ASME and NBIC 2015 Edition Changes

Some Highlights of RevisionsTo the 2015 Edition of the NBIC and

ASME Code January 7, 2015

1

Page 2: ASME and NBIC 2015 Edition Changes

Item # Book Section Description14-1296 BPV I Section I, Revisions to PG-2914-1295 BPV I Section I, Replace A-125 with A-31714-1269 BPV I Section I, Review of PG-28 and Stiffening Rings14-1223 BPV I Section I, Table A-356 Line 1914-1179 BPV I Section I, PG-48.1 and Figure A-8(g)14-1074 BPV I Section I, Review of PG-112 Guidance on use of Data Report Forms14-1071 BPV I Section I, Clarify Requirements for Demonstration versus Qualification of NDE Procedures14-606 BPV I Section I Editorial, PW-44.1 and Endnote 814-423 BPV I Section I, Table A-360 Reference to ASTM E8/E8M Tension Testing of Metallic Materials14-422 BPV I Section I, Table A-360 Reference to B18.1.214-419 BPV I Section I, Table A-360 Reference to QAI-114-418 BPV I Section I, Table A-360 Reference to B16.2514-417 BPV I Section I, Table A-360 Reference to B16.2014-416 BPV I Section I, Table A-360 Reference to B16.1514-415 BPV I Section I, Table A-360 Reference to B1.20.114-337 BPV I Preamble, Section I, Addition of Solar Heated Steam Generator13-1964 BPV I Section I - PL-1 Manufacturers Data Report Form for Locomotive Boilers13-1962 BPV I Section I PEB-8.3 Intent Interpretation13-1676 BPV I Section I, PG-31.313-1568 BPV I Section I, PG-31.2, Nomenclature For Term "S"13-1563 BPV I Section I, Proposed Revisions to PHRSG-3.313-1475 BPV I Section I, Incorporation of Code Case 2359-2, Ni-25Cr-9.5Fe-2.1Al Alloy (UNS N06025)13-1474 BPV I Section I, PG-2613-1367 BPV I Section I; Revision to Code Case 2684-1, for UNS N06674, to add the forging product form13-1039 BPV I Section I, Revise Table PG-19 and Table PW-39 to Address Rules for Use of Alloy 80013-974 BPV I Section I, Table A-360 Reference to B16.9-201213-973 BPV I Section I, Table A-360 Reference to B16.34-2013

2

Page 3: ASME and NBIC 2015 Edition Changes

Item # Book Section Description13-972 BPV I Section I, Table A-360 Reference to B16.5-201313-708 BPV I Section I, Table PG-19 Material 310HCbN13-682 BPV I Section I, Editorial Changes Existing Table PW-39-9 and Proposed Table PW-39-1213-675 BPV I Section I, Revise Table PW-39-1, note (a)(1) , Exclude Welded Stays from 200 F Preheat13-318 BPV I Section I, Specification SA-202

13-316 BPV I Section I, PW-39, Table PW-39-1, General Note (a)(2)(a), Clarify CE Limitations for Weld Basemetals

13-128 BPV ISection I, Revision of Code Case 1876-4 to extend the maximum permitted design temperature from the present 1100F (593C) maximum to 1200F (649C) for Grade 91 (9Cr-1Mo-V) wrought material.

13-120 BPV I Incorporation of Code Case 2328-1 in Section I.12-2098 BPV I BPV I Item, Revision to Table 3 in Code Case 223512-2087 BPV I Revision to BPV Section I, PG-26 adding WSRFs for Nickel Base Alloys

12-2086 BPV I Section I, Appendix A-250.2.3, Revise to Clarify Thickness to be Used For Acceptance Criteria.

12-1796 BPV I Section I Adoption of the ASME CA-1 Standard

12-1793 BPV I Section I, Code Case Request – Use of PM/HIP Grade 91 Steel (UNS K91560) supplied under ASTM A989 / A989M-11.

12-1617 BPV I Section I, Parts Fabrication Certificate Program12-1445 BPV I Addition of Part PFE - Requirements for Feedwater Economizers12-1194 BPV I Section I, P-3 & P-6 Forms12-1117 BPV I Section I, Table A-360, ASTM E 125, E 186, E 280 and E 44612-459 BPV I Section I, Part PL Requirements for Locomotive Boilers11-1459 BPV I BPV I Intent Interpretation, PG-110(e)(2)

11-1208 BPV I Section I PW-36.3, Minimum Thickness For Weld Overlay or Weld Metal Buildup Material Assigned a P Number

11-1180 BPV I Section I, Oxide Growth - Ferritic High Temperature Headers10-1776 BPV I BPV I; PRV and PARV Capacity Certification and Nameplate Stamping

3

Page 4: ASME and NBIC 2015 Edition Changes

Section IInterpretation: Section I, Preamble, Definition of Connection to BoilerQuestion: The fourth paragraph of the Preamble defines the point where boiler external piping begins in terms of where the boiler proper terminates at, as follows:

(a) the first circumferential joint for welding end connections; or(b) the face of the first flange in bolted flanged connections; or(c) the first threaded joint in that type of connection; and which extends up to and including the valve or valves required by this Code.

In the case of boilers where the connection contains one or more fittings between the boiler and final point of connection (e.g. welding neck, elbow or tee), must the Manufacturer list the first of any circumferential weld joint, flange face, or threaded joint as the connection on the Manufacturer’s Data Report?Reply:No, one or more fittings may exist between the boiler and external piping provided the Manufacturer defines where the boiler proper terminates and BEP begins.

4

Page 5: ASME and NBIC 2015 Edition Changes

Section IItem Number 14-1074: Section I, PG-112 – Guidance on use of data report forms• New guidance provided for the use of Form P-3, Form P-4,

and Form PL-1

5

Page 6: ASME and NBIC 2015 Edition Changes

Section IItem Number 14-418: Section I, Table A-360 – Reference to B16.25• Year of publication of all ASME standards listed in ANSI B16.25

Mandatory Appendix II removed so that the latest editions of ASME publications apply.

6

Page 7: ASME and NBIC 2015 Edition Changes

Section IItem Number 14-337: Section I, Preamble –Addition of solar heated steam generator• Includes solar receiver steam generators in the scope

of ASME Section I• Preamble Note 6 – “Solar receiver steam generator – a

boiler system in which water is converted to steam using solar energy as the principle source of thermal energy. The solar energy is typically concentrated onto the solar receiver through the use of an array of mirrors that focus solar radiation on the heat transfer surface.”

7

Page 8: ASME and NBIC 2015 Edition Changes

Section IItem Number 12-1796: Section I – Adoption of ASME CA-1 standard• Includes ASME CA-1 standard in requirements for

obtaining and maintaining a Certificate of Authorization• New paragraph PG-105.2 – “Any organization desiring a

Certificate of Authorization shall apply to ASME in accordance with the certification process of ASME CA-1. Authorization to use Certification Marks may be granted, renewed, suspended, or withdrawn as specified in ASME CA-1.”

8

Page 9: ASME and NBIC 2015 Edition Changes

Section IItem Number 12-1617: Section I – Parts fabrication certificate program• New “PRT” fabricated parts designator added for

ASME Certification Mark• New paragraph in Table A-370:

“Certification Mark with ‘PRT’ Designator”‒ “Manufacture of parts without design responsibility for ASME

Section I at the above location only.”‒ Manufacture of parts without design responsibility for ASME

Section I at the above location and field sites controlled by the above location.”

9

Page 10: ASME and NBIC 2015 Edition Changes

10

Page 11: ASME and NBIC 2015 Edition Changes

11

Page 12: ASME and NBIC 2015 Edition Changes

Section IItem Number 12-459: Section I, Part PL –Requirements for Locomotive Boilers• New Part PL added on requirements for locomotive

boilers• PL-1 – “The rules in this Part are applicable to steam

locomotive boilers and their parts and appurtenances. These rules shall be used in conjunction with the general requirements in Part PG, and the specific requirements in the applicable Parts of this Section that apply to the method of fabrication used.”

12

Page 13: ASME and NBIC 2015 Edition Changes

Item # Book Section Description14-986 BPV IV HLW-431.6 Internally Threaded Fittings Attached by Resistance Welding

14-857 BPV IV Section IV - REVISION - Deletion of specific references to II-D, Appendix A, Metallurgical Phenomena - HF-207

14-831 BPV IV BPV IV - Traceability of Multi-page Data Report Forms14-334 BPV IV BPV IV - Traceability of Multi-page Data Report Forms14-328 BPV IV Section IV - Incorporation of Code Case 2654-114-215 BPV IV Section IV - Proposed Revision to New Nonmandatory Appendix A100

13-1961 BPV IV Section IV - HG-307.5 Electric Immersion Heating Element Support Plates - Intent Interp + Code Revision

13-1960 BPV IV Section IV - HG-403 Heating Surface13-1504 BPV IV Section IV - Revisions to Article 2 in Section HC for greater clarity and consistancy13-1502 BPV IV Section IV - Welding on Cast Sections Requirements13-1473 BPV IV Section IV - New Non-mandatory Appendix A

13-1323 BPV IV Section IV - Revisions to Table HF-300.2 and Table 300.2M to permit brazing Forging brass (SB283 UNS C37700).

13-1233 BPV IV Section IV - Manufacturers with multiple locations13-1025 BPV IV Section IV - HG-401.1, Safety Valve Sizing13-197 BPV IV Section IV - HG-530 Marking of Boilers13-194 BPV IV Section IV - Revision to Table HF-300.2 and HF-300.2M13-185 BPV IV Section IV - Incorporation of Case 2615 and Annulment six months after incorporation

13-182 BPV IV Section IV - Incorporation of CC 2614 and Annulment six months after publication of incorporation

13-181 BPV IV Section IV - Incorporation of CC 2583 and Annulment six months after publication12-1798 BPV IV Section IV - Mandatory Appendix 212-277 BPV IV Section IV - Endnote 16 Revision09-756 BPV IV Addition of SA/CSA-G40.21 Grades 44W and 50W to Section IV.

13

Page 14: ASME and NBIC 2015 Edition Changes

Section IVItem Number 14-986: Section IV, HLW-431.6 – Internally threaded fittings attached by resistance welding

14

Page 15: ASME and NBIC 2015 Edition Changes

Section IVItem Number 14-831: Section IV – Traceability of multi-page data report forms• HG-520.4 – “Requirements for completing multiple

pages of Data Report Forms are shown in Appendix 4.”

• Nonmandatory Appendix L was changed to Mandatory Appendix 4‒ Mandatory Appendix 4-100 (a) – “The following pages

are a guide for completing the Manufacturer’s Data Report Forms.”

‒ Additional requirements for multiple page data reports were added to Mandatory Appendix 4

15

Page 16: ASME and NBIC 2015 Edition Changes

16

Page 17: ASME and NBIC 2015 Edition Changes

Section IVItem Number 13-1502: Section IV – Welding on cast section requirements

17

Page 18: ASME and NBIC 2015 Edition Changes

Section IVItem Number 13-1266: Section IV – Manufacturers with multiple locations• HG-520.2 (c) – “Manufacturers with multiple

locations, each with its own Certificate of Authorization, may transfer parts from one its locations to another without Partial Data Reports, provided the Quality Control System describes the method of identification, transfer, and receipt of the parts.”

• Identical new paragraph also added to HLW-601.2 (c)

18

Page 19: ASME and NBIC 2015 Edition Changes

19

Page 20: ASME and NBIC 2015 Edition Changes

Section IVItem Number 13-197: Section IV, HG-530 – Marking of boilers• HG-530.1 (b) – “the information listed in (a) above, including the

Certification Mark, shall be applied by stamping or etching that leaves a permanent, legible mark.”‒ “The process controls for etching shall be described in the Quality Control

System and shall be acceptable to the Authorized Inspector.”‒ “The process controls shall be established so that the etched characters

shall be at least 0.004 in (0.10 mm) deep.”• HG-530.2 (g)(4) – “marking the required data on a nonmetallic

nameplate at least 3 in. x 4 in. (75mm x 100 mm) in size using letters and numerals at least 1/8 in. (3 mm) high and permanently attaching the nameplate to the casing in some conspicuous place by an adhesive system.”

• HG-530.2 (g)(5) – “the nameplate and the adhesive system shall meet the requirements of Appendix 3…”

20

Page 21: ASME and NBIC 2015 Edition Changes

Section IVItem Number 12-1798: Section IV, Mandatory Appendix 2• Latest edition of QAI-1 referenced in Mandatory

Appendix 2• HG-402.2, HG-515.2 (n) – Certified Individuals

certifying Manufacturer’s Data Reports must meet the requirements of the current edition of ASME QAI-1

21

Page 22: ASME and NBIC 2015 Edition Changes

22

Page 23: ASME and NBIC 2015 Edition Changes

23

Page 24: ASME and NBIC 2015 Edition Changes

Item # Book Section Description14-1667 BPV V Section V: Article 13; Revise T-1311

14-1512 BPV V Section V: Article 8 Mandatory Appendix; VIII-810 Revision of the Term Nonmagnetic to Nonferromagnetic.

14-704 BPV V Section V: Article 4, Figure T-434.3-1; Revision to the General Notes

14-639 BPV V Section V: Revision of Article 2, Appendices VIII & IX; Paragraphs VIII-287 and IX-287 on Measuring Scale

14-10 BPV V Section V: Revision of Article 2, Mandatory Appendix V, Definition of "Radiograph"13-2151 BPV V Section V: Revision of Article 12; Change to T-1224.113-1984 BPV V Section V: Revision of Article 2; Mandatory Appendix VI

13-1981 BPV V Section V: Review of ASTM E2491 - 13 Standard Guide for Evaluating Performance Characteristics of Phased-Array Ultrasonic Testing Instruments and Systems

13-1582 BPV V Section V: Consistent Use of the Term "Through Wall" In All Articles of Section V

13-906 BPV V Section V: Review of ASTM A609 / A609M - 12 Standard Practice for Castings, Carbon, Low-Alloy, and Martensitic Stainless Steel, Ultrasonic Examination Thereof for Adoption as SA-609

13-905 BPV V Section V: Review of ASTM A578 / A578M - 07 (2012 Standard Specification for Straight-Beam Ultrasonic Examination of Rolled Steel Plates for Special Applications for Adoption as SA-578

13-904 BPV V Section V: Review of ASTM A577 / A577M - 90(2012) Standard Specification for Ultrasonic Angle-Beam Examination of Steel Plates for Adoption as SA-577

13-877 BPV V Section V: Code Case for the Implementation of the Acoustic Pulse Reflection (APR) Method13-670 BPV V Section V: Article 4, IX-435.4; Weld Joint Configuration and TOFD13-270 BPV V Section V: Revision of T-22413-269 BPV V Section V: Image Brightness Variation Requirements12-2049 BPV V Section V: Review the Use of the Term "Manufacturer" in Section V12-2047 BPV V Section V: Article 7; Documentation Requirements12-2046 BPV V Section V: Article 6; Documentation Requirements

12-2042 BPV V Section V: Review of ASTM E650 / E650M - 12 Standard Guide for Mounting Piezoelectric Acoustic Emission Sensors for Adoption as SE 650

12-2000 BPV V Section V: Mandatory Appendix to Article 4 for the Examination of HDPE

12-1999 BPV V Section V: Review ASTM E2096 / E2096M - 10 Standard Practice for In Situ Examination of Ferromagnetic Heat-Exchanger Tubes Using Remote Field Testing for Adoption as SE2096

24

Page 25: ASME and NBIC 2015 Edition Changes

Item # Book Section Description

12-1998 BPV V Section V: Review ASTM E165 / E165M - 12 Standard Practice for Liquid Penetrant Examination for General Industry for Adoption as SE 165

12-1997 BPV V Section V: Review ASTM D808 - 11 Standard Test Method for Chlorine in New and Used Petroleum Products (High Pressure Decomposition Device Method) for Adoption as SD 808

12-1996 BPV V Section V: Review ASTM D516 - 11 Standard Test Method for Sulfate Ion in Water for Adoption as SD 516

12-1995 BPV V Section V: Review ASTM D129 - 11 Standard Test Method for Sulfur in Petroleum Products (General High Pressure Decomposition Device Method) for Adoption as SD 129

12-1989 BPV V Section V: Review of ASTM A745 / A745M - 12 Standard Practice for Ultrasonic Examination of Austenitic Steel Forgings for Adoption as SA 745

12-1987 BPV V Section V: Article 4; Mandatory Appendices VII and VIII

12-1986 BPV V Section V: Review of ASTM A435 / A435M - 90(2012) Standard Specification for Straight-Beam Ultrasonic Examination of Steel Plates for Adoption as SA-435

12-1907 BPV V Section V: Article 1, T-120 General; Provide an Appendix II Defining Minimum Training and Experience Requirements for Radiographic and Ultrasonic Methods and Their Techniques

12-1886 BPV V Section V: Article 4; T-471.4.1 Scanning Sensitivity and recording data.12-893 BPV V Section V: Article 4; Revision to Mandatory Appendix II-440

11-1975 BPV V Section V: Adopt ASTM E1647 - 09, Standard Practice for Determining Contrast Sensitivity in Radioscopy, for update of SE-1647

11-1528 BPV V Section V: Article 4; New Nonmandatory Appendix Q; Alternate Straight Beam Calibration Block Examples

11-1371 BPV V Section V: Revisions to Article 8, Mandatory Appendix VIII Eddy Current Examination of Nonmagnetic Heat Exchanger Tubing

11-1199 BPV V Section V: ASTM E1139-12 Standard Practice for Continuous Monitoring of Acoustic Emission from Metal Pressure Boundaries

11-1198 BPV V Section V: ASTM E1118/E1118M-11 Standard Practice for Acoustic Emission Examination of Reinforced Thermosetting Resin Pipe (RTRP)

11-1197 BPV V Section V: ASTM E1067/E1067M-11 Standard Practice for Acoustic Emission Examination of Fiberglass Reinforced Plastic Resin (FRP) Tanks/Vessels

25

Page 26: ASME and NBIC 2015 Edition Changes

Item # Book Section Description

11-1196 BPV V Section V: ASTM E750-10 Standard Practice for Characterizing Acoustic Emission Instrumentation

11-1194 BPV V Section V: Adoption of New Article 18 on Guided Wave UT

11-251 BPV V Section V:Article 7; T-762, Yoke Technique Requirements

10-1813 BPV V Section V: Evaluate APR Technology

10-1576 BPV V Section V: Adopt E999-10, Standard Guide for Controlling the Quality of Industrial Radiographic Film Processing

10-1364 BPV V Section V: Definition of "Examination"

10-1214 BPV V Section V: Article 4; New Paragraph T-462.7 and Nonmandatory Appendix P with accompanying Definition.

09-400 BPV V

Section V, Article 6: Define What Steps in the Penetrant Process Are Required to Have Minimum and Maximum Time Limits and Rewrite Requirements for Hydrophilic Emulsifiers to Reflect Current Practice. Revise T-662 to Establish a Maximum Dwell Time Limit and Also Prevent the Penetrant from Drying During the Dwell Time.

06-484 BPV V Section V: Glossary of Terms

04-1472 BPV V Section V: Review Article 13 26

Page 27: ASME and NBIC 2015 Edition Changes

Section VItem Number 13-269: Section V, Mandatory Appendices VIII and IX – Image Brightness Variation Requirements• New text added to paragraph VIII-277.1 – “If verified by

measurement, pixel intensity variations up to 2% are permitted in the determination of “equal to”.

• New text also added to paragraphs VIII-277.3, VIII-282, IX-277.1, IX-277.3, and IX-282.

27

Page 28: ASME and NBIC 2015 Edition Changes

Section VItem Number 09-400: Section V, T-662 – Establish maximum dwell time limit

28

Page 29: ASME and NBIC 2015 Edition Changes

29

Page 30: ASME and NBIC 2015 Edition Changes

Item # Book Section Description14-545 BPV VIII Section VIII, Division 2; Para. 7.5.5.114-499 BPV VIII Section VIII, Division 2; Table 6.1; Equations For Calculating Forming Strains14-35 BPV VIII Section I & Section VIII, Division 1; Code Case 2652, Add N06696 Plate13-2108 BPV VIII Section VIII, Division 1; Revision to Part UIG-23.13-2074 BPV VIII Section VIII, Division 1; UG-100(e)13-1952 BPV VIII Section VIII, Division 1; Partial Incorporation of Code Case 2418-1.13-1950 BPV VIII Section VIII, Division 1; Re-designation of UNS N08904 from SB to SA specifications13-1577 BPV VIII Section VIII, Division 1; Mandatory Appendix 1-4(c)13-1575 BPV VIII Section VIII, Division 1; UW-53 Technique for Ultrasonic Examination of Welded Joints

13-1455 BPV VIII Section VIII, Division 2; Correct nominal compositions in Division 2 Table 3-A.1 for SA-542 classes C and D

13-1423 BPV VIII Section VIII, Division 2; Incorporate Code Case 2295-3, UNS S32906 (29Cr-6.5Ni-2Mo-N)13-1347 BPV VIII Section VIII, Division 3; KT-312 Upper Limit Pressure of Sphere for Hydrostatic Test13-1295 BPV VIII Section VIII, Division 2; Referenced Standards in Table 1.113-1294 BPV VIII Section VIII, Division 1; Referenced Standards in Table U-3

13-1279 BPV VIII Section VIII, Div. 1 & 2; Appendix 26 & 4.19: Correction of membrane stress due to pressure in collar of reinforced bellows and editorial revisions

13-1261 BPV VIII Section VIII, Division 2; 7.5.5.1 – Use of Automated UT

13-1240 BPV VIIISection VIII, Division 1; Expand the description of Combination Units to include dependent chambers in UG-19 and UG-99. Section VIII, Division 2; Expand the description of Combination Units to include dependent chambers in paragraphs 4.1.8 and 8.1.3

13-1152 BPV VIII Section VIII, Division 2; Table 7.4

13-1104 BPV VIII Section VIII, Division 3; Incorporation of Code Case 2524, Inclusion of European Carbon Steel Material (Error Correction)

13-955 BPV VIII Section VIII, Division 3; KD-221.1 and KD 221.2 Clarify application of closed and open end cylinders13-899 BPV VIII Section VIII, Division 2; Paragraph 7.5.5.2 --Acceptance Criteria for UT in Lieu of RT13-878 BPV VIII Section VIII, Division 1; UG-11(d)(5)13-543 BPV VIII Section VIII, Division 1; UG-37(a) – Use of Welded Product Form Specifications13-519 BPV VIII Section VIII, Division 3; Deletion of Nonmandatory Appendix F13-455 BPV VIII Section VIII, Division 1; Part UIG for CCQ and CPQ.

30

Page 31: ASME and NBIC 2015 Edition Changes

Item # Book Section Description13-454 BPV VIII Section VIII, Division 1; UIG-116(b)13-453 BPV VIII Section VIII, Division 1; Part UIG form CMQ13-452 BPV VIII Section VIII, Division 1; Appendix 3913-449 BPV VIII Section VIII, Division 1; UIG-3 - Terminology13-359 BPV VIII Section VIII, Divisions 1 & 2; Appendix 26 & 4.19: Shear Stress in Bellows Under Torsion Load13-292 BPV VIII Section VIII, Divisions 1 and 2; Table UCS-23 - Withdrawal of Specification SA-20213-231 BPV VIII Section VIII Divisions 1 and 2; Incorporation of Code Case 227013-203 BPV VIII Section VIII, Division 1; UG-11(d)13-175 BPV VIII Section VIII, Division 1 UHA-51/Div.2 3.11.4 revisions and interpretations13-132 BPV VIII Section VIII, Division 2; Table 4.2.3 - Materials for Major Attachment Parts

13-63 BPV VIII Section VIII, Division 1; Fig. UG-118 ); Division 2, Paragraph 2-F.1(h),Fig. 2.F.1; Division 3, Fig. KS-132

12-2301 BPV VIII Section VIII, Division 1; UHT-6(b)(2), Division 2, 3.11.3.3(c)12-1723 BPV VIII Section VIII, Division 3; Correction to Equations in KR523 and KR53112-1041 BPV VIII Section VIII, Division 2; Review Environmental Factor for Structural Stress Method in Division 212-942 BPV VIII Section VIII, Division 3; New Certification Mark12-855 BPV VIII Section VIII, Division 1; Table UW-12, General Note (a)

12-772 BPV VIII Section VIII, Division 3; Clean Up Linear Elastic Verbiage in VIII-3

13-737 BPV VIII Section VIII, Division 1; UW-2(a) Lethal Service for Common Elements;12-697 BPV VIII Section VIII, Division 1; UG-131(e)(2), Metrication unit conversion for 1500 psig12-505 BPV VIII Section VIII, Division 3; Update to KD-141 Leak-Before-Burst Mode of Failure to KD-4 Methodology

12-421 BPV VIII Section VIII, Division 1; Intent interpretation with revision to UCL-11; and revision to VIII-2; Part 3.3.6.2.

12-363 BPV VIII Section VIII, Division 3; KD-6 - Threaded Components

12-312 BPV VIIISection VIII, Division 1; Revise Part UHX, Appendix 5 and Appendix 26 to comply with revisions to U-2(g) and consistency with Division 2. Section VIII, Division 2; Revise paragraphs 4.18, 4.19 and 4.20 for consistency with the Division 1 changes relating to U-2(g).

12-11 BPV VIII Section VIII, Division 1; Fig. UW-21 - Weld Size Requirements31

Page 32: ASME and NBIC 2015 Edition Changes

Item # Book Section Description

11-2106 BPV VIII Section VIII, Division 1; Correction of reference paragraphs for overpressure Protection in the Scope and Subsections.

11-1752 BPV VIII Section VIII, Division 3; Materials Permitted11-1575 BPV VIII Section VIII, Division 1; Part UCD11-1461 BPV VIII Section VIII, Division 1: UG-37(g) and (h); Section VIII, Division 2: 4.5.3.2(d)11-1243 BPV VIII Section VIII, Division 2; Paragraph 3.11.2.2 (b) Section VIII, Division 1; Paragraph UCS-66(f)11-997 BPV VIII Section VIII, Divisions 1 and 2; Incorporation of EN 10028-2:2003 Grade 10CrMo9-1011-995 BPV VIII Section VIII, Division 1: UW-27(a); & Section VIII, Division 2: 6.2.1.1 Hybrid Welding Processes11-441 BPV VIII Section VIII, Division 1; Paragraph UG-45 Allowances for Threading11-7 BPV VIII Section VIII, Division 2; Part 5 Local Failure Check11-5 BPV VIII Section VIII, Division 1; UW-12-(d) - Seamless Vessel Section Joint Efficiency

10-1889 BPV VIII Section VIII, Division 3; Incorporation of final revisions to Code Case 2579, Incorporation to Sec VIII Div 3 (related to 10-811)

10-1380 BPV VIII Section VIII, Division 3; Moving KD-240 Linear Elastic Analysis into a New Mandatory Appendix10-173 BPV VIII Section VIII, Division 1; Reassignment of UNS N08904 from SB-674 to SA-249

08-1594 BPV VIII Section VIII, Division 1; Revision to paragraph UG-136(d)(2), UG-137(d)(2), and UG-38(d)(2) Hydrostatic Pressure Test

08-1506 BPV VIII Section VIII, Division 1; UG-40(e) Section VIII, Division 2, 4.5.208-1299 BPV VIII Section VIII, Division 2; Incorporation of Code Case 256208-1255 BPV VIII Section VIII, Divisions1 and 2; Incorporation of Code Case 2637 for UNS S32205 Material08-918 BPV VIII Section VIII, Division 2; Clad Tubesheets08-39 BPV VIII Section VIII, Divisions 1 and 2; PWHT Exemptions in Section VIII - NPS 4 Limitation07-2041 BPV VIII Section VIII, Division 1; U-1(g)(1), UG-116, UG-12007-693 BPV VIII Section VIII, Division 1; Incorporation of Code Case 2244-206-736 BPV VIII Section VIII, Division 1; UNF-79

05-761 BPV VIII Section VIII, Division 3; Incorporation of Code Case 2524, Inclusion of European Carbon Steel Material.

01-061 BPV VIII Section VIII, Division 3; Rupture Disk Devices32

Page 33: ASME and NBIC 2015 Edition Changes

Section VIIIItem Number 13-63: Section VIII, Division 1, Figure UG-118; Division 2, Figure 2.F.1; Division 3, Figure KS-132• Minor changes made to stamping requirements

for all Section VIII pressure vessels‒ “USER” shall be stamped above the certification

mark on the nameplate if inspected by a user’s inspector

33

Page 34: ASME and NBIC 2015 Edition Changes

34

Page 35: ASME and NBIC 2015 Edition Changes

Section VIIIItem Number 08-39: Section VIII, Division 1 and Division 2 – PWHT exemptions, NPS 4 limitation• For Section VIII, Division I tables UCS-56-3 (P No. 4), UCS-

56-4 (P Nos. 5A, 5B, and 5C), and Section VIII, Division 2 tables 6.10 (P No. 4, Groups 1 and 2) and 6.11 (P Nos. 5A, 5B Group 1, and 5C Group 1), postweld heat treatment exemptions can be applied to pipes larger than NPS 4 in diameter, if other requirements are still met

35

Page 36: ASME and NBIC 2015 Edition Changes

Section VIIIItem Number 07-2041: Section VIII, Division 1; U-1(g)(1), UG-116, UG-120• New paragraph UG-116

(f) – “An unfired steam boiler, referenced in U-1 (g)(1), shall have its maximum designed steaming capacity recorded in the ‘Remarks’ section of the data report.”

36

Page 37: ASME and NBIC 2015 Edition Changes

Item # Book Section Description14-1412 BPV IX Section II, Part C, Adoption of AWS A5.5/A5.5M:2014 as SFA-5.5/SFA-5.5M14-1022 BPV IX SC IX; Editorial Markups of SC IX14-1021 BPV IX SC IX; Appendix K14-1020 BPV IX SC IX; Definition of "bare electrode"14-834 BPV IX SC IX; QW/QB-422 and Appendix D inclusion of A/SA-403 WP S3172614-618 BPV IX SC IX; QW-409.114-473 BPV IX SC IX; Forms QF-482 & QF-48314-452 BPV IX SC IX; QW-171 - Impact Testing14-395 BPV IX SC IX; Addition of S31266 Superaustenitic Stainless Steel14-332 BPV IX SC IX; Definition of Special Positions14-331 BPV IX SC IX; Review of AWS B2.2 E4 WD-114-135 BPV IX SC IX; Addition of A694 Grades F48 and F5014-42 BPV IX SC IX; Incorporation of Code Case 2648 (UNS N10362)14-17 BPV IX SC IX; Bend testing of Aluminum13-2287 BPV IX SC IX; Revision of QG-106.213-2104 BPV IX SC IX; QG-106 - Full Supervision & Control During Qualification13-2128 BPV IX SC IX; Addition of A/SA-403 N0890413-2103 BPV IX SC IX; Effective Date of Section IX13-2043 BPV IX SC IX; Table QW-254.1 and Table QW-258.1 - Strip Cladding13-2040 BPV IX SC IX; Table QW/QB-422 - Revise ISO 15608 Ti Groups13-2005 BPV IX SC IX; Revision to QW-50013-1906 BPV IX SC IX; QW/QB-422 - Alloy UNS S32101 for SA-24013-1857 BPV IX SC IX; QW-404.3513-1812 BPV IX SC IX; Incorporation of UNS N08367 for specifications A/SA-182, A403 and A/SA-47913-1793 BPV IX SC IX; Hybrid Variables13-1736 BPV IX Section II, Part C, Adoption of AWS A5.01/A5.01M:2013 as SFA-5.01/SFA-5.01M

37

Page 38: ASME and NBIC 2015 Edition Changes

Item # Book Section Description

13-1703 BPV IX SC IX; Code Case 2143

13-1701 BPV IX SC IX; QW/QB-422 and Appendix D - Inclusion of ASTM A860 Material13-1655 BPV IX Section II, Part C, Adoption of AWS A5.34/A5.34M:2013 as SFA-5.34/SFA-5.34M13-1519 BPV IX SC IX; QW-409.X13-1448 BPV IX SC IX; Table QW-269 and QW-269.113-1447 BPV IX SC IX; Revision of QW-404.45, and Table QW-257.113-1374 BPV IX SC IX; QG-105.3 - Nonessential Variables13-1071 BPV IX SC IX; Unassigned Base Metals used in Welder Qualifications13-1048 BPV IX SC IX; Friction Stir Welding Procedure Qualification13-1047 BPV IX Section II, Part C, Adoption of AWS A5.11/A5.11M:2010 as SFA-5.11/SFA-5.11M

13-1046 BPV IX Section II, Part C, Adoption of AWS A5.16/A5.16M:2013 as SFA-5.16/SFA-5.16M

13-823 BPV IX SC IX; F-number assignment for new SFA 5.10 AWS Classifications13-822 BPV IX SC IX; Request from B31.3: P-number assignment for A928

13-650 BPV IX SC IX; Assignment of a P-No. for UNS N06025

13-468 BPV IX SC IX; QF-464 HSTIT Specimen13-351 BPV IX Section II, Part C, Adoption of AWS A5.22_A5.22M 2012 as SFA-5.22_SFA-5.22M13-350 BPV IX Section II, Part C, Adoption of AWS A5.4/A5.4M:2012 as SFA-5.4/SFA-5.4M13-349 BPV IX Section II, Part C, Adoption of AWS A5.9_A5.9M 2012 as SFA-5.9_SFA-5.9M13-348 BPV IX Section II, Part C, Adoption of AWS A5.1_A5.1M 2012 as SFA-5.1_SFA-5.1M13-293 BPV IX SC IX Table QW_QB-422 and Appendix D - Withdrawal of Specification SA-20213-275 BPV IX SC IX; Appendix K

12-1810 BPV IX SC IX; Addition of brazing filler metal variables QB-403.3 and QB-403.4 and update QB-252, QB-253, QB-254, QB-255, QB-256, QB-257 and QB-351.1(b)

12-1494 BPV IX SC IX; QW-409.26 - Strip Cladding

12-1139 BPV IX SC IX; Review and Update of SWPSs38

Page 39: ASME and NBIC 2015 Edition Changes

Section IXItem Number 13-2128: Section IX – Addition of A/SA-403 N08904• Modified paragraph QG-106.1 (a) - “The personnel

who produce test joints for procedure qualification shall be under the full supervision and control of the qualifying organization during the production of these test joints.”

• Modified paragraph QG-106.2 (a) – “The personnel who produce test joints for performance qualification shall be tested under the full supervision and control of the qualifying organization.”

39

Page 40: ASME and NBIC 2015 Edition Changes

Section IXItem Number 13-2103: Section IX – Effective date of Section IX• New paragraph QG-100 (e) – “New editions to

Section IX may be used beginning with the date of issuance and become mandatory six months after the date of issuance.”

40

Page 41: ASME and NBIC 2015 Edition Changes

Section IXItem Number 13-1071: Section IX – Unassigned base metals used in welder qualifications Expand table QW-423.1 as follows:

Base Metals for Welder Qualification

Qualified Production Base Metals

Any unassigned metal to the same unassigned metal

The unassigned metal to itself

Any unassigned metal to any P-Number metal

The unassigned metal to any metalassigned to the same P-Number as the qualified metal

Any unassigned metal to any other unassigned metal

The first unassigned metal to the second unassigned metal

41

Page 42: ASME and NBIC 2015 Edition Changes

Item # Book Section Description

14-643 BPV X BPVC Section X Corrections

14-150 BPV X BPVC Section X, Composite Pressure Vessels for High Pressure Fluids.

13-666 BPV X Section X, Adoption of the ASME CA-1 Standard

12-382 BPV XII Section XII - New Mandatory Appendix XIX

11-1576 BPV XII Section XII - TG 440 and TP-2

11-369 BPV XII Section XII, Modal Appendix 1 Allowable Stress Criteria

11-311 BPV XII Section XII, TR-100 through TR-140 – General Requirements

10-1390 BPV XII Section XII - Inclusion of Section XII in CC1750

10-1331 BPV XII 1. Section XII - Review of TG-300 2. Substitute "Competent Authority" in place of "Legal Jurisdiction"

08-97 BPV XII Revision to Section XII, TW-100.1 42

Page 43: ASME and NBIC 2015 Edition Changes

Section XItem Number 13-666: Section X – Adoption of CA-1 Standard• New paragraph RS-203 – “ASME may at any time

make regulations concerning the issuance and use of Certification Marks as it deems appropriate, and all such regulations become binding upon the holders of any valid Certificates of Authorization. The regulation and use of stamps shall be in accordance with ASME CA-1: Conformity Assessment Requirements.

43

Page 44: ASME and NBIC 2015 Edition Changes

44

Page 45: ASME and NBIC 2015 Edition Changes

NBIC Part Reference DescriptionPart 1 1.1 Revised Part 1 scope statementPart 1 1.5 Added requirements for changes of service for a pressure retaining itemPart 1 2.1 Revised Part 1, Section 2 scope statementPart 1 2.5.3 Added requirements for electrical potential disconnect for power boilersPart 1 2.6.3.2 Revised requirements for power boiler drain pipingPart 1 2.9.4 Revised requirements for power boiler economizer safety relief valvesPart 1 3.1 Revised Part 1, Section 3 scope statementPart 1 3.5.3.1 Added requirements for electrical potential disconnect for heating boilersPart 1 3.5.3.2 Added requirements for controls and electrical potential disconnects for potable water heatersPart 1 4.1 Revised Part 1, Section 4 scope statement

Part 1 4.5 Added requirements regarding making pressure relief device selection information available to the Jurisdiction

Part 1 5.1 Revised Part 1, Section 5 scope statementPart 1 S3.4 Revised requirements for CO2 gas detection system alarm threshold levelsPart 1 S3.5 Revised requirements for CO2 gas detection system alarm threshold levelsPart 1 S3.5 Added requirements for CO2 vent lines joints and pipingPart 1 Supplement 4 Added new supplement on installation of biomass fired boilersPart 1 Supplement 5 Added new supplement on installation of thermal fluid heatersPart 2 1.6 Added requirements for changes of service for a pressure retaining itemPart 2 2.2.10.6 h) Revised requirements for flow sensing devices on forced circulation boilersPart 2 2.3.6.6 Added requirements for the scope of NBIC Part 2 in regards to DOT transport tanksPart 2 4.4.8.7 Added requirements for leaving widely scattered corrosion pits in a pressure retaining itemPart 2 5.2 Revised requirements for replacement of stamping or nameplate for a pressure retaining itemPart 2 5.3 Revised NB-136 formPart 2 S1.4.2.8.1 Added requirements for bulged stayed sheets in locomotive boilersPart 2 S2.6.3 Added requirements for evaluation of corrosion in historical boilers

45

Page 46: ASME and NBIC 2015 Edition Changes

NBIC Part Reference DescriptionPart 2 S2.8.1 Added requirements for safety relief valves for historical boilersPart 2 S2.10.4 Revised requirements for stayed surfaces for historical boilersPart 2 S2.10.4.2 Added requirements in regards to bulging stayed historical boilers in historical boilersPart 2 S2.10.6 Revised nomenclature section for calculations relating to historical boilersPart 2 S7.10 Added requirements for change of service from above-ground to underground servicePart 2 Supplement 9 Added new supplement on requirements for change of servicePart 2 Supplement 10 Added new supplement on inspection of stationary high pressure composite pressure vesselsPart 3 1.8 Revised requirements for “NR” quality programs

Part 3 2.5.3 Added requirements for nondestructive examination of welds produced with welding methods without postweld heat treatment

Part 3 2.5.3.2 f) Added requirements for NBIC Welding Method 2 regarding hardness and carbon equivalency testing

Part 3 2.5.3.4 f) Added requirements for NBIC Welding Method 4 regarding hardness and carbon equivalency testing

Part 3 2.5.3.5 d) Added requirements for NBIC Welding Method 5 regarding hardness and carbon equivalency testing

Part 3 2.5.3.6 Added new NBIC welding method, Welding Method 6Part 3 3.2.7 Added requirements for changes of service for a pressure retaining itemPart 3 3.3.4.9 Added requirements for tube plugging in a firetube boilerPart 3 5.7.5 Added requirements for method of attaching nameplatesPart 3 5.13.5.1 Revised guide for completing National Board Form NR-1 reportsPart 3 5.13.6.1 Revised guide for completing National Board Form NVR-1 reportsPart 3 S2.13.9.5 Added requirements for historical boiler barrel replacement repairPart 3 S3.5.2.4 Added requirements for finishing repairs on graphite pressure equipmentPart 3 S3.5.5 Added requirements for tube replacement for graphite pressure equipment

Part 3 S6.14-S6.19 Revised and rearranged requirements for registration, stamping, and documentation of "TR" forms

Part 3 S7.14.2 Added requirements for assembly of spring loaded pressure relief valvesParts 1, 2, and 3 Section 9 Added new glossary terms "Biomass Fired Boiler", "Conveyor System", "Dense Phase Pneumatic

System", "Lean Phase Pneumatic System", and "Seal Weld"46

Page 47: ASME and NBIC 2015 Edition Changes

NBICSeveral general revisions were made to the NBIC• Tables and figures – consistency, resolution, numbering,

placement• Complete revision of Index in NBIC Parts 1, 2, and 3• Administrative requirements removed from Part 3 and

posted on National Board web site• Roman numeral pages formatting updated

• Table of contents moved to beginning

• Interpretation index formatting improved – see National Board web site

• Future – color pictures and figures no longer used

47

Page 48: ASME and NBIC 2015 Edition Changes

48

Page 49: ASME and NBIC 2015 Edition Changes

NBICNBIC Part 1, 1.5; Part 2, 1.6; and Part 3, 3.2.7 –Added requirements for changes of service for a pressure retaining item• “See NBIC Part 2, Supplement 9 for requirements

and guidelines to be followed when a change of service or service type is made to a pressure retaining item. Whenever there is a change of service, the jurisdiction where the pressure retaining item is to be operated shall be notified for acceptance, when applicable. Any specific jurisdictional requirements shall be met.”

49

Page 50: ASME and NBIC 2015 Edition Changes

NBICNBIC Part 1, 2.5.3; 3.5.3.1; 3.5.3.2 – Added requirements for electrical potential disconnect• “A disconnecting means capable of being locked in

the open position shall be installed at an accessible location at the boiler so that the boiler can be disconnected from all sources of potential. The disconnecting means shall be an integral part of the boiler or adjacent to it.”

50

Page 51: ASME and NBIC 2015 Edition Changes

NBICNBIC Part 2, 4.4.8.7 – Added requirements for leaving widely scattered corrosion pits in a pressure retaining item• “Widely scattered corrosion pits may be left in the

pressure retaining item in accordance with the following requirements:”‒ “Their depth is not more than one-half the required

thickness of the pressure-retaining item wall (exclusive of corrosion allowance);”

‒ “The total area of the pits does not exceed 7 in.2 (4500 mm2) within any 50 in.2 (32000 mm2); and”

‒ “The sum of their dimension (depth and width) along any straight line within this 50 in.2 (32000 mm2) area does not exceed 2 in. (50 mm).”

51

Page 52: ASME and NBIC 2015 Edition Changes

NBICNBIC Part 3, 1.8 – Revised requirements for “NR” quality programs• Complete revision of National Board “NR”

Accreditation Program• NBIC Part 3, 1.8.1 a) – “This section provides

requirements that must be met for an organization to obtain a National Board Certificate of Authorization to use the “NR” Symbol Stamp for repair/replacement activities to nuclear items constructed in accordance with the requirements of the ASME Code or other internationally recognized codes or standards for construction of nuclear facilities”

52

Page 53: ASME and NBIC 2015 Edition Changes

NBICNBIC Part 3, 3.3.4.9 – Added requirements for tube plugging in a firetube boiler• “When the replacement of a tube in a firetube

boiler is not practicable at the time the defective tube is detected, with the concurrence of the owner, Inspector, and when required, the Jurisdiction, the tube may be plugged…” using the course of repair prescribed in NBIC Part 3, 3.3.4.9

53

Page 54: ASME and NBIC 2015 Edition Changes

54