at co pipelines 2

Upload: caleyramsay

Post on 04-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 At Co Pipelines 2

    1/10

    Safey Frs. Aways.

    Urban PpeneRepacemen Projec

    Edmonon, Abera

    A NAtURAl GAS PiPEliNE iNitiAtivE

  • 7/30/2019 At Co Pipelines 2

    2/10

    Background

    Projec Oerew

    Safey Frs. Aways.

    For more than 100 years ATCO Pipelines has saely

    and reliably transported natural gas rom producers to

    communities and industrial customers through a networko high-pressure pipelines. For residential customers, these

    high-pressure lines eed the low-pressure local distribution

    pipelines, managed by companies such as ATCO Gas, that

    deliver the natural gas to homes and businesses.

    In the 1950s and 60s a network o high-pressure

    pipelines was built on, what was predominately, the

    outskirts o both Edmonton and Calgary to deliver

    natural gas to the growing communities.

    Over the years, urban development in Edmonton and

    Calgary has overgrown the network o high-pressure

    natural gas pipelines placing homes, schools and

    businesses adjacent to these lines.

    This has created three serious concerns or ATCO Pipelines:

    1. Public Saety Due to the proximity o these

    pipelines to densely populated areas, and the very

    high pressures at which they operate, an incident

    involving these pipelines has the potential or tragic

    consequences.

    Additionally, despite our best eorts to educate the

    public, pipelines are still hit by third parties during

    excavation activities. The current location o these

    pipelines continues to make them vulnerable

    to damage and increases the risk that an incident

    will occur.2. Construction Standards - These pipelines were

    constructed to the standards o 50 years ago and are

    more vulnerable to ailure as they near the end o their

    expected operating lie as high-pressure lines.

    Pipelines built to todays standards have the

    advantage o substantial improvements in materials,

    inspection capabilities and damage prevention

    technologies that reduce the risk o an incident.

    3. Meeting Demand - As Edmonton and Calgary

    continue to grow in size and population, the location

    and capacity o the existing high-pressure networkwill not be able to meet the associated growth in

    demand or natural gas in these cities.

    This situation is a matter o public saety that is

    challenging cities across North America. There have

    already been serious incidents in other jurisdictions

    prompting ATCO Pipelines to re-evaluate the integrity

    o its existing pipeline network.

    As a result, ATCO Pipelines has developed a solution

    that will dramatically improve public saety and

    ensure that customers receive sae, reliable natural

    gas service or decades to come.

  • 7/30/2019 At Co Pipelines 2

    3/10

    the Projec

    Make your oce heard! Open Houses:Century Hotel and Casino

    13103 Fort Road | Thurs. Dec. 6, 4 - 9pm

    Four Points by Sheraton Edmonton Gateway10010 12 Avenue SW | Sun. Dec. 9, 11am - 4pm

    Delta Edmonton South Hotel

    4404 Gateway Boulevard | Mon. Dec. 10, 4 - 9pm

    Radisson Hotel Edmonton South

    4440 Gateway Boulevard | Tues. Dec. 11, 4 - 9pm

    Edmonton Marriott at River Cree Resort

    300 East Lapotac Boulevard (Enoch, AB)

    Wed. Dec. 12, 4 - 9pm

    ATCO Pipelines has developed a proactive solution,

    the Urban Pipeline Replacement (UPR) Project, that

    will be considered or approval by the Alberta UtilitiesCommission (AUC).

    The UPR Project is composed o 10 distinct projects

    that, i approved, will see a new, modern high-pressure

    network o natural gas pipelines constructed inside the

    Transportation/Utility Corridor (TUC) o each city over a

    period o fve years.

    Unlike many other jurisdictions in North America,

    Edmonton and Calgary beneft rom the Province

    o Albertas oresight in establishing the TUCs in the

    1970s to accommodate utility inrastructure as well

    as a ring road. These corridors were specifcally

    designed to provide a controlled space to saely locate

    inrastructure or the growing cities.

    By shiting the high-pressure transmission o natural

    gas to a new, modern pipeline network located within

    the designated TUCs, theUPR Project will reduce the

    risk o a serious incident by up to 95%.

    The new pipelines will have signifcant technological

    improvements over the existing high-pressure network

    including:

    modern pipeline coatings that better protect

    the pipe rom corrosion;

    enhanced welding practices that reduce the

    occurrence o leaks;

    inspection o 100% o the welds during

    construction;

    inline inspection capabilities that will detectdeects in pipelines and identiy repairs required

    prior to an incident occurring, and

    remote monitoring technologies that provide early

    warning o threats to the integrity o the pipeline.

    By shiting the high-pressure transmission o natural gas

    to the TUC, the UPR Project will greatly improve public

    saety and provide the additional capacity to meet the

    growing demand or natural gas.

    ATCO Pipelines believes that the UPR Project is the

    only viable solution to address the long-term saetyand growth o the Edmonton system.

    Cos of he UPR ProjecTheprojectwillbemanagedandfundedby

    ATCO Pipelines, an investor-owned utility, that

    ultimately recovers its costs through customer natural

    gas bills. The impact on customers bills will be

    incrementally phased in over a period o fve years.

    By the end o the project, the average residential bill

    will increase by less than $2 per month.

    ThetotalcostoftheUPRprojectisapproximately

    $600-700 million, which includes the cost to integrate

    the new high-pressure network with the ATCO Gas

    low-pressure distribution system.

    An important component o our submission to the

    Alberta Utilities Commission will be the eedback we

    receive rom you. Online, on the phone, or in person,ATCO Pipelines is committed to listening to your

    comments, answering your questions, addressing

    your concerns and sharing your eedback.

    You can make your voice heard by completing and

    submitting the attached comment card, calling us at

    1-855-802-7546 (Mon. to Fri., 8am - 6pm), visiting our

    web site at www.atcopipelines.com/upr or meeting

    with us at one o the Open Houses.

  • 7/30/2019 At Co Pipelines 2

    4/10

    EdmononPipeli

    neMap

    NaturalGasPip

    elinestoberemoved

    fromH

    igh-Pres

    sureService

    Transportation/

    Utility

    CorridorBound

    aries

    ExistingHigh-P

    ressure

    NaturalGasPip

    elines

    ProposedRelocationof

    High-PressurePipelines

    Foradetailedview

    ofthismap

    visitwww.a

    tcopipelines.com/up

    r

  • 7/30/2019 At Co Pipelines 2

    5/10

    TheTransportation/UtilityCo

    rridors(TUCs)weredesignedtofacilitate

    infrastructuredevelopmentinEdmontonandCalgarybyaccom

    modating

    theprovincialringroadsystem,majorpowerlines,pipelines,regional

    waterandsewerlinesandtelecommunicationlines.

    Thecorridorsarenearlyakilometrewideandprovideasafe

    designatedspacetoplaceh

    igh-pressurenaturalgaspipelines

    .

    Theywereestablishedtoprotectutilityalignmentsfroma

    dvancingurban

    developmenta

    ndofferalong-terms

    olutiontomanyofthelanduse

    challengesass

    ociatedwithdevelopingmajorfacilitiesinanurbansetting.

    TheTUCinEd

    montonincludesAnthonyHenday

    Driveand

    Highway216(Hwy14X).

    transporaion/U

    iliyCorridors(tUCs)

    S a f e y F i r s A l w a y s

  • 7/30/2019 At Co Pipelines 2

    6/10

    the Consequences of NOtProceedng wh he UPR Projec

    Safey Frs. Aways.

    I the Urban Pipeline Replacement (UPR) Project is not

    approved, ATCO Pipelines will pursue a course o action

    to improve the standards o the existing high-pressurepipelines in their current locations.

    This will be carried out over two phases. The frst phase

    requires substantial work just to prepare the lines or

    the testing and ongoing inspection activities that will

    determine their reliability. The second phase will then

    replace those sections o the 50 to 60-year-old pipelines

    that ail the testing or are deemed unreliable.

    Both o these phases will require major construction

    activities that will disturb your neighbourhoods, roadways

    and green spaces, as well as cause disruptions to yournatural gas service as the pipelines are being tested

    and replaced.

    We estimate the cost to complete the work that prepares

    the pipelines or testing and ongoing inspection

    capabilities to be approximately $200 million. There

    will be additional costs incurred to replace unsuitable

    sections o the pipeline. The scope o the required

    replacements can only be determined once the testing

    is completed.

    Under the UPR Project, the existing pipelines would be

    either decommissioned or converted to distribution lines

    carrying natural gas at a much lower, and saer, pressure.

    While these upgrades will improve the integrity o the

    existing pipelines, they do not address our other primary

    concerns. It leaves the pipelines near where we live,

    work and play. Without the ability to meet the growing

    demand or natural gas, new pipelines may still have to

    be constructed in the Transportation/Utility Corridor (TUC

    in the uture.

    This is why we believe the UPR Project is the only

    viable solution. Building new, modern pipelines in

    the TUC will dramatically improve public saety by

    reducing the risk o an incident and protecting the

    pipelines rom other construction activities, while also

    ensuring we can meet the demand or natural gas as

    the cities continue to grow.

  • 7/30/2019 At Co Pipelines 2

    7/10

    Frequeny Asked Quesons

    What is natural gas used or?

    Natural gas is delivered to the vast majority o Alberta

    homes through a network o high-pressure and low-

    pressure pipelines. Natural gas uels many o the comorts

    o our daily lives including heat or homes through natural

    gas urnaces, hot water through hot water tanks, as well as

    cooking appliances, clothes dryers and freplaces. Natural

    gas is also used to generate the electricity that powers

    homes and businesses across the province.

    Are the existing urban high-pressure pipelines sae?

    The current system is operating saely. We undertake

    an intensive integrity program that includes cathodic

    protection surveys and leak inspections, as well as

    monitoring our lines 24-hours-a-day through our Control

    Centre.However,manyofthepipelineswereconstructed50 to 60 years ago. The new pipelines will beneft rom

    the advancements in materials, construction practices

    and damage prevention technologies, and be located

    within the saety o the designated Transportation/Utility

    Corridor (TUC).

    What is the dierence between the high-pressure

    pipelines used or transmission and the low-pressure

    lines used or distribution?

    High-pressuretransmissionpipelinesarethemost

    efcient way to transport large amounts o natural gas

    rom producers to communities and industrial customers.

    Large volumes o gas in the pipeline increase the pressure

    in the pipeline. For residential customers, the high-

    pressure transmission pipelines eed local distribution

    pipelines, managed by companies such as ATCO Gas.

    There are more than 9,000 kilometres o distribution

    pipelines running throughout Edmonton and Calgary

    bringing natural gas directly into your home. The

    distribution pipelines operate at a much lower pressure,

    as the amount o gas travelling through them is much less.A pipeline ailure caused by a leak or hit line at these lower

    pressures is less likely to result in a serious incident.

    Why is it important to move high-pressure pipelines

    to the TUCs?

    Given the high pressures these pipelines operate at, any

    ailure or damage to the pipeline can result in a serious

    incident. This presents a signifcant risk to public saety.

    I a serious incident were to occur in a densely populated

    area it could have tragic consequences.

    Why are you not moving all high-pressure pipelines

    to the TUCs?

    The lines that are not part o this project are either

    located in industrial areas that require high-pressure

    service or are already in a defned corridor and have

    been constructed to current standards.

    What will happen to the old high-pressure pipelines

    near my home?

    I the Urban Pipeline Replacement Project is approvedthere will be 260 kilometres o high-pressure pipelines

    in Edmonton and Calgary removed rom high-pressure

    service. Where appropriate, some o these pipelines will

    be converted to low-pressure distribution service.

  • 7/30/2019 At Co Pipelines 2

    8/10

    Please

    provi

    Name:

    Address:

    Phone

    orEm

    We need your oce.An important component o our submission to

    the Alberta Utilities Commission will be the

    eedback we receive rom you. Online, on the

    phone, or in person, ATCO Pipelines is committed

    to listening to your comments, answering your

    questions, addressing your concerns and sharing

    your eedback.

    This issue is a matter o public saety that will

    have a direct impact on your home and amily.

    You can make your voice heard by completing

    the attached comment card, calling us at

    1-855-802-7546 (Monday to Friday, 8am - 6pm),

    visiting our web site at www.atcopipelines.com/upr

    or meeting with us at one o the Open Houses.

    Iaminte

    Thankyouorprovidin

    willbeconsultingwith

    mayprovidetousinco

    youareaskingtoparti

    wetakeyour

    privacys

    ofcerat403-245-7060

  • 7/30/2019 At Co Pipelines 2

    9/10

    For more than 100 years, ATCO Pipelines has owned andoperated key pipeline inrastructure throughout Alberta

    that transports natural gas to utilities, power generators

    and major industries.

    With ofces in Edmonton and Calgary and acilities

    throughout the province, ATCO Pipelines is committed

    to operating in a responsible and sustainable manner.Our success depends on building and maintaining a sae

    and reliable natural gas pipeline system, while meeting

    high environmental standards and developing strong

    community relationships.

    ATCO Pipelines is part o the ATCO Group o Companies

    an investor-owned, Alberta-based, worldwideorganization with more than 8,800 employees that

    deliver service excellence and innovative business

    solutions through leading companies engaged

    in Structures & Logistics, Utilities, Energy and

    Technologies.

    More inormation can be ound at www.atcopipelines.com

    Who s AtCO Ppenes?

  • 7/30/2019 At Co Pipelines 2

    10/10

    Your inpu s CrcaATCO Pipelines believes that sae communities must be a

    priority. The only way to ensure the right decision is made or

    your home and amily is to get involved and provide your input.Online, on the phone, or in person, ATCO Pipelines is committed

    to listening to your comments, answering your questions,

    addressing your concerns and sharing your eedback.

    Visitwww.atcopipelines.com/upr

    Call1-855-802-7546(Mon.toFri.8am-6pm)

    Completeandreturnthefeedbackcard

    attached to this document

    AttendoneofourOpenHouses

    ATCO Pipelines would like to talk to you in person. Listed

    belowareanumberofOpenHouseswewillbehostingto

    walk you through the details o the project. We will have our

    project experts there to answer any questions you may have.

    I these dates do not work or you and you would like to see

    us in person, please call us at 1-855-802-7546 and we will

    be happy to come and visit you at your home.

    Open House Dates:Thurs. Dec. 6, 4 - 9pm

    Century Hotel and Casino

    Sun. Dec. 9, 11am - 4pm

    Four Points by Sheraton Edmonton Gateway

    Mon. Dec. 10, 4 - 9pm

    Delta Edmonton South Hotel

    Tues. Dec. 11, 4 - 9pm

    Radisson Hotel Edmonton South

    Wed. Dec. 12, 4 - 9pm

    Edmonton Marriott at River Cree Resort

    Note: See page 3 or Open House addresses

    Safey Frs. Aways.