    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Risk

    Expenditure

    Asset Management and Cost Saving

    Maintenance Strategy based on

    Risk-Informed Decision Making.Cost effective, reliable, and safe through TV gAte and ROI

  • 8/22/2019 Asset Management and Risk Management Dnv

    2/14

    2

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Our World is changing

    SOMEHOWRISK-INFORMED

    Costs mustbe decreased

    Increasing

    responsibility

    Worldwidecompetition

    ...........

    Increased flexibilityneeded

    Adaptedavailability needed

    Knowledge Based

    The Others are

    doing itMore or LessPRESCRIPTIVE

  • 8/22/2019 Asset Management and Risk Management Dnv

    3/14

    3

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Understanding of RISK

    Risk = Probability of Failure (PoF) x Consequence of Failure (CoF)

    Whats really new?

    Integral Approach new, traceable assessment criteria risk assessment requires multi-disciplinary team all type of equipment considered under one hat

    more distinctive regarding the identification ofdamage/deterioration mechanism to addressoptimized inspection techniques

    remnant life related (for predictable mechanism) confidence related

    PoF

    CoFSHE-related

    Costs-related

    systematic introduction of CoF

    distinction between SHE and Cost/Reliability CoF

  • 8/22/2019 Asset Management and Risk Management Dnv

    4/14

    4

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Related Guidelines and Documents

    ASME Risk Based InspectionVol. 1 General DocumentVol. 3 Fossil Fuel Fired Electric Power Generating Systems

    EPRI Risk Based In-Service Inspection Evaluation Procedure WOG Application of Risk Based Methods for Piping In-Service Inspection API (American Petroleum Institute)

    API 579 Fitness for ServiceAPI RP 580 Risk Based Inspection (qualitative)API RP 581 Risk Based Inspection (qualitative/quantitative)

    Development of an European Guideline for Risk Based ISI/IST

    and Maintenance:

    Risk Based In-Service Inspection and Maintenance Procedures for European Industries

  • 8/22/2019 Asset Management and Risk Management Dnv

    5/14

    5

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Rank

    ing

    Risk-MatrixRisk-Matrix

    Engineering Judgement Semi-Quantitative Analysis Cause-Consequence A. System Simulation ....

    Optimization

    Safety and Economic relatedOptimization

    ISI/IST Scope, Locations,Method, and Frequency

    Monitoring Design modifications Spare Parts Operation ....

    Scaffolding Insulation Inspections

    Servicing ....

    Realiza

    tion

    Planning andCoordination

    Nr Vorgangsname

    1 Projekt lei tung2 Marktverantwortung

    3 Projektvorlauf

    7 Kick-of f -Meet ing

    8 TP1: Sichtung / Met

    13 Information / Kontro

    17 TP2: Vernetzung / E

    23 TP3: Datenbasis

    27 Information / Kontro

    31 TP4: Mitarbeiter

    35 TP5: Vermarktung

    40 Information / Kontro

    44 A bsch luss

    45 Projektnachlauf

    Kauer

    Schmitt,Schrder,S

    Projektteam

    12/23

    1011121 2 3 4 5 6 7 8 91011121 2 3 4 5 6 7 8 9 1 011121 2 3 4 5 6 7 8 9 10

    ft e 1 . H lft e 2 . H lft e 1 . H l ft e 2 . H l ft e 1 . H l ft e 2. Hlfte

    Expe

    rtPanel

    Plant Specific Data

    Generic DataData

    Mining

    Inspection Reports

    Operating Window

    Medium / Hazards

    Damage/Deterioration

    Mechanism

    Reliability Data

    ....

    Regulatory

    Requirements

  • 8/22/2019 Asset Management and Risk Management Dnv

    6/14

    6

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    TV-Software based Procedure

    Representation of the contributionto risk of the subcomponents ofthe component 01P002:

    PoFi * CoFi

  • 8/22/2019 Asset Management and Risk Management Dnv

    7/14

    7

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Inspection and Maintenance Planning

    Risk-informed decision making using the risk matrix as central elementfor the long term strategy and day to day work planning

    I: Run to FailureCorrective MaintenanceAim at zero expenditure

    I

    II

    IIII

    15 17

    86 6

    5

    17 8

    1

    0

    2

    19

    31

    8231

    2 2 05 2

    18

    11 6 215 4

    Consequence of Failure (CoF)

    ProbabilityofFailure(PoF

    )

    Economic Risk Ranking Diagram

    II: ALARPAs Low as Reasonably Practicable viaPeriodical and Condition BasedMaintenance corresponding to riskPrinciple of expenditure minimization

    III: UnacceptableUrgent measures like Change ofDesign, and/or Operation, Repair etc.

    Principle of Risk Mitigation

  • 8/22/2019 Asset Management and Risk Management Dnv

    8/14

    8

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Risk-Orientied Master Plan

    Explicit measures are planned on the basis of

    the risk identified the information regarding risk driving components,subcomponents and damage/deterioration mechanisms

    the information regarding acting damage/deteriorationmechanisms, remnant life and the confidence level achieved,through which adapted and adequate measures can beselected

    the overall confidence level

    by considering resources, spare part situation, .....

  • 8/22/2019 Asset Management and Risk Management Dnv

    9/14

    9

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Detailed Planning

    No PoFReductionpossible

    Notpossible

    predictable f(t)

    Calculate RemnantUseful Life

    ConfidenceAssessment

    Determine Interval, Method,Scope, and Place

    f (Risk, Remnant Useful Life,Confidence)

    Reductionof PoF

    ConfidenceAssessment

    non-predictable

    Monitoring possible?

    ConditionMonitoring

    InfluenceMonitoring

    ConfidenceAssessment

    Determine Interval, Method,Scope, and Place

    f (Risk, Confidence)

    Reductionof Pof

    Damage /DeteriorationMechanism

  • 8/22/2019 Asset Management and Risk Management Dnv

    10/14

    10

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Example 1: Shut-down postponement of a refinery

    Discussion with the authority regarding the generalpossibility to extend the prescribed interval and aboutthe method going to be used

    Assessment of 464 Subcomponents

    Risk Ranking Result: - Extreme High: 0 %

    - Very High: 7 %- High: 20 %- Medium: 33 %

    - Low: 40 %

    Extension more or less no problem for most of the equipment

    At the end there were 25 pieces of equipment for which it wassimply not possible to extend the interval in the first place

  • 8/22/2019 Asset Management and Risk Management Dnv

    11/14

    11

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Example 1: Shut-down postponement

    For those 25 we developed a detailed procedure how toreplace the internal by non-intrusive inspections(formalistic speaking the non-intrusive is replacing the

    internal inspection)

    The result was that this is possible for additionally 15 pieces

    of equipmentResult:10 pieces of equipment (out of 464) remaining to be

    internally inspected, repaired, or replaced at the originallyscheduled inspection time

    Big Shut Down could be postponed(Savings > 8 Mio EUR)

  • 8/22/2019 Asset Management and Risk Management Dnv

    12/14

    12

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Example 2: Economic Strategy (Combined Cycle)

    heatrecoverysteamgenerator

    gasturbine

    fuelgas

    air intake

    exhaustgas

    water steamcycle

    gene-rator

    electric power

    steam

    turbinegene-rator

    Plant Control

    Gas- line 1

    Gas- line 2

    Bypass 1

    Bypass 2

    Steam- generator1

    Steam- generator2

    Steam- line

    Condensatsystem

    Feedwater system

    Coolingsystem

    Circuit breaker

    Transformers

    SystemausflleFehler pro Historie

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    Fa

    ilures

    Main Components

    84,74

    %8

    4,5

    2%

    8

    4,2

    6%

    80,1

    3%

    79,6

    7%

    78,7

    5%

    509,99

    517,36

    521,01

    74,00%

    76,00%

    78,00%

    80,00%

    82,00%

    84,00%

    86,00%

    Concept 1 Concept 2 Concept 3

    485

    490

    495

    500

    505

    510

    515

    520

    525

    averag

    ePower[MW]

    PmittelAF

    NCF

    The Decision for Concept 1 resultedin saving 40% of capital investment

  • 8/22/2019 Asset Management and Risk Management Dnv

    13/14

    13

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Optimization targets in ROI

    Identification (ranking) of critical systems and components

    Identification of possible damage / deterioration mechanisms

    Suitable inspection and maintenance methods

    Determination of scope, location, and intervals

    Economic balance

    Documentation and traceability

    Adjusted requirements for specifications, quality, certification,...(Risk Oriented Design, Risk Oriented Quality), Insurance Risk,

    .....

  • 8/22/2019 Asset Management and Risk Management Dnv

    14/14

    14

    TV Sddeutschland Bau und Betrieb GmbH

    SDDEUTSCHLAND

    Summary

    ; Cost OptimizationAppropriate balance between costs and benefits

    ; Cost ConcentrationPrioritizing on relevant and critical systems and components

    ; Cost TraceabilitySystematic decision making on thebasis of traceable measures

    ; Code ComplianceAPI, ASME, RIMAP, ...national standards

    Risk

    Expenditure