assessment and retrofit of concrete structures
TRANSCRIPT
-
8/13/2019 Assessment and Retrofit of Concrete Structures
1/20
By
V.Parameswari
A0104394J
-
8/13/2019 Assessment and Retrofit of Concrete Structures
2/20
The process of deterioration of reinforcement due to
chemical or electrochemical change caused in presence of
moisture.
It is a process of returning of a metal to its original
state(ore) by oxidation.
2Fe(s) + O2(g) + H2O(l) Fe(OH)2
Removal of damaged concrete as it may contain cracks,
delamination, etc
If the reinforcing member has rust should be cleaned and aprotective coat may be applied.
Highly corroded steel area which needs replacement.
Replace the removed concrete which prevents the ingress of
corrosion.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
3/20
DIAGONOSIS
PHYSICAL
INSPECTION
STUDY OF
DOCUMENTS
ESTIMATION OFLOAD ACTING
ESTIMATINGENVIRONMENTAL
EFFECTS
RETROSPECTIVEANALYSIS
IS DIAGONOSIS
CONFIRMED
ESTIMATION FOR
FUTURE USE
ASSESMENT OF
STRUCTURAL
ADEQUACY
LOAD TEST
YES
NO
MATERIAL TEST
CHOICE OFACTION
-
8/13/2019 Assessment and Retrofit of Concrete Structures
4/20
One of the cause for corrosion in underground MRT tunnelis water infiltration.
The cracks and rust strains are formed on reinforced
concrete lining segments may be due to
Chlorine attack
Carbonation
Sulfate attack
Alkali-aggregate reaction (AAR)
Delayed ettringite formation(DEF)
-
8/13/2019 Assessment and Retrofit of Concrete Structures
5/20
Soils containing sulphates of calcium sodium, potassiumand magnesium are the primary source of sulphate ions in
groundwater.
A high sulphate content in water is generally indicative of
the presence of magnesium and alkali sulphates. In
combination with ammonium, chloride, nitrate andcarbonate ions the sulphate ion attack is more severe.
The sulfate attack on concrete manifests itself in the form
of expansion, cracking, loss of mass and/or disintegration.
As far as corrosion in underground tunnel DEF will be the
major problem. It is a special case of sulphate attackwhere sulphate ions are formed within the concrete. It
causes swelling of concrete and thus forming map
cracking.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
6/20
In Singapore, MRT are operated all throughout the day.
The possibility of executing the repair strategies in during
the night time from 12am to 5.30am.
Since the testing also done in the night temperature limits
are not taken into account.
If temperature is considered there could be moreconcentration of corrosion.
And can also be done at the intervals of two trains arrival
about 10 min gaps.
The regions which needs repairing can be separated into
different parts so that job can be carried out day by daywithout interruption of traffic.
Planning and scheduling the repairing works for each day.
Involving a small group of skilled labours to complete the
work in time, economically and efficiently.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
7/20
Half cell potential
Ultra sonic pulse velocity (UPV)
Measured by using a digital voltmeter and corrosion of
reinforcements are studied at several points.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
8/20
The results are plotted to get
the contour map of corrosion
of reinforcement.
In tunnels ,indirect transmission method can be followedbecause only one face of the concrete is accessible.
T R
KEY
T-Transmitter
R-Receiver
-
8/13/2019 Assessment and Retrofit of Concrete Structures
9/20
The dynamic modulus of elasticity of concrete is measured bymeasuring the velocity of ultrasonic pulse through concrete.
The test equipment has provisions for generating ultrasonicpulse, transmitting it to concrete, receiving and amplifyingthe pulse and measuring and displaying the pulse travel time.
Good acoustic coupling between the transducers andconcrete is to be established for correct measurement of thespeed.
By this technique one can assess the quality of concrete suchas honey combing & compaction
UPV value in km/sec (V) Concrete quality
V greater than 4.0 Very good
V between 3.5 and 4.0 Good, but may be porous
V between 3.0 and 3.5 PoorV between 2.5 and 3.0 Very poor
V between 2.0 and 2.5 Very poor and low integrity
V Less than 2.0 and reading fluctuating No integrity,
large voids suspected
-
8/13/2019 Assessment and Retrofit of Concrete Structures
10/20
Ultra sonic pulse velocity method is used to find out the
internal cracks and depth of visible cracks causes by
sulphate attack.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
11/20
Strategy 1:
Corrosion inhibitors
Using high grade mix proportion with silica fumes as
mortar
Quick setting cement
Epoxy injection and grouting
Strategy2:
Epoxy coating of reinforcement
Strategy 3: Using zinc primer coating
Strategy 4:
Cathodic protection
-
8/13/2019 Assessment and Retrofit of Concrete Structures
12/20
The surface of the damaged area is removed as there will
be map cracking due to sulphate attack. As the concrete cover is removed the reinforcement is
exposed.
If the reinforcement inside the old concrete had been
severely damaged or had lost substantial proportion of its
cross-sectional area by corrosion ,it may need to bereplaced by new bars.
Replacement is necessary if it had lost more than 10-20%
of the cross-sectional area.
Less corroded reinforcements are cleaned and worn out
reinforcements are replaced. The old concrete surface at the back of the reinforcements
are grouted with epoxy.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
13/20
The new concrete cover is made with a high grade of mixproportions with silica fumes and quick setting compoundlike calcium phosphate is used.
Quick Setting Concrete attains initial setting within15minutes under normal conditions and should be placed
immediately upon mixing. Leave at least 2 hours after
setting before applying any load. It gives a good
compressive strength at earliest time.
Corrosion inhibitors like calcium nitrite is also added tothe concrete.
These admixture forms a passive film (-FeOOH)around the
reinforcements and thus resisting from corrosion. Itprotects from chlorides and sulphates attack.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
14/20
Silica fumes are added to
Make the concrete dense and prevents from shrinkage cracks.
To reduce the chloride associated corrosion and sulphateattack.
To control alkali-silica reaction
to conserve cement
To produce ultra high strength of concrete.
Epoxy coating is a best way to prevent corrosion of
reinforcement if it is done at the early stage.
Since the reinforcement cannot be fully removed and
coated with epoxy this method also fails. One more disadvantage is that when the epoxy coating
breaks that acts as the anode and gets easily corroded.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
15/20
Apply zinc primer coating on the reinforcements wherezinc gets oxidized and acts as a sacrificial film.
Application of zinc primer fails as the reinforcement hasto be fully removed from the concrete structures.
It is costly and time consuming.
Cathodic protection can be also adopted to resist thecorrosion.
The damaged concrete cover is removed.
Sacrificial anodes (e.g.Zn,Mg) can be provided at definiteintervals along with the reinforcements.
Sacrificial anodes takes up the corrosion and they geteasily oxidized.
Thus preventing the reinforcement from corrosion.
This method is time consuming .
-
8/13/2019 Assessment and Retrofit of Concrete Structures
16/20
Therepair material used should be studied on thefollowing properties to have a good bonding with the old
concrete structures:
compatibility requirements of new and old materials
Compatibility in dimensional stability
Shrinkage of concrete
Thermal expansion of concrete
and also some lab tests for bond strength , shear tests and
compression and shear test had to be done.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
17/20
The repaired works are monitored in a periodic intervals.
The concrete is checked whether it had attained a good
bonding with the old concrete.
If any small cracks are formed during the time of
monitoring, Drill in to the crack from the face of concrete
Water or solvent is injected to flush the dirt and foreign
matter.
The surface is allowed to dry
The Epoxy is injected until it floes out through the holes
So it helps in preventing cracks in the future which will
lead to corrosion.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
18/20
Fromthe above all methods using corrosion inhibitors inthe concrete is the economical way.
It does not require much skilled labours.
As quick setting cement is used it will definitely will not
hinder the traffic.
Less time consumption.
Number of labours required is also less.
Materials used are cost effective.
-
8/13/2019 Assessment and Retrofit of Concrete Structures
19/20
REFERENCE MATERIALS:Structural renovation in concrete,by Zongjin Li,Christopher Leung,and Yunping
Xi published by Taylor & Francis 2009
Repair and protection of concrete structures, by Noel.Pmailvaganam,CRC
Press,1992
http://www.youtube.com/watch?v=RAlC75xG4qU
http://www.fhwa.dot.gov/bridge/tunnel/maintman00.cfm
Causes, Evaluation, and Repair of Cracks in Concrete Structures. In Lindsay
Kennedy (ed.) (1998), Concrete repair manual, pp. 453-474 (Causes, Evaluation,
and Repair of Cracks.pdf)
Diagnosis of Deterioration in Concrete Structures: Identification of Defects,
Evaluation and Development of Remedial Action. In Lindsay Kennedy (ed.)
(1998), Concrete repair manual, pp. 198-206 (Diagnosis of deterioration in
concrete structures.pdf)
Electrochemical Tests for Reinforcement Corrossion. In Lindsay Kennedy (ed.)(1998), Concrete repair manual, pp. 413, 424-431 (Electrochemical tests for
reinforcement corrosion.pdf)
Non-structural Cracks in Concrete. In Lindsay Kennedy (ed.) (1998), Concrete
repair manual, pp. 475-497 pt. 1 (Non-structural cracks in concrete pt.1.pdf)
-
8/13/2019 Assessment and Retrofit of Concrete Structures
20/20