  • 7/27/2019 Ash Handling System.ppt

    1/31

    Ash Handling SystemWhat are the types of Ash in Thermal Power

    Plant ?

    Bottom Ash

    Fly Ash

    http://studygalaxy.com/

  • 7/27/2019 Ash Handling System.ppt

    2/31

    Bottom AshThe ash which is directly collected from

    bottom of boiler.

    Bottom ash directly falls down in waterfilled bottom due to gravity.

    Bottom ash is 20% of total ash.

  • 7/27/2019 Ash Handling System.ppt

    3/31

    Fly AshIt is collected from :-

    1-ESP hoppers

    2-Air preheaters hoppers

    3-Economiser hoppers

    It is 80% of total ash.

  • 7/27/2019 Ash Handling System.ppt

    4/31

    Wet systemIn this system ash conveying media is

    water.

    It has two main component:-

    1-Hydro-vactor

    2-Hydro-ejector

  • 7/27/2019 Ash Handling System.ppt

    5/31

    Hydro-vactorWorking Principle:-

    Hopper ash is directly sucked by

    vaccum, which is created by high water

    Jet (hydrovactor).

    This ash mix with water in collectingtank and finally slurry collects in slurrysump.

  • 7/27/2019 Ash Handling System.ppt

    6/31

  • 7/27/2019 Ash Handling System.ppt

    7/31

    Hydro-ejectorWorking Principle:-

    High pressure water jet carriesslurry from the bottom to slurry sump.

    This system operates once in a day

    (24 hrs).

  • 7/27/2019 Ash Handling System.ppt

    8/31

  • 7/27/2019 Ash Handling System.ppt

    9/31

    Final disposal of slurryFinally slurry from slurry sump is

    conveyed by pair of big centrifugal

    pumps to Ash ponds.

    This slurry system is common

    1-for D & E station2-for C & F station

  • 7/27/2019 Ash Handling System.ppt

    10/31

  • 7/27/2019 Ash Handling System.ppt

    11/31

    Fly Ash in Forestry

    Ash pond No1

  • 7/27/2019 Ash Handling System.ppt

    12/31

    Fly Ash in Forestry

    Ash pond No

    1

  • 7/27/2019 Ash Handling System.ppt

    13/31

    Fly Ash in Forestry

    Ash pond No2

  • 7/27/2019 Ash Handling System.ppt

    14/31

    Different Auxillaries in wet

    system (Fstation)1-H.P. pump 3 Nos. 11 kg/cm2

    2-L.P. pump 3 Nos. 6 kg/cm2

    3-Ash slurry pump 3 Nos. in each path2.5 kg/cm2

    4-Air washer pump 2 Nos. 5 kg/cm2

    5-Seal water pump 2 Nos. 18 kg/cm2

  • 7/27/2019 Ash Handling System.ppt

    15/31

    What is the need of dry

    system?It has some good characteristics over

    the wet system:-

    1-Huge quantity ofwater is saved.

    2-Power consumption is less.

    3-Reduction in surface pollution.

    4-Earning, by selling dry ash to cementfactory & bricks manufacturer.

  • 7/27/2019 Ash Handling System.ppt

    16/31

    Components of dry system

    K-pump

    P.D.pump

    Centac compressor

    Acher silo

  • 7/27/2019 Ash Handling System.ppt

    17/31

    K-pumpIt is nothing but the combination of

    silo,Transfer vessel,Dispencing vessel &

    Centrifugal compressor.

    D & E station has common K-pump

    C & F station has another common K-pump.

  • 7/27/2019 Ash Handling System.ppt

    18/31

    Working Principle of K- pumpIt works on the principle ofpressure

    difference.

    Its operation is sequential ,becauseDome Valves from DV-1 to DV-6

    operate in sequence.

  • 7/27/2019 Ash Handling System.ppt

    19/31

  • 7/27/2019 Ash Handling System.ppt

    20/31

    Acher SiloFinally Dry ash is disposed to acher silo

    which is located in AEC campus.

    These are 2 in nos.

    Each has capacity of750 ton .

    INTEGRATED FLY ASH HANDLING SYSTEM: (Schematic flow diagram)

  • 7/27/2019 Ash Handling System.ppt

    21/31

    INTEGRATED FLY ASH HANDLING SYSTEM: (Schematic flow diagram)Stage- I

    C stn. F stn.

    Fly ash Fine Ash Fly ash

    Hoppers Silo (New) Hoppers

    130 Cu.Mtr.

    ( 'C' stn)

    30 TPH

    (After rehibilitation)

    Stage-II 80 TPH

    80 TPH

    Stage-I

    Fine Ash

    Silo (New) E stn. D stn.

    130 Cu.Mtr. Fly ash Fly ash

    ('D/E' stn) Hoppers Hoppers

    80 TPH

    80 TPH

    Stage-II 80 TPH

    To final ash disposal area by closed tanker / truck

    Exist.

    Recip

    Compr

    Compr.

    FINAL FLY ASH

    STORAGE SILO AT

    ACHER

    Capacity :

    750 Cu.Mtr.

    FINAL FLY ASH

    STORAGE SILO AT

    ACHER

    Capacity :

    750 Cu.Mtr.

    Stage II

    CentrifugalCo

    mpr.

    C 1 Existing

    Silo

    (Cap:350 T)

    F stn.

    Intm.

    Hopper

    D/E Exist.

    RCC Silo

    (Cap :450 T)

    Stage I

    Centrifugal

    Compr.

    Stage I

    Centrifugal

    Compr.

    Stage II

    Centrifugal

    Compr.

  • 7/27/2019 Ash Handling System.ppt

    22/31

    Loading of trucks & tankers at

    acherThere are 2 system of loading :-

    1-For truck - water spray system

    2-For tankersby gravity

    D A h l di t A h

  • 7/27/2019 Ash Handling System.ppt

    23/31

    Dry Ash unloading at Acher

    Ash collection in closed tanker at Acher silo

    D A h l di t A h

  • 7/27/2019 Ash Handling System.ppt

    24/31

    Dry Ash unloading at Acher

    Ash collection in closed tanker at Acher silo

  • 7/27/2019 Ash Handling System.ppt

    25/31

    Use of Fly AshFor building construction

    For Cement manufacturing

    For bricks manufacturing

    Ash customers:-

    1-Gujrat ambuja cement

    2-Binani cement, laxmi cement

    3-GCL (RCC pipe mfg.)

    Fl A h d i Bld M t

  • 7/27/2019 Ash Handling System.ppt

    26/31

    Fly Ash used in Bldg. Mat.

    PrivatePrivatePrivate Bungalow Gadhinagr

    Fl A h d i Bld M t

  • 7/27/2019 Ash Handling System.ppt

    27/31

    Fly Ash used in Bldg. Mat.

    Ghodasar Shriji Complex

    Const ction

  • 7/27/2019 Ash Handling System.ppt

    28/31

    Construction

    RCC road near D.M. Plant area

    Construction

  • 7/27/2019 Ash Handling System.ppt

    29/31

    Construction

    RCC road from Crusher house to Coal JN - M

  • 7/27/2019 Ash Handling System.ppt

    30/31

    Future strategiesNow a days we are using almost dry

    system.

    In future our planning is to stop wholewet system except bottom ash which isonly 20%.

    For loading trucks & tankers we arethinking about loading in night shift too.

  • 7/27/2019 Ash Handling System.ppt

    31/31