assembly line balance ok.ppt

Upload: luis-valens

Post on 02-Jun-2018

242 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 assembly line balance OK.ppt

    1/42

    Balance 1

    Assembly Line Balance

  • 8/10/2019 assembly line balance OK.ppt

    2/42

    Balance 2

    Assembly analysis

    Assembly Chart

    It shows the sequence of operations in putting theproduct together. Using the eploded drawing and

    the parts list! the layout designer will diagram theassembly process.

    "he sequence of assembly may ha#e se#eralalternati#es.

    "ime standards are required to decide whichsequence is best. "his process is $nown as assemblyline balancing.

  • 8/10/2019 assembly line balance OK.ppt

    3/42

    Balance %

    "he Assembly Chart

    "he

    assembly chartof a toolbo

  • 8/10/2019 assembly line balance OK.ppt

    4/42

    Balance &

    "ime 'tandards Are (equired for )#ery "as$

  • 8/10/2019 assembly line balance OK.ppt

    5/42

    Balance *

    +lant (ate and Con#eyor 'peed

    Conveyor speed is dependent on the number andunits needed per minute! the si,e of the unit! thespace between units. Conveyor belt speed is

    recorded in feet per minute.

    Example:

    Charcoal grill are in cartons %-%-2& incheshigh. A total of 2!&-- grills are required e#ery day.

  • 8/10/2019 assembly line balance OK.ppt

    6/42

    Balance /

    +lant (ate and Con#eyor 'peed

  • 8/10/2019 assembly line balance OK.ppt

    7/42Balance 0

    Assembly line balancing

    The purpose of the assembly line balancing technique is:1. To equalize the work load among the assemblers2. To identify the bottleneck operation3. To establish the speed of the assembly line4. To determine the number of workstations. To determine the labor cost of assembly and packout!. To establish the percentage workload of each operator". To assist in plant layout#. To reduce production cost

    The assembly line balancing technique builds on:The assembly chart$Time standards$Takt time %minutes&piece' %(lant rate) R *alue)

    (ieces&minutes'.

  • 8/10/2019 assembly line balance OK.ppt

    8/42Balance

    Initial assembly line balancing of toolbo

    "a$t time for 2!--- units per shift! considering 1-3

    downtime and -3 efficiency4 5 .10% minutes per unit.

  • 8/10/2019 assembly line balance OK.ppt

    9/42Balance 6

    Assembly line balancing

    1.+ost of balancing,ubassemblies that cost too high can be taken off the

    line.

    ,-3 could be taken off the assembly line and handledcompletely separate from the main line and we can sa*e money.,-3 .2 / 24 pieces per hour and .41" hour each. 0f balanced)the standard would be 1# pieces per hour and ." hour each.

    ." balanced cost

    .41" by itself cost.14 sa*ings hour per unit

    X ) units per year" hours per year

    $15.00 per hour

    / 1). per year sa*ings

  • 8/10/2019 assembly line balance OK.ppt

    10/42

    Balance 1-

    Assembly line balancing

    ,ubassemblies that can be taken off the line must be:

    1. (oorly loaded. The less percent that is loaded.or e5ample) a ! percent load on the assembly

    line balance would indicate 4 percent lost time.0f we take this 6ob off the assembly line %not tiedto the other operators') we could sa*e 4 percentof the cost.

    2. ,mall parts that are easily stacked and stored.3. 7asily mo*ed. The cost of transportation and the

    in*entory cost will go up) but because of betterlabor utilization) total cost must go down.

  • 8/10/2019 assembly line balance OK.ppt

    11/42

    Balance 11

    Assembly line balancing

    2. 0mpro*ement of assembly line 0mpro*e the busiest %1 percent' workstation first.

    %a' The busiest workstation is (.8. 0t has .1!" minute of work to doper packer. The ne5t closest station is -1 with .1 minute of

    work. -s soon as we identify the busiest workstation) we identify

    it as the 1 percent station) and communicate that this timestandard is the only time standard used on this line from nowon. 7*ery other workstation is limited to 3! pieces per hour.7*en though other workstations could work faster) the 1

    percent station limits the output of the whole assembly line.

    %b' The total hours required to assemble one finished toolbo5 is.!9! hour. The a*erage hourly wage rate times .!9! hourper unit gi*es us the assembly and packout labor cost. -gain)

    the lower this cost is the better the line balance is.

  • 8/10/2019 assembly line balance OK.ppt

    12/42

    Balance 12

    Assembly line balancing

  • 8/10/2019 assembly line balance OK.ppt

    13/42

    Balance 1%

    Assembly line balancing

  • 8/10/2019 assembly line balance OK.ppt

    14/42

    Balance 1&

    Assembly line balancing

    2. 0mpro*ement of assembly line 0mpro*e the busiest %1 percent' workstation first.

    ook at the 1 percent station %(.8.'.

    0f we add a fourth packer) we will eliminate the 1 percent stationat (.8.

    ;ow the new 1 percent %bottleneck station' is -1 %93 percent'.

  • 8/10/2019 assembly line balance OK.ppt

    15/42

    Balance 1*

    'tep7by7step procedure for completing theassembly line balancing form

  • 8/10/2019 assembly line balance OK.ppt

    16/42

    Balance 1/

    'tep7by7step procedure for completing theassembly line balancing form

    9. R *alueThe R *alue goes behind each operation. The plant rate is thegoal of each workstation) and by putting the R *alue on each

    line %operation') one keeps that goal clearly in focus.

    1. +ycle time The time standard.

    11. ;umber of stations

    12. -*erage cycle time

    Rtimecyclestationsofnumber =

    stationsof#

    timecycletimecycleave. =

  • 8/10/2019 assembly line balance OK.ppt

    17/42

    Balance 10

    'tep7by7step procedure for completing theassembly line balancing form

    13.(ercentage load:

    The percentage load tells how busy each workstation is

    compared to the busiest workstation.

    The highest number in the a*erage cycle time column 12 is

    the busiest workstation and) therefore) is called the 1 percentstation.

    ;ow e*ery other station is compared to this 1 percent

    station by di*iding the 1 percent a*erage station time into

    e*ery other a*erage station time. The percent load is an

    indication of where more work is needed or where cost

    reduction efforts will be most fruitful. if the 1 percent station

    can be reduced by 1 percent) then we will sa*e 1 percent for

    e*ery workstation on the line.

  • 8/10/2019 assembly line balance OK.ppt

    18/42

    Balance 1

    'tep7by7step procedure for completing theassembly line balancing form

    13.(ercentage load:

    75ample: percent load of the toolbo5 assembly line balance

    0n igure 411) the a*erage cycle times re*eals that .1!" is the

    largest number and is designated the 1 percent workstation.

    The percentage load of e*ery other workstation is determined by

    di*iding .1!" into e*ery other a*erage cycle time:

    8peration ,,,-1 / .13 & .1!" / 92 percent

    ,,-1 / .14! & .1!" / #" percent

    ,,-2 / .13 & .1!" / "# percent

    and so on.

  • 8/10/2019 assembly line balance OK.ppt

    19/42

    Balance 16

    'tep7by7step procedure for completing theassembly line balancing form

    14.?ours per unit:

    75ample: ?ours per unit of the toolbo5 assembly line balance

    The .1!" time standard is for one person) if considering the people

    number) the hour per unit will be:

    Two people / ." hour per unit

    Three people / .#3 hour per unit

    our people / .1113 hour per unit

    hourperminutes60

    timecycleaverage%100h.p.u.=

    unitperhour.0027860

    .167h.p.u. ==

  • 8/10/2019 assembly line balance OK.ppt

    20/42

    Balance 2-

    'tep7by7step procedure for completing theassembly line balancing form

    1. (iece per hour:0n*ersion of hours per unit.

    1!. Total hours per unit

    ,um of the elements in column 14. or this e5ample is .!9!hour.

    1". -*erage hourly wage rate) say 1 per hour

    1#. abor cost per unit

    Total hours @ a*erage hourly wage

    19. Total cycle time 0t tells us what a perfect line balance would be. 8ur e5ample 3.494 minutes di*ided by ! minutes per hour

    equals .#23 hour per unit.

  • 8/10/2019 assembly line balance OK.ppt

    21/42

    Balance 21

    )fficiency of the assembly line

    %100balanceline1000perhoursofSum

    1000perhoursofSumefficiencyine =

    %100balancelineunitperhoursofSum

    unitperhoursofSumefficiencyine =

    or

    8or our eample9

    %8!%100

    0.06"60

    0.082$efficiencyine ==

  • 8/10/2019 assembly line balance OK.ppt

    22/42

    Balance 22

    Analysis of single model assembly lines

    shw

    ap

    HS

    DR

    #0

    =

    +roduction (ate is gi#en by

    where Rp5 a#erage hourly production rate! units:hr;

    Da

    5 annual demand! units:year;

    Sw5 number of shifts:wee$;

    Hsh5 hrs:shift.

    "his equation assume *- wee$s per year.

  • 8/10/2019 assembly line balance OK.ppt

    23/42

    Balance 2%

    Analysis of single model assembly lines

    p

    c

    R

    ET60

    =

    "he cycle time can be determined as

    where Tc5 cycle time of the line! min.:cycle;

    Rp

    5 production rate! units:hr;

    E 5 line efficiency;

  • 8/10/2019 assembly line balance OK.ppt

    24/42

    Balance 2&

    Analysis of single model assembly lines

    "he cycle rate can be determined as

    where Rc5 cycle rate! cycles:hr;

    Tc

    is in min.:cycle;

    Line efficiency E therefore defined as:

    cc T

    R60

    =

    p

    c

    c

    p

    T

    T

    R

    RE ==

  • 8/10/2019 assembly line balance OK.ppt

    25/42

    Balance 2*

    Analysis of single model assembly lines

    "he number of wor$ers on the line can bedetermined as

    where w5 number of wor$ers on the line;

    WL = wor$load to be accomplished in a gi#en time period.

    T5 a#ailable time in the period.

    AT

    WLw =

    wcpTRWL= TWc = wor$ content time! min:piece.

  • 8/10/2019 assembly line balance OK.ppt

    26/42

    Balance 2/

    Analysis of single model assembly lines

    Using the pre#ious equation! we also ha#e

    "he a#ailable time in the period!T.

    c

    wc

    T

    ETWL60

    =

    T = !"E

    Substitute these terms for WL and AT into wequation, we can state:

    c

    wc

    TTw = integerminimun

    If we assume one wor$er per station! then this ratio alsogi#es the theoretical minimum number of wor$stations onthe line.

  • 8/10/2019 assembly line balance OK.ppt

    27/42

    Balance 20

    Analysis of single model assembly lines

    )ample

    A small electrical appliance is to be produced on a singlemodel assembly line. "he wor$ content of assembling theproduct has been reduced to the wor$ elements listed intable below along with other information. "he line is to bebalanced for an annual demand of 1--!--- units per year."he line will be operated *- wee$s:yr! * shifts:w$! and 0.*hrs:shift.

  • 8/10/2019 assembly line balance OK.ppt

    28/42

    Balance 2

    Analysis of single model assembly lines

    )ample

  • 8/10/2019 assembly line balance OK.ppt

    29/42

    Balance 26

    Analysis of single model assembly lines

    )ample

  • 8/10/2019 assembly line balance OK.ppt

    30/42

    Balance %-

    Analysis of single model assembly lines

    'olution9

    units&hr$$.#$'#.7'(#(#0

    000)100==pR

    b4 "he production rate is9

    c4 "he cycle time Tcwith an uptime efficiency of 6/3 is9

    a4 "he total wor$ content time is9

    Twc5 &.- min.

    .min08.1$$.#$

    '"6.0(60==CT

  • 8/10/2019 assembly line balance OK.ppt

    31/42

    Balance %1

    Analysis of single model assembly lines

    'olution9

    !$.7intmin ==c

    wc

    TTw

    e4 "he a#erage ser#ice time against which the line mustbe balanced is9

    d4 "he theoretical minimum number of wor$ers is gi#en by9

    .min00.108.008.1 === Rcs TTT

  • 8/10/2019 assembly line balance OK.ppt

    32/42

    Balance %2

    Analysis of single model assembly lines

    "he ob>ecti#e in line balancing is to distributethe total wor$load on the assembly line ase#enly as possible among the wor$ers

    =

    *

    1i

    s 'minimi+eor'(minimi+e siwcs T(TTwT

    sub>ect to9

    i,e,(1' sTT

    and

    24all precedence requirements areobeyed.

  • 8/10/2019 assembly line balance OK.ppt

    33/42

    Balance %%

    Analysis of single model assembly lines

    "he algorithms are9

    14Largest Candidate (ule

    24?ilbridge and @ester method

    %4(an$ed positional weights

  • 8/10/2019 assembly line balance OK.ppt

    34/42

    Balance %&

    Largest Candidate (ule

    Step 1:(an$ the "e$s in the descending order.

    Step :Assign the elements to the wor$er at first stationby starting at the top of the list and selecting the firstelement that satisfies precedence requirements and doesnot cause the total sum of "e$ at that station to eceed theallowable "s; when an element is selected for assignmentto the station! start bac$ at the top of the list forsubsequent assignments.

    Step !: when no more element can be assigned withouteceeding "s! then proceed to the net station.

    Step ":repeat steps 2 and % for as many additionalstations as necessary until all elements ha#e beenassigned.

  • 8/10/2019 assembly line balance OK.ppt

    35/42

    Balance %*

    Largest Candidate (ule

    @or$ elements sorted in descending order

  • 8/10/2019 assembly line balance OK.ppt

    36/42

    Balance %/

    Largest Candidate (ule

    'olution9

    "he largest candidate algorithm is carried out as presentedin table below. * wor$ers and stations are required in thesolution. Balance efficiency is computed as9

    8.0'0.1(#

    0.!===

    s

    wc

    wT

    TE

  • 8/10/2019 assembly line balance OK.ppt

    37/42

    Balance %0

    Largest Candidate (ule

    @or$ elements assigned to stations by LC(

  • 8/10/2019 assembly line balance OK.ppt

    38/42

    Balance %

    Analysis of single model assembly lines

    )ample

  • 8/10/2019 assembly line balance OK.ppt

    39/42

    Balance %6

    Analysis of single model assembly lines

    ?ilbridge and @ester method

  • 8/10/2019 assembly line balance OK.ppt

    40/42

    Balance &-

    Analysis of single model assembly lines

    (an$ed positional weights

  • 8/10/2019 assembly line balance OK.ppt

    41/42

    Balance &1

    Analysis of single model assembly lines

    (an$ed positionalweights

    ?ilbridge and@ester method

    Largest Candidate(ule

  • 8/10/2019 assembly line balance OK.ppt

    42/42

    Analysis of single model assembly lines

    #tomation$ %rod#ction Systems$ andComp#ter&'ntegrated (an#)act#ring! By