assessment and retrofit of concrete structures

Upload: sidharth-mahajan

Post on 04-Jun-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    1/20

    By

    V.Parameswari

    A0104394J

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    2/20

    The process of deterioration of reinforcement due to

    chemical or electrochemical change caused in presence of

    moisture.

    It is a process of returning of a metal to its original

    state(ore) by oxidation.

    2Fe(s) + O2(g) + H2O(l) Fe(OH)2

    Removal of damaged concrete as it may contain cracks,

    delamination, etc

    If the reinforcing member has rust should be cleaned and aprotective coat may be applied.

    Highly corroded steel area which needs replacement.

    Replace the removed concrete which prevents the ingress of

    corrosion.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    3/20

    DIAGONOSIS

    PHYSICAL

    INSPECTION

    STUDY OF

    DOCUMENTS

    ESTIMATION OFLOAD ACTING

    ESTIMATINGENVIRONMENTAL

    EFFECTS

    RETROSPECTIVEANALYSIS

    IS DIAGONOSIS

    CONFIRMED

    ESTIMATION FOR

    FUTURE USE

    ASSESMENT OF

    STRUCTURAL

    ADEQUACY

    LOAD TEST

    YES

    NO

    MATERIAL TEST

    CHOICE OFACTION

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    4/20

    One of the cause for corrosion in underground MRT tunnelis water infiltration.

    The cracks and rust strains are formed on reinforced

    concrete lining segments may be due to

    Chlorine attack

    Carbonation

    Sulfate attack

    Alkali-aggregate reaction (AAR)

    Delayed ettringite formation(DEF)

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    5/20

    Soils containing sulphates of calcium sodium, potassiumand magnesium are the primary source of sulphate ions in

    groundwater.

    A high sulphate content in water is generally indicative of

    the presence of magnesium and alkali sulphates. In

    combination with ammonium, chloride, nitrate andcarbonate ions the sulphate ion attack is more severe.

    The sulfate attack on concrete manifests itself in the form

    of expansion, cracking, loss of mass and/or disintegration.

    As far as corrosion in underground tunnel DEF will be the

    major problem. It is a special case of sulphate attackwhere sulphate ions are formed within the concrete. It

    causes swelling of concrete and thus forming map

    cracking.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    6/20

    In Singapore, MRT are operated all throughout the day.

    The possibility of executing the repair strategies in during

    the night time from 12am to 5.30am.

    Since the testing also done in the night temperature limits

    are not taken into account.

    If temperature is considered there could be moreconcentration of corrosion.

    And can also be done at the intervals of two trains arrival

    about 10 min gaps.

    The regions which needs repairing can be separated into

    different parts so that job can be carried out day by daywithout interruption of traffic.

    Planning and scheduling the repairing works for each day.

    Involving a small group of skilled labours to complete the

    work in time, economically and efficiently.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    7/20

    Half cell potential

    Ultra sonic pulse velocity (UPV)

    Measured by using a digital voltmeter and corrosion of

    reinforcements are studied at several points.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    8/20

    The results are plotted to get

    the contour map of corrosion

    of reinforcement.

    In tunnels ,indirect transmission method can be followedbecause only one face of the concrete is accessible.

    T R

    KEY

    T-Transmitter

    R-Receiver

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    9/20

    The dynamic modulus of elasticity of concrete is measured bymeasuring the velocity of ultrasonic pulse through concrete.

    The test equipment has provisions for generating ultrasonicpulse, transmitting it to concrete, receiving and amplifyingthe pulse and measuring and displaying the pulse travel time.

    Good acoustic coupling between the transducers andconcrete is to be established for correct measurement of thespeed.

    By this technique one can assess the quality of concrete suchas honey combing & compaction

    UPV value in km/sec (V) Concrete quality

    V greater than 4.0 Very good

    V between 3.5 and 4.0 Good, but may be porous

    V between 3.0 and 3.5 PoorV between 2.5 and 3.0 Very poor

    V between 2.0 and 2.5 Very poor and low integrity

    V Less than 2.0 and reading fluctuating No integrity,

    large voids suspected

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    10/20

    Ultra sonic pulse velocity method is used to find out the

    internal cracks and depth of visible cracks causes by

    sulphate attack.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    11/20

    Strategy 1:

    Corrosion inhibitors

    Using high grade mix proportion with silica fumes as

    mortar

    Quick setting cement

    Epoxy injection and grouting

    Strategy2:

    Epoxy coating of reinforcement

    Strategy 3: Using zinc primer coating

    Strategy 4:

    Cathodic protection

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    12/20

    The surface of the damaged area is removed as there will

    be map cracking due to sulphate attack. As the concrete cover is removed the reinforcement is

    exposed.

    If the reinforcement inside the old concrete had been

    severely damaged or had lost substantial proportion of its

    cross-sectional area by corrosion ,it may need to bereplaced by new bars.

    Replacement is necessary if it had lost more than 10-20%

    of the cross-sectional area.

    Less corroded reinforcements are cleaned and worn out

    reinforcements are replaced. The old concrete surface at the back of the reinforcements

    are grouted with epoxy.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    13/20

    The new concrete cover is made with a high grade of mixproportions with silica fumes and quick setting compoundlike calcium phosphate is used.

    Quick Setting Concrete attains initial setting within15minutes under normal conditions and should be placed

    immediately upon mixing. Leave at least 2 hours after

    setting before applying any load. It gives a good

    compressive strength at earliest time.

    Corrosion inhibitors like calcium nitrite is also added tothe concrete.

    These admixture forms a passive film (-FeOOH)around the

    reinforcements and thus resisting from corrosion. Itprotects from chlorides and sulphates attack.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    14/20

    Silica fumes are added to

    Make the concrete dense and prevents from shrinkage cracks.

    To reduce the chloride associated corrosion and sulphateattack.

    To control alkali-silica reaction

    to conserve cement

    To produce ultra high strength of concrete.

    Epoxy coating is a best way to prevent corrosion of

    reinforcement if it is done at the early stage.

    Since the reinforcement cannot be fully removed and

    coated with epoxy this method also fails. One more disadvantage is that when the epoxy coating

    breaks that acts as the anode and gets easily corroded.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    15/20

    Apply zinc primer coating on the reinforcements wherezinc gets oxidized and acts as a sacrificial film.

    Application of zinc primer fails as the reinforcement hasto be fully removed from the concrete structures.

    It is costly and time consuming.

    Cathodic protection can be also adopted to resist thecorrosion.

    The damaged concrete cover is removed.

    Sacrificial anodes (e.g.Zn,Mg) can be provided at definiteintervals along with the reinforcements.

    Sacrificial anodes takes up the corrosion and they geteasily oxidized.

    Thus preventing the reinforcement from corrosion.

    This method is time consuming .

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    16/20

    Therepair material used should be studied on thefollowing properties to have a good bonding with the old

    concrete structures:

    compatibility requirements of new and old materials

    Compatibility in dimensional stability

    Shrinkage of concrete

    Thermal expansion of concrete

    and also some lab tests for bond strength , shear tests and

    compression and shear test had to be done.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    17/20

    The repaired works are monitored in a periodic intervals.

    The concrete is checked whether it had attained a good

    bonding with the old concrete.

    If any small cracks are formed during the time of

    monitoring, Drill in to the crack from the face of concrete

    Water or solvent is injected to flush the dirt and foreign

    matter.

    The surface is allowed to dry

    The Epoxy is injected until it floes out through the holes

    So it helps in preventing cracks in the future which will

    lead to corrosion.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    18/20

    Fromthe above all methods using corrosion inhibitors inthe concrete is the economical way.

    It does not require much skilled labours.

    As quick setting cement is used it will definitely will not

    hinder the traffic.

    Less time consumption.

    Number of labours required is also less.

    Materials used are cost effective.

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    19/20

    REFERENCE MATERIALS:Structural renovation in concrete,by Zongjin Li,Christopher Leung,and Yunping

    Xi published by Taylor & Francis 2009

    Repair and protection of concrete structures, by Noel.Pmailvaganam,CRC

    Press,1992

    http://www.youtube.com/watch?v=RAlC75xG4qU

    http://www.fhwa.dot.gov/bridge/tunnel/maintman00.cfm

    Causes, Evaluation, and Repair of Cracks in Concrete Structures. In Lindsay

    Kennedy (ed.) (1998), Concrete repair manual, pp. 453-474 (Causes, Evaluation,

    and Repair of Cracks.pdf)

    Diagnosis of Deterioration in Concrete Structures: Identification of Defects,

    Evaluation and Development of Remedial Action. In Lindsay Kennedy (ed.)

    (1998), Concrete repair manual, pp. 198-206 (Diagnosis of deterioration in

    concrete structures.pdf)

    Electrochemical Tests for Reinforcement Corrossion. In Lindsay Kennedy (ed.)(1998), Concrete repair manual, pp. 413, 424-431 (Electrochemical tests for

    reinforcement corrosion.pdf)

    Non-structural Cracks in Concrete. In Lindsay Kennedy (ed.) (1998), Concrete

    repair manual, pp. 475-497 pt. 1 (Non-structural cracks in concrete pt.1.pdf)

  • 8/13/2019 Assessment and Retrofit of Concrete Structures

    20/20