08/06/2022 NokiaSiemensNetworks ATCA HW TEST WEEKLY MEETING 1 (45) Li Li ATCA HW Test Project __ Weekly Meeting Minutes Date and time Every Wendesday @ 13:30 – 15:00 Place 10001 MeetingRoom, 10F, Building 89, No. 1122, North Qinzhou Road, SH Participants Presen t 10.19 10.26 10.1 2 Li Li 4, chair&sec X X X Zhang Rongqiang(Robin) X Ari Helminen X X X Mao Wenjie X X X Zhang Rui 2 X X X Zhang Jerry Q X X X Han Yong 1 X X X Li Zhiguang X X X Wang Jing 4 (NE_RCC) Liao Changmao X X X Xu Li 1 X Sang Haichao X X Liu Chuanrong X X X Zeng Rui X Ji Ping (NE_Thermal) Meng Yang (NE_DIMM) Lv Sen (NE_SFP) Zheng Chunlei (NE_Mech.) Meeting Minutes:

Upload: richard-pascual

Post on 13-Dec-2015

317 views

Category:

Documents


16 download

TRANSCRIPT

Page 1: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 1 (34)Li Li

ATCA HW Test Project __ Weekly Meeting Minutes

Date and time Every Wendesday @ 13:30 – 15:00Place 10001 MeetingRoom, 10F, Building 89, No. 1122, North Qinzhou Road, SH。Participants Presen

t10.19 10.26 10.1

2Li Li 4, chair&sec X X XZhang Rongqiang(Robin)

X

Ari Helminen X X XMao Wenjie X X XZhang Rui 2 X X XZhang Jerry Q X X XHan Yong 1 X X XLi Zhiguang X X XWang Jing 4 (NE_RCC)Liao Changmao X X XXu Li 1 XSang Haichao X XLiu Chuanrong X X XZeng Rui XJi Ping (NE_Thermal)Meng Yang (NE_DIMM)Lv Sen (NE_SFP)Zheng Chunlei (NE_Mech.)

Meeting Minutes: Whole Version (till Oct. 26)

https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D425051129 AB MN —Common Part (since Oct. 27)https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D436675532 AB4 Part (since Oct. 27)https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D436677461

ATCA Test Tool WikiPage: https://twiki.inside.nokiasiemensnetworks.com/bin/view/ShanghaiHWTestTeam/ATCATestTool

Page 2: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 2 (34)Li Li

Page 3: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 3 (34)Li Li

Agenda ItemsNO. Topic Deadlin

eResponsible Additional Information

Main Target Jun ~ Aug

All team 1). Demo of the completed Automation cases---- Every month, 1-2 categories selected for Demo of ATCsJun. 8: meeting with David for the Demo workshops organization, Once per 2weeksJun. 23: 1st ATC Demo by Sang Haichao (FRU Info.)Jul. 5: 2nd ATC Demo by Li Zhiguang & HanYong (Warm Reset, IPMI_Stress)Aug. 19: 3rd ATC Demo by XuLi(LA) & HanYong(BMC) Room 401 (loop Sun Chunjie, Sergio)Sep. 7: David starts to track ATC in 2H2011, and 1H2012.Sep. 21: 170/281 Automated, 101/281 non-fully-automated David: 2 more ATCs will be added at W1138 (Kontron will provide the Robot cases example at W1138)Sep. 28: 2 new ATCs added, 172/281 ATC, 99/281 non-fully-automatedOct. 12: 171/270=63.33%

2). Communication with Specialists & Customers ---- Clarify the HPRS for AB4 Building BlocksAug. 31: Throughput Discussion will be the main topic with Espoo Switch Experts (Mikko Piironen) CETH109 for AHUB3-B, AHUB4-A, AMPP2-A, ADSP2-A etc.Sep. 28: Li Li reminded Mikko Piironen for this clarification

---- Lesson Learned by analysising the “Closed with Correction” Prontos Jun. 14: done for Radisys, KontronJun. 15: done for Schroff/PPS, EmersonE-Jul: more APP related IPH Prontos need to be controlled by SIV, based on the CT from HZ

---- Set up Complex test configuration, with necessary Test SW installedJul. 11: FUMI/DIMI functionality test clarified with Antonio Moschini

---- Clarify the Test Scope among Vendors &SIV& CustomersJul ~ Aug: Radisys onsite support

---- Competence transfer from HZ MGW TW team, support more TDM API test on SCNAM-B/CJul. 15: Kickoff leading by Fang Haibin; Zhang Hai hold the weekly review meetingJul. 27: SIV configuration & trip preparation done by Li Li & Han Yong, need Ari’s comments before sending out.Aug. 10: TestCase list received from Peng Zhijiang;

SIV’s trip to HZ for API planned at Sep.1 & Sep. 2; ADX usage can be supported in Aug remotely. (Zhu Qingsong)Title level TC list from HZ received, but in title level, hard to understand…

Aug. 17: 1. Ask for the UserGuide of the TW APP from HZ; 2. Ask for the instroduction & test steps for the cases; 3. Test Application is just clarified, so HWP Test introduction is needed given to HZ by SIV team, nominator: Han Yong (Aug?)

3).

ATCA Tools All team 1. QC10: Fill in the related Prontos into “Fault Report ID” for Failed TCs Fill in the reason into “Comment” for Blocked/NA TCs Rules of log storage, includes:

In QC10_TestLab In I&V Test Report

See:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D428173767

Regresion Points: 48h Traffic Test are not mandatory for Regression Job; 12h Traffic Tests can be run on both WR2.0 & WR4.0 packages during the

Regression;

Page 4: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 4 (34)Li Li

48h IPMI_Stress Test are not mandatory for Regression Job, execute them by 12 hours, that’s enough

2. Pronto: When Pronto Closed/Passed, change the TC “Status” accordingly in QC,

in Dev. Project, i.e. ACPI4-C Regression Build before the build released, i.e. R_ABESW3_11_02a

Pronto Creation, correctly selecting the Release/Build:Software Release=“AB3” or “AB maint” Build = “R_ABESW_10_48” or “R_ABESW3_11_02a” etc.

Creating new Prontos, fill-in attribute Analysis -> subsystem by selecting right ProductsName

“Pronto Archive” is the place to querying old Closed Prontos (3 months or before)

Reply the “Information Request” (sometimes, you may directly reply the auto-email)Officially reply it in Pronto Web; Otherwise, the Pronto keep in waiting state.Email reply is also OK;

Jul. 11/Sep. 28: SIV will check all YABP_Testing Prontos with Mandatory Fields:

Subsystem(no Empty) Correction Status(RFT):

Liao 4 at Nov. 4;LiZhiguang 7 at Nov. 4;

Information Request(?)LiZhiguang 2 at Oct. 28;Zhang Rui 1 at Oct. 27;

Jul. 8: Take care of the email sent from [email protected]. TrackView: AB MN: choose Activities by Project= S_AB99_HW – NWS EP CP Platform

ATCA HW Platform Maintenance AB3: choose Activities by Project= S_AAB30_0003 - NWS EP CP AB3 I&V

Project AB4: choose Activities by Project= S_AAB40_0003 – AB4 I&V 102 AB4 I&V Test

103 AB4 I&V Management

4. IXIA I&V is in lack of enough 10G IXIA modules;(4 pcs now, 4 pcs more) ---- Start

apply for 4pcs more 10G IXIA (Jul, 20011?) I&V need to find a way to use the 4pcs 10G IXIAs without disturbing the

Project progress(ATCA, BCN, RT, Dev) Mrs. Cao Fang (Lab Support) can start to help on the backlog maint. March Plan: Conflict with BCN in W1111 W1111.1~W1111.2 used by BCN

W1111.3~W1111.5 used by ATCA AHUB4-A PFAug. 31: 8 pcs more 10G IXIA modules arrived at SIV, now totally 12 10G IXIASep. 20/Oct. 19/Oct. 26: 20 pcs new MM Optical Cables needed to be installed together with the new arrived IXIA boards; 6~8 meters for each cable;Quatation sent out for approval;

5. Milestone Criteria v4.3-----Antti Simojoki Check it for your own project scheduling, together with the I&V MTP

6. CuDo Test: (AB3 & AB4)

May. 3: Matti Amnell plans to visit SH: Thursday: May. 12, Thursday

Meeting with I&V (Li Li, Ari Helminen): 10:00~11:00 Test planning (G34AM-B, Xu Li): 13:00 ~ 14:30

Friday: May. 16, Monday Test planning (SCNAM-C, Han Yong):10:30 ~ 11:30 Test planning (AHUB4-A/HBRT4-A, AHUB3-B/HBRT3-B: Liao

Changmao, Li Zhiguang): 13:00 ~ 14:30 1st Lab visit(4F SIV Lab): 15:00 ~ 16:00

Page 5: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 5 (34)Li Li

7. Updated FRU Information Specification

V0.4: updated at May. 3 Aug. 17: Clarification of BoardSlots in DHCP id, related to AHUB3-B’s PF. Oct. 18: V0.5 FRU IS available by Milan

8. RCA process for CP HW___Antti Simojoki May. 10

What kinds of problems need RCA? Open/New A+B Prontos What will be impact on RCA?Specification, Development, Testing&Approving, Processing etc.

Who will be involved in RCA?Specialists, Designer, Tester, LMs, HWQLT etc.

How can we record the RCA?Template, ShareNet , Change Notes etc.

9. Effort Estimation Method (QM: Shen Yanli) Jun. 22: Introduction Jun. 28: review the proposal Jun. 29: jerry collect the final proposal to ShenYanli

10.SIV KPIs for the 2H2011-2H2012----Ari defined at Jul. 5,2011

Aug. 10: Agreement made inside SIV of the CNN rules; July’s KPI summary sent to Shenyanli;Oct. 19: ATCA I&V KPI need to be shown in SIV Monthly Meeting (Oct. 20)

11. Fillers using in 4F Lab:

12. Lab works for the new ATCA cabinets (Aug. 10)

12-1: Power New DC Power Cabinet will be installed at E-Aug (ShanHualian, Cao Fang)Aug. 17: DC Cabinet received at Aug. 15, need to contact with InstallationSep. 8: send email to Caofang for the available timeSep. 28: Installation Quotation in discussing by ZhaiHouan; Oct. 19: Ordering is un-approved by Julio till Oct. 18;Oct. 26: Shelves installation on-going, LE: Nov. 4

12-2: Cables & PatchPanel PatchCab_4 will be installed with Copper&Optical cables at Agu. 11 (Cao Fang, Xu Li)

12-3: Network Configuration, Portserver Make the ATCA6_Shelf1 work before Aug. 15 (Liao Changmao) AP1: Xu Li check fixed IP address + Port Number available for PortServer? AP2: Configure via TWServer instead of public IP (option2 for TMP usage) AP3: Liao Changmao assigned IP for ATCA6_Shelf1 at Aug. 17; AP4: Liao Changmao gave one RDNet map proposal for RDNet, which need approval for operation (Aug. 12)

Page 6: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 6 (34)Li Li

Sep. 7: we need to wait for other teams’ decision for approval., Ari will check with ZhaiHouan.Sep. 21: ZhaiHouan commented that the cut-off day of implementation is Sep. 23 (?), can we postpone it after Sep. 27, after 11_31 finishedSep. 28/Oct. 12: Liao re-configure at Cisco Switch delayed;

12-4: ADX201 installation Install the equipments at Aug. 10; Workers install the POWER at Aug. 11; Powerup&Cabels the ADX201 for HV before Aug. 15

13. RDNet reconstruction, design by Liao Changmao

14. Support on Technical Service team:Sep. 28: ATCA1_Shelf2 will be shared with TS team, ZhangRui can support, but TS teams are not authorized to do any operations like Reset/Upgrading/Reboot etc.

Innovation_Q1 Apr. 25 ATCA team

Innovation Ideas:-- Li Li-- Jerry-- Xu Li-- Sang Haichao-- Mao Wenjie-- Han Yong

Innovation_Q2 Jun. 30 ATCA team

Innovation Proposals:1. Han Yong: SCNAM-B/D test environment research and setup;Traffic forwarding, multi-channels etc.

Innovation_Q3 Sep. 30

ATCA team

Innovation Proposals:Jul. 27: award to candidates is needed Julio

Nominator1: Zhang Rui: MGW System Test ConceptAug. 30: ReviewedSep. 2: to be updated Sep. 7: SIV send comments to ZhangRui,

Nominator2:

eSW Release Download Management

Someone can do the Download as soon as Release notified by Marco Pagnoncelli, and inform all team to avoid duplicated downloading

Lab Resource Reviewing

Cao FangATCA

Purpose:1). Review the HW resource in HW team;2). Return/Repair/Find necessary HW3). Better estimate of the HW forecast for 2H2011

Business Sharing

Vodafone Network Element orders received: - MSS: 13 -> 19 - MGW: 22 -> 25 -> 34

5 -> 7 -> 5 ->6 prospective MSS Customers: -Telcomcell Indonesia is going to order 5 MSS; -MAX from India is going to order 5 MSS;

- CMC, Bharti, MTS Russia, Omnitel Lithua, Free. Tango

More than 2400 shleves forecast to be delivered in 2011

DCM Data at Oct. 26:

- delivered for Q1/11 is 163 cabinets 349 shelves- delivered for Q2/11 is 163 cabinets 325 shelves

Page 7: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 7 (34)Li Li

- delivered for Q3/11 is 170 cabinets 318 shelves- forecast for Q4/11 is 348 cabinets 542 shelves - forecast for Q1/12 is 280 cabinets 500 shelves- forecast for Q2/12 is 474 cabinets 754 shelves- forecast for Q3/12 is 390 cabinets 791 shelves

Pronto Analysis___non-SIV part for each vendor

Jun. 15 ATCA team

Purpose:Collect all Closed with Correction Prontos for each BuildingBlock from each Vendor, check the missed/leaked Prontos found by Internal Customers Radisys Kontron Schroff/PPS Emerson Interphase

Jun. 29:1). 1st round all finished.2). 2nd round review for adding more RT cases based on the “Yes” Prontos

Program Info AB4: AHUB4-A/HBRT4-A moved to IR3 SCNAM-D/E moved to IR4 SCNAM-C P6 LE moved to 5th August New IR4 created for SCNAM-D/E ASA14-A (Radisys): new added in AB4 IR2 ASA16-A (Schroff): new added in AB4 IR4 IPSMO-A (Emerson): new added in AB4 IR4 ADSP2-B (ACL): new added in AB4 IR4Oct. 19/Oct. 26: LiLi to check with Erkki & Luca when can the Compatibility Matrix updated for the updated?

AB3: 2-slot shelf delivery estimates the earliest 1 year later

– no need to test during the 2H2011, LIG will start with 16-slot configuration first.

Jun. 29: ACAR1-B with 2 MPPAM-B/C + 2 SCNAM-B Power Consumption problem, waiting for the conclusion from Juha, Reijo, Kaj and Wang Jing

1). Shmgr limitation to avoid 4th AMC startup---workaround is to enlarge the Shmgr’s limitation2). ACAR1-B current limitation brings risks to SCNAM-D/E configuration---need clarify with Kontron

AB MN: ADSP-C and ACPI4-B enters MN 30.05.2011.

AHUB3-A enters MN 10.06.2011.SCNAM-B and rest AB3 IR3 products enter MN

01.09.2011.

Page 8: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 8 (34)Li Li

0 Internal Workshop

Bi-Weekly

ATCA team

Nov. 5: MPPAM-B/C internal training (Jerry)---Done

Nov. 11: Automation highlight issues by Robot (XL, SHC, Jerry)---Done Align everybody for the know-how for the Robot creation. Xu Li can provide some official templet for Robot creation

Nov. 26: ATC PassCriteria & Scripts Reading (Zhang Jerry) --- IPMI stress & Ethernet Stability test can be done in parallel for 48 hours, with separate configuration files.Reports at: https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D425602386

Dec. 10: SCNAM-B internal training (Han Yong)-Done

Dec. 17: System Manager for ATCA Testing (Mao Wenjie, Xu Li)--- AHUB3-A works----AHUB4-A (Liao Changmao) LE: W1111, for the PF for AHUB4-A (done at W1111)

Jan. 5: Training from MGW Ui5.0--- CLA overview for the System Test (OM?)--- MGW complained the Upgrading issue, like the same situation in HW Test.

Jan. 20: AMPP1-A test introduction (Mao Wenjie, Zhang Rui)--- throughput traffic test--- lab configuration--- 12 AMPP1-As system testing

Mar. 7-8: 2nd Robot training session in Shanghai (Primary&Advanced) (done at W1110)--- Trainer Jussi Malinen--- provide Ari examples of test cases preferred during the session before Mar. 4(Jerry, XuLi)Basic Training at Mar. 10: Han Yong, Jerry, David, Dai Xiaojiao, ElaineEnhanced Training at Mar. 11: all ATCA(9-10), all BCN(3), David(1)Survey at Mar. 16:Jerry & Han Yong: Get basic ideas, can start the self-development now.David: work with all to create some normal Template.Xu Li: Advance usage, Zhang Rui: find an easier way to deal with some ADSP problems, e.g. U-Boot Mao Wenjie: with the help, finish one Robot case in AMPP1-A Apr. 2: FUMI/DIMI Study Workshop(done)--- Introduction of FUMI/DIMI function, impact on SCNAM-D development(Zhao Liye)--- Test study for FUMI/DIMI--- Impact on the ASMGR-A I&V Tests? (on discussion, Xu Li?)May. 5_Mikko Piironen: special SM configuration needed for FUMI test;Jerry is assigned to research on it.Jun. 8: Jerry made Presentation material for the June’s Team Meeting, cooperating with Elaine from BCNJul. 11: Antonio Moschini give introduction for the FUMI/DIMI ISSep. 5: Antonio Moschini give FUMI test plan, Jerry is discuss with himSep. 21: Jerry check with Antonio with the DIMI planOct. 19: Internal Discussion in Shanghai side, Jerry planned at Oct. 20

PPS come at Oct. 26; I&V Plan on AB4 BuildingBlocks SIV Test Bed preparation for PPS PF at Oct. 26 ~ Oct. 28

Oct. 24: Global Discussion planned at Oct. 24Oct. 26: I&V Test Strategy for FUMI/DIMI on-discussion (OpenHPI/IntegralHPI)

Apr. 2: FUMI/DIMI Study Workshop(done)--- Introduction of FUMI/DIMI function, impact on SCNAM-D development(Zhao Liye)

1 Regression cases selection in QC10

Nov. 19

All team Finished at Mar. 30, 2011. 285 RT cases stored in QC Test Plan---- Adding new RT cases during the work.

Mar. 2:Add more RT cases into Test Plan for ACPI4-C/CPRT4-C

Page 9: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 9 (34)Li Li

QC folder created. AP: Li Zhiguang (Mar. 4)

2 Automation Jun. 30 All team

Liu Chuanrong

Mao Wenjie

Automation 65% in 2H2011:

Test Scope:Link to the whole ATCA Test Case.xls (AB MN & AB3 IR1/2 parts): https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D424878017

Link to the AB MN Automation Test Cases. Xls: https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D424879167

Link to the AB3 Automation Test Cases. Xls:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D424878018

Link to the ATC wiki page:https://twiki.inside.nokiasiemensnetworks.com/bin/view/ShanghaiHWTestTeam/ATCATest#ATCA_Test_Cases_Automation

Test Status:

Dec. 8: 52/59/100 cases PASSED in AB MN, for Full-Automation. >50%Dec. 15: 70/97/146 cases PASSED in AB3, for Full-Automation >50%

Work for supporting the Automation 60% in 1H2011:

May. 18: 60% target achieved, Templates&Keywords created, planning further demostration

Jul. 18: 2H2011 target review meeting with David; Automation Strategy & schedule in 2H2011 defined.

Aug. 17: more RT cases added into ASMGR-A and System, may impact on ATC rate in 2H2011;

3-12 R_ABESW_11_31

Sep. 12 ~ Sep. 27

Xu LiMao WenjieSang HaichaoHanYong (Li Zhiguang)JerryZhang Rui

Test Scope: AHUB3-A/HBRT3-A Xu Li ADSP1-B CR Sang Haichao ADSP1-C Sang Haichao AMPP1-A/NIRT1-A Mao Wenjie ACPI4-A/CPRT4-A Mao Wenjie ACPI4-B/CPRT4-B Li Zhiguang/Han Yong? MPPAM-B Jerry MPPAM-C Jerry ACAR1-B Jerry System Zhang RuiRT Plan, 179 RT cases, 4/25 Prontos in SIV;

RT Report: https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D435622683

Test Status:Sep. 21:

1) Test Status:128/179 Passed, 37/179 No-Run, 14/179 Failed with 4 issues

2) Radisys Regression on IPMC FW, Pekka will escalate it with Giovanni

Sep. 28: finished at Sep. 26, 18/179 Failed with 6 Prontos, 161/179 Passed Released to SGSN/FP/ADX as GB, not to MGW/NG10;

3-12 R_ABESW_11_3 Oct. 17 ~ Mao Wenjie Test Scope:

Page 10: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 10 (34)Li Li

9 Oct. 31 HanYong JerryZhang Rui

ACPI4-A/CPRT4-A Mao Wenjie ACPI4-B/CPRT4-B Han Yong MPPAM-B Jerry MPPAM-C Jerry UPG Tool Zhang RuiRT Plan, 50 RT cases, 2/9 Prontos in SIV;

RT Plan: https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D436312924

Test Status:Oct. 17: Test Kickoff

Oct. 19: Test Status: 29/50 No-Run, 21/50 Passed

Oct. 26: Test Status: 2/50 No-Run, 48/50 Passed, no BlockIssue nor Issues

5-1 R_ABESW4_11_29a

Aug. 18 ~ Aug. 31Sep. 9

Zhang RuiZeng Rui

Test Scope:ASMGR-A (drop1 at Jul. 22)

RT Plan of 12 RT caseshttps://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D434196097Prontos: 0 Prontos targeted for ASMGR-A at 11_29a

Test Status:Aug.17: kickoff

Aug. 31/Sep. 7: 1 case blocked for ATCATester issuel 1 case for IntegralHPI maybe NA; Test will be finished at Sep. 9

5-1 R_ABESW4_11_42a

? Sang Haichao (Han Yong)

Test Scope:SCNAM-B X31 at Oct. 18

Test Status:Aug.18: no NSN Prontos fixed for it, should SIV do RT? Any Customers will use it?Oct. 26: RT not needed, commented by Antonella,

6 WR4.0 compatible test

AB MN WR4.0 Project:From Build 10_48 (?), the eSW will be released with 2 BSPs, based on both WR2.0 and WR4.0 by Milan, and the Regression Tests are required to be executed twice on different BSPs.

Project Manager: Antonella MauriProject Plan:

https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D423790522Impacted Blades:

ADSP1-B, B CR, CMPPAM-B, MPPAM-CAMPP1-A(PDB)SCNAM-B (5/2011)ACPI4-A/B/C and CP1AM-A(no OS binary, so no impact on RT)

Status:

Nov. 24:

Page 11: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 11 (34)Li Li

1). Speedup the Automation2). Double the test environment3). Double the test effort, release time will be extended4). Traffic Test need to be adjust for both test on WR2.0 & WR4.0:

--- 6 AMPP1-As run on WR2.0--- 6 AMPP1-As run on WR4.0The traffic test can run simultaneously, with least changes on the currect

TestBed.5). V4.0 Project plan is ready for review, the first release will come at Jan,2011

Dec. 1 / Dec. 8/Dec. 15:1). V4.0 Project plan is ready for review, the first release will come at Jan,2011 (10_48)2). Long time to maint. the 2 versions in parallel, depend on product line upgraded from FP to FP6 Cougar totally3). Discussion of the risk for only WR4.0 testing On-going with Milan team by Ari.

Dec. 22/ Jan. 5/Jan. 12:1). Decision made for the Regression Scope impacted on WR2.0&WR4.0: ---- Kernel difference does not show in the following test areas:

Reset test cases HW mgmt test cases.

  ---- Kernel differences does show in the following test areas: STM-1 / TDM traffic tests Ethernet traffic tests.

2). Impact on Regression: QC10 need to be updated: add “WR2.0” into “Keyword List” before

Jan. 7, if you think the case need to be executed in both kernels The default kernel to execute the RegressionTest is WR4.03). No impact on 10_48 Regression, it’ll be done in later release.

Jan. 19/ Jan. 26/Feb. 23/ Mar. 2:1). QC10 status check: add “WR2.0” into “Keyword List”---- Li Zhiguang to check ACPI4-A/B/C

Mar.30 1). The 1st RT was planned at Apr. 28 for R_ABESW_11_16; ADSP1-*, MPPAM-*, AMPP1-A, SCNAM-B (5/2011), ACPI4-*/CP1AM-A(no OS binary, so no impact on RT)

2). Antonella will discuss with FlexPF of the necessary of the testsNo need to RT if Flex doesn’t need this drop in WR2.0 or WR.4.0;

-----Antonella’s proposal at Mar. 29: Full regression on WR2 packages (R_ABESW_11_xx) and only selected Regression Test Cases on WR4 packages (R_ABESWWR4_11_xx).

3). SH I&V to re-select the cases,proposals:

At the first time: R_ABESW_11_16, I&V team will try full Regression on both packages.

Sep. 28/Oct. 12: 1). The WR4.0 project come back by required by MGW needs.2). Should SIV prepare for one special shelf for the WR2/4 testing?

8-1 SDT10-A(SSD with ACPI4-B/CPRT4-A, for FlexiLIG)

May. 31 Jun. 30Jul. 8Jul. 31 Aug.

Wang Jing Test Scope: 30h planning + 70h testing, LE: May. 3 units needed due to SAS X-conn. + 1 spare Test Plan:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D429329953 SSD model:VRFS21100GBCRMMA (Virking), which sized in 100GB and offer sustained reads of up to 260 MB/s.This SSD will be installed on CPRT4-A and combined with ACPI4-B.The storage controller LSI 1064E locates in CPRT4-A and communicate

Page 12: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 12 (34)Li Li

31(P5.9) Oct. 12

with IOH through PCI-E 2.5G X4 link. This chip supports 1.5 and 3Gb/s SAS and SATA data transfer rates per port, full duplex. Test Report:

https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D429329953

8-2 HDS60-A(MSS need it to work with CPRT4-A)

1st: M-Dec;

2nd: M-Mar

Jerry Test Scope: Test Requirement: Open Test Plan: SSD model: P02053Test Status:

Oct. 18/Oct. 25: 1). Required at AB MN PMT meeting by Pekka, but MSS is also looking for larger HDD, so the decision is still open.2). SIV nominated Jerry to do the test, Jiping can support on Thermal part;Wang jing can provide a workshop for competency training to Jerry&Jiping; Done at Oct. 21.3). TP sent to Global review at Nov., TR sent

8-3 HDS30-A(with HDSAM-A at ACPI2-A, by all Internal Customers)

M-Dec Jerry? Test Scope: To replace the HDT14-A, which will be EOL at Dec. 24 To be tested with HDSAM-A on ACPI2-A To be finished before M-Dec, before the EOL of HDT14-ATest Status:

Oct. 25: 1).SIV nominated Jerry to do the test, Jiping can support on Thermal part;2). TP sent to Global review at Nov, TR sent to Global Review at M-Dec.3). Same TP on ATCA/BCN, Jerry will coorperate with HuangRui/JiPing for this job;

8-4 8GB DIMMs Thermal Testing

Dec. 15 Wang Jing Test Requirements: M392B1K70CM0_CH9 Passed at Dec. 15, 2010 M392B1K70DM0-CH909 for ACPI4-B arrived at Jul. 29, start at Oct. 19

Test Status: the test priority can be done by the order: ACPI4-B-> ACPI4-C 6pcs 8GB DIMMs arrived in SH at Nov. 1, test can be start at W45.1(Nov. 8)

Dec. 15:The final report of “ACPI4-B&ACPI4-C_DIMM_8GB_M392B1K70CM0_CH9.xls” can be found at : https://sharenet-ims.inside.nokiasiemensnetworks.com/livelink/livelink?func=ll&objId=396003140&objAction=Browse&viewType=1

Aug. 1:Wolfgone & Janned requested new DIMM test, confirmed at Aug.1

Oct. 18:1). Mengyang will start the test from Oct. 19: M392B1K70DM0-CH909

8-5 2GB/4GB DIMMs Thermal Testing with ACPI4-B/C

Apr. 15 -> Mar. 23

Wang Jing Test Status: the test priority can be done by the order: ACPI4-B-> ACPI4-C(cancelled at Jun. 7) The DIMMs to be tested:

M392B5273CH0-CH9 (Samsung 4G DDR3)MT9JDF25672PZ-1G4D1DD (Micron 2G DDR3)

Test Configuration provided by Janne at Dec. 2 Test report will be updated to sharenet:https://sharenet-ims.inside.nokiasiemensnetworks.com/Open/396003140

8-6 1GB DIMMs Thermal Testing with ACPI4-A/B/C

Mar. 3 -> Feb. 7

Wang Jing Test Scope: Samsung M392B2873FH0-CH9: 1GB x8 DDR3 ACPI4-A –> ACPI4-B -> ACPI4-C(cancelled at Jun. 7) Test report will be updated to sharenet:

Page 13: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 13 (34)Li Li

https://sharenet-ims.inside.nokiasiemensnetworks.com/Open/396003140

8-7 Virtum & Micron & Smart & Viking & Samsung & Micron 4G DIMMs with AMPP1-A testing

Wang Jing Test Scope:1). 4GB Virtum & Micron & Smart & Samsung DIMMs test with AMPP1-A Virtium VL495T5369EE6YA-S Passed at Apr. 1 SMART SG572128HG8YZIL1 Passed at Apr. 1 Virtium VL495T5169E-E6SF-S Passed at Jun. 10 Micron MT18HVS51272PKZ-80EC1 Passed at Jun. 30 Virtium VL470L2925F-CCS arrived at Jul 12, but don’t know what’s it

for. Virtium VL53B5263A-K9S arrived at Jul. 18, but don’t know what’s it

for. Virtium VL495T5269E-E7/E6/D5MC-S request sent by KeKe at Sep. 1,

DHL 478 3802 870 on tracking;2). Project defined at Jan. 18, 3). Project Priority=HIGH, Test Order=4

Test Status:Feb. 16/ Mar.2 : 1). Mr. Keijo Kuusisto provided the test configuration at Mar.12). HW delivery at Jan. 26, received at Feb. 163). Test to be started at Mar. 24). Problems existed in the mixed usage with Micron and Virtum&Smart --Keijo

Mar. 16 : 1). AB MN Program Decision based on the I&V Test(DPB can’t start up when DIMM mixed): AMPP1-A don not work with mixed DIMM Configuration Smart, Micron, Virtium to be used exclusively Smart, Micron, Virtium DIMMs will be buyable simultaneously with same c-

code, but significantly Octeon must have same type of DIMMs.2). Internal Customer wants to know why? Keijo Kuusisto Li Li Sami Karhulahti3). CuDo to release notes to Customer for the current Non-Mixed usage

Mar. 30:1). Virtium & Smart can work exclusively, CuDo updated needed;2). SH I&V verify the Virtium&Smart DIMMs exclusively, LE: Mar. 31

Apr. 1: Virtium VL495T5369EE6YA-S and SMART SG572128HG8YZIL1 passed with AMPP1-A

May. 11:Virtium & Samsung test on-planning at AB MN PMT meeting

May. 30:Virtium VL495T5169E-E6SF-S arrived in SH, waiting for the Big Thermal Chamber fixed, 2 PD needed after chamber’s ready.

Jun. 7:Thermal Chamber fixed at Jun. 7, Virtium VL495T5169E-E6SF-S testing with AMPP1-A test started

Jun. 15:1). Virtium VL495T5169E-E6SF-S testing pased at Jun.102). New type Micron MT18HVS51272PKZ-80EC1 planned at AB MN PMT, by Keijo

Jun. 30:1). Micron MT18HVS51272PKZ-80EC1 Passed, TR: https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D432942655

Jul. 13:1). Samsung VL470L2925F-CCS arrived at Jul 12, waiting for the Test Conf. & requirements from Keijo

Page 14: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 14 (34)Li Li

8-8 8G DIMMs with AMPP1-A testing

? Wang Jing Test Status:Mar.9 : 1). Mr. Keijo Kuusisto provided the test configuration and ask for backlog;

8-9 1G/2G DIMMs with ACPI4-A/B

Jun. 7 Jul. 31

Meng Yang

Wang Jing

Test Scope: DIMMs-- Samsung M392B2873FH0-CH9 (1GB, x8, DDR3) passed at Mar. 8 for ACPI4-B; passed at Jan. 28 for ACPI4-A-- Samsung M392B2873GB0-CH9 (1GB, x8, DDR3) requested at May. 26, high Priority, with ACPI4-A & ACPI4-B passed at Aug. 5, Report will be sent out by Meng yang at Aug. 11-- Samsung M392B5673GB0-CH909 (2GB, x8, DDR3) requested at Jun. 30, high Priority, with ACPI4-A & ACPI4-B-- Smart SG572568FH8P6PH1 (2GB, x8, DDR3) Passed at Aug. 12 by MengYang-- Virtium VL33B5763F-K9S (2GB, x8, DDR3) arrived at SH, low test priority

CPUsACPI4-B ACPI4-A(Sanity Check only)

Test Status:

Jun. 7: Thermal Chamber fixed, to be started soon.Jul. 13/Jul. 28: 1). check the DIMM storage and test purposeAug. 12:1). Smart SG572568FH8P6PH1 for ACPI4 by Meng Yang

8-109-1 Master Upgrading

Tool Testing1H2011

2H2011

Zhang Rui Test Scope: Phase 1 at Q2~ Q3, 2011: ACPI4-A/B, ASMGR-A, AHUB3-A, AMPP1-A,

ADSP1-B, ACAR1-B, ACH02-A/B1/. Test finished at Jul. 8, Report at: https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D4332241252/. 2/7 Passed, 5/7 Cases Failed with 6 Prontos

Phase 2 at Q2~ Q3, 2011:

Test Background:1) Project Information, kickoff at Jan. 18 ABMN PMTProject Manager: Piironen, Mikko (NSN - FI/Espoo) All AB1 – AB3 bladesLE. 1H2011

2) Background:SH failed in 14 AMPP1-A, 1 ASMGR-A UCSW for AMPP1-A testing at W1041, 1 SH successed in 1 ACPI4-A/ 1 AMPP1-A(FRUD, IPMI) testing.

3) Open Prontos:PR 19065ESPE07: SHMM: SHMM eSW upgrade using master update script failsPR 79143ESPE02: AMPP1-A LMP cannot be upgraded by remoteUpgrade tool fix schedule open at Milan

4) Mater Upgrade Tool can’t be Maint now, since the authors left NSN;The MUT need to be enhanced for this official project. Effort for Development is in discussion.

Maint. team open at Milan

5) I&V test efforts are estimated as 2PM by Ari.Mar. 15: 3PW at 1H2011 for ACPI4-A/B/C, ASMGR-A, AHUB3-A

5PW at 2H2011 for the rest

Apr. 6: Mr. Zhang Rui is assigned for this job 6) When the project kickoff, the new test set need to be added into QC10, under

AB MN project. Also the burget need to confirmed by Pekka.

Page 15: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 15 (34)Li Li

open till detailed test configuration defined

7) Open issues:1. Test purpose, for tool itself? Or for some combination of upgrading?2. HW requirements, HW combination etc.3. program schedule, finish time of the precondition4. delivery schedule, or BuildPlan5. CuDo Plan from Dev. team

Test Status:Jan. 25: 1). Effort Estimation & Human Resouce negotiation with LM (Ari: 2PM draftly)Feb. 16:1). Mikko Piironen calls for the “features important for usage”, I&V testers are invited for the feature requirements

Mar. 9/Mar. 16/Mar. 30/May. 11:1). I&V test for ACPI4-A/B/C, ASMGR-A, AHUB3-A to be planned at June, 1H2011:3 PWs.2). I&V test for left blades at 2H2011: 5 PWs.3). Test Criteria in discussion: 2-1). Target time (OK) 2-2). Flag for upgrading success 2-3). Upgrading steps4). GreenLight give by Pre-PPDT5). Milan is on-developing

Jun. 7: 1). to be kickoff at R_ABESW_11_25 at Jun~Jul2). Test Requirement on discussion with Mikko Pirronen

Jun. 15:1). Test started by Mr. Zhang Rui, lots of Problems2). Updated Project Plan by Mikko Piironen:

Jun. 29:1). All finished except AMPP1-A, with 3 ~ 4 ProntosWaiting for the UserGuide (ACPI4-x especially)Zhang Rui will provide the report before Jun 30.

Jul. 13:1). Test finished for 1H2011:2/7 Passed, 5/7 Failed with 6 Prontos2). 2H2011 Test Effort Estimation finished at Jun. 26, 4.5 PW for System level test

Sep. 7/Sep. 21/Sep. 28:1). New UPG tool will be released together with R_ABESW_11_31 at Sep. 10;2). SIV need to do the Pronto Verification by Zhang Rui.3). Test Status: 3/7 Failed on ASMGR-A/AMPP1-A/ACPI4-A with 3 Prontos open, 4/7 Passed with 5 Prontos Verified, TR at: https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D435000995

Oct. 19/Oct. 26:1). Based on R_ABESW_11_39, ASMGR-A/AMPP1-A/ACPI4-A/B can’t work still2 Prontos Failed in Verification.

9-2 PIUs UpgradingTime & BootupTime measurement

Jan. 15-> Feb. 23

ATCA team do it manually

Test Scope:Measurement Report:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D426771172

Requirements are raised from Mikko Piironen (SW Architects), higher prority on: AMPP1-A, AHUB2-A and ACPI2-A, and ACPI4-A/B/C TBF:Jan.10 Separate component upgrade time need to be measured, including blades:AHUB2-A, AHUB3-AADSP1-B, ADSP1-B CR, ADSP1-CACPI2-A, ACPI4-A, ACPI4-B, ACPI4-C + G34AM-AAMPP1-AASMGR-A

Page 16: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 16 (34)Li Li

ACAR1-B + MPPAM-B/C + SCNAM-B Seperated operation time need to be measured, including:Reset … Reports before for ATCA&BCN can be found at:https://sharenet-ims.inside.nokiasiemensnetworks.com/livelink/livelink?func=ll&objId=426534713&objAction=Browse&viewType=1 Bootup Time Measurement is required by PMT ( Jan. 11)Reference Document can be found in AB3:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D426955232 Bootup Time at MGW side can be found at :https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D427372846

SCNAM-B Startup Time:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D427399565

T est Status: Mar. 2:1). All measurements received at Feb. 252). Li Li to organize the comparison with Espoo resulthttps://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D428502561

Target time defined.

Jul.21/Aug. 17/Aug. 31/Sep. 7:1). HZ MGW is using SIV’s measurement result to contact with FP to update the SCLI working flow, expecting to shorten the upgrading time in APP.2). Review meeting at Aug. 18 19:00 ~ 20:00, Li Li will join it.3). 1st analysis from FP ready, optimization discussion held at Sep. 2, LiLi will join it.4). Review at W37, LiLi will join it for SIV side.

Page 17: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 17 (34)Li Li

10-6

AB3 Maint. System Test Built-up

Jun. 30 M-Aug

Zhang Rui Test Scope Deistinguish:1). MSS/SGSN and MGW used for cross interconnection2). System Test Cases: Traffic, Perf. , Transport, Stress etc.3). AB3 System Test Configuration Proposal, under:https://sharenet-ims.inside.nokiasiemensnetworks.com/livelink/livelink?func=ll&objid=429594185&objAction=browse&sort=name

Test Status:Mar. 23: Configuration Proposal for Internal Review, to be Update: Apr. 15

Apr. 8: 2nd review at Apr. 8 (Room 501) 1G BI for ADSP1-x done

May. 9: ZhangRui finished the MGW related configuration, start the MSS/SGSN configurationhttps://sharenet-ims.inside.nokiasiemensnetworks.com/livelink/livelink/overview/D431019561

Jun. 24: Demo show, there are still some open issues

Jul. 25/Aug. 10: review with Zhang Rui for the PPT and coming job, nominate as an innovation. Review planned at Aug. 30 10:00 ~ 12:00 Room 401;

11-1

ETHAM-A integration testing with ACPI4-C

Dec. 10 (P5.9)

Li Zhiguang Finished in “ ACPI4-C/CPRT4-C I&V”

11-2

ETHAM-A integration testing with ACPI4-B

Mar. 31 Han Yong Test Finished at Feb. 16, 2011

PR 59011ESPE01: ETHAM-A Hotswap test fail on ACPI4-B.

Test Status:

May. 5: Debugging & Investigation on-going with Kontron.

Jun. 29: RMA ready for Kontron

12 Traffic Test case execution(AMPP1-A)

Nov. 30 Mao Wenjie Test Status:1) It's related to the Competence Transferring from Anrijs at Oct.18 ~ Oct. 22. 2) Together with the RT in 10_33, test result is not good:

1 NOK case need to be re-run in SH 5 Throughput cases need to be re-run by similar changes in configuration 3 Interface cases need to be re-run by changes in configuration

So, let's check the plan based on Anrijs's email:

RE: AB MN TC support for Shang...

8) The execution was BLOCK in 10_38 because of the AMPP1-A errors in ATCATester, so, it will move in W44 by 10_33, or after W46 by 10_40

Nov. 3/24: Progress together with the AB MN Automation Execution job.

Dec. 8/Dec. 15/Dec. 22/ Jan. 5/ Jan. 19: 1). Total 16 AMPP1-As in SH LAB, 5 brokens 5 broken AMPP1-As by traffic related testing, Pronto in pushing:

PR 21828ESPE07: RSYS 77466 / AMPP:FPGA mode reprogramming makes FPGA2 corupt its image 3 can be fixed by Radisys SH, 2 can’t fix(RMA), investigation on-going with Marcin & CDC Radisys

2 broken AMPP1-As from the beginning 1 can be fixed by Radisys SH, 1 can’t fix(RMA)

2). Giovanni responsible for RMA to push the 2 AMPP1-As RMA

Page 18: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 18 (34)Li Li

3). Radisys SH come to NSN Lab to fix the 2 new ones, 1 fixed, 1 can’t be recovered, CDC Radisys is handling it. Jan. 25

4). Keijo push Pronto Solving, Pronto was raised to Critical

Feb. 16: Radisys find the rootcause: caused by a defected component, the voltage monitor and voltage sequencer ADM1066 at U172 and replacing the component fixed the intermittent resetting problem reporting by customer.

Feb. 23: Mao keep on tracking with Giovanni of the RCA, and RMA for repairing broken AMPP1-As

Mar. 16:Radisys suggested to close this Pronto, because problem can’t be reproduced when using “dpbreset+30 Sec wait” to do the Reset.Mao will ask why. And then accept to close the Pronto.

May. 11/May. 18:Test & Verify it in R_ABESW_11_16 with updated procedure, new steps can’t realized the FPGA-reprogramming

Sep. 28:Mao has found the bug inside AMPP1-A script, workshop will be held at Oct. later.

AB4 IR1 I&V MTP can be a good tool for AB4 job.1. QC Test Case Naming Rule, see Chapter 7.12. QC Test Case ID Rule, see Chapter 7.13. Pronto Group, see Chapter 7.24. Deliverables&Schedule for each milestone, see Chapter 5.45. Responsibles&Organization, , see Chapter 5.2

6. … …13 AB4 IR1 I&V

ProjectDec. 20 Li Li

PMTsStatus:1). I&V Project MTP: draft ready at Oct. 21st review at Oct. 28, 2nd review at Nov. 29, 3rd review at Dec. 20, Approved with comments at Dec. 20https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D426494750

2). ElectroMechanics & PowerFeeding test responsibility has been defined between Milan and SH, 200PH provided by I&V team for SystemTest support

3). SanityCheck effort need to be combined into I&V MTP, SC Plan to be ready before RIS

4). AB4 IR1 Schedule: P3 Oct.31 -> Dec. 31, RIS: Jan. 15 -> May. 1 REL: May. 1 -> Jul. 1 RVD: Jul. 1 -> Sep. 1

5). Schedule for each Building Blocks are changed accordingly, see the MTP

6). Doc Review Report templet can be found at:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D427186268

Nov. 24:1). I&V plan review at Nov. 29, except CAB216-A, ADPD2-A, to align with the Product Schedule2). Integration re-schedule depending on the SCNAM-C top priority3). Integration re-schedule for ASH16-A

Dec. 1/Dec. 8/Dec.15/Dec. 22:1). I&V plan 2nd review done at Nov. 29, 3rd review done at Dec. 20, Approved at Dec. 20

Jan. 5/ Jan. 19:1). Global review in W1102 & W1103, for the I&V TPs

Page 19: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 19 (34)Li Li

2). Document Review Report need to be used for reviewing&approvement:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D427186268

7)HV & RVD is planned for subset of IR1: SCNAM-C and G34AM-B for SGSN Network Element (SCNAMC in SG8

CD2 and G34AM-B possibly in SG8 CD4). --SGSN provide the real application and SW platform for HV?(To be

confirmed at Dec. 7 meeting with SG8 people);--Otherwise AB4 should develop test application.

Feb.161). R_ABESW4_11_06a available at Feb. 8, containing G34AM-B2). R_ABESW4_11_06b available at Feb. 11, containing AHUB4-A/HBRT4-A3). R_ABESW4_11_07a available at Feb. 16, containing SCNAM-C4). R_ABESW4_11_08a available at Feb. 23, containing SCNAM-C & G34AM-B

13-0

AB4 IR1 HV P7: Aug. 31Sep. 30 E-Oct

Test Scope Distinguish: IR1 HV: next SGSN(SG8.0) with 8pcs SCNAM-C RVD LE: E-Aug

AB4 NE Configuration by Luca:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D429658142

Test Status:

Mar. 2/Mar. 9/Mar. 23/May. 11:1). It’s confirmed that in AB4 IR2, HV Plan need to be ready before REL2). Luca provided the AB4 Test Configuration 3). Plan the IXIA training for L3 protocol

Jun. 8: kickoff the HV Plan for IR1

Jun. 29: draft ready for review

Jul. 13: 2nd Internal review passed, with FR TW Concept Doc review;HV TP is ready for Global Review

Aug. 10/Aug. 17: 1. TestBed installation on-going (Power, Cables, Network, ADX)---1 ASH16SET-B to be finished at Aug. 19, for the Thermal purpose; ---1 ASH16SET-A to be finished at Aug. 17, for the Function purpose;

2. Test ContentAug. 8: PMT review defined 14 Must cases; API related is optional; Thermal part is important; FR capacity is Must(need ADX);Aug. 11: 1st Global Review done, 14 cases frozen

Aug. 31: 1. 5/14 Passed, 1/14 Failed, 1/14 On-going, 2/14 Blocked, 5/14 No-Run

Sep.7: 1. 7/14 Passed, 3/14 Failed, 1/14 On-going, 1/14 Blocked, 2/14 No-Run

Sep.21: 1. 9/14 Passed, 3/14 Failed, 1/14 Blocked, 1/14 No-Run Issue1: Full-Traffic Failed, Juha is confirming the test scenario with IPH

nowPR68506ESPE01 “SCNAM-C full traffic test cause FPGA stuck problem”Critical Issue2: 2 Thermal cases failed need Pronto; 1 Thermal case need to be re-

run---JiPing

2. HV Report: on-going by Xu Li

Sep. 28:1). 9/14 Passed, 4/14 Failed with 3 issues, 1/14 Blocked2). HV Draft TR in reviewing3). Avago SFPs sent to IPH/Espoo for debugging4). Loop Marco Ripamonti for the Thermal Issues found for ASH16-A approvement

Oct. 12:1). 10/14 Passed, 3/14 Failed with 2 PR, 1/Blocked with SCNAM-C Performance. Issue

Page 20: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 20 (34)Li Li

2). Avago SFP issue is related to IPH tool, fix will be available at next drop (X07?)

13-1 AB4 SCNAM-C Han Yong I&V Plan: Dec. 3 : start I&V cases preparation, 1PM for case&Plugfest

RIS: Feb. 3 -> Feb. 17 –> Mar. 11 -> EA(Mar. 21) -> Mar.31 P5.9: Feb.28->Feb. 7-> Mar. 14 -> Apr. 10-〉Apr. 30-> May. 19 P6: Apr.15-> Mar. 7-> Apr. 12 -> May. 20-> May. 31->Jun. 30-

>Aug. 5 Sep. 20 Sep. 30 M-Oct

SCNAM-C I&V Test Plan:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D427079317 SCNAM-C I&V Test Plan Review Minutes Report:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D426893387

Status:

Nov. 17:1). Discussion for the TASR started with SW Dev. Team, of the “SCNAM-C Plugfest at SGSN like environment “2). Plugfest is planned at Jan. 15

Nov. 24:1). Discussion for FR TestApplication SW Requirement done at Nov.23, open issues in discussion with Espoo&Application2). Effort issue (Li Zhiguang is unavailable before Jan. 15)

Dec. 1/ Dec. 8/Dec. 15/Dec. 22/ Jan.5/ Jan. 12/Jan. 19/Jan. 26:1). I&V Schedule changed according to Prototypes delivery

P5.9: Feb.28->Feb. 7-> Mar. 14 P6: Apr.15-> Mar. 7-> Apr. 12

2). I&V Test Plan global review at Jan. 10: Waiting for Milan’s response; Review Report on-going; I&V Test Plan Approved by Ari (?)3). 2 SCNAM-C sent by Espoo arrived at SH at Jan. 20

Feb. 15/Feb. 23/Mar. 2/Mar. 16:1). Frame Relay Analyzer selected (GL, Anristu), 1 instrument borrowed from GL arrived at SH at W1110.

2). Plugfest with IPH&SGSN at Espoo wasn’t approved till bi-direct FR traffic approved (Mikko)

3). R_ABESW4_11_07a released by Milan after SC at Feb. 16 R_ABESW4_11_08a will released by Milan after SC (with drop at Feb. 19) Which build for RIS? EA: Mar. 3 -> Mar. 21

4). I&V Test Plan to be approved by Milan Expert team , both on Test Content and the P5.9/P6 Milestone clarification (Han Yong with Antonella)

5). I&V Progress: Wait for EA(Mar. 21) to start I&V None at Mar. 23

Mar. 30/ Apr. 13:1). EA released at Mar. 25;2). PoC passed with 1 AP, RIS can kickoff;3). I&V TP to be approved at W1113, and kickoff the RIS4). Pre-tested Cases to be Regression Tested based on EA drop, re-estimate the P5.9/P6 Milestone?

May. 11/May. 19:1). Harri organize the P5.9 review at W1119 based on P5.9 I&V report 2). P5.9 passed with minor concession at May. 19

Jun. 8:1). P5.9 I&V finished: 24/29 passed, 3/29 Failed with 4 Prontos, 2/29 Blocked in discussion with Milan eSW Specialists; (P5.9 Passed at May. 19.)

Jun. 15:1). P6 I&V: 3/5 Passed, 1/5 No-Run, 1/5 On-going with 2 Prontos2). TestTools shows different result for the traffic testing, HanYong is investigating the configuration,3). P6 moved to Aug. 5

Page 21: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 21 (34)Li Li

Jul. 4/Jul. 27:1). P6 SIV part has been finished: totally 6 Prontos open, waiting for P6 review;2). SCNAM-C a01 available in R_ABESW4_11_29a, Han Yong is checking the Prontos together with APPs3). Hanyong supported Paul.Interphase for Pronto Reproducing at W1133, will support Paul’s Espoo visiting at W1134(Jukka)

Aug. 31/Sep. 7/Sep.21/Sep. 28/Oct. 12/Oct. 19:1). Avago SFPS1L not compatible with SCNAM-C/B, need to check with IPH & Avago together;Sep.6: Juha&IPH think it’s caused by the Avago is sensitive with the cables;Sep.7: HanYong is contacting with Local Avago support for clarification;Highlight need to be sent to Internal Customers for risk announcation; loop ZhaiHouan already for SFP re-testing?Oct. 12: related to enable the TCLKA, investigation on-goingOct. 13: PR69720ESPE01 create for the iphTDMTest Tool ssue on IPH

2). X05 verification on-going from Sep. 7 ~ Sep. 9 by HanYong, FPGA issues are not fixed totally so far.

3). HanYong will check SGSN prontos to see SIV gaps, e.g.:68412ESPE01 SCNAM-C drops and corrupts UDP packets sent by ATCA SGSN SCNAM-C

A - Critical

4). P6 is blocked by the result of multi-Channel testingPR 68765ESPE01: SCNAM-C full traffic test issues Oct. 18: X06 released at Oct. 1 can’t solve it; IPH misunderstood the NSN

Req. before, 3 STM-1 can be supported only now; Req. Discussion is on-going;

Oct. 19: Lesson Learnt sharing to In-House team(Li Ling): Hanyong instroduced it, and, FPGA has known the real Req. needs in SCNAM-E Oct. 21 FPGA Image verification Failed; Oct. 25 FPGA Image verificationFailed still

13-2 AB4 G34AM-B 2nd Proto: Jan.14

IT: Jan. 17

RIS: Jan. 19

P5.9: Mar. 4

P6: Mar. 28

Xu Li Status: Jan.1 : start I&V cases preparation, 1PM for case&Plugfest RIS: Feb.16Jan. 19 Feb. 20 (?) P5.9: Apr. 15 Feb. 28 Mar. 4 Mar. 18 P6: May. 18 Mar. 28 (Mar. 23)

1). TestApplicationSoftwareRequirement is ready for P4.1, the sharenet link can be provided by Xu Li: https://sharenet-ims.inside.nokiasiemensnetworks.com/Open/D4246023502). I&V proposal:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D4246664473). G34AM-B HW Entity Integration Test Plan ready at Jan.5:(https://sharenet-ims.inside.nokiasiemensnetworks.com/Open/425840403)https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D4267422774). G34AM-B I&V Test Plan:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D4262685935). G34AM-B I&V Test Plan Review Minutes Report:

Mar. 23:P6 partially passed.

13-3 ASH16SET-B(ASH16-A 40G/ SHALD-B / ASMGR-A/ADPDU-A/ADPEM-A/CAB208-A)

RIS:

P5.9: May. 16

P6: Jun. 15

Shan Hualian Mechanic Test Plan (Shan Hualian) included in CAB216SET-B Mechanic&Thermal Testing RIS: ? P5.9: May. 16 P6: Jun. 15 (cancelled)

Status:

Nov. 24:1). Schroff selected as vendor2). Integration test will be done firstly3). Start I&V preparation a.s.a.p Dec. 1/ Dec. 8:1). No Need to order ASMGR-B & ASH16-A seperately

Page 22: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 22 (34)Li Li

2). I&V Test Plan to be finished before Jan. 30, Review at Mid Feb.--Schroff did the singnal backplan test;--SH I&V focus on the ASMGR-B (IPMI) testing3). Open-HPI test lib can be used as bases, Zhang Rui provide the materials and store TCs in QC10.4). Configure the ASH16-A on EC208-A, BAT132467 created for PDUs/cablesets at Jan. 18

Dec. 22/Jan. 5/ Jan. 12/Feb. 23/Mar. 2:1). ASH16-A DR1 order approved (BAT130979)2). new firmware of ASMGR-A is in discussion(Marco Dotti)3). Test Scope to be discussed with Responsibles, like Vendor’s test responsibility, NSN only focus on the ShelfManager SW testing4). Discuss with PMT for the ASMGR-A FW delivery date & I&V date (Li Li)

Mar. 30:1). Only Mechanics testing needed, Shan Hualian’s team take it2). ASMGR-A new FW issues transferred to AB4 IR2 scope

13-4 CAB216-A / DO216-A / CMA19-A

P5.9: May. 20

Shan Hualian Dec. 1/ Dec. 8:1). Get the Effort Estimation from SH/Milan DEV. team

Dec. 15:1). Cabinet test with PSVT, only 1 Thermal case plan by WangJing in the CAB216-A MT plan by Chen Yuan

Dec. 22:1). CAB216-A MT in review, 2 new thermal cases suggested from I&V team(Wang Jing), at Dec. 172). 200PH support from HW Test team was estimated in the AB4 I&V MTP, at Dec. 203). P5.9 can be reached without ADPD2-A/APEM2-A/cables?

Jan. 12/Jan 19/Jan. 26: 1). CAB216-A system level test is divided into BCN3 and AB42). System level test scope&configuration need I&V support----Configuration clarification with Reijo----Support ShanHualian to get the configuration list availability check. 3). 3 extra ASH16SET-Bs needed for the Static Pull Test

14 AB4 IR2 I&V Project (Gigabix)

Schedule P3: Mar. 31 -> Apr. 6 RIS: Aug. 31 -> Sep. 30 REL: Nov. 31 -> Dec. 31 RVD: Feb. 28, 2012 -> Mar. 31, 2012

Status: ANPI1-A/NIRT3-A cancelled at PPDT at Mar. 9, 2011 AB4 IR2 Program Schedule updated, based on the Delivery delay from

ADSP2-A (RIS, REL, RVD delayed 1 or 2 months), at Mar. 30, P3 review meeting

Test Scope for HV&RCC in discussion, by Jukka & Luca LiLi_1026: check, if SGSN or MGW like needed?

Ansku & LiLi checked 1 minor concession of the IR2 RIS, done at Oct. 21

14-1 AB4 IR2 I&V MTP

Apr. 4 Li Li Scope: AB4 IR2 I&V MTP ready at:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D428320920 AB4 Sanity Check Plan updated_Antonella Mauri & Marco Dotti:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D428970295 I&V TestPlan, I&V Test Report templates ready for use---reviewed at Mar.1https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D428752996

Status:Mar. 2/Mar. 30/ Apr. 14: 1). AB4 IR2 I&V MTP 1st review at Mar. 1, to be updated before Apr. 42). Program Scope & Process are still in discussion, t.b.d at W11103). Add more requirements before RIS based on Thermal

Page 23: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 23 (34)Li Li

4). AB4 IR2 HV & RCC test scope need to be aligned with Luca: Jukka is leading the discussion, to be updated into the IR2 MTP.

14-2

AB4 IR2 HV Test Scope Distinguish: IR2 HV: Ui6.0 Open MGW with AHUB3-B, ADSP2-A (ACPI5-A optional)

AB4 NE Configuration by Luca:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D429658142

Test Status:

14-3 AHUB3-B/ HBRT3-B

Li ZhiguangThermal

P3: Feb. 15 Feb. 28 Mar. 7- HW DR1 release: Feb. 25Mar. 21- 1st SW release: Feb. 25Apr. 15- HW DR2 release: May. 4(?) I&V Kickoff : Mar. 18- I&V TP ready for global review: Apr. 4- PlugFest Review (?) PlugFest : Apr. 18 (W1116) RIS: Mar. 4 Apr. 25 NOS1.15 (NTS CLI): Jul. 15 Aug. 26 Aug. 29 P5.9: Jun. 30 Aug. 17 Sep. 14 P6: Aug. 31 Nov. 15 Dec. 14

Test Status:Feb. 16:1). Li Zhiguang can’t start the work before Mar. for the ACPI4-C job2). RIS & PlugFest need to be re-organized

Mar. 18:1). I&V Kickoff at Mar. 18, I&V Schedule defined based on the updated eSW/HW plan from Dasan.2). User Manual ready at Apr. 5 from Dasan3).

Apr. 13:1). Use the new Test Plan template for TP2). PF test plan review from Dasan3). PF execution in W11164). I&V Test Plan review, 1st round

May. 11/May. 18:1). LiLi send to Paivi the Proposal List for Pre-Integration tests to Dasan, asking how many test cases can be covered at Vendor side, and when to finish them.Paivi rejected because NSN SIV was expected to select the coverage based on Dasan’s MT Plan, which not received till May. 182). NTS function in NOS1.13, for P5.9 is in discussion3). Complex Test Topology sent for review at May. 18, by Li Zhiguang

Jun. 16:1). 3/167 passed, 164/167 no-run2). L2/L3 configuration on global review

Jun. 29:1). 6/93 Failed with 4 Prontos, 13/93 Passed, 74/93 No-Run2). 2nd PlugFest during Jun. 27~29, 4/9 TCs Passed, 5/9 No-Run

Jul. 13/Jul. 22/Jul. 27/Aug. 10:1). 10/93 Failed with 7 Prontos, 23/93 Passed, 43/93 MT duplicated; 17/93 No-Run2). 2nd PlugFest review at Jul. 12, 8/11 Passed, 2/11 PassedWithNotes, 1/11 Failed with NOS1.15 Fix:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D4329528533). Thermal Test Problems: 1/. IPMC M7 at 55C, no IPMC&inlet sensor; HW debugging needed in Dasan(sent at Aug. 8) 2/. CRC error at 55C; (more check needed when new HW received from Dasan), LE: Aug. 18 3/. Clarification of Temperature Sensors 4/. Operating Voltage Problem ( DCDC module change needed for Dasan’s HW)

Page 24: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 24 (34)Li Li

4). NOS.1.15 was wrongly delivered to NSN, need Dasan’s new release before Aug. 12, now SIV was blocked

Aug. 31/Sep. 7:1). NOS1.15 available at Sep. 1, to start the 16 cases for P5.92). Themral Operating Voltage problem need to be checked with eSW updating3). Themral Sensor problem need to be checked together with HW Spec. and new IPMC FW4). 4 FUMI/DIMI TCs transferred from P5.9 to P64). 18/89 Failed with 18 Prontos open, 57/89 Passed, 14/89 No-Run; LiZhiguang can finish them before Sep. 13

Sep. 21:1). P6 Status: 70/78 No-Run, 2/78 Failed, 6/78 Passed2). P6 execution need to be finished before E-Oct, to reserve time for fix verification

Sep. 28/Oct. 12/Oct. 19/Oct. 26:1). P6 Status: 30/78 No-Run, 18/78 Failed with 11 Prontos, 30/78 Passed2). P6 execution need to be finished before E-Oct Nov. 18, to reserve time for fix verification, P6 delayed to Dec. 143). CuDo ready for testing4). What’s the status of “L3 related webex session after plugfest (VRF, BFD, sub interface etc.” ---asked by Paivi via weekly tracking---ask Sami5). L2/L3 Switch Test need to use ATCA5 testbed in Nov.; 2 weeks reserved for 8 TCs;

14-5 ASH16SET-A(ADPD2-A & APEM2-A & ASMGR-A FW)

Nov Xu Li Zhang Rui

1st Drop: Jun. 15 (HPM209/IPMITool/HPM156/HPM158/C-Code format/PWM76/IPMB_RETRY_TIMEOUT)

2nd Drop: Aug. 31 (FUMI&DIMI) Oct. 20 PlugFest with PPS: Oct. 26 ~ oct. 28 RIS: Sep. 12 P5.9: Oct. 30 P6: Nov. 21

Test Scope & Organization:1. ASH16SET-A Mech&Power test: Shan Hualian, focus on PDU&PEM test

ASH16SET-A ASMGR-A FW test: Li Li, focus on FUMI&DIMI test on ASH16-A

2. Feature Test & Bug Fix Test are tracked by different projects in ATCA:BugFix from Schroff will be automatically published to AB3 & AB4 , after it's verified in AB MN Project;NewFeature from Schroff will be automatically published to AB MN & AB3, after it's verified in AB4 Project;

3. NewFeature Test in AB4 IR2 needs to integrate all ATCA Blades&AMCs to verify the FUMI&DIMI function, and plans the HW Verification test in System Level.

4. Effort Estimation at Mar. 28 by Ari:PSVT: Shan Hualian: 2 Person * 2 WeeksI&V: Li Li: 1 Person * 6 Weeks for P5.9 1 Person * 2 Weeks for P6 1 Person * 4 Weeks for RVD

Test Status:Mar. 30: 1). P3 passed (Marco Ripamonti) at Mar. 282). ASMGR-A FW Test Scope in discussion with Marco Dotti (Li Li)3). PF plan in discussion between Sami & Marco

Jun. 29:1). All new HWs available for Power Test, but need cooperation for 3-shelves configuration in Jul.

Jul. 27/Aug. 10: 1). 1st drop of FW need to be RT in AB1/2/3/4 hybrid environment; zhang rui do RT, together with Marco Dotti’s SC plan.2). Jul.14 drop(FW1) kickoff at Aug.17 at R_ABESW4_11_29a, 3). R_ABESW4_11_29a test status:1/12 Blocked by ATCATester, 1/12

Page 25: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 25 (34)Li Li

Investigating, 10/12 passed

Sep. 21 / Sep. 28/Oct. 12/Oct. 19/Oct. 26: 1). XuLi will provide the draft I&V plan for global review at E-Sep;2). PPS PF planned at E-Oct3). Contact with Milan to distinguish the responsibility of the FUMI/DIMI testing for each BuildingBlocks Oct.11 workshop Oct. 12 workshop Oct. 20: SIV internal Discussion workshop:

Prepare for own FUMI/DIMI I&V TP Oct. 24: SIV invite Global Discussion workshop ASMGR-A Plan on-going4). Zhang Rui check the R_ABESW4_11_29a coverage on the Drop1 requirements (7 items), mapping with cases.5). P6 at Nov. 18 has risk, since PPS said their current 2.8.0.1 can only support FUMI/DIMI on IntegralHPI, not in OpenHPI(available at Nov)Oct. 26: Check with Marco Dotti, if this P6 Scope/Schedule needs to be updated?

14-6 ASH16SET-A(ADPD2-A & APEM2-A & ASMGR-A FW)

Aug.1Aug. 9

?

Zhu ChihengZhang Baoyao

Test ScopeTP from Zhu Chiheng/Milan

Test Status:Dec. 1/ Dec. 8:1). Get the Effort Estimation from SH/Milan DEV. Team2). New PDU with new PEMs, need new power cable design, which not started yet in Espoo

Dec. 22:1). Cancelled from AB4 IR1 schedule

Jul. 13:1). Setting up ATCA_6 with new ADPD2-A/ADPE2-A/CVKPA025, waiting for the Power Solution (Cao Fang)2). Review Power TP to see if 3*16 full configuration needed: Jul 18 meeting with ZhuChiheng

Jul. 27:1). Temperorary ATCA_6-Shelf_1 with new ADPD2-A/ADPE2-A/CVKPA025 setup, for ZhuChiheng’s Power test2). Cabling with ADPD2-A/ADPE2-A/CVKPA025 may have problems, need Liu Yongming contact with Milan experts3). Delta solution for the DC Power Supply is in ordering.—Shan Hualian

Aug. 9:1). Power Test finished and review finished;2). Cabinet recover finished by Zhang Rui;

Aug. 31/Sep. 7/Sep. 28:1). More Power test to be done, negotiating with Milan for the TestBed & Schedule2). Zhang Baoyao (DD1) finished more Power Test on ATCA6_Shelf1 at Sep. 73). Review meeting at Sep. 28, Li Li will join that.4). IR1 HV Thermal testing issues are in discussion by Espoo & SH & Milan(Marco Ripamonti)

14-7 ASA14-A (Radisys)

P3: - HW DR1 release: ?- 1st SW release: ?- HW DR2 release: ? RIS: P5: P5.9: Jun. 2012? P6:

Test Status:Sep:1). 14-slots AC shelves added into AB4 IR2, to be released at 1H2012;

Oct. 19:1). 1 pcs prototype ordered by Li Li at Oct. 182). Ordering more for installation:

Page 26: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 26 (34)Li Li

CAB216SET-D Mounting Brackets

15 AB4 IR3 I&V Project (Siliconix)

P0 approved at PPDT at Mar. 9, 2011 RFQ milestone reviewed and approved at Mar. 17, 2011-3-17 P3: E-Sep E-Oct

15-1 AB4 IR3 I&V MTP

Sep. 15 Li Li Scope: AB4 IR3 I&V MTP ready at:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D434762035

Status:Sep. 7: 1). LiLi is preparing for the IR3 I&V MTP, draft at Sep. 9; review before Sep. 15Sep. 21:1). 1st PMT reviewed at Sep. 14, updated to be done before Sep. 23Sep. 28:1). Updated with Ari’s comments

15-2 UIRT1-A

RTM debug Card (In-House)

RIS: Sep. 19

P5.9: Oct. 13

P6: Oct. 27

Mao Wenjie

SH DD2 team(LM: Cai Ning)

P1: Apr. 20 P3: May. 19 P4.1: Aug. 26, I&V TP Planning can kickoff here RIS: Sep. 19 P5: Sep. 19 P5.9: Oct. 13 P6: Oct. 27

Test Status:Feb. 16:1). RS in discussion

May. 18:1). Development plan frozen, SIV can kickoff2). UIRT1-A combined with ACAR1-B and ACPI4-B, Mao can start to think about the Test Environment, RIS: Sep.

Jun. 8:1). 1st review for configuration finished at Jun. 7, Mao will contact with DD1 for the comments

Sep. 7:1. MaoWenjie provides I&V TP for review at Sep. 15; do ET before P5.9&P6

Sep. 28:1. Mao has start the UIRT1-A testing at Sep. 27, FW updated successfully2. Mao will update the QC10, LE: Sep. 29

Oct. 12/ Oct. 19/Oct. 26:1. P5.9 I&V finished: 3/15 N/A, 12/15 Passed2. Mao wenjie finished the TR into ShareNet, and finish the CuDo test as well.3. P6 review at Oct. 26

15-3 AB4 AHUB4-A/HBRT4-A

Liao Changmao

I&V Plan: Nov. 15 : start I&V cases preparation, 2.5 PM for case&Plugfest&tool usage RIS: Feb.14Feb. 10Feb. 27 PlugFest: Mar. 22

(Transferred to Incr3 at May. 5)

P5.9: Apr.22Apr. 29 Aug. 31Sep. 20(NOK)Sep. 26 P6: Sep. 16 Oct. 31 Dec. 16

AHUB4-A/HBRT4-A I&V Test Plan:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D426466402 AHUB4-A/HBRT4-A I&V Test Plan Review Minutes Report:https://sharenet-ims.inside.nokiasiemensnetworks.com/Overview/D427335377

I&V Status:

Page 27: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 27 (34)Li Li

Nov. 10/17/24:1). AHUB4-A prototype_1 arrived at Nov. 8, start I&V preparation from now on;DIMMs (MT18HVS25672PKZ-80EH1) to be shipped by Mikko from Espoo for startup;2). Considering 40GB traffic for Prototype2, SFP(Karhulahti, Sami)&IXIA 40GB ordering need to be considered3). “TestApplication SW Requiement” to be ready at Dec. 15.

Backplan between AHUB4 and other AB4 units --- no need

Dec. 1:1). 6QSFP needed (3 pcs 100m over OM3 MMF + 3pcs 125m over OM4 MMF)2). 2 pcs 40GB IXIA card needed (Only sigle 40GB port per card)—to discuss if offline.3). AB4 I&V Test Plan to be review at Jan. 20 (both 10GB & 40GB)

Dec. 8/ Dec. 15/Dec. 22/ Jan. 5/ Jan. 12/ Jan. 19/Jan 20/Jan. 26/Feb. 23/Mar. 2:1). 1pcs 40GB IXIA board + 4pcs 10G IXIA ports can be used for AHUB4-A 40GB test, while, 6pcs QSFP still can be ordered; Dasan need to do more 40GB test.2). 3pcs DIMMs arrived at SH, QSFP on delivery, ASH16SET-B on delivery, AHUB4-A/HBRT4-A DR2 on delivery3). UserGuide updated from Dasan at Feb. 114). Dasan PlugFest TestPlan is on discusstion, LE: W1109 ~ W11105). 1st Global review at Jan. 20, for the I&V TP; 2nd Global review at Feb. 22

Mar. 9/Mar. 16/Mar. 23/Mar.30:1). I&V TP Review Minutes on discussion (Liao )2). PlugFest planned at W1111, FP Plan with Dasan at Mar. 3 I&V review comments sent out PF Plan from Dasan V1.2 at Mar. 93). AHUB4-A/HBRT4-A RIS passed at Feb. 17 by Jarkko(?)4). AHUB4-A/HBRT4-A PlugFest Configuration definition Job responsibility in W1111, supporting from ACAR1-B&AMPP1-A & XuLi5). AHUB4-A/HBRT4-A PF Status, approved at Mar. 22:

4/33 blocked, 2/33 Failed, 22/33 Passed, 2/33 Skipped, 3/33 passed with notes6). Fill in QC10 with Case Tile, LE: Apr. 13( P5/9/P6 mentioned) Detailed Description can be filled in together with the ET execution.(Log Saving)7). Check the available eSW package for I&V

May. 11:1). NOS1.12 available in R_ABESW4_11_18a at May. 6, start the I&V tests2). Extra cases in AHUB3-B need to be added into AHUB4-A as well, excluding NTS and 40GB 3). AHUB4-A moved to AB4 IR3

Jun. 8:Liao thinks about the HPRS Compliance Matrix, similar like AHUB3-B

Jun. 15:Ask Dasan to support QSFP(Tyco) usage in W26 during 2nd FP for AHUB3-B

Jun. 29:QSFP cable testing, Dasan’s is very short.

Jul. 13/Jul. 27/Aug. 10:1). Dasan retest the NSN longer Tyco QSFP cable, which can’t work same as in NSN Lab; Jan need to send more Tyco QSFP cables for test later;

2). Test Status: 8/55 Failed with 8 Prontos, 1/55 NA with “AHUB4-A/HBRT4-A BI interfaces can’t support 10*1G -〉1* 10G for 1->Many configuration”, 9/55 No-Run, 37/55 Passed

3). 9 ET cases will be done after AB4 IR1 HV done.

Aug. 17: P5.9: Apr.22Apr. 29 Aug. 31Sep. 15? (Thermal from Sep. 1) P6: Sep. 16 Oct. 31 (NOS1.15 at Aug. 26; 10GB IXIA 2pcs*2month)

Page 28: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 28 (34)Li Li

Aug. 31:1). NOS1.15 to be ready at Sep. 1, Thermal&P6 test to be start at Sep, 1

Sep. 7:1). Thermal to be started at Sep. 13 ~ Sep. 20; P5.9 I&V Status:9/55 No-Run, 8/55 Failed with 13 Prontos, 1/55 NA, 37/55 Passed2). P6 to be started at Sep. 9, 64/66 No-Run, 2/66 Passed

Sep. 21/ Sep. 28/Oct. 12/Oct. 19/Oct. 26:1). P5.9 test finished at Sep. 19: 9/55 Failed with 21 Prontos Open, 45/55 Passed, 1/55 NA because no need to be tested;2). P5.9 review at Sep. 20 NOK, because of the eSW plan(FUMI/DIMI)3). P6 Test Status:9/66 Failed with 6 PRs, 1/66 NA, 2/66 Blocked, 20/66 No-Run, 34/66 Passed

4). PR 53891ESPE03 is block issue for 2 ET cases, highlighted to Giovanni asking for fix plan at Sep. 28: QSFP selection is still on-going with IXIA; Paivi ordered 1pcs of 40G optical cables for SIV, by BAT149763

5). HPRS Traceability Matrix need to be enhanced by Dasan(comments sent by Sep. 21)6). P6 execution will be finished before E-Oct7). CuDo is ready for testing8). New Problem Sharing: --- 55905ESPE03: Problems of AHUB4-A's BI Switch on forwarding broadcast/dlf/multicast packets - B-Major

Oct. 26: Discussion on-going with Dasan

15-4 ADSP2-A Sang Haichao P3: Feb. 28 - HW DR1 (NSN) release: May. 15 Jun. 2Jun. 30Jul. 7 Aug. 19

Sep. 16 Sep. 23 (ETA at SH at Oct. 4) Oct. 14- V0.7 SW (NSN) release: Oct. 6- V0.8 SW (NSN) release: Oct. 17- EFD SW (NSN) release: Nov. 30- V1.0 SW (NSN) release: Jan. 1- HW DR2 (NSN with PG2) release: Jul. 20 Aug. 3Oct. 3Sep. 15

Jan. 20- 1st PF : Oct. 17 ~ Oct. 21 (W1142) RIS: Jun. 20 Jul. 4(?) Sep. 15 Oct. 31 P5.9: Aug. 15 Sep. 15 Nov. 30 Mar. 31 P6: Oct. 15 Nov. 15 Jan. 31, 2012 May. 31

Test Status:

Mar. 2/Mar. 9/Mar. 16: 1). ADSP2-A P3 Milestone OK 28.2.20112). Sang Haichao can start the material reading 3). I&V kickoff planned at Apr. 14). HW/eSW delivery delayed from AdvanTech, RIS plan updated5). Sang Haichao, Wang jing, Zhang Rui are invited to review the 1st Test Plan from AdvanTech.

Jun. 8/Jun 15:1). Sang Haichao finished the I&V Test Plan Draft, will invite the 1st global reviewSang need to insert the HPRS traceability matrix, and update the whole Pronto history Analysis into the I&V TP;

Jun. 29:1). TP review at Jun. 29 internally

Jul. 22/ Aug. 10/Aug. 31/Sep. 21/Oct. 12:1). ACL’s SW/HW Test Plans(Jun) Review comments sent to Paivi, waiting for

Page 29: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 29 (34)Li Li

the response2). 1st Global review with Milan, at Aug. 1; 2nd Global review with Espoo planned at Sep. 13; Asked for TP approvement at Sep. 20 by SangHaichao after updating.3). ACL delayed the DR1 delivery date to Aug. 19, which will impact on the 1st PF;And need to check is there any update for the HW/eSW delivery plan from ACL.4). Li Li Check the latest HW/SW delivery information from Milan(Antonella) and Espoo(Paivi, Petri, Jarkko) 5). UserGuide availability check before RIS (Oct. 31); Quick Guide is asked by Paivi at Sep. 286). DSP TW development inside NSN check with Mikko & Li Li & Jukka (Sep. 14)7). DSP_TW development responsibility taken by haibin’s team at Sep. 22 (Hu Guangfu)8). PF plan review at Oct. 12, comments sent to ACL for updating, some HPRS is also checked by Petri9). PF Status: 33% failed / 22% blocked / 45% passed RIS delayed Mechanical Investigation on-going by Espoo&Milaln; E-Keying Checking BI/FI Down Status

15-5 ACPI5-A/CPRT5-A (Emerson)

? Zhang Jerry Test Scope: P3: Jul. 30 Sep. 30 E-Oct- 1st HW Delivery: DA02(2* 70W/1.4GHz), sent from ZhongShan at Aug. 2; CPRT5-A received at Sep. 27CMSAS040 received at Sep. 28

- HW 0.3/0.4 + GA01 for PlugFest- HW 0.5/0.6 - HW 0.7/0.8

- GA01- GA02- RHUP(Build 02)- GA03- GA04- RHUP(Build 03)- DIMI GA1.1- FUMI GA

1st PlugFest(40 cases): Aug. 8 ~ Aug. 16 2nd PlugFest(67 cases): Sep. 19 ~ Sep. 23 (W38)M-Dec RIS: Oct. 10 E-Dec P5.9: Jan Feb. 28 P6: Mar Apr. 15

Test Status:Mar. 16:1). Test Concept document ready for review at W1111, according to the RFQ

Jun. 15:Emerson is chosed as the vendor

Jun. 29:1). Reijo is answering the Open Questions from Emerson, need SW part finished 2). Kai Kiiskila will take the PPM job after August

Jul. 13/Aug. 10:1). 1st PF planned at Aug. 8 ~ Aug. 12/Aug. 15 ~ Aug. 16; PF Plan reviewed by NSN at W1129 ~ W1130;2). 1st PF Test Status: -- 8/40 Passed -- 32/40 No-Run2). Waiting for P3 to start the I&V Planning

Aug. 17:1. I&V TP proposal by Jerry&Jiping

Aug. 31/Sep. 7:1. after the business trip to Emerson, ShenZhen, Clarify 3 Concept issue with

Page 30: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 30 (34)Li Li

NSN Customers: Jerry---HDD---FrameSize to Throughput 2. 2nd PF planning, delay from Sep. 19 to M-Dec for unstable prototype V0.1, Sami3. Prototypes ordering for V0.3/0.4 and V0.5/V0.6, Salla

Oct. 19/Oct. 26:1. Emerson’ s Scheduel review for P32. 0.3/0.4 will be used for Processor Selection Test during Dec. Internal

Discussion at Oct. 28 with Jiping/Wangjing/Jerry/Ari

15-6 AMPP2-A/NIRT2-A (ACL)

Han Yong Test Scope:- AMPP2-A won’t be used in 2-slot shelves, by Erkki’s comments at

Sep. 20

P3: Sep. 12 Sep. 30 E-Oct- 1st HW Delivery: Oct. 21- V0.4 eSW Delivery at Oct. 21- V0.6 eSW Delivery at Dec. 9- 2nd HW Delivery: Jan. 20- V0.8 eSW Delivery at Jan. 20- V1.0 eSW Delivery at Feb. 24- EFD eSW Delivery at Mar. 23- PlugFest: M-Oct E-Dec RIS: E-Dec P5.9: Mar. 28 P6: Apr. 31

Test Status:Mar. 16:1). Test Concept review according to the RFQ

Jun. 15:1). Kickoff by ACL, asking for the plans updating.

Jun. 29/Sep. 7:1). ACL provided the latest eSW Build Plan, Timo will organize P3 checking at Jul.2). ACL refused to join twice PF, so the RIS is in discussion

Sep. 28:1). AMPP2-A won’t be used in 2-slot shelves, by Erkki’s comments at Sep. 20

16 AB4 IR4 I&V Project (Suffix)

? New created in June for SCNAM-D/E

16-0 AB4 IR4 I&V

MTP Scope: AB4 IR4 I&V MTP ready at:

Status:

16-1 SCNAM-D ? Sang Haichao P3: Feb. 18, 2011- HW DR1 release: Aug. 15- 1st SW release: ?- HW DR2 release: ? RIS: Mar. 20, 2012 EIT: P4.1 ~ RIS P4.1: Aug. 12 P5: Mar. 27,2012 P5.9: May. 29,2012 P6: Jul. 31,2012

Page 31: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 31 (34)Li Li

Test Status:Feb. 16/ Mar. 2/Mar 16/Mar. 30:1). TestApplicationRequirement discussion on-going with eSW team(Mar. 17)2). SCNAM-D test responsibility transferred to Mr. Sang Haichao

Jun.8:1). SCNAM-D TW Clarification done with DSP team

Jun. 29:1). DSP’s P-o-C tool not started for develop yet__Chen Zhuo2). HEI Test Configuration& ProntoAnalysis done by HanYong&SangHaichao(ADSP-x related tools are unavailable for HEI per ZhangHai’s comments)

Jul. 13:1). DSP started the Development for the P-o-C tool_ZhaoDun, ChenZhuoTestbed setup in 4F lab, with support from David, Sang Haichao2). EIT TP global reviewing

Aug. 10/Aug. 31:1). DSP team met the problems of how to load the image into DSP chips:

1/. By JTAG from Radisys: Antonella checking…2/. By PPC 3/. By installing the MGW SW (not recommended for mismatch the P-o-C)

Sep. 7: 1). SIV accept the FP based TW, since it’s only for FLIP multi-channel testing; but the FP TestBed need to be shared between SIV&DSP(email sent by Ari)

2). Monthly meeting among DSP&SIV team, to track the TW development progress, align with FP for the compiling possibility

3). Sang Haichao is the main contact person to support EIT in SCNAM-D (Oct ~ Mar); and Sang Haichao will take over the SCNAM-B RT

Sep. 28: 1). DSP_TW development review of Sprint1110 at Sep. 26, demo will be shown at Sprint1111;2). DSP_TW is not involved into worst traffic mode from MGW India, which need clarification by Zhaihouan in SCNAM-D Dev. Program firstly, ZhangYanhong will check the dynamic traffic Lesson Learnts from SCNAM-B firstly. Review at Sep. 30 SCNAM-D/E Internal Meeting

Oct. 26:1). DSP_TW Sprint1111 review at Oct. 27; by FuQiong2). DSP_TW discussion of the WorstTrafficMode planned at M-Nov, By ZhaiHouan3). SCNAM-D DR1 EIT, Thermal Part, start at Oct. 31 ~ Nov. 11, support from SIV needed, for ACAR1-B, MPPAM-X

16-2 SCNAM-E ? Han Yong P3: Mar. 1- HW DR1 release: Jan. 9- 1st SW release: ?- HW DR2 release: ? RIS: May. 4 EIT: P4.1 ~ RIS P5: May. 11 P5.9: Jul. 6 P6: Aug. 31

Test Status:Feb. 16/ Mar. 2/Mar 16/Mar. 30:1). TestApplicationRequirement discussion on-going with eSW team(Mar. 17)2). SCNAM-E P3 passed at Mar. 1 with concession

Jun. 15:1). SCNAM-E TW clarification planning… (eSW, SIV)

Jun. 29:

Page 32: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 32 (34)Li Li

1). Mao Wenjie for SCNAM-E P-O-C Tool Development, which is transferred from eSW team.2). HEI Test Configuration& ProntoAnalysis done by HanYong&SangHaichao(ADSP-x related tools are unavailable for HEI per ZhangHai’s comments)

Jul. 13:1). Mao Wenjie’s Concept Document ready for review at Jul. 132). EIT TP global reviewing 3). Instruments review done with Dev. Team

Aug. 10/Aug. 31/Sep. 7/ Sep. 28:1). Review of the P-o-C TW at Aug. 232). Statistic function review at E-Oct, since Mao is fully occupied at Sep&Oct for RT and UIRT1-A ET; TW_APP development will continue from Oct. 13.

16-3 SDH_Driver Competence Transfer

Han YongSang Haichao

Kickoff: Jul. 18 by FangHaibin- SIV visiting HZ MGW: Sep. 1 ~ Sep. 2 (Hanyong, Xu Li, Jerry) 1st drop for testing at Oct. 10

Dev. Responsibility Summary by Marcelo at Sep. 15 : - SCNAM-B DRV_ADPT Layer responsibility still with MGW HZ, and

future transfer to SH eSW. - SCNAM-B NSN Test Tools, improvements and responsibility by SH

eSW.

Test Status:Sep. 28/Oct. 12/Oct. 26:1. I&V Test Plan for SCNAM-x SDH Driver ready for review at Sep. 26;2. Attenuator and Special SFPs need to be ordered a.s.a.p to avoid blocking

issues3. I&V cases execution status: 21/80 finished 4.

16-4 ASA16-A (Schroff)

P3: - HW DR1 release: Jun. 1- 1st SW release: ?- HW DR2 release: ? RIS: P5: P5.9: P6:

Test Status:Sep. 28:Product decision made at Sep. 15 by the PPDT meeting; Schroff is the vendor;

16-5 IPSMO-A P3: - HW DR1 release: ?- 1st SW release: ?- HW DR2 release: ? RIS: P5: P5.9: P6:

Test Status:Oct. 12:1). IPSMO-A added into AB4 IR4 at Oct. 62). I&V Efforts estimated at Oct. 11, 600PHs totally

16-6 ADSP2-B (ACL with 8pcs CPUs)

? ? P3: - HW DR1 release: Jan. 2012?- 1st SW release: ?- HW DR2 release: ? RIS:

Page 33: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 33 (34)Li Li

P5: P5.9: P6:

Test Status:Oct. 18:1). Informed via AB4 PMT that it’s decided

Page 34: ATCA HW Test weeklymeeting_reports.doc

18/04/2023NokiaSiemensNetworks

ATCA HW TEST WEEKLY MEETING 34 (34)Li Li

APpendix 1: Action pointsWho What AP Given Deadline Status Comments/Result

Li Li AB MN Weekly Meeting organization Li Li Nov. 3 Done Outlook invitation sent out at Oct. 28.