atlas ls1 infrastructure: installation of a new 10’000 litre lhe dewar for the solenoid

6
ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid N. Delruelle on behalf of the TE/CRG group LS1 Infrastructure Meeting – 16 Apr 2014

Upload: aleta

Post on 23-Feb-2016

26 views

Category:

Documents


0 download

DESCRIPTION

ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid. N. Delruelle on behalf of the TE/CRG group LS1 Infrastructure Meeting – 16 Apr 2014. Outline. layout of the new supply 10’000 litre LHe dewar Interconnecting valve box - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

ATLAS LS1 infrastructure: Installation of a new 10’000 litre

LHe dewar for the SolenoidN. Delruelle on behalf of the TE/CRG groupLS1 Infrastructure Meeting – 16 Apr 2014

Page 2: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

2

Outline

► layout of the new supply 10’000 litre LHe dewar Interconnecting valve box 2 Transfer Lines TL4 and TL5

► Planning of the new supply Manufacture Integration in UX15

TE/CRG/N.Delruelle – LS1 infrastructure – 16 Apr 2014

Page 3: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

3

Layout of the new supply

TE/CRG/N.Delruelle – LS1 infrastructure – 04 Dec 2013

New transfer line TL4

New valve box

New 10’000 L dewar

New transfer line TL5

Existing transfer line TL1

Existing transfer line TL2

Courtesy of Jos Metselaar

Page 4: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

4

Layout of the new supply

TE/CRG/N.Delruelle – LS1 infrastructure – 04 Dec 2013

New 10’000 L dewar

New valve box

New transfer line TL4

Existing transfer line TL2

Existing transfer line TL3 to solenoid

Courtesy of Jos Metselaar

Page 5: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

5

Manufacture planning

► The valve box: Manufacturing: by week 12/2014 18/2014 Test of the electrical cabinet: by week 14/2014 18/2014

► Transfer lines TL4 & TL5: Manufacturing: by week 10/2014 ˅

► The 10’000 litre LHe dewar: Manufacturing inner & outer vessel: by week 5/2014 16/2014 Insulation: by week 7/2014 18/2014 Inner plumbing: by week 10/2014 21/2014 Test of the electrical cabinet: by week 10/2014 22/2014

TE/CRG/N.Delruelle – LS1 infrastructure – 16 Apr 2014

Page 6: ATLAS LS1 infrastructure: Installation of a new 10’000  litre LHe dewar  for the Solenoid

6

Installation planning in Point 1

► The valve box: Installation: week 20/2014 (12 May)

► Transfer lines TL5: Installation: from week 20 to week 23/2014 (from 12 May to

06 June) Leak test on TL5: week 24/2014 (09 June)

► The 10’000 litre LHe dewar & TL4: Handling & Installation: week 24/2014 (09 June) Connection between dewar and TL4: week 25/2014 (16 June) Leak test on TL4: week 26/2014 (23 June) Cutting & connection to existing TL3: from week 27 to

week 29/2014 (from 01 July to 18 July)

TE/CRG/N.Delruelle – LS1 infrastructure – 16 Apr 2014