assembly line balance ok.ppt
TRANSCRIPT
-
8/10/2019 assembly line balance OK.ppt
1/42
Balance 1
Assembly Line Balance
-
8/10/2019 assembly line balance OK.ppt
2/42
Balance 2
Assembly analysis
Assembly Chart
It shows the sequence of operations in putting theproduct together. Using the eploded drawing and
the parts list! the layout designer will diagram theassembly process.
"he sequence of assembly may ha#e se#eralalternati#es.
"ime standards are required to decide whichsequence is best. "his process is $nown as assemblyline balancing.
-
8/10/2019 assembly line balance OK.ppt
3/42
Balance %
"he Assembly Chart
"he
assembly chartof a toolbo
-
8/10/2019 assembly line balance OK.ppt
4/42
Balance &
"ime 'tandards Are (equired for )#ery "as$
-
8/10/2019 assembly line balance OK.ppt
5/42
Balance *
+lant (ate and Con#eyor 'peed
Conveyor speed is dependent on the number andunits needed per minute! the si,e of the unit! thespace between units. Conveyor belt speed is
recorded in feet per minute.
Example:
Charcoal grill are in cartons %-%-2& incheshigh. A total of 2!&-- grills are required e#ery day.
-
8/10/2019 assembly line balance OK.ppt
6/42
Balance /
+lant (ate and Con#eyor 'peed
-
8/10/2019 assembly line balance OK.ppt
7/42Balance 0
Assembly line balancing
The purpose of the assembly line balancing technique is:1. To equalize the work load among the assemblers2. To identify the bottleneck operation3. To establish the speed of the assembly line4. To determine the number of workstations. To determine the labor cost of assembly and packout!. To establish the percentage workload of each operator". To assist in plant layout#. To reduce production cost
The assembly line balancing technique builds on:The assembly chart$Time standards$Takt time %minutes&piece' %(lant rate) R *alue)
(ieces&minutes'.
-
8/10/2019 assembly line balance OK.ppt
8/42Balance
Initial assembly line balancing of toolbo
"a$t time for 2!--- units per shift! considering 1-3
downtime and -3 efficiency4 5 .10% minutes per unit.
-
8/10/2019 assembly line balance OK.ppt
9/42Balance 6
Assembly line balancing
1.+ost of balancing,ubassemblies that cost too high can be taken off the
line.
,-3 could be taken off the assembly line and handledcompletely separate from the main line and we can sa*e money.,-3 .2 / 24 pieces per hour and .41" hour each. 0f balanced)the standard would be 1# pieces per hour and ." hour each.
." balanced cost
.41" by itself cost.14 sa*ings hour per unit
X ) units per year" hours per year
$15.00 per hour
/ 1). per year sa*ings
-
8/10/2019 assembly line balance OK.ppt
10/42
Balance 1-
Assembly line balancing
,ubassemblies that can be taken off the line must be:
1. (oorly loaded. The less percent that is loaded.or e5ample) a ! percent load on the assembly
line balance would indicate 4 percent lost time.0f we take this 6ob off the assembly line %not tiedto the other operators') we could sa*e 4 percentof the cost.
2. ,mall parts that are easily stacked and stored.3. 7asily mo*ed. The cost of transportation and the
in*entory cost will go up) but because of betterlabor utilization) total cost must go down.
-
8/10/2019 assembly line balance OK.ppt
11/42
Balance 11
Assembly line balancing
2. 0mpro*ement of assembly line 0mpro*e the busiest %1 percent' workstation first.
%a' The busiest workstation is (.8. 0t has .1!" minute of work to doper packer. The ne5t closest station is -1 with .1 minute of
work. -s soon as we identify the busiest workstation) we identify
it as the 1 percent station) and communicate that this timestandard is the only time standard used on this line from nowon. 7*ery other workstation is limited to 3! pieces per hour.7*en though other workstations could work faster) the 1
percent station limits the output of the whole assembly line.
%b' The total hours required to assemble one finished toolbo5 is.!9! hour. The a*erage hourly wage rate times .!9! hourper unit gi*es us the assembly and packout labor cost. -gain)
the lower this cost is the better the line balance is.
-
8/10/2019 assembly line balance OK.ppt
12/42
Balance 12
Assembly line balancing
-
8/10/2019 assembly line balance OK.ppt
13/42
Balance 1%
Assembly line balancing
-
8/10/2019 assembly line balance OK.ppt
14/42
Balance 1&
Assembly line balancing
2. 0mpro*ement of assembly line 0mpro*e the busiest %1 percent' workstation first.
ook at the 1 percent station %(.8.'.
0f we add a fourth packer) we will eliminate the 1 percent stationat (.8.
;ow the new 1 percent %bottleneck station' is -1 %93 percent'.
-
8/10/2019 assembly line balance OK.ppt
15/42
Balance 1*
'tep7by7step procedure for completing theassembly line balancing form
-
8/10/2019 assembly line balance OK.ppt
16/42
Balance 1/
'tep7by7step procedure for completing theassembly line balancing form
9. R *alueThe R *alue goes behind each operation. The plant rate is thegoal of each workstation) and by putting the R *alue on each
line %operation') one keeps that goal clearly in focus.
1. +ycle time The time standard.
11. ;umber of stations
12. -*erage cycle time
Rtimecyclestationsofnumber =
stationsof#
timecycletimecycleave. =
-
8/10/2019 assembly line balance OK.ppt
17/42
Balance 10
'tep7by7step procedure for completing theassembly line balancing form
13.(ercentage load:
The percentage load tells how busy each workstation is
compared to the busiest workstation.
The highest number in the a*erage cycle time column 12 is
the busiest workstation and) therefore) is called the 1 percentstation.
;ow e*ery other station is compared to this 1 percent
station by di*iding the 1 percent a*erage station time into
e*ery other a*erage station time. The percent load is an
indication of where more work is needed or where cost
reduction efforts will be most fruitful. if the 1 percent station
can be reduced by 1 percent) then we will sa*e 1 percent for
e*ery workstation on the line.
-
8/10/2019 assembly line balance OK.ppt
18/42
Balance 1
'tep7by7step procedure for completing theassembly line balancing form
13.(ercentage load:
75ample: percent load of the toolbo5 assembly line balance
0n igure 411) the a*erage cycle times re*eals that .1!" is the
largest number and is designated the 1 percent workstation.
The percentage load of e*ery other workstation is determined by
di*iding .1!" into e*ery other a*erage cycle time:
8peration ,,,-1 / .13 & .1!" / 92 percent
,,-1 / .14! & .1!" / #" percent
,,-2 / .13 & .1!" / "# percent
and so on.
-
8/10/2019 assembly line balance OK.ppt
19/42
Balance 16
'tep7by7step procedure for completing theassembly line balancing form
14.?ours per unit:
75ample: ?ours per unit of the toolbo5 assembly line balance
The .1!" time standard is for one person) if considering the people
number) the hour per unit will be:
Two people / ." hour per unit
Three people / .#3 hour per unit
our people / .1113 hour per unit
hourperminutes60
timecycleaverage%100h.p.u.=
unitperhour.0027860
.167h.p.u. ==
-
8/10/2019 assembly line balance OK.ppt
20/42
Balance 2-
'tep7by7step procedure for completing theassembly line balancing form
1. (iece per hour:0n*ersion of hours per unit.
1!. Total hours per unit
,um of the elements in column 14. or this e5ample is .!9!hour.
1". -*erage hourly wage rate) say 1 per hour
1#. abor cost per unit
Total hours @ a*erage hourly wage
19. Total cycle time 0t tells us what a perfect line balance would be. 8ur e5ample 3.494 minutes di*ided by ! minutes per hour
equals .#23 hour per unit.
-
8/10/2019 assembly line balance OK.ppt
21/42
Balance 21
)fficiency of the assembly line
%100balanceline1000perhoursofSum
1000perhoursofSumefficiencyine =
%100balancelineunitperhoursofSum
unitperhoursofSumefficiencyine =
or
8or our eample9
%8!%100
0.06"60
0.082$efficiencyine ==
-
8/10/2019 assembly line balance OK.ppt
22/42
Balance 22
Analysis of single model assembly lines
shw
ap
HS
DR
#0
=
+roduction (ate is gi#en by
where Rp5 a#erage hourly production rate! units:hr;
Da
5 annual demand! units:year;
Sw5 number of shifts:wee$;
Hsh5 hrs:shift.
"his equation assume *- wee$s per year.
-
8/10/2019 assembly line balance OK.ppt
23/42
Balance 2%
Analysis of single model assembly lines
p
c
R
ET60
=
"he cycle time can be determined as
where Tc5 cycle time of the line! min.:cycle;
Rp
5 production rate! units:hr;
E 5 line efficiency;
-
8/10/2019 assembly line balance OK.ppt
24/42
Balance 2&
Analysis of single model assembly lines
"he cycle rate can be determined as
where Rc5 cycle rate! cycles:hr;
Tc
is in min.:cycle;
Line efficiency E therefore defined as:
cc T
R60
=
p
c
c
p
T
T
R
RE ==
-
8/10/2019 assembly line balance OK.ppt
25/42
Balance 2*
Analysis of single model assembly lines
"he number of wor$ers on the line can bedetermined as
where w5 number of wor$ers on the line;
WL = wor$load to be accomplished in a gi#en time period.
T5 a#ailable time in the period.
AT
WLw =
wcpTRWL= TWc = wor$ content time! min:piece.
-
8/10/2019 assembly line balance OK.ppt
26/42
Balance 2/
Analysis of single model assembly lines
Using the pre#ious equation! we also ha#e
"he a#ailable time in the period!T.
c
wc
T
ETWL60
=
T = !"E
Substitute these terms for WL and AT into wequation, we can state:
c
wc
TTw = integerminimun
If we assume one wor$er per station! then this ratio alsogi#es the theoretical minimum number of wor$stations onthe line.
-
8/10/2019 assembly line balance OK.ppt
27/42
Balance 20
Analysis of single model assembly lines
)ample
A small electrical appliance is to be produced on a singlemodel assembly line. "he wor$ content of assembling theproduct has been reduced to the wor$ elements listed intable below along with other information. "he line is to bebalanced for an annual demand of 1--!--- units per year."he line will be operated *- wee$s:yr! * shifts:w$! and 0.*hrs:shift.
-
8/10/2019 assembly line balance OK.ppt
28/42
Balance 2
Analysis of single model assembly lines
)ample
-
8/10/2019 assembly line balance OK.ppt
29/42
Balance 26
Analysis of single model assembly lines
)ample
-
8/10/2019 assembly line balance OK.ppt
30/42
Balance %-
Analysis of single model assembly lines
'olution9
units&hr$$.#$'#.7'(#(#0
000)100==pR
b4 "he production rate is9
c4 "he cycle time Tcwith an uptime efficiency of 6/3 is9
a4 "he total wor$ content time is9
Twc5 &.- min.
.min08.1$$.#$
'"6.0(60==CT
-
8/10/2019 assembly line balance OK.ppt
31/42
Balance %1
Analysis of single model assembly lines
'olution9
!$.7intmin ==c
wc
TTw
e4 "he a#erage ser#ice time against which the line mustbe balanced is9
d4 "he theoretical minimum number of wor$ers is gi#en by9
.min00.108.008.1 === Rcs TTT
-
8/10/2019 assembly line balance OK.ppt
32/42
Balance %2
Analysis of single model assembly lines
"he ob>ecti#e in line balancing is to distributethe total wor$load on the assembly line ase#enly as possible among the wor$ers
=
*
1i
s 'minimi+eor'(minimi+e siwcs T(TTwT
sub>ect to9
i,e,(1' sTT
and
24all precedence requirements areobeyed.
-
8/10/2019 assembly line balance OK.ppt
33/42
Balance %%
Analysis of single model assembly lines
"he algorithms are9
14Largest Candidate (ule
24?ilbridge and @ester method
%4(an$ed positional weights
-
8/10/2019 assembly line balance OK.ppt
34/42
Balance %&
Largest Candidate (ule
Step 1:(an$ the "e$s in the descending order.
Step :Assign the elements to the wor$er at first stationby starting at the top of the list and selecting the firstelement that satisfies precedence requirements and doesnot cause the total sum of "e$ at that station to eceed theallowable "s; when an element is selected for assignmentto the station! start bac$ at the top of the list forsubsequent assignments.
Step !: when no more element can be assigned withouteceeding "s! then proceed to the net station.
Step ":repeat steps 2 and % for as many additionalstations as necessary until all elements ha#e beenassigned.
-
8/10/2019 assembly line balance OK.ppt
35/42
Balance %*
Largest Candidate (ule
@or$ elements sorted in descending order
-
8/10/2019 assembly line balance OK.ppt
36/42
Balance %/
Largest Candidate (ule
'olution9
"he largest candidate algorithm is carried out as presentedin table below. * wor$ers and stations are required in thesolution. Balance efficiency is computed as9
8.0'0.1(#
0.!===
s
wc
wT
TE
-
8/10/2019 assembly line balance OK.ppt
37/42
Balance %0
Largest Candidate (ule
@or$ elements assigned to stations by LC(
-
8/10/2019 assembly line balance OK.ppt
38/42
Balance %
Analysis of single model assembly lines
)ample
-
8/10/2019 assembly line balance OK.ppt
39/42
Balance %6
Analysis of single model assembly lines
?ilbridge and @ester method
-
8/10/2019 assembly line balance OK.ppt
40/42
Balance &-
Analysis of single model assembly lines
(an$ed positional weights
-
8/10/2019 assembly line balance OK.ppt
41/42
Balance &1
Analysis of single model assembly lines
(an$ed positionalweights
?ilbridge and@ester method
Largest Candidate(ule
-
8/10/2019 assembly line balance OK.ppt
42/42
Analysis of single model assembly lines
#tomation$ %rod#ction Systems$ andComp#ter&'ntegrated (an#)act#ring! By