate this room from the exterior by a single flap door of 6 mil polyethylene sheeting.

3.3 LOAD-OUT AREA

3.3.1 The load-out area is the transfer area from the building to a truck or dumpster. It may be the Clean Room of the Equipment Decontamination unit or a separate room or loading dock area. Erect Critical and Primary barriers as described in Section 01526 - Temporary Enclosures in load-out area.

Page 110: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 7 Decontamination Units

A. During transfer of material from load-out area erect primary barriers as described in Section 01526 - Temporary Enclosures as necessary to seal path from load-out area to truck or dumpster.

B. Provide a lockable door to secure the work area during non-work hours.

3.3.2 Decontamination Sequence: Take all equipment or material from the Work Area through

the Equipment Decontamination Unit according to the following procedure:

A. At washdown station, thoroughly wet clean contaminated equipment or sealed polyethylene bags and pass into Wash Room.

B. When passing equipment or containers into the Wash Room, close all doorways of the Equipment Decontamination Unit, other than the doorway between the Washdown Station and the Wash Room. Keep all outside personnel clear of the Equipment Decontamination Unit.

C. Once inside the washroom, wet clean the bags and/or equipment.

D. When cleaning is complete pass items into Holding Room. Close all doorways except

the doorway between the Holding room and the Clean Room.

E. Workers from the building exterior enter Holding Area and remove decontaminated equipment and/or containers for disposal.

F. Require these workers to wear full protective clothing and appropriate respiratory

protection.

G. At no time is a worker from an uncontaminated area to enter the enclosure when a removal worker is inside.

3.4 CONSTRUCTION OF THE DECONTAMINATION UNITS

3.4.1 Walls and Ceiling: Construct airtight walls and ceiling using polyethylene sheeting, at least 6 mil in thickness. Attach to existing building components or a temporary framework.

3.4.2 Floors: Use 2 layers (minimum) of 6 mil polyethylene sheeting to cover floors in all areas

of the Decontamination Units. Use only clear plastic to cover floors.

3.4.3 Flap Doors: Fabricated from three (3) overlapping sheets with openings a minimum of three feet (3') wide. Configure so that sheeting overlaps adjacent surfaces. Weigh sheets at bottoms as required so that they quickly close after being released. Put arrows on sheets to indicate direction of overlap and/or travel. Provide a minimum of six feet (6') between entrance and exit of any room. Provide a minimum of three feet (3') between doors to airlocks, if applicable.

3.4.4 If the Decontamination area is located within an area containing friable asbestos on

overhead ceilings, ducts, piping, etc., provide the area with a minimum 1/4 inch hardboard or 1/2 inch plywood "ceiling" with polyethylene sheeting, at least 6 mil in thickness covering the top of the "ceiling".

3.4.5 Visual Barrier: Where the Decontamination area is immediately adjacent to and within

view of occupied areas, provide a visual barrier of opaque polyethylene sheeting at least 6 mil in thickness so that worker privacy is maintained and work procedures are not

Page 111: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 8 Decontamination Units

visible to building occupants. Where the area adjacent to the Decontamination area is accessible to the public, construct a solid barrier on the public side of the sheeting to protect the sheeting. Construct barrier with wood or metal studs covered with minimum 1/4 inch thick hardboard or 1/2 inch plywood. Where the solid barrier is provided, sheeting need not be opaque.

3.4.6 Alternate methods of providing Decontamination facilities may be submitted to the

Construction Manager for approval. Do not proceed with any such method(s) without written authorization of the Construction Manager.

3.4.7 Electrical: Provide subpanel at Clean Room to accommodate all removal equipment.

Connect all electrical branch circuits in Decontamination unit and particularly any pumps in shower room to a ground-fault circuit protection device.

3.5 CLEANING OF DECONTAMINATION UNITS

3.5.1 Clean debris and residue from inside of Decontamination Units on a daily basis or as otherwise indicated on Contract Drawings. Damp wipe or hose down all surfaces after each shift change. Clean debris from shower pans on a daily basis.

3.5.2 If the Clean Room of the Personnel Decontamination Unit becomes contaminated with

asbestos-containing debris, abandon the entire Decontamination Unit and erect a new Decontamination Unit. Use the former Clean Room as an inner section of the new Equipment Room.

3.6 MAINTENANCE OF DECONTAMINATION UNITS

3.6.1 Inspect all seals and doorways prior to each work shift and as indicated by conditions throughout removal. Repair immediately if necessary. Clean and dry decontamination units at the end of each work shift.

3.7 SIGNS

3.7.1 Post an approximately 20 inch by 14 inch manufactured caution sign at each entrance to the Work Area displaying the following legend with letter sizes and styles of a visibility required by 29 CFR 1926:

A. LEGEND

DANGER ASBESTOS CANCER AND LUNG DISEASE HAZARD AUTHORIZED PERSONNEL ONLY RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED IN THIS AREA

B. Provide spacing between respective lines at least equal to the height of the respective upper line.

3.7.2 Post an approximately 10 inch by 14 inch manufactured sign at each entrance to each

Work Area displaying the following legend with letter sizes and styles of a visibility at least equal to the following: A. LEGEND NOTATION

NO FOOD, BEVERAGES OR TOBACCO PERMITTED 3/4" Block

Page 112: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01563 01563 - 9 Decontamination Units

ALL PERSONS SHALL DON PROTECTIVE 3/4" Block CLOTHING (COVERINGS) BEFORE ENTERING THE WORK AREA ALL PERSONS SHALL SHOWER IMMEDIATELY 3/4" Block AFTER LEAVING WORK AREA AND BEFORE ENTERING THE CHANGING AREA

3.7.3 Post Work Area emergency procedures END OF SECTION - 01563

Page 113: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01601 01601 - 1 Materials and Equipment

SECTION 01601 - MATERIALS AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Manual sections apply to this Section.

1.2 SUMMARY

1.2.1 This Section specifies administrative and procedural requirements governing the Contractor's selection of products for use in the project.

1.2.2 The Contractor's Construction Schedule and the Schedule of Submittals are included

under Section 01301 - Submittals.

1.2.3 Standards: Refer to Section 01091 - Definitions and Standards for applicability of industry standards to products specified.

1.2.4 Administrative procedures for handling requests for substitutions made after award of the

Contract are included under Section 01632 - Product Substitutions. 1.3 DEFINITIONS

1.3.1 Definitions used in this Article are not intended to change the meaning of other terms used in the Contract Documents, such as "specialties," "systems," "structure," "finishes," "accessories," and similar terms. Such terms are self-explanatory and have well recognized meanings in the construction industry.

1.3.2 "Products" are items purchased for use in performing the Work or for incorporation in the

Work, whether purchased for the Project or taken from previously purchased stock. The term "product" includes the terms "material", "equipment", "system", and terms of similar intent.

1.3.3 "Named Products" are items identified by manufacturer's product name, including make

or model designation, indicated in the manufacturer's published product literature, that is current as of the date of the Contract Documents.

1.3.4 "Foreign Products", as distinguished from "domestic products", are items substantially

manufactured (50 percent or more of the product's value) outside of the United States and its possessions, or produced or supplied by entities substantially owned (more than 50 percent) by persons who are not citizens of nor living within the United States and its possessions.

1.3.5 "Materials" are products that are substantially shaped, cut, worked, mixed, finished,

refined or otherwise fabricated, processed, or installed to form a part of the Work.

1.3.6 "Equipment" are products that may be either operational or fixed.

1.3.7 Operational Equipment are products with operating parts, whether motorized or manually operated, that require temporary or permanent service connections, such as wiring or piping.

Page 114: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01601 01601 - 2 Materials and Equipment

1.3.8 Fixed Equipment are products necessary for accomplishing the work that are used as a temporary facility during the work and removed afterward.

1.4 SUBMITTALS

1.4.1 Required submittals: A general listing of products requiring submittals is included at the end of Section 01301 - Submittals. This listing may not be complete. Submittal requirements are found in each specification section. Prepare a schedule in tabular form showing each product listed. Include the manufacturer's name and proprietary product names for each item listed.

1.4.2 Product List Schedule: Prepare a schedule showing products specified in a tabular form

acceptable to the Owner's Representative. Include generic names of products required. Include the manufacturer's name and proprietary product names for each item listed.

1.4.3 Coordinate the product list schedule with the Contractor's Construction Schedule and the

Schedule of Submittals.

1.4.4 Form: Prepare the product listing schedule with information on each item tabulated under the following column headings:

A. Related Project Manual Section number.

B. Generic name used in Contract Documents.

C. Proprietary name, model number and similar designations.

D. Manufacturer's name and address.

E. Supplier's name and address.

F. Installer's name and address.

G. Projected delivery date, or time span of delivery period.

1.5 CONSTRUCTION MANAGER’S ACTION

1.5.1 The Construction Manager will respond in writing to the Contractor within 2 weeks of receipt of the completed product list schedule. No response within this time period constitutes no objection to listed manufacturers or products, but does not constitute a waiver of the requirement that products comply with Contract Documents. The Construction Manager’s response will include the following:

A. A list of unacceptable product selections, containing a brief explanation for this action.

1.6 QUALITY ASSURANCE

1.6.1 Compatibility of Options: When the Contractor is given the option of selecting between two or more products for use on the project, the product selected shall be compatible with products previously selected, even if previously selected products were also options.

1.7 PRODUCT DELIVERY, STORAGE, AND HANDLING

Page 115: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01601 01601 - 3 Materials and Equipment

1.7.1 Deliver, store and handle products in accordance with the manufacturer's recommendations, using means and methods that will prevent damage, deterioration and loss, including theft.

1.7.2 Schedule delivery to minimize long-term storage at the site and overcrowding of

construction spaces.

1.7.3 Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft and other losses.

1.7.4 Deliver products to the site in the manufacturer's original sealed container or other

packaging system, complete with labels and instructions for handling, storing, unpacking, protecting and installing.

1.7.5 Inspect products upon delivery to ensure compliance with the Contract Documents, and

to ensure that products are undamaged and properly protected.

1.7.6 Store products at the site in a manner that will facilitate inspection and measurement of quantity or counting of units.

1.7.7 Store heavy materials away from the project structure in a manner that will not endanger

the supporting construction.

1.7.8 Store products subject to damage by the elements above ground, under cover in a weathertight enclosure, with ventilation adequate to prevent condensation. Maintain temperature and humidity within range required by manufacturer's instructions.

PART 2 - PRODUCTS 2.1 PRODUCT SELECTION

2.1.1 General Product Requirements: Provide products complete with all accessories, trim, finish, safety guards and other devices and details needed for a complete installation and for the intended use and effect. Products must comply with the Contract Documents, be undamaged and, unless otherwise indicated, be unused at the time of installation.

2.1.2 Standard Products: Where available, provide standard products of types that have been

produced and used successfully in similar situations on other projects.

2.1.3 Product Selection Procedures: Product selection is governed by the Contract Documents and governing regulations, not by previous project experience. Procedures governing product selection include the following:

2.1.4 Descriptive Specification Requirements: Where Specifications describe a product or

assembly, listing exact characteristics required, with or without use of a brand or trade name, provide a product or assembly that provides the characteristics and otherwise complies with Contract requirements.

2.1.5 Performance Specification Requirements: Where Specifications require compliance with

performance requirements, provide products that comply with these requirements, and are recommended by the manufacturer for the application indicated. General overall performance of a product is implied where the product is specified for a specific application.

A. Manufacturer's recommendations may be contained in published product literature, or

by the manufacturer's certification of performance.

Page 116: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01601 01601 - 4 Materials and Equipment

2.1.6 Compliance with Standards, Codes and Regulations: Where the Specifications only

require compliance with an imposed code, standard or regulation, select a product that complies with the standards, codes or regulations specified.

PART 3 - EXECUTION 3.1 INSTALLATION OF PRODUCTS

3.1.1 Comply with manufacturer's instructions and recommendations for installation of products in the applications indicated.

END OF SECTION - 01601

Page 117: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01632 01632 - 1 Substitutions

SECTION 01632 - SUBSTITUTIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to this Section.

1.2 SUMMARY

1.2.1 This Section specifies administrative and procedural requirements for handling requests for substitutions made after award of the Contract.

1.2.2 Standards: Refer to Section 01091 - Definitions and Standards for applicability of industry

standards to products specified. 1.3 DEFINITIONS

1.3.1 Definitions used in this Article are not intended to change or modify the meaning of other terms used in the Contract Documents.

1.3.2 Substitutions: Requests for changes in products, materials, equipment, and methods of

construction required by Contract Documents proposed by the Contractor after award of the Contract are considered requests for "substitutions". The following are not considered substitutions:

A. Substitutions requested by Bidders during the bidding period and accepted prior to

award of Contract are considered as included in the Contract Documents and are not subject to requirements specified in this Section for substitutions.

B. Revisions to Contract Documents requested by the Owner or Construction Manager.

C. Specified options of products and construction methods included in Contract Documents.

D. The Contractor's determination of and compliance with governing regulations and orders issued by governing authorities.

1.4 SUBMITTALS

1.4.1 Substitution Request Submittal: Requests for substitution will be considered if received within two weeks prior to beginning work affected by the substitution. Requests received less than two weeks before commencement of affected Work may be considered or rejected at the discretion of the Construction Manager.

A. Submit 3 copies of each request for substitution for consideration. Submit requests in

the form and in accordance with procedures required for Change Order proposals.

B. Identify the product, or the fabrication or installation method to be replaced in each request. Provide complete documentation showing compliance with the requirements for substitutions, and the following information, as appropriate:

C. Product Data, including Drawings and descriptions of products, fabrication, installation

procedures, and manufacturer's instructions for use

Page 118: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01632 01632 - 2 Substitutions

D. Samples, where applicable or requested

E. Coordination information, including a list of changes or modifications needed for other

parts of the work and for construction performed by the Owner and separate contractors that will become necessary to accommodate the proposed substitution

F. A statement indicating the substitution's effect on the Contractor's Construction

Schedule compared to the schedule without approval of the substitution, and an indication of the effect of the proposed substitution on overall Contract Time.

G. Cost information, including a proposal of the net change, if any in the Contract Sum.

H. Certification by the Contractor that the substitution proposed is in every significant

respect equal to or better than that required by the Contract Documents, and that it will perform adequately in the application indicated. Include the Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of the failure of the substitution to perform adequately.

1.4.2 Construction Manager’s Action: Within one week of receipt of the request for

substitution, the Construction Manager will request additional information or documentation necessary for evaluation of the request. Within 2 weeks of receipt of the request, or one week of receipt of the additional information or documentation, whichever is later, the Construction Manager will notify the Contractor of acceptance or rejection of the proposed substitution. Acceptance will be in the form of a Change Order.

PART 2 - PRODUCTS 2.1 SUBSTITUTIONS

2.1.1 Conditions: The Contractor's substitution request will be received and considered by the Construction Manager when one or more of the following conditions are satisfied, as determined by the Construction Manager; otherwise requests will be returned without action except to record noncompliance with these requirements.

A. Extensive revisions to Contract Documents are not required.

B. Proposed changes are in keeping with the general intent of Contract Documents.

C. The request is timely, fully documented, and properly submitted.

D. The specified equipment, product or method of construction cannot be provided within

the Contract Time. The request will not be considered if the equipment, product or method cannot be provided as a result of failure to pursue the work promptly or coordinate activities properly.

E. The specified equipment, product or method of construction cannot receive necessary

approval by a governing authority, and the requested substitution can be approved.

F. A substantial advantage is offered the Owner, in terms of safety, cost, time, energy conservation or other considerations of merit, after deducting offsetting responsibilities the Owner may be required to bear. Additional responsibilities for the Owner may include additional compensation to the Construction Manager for redesign and evaluation services, increased cost of other construction by the Owner or separate Contractors, and similar considerations.

Page 119: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01632 01632 - 3 Substitutions

G. The specified equipment, product or method of construction cannot be provided in a manner that is compatible with other materials, and the Contractor certifies that the substitution will overcome the incompatibility.

H. The specified equipment, product or method of construction cannot be coordinated with

other materials, and the Contractor certifies that the proposed substitution can be coordinated.

I. The specified equipment, product or method of construction cannot provide a warranty

required by the Contract Documents and the Contractor certifies that the proposed substitution provides the required warranty.

2.1.2 The Contractor's submittal and Construction Manager acceptance of Shop Drawings,

Product Data or Samples that relate to construction activities not complying with the Contract Documents does not constitute an acceptable or valid request for substitution, nor does it constitute approval.

PART 3 – EXECUTION (Not Applicable) END OF SECTION - 01632

Page 120: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01701 Project Closeout 01701 - 1 Project Closeout

SECTION 01701 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.2 SUMMARY

1.2.1 This Section specifies administrative and procedural requirements for project closeout, including but not limited to:

A. Inspection procedures.

B. Project record document submittal.

C. Submittal of warranties.

D. Final cleaning.

1.3 DESCRIPTION OF REQUIREMENTS

1.3.1 Definitions: Project closeout is the term used to describe certain collective project requirements, indicating completion of the Work, that are to be fulfilled near the end of the Contract time in preparation for final acceptance and occupancy of the Work by the Owner, as well as final payment to the Contractor and the normal termination of the Contract.

A. Specific requirements for individual units of work are included in the appropriate

sections in Divisions 2 through 16.

B. Time of closeout is directly related to "Substantial Completion"; therefore, the time of closeout may be either a single time period for the entire Work or a series of time periods for individual elements of the Work that have been certified as substantially complete at different dates. This time variation, if any, shall be applicable to the other provisions of this section.

1.4 PREREQUISITES TO SUBSTANTIAL COMPLETION

1.4.1 General: Complete the following before requesting the Construction Manager to inspect for certification of substantial completion, either for the entire Work or for portions of the Work. Include list of known exceptions.

A. In the progress payment request that coincides with, or is the first request following, the

date substantial completion is claimed, show either 100% completion for the portion of the Work claimed as "substantially complete", or list incomplete items, the value of incomplete work, and reasons for the Work being incomplete.

B. Include supporting documentation for completion as indicated in these contract documents.

C. Submit a statement showing an accounting of changes to the Contract Sum.

D. Advise Owner of pending insurance change-over requirements.

Page 121: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01701 Project Closeout 01701 - 2 Project Closeout

E. Submit specific warranties, workmanship/maintenance bonds, maintenance

agreements, final certifications and similar documents.

F. Obtain and submit releases enabling Owner's full, unrestricted use of the Work and access to services and utilities. Where required, include occupancy permits, operating certificates and similar releases.

G. Submit record drawings, maintenance manuals, damage or settlement survey, and

similar final record information.

H. Complete final cleaning up requirements, including touch-up painting of marred surfaces.

I. Touch-up and otherwise repair and restore any damages to finishes, floors, walls, or

any other item or fixture which is the result of Contractor's actions.

1.4.2 Inspection Procedures: Upon receipt of Contractor's request for inspection, the Construction Manager will either proceed with inspection or advise Contractor of unfulfilled prerequisites.

A. Following initial inspection, Construction Manager will either prepare the certificate of

substantial completion, or will advise Contractor of work which must be performed before the certificate will be issued. The Construction Manager will repeat the inspection when requested and when assured that the Work has been substantially completed.

B. Results of the completed inspection will form the initial "punch-list" for final acceptance. 1.5 PREREQUISITES TO FINAL ACCEPTANCE

1.5.1 General: Complete the following before requesting the Construction Manager’s final inspection for certification of final acceptance, and final payment as required by the General Conditions. List known exceptions, if any, in request:

A. Submit the final payment request with final releases and supporting documentation not

previously submitted and accepted. Include certificates of insurance for products and completed operations where required.

B. Submit an updated final statement, accounting for final additional changes to the Contract Sum.

C. Submit a certified copy of the Construction Manager’s final punch-list of itemized work

to be completed or corrected, stating that each item has been completed or otherwise resolved for acceptance and has been endorsed and dated by the Construction Manager.

D. Submit consent of surety.

1.5.2 Reinspection Procedure: The Construction Manager will reinspect the Work upon receipt

of the Contractor's notice that the work, including punch-list items resulting from earlier inspections, has been completed, except for these items whose completion has been delayed because of circumstances that are acceptable to the Construction Manager.

Page 122: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01701 Project Closeout 01701 - 3 Project Closeout

A. Upon completion of reinspection, the Construction Manager will either prepare a certificate of final acceptance, or will advise the Contractor of work that is incomplete or of obligations that have not been fulfilled, but are required for final acceptance.

B. If necessary, the reinspection procedure will be repeated at the expense of the contractor.

1.6 RECORD DOCUMENT SUBMITTALS

1.6.1 General: Specific requirements for record documents are indicated in the individual sections of these specifications. Other requirements are indicated in the General Conditions. General submittal requirements are indicated in "submittals" sections.

A. Do not use record documents for construction purposes; protect from deterioration and

loss in a secure, fire-resistive location; provide access to record documents for the Construction Manager’s reference during normal working hours.

1.6.2 Record Drawings: Maintain a record set of blue or black line white-prints of contract

drawings and shop drawings in a clean, undamaged condition. Mark-up the set of record documents to show the actual installation where the installed work varies substantially from the work as originally shown. Mark whichever drawing is most capable of showing the actual "field" condition fully and accurately; however, where shop drawings are used for mark-up, record a cross-reference at the corresponding location on the working drawings. Give particular attention to concealed work that would be difficult to measure and record at a later date.

A. Mark record sets with red erasable pencil and, where feasible, use other colors to

distinguish between variations in separate categories of work.

B. Mark-up new information which is known to be important to the Construction Manager, but for some reason was not shown on either contract drawings or shop drawings.

C. Note related change-order number where applicable.

D. Organize record drawing sheets into manageable sets, bind with durable paper cover

sheets, and print suitable titles, dates and other identification on cover of each set.

1.6.3 Record Specifications: Maintain one complete copy of the Project Manual, including specifications and addenda, and one copy of other written construction documents such as change orders and similar modifications issued in printed form during construction. Mark these documents to show substantial variations in the actual work performed in comparison with the text of the specifications and modifications as issued. Give particular attention to substitutions, selection of options and similar information on work where it is concealed or cannot otherwise be readily discerned at a later date by direct observation. Note related record drawing information and product data, where applicable.

A. Upon completion of the Work, submit record specifications to the Construction

Manager for the Owner's records.

1.6.4 Record Product Data: Maintain one copy of each product data submittal. Mark these documents to show significant variations in the actual Work performed in comparison with the submitted information. Include both variations in the products as delivered to the site, and variations from the manufacturer's instructions and recommendations for installation. Give particular attention to concealed products and portions of the Work which cannot

Page 123: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01701 Project Closeout 01701 - 4 Project Closeout

otherwise be readily discerned at a later date by direct observation. Note related change orders and mark-up of record drawings and specifications.

A. Upon Completion of mark-up, submit complete set of record product data to the

Construction Manager for the Owner's records.

1.6.5 Record Sample Submittal: Immediately prior to date or dates of substantial completion, the Contractor will meet at the site with the Construction Manager and the Owner's personnel, if desired, to determine which, if any, of the submitted samples that have been maintained by the Contractor during progress of the Work, are to be transmitted to the Owner for record purposes. Comply with delivery to the Owner's sample storage space.

1.6.6 Miscellaneous Record Submittals: Refer to other sections of these specifications for

requirements of miscellaneous record-keeping and submittals in connection with the actual performance of the Work. Immediately prior to the date or dates of substantial completion, complete miscellaneous records and place in good order, properly identified and bound or filed, ready for continued use and reference. Submit to the Construction Manager for the Owner's records.

PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 2.1 FINAL CLEANING

2.1.1 General: Special cleaning requirements for specific units of Work are included in the appropriate sections of Division 2 through 16. General Cleaning during the regular progress of the Work is required by the General Conditions and is included under Section 01503 - Temporary Facilities.

2.1.2 Cleaning: Provide final cleaning of the Work at the time indicated. Employ experienced

workers or professional cleaners for final cleaning. Clean each surface or unit of work to the condition expected from a normal, commercial building cleaning and maintenance program.

A. Replace all HVAC Filters using materials supplied by Owner or clean non-replaceable

filters.

B. Clean light fixtures and lamps which have been affected by the work so as to function with full efficiency. Replace lamps where inoperable.

C. Removal of Protection: Except as otherwise indicated or requested by the

Construction Manager, remove temporary protection devices and facilities which were installed during the course of the work to protect previously completed work during the remainder of the construction period.

2.1.3 Compliances: Comply with safety standards and governing regulations for cleaning

operations. Do not burn waste materials at the site. Do not bury debris or excess materials on the Owner's property. Do not discharge volatile or other harmful or dangerous materials into drainage systems. Remove waste materials from the site and dispose of in a lawful manner.

END OF SECTION - 01701

Page 124: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01711 01711 - 1 Project Decontamination

SECTION 01711 - PROJECT DECONTAMINATION 1. PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.2 SUMMMARY

1.2.1 Work of this Section includes the decontamination of the air in the Work Area which has been, or may have been, contaminated by the elevated airborne asbestos fiber levels generated during abatement activities, or which may previously have had elevate fiber levels due to friable ACM in the space.

1.2.2 Work of this Section includes the cleaning, decontamination and removal of temporary

facilities installed prior to abatement work, including:

A. Primary and critical barriers erected by work of Section 01526 – Temporary Enclosures

B. Decontamination unit erected by work of Section 01563 – Decontamination Units

C. Negative pressure system installed by work of Section 01513 – Temporary Negative Pressure and Air Circulation System

1.3 DESCRIPTION OF REQUIREMENTS

1.3.1 General: Decontamination of the Work Area following asbestos abatement.

1.3.2 If the asbestos abatement work is on damaged or friable materials the work procedure uses two cleanings of the primary barrier plastic prior to its removal and one cleaning of the room surfaces to remove any new or existing contamination. Unless specifically indicated otherwise all materials are considered damaged or friable for purposes of this section. If the asbestos abatement work is on undamaged and non-friable materials, then the work procedures uses one cleaning of the primary barrier plastic and one cleaning of the room surfaces to remove any new or existing contamination. In both cases operation of the negative pressure system is used to remove airborne fibers generated by the abatement work.

1.3.3 At all times, operation of the negative pressure system shall be used to remove airborne

givers generated by the abatement work. 1.4 RELATED WORK SPECIFIED ELSEWHERE

1.4.1 Removal of Gross Debris is integral with the performance of abatement work and as such is specified in the appropriate work section(s) of these specifications:

A. Section 02081 – Removal of Asbestos-Containing Materials, OSHA Class I

B. Section 02083 – Removal of Asbestos-Containing Materials, OSHA Class II

C. Section 09805 - Encapsulation of Asbestos-Containing Materials

Page 125: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01711 01711 - 2 Project Decontamination

1.5 CLEARANCE AIR SAMPLING BY THE OWNER

1.5.1 Work Area Clearance: Air testing and other requirements which must be met before release of Contractor and reoccupancy of the work area are specified in Section 01714 - Work Area Clearance.

PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 GENERAL

3.1.1 Work of This Section includes the decontamination of air in the Work Area which has been, or may have been, contaminated by the elevated airborne asbestos fiber levels generated during abatement activities, or which may previously have had elevated fiber levels due to friable asbestos-containing materials in the space.

3.1.2 Work of This Section includes the cleaning, decontamination, and removal of temporary

facilities installed prior to abatement work, including:

A. Primary and Critical Barriers erected by work of Section 01526 – Temporary Enclosures

B. Decontamination Unit erected by work of Section 01563 – Decontamination Units

C. Negative Pressure System installed by work of Section 01513 – Temporary Negative Pressure and Air Circulation System

3.2 START OF WORK

3.2.1 Previous Work: During completion of the asbestos abatement work specified in other sections, the Secondary Barrier of polyethylene sheeting will have been removed and disposed of along with any gross debris generated by the asbestos abatement work.

3.2.2 Start of Work: Work of this section begins with the cleaning of the Primary Barrier. At

start of work the following will be in place:

3.2.3 Primary Barrier: Two layers of polyethylene sheeting on floor and two layers on walls.

3.2.4 Critical Barrier: An airtight barrier between the Work Area and other portions of the building or the outside.

3.2.5 Critical Barrier Sheeting: Over lighting fixtures and clocks, ventilation openings,

doorways, convectors, speakers and other openings.

3.2.6 Decontamination Units: For personnel and equipment in operating condition.

3.2.7 Negative Pressure System: In operation. 3.3 WORK SEQUENCE

3.3.1 First Cleaning; Carry out a first cleaning of all surfaces of the work area including items of remaining sheeting, tools, scaffolding and/or staging by use of damp-cleaning and mopping, and/or a High Efficiency Particulate Air (HEPA) filtered vacuum. (Note: A HEPA vacuum may fail if used with wet material.) Do not perform dry dusting or dry sweeping. Use each surface of a cleaning cloth one time only and then dispose of as

Page 126: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01711 01711 - 3 Project Decontamination

contaminated waste. Continue this cleaning until there is no visible debris from removed materials or residue on plastic sheeting or other surfaces.

A. Remove All Filters in Building Air Handling System(s) and dispose of as asbestos-

containing waste in accordance with requirements of Section 02084 - Disposal of Asbestos-Containing Waste Material.

B. Wait 24 Hours to allow HEPA filtered fan units to clean air of airborne asbestos fibers. Use oscillating fans as necessary to assure circulation of air in all parts of work areas during this period. Maintain negative pressure system in operation for the entire 24-hour period.

3.3.2 Second cleaning: Conduct a second cleaning of all surfaces in the work area in the same

manner as the first cleaning.

3.3.3 Visual Inspection: Before application of any sealer to abated surfaces as a lock-down, perform a visual inspection to determine if all ACM, including debris and residue, has been removed. Perform visual inspection along with the Consultant. When the area is visually clean, and if after sweeping of all surfaces with a leaf blower no debris, residue, dust or other material is found, complete the certification found in Appendix E. Visual inspection is not complete until confirmed in writing on the certification by the Consultant. After this visual inspection is passed, lock-down sealants can be applied and the work area decontamination process can be initiated.

A. Temporary lighting: Provide a minimum of 100 foot candles of lighting on all surfaces

in the areas to be subjected to visual inspection. Provide hand held lights providing 150 foot candles at 4 feet capable of reaching all locations in work area.

B. Provide ladders, scaffolding, and lifts as required to provide access to all surfaces in the area to be subjected to visual inspection. Access is to allow touching of all surfaces.

3.3.4 Sealing of Substrate: Perform sealing of substrate or installation of spray-applied finishes

or fireproofing, where required, at this time. Maintain pressure differential systems in operation during encapsulation work. Perform work only after meeting the following requirements:

A. Surfaces to be covered with sealer have met the requirements for a visual inspection

in this section.

3.3.5 Clearance Air Sampling: After the work area has been found visually clean, air samples will be taken and analyzed in accordance with the procedure set forth in Section 01714 - Work Area Clearance:

A. If Release Criteria are not met, repeat First Cleaning and continue decontamination

procedure from that point.

B. If Release Criteria are met continue cleaning and clearance procedures as given below.

3.4 REMOVAL OF WORK AREA ISOLATION

3.4.1 After all requirements of this section and Section 01714 - Work Area Clearance have been met:

A. Remove the Critical Barriers separating the Work Area from the rest of the building.

Page 127: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01711 01711 - 4 Project Decontamination

B. HEPA vacuum carpeting designated to remain in work areas using a floor cleaning

attachment adjusted so that rubber skirting is in contact with carpet surface. Use a passive (non power brush type) floor attachment with rubber floor seals and adjustable above-floor height. Completely clean carpeting in one direction with each pass of the floor attachment overlapping the previous pass by one-half the attachment width. At the completion of one such cleaning, vacuum clean in the same manner in a direction at right angles to the initial cleaning.

C. Shut down and remove the negative pressure system: Seal HEPA filtered fan units,

HEPA vacuums and similar equipment with 6 mil polyethylene sheet and duct tape to form a tight seal at intake end before being moved from Work Area.

D. Remove Personnel Decontamination Unit

E. Remove any small quantities of residual material found with wet wiping, HEPA filtered

vacuum cleaners and local area protection. If significant quantities, as determined by the Consultant, are found then the entire area affected shall be decontaminated as specified in Section 01712 - Cleaning and Decontamination Procedures.

F. Remove all equipment, materials, debris from the work site.

G. Dispose of all asbestos-containing waste material as specified in Section 02084 -

Disposal of Asbestos Containing Waste Material. 3.5 CERTIFICATE OF VISUAL INSPECTION

3.5.1 A Certificate of Visual Inspection form can be found in Appendices. This certification is to be completed by the Contractor and certified by the Consultant. Submit completed Certificate with Application for Final Payment. Final payment will not be made until this Certificate is executed.

3.6 SUBSTANTIAL COMPLETION OF ABATEMENT WORK

3.6.1 Asbestos Abatement Work is Substantially Complete upon meeting the requirements of this section and Section 01714 - Work Area Clearance, including submission of:

A. Certificate of Visual Inspection

B. Receipts documenting proper disposal as required by Section 02084 - Disposal of

Asbestos-Containing Waste Material

C. Punch list detailing repairs to be made and incomplete items. END OF SECTION - 01711

Page 128: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01712 01712 - 1 Cleaning and Decontamination Procedures

SECTION 01712 - CLEANING AND DECONTAMINATION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Manuals sections apply to work of this section.

1.2 DESCRIPTION OF THE WORK

1.2.1 Cleaning and decontamination is to be performed in all work areas. 1.3 RELATED WORK SPECIFIED ELSEWHERE

1.3.1 Work Area Clearance: Specified in Section 01714 - Work Area Clearance PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 GENERAL

3.1.1 Complete the following before start of work of this section: 01503 - Temporary Facilities 01513 - Negative Pressure and Air Circulation System 01562 - Respiratory Protection 01526 - Temporary Enclosures 01560 - Worker Protection 01563 - Decontamination Units 3.2 WET CLEANING

3.2.1 Accomplish wet cleaning during decontamination with paper towels or disposable rags and amended water. Change water frequently.

3.2.2 Material adhered to a surface with removal encapsulant may require the application of

additional removal encapsulant to facilitate cleaning. 3.3 REMOVAL OF ASBESTOS-CONTAINING DEBRIS

3.3.1 Remove asbestos-containing debris and decontaminate the area involved using the following sequence:

A. Pick up large pieces of debris and place in the bottom of a 6 mil polyethylene disposal

bag conforming to the requirements of Section 02084 - Disposal of Asbestos-Containing Waste Material. Place pieces in the bag without dropping and avoiding unnecessary disturbance and release of material.

B. Remove all small debris with the HEPA vacuum.

C. HEPA vacuum ladder and/or any tools used and pass out of the work area.

Page 129: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01712 01712 - 2 Cleaning and Decontamination Procedures

D. HEPA vacuum all surfaces in the room starting at the top of wall and working downward to the floor. Then start at corner of floor farthest from Work Area entrance and work towards entrance.

E. HEPA vacuum the floor using a floor attachment with rubber floor seals and adjustable

floor to attachment height. Adjust the height so that the rubber seals just touch the floor if carpeted and are within 1/16" of hard surface floors. Vacuum the floor in parallel passes with each pass overlapping the previous by one-half the width of the floor attachment. At the completion of one cleaning vacuum the floor a second time at right angles to the first.

3.4 CLEANING AND DECONTAMINATING OBJECTS

3.4.1 HEPA vacuum all surfaces of object and immediate area before moving the object.

3.4.2 Pick up object, if possible, and HEPA vacuum all surfaces.

3.4.3 Wet clean object, if possible, and place in storage location.

3.4.4 Decontaminate area where object was located by HEPA vacuuming twice, in two perpendicular directions. Wet clean if necessary to remove any debris.

3.4.5 Return object to its original location.

3.5 DECONTAMINATION OF ROOMS

3.5.1 HEPA vacuum all surfaces in the room starting at the ceiling, then top of wall and working downward to the floor.

3.5.2 HEPA vacuum the floor using a floor attachment with rubber floor seals and adjustable

floor to attachment height. Adjust the height so that the rubber seals just touch the floor if carpeted and are within 1/16" of hard surface floors. Vacuum the floor in parallel passes with each pass overlapping the previous by one half the width of the floor attachment. At the completion of one cleaning, vacuum the floor a second time at right angles to the first.

3.5.3 Operate HEPA filtered fan unit in space for 12 hours minimum.

3.5.4 At completion of Decontamination Work workers decontaminate in accordance with

Section 01560 - Worker Protection

3.5.5 Secure area from occupancy until air monitoring results per Section 01714 Work Area Clearance indicate area is safe for reoccupancy.

END OF SECTION - 01712

Page 130: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01714 01714 - 1 Work Area Clearance

SECTION 01714 - WORK AREA CLEARANCE PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.1.2 Visual Inspection: Required as a prerequisite of air testing, is set forth in Section 01711 -

Project Decontamination.

1.1.3 Air Monitoring: Performed by the Owner during abatement work, is described in Section 01410 – Air Monitoring by the Owner

1.2 SUMMARY

1.2.1 Not in Contract Sum: This section describes work being performed by the Owner. This work is not in the Contract Sum.

1.2.2 This Section sets forth required post-abatement airborne asbestos concentrations in the

Work Area and describes testing procedures the Owner will use to measure these levels. 1.3 CONTRACTOR RELEASE CRITERIA

1.3.1 The Asbestos Abatement Work Area is cleared when the Work Area is visually clean and airborne asbestos structure concentrations have been reduced to the clearance limit value identified in this Section.

1.4 VISUAL INSPECTION

1.4.1 Work of this Section will not begin until the visual inspection described in Section 01711 - Project Decontamination is complete and has been certified by the Consultant.

1.5 AIR MONITORING

1.5.1 To determine if the elevated airborne asbestos structure concentration encountered during abatement operations has been reduced to the specified level, the Owner will secure samples and analyze them according to the following procedures.

1.6 SCHEDULE OF AIR SAMPLES

1.6.1 General: The number and volume of air samples taken and analytical methods used by the Owner will be in accordance with the scheduled identified in this Section. Sample volumes given may vary depending upon the analytical instruments used.

1.7 PHASE CONTRAST MICROSCOPY

1.7.1 In each regulated Work Area, a minimum of 7 samples will be taken and analyzed as follows:

1.7.2 Samples will be collected on 25 mm phase contrast microscopy (PCM) cassettes with the

following filter media:

A. PCM: 0.8 mixed cellulose ester in a cassette with a 50 mm. conductive extension cowl.

Page 131: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01714 01714 - 2 Work Area Clearance

1.7.3 Number of PCM samples will be as follows:

Sample Type Minimum Number of Samples

Recommended Volume (Liters)

Flow Rate (Liters per minute)

Inside work area

5 1,500-3,850 5-15

Field blank

2 NA NA

1.7.4 Analysis: Fibers on each filter will be measured using the most recent revision of NIOSH

Method 7400.

1.7.5 Fibers: referred to in this section include fibers regardless of composition as counted by the phase contrast microscopy method used.

1.7.6 Release Criteria: Decontamination of the work site is complete when every Work Area

sample is at or below the Limit of Quantification of 0.01 f/cc. If any sample is above this limit then the decontamination is incomplete and re-cleaning per section 01711 - Project Decontamination is required.

1.8 TRANSMISSION ELECTRON MICROSCOPY

1.8.1 TEM air samples will be collected only if requested by the Owner

1.8.2 In each homogeneous work area after completion of all cleaning work, the following samples will be taken and analyzed:

Sample Type Minimum Number

of Samples Minimum Volume

(Liters) Flow Rate (Liters

per minute) Inside work area

5 1,200 3-10

Field blank

2 NA NA

Lab blank

1 NA NA

1.8.3 Analysis will be performed using the analysis method set forth in the AHERA Regulation

40 CFR Part 763 Appendix A.

1.8.4 Asbestos Structures referred to in this Section include asbestos fibers, bundles, clusters or matrices, as defined by method of analysis.

1.8.5 Release Criteria: Decontamination of the work site is complete if either of the following

two sets of conditions are met:

A. All Work Area sample volumes are greater than 1,199 liters for a 25 mm. sampling cassette.

B. The average concentration of asbestos of the five Work Area Samples does not exceed the filter background level of 70 structures per square millimeter of filter area.

1.8.6 If these conditions are not met then the decontamination is incomplete and the cleaning

procedures of Section 01711 – Project Decontamination shall be repeated.

Page 132: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 01714 01714 - 3 Work Area Clearance

1.8.7 Termination of Analysis: if the arithmetic mean (average) asbestos concentration on the field or lab blank filters exceed 70 structures per square millimeter of filter area the analysis will cease and new samples collected.

1.9 LABORATORY TESTING

1.9.1 PHASE CONTRAST MICROSCOPY

A. Samples will be sent by overnight courier for analysis by Phase Contrast Microscopy. Samples will not be carried on weekends, so samples shipped on Friday would arrive on the following Monday. Verbal results will normally be available the same day of receipt of samples by the laboratory. All laboratory results will be available to the Contractor.

1.9.2 TRANSMISSION ELECTRON MICROSCOPY

A. Samples will be sent by overnight courier for analysis by Transmission Electron

Microscopy. Samples will not be carried on weekends, so samples shipped on Friday would arrive on the following Monday. Verbal results will normally be available the same day of receipt of samples by the laboratory. All laboratory results will be available to the Contractor.

1.10 RE-SAMPLING

1.10.1 If, for any reason, the Final Air Clearance Samples do not meet the minimum clearance requirements, re-cleaning and re-sampling must be accomplished. The additional cost of re-sampling and re-analysis will be taken on by the Contractor and the method of sampling and analysis will be the same as that used for the first set of samples.

PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION - 01714

Page 133: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

02046-1

SECTION 02046 - CUTTING AND PATCHING - ASBESTOS-CONTAINING MATERIALS 1. PART 1 - GENERAL 1.1. RELATED DOCUMENTS Drawings and general provisions of Contract, including General and Supplementary

Conditions and other Division - 1 Specification Sections, apply to work of this section. 1.2. SUBMITTALS Before the Start of Work: Submit the following to the Owner's Representative for review.

Begin no work until these submittals are returned with Owner's Representative's approval indicating that the submittal is returned for unrestricted use or final-but-restricted use.

1.2.1. Tools: Equipped with HEPA vacuum dust collection attachments. 2. PART 2 - PRODUCTS 2.1. Provide local exhaust ventilation systems that comply with ANSI 29.2-1971. 2.2. Products for encapsulation are specified in Section 09805. 3. PART 3 - EXECUTION 3.1. Before beginning work of this section, comply with: Section 01503 - Temporary Facilities - Asbestos Abatement Section 01513 - Negative Pressure and Air Circulation System Section 01526 - Temporary Enclosures Section 01560 - Worker Protection - Asbestos Abatement Section 01562 - Respiratory Protection Section 01563 - Decontamination Units 3.2. Perform cutting, drilling, abrading, or otherwise penetrating any asbestos-containing material

in a manner that will minimize the dispersal of asbestos fibers into the air. 3.3. Provide adequate local exhaust to capture fibers produced by cutting, drilling, or abrading by

means of an approved High Efficiency Particulate Air (HEPA) filter vacuum. Use specialized equipment such as drills or saws having integral ventilation hoods which are connected to a HEPA vacuum with a flexible hose. Handle and dispose of HEPA filters as contaminated material. See Section 02084.

3.4. Thoroughly saturate absorbent surfaces of asbestos-containing material to be penetrated

with a penetrating type encapsulant. Allow encapsulant to penetrate to substrate before working on materials.

3.5. Seal edges of asbestos-containing material exposed by cutting, drilling, or abrading, etc.

with two (2) coats of an approved penetrating encapsulant applied in accordance with manufacturers' printed instruction for use of the encapsulant as an asbestos coating and requirements of Section 09805.

END OF SECTION - 02046

Page 134: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02081 02081 - 1 Removal of Asbestos Containing Material, Class I

SECTION 02081 - REMOVAL OF ASBESTOS-CONTAINING MATERIALS, OSHA CLASS I PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other sections of the Asbestos Abatement Project Manual apply to work of this section.

1.2 APPLICABILITY

1.2.1 This section applies to Class I work as defined by OSHA 29 CFR 1926.1101 and means activities involving the removal of ACM which is thermal system insulation (TSI) or surfacing material. This includes, but is not limited to, the removal of asbestos-containing pipe insulation, duct insulation, hard plaster systems, acoustical plaster and fireproofing.

1.3 RELATED WORK SPECIFIED ELSEWHERE

1.3.1 Installation of Critical and Primary Barriers, and Work Area Isolation Procedures are set forth in Section 01526 - Temporary Enclosures.

1.3.2 Project Decontamination procedures after removal of the Secondary Barrier are specified

in Section 01711 - Project Decontamination.

1.3.3 Disposal of asbestos-containing waste is specified in Section 02084 - Disposal of Asbestos-Containing Waste Material.

1.4 SUBMITTALS

1.4.1 Before Start of Work: Submit the following to the Construction Manager for review. Provide copies of the submittals to the consultant. Do not start work until these submittals are returned with Construction Manager’s approval indicating that the submittal is returned for unrestricted use.

A. Pre-Abatement Inspection Form: Submit completed and signed form to the

Environmental Consultant. Pre-Abatement Inspection form can be found in the appendices.

B. Surfactant: Submit product data, use instructions and recommendations from manufacturer of surfactant intended for use. Include data substantiating that material complies with requirements.

C. Removal Encapsulant: Submit product data, use instructions and recommendations

from manufacturer of removal encapsulant intended for use. Include data substantiating that material complies with requirements.

D. NESHAP Certification: Submit certification from manufacturer of surfactant or removal

encapsulant that, to the extent required by this specification, the material, if used in accordance with manufacturer's instructions, will wet Asbestos-Containing Materials to which it is applied as required by the National Emission Standard for Hazardous Pollutants (NESHAP) Asbestos Regulations (40 CFR 61, Subpart M).

E. Material Safety Data Sheet: Submit the Material Safety Data Sheet, or equivalent, in

accordance with the OSHA Hazard Communication Standard (29 CFR 1910.1200) for

Page 135: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02081 02081 - 2 Removal of Asbestos Containing Material, Class I

each surfactant, encapsulating material and solvent proposed for use on the work. Include a separate attachment for each sheet indicating the specific worker protective equipment proposed for use with the material indicated.

F. Glovebags: Submit product data.

G. Mini-Enclosures: Submit sketch of mini-enclosure arrangement to be used.

PART 2 - PRODUCTS 2.1 MATERIALS

2.1.1 Wetting Materials: For wetting prior to disturbance of Asbestos-Containing Materials use either amended water or a removal encapsulant:

2.1.2 Amended Water: Provide water to which a surfactant has been added. Use a mixture of

surfactant and water which results in wetting of the Asbestos-Containing Material and retardation of fiber release during disturbance of the material equal to or greater than that provided by the use of one ounce of a surfactant consisting of 50% polyoxyethylene ester and 50% polyoxyethylene ether mixed with five gallons of water.

2.1.3 Removal Encapsulant: Provide a penetrating type encapsulant designed specifically for

removal of Asbestos-Containing Material. Use a material which results in wetting of the Asbestos-Containing Material and retardation of fiber release during disturbance of the material equal to or greater than that provided by water amended with a surfactant consisting of one ounce of a mixture of 50% polyoxyethylene ester and 50% polyoxyethylene ether in five gallons of water.

2.1.4 Polyethylene Sheet: Provide polyethylene film in the largest size possible to minimize

seams, 6.0 mil thick as indicated, frosted or black as indicated.

2.1.5 Flame Resistant Polyethylene Film: Provide flame resistant polyethylene film that conforms to requirements set forth by the National Fire Protection Association Standard 701, Small Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mil thick as indicated, frosted or black as indicated.

2.1.6 Duct Tape: Provide duct tape in 2" or 3" widths as indicated, with an adhesive which is

formulated to stick aggressively to sheet polyethylene.

2.1.7 Spray Cement: Provide spray adhesive in aerosol cans which is specifically formulated to stick tenaciously to sheet polyethylene.

2.1.8 Disposal Bags: Provide 6 mil thick leak-tight polyethylene bags labeled as required by

Section 02084 - Disposal of Asbestos Containing Waste Material.

2.1.9 Fiberboard Drums: Provide heavy duty leak tight fiberboard drums with tight sealing locking metal tops.

2.1.10 Paper Board Boxes: Provide heavy duty corrugated paper board boxes coated with

plastic or wax to retard deterioration from moisture. Provide in sizes that will easily fit in disposal bags.

2.1.11 Felt: Standard felt approximately 1/16" thick and 36" to 72" in width.

Page 136: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02081 02081 - 3 Removal of Asbestos Containing Material, Class I

2.1.12 Glovebag: Constructed of a minimum of 6 mil thick plastic, seamless at the bottom, with two sealed inward projecting long sleeved gloves and equipped with a pouch for storage of tools and ports for sprayer wand and HEPA vacuum attachment.

PART 3 - EXECUTION 3.1 SECONDARY BARRIER

3.1.1 Secondary Barrier: Over the Primary Barrier, install as a drop cloth a clear 6 mil sheet plastic in all areas where asbestos removal work is to be carried out. Completely cover floor with sheet plastic. Where the work is within 10'-0" of a wall extend the Secondary Barrier up wall to ceiling. Support sheet plastic on wall with duct tape, seal top of Secondary plastic to Primary Barrier with duct tape so that debris is unable to get behind it. Provide cross strips of duct tape at wall support as necessary to support sheet plastic and prevent its falling during removal operations.

A. Install secondary barrier at the beginning of each work shift. Install only sufficient

plaster for work of that shift.

B. Remove secondary barrier at end of each work shift or as work in an area is completed. Fold plastic toward center of sheet and pack in disposal bags. Keep material on sheet continuously wet until bagged.

C. Install walkways of black 6-mil plastic between active removal areas and

decontamination units to protect primary layer from tracked material. Install walkways at the beginning of, and remove at the end of, each work shift.

3.2 WORKER PROTECTION

3.2.1 Before beginning work with any material for which a Material Safety Data Sheet has been submitted provide workers with the required protective equipment. Require that appropriate protective equipment be used at all times.

3.3 WET REMOVAL

3.3.1 Thoroughly wet Asbestos-Containing Materials to be removed prior to stripping and/or tooling to reduce fiber dispersal into the air. Accomplish wetting by a fine spray (mist) of amended water or removal encapsulant. Saturate material sufficiently to wet to the substrate without causing excess dripping. Allow time for amended water or removal encapsulant to penetrate material thoroughly. If amended water is used, spray material repeatedly during the work process to maintain a continuously wet condition. If a removal encapsulant is used, apply in strict accordance with manufacturer's written instructions. Perforate outer covering of any installation which has been painted and/or jacketed in order to allow penetration of amended water or removal encapsulant, or use injection equipment to wet material under the covering. Where necessary, carefully strip away while simultaneously spraying amended water or removal encapsulant on the installation to minimize dispersal of asbestos fibers into the air.

3.3.2 Mist work area continuously with amended water whenever necessary to reduce airborne

fiber levels.

3.3.3 Remove saturated Asbestos-Containing Material in small sections from all areas. Do not allow material to dry out. As it is removed, simultaneously pack material while still wet into disposal bags.

Page 137: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02081 02081 - 4 Removal of Asbestos Containing Material, Class I

3.3.4 Evacuate air from disposal bags with a HEPA filtered vacuum cleaner before sealing. Twist neck of bags, bend over and seal with minimum three wraps of duct tape. Clean outside and move to Wash Down Station adjacent to Material Decontamination Unit.

3.3.5 Fireproofing or Architectural Finish on Scratch Coat: Remove materials in manageable quantities and control the descent to staging or floor below; if over 10' use drop chute to contain material during descent. If using amended water, spray mist surface continuously during work process. If using removal encapsulant follow manufacturer's written instructions. Remove residue remaining on scratch coat after scraping using stiff nylon bristled hand brush. Use high pressure washer only with written authorization of Construction Manager. If a removal encapsulant is used remove residue completely before encapsulant dries. If substrate dries before complete removal of residue re-wet with amended water or removal encapsulant.

3.3.6 Fireproofing or Architectural Finish on Wire Lath: Cut wire lath into 2' X 6' sections and cut hanger wires. Do not drop on floor. Remove ACM from lath as necessary to enable lath to be packaged for disposal. Roll or fold up complete with any residual ACM and hand place in container as asbestos waste. After removal of lath and ACM remove any overspray on decking and structure. Use high pressure washer only with written authorization from Construction Manager. Use one of the following methods for containing waste.

3.3.7 Deposit material in corrugated paper board box. When box is full duct tape closed and place in disposal bag.

3.3.8 Wrap material in felt and place in fiberboard drum lined with two disposal bags. Use caution to insure that all edges of wire lath that could cut plastic are covered with felt.

3.3.9 Place material directly in a steel drum. Seal drums when full with leak tight seal. Drum is to be leak tight in any orientation.

3.3.10 Pipe Insulation: Spray with a mist of amended water or removal encapsulant. Allow amended water or removal encapsulant to saturate material to substrate. If a removal encapsulant is used, use in strict accordance with manufacturer's instructions. Cut bands holding preformed pipe insulation, slit jackets at seams, remove and hand-place in a disposal bag. Remove job-molded fitting insulation in chunks and hand place in a disposal bag. Do not drop to floor. Remove any residue on pipe or fitting with stiff bristle nylon hand brush. In locations where pipe fitting insulation is removed from pipe with straight runs insulated with fibrous glass or other non-asbestos-containing fibrous material, remove fibrous material 6" from the point where it contacts the asbestos-containing insulation.

3.4 GLOVEBAGS

3.4.1 Comply with all applicable OSHA Class I removal procedures, including supervision by a competent person as defined by the regulation, wet methods and use of HEPA filtered vacuums. At least two persons shall perform Class I glovebag removals.

3.4.2 Complete requirements of the following:

A. Section 01529 – Mini Enclosures and Glovebags

B. Section 01560 - Worker Protection

C. Section 01562 - Respiratory Protection

Page 138: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02081 02081 - 5 Removal of Asbestos Containing Material, Class I

3.5 MINI-ENCLOSURES

3.5.1 A Mini-Enclosure consists of a small Work Room with an attached separate Change Room. Worker decontamination requires a remote personnel decontamination unit.

3.5.2 Complete requirements of the following:

A. Section 01529 – Mini Enclosures and Glovebags

B. Section 01560 - Worker Protection

C. Section 01562 - Respiratory Protection

3.6 LOCALIZED CONTROL OF MATERIAL RELEASE

3.6.1 Pipe Insulation: HEPA vacuum surface of pipe insulation. Cut bands holding preformed pipe insulation, slit jackets at seams while holding HEPA vacuum under cut, remove and hand-place in a disposal bag. Remove job-molded fitting insulation in chunks, using nozzle of HEPA vacuum to collect debris generated, and hand-place in a disposal bag. Do not drop to floor. Remove any residue on pipe or fitting with wire brush. Brushing toward the nozzle of a HEPA vacuum. In locations where pipe fitting insulation is removed from pipe with straight runs insulated with fibrous glass or other non-asbestos-containing fibrous material, remove fibrous material 6" from the point where it contacts the asbestos-containing insulation. Use a two worker crew for work, with one worker removing material and one worker holding the nozzle of a HEPA vacuum in the location of disturbance.

3.6.2 Material sprayed on wire lath: Hold the nozzle from an operating HEPA filtered vacuum

cleaner in the immediate vicinity of and below the work while cutting the wire lath or otherwise disturbing the Asbestos-Containing Material. Use a two-worker crew for cutting, with one worker cutting and one worker holding the HEPA vacuum nozzle.

3.7 LOCAL VENTILATION AND COLLECTION SYSTEM:

3.7.1 Provide local ventilation and collection systems as described below for each area where amosite or dry Asbestos-Containing Material is being removed or otherwise disturbed:

3.7.2 Provide HEPA filtered fan units in addition to those required by section 01513 –

Temporary Negative Pressure and Air Circulation System, in the vicinity of the work. Arrange so that the units exhaust into the Work Area oriented in a direction away from the work. Extend a 12" diameter flexible non-collapsing duct from the intake end to a point no more than 4'-0" from any scraping or wire brushing activity.

3.7.3 Locate intake of duct so that air flow is horizontally and slightly downward into intake.

Replace primary filters on HEPA filtered fan units at an interval of no greater that 30 minutes. Allow no more than one scraping or wire brushing activity per fan unit.

3.8 HAZARDOUS WASTE MANAGEMENT

3.8.1 Manage and dispose of hazardous waste in accordance with the requirements of Section 02086 – Hazardous Waste Management.

Page 139: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02081 02081 - 6 Removal of Asbestos Containing Material, Class I

3.8.2 Do not mix potentially hazardous waste streams. Where feasible, separate each type of hazardous waste from other types of hazardous wastes, from asbestos waste and from construction waste.

3.8.3 Segregate, package, label, transport and dispose of hazardous waste in accordance with

DOT, EPA, State and Local regulations. END OF SECTION - 02081

Page 140: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02083 02083 - 1 Removal of Asbestos-Containing Materials, Class II

SECTION 02083 - REMOVAL OF ASBESTOS-CONTAINING MATERIALS, OSHA CLASS II PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.2 APPLICABILITY

1.2.1 This section applies to Class II work as defined by OSHA 29 CFR 1926.1101 and means activities involving the removal of ACM which is not thermal system insulation (TSI) or surfacing material. This includes, but is not limited to, the removal of asbestos-containing wallboard, floor tile and sheeting, roofing and siding shingles, and construction mastics.

1.3 RELATED WORK SPECIFIED ELSEWHERE

1.3.1 Supervision by a Competent Person is specified in Section 01043 - Project Coordination

1.3.2 Installation of Critical Barriers is set forth in Section 01526 – Temporary Enclosures

1.3.3 Section 01527 – Regulated Areas

1.3.4 Section 01560 – Worker Protection

1.3.5 Section 01562 – Respiratory Protection

1.3.6 Project Decontamination procedures after removal are specified in Section 01711 – Project Decontamination.

1.3.7 Disposal of asbestos-containing waste is specified in Section 02084 – Disposal of

Asbestos-Containing Waste Material. 1.4 SUBMITTALS

1.4.1 Before Start of Work: Submit the following to the Construction Manager for review. Provide a copy of submittals to the Consultant. Do not start work until these submittals are returned with Construction Manager’s approval indicating that the submittal is returned for unrestricted use.

1.4.2 Pre-Abatement Inspection: Submit completed and signed Pre-Abatement Inspection for

the work area. Pre-Abatement Inspection form can be found in the appendices.

1.4.3 Surfactant: Submit product data, use instructions and recommendations from manufacturer of surfactant intended for use. Include data substantiating that material complies with requirements.

1.4.4 Removal Encapsulant: Submit product data, use instructions and recommendations from

manufacturer of removal encapsulant intended for use. Include data substantiating that material complies with requirements.

1.4.5 Material Safety Data Sheet: Submit the Material Safety Data Sheet, or equivalent, in

accordance with the OSHA Hazard Communication Standard (29 CFR 1910.1200) for

Page 141: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02083 02083 - 2 Removal of Asbestos-Containing Materials, Class II

each surfactant, encapsulating material and solvent proposed for use on the work. Include a separate attachment for each sheet indicating the specific worker protective equipment proposed for use with the material indicated.

1.4.6 Adhesive Removal Solvent: Submit product data, use instructions and recommendations

from manufacturer of adhesive removal solvent intended for use. Include data substantiating that material complies with requirements.

PART 2 - PRODUCTS 2.1 WETTING MATERIALS

2.1.1 For wetting prior to disturbance of Asbestos-Containing Materials use either amended water or a removal encapsulant:

2.1.2 Amended Water: Provide water to which a surfactant has been added. Use a mixture of

surfactant and water which results in wetting of the Asbestos-Containing Material and retardation of fiber release during disturbance of the material equal to or greater than that provided by the use of one ounce of a surfactant consisting of 50% polyoxyethylene ester and 50% polyoxyethylene ether mixed with five gallons of water.

2.1.3 Removal Encapsulant: Provide a penetrating type encapsulant designed specifically for

removal of Asbestos-Containing Material. Use a material which results in wetting of the Asbestos-Containing Material and retardation of fiber release during disturbance of the material equal to or greater than that provided by water amended with a surfactant consisting of one ounce of a mixture of 50% polyoxyethylene ester and 50% polyoxyethylene ether in five gallons of water.

2.2 POLYETHYLENE SHEET

2.2.1 Provide polyethylene film in the largest size possible to minimize seams, 4.0 or 6.0 mil thick as indicated, frosted or black as indicated.

2.3 FLAME RESISTANT POLYETHYLENE SHEET

2.3.1 Provide flame resistant polyethylene film that conforms to requirements set forth by the National Fire Protection Association Standard 701, Small Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mil thick as indicated, frosted or black as indicated

2.4 DUCT TAPE

2.4.1 Provide duct tape in 2" or 3" widths as indicated, with an adhesive which is formulated to stick aggressively to sheet polyethylene.

2.5 SPRAY CEMENT

2.5.1 Provide spray adhesive in aerosol cans which is specifically formulated to stick tenaciously to sheet polyethylene.

2.6 DISPOSAL BAGS

2.6.1 Provide 6 mil thick leak-tight polyethylene bags labeled as required by Section 02084 - Disposal of Asbestos Containing Waste Material.

Page 142: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02083 02083 - 3 Removal of Asbestos-Containing Materials, Class II

2.7 FIBERBOARD DRUMS

2.7.1 Provide heavy duty leak tight fiberboard drums with tight sealing locking metal tops. 2.8 PAPER BOARD BOXES

2.8.1 Provide heavy duty corrugated paper board boxes coated with plastic or wax to retard deterioration from moisture. Provide in sizes that will easily fit in disposal bags.

2.9 ADHESIVE REMOVAL SOLVENT

2.9.1 Written permission to use adhesive removal solvent must be given by the Construction Manager. Provide a slow-drying solvent intended to remove adhesive. Provide material that is not flammable, does not create combustible vapors and has no significant inhalation hazard.

2.9.2 Provide materials that have less than 250 g/l of volatile organic solvents (VOCs).

PART 3 - EXECUTION 3.1 ALL CLASS II WORK

3.1.1 Competent Person: All Class II work shall be supervised by a competent person as defined by the regulation.

3.1.2 Critical Barriers: Critical barriers shall be placed over all openings to the regulated area

or utilize an alternate barrier or isolation method which prevents migration of airborne asbestos from the regulated area and meets the requirements of the regulation.

3.1.3 Impermeable Dropcloths: Impermeable dropcloths shall be placed on surfaces beneath

all removal activity. Dropcloths shall extend horizontally in all directions one foot for every vertical foot the work surface is above the floor.

3.1.4 Controls: Comply with the work practices specified for each type of Class II asbestos

work being performed as outlined in the following sections.

3.1.5 HEPA Filtration: Vacuums, powered saws and other equipment which may generate asbestos fibers shall be equipped with HEPA-filtered exhausts.

3.1.6 Wet Methods: Wet methods or wetting agents to control employee exposures shall be

employed.

3.1.7 OSHA requires the prompt cleanup of wastes and debris and placement in leak-tight containers and labeled with the following information:

DANGER CONTAINS ASBESTOS FIBERS AVOID CREATING DUST CANCER AND LUNG DISEASE HAZARD

3.1.8 Establish a decontamination area that is adjacent to the regulated area for decontamination of employees and their equipment. At a minimum the decontamination shall consist of an area covered by an impermeable drop cloth on the floor or horizontal working surface of sufficient size to accommodate cleaning of equipment and removing personal protective equipment without spreading contamination. Work clothes must be cleaned with a HEPA vacuum before it is removed. All equipment and surfaces of

Page 143: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02083 02083 - 4 Removal of Asbestos-Containing Materials, Class II

containers filled with ACM must be cleaned prior to removing them from the equipment room or area. Entry to and exit from the regulated area shall be through the decontamination area.

3.2 VINYL AND ASPHALT FLOORING MATERIALS

3.2.1 Before beginning work with any material for which a Material Safety Data Sheet has been submitted provide workers with the required protective equipment. Require that appropriate protective equipment be used at all times.

3.2.2 Flooring or its backing shall not be sanded.

3.2.3 Vacuums equipped with HEPA filter, disposable dust bag, and metal floor tool (no brush)

shall be used to clean floors.

3.2.4 Resilient sheeting shall be removed by cutting with wetting of the snip point and wetting during delamination. Rip-up of resilient sheet floor material is prohibited.

3.2.5 All scraping of residual adhesive and/or backing shall be performed using wet methods.

3.2.6 Dry sweeping is prohibited.

3.2.7 Mechanical chipping is prohibited unless performed in a negative pressure enclosure.

3.2.8 Tiles shall be removed intact, unless the contractor demonstrates that intact removal is

not possible.

3.2.9 When tiles can be heated and can be removed intact, wetting may be omitted. END OF SECTION - 02083

Page 144: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02084 02084 - 1 Disposal of Asbestos-Containing Waste Materials

SECTION 02084 - DISPOSAL OF ASBESTOS-CONTAINING WASTE MATERIAL PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.1.2 Section 01092 - Codes and Regulations describes applicable federal, state and local

regulations. 1.2 DESCRIPTION OF THE WORK

1.2.1 This section describes the disposal of Asbestos-Containing Materials. Disposal includes packaging of asbestos-containing waste materials. Disposal may be accomplished either by land filling or converting asbestos containing materials to non-asbestos waste.

1.3 SUBMITTALS

1.3.1 Before Start of Work: Submit the following to the Construction Manager for review. Provide a copy of submittals to the Consultant. Do not start work until these submittals are returned with Construction Manager approval indicating that the submittal is returned for unrestricted use.

A. Copy of state or local license for waste hauler.

B. Name and address of landfill where asbestos-containing waste materials are to be

buried. Include contact person and telephone number.

C. Chain of custody form and form of waste manifest proposed

1.3.2 Within 35 days of departure from building, submit copies of all manifests and disposal site receipts to Construction Manager and provide a copy to the Consultant.

PART 2 - PRODUCTS 2.1 DISPOSAL BAGS

2.1.1 Provide 6 mil thick leak-tight polyethylene bags labeled with three labels with text as follows:

2.1.2 First Label: Provide in accordance with 29 CFR 1910.1200(f) of OSHA's Hazard Communication standard: DANGER CONTAINS ASBESTOS FIBERS AVOID CREATING DUST CANCER AND LUNG DISEASE HAZARD BREATHING AIRBORNE ASBESTOS FIBERS IS HAZARDOUS TO YOUR HEALTH

2.1.3 Second Label: Provide in accordance with U. S. Department of Transportation regulation

on hazardous waste marking 49 CFR parts 171 and 172. Hazardous Substances:

Page 145: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02084 02084 - 2 Disposal of Asbestos-Containing Waste Materials

RQ-ASBESTOS WASTE CLASS 9 NA22120PG III

2.1.4 Third Label: Provide the name of the waste generator (Owner), the location from which the waste was generated and the names and addresses of the contractor and transporter. This label must be durable, able to repel dirt and moisture (e.g. permanent marker). Label must be placed directly on disposal bag(s) in a legible format. Peel and stick type labels are expressly prohibited.

PART 3 - EXECUTION 3.1 SEQUENCE

3.1.1 Comply with the following sections during all phases of this work:

A. Section 01560 - Worker Protection

B. Section 01562 - Respiratory Protection 3.2 GENERAL

3.2.1 All waste is to be hauled by a waste hauler with all required licenses from all state and local authority with jurisdiction.

3.2.2 Seal asbestos waste in leak-proof impermeable containers labeled in accordance with

Title 29, Code of Federal Regulations, Section 1910.1200 (f).

3.2.3 Protect interior of truck or dumpster with Critical and Primary Barriers as described in Section 01526 - Temporary Enclosures.

3.2.4 Carefully load containerized waste in fully enclosed dumpsters, trucks or other

appropriate vehicles for transport. Exercise care before and during transport, to insure that no unauthorized persons have access to the material. Vehicle must be placarded with DOT label.

3.2.5 Do not store containerized materials outside of the Work Area. Take containers from the

Work Area directly to a sealed truck or dumpster.

3.2.6 Do not transport disposal bagged materials on open trucks. Double bagged material may be transported on open trucks if they are first loaded in sealed drums. Label drums with same warning labels as bags. Uncontaminated drums may be reused. Treat drums that have been contaminated as asbestos-containing waste and dispose of in accordance with this specification.

3.2.7 Advise the landfill operator or processor, in advance of transport, of the quantity of

material to be delivered.

3.2.8 At disposal site unload containerized waste:

A. At a disposal site, sealed plastic bags may be carefully unloaded from the truck. If bags are broken or damaged, return to work site for re-bagging. Clean entire truck and contents which have been in contact with containerized waste, using procedures set forth in Section 01711 - Project Decontamination.

Page 146: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02084 02084 - 3 Disposal of Asbestos-Containing Waste Materials

B. Ensure that no visible emissions are released to the outside air from sealed plastic bags or impermeable containers while transporting or handling at the site where materials and waste are deposited.

3.2.9 Retain receipts from landfill or processor for materials disposed of.

3.2.10 At completion of hauling and disposal of each load, submit copy of waste manifest, chain

of custody form, and landfill receipt to Construction Manager and provide a copy to the Consultant.

END OF SECTION - 02084

Page 147: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02086 02086 - 1 Hazardous Waste Management

SECTION 02086 – HAZARDOUS WASTE MANAGEMENT PART 1 – GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Manual sections apply to the work of this section.

1.2 RELATED SECTIONS

1.2.1 Section 01092 – Codes, Regulations and Standards

1.2.2 Section 02084 – Disposal of Asbestos-Containing Waste Materials 1.3 DESCRIPTION OF THE WORK

1.3.1 This section describes the segregation, packaging, labeling, transport, and disposal or recycling of waste materials generated by demolition activities and the subsequent shipment of properly packaged and labeled waste materials to an approved disposal site or recycling facility.

1.4 CODES AND REGULATIONS

1.4.1 General Applicability of Codes and Regulations: Except to the extent that more explicit or more stringent requirements are written directly into the Contract, all applicable codes and regulations have the same force and effect (and are made a part of the Contract by reference) as if copies directly in the Contract or as if published copies are bound herewith.

1.4.2 Contractor Responsibility: The Contractor shall assume full responsibility and liability for

the compliance with all applicable Federal, State and local regulations pertaining to hazardous waste management and disposal or recycling. Contractor shall hold the Owner and Construction Manager harmless for failure to comply with any applicable work hauling, disposal, safety, health or other regulations on the part of the Contractor, the Contractor’s employees or Subcontractors.

1.4.3 Federal Requirements: which govern the management, hauling and disposal or recycling

of hazardous waste include, but are not limited to, the following:

A. DOT: U.S. Department of Transportation, including but not limited to:

a. Hazardous Substances Title 49, Part 171 and 172 of the Code of Federal Regulations

b. Hazardous Material Regulations General Awareness and Training Requirements for Handlers, Loaders, and Drivers Title 49, Parts 171-180 of the Code of Federal Regulations

c. Hazardous Material Regulations Editorial and Technical Revisions Title 49, Parts 171-180 of the Code of Federal Regulations

B. EPA: U.S. Environmental Protection Agency, including but not limited to

Page 148: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02086 02086 - 2 Hazardous Waste Management

a. Management of Hazardous Waste Resource Conservation and Recovery Act

(RCRA) Title 40, Parts 260-268 of the Code of Federal Regulations

C. State Requirements: Abide by all state requirements which govern the management,

hauling and disposal or recycling of hazardous materials.

D. Local Requirements: Abide by all local requirements which govern the management, hauling and disposal or recycling of hazardous materials.

1.5 DEFINITIONS

1.5.1 Toxicity Characteristic Leaching Procedure (TCLP): A laboratory test method to determine the mobility of both organic and inorganic analytes present in liquid, solid and multiphasic wastes performed in accordance with test methods required under 40 CFR Part 268.

1.6 SUBMITALS

1.6.1 Before Start of Work: Submit the following to the Construction Manager for review. Provide copy of submittals to Consultant. Do not start work until these submittals are returned with Construction Manager’s action stamp indicating that the submittal is returned for unrestricted use.

A. Copy of state and local licenses for waste hauler

B. U.S. EPA Identification Number of waste hauler

C. Name and address of waste disposal facility where hazardous waste materials are to

be disposed including:

a. Contact person and telephone number b. Copy of state license and permit c. Disposal facility permits

D. Name and address of waste recycling facility where hazardous waste materials are to

be recycled including:

a. Contact person and telephone number b. Copy of state license and permit c. Recycling facility permits

E. Specimen copy of Uniform Hazardous Waste Manifest form

F. Copy of EPA Notice of Hazardous Waste activity form

G. Copy of forms required by state and local agencies

H. Sample of disposal label to be used

1.6.2 During Work: Submit the following as required by the work

A. TCLP rest results, as required to characterize waste for segregation and packaging

purposes

Page 149: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02086 02086 - 3 Hazardous Waste Management

B. Copies of all executed manifests and disposal or recycling site receipts

PART 2 – PRODUCTS 2.1 MATERIALS

2.1.1 Disposal Bags: Provide 6-mil thick leak-tight polyethylene bags

2.1.2 DOT Hazardous Waste Disposal Drums: Provide DOT 17-H Open-Top Drums (55 gallon) in accordance with DOT regulations title 49 CFR Parts 173, 178 and 179.

2.1.3 DOT Hazardous Waste Labels: in accordance with DOT regulations Title 49 CFR Parts

173, 178 and 179. PART 3 – EXECUTION 3.1 GENERAL

3.1.1 Do not mix potentially hazardous waste streams. Where feasible, separate each type of hazardous waste from other types of hazardous wastes, from asbestos waste and from construction waste.

3.1.2 Segregate, package, label, transport and dispose or recycle hazardous waste in

accordance with DOT, EPA, State and local regulations. 3.2 HAZARDOUS WASTE DESIGNATION

3.2.1 Where not otherwise designated by the Owner as hazardous waste, characterize all suspect waste products by conducting representative TCLP testing.

3.2.2 Representative sampling of waste products will be in accordance with EPA Document

SW 846

3.2.3 TCLP test analysis will be performed in accordance with EPA Method 1311 3.3 HAZARDOUS WASTE

3.3.1 The following waste products are designated by the Owner as non-salvageable and as Hazardous Waste Types:

A. Suspect PCB containing waste

a. Fluorescent light ballasts

B. Suspect mercury containing waste

a. Fluorescent lamps b. Boiler switches

C. Universal wastes

a. Batteries in exit and emergency lighting

Page 150: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02086 02086 - 4 Hazardous Waste Management

D. Suspect CFC/HCFC containing waste a. Refrigerants in window air-conditioning units

3.4 HAZARDOUS WASTE PACKAGING AND LABELING:

3.4.1 Package each segregated hazardous waste in specified containers as follows. IMPORTANT: Do not mix waste streams

A. Package in DOT 17-H open-top drums with polyethylene disposal bag liners

B. Fill liner bag only with same waste type, then neck liner bags down into DOT 17-H

open-top drum and seal with duct tape

C. Install gasket on lid, apply lock ring, and seal

D. Apply hazardous waste label to drum side with DOT shipping data information

E. Adjacent to each label, enter the date when waste was first placed in each drum 3.4.2 Sealed and Labeled Containers: Maintain all containers in a continuously sealed

condition after they have been sealed.

A. Do not reopen sealed containers

B. Do not place additional waste in sealed containers

3.5 TEMPORARY STORAGE

3.5.1 Partially filled containers of hazardous waste may be stored at the work site for intermittent packaging provided that:

A. Each container is properly labeled when it is first placed into service

B. Each container remains closed at all times except when compatible waste types are

added

C. When moved from site to site, each container remains within the geographic boundaries of the facility without moving nor crossing public access highways

3.6 REMOVAL OF HAZARDOUS WASTES

3.6.1 Immediately seal containers of hazardous waste as each container is filled. Remove containers of hazardous waste from the work site within 72 hours of being sealed.

3.6.2 Transport sealed containers from the work site to an approved disposal site or recycling

center.

3.6.3 Continuously maintain custody of all hazardous material generated at the work site including security, short-term storage, transportation and disposition until custody is transferred to an approve disposal site or recycling center. Document continuous chain of custody.

3.6.4 Do not remove, or cause to be removed, hazardous waste from Owner’s property without

a legally executed Uniform Hazardous Waste manifest.

Page 151: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02086 02086 - 5 Hazardous Waste Management

3.6.5 At completion of hauling and disposal or recycling of each load, submit copy of waste manifest, chain of custody, and landfill receipt to Construction Manager. Provide copies to Consultant.

3.7 RECYCLING AND RECORY

3.7.1 Turn over waste which contains materials for which recovery and/or recycling is possible to an approved recycling center. Materials subject to recycling may include:

A. Fluorescent lamps B. Liquid mercury C. Lead acid batteries D. Refrigerants containing CFCs

3.8 BACKCHARGES

3.8.1 Where Contractor fails to fulfill packaging, handling, transportation, disposal or recycling requirements as outlined herein, the Owner will charge back to the Contractor all costs associated with insuring that hazardous wastes are segregated, packaged, transported and disposed of or recycled in accordance with all applicable Federal, State and local regulation.

3.8.2 Environmental pollution of Owner’s property or other environments resulting from

Contractor’s hazardous waste management activities will be promptly remediated under Consultant’s direction, to the Consultant’s sole satisfaction, and at the Contractor’s sole expense.

3.8.3 Contractor agrees to either reimburse the Owner, or reduce the Contract amount by

change order, to cover all costs associated with waste re-packaging, was re-segregation, or pollution remediation efforts.

3.9 REMOVAL OF NON-HAZARDOUS WATSE MATERIALS

3.9.1 Transport and legally dispose of non-hazardous waste products, materials, residues and refuse at a location not on Owner’s property.

3.9.2 Non-hazardous waste products, materials, residues and refuse include, but are not

necessary limited to:

A. Materials which are determined to be non-hazardous wastes though objective sampling in accordance with EPA Document SW-846 and laboratory analysis in accordance with EPA Method 1311.

B. Emptied hazardous material contains holding a material with constituents listed on the MSDS as hazardous

a. When a container is emptied of its hazardous contents by pouring or scraping so

that less than one inch of material remains in the bottom of the container, the container is considered empty and is not in itself a hazardous waste

b. Emptied hazardous material containers may be disposed of as construction debris waste.

C. Personnel protective clothing and safety equipment with minimum or trace

contamination, as determined by visual inspection of Construction Manager

Page 152: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 02086 02086 - 6 Hazardous Waste Management

D. Keep premises in a clean and orderly condition during performance of abatement work.

E. Place non-hazardous construction debris wastes on a daily basis in secure

containers for local landfill disposal

END OF SECTION – 02086

Page 153: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 09805 09805 - 1 Encapsulation of Asbestos-Containing Materials

SECTION 09805 - ENCAPSULATION OF ASBESTOS-CONTAINING MATERIALS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

1.1.1 Drawings and general provisions of Contract and other Asbestos Abatement Project Design sections apply to work of this section.

1.2 DESCRIPTION OF WORK

1.2.1 The extent of encapsulation work is shown on the drawings and as herein specified.

1.2.2 The encapsulation work includes:

A. Sealing of exposed edges of drywall and plaster system finishes with 2 coats of penetrating encapsulant.

B. Sealing of pipe insulation ends where material in inaccessible for removal with 2 coats of penetrating encapsulant and 1 coat of bridging encapsulant.

1.3 RELATED WORK SPECIFIED ELSEWHERE

1.3.1 Asbestos abatement project requirements to be completed prior to start of the work of this sections are set forth in the following sections:

A. 01503 – Temporary Facilities

B. 01513 – Temporary Negative Pressure and Air Circulation System

C. 01526 – Temporary Enclosures

D. 01560 – Worker Protection

E. 01562 – Respirator Protection

F. 01563 – Decontamination Units

1.3.2 Asbestos abatement project requirements to be completed at completion of the work of

this section are set forth in the following sections:

A. 01711 – Project Decontamination 1.4 DEFINITNIONS

1.4.1 Encapsulant: A material that surrounds or embeds asbestos fibers in an adhesive matrix to prevent release of fibers

A. Bridging encapsulant: an encapsulant that forms a discrete layer on the surface of an

in situ asbestos matrix

B. Penetrating encapsulant: an encapsulant that is absorbed by the in situ asbestos matrix without leaving a discrete surface layer

Page 154: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 09805 09805 - 2 Encapsulation of Asbestos-Containing Materials

C. Removal encapsulant: a penetrating or wetting encapsulant specifically designed to minimize fiber release during removal of asbestos-containing materials rather than for in situ encapsulation.

1.4.2 Encapsulation: Treatment of ACM with an encapsulant. Application of a sealer to a

substrate following completion of removal of ACM is not considered an encapsulation. 1.5 SUBMITTALS

1.5.1 Before Start of Work, submit the following to the Construction Manager for review. Provide a copy of submittals to the Consultant. Do not begin work until these submittals are returned with the Construction Manager’s action stamp indicating that the submittal has been Received – No Reviewed.

1.5.2 Product Data: Submit manufacturer's technical information including label analysis and

application instructions for each material proposed for use.

1.5.3 Installation Instructions: Submit manufacturer's installation instructions with specific project requirements noted.

1.5.4 Performance Warrantee: Submit manufacturer's performance guarantee.

1.5.5 Certification: Submit written approval of entity installing the encapsulant from

encapsulant manufacturer.

1.5.6 Material Safety Data Sheet: Submit the Material Safety Data Sheet, or equivalent, in accordance with the OSHA Hazard Communication Standard (29 CFR 1910.1200) for each surfactant, encapsulating, and wetting material proposed for use on the work. Include a separate attachment for each sheet indicating the specific worker protective equipment proposed for use with the material indicated.

1.6 DELIVERY AND STORAGE

1.6.1 Deliver materials to the job site in original, new and unopened packages and containers bearing manufacturer's name and label, and following information:

A. Name or title of material

B. Manufacturer's stock number and date of manufacture

C. Manufacturer's name

D. Thinning instructions

E. Application instructions

1.6.2 Deliver materials together with a copy of the OSHA Material Safety Data Sheet for the

material. 1.7 JOB CONDITIONS

1.7.1 Apply encapsulating materials only when environmental conditions in the work area are as required by the manufacturer's instructions.

PART 2 - PRODUCTS

Page 155: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Section 09805 09805 - 3 Encapsulation of Asbestos-Containing Materials

2.1 ENCAPSULANTS

2.1.1 Provide penetrating or bridging type encapsulants specifically designed for application to the asbestos-containing material to which it is being applied and which satisfies fire ratings and is compatible with both the substrate and put-back material.

PART 3 - EXECUTION 3.1 GENERAL

3.1.1 Prior to applying any encapsulating material, ensure that application of the sealer will not cause the base material to fail and allow the sealed material to fall of its own weight or separate from the substrate. Should Contractor doubt the ability of the installation to support the sealant, request direction from the Manufacturer before proceeding with the encapsulating work.

3.1.2 Do Not Commence Application of encapsulating materials until all removal work within

the work area has been completed. 3.2 WORKER PROTECTION

3.2.1 Before beginning work with any material for which a Material Safety Data Sheet has been submitted provide workers with the required protective equipment, which may include combination HEPA/chemical cartridges. Require that appropriate protective equipment be used at all times.

3.3 DRYING ENCAPSULATED SURFACES

3.3.1 General: Following encapsulation work, allow the HEPA filtered fan units to operate for a sufficient length of time that all encapsulated surfaces dry thoroughly. During period of drying, operate Temporary Pressure Differential and Air Circulation System.

3.3.2 Do not star the work of Section 01711 – Project Decontamination until all encapsulated

surfaces are completely dry. END OF SECTION - 09805

Page 156: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Appendix A - 1

ASBESTOS ABATEMENT DRAWINGS

Page 157: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Appendix B - 1

CERTIFICATE OF WORKER’S ACKNOWLEDGMENT

Project Name: Tri-C Metro Campus-CBL-IM-HVAC 8001 Projects – Asbestos Abatement

Project Address: 2900 Community College Avenue, Cleveland, Ohio

Date: Contractor:

WORKING WITH ASBESTOS CAN BE DANGEROUS. INHALING ASBESTOS FIBERS HAS BEEN LINKED WITH VARIOUS TYPES OF CANCER. IF YOU SMOKE AND INHALE ASBESTOS FIBERS THE CHANCE THAT YOU WILL DEVELOP LUNG CANCER IS GREATER THAN THAT OF THE NON-SMOKING PUBLIC.

Your employer’s contract with the Owner for the above referenced project requires that: You be supplied with the proper respirator and be trained in its use. You be trained in safe work practices and in the use of the equipment found on the job. You receive a medical examination. These things are to have been done at no cost to you.

RESPIRATORY PROTECTION: You must have been trained in the proper use of respirators and informed of the type of respirator to be used on the above referenced project. You must be given a copy of the written respiratory protection manual issued by your employer. You must be equipped at no cost with the respirator to be used on the above reference project.

TRAINING COURSE: You must have been trained in the dangers inherent in handling asbestos and breathing asbestos dust and in proper work procedures and personal and area protective measures. This training must have been the equivalent in curriculum, training method and length to the US EPA Model Accreditation Plan asbestos abatement worker training (40 CFR Part 763, Subpart E, Append C).

MEDICAL EXAMINATION: You must have had a medical examination within the past 12 months at no cost to you. The examination must have included health history, pulmonary function tests and may have included an evaluation of a chest x-ray.

By signing this document, you are acknowledging only that the Owner of the building you are about to work in has advised you of your rights to training and protection relative to your employer.

Signature:

Printed Name:

ODH License Number:

Witness:

Page 158: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Appendix C - 1

PRE-ABATEMENT INSPECTION FORM

Project Name: Tri-C Metro Campus – CBL-IM-HVAC 8001 Project - Asbestos Abatement

Project Location: Tri-C Metro Campus, 2900 Community College Avenue, Cleveland, Ohio

Specific Work Area Location:

Material to be Removed: Quantity:

Project Manual Section: Accept N/A Comments

01513 – Negative Pressure

01526 – Temporary Enclosure

01527 – Regulated Areas

01529 – Mini Enclosures and Glovebags

01560 – Worker Protection

01562 – Respiratory Protection

01563 – Decontamination Units

02081 – Removal of ACM, Class I

02083 – Removal of ACM, Class II

Contractor:

In accordance with the Asbestos Abatement Project Design, the Contractor hereby certifies the Work Area has been appropriately prepared.

Signature: Date:

Print Name: Title:

Page 159: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Appendix C - 1

VISUAL INSPECTION FORM Project Name: Tri-C Metro Campus – CBL-IM-HVAC 8001 Projects – Asbestos Abatement

Project Location: 2900 Community College Avenue, Cleveland, Ohio

Specific Work Area:

Material Removed: Quantity:

Contractor Certification of Visual Inspection:

In accordance with Section 01711 – Project Decontamination, the Contractor hereby certifies that he has visually inspected the Work Area (all surfaces including but not limited to pipes, beams, ledges, walls, ceilings, floors, decontamination unit and sheet plastic) and has found no dust, debris or residue.

Signature: Date:

Print Name: Title:

Consultant Certification of Visual Inspection:

The Consultant hereby certifies that he has accompanied the Contractor on the visual inspection and verifies that this inspection has been thorough and to the best of his knowledge and believe, the Contractor’s certification above is a true and honest one.

Signature: Date:

Print Name: Title:

Air clearance not required

PCM air clearance required Results expected:

TEM air clearance required Results expected:

Notes:

Page 160: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:

Asbestos Abatement Project Design DRAFT 5/10/19 Tri-C-Metro Campus-CBL-IM-HVAC 8001 Projects PSI Project Number 01372563

Appendix E - 1

CERTIFICATE OF REOCCUPANCY Project Name: Tri-C Metro Campus-CBL-IM-HVAC 8001 Projects – Asbestos Abatement

Project Location: 2900 Community College Avenue, Cleveland, Ohio

Specific Work Area:

Material Removed: Quantity:

Air Clearance Sample Collection:

Following successful visual inspection of the work area, the Consultant has collect the following air clearance samples:

Air clearance not required

PCM Number of PCM samples collected:

TEM Number of TEM samples collected:

Sample collected using aggressive methods

Air Clearance Sample Results:

The air clearance sampling results are within the limits identified in the Release Criteria of Section 01714 – Work Area Clearance. The work area has been found acceptable for reoccupancy.

Signature: Date:

Print Name: Title:

Notes:

Page 161: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:
916161
Rectangle
916161
Polygon
916161
Rectangle
916161
Rectangle
Page 162: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:
916161
Rectangle
916161
Rectangle
916161
Oval
916161
Oval
916161
Rectangle
916161
Rectangle
916161
Rectangle
916161
Rectangle
916161
Rectangle
916161
Polygon
916161
Oval
Page 163: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:
916161
Rectangle
916161
Rectangle
916161
Rectangle
916161
Rectangle
Page 164: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:
916161
Rectangle
916161
Polygon
916161
Rectangle
916161
Oval
916161
Oval
916161
Polygon
Page 165: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:
916161
Rectangle
916161
Rectangle
916161
Rectangle
916161
Rectangle
916161
Rectangle
Page 166: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:
916161
Rectangle
916161
Polygon
Page 167: Asbestos Abatement Project Design · C. “Report of Findings of Partial Inspection for Asbestos Containing Materials at Cuyahoga ... beginning of this project. Arts & Music Auditorium:
916161
Rectangle
916161
Rectangle
916161
Oval
916161
Oval
916161
Polygon
916161
Rectangle
916161
Oval
916161
Oval
916161
Oval