ATLAS Workshop, May 15-16, ANL. ATLAS Multi-User Potential. P.N. Ostroumov B. Mustapha, A. Perry (IIT), M. Fraser (CERN) – Beam optics and hardware design S.A. Kondrashev, C. Dickerson, R. Vondrasek – EBIS development May 15, 2014. Motivations. - PowerPoint PPT PresentationTRANSCRIPT
ATLAS Multi-User Potential
P.N. Ostroumov
B. Mustapha, A. Perry (IIT), M. Fraser (CERN) – Beam optics and hardware designS.A. Kondrashev, C. Dickerson, R. Vondrasek – EBIS development
May 15, 2014
ATLAS Workshop, May 15-16, ANL
Motivations
The issue: In the past 2 years, the requested experimental beam time significantly exceeded the 5000-5500 hours that ATLAS can deliver yearly. With CARIBU online, the demand for beam time may double.
The solution: Develop and implement a system for the delivery of stable and radioactive beams to 2 or 3 experiments simultaneously.
The upgrade could be performed in three stages
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
2
Stage I of the ATLAS Multi-User Upgrade Will allow:
– The simultaneous acceleration of two beams– One stable from ATLAS-ECR and one radioactive from CARIBU-EBIS– One to the Booster energy and one to the full ATLAS energy
Will require– Replacing the ECR charge breeder with the newly developed EBIS breeder – Building an achromatic LEBT upstream of the RFQ– Building a pulsed switchyard for one beam extraction at the end of Booster– Relocating and installing an existing ECR as a second source for stable beams
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
3
EBIS: A Key Component of ATLAS Multi-User Upgrade Will be installed on-line in 2015, replaces ECR charge breeder
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
4
Measured Cs transmission efficiency: 55 ± 5 % ~ 13% breeding efficiency into a single charge state
Will be ready for online installation at CARIBU in 2015 – already funded Will enhance both the intensity and purity of CARIBU beams
EBIS Charge Breeder: Successful Off-line Commissioning
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
5
Time Structure of CARIBU-EBIS and ATLAS-ECR Beams
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
6
t
t
t
Radioactive ions from CARIBU-EBIS
Stable ions from ATLAS-ECR
Combined beam structure
Up to 3% Duty Factor
96 % Duty Factor
EBIS beam is ~ 10 μs to 1 ms pulse with 30 Hz repetition rate < 3 % DF DC beam from ECR could be injected into ATLAS in the remaining 97% DF CARIBU Beam masses range from 80 to 170 with Z ranging from 30 to 70 The highest charge-to-mass ratio they could be ionized to is 1/4. ATLAS accelerates any beam with a charge-to-mass ratio > 1/7 The useful charge-to-mass ratio range for the multi-user capability is 1/7 to 1/4 If EBIS is operated at 10 Hz, higher q/A 1/3 can be achieved
Stage I: Modify Injection to combine two beams
New achromatic LEBT to transport beams of slightly different q/A Pulsed electrostatic deflector to combine stable beam from ECR and RIB from EBIS
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop7
Second ECR
EBIS replacing ECR-1charge breeder
CARIBU
Achromatic LEBT
ECR-2
PII
RFQ
EBIS
Pulsed E-Deflector
Stage I: More Examples of Possible Simultaneous Beams Q/A is within 1% for Each Raw
Q/A Stable ATLAS beams CARIBU beams
0.25000 20Ne5+, 28Si7+, 36Ar9+ 84Se21+, 88Kr22+, 92Sr23+, 101Mo25+, 105Ru26+
0.24138 58Ni14+ 83As20+, 95Y23+, 104Tc25+, 112Pd27+, 117Cd28+
0.24000 50Ti12+ 88Br21+, 91Rb22+, 101Zr24+, 105Ru25+, 117Cd28+
0.23809 63Cu15+ 89Rb21+, 97Sr23+, 105Mo25+, 109Rh26+, 113Ag27+
0.23596 89Y21+ 89Kr21+, 97Sr23+, 102Zr24+, 111Rh26+, 119Cd28+
0.23214 56Fe13+ 94Kr22+, 100Sr23+, 113Rh26+, 126Sn29+, 143Ce33+
0.22917 48Ti11+, 74Ge17+ 92Kr21+, 105Nb24+, 109Tc25+, 119Pd27+, 149Nd34+
0.22857 35Cl8+ 100Y23+, 109Tc25+, 127Sn29+, 132I30+, 159Gd36+
0.22500 40Ca9+, 102Ru23+, 120Sn27+ 89Br20+, 112Rh25+, 139Xe31+, 157Sm35+, 156Eu35+
0.22368 76Ge17+ 90Br20+, 99Sr22+, 135Te30+, 128Cs31+, 161Gd36+
0.22034 59Co13+ 91Rb20+, 105Zr23+, 123Cd27+, 131Te29+, 146Pr32+
0.20513 78Kr16+ 93Y19+, 102Mo21+, 132Sn27+, 141I29+, 162Eu34+
0.20408 98Mo20+ 98Sr20+, 108Mo22+, 117Pd24+, 136Sb28+, 161Sm33+
0.20312 64Zn13+ 83Se17+, 93Y19+, 117Ag24+, 132I27+, 166Tb34+
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop8
Stage I More Examples of Possible Simultaneous Beams (2)
Q/A Stable ATLAS beams CARIBU beams
0.20000 40Ar8+,60Ni12+, 90Zr18+, 130Te26+ 85Se17+, 110Mo22+, 124In25+, 141I28+, 159Pm32+
0.18939 132Xe25+ 105Ru20+, 126In24+, 137I26+, 153Pr29+, 165Tb31+
0.17968 128Xe23+ 95Y17+, 105Tc19+, 134Sn24+, 144Xe26+, 149La27+
0.17857 84Kr15+ 100Nb18+, 111Tc20+, 117Cd21+, 141Xe25+, 147La26+
0.17721 79Br14+, 107Ag19+ 96Rb17+, 107Nb19+, 119Cd21+, 135Te24+, 151Nd27+
0.17500 80Se14+ 91Kr16+, 97Zr17+, 109Ru19+, 131Sb23+, 143Ba25+
0.15546 238U37+ 83Se13+, 90Kr14+, 97Sr15+, 103Zr16+, 141I22+
0.15116 86Kr13+ 86Se13+, 92Rb22+, 100Sr23+, 105Zr24+, 106Nb24+
0.15000 180Hf27+ 87Br13+, 94Kr14+, 100Sr15+, 101Y15+, 107Nb16+
0.14904 208Pb31+ 88Se13+, 88Br13+, 94Rb14+, 100Y15+, 107Nb16+
0.14832 209Bi31+ 87Se13+, 87Br13+, 95Rb14+, 102Y15+, 108Nb16+
0.14721 197Au29+ 89Se13+, 89Br13+, 95Rb14+, 102Y15+, 108Nb16+
0.14286 133Cs19+ 84As12+, 98Rb14+, …
May 15, 20139
ATLAS Multi-User Potential ATLAS Workshop
ATLAS as a Multi-User Facility, Stage I
Area II, ~ 6 MeV/u ion beam
(9 -15) MeV/u beam to Area III or IV
May 15, 2014
ATLAS Multi-User Potential ATLAS Workshop
10
ECR
Pulsed switchyard
Stage I Example: Detailed start-to-end 3D beam dynamics simulations 132Sn27+ from EBIS and 48Ca10+ from ECR
May 8, 2013
ATLAS Multi-User Potential Heavy-Ion Discussion Group
11
48Ca10+ at 5.9 MeV/u
extracted and sent to Area II
132Sn27+ at 5.9 MeV/u
injected into ATLAS
132Sn27+ at 10 MeV/u
out of ATLAS to Areas III or IV
Stage I: Schedule and Funding
Schedule – Could be completed in two years from now– EBIS installation will take 3 months and is scheduled for next year. It will not
interrupt ATLAS operations with stable beams– Installation and commissioning of the achromatic LEBT and pulsed switchyard can
take 2-3 months and can be done during ATLAS scheduled shutdown– This installation schedule is based on our experience with the recent ATLAS
upgrades: LEBT modification, RFQ installation and Booster upgrade.– If the project starts in 2015, the completion is most likely in 2017
Funding:– The EBIS installation is funded by Accelerator Improvement funds (AIP)– Relocation of the existing ECR is partially funded by ATLAS Capital Equipment funds– New funding is required for a building extension to house the second ECR- $0.6M,
achromatic LEBT and switchyard - ~$1M– Total required funding is ~ $2M
May 15, 2014
ATLAS Multi-User Potential ATLAS Workshop
12
Stage II of the ATLAS Multi-User Upgrade Will allow:
– Simultaneous acceleration of two beams (one stable and one radioactive) to the full energy of ATLAS
– The acceleration of higher intensity stable beams to the full ATLAS energy Higher intensity radioactive beams from AIRIS (see C. Hoffman’s Talk)
Will require– Replacing the three old split-ring cryostats with two new QWR cryostats, one 72 MHz (intensity upgrade) and one 109 MHz (energy upgrade).– Upgrading the existing 109 MHz cryomodule with an additional cavity and
replacing VCX tuners to allow 3 MV voltage operation – Modifying the 40-deg bend to be achromatic– Reconfiguring the shielding to accommodate higher intensity beams in ATLAS– Creating a pulsed switchyard upstream of Area III
Example of beams:• 132Sn from CARIBU and the EBIS breeder going to HELIOS, • 48Ca (Q=9, 10, or 11) to 64Ni region from the ECR ion source going to either
the FMA or AGFA for heavy element spectroscopy
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
13
Stage II: Replace old split-ring resonators with new QWRs
A/q Example of stable beams
Booster Energy-1 new cryostat(MeV/u)
ATLAS Energy-1 new cryostat(MeV/u)
ATLAS Energy- 2 new cryostats(MeV/u)
2 C6+ 16.5 25.1 34.0
3 Ar12+, O5+ 12.3 18.5 25.1
4 Ca11+, Ni16+ 10.0 14.8 20.0
5 Ar8+, Zr18+ 8.5 12.4 16.8
6 Kr14+, Xe21+ 7.4 10.7 14.4
7 Au, Pb, Bi, U 6.6 9.4 12.6
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
14
Table of possible beam energies in the Booster and ATLAS after one and two new cryostats (no stripping required)
Upgrade existing 109 MHz cryomodule: add additional cavity, replace VCXs, average voltage per cavity is 3 MV
A new =0.077 QWR cryomodule, 7 cavities, VACC=3 MV
A new =0.15 QWR cryomodule, 8 cavities, VACC=3 MV
Stage II: Schedule and Funding Schedule
– Construction and off-line commissioning of two new cryomodules: 4-5 years. It will not interrupt ATLAS operation
– Installation and beam commissioning of cryomodules, relocation of the existing 109 MHz cryomodule and installation of achromatic 40-deg bend: 6 months
– This installation schedule is based on our recent experience with substantial modifications of the Tandem and Booster areas
Funding– Upgrading the existing 109 MHz cryomodule, AIP funding, $1.5M. It will take
place independently from the multi-user upgrade– Two new cryomodules, 40-deg bend, enhanced shielding walls: ~$(10-12)M
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
15
Stage III of the ATLAS Multi-User Upgrade
Will allow:– The simultaneous acceleration of three beams; two stable and one radioactive to
either Booster or ATLAS energy to serve 3 different experiments simultaneously– Even higher intensity ATLAS beams, both stable from a new SC ECR and
radioactive by combining multiple charge states– Intensities of stable beams will be a factor of 5-10 higher than now
Will require:– Replacing one of the existing ECR with a new high-performance SC ECR source– Developing and installing a chopper system in the LEBT to inject two stable
beams with close q/A into two separate RF buckets of the RFQ– Modifying the injection for multiple-charge-state radioactive beams from EBIS– Developing and installing two RF switchyards for Areas II and III– Modifying experimental beam lines to allow the transport of multiple-charge-
state and larger emittance beams Example of Beams:
– 102Ru to HELIOS and 208Pb to Gammasphere and a radioactive beam to Target Area II or III, IV.
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
16
Stage III: Schedule and Funding
Schedule– Longest lead time is the development of the SC ECR: 4 years. It can be started
now if funding is available– All modifications of ATLAS injector, beamlines can be performed in parallel
with ATLAS operations– May require one month of beam commissioning to implement new modes of
ATLAS operation
Funding– $(6-8)M, the most costly item is the SC ECR
May 15, 2014
ATLAS Multi-User Potential ATLAS Workshop
17
Past Performance Guarantees Future Success 3 ATLAS Upgrade projects: RFQ, Cryomodule and EBIS were delivered on
schedule with originally conceived parameters
May 15, 2014
ATLAS Multi-User Potential ATLAS Workshop
18
Summary The first stage of the Multi-User Upgrade can be implemented within 2
years at low cost
Replacement of remaining 3 split-ring cryomodules with 2 new cryomodules enables the acceleration of different q/A beams to the highest available energies including dual charge state beam from CARIBU EBIS
Once a decision is made to build 2 new cryomodules, we can proceed with the next 2 stages of the multi-user upgrade.
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
19
Questions?
May 15, 2014
ATLAS Multi-User Potential ATLAS Workshop
20
Back-up Slides
May 15, 2014
ATLAS Multi-User Potential ATLAS Workshop
21
Stage I: Add Switchyard to extract one beam after Booster
Build a chicane under the main ATLAS beam line to extract one beam to Area II The second beam continues to ATLAS for further acceleration for Area III or IV The chicane consists of a pulsed kicker, a septum and three regular magnets The 40-deg bend will be modified to be achromatic for future stages of the upgrade
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
22
Stage I Example: 132Sn27+ from EBIS and 48Ca10+
from ECR 132Sn27+ 48Ca10+
May 8, 2013
ATLAS Multi-User Potential Heavy-Ion Discussion Group
23
Two separate beams at their sources
Combined beams in the LEBT
Two beams injectedinto the RFQ
Stage I Example: 132Sn27+ from EBIS and 48Ca10+
from ECR (2) 132Sn27+ 48Ca10+
May 8, 2013
ATLAS Multi-User Potential Heavy-Ion Discussion Group
24
Two beams out of RFQ into PII
Two beams out of PII into Booster
Two beams out of Booster @ 5.9 MeV/u
Kicker Magnet Pulsed magnet Could be iron or ferrite magnet Ferrite magnets
– Rise- and fall-time can be very short – nsec
– Operate at high frequencies, MHz– High resistivity, low eddy current– Saturation field is up to 0.6T
Low inductance – single-turn coil Pulse Forming Network (PFN) as a
power supply
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
25
Septum Magnet, DC Magnet
Required current ~kAmps Very high power is needed
– up to 100 kW
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
26
Beamline
Stage II of Multi-User Upgrade
May 15, 2013
ATLAS Multi-User Potential ATLAS Workshop
27
New cryomodule =0.077
Remove all split-ring cryomodules New cryomodule =0.15, 8 cavities
Pulsed switchyards