asd/aia s3000l steering committee (s3000l_sc01) 11.04.-14.04.2011 – paris, gifas

7
1 Cassidian Air Systems ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS S4000M – History of S4000M – History of development development

Upload: duaa

Post on 06-Jan-2016

38 views

Category:

Documents


3 download

DESCRIPTION

ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS S4000M – History of development. Cassidian Air Systems. ASD S4000M Scheduled Maintenance Analysis. The specification S4000M is designed to cover the activities of a Scheduled Maintenance Analysis (SMA) process . - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS

1

Cassidian Air Systems

ASD/AIA S3000L Steering Committee (S3000L_SC01)

11.04.-14.04.2011 – Paris, GIFAS

S4000M – History of developmentS4000M – History of development

Page 2: ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS

2

The specification S4000M is designed to cover the activities of aScheduled Maintenance Analysis (SMA) processScheduled Maintenance Analysis (SMA) process.

The concept of this specification was originated in 2006.in 2006.

24.06.2009 24.06.2009 Publication of S4000M, Issue 0.1, in BrusselsPublication of S4000M, Issue 0.1, in Brussels(together with ASD/AIA S3000L)

2010 Commenting phase and harmonization with international organizations (e.g. ATA, MSG-3 group)

12/2010 End of incorporation of comments (ca. 50-60 extended technical comments)

01/2011 End of editorial finalization of issue 1.0

??/2011 Publication of issue 1.0 (depends on ATA/MSG-3 related constraints)

2012 Issue 1.1 with new chapter OPMOPM (Optimization of Preventive Maintenance during in-service)

ASD S4000MASD S4000MScheduled Maintenance Analysis

Page 3: ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS

3

The specification S4000M is designed to cover the activities of aScheduled Maintenance Analysis (SMA) processScheduled Maintenance Analysis (SMA) process.

Specification is devided in 3 main chapters plus one chapter in preparation:

• System and powerplant analysis

• Structure analysis

• Zonal analysis

• Optimization of Preventive Maintenance (OPM) - new

ASD S4000MASD S4000MScheduled Maintenance Analysis - Content

Page 4: ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS

4

FC = Failure Cause

EFC = External Failure Cause

SafetyS4000M, MSG-3 and RCM

Ecology and lawnew in S4000M !new in S4000M !

Mission and operation S4000M, MSG-3 and RCM

Economy S4000M, MSG-3 and RCM

MSG-2 (civil), RCM MSG-2 (civil), RCM (military)(military)

Bottom upBottom up investigation of failure causes

ASD S4000MASD S4000MMSG-3 (zivil)MSG-3 (zivil)

Top DownTop Down investigation of failure effects and validation of failure

Advantage: also external Advantage: also external failure causes are failure causes are consideredconsidered

failure effects

next higher effects

end effects

The considered failures can be relevant for:

relevant for certification relevant for qualification (acceptance)

ASD S4000MASD S4000MIdentification of critical failures / failure causes of a system

Page 5: ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS

5

Chapter IIChapter II

System and System and Powerplant AnalysisPowerplant Analysis

Chapter IIIChapter III

Structure AnalysisStructure Analysis

Chapter IVChapter IV

Zonal AnalysisZonal Analysis

Chapter IChapter I

IntroductionIntroduction

Chapter VChapter V

Definitions and Definitions and abbreviationsabbreviations

ZonesRemark:Remark:

MSG-3MSG-3 and RCMRCM analysis show gaps concerning Structure and Zonal Analysis.

often specific rules and extensions must be implemented for projects (e.g. by a Project Procedure Handbook - PPHPPH for A380 at Airbus)

ASD S4000MASD S4000MStructure of S4000M chapters

Page 6: ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS

6

OPMprocess

basic information for OPM activities

Operational data

Maintenance concept

Documentation of original results of SMA

as LSA tasks with interval, MTA und

packaging of the tasks

Adjustment of Scheduled Maintenance because of OPM results

! IMPORTANT !

In the LSA database, the complete viewcomplete view on scheduled maintenance is documented:

Single tasks with original interval / packaging / OPM adjustmentSingle tasks with original interval / packaging / OPM adjustment (traceability to original task is guaranteed by complete documentation within LSA database)

OPM process will be integrated into S4000M as an own chapter (in the next issue).

ASD S4000MASD S4000MASD S4000M and OPM (Optimization of Preventive Maintenance)

Page 7: ASD/AIA S3000L Steering Committee (S3000L_SC01) 11.04.-14.04.2011 – Paris, GIFAS

7

In-service experience

OPMprocess

Maintenance concept

Optimization of non-scheduled maintenance

TasksTasks

TasksTasks …

System & Powerplant AnalysisStructure AnalysisZonal AnalysisOPM

Optimization of scheduled maintenance

ASD S4000MASD S4000MRelations of the ILS disciplines and corresponding specifications